P5 Draft Technical Specification
P5 Draft Technical Specification
The systems shall be complete and functional in all respects and shall comply with the relevant
statutory requirements and include all items necessary for efficient operation.
The Contractor shall include all permit and inspection fees payable to all Authorities, overtime
payments and all other charges and costs necessary to complete the works within the submitted
construction program and obtain all necessary authority approval.
PUMP HOUSE
b) Overhead Crane
i) Electric overhead crane (capacity: 18 tons) complete with all machinery and
equipment necessary for the satisfactory operation of the system.
ii) Monorail crane with manual chain hoist and complete necessary accessories.
Page A / 1
Technical Specifications
Section A: Scope of Work
iii) Electrical works consists of starter panel, power and signal cables.
iv) Supply and installation of brackets, support, saddles etc. which are required to
support girder and rails.
v) Testing and commissioning including JKK testing & issuance of PMA certification.
vii) 24 months comprehensive maintenance and attendance during the defects and
liability period.
c) Mechanical Ventilation
Ventilation system for pump house complete with exhaust fan system, fresh air fan
system, ductwork, starter panels, power & control wiring and other necessary accessories.
d) Fire Protection
i) Clean gas cylinders complete with fittings and charged with the relevant agent.
Fire Extinguishers
Air cooled split DX systems complete with indoor unit, condenser unit, local starters,
switches, power and control wiring, wired remote control, timer, drain pipes, refrigerant
piping system complete with insulation, hangers, brackets and other necessary
accessories
Page A / 2
Technical Specifications
Section A: Scope of Work
g) Other Works
i) Preparation of shop drawings, as-built drawings, operation manual, and all other
related documents.
ii) Liaising with the related authorities to arrange for the inspection of the works, water
meter installation, etc.
iii) Making good, patching of holes and openings, and furring of incidental directly
undertaken by this contractor.
iv) Testing, providing services for testing and commissioning of all equipment and
services, including joint testing with all other subcontractors in stages as necessary
for Authority inspection and approvals.
v) 24 months comprehensive maintenance and attendance during the defects liability
period.
vi) Operation training of plant for 2 weeks to be provided for the client.
END OF SECTION
Page A / 3
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
Treated water pumps shall be of constant speed, vertical split casing type, single stage,
double entry volute centrifugal pumps. The speed of the rotation shall not exceed 1000
rpm for the treated water pumps. The pump vibration and noises shall be tested to the
requirement of JIS B 8301 and the running shall be smooth and free from excessive
vibration and extraordinary noises in any part. The total amplitude of vibrations during
testing at the manufacturer’s works shall not exceed the maximum values in accordance
with JIS B 8301 Part 9.4.
The pumps shall be installed at floor level of the pumping station with motors directly
coupled.
The design of the pumps and shafting and the associated pipework and valve, and the
selection of materials for construction shall be carefully carried out to obviate the effects
of the electrolytic action and corrosion action with due consideration to the water
analyses shown in Specification.
a) Pump casing
Pump casings shall be manufactured from close gained cast iron in accordance
with BS 1452 Grade 250 or better. The Tenderer may propose alternatives such
as the materials that are of greater tensile strength and more ductile than cast
iron or Meehanite such as spheroidal graphite cast iron in accordance with BS
2789 Grade 420/12.
The pump shall be of the double volute type and designed to produce a smooth
flow with gradual changes in velocity. The casing shall be split axially with the
suction and discharge nozzles and casing feet cast in the one casing half. The
interior of the pumps shall be easily inspected by removing the other half of the
casing without disturbing the pipe connections or pump alignment.
The flanges between the halves shall be machined on face and edge, and sealed
by a pre-cut gasket of approved materials. The two halves of the casing shall be
accurately located by the use of straight dowel pins to eliminate mismatch
between the two halves which would impair both hydraulic and mechanical
performance.
Each pump casing shall be fitted with a drainage cock at its lowest point and air
vent with cock at its highest point.
b) Pump shafts
Pump shafts shall be manufactured from stainless steel Type JIS SUS 316 or
better and shall be adequately sized and designed to minimize deflection.
Deflector plates of stainless-steel material shall be welded to each pump shaft
to prevent water seepage to the bearing housings. All wearing and immersed
surfaces shall be protected with renewable bronze sleeves.
c) Bearings
Pump bearings shall be designed for a minimum service life of 40,000 hours.
Bearings shall be of heavy duty of single or double row anti-friction type,
designed to withstand any thrust and axial loads.
The bearing at the coupling end shall be of the self aligning ball type while the
bearing at the opposite end shall be of the double thrust ball type to withstand
any thrust imposed on the bearing.
Page B / 1
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
Bearings shall be grease lubricated type with readily accessible grease supply
and grease relief fittings.
d) Wearing rings
The casing shall be fitted with removable bronze wearing rings designed to
provide a smooth flow of water into the impeller eye. The casing ring shall be
provided with a positive means of preventing rotation. The impeller shall also be
fitted with removable bronze wearing rings and held in place by set screws.
The Contractor shall supply and install a water lubrication system designed to
cool and flush the mechanical seals as specified in the Specification.
f) Impellers
g) Motor coupling
The pump shall be directly couple to its driver by means of form flex coupling
type. The coupling and shaft shall be enclosed with an approved metal guard.
h) Pressure gauges
Both suction and delivery branches of the pump shall be fitted with pressure
gauges. Precautions shall be taken to ensure that the gauges cannot be
overstressed.
i) Motor Pedestal
Motor pedestal for the pump and the driving motor shall be of substantial cast
iron or stress-relieved fabricated steel and shall be supplied together by pump
manufacturer. They shall have machined landing for accurate alignment of
packings under the motor for maintaining alignment. The pedestal shall be
properly design to cater the load of motor
Page B / 2
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
2.1 General
The Contractor shall design, supply, install, test and commission the water lubrication
system for the treated water pumps. The system shall flush and cool the mechanical
seals at the pump stuffing boxes.
The Contractor shall design, supply, install, test and commission a bypass line from the
pump discharge casing to the pump mechanical seals. The bypass line shall be of
stainless-steel tube, complete with stainless steel pipe sockets and connectors and shall
not be less than 25 mm in diameter. A sight glass shall be provided at each bypass line
for monitoring purpose.
3.0 Motors
All electric motors shall comply with the requirements of BS 4999 and BS 5000.
Constant speed AC motors shall be of the induction type suitable for operation on a 3-
phase supply and shall be capable of operating continuously, at rated torque, at any
voltage between +5 and –10 percent of the nominal valve, and nominal frequency +2
and –2 Hertz.
The maximum motor speed shall be 1500 rpm. All AC motors rated 0.18kW and above
shall be of the three-phase type.
Motors up to 2.2kW shall be of the squirrel cage rotor type suitable for direct-on-line
starting having a starting current not greater than 6 times the full load current.
Motors above 2.2kW and up to 75kW shall be of the squirrel cage type suitable for closed
transition auto-transformer type starting with the starting current limited to 250% of the
full load current.
Non-submersible motors above 75kW shall be of the slip ring wound rotor type suitable
for rotor resistance type starting with starting current limited to 150% of the full load
current.
Submersible motors above 75kW shall be of the squirrel cage type suitable for closed
transition autotransformer starting with the starting current limited to 250% of the full load
current.
All motors shall be capable of running continuously at a brake horsepower not less than
10% in excess of that absorbed by the driven equipment under any operating conditions.
The reserve power requirements shall be added to the calculated power prior to any
other adjustments e.g. high ambient temperature at Site. In addition, all motors shall be
suitable for 15 starts per hour for 415 volt rated motors.
The motors shall be commercially silent in operation and the overall A-weighted sound
pressure level shall not exceed 83 dBA at 1 metre. In addition, the motors shall run free
from vibration and their rotors shall be perfectly balanced both statically and dynamically
in an approved manner. The motor bearing vibration severity shall not exceed 20 microns
peak to peak when measured in the direction of the three mutually perpendicular axis at
Page B / 3
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
the bearings and mounting points of the motor. Motors shall be balanced with the full key
in the keyways.
A proven track record shall be submitted with the Tender to demonstrate the motor
manufacturer’s past experience in the design and manufacture of high voltage motors of
comparable size and type required under the Contract.
The enclosures of submersible pump motors shall afford a mechanical protection not
less than IP 68.
Enclosures for all motors shall afford a mechanical protection not less than IP 54 for
those installed indoor and IP 55 for those installed outdoor and in chemical or chlorine
plant areas. The method of cooling for these motors shall be to classification IC 411
(totally enclosed fan ventilated, plain or ribbed frame). The flow of cooling air shall be in
the direction of the driven equipment.
The maximum temperature of the motor casing, normally accessible by hand shall not
be more than 80ºC at an ambient temperature of 40ºC.
Thermoplastic fans and fan covers shall not be employed. All fans and fan covers shall
be made of metal and treated with a corrosion resistant coating.
Motors fitted with unidirectional fans shall be provided with an arrow permanently
indicating the direction of rotation. Indication by means of a painted or adhesive arrow is
not acceptable.
Totally enclosed motors shall be provided with suitable means of breathing and drainage
to prevent accumulation of condensation.
All motors shall be given corrosion resistant paint finishes and shall have corrosion
resistant parts.
All motor frames and bearing end shields shall be constructed of ferrous metals. Motor
frames made of aluminium alloy will not be accepted. Frame sizes shall be in accordance
with IEC 72 and IEC 72A.
3.3 Windings
Windings shall be made of copper and impregnated to render then non-hygroscopic and
oil resistant and shall be braced to prevent any movement of the coils during all
conditions of service.
All windings shall be adequately supported, braced and blocked to provide sufficient
rigidity and to limit end-winding vibration and subsequent cracking of the winding
insulation at the slot exists. Winding shall be capable of withstanding the dynamic forces
which result from system fault conditions.
Motors will be operating in an ambient temperature in the order of 40ºC. Motor insulation
shall be to BS 2757 Class F, with the temperature rise (by resistance method) limited to
80K, for both stator and rotor windings.
3.4 Bearings
Bearings shall be plain or rolling type as appropriate. Vertical shafts shall have approved
guide and thrust bearings incorporated in the motor body to carry the weight of the motor.
Page B / 4
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
Bearings shall have a C3 internal radial clearance. The bearing temperature rise,
measured near the outer ring of the bearing shall never exceed 50K and the temperature
of the outer ring of the bearing shall never exceed 90K.
Bearings shall be designed to exclude the ingress of dust and water and sealed to
prevent leakage of lubricant along the shaft.
Motors up to 2.2kW and submersible motors of all ratings shall have sealed bearing
housing without lubrication nipples. The grease which shall be supplied by the
manufacturers shall be sufficient for at least 30,000 hours of continuous operation.
Each motor above 2.2kW shall have readily accessible lubricating valves which shall
enable the correct amount of lubrication (without over lubricating) when regressing whilst
the motor is running. The interval between lubrication and the requisite quantity and type
of grease shall be given on the lubrication plate which shall be mounted adjacent to the
motor name plate.
Excess and old grease shall be forced out through an opening in the outer bearing case.
Any surplus grease shall be ejected out of the motor casing to a separate container.
Spent grease retaining systems will not be accepted. The lubrication nipple shall be of
the conical type. Where necessary for accessibility, nipples shall be remotely mounted
at a point as close to lubrication point as practical and connected thereto by means of
double-walled copper brazed steel tubing. For large motors forced lubrication may be
provided as an alternative and details of the system shall be submitted with the Tender.
A flow indicator and/or pressure switch shall be provided on forced lubricating systems
to indicate failure of the system.
For submersible pump motors exceeding 37kW rating and non-submersible motors
exceeding 75kW rating, bearing temperature monitoring system employing RTDs shall
be provided. RTD sensors shall be suitable for connection of 3 wire instrument cables.
Dial type analogue indicators with trip and alarm contacts shall be provided for each
bearing on the respective starter panel.
Each 415-volt motor rated above 2.2kW shall be fitted with three PTC type thermistors
(one number per phase) and all the leads of these three thermistors shall be terminated
inside a separate terminal box with IP 55 degree of protection, where the thermistors
shall be connected in series. For 415-volt motors rated above 75kW, six PTC type
thermistors (2 numbers per phase) shall be provided.
Motors with thermistors shall be fitted with a non-corrodible metal thermistor data plate
which shall include the following information:-
i. Thermistor manufacturer
ii. Type number
iii. Tripping temperature (ºC)
iv. Resistance of each thermistor at the tripping temperature
v. Number of thermistors embedded per winding
Page B / 5
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
In addition to the above a stainless-steel warning plate with the inscription “WARNING”!
THERMISTORS INSTALLED. DO NOT MEGGER” shall be installed in a prominent
position on the thermistor terminal box.
Anti-condensation space heaters shall be provided on all motors above 2.2kW unless
otherwise specified. The heaters shall be suitable for use on a single phase a.c. supply
and wired to a separate terminal box. A prominent warning label with the inscription
‘WARNING – CIRCUIT MAY BE LIVE’ shall be installed. Each heater shall be provided
with a switch in the respective starter and automatic control to disconnect it when its
motor is in operation. Each heater shall be sufficiently rated to maintain the temperature
above dew point when the motor is stationary.
3.7 Brushgear
On slip-ring and commutator motors, the brushgear shall be designed to operate without
injurious sparking, with the minimum need for adjustment or replacement of brushes.
Removable hinged covers shall provide access to the brushgear, slip-rings or
commutator.
Brush holders shall incorporate constant force springs to maintain optimum contact
pressure throughout the life of brushes. Constant force springs shall apply the designed
pressure at all times, independent of the length of the brush. Brushgear box length shall
be suitable to accommodate long length of brushes and to reduce the necessity for
changing brushes between scheduled shutdown periods.
The force which the spring exerts shall be fixed during its manufacture. Furthermore, to
reduce maintenance and to elimate mal-adjustment due to human error, all mechanical
fingers, pivots, rivets and hold-off devices which are otherwise necessary with
conventional brush holders shall be avoided. To provide positive identification each
spring assembly shall be clearly marked with the value of the force fixed during
manufacture.
The springs shall be of simple plug-in clip designs and shall allow easy access to brushes
for examination or replacement.
The Contractor shall ensure that the carbon brushes selected are readily available locally
a designed for long life.
3.8 Slip-rings
The slip-rings shall be placed adjacent to the bearing in the non-driving end and be of
the external type, separately enclosed and separated from the main motor frame. The
slip-ring space of motors with a degree of protection conforming to IP 54 shall be
screened off from other parts of the motor. A filter that can be easily removed and cleaned
shall be provided to collect the dust from the brushes.
Terminal boxes shall be positioned to accept adequately supported cables which rise
vertically from below, or alternatively angled in such a way as to accept cables from a
cable try without stress being introduced to the cable. The required positions of the cable
boxes shall be approved before manufacture.
Page B / 6
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
Each terminal box of stator/rotor shall be fitted with an approved phase segregated cable
termination and sealing/spreading box, cable glands and all fittings necessary to
terminate the cables and cores. Phase segregation shall be provided by earthed metallic
barriers forming completely distinct individual phase compartments, so as to restrict any
electrical break down to an earth fault between phase to phase.
Terminal and cable termination boxes shall provide sufficient space for segregating the
cores and maintaining the minimum insulation clearances and creepage distances
applicable. Cable terminal and sealing/spreading boxes shall be suitable for a maximum
fault level of 50kA for 0.25 sec. on 415-volt system.
Terminal boxes shall be fitted with pressure relief diaphragm, so that products of an
electrical breakdown within the terminal box will be relieved outside the terminal box.
Pressure relief shall be located between the terminal box and the motor, so arranged
that potential for injury to personnel is minimised.
Cable sealing box to accommodate XLPE insulated cables shall be suitable for housing
heat shrinkable termination kits and shall be supplied with compression glands. Gland
plates and glands to be used for single core cables shall be made of non-magnetic
material such as brass or stainless steel.
Cable sealing box to accommodate PVCSWAPVC cable and mounted indoors shall be
air insulated, totally enclosed and sealed to exclude moisture and dust.
Clamping devices shall be provided inside the terminal box to separate and support the
cable conductors and to withstand the short circuit current. Material used for clamping
devices shall be non-hygroscopic.
Approved indoor/outdoor type glands shall be provided in accordance with the relevant
section of the Specification for termination of PVCSWAPVC cables.
Internal surfaces of terminal boxes shall be painted white to aid detection of dust and
other foreign matter.
Stud terminals mounted on terminal boards shall be provided in terminal boxes. Loose
or flying leads shall not be used. An earthing terminal shall also be provided in each
terminal box.
Information provided on the rating plate shall be in accordance with IEC 34-1. The values
provided should as far as possible be actually measured and shall be based on the
specified operating conditions. The rating plates shall include, but not limited to the data
stated below:
Page B / 7
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
For motors with rated output exceeding 2.2kW, the following additional information shall
be provided on a separate rating plate.
- Bearing size
- Bearing type
- Clearance
- Type of lubricant
- Lubrication intervals, where applicable
- Minimum and maximum allowable quantity of lubricant for the DE and NDE bearings
All motors larger than 2.2kW shal be provided with power factor correction capacitors in
respective starter boards to correct the power factor of the motors to not less than 0.9
lagging under all operating load conditions.
Electrically operated actuators for valves and penstocks shall be sized to guarantee
closure at the maximum possible differential pressure across the door. The safety margin
of motor power available for unseating the door shall be at least 50 percent in excess of
maximum closing torque at the nominal supply voltage. For valve sizes 300mm or greater
the closing and opening shall take approximately 2 minutes for each operation unless
otherwise specified. For valve sizes less than 300mm, the operating speed for closing
and opening shall be 300mm per minute. In addition, for valve sizes of 600mm and
above, the electric actuator shall include a pulsing timer assembly. The pulsing timer
assembly shall provide automatic inching operation of the valve over a pre-selected
portion of the valve travel to effectively achieve 2-speed valve movement. The point at
which change of speed shall occur shall be selected by setting of a limit switch in each
direction. The pulse timer shall incorporate an adjustable approximate starting period of
0-15 seconds and an adjustable approximate stopping period of 0-120 seconds per
pulse. The available pulses shall not be less than 20.
The electric motors shall be Class F insulated and tropicalised and conform with the
Specification with a time rating of 15 minutes or twice the valve/penstock stroking time,
whichever is longer. Duty rating shall S2 or S4.
A space heater shall be provided in the electric actuator. The heater shall be suitable for
use on a single-phase a.c. supply and wired to the terminals compartment. The heater
shall be sufficiently rated to maintain the temperature above dew point when the actuator
motor is stationary.
The actuator gearbox shall be of totally enclosed oil bath lubricated type, suitable for
operation at any angle and provided with the appropriate filing and drain plugs. The drive
shall incorporate a lost motion hammerblow feature. The output shaft shall be hollow to
accept a rising stem. Thrust bearings of the ball or roller type shall be provided in such a
way that the gear case can be opened for inspection or disassembled without releasing
the stem thrust or taking the valve out of service.
Page B / 8
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
A handwheel shall be provided for emergency operation and shall be arranged such that
when engaged the motor shall be automatically disconnected mechanically and
electrically and the drive being restored to power only after disengaging the handwheel
and by starting the motor. The handwheel and any gearing shall be such as to permit
emergency manual operation in a reasonable time and in any case shall not exceed one
hour. Clockwise operation of the hand wheel shall give closing movement of the valve
unless otherwise stated.
The actuator shall be furnished with a drive bushing easily detachable for machining to
suit the spindle or gearbox input shaft. The drive bushing shall preferably be positioned.
Rotor resistance starters shall be rated for uninterrupted duty and intermittent duty Class
0.1 with on load factor of 60 % and utilisation category AC-3. The rated operational
voltage (Ue) and the rated insulation voltage (Ui)) shall be not less than 440V A. C.
The rated operational current (Ie) shall be not less than the full load current of the motor.
The corresponding rated thermal current (Ith) and the rated operational power with the
starter gear assembly shall be entered in the Technical Schedule.
Coordination with the short-circuit protective device (S.C.P.D.) shall be Type "b" as
defined in Appendix C of BS 4941 for a prospective short-circuit current not less than the
value stated in Particular Specification. For this purpose, the S.C.P.D. shall be the
suitably and motor circuit fuse.
Thermal overload relays shall be Type 2 and sensitive to phase failure. Time current
characteristics shall be supplied by the manufacturer on 28mm x 56mm logarithmic
decides. These curves shall have a tolerance not exceeding ±10%.
Starters shall be suitable for both automatic and non-automatic methods of control. When
opening by overload relay involves energizing an auxiliary relay from the control supply,
the pick-up voltage of this auxiliary relay shall be below the drop-out voltage of the main
contractor.
The rated control supply voltage (Ue) shall be equal to the nominal voltage of the A.C.
item specified.
Test certificates shall be supplied for the following type and special tests to BS 4941:
Part 4.
Page B / 9
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
i) Twisted conductors shall be used in all signal leads, and shall be constructed with
26 - 33 twists per metre.
ii) The minimum cross-sectional area for low level signals shall be 0.65 square min
copper.
iii) An overall screen shall be included in signal cables for digital contact closure,
digital pulse, high level analogue and actuator drive signals.
iv) Individual screens for each twisted pair together with an overall screen shall be
included in signal for low level analogue signals.
(vi) Insulation between conductors and earth shall not be less than 10 megaohms at
50OV.
(vii) The different types of signals shall be segregated from each other and shall be
contained in separate cables.
Strict segregation shall be followed with not more than one type of signal run in any
multicore cable.
The ultrasonic continuous measurement equipment for level measurement and open
demand flow shall be similar to the ultrasonic measurement equipment.
The maximum allowable separation between the signal converter and the transmitter
shall be 150m. Special coaxial cable between these two units shall be supplied by the
manufacturer.
The signal converter shall be to IP65, (IEC 529) and provide a 4-20 mA d.c. output signal
for remote indication. A suitable power supply unit shall be incorporated within it, so that
converter shall be operable from a 240V 5014z power supply. A built-in temperature
compensation to compensate errors due to variation of sound speed in air with
temperature shall be incorporated and suitable for the environment of installation. It shall
have solid-state modular plug-in printed circuit boards or equivalent for easy
maintenance. A minimum of 2 independent continuously adjustable set points and relays
(SPDT min. 4A 240V 50Hz resistive) shall be provided within the converter.
Page B / 10
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
For open channel flow measurement, a linearizer shall be incorporated and programme
with Q/h characteristic of the channel.
The level sensor shall be the capacitor type located in a stilling chamber.
The detector shall be of AISI stainless steel frame PTFE lining or other equivalent
approved lining and Hastelloy C electrodes. Flanges shall be carbon steel.
For metallic pipe which must be similarly earthed, the metering tube shall be effectively
bonded to the pipes.
The metering tube shall have an external finish to be suitable for total continuous
submergence in water (i.e. IP68).
The signal converter shall be to IP65 protection or if to IP64 protection shall be provided
with a suitable weatherproof enclosure. It shall be suitable for the flow velocity ranges
used. Special cables between signal converter and the metering tube
shall be supplied by the manufacturer. The signal cable between the signal converter to
the indicator or receiving device shall be screened two core cable of appropriate size.
The design of the system shall be such as to allow a maximum separation between the
signal converter and the metering tube of 200m.
The signal converter shall have a 4-20 mA d.c. output signal for flow rate and a pulsed
(30ms pulse width) output signal for a remote counter indicator.
Orifice plates shall be of square edge concentric bore type manufactured from stainless
steel and shall comply with BS 1042 : Part 1.
The orifice plate shall be designed to obtain an optional range of not less than 2:1 and a
pressure loss of not more than 50 % of the differential pressure.
Page B / 11
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
These shall be of Cast Iron designed to BS 1042. Internal surface shall be coated with
non-toxic epoxy. Flanges shall be made to suit the pipework in the system.
5.8 Transmitter
The transmitter to be used in conjunction with differential pressure sensing device shall
be similar to Electronic Differential Pressure Transmitter model 115DP manufactured by
Rosemount or equal approved.
Differential pressure (DP) transmitters shall be compatible with the primary sensors in
range and accuracy. For flow measurement, the DP transmitter shall incorporate inbuilt
square root extraction such that its 4-2OmA DC output signal is linearly proportional to
the flow rate.
The transmitter to be used in conjunction with pressure sensing devices shall be similar
to Electronic Gauge Pressure Transmitter model 115DP manufactured by Rosemount or
equal approved.
Analogue : 4 - 20 mA
Flow rates : Litres per second, cubic metres/min. Megalitres per day
Generally, the accuracy of a whole instrumentation system i.e. the sensor, transmitter,
indicator or other measured figure for a declared range, unless otherwise specified.
If the declared range for the above guaranteed accuracy falls short of the specified range
of measurement, then the Contractor shall declare the minimum figure measurement
with + 0.2% accuracy. Alternatively, the Contractor shall declare the range for accuracy
up to +/- 0.2%, taking into consideration of the maximum figure specified to be measured.
Page B / 12
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
5.12 Indicators
Analogue signal operated circular type indicators shall be similar to cirscale pattern.
