Contractor's Obligation: Construct and Complete The Works Provide Everything Necessary, I.E
Contractor's Obligation: Construct and Complete The Works Provide Everything Necessary, I.E
Contractor’s Obligation
Introduction
This section represents the largest number of clauses in the ICE
Conditions of Contract (clause 8 to 35). There is no clauses have been
considered elsewhere. Clause 14 (Programme) has been dealt with in
Chapter 2 (Contract Documents), and clause 15 (Contractor’s
superintendence)
Design responsibility
Design
Specification
The contractor must take full responsibility for both the temporary
or permanent works during construction. This includes responsibility
for all site operations and methods of construction in respect of their:
Adequency
Stability
Safety
Contract Agreement
Performance Security
Inspection of site
Form and nature of the site including the ground and subsoil
Extent and nature of the project
Work and materials necessary for constructing and completing
the works
Communication and access to the site
Accommodation that may be required
Possible risks and contingencies
The contractor will therefore formulate the tender on the basis of:
Intention to claim
Action by engineer
Misconduct
Incompetence
Negligence
Failing in the performance of duties
Failing to conform with particular provisions regarding safety
Persisting in conduct which is prejudicial to safety or health
Then such a person must not be re-employed upon the works without
the permission of the engineer. For example, where an employee is
dismissed by the contractor for one of the above reasons, that same
person would not be able to work again on that project, in the
services of a subcontractor.
The engineer is responsible for providing the contractor with all the
information necessary for the contractor to set out the works. This
information should comprise properly dimensioned drawings
showing line, level and location. Delays in the presentation of the
information from the engineer could result in an extension of time.
The setting out of the works is the responsibility of the contractor.
This includes the provision of all necessary instruments, appliances
(e.g. profile boards) and labour. The setting out involves the
correctness of the:
Position
Levels
Dimensions
alignment
lights
guards
fencing
warning signs
watching
Employer’s responsibilities
The contractor is to take full responsibility for the care of the works
and the materials, plant and equipment that are to be incorporated in
the works from the contract commencement date until the date of the
issue of the certificate of substantial completion for the whole of the
works. At this point the responsibility for the care for the works
passes to the employer. If the engineer issues a certificate of
substantial completion for any section of the permanent works, the
contractor will cease to be responsible for the care of that section of
the works. The contractor is responsible for the care of any
outstanding work during the defects correction period or until such
work is completed.
Excepted risks
There are a number of excepted risks for which the contractor is not
liable for loss and damage. These include:
The contractor must insure the works in the joint names of the
contractor and employer. This will include the materials, plant and
equipment that are to be incorporated within the works. The extent
of the insurance cover is to be the full replacement costs, plus an
additional 10 per cent to allow for incidental costs. These incidental
costs might include demolition and removal of debris, professional
fees and extra costs incidental to the insurance work. The principle of
the insurance clause is that the employer should be left in the same
financial position as would have been the case prior to an insurance
claim arising.
Extent of cover
The insurance required for the contract must cover any loss or
damage other than that arising from the excepted risks that have
been defined in clause 20 (2). The period of cover runs from the
works commencement date until the issue of the certificate of
substantial completion.
The insurance must also extend to cover any loss or damage arising
during the defects correction period from a cause occurring prior to
the issue of the certificate of substantial completion. The insurance
must also cover the work carried out by the contractor in competing
any outstanding work and defects under clause 49 and 50.
Any amounts that are not insured or cannot be recovered from the
insurers, e.g. excess amounts, are to be borne by either the contractor
or the employer in accordance with their respective responsibilities
under clause 20.
Indemnity by contractor
Indemnity by employer
Transport of materials
contractor’s equipment
surplus material
rubbish
temporary works
the whole of the site and permanent works must be left in a clean and
workmanlike condition to the satisfaction of the engineer.