COOL METRO Final Report
COOL METRO Final Report
COOL METRO Final Report
ON
TUNNELING WORK OF METRO RAIL
PROJECT AT AZADPUR AND MUKUNDPUR
NEW DELHI
SUBMITTED BY:
GROUP-3B
Page 1 of 44
GOVT OF NCT OF DELHI
ARYABHATT INSTITUTE OF TECHNOLOGY
(A Delhi Government Institute under DTTE and affiliated with GGSIP University, Delhi)
G. T. K. ROAD, DELHI 110033
DECLARATION
We, Group – 3B Students of Diploma in Civil Engineering hereby declare that the PRACTICAL
TRAINING REPORT “TUNNELING WORK OF METRO RAIL LOCATED AT AZADPUR AND
MUKUNDPUR, NEW DELHI” which is submitted by us to Aryabhatt Institute of Technology (ABIT),
Delhi as required for Civil Engineering 5th Semester as per Board of Technical Education (BTE), Delhi has
not previously prepared in any degree, Diploma or any other similar title or recognition.
Place:
Date:
Group – 3B
ARJUN SINGH (1401041009)
DEEPANSHU VERMA (1401041016)
PUNEET KUMAR (1401041043)
SAKET SAURABH (1401041055)
Page 2 of 44
GOVT OF NCT OF DELHI
ARYABHATT INSTITUTE OF TECHNOLOGY
(A Delhi Government Institute under DTTE and affiliated with GGSIP University, Delhi)
G. T. K. ROAD, DELHI 110033
CERTIFICATE
On the basis of the declaration submitted by Group – 3 (B) students of Civil Engineering of this Institute
we hereby certify that the students of group 3 (B) have completed PRACTICAL TRAINING REPORT
“TUNNELING WORK OF METRO RAIL LOCATED AT AZADPUR AND MUKUNDPUR, NEW
DELHI” which is submitted to this institute as required for Civil Engineering 5th Semester as per Board of
Technical Education (BTE), Delhi. This report may be used for all academic purposes.
Mr. A. K. Choudhary
(Principal)
This is to certify that the student examined by us in viva voice examination held at Aryabhatt Institute of
Page 3 of 44
TABLE OF CONTENTS
i. Title 1
ii. Declaration 2
iii. Certificate 3
v. List of figures 5
vi. Acknowledgement 7
vii. Abstract 8
1.1 Introduction 9
2. Safety Induction 12
3. Project Description 13
4. Tunnel 17
4.1 Introduction 17
Page 4 of 44
4.3 Soil Investigation 17
4.10 Materials which are being used During the time of construction of Tunnel 31-32
5. Tunnel 33
5.1 Introductions 33
8. Conclusion 40
9. Reference 41
Page 5 of 44
LIST OF FIGURES
1. Metro rail 9
6. Plan of tunnel 18
7. (EPB) TBM 18
Page 6 of 44
ACKNOWLEDGEMENT
It gives us great pleasure to express our deep and sincere gratitude to our institute for giving us such a
great chance to work with DMRC. We would like to express our special thanks of gratitude to MR. A.K.
UPADHYAY (H.O.D. CIVIL ENGINEERING), Dr. M. S. RAO Project Guide) and MR. VAGESH
KUMAR (SR. LECTURER CIVIL ENGINEERING) for such a great supervision for practical training
report.
We take this opportunity to express our thanks to the DELHI METRO RAIL CORPORATION, for help
and cooperation in the preparation of this project. We are also very thankful to MR. RAJESH KUMAR
(ASSISTANT ENGINER) for teaching us all the aspects of the construction.
Finally, we would like to pay our sincere thanks to OUR PARENTS and FRIENDS for their great
motivation and support.