All circular indicators, except where otherwise stated shall be 150mm diameter. They
shall have black bexels, corporated a device for correct zeroing of the pointer and
designed to minimize parallax. They shall be suitable for flush mounting within the
panel, or pedestal, cubicle etc. as required. Other sizes where specified shall have
the same installation arrangement.
The maximum range of all instruments shall, unless otherwise specified, be not less
than 10% greater than the normal maximum indication.
The selection, number of pens, chart speed and chart scale details shall be as specified
elsewhere.
5.14 Integrators
Integrators shall be either combined with the recorder/indicator specified in Clause 5.13.
The integrator shall be able to retransmit an output signal to a remote counter. The
integrator (either combined or separate) shall have a minimum 6-digit counter type with
the first right hand digit representing 0.01 megalitres/10 cu. metres as specified
elsewhere.
5.15 Alarms
Alarm conditions shall be annunciated on an alarm annunciator panel. The system shall
be designed to fail-safe, and alarms shall be initiated by the opening of a relay contact,
which shall be detected by the alarm annunciator system, which will sound and alarm
Maxon and illuminate the relevant alarm annunciator. These shall operate at 24 d.c.
All alarm panels shall include "accept" and "test" pushbuttons and automatic resetting
shall be included. Alarms shall hold until accepted, initially being indicated by flashing
light which shall change to steady when the alarm in accepted. The alarm light has
cleared and the accept button has been pressed. Any flashing alarm annunciator shall
be accompanied by an audible which shall cancel when either the accept button is
pressed or the alarm condition clears.
These shall operate at 24V d.c. and where necessary the d.c. supply and the interposing
relay shall be supplied.
Page B / 13
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
Alarm levels in pumping wells and water holding tanks shall be normally detected using
level electrodes, unless otherwise specified. The electrodes shall be manufactured from
stainless steel, and the electrodes heads shall be waterproof and shall allow an
adjustment in electrode level of at least 150mm to be made.
Alternatively, these may be extracted from the 4-2OmA signal of the level indicator via a
trip amplifier provided in this Contract.
Twin illuminated pushbuttons shall be employed for motor starting and stopping. The
"start" pushbutton shall be illuminated green to show that the motor is ready to start and
the "stop" pushbutton shall be illuminated red to indicate that the motor is running.
These shall operate at 24V d.c. and where necessary the d.c. supply and interposing
relays shall be supplied.
i. Signal cables shall not be run in the same conduit, duct or cable tray as power
cables.
ii. Conduits, ducting, cabling, cable tray etc. may be made of insulating or conducting
materials and where it is of the latter, all cable armour and screens shall be isolated
from conducting material. All cable armour and screens shall be isolated from the
insulating.
iii. Signal cables shall be routed to avoid sources of electromagnetic interference e.g.
electrically powered equipment, fluorescent lightning fittings, etc.
iv. All signal cables running from externally mounted items, i.e exposed to weather
shall be protected with al lightning protection device.
i. Before and during installation up to the time of making off, all cables ends shall be
firmly supported and kept sealed off against ingress of moisture.
ii. The Contractor shall ensure that draw strain is taken on the armoring and the cable
is adequately protected where it enters a duct or pipe.
Page B / 14
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
iii. Where a change of cables direction is required the bending radius shall not be less
than 12 diameters except with the approval of the S.O.
iv. Where cables enter a building through foundation and or concrete flooring, these
shall be provided with a continuous pitch fiber or equal and approved l00 mm. duct
for cables of up to 70mm sq and 150mm ducts for cables above 70mm. sq to ensure
easy entry and minimum radius bends as recommended by the manufacturer of the
cable. These ducts will be provided by the Contractor.
v. Where cables pass through manholes or draw-pits they shall be supported and
spaced clear of the invert of the ducts at a point of entry so that any ground water
etc. finding its way into the duct may drain freely.
vi. Where cables pass through wet wells the duct work shall be of hot dip galvanised
mild steel heavy duty conduit.
vii. All joints where these have been approved by the S.0 shall be made in sealing
chambers of approved design and filled with a non-hygroscopic sealing compound
to be approved by the S.O.
All terminations shall be of the serrated bar type as manufactured by Kippon Electricals
Ltd., Sheernees, Kent, England or equal similar approved.
i. Earthing shall comply with the Regulations of the Institution of Electrical Engineers,
the requirements of the Supply Authority and conform to BS Code of Practice 10 13.
b) Suitable inspection with concrete covers to allow ready access to the electrode
connections.
d) A bolted removable tinned copper link mounted in a suitably located link base
with porcelain carriers.
e) A bolted removable tinned copper link mounted in a suitably located link base
with porcelain carriers.
iii. The earth electrodes shall be in the form of steel core copper rods suitably grouped
and connected.
iv. All metal work, other than current carrying parts of the electrical system, shall be
properly bonded to earth.
Page B / 15
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
Earthing screens of cables carrying signals shall be single point earthing established and
adhered to throughout the installation to avoid the production of "earth loops". Each cable
screen shall be earthed at the end nearest the central marshalling board only and
isolated from earth through the remainder of their length.
6.1 Pipeworks
Pipework shall be supplied to the general arrangements and limits indicated on the S.O.
drawings and shall include all necessary specials, jointing materials, flange adaptors,
etc. The layout and design of the pipework shall be such as to facilitate its erection and
the dismantling of any section for maintenance as follows :
a) All pipes and special shall be of mild steel and conforming to MS 708:1981 to BS
534:1981.
b) All mild steel pipes and specials shall be painted with one (1) layer of zinc chromate
and two (2) layers of gloss finish coating while ductile iron pipes and specials shall
be painted with two (2) layers of gloss paint.
c) All mild steel pipes shall be lined internally with concrete.
d) All flanges shall be machined and drilled to BS 4504 Table 16/11.
e) Flanged items shall be supplied complete with bolts, nuts and jointing materials.
Where a common manifold pipe is used, individual pump delivery branches unless
otherwise shown on the drawings shall be jointed to it in a horizontal plane and radiused
or angled to prevent sharp changes of flow. At joints in civil engineering structures,
flexibility shall be provided in pipework to accommodate differential settlement. Template
pipes, collars and cut pipes or flexible joints shall be provided in all pipe runs between
fixed points to accommodate construction tolerance in the civil structures.
All pipes of 50mm dia. or above connected to items of plant shall have flanged
connections. All pipes shall be checked for alignment and mating of flanges and
connections before being secured. Pipes shall not be sprung into position.
Adequate supporting and anchoring arrangements for all pipes shall be provided and
particular care shall be taken to ensure that pipework thrusts are, as far as possible, not
transmitted to machinery or other associated plant. Where concrete supports are
required, the Contractor shall indicate these on his drawings and the necessary work
shall be arranged by the S.O.
Each pump delivery branch and delivery main shall have provision for the fitting of a
pressure gauge to indicate generated head in metres and bars, the zero indicating
atmospheric pressure.
The gauge provided by Contractor shall comply with BS 1780 and the materials of
construction shall be bronze, stainless steel or other approved corrosion resistant
material other than aluminium.
Gauges shall be at least 150mm in diameter liquid filled type, fitted with an isolating cock
and snubber, and shall be securely attached to the pump discharge pipe above the floor
and easily visible.
Page B / 16
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
The full-scale range of the pressure gauge provided shall be approximately 30% above
the anticipated normal operating head generated by the pump.
The delivery main and each delivery branch also shall be installed with pressure sensor
to indicate the pressure at the delivery main. The reading shall be transmitted to pump
control panel.
The pressure sensor shall be IP65 protection type with 4 to 20mA output signal. The
accuracy shall be ±0.5%. The enclosure and wetted parts shall be acid resistant stainless
steel. The next operating pressure shall be at least 20 Bar.
6.3 Valves
a) All butterfly valves shall conform to BS 5155 and shall be used for pipe
sizes above 250mm diameter.
b) The butterfly valve shall be fully designed for pressure rating of PN 16.
c) For butterfly valve with motorized gear, a suitable hand wheel for
headstock shall be provided.
a) General
The non-slam check valve shall conform to BS 5155 and shall be with high
operating reliability and minimum pressure losses.
b) Design and Finish
i. The non-slam type check valve shall be designed to be of short
stroke, shock free closure and can be installed in any position i.e.
horizontal, vertical or inclined.
ii. The check valve shall also be designed such that the minimum
cross-sectional area of the pipe.
iii. The check valve shall be used for automatic operation by the use of
a direct spring-loaded closing element.
iv. The valve shall be with metal to metal seat and shall operate with
minimum wearing parts and minimum maintenance.
v. The valve shall be designed with the flow diffuser to minimize
pressure losses and shall be flanged and drilled to BS 4504 Table
16/11.
a) General
Electric actuator for operating valves and penstock shall be of the heavy-duty type
and shall be made by reputable manufacturer with similar project references in
Malaysia. Contractor shall propose actuator manufacture that has a principal office
Page B / 17
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
The actuators shall be suitable for use on a nominal 415-volt 3 phase 50 Hz power
supply and are to incorporate motor, integral controls and terminals for remote
control and indication connections.
b) Ambient Temperature
c) Motor
The electric motor shall be Class F insulated, with a time rating of at 15 minutes at
104 oF (40 oC) or twice the valve stroking time, whichever is the longer, at an
average load of at least 33% of maximum valve torque.
d) Gearing
The actuator gearing shall be totally enclosed in an oil-filled gear case suitable for
operation at any angle. All main drive gearing must be of metal construction.
e) Hand Operation
A hand wheel shall be provided to emergency operation, engaged when the motor
is declutched by a lever similar means, the drive being restored to power
automatically by starting the motor.
The handwheel drive must be mechanically independent of the motor drive and
shall be direct 1:1 ratio for emergency operation.
Electric actuator shall be equipped with mechanical open and close torque and
position limit switches with separate changeover volt free contacts at each end of
travel for remote indication and interlocking.
Electronic means for actuator position and torque measurements is not acceptable.
Digital LCD indicator that requires battery back-up during power outage is not
acceptable.
Integral to the actuator shall be local controls for open / close / stop and a local /
remote selector switch pad lockable in any one of the following three positions:
local control only, off (no electrical operation), remote controls plus local stop only.
Open / close limits switches shall be provided for remote indication of valve
position, with each contact rated at 5A, 250V AC, 30V DC.
Page B / 18
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
Contacts that are activated electrically requiring the use battery back-up during
hand operation when there is a power outage will not be acceptable.
a) To counter water hammer, surge vessel shall be installed at the pump house.
b) Manufacturers are required to submit the complete sets of drawings, calculation and
etc. to DOSH for approval.
The details of the sluice valve, butterfly valves and non-slam check valves to be supplied
and installed are tabulated below: -
The normally closed pilot shall be of brass and bronze construction with a spring to adjust
the opening pressure.
The inner valve shall be of stainless steel 316 construction and the inner valve shall have
EPDM resilient compound for seating. The EPDM compound must be bonded
permanently to the inner valve and be ground flat and square to assure maximum
performance.
The pilot shall be self-cleaning by locating the inlet directly into the seat area through the
bottom of the pilot and the outlet ninety degrees to the inlet.
Page B / 19
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
Stainless steel items shall be manufactured from Grade 316S31 steel complying with BS
970, Part 1 or BS 1449, Part 2. Bolt lengths shall be sufficient to ensure that nuts are
fully threaded when tightened in their final position.
Stainless steel safety chain shall be manufactured from Grade 316S31 steel complying
with BS 970, Part 1. Chain links shall be welded and have an internal length not
exceeding 5 mm and an internal width of between 12mm and l8mm. The fins caused by
welding shall be removed and the weld shall smoothly-finish all round. When tested in
accordance with Clause 7.3 of BS 4942, Part 2, each chain shall withstand a breaking
force of 30kN and a proof force of 15 KN.
Mild steel and aluminium alloy industrial type flooring and stair treads shall comply with
the relevant provisions of BS 4592.
After fabrication, mild steel flooring and stair treads shall be hot dip galvanised in
accordance with BS 729.
Each floor panel shall be secured to the supporting members and adjoining panels with
proprietary clips.
The weight of any single panel shall not exceed 35 Kg, without the S.0's agreement.
Fixing bolts, nuts and washers for concrete, brick or masonry shall be of stainless steel
Grade 316S31 to 13S 970 : Part 1 or BS 1449, Part 2. The bolts may be rag or indented
bolts to BS 1494 : Part 2, expansion bolts, or resin bonded bolts. The Contractor shall
submit details of the type he proposes to use, including manufacturer's specification
literature, for the S.O.'s approval.
Dimensions of holes and box-outs for fixing bolts shall be shown on machinery
foundations drawings.
When the bolts etc. are used for fixing aluminium items they shall be insulated from the
aluminium by a non-metallic sleeve and under-washer.
Page B / 20
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
The building-in material for use with rag or indented bolts, shall be a proprietary epoxy
non-shrink grout or a proprietary non-shrink mortar or caulking compound. Bolts shall not
be brought into service until they are effectively anchored and the building in material
has achieved adequate strength.
All sections of the plant which constitute a safety hazard shall be covered by substantial
guards or barriers which shall comply with the Safety regulations.
All parts that in normal working are hotter than 60 degrees C or colder than -5 degrees
C shall either be adequately fenced or shall be lagged.
All live electrical conductors, including conductors forming part of electrical apparatus,
shall be either insulated or so fenced or placed as to prevent danger.
Guards shall be fabricated in mild steel wire mesh or expanded steel sheet, or should a
fully enclosed type be necessary, in mild steel sheet.
Guards shall be bolted in position in such a way that they cannot be unintentionally
dismantled or removed.
All mild steel used in the construction of guards, including brackets shall be hot dip
galvanised unless otherwise specified.
Drawings of safety guard shall be submitted to the S.O.'s for approval before
manufacture.
The positions of all greasing and oiling points shall be arranged so as to be readily
accessible for routine servicing. Where necessary, to achieve this, suitable extension
pipes shall be fitted.
Manual grease lubrication points shall use hexagon headed nipples to BS 1486 : Part 1.
If more than one type of grease is required, a different size of nipple shall be used for
each type and labels to indicate the special lubricant required.
Dip sticks or level plugs shall not be used without the approval of the S.0's.
Automatic lubrication shall be provided where specified and full details of the system
shall be submitted to the S.O. for approval.
Where continual grease or oil feeding is required, the capacity of the reservoir shall be
sufficient for not less than seven days continuous service.
Page B / 21
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
All equipment shall be suitable and uniformly labelled as to its operation, compatible with
the designation used on the appropriate electrical control cubicle.
Details of all labels and warning notices shall be submitted to the S.O. prior to
manufacture.
Labels and warning notices shall be of engraved plastic material and shall be screwed
or bolted in position. Adhesive bonding is not acceptable.
Unless otherwise specified, plant and machinery shall be finish painted to the following
colours:-
Plant (Common)
PVC pipework shall be unpainted but banding of the basic identification colour and the
appropriate colour codes shall be applied.
Page B / 22
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
7.1 General
This section covers electrical works to be carried out in association with the station
pumping system.
The equipment to be provided and installed at the Pump House includes but not limited
to the following:-
iv. Cabling
v. Earthing
The Contractor shall be deemed to have visited the site and allowed for all necessary
cost. All electrical works, irrespective of the nature of the installation shall incorporate
value engineering in respect of energy saving and cost saving in ongoing maintenance,
etc.
This section shall be read in conjunction with all other sections describing the various
equipment of the works,
7.2 6,600V Pump House Switchboard (Pump Starter Board) for Constant Speed Pump
Rotor resistance starter shall be provided and the starter shall comprise the following:
i. One suitably rated TPN, 4 pole motor protection MCCB with padlock and key for
locking in the off position.
ii. One four pole main contactor of the fail-safe type, having easily removable contacts,
arc chutes or pockets and inherent under voltage release or as required.
iv. One 90mm ammeter with suitably scaled and ammeter selector switch.
Page B / 23
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
vii. One solid state type rectifier device and sets of relays and controls for starting
complete with all auxiliary contacts for:
a. Auxiliary Controls
b. Signal Lamps
c. Delay timer to limit the starting frequency to less than 4 starts per
hour and 2 consecutive starts within 5 minutes in any hour
ix. One set of auxiliary contacts for the motor starter heaters.
x. One anti condensation heater with thermostat automatically energized when the
motor is not running and de-energize them when the motor is running.
"MOTOR - AMBER
FAILED OVERHEATING"
xx. One MCB suitably rated for the starter anti condensation heater circuit.
Page B / 24
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
xxiii. Power Factor correction capacitor banks complete with suitably rated MCCB,
contactors, automatic controller, etc.
Full details of the compartment’s fascia, starter components and control wiring shall be
provided for approval prior to commencement of manufacture.
This shall be the front and rear access type with Form 4 construction to BS5486. Cable
entry shall be, from the bottom.
Enclosure classification shall be IP54 to BS5490. It should be located in the pump house
as shown on drawing.
i. Incomer
1 - 4 poles TPN air circuit breaker (ACB) withdrawable type complete with
operating push buttons and indicating lights
1 - set supply "available" indicating lights
Page B / 25
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
The power supply is 415 Volts, 3 phase, 50 Hz and shall be taken from the 415V
main switchboard.
All MCCB shall have door interlock. All the necessary interconnecting cables shall
be provided under this Contract.
7.4.1 Cabling
All cables inclusive of trenching, backfilling, road crossing trays, ladders, brackets,
supports and etc. for all equipment supplied under this contract shall be provided.
The Specialist Sub Contractor shall supply and install all cables from the Main
switchboard to the various other Boards and equipment specified and then to all
associated plant components. Some of the main feeders are indicated on drawings, as
guide only. The Contractor shall size cables and submit cable schedule for approval.
For long low voltage cable routes, voltage drop shall be taken into considerations.
Start/Latched stop local pushbutton control station shall be provided for each pump and
plant.
7.4.3 Earthing
Earthing systems shall comply with the requirements of BS 7430 Earthing, 1EE
Wiring Regulations, TNB and JBE as required.
The main ear thing systems shall consist of earth bars, circuit protective
conductors, equipotential bonding conductors, concrete electrode pits complete
with 15.6mm dia. x 5,467mm long (minimum), hard drawn copper or copper clad
steel earth electrodes and gunmetal clamps, interconnecting 25mm x 3.125mm
copper strips in 50mm diameter PVC pipes.
Page B / 26
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
The earth resistance value measured at the Main Earth Bar shall not exceed I
ohm. The earth connections for all sections of each installation shall be
continuous throughout. Each individual earth systems shall achieve its required
earth resistance value before being interconnected with other earth systems.
The main bonding cables shall not be less than 16 sq. mm and supplementary
bonding of non-electrical plant not less than 10 sq. mm All connections shall be
made using compression type cable lugs, taped on completion to completely
sea] the lug and any bare copper from the atmosphere.
The earth network conductor comprising tinned copper tapes and/or cables shall
be securely supported and clamped in a neatly spaced manner on building
structures, cable trench walls all on cable trays, and neatly run vertically,
horizontally, parallel to adjacent walls, ceilings, beams, etc. appropriate. The
earthing installation shall be protected from any mechanical damage or
corrosion.
A main earth bar (complete with test links) shall be installed in a convenient
location preferably in cable trenches 600 mm above the finished floor level. The
main earth bar shall comprise a high conductivity copper bar supported on
porcelain barrel type insulators and wall mounted. The earth bar shall be of
sufficient length to accommodate bolted copper tape/cable connections to:
a. The earthing conductors between the earth bar and the earth
electrodes.
b. Circuit protective conductors between the earth bar and exposed
conductive parts.
c. Main equipotential bonding conductors between exposed and
extraneous conductive parts.
d. System neutral earthing conductors.
The size of the main earth bars for the 415-volt system the cross-sectional area
shall not be less than less than 150 sq. mm.
The main earth conductor shall also be provided with adequate number of spare
terminals including cable lugs, bolts, etc.
The sizes of earth continuity conductors for 415-volt system shall be as follows:
Page B / 27
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
For cable sizes less than 35 sq. mm : 13 mm x 1.6 mm tinned copper tape.
Particular care shall be taken on cable termination boxes to ensure that the cable
sheath and armour are adequately bonded to the frame of the item of plant to
which the cable is connected. The armour of the cable shall not be used as the
sole earth return path conductor. Cable armouring shall be bonded to earth at
both ends.
iv. Joints
Bar to bar tee joints and tape to tape joints (for underground connections) shall
be of 'Furseweld' or 'Cadweld' method to the approval of S.O. All earthing tape
connections to electrical apparatus shall be made by using a bolted connection
in a visible and accessible position. Before the connection is made, the tape
surfaces shall be tinned.
v. Earthling Points
vi. Electrodes
Each earth point shall comprise an extensible type earth electrode of diameter
not less than 16mm, made of hard drawn steel cored copper rods with internal
screw and socket joint, hardened steel tip driving heads and connector clamps.
The rods shall have an electrolytically bonded layer of copper of not less than
0.38mm thickness. The Contractor shall determine the length and number of
electrodes required for each earthing, after the resistivity of the soil at the
particular location has been measured at site and witnessed by S.O. The
electrodes shall be interconnected by means 25mm x 3mm tinned copper tape
laid at a depth of 750mm below ground level.
Page B / 28
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
Where ground conditions make deep driving of single earth electrode impossible
to achieve the desired earth resistance, a matrix arrangement of electrodes
joined to one another by 25mm x 3mm tinned copper tape buried at a depth of
600mm shall be used to form an earth mat in order to achieve the desired earth
resistance value. The Contract Rates shall be deemed to include all the
necessary electrodes, tapes, interconnections, etc. required to achieve the earth
resistance value.
All joints shall be protected against corrosion and the ingress of moisture by the
application of two coats of an approved anti corrosion conductive paint.
At each earthing point an approved nonferrous clamp shall be provided for the
connection of the tinned copper tapes to electrodes. These connections shall be
housed in individual electrode inspection chambers at every earthing point with
a cover set flush to ground level. The inspection chamber shall be of 'Furse'
make type PT 205 or approved equivalent.
Marker posts shall be provided to mark the position of the electrodes adjacent to
the earth chambers. The marker posts shall be similar to those provided for cable
routes.
All excavation of trenches for the installation of the copper tapes, earth
electrodes and the inspection chamber shall be carried out by the Contractor to
the requirement of the S.O. The Contractor shall be responsible for the backfilling
and reinstatement of the trenches, setting and alignment of the inspection
chambers to the satisfaction of the S.O.
x. Testing of Electrodes
The works shall also include for testing of all earth electrodes to the satisfaction
of the S.O. The test instruments required for the tests shall be provided by the
Contractor.
After the earthing installation has been completed, the Contractor shall
demonstrate to the S.O. that the resistance of the electrodes to earth and the
continuity of the earth network are within the limits specified. Any additional earth
electrodes, if required, shall be provided by the Contractor. Earth tests shall also
include measurement of the resistance value of each individual earth point.
Earth resistance testing shall also be carried once in the driest period or any time
which is deemed suitable by the S.O. during the Defects Liability Period. Should
the earth resistance value be less than the specified value, the Contractor shall
install additional earthing points in order to achieve the specified value. The
Contract Rates shall be deemed to have taken into account the additional
earthing points required and there shall be no claims for cost in this respect.
Page B / 29
Technical Specifications
Section 2: Station Main Pumps & Pipeworks
Scope of work
The Contractor shall supply, deliver, install and test a complete surge and
transient system for the individual instrument, equipment and system.
The single mode power line shunt surge protection device shall be rated for
8OkA per phase, 8/20~ts single shot surge capacity (Imax). The unit shall
contain at least 160kA (8/20gs) of internal surge material providing robustness
and additional life for multiple numbers of smaller impulses. It shall be designed
for mounting at main power switchboards and distribution boards. Each phase
shall have individual module.
The device shall come with fast responsive Metal Oxide Varistors (MOV) and
diodes to provide effective surge protection with low let through voltage to protect
the sensitive electronics and electrical circuits. The rated voltage shall be 240 V
at 50Hz. Surge arrestors must be designed to operate within the temperature
rating of 10 to 60 deg. C.
