PDN Handbook Volume II
PDN Handbook Volume II
PDN Handbook Volume II
VOLUME II
For Office Use Only
Government of Maharashtra
Water Resources Department
VOLUME II
(SPECIFICATION FOR
VARIOUS TYPES OF PIPE)
2020
INDEX
Page No.
Sr. Description HDPE PVC GRP PSC PCCP BWSC MS DI SWSR PVC
No. of Item PIPE PIPE PIPE PIPE PIPE PIPE PIPE PIPE P PIPE -O
PIPE
1 Introduction 1 1 1 1 1 1 1 1 1 1
11 Post-delivery 16 11 13 9 10 10 13 16 10
testing of 13
pipes
12 Site 16- 11-12 13- 10- 10-12 10-12 13- 16-18 10-12 13-
Preparation 17 14 11 15 15
13 Excavation for 17- 12-13 14- 11- 12-13 12-13 15- 18-19 12-13 15-
Pipe Trenches 18 15 12 16 16
HDP PVC GRP PSC PCCP BWSC MS DI SWSR PVC
Sr. Descriptio E PIPE PIPE PIPE PIPE PIPE PIPE PIPE P PIPE -O
No n of Item PIPE PIP
E
14 Laying of 18- 13 15- 12 13 13 16- 19-20 13-14 16
Pipes 19 17 17
15 Jointing of 20- 14-16 17- 13- 14 13-14 17- 20-22 14 16-
Pipes 22 20 15 18 18
16 Field Testing 22 16-17 20- 16 14-15 14-15 18- 22-24 14- 18-
Of Pipeline 21 19 15 20
System
17 Backfilling of 23 17-18 21 17 15-16 15-16 19- 24-25 15-16 20
Pipe Trenches 20
18 Permanent 23- 18-19 22 17- 16 16 20- 25 16
markings of 24 18 21 21
Pipe
alignment
19 Third Party 24- 19-20 22- 18- 16-18 16-17 21- 26-27 16-17 21-
Inspection 25 23 19 22 22
20 Quality 25- 20-21 24- 19- 18-19 18-19 22- 27-29 17-19 22-
Control and 27 25 20 24
Quality 24
assurance
21 Operation,Ma 27 22 25 21 19-20 19-20 24- 29 19
intenance and 25 24
Handing over
of the System
to WUA
22 Mode Of 27- 22-23 26 21- 20 20 25- 29-30 20 25
Measurement 28 22 26
and Payment
Govt. of Maharashtra
2020
0
SPECIFICATION FOR HIGH DENSITY POLYETHYLENE PIPE (HDPE)
1.0 Introduction
HDPE pipe is a type of flexible plastic pipe used for fluid and gas transfer. HDPE
material is a polyethylene thermoplastic made from petroleum and its high level of
impermeability and strong molecular bond makes it suitable for high pressure
pipelines. The toughness and resistance to chemicals as well as the corrosion resistance
and low weight have contributed to its growing use in situations where cost effective
and durable fluid and gas pipe systems are required. HDPE pipe is made from food
grade polyethylene virgin material as such they are safe for the transfer of potable
water.
The Contractor shall provide on-site training on HDPE pipe laying, jointing,
testing and maintenance etc., to the personnel authorized by Engineer-in-Charge. The
contractor should provide technical Manual on HDPE pipes including precautions to be
taken during operation of the pipeline.
1
3.0 Raw Materials
Raw material used to manufacture the HDPE Pipes is High Density Polyethylne
of PE 63, PE 80 and PE 100 grade.
a) The material used for the manufacturer of pipes should not constitute toxicity
hazard, should not support microbial growth, should not give rise to
unpleasant taste or odour, cloudiness or discoloration of water. Pipe
manufacturers shall obtain a certificate to this effect from the manufacturers
of raw material as per the satisfaction of the Engineer-in-Charge.
b) High density Polyethylene (HDPE) used for the manufacture of pipes shall
conform to designation PEEWA-45-T-003 or PEEWA-45-T-006 or PEEWA-50-
T-003 or PEEWA-50-T-006 or PEEWA-57-T-003 or PEEWA-57-T-006 of IS 7328.
HDPE conforming to designation PEEWA-45-T-012 or PEEWA-50-T-012 or
PEEWA-57-T-012 of IS 7328 may also be used with the exception that Melt
Flow Rate (MFR) shall be between 0.20 to 1.10 g/10 min. In addition the
material shall also conform to clause 5.6.2 of IS 7328.
c) The Specified base Density shall be between 940.5 to 958.40 kg/cm3 ( both
inclusive) determined at 270C according to procedure prescribed in IS 7328.
The value of density shall not differ from the nominal/agreed value by more
than 3 kg/m3.
d) The Melt Flow Rate (MFR) of the material shall be between 0.20 and 1.10
gm/10 min. (both inclusive) when tested at 190°C with nominal load of 5kgf
as determined by method prescribed in IS 2530. The MFR of the material shall
also be within ±20 percent of the value declared by the manufacturer.
e) The resin shall be compounded with carbon black. The carbon black content
in the material shall be within 2.5 ± 0.5 % and the dispersion of carbon black
shall be satisfactory when tested as per procedure described in IS 2530.
f) The percentage of anti-oxidant used shall not be more than 0.3 percent by
mass of finished resin. The anti-oxidant used shall be physiologically
harmless and shall be selected from the list given in IS 10141.
2
4.0 Manufacturing of Pipes and Specials
To make pipe lengths, HDPE material is heated and extruded through a die,
which determines the diameter of the pipeline. The wall thickness of the pipe is
determined by a combination of the size of the die, speed of the screw and the speed
of the haul-off tractor. The General manufacturing process of HDPE Pipe is as given the
below.
4.1 Workmanship/Appearance
Pipes shall be free from all defect including indentations, delaminating,
bubbles, pinholes, cracks, pits, blisters, foreign inclusions that due to their
nature, degree of extent detrimentally affect the strength and serviceability of
the pipe. The pipe shall be as uniform as commercially practicable in colour
opacity, density and other physical properties as per relevant IS Code or
equivalent International Code. The inside surface of each pipe shall be free of
scouring, cavities, bulges, dents, ridges and other defects that result in a
variation of inside diameter from that obtained on adjacent unaffected portions
of the surface. The pipe ends shall be cut clearly and square to the axis of the
pipe.
4.2 Classification of Pipes:
a) Pipes shall be classified according to the grade of materials as given in
following Table No.1
3
Table No.1: Classification of Pipe material (Reproduced from IS 4984)
Sr. Material grade MRS ( Minimum required Maximum allowable
No. strength) of material in MPa hydrostatic design stress
(N/mm2)., @20 Degree Mpa. (N/mm2)
Celsius, 50 years At 20 At 30
degree degree
Celsius Celsius
1 2 3 4 5
i) PE 63 6.3 5.0 4.0
ii) PE 80 8.0 6.3 5.0
iii) PE 100 10.0 8.0 6.3
c) The nominal diameter of pipes covered in IS 4984 are 16, 20, 25, 32, 40, 50,
63, 75,90, 110, 125, 140, 160, 180, 200, 225, 250, 280, 315, 355, 400, 450,
500, 560, 630, 710, 800, 900 and 1000 mm.
4
fittings /specials shall be moulded at factory only. No fabrication or moulding
shall be allowed at site, unless specifically permitted by the Engineer-In-Charge.
Fittings shall be welded on to the pipes or other fittings by use of Electro - fusion
process.
When engineering HDPE fittings, the manufacturer can either use an
injection molding or create a fabricated fitting. Generally speaking, injection
molds are used to construct fittings up to 12” in diameter. Any fittings over 12”
in diameter are usually fabricated from sections of pipe or other parts. The
larger fittings are fabricated because their size exceeds injection moulding
equipment capacities. Less common fittings may also be fabricated because
their low demand does not constitute the creation of a mould.
All pipes of the same size, same pressure rating and same grade and also manufactured
essentially under similar conditions of manufacture, shall constitute a lot. For
ascertaining conformity of the lot to the requirements of this specification, samples
shall be selected as per following.
The number of test samples shall be in accordance with following Table No.3. These
pipes shall be selected at random from the lot and in order to ensure the randomness
of selection, a random number table shall be used. In the absence of a random number
table, the following procedure may be adopted.
Starting from any pipe in the lot, count them as 1,2,3, 4, etc, up to r and so on where
r is the integral part of N/n, N being the number of pipes in the lot and n is the number
5
of pipes in the samples. Every rth pipe so counted shall be drawn so as to constitute
the required sample size.
The number of pipes given for the first sample in col 3 of Table No.3 shall be examined
for dimensional and visual requirements given in following para No. 6.1 & 6.2. A pipe
failing to satisfy any of these requirements shall be considered as defective. The lot
shall be deemed to have satisfied these requirements, if the number of defectives
found in the first sample are less than or equal to the corresponding acceptance
number given in Col 5 of Table No.3. The lot shall be deemed not to have met these
requirements if the number of defectives found in the first sample is greater than or
equal to the corresponding rejection numbers given in col 6 of Table 3. If, however, the
number of defectives found in the first sample lies between the corresponding
acceptance and rejection numbers given in col 5 and 6 of Table 3, the second sample
of the size given in col. 3 of Table 3 shall be taken and examined for these
requirements. The lot shall be considered to have satisfied these requirements, if the
number of defectives found in the cumulative sample is less than or equal to the
corresponding acceptance number given in co1 5 of Table 3; otherwise not.
5.2 Hydraulic Characteristics, Reversion, Overall Migration, Density, MFR and Carbon
Black Content/Dispersion Tests.
The lot having satisfied dimensional and visual requirements as mentioned in 5.1 above
shall be tested for hydraulic characteristics, reversion, overall migration, density, MFR
and carbon black content /dispersion requirements (as mentioned in following para
no. 6.3 to 6.8). A separate sample size for each of the test shall be taken as stipulated
in following Table 4 and selected at random from the sample already examined for
6
dimensional and visual inspection. All the pipes in each of the sample size shall be
tested for compliance in the requirements for hydraulic characteristics, reversion,
overall migration, density, MFR, and carbon black content /dispersion. The lot shall
be considered to have met the requirements of these tests, if none of samples tested
fails.
Upto 150 3
150 to 1200 5
1201 to 35000 8
For sample testing of injection moulded & fabricated specials, sampling criteria shall
be as mentioned in IS 8360 and IS 8008 respectively.
6.1 Dimensions:
7
TableNo.5 Outside diameter, tolerance and ovality of pipes
(reproduced from IS 4984)
Nominal Outside Tolerance (mm) (Only Ovality
Diameter DN Diameter (mm) +ve Tolerance) (mm)
16 16 0.3 1.2
20 20 0.3 1.2
25 25 0.3 1.2
32 32 0.3 1.3
40 40 0.4 1.4
50 50 0.5 1.4
75 75 0.7 1.6
90 90 0.9 1.8
110 110 1.0 2.2
125 125 1.2 2.5
140 140 1.3 2.8
160 160 1.5 3.2
180 180 1.7 3.6
200 200 1.8 4.0
225 225 2.1 4.5
250 250 2.3 5.0
280 280 2.6 9.8
315 315 2.9 11.1
355 355 3.2 12.5
400 400 3.6 14.0
450 450 4.1 15.6
500 500 4.5 17.5
560 560 5.0 19.6
630 630 5.7 22.1
710 710 6.4 24.9
800 800 7.2 28
900 900 8.1 31.5
1000 1000 9.0 35.0
8
6.1.2 Wall thickness:
The wall thickness shall be measured by a dial Vernier or ball ended
micrometer. The minimum & maximum wall thickness of pipes of PE 63, PE 80
and PE 100 grade material shall be as given in following table 6, 7 and 8
respectively.
Table 6. Wall thickness of pipes for material grade PE 63.
All dimensions in mm.
(reproduced from IS 4984)
Nominal Wall thickness of pipes for pressure ratings of
Diameter
DN PN 2.5 PN 4 PN 6 PN 10 PN 12.5 PN 16
Mi Max Min Max Min Max Min Max Min Max Min Max
n. . . . . . . . . . . .
16 - - - - - - - - 2.2 2.6 2.7 3.2
20 - - - - - - 2.3 2.8 2.7 3.2 3.4 3.9
25 - - - - 2 2.4 2.8 3.3 3.4 4 4.2 4.8
32 - - - - 2.3 2.7 3.6 4.2 4.4 5 5.4 6.1
40 - - 2 2.4 2.8 3.3 4.5 5.1 5.5 6.2 6.7 7.6
50 - - 2.4 2.9 3.5 4.1 5.6 6.4 6.8 7.7 8.4 9.4
63 2.0 2.4 3 3.5 4.4 5.1 7 7.9 8.6 9.6 10.5 11.8
75 2.3 2.7 3.6 4.2 5.3 6 8.4 9.4 10.2 11.4 12.5 14
90 2.8 3.2 4.3 5 6.3 7.2 10 11.2 12.2 13.6 15 16.7
110 3.4 3.9 5.3 6 7.7 8.7 12.3 13.7 14.9 16.6 18.4 20.4
125 3.8 4.4 6 6.8 8.8 9.8 13.9 15.5 16.9 18.8 20.9 23.2
140 4.3 4.9 6.7 7.6 9.8 11 15.6 17.4 19 21.1 23.4 25.9
160 4.9 5.6 7.7 8.6 11.2 12.5 17.8 19.8 21.7 24 26.7 29.6
180 5.5 6.2 8.6 9.7 12.6 14.1 20.0 22.2 24.4 27 30 33.2
200 6.1 6.9 9.6 10.7 14 15.6 22.3 24.7 27.1 30 33.4 36.9
225 6.9 7.7 10.8 12 15.7 17.5 25. 27.7 30.5 33.7 37.5 41.5
250 7.6 8.6 11.9 13.3 17.5 19.6 27.8 30.8 33.8 37.4 41.7 46.1
280 8.5 9.6 13.4 14.9 19.6 21.7 31.2 34.5 37.9 41.9 46.7 51.6
315 9.6 10.7 15 16.7 22 24.4 35 38.7 42.6 47.1 52.5 58
355 10. 12.1 16.9 18.8 24.8 27.5 39.5 43.6 48 53 59.2 65.3
8
400 12. 14.2 19.1 22.1 28 32.3 44.5 51.4 54.1 62.4 - -
2
450 13. 15.9 21.5 25 31.4 36.3 50 57.7 - - - -
7
500 15. 17.7 23.9 27.6 34.5 40.4 55.6 64.1 - - - -
2
560 17 19.8 26.7 30.9 39.1 45.2 - - - - - -
630 19. 22.2 30 34.7 44 50.8 - - - - - -
1
9
Nominal Wall thickness of pipes for pressure ratings of
Diameter
DN PN 2.5 PN 4 PN 6 PN 10 PN 12.5 PN 16
Mi Max Min Max Min Max Min Max Min Max Min Max
n. . . . . . . . . . . .
710 21. 25 33.9 39.1 49.6 57.2 - - - - - -
6
800 24. 28.1 38.1 44.1 55.9 64.4 - - - - - -
3
900 27. 31.6 42.9 49.5 - - - - - - - -
3
1000 30. 35.1 47.7 55 - - - - - - - -
3
Table 7. Wall thickness of pipes for material grade PE 80.
All dimensions in mm.
(Reproduced from IS 4984)
Nominal Wall thickness of pipes for pressure ratings of
Diameter
DN PN 6 PN 10 PN 12.5 PN 16
Min. Max. Min. Max. Min. Max. Min. Max.
16 - - - - - - 2.3 2.7
20 - - 1.9 2.3 2.3 2.7 2.8 3.3
25 - - 2.3 2.7 2.8 3.3 3.5 4
32 1.9 2.3 3 3.4 3.6 4.2 4.5 5.1
40 2.3 2.7 3.7 4.3 4.5 5.1 5.6 6.3
50 2.9 3.4 4.6 5.3 5.6 6.4 6.9 7.8
63 3.6 4.2 5.8 6.6 7 7.9 8.7 9.8
75 4.3 4.9 6.9 7.8 8.4 9.4 10.4 11.6
90 5.1 5.8 8.2 9.3 10 11.2 12.5 13.9
110 6.3 7.1 10 11.2 12.3 13.8 15.2 16.9
125 7.1 8 11.4 12.8 13.9 15.5 17.3 19.2
140 8 9 12.1 14.3 15.6 17.4 19.4 21.5
160 9.1 10.2 14.6 16.3 17.8 19.8 22.1 24.5
180 10.2 11.5 16.4 18.3 20 22.8 24.9 27.6
200 11.4 12.7 18.2 20.3 22.3 24.7 27.6 30.6
225 12.8 14.3 20.5 22.8 25 27.7 31.1 34.4
250 14.2 15.8 22.8 25.3 27.8 30.8 34.5 38.2
280 15.9 17.7 25.5 28.3 31.2 34.5 38.7 42.7
315 17.9 20 28.7 31.8 35 38.7 43.5 48
355 20.1 22.3 32.3 35.8 39.5 43.6 49 54.1
400 22.7 26.3 36.4 42.1 44.5 51.4 55.2 63.7
10
Nominal Wall thickness of pipes for pressure ratings of
Diameter
DN PN 6 PN 10 PN 12.5 PN 16
Min. Max. Min. Max. Min. Max. Min. Max.
450 25.5 29.5 41. 47.4 50 57.7
500 28.3 32.8 45.5 52.5 55.6 64.1
560 31.7 36.7 51. 58.8
630 35.7 41.3 57.3 66.1
710 40.2 46.5
800 45.3 52.3
900 50.1 58.8
1000 56.6 65.3
Table No.9: Requirements of pipe for Internal Pressure Creep Rupture Test
(reproduced from IS 4984)
Sr. Test Test Temp. Test duration Induced stress in MPa. for
No. degree (Min. holding PE 63 PE 80 PE 100
Celsius time)
i) Acceptance Test 80 48 3.8 4.9 5.7
12
6.4 Reversion Test
When tested according to the procedure given in IS 4984, value of the
longitudinal reversion shall not be greater than 3 %.
6.5 Overall Migration Test
When tested from a composite sample of minimum 3 pipes as per IS
9845, the overall migration of constituents shall be within the limits stipulated
in IS 10146.
6.6 Density
When tested from a composite sample of minimum 3 pipes as per IS
7328, it shall meet the requirement as given in preceeding para 3.0, (C).
13
The vehicle shall have side supports approximately spaced 2 m apart, and the pipes
shall be secured effectively during the transportation. All posts shall be flat with no
sharp edges. Strapping the pipe bundles during transit may be required to avoid
excessive movement in the truck.
Polyethylene pipes shall not be transported with other metallic items in the same
vehicle.
Coiled pipe with outer diameter < 63 mm may be supplied on pallets. The coils
should be firmly strapped to the pallets, which in turn be firmly secured to the
vehicle. Coiled pipe with outer diameter ≥ 63 mm should be supplied individually.
There should be facilities to ensure that each coil is securely fastened throughout
transit and the un-loading process.
To save on transport cost nesting of coils/ straight lengths can be considered, if
agreed to between the purchaser and the supplier.
Pipes manufactured at factory are to be carried to the site of work directly or stacked
suitably and neatly on contractors yard along the alignment/road side/elsewhere
near by the work site or as directed by the Engineer In-Charge.
14
• When releasing coils, it must be remembered that the coil is under tension and must
be released in a controlled manner. The end of the coil should be retained at all
times, then the straps released steadily, one at a time. If the coil has bands at
different layers of the coil, then they should be released sequentially starting from
the outer layers.
10.0 Valves
For PDN work, various Valves as mentioned below are required to be provided on
pipeline at various location.
A control valve is a valve used to control fluid flow by varying the size of the flow
passage as directed by a signal from a controller. This enables the direct control
of flow rate and the consequential control of process quantities such
as pressure, temperature, and liquid level.
Common types of control valve are as given below.
A) Sliding Stem
Globe valve
Angle body valve
Angle seat piston valve
B) Rotary
15
Butterfly valve
Ball valve
C) Other
Pinch valve
Diaphragm valve
12.2 Demarcation
All materials such as pegs, bamboo’s and strings and templets for
marking out slopes, and labour required for line out should be provided by the
Contractor at his own cost. The center line of excavation shall be clearly marked
by pegs or by stones at each chain or change of direction or at shorter intervals
on curves, in the beginning. The final line out will be done by fixing reference
stone at suitable distances on either side of the center line, beyond the canal
edges so that they are not disturbed during the construction period. The
position of these stones will be marked on the cross section.
12.3 Contractor shall provide and maintain the quarry roads and temporary roads
required for construction activity at his own cost.
12.4 Fixing Permanent Benchmark
(a) Benchmarks fixed by the Survey of India and temporary benchmarks established
by the Engineer In-charge in vicinity of PDN work will serve as control points for
these works. The Contractor shall establish sufficient number of reference
benchmarks for facilitating setting out of work and taking levels for the purpose
of measurements.
(b) Before starting any work, the Contractor shall erect reference benchmarks,
reference lines and check profiles at convenient locations approved by the
Engineer In-Charge. The benchmark concrete block shall be 200mm x200mm
x600mm with 400mm embedded in the firm ground and 200 mm projecting
16
above ground. The word ‘BM’ showing value of R.L. in ‘m’ shall be conspicuously
carved and painted on the benchmark.
(c) The check profile shall be located 30m apart or closer as directed by the
Engineer In-Charge so as to ensure execution of all slopes, steps and elevations
to the profile or profiles indicated in the approved drawings. All important levels
and all control points with respect to benchmarks and reference lines shall be
fixed and correlated by the Contractor. The Contractor is fully responsible for
maintaining all setting out work & Benchmark established by Engineer-In-
charge.
(d) All materials, labour and equipments (theodolites, levels, distometre, etc.) for
setting out works including construction of benchmarks in concrete, reference
lines, check profiles and surveys as may be required at the various stages of
construction shall be supplied by the Contractor at his cost. For this following
numbers of minimum equipments shall be provided and maintained in
good working condition by the Contractor.
All equipments shall be of standard and approved make and precision, and
shall be made available in advance of starting of the work. All equipment
shall be maintained, repaired and got tested and certified as and when
required for its accuracy from the standard test houses or from the
manufactures and to the satisfaction of the Engineer-In-Charge.
14.1 Each pipe shall be thoroughly checked for any damages before laying and only
pipes that approved by Engineer-in-Charge shall be laid.
14.2 The pipe line may be laid along side of the trench and jointed there. There after
the jointed pipeline shall be lowered into the trench carefully without causing
undue bending. The pipeline shall be laid inside the trench with a slack of up to
2 m/100 m of pipe line.
14.3 Polyethylene pipes conforming to IS 4984, being black in colour, when subjected
to direct sunlight or warm ambient temperature may become warmer than the
ground temperature. When placed inside the trench, the pipe will contract in
length as it cools to the surrounding soil temperature. If the pipe is connected
to sub-surface structures (such as preset valve, etc) before it is cooled
sufficiently, excessive pull forces could develop. Allow the pipe to cool to
ambient temperature prior to making a connection to an anchored joint.
18
14.4 Polyethylene pipe requires no special bed preparation for laying the pipe
underground, except that there shall be no sharp objects around the pipe.
However, while laying in rocky areas suitable sand bedding should be provided
around the pipe and compacted. 100 mm compacted fine sand bedding under
and around the pipe be provided in rocky areas.
14.5 During the pipe laying of continuous fusion jointed systems, due care and
allowance should be made for the movements likely to occur due to the thermal
expansion/contraction of the material. This effect is most pronounced at end
connections to fixed positions (such as valves etc.) and at branch connections.
Care should be taken in fixing by finishing the connections at a time the length
of the pipe is minimal (lower temperature times of the day).
14.6 The flexibility of polyethylene pipes allows the pipe to be cold bend. The fusion
jointed PE pipe is also flexible as the plain Pipe. Thus the total system enables
directional changes within the trench without recourse to the provision of
special bends or anchor blocks. However, the pipe should not be cold bend to a
radius less than that mentioned in IS 7634 (Part-II).
14.7 The Installation of flanged fittings such as connections to sluice/air/gate valves
and hydrant tees etc., requires the use of stub ends (collars/flange adaptors)
complete with backing rings and gaskets. Care should be taken when tightening
these flanges to provide even and balance torque.
Provision should be made at all heavy fittings installation points for supports
(such as anchoring of the flange in the soil) for the flange joint to avoid the
transfer of valve wheel turning torque on to the PE flange joint
14.8 The pipe shall be laid on a stable foundation. Where water is present or where
the trench bottom is unstable, excess water should be removed before laying
the pipe. In case there is a chance of floatation because of likely flood, the pipe
shall be encased with concrete weights as per the buoyancy calculations.
14.9 Under National / State Highways, a concrete / Hume pipe shall be covered over
the pipe.
14.10 Polyethylene pipes are non-metallic, so once buried, metal detector type
locators are ineffective. To facilitate locating a buried PE pipe, metallic locating
tapes or copper wires can be placed alongside the pipe. Locating tapes/wires
are placed slightly above the crown of the pipe before the final back fill.
Because of high integrity of properly made fusion joints, PE pipes can be
used with special installation techniques such as horizontal directional drilling,
pipe bursting, micro tunnelling methods of trench less technologies.
19
15.0 Jointing of Pipes
Jointing of pipes should be done as per Procedure mentioned in IS 7634. The
commonly used joints are as follows:
a) Fusion welding:
1) Butt fusion welding;
2) Socket fusion welding;
3) Electro fusion welding;
b) Insert type joints;
c) Compression fittings/push fit joints;
d) Flanged joints
e) Spigot and socket joints.
The detailed Jointing Procedure of above mentioning various joints shall be as
per IS 7634 (Part-II)
20
bore is expanded by immersion in oil bath (130°C) where the heat of the oil
bath would soften the pipe to enable insertion of fitting.
This type of jointing is used normally for pipe diameters up to 110 mm and
internal pressure below 0.4 MPa.
15.3 Compression Fittings
Compression fittings are detachable joints and are made of metal or
plastics [polypropylene (PP)] or a combination of both. Compression
fittings form a tight seal by applying a compressive force to the pipe and
pipe fitting. The fitting is compressed against the pipe with a force
sufficient to eliminate all space remaining in the joint, thus preventing the
fluid from leaking.
It is critically important to the integrity of the fitting that excessive force is
avoided in tightening the nut. If the fitting is over tightened, the gripper
(clip ring) will deform and cause leaks. Over tightening is the most common
cause of leaks in compression fittings. As a general rule, a compression
fitting should be ‘finger tight’ and then tightened one turn with a wrench.