Group – 3B
ARJUN SINGH (1401041009)
DEEPANSHU VERMA (1401041016)
PUNEET KUMAR (1401041043)
SAKET SAURABH (1401041055)
Page 7 of 44
ABSTRACT
Writing project report on “construction of tunnel for metro rail ’’. This report is based on the practical
The growing demand for public transport in mega cities has serious effects on urban ecosystems,
especially due to the increased atmospheric pollution and changes in land use patterns. An ecologically
sustainable urban transport system could be obtained by an appropriate mix of alternative modes of
transport resulting in the use of environmentally friendly fuels and land use patterns. The introduction of
CNG in certain vehicles and switching of some portion of the transport demand to the metro rail have
resulted in a significant reduction of atmospheric pollution in Delhi. The Delhi Metro provides multiple
benefits: reduction in air pollution, timesaving to passengers, reduction in accidents, reduction in traffic
congestion and fuel savings. There are incremental benefits and costs to a number of economic agents:
government, private transporters, passengers, general public and unskilled labour. The study tries to
measure all these benefits and cost of providing these benefits. There is no doubt that, at a time when
Delhi’s urban transport problems were getting more and more complex, the bold decision to have a metro
Page 8 of 44
1. Delhi Metro Rail Corporation ( DMRC )
1.1. INTRODUCTION
Delhi Metro is a metro system serving Delhi, Gurgaon, Noida, Faridabad and Ghaziabad in the National
Capital Region of India. Delhi Metro is the world's 12th largest metro system in terms of length and
number of stations too. Delhi Metro is India's 3rd urban mass rapid transportation system, after Kolkata
Metro and Chennai MRTS. Delhi Metro is India's first modern public transportation system, which has
revolutionized travel by providing a fast, reliable, safe, and comfortable means of transport
As of Sept 2015, the network consists of five color-coded lines (Red, Blue, Green, Yellow, Violet), plus
a sixth Airport Express line, with a total length of 208 kilometers, serving 157 stations, (including the 6
Airport Express stations). All stations have escalators, elevators, and tactile tiles to guide the visually
impaired from station entrances to trains. It has a combination of elevated, at-grade, and underground
lines, and uses both broad gauge and standard gauge
Delhi Metro Rail Corporation Limited (DMRC), a state-owned company with equal equity participation
from Government of India and Government of National Capital Territory of Delhi built and operates the
Delhi Metro. However, the organization is under administrative control of Ministry of Urban
Development, Government of India.
Besides construction and operation of Delhi metro, DMRC is also involved in the planning and
implementation of metro rail, monorail and high-speed rail projects in India and providing consultancy
services to other metro projects in the country as well as abroad.
The Delhi Metro is being built in phases. Phase I completed 58 stations and 65.0 km of route length, of
which 13.0 km is underground and 52.1 km surface or elevated. The inauguration of the Dwarka–
Barakhamba Road corridor of the Blue Line marked the completion of Phase I on October 2006. Phase II
of the network comprises 124.6 km of route length and 85 stations, and is fully completed, with the first
section opened in June 2008 and the last line opened in August 2011. Phase III(167.27 km, 69 stations)
and Phase IV(113.2 km) are planned to be completed by 2016 and 2021 respectively, with the network
spanning 413 km.
Page 9 of 44
1.1.1. NETWORK MAP OF DELHI METRO
Delhi, the national capital with the population of about 12 million is, perhaps, the only city of its size in
the world, which depends almost entirely on buses on it sole mode of mass transport.bus services are
inadequate and heavily over-crowded. This situation had led to proliferation of personalized vehicles, so
much so that Delhi has more registered vehicle than the total number of vehicles in Mumbai,Calcutta and
Chennai put together. Nearly 70% of these are two wheelers. The result of extreme congestion on the road,
ever slowing speeds, increasing accident rate, fuel wastage and environmental pollution . Delhi has now
become the fourth most city in the world, with automobiles contributing more than two thirds of the total
atmospheric pollution. Pollution related health problems are reaching disconcerting levels.
Page 10 of 44
FIGURE No. 3 NEED FOR METRO- A PICTORIAL VIEW OF TRAFFIC ON THE ROADS OF DELHI
As per metro project reconnaissance surveys it was observed that to meet the transport demands of ever
growing population of Delhi, the number of buses must be at least doubled and personalized vehicles will
grow threefold. This sure to lead to further worsening of the levels of congesting and pollution , which had
already crossed acceptable limits in many parts of the city. Immediate steps are, therefore, needed to
improve both the quality and availability of mass transport service. This is possible only if a rail-based
mass transit system, which is non-polluting and eco-friendly in cognizance with existing transportation
systems.