END OF SECTION
Page B / 30
Technical Specifications
Section C: SCADA, Telemetry & Instrumentation
-As per attached Air Selangor ‘SCADA and Instrumentation System Specifications’ Rev. 2.0
dated 30.5.2017’
Page C / 1
SCADA AND INSTRUMENTATION
INSTRUMENTATION
SYSTEM SPECIFICATIONS
SPECIFICATIONS
Revision Date
Initial release 4.1.2010
1.0 8.8.2011
2.0 30.5.2017
TABLE OF CONTENTS
1.0 INTRODUCTION
1.1 Type of Water Supply System…………………………………………. 5
1.2 Typical Diagram of SCADA and Instrumentation ………………... 7
5.0 INSTRUMENTATION
5.1 Ultrasonic Level Sensor……………..………………………………... 18
5.2 Pressure Transmitter……………………………………….………….. 20
5.3 Flowmeter……………………………………………………………… 22
5.4 Touch Panel ………... ……..…………………..……………………… 25
Page 1 of 72
6.4 Sealed Lead Acid (SLA) Battery…………………………………….. 28
9.1 General……………………………………………..…………………… 51
9.2 Power Lines Surge Protector for Main Incoming Supply……….. 51
9.3 Power Line Surge Filter for RTU and Instruments…………..……... 52
9.4 Single Lines Surge Protector for Data Transmission & Control
System …………………………………………………………………….. 53
9.5 Earth Conductor for the Power & Signal Lines Surge…..………... 54
10.0 OTHERS
10.1 Control Relay……………..……………………………………………… 55
10.2 Interposing Relay……………………………....…………….………….. 55
10.3 Circuit Breaker.………………………………………………………… 56
10.3.1 General …………………………………….………...……………55
10.3.2 Miniature Circuit Breakers (MCB) ………………………….... 56
10.3.3 Auto-Reclosure Earth Leakage Circuit Breakers
(MCB)..……………………………………………………………...57
Page 2 of 72
11.0 INSTRUMENT PANEL
11.1 Design and Construction ………..……………………………….. 58
11.2 Component Arrangement ……………… ………………………. 59
11.3 Wiring and Cabling………...……………….………….…………… 60
11.4 Terminal Blocks ……….……..…………………..…………………… 62
11.5 Cable Terminations ………………………………………………….. 63
12.0 DEVELOPMENT
12.1 Requirement of Submission Process ……………………………. 68
12.2 Commissioning Test…………………………………………………. 24
12.3 Operation and Maintenance Instruction Manual …………… 71
Page 3 of 72
1.0 INTRODUCTION
Table 1.0 and 2.0 show the different types of water supply systems. The
tables also show the primary instrumentation equipment requirements.
TYPE code of
Description of the Installation
installation
RESERVOIR
Table 1.0
Page 4 of 72
TYPE code of
Description of the Installation
installation
PUMP HOUSE
Table 2.0
Page 5 of 72
TNB Supply
240V AC
ELCB
24V DC
MCB
Field Sensor
(2 wire system) 2 2 Fused Fused Fused
4C X 2.5mm 4C X 2.5mm
- Level LPU ( 4-20mA & Power )
LPU
- Pressure Power
Supply
ETHERNET CABLE 4G
Communication
Port RJ45 Modem
ETHERNET CABLE
< 1 Ohm
< 1 Ohm RJ45
LOW LOSS
Analog CABLE
Input HMI
Surge
4C X 2.5mm
2
4C X 2.5mm2 Touch Panel Arrestor
LPU (24 VDC ONLY) LPU
Digital
Field Sensor 4C X 2.5mm
2
4C X 2.5mm
2 Local Alarm Indicator
LPU LPU Input
- ( 4-20mA ONLY)
2
Flowwmeter 4C X 2.5mm
4C X 2.5mm
2
LPU LPU
(TOTALIZER ONLY) Digital
EXTERNAL
Output
TERMINAL ANTENNA
BLOCK
< 1 Ohm
Sump
Pump 4C X 2.5mm X PUMP
Flowmeter
Chamber
Control 2
4C X 2.5mm X PUMP (Optional)
Circuit
2
- Pump 4C X 2.5mm X PUMP
MT/2017/v2
Page 6 of 72
2.0 GENERAL REQUIREMENTS
Page 7 of 72
The different principle type to be employed for each category
of measurement shall be as follows:
Cable for AC, DC, control and signal shall be segregated and
shall not be mixed in the same multicore cable. Each cable
shall carry signals of only duty group and shall have separate
panel or junction box.
Page 8 of 72
2.3 System Design
2.3.2 Construction
2.3.3 Labeling
Page 9 of 72
Superintending Officer (S.O.) to permit easy identification and
cross reference to diagram. Components shall be individually
identifiable from layout diagram relating to individual boards
or units.
Wiring tags shall be so positioned that neither the tag, nor any
possible wiring conductor there on may come into contact
with any cover. Sufficient slack shall be left at the end of all
wires in forms, so as to permit replacement of components and
sub-assemblies without difficulty.
Page 10 of 72
Wiring of cable forms, feeding hinged frameworks carrying
apparatus shall be formed and run in such a manner as to
prevent rubbing action and possibility of breakage of wires.
The hinged mountings shall open and close without straining
the wiring.
Page 11 of 72
3.0 SCADA SYSTEM – OUTSTATION
3.1 General
Two (2) types of RTU shall be used for different type of function.
Each type of RTU provided for the scheme shall be from the same
manufacturer to provide standardization and interchangeability of
equipment.
Page 12 of 72
Analogue output modules shall convert data words into proportional,
isolated 4-20 mA DC analogue output signal to adjust gate positions
with minimum 8-bit resolution. The analogue power output shall be
able to drive up to 500 ohm maximum resistance load.
The RTUs shall come with one TCP/IP Ethernet port, one HART port,
one RS-232 and one RS485 serial port as the port for RTU to RTU
communication using Master/Slave configuration and
communicating using HART protocol to sensors. Data signal from the
outstations shall be transmitted to the master station via the same
single communication network using VPN connection. An additional
industrial din-rail type switches need to be installed when more TCP/IP
Ethernet port is required.
Page 13 of 72
The RTU shall be suitable for operation a single phase 240 V + 10%
50Hz supply with auxiliary power supplies at 24 V DC supply or 24 VDC
supply from a solar power system.
The RTU shall be of a low-power design. This is to allow easy and cost
effective installations using other power sources such as solar or
battery power. A low power design will also enhance reliability of the
CPU module.
Page 14 of 72
4.0 COMMUNICATION SYSTEM
4.1 General
The modem shall come with minimum of 1 TCP/IP Ethernet ports and
1 RS-232 / RS485 serial port as the port for communication.
The modem shall have built-in firewall and supports virtual private
network (VPN) for secure communication to M2M Gateway located
at Operation Command Center. L2TP, SSH or OpenVPN protocol are
acceptable.
Page 15 of 72
4.3 Antenna
The signal cable shall be a 50 Ohm RF Coaxial Cable (low loss type)
to reduce attenuation. Minimum specifications are stated below:
Page 16 of 72
5.0 INSTRUMENTATION
The sensor, which shall be a two wire system with power and output
analog signal on the same pair of line, minimum of 12-meter range
and positioned at least 250 mm above the high water level. It shall
contain an electro-dynamic transducer for the transmission and
reception of sound waves. The sensor shall support HART protocol.
A timing unit shall be included for determining the time for the overall
travel and converting this time into distance. The reaction time shall
not be more than 5s.
The design and application of ultrasonic level meters shall take into
account the tank type, the material, size, shape, environment,
process fluid or material, the pressure of foam, granules, size etc. The
installation shall be chosen carefully in order to avoid any
degradation of performance from spurious reflections, absorption,
sound velocity variations, sensors detection area, temperature
fluctuations, shielding, stilling tube or other measures shall be
provided to avoid effects on the measurement.
Page 17 of 72
7.5 TYPICAL INSTALLATION & WIRING OF ULTRASONIC LEVEL TRANSMITTER
Junction Box
L
P
U
2.5 mm PVC
cable
Flexibble GI Conduit
Ultrasonic Level
Sensor
6 mm PVC
cable
Cable Gland
Conduit
Rev v2 4/17
Page 18 of 72
5.2 Pressure Transmitter
The system shall be of the gauge pressure type and the transmitter
shall be a two wire system with power and output analog signal on
the same pair of line. The output of the system shall be linearly
proportional to the pressure and shall have a live zero 4 to 20 mA DC
against a load at least 600 ohms. Zero and span calibration shall be
non-interacting and shall be easily accessible to facilitate calibration
works.
The pressure transmitter shall come with stainless steel housing and
process connection. Ingress protection for the device shall be to IP65.
Page 19 of 72
3.0 TYPICAL INSTALLATION AND WIRING OF PRESSURE TRANSMITTER
Venting
Valve
(4C x 1.5mm
amoured screen cable)
Panel Body
Panel Door
Cable Gland Ring
Isolating Cork
6 mm PVC
cable
Page 20 of 72
5.3 Flowmeter
a) ISO 4064:2005
• Pt 1, Pt 2 and Pt3 – Measurement of Water Flow in closed
conduits – Meters for cold potable water
b) ISO 6817
• Measurement of conductive fluid flow in closed conduits
• Method of Using Electromagnetic Flow Meter
c) ISO 9104
• Test and Measurement of Fluid Flow in Closed Conduits For
Electromagnetic Flow Meters For Liquids
d) EN 60529
• Degree Of Protection By Housing (IP Code)
e) EN 61010
• Protection Measures For Electrical For Measurement,
Control, Regulation and Laboratory Procedures
The sensor shall have a combined accuracy with converter for 0.25%
or better and repeatability of at least 0.5%. The sensor shall able to
measure bi-directional flow and come with empty pipe detection
feature. The sensor shall operate satisfactorily in ambient
temperatures up to 60°C.
Page 22 of 72
4.0 TYPICAL INSTALLATION AND WIRING OF FLOWMETER
L L L
P P P
U U U
2.5 mm2
PVC cable
1.5 mm2
amoured
screen
FLOW CONVERTER
Panel Body
Panel Door
Cable Gland Ring
6 mm2 PVC
cable Flowmeter
Chamber
Field Cable to GI Conduit
To Earth RTU Panel
Station Conduit
4 mm2 PVC
cable
Page 23 of 72
5.4 Touch Panel
5.4.1 General
It shall also incorporate RESET and security features. The flow rate shall
have programmable scaling.
The Touch Panel shall be a HMI and programmable type. It shall have
supports for remote access via intranet or internet.
• Know-how Protection
- Algorithms can be protected against unauthorized access and
modifications.
• Copy Protection
- On the Memory Card, individual blocks are linked to the serial
number of the original memory card. This means that programs
cannot be copied. They will only run with the intended memory
card.
• Access protection
- Access protection functionality offers security against
unauthorized project-planning changes. Permission levels can be
used to grant separate rights to different user groups.
• Manipulation protection
- The system helps to protect the data being transmitted to the
controller from unauthorized manipulation. The controller
recognizes when a transmission of engineering data has been
changed or comes from an unknown source.
Page 25 of 72
6.0 POWER SUPPLY
6.1 General
The solar panels shall be water proofed and all the metallic part must
be corrosion free. It shall not lose its transparency after prolonged
exposure to high radiation, high temperature, dust, oil and
precipitation in the tropics.
The glass surface of the solar panels shall be tempered glass and able
to provide ultra-clear performance for excellent light transmission
and protects from wind and impact. Terminal enclosure on the solar
panel shall be designed for trouble-free field wiring and environment
protection.
The solar panel shall be installed at the top of the reservoir and shall
be fixed to a roof top or mounted on top of a minimum 3m GI pole
complete with arm, bracket and fixing accessories to avoid from
vandalism.
Page 28 of 72
7.0 DISTRIBUTION – CABLING
Cabling between the various items shall be the types as shown in the
Drawings.
a) Delivery
b) Conductors
c) Insulant Colours
Page 29 of 72
d) Rating
a) Instrumentation Cable
i. PVC/PVC
Page 30 of 72
The cable shall be used for the exposed installation type and
shall not less than 1.5mm dia.
ii. PVC/PVC/SWA/PVC
The cable shall be used for buried installation type and shall
not less than 1.5mm dia.
C) PVC/SWA/PVC
Page 31 of 72
The amour bedding shall consist of an extruded layer of Type 6
or Type1 PVC compound complying with BS 6746. The radial
thickness shall be in accordance with BS 6346.
The outer covering the amour wires for all multicore control
cable shall consist of a black extruded PVC sheath which shall
comply with the requirements of BS 6746 for Type 1 compound.
The thickness shall be in accordance with BS 6346.
The sand used shall be fine river sand with no stones included.
A layer of bricks shall be placed over the cables. Backfilling
shall be made with first quality material and well compacted
where cable trenches run across turfed area and roadways.
(ii) PVC
(iii) PVC/PVC
7.3.1 General
Page 33 of 72
25 Grade Cement
T6 Grade Iron
(Both-way)
GI pipe
Figure 5.0
Photo 6.0 (a) and (b) illustrates the typical installation of concrete box
at GI conduit jointing.
Photo 6(a)
Page 34 of 72
Photo 6(b)
Page 35 of 72
Cable hangers, cleats, saddles, brackets and similar supporting
devices shall be of an approved type and of adequate strength for
the cables they are supporting. They shall be treated to withstand
site conditions without corroding. Self-locking plastic buckle clips
and strapping shall not be used. Re-usable cable ties may however
be used. Cable ties shall be of nylon for indoor installations and
stainless steel straps covered with PVC/nylon for outdoor installations.
Nylon straps shall be of ultraviolet stabilized type.
Page 36 of 72
Initiating devices for plant protection and personnel safety shall be
connected by individual cables direct to the tripping or safety
device and shall not be routed via any intermediate junction,
marshalling box, cabinet, relay, etc. The other sheaths of such
cables shall be coloured orange. Other circuits may, subject to the
provisions of the above paragraph, be grouped in multipair cables.
Terminals and glanding facilities shall be provided in junction boxes,
marshalling boxes, switchgear, etc. as appropriate.
Cable tray shall be of the heavy duty, return flange perforated type,
fabricated out of electrogalvanised steel sheet and polyester power
coated.
above 300 mm
to 600 mm 2.0 mm 800 mm
The height of the return flange shall not be less than 50 mm.
Page 37 of 72
than 25 mm. Where trays are tiered, clear access shall be available
to all trays, with minimum 300 mm separation between trays.
Arms and supporting channels for cable trays shall be hot dipped
galvanized and shall be mill strut or approved equal. Fixings for cable
trays shall be disposed at regular intervals specified and not more
than 200 mm from bends to fix together adjacent sections of cable
trays and/or accessories.
7.3.3 Conduit
Page 38 of 72
Particular care must be taken to ensure that no water is allowed to
enter the conduit at any time and all conduits shall be arranged with
adequate ventilation and drainage where necessary as directed by
the S.O. Inaccessible junction boxes will not be allowed.
Cables for drawing into conduit shall be single core PVC insulated,
non-sheathed, 1000 V grade and shall be supplied by an approved
manufacturer. Insulation shall be coloured to indicate phase and
neutral in accordance with the I.E.E. Regulations. Care is to be taken
in the number of cables in conduit and in no case shall conduits
enclose more cables than that set out in the I.E.E. Regulations. No
single conduit serving a single phase socket outlet, lighting point or
Page 39 of 72
switch shall contain more than one phase. Switch wires shall be white
in colour.
All conduits before painting shall be washed with I.C.I Litho form or
approved material and shall then be primed with an approved
chromate primer followed by one undercoat and two coats of
approved gloss finish for general areas. In chemical building and
other corrosive areas such as chlorine building, the undercoat and
top coats shall be resistant to corrosion.
7.3.4 Trunking
Trunking shall only be used with the written consent of the S.O., where
large multiple parallel conduit runs occur.
The Contractor shall ensure that the size of the trunking is adequate
for the number of cables passing through it, but as a minimum the
size should be 50 mm x 50 mm. All bends, tees and intersections shall
be of the gusset type and manufactured by the maker of the trunking
and to a similar standard. The trunking shall be fixed to the ceilings
by means of a secure and permanent fastening to be approved by
the S.O.
Page 40 of 72
Trunking shall be supported at intervals not exceeding 2 metre
horizontally of 2.5 metre vertically.
Cover plates shall be supplied in short lengths for easy removal. Every
entry to finished trunking shall be so placed as to prevent the ingress
of water. Cover plates shall be securely fixed after wiring is
completed.
For cables containing termite repellents, the drums shall bear a label
on the outside, warning that gloves shall be worn when handling the
cable.
The exact location of each cable trench will be settled on the Site by
the S.O. when the Contractor is ready to commence work.
Page 41 of 72
Before the cables are laid, the bottom of the trench shall be lined
with sand to a thickness of 150 mm to form a bed. After the cables
are laid, the first 150 mm depth of cover backfill shall consist of sand,
over which shall be placed protective covers.
After all cables and protective covers have been laid, the trenches
shall be refilled in 150 mm layers, each layer being well rammed and
consolidated.
The Contractor shall include for all materials and labour to reinstate
the ground to the same condition prior to excavation i.e turfing,
drains and roads, etc.
If an existing cable lies along the route, the Contractor shall generally
avoid excavating the existing tiles. If it becomes inevitable to move
the cable, the same shall be done after seeking permission from S.O.
Page 42 of 72
7.5 Cable Protective Covers
Page 43 of 72
vi) Position of earth electrodes, earth rods disconnecting
chamber and interconnecting earth tapes
x) Load rating in KW
Page 44 of 72
8.0 EARTHING SYSTEM
The earth resistance value measured at the Main Earth Bar shall not
exceed 1 ohm. The earth connections for all sections of each
installation shall be continuous throughout. Each individual earth
systems shall achieve its required earth resistance value before being
interconnected with other earth systems.
The main bonding cables shall not be less than 10 sq. mm and
supplementary bonding of non-electrical plant not less than 6 sq.
mm. All connections shall be made using compression type cable
lugs, taped on completion to completely seal the lug and any bare
copper from the atmosphere.
Page 45 of 72
The earth network conductor comprising tinned copper tapes
and/or cables shall be securely supported and clamped in a neatly
spaced manner on building structures, cable trench walls all on
cable trays, and neatly run vertically, horizontally, parallel to
adjacent walls, ceilings, beams, etc. appropriate. The earthing
installation shall be protected from any mechanical damage or
corrosion.
A main earth bar (complete with test links) shall be installed in any
convenient location preferably in cable trenches 600 mm above the
finished floor level. The main earth bar shall comprise a high
conductivity copper bar supported on porcelain barrel type
insulators and wall mounted. The earth bar shall be of sufficient length
to accommodate bolted copper tape/cable connections to:
- The earthing conductors between the earth bar and the earth
electrode
- Circuit protective conductors between the earth bar and
exposed conductive parts
- Main equipotential bonding conductors between exposed
and extraneous conductive parts
- System neutral earthing conductors
Earth studs shall have a minimum size of M8. The main earth
conductor shall also be provided with adequate number of spare
terminals including cable lugs, bolts, etc.
The size of earth continuity conductors shall be as follows:
Page 46 of 72
Earthing tape connection shall be run in approved positions and
fixed in an approved manner generally in square and symmetrical
lines using gun-metal saddles of appropriate size for securing tapes
at intervals not exceeding 900 mm. The copper tapes shall be
supplied in long unbroken lengths to avoid unnecessary jointing.
8.4 Joints
Bar to bar tee joints and tape to tape joints (for underground
connections) shall be of ‘Furseweld’ or ‘Cadweld’ method to the
approval of S.O. All earthing tape connections to electrical
apparatus shall be made by using a bolted connection in a visible
and accessible position. Before the connection is made, the tape
surfaces shall be tinned.
8.6 Electrodes
Page 47 of 72
driving heads and connector clamps. The rods shall have an
electrolytically bonded layer of copper of not less than 0.38mm
thickness. The Contractor shall determine the length and number of
electrodes required for each earthing, after the resistivity of the soil
at the particular location has been measured at site and witnessed
by S.O. The electrodes shall be interconnected by means 25mm x
3mm tinned copper tape laid at a depth of 750mm below ground
level.
Page 48 of 72
8.9 Excavation of Trenches
The works shall also include for testing of all earth electrodes to the
satisfaction of the S.O. The test instruments required for the tests shall
be provided by the Contractor.
Earth resistance testing shall also be carried once in the driest period
or any time which is deemed suitable by the S.O. during the Defects
Liability Period. Should the earth resistance value be less than the
specified value, the Contractor shall install additional earthing points
in order to achieve the specified value. The Contract Rates shall be
deemed to have taken into account the additional earthing points
required and there shall be no claims for cost in this respect.
Page 49 of 72
9.0 LIGHTNING PROTECTION SYSTEM
9.1 General
9.2 Power Lines Surge Protector for Main Incoming Supply (Category 1)
The power line surge protection for the Main Incoming Supply shall
be rated at 40kA (8/20µs) per conductor with per phase rating of
80kA (8/20µs). The unit shall be tested to 20kA (8/20µs) suitable for
robustness and suitable for severe lighting environment. The
protector must provide reliable protection status indicator of
electronic type for each phase.
The Protector shall be full mode with line to neutral, line to earth and
neutral to earth protection. The let-through voltage shall be less than
750Vrms when subject to 3kA (8/20µs) waveform or less than
1,200Vrms when subject to 20kA (8/20µs) waveform.
Page 50 of 72
differential mode (L-N, L-E). To avoid from component expulsion due
to overvoltage the protector shall be metal encased.
The protector shall come with fast responsive Metal Oxide Varistors
(MOV) to provide low let-through voltage to protect the sensitive
electronics and electrical circuits.
9.3 Power Line Surge Filter for RTU and Instruments (Category 2)
A power lines surge filter capable of carrying the full load current shall
be installed in series at the incoming power supply toward the final
circuit to the RTU and instruments in order to deliver efficient
protection against transient over voltages.
The surge filter shall be rated for 220-240 VAC, 50Hz, single phase, 10
Amps running current at 45 degrees C ambient, 0-90% working
humidity. It shall have minimum surge rating of 40kA (8/20µs) per
conductor. For the solar panel installation, the surge filter shall be
rated for 24V DC at 2 Amps running current.
i. Phase to Neutral
ii. Phase to Earth
The surge filter ‘let-through’ voltage in full mode must not exceed
600V when tested to 6kV (1.2/50µs), 3kA (8/20µs) test waveforms. It
shall have a reliable visual indication and is recommend to be
Page 51 of 72
housed in metal enclosure to prevent any package rupture or
expulsion of the Metal Oxide Varistor in the event of overload. The
protector shall be installed as near as possible to the equipment to
be protected to endure its effectiveness. It must have visible indicator
and dry contact to RTU to indicate it healthiness. The contact must
be connected to RTU for remote indication.
The surge filter shall specifically be designed for lightning and surge
protection on power lines. It should have 5 years manufacturing
defects from the manufacturer and has ISO 9002 certificate. The
surge protection should be provided with test report from local
independent bodies.
9.4 Signal Lines Surge Protector for Data Transmission and Control System
The protector for data lines shall be able to provide protection in all
mode or full modes i.e. line to line and line to earth. The peak transient
‘let-through’ voltage shall not exceed twice its normal operating
voltage when subject to a test conducted in accordance to
AS1768:2007, BS 6651:1999 Annex C and IEEE C62.41:1991 location
category C and ITU (formerly known as CCITT IX K17) 10/700µs signal
lines test waveform. The protector shall have a peak surge rating of
20 kA on 8/20 microsecond wave shape on each protected wires.
The protector shall be series, in-line devices and shall have separate
plug and base design with provided facilitates ease of module
replacement. To avoid earth loops that can potentially interrupt the
low noise signal in the instrument, the connection between the base
of the protector and the earth terminal shall be separated with high
energy Gas Discharge Tube (GDT). The GDT will only allow
equipotential bonding under surge condition.
Page 52 of 72
The protector shall be particularly designed to divert transients on
long-lines, high exposure lines and lines susceptible to power lines
and lightning induction. Thus, the overall transient protectors (cap
and base together) shall be a multistages design in order to provide
low let-through voltage.
9.5 Earth Conductors for the Power & Signal lines Surge Protection
Earth wires terminate at the all the power lines surge protectors shall
be at least 10 mm² in diameter. For all signal lines surge protectors
shall be at least 4.0mm² diameter. They shall be laid alongside
incoming cable pairs (dirty lines) and kept away or as far as possible
from equipment side cable (clean lines).
Page 53 of 72
10.0 OTHER COMPONENTS
Page 54 of 72
The number of different contact configurations on relay shall be kept
to a minimum even if some relays have unused contacts, to assist in
keeping spares stock to a minimum.
10.3.1 General
Page 55 of 72
Each pole shall be provided with ambient temperature
compensated bi-metallic thermal element for inverse time
delay protection and magnetic element for short circuit
protection. Where switching of neutral is required and for DC
circuits, the MCB shall be of double-pole type.
Page 56 of 72
11.0 INSTRUMENT PANEL
The instrument, local control and supervisory panel complete with all
associated equipment and terminal rack, etc shall generally be free
–standing floor-mounted cabinets of the cubicle.
Material shall be from mild steel sheets with 2mm minimum thickness
on walls and inside compartments. It shall be treated with phosphate,
primed and finished with coats of beige color polyester powder paint
to RAL7032 and shall be more than 80 micron of thickness.
Page 57 of 72
Outdoor panel shall have a non-flat roof type with angle more than
90 degree. All outdoor panel shall be installed with security features
illustrated in Figure 7© below.
Goup 1 : Power, control and very high level signal wiring (above
50V)
a) AC power supplies
b) DC power supplies
c) AC current signals above 50mA
d) AC voltage and control signals above 50 volts
Circuits supplied at 240V or above, between 240V and 110 VDC shall
also be segregated from each other and from other circuits. Access
to wiring and components of circuits having voltages exceeding
240V shall not be possible unless and until the circuit has been
isolated.
All wiring shall neatly and securely fixed by insulated cleats, bunched
and secured by approved plastic strapping, or run in approved
insulated wiring trunking or non-corrodible flexible tubing. Wiring for
future equipment shall be secured and terminated on the terminal
blocks. Inter-section wiring in multi-section cabinets shall be via a
terminal block in each section.