The fitting should then be tested, and if slight weeping is observed, the
fitting should be slowly tightened a bit more until the weeping stops.
Compression fittings are especially useful in installations that may require
occasional disassembly or partial removal for maintenance, etc, since
these joints can be detached and re-joined without affecting the integrity
of the joint. They are also used in situations where a heat source, in
particular a heating plate, is prohibited and inside bead formation by butt
fusion is not preferred.
For coiled polyethylene pipes, of small diameters (Less than 110 mm)
where the working pressure do not exceed 1.6 MPa, jointing by
polypropylene (PP) compression fittings is generally recommended over
fusion jointing.
15.4 Flanged Joints
These are used for jointing the PE pipes particularly of larger size to valves
and vessels and large size metal pipes, and where non-PE pipes are to be
joined with PE pipes.
It contains slip-on metallic/polyethylene flanges with collar/stub ends. The
collar/stub end is welded by butt, socket or electro fusion. In case
polyethylene flanges are used a suitable metallic backing plates shall be used
to support the polyethylene flanges so that the bolt force does not deform
the plastic flange. Sealing is improved by incorporating a natural or synthetic
rubber gasket between the flanges.
21
The socket (bell) could be an integral part of the pipe at one end or a special
coupler, into which the free ends (spigot ends) of the pipes are pushed to
achieve a water tight joint. Various types of ‘O’ rings are available in the
market and the user may check with the manufacturer about the suitability
of the same as per site conditions.
These joints are normally weak in longitudinal pull and hence need
anchoring wherever such a tendency of longitudinal pull is likely in the pipe
line.
This type of joint is best used for non-pressure applications, such as gravity
lines and for encasing cables or smaller diameter pipes.
22
under rejection, the same shall be recovered from the outstanding dues of the
Contractor.
(a) The type of material used for backfilling and the manner of depositing the material,
shall be subject to approval by Engineer-in-Charge.
(b) The backfill material shall be placed to the line and grades as shown on drawings or
as prescribed in this paragraph or as directed by the Engineer-in-Charge.
(c) The backfill material shall be placed carefully and spread in uniform layers of not
more than 15cm thickness, with the first layer watered and compacted by stamping
or by mechanical means. The backfill shall be brought up as uniformly as practicable
on both sides of pipe to prevent unequal loading.
(d) Only soft earth and gravel of good quality free from boulder, roots, vegetable
matters etc. shall be used for refilling trench upto 300mm above top of pipe. If
sufficient quantity of suitable (Sharp edge stone free) excavated earth is not
available, the trench shall be filled by borrowed gravel material upto 300 mm above
top of pipeline. Remaining trench can be filled with available material.
(e) When compacting the soil against steep rock, abutment walls of concrete structures,
rollers shall not be used close to structures as structural damage is very likely more
particularly when structures have not been fully cured. The size and weight of
equipment will depend on nature of material, the height and load assumed in design
of structure. The backfill close to the structure up to the rolled layer shall be
compacted in suitable uniform layers, using pneumatic / hand tampers as
appropriate for dry density at average bulk density (+/- 10%). The moisture content
of the earth fill placed against the rock or the structure shall be on higher/lower side
of OMC by about 2% or so, to allow it to be compacted. Profuse watering shall be
done to pervious materials (sand) before compaction as per instruction of the
Engineer-in-Charge. Compaction at junction of earthwork and backfill around the
structure shall be carried out with special care.
(f) The trench shall be refilled so as to built-up the original ground level.
23
18.3 These blocks shall be able to locate the pipeline as and where it is laid all over
the work. The contractor shall mark each block with specific distinct
identification mark.
18.4 The contractor shall show all this blocks jointly to the Engineer in-charge or his
representative, representative of WUA, concern farmers sharing the
boundaries, TPI, any other stake holders in the command.
18.5 Contractor shall maintained these blocks in proper order during operation &
maintenance period of this contract. Any damage done to these blocks for the
reasons whatsoever shall be made good at the cost of contractor.
18.6 The contractor shall submit the location of such blocks with specific
identification marks with schedule on a special command area map.
18.7 The map of marking of the block shall be handed over to WUA while handing
over the command area.
18.8 The Geotagging map showing Latitude and Longitude Value of each apex of
laid pipeline shall be submitted to Department and WUA for future reference.
18.9 The contract shall fix information boards of 1.2 m x 0.9 m size at various location
as directed by Engineer-in-charge. On this boards, salient features of the work
(eg. Pipe diameter, pipe type, discharge, any other specific details suggested by
Engineer-In-Charge) shall be written.
24
the latest editions of relevant IS Codes and determined by the Engineer In-
charge. The day-to-day and periodical tests to be carried out on materials
mixes and placed concrete, mortar etc. shall be specified by the Engineer In-
charge from time to time and the Contractor shall provide free of cost all
facilities towards collections of samples etc. unless otherwise specified.
Labours for collecting samples and transportation of the samples to quality
control authorities for test shall be provided free cost of by the contractor.
Also electricity, fuel, water curing tank and stores etc shall be provided free
of cost by the contractors.
(b) The materials shall be tested in QC laboratory or at any other place directed
by the Engineer In-charge. The Contractor shall obtain the test results from
the concern authority and the results given by such authorities shall be
considered to determine whether all materials, workmanship are of
respective standard described in contract and in accordance with the
instructions of the Engineer In-charge. The Contractor’s representatives
shall, however, be given access to all operations and tests that may be
carried out as aforesaid so that he may satisfy himself regarding the
procedure and methods adopted. It shall then be the Contractor’s
responsibility to produce on the work, materials and finished item to the
standard as determined by the laboratory tests or to take follow up action
to rectify the quality.
(c) Testing charges for testing of Cement, TMT bars, all types of pipes and
specials including cost of samples and its collection shall be borne by the
Contractor.
(d) The Contractor shall make suitable arrangements to see that one of his
representatives remains present at the time of taking samples and shall
authenticate the facts. If the Contractor, fails to keep his representative
present at site at the time of taking samples or fail to provide required
labours and other equipment to collect the samples, the same shall be taken
by the Engineer In-charge, and the samples selected shall be considered as
authentic. The cost incurred by the Engineer-In-charge when the Contractor
fails to provide required men and materials for collecting samples and or
their transport shall be recovered from the Contractor.
25
Sr. No. Personnel with Qualification Nos.
1 Quality Assurance Engineer(Civil One
Engineering Graduate with 2 Year
experience in QA testing and report
generation work)
2 Laboratory Assistants(Twevlth Pass with
Two to Four
Science subject with 2 year experience in
(As per work)
testing of material)
3 Laboratory Attendants Two to Four
(One for each L.A.)
20.3 Following minimum equipments shall be available in the field laboratory setup
by the contractor.
Sr. No. Work Apparatus for Tests
1 Earth Work – Field density, Moisture Content,
Field testing Equipments Sieves for Sand & Metal.
2 Concrete Work - Silt, Gradation, Moisture Content,
Slump, & Cube Moulds, CTM
20.4 It is the responsibility of the contractor to assure the desired quality of
work. Whenever the testing of construction materials, pipes are required as
per the detailed specifications or otherwise required by the Engineer-in-
Charge, the same shall be carried out at the laboratory, selected by the
Engineer-in-Charge at Contractor’s cost. The other tests of mortar, concrete,
sand, coarse aggregates etc. shall be carried out in field laboratory set up by
the contractor in presence of quality control representative at contractors
cost. Contractor shall through this procedure assure the quality of work.
20.5 The materials, mixes and any other arrangements, including labours, shall be
supplied by the contractor. The samples for testing shall be taken in the
presence of Engineer-in-Charge or his representative /QC present on site. The
contractor or his authorized representative shall have a free access in these
laboratories, to get himself satisfied about procedures of testing etc. Even
if the contractor or his representative fails to remain present while
collecting samples or testing, the results will be considered as authentic and
binding on the contractor.
20.6 Contractor shall provide all test reports of material used in the work as desired
from the NABL (National Accreditation Board for Testing & Calibration
Laboratories) approved laboratories and from Quality Control, MERI
laboratories of the WRD. Contractor shall provide periodical quality assurance
report (Weekly/fortnightly/monthly) to Engineer in Charge along with proofs in
support of quality of material brought for the work, the process/ execution of
work is as per specification.
26
20.7 Contractor shall submit the account of all materials brought for the work, which
are necessary for execution of work and any other data necessary to assess the
quality of work.
20.8 If he fails to fulfill the above requirement, the required manpower for testing
and field laboratory with required equipments will be deployed by the Engineer
in charge and the charges for the same will be recovered from the contractor.
21.4 During the O & M period, contractor shall give training to the members of WUA
about O & M of PDN work and its efficient use and protection of the system
from any damages.
21.5 The contractor shall prepare a detail map of the permanent marking along the
alignment of pipe and submit the same to Engineer In-charge. The Engineer In-
charge shall verify and endorse the location of the marking and handover these
signed maps as a permanent record to WUA. Along with this, the detailed
Geotagged map of laid pipeline shall be handed over to WUA.
21.6 In association of the members of WUA, the Engineer In-charge shall confirm the
release of designed discharge through every outlet before handing over. In case
of any short fall or defect, it should be made good from the contractor at his
own cost.
22.0 Mode of Measurement and Payment
22.1 Measurement
The net length of pipes as laid or fixed shall be measured in running meters
correct to a cm. Specials shall be excluded and measured in running meters or
numbers as specified by Engineer-in-charge and paid for separately under the
relevant item. The portion of the pipe overlapped at the joints shall not be
included in the length of pipe work. Excavation, refilling, anchor blocks, thrust
27
blocks wherever required shall be measured and paid for separately under
relevant items of work.
22.2 Payment
The break up to payment for supplying, laying and jointing of pipes shall be as
under:-
A) 80% of the payment will be released after supplying, lowering, laying,
Jointing and third party inspection of pipes in one WUA area.
B) Balance 10% of the payment will be released after satisfactory hydraulic
testing of pipeline and backfilling of trenches.
C) Remaining 10% amount will be withheld and it will be released after
successful maintenance and operation for a period of five years after
commissioning of work of respective WUAs.
The schedule of release of this 10% will be in following manner,
1) After Successful Operation and Maintenance for First year-2%
2) After Successful Operation and Maintenance for Second year-2%
3) After Successful Operation and Maintenance for Third year-2%
4) After Successful Operation and Maintenance for Fourth year-2%
5) After Successful Operation and Maintenance for Fifth year-2%
----------***----------
28
Govt. of Maharashtra
Water Resources Department
SPECIFICATION FOR
POLYVINYL CHLORIDE PIPES
(PVC)
2020
0
SPECIFICATION FOR POLYVINYL CHLORIDE PIPES (PVC)
1.0 Introduction
Polyvinyl Chloride (PVC) pipes are made by a continuous extrusion process. These
pipes are supplied with plain or with socket-ends. .
The Contractor shall provide on site training on PVC pipe laying, jointing, testing
and maintenance etc.,to the personnel authorized by the Engineer-in-charge. The
contractor should provide technical Manual on PVC pipes including precautions to
be taken during operation of the pipeline.
1
The addition of the manufacturer’s own rework material is permissible. The
quantity of rework material used is to be declared by the manufacturer. No
other rework material shall be used.
2
Table No.1 Scale of Sampling for Visual Appearance and Dimensional Requirements
(Reproduced from IS 4985)
These pipes shall be selected at random from the lot and in order to ensure the
randomness of selection, a random number table shall be used. In the absence of a
random number table, following procedure may be adopted.
Starting from any pipe in the lot, count them as 1, 2,3, etc, upto r and so on, where
r is the integral part of N/n, N being the number of pipes in the lot,and n is the
number of pipes in the sample. Every rth pipe so counted shall be withdrawn so as to
constitute the required sample size.
3
5.2 Reversion Test, Vicat softening test, Density, Sulphated ash content test,
Resistant to external blows at 00c , Internal hydrostatic pressure test.
The lot having satisfied dimensional and visual requirements as mentioned in para
5.1 above, shall be tested for Reversion Test, Vicat softening test, Density, Sulphated
ash content test, Resistant to external blows at 00 c , internal hydrostatic pressure
test as mentioned in following para no 6.5 to 6.10. A separate sample size for each
of the test shall be taken as stipulated in following Table no.2 (for Reversion Test,
Vicat softening test and Density test ), Table no.3 (for Sulphated ash content test),
Table no.4 (for Resistant to external blows at 00 c) and Table no.5 (for internal
hydrostatic pressure test),
4
Table 4 Scale of sampling for Resistance to External Blows at 0 0C
(Reproduced from IS 4985)
NOTE – The number mentioned in col 3 to 6 in the above table represent the number of times the test is to be
carried out and do not represent either the number of pipe samples or number of blows or number of failures.
The criteria for conformity of various test mentioned above shall be the same as that
for dimensional and visual requirements as mentioned in above para no. 5.1.
These test shall be carried out by the agency in the presence of representative
of Engineer In-charge /WRD/QC/TPI.
5
6.1 Dimensions
6.1.1 The mean outside diameter, outside diameter at any point and wall
thickness of pipe shall be as given in following Table no.6
6.1.2 Length :The length of pipe shall be 4,5 or 6 m. The pipe may be supplied
in other lengths, as agreed between the manufacturer and the purchaser
6.3 Opacity
The wall of the plain pipe shall not transmit more than 0.2 % of the visible
light falling on it when tested in accordance with IS 12235
6.7 Density
When determined in accordance with IS 13360, the density of the pipe shall
be between 1.40 and 1.46.
6
7
6.8 Sulphated ash content test
When tested as per method prescribed in IS 4985, the sulphated ash
content in the pipe shall not exceed 11 percent.
When transporting pipes, flat bed vehicles should be used. The bed should be free
from nails and other projections. When practical, pipes should rest uniformly on the
vehicel over the whole length.
8
The vehicles should have side supports approximately 2 m apart and the pipes
should be secured effectively during transport. All posts should be flat with no sharp
edges.
When loading spigot and socket pipes, the pipes should be stacked on the vehicle so
that the socket do not take excessive loads.
Where pipes overhang the vehicle, the amount of overhang should not exceed I m.
High stiffness pipes should be placed at the bottom of the load and low stiffness
pipes at the top.
Care should be taken to avoid positioning the pipes near to any exhaust systems or
any other potential hazards such as diesel oil, paints or solvents.
When pipes are transported in bundles, the bundles should be secured effectively
and off- loaded with due care.
Mechanical lifting equipment used for lifting pipes and pipe bundles should not
damage the pipe. Fork-lift forks should be flat and protected. Cranes should have
spreader bars. No wire ropes, chains or hooks should be used. Slings should be made
of rope or webbing 7 to 10 cm wide.
If pipes have been telescoped for transporting, the inner pipes should be removed
first and stacked separately.
10.0 Valves
For PDN work, various Valves as mentioned below are required to be provided on
pipeline at various locations.
10.1 Air Valve :
The effect of air valve in the long-distance water pipelines are in the following
three areas: firstly, in the water filled stage of the pipeline, filled with water by
a certain velocity, the air valve can discharge the remained gas in the pipe;
secondly, at the normal working stage, the air valve can discharge the small
amount of gas gathered in the pipe timely; finally, during the pump failure or
maintenance stages, the air valve will replenish the gas into the pipe to break
the vacuum. According to the orifice size, displacement and work pressure, air
valve is divided into high pressure trace exhaust valve, low pressure air release
valve and combined air valve.
10.2 Scour Valve :
These Valves are generally provided to drainout the pipeline.The exact location
of Scour valves is frequently influenced by opportunities to dispose off the
water. Where the main pipeline crosses a stream or drainage structures, there
will usually be a low point in the line but if the main pipeline goes under the
stream or drain, it cannot be completely drained into the channel. In such a
situation it is better to locate a scour connection at the lowest point that will
drain by gravity and provide for pumping out the part below the drain pipeline.
10.3 Control Valve :
A control valve is a valve used to control fluid flow by varying the size of the flow
passage as directed by a signal from a controller. This enables the direct control
of flow rate and the consequential control of process quantities such
as pressure, temperature, and liquid level.
Common types of control valve are as given below.
A) Sliding Stem
Globe valve
Angle body valve
Angle seat piston valve
B) Rotary
Butterfly valve
Ball valve
10
C) Other
Pinch valve
Diaphragm valve
All equipments shall be of standard and approved make and precision, and
shall be made available in advance of starting of the work. All equipment
shall be maintained, repaired and got tested and certified as and when
required for its accuracy from the standard test houses or from the
manufactures and to the satisfaction of the Engineer-In-Charge.
13.3 Surface or sub-soil water met with during trench excavation (PDN) and
structure excavation shall be diverted to nearby drain/nalla by cutting an
open channel from trench. When the drain/nalla bed is higher than the sub-
soil water level met with, the bailing out by suitable means of pumping shall
12
be resorted to for dewatering sub-soil water below the drain/nalla bed level.
No distinction shall be made as to whether the material being excavated is
dry,moist, wet or slushy. The Contractor shall have to excavate the PDN pipe
trench and structure in under water level conditions also i.e. under
wet/slushy condition after providing sufficient arrangement of dewatering.
The material excavated under water level condition which requires
intermediate stacking for drying shall have to be rehandled. No extra
payment for efforts for drying out of soil, re-handling of dry soil, etc. shall be
given. No payment for extra efforts for excavation under this condition shall
be made.
13.4 Over excavation performed by the Contractor for any purpose or reason,
except for additional excavation as may be directed by the Engineer-In-
charge, shall be rectified at the cost of the Contractor. Filling and compaction
for such over excavation using the material as directed by the Engineer In-
Charge shall also be at the cost of the Contractor.
13.5 In the PDN and structure section where expansive type of the soil such as CH
type of soil is encountered and over which PDN cannot be directly laid, the
PDN trench and structure shall be over excavated to the extent as directed by
the Engineer In Charge and such over excavated section shall be filled with
suitable murum type soil to be placed in uniformly compacted layers as
directed by the Engineer In Charge. The over excavation made in such strata,
filling by suitable soil, and watering and compacting such soil will be paid
separately under relevant items. Above provision for over excavating and
filling with suitable murum type or good soil available material shall be
applicable in case such treatment is found essential.
13
To sustain thrust caused by internal pressure, concrete anchor blocks should be
provided at all changes of direction, tees, blank ends, large reductions in diameter
and valves.
Metal marker tape can be laid into the final backfill to enable electronic location of
the pipe line, if required.
PVC solvent cement is quick drying, therefore it shall be applied as quickly and
carefully as possible and in consistence with good workmanship. For larger sizes, it
is advisable for two workers to work simultaneously on the pipe and socket. Within
20 sec after the last application of solvent cement, insert the pipe into socket in a
single steady and every controlled but forceful action.
15
15.5 Screwed or threaded joint
These are similar to the joints used with metal pipes. If the pipe has to be joined by
screw threads, only thick walled pipe should be used and cut with taper threads.
Some manufacturers supply pipes with factory cut threads. Threaded pipes shall not
be subjected to a pressures exceeding two-thirds of the rating for unthreaded pipes.
Injection moulded threaded joints are used for jointing PVC to metal pipes. Injection
moulded threads are less notch sensitive than cut threads.
16.1 General
All pipelines should be tested before being brought into service. The test
should be a hydrostatic test performed by filling the pipeline with water and
raising the pressure to the selected test pressure and maintaining this for a
sufficient period to allow for absorption of water by the pipe material.
`16.2 Site Test Pressure
The test should confirm to following conditions
a) be carried out at ambient temperature;
b) be applied for at least 1 h, but not more than 24 h; and
c) not exceed 1.5 times the maximum rated pressure of the lowest rated
component.
16.3 Test Procedure
Where,
Q = 4.5 liters per 1.6 km per 25 mm of nominal bore per 30 m head of test
pressure per 24 hours.
On completion of any test, the residual pressure should be released
slowly and in a carefully controlled manner.
All defects revealed in the test should be rectified and the procedure
repeated until a satisfactory result is obtained.
If any leakage is found during testing of pipeline, Contractor will have to
attend the same immediately and rectify at his cost . If Contractor fails to
rectify the defect, the entire length of pipeline between two adjacent
outlets shall be rejected. If any intermediate payment is made to the
Contractor for portion under rejection, the same shall be recovered from
the outstanding dues of the Contractor.
17
17.0 Backfilling of Pipe Trenches
(a) The type of material used for backfilling and the manner of depositing
the material, shall be subject to approvalby the Engineer-in-Charge.
(b) The backfill material shall be placed to the line and grades as shown on
drawings or as prescribed in this paragraph or as directed by the Engineer-in-
Charge.
(c) The backfill material shall be placed carefully and spread in uniform
layers of not more than 15cm thickness, with the first layer watered and
compacted by stamping or by mechanical means. The backfill shall be brought
up as uniformly as practicable on both sides of pipe to prevent unequal
loading.
(d) Only soft earth and gravel of good quality free from boulder, roots,
vegetable matters etc. shall be used for refilling of trench upto 300mm above
the top of the pipe. If sufficient quantity of suitable (Sharp edge stone free)
excavated earth is not available, the trench shall be filled by borrowed gravel
material upto 300 mm above top of pipeline. Remaining trench can be filled
with available material.
(e) When compacting the soil against steep rock, abutment walls of
concrete structures, rollers shall not be used close to structures as structural
damage is very likely more particularly when structures have not been fully
cured. The size and weight of equipment will depend on nature of material,
the height and load assumed in design of structure. The backfill close to the
structure up to the rolled layer shall be compacted in suitable uniform layers,
using pneumatic / hand tampers as appropriate for dry density at average
bulk density (+/- 10%). The moisture content of the earth fill placed against
the rock or the structure shall be on higher/lower side of OMC by about 2%
or so, to allow it to be compacted. Profuse watering shall be done to pervious
materials (sand) before compaction as per instruction of the Engineer-in-
Charge. Compaction at junction of earthwork and backfill around the
structure shall be carried out with special care.
(f) The trench shall be refilled so as to built-up the original ground level.
18
18.4 The contractor shall show all this blocks jointly to the Engineer-in-charge or
his representative, representative of WUA, concern farmers sharing the
boundaries, TPI, any other stake holders in the command.
18.5 Contractor shall maintain these blocks in proper order during operation &
maintenance period of the contract. Any damage done to these blocks for
the reasons whatsoever shall be made good at the cost of contractor.
18.6 The contractor shall submit the location of such blocks with specific
identification marks with schedule on a special command area map.
18.7 The map of marking of the block shall be handed over to WUA while handing
over the command area.
18.8 The Geotagging map showing Latitude and Longitude value of each apex of
laid pipeline shall be submitted to Department and WUA for future
reference.
18.9 The contract shall fix information boards of 1.2 m x 0.9 m size at various
location as directed by Engineer-in-charge. On this boards, salient features of
the work (eg. Pipe diameter, pipe type, discharge, any other specific details
suggested by Engineer-In-Charge) shall be written.
19
otherwise specified. Labours for collecting samples and transportation of
the samples to quality control authorities for test shall be provided free
of cost by the contractor. Also electricity, fuel, water curing tank and
stores etc shall be provided free of cost by the contractors.
(b) The materials shall be tested in QC laboratory or at any other place
directed by the Engineer In-charge. The Contractor shall obtain the test
results from the concern authority and the results given by such
authorities shall be considered to determine whether all materials,
workmanship are of respective standard described in contract and in
accordance with the instructions of the Engineer In-charge. The
Contractor’s representatives shall, however, be given access to all
operations and tests that may be carried out as aforesaid so that he may
satisfy himself regarding the procedure and methods adopted. It shall
then be the Contractor’s responsibility to produce on the work, materials
and finished item to the standard as determined by the laboratory tests
or to take follow up action to rectify the quality.
(c) Testing charges for testing of Cement, TMT bars, all types of pipes and
specials including cost of samples and its collection shall be borne by the
Contractor.
(d) The Contractor shall make suitable arrangements to see that one of his
representatives remains present at the time of taking samples and shall
authenticate the facts. If the Contractor, fails to keep his representative
present at site at the time of taking samples or fail to provide required
labours and other equipment to collect the samples, the same shall be
taken by the Engineer In-charge, and the samples selected shall be
considered as authentic. The cost incurred by the Engineer-In-charge
when the Contractor fails to provide required men and materials for
collecting samples and or their transport shall be recovered from the
Contractor.
20
Sr.
Personnel with Qualification Nos.
No.
1 Quality Assurance Engineer(Civil One
Engineering Graduate with 2 Year
experience in QA testing and report
generation work)
2 Laboratory Assistants(Twevlth Pass with
Two to Four
Science subject with 2 year experience in
(As per work)
testing of material)
3 Laboratory Attendants Two to Four
(One for each L.A.)
Sr.
Work Apparatus for Tests
No.
1 Earth Work – Field density, Moisture Content,
Field testing Equipments Sieves for Sand & Metal.
2 Concrete Work - Silt, Gradation, Moisture Content,
Slump, Cube Moulds&CTM
20.4 It is the responsibility of the contractor to assure the desired qualityof work.
Whenever the testing of construction materials, pipes are required as per the
detailed specifications or otherwise required by the Engineer-in-Charge,the
same shall be carried out at the laboratory, selected by the Engineer-in-
Charge at Contractor’s cost. The other tests of mortar,concrete,sand, coarse
aggregates etc.shall be carried out in field laboratory set up by the contractor
in presence of quality control representative at contractors cost. Contractor
shall through this procedure assure the quality of work.
20.5 The materials,mixes and any other rrangements,including labours,shall be
supplied by the contractor.The samples fo testing shall be taken in the
presence of Engineer-in-Charge or his representative /QC present on site. The
contractor or his authorized representative shall have a free access in these
laboratories,to get himself satisfied about procedures of testing etc. Even if
the contractor or his representative fails to remain present while collecting
samples or testing,the results will be considered as authentic and binding on
the contractor.
20.6 Contractor shall provide all test reports of material used in the work as
desired from the NABL (National Accreditation Board for Testing & Calibration
Laboratories) approved laboratories and from Quality Control, MERI
laboratories of the WRD. Contractor shall provide periodical quality assurance
report (Weekly/fortnightly/monthly) to Engineer in Charge along with proofs
21
in support of quality of material brought for the work, the process/ execution
of work is as per specification.
20.7 Contractor shall submit the account of all materials brought for the work,
which are necessary for execution of work and any other data necessary to
assess the quality of work.
20.8 If he fails to fulfill the above requirement, the required manpower for testing
and field laboratory with required equipments will be deployed by the
Engineer in charge and the charges for the same will be recovered from the
contractor.