BENEFITS
Page 11 of 44
2. SAFETY INDUCTION
2.1 SAFETY INDUCTION FORMAT
Helmet colours
Green- safety officer
Violet- ITD officer
White -DMRC officer (client)
Red- electricians
Blue- contactors
Orange –security
Jacket colours
Red- workers
Green-staff and contactors
Do’s:
8. Be confidential in nature.
9. Use fair and polite language and maintain decorum of office site.
10. Inform the concerned authority in case you are going out of station.
Don’ts:
Page 13 of 44
3. PROJECT DESCRIPTION
Key Details
Location: Azadpur Metro Station, New Delhi, India
Contractor: CEC-CICI JV
Design Consultant: GEODATA Engineering
Client Consultant: SYSTRA
Contract Details
Liquidity Damages: 0.01% of fixed lump sum per week of delay for key
Defect Liability Period: 52 weeks after the date of issue of Taking-Over Certificate
Page 14 of 44
3.2 PLAN OF PROJECT
Cut & Cover Tunnel: Mukundpur Section: Top-Down Construction Method with Diaphragm Wall.
Ground improvement by Jet grouting at the outer portion of North Shaft and South Shaft.
Secant pile foundation at the boundary of UG Azadpur Station to resist the earth pressure during
Construction.
Construction of temporary struts of 3 or 4 layers to support the secant piles (after excavation of
soil) during construction of UG Station.
Earth mat is spread over the entire station in between soil surface and PCC to take care of lightning
effect.
Dewatering
Stone column
D-Wall
Page 16 of 44
4. TUNNEL
4.1 INTRODUCTION
A tunnel is an underground or underwater passageway, enclosed except for entrance and exit, commonly
at each end.
A tunnel may be for foot or vehicular road traffic, for rail traffic, or for a canal. The central portions of a
rapid transit network are usually in tunnel.
For soft, cohesive soils tunnel boring machines with earth pressure support are a preferred option. So
called Earth Pressure Balance Shields (EPB) turn the excavated material into a soil paste that is used as
pliable, plastic support medium. This makes it possible to balance the pressure conditions at the tunnel
face, avoids uncontrolled inflow of soil into the machine and creates the conditions for rapid tunneling
with minimum settlement.
Page 17 of 44
4.4TUNNEL IN CC-04 PROJECT
According to the construction methodology of this project the tunneling should be done with two
Herrenknech EPB (Earth Pressure Balance) TBM (Tunnel Boring Machine) are used for Tunnel
Excavation work to overcome some of the complicated tight curves and slopes.
Shalimarbagh
C&C
Station
Mukundpur
Ramp
Page 18 of 44
4.7 METHOD USED FOR TUNNELLING AT THE SITE
This method is so called because in this method, the whole section of the tunnel is attacked at the same
time.
In this method, drilling is done on the whole section of the proposed tunnel, and the drill holes are charges
with explosive and blasted at a time. After excavating one round or pull of the tunnel, drilling is started
from the next round or pull and this process is repeated till the whole tunnel is derived.
4.7.2 PROCEDURE
a)SETTING UP AND DRILLING: Before actual drilling holes of the desired size, it is important to know
the drilling pattern and their number in order to break the greatest volume of rock with less quantity of
explosive and less disturbance to the strata. The best pattern to produce this result will vary with several
factors such as the size of the tunnel, the the depth of holes to be drilled, the kind of rock and the method
of mounting the drills.
After marking the drilling pattern, holes are made with drills. The drills are usually worked by a pressure
of 5.5 to 7 kg per sq. cm. it is common practice to drill the required number of holes according to the
decided pattern which slope towards a common point or line near the centre of the face to produce an
initial come or wedge. The diameter of holes is generally 25to 37.5 mm and their length may vary.
Normally the length of holes is kept 4m in hard rocks.
b) CHARGING AND BLASTING: After drilling, stone dust, loose rock and water in each hole are blown
out at high air pressure. Each hole is then charged and loaded with explosive. To do this a cartridge of
explosive is first inserted into the hole with a suitable detonator fixed to it. This insertion of first cartridge
with detonator is called priming the hole. After this , the remaining cartridge are inserted , depending upon
the explosive required to be filled in the hole. The rest of the hole is then filled with clay which should be
tamped properly. This process of plugging the hole with clay is known as stemming.