Page 58 of 72
Terminal blocks for analogue current signals shall permit the insertion
multimeter test leads without disconnecting any wiring.
Each row of terminal blocks provided shall contain at least 25% spare
terminals over the number required for terminating all cores of
external cables in that row. All spare cores of external cables shall
be terminated in the terminal block and labeled accordingly.
Small wiring used for extra low voltage and instrument signal
which are likely to be affected by interference shall be
screened and/or spaced from power cables to ensure no
distortion or mal- operation.
Page 60 of 72
11.3.2 Terminal Blocks
Terminal blocks for control wiring shall clamp the wire securely
and without damage between two plates by means of a
captive screw or by means of cage clamp. Terminals for
incoming and outgoing power connection shall be of the
bolted type with brass nuts and locknuts, each core being
fitted with a suitable lug.
Page 61 of 72
11.3.3 Cable Terminations
All cable boxes, glands, gland plates and all other apparatus
necessary to terminate all incoming and outgoing power and
control cables shall be provided. Non- magnetic gland plates
of not less than 6 mm thick shall be provided where single core
cables are terminated. For cable sizes 400 sq. mm above,
insulated cable glands shall be fitted.
Page 62 of 72
PVC TRUNKING
PVC TRUNKING
RTU & MODEM
COMPARTMENT
PVC TRUNKING
COMPONENT
PVC TRUNKING
CONTROL DC COMPONENT COMPARTMENT
COMPONENT COMPARTMENT 1
COMPARTMENT
PVC TRUNKING
PVC TRUNKING
AC SOCKET
TERMINAL BLOCK
(OPTIONAL)
BATTERY
CHARGER
COMPARTMENT ELECTRICAL
COMPONENT
COMPARTMENT
2
BATTERY
COMPARTMENT INCOMING /
OUTGOIING
CABLE
CONCRETE BASE
MOUNTING
10 cm 15 cm
TOUCH PANEL
SWL SWL RES RES SWL RES
HIGH LOW HIGH LOW OVF OVF
15 cm
SWL OUTP RES HMI TOUCH
0.00 M 0.00 M 0.00 M
PROTECTED
PANEL
STEEL BOX
INP OUTF1 OUTF2 2 NOS VERMIN PROOF
0.00 M 0.00 m3/H 0.00 M VENTILATION LOUVERS WITH
WIREMESH ON INTERNAL FACE
AND WEATHERPROOF COVER
ON EXTERNAL FACE
15 cm
HMI TOUCH
15 cm
PANEL
PROTECTED
STEEL BOX
10 cm 15 cm
15 cm
20 cm
STEEL BAR
Page 64 of 72
20 cm
STEEL BAR
CLEAR
WINDOW FOR
10 cm 15 cm
TOUCH PANEL
15 cm
RES RES
0.00 M HIGH
HMI TOUCH
PROTECTED
PANEL
OUTF2 RES STEEL BOX
0.00 M OVF 2 NOS VERMIN PROOF
VENTILATION LOUVERS WITH
WIREMESH ON INTERNAL FACE
AND WEATHERPROOF COVER
ON EXTERNAL FACE
15 cm
HMI TOUCH
15 cm
PANEL
PROTECTED
STEEL BOX
10 cm 15 cm
15 cm
20 cm
STEEL BAR
Page 65 of 72
12.0 DEVELOPMENT
a) Level instruments
b) Pressure instruments
c) Flow instruments
Page 68 of 72
e) All alarms and trips shall be tested by operation of the
primarily initiating device.
Page 69 of 72
correct display on the existing visual display and
logging equipment.
12.3.1 General
Page 70 of 72
12.3.2 Spare Parts
Page 71 of 72
(This page is intentionally left bank)
Page 72 of 72
Technical Specifications
Section D: Overhead Crane System
1.1 General
All sales taxes, import duties, permits and inspection fees payable to all authorities,
overtime payments and all other charges and costs necessary to complete the
installation within the time schedule shall be included in the Quotation. All equipment
and accessories to be supplied shall be fully tropicalized and shall be designed to
give full operation of the crane system as intended.
Tenderers shall note that the Specification and drawings are intended to set out the
basic and minimum requirements for the installation. Although equipment offered
shall not differ in basic type from that called for in the specifications, tenderers may
offer equipment which they consider both fulfill the basic requirements of the
Specification and also provides additional benefits in the form of greater ease,
simplicity or safety of operation or longer working life of the equipment provided no
other qualities are sacrificed to gain such benefits.
The design, calculation, manufacture, installation and testing of the system shall be in
accordance with the best engineering practice, the latest relevant Standards and shall
comply with the latest Rules and Regulations of :
4. The relevant Malaysian Standards, British Standards (BS 2573 , BS 466) and
other Standards approved by Local Authorities
The crane steel structure shall only be fabricated by the crane manufacturer with
Crane Fabrication License issued by Jabatan Keselamatan dan Kesihatan
Pekerjaan (JKKP).
Page D / 1
Technical Specifications
Section D: Overhead Crane System
Crane girder shall be designed to A4 as per BS466 1984. The maximum allowable
deflection shall be span/750.
Crane girder shall be double girder type and welded from steel plates to form boxes.
The design as regards to safety clearances, railing etc. are in accordance with
specified safety regulations of the local authority.
Maintenance platform with hand-rail shall be provided along one side of the girder for
maintenance platform. Platform shall be provided with toe plates having a minimum
height of 100mm above floor level. These shall have a minimum thickness of 6mm
and shall not be fixed to the floor.
End carriage shall be welded box design. Wheel base shall not be less than span/7. It
shall be designed so that the weight of the crane and its load is equally distributed
between the carriage wheels. The end carriages must be equipped with buffers at the
four ends.
Wheels shall be spheroidal graphite cast iron GGG70 which is low wear material due
to self-lubricating. All wheels are with anti-friction bearing and easy to change.
End carriage must be equipped with Limit Switch for long travel. In addition, anti-
collision device shall be provided for preventing the collision with the existing crane at
the same bay.
Travel motor shall be direct coupled to the driven wheels. Open-pinion drive is not
allowed. The travel motor shall be classified in FEM 4m and travel wheel shall be
classified to FEM2m.
1.7 Hoist
The hoist shall be electric driven wire rope hoist with modular design made of
standard series components. The individual components are optimally matched. The
hoist duty class shall be FEM 2m.
Hoist motor shall be 3-phase A.C. squirrel-cage induction motor, 4 poles, with
cylindrical rotor and low flywheel mass, classified in group FEM 4m to FEM 9.682.
The motor shall ensure reliable starting even at under voltage and with high hoisting
Page D / 2
Technical Specifications
Section D: Overhead Crane System
load and shall directly coupled to the gearbox without using coupling. The motor shall
be installed outside the wire rope drum for easy maintenance and better ventilation.
The motor shall be designed for heavy duty, 60% ED and 360 starts/hour, minimum
S4 duty high protection class IP 55 and temperature control with thermistor
temperature sensors to guard against overloading/overheating of motor.
Manual release shall be provided so that the breaking system can be released
manually in the event of failure in power supply.
The motor brake shall be twin-disc magnetic disc brake encapsulated and has
asbestos-free brake lining with long service life of at least 1-2x106 braking operations.
Standard protection class IP55 to be supplied.
1.7.3 Gear
The gear shall be maintenance-free gear complete with enclosed housing with
highest accuracy and stability, gearing with high degree of flank hardness optimised
after hardening by honing (high service life, low noise). Lifetime oil lubrication is to be
provided.
Designed for high safety and long service life, highly flexible special bright wire rope
or special galvanised rope, according to DIN 3063 and DIN 3067 with safety factor of
5.0 shall be supplied with the hoist. The hoist drum shall have fine machined drum
grooves to minimise wear on the rope. The return sheaves shall be resistant to wear.
Robust bottom hook block with low headroom, hook in forged ST52 steel shall be
provided.
Extremely wear-resistant rope guide in spheroidal graphite cast iron, high resistance
to diagonal pull shall be incorporated in the hoist drum and it shall not have
temperature limitations in its service life. No plastic material shall be used as rope
guide.
The wire rope drum of the hoist shall be supported by anti-friction bearings of
standard type readily available from the market and they shall be the greased-for-life
type. The inner and outer races of the bearings shall form integral part of the bearings
and in no way shall the outer surface of the wire rope drum be used as inner race of
the bearing.
Reliable overload cut-off device shall be provided. Overload cut-off shall be electronic
device type and load measurement shall be taken at rope anchorage via load sensor.
Gear-type limit switch shall be provided as emergency hoist limit switch for cut-off in
top and bottom hook position. In addition, a further two switch elements are to be
installed to act as the operational hoist limit switch.
Page D / 3
Technical Specifications
Section D: Overhead Crane System
1.9 Crab
The crab for the cross travel of hoist shall be designed to FEM standards.
The crab must equip with Limit Switch for cross travel. The crab shall cut off at both
ends of travels.
The material of the travel wheels shall be Spheroidal Graphite Cast Iron which
provides a self-lubricating effect to the rail surface.
Driven motor shall be direct coupled to the driven wheels. Open-pinion drive is not
allowed.
The travel motor shall be classified in FEM 4m, S4 duty and travel wheel shall be
classified to FEM2m.
1.10 Control
The control of the crane shall be by Pendant Station Mobile Along Crane Bridge. The
pendant shall comply the following features:
Control panels include main contactors, control transformer & control switchgears
shall be fitted on the crane girder.
Control panel for hoist and cross travel shall be fitted to the hoist unit. All control
panels shall be IP55 protection.
The following speeds shall be followed unless otherwise specified on the tender
drawings.
1.12 Motors
All motors must classified to minimum FEM 4m, S4 duty and 60%ED. Motors shall
have insulation class F and equipped with thermistor temperature sensors to guard
against overloading/overheating of motor.
Hoist power supply shall be via flat cable festoon system. All the cable carriages shall
be galvanised steel type. No plastic material is allowed.
Page D / 4
Technical Specifications
Section D: Overhead Crane System
The power supply feeding shall share with the PVC insulated 4 pole conductor
system. Current collector trolley for crane mobile power feeding shall be suitable and
able to fix to the conductor system.
The crane and hoist shall be designed to minimise noise. The overall noise level for
this equipment shall not exceed 85dBA at 1 meter distance.
END OF SECTION
Page D / 5
Technical Specifications
Section E: Air Conditioning and Mechanical Ventilation
Coils
Housing
Fans
Motors
Corrosion Protection
Page E / 1
Technical Specifications
Section E: Air Conditioning and Mechanical Ventilation
Control Cabinet
b) Refrigerant dual pressure switches with manual reset on high pressure cut out.
2.0 Fans
2.1 General
Fans shall be of the type, size, arrangement and capacity as indicated in the
schedule and/or as shown on the drawings.
Fans and motors shall be selected to provide air flow rates of 10% more than that
specified against the corresponding increase in system resistance.
All motor/impeller rotors shall be satirically and dynamically balanced to International
Standard I.S.O. “Balance Quality of Rotating Rigid Bodies” and shall be free from
vibration at all operating speeds and during starting and stopping cycles.
Fan motors shall comply in all respects with the “Motors” clause in the section on
Electrical Works of this specification. Motor bearings shall be of the ball or roller type,
sealed for life or grease packed fitted with lubricant retaining and dust excluding seals
extended through the casing, and shall be selected for an operating life or not less
than 150,000 hours.
Fans shall not be operated in a partially completed system for any purpose whatever
and before start-up, all connected ductwork and equipment must be cleaned.
Page E / 2
Technical Specifications
Section E: Air Conditioning and Mechanical Ventilation
3.1 General
This section of the specification covers the supply and installation of the electrical and
control requirements for the air-conditioning and mechanical ventilation services.
All controls shall be adjusted as necessary to achieve satisfactory operation of the plant
in accordance with the intent of this specification and to approval.
Where vibration is present, all materials, equipment, components and devices which
could be affected by vibration shall be protected in an approved manner.
Supply and install the complete electrical installation as required for satisfactory
operation, control, maintenance and safety of the air conditioning plant and mechanical
ventilation systems, under all conditions of service and suitable for the working
environment.
In summary, the works to be supplied and installed shall include, but not necessarily be
limited to, the following items and equipment:
(a) All control wiring and connections between the switchboards, thermostats,
control valves and the like.
(c) Supply of "as built" drawings prior to the issuance of a Certificate of Practical
Completion.
END OF SECTION
Page E / 3
Technical Specifications
Section F: Fire Protection
1.1 General
The clean gas systems shall be in accordance with the rules and regulations of
National Fire Protection Association (NFPA 12) and (NFPA 2001) or other relevant
standards as may be approved by the S.O.
The manufacturer from the country of origin shall guarantee the performance and
selection of the components of the complete carbon dioxide extinguishing system and
complying with the specification and relevant codes.
Generally, the clean gas systems shall consist of but not limited to the following: -
(i) Cylinders of gases complete with discharge valves and discharge cables.
(ii) Manual discharge breakglass device.
(iii) Schedule 40 and 80 pipes complete with fittings, brackets and painting.
(iv) Gas discharge nozzles.
(v) Smoke and heat detectors for detection and actuation of the system.
(vi) Wiring in metal conduit.
(vii) Control panel complete with battery charger, booster charger, 24 V.D.C. Ni-Cd
battery, alarm bell, gas discharging system, ammeter, voltmeter, function
indicators and alarm test switches, etc. The control panel must be approved
by the Jabatan Perkhidmatan Bomba Malaysia.
(viii) Any necessary warning signs and instructions.
(ix) Red and green flashing indicator lights.
Page F / 1
Technical Specifications
Section F: Fire Protection
Page F / 2
Technical Specifications
Section F: Fire Protection
2.1 General
Contractor shall supply and install the Portable Fire Extinguishers as shown in the
drawings. All materials shall be new and unused, be of best quality of items
respective kind, free from defects and approved for use by the Chief Inspectorate of
Fire Services, Malaysia.
It shall conform to M.S. 1179, M.S. 1180, M.S. 1181 M.S. 1182 and approved by Fire
Officers Committee.
Fire Extinguishers shall be supplied fully charged and with mounting brackets.
Page F / 3
Technical Specifications
Section F: Fire Protection
Carbon dioxide shall be capable of extinguishing Class E fire and conform to B.S.
3326. It shall be supplied with horn, hose and valve assembly.
2.4 Details
Full details of the fire extinguishers installed shall be attached to each of the
extinguisher and a complete list given to the Owner on the day when the certificate or
practical completion is issued. Details required are:-
The above information will also be required to be displayed at each of the installed
fire extinguishers.
2.5 Approval
All portable extinguisher shall be tested and bear the certificate of approval by the
Jabatan Bomba Dan Penyelamat Malaysia. All fees in connection with testing and
approval shall be borne by the Contractor.
3.1 General
This section of the specification covers the supply and installation of the electrical and
control requirements for the fire protection services.
Supply and install the complete electrical installation as required for satisfactory
operation, control, maintenance and safety of the fire protection equipment under all
conditions of service and suitable for the working environment.
In summary, the works to be supplied and installed shall include, but not necessarily
be limited to, the following items and equipment:
Page F / 4
Technical Specifications
Section F: Fire Protection
1. All final power circuits between the switchboards and the various plant
components, including connections to boards and equipment.
2. Fire alarm panels and all control wiring works between the panel and field
devices.
3. Fire alarm signal wiring to the air-conditioning and mechanical ventilation services
switchboards and DDC system for fire mode operation.
4. Clean gas alarm panels and associated wiring.
5. Testing and commissioning of the entire installation.
6. Supply of “as-built” drawings prior to issue of a Certificate of Practical
Completion.
END OF SECTION
Page F / 5
Technical Specifications
Section G: Cold Water
Page G / 1
Technical Specifications
Section G: Cold Water
All piping shall be of the best available quality and shall be supplied in clean full standard
straight lengths, free from any defects such as mill scale, rust, burns, dents, kinks, etc.
and with all ends sealed against the ingress of foreign matter and protected against
mechanical damage. All piping shall be kept in a clean condition at all times during
storage, fabrication, installation and testing.
1.2 Installation
All piping shall be run generally parallel to the axes of the building as close to the ceiling
or other construction as practical and free of unnecessary traps or bends. Bending or off
setting of finished piping connections and “cooking” of fittings or trim will not be permitted.
No pipes shall be installed so as to cause an unacceptable noise under normal
operations. If such a noise does occur, then the Sub-Sub-Contractor will alter the pipe
work as necessary and as directed by the Engineer.
Install piping clear of all doors, windows, access spaces, service areas, etc.
Where immersions thermostats or thermometer bulbs are installed in small piping, the
pipe shall be at least one size larger than the main straight run.
All cut pipes shall be reamed and filed to remove burrs.
All ends of pipes shall be capped with metal or PVC caps, or if not screwed, with wooden
plugs. Any other method will not be accepted.
Supply and install of all vents, stacks and other piping passing through the roof or walls a
stack counter flashing fitting, consisting of a overlapping coupling, caulked to the pipe
with poured lead, or screwed to the pipe with a water tight joint. The couplings shall
extend over a cylindrical flashing sleeve and be made watertight with Permaseal, or
similar compound.
Cover flashing shall be brazed all around and shall lap over the flashing a minimum
distance of four inches.
END OF SECTION
Page G / 2
Technical Specifications
Section H: Painting & Identification
1.1 General
This section of the specification covers the painting and finishes requirements
pertaining to the installations covered by this specification.
Painting shall be carried out by capable and skilled tradesmen under the direction of
a competent painter foreman and under conditions that will not mar the finish. Paints
shall be applied evenly and strictly in accordance with the specific recommendation of
the manufacturer and on correctly prepared surfaces. Brushes, paint containers and
all other painting accessories shall be kept clean and in good condition at all times.
Where necessary, finished paintwork shall be protected during the progress of site
works by suitable dust covers.
Factory assembled steel components and pre-fabricated metal parts shall be painted
before dispatch with a good coat of zinc chromate or other anti-corrosive primer to
provide adequate protection against the action of dampness and weather during the
transport to site and subsequent erection.
Materials for site fabrication such as piping rolled steel sections and sheet metal shall
be supplied unpainted and primed after fabrication as necessary for protection
against corrosion.
Paint with first quality materials as specified in this section of all parts of the
installation covered by the work of this contract to approval.
The work shall include painting of all exposed work, equipment and machine bases,
supports and the following items but excluding normally bright and polished metal
components.
1.3 Material
Paints, fillers, temporary surface dressings and all other painting materials shall be
the products of an approved manufacturer and of the best quality in their respective
types. All painting materials shall be delivered to site in the original manufacturer's
sealed and labelled containers.
All paints shall be such that if applied in strict accordance with specific instructions of
manufacturer the finished surfaces will remain of true colour, will not fade, tarnish,
peel or otherwise deteriorate for a minimum of three years.
All sealers, primers, undercoats and finishing paints shall be of the type specified by
the manufacturer as appropriate for the particular application. Sealing compounds
shall be approved proprietary fillers.
Page H / 1
Technical Specifications
Section H: Painting & Identification
Equipment supplied in a factory finished condition will be acceptable provided that the
finish is of high standard, acceptable in colour, and does not require extensive
touching up. Otherwise factory finished equipment shall be cleaned, wire brushed and
painted on site with not less than two coats of approved finishing paint.
All other equipment and metalwork shall be painted with one coat of zinc chromate or
similar approved metalwork primer and two coats of full gloss enamel paint of the
specified colour.
All galvanised steel surfaces shall be cleaned of all oil and other protective coatings
used in manufacture and given one complete coat of approved type etching primer
before applying the finishing coats as above.
All pipework including fittings and valves shall be cleaned and painted externally with
one priming coat and two finish coats.
The final coat of paint on each piping service shall constitute the basic identification
colour or ground colour of the service. In addition to the basic colour all pipes shall
have identification colours painted on in the form of bands of colours in and lettering
to approval.
Alternatively, proprietary self adhesive labels may be utilized provided that a sample
is submitted for approval prior to installation.
a) Identification
b) Sign Writing
All items of equipment such as exposed fans, air handling unit casings, and similar
items shall be labelled in accordance with the symbolism and equipment identification
used throughout this specification and drawings or otherwise to approval.
Page H / 2
Technical Specifications
Section H: Painting & Identification
Where specified all concrete bases for mechanical equipment and switchboards shall
be first treated with one coat of linseed oil putty or other suitable sealer and then
painted with two coats of approved synthetic emulsion paint.
Upon completion of painting the whole installation and the surrounding building
surfaces shall be thoroughly cleaned of all paint marks, grease, oil and dirt. Normally
bright metal parts of installation and all equipment identification plates shall be
polished to approval.
1.9 Labeling
Labels shall be attached using round head screws and glued to prevent distortion. On
valves, labels may be attached to hand wheels or spindles using key rings.
END OF SECTION
Page H / 3
Technical Specifications
Section J: Testing & Commissioning
1.1 General
This section of the specification covers the testing and commissioning requirements for
the works.
Provide all necessary competent personnel and equipment to carry out testing and
commissioning of the installations covered by this specification. Balancing and
commissioning shall be carried out by personnel trained in that task and preferably
holding appropriate recognised qualifications.
All tests shall be carefully pre-planned and scheduled to ensure that they are co-
ordinated with the work of other trades involved and that they are carried out in a safe
and efficient manner with the minimum of inconvenience to all concerned.
Where the work is being carried out in an occupied or partially occupied building,
responsibility shall be taken to advise the owners and/or management of the building
regarding the nature of the tests and co-ordinate with them to minimise any possible
hazards or inconvenience that may arise due to the tests. Notification shall be given at
least three (3) days in advance of carrying out any tests so that a representative may
observe the test.
All tests required by statutory authorities such as the Local Fire Authorities and Health
Authorities shall be carried out to prove that the systems operate to their satisfaction and
in accordance with the appropriate Codes and Regulations.
(a) Pressure and leak test all ductwork as outlined in "Ductwork, Air Outlets and
Fittings".
(b) Operate all air handling systems and fans with temporary filters installed.
Thoroughly clean out air handling units, filter chambers and air plenums.
(c) Thoroughly clean and flush out all water systems including all equipment which
forms part of and is connected to the systems.
Cleaning and flushing of pipework shall be carried out initially with coils and
valves by passed, in a power flush mode prior to cleaning of the equipment.
Flushing out shall be carried out using non-foaming detergent compatible with
the water treatment chemical used. A second flushing procedure shall then be
carried out using clean water only prior to final commissioning and chemical
dosing of the system. All strainers baskets shall be removed and cleaned out.
(d) Provide manufacturers' test certificates for all proprietary manufactured items.
(e) Test log sheets proposed to be used during the commissioning tests shall be
submitted for approval at least 1 week prior to the commencement of the tests.
Page J / 1
Technical Specifications
Section J: Testing & Commissioning
Allowable pressure drops must not exceed 5% of test pressure during the initial
pump-up and shall hold constant thereafter for the test period of minimum 24 hours.
Welded joints which leak shall not be caulked but shall be cut out and re-welded. Any
other work shall be replaced.
1.4 Commissioning
Carry out all commissioning tests necessary to put the systems into commercial use and
to approval before Practical Completion is granted. Each item of equipment individually,
each sub-system and each complete system as a whole shall be checked and adjusted
to the design duties and generally as follows:
All air systems shall be adjusted and balanced so that air flows at all points in
the system are within -0% to +10% of the specified flow rates.
Performance testing of the air systems shall be carried out with additional filters
or blanking plates installed to simulate the system operating conditions when
the air filters are 50% loaded.
In addition air distribution from supply air outlets shall be checked and adjusted
as necessary to ensure that the direction and "throw" of air is adequate for the
application, free from unacceptable draughts and generally uniform over the
face of each outlet.
Air flow adjustments shall be made in such a manner that pressure drops
through dampers at or near the faces of outlets are the minimum possible.
Pressure drops required for restricting flow rates in low resistance branches
such as short runs nearest to the fan shall be primarily achieved by means of
the dampers provided at branch take-off points at the main duct. Adjustable fan
drives, where provided, shall be used to obtain the correct air flow rates at the
minimum possible fan speed with the minimum use of the dampers in the
highest resistance run of ducting.
Outside return and relief air dampers where applicable shall be adjusted to
design air quantities at minimum and maximum positions and any intermediate
position.
For ceiling diffusers a discharge funnel of approved design shall be placed over
the outlets to direct all air in a downward direction to facilitate final
measurement and adjustment of the air flow rate. Pitot tubes or direct reading
voltmeters with pitot probes shall be used for measurement of air flow rates in
ducts where required and shall be based on the average of multiple readings at
Page J / 2
Technical Specifications
Section J: Testing & Commissioning
not more than 300 centres and not less than one reading per 0.1m2 of cross-
sectional area of the duct.
All pressure and flow actuated controls, relief devices, bleeds, vents and drains
shall be checked and proven to approval.
All temperature control valves shall be fully opened during balancing of water
flows. Final settings of all regulating valves shall be permanently marked in an
appropriate manner.