21.1 The contractor shall operate and maintain the complete pipe distribution
network for the period of 5 (five) years after commissioning. Out of this
period, during last two years the operation of the schemes shall be done by
the contractor jointly along with WUA. On completion of O & M period, the
system shall be handed over to WUA
21.2 During rotation period, once in every year, the Contractor shall perform
hydraulic test to the satisfaction of Engineer In-charge to verify the flow of
designed discharge, detect or confirm any leakage in the system and rectify
at his own cost. The testing shall preferably be conducted jointly with
members of WUA/representative of Engineer In-charge, technical
representative of contractor and any other stake holder.
21.3 On completion of every Irrigation season, the contractor shall flush the pipe
line from its tail flush valve so that any siltation, vegetation or obstruction is
cleaned and pipe is able to flow designed discharge for next season.
21.4 During the O & M period, contractor shall give training to the members of
WUA about O & M of PDN work and its efficient use and protection of the
system from any damages.
21.5 The contractor shall prepare a detail map of the permanent marking along
the alignment of pipe and submit the same to Engineer In-charge. The
Engineer In-charge shall verify and endorse the location of the marking and
handover these signed maps as a permanent record to WUA. Along with this,
the detailed Geotagged map of laid pipeline shall also be handed over to
WUA.
21.6 In association of the members of WUA, the Engineer In-charge shall confirm
the release of designed discharge through every outlet before handing over.
In case of any short fall or defect, it should be made good from the contractor
at his own cost.
22.0 Mode of Measurement and Payment
22.1 Measurement
The net length of pipes as laid or fixed shall be measured in running meters
correct to a cm. Specials shall be excluded and measured in running meters
or numbers as specified by Engineer-in-charge and paid for separately under
22
the relevant item. The portion of the pipe overlapped at the joints shall not
be included in the length of pipe work. Excavation, refilling, anchor blocks,
thrust blocks wherever required shall be measured and paid for separately
under relevant items of work.
22.2 Payment
The break up to payment for supplying, laying, jointing & hydraulic testing of
pipe line shall be as under:-
A) 80% of the payment will be released after supplying, lowering, laying,
jointing and third party inspection of pipes in one WUA area.
B) Balance 10% of the payment will be released after satisfactory hydraulic
testing of pipeline and backfilling of trenches.
23
Govt. of Maharashtra
Water Resources Department
SPECIFICATION FOR
GLASS FIBER REINFORCED
PLASTIC PIPES (GRP)
2020
0
SPECIFICATION FOR GLASS FIBER REINFORCED PLASTIC PIPES
(GRP)
1.0 Introduction
Glass fibre reinforced Plastic (GRP) pipe is a machine made tubular pipe
containing glass fibre reinforcements embedded in or surrounded by cured
thermosetting resin. The composite structure may contain silicious aggregates,
fillers, thixotropic agents. Thermoplastic or thermosetting liner and/ or surface layer
may be provided for pipe.
As with many other composite materials, the two materials supplement each
other to form a stronger compound. Plastic resins are strong in compressive
loading; the glass fibers are very strong in tension. By combining the two
materials, GRP becomes a material that resists both compressive and tensile forces
very well.
The Contractor shall provide on-site training on GRP pipe laying, jointing,
testing and maintenance etc., to the personnel authorized by Engineer-in-charge.
The contractor should provide technical Manual on GRP pipes including precautions
to be taken during operation of the pipeline.
1
mentioned here but pertaining to the use of GRP Pipes form part of these
Specifications.
IS 12709 Glass Fiber Reinforced Plastics (GRP) pipes, joints and fittings for
use for Potable water supply
IS 13916 Code of practice for Installation of Glass Fiber Reinforced Plastic
(GRP)piping system
IS 14402 GRP pipes joints and fittings for use sewerage, industrial
waste and water (Other than Potable)
IS 11273 Woven roving fabrics of 'E' glass fiber
IS 11320 Glass fiber rovings for the reinforcement of
polyester and epoxide resin systems
IS 11551 Glass fiber chopped strand mat for the reinforcement of
polyester resin system.
IS 5382 Rubber sealing rings for gas mains, water mains and sewers
3.1 Resins- Appropriate type of unsaturated polyester resins system confirming to IS 6746
shall be used. The resin and additives used shall be such that they contain no
ingredients, that is, in an amount that has been demonstrated to migrate into water
in quantities that are considered to be toxic.
3.2 Glass Fiber Reinforcement- Glass fiber reinforcement shall be commercial grade E type
(i.e which does not contain more than 1% by mass of alkali )and shall conform to IS
11273, IS 11320 or IS 11551 as appropriate.
3.3 Aggregates- Silicious sand of size range between 0.05mm and 0.8mm may be
incorporated in composite structure.
3.4 Filler- Inert Fillers (with particle size below 0.05mm) may be incorporated either on
their own or with aggregates.
3.5 Additives- Additives may be incorporated for modifying the properties of the resin.
4.2.2 Stiffness Class (SN) : Four Stiffress classes of pipes are 4 namely A,B,C, and D
correspond to minimum pipe Stiffness valve of 62,124, 248 and 496 kPa
respectively at 5 % deflection.
3
5.0 Sampling criteria for Selection of Pipe for Testing Purpose
All pipes of same pressure class, stiffness Class and produced under relatively
uniform composition and condition of manufacture shall constitute a lot One pipe
selected at random from a lot shall be checked for conformance to the
dimensions,
workmanship, pipe stiffness, Hydraulic test, longitudinal strength test, hoop tensile
strength test and additional tests to establish potability of water as mentioned in
following para No. 6.0
The lot shall be declared as conforming to the requirements of the specification, if
the sample pipe meets the requirements of all the tests, otherwise not.
6.1 Dimensions
a. Inside Diameter
Inside diameters of pipes shall be within the range given in following Table
No.1 and shall meet the tolerance as specified in this table
4
Table 1 Specified Inside Diameters and Tolerances
All dimensions in millimeters.
(Reproduced from IS 12709)
Nominal Diameter, Inside Diameter Range, ID Tolerances on
DN Declared ID
Min Max
200 196 204 +/-1.5
250 246 255 +/-1.5
300 296 306 +/-1.8
350 346 356 +/-2.0
400 396 408 +/-2.4
450 446 459 +/-2.7
500 496 510 +/-3.0
600 596 612 +/-3.6
700 695 714
800 795 816 +/-4.2
900 895 918
1000 995 1020
1100 1095 1120
1200 1195 1220
1300 1295 1320
1400 1395 1420 +/-5.0
1500 1495 1520
1600 1595 1620
1800 1795 1820
2000 1995 2020
2200 2195 2220
2400 2395 2420
2600 2595 2620 +/-6.0
2800 2795 2820
3000 2995 3020
b. Outside Diameter
The Outside diameter of pipes shall be as given in following Table No.2,
subject to tolerance as specified in this table.
5
Table No.2 Specified outside diameters and Tolerances
(Reproduced from IS 12709)
Sr. Nominal Outside diameter Outside Tolerance
No. (DN) mm Diameter (OD)
1 200 208 + 2.0
2 250 259 + 2.1
3 300 310 + 2.3
4 350 361 + 2.4
5 400 412 + 2.5
6 450 463 + 2.7
7 500 514 + 2.8
8 600 614 + 3.0
9 700 718 + 3.3
10 800 820 + 3.5
11 900 922 + 3.8
12 1000 1024 + 4.0
13 1100 1126 + 4.3
14 1200 1228 + 4.5
15 1300 1330 + 5.0
16 1400 1432 + 5.0
17 1500 1534 + 5.0
18 1600 1636 + 5.5
19 1800 1840 + 6.0
20 2000 2044 + 6.5
21 2200 2248 +7.0
22 2400 2452 +7.5
23 2600 2656 +8.0
24 2800 2860 +8.5
25 3000 3064 +9.0
d. Wall thickness- The minimum wall thickness at any point shall not be less
than the wall thickness specified in the manufacturer's data sheets. The
manufacturer shall ensure that the wall thickness specified in his data sheet
shall be such as to satisfy the inside or outside diameters as per Table No.1
or Table No.2 above.
6
6.2 Workmanship
Workmanship shall be in accordance with good practice as listed in following
Table No. 3 and shall meet the acceptance criteria specified.
Table no.3 : Allowable Defects (Reproduced from IS 12709)
Name Definition Visual Acceptance Levels
Each length of pipe shall have sufficient strength to exhibit the minimum pipe
stiffness (F/ ∆y) specified in the following Table 4 when tested in accordance
with of IS 12709
7
Table No.4 Pipe Stiffness at 5 percent Deflection
(Reproduced from IS 12709)
8
6.5 LONGITUDINAL STRENGTH TEST
For size up to DN 600 the pipe shall withstand, without failure, the beam loads specified in
following Table 6, when tested in accordance with IS 12709. For pipes sizes larger than DN
600 and alternatively for smaller sizes adequate beam strength shall be demonstrated by
tensile tests conducted in accordance with IS 12709 for pipe wall specimens oriented in the
longitudinal direction. The minimum tensile strength specified in Table 6 shall be complied
with
Table 6 Beam Strength Test Loads and Longitudinal Tensile Strength of Pipe Wall
(Reproduced from IS 12709)
Nominal Beam Load Minimum Longitudinal Tensile Strength in kN/m of
Diameter P Circumference for Pressure Class of
DN kN PN 3 PN 6 PN 9 PN 12 PN 15
200 3.6 102 102 102 102 102
250 5.3 102 102 102 102 110
300 7.1 102 102 102 112 136
350 9.8 102 102 115 131 154
400 13.3 102 102 130 149 177
450 17.8 102 102 138 159 185
500 19.6 102 102 154 176 205
600 28.5 102 123 184 211 246
700 - 102 140 215 246 280
800 - 102 154 231 265 304
900 - 105 174 260 298 341
1 000 - 122 193 290 331 379
1 100 - 127 212 318 363 417
1 200 - 140 212 318 363 431
1300 - 152 226 345 393 498
1 400 - 164 247 371 423 504
1500 - 175 265 397 454 540
1 600 - 185 283 423 484 574
1 800 - 206 318 476 545 646
2 000 - 231 329 492 563 678
2 200 - 254 361 541 619 745
2 400 - 280 394 591 676 813
2 600 - 301 427 640 732 880
2 800 - 326 459 690 789 949
3 000 - 347 492 739 844 1 016
9
Table 7 Minimum Hoop Tensils Strength of Pipe Wall
(Reproduced from IS 12709)
Nominal Minimum Hoop Tensile Strength in kN/m Width of
Diameter Circumference for Pressure Class
(mm)
PN 3 PN 6 PN 9 PN 12 PN 15
200 122 244 366 488 610
250 152 304 456 608 760
300 182 364 546 728 910
350 213 426 639 852 1 065
450 243 486 729 972 1 215
500 304 608 912 1 216 1 520
600 365 730 1 095 1 460 1 825
700 425 850 1 275 1 700 2 125
800 486 972 1 458 1 944 2 430
900 547 1 094 1 641 2 188 2 735
1 000 608 1 216 1 824 2 432 3 040
1 100 668 1 336 2 004 2 672 3 340
1200 729 1458 2187 2916 3645
1300 790 1580 2369 3159 3949
1 400 851 1 702 2 553 3 404 4 255
1500 911 1823 2734 3645 4556
1 600 972 1 944 2 916 3 888 4 860
1 800 1 094 2 188 3 282 4 376 5 470
2 000 1 215 2 430 3 645 4 860 6 075
2 200 1 337 2 674 4 011 5 348 6 685
2 400 1 458 2 916 4 374 5 832 7 290
2 600 1 580 3 160 4 740 6 320 7 900
2 800 1 701 3 402 5 103 6 804 8 505
3 000 1 823 3 646 5 469 7 292 9 115
10
7.0 Marking on Pipes
Each pipe shall be indelibly marked in English language at either end of each
pipe. The marking shall show the following.
1. Manufactures name or trademark.
2. Grade of raw material
3. Pressure rating.
4. Nominal diameter
5. Lot/batch No. of manufacturer.
6. BIS certification mark.
7. Third Party Certification mark for each lot
8. Name of Department/Project for pipe which pipes are manufactured.
9. Any other important matter that the manufacturer or purchaser deems fit to
be inscribed.
11
9.0 Stacking Of Pipes
Following precaution shall be taken so as to eliminate potential damage to
pipes.
Pipes and fittings with diameters of less than 1.0 m may be stored directly on
sandy soil, the ground should be flat and free from sharp, projection and
stones/rocks bigger than 40 mm in diameter or of other potentially damaging
debris.
Pipes with diameters greater than 1.0 m may be stored on their delivery
cradles at a maximum distance of 6 m c/c.
• If the surface is not flat or is sloping, then all the pipes shall be checked to
prevent rolling.
• All rubber rings, gaskets and other items shall be stored in a cool, dry and dark
place to avoid damage of any kind.
10.0 Valves
For PDN work, various Valves as mentioned below are required to be provided on
pipeline at various location.
10.1 Air Valve :
The effect of air valve in the long-distance water pipelines are in the following
three areas: firstly, in the waterfilled stage of the pipeline, filled with water by a
certain velocity, the air valve can discharge the remained gas in the pipe;
secondly, at the normal working stage, the air valve can discharge the small
amount of gas gathered in the pipe timely; finally, during the pump failure or
maintenance stages, the air valve will replenish the gas into the pipe to break the
vacuum. According to the orifice size, displacement and work pressure, air valve
is divided into high pressure trace exhaust valve, low pressure air release valve
and combined air valve.
10.2 Scour Valve :
These Valves are generally provided to drainout the pipeline. The exact location
of Scour valves is frequently influenced by opportunities to dispose off the water.
Where the main pipeline crosses a stream or drainage structures, there will
usually be a low point in the line but if the main pipeline goes under the stream
or drain, it cannot be completely drained into the channel. In such a situation it
is better to locate a scour connection at the lowest point that will drain by gravity
and provide for pumping out the part below the drain pipeline.
10.3 Control Valve :
A control valve is a valve used to control fluid flow by varying the size of the flow
passage as directed by a signal from a controller. This enables the direct control
of flow rate and the consequential control of process quantities such
as pressure, temperature, and liquid level.
Common types of control valve are as given below.
A) Sliding Stem
12
Globe valve
Angle body valve
Angle seat piston valve
B) Rotary
Butterfly valve
Ball valve
C) Other
Pinch valve
Diaphragm valve
All equipments shall be of standard and approved make and precision, and
shall be made available in advance of starting of the work. All equipment
shall be maintained, repaired and got tested and certified as and when
required for its accuracy from the standard test houses or from the
manufactures and to the satisfaction of the Engineer-In-Charge.
13.2 The usable excavated material available from the excavated trenches (PDN)
shall be used in backfilling. If such usable material is in excess of the
requirement of backfilling, the same shall be deposited in the spoils as and
where directed by the Engineer In-charge. Unuseful material from excavation
shall be deposited in spoils as and where directed by Engineer-In-charge.
14
13.3 Surface or sub-soil water met with during trench excavation (PDN) and
structure excavation shall be diverted to nearby drain/nalla by cutting an open
channel from trench. When the drain/nalla bed is higher than the sub-soil
water level met with, the bailing out by suitable means of pumping shall be
resorted to for dewatering sub-soil water below the drain/nalla bed level. No
distinction shall be made as to whether the material being excavated is dry,
moist, wet or slushy. The Contractor shall have to excavate the PDN pipe
trench and structure in under water level conditions also i.e. under
wet/slushy condition after providing sufficient arrangement of dewatering.
The material excavated under water level condition which requires
intermediate stacking for drying shall have to be rehandled. No extra payment
for efforts for drying out of soil, re-handling of dry soil, etc. shall be given. No
payment for extra efforts for excavation under this condition shall be made.
13.4 Over excavation performed by the Contractor for any purpose or reason,
except for additional excavation as may be directed by the Engineer-In-charge,
shall be rectified at the cost of the Contractor. Filling and compaction for such
over excavation using the material as directed by the Engineer In- Charge shall
also be at the cost of the Contractor.
13.5 In the PDN and structure section where expansive type of the soil such as CH
type of soil is encountered and over which PDN cannot be directly laid, the
PDN trench and structure shall be over excavated to the extent as directed by
the Engineer In Charge and such over excavated section shall be filled with
suitable murum type soil to be placed in uniformly compacted layers as
directed by the Engineer In Charge. The over excavation made in such strata,
filling by suitable soil, and watering and compacting such soil will be paid
separately under relevant items. Above provision for over excavating and
filling with suitable murum type or good soil available material shall be
applicable in case such treatment is found essential.
15
Place the pipe in the trench, taking care to dig a small hollow at each end so that
the groove and the socket are well separated from the sand and gravels in the
bottom of the trench.
Anchor the first pipe section laid according to the method described and leave
its ends free along a space enough for insertion of the next section and for
checking. Place the next pipe section in the trench and leave enough space for
the operator to be free to move and to work between the two pipe sections so
as to carry out the cleaning and checking operations.
Clean the coupling area of the joint once more with a cloth and also clean the
flared portion of the lead-in using suitable lubricant.
Clean the groove again, take the rubber ring gasket and lubricate it by running it
between the hands and checking at the same time, it being in good condition. It
should be ensured that every portion of the ring or inside of the socket must not
lacks lubricant as it will impair good insertion of the pipe.
For socket and spigot type of joint, pass the rubber ring under the pipe until it
settles into the groove, then pull it forcibly upwards and follow the ring with the
hands so that three quarters of it is positioned in the groove, then lift the ring
above the upper generating line of the pipe forcibly and then release it so that it
falls into the groove thus being freed of any twists.
Run the hands around the pipe to check that the whole of the packing is in its
seating and, in the case of large diameter pipes, smear lubricant again above the
inserted rubber ring gasket/packing.
Align and bring together the two pipe sections until rubber ring touches the
flared portion of the lead-in. When this has taken place, examine the position of
the ring and above all, ensure that there are no sand or other foreign bodies
present.
Fit the socket onto the spigot very slowly dwelling half way along the coupling
area, and check the position of the packing visually.
Proceed with the joint until the socket is halted by the abutment ledge. The next
pipe section should not be fitted until the previous pipe section has been
anchored with an overlay of sand.
Check the rubber ring gasket/packing after the joint has been coupled. This check
must always be carried out and is performed with a blade of steel or of another
metal having a thickness of 0.4/0.5 mm, a width of 15 mm and any length greater
than 200 mm, the blade being inserted into the annular space between the
socket and the spigot. This check should be conducted along all the
16
circumference where the packing is compressed so as to ensure that the rubber
ring has a homogeneous depth and is therefore correctly positioned in its seating.
If the ring is found to be seated differently at one point than other points or if
there is any doubt, disconnect the joint, check the rubber ring and replace it if it
shows any permanent signs of faulty seating, check once more the coupling area
of the joint, the flared, lead-in of the socket and the groove on the spigot. When
re-inserting the pipe section, take extra care to align the pipes perfectly. When
uncoupling pipe sections, never use chains or steel cables in direct contact with
the pipes.
Check once again the position of the ring with the blade.
RCC thrust blocks should be provided at bends and at places of reductions in
cross section to take care of thrust.
The pipe should be uniformly and continuously supported throughout its whole
length with firm stable bedding material. The bedding material should be placed
so as to give complete contact between the bottom of the trench and pipe. The
bedding material should be watered and compacted.
17
15.1.2 Spigot and Socket Joint with Double Watertight Rubber Ring Gasket/Packing
This joint is made with double rubber ring and is suitable for high pressure (3
PN and above).
15.1.3 Double Socket Coupling Joint with Watertight Rubber Ring Gasket/Packing
This joint is made with double socket type coupling and is suitable both for
low and high pressure.
The pipe to be connected shall be placed on the bed with the sufficient
distance from previously joined pipe to allow lowering of pipe with the
coupling into position. Pull the pipe with coupling on to the previously laid
pipe by means of jack after clamping the pipe. Care shall be taken in the
alignment of the coupling with pipes.
18
15.2.2 Spigot and Socket Joint with Glue and Overlay
This type of joint is suitable both for low and high pressure. Gluing the joint
should be done with suitable adhesive and overlay with the same material as
used in pipe. The minimum thickness of overlay shall be 1.5 times of the
thickness of pipes.
19
15.2.4 Flanged Joint
The flange joint is used for connecting the valves, pumps or any other
apparatus or pipes of different materials. The flanged joint is made from the
same material as the pipe.
20
16.3 Test Procedure
The following procedure is recommended for GRP pipe testing:
a) GRP pipelines shall be pressure tested at ambient temperature.
b) During the test period, make-up water is continuously added to maintain
the pressure.
16.4 Leak Detection
Each full length of pipe section, fittings and joints shall be leak tight. If any
leakage is found during testing of pipeline, Contractor will have to attend
immediately and rectify at his cost. If Contractor fails to rectify the defect, the
entire length of pipeline between two adjacent outlets shall be rejected and
not accepted. The payment shall not be made for the rejected work. If any
intermediate payment is made to the Contractor for portion under rejection,
the same shall be recovered from the outstanding dues of the Contractor.
23
20.0 Quality Control and Quality assurance
20.1 On award of contract, the Contractor will have to provide adequate quality
assurance setup including Quality Assurance Engineer backed with suitable
laboratory assistants, labours and well equipped laboratory for taking
necessary field test required as per specifications and as per instructions of
Engineer in charge.
20.2 Following minimum persons shall be employed by the contractor at work site
for Quality Assurance.
24
20.6 Contractor shall provide all test reports of material used in the work as
desired from the NABL (National Accreditation Board for Testing &
Calibration Laboratories) approved laboratories and from Quality Control,
MERI laboratories of the WRD. Contractor shall provide periodical quality
assurance report (Weekly/fortnightly/monthly) to Engineer in Charge along
with proofs in support of quality of material brought for the work, the
process/ execution of work is as per specification.
20.7 Contractor shall submit the account of all materials brought for the work,
which are necessary for execution of work and any other data necessary to
assess the quality of work.
20.8 If he fails to fulfill the above requirement, the required manpower for testing
and field laboratory with required equipments will be deployed by the
Engineer in charge and the charges for the same will be recovered from the
contractor.
25
22.0 Mode of Measurement and Payment
22.1 Measurement
The net length of pipes as laid or fixed shall be measured in running meters
correct to a cm. Specials shall be excluded and measured in running meters or
numbers as specified by Engineer-in-charge and paid for separately under the
relevant item. The portion of the pipe overlapped at the joints shall not be
included in the length of pipe work. Excavation, refilling, anchor blocks, thrust
blocks wherever required shall be measured and paid for separately under
relevant items of work.
22.2 Payment
The break up to payment for supplying, laying, jointing & hydraulic testing of
pipe line shall be as under:-
A) 80% of the payment will be released after supplying, lowering, laying,
jointing and third party inspection of pipes in one WUA area.
B) Balance 10% of the payment will be released after satisfactory hydraulic
testing of pipeline and backfilling of trenches.
C) Remaining 10% amount will be withheld and it will be released after
successful maintenance and operation for a period of five years after
commissioning of work of respective WUAs.
The schedule of release of this 10% will be in following manner,
1) After Successful Operation and Maintenance for First year-2%
2) After Successful Operation and Maintenance for Second year-2%
3) After Successful Operation and Maintenance for Third year-2%
4) After Successful Operation and Maintenance for Fourth year-2%
5) After Successful Operation and Maintenance for Fifth year-2%
26
Govt. of Maharashtra
Water Resources Department
Specifications for
Pre-stressed Concrete Non Cylinder
Pipes (P.S.C.)
2020
0
Specifications for Prestressed Concrete Non-Cylinder (P.S.C.) Pipe
1.0 Introduction
Prestressed Concrete Non-Cylinder Pipe is suitably compacted concrete core
longitudinally prestressed with pretensioned high tensile steel wire embedded In the
concrete, circumferentially prestressed and coated with cement mortar or concrete
to protect the circumferential prestressing wire, to withstand internal pressure and
external design loads.
The Contractor shall provide on-site training on PSC pipe laying, jointing, testing and
maintenance etc., to the personnel authorized by Engineer-in-Charge. The contractor
should provide technical Manual on PSC pipes including precautions to be taken
during operation of the pipeline.
1
IS: 784 Specifications for Prestressed Concrete pipes (Including specials)
IS:783 Code of practice for Laying of Concrete Pipes
IS:3597 Methods of Test for Concrete pipes
IS 1785 Specifications for Plain Hard –drawn steel wire for Prestressed
Part 1, Part 2 Concrete.
IS 383 Specifications for coarse and fine aggregates from natural sources for
concrete
IS 1566 Specifications for Hard Drawn Steel Wire for Concrete Reinforcement
IS:2062 Specification for steel for General Structural purposes
IS: 5382 Specification of Rubber Sealing Rings for Gas Mains, Water Mains & Sewers
Raw materials used to manufacture PSC Pipes are cement, aggregates, water,
admixture, steel reinforcement, steel for specials, rubber sealing rings.
3.1 Cement
The cement used in the manufacture of PSC pipes shall conform to one of the
following.
1) 43/53 grade Ordinary Portland Cement conforming to IS:8112/IS 12269
2) Rapid Hardening Portland cement conforming to IS: 8041
3) Portland Slag cement (with not more than 50% slag) conforming to IS: 455
4) Sulphate resisting Portland Cement conforming to IS: 12330
3.2 Aggregate
The coarse and fine aggregates shall conform to I.S.383. The maximum size of
aggregate shall not exceed one third the thickness of the pipe or 20mm
whichever is smaller. Silt Content in fine aggregates shall be less than 3
percent. The fineness modulus of aggregates for coating shall be between 2.6
to 3.2.
3.3 Water
The water used in the preparation of concrete mix shall be clean and free from
harmful or injurious compounds such as acids, alkali, oil, organic material or
other substances and shall conform to the requirements of mixing water as per
IS : 456.
2
3.4 Admixtures
Admixtures may be used with the approval of the purchaser. However, use of
any admixture containing chlorides in any form shall be prohibited The
admixtures shall conform to IS 9103.
3.5 Steel wires
Prestressing steel wire shall conform to IS 1785.
3.6 Steel for Specials
Steel plates for Specials shall conform to IS: 2062
3.7 Rubber Sealing Rings
• Rubber sealing ring shall comply with IS 5382
• Every ring shall be visually checked for defects, particularly at joints.
• Sealing ring shall be clearly labeled in bundle to indicate type of joints,
internal diameter and name of manufacturer.
• Not more than 2 splices in each ring shall be permitted.
• Composition of natural rubber in sealing ring shall be as per IS 784.
