Industrial Waste Water IKEA Application Example Turkey
Industrial Waste Water IKEA Application Example Turkey
Industrial Waste Water IKEA Application Example Turkey
MEMBRANA GmbH
Wuppertal, Germany
Norbert Selzer
www.liqui-flux.com
Content
Introduction of Membrana
Initial position of the Project
Pilot trials
Plant design
Operating experience
Summary and preview
2
SEPARATIONS MEDIA ENERGY STORAGE
High Performance Filtration Ion Exchange Membranes
INDUSTRIAL TRANSPORTATION
HEALTHCARE ELECTRONICS
& SPECIALTY & INDUSTRIAL
- Liquid filtration - Hemodialysis Rechargeable and Lead acid battery
- Degasification - Plasmapheresis Disposable separators
- Blood lithium battery
- Gasification
oxygenation separators
- Debubbling
Polypore separator
3
Membrana’s core business
Healthcare
Dialysis membranes Oxygenation membranes
Industrial Separation
Membrane Contactors Filtration Modules Flat sheet membranes
4
History and status:
5
Initial situation of the Project
6
Existing Waste Water Treatment Plant
7
Clean water quality
pH 7,1-7,8 pH 7-8
8
Pilot trials in 2 phases
Phase B Phase A
UF Pilot system
Pilot RO
9
UltraPES Membrane
Protective Separation
layer Support layer layer
Multifiber
P.E.T.® Technology
Membrane Characteristics
Membrane Type Hollow Fiber, Inside - Out
Membrane Material Polyethersulfone
Cross-section of the 3-layer structure Nominal Cut-off 80 kDa
Outer / Inner Diameter 1,25 / 0,8 mm
Burst Pressure > 12 bar
10
Liqui-Flux® UF Module W02
11
Pilot system in the field
12
Phase A: Start of pilot trial
13
Phase A: Stable operation achieved
Pilot trial - waste water Turkey 90 lmh; BW every 59 min; PAC 0,5 mg Al/l; CEB H2SO4
1000 10
900 9
800 8
700 7
TMF [l/h/m²/bar]
Turbidity [NTU]
600 6
500 5
400 4
300 3
200 2
100 1
0 0
07.04.2007 09.04.2007 11.04.2007 13.04.2007 15.04.2007 17.04.2007
14
Phase B: Adjusting with the treatment of the WWTP
Simulation of overdosing in pilot sedimentation - UF 65 lmh; BW every 39 min; PAC 0,5 mg Al/l
1600
CEB NaOH + NaOCl,
CEB NaOH + NaOCl,
1400 10 min
10 min
1200
TMF [l/hm²bar]
1000
800
600
400
200
0
27.08.2007 27.08.2007 28.08.2007 28.08.2007 29.08.2007 29.08.2007 30.08.2007 30.08.2007 31.08.2007 31.08.2007 01.09.2007
00:00 12:00 00:00 12:00 00:00 12:00 00:00 12:00 00:00 12:00 00:00
15
Filtrate quality in pilot trial
Parameter Range
Turbidity [NTU] <=0.01…0.02
16
System design of UF&RO
17
System design of Ultrafiltration
18
Operating experience I
From August until September 2007 the 7 UF and RO racks were started one after
another, one UF rack then one RO rack and so on.
At this point in time a good basis from the piloting was available to increase the flux
of the UF up to the scheduled value of 75 l/h/m² within a few weeks. At the beginning
the backwash interval was adjusted to 30 minutes and in several steps increased to
60 minutes. Transmembrane pressure (tmp) during filtration stayed below 0.2 bar
(2.9 psi).
The chemical enhanced backwash was adjusted several times to fit to the raw water
quality. The standard procedure now is cleaning with NaOH at pH >12 with addition
of 200ppm chlorine. After a backwash an acid step at pH 2 for rinsing out the caustic
follows.
During the start-up it was examined by sampling that all modules get the same
concentration of chemicals.
19
Operating experience II
Two events during the last 3 years required special activities.
One year later, around New Year 2008/2009 an increase of the tmp took place
during several weeks until 0.6-0.7 bar were reached. The caustic CEB did not work
well. After checking the water analyses from the WWTP, which is done regularly by
the operating company, high values of metals (Al, Mn, 0.4-0.5 ppm) were obvious. A
CIP with citric acid for 1h at 38°C recovered the flux to a value in the range of the
start value.
20
Operating experience III
During 9 of 12 month in a year one CEB per day is satisfying. In case of high
contamination in the raw water the operator switches the CEB to every 12h and in
single cases to every 8h.
The filtrate quality is checked continuously regarding SDI-15 (<3) and turbidity (<0.1
NTU).
With this water quality the yield of the RO could be raised from 75% at the beginning
of the operation up to 85% today.
The final quality of product water has been maintained during the whole operation
time without any restrictions.
21
Summary and preview
By the combination of Inline-coagulation, Ultrafiltration and Reverse osmosis a
system design has been installed which works safely and economically despite the
changing load in the waste water from the different industrial companies.
The used Ultrafiltration membranes have been demonstrating their suitability by a
low fouling tendency and favorable cleaning properties.
In combination with a sophisticated module and system design, and an operation
adapted to the local situation, this process system obtains central importance in
industrial waste water recycling.
Alternatively to the pre-treatment from the existing system in this project
(sedimentation, gravel filter) for new systems, depending on the load of the water,
other process steps like flotation and sieve filter should be tested and considered.
UF system costs may be reduced by usage of modules with increased membrane
surface: 75sqm
22