After charging each hole, the detonator wires are joined in series or parallel or parallel and series and the
final wires are taken out of the tunnel and the explosive is blasted with the help of an exploder. This, the
explosion will take place, depending upon the delay period of the detonators.
Page 19 of 44
The quantity of explosive required depends upon the type of rock to be blasted. On average, 2 to 2.6 kg of
explosive is required for 1 cubic metre of hard rock.
c) SCALING: At the end of blasting, some rock fragments may hang loosely from ceiling or walls of the
tunnel. These loose rock pieces may fall off without warning and cause accident during subsequent
operations and hence they are to be removed. The operation of removing such loose rock fragments and
hammering off projecting pointed rocks is known as scaling. This is done with the help of steel rods and
water jets.
d) MUCKING: After blasting and scaling, the blasted material is removed from the tunnel and dumped at a
suitable site. This operation of removing the excavated or blasted material from the tunnel and dumping
the same at a predetermined site is known as mucking.
e) TUNNEL SUPPORTING: After mucking, the interior surface of the blasted portion is supported by
The design of the supporting structure depends upon the nature of rock through which the tunnel is driven.
A common timbering arrangement consists of ribs, supported on columns. The ribs are usually made up of
mild steel in the form of H-section.
For supporting the tunnel after mucking, frames are erected at suitable spacing with columns and ribs. The
portion between the two adjacent frames is filled with precast concrete blocks. Rubbing is done in such a
way that a uniform profile of the proposed tunnel is formed.
f) GROUTING AND LINING: Before the tunnel is finally lined, it is necessary to grout the weaker
sections with cement slurry (1:3) so that the weaker strata is stabilized. Finally the tunnel is lined.
Page 20 of 44
4.8 Component of TBM Machine
1) Cutter head (41 ton)
7) Gantry car
I) Air Bridge
Cutting wheel:
I. Cutting Discs: It is the main tool used for cutting. These are made up of tungsten
and have sharp edges.
II. Cutting Tool: These are 68 teeth welded along surface in 8 rows, four having 9
teeth & four having 8 no. The main purpose is scrap out muck. This tool comes into
act when the TBM encounter soil strata instead of rock.
III. Scraping Picks: These are placed along the periphery of cutting wheel. It clears the
muck from excavation face. There are16 buckets installed in cutting wheel.
Page 21 of 44
Front shield: The middle portion of TBM is front shield which contain empty and working
chamber, screw conveyor, motor and thrust cylinder. The weight of front shield is about 80
tons.
Middle shield: Provides structural strength to machine. All the hydraulic& electrical
connection is provided in it. The ring support for the thrust cylinder & erector cross are
arranged which serves for the bracing of shield.
Push rams: Main purpose is to push the machine forward.
Tail skin: This is the last part of the TBM consist of pipe shield that is connected with the
middle shield by articulation cylinder. In the protection of shield the concrete rings are
placed with the help of erector and grouted using grout pipes.
Screw Conveyor: Fitted to the connecting flange in the pressure bulkhead & runs from the
base of front shield to discharge point of conveyor belt. Due to screw diameter and core
diameter maximum grain size of 300mm can be transported.
Man Lock: Small room that connect middle and front shield. Connect top area of cutter
head with the middle shield. It is used of any maintenance and repair. The man lock is filled
with compressed air when any maintenance is required. The level of muck area is
maintained above screw conveyor so air doesn’t escape.
Belt Conveyor: Used for transporting material from discharge point to muck car . It is
Bridge: Connect two shield and gantries. It houses the conveyor belt on the top of it, which
carries muck.
Erector: This is the circular ring connected with the middle shield & tail skin, used for
Gantries: Total 4 gantries that attach behind the TBM carry different motors.
Page 22 of 44
4.9 TBM Assembly Construction process after transportation of
TBM at site
Step-1
Step-2
Step-3
Step-4
Step-5
Step-6
Step-7
Page 23 of 44
4.10 TBM INITIAL DRIVE
1.TBM launching point Test the water TBM launching point survey
2. TBM launching eye mechanically knockout of a thickness of 60cm-65cm. Construction should be noted
that whether there is water leakage and sand leakage of situation
3. Launching eye frame installation, construction pay attention to the launching point of coordinates and
elevation.