The Manufacturing of pipes and specials for PSC pipes shall be as per IS 784. The
mould and method of manufacture of pipe shall be such that the form and
dimensions of the finished pipe conform to IS 784 and the surface and edges of the
pipes are clean and true. Various steps involved in pipe manufacturing process are as
given below.
3
Cross-section of PSC Pipe Joint
PSC pipe shall be designed to withstand the combined effects of internal water
pressure & external loads. Design of PSC pipes shall be site specific as internal water
pressure will depend on pipe profile whereas external loads will depend on maximum
cover (i.e. overburden) over the crown of pipe.
All the pipes manufactured under relatively similar conditions in respect of raw-
materials and processing operation, shall be grouped together to constitute a lot Each
lot shall be taken separately for sampling and evaluation, for conformity to the
requirements of IS 784. Scale of sampling shall be as given in following Table No.1.
4
Table No.1 Scale of Sampling and No. of Acceptable defective tests
(Reproduced from IS 784)
Pipe selected as per sampling criteria mentioned in above para 5.0 are subject to
following tests before delivery from factory.
6.1 Dimensions
6.1.1 Length -
Length of Pipe shall be 2 to 6m. For pipes upto and including 300mm
diameter, the length shall not be more than 3m.
6.1.2 Nominal internal diameter of the pipe and minimum core thickness
shall be as per following Table No. 2
5
Table 2 Nominal Internal Diameter and Minimum Core Thickness of Pipes
(Reproduced from IS 784)
Nominal Internal Minimum Core Nominal Internal Minimum Core
Diameter of Pipe Thickness Diameter of Pipe Thickness
(mm ) (mm ) (mm ) (mm )
200 35 1300 75
250 35 1400 75
300 35 1500 80
350 35 1600 85
400 35 1700 90
450 35 1800 95
500 35 1900 100
600 40 2000 105
700 40 2100 110
800 45 2200 115
900 55 2300 120
1000 60 2400 125
1100 65 2500 130
1200 70 - -
Note : Core thickness for pipes needs to be designed based on internal hydrostatic pressure and
external overburden, based on actual site conditions.
6.1.3 The deviation from straight line taken between two points one meter
apart, along the pipe barrel shall not exceed 5mm.
6.1.4 The pipe shall be free from local depressions or bulges greater than
5mm extending over a length, in any direction.
7
All pipes shall be loaded in trucks by mechanical crane/ tripod and unloaded
carefully using crane/ tripod. No unloading using crow bars or on tires will be
allowed in any case. Rubber belt may be used instead of crow bars or chains.
Pipes should be loaded at the works for transportation, either by rail or by road, in
such a way that they are secure and that no movement can take place on the
vehicle during transit. The same care is needed if pipes are to be transferred from
one vehicle to another, however, short the journey may be.
Un-loading of pipes should be carried out by means of chain block with shear legs
or crane of adequate capacity, using properly designed slings and spreader beams
or specially designed lifting beams. Slings should be placed around the
circumference of the pipe and should not be threaded through the pipe bore' as
the latter method may damage the jointing surfaces. For the same reasons, hooks
located in the ends of the pipes should not be used.
(c) The check profile shall be located 30m apart or closer as directed by the
Engineer In-Charge so as to ensure execution of all slopes, steps and elevations
to the profile or profiles indicated in the approved drawings. All important
levels and all control points with respect to benchmarks and reference lines
shall be fixed and correlated by the Contractor. The Contractor is fully
responsible for maintaining all setting out work & Benchmark established by
Engineer-In-charge.
(d) All materials, labour and equipments (theodolites, levels, distometre, etc.) for
setting out works including construction of benchmarks in concrete,
10
reference lines, check profiles and surveys as may be required at the various
stages of construction shall be supplied by the Contractor at his cost. For this
following numbers of minimum equipments shall be provided and
maintained in good working condition by the Contractor.
1. Total station and its accessories 1 set
2. Theodolites (Accuracy 1 second) 1 No.
3. Levels 2 Nos.
4. Staves 4 Nos.
5. Tapes, chains, ranging rods etc. As required
All equipments shall be of standard and approved make and precision, and
shall be made available in advance of starting of the work. All equipment
shall be maintained, repaired and got tested and certified as and when
required for its accuracy from the standard test houses or from the
manufactures and to the satisfaction of the Engineer-In-Charge.
11
13.4 Over excavation performed by the Contractor for any purpose or reason,
except for additional excavation as may be directed by the Engineer-In-charge,
shall be rectified at the cost of the Contractor. Filling and compaction for such
over excavation using the material as directed by the Engineer In- Charge shall
also be at the cost of the Contractor.
13.5 In the PDN and structure section where expansive type of the soil such as CH
type of soil is encountered and over which PDN cannot be directly laid, the
PDN trench and structure shall be over excavated to the extent as directed by
the Engineer In Charge and such over excavated section shall be filled with
suitable murum type soil to be placed in uniformly compacted layers as
directed by the Engineer In Charge. The over excavation made in such strata,
filling by suitable soil, and watering and compacting such soil will be paid
separately under relevant items. Above provision for over excavating and
filling with suitable murum type or good soil available material shall be
applicable in case such treatment is found essential.
12
15.0 Jointing of Pipes
15.1 Jointing of pipes shall be done as per procedure mentioned in IS 783. The
sections of the pipe should be jointed together in such a manner that there
shall be as little unevenness as possible along the inside of the pipe. As soon
as joint assembly is complete, the last pipe laid should be firmly restrained in
position until backfilling over it is complete and well compacted.
15.2 The joint are mainly of two types, viz. Rigid joints and Flexible joints.
15.2.1 Rigid joints - In this type of joint, the water seal is effected by cement
mortar or similar material which will not allow any movement between the
two pipes. These joints can be of three types as mentioned below.
I. Socket and Spigot Joint - The annular space between socket and spigot is filled
with cement mortar (1 : 2). This joint is used for low pressure pipe line.
II. Collar Joint - Collars of 15 to 20 cm wide cover the joint between two
pipes. A slightly damp mixtures of cement and sand is rammed with
caulking tool.
III. Flush Joint : This joint can be internal or external as given below.
13
(a) Internal flush joint - This joint is generally used for culvert pipes of 900
mm diameter and over. The ends of the pipes are specially shaped to
form a self centering joint with an internal jointing space 1.3 cm wide.
The finished joint is flush with both inside and outside with the pipe
wall. The jointing space is filled with cement mortar mixed sufficiently
dry to remain in position when forced with a trowel or rammer.
(b) External flush joint - This joint is suitable for pipes which are too small
for jointing from inside. Great care shall be taken in handling to .ensure
that the projecting ends are not damaged as no repairs can be readily
effected from inside -the pipe.
15.2.2 Flexible Joints - In this type of joint, the water seal is effected because
of contact pressure between the sealing rubber ring (or similar material)
and the pipe surface. These are mainly of two types.
14
I. Roll on Joint - A rubber ring ( circular in cross-section) is placed at or near
the end of the spigot and rolls along it as the spigot enters the socket.
17
18.4 The contractor shall show all this blocks jointly to the Engineer-in-charge or his
representative, representative of WUA, concern farmers sharing the
boundaries, TPI, any other stake holders in the command.
18.5 Contractor shall maintain these blocks in proper order during operation &
maintenance period of the contract. Any damage done to these blocks for the
reasons whatsoever shall be made good at the cost of contractor.
18.6 The contractor shall submit the location of such blocks with specific
identification marks with schedule on a special command area map.
18.7 The map of marking of the block shall be handed over to WUA while handing
over the command area.
18.8 The Geotagging map showing Latitude and Longitude value of each apex of laid
pipeline shall be submitted to Department and WUA for future reference.
18.9 The contract shall fix information boards of 1.2 m x 0.9 m size at various location
as directed by Engineer-in-charge. On this boards, salient features of the work
(eg. Pipe diameter, pipe type, discharge, any other specific details suggested by
Engineer-In-Charge) shall be written.
18
water curing tank and stores etc shall be provided free of cost by the
contractors.
(b) The materials shall be tested in QC laboratory or at any other place directed
by the Engineer In-charge. The Contractor shall obtain the test results from
the concern authority and the results given by such authorities shall be
considered to determine whether all materials, workmanship are of
respective standard described in contract and in accordance with the
instructions of the Engineer In-charge. The Contractor’s representatives
shall, however, be given access to all operations and tests that may be
carried out as aforesaid so that he may satisfy himself regarding the
procedure and methods adopted. It shall then be the Contractor’s
responsibility to produce on the work, materials and finished item to the
standard as determined by the laboratory tests or to take follow up action
to rectify the quality.
(c) Testing charges for testing of Cement, TMT bars, all types of pipes and
specials including cost of samples and its collection shall be borne by the
Contractor.
(d) The Contractor shall make suitable arrangements to see that one of his
representatives remains present at the time of taking samples and shall
authenticate the facts. If the Contractor, fails to keep his representative
present at site at the time of taking samples or fail to provide required
labours and other equipment to collect the samples, the same shall be
taken by the Engineer In-charge, and the samples selected shall be
considered as authentic. The cost incurred by the Engineer-In-charge when
the Contractor fails to provide required men and materials for collecting
samples and or their transport shall be recovered from the Contractor.
20
21.0 Operation, Maintenance and Handing over of the System
21.1 The contractor shall operate and maintain the complete pipe distribution
network for the period of 5 (five) years after commissioning. Out of this period,
during last two years the operation of the schemes shall be done by the
contractor jointly along with WUA. On completion of O & M period, the system
shall be handed over to WUA
21.2 During rotation period, once in every year, the Contractor shall perform
hydraulic test to the satisfaction of Engineer In-charge to verify the flow of
designed discharge, detect or confirm any leakage in the system and rectify at
his own cost. The testing shall preferably be conducted jointly with members
of WUA/representative of Engineer In-charge, technical representative of
contractor and any other stake holder.
21.3 On completion of every Irrigation season, the contractor shall flush the pipe
line from its tail flush valve so that any siltation, vegetation or obstruction is
cleaned and pipe is able to flow designed discharge for next season.
21.4 During the O & M period, contractor shall give training to the members of WUA
about O & M of PDN work and its efficient use and protection of the system
from any damages.
21.5 The contractor shall prepare a detail map of the permanent marking along the
alignment of pipe and submit the same to Engineer In-charge. The Engineer
In-charge shall verify and endorse the location of the marking and handover
these signed maps as a permanent record to WUA. Along with this, the
detailed Geotagged map of laid pipeline shall also be handed over to WUA.
21.6 In association of the members of WUA, the Engineer In-charge shall confirm
the release of designed discharge through every outlet before handing over.
In case of any short fall or defect, it should be made good from the contractor
at his own cost.
21
22.2 Payment
The break up to payment for supplying, laying, jointing & hydraulic testing of
pipe line shall be as under:-
A) 80% of the payment will be released after supplying, lowering, laying,
jointing and third party inspection of pipes in one WUA area.
B) Balance 10% of the payment will be released after satisfactory hydraulic
testing of pipeline and backfilling of trenches.
C) Remaining 10% amount will be withheld and it will be released after
successful maintenance and operation for a period of five years after
commissioning of work of respective WUAs.
The schedule of release of this 10% will be in following manner,
1) After Successful Operation and Maintenance for First year-2%
2) After Successful Operation and Maintenance for Second year-2%
3) After Successful Operation and Maintenance for Third year-2%
4) After Successful Operation and Maintenance for Fourth year-2%
5) After Successful Operation and Maintenance for Fifth year-2%
----------***----------
22
Govt. of Maharashtra
Water Resources Department
SPECIFICATIONS FOR
PRE-STRESSED CONCRETE
CYLINDER PIPE (PCCP)
2020
0
SPECIFICATIONS FOR PRESTRESSED CONCRETE CYLINDER PIPES
(PCCP)
1.0 Introduction
The Prestressed Concrete Cylinder Pipe (PCCP) comprises of a welded sheet steel
cylinder with steel socket and spigot rings welded to its ends, lined with concrete
suitably compacted and circumferentially prestressed to withstand internal pressure
and external design load. PCCP pipe is subsequently coated with cement mortar to
protect the steel cylinder and prestressing wires.
The Contractor shall provide on-site training on PCCP pipe laying, jointing, testing and
maintenance etc., to the personnel authorized by Engineer-in-Charge. The contractor
should provide technical Manual on PCCP pipes including precautions to be taken
during operation of the pipeline.
Raw materials used to manufacture PCCP Pipes are cement, aggregates, water,
admixture, steel reinforcement, steel for cylinders and specials.
3.1 Cement
The cement used in the manufacture of PCCP pipes shall conform to one of the
following.
1) 43/53 grade Ordinary Portland Cement conforming to IS:8112/IS 12269
2) Rapid Hardening Portland cement conforming to IS: 8041
3) Portland Slag cement (with not more than 50% slag) conforming to IS: 455
4) Sulphate resisting Portland Cement conforming to IS: 12330
3.2 Aggregate
The coarse and fine aggregates shall conform to I.S.383. The maximum size of
aggregate shall not exceed one third the thickness of the pipe or 20mm
whichever is smaller. Silt Content in fine aggregates shall be less than 3 percent.
The fineness modulus of aggregates for coating shall be between 2.6 to 3.2.
3.3 Water
The water used in the preparation of concrete mix shall be clean and free from
harmful or injurious compounds such as acids, alkali, oil, organic material or
other substances and shall conform to the requirements of mixing water as per
IS : 456.
3.4 Admixtures
Admixtures may be used with the approval of the purchaser. However, use of
any admixture containing chlorides in any form shall be prohibited The
admixtures shall conform to IS 9103.
3.5 Steel reinforcement
3.5.1 Prestressing steel wire shall conform to IS 1785.
3.5.2 Untensioned reinforcement may consist of MS bars conforming to IS432
or HYSD bar conforming to 1786
2
4.0 Manufacturing of Pipes and Specials
The Manufacturing of pipes and specials for PCCP pipes shall be as per IS 784.
The mould and method of manufacture of pipe shall be such that the form and
dimensions of the finished pipe conform to IS 784 and the surface and edges of
the pipes are clean and true. Various steps involved in pipe manufacturing
process are as given below.
PCCP pipe shall be designed to withstand the combined effects of internal water
pressure & external loads. Design of PCCP pipes shall be site specific as internal water
pressure will depend on pipe profile whereas external loads will depend on maximum
cover (i.e. overburden) over the crown of pipe.
3
5.0 Sampling criteria for Selection of Pipe for Testing Purpose
All the pipes manufactured under relatively similar conditions in respect of raw-
materials and processing operation, shall be grouped together to constitute a lot Each
lot shall be taken separately for sampling and evaluation, for conformity to the
requirements of IS 784 Scale of sampling shall be as given in following Table No.1.
Table No.1 Scale of Sampling and No. of Acceptable defective tests
(Reproduced from IS 784)
Pipe selected as per sampling criteria mentioned in above para 5.0 are subject to
following tests before delivery from factory.
1) Steel Cylinder Test.
2) Dimensions - Length, Internal diameter, Core thickness, straightness and finish.
3) Hydrostatic Factory Test
4) Permeability Test on Coating
5) Mortar soundness test
6.1 Steel Cylinder Test: During manufacturing, each steel cylinder with steel and spigot rings
welded on shall be subjected to water pressure which stresses the steel to at least 140
N/mm2but not more than 175 N/mm2. While under stress, the assembly, especially
welds shall not show any leakage. If any leakage is found, assembly shall be repaired
and whole assembly retested.
6.2 Dimensions
6.2.1 Length -
Length of Pipe shall be 2m to 6m. For pipes upto and including 300mm
diameter, the length shall not be more than 3m.
6.2.2 Nominal internal diameter of the pipe and minimum core thickness shall be as
per following Table No. 2
4
Table 2 Nominal Internal Diameter and Minimum Core Thickness of Pipes
(Reproduced from IS 784)
Nominal Internal Minimum Core Nominal Internal Minimum Core
Diameter of Pipe Thickness Diameter of Pipe Thickness
(mm ) (mm ) (mm ) (mm )
200 35 1300 75
250 35 1400 75
300 35 1500 80
350 35 1600 85
400 35 1700 90
450 35 1800 95
500 35 1900 100
600 40 2000 105
700 40 2100 110
5
Table No.3 : Minimum wall thickness of joint rings.
(Reproduced from IS 784)
Nominal Internal Diameter Minimum wall thickness of joint rings.
(mm ) (mm )
200 5.0
250 5.0
300 5.0
350 5.0
400 5.0
450 5.0
500 5.0
600 5.0
700 5.0
800 5.0
900 5.0
1000 7.0
1100 7.0
1200 8.0
1300 8.0
1400 8.0
1500 8.0
1600 10.0
1700 10.0
1800 10.0
1900 12.00
2000 12.00
6
Nominal Internal Diameter Minimum wall thickness of joint rings.
(mm ) (mm )
2100 12.00
2200 12.00
2300 14.00
2400 14.00
2500 14.00
6.2.5 The deviation from straight line taken between two points one meter
apart, along the pipe barrel shall not exceed 5mm.
6.2.6 The pipe shall be free from local depressions or bulges greater than 5mm
extending over a length, in any direction.
6.3 Hydrostatic Factory Test
The pipe shall be subjected to hydrostatic test after coating in accordance with
IS 3597. For this test, the pipe is placed on a hydrostatic test bench, filled with
water and pressure has to be raised slowly up to designed factory test pressure.
Pressure shall be maintained by pumping water as per IS 3597.The pipe must
not show leakage Damp or wet patches shall be accepted. If the pipe fails to
pass the test, it can be cured or repaired to improve its water tightness and then
retested. In case the pipe does not stand the rated internal pressure, it shall be
accepted for lower pressure to which it withstands, at the discretion of
Engineer-in-charge, provided all other requirements are conforming to this
standard.
7
6.5 Mortor soundness test
After the mortar coating is cured and prior to transport, the coating on each
pipe shall be checked for delamination and hollows by tapping the exterior with
hammer having head of mass of not more than 0.5 kg. Any hollows or
drumming areas detected by sounding shall be repaired by approved method.
A pipe section must be rolled or otherwise moved, such operation shall be done
slowly and with every reasonable precaution against damage. Any portion of the
lining, coating that may become damaged shall be repaired with polymer Mortar.
All pipes shall be loaded in trucks by mechanical crane/ tripod and unloaded
carefully using crane/ tripod. No unloading using crow bars or on tires will be
allowed in any case. Rubber belt may be used instead of crow bars or chains.
Pipes should be loaded at the works for transportation, either by rail or by road, in
such a way that they are secure and that no movement can take place on the vehicle
during transit. The same care is needed if pipes are to be transferred from one
vehicle to another, however, short the journey may be.
8
Un-loading of pipes should be carried out by means of chain block with shear legs
or crane of adequate capacity, using properly designed slings and spreader beams
or specially designed lifting beams. Slings should be placed around the
circumference of the pipe and should not be threaded through the pipe bore' as the
latter method may damage the jointing surfaces. For the same reasons, hooks
located in the ends of the pipes should not be used.
9
the air valve will replenish the gas into the pipe to break the vacuum. According
to the orifice size, displacement and work pressure, air valve is divided into high
pressure trace exhaust valve, low pressure air release valve and combined air valve.
10.2 Scour Valve :
These Valves are generally provided to drainout the pipeline. The exact location
of Scour valves is frequently influenced by opportunities to dispose off the
water. Where the main pipeline crosses a stream or drainage structures, there
will usually be a low point in the line but if the main pipeline goes under the
stream or drain, it cannot be completely drained into the channel. In such a
situation it is better to locate a scour connection at the lowest point that will
drain by gravity and provide for pumping out the part below the drain pipeline.
10.3 Control Valve :
A control valve is a valve used to control fluid flow by varying the size of the
flow passage as directed by a signal from a controller. This enables the direct
control
of flow rate and the consequential control of process quantities such
as pressure, temperature, and liquid level.
12.2 Demarcation
All materials such as pegs, bamboo’s and strings and templets for
marking out slopes, and labour required for line out should be provided by the
Contractor at his own cost. The center line of excavation shall be clearly
marked by pegs or by stones at each chain or change of direction or at shorter
intervals on curves, in the beginning. The final line out will be done by fixing
reference stone at suitable distances on either side of the center line, beyond
the canal edges so that they are not disturbed during the construction period.
The position of these stones will be marked on the cross section.
12.3 Contractor shall provide and maintain the quarry roads and temporary roads
required for construction activity at his own cost.
12.4 Fixing Permanent Benchmark
(a) Benchmarks fixed by the Survey of India and temporary benchmarks
established by the Engineer In-charge in vicinity of PDN work will serve
as control points for these works. The Contractor shall establish
sufficient number of reference benchmarks for facilitating setting out of
work and taking levels for the purpose of measurements.
(b) Before starting any work, the Contractor shall erect reference
benchmarks, reference lines and check profiles at convenient locations
approved by the Engineer In-Charge. The benchmark concrete block
shall be 200mm x200mm x600mm with 400mm embedded in the firm
ground and 200 mm projecting above ground. The word ‘BM’ showing
value of R.L. in ‘m’ shall be conspicuously carved and painted on the
benchmark.
(c) The check profile shall be located 30m apart or closer as directed by the
Engineer In-Charge so as to ensure execution of all slopes, steps and
elevations to the profile or profiles indicated in the approved drawings.
All important levels and all control points with respect to benchmarks
and reference lines shall be fixed and correlated by the Contractor. The
Contractor is fully responsible for maintaining all setting out work &
Benchmark established by Engineer-In-charge.
(d) All materials, labour and equipments (theodolites, levels, distometre,
etc.) for setting out works including construction of benchmarks in
concrete, reference lines, check profiles and surveys as may be required
at the various stages of construction shall be supplied by the Contractor
at his cost. For this following numbers of minimum equipments shall
be provided and maintained in good working condition by the
Contractor.
11
1. Total station and its accessories 1 set
2. Theodolites (Accuracy 1 second) 1 No.
3. Levels 2 Nos.
4. Staves 4 Nos.
5. Tapes, chains, ranging rods etc. As required
All equipments shall be of standard and approved make and precision, and
shall be made available in advance of starting of the work. All equipment
shall be maintained, repaired and got tested and certified as and when
required for its accuracy from the standard test houses or from the
manufactures and to the satisfaction of the Engineer-In-Charge.
12
13.4 Over excavation performed by the Contractor for any purpose or reason, except
for additional excavation as may be directed by the Engineer-In-charge, shall be
rectified at the cost of the Contractor. Filling and compaction for such over
excavation using the material as directed by the Engineer In- Charge shall also
be at the cost of the Contractor.
13.5 In the PDN and structure section where expansive type of the soil such as CH
type of soil is encountered and over which PDN cannot be directly laid, the PDN
trench and structure shall be over excavated to the extent as directed by the
Engineer In Charge and such over excavated section shall be filled with
13
15.0 Jointing of Pipes
15.1 Jointing of pipes shall be done as per procedure mentioned in IS 783. The
sections of the pipe should be jointed together in such a manner that there
shall be as little unevenness as possible along the inside of the pipe. As soon as
joint assembly is complete, the last pipe laid should be firmly restrained in
position until backfilling over it is complete and well compacted.
15.2 Jointing process of PCCP pipe consist of following steps.
Aligning of pipes at joint locations.
Field welding of socket ring at joint externally.
Fixing of diaper with steel strap at joint location.
Pouring of cement mortar through diaper at joint location.
Filling inside of joints by cement mortar.
15.3 The basic requirements for all joints are as enumerated below.
a) cleanliness of all parts, particularly joint surface;
b) correct location of components;
c) centralization of spigot within socket;
d) provision of the correct gap between the end of the spigot and the back
of the socket
16.0 Field Testing of Pipeline system
16.1 All pipelines should be tested before being brought into service. The test should
be a hydrostatic test performed by filling the pipeline with water and raising the
pressure to the selected test pressure and maintaining this for a sufficient period
to allow for absorption of water by the pipe material.
16.2 AS per I.S.784, the test pressure should be 1.5 times design working pressure.
16.3 Test procedure: Each section should be properly sealed off, preferably with
special stop secured by adequate anchors. The thrust on the stop ends should be
calculated on the full socket internal diameter and the anchors designed to resist
it. It may often be economical to provide .a concrete anchor block of couple of
pipes laid and earth tamped around which has subsequently to be demolished
rather than risk movement of the stop ends during testing. Hydraulic jacks may be
inserted between the temporary anchors and stop ends in order to take up any
horizontal movement of the temporary anchor. All permanent anchors should be
in position and, if of concrete, should have developed adequate strength before
testing begins. The section under test should be filled with water, taking care that
all air is displaced either through vents at the high points, or by using a swab.
After filling, the pipeline should be left under operating pressure for a
period in order to achieve conditions as stable as possible for testing. The length
of this period will depend upon many factors such as initial permeability,
absorption, movement of the pipeline under pressure and the quantity of air
trapped.
More water should be pumped in from a calibrated container until the
required test pressure is reached. The test pressure should be maintained
14
throughout the test by means of continuous pumping. The rate of loss of water
from the container should be determined at regular intervals. The generally
accepted standard for absorbent pipelines such as PSC pipes is 3 liter per
millimeter of pipe diameter per kilometer of pipeline per day for each 30 meter
head-of pressure applied.
16.4 Leak Detection - If the test is not satisfactory, the fault should be found and
rectified. Where there is difficulty in locating a fault, the section under test should
be subdivided and each part tested separately.
If any leakage is found during testing of pipeline, Contractor will have to attend the
same immediately and rectify at his cost within. If Contractor fails to rectify the
defect, the entire length of pipeline between two adjacent outlets shall be
rejected. If any intermediate payment is made to the Contractor for portion under
rejection, the same shall be recovered from the outstanding dues of the
Contractor.
16.5 Final Testing – After all sections have been jointed together on completion of
section testing, a test on the complete pipeline should be carried out. This test
should be carried out at a pressure not less than the working pressure of the
pipeline, care being taken to ensure that the pressure at the lowest point in the
pipeline does not exceed the maximum. During the test, an inspection should be
made of all work which has not been subjected to sectional tests.
16
1 Engineers India Limited, Mumbai
2 R.I.T.E.S. (Rail India Technical Economics Services) Mumbai
3 S.G.S, Mumbai
4 Visvesvaraya National Institute of Technology, Nagpur
5 VJTI, Mumbai
6 CWPRS (Central Water & Power Research Station), Pune
7 CIPET (Central Institute of Plastics Engineering & Technology)
(b) The materials shall be tested in QC laboratory or at any other place directed
by the Engineer In-charge. The Contractor shall obtain the test results from
the concern authority and the results given by such authorities shall be
considered to determine whether all materials, workmanship are of
respective standard described in contract and in accordance with the
instructions of the Engineer In-charge. The Contractor’s representatives
shall, however, be given access to all operations and tests that may be
carried out as aforesaid so that he may satisfy himself regarding the
procedure and methods adopted. It shall then be the Contractor’s
responsibility to produce on the work, materials and finished item to the
standard as determined by the laboratory tests or to take follow up action
to rectify the quality.