Any major adjustment necessary to water flow rate shall be made by partial
closing of pump discharge valves when such valves are suitable for throttling.
Valves used to regulate final blows to equipment shall be clearly and
permanently marked in the balance position.
(iv) Air pressure drops through all filter banks, coils, etc.
Page J / 3
Technical Specifications
Section J: Testing & Commissioning
The operation of all indicating lights and associated detector devices shall be
proved under simulated conditions. Detector devices that fail to operate
normally after two consecutive tests shall be rejected and replaced
All instruments and appliances necessary to complete the performance tests specified
shall be supplied for the duration of the tests.
Test instruments proposed for use during performance testing shall all be checked for
accuracy by the manufacturer or an approved laboratory.
Calibration certificates shall be provided for each of the instruments to be used prior to
the commencement of tests.
All instruments provided as part of the installation shall be checked and calibrated as
specified above and again after 6 months of normal operation. Any instrument which
will not hold calibration shall be replaced.
If any excessive noise is evident, noise level measurements shall be taken in selected
and approved locations.
Background noise levels during testing shall be below measured values by at least 6dB
in all octaves.
Copies of all data recorded during commissioning of the installation together with all
necessary inspection certificates from local authorities and appropriate manufacturer's
pressure test certificates and performance curves or tables for the following items shall
be provided.
(a) Chillers
(b) Fans
(d) Pumps
Page J / 4
Technical Specifications
Section J: Testing & Commissioning
Practical Completion will not be granted until all data, certificates and performance
curves etc. referred to above have been received and approved.
The following procedure shall be adopted prior to handing over the installation:
(a) All preliminary testing, checking, adjusting and balancing of the installation shall
be carried out before forwarding notification that the installation is considered to
have reached Practical Completion.
(b) After inspection, and when the Engineer is satisfied and agrees that the
installation is ready for handing over the plant shall be finally commissioned and
Installation Manuals together with post contract drawings shall be provided as
specified.
(c) Practical Completion will be certified only after the plant has been inspected
and approved and the above requirements fulfilled.
END OF SECTION
Page J / 5
Technical Specifications
Section K: Maintenance & Servicing
1.1 General
Routine maintenance and servicing shall be carried out for a period of 24 months (or
otherwise as specified in the Contract) from date of Practical Completion to the end of
the Maintenance and Defects & Liability Period.
Regular maintenance shall be carried out on a monthly basis and emergency service
shall be carried out on a 24 hour call out basis.
The Contractor shall check, maintain and service the equipment regularly for proper and
efficient functioning of the equipment and systems according to the maintenance check
list for each service, generally or as described in this section for the duration of the
Defects Liability Period.
The Contractor shall ensure that all required works is carried out by trained personnel
with the experience and qualifications as required by the relevant authority. These
personnel shall also be acceptable to the Engineer.
All routine maintenance work is to be carried out on site during the operation of the
plant. In case of unforeseen large work on individual aggregates, the Contractor shall
carry out certain works in his own workshop or elsewhere.
The following consumable items shall be supplied as necessary during regular service
and maintenance.
During the duration of the maintenance period, no parts of the system shall be altered or
modified in any way by the Owner without the knowledge and agreement of the
Contractor. Maintenance service as provided under the maintenance period shall not
include labour, expenses and material necessary to repair damage to the equipment
caused by accident or abuse or arising from acts of third parties or any force of nature.
Page K / 1
Technical Specifications
Section K: Maintenance & Servicing
i) The said routine maintenance service shall be rendered during normal business
hours.
ii) The contractor shall respond to all emergency calls and breakdown immediately
and endeavour to complete the remedial works within 24 hours basis all round
the year including weekend and public holidays.
iii) The duration of maintenance will be for twenty-four (24) months (or otherwise
as specified in the Contract) from the date of handing over to the end user.
Page K / 2
Technical Specifications
Section K: Maintenance & Servicing
a) Check all crankcase heaters, contactors, timers, holding relays, cut-off valves.
Adjust or replace as necessary.
b) Flow switches and thermostats shall be checked for correct operation.
v) Biannual Service
Check the performance of the complete air conditioning and mechanical ventilation
equipment.
i) Ensure that all portable extinguishers are in the 'as-built' positions and that
they are not damaged impaired, leaking or in discharged condition.
ii) Ensure that all clean gas cylinders are fully charged and that all seal wires
are intact. The Contractor shall test each clean gas system under simulated
alarm condition and ensure that all indications on the control panel and also
the control mechanism work accordingly except that the gas will not be
released. The 'actuation' shall be by triggering of heat and smoke detectors
provided in the room.
iii) Check all Ni-Cd batteries and ensure that the battery water is filled up to
predetermined levels and that the terminals are clean.
iv) Ensure that all the battery chargers and associated components are in good
working condition. The Contractor shall record the condition of each set of
batteries in the logbook after each inspection.
A quarterly report shall be submitted to the Owner stating the condition of the equipment
including associated motors.
A biannual report shall be submitted to the Owner stating the condition of the:
END OF SECTION
Page K / 3
Technical Specifications
Section L: Surge Vessel
(a) General
Each surge vessel shall be of the horizontally mounted cylindrically type with dished heads.
The vessel shall function to provide protection to the pumping facilities and pumping main against
the surges by limiting the pressure variation in the system to the minimum as caused by the
following:
i. Starting of pumps
ii. Normal and emergency stoppage of pumps
iii. Power supply failure
Each vessel shall be of butt-welded construction, amply proportioned and designed to withstand
separately or in combination the loads and forces exerted by:
The design, construction and testing of the vessel shall conform to the ASME Boiler and Pressure
Vessel Code, Section VIII Unfired Pressure Vessels. The vessel shall be approved by the local
authority. Corrosion allowance of 1.5 for the shell and the dish end shall be provided. The surge
vessel shall be internally and externally abrasive blast and lined with two (2) coats of non-toxic
epoxy and three (3) coats of epoxy paint respectively.
Surge vessel design calculations shall be performed with reputable design software and endorsed
by competent person then shall be submitted to consultant prior manufacturing of the vessel.
Manufacturer data report shall be furnished upon completion of fabrication and hydrostatic testing.
(b) Material
Steel plate for the pressure vessel shall conform to SA-516 Grade 70 to ‘Fine’ Grain Practice or
an equivalent steel having good notch toughness. Material for vortex plate, baffle plate, manhole
and so for the shall conform to that specified for the pressure vessel.
(c) Welding
All welding shall be in accordance with the current ASME Boiler for the Unfired Pressure Vessels.
All but welds shall be fully radiographed in accordance with the above code. Joints shall have a
maximum joint efficiency of 100% of that of the connecting plates. All the radiographs, including
location plans and interpretations shall be submitted to the S.O. for approval.
All nozzles necks, saddle supports, brackets and all other weld attachments shall be performed
with dye penetration test before hydrostatic testing. Certificates shall be provided to confirm the
result of shop fabrication procedures and welding test as required by the ASME specification.
Page L / 1
Technical Specifications
Section L: Surge Vessel
(d) Supports
Each vessel shall b adequately supported on fabricated steel saddles, permanently fixed to the
vessel and designed to withstand the maximum load imposed thereon. Vessel saddle support shall
be suitable for right anchorage to the concrete floor with stainless steel holding down bolts.
(e) Accessories
i. Access manhole at least 600mm in diameter shall be provided in the shell of the vessel at
top and bottom.
ii. The main pipework valves shall be as generally shown on the drawings, flanges of
pipework shall be in accordance with BS EN 1092 and shall be drilled in accordance with
details shown in Appendix 3.1 Section 3 of Specification.
iii. Two safety valves to BS 1123 or ASME approved spring-loaded pressure relief valve with
stainless steel trim, suitable for air and water services shall be calibrated with valid
certificate provided for each vessel. The calibrated safety valve shall be set relieve at
pressure in excess of the design pressure. The valve shall not be less than 50mm diameter
and shall be installed such that it is accessible from the access platform. A spare safety
valve shall also be supplied under the Contract.
iv. A lubricated plug valve of the 3-way, 2 port, 2 position type rated to at least the design
pressure shall be furnished in order to select either of the two relief valves to service.
Piping between vessel and relief valve shall be furnished.
v. A sight glass gauge shall be furnished with an isolating cock which shall be shut
automatically in the event of breakage of the gauge glass. The gauge glass shall be
protected with a metal surround with the sides and back painted matt white. The front shall
have 12mm thick transparent armored glass providing not less than 50mm wide clear view
of the glass gauge. The assembly shall facilitate easy dismantling for cleaning and removal
of the gauge glass.
vi. Pressure gauges of the Bourdon type 200m dial diameter shall be provided, contained in
black aluminum case with stainless steel trim and suitably graduated to suit the test
pressure rating of the surge vessels and calibrated with valid certificates.
vii. An orifice plate of stainless steel type 316 construction suitable for insertion between pipe
flanges shall be provided.
viii. Galvanised mild steel ladders with safety cage and maintenance platforms complete with
handrails for access manholes, electrodes, pressure gauges, sight glass gauge, safety
valves, controls valves and all other appurtenances required shall also be provided.
The control system shall maintain the water level in the surge vessels between two set
points (high water and low water level). Air is either released or pumped into surge vessels
to achieve this requirement.
Page L / 2
Technical Specifications
Section L: Surge Vessel
Each surge vessel shall be provided with six level electrodes set to the following pre-
determined levels:
Only one set of electrodes from one of the surge vessels shall be used at a time to control
all the surge vessels. A selector switch shall be provided within the starter board to choose
the duty set of electrodes.
The acceptable water level in the surge vessel during the pumping operation shall be
between the high water level and low water level.
When the water level in the surge vessel rises above ‘high’ level, the electrical motorized
compressed air supply valve shall automatically open to supply compressed air to surge
vessel. When the water level drops below the ‘normal’ water level, the electrical motorized
compressed air supply valve shall automatically close. The period of air changing shall be
limited to 30 minutes for all the surge vessels.
When the pressure in the receiver drops below the compressor cut-in setting, the duty
compressor shall automatically start and shall continue to run until the pressure in the
receiver rises to cut-out setting. The period of air changing shall be limited to 30 minutes
for the air receiver.
When the water level drops below the ‘low’ water level, a suitably sized control electrical
motorized valve shall gradually open to release the air within the vessel to allow the water
level rise. When the water level rises above the ‘normal’ water level, the control valve shall
automatically close. The noise generated from the air being released shall not exceed 80
dBA at 3 meters away. A silencer shall be provided if required to reduce the noise level.
A delay timer shall also be provided to prevent frequent opening and closing the air inlet
and air release valves during surges and starting of pumps.
The pumps shall be prevented from starting when the water level is at the ‘high-high’ water
level, or the ‘low-low’ water level and if more than one (1) surge vessel is out of services.
Under any of these conditions a ‘Surge Vessel Abnormal’ signal shall be sent to each pump
starter panel. Facilities to override the ‘Pump Start Inhibit’ during the above conditions shall
be provided via a ‘Surge Vessel Abnormal’ override switch mounted within the air
compressor starter board.
Each surge vessel shall be provided with a continuous water level monitoring system,
comprising of a differential pressure transmitter, vertical edgewise bar graph indicator with
digital display at the starter board and associated relays and cabling.
Each differential pressure transmitter shall be of rugged construction, suitable for the
application and;
Page L / 3
Technical Specifications
Section L: Surge Vessel
ii. Be capable of withstanding 100% overload (i.e. twice the pressure required for full
output) without sustaining damage.
vi. Have an accuracy within +0.5% of span, repeatability of within +0.2% of span and
dead band not exceeding 0.2% of span.
ii. Two isolating and one bypass valves for each transmitter.
The differential pressure transmitter for measuring the surge vessel water level shall have
the low pressure side filled to a reference level and a facility for topping up shall be
provided.
(a) General
The surge vessel provided shall be charged by the air compressor. The details of the two
(2) air compressor offered shall be provided by the tenderer as follows;
i. Manufacturer
ii. Type
iii. Speed
iv. Free air delivery
v. Delivery pressure
vi. Power absorbed
The contractor shall be required to supply and install the pipework, valves and fitting and
make the necessary connections to the air pipelines for air supply to the surge vessel.
Recharge time shall be less than 10 minutes.
All cabling, relays, contacts, etc. required for the air compressor power and control system
shall be included in the Contract Sum.
A complete compressed air generation and distribution system consists f air compressor,
compressed air storage tank, dryer, compresses air distribution pipework and compresses
air filter regulator, drain valve check valve and shut off valve.
Page L / 4
Technical Specifications
Section L: Surge Vessel
The compressed air distribution pipework shall be designed based in a ring-main air
distribution system in order to obtain even distribution of pressure at different points of the
system. Rigid piping such as galvanized iron pipes shall be used for the ring-main air
distribution system.
Shut of valve shall be installed at necessary locations such as usage point, T-connections,
etc. for sectional shut down and maintenance purposes.
Condensate and water drainage valve must be available at the lowest point of every
distribution ring to facilitate condensate discharge. The drain valve must be electrical driven
auto discharge type.
Pressure gauge or sensors for monitoring of air distribution pressure must be provided for
every distribution ring at the furthest point from the main header.
Compressed air filter regulator is essential for pre-setting the air pressure and the
prevention of condensate water into the control equipment at each sub-station connected
to the ring-main.
The size of the G.I. pipes for the header assembly shall be 25mm DN whilst the ring main
shall be 20mm DN HDG pipe.
For compressed air generation, a piston or screw type compressor is requiring. The
compressor must be of an oil free type with piston or screw operation principle to guarantee
an air-preparation without using oil.
The maximum output pressure of the air compressor must not exceed 10 bar, but as a
minimum it should be able to deliver up to 8 bar pressure. Each pneumatic network shall
consist of at least 2 air compressors (1 duty / 1 standby) with each air compressor having
the capability to operate the pneumatic network system independently. Both the air
compressor mist work under alternating conditions. The sizing of the compressor shall be
based on maximum run-time of not exceeding 10 minutes/hour and shall not be lower than
1 cycle/hour.
The air compressor must be complete with simple control where it is able to auto start while
the air pressure is lower than the preset value and auto cut off when the desired maximum
pressure is achieved.
Page L / 5
Technical Specifications
Section L: Surge Vessel
Standby compressed air stored in vessel / tanks is required as a buffer between the air
compressor and air supply network. Additionally, it works as a pre-separator for the
accumulating condensate. The average standby capacity of the surge vessel shall be of a
minimum of 2 hours supply to the pneumatic network.
The surge vessel shall be able to store compressed air with a pressure of up to 10 bar and
contractor is responsible for obtaining of the JKKP approval. Material for the surge vessel
shall be of welded steel with appropriate epoxy coating of minimum thickness 200 microns
to provide a guarantee of minimum service lifespan of 20 years.
Minimum test pressure shall be 1.3 x the nominal pressure. The surge vessel shall be
complete with the following equipment:
END OF SECTION
Page L / 6
ELECTRICAL SERVICES
GENERAL SPECIFICATION
Page 1
TABLE OF CONTENT
ELECTRICAL SERVICES
TECHNICAL SPECIFICATIONS
SECTION TITLE
PAGE 1
1.0 GENERAL
.1 DESCRIPTION
.2 WORK INCLUDED
.2 The electrical work shall be shown on the Shop Drawings to indicate the
general system arrangement and configuration. The work of this Division
shall include coordination with the work of other Divisions of the
Specifications and the Contract Documents so as to provide a complete
and operational system capable of being readily operated and
maintained, including approved rearrangement of the system and
equipment and rerouting of distribution services to enable the complete
system to fit within the confines of the allotted electrical spaces, all to the
satisfaction of the Employer's Representative or as directed by the
Employer.
PAGE 2
END OF SECTION
SYSTEM IDENTIFICATION
SECTION 18001
Page 1
1.0 GENERAL
1.1 DESCRIPTION
.1 Mechanical Division
.1 Valve Tags
.2 Piping Identification
.3 Equipment Identification
.4 Duct Identification
.2 Electrical Division
.1 HV panels
.2 DC Supply Systems
.3 Transformers
.6 Auxiliary Boards
.7 Marshalling Cabinets
.8 Motor Starters
Page 2
.18 Earth Bars, Earth Points/ Test Points and Earth Chamber
.19 Firestops
1.3 SUBMITTALS
.2 Shop Drawings: Submit valve tag chart - pipe, duct, equipment labels,
paint and colour chart.
2.0 PRODUCTS
Page 3
.4 All identification plates must be engraved and must be secured with rivets
or brass/cadmium plate screws. The use of Dymo type or the like is
unacceptable.
.1 Stencil system number and service (supply, return, exhaust) onto ducts at
strategic locations. Provide arrows to show direction of flow.
Page 4
Hanging or fixed to
ceiling
Fixed to wall
Fixed to wall
Page 5
Fixed to wall
Fixed to wall
Fixed to wall or
fencing or hanging to
shelter ceiling
Page 6
Fixed to wall
Hanging or fixed to
ceiling or fixed to wall
.4 Text font size and colour selection samples shall be submitted to E.R. for
approval. However, the minimum text size shall be based on reasonable
and acceptable viewing distance to E.R. approval as well as in
compliance with relevant and approved British Standard.
Page 7
ACMV SYSTEMS
Chilled Water CHWS N/A Pipe Band Dark Blue Black or
Supply Pipe White
Service
Identification
Text
Arrow
Chilled Water CHWR N/A Pipe Band Light Blue Black or
Return Pipe White
Service
Identification
Text
Arrow
Plant Rooms EA N/A Service N/A Black or
and Car Park Identification White
Ventilation Text
(Exhaust)
Arrow
Plant Rooms SA N/A Service N/A Black or
and Car Park Identification White
Ventilation Text
(Supply Air)
Arrow
Kitchen KEA N/A Service N/A Black or
(Exhaust Air) Identification White
Text
Arrow
Kitchen KSA N/A Service N/A Black or
(Supply Air) Identification White
Text
Arrow
Toilet TEA N/A Service N/A Black or
(Exhaust Air) Identification White
Text
Arrow
Toilet (Supply TSA N/A Service N/A Black or
Air) Identification White
Text
Arrow
Smoke Spill SSE N/A Service N/A Black or
(Exhaust Air) Identification White
Text
Arrow
Smoke Spill SSA N/A Service N/A Black or
(Make-up Air) Identification White
Text
Arrow
Air/Cond ASA N/A Service N/A Black or
(Supply Air) Identification White
Text
Arrow
Air/Cond AFA N/A Service N/A Black or
(Fresh Air) Identification White
Text
Arrow
SYSTEM IDENTIFICATION
SECTION 18001
Page 8
ACMV SYSTEMS
Air/Cond AEA N/A Service N/A Black or
(Exhaust Air) Identification White
Text
Arrow
Air/Cond ARA N/A Service N/A Black or
(Return Air) Identification White
Text
Arrow
Staircase SPA N/A Service N/A Black or
Pressurisation Identification White
Text
Arrow
Lobby LPA N/A Service N/A Black or
Pressurisation Identification White
Text
Arrow
FIRE PROTECTION SYSTEMS
Sprinkler Main SP Fireman Red Service N/A White To include
Pipes and Identification system
Risers Text stage code
Arrow
Sprinkler Drain SP-D Fireman Red Service N/A White To include
Pipe Identification system
Text stage code
Arrow
Sprinkler SP-T Fireman Red Service N/A White
Transfer Pipe Identification
Text
Arrow
Wet Riser WR Fireman Red Service N/A White To include
Main Pipes Identification system
and Risers Text stage code
Arrow
Wet Riser WR-R Fireman Red Service N/A White To include
Return Pipe Identification system
Text stage code
Arrow
Wet Riser WR-T Fireman Red Service N/A White To include
Transfer Pipe Identification system
Text stage code
Arrow
DOMESTIC WATER AND
SANITARY PLUMBING
Domestic CW-IN Blue Service N/A Black or BAND is
Water main Identification White required with
incoming pipe Text background
to Tank colour code for
Arrow ABS or other
plastic
polymer pipe
SYSTEM IDENTIFICATION
SECTION 18001
Page 9
application
Page 10
NATURAL GAS
Gas supply NG Yellow Service N/A Black or to
and service Identification Gas Malaysia
pipe Text requirements
Arrow
IRRIGATION SYSTEMS
Irrigation IW-IN N/A Pipe Band Dark Green Black or
Water main White
incoming pipe Service
to Tank Identification
Text
Arrow
Distribution IW-S N/A Pipe Band Dark Green Black or
Pipe for White
Irrigation Service
Water Identification
Text
Arrow
Page 11
Item Lettering
HV Cable Ladder 100mm
HV Panels 25mm
DC Supply Systems 25mm
Transformers 25mm
LV Main Switchboards, Motor Control Centres 25mm
and Automatic Transfer Switches
Distribution Panel boards 12mm
Auxiliary Boards 12mm
Marshalling Cabinets 12mm
Motor Starters 12mm
Fuse Disconnecting Switches / Isolators 12mm
Busbar Trunkings (Busways) 25mm
Feeder Cables 12mm
Cables Trunkings, Trays and Ladders 12mm
Flush Floor Trunking Systems 12mm
Switches and Socket Outlets 5mm
Standby Generators 25mm
Uninterruptible Power Supply System 25mm
Public Address System 25mm
Satellite Master Antenna System 25mm
Earth Bars, Earth Points/ Test Points and 25mm
Earth Chamber
Firestops 12mm
Ballasts (Greater than 415 volts) 12mm
Page 12
SERVICES SYSTEMS CONDUIT FACTORY PRE- BAND COLOUR HOT DIP GALVANISED
COLOUR PAINTED
ELECTRICAL Orange with Conduit Orange band and Cable Ladder, Tray and
(ESSENTIAL) Red band Red band Trunking
ELECTRICAL (UPS) Orange with Conduit Orange band and Cable Ladder, Tray and
Yellow band Yellow band Trunking
PA SYSTEM White Conduit White band Cable Ladder, Tray and
Trunking
SMATV SYSTEM Pink Conduit Light Blue band Cable Ladder, Tray and
Trunking
.6 Coloured bands shall be of painting type with etching primer and two coat
of approved type colour paint.
3.0 EXECUTION
3.1 EQUIPMENT
.2 Mask all labels prior to field painting of equipment. Labels that are
painted over will be replaced at no extra cost to the Employer.
3.2 DUCTWORK
Page 13
.1 One (1) band on which one name of the service with directional
arrow and text font size not less than 36mm height.
.2 Laminated control and circuit diagram shall be provided for all control
panels.
.1 Furnish and install an identification plate for each distribution panel board,
marshalling cabinet and TNB tariff metering kiosk labelled with the
identification indicated in the approved drawing / Contract Document.
Mount at the top of each board or cabinet.
Page 14
.1 Furnish and install identification plates for busbar trunkings labelled with
busbar trunking designations. Install at each busbar trunking in every
electrical closet, route changes and on straight horizontal runs at not
more than 15 metre intervals. Where busbar penetrates a wall, floor, etc.,
provide identification plate on busbar within one metre on each side of
wall, floor, etc.
.1 Furnish and install a red identification plate for each automatic transfer
switch. Labelling shall indicate the switch number, the load served, and
the sources of normal and standby generator power and the size and type
of cables (emergency and normal).
.1 Furnish and install an identification plate for each motor starter and those
in a motor control centre, etc. Labelling must indicate the motor served
and the source of supply.
3.13 SWITCHES
.1 Furnish and install an identification plate for each switch controlling loads,
which are not local to the switch. Labelling shall be as directed by the
Employer's Representative.
.1 Furnish and install an identification plate on each earth bar and earth
terminal. Engraving must indicate earth bar/terminals; functions e.g.
power riser earth, telecommunication earth and power transformer
neutral.
SYSTEM IDENTIFICATION
SECTION 18001
Page 15
3.15 LUMINAIRES
END OF SECTION
QUALITY ASSURANCE, INSPECTION, TESTING AND COMMISSIONING
SECTION 18002
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.4 Perform site tests and commissioning for all mechanical and electrical
equipment and plant
1.3 SUBMITTALS
.4 Quality Plan
PAGE 2
.1 British Standards
.2 IEC Recommendations
.3 Malaysian Standards
2.0 PRODUCTS
Not used
3.0 EXECUTION
.4 Quality Plan
PAGE 3
.6 Quality Plan and Manual shall be prepared by the Contractor for all items
and services to be supplied, after the Contract has been placed, but
before commencement of fabrication, and shall be subject to evaluation
and acceptance by the Employer's Representative before start of works.
.1 Quality policy
.5 Lines of communication
.6 Customer relations
.7 Laboratory facilities
.2 Contract Review
.4 Procurement Control
.5 Controls on Sub-contractors
.7 Production Control
QUALITY ASSURANCE, INSPECTION, TESTING AND COMMISSIONING
SECTION 18002
PAGE 4
.9 Controls of Non-conformances
.13 Records
.3 Product Checklists
.9 Pre-commissioning
.10 Commissioning
QUALITY ASSURANCE, INSPECTION, TESTING AND COMMISSIONING
SECTION 18002
PAGE 5
.14 Records
.4 Quality Plan
PAGE 6
.2 The Contractor's Q.C. Section shall liaise closely with the Employer's
Representative in charge of Quality Assurance / Quality Control, and to
whom it shall give fullest cooperation. It is the underlying principle of this
contract document that while the Contractor's Q.C. Engineer implements
the Contractor's quality programme, the adequacy and effectiveness of
that implementation shall be audited by the Employer's Representative at
Site whose recommendations on improving or maintaining quality shall be
acted upon promptly by the Contractor's Q.C. Section.