4. Cradle and reaction frame installation Check base slab elevation before setting cradle and reaction
frame. The cradle and reaction frame must be set to the correct position both line and elevation
5. Launching eye artificial knockout TBM test the proper manpower to get rid of knockout. This
construction project there are certain risks that need to grasp the time is shorter time to complete in order
to reduce the risk.
6. TBM Beginning excavate construction because no crane to follow all of the power supply via the
hydraulic pipes and wires extended, extension of the pipeline construction process is very important work.
TBM is starting by hydraulic jack working against reaction frame.
7. Transfer of equipment TBM Beginning excavate construction complete, follow-up work Temporary
ring dismantle Work platforms and rail assembly Follow up put in gantry car system.
Page 24 of 44
FIGURE No. 9 AN OVERVIEW OF TUNNEL (TBM-1A) AT MUKUNDPUR, DELHI
Page 25 of 44
FIGURE No.11 THRUST CYLINDER READING INSIDE THE TBM CABIN
Page 26 of 44
FIGURE No.13 DIGITAL SCREEN INSIDE THE TBM CABIN
Page 27 of 44
FIGURE No. 15 TUNNEL BORING MACHINE CUTTER HEAD AT GURUDWARA SHAFT
Page 28 of 44
4.8 Manpower Details in Tunnelling Operations (in one shift/TBM)
SN Name No.
1 Senior Tunnel Engineer 1
2 Tunnel Engineer 1
3 Tunnel Supervisor 1
4 TBM operator 2
5 Erector Operator 1
6 Ring Builder 4
7 Rail Fitter 4
8 Gantry Operator 1
9 Grout Operator 3
10 Pipe Extension 3
11 Helper 3
12 Welder 1
Bottom Shaft
1 Foremen 1
2 Loco operator 2
3 Rigger 4
Surface shaft
1 surface foremen 1
2 Mucking Supervisior 1
3 Chiller Operator 1
4 Surface labour 8
5 Grout plant operator 6
6 Grout plant labour 2
7
wheel wash
Page 29 of 44
4.9 TBM EARTH PRESSURE MANAGEMENT PROCESS
1) Increase the
rotation speed of
Upper control limit value:
the screw
Design earth pressure + 0.2 conveyor
kgf/cm2 2) Reduce the TBM
speed
1) Lower the
Control the lower limit: Design rotation speed of
earth pressure-0.2kgf/cm2 the screw
conveyor
2) Increase the TBM
Page 30 of 44
4.10 Materials which are being used during the time of
construction of Tunnel
Permanent Materials
Pre-cast segment
Segment bolts
EPDM Gasket
Back fill grout-cement, bentonite, silicate, and stabilizer
Segment repair materials
Tail seal grease
Temporary Materials
Polymer
Foam
Hydraulic oils
Grease
1) Bentonite
Bentonite in civil engineering applications is used traditionally as a thixotropic, support and lubricant
agent in diaphragm walls and foundations, in tunneling, in horizontal directional drilling and pipe jacking.
Bentonite, due to its viscosity and plasticity, also is used in Portland cement and mortars.
Function
Geo-construction
Horizontal directional drilling
River crossing
Stabilize water sensitive formation
Improve the bore hole stability
Advantage
Page 31 of 44
2) Polymer
Polymer is a liquid emulsion containing partially hydrolyzed poly-acryl amide copolymer is used primarily
as a borehole stabilizer to prevent reactive shale and clay from swelling and sloughing and is also used to
improve the slurry rheological properties.
Function
Water wells
Geo-construction
Horizontal directional drilling
River crossing
Stabilize water sensitive formation
Advantage
3) Foam
The use of foam and additives is essential to facilitate ground excavation while tunnel boring, particularly
in difficult geological environment. In tunneling EPB machine can be prevented by action upon the voids
and intersects within the excavated soil by the controlled injection of foams and additives at the cutting
face.
Advantage
Horizontal directional drilling
Enhance slurry rheological properties
FIGURE No. 16 MATERIALS USED FOR CONSTRUCTION OF TUNNELS
Page 32 of 44
5. STATION
5.1 INTRODUCTION
According to the construction methodology, the method used for construction of station is Bottom-up
Construction method. The length of station is 253m. For identification areas in station, the area is divided
into 1 to 29 Grids. So work is done according to the grid no. The depth of station is 15 m which contain
south shaft and north shaft also.