(c) Testing charges for testing of Cement, TMT bars, all types of pipes and
specials including cost of samples and its collection shall be borne by the
Contractor.
(d) The Contractor shall make suitable arrangements to see that one of his
representatives remains present at the time of taking samples and shall
authenticate the facts. If the Contractor, fails to keep his representative
present at site at the time of taking samples or fail to provide required
labours and other equipment to collect the samples, the same shall be
17
taken by the Engineer In-charge, and the samples selected shall be
considered as authentic. The cost incurred by the Engineer-In-charge when
the Contractor fails to provide required men and materials for collecting
samples and or their transport shall be recovered from the Contractor.
20.0 Quality Control and Quality assurance
20.1 On award of contract, the Contractor will have to provide adequate quality
assurance setup including Quality Assurance Engineer backed with suitable
laboratory assistants, labours and well equipped laboratory for taking
necessary field test required as per specifications and as per instructions of
Engineer in charge.
20.2 Following minimum persons shall be employed by the contractor at work site
for Quality Assurance.
20.3 Following minimum equipments shall be available in the field laboratory setup
by the contractor.
21.2 During rotation period, once in every year, the Contractor shall perform
hydraulic test to the satisfaction of Engineer In-charge to verify the flow of
designed discharge, detect or confirm any leakage in the system and rectify at
his own cost. The testing shall preferably be conducted jointly with members of
WUA/representative of Engineer In-charge, technical representative of
contractor and any other stake holder.
21.3 On completion of every Irrigation season, the contractor shall flush the pipe line
from its tail flush valve so that any siltation, vegetation or obstruction is cleaned
and pipe is able to flow designed discharge for next season.
19
21.4 During the O & M period, contractor shall give training to the members of WUA
about O & M of PDN work and its efficient use and protection of the system
from any damages.
21.5 The contractor shall prepare a detail map of the permanent marking along the
alignment of pipe and submit the same to Engineer In-charge. The Engineer In-
charge shall verify and endorse the location of the marking and handover these
signed maps as a permanent record to WUA. Along with this, the detailed
Geotagged map of laid pipeline shall also be handed over to WUA.
21.6 In association of the members of WUA, the Engineer In-charge shall confirm the
release of designed discharge through every outlet before handing over. In case
of any short fall or defect, it should be made good from the contractor at his
own cost.
Specifications for
Bar/Wire Wrapped Steel
Cylinder Pipes (BWSC).
2020
0
Bar/Wire Wrapped Steel Cylinder (BWSC) Pipes.
1.0 Introduction :
Bar/Wire wrapped steel cylinder (BWSC) pipe comprises of a welded steel sheet
cylinder with steel socket & spigot rings welded to its ends, lined with centrifugally
applied cement mortar within the steel cylinder. Reinforcement consisting of
continuous steel bars/wire helically wound around the outside of the cylinder is
subsequently coated with dense cement mortar.
The Contractor shall provide on-site training on BWSC pipe laying, jointing, testing
and maintenance etc., to the personnel authorized by the Engineer-in-charge. The
contractor should provide technical manual on BWSC Pipes including precautions to
be taken during operation of the pipeline.
1
IS: Specifications for Bar/Wire Wrapped Steel Cylinder pipes
15155
IS: 7322 Specifications for Specials for Steel Cylinder Reinforced Concrete pipes
IS 1566 Specifications for Hard Drawn Steel Wire for Concrete Reinforcement
IS 383 Specifications for coarse & fine aggregates from natural sources for
concrete
IS 432 Specifications for Mild steel & medium steel bar/wire for Concrete
Part Concrete.
1&2
Raw materials used to manufacture BWSC Pipes are cement, aggregates, water,
admixture, steel reinforcement, Steel plates. .
3.1 Cement
The cement used in the manufacture of BWSC pipes shall conform to one of
the following.
1) 43/53 grade Ordinary Portland Cement conforming to IS:8112/IS
12269
2) Rapid Hardening Portland cement conforming to IS: 8041
3) Portland Slag cement (with not more than 50% slag) conforming to
IS: 455
4) Sulphate Resisting Portland Cement conforming to IS: 12330
2
3.2 Aggregate
The coarse and fine aggregates shall conform to I.S.383. The maximum size of
aggregate shall not exceed one third the thickness of the pipe or 20mm
whichever is smaller. Silt Content in fine aggregates shall be less than 3
percent. The fineness modulus of aggregates for coating shall be between 2.6
to 3.2.
3.3 Water
The water used in the preparation of concrete mix shall be clean and free from
harmful or injurious compounds such as acids, alkali, oil, organic material or
other substances and shall conform to the requirements of mixing water as
per IS : 456.
3.4 Admixtures
Admixtures may be used with the approval of the purchaser. However, use of
any admixture containing chlorides in any form shall be prohibited The
admixtures shall conform to IS 9103.
The manufacturing of pipes & specials for BWSC pipes shall be as per IS 15155.
• Placing of rich cement mortar lining in the core by centrifugal method. ( minimum
cement content- 540kg/m3 , minimum water cement ratio – 0.42, minimum
compressive strength of cement mortar at 28 days-35 N/mm 2, minimum
compressive strength of cement mortar at the time of wrapping of bar/wire -10
N/mm2)
3
• Rich cement mortar out coating ( Cover coating) on pipe (shall preferably be
applied within 16 hours after the bar/wire is wound). ( minimum cement content-
540kg/m3 , minimum water cement ratio – 0.27, minimum compressive strength
of cement mortar at 28 days-35 N/mm2).
• Curing of concrete.
4
Table No.1 Scale of Sampling and No. of Acceptable defective tests
(Reproduced from IS 15155)
6.1 Steel Cylinder Test : During manufacturing, each steel cylinder with steel and
spigot rings welded on shall be subjected to water pressure which stresses the steel
to at least 140 N/mm2but not more than 175 N/mm2. While under stress, the
assembly, especially welds shall not show any leakage. If any leakage is found,
assembly shall be repaired and whole assembly retested.
5
6.2 Dimensions
6.2.1 Length -
Length of Pipe shall be 4m to 8m.
6.2.2 Nominal internal diameter of the pipes, minimum wall thickness and
minimum thickness of cement mortar lining shall be as per following
Table no.2
6
6.2.3 The deviation from straight line taken between two points one meter
apart, along the pipe barrel shall not exceed 5mm.
6.2.4 The pipe shall be free from local depressions or bulges greater than
5mm extending over a length, in any direction.
The vehicle shall have side supports approximately spaced 2 m apart, and the
pipes shall be secured effectively during the transportation. All posts shall be flat
with no sharp edges.
A pipe section must be rolled or otherwise moved, such operation shall be done
slowly and with every reasonable precaution against damage. Any portion of the
lining, coating that may become damaged shall be repaired with polymer Mortar.
All pipes shall be loaded in trucks by mechanical crane/ tripod and unloaded
carefully using crane/ tripod. No unloading using crow bars or on tires will be
allowed in any case. Rubber belt may be used instead of crow bars or chains.
Pipes should be loaded at the works for transportation, either by rail or by road,
in such a way that they are secure and that no movement can take place on the
vehicle during transit. The same care is needed if pipes are to be transferred from
one vehicle to another, however, short the journey may be.
Un-loading of pipes should be carried out by means of chain block with shear legs
or crane of adequate capacity, using properly designed slings and spreader beams
or specially designed lifting beams. Slings should be placed around the
circumference of the pipe and should not be threaded through the pipe bore' as
the latter method may damage the jointing surfaces. For the same reasons, hooks
located in the ends of the pipes should not be used.
8
Typical Lifting beam
10.0 Valves
For PDN work, various Valves as mentioned below are required to be provided on
pipeline at various location.
9
amount of gas gathered in the pipe timely; finally, during the pump failure or
maintenance stages, the air valve will replenish the gas into the pipe to break the
vacuum. According to the orifice size, displacement and work pressure, air valve
is divided into high pressure trace exhaust valve, low pressure air release valve
and combined air valve.
10.2 Scour Valve :
These Valves are generally provided to drainout the pipeline. The exact location
of Scour valves is frequently influenced by opportunities to dispose off the water.
Where the main pipeline crosses a stream or drainage structures, there will
usually be a low point in the line but if the main pipeline goes under the stream
or drain, it cannot be completely drained into the channel. In such a situation it
is better to locate a scour connection at the lowest point that will drain by gravity
and provide for pumping out the part below the drain pipeline.
10.3 Control Valve :
A control valve is a valve used to control fluid flow by varying the size of the flow
passage as directed by a signal from a controller. This enables the direct control
of flow rate and the consequential control of process quantities such
as pressure, temperature, and liquid level.
B) Rotary
Butterfly valve
Ball valve
C) Other
Pinch valve
Diaphragm valve
10
ownership of all the usable material, so removed from clearing site and/or
excavation shall rest with the Engineer In-charge. Useful material shall be
stacked as directed. The Contractor shall dispose off all unuseful materials as
directed by the Engineer In-charge.
12.2 Demarcation
All materials such as pegs, bamboo’s and strings and templets for
marking out slopes, and labour required for line out should be provided by
the Contractor at his own cost. The center line of excavation shall be clearly
marked by pegs or by stones at each chain or change of direction or at shorter
intervals on curves, in the beginning. The final line out will be done by fixing
reference stone at suitable distances on either side of the center line, beyond
the canal edges so that they are not disturbed during the construction period.
The position of these stones will be marked on the cross section.
12.3 Contractor shall provide and maintain the quarry roads and temporary roads
required for construction activity at his own cost.
12.4 Fixing Permanent Benchmark
(a) Benchmarks fixed by the Survey of India and temporary benchmarks
established by the Engineer In-charge in vicinity of PDN work will serve
as control points for these works. The Contractor shall establish sufficient
number of reference benchmarks for facilitating setting out of work and
taking levels for the purpose of measurements.
(b) Before starting any work, the Contractor shall erect reference
benchmarks, reference lines and check profiles at convenient locations
approved by the Engineer In-Charge. The benchmark concrete block shall
be 200mm x200mm x600mm with 400mm embedded in the firm ground
and 200 mm projecting above ground. The word ‘BM’ showing value of
R.L. in ‘m’ shall be conspicuously carved and painted on the benchmark.
(c) The check profile shall be located 30m apart or closer as directed by the
Engineer In-Charge so as to ensure execution of all slopes, steps and
elevations to the profile or profiles indicated in the approved drawings.
All important levels and all control points with respect to benchmarks and
reference lines shall be fixed and correlated by the Contractor. The
Contractor is fully responsible for maintaining all setting out work &
Benchmark established by Engineer-In-charge.
(d) All materials, labour and equipments (theodolites, levels, distometre,
etc.) for setting out works including construction of benchmarks in
concrete, reference lines, check profiles and surveys as may be required
at the various stages of construction shall be supplied by the Contractor
at his cost. For this following numbers of minimum equipments shall
be provided and maintained in good working condition by the
Contractor.
11
1. Total station and its accessories 1 set
2. Theodolites (Accuracy 1 second) 1 No.
3. Levels 2 Nos.
4. Staves 4 Nos.
5. Tapes, chains, ranging rods etc. As required
13.2 The usable excavated material available from the excavated trenches (PDN)
shall be used in backfilling. If such usable material is in excess of the
requirement of backfilling, the same shall be deposited in the spoils as and
where directed by the Engineer In-charge. Unuseful material from excavation
shall be deposited in spoils as and where directed by Engineer-In-charge.
13.3 Surface or sub-soil water met with during trench excavation (PDN) and
structure excavation shall be diverted to nearby drain/nalla by cutting an open
channel from trench. When the drain/nalla bed is higher than the sub-soil
water level met with, the bailing out by suitable means of pumping shall be
resorted to for dewatering sub-soil water below the drain/nalla bed level. No
distinction shall be made as to whether the material being excavated is dry,
moist, wet or slushy. The Contractor shall have to excavate the PDN pipe
trench and structure in under water level conditions also i.e. under wet/slushy
condition after providing sufficient arrangement of dewatering. The material
excavated under water level condition which requires intermediate stacking
for drying shall have to be rehandled. No extra payment for efforts for drying
out of soil, re-handling of dry soil, etc. shall be given. No payment for extra
efforts for excavation under this condition shall be made.
13.4 Over excavation performed by the Contractor for any purpose or reason,
except for additional excavation as may be directed by the Engineer-In-charge,
shall be rectified at the cost of the Contractor. Filling and compaction for such
12
over excavation using the material as directed by the Engineer In- Charge shall
also be at the cost of the Contractor.
13.5 In the PDN and structure section where expansive type of the soil such as CH
type of soil is encountered and over which PDN cannot be directly laid, the
PDN trench and structure shall be over excavated to the extent as directed by
the Engineer In Charge and such over excavated section shall be filled with
suitable murum type soil to be placed in uniformly compacted layers as
directed by the Engineer In Charge. The over excavation made in such strata,
filling by suitable soil, and watering and compacting such soil will be paid
separately under relevant items. Above provision for over excavating and
filling with suitable murum type or good soil available material shall be
applicable in case such treatment is found essential.
13
15.2 Jointing process of BWSC pipe consist of following steps.
Aligning of points at joint locations.
Field welding of socket ring at joint externally.
Fixingof diaper with steel strap at joint location.
Pouring of cement mortar through diaper at joint location.
Filling inside of joints by cement mortar.
15.3 The basic requirements for all joints are as enumerated below.
a) Cleanliness of all parts, particularly joint surface;
b) Correct location of components;
c) Centralization of spigot within socket;
d) Provision of the correct gap between the end of the spigot and the back of
the socket
16.1 All pipelines should be tested before being brought into service. The test
should be a hydrostatic test performed by filling the pipeline with water and
raising the pressure to the selected test pressure and maintaining this for a
sufficient period to allow for absorption of water by the pipe material.
`16.2 AS per I.S.784 the test pressure should be 1.5 times design working pressure.
16.3 Test procedure : Each section should be properly sealed off, preferably with
special stop secured by adequate anchors. The thrust on the stop ends should
be calculated on the full socket internal diameter and the anchors designed to
resist it. It may often be economical to provide .a concrete anchor block of
couple of pipes laid and earth tamped around which has subsequently to be
demolished rather than risk movement of the stop ends during testing.
Hydraulic jacks may be inserted between the temporary anchors and stop ends
in order to take up any horizontal movement of the temporary anchor. All
permanent anchors should be in position and, if of concrete, should have
developed adequate strength before testing begins. The section under test
should be filled with water, taking care that all air is displaced either through
vents at the high points, or by using a swab. After filling, the pipeline should
be left under operating pressure for a period in order to achieve conditions as
stable as possible for testing. The length of this period will depend upon many
factors such as initial permeability, absorption, movement of the pipeline
under pressure and the quantity of air trapped.
16.4 Leak Detection - If the test is not satisfactory, the fault should be found and
rectified. Where there is difficulty in locating a fault, the section under test
should be subdivided and each part tested separately.
If any leakage is found during testing of pipeline, Contractor will have to
attend the same immediately and rectify at his cost within. If Contractor fails
to rectify the defect, the entire length of pipeline between two adjacent
outlets shall be rejected. If any intermediate payment is made to the
Contractor for portion under rejection, the same shall be recovered from the
outstanding dues of the Contractor.
16.5 Final Testing – After all sections have been jointed together on completion of
section testing, a test on the complete pipeline should be carried out. This test
should be carried out at a pressure not less than the working pressure of the
pipeline, care being taken to ensure that the pressure at the lowest point in
the pipeline does not exceed the maximum. During the test, an inspection
should be made of all work which has not been subjected to sectional tests.
15
shall be on higher/lower side of OMC by about 2% or so, to allow it to be
compacted. Profuse watering shall be done to pervious materials (sand) before
compaction as per instruction of the Engineer-in-Charge. Compaction at
junction of earthwork and backfill around the structure shall be carried out with
special care.
(f) The trench shall be refilled so as to built-up the original ground level.
17
20.0 Quality Control and Quality assurance
20.1 On award of contract, the Contractor will have to provide adequate quality
assurance setup including Quality Assurance Engineer backed with suitable
laboratory assistants, labours and well equipped laboratory for taking
necessary field test required as per specifications and as per instructions of
Engineer in charge.
20.2 Following minimum persons shall be employed by the contractor at work site
for Quality Assurance.
Sr.
Personnel with Qualification Nos.
No.
1 Quality Assurance Engineer(Civil Engineering One
Graduate with 2 Year experience in QA testing and
report generation work)
2 Laboratory Assistants(Twevlth Pass with Science Two to Four
subject with 2 year experience in testing of material) (As per work)
3 Laboratory Attendants Two to Four
(One for each
L.A.)
Sr.
Work Apparatus for Tests
No.
1 Earth Work – Field density, Moisture Content,
Field testing Equipments Sieves for Sand & Metal.
2 Concrete Work - Silt, Gradation, Moisture Content,
Slump, Cube Moulds & CTM
20.4 It is the responsibility of the contractor to assure the desired quality of
work. Whenever the testing of construction materials, pipes are required as
per the detailed specifications or otherwise required by the Engineer-in-
Charge, the same shall be carried out at the laboratory, selected by the
Engineer-in-Charge at Contractor’s cost. The other tests of mortar, concrete,
sand, coarse aggregates etc. shall be carried out in field laboratory set up
by the contractor in presence of quality control representative at
contractors cost. Contractor shall through this procedure assure the quality
of work.
20.5 The materials, mixes and any other arrangements, including labours, shall
be supplied by the contractor. The samples for testing shall be taken in the
presence of Engineer-in-Charge or his representative /QC present on site. The
contractor or his authorized representative shall have a free access in these
laboratories, to get himself satisfied about procedures of testing etc. Even
18
if the contractor or his representative fails to remain present while
collecting samples or testing, the results will be considered as authentic
and binding on the contractor.
20.6 Contractor shall provide all test reports of material used in the work as desired
from the NABL (National Accreditation Board for Testing & Calibration
Laboratories) approved laboratories and from Quality Control, MERI
laboratories of the WRD. Contractor shall provide periodical quality assurance
report (Weekly/fortnightly/monthly) to Engineer in Charge along with proofs
in support of quality of material brought for the work, the process/ execution
of work is as per specification.
20.7 Contractor shall submit the account of all materials brought for the work,
which are necessary for execution of work and any other data necessary to
assess the quality of work.
20.8 If he fails to fulfill the above requirement, the required manpower for testing
and field laboratory with required equipments will be deployed by the
Engineer in charge and the charges for the same will be recovered from the
contractor.
21.0 Operation, Maintenance and Handing over of the System
21.1 The contractor shall operate and maintain the complete pipe distribution
network for the period of 5 (five) years after commissioning. Out of this period,
during last two years the operation of the schemes shall be done by the
contractor jointly along with WUA. On completion of O & M period, the system
shall be handed over to WUA
21.2 During rotation period, once in every year, the Contractor shall perform
hydraulic test to the satisfaction of Engineer In-charge to verify the flow of
designed discharge, detect or confirm any leakage in the system and rectify at
his own cost. The testing shall preferably be conducted jointly with members
of WUA/representative of Engineer In-charge, technical representative of
contractor and any other stake holder.
21.3 On completion of every Irrigation season, the contractor shall flush the pipe
line from its tail flush valve so that any siltation, vegetation or obstruction is
cleaned and pipe is able to flow designed discharge for next season.
21.4 During the O & M period, contractor shall give training to the members of WUA
about O & M of PDN work and its efficient use and protection of the system
from any damages.
21.5 The contractor shall prepare a detail map of the permanent marking along the
alignment of pipe and submit the same to Engineer In-charge. The Engineer
In-charge shall verify and endorse the location of the marking and handover
these signed maps as a permanent record to WUA. Along with this, the
detailed Geotagged map of laid pipeline shall also be handed over to WUA.
19
21.6 In association of the members of WUA, the Engineer In-charge shall confirm
the release of designed discharge through every outlet before handing over.
In case of any short fall or defect, it should be made good from the contractor
at his own cost.
22.2 Payment
The break up to payment for supplying, laying, jointing & hydrostatic testing
of pipeline shall be as under:-
A) 80% of the payment will be released after supplying, lowering, laying,
jointing and third party inspection of pipes in one WUA area.
B) Balance 10% of the payment will be released after satisfactory hydraulic
testing of pipeline and backfilling of trenches.
C) Remaining 10% amount will be withheld and it will be released after
successful maintenance and operation for a period of five years after
commissioning of work of respective WUAs.
The schedule of release of this 10% will be in following manner,
1) After Successful Operation and Maintenance for First year-2%
2) After Successful Operation and Maintenance for Second year-2%
3) After Successful Operation and Maintenance for Third year-2%
4) After Successful Operation and Maintenance for Fourth year-2%
5) After Successful Operation and Maintenance for Fifth year-2%
A certificate regarding smooth working of pipe distribution network from the
Chairman of WUA shall be binding for annual release of this amount.
----------***---------
20
Govt. of Maharashtra
SPECIFICATIONS FOR
2020
0
SPECIFICATION FOR MILD STEEL PIPES (M.S)
1.0 Introduction
Mild steel Pipes can be manufactured from mild steel produced by the open hearth
or electric furnace or one of the basic oxygen processes. The pipes shall be
manufactured by either seamless(s) process or electric resistance inducing induction
welding (ERW) process or Submerged Arc Welding (SAW) process.
The Contractor shall provide on-site training on M.S. pipe laying, jointing,
testing and maintenance etc., to the personnel authorized by the Engineer-in-charge.
The contractor should provide technical Manual on M.S. pipes including precautions
to be taken during operation of the pipeline.
IS: 3589 Specification for Steel pipes for Water and Sewage (168.3 to 2540
mm Outside Diameter).
Note: The provisions of various clauses of the above IS code are
deemed to be applicable to diameters above 2540mm as well.
IS: 5822 Code of Practice for Laying of Electrically Welded steel pipes for
water supply.
Note: The provisions of various clauses of the above IS code are
deemed to be applicable to diameters above 2540mm as well.
I.S.4711 Methods for sampling of steel pipes, tubes & fittings
IS: 2062 Specification for Hot Rolled Medium and High Tensile Structural Steel
IS: 814 Specification for Covered Electrodes for Manual Metal Arc Welding
of Carbon and carbon Manganese Steel
IS: 3613 Acceptance tests for wire flux combinations for submerged arc
welding.
IS: 456 Code for practice for plain and reinforced concrete.
IS: 800 Code of practice for general construction in Steel.
1
IS: 816 Code of practice for use of Metal Arc Welding for General
Construction in mild steel
IS: 4353 Recommendation for Submerged Arc Welding of Mild Steel & Low
Alloy Steels.
IS: 1182 Recommended practice for Radiographic examination of Fusion-
Welded Butt Joints in steel plants.
IS: 2595 Code of Practice for Industrial Radio-graphic Testing.
IS: 4853 Recommended Practice for Radiographic Examination of Fusion
Welded Butt Joints In Steel Pipes.
Raw material use to manufacture the M.S. Pipes (with or with or coating) is steel
plates, Welding Consumables, Cement, aggregate, water, admixtures, steel
reinforcement, primer, red oxide paint.
3.1 Steel Plates - The steel plates for pipes, fittings, specials shall be of mild steel
of various grades conforming to IS 2062. Steel plates shall be procured from reputed
manufacturers such as JINDAL, SAIL, ESSAR, ISPAT TISCO etc.
3.3 Cement : The cement used for coating to in the manufacture of M.S.pipes shall
confirm to one of the following.
1) 43/53 grade Ordinary Portland Cement confirming to IS:8112/IS 12269
2) Rapid Hardening Portland cement confirming to IS: 8041
3) Slag cement (with not more than 50% slag) confirming to IS: 455
4) Sulphate Resistant Cement confirming to IS: 12330
3.4 Aggregate : The coarse and fine aggregates shall conform to I.S.383. The
maximum size of aggregate shall not exceed one third the thickness of the pipe or
20mm whichever is smaller. Silt Content in fine aggregates shall be less than 3
percent. The fineness modulus of aggregates for coating shall be between 2.6 to 3.2.
3.5 Water : The water used in the preparation of concrete mix shall be clean and free
from harmful or injurious compounds such as acids, alkali, oil, organic material or
other substances and shall conform to the requirements of mixing water as per IS :
456.
3.6 Admixtures : Admixtures may be used with the approval of the purchaser.
However, use of any admixture containing chlorides in any form shall be prohibited
The admixtures shall conform to IS 9103.
2
3.7 Steel for Reinforcement : Steel reinforcement shall conform to IS
1786:2008
Designation
The pipes shall be designated by the method of manufacture followed by the grade
number corresponding to the minimum specified tensile strength in MPs following
the symbol Fe as given in Table 1
Example:
ERW- Fe 410 indicates electric resistance welded or induction welded steel pipe
having a minimum tensile strength of 410 MPa.
3
Table 1 Designation of the Grades of the pipes
The size of the pipes shall be designated by their outside diameters in mm.
4.3 Protective coating for pipes : Generally pipes are coated internally as well as
externally for corrosion protection as per provisions of IS 3589. Various types of
coatings applied to MS pipes are as mentioned below.
4.3.1 Cement Mortar Lining : The inside of all pipes shall receive a cement mortar
lining applied by centrifugal spinning, whereas outside of pipe shall receive a
reinforced cement mortar coating ( i.e. Gunniting with wire mesh) applied by either
mechanical or pneumatic placement. The minimum thickness of inside mortar lining
shall be 6 to 12mm depending on outside diameter of pipe as given in IS 3589,
whereas minimum thickness of outside cement mortar coating (i.e. Gunnitting) shall
be 20mm.
4.3.2 Liquid Epoxy Coating : This system may consists of any one of the following three
types.
(i) two part chemically cured epoxy primer and one or more coatings of a different
two-part, chemically cured Epoxy top coat.
(ii) two or more coats of the same two-part, chemically cured epoxy coating, in which
case the first coat shall be considered as the primer coat.
(iii) a single coat of two-part, solvent for chemically cured epoxy coating.
Unless otherwise specified by the purchaser, the minimum dry film thickness
DFT provided shall be atleast 406 micronm .