.1 General
QUALITY ASSURANCE, INSPECTION, TESTING AND COMMISSIONING
SECTION 18002
PAGE 7
.3 Guarantees
.4 Rejection
PAGE 8
.5 Sub-Contracts
.1 General
PAGE 9
.2 Material Tests
.3 Acceptance Tests
QUALITY ASSURANCE, INSPECTION, TESTING AND COMMISSIONING
SECTION 18002
PAGE 10
.4 Test Certificates
.1 Within 30 days of the completion of any test, three (3) sets of all
principal test records; test certificates and correction and
performance curves shall be supplied to the Employer's
Representative.
.3 When all equipment has been tested, the test certificates from all
Works and Site tests shall be compiled by the Contractor into
volumes and bound in an approved form complete with index and
four copies of each volume shall be supplied to the Employer's
Representative.
.1 Type tests are required on all equipment whether specifically noted or not
to prove the general design of the equipment in accordance with the
relevant acceptable Standards and the Contractor may submit test
certificates of tests, which have been carried out on identical equipment.
Notwithstanding any provision in a Standard, the Employer's
Representative shall have the right to accept or reject such certificates in
lieu of the specified type tests.
.2 The type tests prescribed shall be carried out at the Contractor's cost in all
cases where such certificates are not available or are rejected.
PAGE 11
.1 General
.8 The testing shall be carried out during normal working hours as far
as is practicable.
PAGE 12
.3 The Contractor shall provide all labour, materials and instruments and
other resources necessary for the use of the Employer's Representative
for checking, setting out of the Works, for the periodic measurement of the
works executed and for the aforementioned Site inspections and tests.
.5 The Contractor shall provide all erection check lists for the Works, copies
of which are to be provided to the Engineer after signing at each stage of
inspection.
.6 The Contractor shall record the results of the tests clearly, on an approved
form and with clear reference to the equipment and items to which they
refer, so that the record can be used as the basis for maintenance tests
by the Employer during the working life of the equipment. The required
number of site test result records shall be provided by the Contractor to
the Engineer as soon as possible after completion of the tests. Both the
Employer and his representative require this information before the plant
will be accepted for initial energizing.
PAGE 13
.1 General
PAGE 14
The date and place at which works cleaning will be carried out shall be
notified to the Employer's Representative at least two weeks in advance
for witnessing and inspection.
.1 Surface Condition
The metal surfaces shall be clean and free of mill scale, rust, dirt,
grease and any other deleterious matter.
Where metal surfaces are to. be painted the surface profiles shall
conform with the painting specification requirements.
Where this does not apply, surfaces shall have a surface texture
not coarser than Grade 80 abrasive paper.
.2 Abrasives
.1 General
.1 General
QUALITY ASSURANCE, INSPECTION, TESTING AND COMMISSIONING
SECTION 18002
PAGE 15
When all plant has been erected and lagged or at such other time
as may be agreed with the Employer's Representative for
subassemblies, the installation shall undergo a procedure for Site
cleaning in accordance with the requirements and associated
Schedules as specified herein.
All piping and vessel shall be flushed with air or oil, or steam or
deionised, distilled, potable or sea water, as deemed appropriate
by the Employer's Representative to remove loose debris.
Before any machine is run on Site, the oil systems shall have been
thoroughly cleaned and flushed. The complete system shall be
flushed, excluding such items as bearings and control valves etc.
Temporary strainers shall be incorporated in the flushing
arrangements to collect foreign matter and debris, and to indicate
when a satisfactory state of cleanliness has been achieved.
Once the strainer have appeared free from debris the circulation of
flushing oil shall continue for a further three hours, and the
strainers again checked to confirm satisfactory cleanliness of the
system. All flushing oil, temporary pipework, strainers, and any
other materials required for the Site flushing procedure shall be
supplied under this Contract. Both hot and cold flushing shall be
carried out.
.5 Inspection
At the end of the plant cleaning operations at Site the plant shall be made
available for inspection. In the even that the surfaces are not cleaned to
the Employer's Representative satisfaction such parts of the cleaning
procedure or agreed alternatives as are deemed necessary to overcome
the deficiencies shall be carried out at the Contractor's sole expense.
PAGE 16
.1 General
PAGE 17
.1 Contract title.
PAGE 18
.12 The Contractor shall remain fully responsible for the operation,
maintenance and cleaning of equipment as necessary throughout
the commissioning period up to the time takeover.
.14 The Contractor shall comply fully with such safety procedure and
permit systems and shall accept and accommodate the resulting
limitations on access to his plant without claim on the Employer.
.16 The Contractor shall supply all test equipment, paper charts,
continuous stationery, and magnetic tape and disc, tools,
chemicals, lubricating oils and grease and other materials required
for the aforementioned operations.
.17 The Contractor shall make available load for the purpose of these
tests but gives no guarantee that the availability will be continuous
or non any specific load, but every endeavor will be made to give a
load as near as possible to the rating of the machines.
.18 The timing for implementing the tests shall be mutually agreed
between the Contractor and the Employer's Representative.
.20 For purposes of this Contract, the provisions of this Section shall
apply also to works and installation supplied from sub-contractors.
PAGE 19
.1 Welding Manual
.3 Control of Welders
PAGE 20
.4 The Contractor shall prepare all check sheets for the inspections,
the format of them shall be agreed with the Employer’s
Representative at Site. Such check sheets must be signed by the
QUALITY ASSURANCE, INSPECTION, TESTING AND COMMISSIONING
SECTION 18002
PAGE 21
TABLE 1
.5 Control of NDT
PAGE 22
.4 In the case of radiography, the Contractor shall comply with all the
requirements of the Act 304 of the Government of Malaysia -
Atomic Energy Licensing Act 1984. Radiographic works shall only
be carried out after normal working hours, from 7 p.m. to 7 a.m.
the next day. However, the Employer his Representative may
delay permission to start radiography or suspend it for any
duration during the permitted hours if urgent construction works
and/or plant operational activities need to proceed without
interference.
.1 Pressure-containing Welds
PAGE 23
.2 All hydrostatic tests shall be carried out prior to surface coating or painting
and cast iron enclosures may be subjected to hammering as required by
the Employer’s Representative.
.4 The manufacturer shall supply labour and appliances for such testing as
may be carried out on his premises. Failing facilities at his own works the
manufacturer shall make arrangements for carrying out the tests
elsewhere.
.5 The testing shall include, but not be limited to, the following: -
.4 The body of each valve of fitting shall be tested to not less than
one and one half times its design pressure and where appropriate
the latest requirements of JKKP, shall apply. In the particular case
of safety valves the seats shall be blanked and the hydrostatic
pressure applied only the part of the body at the inlet valve.
.5 With the exception of the following items and items which may
suffer internal damage e.g. bellow operated instruments, etc., each
assembled fitting shall be tested to not less than one and one half
times its design pressure.
QUALITY ASSURANCE, INSPECTION, TESTING AND COMMISSIONING
SECTION 18002
PAGE 24
.3 Pumps, fans, compressors and other rotating equipment shall be given full
load tests, and run to 15% over speed for 5 minutes to check vibration.
main and auxiliary gear boxes shall be subjected to shock load tests and
a six-hour endurance run at rated speed and maximum torque.
.4 The Contractor shall submit single line diagrams including the layout of
the plant together with the location of test instrumentation and the
principal dimensions of the layout. All calculations to derive performance
data shall be made strictly in accordance with formula given in the
approved Standards. Any alterations or deviations form the approved
Standard test layout or formula shall be subjected to the prior approval of
the Employer’s Representative.
.5 The formula used for correcting test results to Site conditions shall be
subjected to the Employer’s approval and be given with the test results
together with calibration details of any measuring instruments.
.6 All pressure gauges, flow meters, venturi tubes or ducts, orifice plates and
other instruments to be sued for works tests shall be subjected to routine
calibration against Standard instruments. Calibration records shall be
available for inspection by the Employer’s Representative.
QUALITY ASSURANCE, INSPECTION, TESTING AND COMMISSIONING
SECTION 18002
PAGE 25
.7 Wherever possible, Plant items shall be tested with the driving motor
specifically purchased for the respective item. Where such an
arrangement is not practical then it will be permissible to utilities a test
motor providing fully technical performance details are available for
scrutiny by the Employer’s Representative.
.8 The Tenderer shall demonstrate the Plant he is proposing for this Contract
is of a satisfactory proven type in commercial operation. In such a case,
at his own expense, he will arrange for one representative each from both
the Employer’s Representative and the Employer’s organisation to visit
such units and to meet with responsible representative of the respective
owners/operators.
.11 The performance test shall be conducted over the full operating range of
the pump to a closed valve condition and a minimum of five measurement
points covering the full range shall be taken. Curves indicating Quantity
vs. head, Quantity vs. Power absorbed, and Quantity vs. Pump efficiency
shall be provided. In additional curve of the NPSH required vs. Quantity
shall be provided except when the suction conditions do not require this
test. Any proposal for the omission of this test shall be to the approval of
the Employer’s Representative.
.12 On completion of the tests the Contractor shall submit a report showing
the test results obtained together with the curves corrected to the Site
operating conditions.
.13 The Tenderer is to state his normal practice with regard to the testing of
turbine components, the trial erection of the turbine, and the steaming of
the turbine assembly in works to prove the satisfactory mechanical
operation prior to dispatch to Site.
.15 All inspection, testing, marking and certification for Air Receivers shall be
performed to the appropriate ANSI, ASTM and ASME Standards.
QUALITY ASSURANCE, INSPECTION, TESTING AND COMMISSIONING
SECTION 18002
PAGE 26
.16 The vessels shall be constructed and tested under the supervision of a
third party inspector approved by the Employer’s Representative. Safety
valves, bursting discs and other fittings shall be tested in accordance with
the requirements of the appropriate ANSI, ASTM and ASME Standards.
.17 The Contractor shall carry out at his Works, tests as required by ANSI,
ASTM and ASME Standards to prove the capacities of the lifting
equipment. Test Certificates shall be provided and shall include the
material of fabrication, welding and non-destructive testing, electrical
equipment, wire ropes, hooks, chain blocks, shackles, runway beam, eye
bolts and any other related items which are provided.
.18 All tests shall be carried out in the presence of the E.R. and the
nominated third party inspector. Upon completion of the tests, the
equipment shall be clearly marked with the equipment’s safe working load
(SWL) and any marking that the E.R. may require. A permanent
nameplate shall be attached containing the following information: -
Date of manufacture
Date of test
Load applied
.19 The testing of storage tanks shall conform to the appropriate ASME and
ANSI Standards.
.1 Preliminaries
PAGE 27
.2 Hydrostatic Testing
.3 Repeat Testing
.4 Welded Pipework
.1 General Checks
PAGE 28
.2 HV Dielectric Tests
.2 All high voltage cables, the main and auxiliary circuits in switch
gear and bus systems shall be subjected to a high voltage test at
the appropriate voltages.
.3 Tests on the 415/240V system shall comply with BS 7671 (formerly IEE
Wiring Regulations 16th Edition). In this respect detailed inspection of the
installations shall be carried out prior to the tests being performed. The
sequence of performance of site tests shall be:
PAGE 29
.6 Polarity checks.
.4 Protection System
.1 Secondary Injection
.2 Primary Injection
PAGE 30
.5 DC Operations
.6 On Load Tests
.1 On load checks shall be made after the protective gear has been
placed in service to ensure that all connections and test links have
been replaced and test leads removed, as well as to confirm the
integrity of the current transformer circuits. Where necessary
voltage readings shall be taken at the terminals on each relay to
ensure that loop connections between the relays are complete.
.7 Other Tests
.1 After the Contractor has notified the Employer's Representative that the
plant is ready for commercial service, and providing the Employer's
Representative is satisfied that the works and installation is ready for
commercial service, the plant with all its auxiliaries is required to operate
under the various modes of operation as stipulated by the Employer's
Representative and under the working condition of the station within the
limits of output specified and either continuously or intermittently, as may
be more convenient for the working of the station without failure or
interruption of any kind for a period of 30 days.
.2 The plant will be operated by the Contractor under the supervision of the
Employer's Representative during the reliability test period, but the
Contractor shall be allowed to make any minor adjustments which may be
necessary, provided that such adjustments do not in any way interfere
with or prevent the commercial use of the plant by the Employer's
Representative or result in reducing the output or decreasing the
efficiency.
PAGE 31
.5 During the Reliability Run the Employer's Representative shall have the
right to request the Contractor to repeat certain operational tests or
maneuvers performed during the commissioning test to prove the integrity
of the plant including the Control system, and the Contractor shall comply.
.6 Should any failure or interruption occur in any portion of the plant due to,
or arising from, faulty design, material, workmanship or omission or
incorrect erection, sufficient to prevent safe and full commercial use of the
plant, the reliability run shall be considered void and the reliability test
period of 30 days shall recommence after the Contractor has remedied
the defects. All adjustments made by the, Contractor shall be recorded by
him in a manner to be specified by the Employer's Representative.
.7 Within one month of the completion of the reliability run, the Contractor
shall submit one report covering the observations, adjustment made
during the period.
END OF SECTION
IMPLEMENTATION OF TESTING AND ADJUSTING, COMMISSIONING,
HANDOVER-PROCEDURE
SECTION 18003
PAGE 1
1.0 INTRODUCTION
.1 Task Description
PAGE 2
PAGE 3
.2 Documentation Example
.1 Important Note
PAGE 4
.2 Electrical Services
.1 Electrical Systems
.3 General Activities
.1 Required Action
PAGE 5
.1 During construction.
PAGE 6
.2 Test Equipment
.1 General Requirements
All field test instruments to be used on the works shall comply with
the following:
.3 Documentation Examples
.1 During Construction
.4 Local AuthoritiesTesting
.1 During Construction
PAGE 7
4.0 IMPLEMENTATION/DESCRIPTION
.1 Commissioning Manager
.3 No defect shall be cleared from the report log until it has been
signed by the Contractor, the organization initiating the snag, and
the Employer’s Representative.
.4 Two defect logs shall be maintained. The main log showing all
defects shall be maintained in a complete form.
PAGE 8
reviewed with the trade contractor and specified dates agreed for
defect clearance.
.1 General
PAGE 9
.1 Draft Cover
.2 Draft Tab.
.3 Sample Format.
.1 Requirements
.2 All soft copy as-built / record drawings shall be in the form of CD.
.7 The quantities and types of print and tracing to be issued for "As-
Built" use are the same as for normal document issues, as set out
in the Project Procedures Manual.
PAGE 10
.1 Important Note
.5 OPERATING .1 General
PROCEDURES .2 Initial Set-Up
.3 Routine Inspection Charts
.4 Equipment Start-Up /Shut
Down
Procedures
.5 Filling-Up
.6 Draining Down
.7 Lubrication Charts
IMPLEMENTATION OF TESTING AND ADJUSTING, COMMISSIONING,
HANDOVER-PROCEDURE
SECTION 18003
PAGE 11
.8 Filtration Charts
.9 Preventative Maintenance
.10 Lead/Lag Arrangements
.11 Fault Finding
.6 EMERGENCY .1 General
PROCEDURES .2 Health and Safety
.3 Failure of Electrical Supply
.4 Failure of Water Supply
.5 Failure of Gas Supply
.6 Refrigerant Leaks
.7 Water Leaks
.8 Fuel Oil Leaks
.9 Fire Situations on MEP
Systems
.10 First Aid Procedures
PAGE 12
.1 General
.2 Given the requirements of the Health and Safety at Work Act and
the need to maintain warranty conditions it is an absolute
prerequisite that full training occurs prior to handover of any
equipment or systems.
.2 Training Periods
.1 The following schedule sets out for each facility, the general
systems / equipment requiring demonstration/training and also
IMPLEMENTATION OF TESTING AND ADJUSTING, COMMISSIONING,
HANDOVER-PROCEDURE
SECTION 18003
PAGE 13
.4 Documentation Examples
.2 Sample Format
PAGE 14
Building : Contractor:
Date of seminar
Time of seminar
Location of seminar
.4 Title of Seminar
.5 Attendance List
.1 Introductions of Instructors
.2 Introductions of Owners Representatives
.3 Introductions of Manufacturers Specialists
.4 Presentations of Course Training Aids
.5 Statements of Course Aims/Scope
.7 Training (Classroom)
.8 Field Training
PAGE 15
.1 General
.2 Similar list to (a) above covering spare parts etc. for all
other equipment for each spare parts have not been
included in the Trade Contract.
PAGE 16
.1 Introduction
This information may be presented in draft form but the content must
encompass all aspects relating to the operation and fault finding areas.
.5 This training will take place after receipt of the draft documents and with
the agreement of the Building Manager or Building Services Manager in
respect of content, time scale and dates for training.
IMPLEMENTATION OF TESTING AND ADJUSTING, COMMISSIONING,
HANDOVER-PROCEDURE
SECTION 18003
PAGE 17
The snag list will consist of items both in numbers and content that are
considered manageable by the Building Manager. The attachment of the
list at this time does not deem to represent or limit the scope for adding
items that arise through the operation of areas and system by operations
throughout the defects liability period. A status report of the current snag
list will be provided with the certificate of readiness.
.7 Keys
All door keys are to be presented to the Building Manager from the Project
Executive in an orderly manner at a mutually acceptable time. This will
also include all keys associated with engineering items of plant and
equipment.
.8 Authority
These items are covered by the narrative for the Certificate of Practical
Completion and do not from part of this procedure.
.10 Certificate
.3 A status report on the current snag list as the date of issue of the
certificate will also be attached.
.4 Documentation Examples
END OF SECTION
LIGHTING WIRING, POWER CABLING AND CONTROL WIRING
SECTION 18004
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.1 To install, test and commission lighting wiring, power cabling and control wiring in
accordance with the Contract Documents
1.3 SUBMITTALS
.1 Tender Stage
.2 Construction Stage
.3 Site Installation
.3 O&M manuals
LIGHTING WIRING, POWER CABLING AND CONTROL WIRING
SECTION 18004
PAGE 2
.1 Standards To Comply
.2 Workmanship
.1 Contractor shall have a proven track record and the wiremen shall have
at least 10 years experience in wiring for commercial building and hold a
PW4 Wiremen Certificate.
2.0 PRODUCT
.1 General requirement
.2 The workmanship shall be of first grade quality and shall be complete for
satisfactory operation, control, maintenance and safety under all
conditions of services.
.1 The electrical Trade shall furnish all data and wiring diagrams for those
items of equipment where there is joint coordination and responsibility for
the wiring and interface between the Electrical Trade and the BSS and/or
BCS Contractors. Such items shall include but are not limited to the motor
starters, fire pump and controllers, domestic water pumping units,
terminal units, water chilling unit control panels, emergency generator,
transfer switches, fire alarm system (point location, point type
LIGHTING WIRING, POWER CABLING AND CONTROL WIRING
SECTION 18004
PAGE 3
identification), etc. the data and wiring diagrams furnished to the BSS and
BCS Contractors shall indicate those terminals which have been provided
for the use of the BCS and BSS Contractor. The diagrams shall first be
submitted to the BSS Contractor who, upon completion of marking up the
drawings showing BSS interfaces and connections, shall forward them to
BCS Contractor.
.3 Provide one composite drawing for each item of equipment indicating the
wiring in its entirety including interlocks. Any omissions or errors noticed
by the BCS Contractor shall be brought to the electrical trade and BSS
Contractor or relevant parties immediately.
.5 Include all internal wiring of panels (in detail) in the composite wiring
diagram. For items such as motor starters and etc. all jumpers added or
removed shall be clearly indicated as being “added” or “removed”.
.7 Complete the composite wiring diagrams and return the diagrams to the
Electrical trade who will verify that the composite wiring drawings are
correct. Any corrections required shall be made by the BCS Contractor.
.3 Examination of documents
PAGE 4
.1 All cables used shall be of the appropriate grade complying with the
relevant standards BS 6004 & BS 7671 and to the approval of the latest
electricity Supply Regulations and local authority.
.3 Conductors shall be of adequate size and rating for the particular duties
and terminations.
.4 All cables shall be installed in one continuous length between the points
of connection and no joints of any description, other than those required
for terminating the cables, shall be allowed.
.5 Method of wiring
.1 The wiring shall be drawn into the conduits after the conduits have been
completely fitted.
.2 The wiring system will be of the loop-in type and connections will only be
allowed in switches, lamp fittings and switched socket outlets.
.5 The maximum numbers of PVC insulated cables drawn into any conduit
must comply with BS 7671.
PAGE 5
.9 The lighting circuit and power circuit will have their own separate conduits
and raceways where applicable.
.2 The motor will remain ‘ON’ when the momentary ‘ON’ contact is
re-opened..
.3 The motor will stop even when the momentary ‘OFF’ contact is re-
closed and
.4 Following a loss of power to the controller, the motor shall not re-
start until the momentary contact across the start terminals is
closed.
PAGE 6
.1 A pair of terminal shall be wired such that when the BCS detects
an open contact it shall indicate that the motor is ‘OFF’ and when
the BCS detects a close contact the motor is ‘ON’.
.1 A pair of terminals shall be wired such that when the BCS detects
‘close’ contact and at the same time an open contact on status
monitoring then the motor is in ‘alarm’ condition.
.2 The load on the motor starter side of the terminal strip shall be
such that the BCS relays required to execute the various control
and monitoring function shall not require a rating greater than 5
amps 240V.
PAGE 7
.2 The Contractor shall provide all wiring, and relays, etc. as necessary to
provide a terminal strip interface as detailed herein to which the FAS
interface so as to undertake override stop control and also status of the
motor.
A pair of terminals shall be wired such that when the FAS closes a
relay contact across the terminals then the motor stops regardless
of the position of the motor controller HOA switch and regardless
of the status received by the BCS. When the relay contact is
opened the FAS shall not cause the motor to start but it will not
inhibit the motor from being started. An additional terminal shall be
provided for the termination of the screen between the controller
and the terminal strip.
.2 Motor Status
A pair of terminals shall be wired such that when the FAS detect
an open contact it shall indicate that the motor is ‘OFF’. An
additional terminal shall be provided for the termination of the
screen on the wiring between motor controller and the terminal
strip.
3.0 EXECUTION
3.1 TESTS
.1 Site Tests
LIGHTING WIRING, POWER CABLING AND CONTROL WIRING
SECTION 18004
PAGE 8
.2 Visual Inspection
.3 Continuity Test
END OF SECTION
CONDUIT RACEWAY TRUNKING CABLE TRAY AND CABLE LADDER
SECTION 18005
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.6 Conduit, 'raceway’ trunking, cable tray and cable ladder fittings and accessories.
1.3 SUBMITTALS
.1 Tender Stage
.2 Construction Stage
.4 Site Installation
CONDUIT RACEWAY TRUNKING CABLE TRAY AND CABLE LADDER
SECTION 18005
PAGE 2
.3 O&M manuals
.1 Except as modified by the Contract Documents, comply with the latest applicable
provisions and latest recommendation of the following: -
PAGE 3
.17 JIS G 3131 Hot Rolled Mild Steel Plates, Sheets and Strips.
.2 PRODUCT
2.1 CONDUIT
PAGE 4
.2 All conduit shall be heavy gauge galvanized, class B, screwed steel type
complying to BS 31 or other relevant BS standards.
.3 All conduit fittings, cover lids and accessories shall be of the galvanized
type or of the equivalent quality proprietary fitting made of aluminium die
casting. Prefabricated conduit bends, elbows, draw boxes and etc. shall
conform to the relevant BS standards.
.4 Draw in boxes shall be provided to give access to all conduits for the
drawing in of cables. The draw in boxes shall be approximately sized so
as to allow neat diversion of cables from one conduit to another without
cramping. Cable joints are not allowed in draw in boxes under any
circumstances. Where conduit is to be installed in point to point runs draw
in boxes shall be installed in every 9 meter. No box shall be installed so
as to be inaccessible after completion of the structure or other services.
.6 Couplers shall have dimensions associated with the diameter ‘D’ of the
conduit as follows: -
.10 The maximum number and size of the installed cable within a conduit will
be such that a space factor of 40% is not exceeded. The Contractor is
required to substantiate the conduit sizes with technical calculation on
conduit capacity.
CONDUIT RACEWAY TRUNKING CABLE TRAY AND CABLE LADDER
SECTION 18005
PAGE 5
.11 All conduits exposed and run above false ceiling shall be pre-painted from
factory with etching primer and two coat of approved type colour paint.
Conduit for essential and UPS circuit shall complete with additional 50mm
width painted colour band at 1.5m intervals.
.1 Where it is found that several surface-run conduit cable runs are grouped
together, thereby utilizing extensive space on walls or steel structural
works, the Contractor may, with the Employer’s Representative approval,
use steel trunking in lieu of conduit for PVC cables runs.