Page 33 of 44
5.2 Bottom-Up Construction Methodology
PCC
Base slab
Concourse slab
Roof slab
Backfilling
Page 34 of 44
6. PROJECT CAPTURED
FIGURE No.18 OUTSIDE MUKUNDPUR TUNNEL (1-A)
Page 35 of 44
FIGURE No.20 INSIDE MUKUNDPUR TUNNEL (1-A)
FIGURE No. 21 LIFTING OF MUCK CAR WITH THE HELP OF 110 TON GANTRY CRANE
Page 36 of 44
FIGURE No.22 CONSTRUCTION OF ANCILLARY BUILDING NORTH
Page 37 of 44
FIGURE No.23 THE SOUTH SHAFT
Page 38 of 44
7. PRECAUTIONS & SAFETY MEASURES
Cross sectional dimensions of the tunnel should be decided to achieve economy in its construction.
Economic calculations for extent of equipment and labour should be made before tunnel
construction.
Pattern of blasting the material in different locations should be decided for maintaining speed of
The sequence of operations must be decided so that proper use of labour and equipment is made.
Labour should be well organised to maintain continuous progress of the tunnelling operations.
Care should be exercised to see that every operation is completed at scheduled time.
The excavated material should be piled up in a manner suitable to the method of loading being
employed.
The sequence and type of lining should be determined in advance to achieve economy.
Selection of multi-purpose and uniform type of equipment should be made, according to the size
Page 39 of 44
8. CONCLUSION
Our practical training work was carried out on tunnelling work of Delhi Metro Rail Project.
The project site located at Azadpur and Mukundpur of Delhi. In this training an attempt
has been made to understand the various salient features of DMRC project works in
general & tunnelling work in particular. Further emphasis was given on TBMs working
operations in the field. It was a wonderful learning experience at DELHI METRO RAIL
PROJECT for one month in Delhi. We gained a lot of insight regarding almost every aspect
of site & office. We were given exposure in almost all the departments at the site.
In the past 1 month we have learnt a lot about site work. we have seen the difference
between the theoretical studies and practical work on field. We realized that though the
basics of work on site are the same as theoretical studies but there is a lot of difference
between the executions of the work on site. Such training will help in reducing the gap
between theoretical and practical knowledge which indirectly helps in quality aspects in
later stages.
While working with TBM (Tunnel Boring Machine) which is most important in any
MRTS project and we have observed that this is one of the safest way of tunnelling as it
needs no blasting. It can also be concluded that these trainings are helpful in enhancing
communication skills due to interaction with Senior Engineers, Managers and even Project
Leader sometimes.
It is further concluded that such rail projects should be carried out in various cities of India
in order to improve the lives of citizens and better coordination among existing modes of
transportation systems.
Page 40 of 44
9. REFERENCES
Web article (2016) retrieved from http://en.wikipedia.org
Web article (2015) retrieved from www.cici.co.in
Web article (2016) retrieved from www.continental-holdings.com
Web article (2016) retrieved from www.delhimertrorail.com
Web article (2013) retrieved from www.gcminfrastructure.com
Web article (2016) retrieved from www.youtube.com
Web article (2015) retrieved from www.herrenknecht.com
Web article (2016) retrieved from www.bietcivil.blogspot.in Posted By Rambabu Palaka
Web article (2016) retrieved from www.osha.gov
Varshney, A. B. (2014-15). A text book on Concrete Technology, Satya Prakashan Tech India
publications, New Delhi
Varshney, A. B. (2015). A text book on Civil Estimating and Costing, S. K. Kataria & Sons
Publisher of Engineering and Computer Books, Daryaganj, New Delhi
Page 41 of 44
10. GROUP DETAILS
Our Career Objective:
We respect my commitments to in any field of work. We try not to put myself under Pressure in critical
situations. We always believe that growth of our organization Means growth of our self.
Group – 3B:
Educational Qualification:
10th passed from CBSE Board
Pursuing Civil Engineering 3rd Year (5th semester) from Aryabhatt Institute of Technology G. T. K.
Page 42 of 44
End of report
Page 43 of 44
Page 44 of 44