After curing but prior to burial the coating system shall be a continous film,
free of thin spots and other imperfections and shall pass electrical inspection
for continuity.
4
4.3.3 Fusion bonded epoxy coating :
MATERIAL
The epoxy powder shall consist of a one-component, fusion bonded material
consisting of epoxy resin, curing agents, catalysts, fillers, colorants, flow control
agents, and ultraviolet light resistant agents that when applied to the preheated
substrate, will uniformly coalesce and cure to produce a homogeneous film that
complies with the requirements of this standard.
Application capability, when applied by electrostatic spray, fluidized bed, or air spray
to the preheated article and subsequently cured, the epoxy powder shall produce a
uniform protective coating.
The primer shall be applied to the properly prepated pipe surface before application
of the inner layer tape.
The inner layer tape shall consist of a polyolefin backing with a laminated adhesive.
The inner layer tape shall be applied after the primer and before the outer layer tape.
The outer layer shall consist of polylefin backing with a laminated elastomer type
adhesive.
5
5.0 Sampling criteria for Selection of Pipe for Testing Purpose
All pipes manufactured by the same process under similar conditions of production
shall constitute a lot.
The number of pipes to be selected from a lot for the checking of dimensional
characteristics depends on the size of the lot and shall be taken in accordance with
relevant columns of following Table No.2. AII these items shall be taken at random
from the lot by using suitable random number tables or by using any other procedure
which ensures randomness.
Table No.2 Scale of Sampling and Permissible Number of Defectives for Mass and
Dimensional Characteristics
(Reproduced from IS 4711)
Each of the items selected according to above shall be inspected for dimensional
characteristics as mentioned below para 6.0. Any items failing to meet one or more
dimensional requirements shall be considered as defective. If the number of
defective found in the sample checked for dimensional characteristics is less than or
equal to the corresponding acceptance number, the lot shall be deemed as having
met the dimensional requirements of the relevant specification, otherwise not.In the
case of those lots which have been found unsatisfactory, all the items in the lot may
be inspected for dimensional characteristics and the defective be removed, if agreed
to between the purchaser and the supplier.
6
The lot shall also be tested for appropriate physical characteristics like tensile
strength, bend, flattening and drift tests. The number of items to be drawn in
accordance with following Table 3 may be taken at random from that already drawn
for dimensional inspection.
Table No.3 Scale of Sampling and Permissible Number of Defectives for Physical
tests (Tensile, Bend, Flattening and Drift)
(Reproduced from IS 4711)
For any of the physical tests, if in the first sample the number of defective items is
less than or equal to the corresponding acceptance number (a) the lot shall be
declared as conforming to the requirement of that test. If the number of defective is
greater than or equal to the corresponding rejection number (r), the lot shall be
deemed as not meeting the requirement of that particular physical test. If the
number of defective is greater than the acceptance number but less than the
rejection number, a second sample of the same size as the first shall be taken to
determine the conformity or otherwise of the lot. The number of defective found in
the first and second samples shall be combined and if the combined number of
defective is less than or equal to the corresponding acceptance number of the second
sample, the lot shall be declared as conforming to the requirements of the particular
physical test, otherwise not. Each pipe shall be hydraulically tested at the
manufacturer’s works before the pipe is coated, wrapped or lined.
7
6.0 Pre Delivery Testing of Pipes
Pipe selected as per sampling criteria mentioned in earlier para 5.0 are subject to
following tests before delivery from factory
6.1 Dimensions :
6.1.1 Outside diameter : The tolerance on the specified outside diameter of pipe wall
shall be as given in following Table No.4
Tolerance on outside diameter of pipes.
6.1.2 Wall thickness : the tolerance on the specified wall thickness of pipe shall be as
follows.
6.1.3 Ovality : Ovelity shall not exceed 1% of the specified outside diameter for pipes
having diameter to thickness ratio not exceeding 100. Where the diameterto
thickness ratio exceeds 100 the tolerance on ovality is not specified and should be
agreed between the manufacturer & the purchaser.
6.1.4 Straightness : Finished pipe shall not deviate from straightness by more than
0.2 % of the total length.
6.2 Tensile Strength : The tensile properties of strip cut longitudinally (excluding the
weld) from selected pipes shall show the properties as given in following Table No.5.
8
Steel Method Em Es A
grades Tensile Yield Elongation %
Strength MPa Stress GI5.65
Min Min Min
Fe330 ERW & seamless & 330 195 20
SAW
Fe410 ERW & seamless & 410 235 18
SAW
ERW & seamless & 450 275 15
SAW
Yield stress valus are for design purposes only either the upper yield stress ReH or the 0.5 % of proof stress
(total elongation) ReH 0.5 is to be determined.
This test shall be carried out in accordance with IS 2328. A ring not less than 40mm
long cut from one end of each selected pipe shall when cold be flattened between
two parallel flat surfaces without showing either crack or flaw until the distance
between the plates H(mm) measured under load is not greater than the value given
by the following equation H=(1+c)a/c+a/d
Where a=specified thickness of the pipe (mm)
d=spefied outside diameter of the pipe(mm)
c=a constant dependent on the steel grade
Value of C=0.09 for Fe330
=0.07 for Fe410 & Fe450
Notes:
i. If any flaw appears during flattening test it may be removed by grading or filling. In
such case if the remaining wall thickness is not less than the minimum permitted
thickness as per clause the sample shall be accepted.
ii. superficial rupture resulting from surface imperfections shall not be cause of
rejection.
9
6.4 Guided bend test (for SAW pipes).
Strips not less than 40mm wide cut circumferentially from pipes perpendicular to
weld seam which the weld near the middle of the sample shall without fracture be
doubled over around bar the diameter of which shall be calculated as given below.
The weld reinforcement shall be removed from the faces.
The specimen shall not be fractured completely. Cracks 6.35 mm or less in length at
the edge of the specimen or 3.18mm or less in length in the centre of the specimen
shall be disregarded. Any crack greater than 3.18mm in length and regardless of the
depth located within the weld metal shall be a cause of rejection. Any pop-out greater
than 3.18mm in length (6.35mm at the edge)& 12.5% or less of the specified wall
thickness in depth and located in the parent metal. The heat affected zoze, or the
fusion line, shall not be the cause for rejection.
P =2ST/D
Where
P= hydraulic test pressure MPa
D=specified outside diameter of the pipe in mm’
T=specified thickness of the tube in mm
S= stress 60% of the specified minimum yield stress in MPa. The maximum tress
pressure to be limited to 5MPa wherever applicable.
The hydraulic test pressure shall be applied for 5s.
The test pressure shall ensure that the plate material is stressed to 80% of the
minimum yield strength and at least 1.5 times the allowable working pressure as
specified by the Engineer. Each pipe shall be filled with water and the pressure slowly
and uniformly increased until the required test pressure is reached.
The maximum elapsed Time shall Not Exceed the Maximum Time as given:- Maximum
4.0 Hrs.Any pipe showing flash rusting shall be relisted.
The blast cleaned pipe surface shall be tested for the presence of soluble salts. If the
concentration is more than 2µgm/cm², the pipe surface shall be chemically cleaned
using phosphoric acid or any other suitable method. The cleaned pipe shall be
retested to confirm the removal of soluble salts. Any foreign material or shot/grit
present in the pipe shall be removed by suitable means (mechanical brush, high-
pressure air jets, etc.) the Blast cleaned surface shall not be contaminated with dirt,
dust metal particles. Oil water or any other foreign material, nor shall the surface or
10
its anchor pattern be scarred or burnished. All blast cleaned pipe surface shall be
thoroughly inspected under adequate lighting to determine anchor pattern, quality
of blasting and identify any surface defects prior to coating application.
The vehicle shall have side supports approximately spaced 2 m apart, and the pipes
shall be secured effectively during the transportation. All posts shall be flat with no
sharp edges.
Padding shall be provided between coated pipes and timber skids to avoid damage
to the coating.
Pipes manufactured at factory are to be carried to the site of work directly or stacked
suitably and neatly along the alignment/ road side/elsewhere near by the work site,
as directed by the Engineer.
All pipes shall be loaded in trucks by mechanical crane/ tripod and unloaded carefully
using crane/ tripod. No unloading using crow bars or on tires will be allowed in any
case. Rubber belt may be used instead of crow bars or chains.
Pipes should be loaded at the works for transportation, either by rail or by road, in
such a way that they are secure and that no movement can take place on the vehicle
during transit. The same care is needed if pipes are to be transferred from one vehicle
to another, however, short the journey may be.
The pipes and specials shall be handled in such a manner as not to distort their
circularity or cause any damage to their out coating
Pipes shall not be thrown down from the trucks nor shall be dragged or rolled along
hard surfaces.
11
Slings of canvas on equally non-abrasive material of suitable width or special
attachment shaped to fit the pipe ends shall be used to lift and lower coated pipes
so as to eliminate risk of damage to the coating.
10.0 Valves
For PDN work, various Valves as mentioned below are required to be provided on
pipeline at various location.
12
10.3 Control Valve :
A control valve is a valve used to control fluid flow by varying the size of the flow
passage as directed by a signal from a controller. This enables the direct control
of flow rate and the consequential control of process quantities such
as pressure, temperature, and liquid level.
A) Sliding Stem
Globe valve
Angle body valve
Angle seat piston valve
B) Rotary
Butterfly valve
Ball valve
C) Other
Pinch valve
Diaphragm valve
The Contractor shall clear the entire area required for setting out. All tree
stumps, roots, brushwood, rubbish of all kinds, loose stones and all other
objectionable materials shall be removed by the Contractor. Buried irrigation
pipeline, and other structure, if any, shall be removed by the Contractor. The
ownership of all the usable material, so removed from clearing site and/or
excavation shall rest with the Engineer In-charge. Useful material shall be
stacked as directed. The Contractor shall dispose off all unuseful materials as
directed by the Engineer In-charge.
13
12.2 Demarcation
All materials such as pegs, bamboo’s and strings and templets for marking out
slopes, and labour required for line out should be provided by the Contractor
at his own cost. The center line of excavation shall be clearly marked by pegs
or by stones at each chain or change of direction or at shorter intervals on
curves, in the beginning. The final line out will be done by fixing reference
stone at suitable distances on either side of the center line, beyond the canal
edges so that they are not disturbed during the construction period. The
position of these stones will be marked on the cross section.
12.3 Contractor shall provide and maintain the quarry roads and temporary roads
required for construction activity at his own cost.
12.4 Fixing Permanent Benchmark
(a) Benchmarks fixed by the Survey of India and temporary benchmarks
established by the Engineer In-charge in vicinity of PDN work will serve as
control points for these works. The Contractor shall establish sufficient
number of reference benchmarks for facilitating setting out of work and taking
levels for the purpose of measurements.
(b) Before starting any work, the Contractor shall erect reference benchmarks,
reference lines and check profiles at convenient locations approved by the
Engineer In-Charge. The benchmark concrete block shall be 200mm x200mm
x600mm with 400mm embedded in the firm ground and 200 mm projecting
above ground. The word ‘BM’ showing value of R.L. in ‘m’ shall be
conspicuously carved and painted on the benchmark.
(c) The check profile shall be located 30m apart or closer as directed by the
Engineer In-Charge so as to ensure execution of all slopes, steps and elevations
to the profile or profiles indicated in the approved drawings. All important
levels and all control points with respect to benchmarks and reference lines
shall be fixed and correlated by the Contractor. The Contractor is fully
responsible for maintaining all setting out work & Benchmark established by
Engineer-In-charge.
(d) All materials, labour and equipments (theodolites, levels, distometre, etc.) for
setting out works including construction of benchmarks in concrete, reference
lines, check profiles and surveys as may be required at the various stages of
construction shall be supplied by the Contractor at his cost. For this following
14
numbers of minimum equipments shall be provided and maintained in
good working condition by the Contractor.
3. Levels 2 Nos.
4. Staves 4 Nos.
All equipments shall be of standard and approved make and precision, and
shall be made available in advance of starting of the work. All equipment
shall be maintained, repaired and got tested and certified as and when
required for its accuracy from the standard test houses or from the
manufactures and to the satisfaction of the Engineer-In-Charge.
13.1 Excavation of pipe trenches shall be carried out as per excavation line shown
in the drawing or as directed by Engineer In -charge. Contractor must assume
all responsibility for deductions and conclusion made by him as to the nature
of the materials to be excavated and the difficulties of making and maintaining
the required excavation. The trench width at bottom shall be 300 mm more
than 1.5 times outside pipe diameter. In any case trench width shall not be less
than 500 mm.
13.2 The usable excavated material available from the excavated trenches (PDN)
shall be used in backfilling. If such usable material is in excess of the
requirement of backfilling, the same shall be deposited in the spoils as and
where directed by the Engineer In-charge. Unuseful material from excavation
shall be deposited in spoils as and where directed by Engineer-In-charge.
13.3 Surface or sub-soil water met with during trench excavation (PDN) and
structure excavation shall be diverted to nearby drain/nalla by cutting an open
channel from trench. When the drain/nalla bed is higher than the sub-soil
water level met with, the bailing out by suitable means of pumping shall be
resorted to for dewatering sub-soil water below the drain/nalla bed level. No
distinction shall be made as to whether the material being excavated is dry,
moist, wet or slushy. The Contractor shall have to excavate the PDN pipe
15
trench and structure in under water level conditions also i.e. under wet/slushy
condition after providing sufficient arrangement of dewatering. The material
excavated under water level condition which requires intermediate stacking
for drying shall have to be rehandled. No extra payment for efforts for drying
out of soil, re-handling of dry soil, etc. shall be given. No payment for extra
efforts for excavation under this condition shall be made.
13.4 Over excavation performed by the Contractor for any purpose or reason,
except for additional excavation as may be directed by the Engineer-In-charge,
shall be rectified at the cost of the Contractor. Filling and compaction for such
over excavation using the material as directed by the Engineer In- Charge shall
also be at the cost of the Contractor.
13.5 In the PDN and structure section where expansive type of the soil such as CH
type of soil is encountered and over which PDN cannot be directly laid, the
PDN trench and structure shall be over excavated to the extent as directed by
the Engineer In Charge and such over excavated section shall be filled with
suitable murum type soil to be placed in uniformly compacted layers as
directed by the Engineer In Charge. The over excavation made in such strata,
filling by suitable soil, and watering and compacting such soil will be paid
separately under relevant items. Above provision for over excavating and
filling with suitable murum type or good soil available material shall be
applicable in case such treatment is found essential.
16
Care shall be taken to see that the longitudinal joints of the consecutive pipes
are staggered by at least 30” and should be kept in upper third of the pipeline,
if there are two longitudinal joints they should be on the sides.
While assembling, the pipe faces shall be brought close enough to leave a
uniform gap not exceeding 3 mm.
The spiders from inside and tightening rings from outside or other suitable
equipment should be used to keep the two faces in shape and position till at
least one run of welding is carried out.
The pipe faces shall first be tack-welded alternately at one or more
diametrically opposite pairs of points. After completing tack-welding, full
welding shall be carried out in suitable runs following a sequence of welding
portions of segments diametrically opposite.
17
The welded joints shall be tested in accordance with procedure laid down in IS
3600 (Part 1) : 1985. One test specimen taken from at least one field joint out
of any 10 shall be subjected to test.
If the results of the tensile test do not conform to the requirements specified,
retests of two additional specimen from the same section shall be made, each
of which shall conform to the required specifications. In case of failure of one
or two, extensive gouging (scooping out) and repairing shall be carried out as
directed by the authority.
18
16.4 Leak Detection
Examination Under Pressure.
Under the test pressure no leak or sweating shall be visible at all section
of pipes, fittings, valves, hydrants and welded joints. Any defective pipes,
fittings, valves or hydrants discovered in consequence of this pressure test
shall be removed and replaced by sound material and the test shall be
repeated until satisfactory to the Authority.
If the test is not satisfactory, the fault should be found and rectified.
Where there is difficulty in locating a fault, the section under test should be
subdivided and each part tested separately.
If any leakage is found during testing of pipeline, Contractor will have
to attend the same immediately and rectify at his cost. If Contractor fails to
rectify the defect, the entire length of pipeline between two adjacent outlets
shall be rejected. If any intermediate payment is made to the Contractor for
portion under rejection, the same shall be recovered from the outstanding
dues of the Contractor.
(h) The spiders provided during assembly and welding shall be retained until the
trench is refilled and consolidated. Where timbers are placed under the pipeline
to aid alignment, these shall be removed before backfilling. For further
precautions and use of material in backfilling, reference should be made to IS
3114 : 1994.
18.1 The contractor shall establish the sufficient number of reference blocks on
the alignment of PDN preferably at the interval of 30m or as suitable on the
field boundaries so as they will not be disturbed during the agricultural
activities of the farmers.
18.3 These blocks shall be able to locate the pipeline as and where it is laid all over
the work. The contractor shall mark each block with specific distinct
identification mark.
18.4 The contractor shall show all this blocks jointly to the Engineer-in-charge or
his representative, representative of WUA, concern farmers sharing the
boundaries, TPI, any other stake holders in the command.
18.5 Contractor shall maintain these blocks in proper order during operation &
maintenance period of the contract. Any damage done to these blocks for
the reasons whatsoever shall be made good at the cost of contractor.
18.6 The contractor shall submit the location of such blocks with specific
identification marks with schedule on a special command area map.
18.7 The map of marking of the block shall be handed over to WUA while handing
over the command area.
20
18.8 The Geotagging map showing Latitude and Longitude value of each apex of
laid pipeline shall be submitted to Department and WUA for future reference.
18.9 The contract shall fix information boards of 1.2 m x 0.9 m size at various
location as directed by Engineer-in-charge. On this boards, salient features of
the work (eg. Pipe diameter, pipe type, discharge, any other specific details
suggested by Engineer-In-Charge) shall be written.
19.1 Work of PDN shall be inspected, tested and certified by PMC / TPI / QC.
Modalities of PMC / TPI / QC Inspection shall be separately decided and given
by Engineer In-charge.
Third party Inspection can be done form any one of the following services
3 S.G.S, Mumbai
5 VJTI, Mumbai
(a) All materials before being utilized in works shall be inspected and tested,
by the Engineer In-charge or his representative/QC. The nature of testing
and periodical intervals at which such testing is to be done etc. shall be as
per the latest editions of relevant IS Codes and determined by the Engineer
In-charge. The day-to-day and periodical tests to be carried out on
materials mixes and placed concrete, mortar etc. shall be specified by the
Engineer In-charge from time to time and the Contractor shall provide free
of cost all facilities towards collections of samples etc. unless otherwise
21
specified. Labours for collecting samples and transportation of the samples
to quality control authorities for test shall be provided free of cost by the
contractor. Also electricity, fuel, water curing tank and stores etc shall be
provided free of cost by the contractors.
(b) The materials shall be tested in QC laboratory or at any other place directed
by the Engineer In-charge. The Contractor shall obtain the test results from
the concern authority and the results given by such authorities shall be
considered to determine whether all materials, workmanship are of
respective standard described in contract and in accordance with the
instructions of the Engineer In-charge. The Contractor’s representatives
shall, however, be given access to all operations and tests that may be
carried out as aforesaid so that he may satisfy himself regarding the
procedure and methods adopted. It shall then be the Contractor’s
responsibility to produce on the work, materials and finished item to the
standard as determined by the laboratory tests or to take follow up action
to rectify the quality.
(c) Testing charges for testing of Cement, TMT bars, all types of pipes and
specials including cost of samples and its collection shall be borne by the
Contractor.
(d) The Contractor shall make suitable arrangements to see that one of his
representatives remains present at the time of taking samples and shall
authenticate the facts. If the Contractor, fails to keep his representative
present at site at the time of taking samples or fail to provide required
labours and other equipment to collect the samples, the same shall be
taken by the Engineer In-charge, and the samples selected shall be
considered as authentic. The cost incurred by the Engineer-In-charge when
the Contractor fails to provide required men and materials for collecting
samples and or their transport shall be recovered from the Contractor.
20.1 On award of contract, the Contractor will have to provide adequate quality
assurance setup including Quality Assurance Engineer backed with suitable
laboratory assistants, labours and well equipped laboratory for taking
necessary field test required as per specifications and as per instructions of
Engineer in charge.
20.2 Following minimum persons shall be employed by the contractor at work site
22
Sr.
Personnel with Qualification Nos.
No.
Sr.
Work Apparatus for Tests
No.
23
20.5 The materials, mixes and any other arrangements, including labours, shall
be supplied by the contractor. The samples for testing shall be taken in the
presence of Engineer-in-Charge or his representative /QC present on site.
The contractor or his authorized representative shall have a free access in
these laboratories, to get himself satisfied about procedures of testing etc.
Even if the contractor or his representative fails to remain present while
collecting samples or testing, the results will be considered as authentic
and binding on the contractor.
20.6 Contractor shall provide all test reports of material used in the work as desired
from the NABL (National Accreditation Board for Testing & Calibration
Laboratories) approved laboratories and from Quality Control, MERI
laboratories of the WRD. Contractor shall provide periodical quality assurance
report (Weekly/fortnightly/monthly) to Engineer in Charge along with proofs
in support of quality of material brought for the work, the process/ execution
of work is as per specification.
20.7 Contractor shall submit the account of all materials brought for the work,
which are necessary for execution of work and any other data necessary to
assess the quality of work.
20.8 If he fails to fulfill the above requirement, the required manpower for testing
and field laboratory with required equipments will be deployed by the
Engineer in charge and the charges for the same will be recovered from the
contractor.
21.1 The contractor shall operate and maintain the complete pipe distribution
network for the period of 5 (five) years after commissioning. Out of this period,
during last two years the operation of the schemes shall be done by the
contractor jointly along with WUA. On completion of O & M period, the system
shall be handed over to WUA
21.2 During rotation period, once in every year, the Contractor shall perform
hydraulic test to the satisfaction of Engineer In-charge to verify the flow of
designed discharge, detect or confirm any leakage in the system and rectify at
his own cost. The testing shall preferably be conducted jointly with members
of WUA/representative of Engineer In-charge, technical representative of
contractor and any other stake holder.
24
21.3 On completion of every Irrigation season, the contractor shall flush the pipe
line from its tail flush valve so that any siltation, vegetation or obstruction is
cleaned and pipe is able to flow designed discharge for next season.
21.4 During the O & M period, contractor shall give training to the members of WUA
about O & M of PDN work and its efficient use and protection of the system
from any damages.
21.5 The contractor shall prepare a detail map of the permanent marking along the
alignment of pipe and submit the same to Engineer In-charge. The Engineer
In-charge shall verify and endorse the location of the marking and handover
these signed maps as a permanent record to WUA. Along with this, the
detailed Geotagged map of laid pipeline shall also be handed over to WUA.
21.6 In association of the members of WUA, the Engineer In-charge shall confirm
the release of designed discharge through every outlet before handing over.
In case of any short fall or defect, it should be made good from the contractor
at his own cost.
22.0 Mode of Measurement and Payment
22.1 Measurement
The net length of pipes as laid or fixed shall be measured in running meters
correct to a cm. Specials shall be excluded and measured in running meters or
numbers as specified by Engineer-in-charge and paid for separately under the
relevant item. The portion of the pipe overlapped at the joints shall not be
included in the length of pipe work. Excavation, refilling, anchor blocks, thrust
blocks wherever required shall be measured and paid for separately under
relevant items of work.
22.2 Payment
The break up to payment for supplying, laying, jointing & hydraulic testing of
pipe line shall be as under:-
25
The schedule of release of this 10% will be in following manner,
26
Govt. of Maharashtra
SPECIFICATIONS FOR
2020
0
SPECIFICATION FOR DUCTILE IRON PIPES (DI)
1.0 Introduction
Ductile iron (DI) pipes are manufactured from ductile iron. Ductile iron is a type of
iron in which graphite is present primarily in spherical or nodular form.
The Contractor shall provide on-site training on DI pipe laying, jointing, testing and
maintenance etc., to the personnel authorized by the Engineer-in-charge. The
contractor should provide technical Manual on DI pipes including precautions to be
taken during operation of the pipeline.
IS 8329 Centrifugally cast(spun) ductile iron pressure pipes for water, gas and
sewage
IS 9523 Ductile iron fittings for pressure pipes for water, gas and sewage
IS 12288 Code of practice for use and laying of Ductile Iron pipes
IS 11606 Methods for sampling of Cast Iron pipes and fittings
IS 5382 Rubber sealing rings for gas mains, water mains and sewers
IS 638 Specification for Sheet Rubber Jointing and Rubber Insertion Jointing
IS 1608 Mechanical testing of metals -tensile testing
IS 1500 Methods for Brunel hardness test for metallic materials
1
manufacture of pipes shall be of good quality commensurate with the
mechanical requirements specified in IS8329.
3.2 Cement : The cement used for the pipe lining shall conform to the existing
standards of cement. Following types of cement can be used for lining.
a) Ordinary Portland cement conforming to IS 8112 or IS 415.
b) Sulphate resisting Portland cement conforming to IS 12330 or IS 6909.
c) High alumina cement conforming to IS 6542.
3.3 Sand : The sand used shall have a controlled granulometric distribution from
fine to coarser elements. It shall be clean and shall be composed of inert, hard,
strong & stable granular particles. The gradation of sand shall be as specified in
IS 8329.
3.4 Water : The water used for the preparation of mortar shall not contain
substances deleterious to the mortar.
3.5 Zinc : Zinc used for coating purpose is metallic zinc with content of atleast 99
% by mass.
3.6 Bitumen: Bitumen used for coating purpose shall be smooth, tenacious and
hard as specified in IS 8329.
3.7 Polyethylene: The density of polyethylene shall be between 910 to 930 kg/m³.
3.8 Rubber gasket : Rubber gaskets used with push-on joints or mechanical shall
conform to IS5382, whereas rubber gaskets for use with flanged joints shall
conform to IS638.
4.1 The metal used for the manufacture of pipes shall be of good quality,
commensurate with the mechanical requirements laid down of IS 8329.
4.2 The pipes shall be stripped with all precaution to avoid warping or shrinkage
defects, detrimental to their good quality. The pipes shall be sound and free
from surface or other defects.
4.3 Pipes centrifugally cast shall be heat-treated in order to achieve the necessary
mechanical properties and to relieve casting stresses caused due to the method
of manufacture and repair work.
4.4 If necessary, the pipes may be subjected to reheat treatment to ensure that
Brinell hardness dose not exceed the specified value and the other
mechanical properties specified in IS8329 are achieved.