.4 Steel trunking shall be supplied in standard length, with each length being
provided with a sleeve-type coupling and external earth bonding link of
copper size 35 mm sq.. All trunking shall have a smooth interior with
cover plates overlapping the sides of the trunking. In general, the trunking
shall be designed for exceptional strength and rigidly with trunking length
fitted with “butt-up” joints form the necessary runs. Suitable adaptors shall
be utilised for any change in cross section of trunking runs. All such
adaptors, bends, tee pieces and stop bends used in the trunking
installation shall be pre-fabricated. All accessories including tee pieces,
bends, intersections and other similar accessories shall be purpose made
by the trunking manufacturer. The Contractor shall be required to submit
technical calculation to justify the structural integrity of the support
requirement on cable trunking.
.6 In horizontal and vertical trunking runs, insulated type cable support and
retaining clips shall be fitted to support the weight of the cables.
PAGE 6
support on them. In any event, the maximum support spacing shall not
exceed that defined in Table 4D of the 16th edition of the IEE wiring
regulations. No sagging of any trunking will be permitted. All such
suspension units, angle supports to or structures shall be of hot-dipped
galvanized.
.10 Where vertical trunking runs pass through floors of the buildings, fibre-
resisting barriers with individual sleeve mouldings (this material shall be
approved by the Jabatan Bomba Malaysia), shall be fitted in the trunking
at individual floor levels. All such fire barriers shall have a minimum fire
rating of 3 hours.
.11 For all trunking, a 50mm width painted colour band at 1.5m intervals to be
used for all installation.
.1 Wherever cable trays are required for use in the contract works, the
Contractor shall supply and install perforated type: hot-dipped galvanized
complete with all necessary bends, tee pieces and adaptors for changes
in width of trays where required. The trays shall be of heavy-duty
construction from at least 1.6 mm sheet steel for trays to 300 mm in width
and 2 mm sheet steel for trays in access of 300mm.
.3 Cable trays may either be suspended from the underside of floor slabs or
roof structural work on column of wall supports, or installed on floor-
mounted. All such suspension units, angle supports to or structures shall
be of hot-dipped galvanized.
PAGE 7
.5 In the event of a single layer of cable trays being insufficient to cater for
the cables to be laid thereon, the Contractor shall install two or more
layers of cable trays on a common set of hangers. The supports or
structure shall be sufficient robust construction to cater for the additional
weights of the trays and cables.
.7 Cable trays shall be installed with the greater dimension in the horizontal
plane unless otherwise agreed with the Employer’s Representative.
.8 All cable tray systems shall be fully earth equipotential bonded throughout
using 25mm X 3mm copper tape with square clamp installed on the
jointing connection of copper tapes.
.10 The colour of paint applied shall comply with TM’s requirement. For all
other services, painted colour band shall be in the form of a 50mm width
at 1.5m intervals or a minimum of one band per section.
.1 General
.1 Flush floor trunking system will be used for floor distribution and
shall be supplied and install complete with all necessary trunking,
junction boxes with fly over, services outlet boxes, reducers,
elbow box, vertical access box, end cap, trunking support bracket
and adaptor junction boxes for connection to under floor trunking
system.
PAGE 8
.3 The flush floor trunking shall be firmly fixed to floor slab with
galvanized sheet steel floor fixing with bracket and screws
manufactured from the same manufacturer.
PAGE 9
.4 Services Box
.3 The hinge for the coverlid of services box shall be of the robust
material and the construction of opening manoeuvred of the
coverlids shall be of long-lasting type.
.5 Material
.6 Earthing
.1 The cover of the services outlet box shall be provided with a brass
earth terminal and shall be earthed to the main trunking body.
.7 Test
PAGE 10
.1 Loading requirements The flushed trunking system shall be able to withstand the
following loading test requirements. Whilst it is recognised
that there is currently no test conducted on the existing
flushed floor trunking construction to these loading. It is the
absolute contractual requirement of the successful flushed
floor trunking supplier to have the loading tests to be
conducted by an independent testing laboratory such as
SIRIM within 1.5 months from the confirmation of selection.
.1 General
.1 The under floor trunking system shall be suitable for use in the
distribution of power, telephone and data services within concrete
or floor screeds and finishes in accordance with the layouts shown
in the Drawings and as specified herein.
PAGE 11
.4 Junction Box
.1 The junction boxes shall be flushed with the final finished floor
level and the junction box base frame and pillar supports shall be
manufactured of zinc alloy die-cast in one piece to give the base
unit the mechanical strength. The junction box lid and metal fly
over shall be zinc alloy die-cast heavy load bearing materials. The
trap cover with 6mm recess, suitable for vinyl tile, ear par or
ceramic tile floor finish, shall be installed for the junction box. The
junction box shall be provided with overlapping flanges for
securing onto the floor slab, and flyovers for segregation of
intersecting cables. Knockout trunking outlets trap cover
supported by the frame and height adjustable pillar screws shall
be provided with neoprene rubber gaskets to prevent noise and
ingress of moisture and dust.
.1 The service outlet boxes frame and cover shall be manufactured of zinc
alloy die-cast heavy load bearing materials and the base frame and pillar
CONDUIT RACEWAY TRUNKING CABLE TRAY AND CABLE LADDER
SECTION 18005
PAGE 12
.2 The trap lifting handle shall be retractable into the trap cover without the
need of cutting the floor finish materials and it shall not protrude from the
trap cover. The lid, frame and accessories plate shall be epoxy coated for
protection and against corrosion.
.3 The junction boxes and concealed outlet floor boxes shall be supplied
with disposable screeding lids, so that the traps will not be covered with
cement or concrete during screeding or casting of concrete and the traps
shall only be installed after screeding and/or casting.
.4 Generally the service outlet box shall be supplied with multiple lids for 2
compartments service outlets and 1 lid for 3 compartment service outlet.
3.0 EXECUTION
.1 General
.1 Rigid conduits, trunking, trays and ladders shall be run truly vertical,
horizontal or parallel with the features of the building and in accordance
with BS 7671. The Contractor shall be responsible for coordinating the
routing with other specification Divisions.
.3 The maximum size of damaged area for which such repairs is acceptable
shall be in compliance with BS EN ISO-1461:1999.
.2 Conduit Installation
PAGE 13
.3 Conduits shall not be laid across expansion joints and where these occur
in the run of a line of conduits, the conduits shall be brought below the
expansion joint and a length of flexible conduit installed, sufficient to allow
for a total movement of +/-10mm.
.5 The cut section shall be renovated using at least two coats of good quality
zinc-rich paint complying with BS 4652.
.6 Inspection type elbows, bends or tees shall only be used with the written
consent of the Employer's Representative.
.10 The length of thread on the ends of the conduits shall suit the length of
internal thread in the end of the fitting accessory. Excess length of thread
shall not be permitted.
.13 Conduit runs on the surfaces of buildings or ducts shall be fixed by means
of saddles and with colour band, unless otherwise specified.
.14 Three piece conduit unions should be used. At the discretion of the
Employer's Representative, running couplings with hexagonal locknuts
may be used, the exposed threads being given a coat of zinc paint.
PAGE 14
.16 All free ends of conduits shall be fitted with approved bushes.
.18 The ends of flexible conduits shall be connected to the fixed conduit
system and the equipment by means of approved adaptors. A stranded
copper earth wire of section complying with BS 7671 shall be run
internally between motor and starter and connected in an approved
manner.
.3 Trunking Installation
.1 Trunking shall be run neatly on the surface of the building and at least
150mm clear of plumbing and mechanical services.
.3 The practice of cutting and bending the material of the trunking to form
attachments shall not be accepted.
.1 Cable trays and cable ladders shall not be cut at site. Instead, they shall
be supplied in different lengths from the factory for assembly at site.
PAGE 15
.3 The splice connector plates shall be located outside of tray side rails.
The adjacent tray or ladder sections shall be bolted using nuts and
washers, on the outer side of the tray. The torque nuts used shall be to
manufacturer's specified value.
.10 Cable trays and ladders shall be installed above piping and other
obstructions to meet the required headroom. The minimum clearance
from the top of the tray side rails shall be 300mm.
.11 The side of the cable tray facing the wall shall have a clearance as per
manufacturer's recommendation. The other side of the cable tray shall
have a minimum clearance of 100 mm.
• Bends, elbow, hinged splices, etc. shall be proprietary and shall not be
fabricated at site.
PAGE 16
.1 Horizontal and vertical supports shall provide at least 30mm bearing length from
each rail and shall have provisions for hold-down clamps and fasteners.
.2 The side rail shall bear on the support. Where necessary, shims shall be used to
elevate the trays or ladders and provide bottom clearance to the supports. The
trays or ladders shall not bear on the support.
.4 Horizontal trays and ladders shall be supported by either wall mounted support
brackets or hanger rod system. The intervals between support shall be as
recommended by the manufacturer but this shall not exceed 1 metre for wall
mounted support brackets and 1.2 metres for hanger rod system.
.6 Sloping trays and ladders shall be supported at intervals not exceeding those
used for the horizontal trays and ladders of the same design.
.8 Cables shall be supported by proprietary make hanger system and cable clamps
on the cable tray and ladder. Cable straps are not acceptable in this Contract.
.2 Splice connectors shall be attached by round head bolts with nuts and washers
located on the outside of the tray or ladder.
PAGE 17
.1 Conduits shall be attached to the side rail with conduit clamps and brackets.
Holes shall not be made in side rail for conduit attachment.
.2 The minimum bending radius of cables exit from trays or ladders shall be
maintained using drop-out plates, vertical riser elbow fittings, or other
accessories designed to control bending.
.3 Cable tray and ladders edges and flanges at locations of cable exit from trays
shall be suitably sheathed to prevent injury to cable insulation.
.1 These divider strips shall be installed where different system wiring is installed in
a common tray or where shown in the design drawings.
.2 Divider strips shall be anchored to every ladder rung using fasteners, which
attach to the tray without the need for drilling or punching at site.
.3 The fastener shall attach to the tray without the need for any drilling or punching
of hole at site. The fasteners shall also present minimum exposure to the cables
by having rounded exposed parts.
.1 Fire stop seals shall be provided where cable raceways, trays or ladders pass
through floors or walls.
.3 For cable ladders and cable trays passing through the floor slabs and walls, the
installation of fire stop shall only be carried out after the utility or services
provider has completed their cabling installation works.
3.7 EARTHING
.1 All cable trays, ladders and interconnecting trunking and conduit shall be earthed
as described in the earlier paragraphs.
.2 Earth links shall be used to electrically interconnect joined sections of the cable
trunking, cable tray and cable ladder system. The resistance measured between
adjacent sections shall not exceed 0.01 Ohms.
PAGE 18
.3 On arrival at site, the consignment shall be checked against the delivery notes.
.4 On delivery to site, the products shall be stored indoor, in a clean, dry and well
ventilated place. Galvanised articles shall not be stored on clinkers or ashes.
3.9 TESTS
.1 Type Tests
PAGE 19
.1 Conduits, ‘raceway’ trunkings, cable trays, cable ladders, their fittings and
accessories and fire resisting trunking shall be subjected to the following:
-
.1 Visual inspection
.2 Correct markings
.3 Dimension checks
.5 Damage on galvanising
.2 Uniformity of coating
.3 Deflection tests
PAGE 20
.2 Damage on galvanising.
.4 Store indoor.
.4 Damage on galvanising
END OF SECTION
6001000V PVC SHEATED CABLES
SECTION 18006
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.1 Manufacture, test at Works, deliver to site, install, test and commission the
following for low voltage cables in accordance with the Contract Documents: -
PAGE 2
1.3 SUBMITTALS
.1 Tender stage
.4 Type test certificates on fire resistance and halogen free content from
internationally recognised independent testing laboratory.
.2 Construction Stage
.4 Site Installation
6001000V PVC SHEATED CABLES
SECTION 18006
PAGE 3
.3 O&M manuals
.1 Standards to Comply
Except as modified by the Contract Documents, comply with the latest applicable
provisions and latest recommendations of the following:
PAGE 4
.17 BS EN 10257 Zinc or Zinc Alloy Coated Non-Alloy Steel Wire for
-1:1998 Arranging either Power Cables or
Telecommunication Cables. Land Cables
.2 Manufacturing Experience
2.0 PRODUCT
.1 All cables for the internal wiring distribution of the building, including the
external underground cable distribution submain, shall be supplied and
installed by the Contractor.
6001000V PVC SHEATED CABLES
SECTION 18006
PAGE 5
.6 For control cables having more than seven (7) cores, the direction of lay
shall alternate for each successive layer.
.7 For multi-core cable, sheath or bedding shall be applied over the laid up
cores. It shall be compatible with the operating temperature of the cable
and the thickness shall comply with IEC 60502.
.10 The outer sheath of large cables shall be impressed or embossed with
the rated cable voltage, cable size, year of manufacture and name of
manufacturer.
.11 For 1.5mm2, 2.5mm2, 4 mm2 and 6 mm2 PVC insulated cable used for
final sub-circuits (lighting, 13A switched socket outlets and others loads
from distribution board), compliance to BS6004.
6001000V PVC SHEATED CABLES
SECTION 18006
PAGE 6
.12 For 10 mm2, 16 mm2 and 25 mm2 2core or 4core PVC/PVC insulated
cable used for sub-main, compliance to BS 6346, unless otherwise
specified in drawing.
.13 For 25 mm2 and 35 mm2 2core or 4core XLPE/PVC insulated cable used
for sub-main, unless otherwise specified in drawing, compliance to BS
6346. For 50 mm2 and above 1core XLPE/PVC insulated cable used for
sub-main, compliance to BS 6346.
.2 600/1000V Fire resistant mineral-insulated and low smoke halogen free cable
.1 All single and multi-core double insulated fire resistant cables shall
comply to standard BS6387, 1994 Category CWZ with extension of
600/1000V test, IEC 60331 and IEC 60332 part 1, IEC 60332 part 3
Category A, B and C, IEC 61034 and free from halogen acid gases when
tested in accordance with IEC 60754-2.
.2 The cables shall be rated at 600/1000V. The thickness shall comply with
IEC 60502. A gas mica fire resistance tape shall apply over the conductor
to meet the fire resistance test requirement. The sheath shall be a robust
extruded mineral insulated low smoke halogen free type complies with
IEC 60754-2.
.3 All fire resistant cables shall be installed strictly in accordance with the
manufacturer’s recommendation. Cables shall be laid in straight and neat
manner. Clipping of the cables to the trays and cable ladders shall be
done in accordance to the manufacturer’s recommendation and with
metal galvanized type clips/straps/clamps. When single cored cables are
used, the cables shall be laid in three-phase group. Whenever bending of
the cable is required the work shall be done in strict accordance to the
cable manufacturer’s instruction. Cable bending radius shall be restricted
to a minimum of 6 times the cable diameter for single core cable and
multi-core cable during installation.
PAGE 7
.7 All fire resistant cables shall comply with local authority requirements in
all respects. All relevant test Certificates shall be from an internationally
recognised independent testing laboratory.
.3 PVC/SWA/PVC
.7 The outer covering over the armour wires for all multicore control cables
shall consist of a black extruded PVC sheath, which shall comply to PVC
compound Type TM 1. The thickness shall be in accordance with BS
6346.
PAGE 8
continuity. The glands shall be provided with earth tails for connection to
earth conductors and PVC shrouds.
3.0 EXECUTION
.1 Immediately after the Works Tests seal both ends of each cable length against
the ingress of moisture, dirt and insects and protect the end projecting from the
drum against mechanical damage during handling and transit. For large size
cables and long lengths where drumming is necessary, the ends of the cable
shall be marked 'A' and 'Z' as appropriate. Each drum shall bear a distinguishing
number either printed on one flange or printed on a nameplate and attached to
the flange. Particulars of the cable i.e. voltage, circuit label, length, cable type,
conductor size, conductor material, number of cores, gross and nett weights etc.
shall be clearly shown on one flange of the drum. The direction of rolling shall be
conspicuously indicated by an arrow. Small size cables shall be coiled.
.2 The preferred lengths should be such that no joint shall be made on each cable
circuit.
.2 Install cable on cable trays in appropriate spacing and allow for bending radius
larger than the minimum recommended by manufacturer. Where single-core
cables are used, in three-phase supplies, the three phase cables shall be laid in
trefoil.
.4 Do not expose cut cable ends but seal them until cable termination is made.
.5 After cable is pulled install cable on the cable tray immediately before pulling the
next cable.
.8 Earth cable armour and sheaths near all terminals according to manufacturer's
recommendations.
6001000V PVC SHEATED CABLES
SECTION 18006
PAGE 9
.10 Fire-seal around all cables at all penetrations of fire-rated walls and floors to
maintain fire rating.
.11 Appropriate colour sleeving shall be provided for all LV cables entering and
exiting the electrical risers before cable termination.
3.4 TESTS
.1 Type Tests
.2 Routine Tests
.1 Carry out at works all relevant routine tests in the IEC and provide routine
test report for all cables supplied.
.1 Cut one 15 metre long cable sample of the largest cross section from the
completed cables and subject it to the following tests: -
.1 Dimension checks
PAGE 10
.4 Site Tests
END OF SECTION
11/6.35KV XLPESWAPVC CABLE
SECTION 18007
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.1 Manufacture, test at works, deliver to site, install, test and commission 3-core
11/6.35kV XLPE/SWA/PVC cable for high voltage feeder circuits in accordance with
the Contract Documents.
1.3 SUBMITTALS
.1 Tender Stage
.2 Construction Stage
PAGE 2
.4 Site Installation
.3 O&M manuals
.1 Standards to Comply
PAGE 3
.2 Skilled Labour
.3 Manufacturer's Experience
2.0 PRODUCTS
.1 Calculation of the continuous current rating of the cables shall be made according to
IEC 60287. Derating tables specifically for this installation method and cable
construction shall be provided by the manufacturer.
PAGE 4
.1 General
.2 Conductors
.3 Conductor Screen
.4 Insulation
.5 Insulation Screen
PAGE 5
.2 The metallic part shall be applied directly over the semi-conducting part
and comprise annealed high conductivity copper tapes or concentric
layer of wires.
.6 Core Identification
.1 A sheath or bedding shall be applied over the laid up cores. It may have
low smoke and low halogen emission characteristics and shall be
compatible with the operating temperature of the cable. The thickness
shall comply with IEC 60502.
.9 Metallic Armour
PAGE 6
PAGE 7
.1 Supply and deliver factory manufactured terminations, joints and their materials
and tools for the complete installation of the cable.
.3 Instruction manuals for the termination and jointing shall be provided. Step by step
instructions shall be listed in the manual together with clearly illustrated drawings
to enable the terminations to be easily carried out.
.4 For the purpose of cable termination and jointing, tool kits for satisfactory
completion of the work shall be provided. Materials for cable termination and
jointing shall not be included in the tool kit but shall be supplied separately. The
tool kit supplied shall have a list of tools with the quantities stated.
.5 Terminations and joints are to be subjected to type approval tests. The impulse
voltage withstand level of these accessories shall not be less than the impulse
level of the cable and switchgear.
.8 All cables entering or leaving terminal boxes shall be provided with separate
terminations so that any cable out of a number of such cables can be removed or
replaced without disturbing the remainder.
PAGE 8
.10 All cable lugs of compression type shall be provided as per manufacturers
recommendation
3.0 EXECUTION
.1 Before excavation the cable trenches, the Contractor should confirm with various
Authorities to confirm the exact location of the existing service pipes, ducts,
cables.
.2 Any damages caused by the Contractor to the existing service pipes, cables,
ducts, etc., as a result of excavation, shall be properly remedied and reinstated
to their original conditions by the Contractor at his own expense to the
satisfaction and approval of the Employer Representatives.
.2 Temporary sealing of cable ends when necessary and testing of cut ends
prior to connection.
.3 Supply, delivery and erection of all supports, bushes and other items
required for erection and fixing of cables.
.1 The centre line of these routes will be pegged out by the Contractor and
approved by the Employer’s Representative. The costs for cable route survey
shall be borne by the Contractor.
.2 The cable route for underground cables shown in the drawing are approximate
only.
11/6.35KV XLPESWAPVC CABLE
SECTION 18007
PAGE 9
.1 The exact location of each cable trench will be settled on the site by the
Employer’s Representative when work is ready to commence.
.4 Before the cables are laid, the bottom of the trench is to be lined with sand or
sifted soil, which is to be compacted to a thickness of 75mm depth or cover
backfill, shall consist of sand or sifted soil over which shall be placed protective
covers. Backfilling and reinstatement of open trenches after placing of the cable
protective covers shall also be carried out. Particular attention shall be taken to
ensure that trenches are evenly graded prior to placing the bedding material.
Cables passing under roadways shall be insulated in 100mm/150mm diameter
G.I. or steel pipes buried to a minimum depth of 900mm. Cables shall not cross
in straight runs of trench or in any other position except where a cross may be
permitted if it is impossible to void by advance planning of the lay of cables in a
trench.
.5 Routing and excavation of all trenches shall be carried out correctly and
satisfactorily and at such times and places to suit the programme of cable
installation work.
.6 Only enough ground shall be opened at a time such that cable laying and
backfilling may proceed without delay in order to avoid having trenches opened
for long periods. Excavations shall be carried out generally by mechanical
equipment or by hand. In cases where special care has to be taken of existing
structures etc. the excavation shall be carried out carefully by hand.
.7 It shall be strictly understood that the rates for excavation, inserted in the Bill of
Quantities shall cover all types of subsoil encountered, including weathered rock
and shale, but excluding solid rock and rock fill. Where solid rock or rock fill is
encountered during excavation for trenches is shall be removed by the use of a
pneumatic drill or blasting, borne by the Contractor. All excavated materials shall
be deposited alongside the trenches.
11/6.35KV XLPESWAPVC CABLE
SECTION 18007
PAGE 10
.1 Trenches shall be backfilled with soil and shall be consolidated after every
150mm of backfill using a mechanical rammer. The finished surface shall be left
proud by 50mm to allow for subsidence and the contractor shall be responsible
for the removal of any surplus soil to a position indicated by the Engineer.
.1 Cable Markers, marked ‘H.T. Cable’ shall be installed at every 15m along the
route and at any changes in direction or as directed by the
Engineer.
.1 Immediately after the Works Tests seal both ends of each cable length against the
ingress of moisture, dirt and insects and protect the end projecting from the drum
against mechanical damage during handling and transit using thermo-fit heat
shrinkable polymeric end-cap. The ends of the cable shall be marked 'A' and 'Z'
as appropriate. Each drum shall bear a distinguishing number either printed on
one flange or printed on a nameplate and attached to the flange.
.2 Particulars of the cable i.e. voltage, circuit label, length, cable type, conductor size,
conductor material, number of cores, gross and nett weights etc. shall be clearly
shown on one flange of the drum. The direction of rolling shall be conspicuously
indicated by an arrow.
.3 The preferred drum lengths should be such that no joint is to be made on each
cable circuit.
3.8 TERMINATIONS
PAGE 11
.1 Contractor shall be responsible for routing the cables in coordination with other
specification Divisions and installing cable on cable ladders in appropriate spacing
allowing for bending radius larger than the minimum recommended by
manufacturer or as detailed in the drawings.
.3 Install cable in riser shaft by lowering the cable from the upper floor to a
lower floor. Hoist cable drums and place them securely on designated upper floor.
Arrangement for hoisting shall be made with other specification Divisions.
Insulation resistance test cable prior to pulling. Prevent cable from uncontrollable
release from cable drum under its own weight by installing an appropriate braking
system. Pull cable down in the riser shaft guided by cable roller guide suitable for
holding the cable in position. Cable guide and roller shall be fixed at every floor.
Pull cable after placing cable stocking at the pulling end by a winch placed at the
lower floor. Excess length of cable shall be properly coiled and protected from
damage.
.4 Do not expose cut cable ends but seal using thermo-fit heat shrinkage material
until cable termination is made.
.5 After cable is pulled install cable on the cable ladder immediately before pulling the
next cable. Cable shall be held to cable ladders using proper metallic cable
fasteners at 1m intervals.
.8 All cables shall be installed on cable ladder. They shall be spaced according to the
Contract Documents and shall be such that cables current carrying capacities are
not adversely derated. Appropriate coloured sleeving shall be used for H.T. cable
identification before cable termination.
.10 Earth cable armour and sheaths at all cable terminations according
to manufacturer's recommendations.
11/6.35KV XLPESWAPVC CABLE
SECTION 18007
PAGE 12
3.10 TESTS
.1 Type Tests
.2 Routine Tests
.1 Cut one 15 metre long cable sample of the largest cross-section from the
completed cables and subjected it to the following tests:
.1 Dimension checks
.4 Capacitance test
PAGE 13
.4 Site Tests
.1 Visual inspection
.3 Cable routes.
.7 No cable joints.
PAGE 14
END OF SECTION
SWITCHES AND SWITCHED SOCKET OUTLETS
SECTION 18008
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.1 Manufacture, test at Works, deliver to site, install and commission, switches and
switched socket outlets in accordance with the Contract Document.
