Universiti Teknologi Mara Final Examination: Course
Universiti Teknologi Mara Final Examination: Course
Universiti Teknologi Mara Final Examination: Course
TIME 3 HOURS
INSTRUCTIONS TO CANDIDATES
2. Answer ALL questions in the Answer Booklet. Start each answer on a new page.
3. Do not bring any material into the examination room unless permission is given by the
invigilator.
4. Please check to make sure that this examination pack consists of:
PART A
QUESTION 1
Adidos Manufacturing Sdn Bhd produces high quality shoes. Manufacturing these shoes
require 10 separate tasks. There are 420 minutes available for manufacturing the shoes in
the plant each day and the weekly demand is 300 shoes. The information for the tasks is as
follows:
TASK TIME
TASK (MINUTES) PREDECESSOR
A 1 -
B 3 A
C 2 B
D 4 B
E 1 C,D
F 3 A
G 2 F
H 5 G
I 1 E,H
J 3 I
b) Assuming a 5 days work a week, calculate the cycle time of the line.
(1.5 marks)
QUESTION 2
Suri Sutra Inc. decides to relocate its existing obsolete plant. The company has conducted a
study on several locations and finally come out with three alternatives. The cost structures
are as follows:
The production can be sold for RM150 per unit and the estimated annual production for each
location is 30,000 units.
c) How much does each location has to produce to gain a profit of RM25.000?
(4.5 marks)
d) Determine the profit for each location based on the estimated annual production
volume.
(4.5 marks)
QUESTION 3
A dam construction project requires nine (9) activities as per the following table.
b) Calculate the earliest start time and latest start time for each event.
(4 marks)
e) Calculate the total float and the free float for activity D.
(2 marks)
QUESTION 4
Ixora Confectionary is in the process of developing an aggregate capacity plan from January
until June 2020. The company has signed a contract promising to deliver the products to
customers according to the schedule below:
January 6000
February 5100
March 5700
April 6300
May 5700
June 6300
Apart from the contract, the normal monthly demand from other buyers is 1200 units.
Additional information:
a) Prepare an aggregate production plan for Ixora Confectionary for the months of January
through June 2020 by using varying workforce level and meet exact demand strategy.
(8 marks)
QUESTION 5
Sri Kedah Clothing uses a specialized sewing machine in producing its products. Based on
the detailed breakdown and repair record prepared by the maintenance department over the
last 36 months, the sewing machine has broken down at the rate indicated in the following
table:
FREQUENCY OF BREAKDOWNS
NUMBER OF BREAKDOWNS
(MONTHS)
0 8
1 12
2 10
3 5
5 1
Each breakdown costs the company RM400 in time and service expenses. Recently, an
external maintenance company offered Sri Kedah Clothing a scheduled preventive
maintenance contract to overcome the problem. This new scheme guarantees no
breakdown, but would cost Sri Kedah Clothing RM600 per month.
Should Sri Kedah Clothing accept the scheduled preventive maintenance contract? Justify
your answer.
(10 marks)
PARTB
QUESTION 1
QUESTION 2
QUESTION 3
QUESTION 4
QUESTION 5