2
Pipe Manufacturing Procedure
Molten Iron
Induction Furnace
Spheroidization
Core Making
Centrifugal Casting
Annealing
Zinc Spraying
Grounding & Grinding
Hydraulic Testing
Cement Lining
Cultivating
Bitumen Coating
Packing
3
The value of K will depend on following service conditions.
(Reproduced from IS 8329)
Service conditions
Nominal Water Sewers Gas main
dia Main
80-300 K9-K12 K7-K12 K9-K12
350-600 K8-K10 K7-K10 K9-K10
700-2000 K7-K10 K7-K10 K9-K10
For screwed or welded on flange pipes the minimum classes as per working pressure
criteria are given below.
4
Applications of the finishing layer may be done by any proven process such
as spraying or brush coating at the manufacturer’s choice. It shall uniformly
cover zinc coating and be free from bare patches or lack of adhesion.
The mean dry film thickness of the finishing layer shall not be less that
70µm. with nowhere less than 50µm.
b) Bituminous coating :
Coating shall not be applied to any pipe unless its surfaces are clean,
dry & free from rust.
The mean thickness of coating shall be not less than 70µm & the local
minimum thickness shall be not less than 50µm.
Where the coating material has a bitumen base, it shall be smooth &
tenacious and hard enough not to flow, when expose to temperature of 65 0
c but not so brittle at a temperature of 00C as to chip off when scribed with
a penknife.
c) External sleeving :
The polythelene sleeves may be supplied, for encasement of the pipes at
site, alongwith the pipes if ordered by the purchaser. This encasement
shall be so designed that prevent contact between pipe and surroundings
backfill and bedding material.
The material used for making the film is polyethylene or a mixture of
polyethylene and /or ethylene and olefin copolymers. Its density shall be
between 910 & 930 kg/m3
If protection against ultra violet rays is required , the material shall be
stabilized by the additions of an appropriate product, if carbon black is
used for this purpose the addition shall be in the range of 2 to 3 % by
mass.
4.7.2 Internal lining : Depending upon the internal conditions of use, the internal
lining can be of following two types as specified in IS 8329.
a) Cement mortar lining : The cement used for the lining shall be either ordinary
Portland cement or sulphate resisting portland cement or high alumina cement.
The mortar of the lining shall be composed of cement, sand & water. Additives
, which shall be specified may be used, provided that they do not prejudice the
quality of the coating & that of the transported water. The mortar shall contain
by mass atleast 1 part of cement to 3.5 parts of sand
All foreign bodies , loose scale or any other material which could be detrimental
to good contact between the metal & the lining shall be removed from the
surface to which the lining is to be applied. The inner surface of pipe shall also
be free of any metal projections likely to protrude beyond 50% of thickness of
the lining.
The cement mortar lining at works is applied by a centrifugal spinning process
or a centrifuged sprinkler or combination of both methods.
5
Lining thickness varies from 3mm to 9mm depending on pipe thickness as
specified in IS8329.
The surface of the cement mortar lining shall be uniformly smooth. Only
isolated grains of the sand are allowed to appear on the surface of the lining.
When specified, the cement lining shall be given a seal coat of bituminous
material or any other epoxy base material compatible with cement mortar
lining. The purpose of the seal coat is to minimize lime, leaching of the cement
mortar as well as to restrict the unwanted rise in pH value of the transmitted
water.
b) Bituminous paint : The specification for this shall be as given in sub para (b) of
para 4.7.1 above.
In a consignment, all pipes/ fittings of the same class, type and dimensions
produced by a single manufacturing unit shall constitute a lot. Each lot shall be
inspected separately for ascertaing its conformity to the requirements of
specification given in IS 8329.
Each pipe shall be checked for visual characteristic such as surface defect, finish
& position of socket, flanges, threads, collars.
The lot which has been found satisfactory in respect of visual requirements,
shall be tested for dimensional requirements as specified in following para No.
6.0. Numbers of pipes to be selected from the lot for checking dimensional
requirements shall be as per following Table No.1.
Table No.1 Scale of sampling and criteria for acceptance for dimensional
requirements of pipes.
(Reproduced from IS 11606)
Lot size Sample size Acceptance No.
Upto 50 8 0
51-100 13 1
101-150 20 1
151 -300 32 2
301 & above 50 3
Each of the items selected according to above para shall be inspected for
dimensional requirements. Any item failing to meet above requirements shall
be termed defective. If the number of defectives found in the sample is less
than or equal to acceptance number given in column 3 of above Table 1, the lot
shall be deemed as conforming to the requirements specified. Otherwise, the
lot shall be rejected or subjected to 100 % inspection for the requirements.
The lot found conforming in respect of dimensional requirements shall then be
tested for mechanical acceptance tests as specified in following para No.6.
6
The mechanical acceptance tests shall be carried out on samples of ductile iron
pipes which shall be grouped in following batch sizes.
DN (mm) Maximum Batch Size
80 - 250 200 pipes
300 - 600 100 pipes
700- 1000 60 pipes
1 100 – 1400 40 pipes
1 600 – 2 000 30 pipes
6.1 Dimensions:
Various dimensions of pipes shall be as per the relevant tables of IS.8329 for different
class of pipes.
6.1.1 Critical dimension: Critical dimensions for socket and spigot of pipes for push-
on flexible joints and mechanical joints for classes K7 , K8,K9 & K10 are given in the
following table no.2.
7
Table no.2: Dimensions of sockets & Spigots
All dimensions are in mm
(Reproduced from IS 8329)
6.1.2 External Diameter : External diameter (DE) of the spigot end of socket and
spigot pipes is measured circumferentially using a diameter tape. The positive
8
tolerance for external diameter is + 1 mm and applies to all thickness classes of
pipes. The negative tolerance of the external diameter depends on the design of
each type of joint and maximum negative tolerance is as specified in following
Table No.3
Table 3 External diameter DE (mm)
(Reproduced from 8329)
Dn Nominal Tolerance
(1) (2) (3)
80 98 +1,-2.2
100 118 +1,-2.8
125 144 +1,-2.9
150 170 +1,-3
200 222 +1,-3.1
250 274 +1,-3.3
300 326 +1,-3.4
350 378 +1,-3.5
400 429 +1,-3.6
450 480 +1,-3.8
500 532 +1,-4
600 635 +1,
700 738 +1,-4.3
750 789 +1,-4.4
800 842 +1,-4.5
900 945 +1,-4.8
1000 1048 +1,-5
1100 1152 +1,-6
1200 1255 +1,-6.2
1400 1462 +1,-6.6
1500 1565 +1,-7
1600 1668 +1,-7.4
1800 1875 +1,-8.2
2000 2082 +1,-9
9
6.1.3 Wall Thickness
The tolerance on the wall thickness (e) and the flange thicknes (b) of the pipes
shall be as follows :
Dimensions Tolerance (mm)
i) Wall thickness -(1.3+0.001 DN)1
ii) Flange thickness (b) ±(2+0.05b)
6.1.4 Length
The Standard working length of socket and spigot pipes shall be 4 m, 5
m , 5.5m and 6 m and for flanged pipes shall be 4m, 5 m, and 5.5 m. Other
lengths are available by agreement between the manufacturer and the
purchaser.
The tolerance on length of pipes shall be as follows :
Type of Casting Tolerance
(mm)
i) Socket and spigot and plain ± 100
ended pipes
ii) Flanged pipes ± 10
10
Table 5 Allowable ovality for Mechanical Joint Pipe
(Reproduced from IS 8329)
Nominal Diameter Maximum Ovality of
DN Spigot of External
(mm) Diaameter DE
(mm)
(1) (2)
80 to 150 5
200 to 350 10
400 to 500 20
600 to 800 30
900 to 1000 40
1100 to 1400 50
1600 to 2000 60
6.1.6 Deviation from a straight line: The pipes shall be reasonably straight when
the pipe is rolled along gantries, separated by distance approximately two-thirds
the length of the pipe to be checked, the maximum deviation from a straight line
in mm shall not be greater than 1.25 times the length L, in metres of the pipe;
A Sample shall be cut from the spigot end of the pipe. This sample may be
cut perpendicular to or parallel with the pipe axis, but in case of dispute the
parallel to axis sample shall be used.
A test bar shall be machined from each sample to be representative of the
metal at the mid-thickness of the sample.
11
The test bars shall have a gauge length at least five times the nominal test
bar diameter. The ends of the test bars shall be such that they will fit the
testing machine.
Two methods of measuring the tensile strength are method A or method B
as explained below:
Method A—Machine the test bar to its nominal diameter +/- 10 percent,
measure the actual diameter before the test with an accuracy of 0.01 mm and
use this measured diameter to calculate the cross- sectional area and the
tensile strength.
Method B—Machine the test bar to its nominal area Sₒ within a specified
tolerance on diameter and use the nominal area to calculate the tensile
strength.
The sample shall be tested as per procedures laid down in IS 1608. The test
results shall satisfy the following requirements.
Nominal Diameter Minimum Tensile strength Minimum Elongation at break
(DN) (mm) (MPa) (%)
80-1000 420 10
1100-2000 420 7
For ductile iron pipes upto DN 1000, if the tensile strength of specimen is not
found within limits, and microstructure reveals 75 percent ferrite with
spheroidal graphite and percentage elongation ≥7, it shall be taken as meeting
the requirements.
6.3 Brinell Hardness Test :
When tested in accordance with IS 1500, the Brinell hardness shall not
exceed 230 HB on the external un-machined surface.
6.4 Hydrostatic Test :
All pipes shall be tested hydrostatically at a pressure specified in following
Table no.6. To perform the test, pressure shall be applied internally and
shall be steadily maintained for a period of 10sec. The pipes shall withstand
the pressure test and shall not show any sign of leakage, sweating or other
defects of any kind.
Test shall be carried out before the application of surface coating and lining.
12
Table no.6 Hydrostatic Test Pressure
(Reproduced from IS 8329)
Nominal Minimum Hydrostatic Test Pressure at Works, MPa
Diameter Centrifugally cast pipes with Pipes with screwed or welded on
(DN) (mm) flexible joints flanges
Class K7 Class Class K9, PN PN 16 PN 25 PN 40
K8 Class 10 Flange Flange Flange
K10, Flan
Class ge
K12
(1) (2) (3) (4) (5) (6) (7) (8)
80 to 300 3.2 4.0 5.0 1.6 2.5 3.2 4.0
350 to 600 2.5 3.2 4.0 1.6 2.5 3.2 4.0
700 to 1000 1.8 2.5 3.2 1.6 2.5 3.2 --
1100 to 1.2 1.8 2.5 1.6 2.5 2.5 --
2000
Each pipe shall be indelibly marked in English language at either end of each
pipe. The marking shall show the following.
The first layer of pipes should be laid on a firm foundation consisting of solid timbers
set level on the ground. Subsequent layers should be placed according to the method
of stacking adopted. Care should be taken so that the pipes do not rest on their
sockets. The height of any stack should not exceed 2 m. Stacking of pipes can be either
square or parallel or nested as explained below.
14
Methods for Stacking of Pipes
Square Stacking Parallel Stacking with Nested (Pyramid)
timbers Stacking
nd All the pipes are parallel Nested stacking consists
2 and subsequent
layers are set at right with the sockets of of placing each pipe
angles to previous successive layers reversed between the two pipes
layer with spigots & end-to-end with sockets underneath it, with the
sockets alternating in projecting beyond spigot sockets being all at one
each layer & sockets end. end of each layer &
project beyond spigot Timber battens placed about being reversed in
end. 600 mm from each end at successive layers.
The pipes rest right angles to the pipes are The bottom layer should
directly upon those used to separate the be firmly anchored to
beneath it. successive layers. prevent the stack
Care is needed in Wedges at both ends of each collapse.
placing to prevent batten prevent pipe
damage. movement.
Bitumen-sheathed pipes should not be stacked but laid in a single layer supported on
timbers placed under the uncoated portions of the spigots and sockets.
10.0 Valves
For PDN work, various Valves as mentioned below are required to be provided on
pipeline at various location.
15
10.2 Scour Valve :
These Valves are generally provided to drainout the pipeline. The exact location
of Scour valves is frequently influenced by opportunities to dispose off the water.
Where the main pipeline crosses a stream or drainage structures, there will usually
be a low point in the line but if the main pipeline goes under the stream or drain,
it cannot be completely drained into the channel. In such a situation it is better to
locate a scour connection at the lowest point that will drain by gravity and provide
for pumping out the part below the drain pipeline.
A control valve is a valve used to control fluid flow by varying the size of the flow
passage as directed by a signal from a controller. This enables the direct control
of flow rate and the consequential control of process quantities such
as pressure, temperature, and liquid level.
A) Sliding Stem
Globe valve
Angle body valve
Angle seat piston valve
B) Rotary
Butterfly valve
Ball valve
C) Other
Pinch valve
Diaphragm valve
The Contractor shall clear the entire area required for setting out. All tree
stumps, roots, brushwood, rubbish of all kinds, loose stones and all other
objectionable materials shall be removed by the Contractor. Buried irrigation
pipeline, and other structure, if any, shall be removed by the Contractor. The
ownership of all the usable material, so removed from clearing site and/or
16
excavation shall rest with the Engineer In-charge. Useful material shall be
stacked as directed. The Contractor shall dispose off all unuseful materials as
directed by the Engineer In-charge.
12.2 Demarcation
All materials such as pegs, bamboo’s and strings and templets for marking out
slopes, and labour required for line out should be provided by the Contractor
at his own cost. The center line of excavation shall be clearly marked by pegs
or by stones at each chain or change of direction or at shorter intervals on
curves, in the beginning. The final line out will be done by fixing reference
stone at suitable distances on either side of the center line, beyond the canal
edges so that they are not disturbed during the construction period. The
position of these stones will be marked on the cross section.
12.3 Contractor shall provide and maintain the quarry roads and temporary roads
required for construction activity at his own cost.
12.4 Fixing Permanent Benchmark
(a) Benchmarks fixed by the Survey of India and temporary benchmarks
established by the Engineer In-charge in vicinity of PDN work will serve as
control points for these works. The Contractor shall establish sufficient number
of reference benchmarks for facilitating setting out of work and taking levels
for the purpose of measurements.
(b) Before starting any work, the Contractor shall erect reference benchmarks,
reference lines and check profiles at convenient locations approved by the
Engineer In-Charge. The benchmark concrete block shall be 200mm x200mm
x600mm with 400mm embedded in the firm ground and 200 mm projecting
above ground. The word ‘BM’ showing value of R.L. in ‘m’ shall be
conspicuously carved and painted on the benchmark.
(c) The check profile shall be located 30m apart or closer as directed by the
Engineer In-Charge so as to ensure execution of all slopes, steps and elevations
to the profile or profiles indicated in the approved drawings. All important
levels and all control points with respect to benchmarks and reference lines
shall be fixed and correlated by the Contractor. The Contractor is fully
responsible for maintaining all setting out work & Benchmark established by
Engineer-In-charge.
(d) All materials, labour and equipments (theodolites, levels, distometre, etc.) for
setting out works including construction of benchmarks in concrete, reference
lines, check profiles and surveys as may be required at the various stages of
17
construction shall be supplied by the Contractor at his cost. For this following
numbers of minimum equipments shall be provided and maintained in
good working condition by the Contractor.
3. Levels 2 Nos.
4. Staves 4 Nos.
All equipments shall be of standard and approved make and precision, and
shall be made available in advance of starting of the work. All equipment
shall be maintained, repaired and got tested and certified as and when
required for its accuracy from the standard test houses or from the
manufactures and to the satisfaction of the Engineer-In-Charge.
13.1 Excavation of pipe trenches shall be carried out as per excavation line shown in
the drawing or as directed by Engineer In -charge. Contractor must assume all
responsibility for deductions and conclusion made by him as to the nature of
the materials to be excavated and the difficulties of making and maintaining
the required excavation. The trench width at bottom shall be 300 mm more
than 1.5 times outside pipe diameter. In any case trench width shall not be less
than 500 mm.
13.2 The usable excavated material available from the excavated trenches (PDN)
shall be used in backfilling. If such usable material is in excess of the
requirement of backfilling, the same shall be deposited in the spoils as and
where directed by the Engineer In-charge. Unuseful material from excavation
shall be deposited in spoils as and where directed by Engineer-In-charge.
13.3 Surface or sub-soil water met with during trench excavation (PDN) and
structure excavation shall be diverted to nearby drain/nalla by cutting an open
channel from trench. When the drain/nalla bed is higher than the sub-soil
water level met with, the bailing out by suitable means of pumping shall be
resorted to for dewatering sub-soil water below the drain/nalla bed level. No
distinction shall be made as to whether the material being excavated is dry,
moist, wet or slushy. The Contractor shall have to excavate the PDN pipe trench
and structure in under water level conditions also i.e. under wet/slushy
18
condition after providing sufficient arrangement of dewatering. The material
excavated under water level condition which requires intermediate stacking for
drying shall have to be rehandled. No extra payment for efforts for drying out
of soil, re-handling of dry soil, etc. shall be given. No payment for extra efforts
for excavation under this condition shall be made.
13.4 Over excavation performed by the Contractor for any purpose or reason,
except for additional excavation as may be directed by the Engineer-In-charge,
shall be rectified at the cost of the Contractor. Filling and compaction for such
over excavation using the material as directed by the Engineer In- Charge shall
also be at the cost of the Contractor.
13.5 In the PDN and structure section where expansive type of the soil such as CH
type of soil is encountered and over which PDN cannot be directly laid, the PDN
trench and structure shall be over excavated to the extent as directed by the
Engineer In Charge and such over excavated section shall be filled with suitable
murum type soil to be placed in uniformly compacted layers as directed by the
Engineer In Charge. The over excavation made in such strata, filling by suitable
soil, and watering and compacting such soil will be paid separately under
relevant items. Above provision for over excavating and filling with suitable
murum type or good soil available material shall be applicable in case such
treatment is found essential.
20
15.2 Flanged Joint-
Flanged joints are made on pipes having a machined flange at each end of
the pipe. The seal is usually affected by means of a flat rubber gasket
compressed between two flanges by means of bolts which also serve to
connect the pipe rigidly. Gaskets of other materials, both metallic and non-
metallic, are used for special applications.
In case of ductile iron pipes with screwed on flanges or welded flanges, the
flanges shall be at right angle to the axis of the pipe and shall be machined
on face. The bolt holes shall be either cored or drilled.
15.3 Jointing Procedure-
Procedure for jointing will vary according to the type of joint being used.
Basic requirements for all types are:
a) Cleanliness of all parts,
b) Correct location of components,
c) Centralization of Spigot within socket, and
d) Strict compliance with manufacturer's jointing instructions.
The inside of sockets and the outside of spigots should be cleaned and wire
brushed for a distance of 150 to 225 mm.
Glands & gaskets should be wiped clean and inspected for damage.
When the pipeline is likely to be subjected to movement due to subsidence
or temperature variations, the use of flexible joints is recommended. A gap
21
should be left between the end of the spigot and the back of socket to
accommodate such movement.
All pipelines should be tested before being brought into service. The test
should be a hydrostatic test performed by filling the pipeline with water and
raising the pressure to the selected test pressure and maintaining this for a
sufficient period to allow for absorption of water by the pipe material.
After a new pipeline is laid and jointed, testing shall be done for:
a) mechanical soundness and leak tightness of pipes and fittings;
b) leak tightness of joints; and
c) Soundness of any construction work, in particular that of the
anchorages.
22
water, taking care that all the air is displaced either through vents at the
high points or by using a pig or a sphere.
After filling, the pipeline should be pressurized to the specified operating
pressure and left for a period of time to achieve stable conditions. The
length of this period of time depends on many factors such as slight
movement of the pipeline under pressure whether air is trapped in the
pipeline or whether the pipeline has a concrete lining which absorbs water.
The pipeline is then pressurized up to the full test pressure and the section
under test completely closed off. The test should be maintained for a period
of not less than 10 minutes to reveal any defects in the pipes, joints or
anchorages.
23
Table no-7 Maximum Field hydrostatic test pressure for ductile iron
pipelines with flexible joints
(Reproduced from IS 12288)
(a) The type of material used for backfilling and the manner of depositing
the material, shall be subject to approval by the Engineer-in-Charge.
(b) The backfill material shall be placed to the line and grades as shown on
drawings or as prescribed in this paragraph or as directed by the Engineer-in-
Charge.
(c) The backfill material shall be placed carefully and spread in uniform
layers of not more than 15cm thickness, with the first layer watered and
compacted by stamping or by mechanical means. The backfill shall be brought
up as uniformly as practicable on both sides of pipe to prevent unequal loading.
(d) Only soft earth and gravel of good quality free from boulder, roots,
vegetable matters etc. shall be used for refilling of trench upto 300mm above
the top of the pipe. If sufficient quantity of suitable (Sharp edge stone free)
excavated earth is not available, the trench shall be filled by borrowed gravel
material upto 300 mm above top of pipeline. Remaining trench can be filled
with available material.
(e) When compacting the soil against steep rock, abutment walls of
concrete structures, rollers shall not be used close to structures as structural
damage is very likely more particularly when structures have not been fully
cured. The size and weight of equipment will depend on nature of material, the
height and load assumed in design of structure. The backfill close to the
structure up to the rolled layer shall be compacted in suitable uniform layers,
using pneumatic / hand tampers as appropriate for dry density at average bulk
density (+/- 10%). The moisture content of the earth fill placed against the rock
or the structure shall be on higher/lower side of OMC by about 2% or so, to
allow it to be compacted. Profuse watering shall be done to pervious materials
(sand) before compaction as per instruction of the Engineer-in-Charge.
24
Compaction at junction of earthwork and backfill around the structure shall be
carried out with special care.
(f) The trench shall be refilled so as to built-up the original ground level.
18.1 The contractor shall establish the sufficient number of reference blocks on
the alignment of PDN preferably at the interval of 30m or as suitable on the
field boundaries so as they will not be disturbed during the agricultural
activities of the farmers.
18.3 These blocks shall be able to locate the pipeline as and where it is laid all over
the work. The contractor shall mark each block with specific distinct
identification mark.
18.4 The contractor shall show all this blocks jointly to the Engineer-in-charge or his
representative, representative of WUA, concern farmers sharing the
boundaries, TPI, any other stake holders in the command.
18.5 Contractor shall maintain these blocks in proper order during operation &
maintenance period of the contract. Any damage done to these blocks for the
reasons whatsoever shall be made good at the cost of contractor.
18.6 The contractor shall submit the location of such blocks with specific
identification marks with schedule on a special command area map.
18.7 The map of marking of the block shall be handed over to WUA while handing
over the command area.
18.8 The Geo-tagging map showing Latitude and Longitude value of each apex of
laid pipeline shall be submitted to Department and WUA for future reference.
18.9 The contract shall fix information boards of 1.2 m x 0.9 m size at various location
as directed by Engineer-in-charge. On these boards, salient features of the work
(e.g. Pipe diameter, pipe type, discharge, any other specific details suggested by
Engineer-In-Charge) shall be written.
25
19.0 Third Party Inspection
19.1 Work of PDN shall be inspected, tested and certified by PMC / TPI / QC.
Modalities of PMC / TPI / QC Inspection shall be separately decided and given
by Engineer In-charge.
Third party Inspection can be done form any one of the following services
or from any other mutually agreed agency.
1 Engineers India Limited, Mumbai
2 R.I.T.E.S. (Rail India Technical Economics Services) Mumbai
3 S.G.S, Mumbai
4 Visvesvaraya National Institute of Technology, Nagpur
5 VJTI, Mumbai
6 CWPRS (Central Water & Power Research Station), Pune
7 CIPET (Central Institute of Plastics Engineering & Technology)
(a) All materials before being utilized in works shall be inspected and tested,
by the Engineer In-charge or his representative/QC. The nature of testing
and periodical intervals at which such testing is to be done etc. shall be as
per the latest editions of relevant IS Codes and determined by the Engineer
In-charge. The day-to-day and periodical tests to be carried out on
materials mixes and placed concrete, mortar etc. shall be specified by the
Engineer In-charge from time to time and the Contractor shall provide free
of cost all facilities towards collections of samples etc. unless otherwise
specified. Labours for collecting samples and transportation of the samples
to quality control authorities for test shall be provided free of cost by the
contractor. Also electricity, fuel, water curing tank and stores etc shall be
provided free of cost by the contractors.
(b) The materials shall be tested in QC laboratory or at any other place directed
by the Engineer In-charge. The Contractor shall obtain the test results from
the concern authority and the results given by such authorities shall be
considered to determine whether all materials, workmanship are of
respective standard described in contract and in accordance with the
instructions of the Engineer In-charge. The Contractor’s representatives
shall, however, be given access to all operations and tests that may be
carried out as aforesaid so that he may satisfy himself regarding the
procedure and methods adopted. It shall then be the Contractor’s
responsibility to produce on the work, materials and finished item to the
26
standard as determined by the laboratory tests or to take follow up action
to rectify the quality.
(c) Testing charges for testing of Cement, TMT bars, all types of pipes and
specials including cost of samples and its collection shall be borne by the
Contractor.
(d) The Contractor shall make suitable arrangements to see that one of his
representatives remains present at the time of taking samples and shall
authenticate the facts. If the Contractor, fails to keep his representative
present at site at the time of taking samples or fail to provide required
labours and other equipment to collect the samples, the same shall be
taken by the Engineer In-charge, and the samples selected shall be
considered as authentic. The cost incurred by the Engineer-In-charge when
the Contractor fails to provide required men and materials for collecting
samples and or their transport shall be recovered from the Contractor.
20.1 On award of contract, the Contractor will have to provide adequate quality
assurance setup including Quality Assurance Engineer backed with suitable
laboratory assistants, labours and well equipped laboratory for taking
necessary field test required as per specifications and as per instructions of
Engineer in charge.
20.2 Following minimum persons shall be employed by the contractor at work site
for Quality Assurance.
Sr.
Personnel with Qualification Nos.
No.
27
20.3 Following minimum equipments shall be available in the field laboratory setup
by the contractor.
Sr.
Work Apparatus for Tests
No.
28
20.8 If he fails to fulfill the above requirement, the required manpower for testing
and field laboratory with required equipments will be deployed by the Engineer
in charge and the charges for the same will be recovered from the contractor.
21.1 The contractor shall operate and maintain the complete pipe distribution
network for the period of 5 (five) years after commissioning. Out of this period,
during last two years the operation of the schemes shall be done by the
contractor jointly along with WUA. On completion of O & M period, the system
shall be handed over to WUA
21.2 During rotation period, once in every year, the Contractor shall perform
hydraulic test to the satisfaction of Engineer In-charge to verify the flow of
designed discharge, detect or confirm any leakage in the system and rectify at
his own cost. The testing shall preferably be conducted jointly with members
of WUA/representative of Engineer In-charge, technical representative of
contractor and any other stake holder.
21.3 On completion of every Irrigation season, the contractor shall flush the pipe
line from its tail flush valve so that any siltation, vegetation or obstruction is
cleaned and pipe is able to flow designed discharge for next season.
21.4 During the O & M period, contractor shall give training to the members of WUA
about O & M of PDN work and its efficient use and protection of the system
from any damages.
21.5 The contractor shall prepare a detail map of the permanent marking along the
alignment of pipe and submit the same to Engineer In-charge. The Engineer In-
charge shall verify and endorse the location of the marking and handover these
signed maps as a permanent record to WUA. Along with this, the detailed
Geotagged map of laid pipeline shall also be handed over to WUA.
21.6 In association of the members of WUA, the Engineer In-charge shall confirm
the release of designed discharge through every outlet before handing over. In
case of any short fall or defect, it should be made good from the contractor at
his own cost.
22.0 Mode of Measurement and Payment
22.1 Measurement
The net length of pipes as laid or fixed shall be measured in running meters
correct to a cm. Specials shall be excluded and measured in running meters or
numbers as specified by Engineer-in-charge and paid for separately under the
29
relevant item. The portion of the pipe overlapped at the joints shall not be
included in the length of pipe work. Excavation, refilling, anchor blocks, thrust
blocks wherever required shall be measured and paid for separately under
relevant items of work.
22.2 Payment
The break up to payment for supplying, laying, jointing & hydraulic testing of
pipe line shall be as under:-
----------***----------
30
Govt. of Maharashtra
Water Resources Department
SPECIFICATIONS FOR
SPIRALLY WOUND STEEL
REINFORCED PIPES (SWSRP)
2020
0
SPECIFICATION FOR SPIRALLY WOUND STEEL REINFORCED PIPES (SWSRP)
1.0 Introduction
The Spirally Wound Steel Reinforced Pipes (SWSRP) are structured wall
pipes comprising of an HDPE inner smooth layer, spiral steel skeleton and
outer corrugated profile of HDPE. This pipe utilizes a state – of – the – art
manufacturing process which results in a product which has an excellent
external overburden bearing capacity and internal pressure sustenance.
SWSRP Pipes
2.0 Applicable IS Codes, ISO Codes
The manufacturing, testing, supplying, laying, jointing and testing at work sites
of SWSRP pipes shall comply with all currently applicable statutes, regulations,
standards and Codes. In particular, the following standards, unless otherwise
specified herein, shall be referred. In all cases the latest revision of the Codes
shall be referred to. If requirements of this Specification conflict with the
requirements of the standards/Codes, this Specification shall govern. Others
Codes not specifically mentioned here but pertaining to the use of SWSRP Pipes
form part of these Specifications.
1
IS 2530: 1963 Methods of test for polyethylene molding materials and
polyethylene compounds
IS 7328 : 1992 High DENSITY polyethylene materials for moulding and
extrusion
ISI 12235 (Part6) - Thermoplastic pipes and fittings methods of tests part 6 :
2004 Stress relief test
ISI 12235 (Part 9) Thermoplastic pipes and fittings methods of tests part 9 :
- Resistance to external blows
2004
IS 16098 Part- Structured wall Plastics Piping Systems for Non pressure
I:2013 drainage & Sewerage - Pipes and fittings with smooth
external surface
IS 16098 Part- Structured wall Plastics Piping Systems for Non pressure
II:2013 drainage & Sewerage- Pipes and fittings with non-smooth
external surface
3
Table No.3 : Scale of sampling for test other than visual and dimensional
requirements ( reproduced from IS 16058)
No of pieps in lot Sample size for Sample size for
ID ≤ 500mm ID ≥ 500mm
Upto 1000 2 1
1001 to 3000 3 2
More than 3000 4 3
These pipes shall be selected at random from the lot and in order to ensure
the randomness of selection, a random number table shall be used.
4
6.1 Dimensions
6.1.1 Length:
The length of pipe shall be 4, 5 or 6 m. The pipe may be supplied in
other lengths, as agreed between the manufacturer and the
purchaser
6.1.2 Diameter of pipe
The internal diameter (DN/ID) shall be as per table No.4
Table 4 : Nominal sizes shall be as per Table 4 : Nominal sizes , minimum means
inside diameters, thickness of inside layer ( reproduced from IS 16058)
5
6.2 Visual Appearance
The structured outer layer of finished pipes shall be uniformly corrugated.
The inner layer shall be smooth and plain. Both layers shall be free from any
visual defects such as cracks, blisters, foreign inclusions and any other visual
irregularities which may cause harm to its construction integrities. The inner
surface may reflect slight shallow undulation.
6.3 Colour of Finished Pipe
Colour of Finished Pipes shall be declared by manufacturer. The colour of
outer layer should be preferably black.
For the wall thickness, e, the maximum measured wall thickness of the pipe excluding ec shall be
taken
6
Table 6 Mechanical Characteristics (Reproduced from IS 16098 Part-II)
Each pipe shall be indelibly marked in English language at either end of each
pipe. The marking shall show the following.
1. Manufactures name or trademark.
2. Grade of raw material
3. Pressure rating.
4. Nominal diameter
5. Lot/batch No. of manufacturer.
6. BIS certification mark.
7. Third Party Certification mark for each lot
8. Name of Department/Project for which pipes are manufactured.
9. Any other important matter that the manufacturer or purchaser deems fit to
be inscribed.
7
8.0 Transportation of Pipe:
When transporting pipes, flat bed vehicles should be used. The vehicle
should be free from nails and other projections. Pipes should rest
uniformly on the vehicle over the whole length.
The pipes should be secured effectively during transport.
When loading spigot and socket pipes, the pipes should be stacked on the
vehicle so that the socket do not take excessive loads.
Mechanical lifting equipment used for lifting pipes and pipe bundles
should not damage the pipe. Loading boom or fork lift should not be used
directly on or inside the pipe.
The arrangement of loading the pipes in the truck in a telescopic manner
(i.e. smaller diameters inserted in next higher sizes) is advised.
If pipes have been telescoped for transporting, the inner pipes should be
removed first and stacked separately.
8
9.0 Stacking of Pipes at Site
The area selected for stacking should be plain and care is to be taken to
remove any pointed objects / stones from the area.
Pipes shall be smoothly lowered to ground.
Pipes should not be dragged against the ground to avoid the damages to
the pipes.
Stacking shall done on a flat clear area as shown below.
Stack height should not be higher than 2.5 m.
The stacks should be covered with an LDPE Sheet to avoid direct
exposure to sunlight.
10.0 Valves
For PDN work, various Valves as mentioned below are required to be provided
on pipeline at various location.
9
is divided into high pressure trace exhaust valve, low pressure air release
valve and combined air valve.
A control valve is a valve used to control fluid flow by varying the size of the
flow passage as directed by a signal from a controller. This enables the direct
control of flow rate and the consequential control of process quantities
such as pressure, temperature, and liquid level.
Common types of control valve are as given below.
A) Sliding Stem
Globe valve
Angle body valve
Angle seat piston valve
B) Rotary
Butterfly valve
Ball valve
C) Other
Pinch valve
Diaphragm valve
11
All equipments shall be of standard and approved make and precision, and shall be
made available in advance of starting of the work. All equipment shall be
maintained, repaired and got tested and certified as and when required for its
accuracy from the standard test houses or from the manufactures and to the
satisfaction of the Engineer-In-Charge.
13.0 Excavation for Pipe Trenches
13.1 Excavation of pipe trenches shall be carried out as per excavation line shown in
the drawing or as directed by Engineer In -charge. Contractor must assume all
responsibility for deductions and conclusion made by him as to the nature of the
materials to be excavated and the difficulties of making and maintaining the
required excavation. The trench width at bottom shall be 300 mm more than 1.5
times outside pipe diameter. In any case trench width shall not be less than 500
mm.
13.2 The usable excavated material available from the excavated trenches (PDN) shall
be used in backfilling. If such usable material is in excess of the requirement of
backfilling, the same shall be deposited in the spoils as and where directed by the
Engineer In-charge. Unusful material from excavation shall be deposited in spoils
as and where directed by Engineer-In-charge.
13.3 Surface or sub-soil water met with during trench excavation (PDN) and structure
excavation shall be diverted to nearby drain/nalla by cutting an open channel
from trench. When the drain/nalla bed is higher than the sub-soil water level met
with, the bailing out by suitable means of pumping shall be resorted to for
dewatering sub-soil water below the drain/nalla bed level. No distinction shall be
made as to whether the material being excavated is dry, moist, wet or slushy.
The Contractor shall have to excavate the PDN pipe trench and structure in under
water level conditions also i.e. under wet/slushy condition after providing
sufficient arrangement of dewatering. The material excavated under water level
condition which requires intermediate stacking for drying shall have to be
rehandled. No extra payment for efforts for drying out of soil, re-handling of dry
soil, etc. shall be given. No payment for extra efforts for excavation under this
condition shall be made.
13.4 Over excavation performed by the Contractor for any purpose or reason, except
for additional excavation as stated here in above or as may be directed by the
Engineer-In-charge, shall be rectified at the cost of the Contractor. Filling and
compaction for such over excavation using the material as directed by the
Engineer In- Charge shall also be at the cost of the Contractor.
13.5 In the PDN and structure section where expansive type of the soil such as CH type
of soil is encountered and over which PDN cannot be directly laid, the PDN trench
and structure shall be over excavated to the extent as directed by the Engineer
In Charge and such over excavated section shall be filled with suitable murum
type soil to be placed in uniformly compacted layers as
12
directed by the Engineer In Charge. The over excavation made in such
strata, filling by suitable soil, and watering and compacting such soil will be
paid separately under relevant items. Above provision for over excavating
and filling with suitable murum type or good soil available material shall be
applicable in case such treatment is found essential.
14.1 Each pipe shall be thoroughly checked for any damages before laying and only
pipes that are approved by Engineer-in-Charge shall be laid.
14.2 The pipe line may be laid along side of the trench and jointed there. There after
the jointed pipeline shall be lowered into the trench carefully without causing
undue bending. The pipeline shall be laid inside the trench with a slack of up to
2 m/100 m of pipe line.
14.3 Polyethylene pipes being black in colour, when subjected to direct sunlight or
warm ambient temperature may become warmer than the ground temperature.
When placed inside the trench, the pipe will contract in length as it cools to the
surrounding soil temperature. If the pipe is connected to sub- surface structures
(such as preset valve, etc) before it is cooled sufficiently, excessive pull forces
could develop. Allow the pipe to cool to ambient temperature prior to making a
connection to an anchored joint.
14.4 Polyethylene pipe requires no special bed preparation for laying the pipe
underground, except that there shall be no sharp objects around the pipe.
However, while laying in rocky areas suitable sand bedding should be provided
around the pipe and compacted. 100 mm compacted fine sand bedding under
and around the pipe be provided in rocky areas.
14.5 During the pipe laying of continuous fusion jointed systems, due care and
allowance should be made for the movements likely to occur due to the thermal
expansion/contraction of the material. This effect is most pronounced at end
connections to fixed positions (such as valves etc.) and at branch connections.
14.6 The flexibility of polyethylene pipes allows the pipe to be cold bend. The fusion
jointed PE pipe is also flexible as the plain Pipe. Thus the total system enables
directional changes within the trench without recourse to the provision of
special bends or anchor blocks.
14.7 The pipe shall be laid on a stable foundation. Where water is present or where
the trench bottom is unstable, excess water should be removed before laying
the pipe. In case there is a chance of floatation because of likely flood, the pipe
shall be encased with concrete weights as per the buoyancy calculations.
14.8 Polyethylene pipes are non-metallic, so once buried, metal detector type
locators are ineffective. To facilitate locating a buried PE pipe, metallic locating
tapes or copper wires can be placed alongside the pipe. Locating
13
tapes/wires are placed slightly above the crown of the pipe before the
final back fill.
14
d) The test pressure shall be 1.5 times the rated pressure of pipes or of
the proposed maximum design pressure of the section. Apply the
pressure by continuously pumping at a constant rate.
e) Tests should be performed on reasonable lengths of pipelines. Long
lengths more than 2 000 m may make leak detection more difficult.
f) Acceptance criteria — If the pressure remains steady (within 5 percent
of the target value) for 1½ h, leakage is not indicated.
g) If the test is not complete because of leakage or equipment failures,
the test section shall be depressurized and allowed to relax for at least
8 h, before starting the next testing sequence.
16.2 If any leakage is found during testing of pipeline, Contractor will have to
attend the same immediately and rectify at his cost within. If Contractor
fails to rectify the defect, the entire length of pipeline between two
adjacent outlets shall be rejected. If any intermediate payment is made to
the Contractor for portion under rejection, the same shall be recovered
from the outstanding dues of the Contractor.
15
(f) The trench shall be refilled so as to built-up the original ground level.
16
4 Visvesvaraya National Institute of Technology, Nagpur
5 VJTI, Mumbai
6 CWPRS (Central Water & Power Research Station), Pune
7 CIPET (Central Institute of Plastics Engineering & Technology)
17
20.1 On award of contract, the Contractor will have to provide adequate
quality assurance setup including Quality Assurance Engineer backed with
suitable laboratory assistants, labours and well equipped laboratory for
taking necessary field test required as per specifications and as per
instructions of Engineer in charge.
20.2 Following minimum persons shall be employed by the contractor at work
site for Quality Assurance.
18
20.6 Contractor shall provide all test reports of material used in the work as
desired from the NABL (National Accreditation Board for Testing &
Calibration Laboratories) approved laboratories and from Quality Control,
MERI laboratories of the WRD. Contractor shall provide periodical quality
assurance report (Weekly/fortnightly/monthly) to Engineer in Charge
along with proofs in support of quality of material brought for the work,
the process/ execution of work is as per specification.
20.7 Contractor shall submit the account of all materials brought for the work,
which are necessary for execution of work and any other data necessary
to assess the quality of work.
20.8 If he fails to fulfill the above requirement, the required manpower for
testing and field laboratory with required equipments will be deployed by
the Engineer in charge and the charges for the same will be recovered
from the contractor.
21.2 During rotation period, once in every year, the Contractor shall perform
hydraulic test to the satisfaction of Engineer In-charge to verify the flow
of designed discharge, detect or confirm any leakage in the system and
rectify at his own cost. The testing shall preferably be conducted jointly
with members of WUA/representative of Engineer In-charge, technical
representative of contractor and any other stake holder.
21.3 On completion of every Irrigation season, the contractor shall flush the
pipe line from its tail flush valve so that any siltation, vegetation or
obstruction is cleaned and pipe is able to flow designed discharge for next
season.
21.4 During the O & M period, contractor shall give training to the members of
WUA about O & M of PDN work and its efficient use and protection of the
system from any damages.
21.5 The contractor shall prepare a detail map of the permanent marking along
the alignment of pipe and submit the same to Engineer In-charge. The
Engineer In-charge shall verify and endorse the location of the marking
and handover these signed maps as a permanent record to WUA. Along
with this, the detailed Geotagged map of laid pipeline shall be handed
over to WUA.
21.6 In association of the members of WUA, the Engineer In-charge shall
confirm the release of designed discharge through every outlet before
handing over. In case of any short fall or defect, it should be made good
from the contractor at his own cost.
19
22.0 Mode of Measurement and Payment
22.1 Measurement
The net length of pipes as laid or fixed shall be measured in running meters
correct to a cm. Specials shall be excluded and measured in running
meters or numbers as specified by Engineer-in-charge and paid for
separately under the relevant item. The portion of the pipe overlapped at
the joints shall not be included in the length of pipe work. Excavation,
refilling, anchor blocks, thrust blocks wherever required shall be
measured and paid for separately under relevant items of work.
22.2 Payment
The break up to payment for supplying, laying and jointing of pipes shall
be as under:-
A) 80% of the payment will be released after supplying, lowering, laying,
Jointing and third party inspection of pipes in one WUA area.
B) Balance 10% of the payment will be released after satisfactory
hydraulic testing of pipeline and backfilling of trenches.
C) Remaining 10% amount will be withheld and it will be released after
successful maintenance and operation for a period of five years after
commissioning of work of respective WUAs.
The schedule of release of this 10% will be in following manner,
1) After Successful Operation and Maintenance for First year-2%
2) After Successful Operation and Maintenance for Second year-2%
3) After Successful Operation and Maintenance for Third year-2%
4) After Successful Operation and Maintenance for Fourth year-2%
5) After Successful Operation and Maintenance for Fifth year-2%
A certificate regarding smooth working of pipe distribution network from
the Chairman of WUA shall be binding for annual release of this amount.
----------***----------
20
Govt. of Maharashtra
Water Resources Department
SPECIFICATIONS FOR
UNPLASTICIZED POLYVINYL
CHLORIDE PIPES (PVC-O)
2020
SPECIFICATION FOR UNPLASTICIZED POLYVINYL CHLORIDE PIPES (PVC-O)
1.0 Introduction
Technology for manufacturing pipes, which involves process of controlled
circumferential and axial orientation of molecular structure resulting in formation of
laminar structure of the material used in the pipe construction, is commonly known
as PVC-O (Polyvinyl Chloride - Oriented). Manufacturing of pipes by this technology
increases performance and strength of pipes.
The Contractor shall provide onsite training on PVC-O pipe laying, jointing, testing
and maintenance etc., to the personnel authorized by the Engineer-in-charge. The
contractor should provide technical Manual on PVC-O pipes including precautions to
be taken during operation of the pipeline.
IS - 10151 Specification for polyvinylchloride (PVC) & its copolymers for its safe use
in contact with foodstuffs pharmaceuticals& drinking water.
< 1.4 32
I 45.0 450
1.6 28
< 1.4 36
II 50.0 500
1.6 31
For this purpose, the number of pipes given for the first sample in Col No. 4 of
Table No.4 shall be taken from the lot. The sample pipe failing the Vicat
softening test shall be considered as defective. The lot shall be deemed to
have met the requirement given in this specification for the Vicat softening
test. If the number of defectives found in the first sample is less than or equal
to the corresponding acceptance number given in Col No. 6. The lot shall be
deemed not to have met these requirements, if the number of defectives
found in the first sample is greater than or equal to the corresponding
rejection number given in Col No.6. If, however, the number of defectives in
the first sample lies between the corresponding acceptance and rejection
numbers given in Col No.6 and Col. 7 a second sample of size given in Col No.4
shall be taken and examined for the requirement. The lot shall be considered
to have satisfied the requirement, if the number of defectives found in the
cumulative sample is less than or equal to the corresponding acceptance
number given in Col No.6 otherwise not.
5.3 Density
The lot having satisfied the requirement for visual appearance and colour and
dimensional requirement shall be tested for density. For this purpose,
procedure adopted for sampling and criteria for conformity shall be the same
as that given in above point No. 5.2 and Table No.4.
The lot having been found satisfactory according to above para 5.1, 5.2 and 5.3
shall be tested for resistance to external blows at 0o C. For this purpose, the
procedure adopted for sampling and criteria for conformity shall be as per
following Table No. 5.
6.1 Dimensions
6.1.2 Wall Thickness: The wall thickness of the pipes shall confirm to values
specified in following Table No.8
6.3 Colour
The colour of the pipe shall be any shade of grey, blue or cream. The pipe may
also be supplied in any other colour as agreed to between the manufacturer
and the supplier. Slight variations in the appearance of the colour may be
permitted.
6.4 Opacity
The wall of the pipe shall not transmit more than 0.2 % of the visible light
falling on it when tested in accordance with IS 12235
10.0 Valves
For PDN work, various Valves as mentioned below are required to be provided on
pipeline at various locations.
10.1 Air Valve :
The effect of air valve in the long-distance water pipelines are in the following
three areas: firstly, in the water filled stage of the pipeline, filled with water by a
certain velocity, the air valve can discharge the remained gas in the pipe;
secondly, at the normal working stage, the air valve can discharge the small
amount of gas gathered in the pipe timely; finally, during the pump failure or
maintenance stages, the air valve will replenish the gas into the pipe to break the
vacuum. According to the orifice size, displacement and work pressure, air valve
D:\POOJA\HANDBOOK FINAL\HANDBOOK VOLUME II\10 O-PVC SPECIFICATIONS print copy.docx
012
is divided into high pressure trace exhaust valve, low pressure air release valve
and combined air valve.
10.2 Scour Valve :
These Valves are generally provided to drainout the pipeline.The exact location
of Scour valves is frequently influenced by opportunities to dispose off the water.
Where the main pipeline crosses a stream or drainage structures, there will
usually be a low point in the line but if the main pipeline goes under the stream
or drain, it cannot be completely drained into the channel. In such a situation it is
better to locate a scour connection at the lowest point that will drain by gravity
and provide for pumping out the part below the drain pipeline.
10.3 Control Valve :
A control valve is a valve used to control fluid flow by varying the size of the flow
passage as directed by a signal from a controller. This enables the direct control
of flow rate and the consequential control of process quantities such
as pressure, temperature, and liquid level.
Common types of control valve are as given below.
A) Sliding Stem
Globe valve
Angle body valve
Angle seat piston valve
B) Rotary
Butterfly valve
Ball valve
C) Other
Pinch valve
Diaphragm valve
13.1 Excavation of pipe trenches shall be carried out as per excavation line shown
in the drawing or as directed by Engineer In -charge. Contractor must assume
all responsibility for deductions and conclusion made by him as to the nature
of the materials to be excavated and the difficulties of making and maintaining
the required excavation. The trench width at bottom shall be 300 mm more
than 1.5 times outside pipe diameter. In any case trench width shall not be less
than 500 mm.
13.2 The usable excavated material available from the excavated trenches (PDN)
shall be used in backfilling. If such usable material is in excess of the
requirement of backfilling, the same shall be deposited in the spoils as and
where directed by the Engineer In-charge. Unuseful material from excavation
shall be deposited in spoils as and where directed by Engineer-In-charge.
13.3 Surface or sub-soil water met with during trench excavation (PDN) and
structure excavation shall be diverted to nearby drain/nalla by cutting an open
channel from trench. When the drain/nalla bed is higher than the sub-soil
water level met with, the bailing out by suitable means of pumping shall be
resorted to for dewatering sub-soil water below the drain/nalla bed level. No
distinction shall be made as to whether the material being excavated is dry,
moist, wet or slushy. The Contractor shall have to excavate the PDN pipe
trench and structure in under water level conditions also i.e. under wet/slushy
condition after providing sufficient arrangement of dewatering. The material
excavated under water level condition which requires intermediate stacking
for drying shall have to be rehandled. No extra payment for efforts for drying
out of soil, re-handling of dry soil, etc. shall be given. No payment for extra
efforts for excavation under this condition shall be made.
13.4 Over excavation performed by the Contractor for any purpose or reason,
except for additional excavation as may be directed by the Engineer-In-charge,
shall be rectified at the cost of the Contractor. Filling and compaction for such
over excavation using the material as directed by the Engineer In- Charge shall
also be at the cost of the Contractor.
13.5 In the PDN and structure section where expansive type of the soil such as CH
type of soil is encountered and over which PDN cannot be directly laid, the
PDN trench and structure shall be over excavated to the extent as directed by
the Engineer In Charge and such over excavated section shall be filled with
suitable murum type soil to be placed in uniformly compacted layers as
directed by the Engineer In Charge. The over excavation made in such strata,
D:\POOJA\HANDBOOK FINAL\HANDBOOK VOLUME II\10 O-PVC SPECIFICATIONS print copy.docx
015
filling by suitable soil, and watering and compacting such soil will be paid
separately under relevant items. Above provision for over excavating and
filling with suitable murum type or good soil available material shall be
applicable in case such treatment is found essential.
16.1 General
All pipelines should be tested before being brought into service. The test should
be a hydrostatic test performed by filling the pipeline with water and raising the
pressure to the selected test pressure and maintaining this for a sufficient period
to allow for absorption of water by the pipe material.
16.2 Site Test Pressure
The test should confirm to following conditions
a) be carried out at ambient temperature;
b) be applied for at least 1 h, but not more than 24 h; and
c) not exceed 1.5 times the maximum rated pressure of the lowest rated
component.
19.1 Work of PDN shall be inspected, tested and certified by PMC / TPI / QC.
Modalities of PMC / TPI / QC Inspection shall be separately decided and given
by Engineer In-charge.
Project management consultants (PMC) should have approved laboratories
certification or collaboration with N.A.B.L. (National Accreditation Board for
Testing and Calibration Laboratories)
Third party Inspection can be done form any one of the following services
or from any other mutually agreed agency.
1 Engineers India Limited, Mumbai
2 R.I.T.E.S. (Rail India Technical Economics Services)Mumbai
3 S.G.S, Mumbai
4 Visvesvaraya National Institute of Technology, Nagpur
5 VJTI, Mumbai
D:\POOJA\HANDBOOK FINAL\HANDBOOK VOLUME II\10 O-PVC SPECIFICATIONS print copy.docx
021
6 CWPRS(Central Water & Power Research Station), Pune
7 CIPET (Central Institute of Plastics Engineering & Technology)
21.1 The contractor shall operate and maintain the complete pipe distribution
network for the period of 5 (five) years after commissioning. Out of this period,
during last two years the operation of the schemes shall be done by the
contractor jointly along with WUA. On completion of O & M period, the system
shall be handed over to WUA
21.2 During rotation period, once in every year, the Contractor shall perform
hydraulic test to the satisfaction of Engineer In-charge to verify the flow of
designed discharge, detect or confirm any leakage in the system and rectify at
his own cost. The testing shall preferably be conducted jointly with members
of WUA/representative of Engineer In-charge, technical representative of
contractor and any other stake holder.
21.3 On completion of every Irrigation season, the contractor shall flush the pipe
line from its tail flush valve so that any siltation, vegetation or obstruction is
cleaned and pipe is able to flow designed discharge for next season.
21.4 During the O & M period, contractor shall give training to the members of WUA
about O & M of PDN work and its efficient use and protection of the system
from any damages.
21.5 The contractor shall prepare a detail map of the permanent marking along the
alignment of pipe and submit the same to Engineer In-charge. The Engineer In-
charge shall verify and endorse the location of the marking and handover
these signed maps as a permanent record to WUA. Along with this, the
detailed Geotagged map of laid pipeline shall also be handed over to WUA.
21.6 In association of the members of WUA, the Engineer In-charge shall confirm
the release of designed discharge through every outlet before handing over.
In case of any short fall or defect, it should be made good from the contractor
at his own cost.
----------***----------