1.3 SUBMITTALS
.1 Tender Stage
.1 Switches.
.4 Isolator
.5 Fireman switch
.2 Construction Stage
PAGE 2
.4 Site Installation
.3 O&M manuals
PAGE 3
.10 BS 5733
.2 Manufacturer's Experience
2.0
2.1 GENERAL
.2 Switches shall be rated at 5, 10, 15 amp. As determined by circuit load which for
inductive lighting circuits shall be assessed at twice the steady state connected
load current, one way or two way as indicated in the Tender Drawings and fixed
generally at a height of 1500mm from floor level and where located in rooms, the
switch shall where possible be located on the inside of the room on the handle
side of the door. Measurement shall be to bottom of Switch.
SWITCHES AND SWITCHED SOCKET OUTLETS
SECTION 18008
PAGE 4
.3 Switch cover plates for the office areas, lobbies and public areas shall be of the
flush type, plate colour, decorative typed to be selected by ID/architect.
.4 Switches for service areas shall be of the metal-clad type approved by the
Employer’s representative mounted in flushed conduit boxes as specified.
.5 Weatherproof type of switches shall be used for outdoor application and shall
have minimum IP54 protection.
.7 A single pole switches shall be connected to break the phase wire of the supply,
the neutral wire shall not be through switch boxes.
.8 Where group of switches, from the same source of supply are to be installed at
the same location. The Contractor may propose grid switch system subject to the
approval of Employer’s Representative.
.2 13A S/S/O shall be 3 rectangular pin switch shuttered outlets, one or two gang
for indoor service except as otherwise shown on the drawings and either surface
or flush mounted according to location.
.3 S/S/O shall be the quick make, slow break type with silent, totally enclosed
switch action and solid silver alloy contacts. Switched socket outlet for office,
lobbies and public areas shall be housed in steel boxes finished aluminium
stoved enamel, to BS 3676 and BS 1363 with conduit knock-outs. Switches
sockets outlets for the plant room and other general non-public areas, where
specified shall be of the metal-clad type.
.5 Generally, socket outlets shall be positioned 300mm above finished floor level
except otherwise shown on the drawing where they shall be positioned 1500 mm
above finish floor level or 150mm above counters or benches whichever is
suitable, or as directed by the Employer’s Representative. Measurement shall be
to bottom of Switch Socket Outlet.
SWITCHES AND SWITCHED SOCKET OUTLETS
SECTION 18008
PAGE 5
.7 Decorative typed and colour of faceplate for the office areas, lobbies and public
areas shall be selected by ID/architect.
.8 S/S/O and switches, where mounted in the same area, shall have consistent
profile and thickness.
.9 The above weatherproof switch socket outlet and plug shall be of IP 65 rating.
.1 All fireman switches shall have cast die-aluminium IP65, weather proof
enclosures and are design to comply to IEC 60529 rating of IP65 Ingress
Protection.
.2 Switches shall be type tested to IEC 60947-3 and have utilization category of
AC23A with duty rating 240V/415V AC, 50Hz.
.1 Isolators or disconnecting switches shall comply with IEC 60947-3. They shall be
of the on-load, rotary type and interlocked with the housing and provided with
means of operation from the front so that all enshrouded live parts can be made
dead with the switch off. All fixed contacts shall be shrouded. Isolators shall
comprise of a quick-make and break, positive action mechanism. Isolators shall
not be door-mounted.
3.0 EXECUTION
3.1 TESTS
.1 Type Tests
.2 Routine Tests
SWITCHES AND SWITCHED SOCKET OUTLETS
SECTION 18008
PAGE 6
.1 Before the products leave the works, the manufacturer shall carry out the
relevant routine tests on the total assembly and on parts thereof when
delivered with time intervals and the results shall be recorded in a test
report.
.4 Site Tests
.1 Visual Inspection
.3 Polarity checks.
.2 Tests
END OF SECTION
PROTECTION, METERING AND CONTROL
SECTION 18009
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.1 Relays
.2 Protection devices
.3 Metering devices
.5 Indicating lights
.6 Alarm schemes
1.3 SUBMITTALS
.1 Tender Stage
.2 Construction Stage
.7 Cable schedules
PAGE 2
.4 Site Installation
.3 O&M manuals
PAGE 3
.3 Manufacturer/supplier shall have full parts back-up and service availability for the
equipment provided.
2.0 PRODUCTS
PAGE 4
.2 The Contractor shall carry out all short-circuit calculations, check the adequacy of
all equipment short-circuit ratings, provide the best protective device and
coordinate all protective devices in the system. Where computer software is
used for carrying out protection coordination exercise, the Contractor shall
provide full details of the software and shall be responsible for all results
generated from the software.
.3 Protection for the various circuits shall be but not limited to the following: -
Circuit Type Protection Requirement
2.2 RELAYS
.1 Relays shall be of types complying with IEC 60255 and shall have approved
characteristics and be flush-mounted in dust and moisture-proof cases with glass
fronts. Attention is particularly drawn to the tropical and humid climate and the
relay designs shall be entirely suitable for duty under these conditions. Bezels of
relays shall be of approved construction and shall be arranged so that
adjustments, testing and replacement can be effected with the minimum of time
and labour.
.2 Relays of the hand reset type shall be capable of being reset without opening the
case. Relays with provision for manual operation from outside the case, other
than for resetting, will not be accepted.
PAGE 5
.4 Relay contacts shall be suitable for making and breaking the maximum currents
which they may be required to control in normal service but where contacts of the
protective relays are unable to deal directly with the tripping currents, auxiliary
contactors, relays or auxiliary switches shall be provided. Separate contacts
shall be provided for alarm and tripping functions. Relay contacts shall make
firmly without bounce and the whole of the relay mechanisms shall be as far as
possible unaffected by vibration or external magnetic fields.
.5 Relays, where appropriate, shall be provided with flag or light emitting diode
indicators, and phase coloured where applicable. Flag or light emitting diode
indicators shall be of the hand reset pattern. Where two or more phase elements
are included in one case, indicators shall be provided for each element.
.6 Relays which rely for their operation an external DC supply shall utilise for this
purpose the trip supply of the associated circuit breaker. This supply shall be
monitored and an alarm provided in the event of failure unless otherwise
specified.
.8 Test facilities shall be provided for each current and voltage transformer
secondary circuit so as to give access for testing of protection relays and
associated circuits. The facilities shall comprise test terminals for front of panel
mounting. Alternatively the same may be accomplished by the use of test
sockets and plugs.
.9 Each current transformer circuit shall be earthed through a removable link at one
point only in the relay panel.
.11 Relays shall be of the draw-out type with automatic shorting of all current
transformer circuits when the relay is withdrawn or when the test links are moved
from their normal operating position.
.12 When specified, electrically reset tripping relays shall be provided where
necessitated by the system of control, such as for those circuits subject to remote
supervisory control.
PAGE 6
.3 If the power pack is separately housed from the relay units which it is
supplying, care must be taken that the cabling between the power pack
and the relay units, and between relay units is adequately screened and
physically separate from all 'power type' circuits associated with the CT,
VT and DC tripping circuits. All interconnecting screened cables shall
preferably be terminated by plugs and sockets.
.5 All input and output terminals of the power packs which are connected to
'power type' circuits shall be subjected to the same over-voltage, impulse
and interference tests as specified for static protection.
PAGE 7
.10 Wherever practical, the design of the relay scheme shall be based on the
'fail-safe' principle. Care shall be taken to ensure that loss of DC supply
or an open circuit does not cause incorrect opening or closing of circuit
breaker.
PAGE 8
.2 I.D.M.T. earth fault relays (where specified) shall be of the solid state or
numerical type and have adjustable operating setting from 8% to 80% of
the normal full relays load secondary current, with an adjustable time
setting, these earth fault relays shall provide selectable alternative time
current characteristics and high set definite time operation.
.3 In cases where the individual over current and/or earth fault elements are
effectively combined into one relay, this relay shall still provide indication
to discriminate the reason the relay has operated (i.e.,I.D.M.T.) over
current or earth fault, high set over current or earth fault) and which phase
has faulted.
.1 All necessary indications, tripping relays and alarm relays associated with
the winding temperature protection shall be provided and set into
operation under this Contract.
.2 The protection shall operate for phase faults and earth faults within the
protected zone and remain stable for through faults equal to the maximum
fault current ratings of the associated switchgear.
PAGE 9
.3 Phase fault and earth fault sensitivities should not be more than 120 percent and
40 percent respectively of the nominal rated current of the circuit.
.2 A time-delayed trip output shall be provided such that there shall be no risk
of incorrect operating caused for example by rotor swings accompanying a
system electrical fault.
.2 The over voltage relay shall have an adjustable setting range up to 1.4
per unit rated voltage and shall have an adjustable time delay.
PAGE 10
.2 The protection shall monitor the generator terminal impedance vector and
shall have a negative reactance offset mho (circular) characteristic with
adjustable offset and adjustable diameter.
.1 Electrically reset tripping relays with hand reset flag indicators shall be
used and these are to be arranged for pushbutton re-setting where
appropriate.
.2 The operating time of all tripping relays shall be less than 10 milliseconds.
.3 All auxiliary relays necessary to ensure the correct sequence of trip relay
resetting shall be included.
.1 Flag indication relays shall be hand-reset type. Trip flag indication relays
shall be current operated and shall operate in series with the appropriate
tripping relay.
PAGE 11
.2 MCP shall have magnetic trip adjustable from 7 to 10 times its rated
current together with adjustable thermal overload trips meeting the
heating characteristics of motors. Where motor protection requirements
available in MCB's are inadequate, additional motor protection relays
shall be provided.
.15 Fuses
.1 High breaking capacity (HBC) type fuse links with time characteristics in
accordance with IEC 60269 and having full range breaking capacities of
at least 50kA shall be used. The maximum rating shall be 630A.
.1 Thermal overload
.2 Phase unbalance
.3 Phase reversal
.4 Single phasing
.6 Stalling
PAGE 12
.8 Rotor protection
.4 Motor protection relays of the static type shall have selectable thermal
operating characteristics.
.7 The single phasing protection shall have a fixed definite time delay.
.10 For motors with operating conditions beyond those covered by overload
relays, special protection systems may be considered, e.g. installation of
thermistor temperature sensors in the motor windings with its relay
installed in the switchgear compartment, bearing lubricating oil alarm and
trips etc.
PAGE 13
.1 All motor feeders shall be provided with a three element, positive acting,
ambient temperature corrected, time adjustable, hand reset-type thermal
overload relay suitable for overcurrent protection, either direct acting or
CT operated, with 70% to 120% setting range, with current range, clearly
engraved.
.1 Where indicated in the design drawings, motors shall be fitted with core
balance type earth fault protection relays. Relays shall be manually
resettable after opening of the assembly compartment cover. The relays
shall only operate on an earth fault current of less than 3% of the rated
nominal motor current with a maximum of 6A. The relays shall be
equipped with a clear trip indication of the relay.
.4 Performance Criteria
PAGE 14
.2 Voltage Independent
.5 Construction
.2 Operating mechanism
3. Terminals
The RCCB shall have cable terminals with safety guards to protect
against misconnection.
PAGE 15
.1 The power metering for the incomers shall be capable to monitoring all
the important electrical parameters including 3 phase current, voltage,
power factor, kWhr, KVARhr, harmonics and maximum demand.
.1 All instruments shall be of the flush mounting type and shall have an
enclosure with a degree of protection of at least IP 52 and comply with
IEC 60051.
.2 All meters should be of the square pattern type 96 x 96mm bezel case,
and mounted at a suitable height for easy reading from the front. Scales
shall be in actual values and arranged in 90o . Where appropriate, meters
shall have facilities for external zero adjustments.
.5 Ammeters and voltmeters shall have accuracy class 1.5. Kilowatt hour
and maximum demand metres shall have accuracy class 2.5. Power
factor meter shall have a scale reading of 0.5 capacitive 1-0.5 inductive
with a class accuracy of 2.5.
.6 Ammeters for motor duty (if required) shall have a compressed overload
scale and shall be suitable to withstand the motor starting currents.
PAGE 16
.8 Motor starter units with a motor feeder cable of 4mm2 cross section and
more, (usually from 4kW and above) shall be equipped with a current
transformer for a remote ammeter. Motors connected with a feeder cable
of 2.5mm2 will use a direct reading remote ammeter.
.1 Circuit breakers shall be provided with electrical controls at the circuit breakers,
suitably mounted in the mechanism box or marshalling kiosk for use under
maintenance or emergency conditions. A multi-pole lockable changeover
selector switch shall be provided at the circuit breaker and labelled ‘LOCAL’ and
‘REMOTE’.
.2 Individual healthy trip lamps shall be provided and these shall be coloured white
and mounted adjacent to the associated circuit breaker control switches. Healthy
trip indicators shall be connected so as to give on demand only, supervision of
the trip circuit with the circuit breaker either open or closed, in order to minimise
drain on the station battery. A series resistance shall be provided so that a short
circuit of the lamp or relay shall not result in trip coil operation.
.1 Control Relays
.4 Where relays are used in the 11kV and 415V switchboard trip
circuits, they shall have single 30V DC and 240V AC coils,
respectively. All coils shall be continuously rated.
PAGE 17
.6 Control relays shall be of the plug-in type with the plug-in bases
having facilities for rail mounting. The terminals of plug-in bases
shall be designed to accept two wires with cross-section of 2.5 sq.
mm.
.2 Timers
.1 The timers for the motor circuits, shall be of the 'ON' delay 'OFF'
delay type, Electronic, Synchronous or Pneumatic timers as called
for by the application with 2 N/O and 2 N/C contacts, capable of
withstanding the thermal effect of switching and have very close
accuracies. They shall have variable setting and suitable for
mounting on normal contactor or for rail mounting within switch
panel.
.3 Selector Switches
PAGE 18
.2 One set of 'Accept', 'Reset' and 'Test' buttons shall be provided for the
whole mimic.
.4 Lamp indications shall be provided and these shall utilise the same button
for test as those provided for the annunciator.
.2 Indicating Lamps
.2 Lamp fittings shall allow adequate ventilation and allow for easy removal
for replacement of the lamps without requiring the use of extractors.
.3 The rated lamp voltage shall be 10 volts in excess of the auxiliary supply
voltage, whether AC or DC. Alternatively, low voltage lamps with series
resistors will be acceptable.
.4 The lamp lens shall be in standard colours, red, green, blue, white and
amber to the Employer's Representative's approval. The colours shall be
in the lenses and not applied coatings. The different coloured lenses
shall be interchangeable.
.5 Lamp test facilities shall be provided so that all lamps on the panel can be
tested simultaneously by operation of a common key. Where alarm
facias are specified, all alarm and monitoring indications (apart from
circuit breaker isolator position indications) shall be incorporated in the
facia.
PAGE 19
.7 When the circuit breaker is tripped on a fault condition the lamp will illuminate to
show discrepancy.
.8 All discrepancy indicators shall be complete with a light which shall illuminate
"steady" when at discrepancy. On hand dressing the indicator to the correct
position the light shall go out.
.1 The Building Control System (BCS), Fire Alarm System (FAS) and Generator
Control System (GCS) shall interface to instrumentation and final control
elements (control relays, etc). The following is a list of the base building
electrical equipment and motors that will be controlled and/or monitored.
.3 all AHUs and outside air make-up units VAV terminal boxes
.7 exhaust and supply fan serving the transformer and switchgear rooms
.13 main switchboard circuit breakers status and main switchboard circuit
breakers status and electrical reading of current, voltage, frequency /
power factor, etc
.14 supply and return temperatures, pressure and flow rates at building
chilled water take-offs
PAGE 20
.16 water storage tank (water level alarms) and booster pumps
.19 light status :on/off for outgoing circuits, and on/off & trip status for
incoming breaker of office lighting DBs
.2 The Contractor shall incorporate in the electrical equipment supplied, under the
other building scope of work for other packages, all the necessary auxiliary
contacts, control relays, current transformers, potential transformers, etc. and
install all the wiring connections, between the said equipment and the respective
system panels including the provision of all terminal strips in the panels to enable
the equipment to be controlled and/or monitored as outlined above. The
Contractor has to determine from the above list those equipment under his scope
of work and furnish the required components and wiring accordingly.
.1 Alarms shall be sub-divided into trip and non-trip functions and each arranged to
operate a common bell or buzzer unless otherwise specified.
.2 Means shall be provided for silencing audible alarms whilst leaving the bell or
buzzer free to sound if any other alarm circuit is energised.
.3 Power supply for activating alarms and operation of any auxiliary relay etc. shall
be 240V as appropriate.
.4 Alarm indicating lamps shall remain alight until cancelled by the resetting of the
devices initiating the alarms and the operation of a separate cancellation switch.
.5 For the purpose of transmission to the remote control centre, alarms shall be
mainly segregated into groups but with some individual alarms and the
Contractor shall include for all auxiliary switches and relays necessary to present
these signals to the supervisory equipment interposing relays.
.6 The following shall be incorporated into the alarm and indication schemes for
transmission to the remote control centres: -
PAGE 21
.5 Earthing status
.2 Earthing status
.3 Transformers
.2 Ammeter signal
PAGE 22
.3 ON/OFF/WITHDRAW status
.1 ON/OFF status
.3 Remote start/stop
.1 Remote start/stop
.8 Distribution Board
.1 ON/OFF status
.2 Protection trip
.1 ON/OFF status
.2 Protection trip
.1 Charger on float-charge
.2 Charger on quick-charge
PAGE 23
.4 Electrolyte level
.9 Earthfault alarm
.1 Input Voltage
.2 Input current
.5 Inverter output KW
.6 DC Voltage
.7 Batter Current
.8 Inverter Fault
.9 Charger fault
PAGE 24
3.0 EXECUTION
3.1 GENERAL
.2 All control and relay equipment shall be flush mounted on panels. Equipment
and terminals, terminal blocks, and panel wiring shall be so arranged and
effected that they require a minimum of disturbance to associated and adjacent
equipment for access.
.3 Where relay movements and other sensitive equipment are mounted on hinged
front panels, these shall be designed to minimise shock and wiring shall be so
arranged as to impose no strain on the terminations. No equipment whatsoever
shall be mounted on the rear access doors.
.4 The arrangement and mounting of all indicating devices, control switches, relays,
and other apparatus shall be to the approval of the Employer's Representative.
.5 The Contractor shall submit for the Employer's Representative's approval the
total system protection coordination and grading including the setting values of
the protective devices. This shall be done 1 month prior to the commissioning
date.
.1 All protection, metering and control devices shall be fitted to their respective
switchboards and delivered to site as complete units. All sensitive and movable
parts shall be packed in suitable packaging material to prevent movement and
damage during shipment.
3.3 TESTS
PAGE 25
.1 Type Tests
.2 Routine Tests
.1 Before the products leave the works, the manufacturer shall carry out the
relevant routine tests in accordance with the IEC. Static relay electronic
components shall be heat soaked and burnt-in. Results of the tests shall
be submitted to the Employer's Representative.
.4 Site Tests
.1 Provide training schedule and agenda and list of instructors from original
equipment manufacturer (OEM) and the trader contractor.
END OF SECTION
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.1 Manufacture, test at Works, deliver to site, install and commission low voltage AC
distribution panels and marshalling cabinets.
.2 Auxiliary board
.3 Marshalling cabinets
1.3 SUBMITTALS
.1 Tender Stage
.2 Construction Stage
.4 Site Installation
PAGE 2
.3 O&M manuals
.1 Except as modified by the Contract Documents, comply with the latest applicable
provisions and latest recommendations of the following:-
.6 ASTM D3359-02 Standard Tests Methods for Tape Test Methods for
Measuring Adhesion by Tape Test ASTM
International
.7 BS 3900 Pt. F2
.8 BS 7079
DISTRIBUTION PANELS, AUXILIARY BOARD AND
MARSHALLING CABINETS
SECTION 18010
PAGE 3
2.0 PRODUCT
2.1 GENERAL
.1 The distribution panels, auxiliary board and marshalling cabinets shall be non-
ventilated, naturally cooled, metal-enclosed type, flush fronted and suitable for
front access and shall be built to comply with IEC 60439-1. All louvers shall be
covered with wire mesh.
.2 The distribution panels and auxiliary board shall be mounted and house
moulded-case circuit breakers, miniature circuit breakers, residual current
devices and busbars as indicated in the Contract Documents.
.4 All necessary fixing material, mounting bolts, etc. shall be provided for the type of
mounting mentioned.
.5 All operating devices shall be mounted for installation, cable termination and
maintenance operation at the front of the panel.
.6 All distribution panel located outside riser and public area shall have key lock
handle.
.1 The construction of feeder pillar shall comply to local authority requirements. The
contractor shall obtain approval on the location and construction of the feeder
pillar from local authority's.
.2 The feeder pillar shall be Form 1 construction and manufactured from sheet steel
thickness of 2 mm thick minimum, anti-rust coated steel plate. The structure shall
be reinforced with angles or channel irons. The feeder pillar roof shall be a
“house” pattern and not flat.
.3 The feeder pillar shall rest on an angle iron frame where suitable holes have
been prepared to locate foundation bolts and to secure the feeder pillar onto a
concrete footing.
DISTRIBUTION PANELS, AUXILIARY BOARD AND
MARSHALLING CABINETS
SECTION 18010
PAGE 4
.5 Doors for the feeder pillar shall be lockable with either wedge type locks
protected by screw plug or some other form of secret lock approved by the
Employer’s Representative. The doors shall be hinged internally to prevent
unauthorised access. Door hasp shall also be provided for additional padlock
security.
.6 The feeder pillar shall be self-ventilated and weatherproof and complying IP 65.
Anti-corrosive treatment shall be applied to the feeder pillar and shall be finished
with two coats of approved paint. A non-perishable resilient gasket shall be
provided all round the edge of the feeder pillar door.
.7 Additional 20% spares MCCB/MCB shall be provided. Socket outlet and lighting
shall be provided within the feeder pillar for night time maintenance.
.8 Contactor and time switch provided in the feeder pillar shall be approved type.
The activating coil of each contactor shall be wired up by means of a set of minor
fuses so that it can be energised by any of the following: -
.1 The enclosure structure shall be fabricated from rolled steel angle sections and
shall be self supporting when assembled, uniform in height and depth from front
to back. Sheet steel used shall not be less than 2 mm thick, anti-rust coated steel
plate.
.2 The distribution panels, auxiliary board and marshalling cabinets shall be rigidly
constructed to be stand alone units without any danger of sagging, deformation
or warping.
.3 The front covers of the distribution panels, auxiliary board and marshalling
cabinets shall be of hinged-door type. The front doors shall be provided with
lockable push button typed. The doors shall be arranged to seal onto the board
DISTRIBUTION PANELS, AUXILIARY BOARD AND
MARSHALLING CABINETS
SECTION 18010
PAGE 5
.4 For all internal DB, the degree of protection for the enclosures as per IEC 60529
shall at least be IP 41. When the doors are opened, the degree of protection to
all live parts shall at least be IP 20.
.6 The incoming and outgoing cable entry on the distribution panels and auxiliary
board shall be protected with rubber material to prevent cables damage.
.1 All components shall be standardized as far as practical and shall comply with
relevant IEC publications.
.2 Busbars
.1 Busbars for the distribution panel and auxiliary board shall be of plain
hard-drawn, high conductivity, electrolytic copper bars in accordance with
BS EN 13601:2002 and of adequate rectangular cross-section to carry
continuously the specified current without overheating and shall be rigidly
mounted on insulators so as to withstand any mechanical force to which
they may be subjected under maximum fault condition.
.2 Busbars shall be coloured red, yellow and blue and black at appropriate
points to distinguish the phases and neutral. No tapes shall be used.
• Typed test certificates shall be produced for the MCCB selected from
international recognized testing laboratory.
PAGE 6
.1 Miniature circuit breakers shall comply with IEC 60898-1. They shall be
incorporated with overcurrent protection. Their selection for use shall be
matched as their operating characteristics.
.2 Typed test certificates shall be produced for the MCB selected from
international recognized testing laboratory.
.3 Performance Criteria
.1 Breaking Capacity
.2 Co-ordination
.3 Installation
PAGE 7
.4 Construction
.1 Trip Characteristics
.2 Operating mechanism
The operating handle shall be of the toggle type with facility for installation
of padlock device.
All MCB shall have optional field installable accessories like shunt-trip
coil, under-voltage release, ON/OFF indications, alarm switch, etc. The
installation shall be flexible such that to allow for fitting of accessories to
either the left of right side of the MCB.
All MCB must be suitable for remote controlled on/off operations via an
electrical motor operator.
DISTRIBUTION PANELS, AUXILIARY BOARD AND
MARSHALLING CABINETS
SECTION 18010
PAGE 8
.3 Terminals
.2 As a standard, assemblies shall have facilities for the entry of cables from
the top and bottom. Cable entries, cable clamping, earthing facilities and
supporting devices shall be provided suitable for the type, size and
number of cables.
PAGE 9
.9 Wiring shall never be mounted direct to metal. The filling factor for
channels shall be exceed 70%. Where supporting of a wire is not feasible,
the wire or part of it shall be as short as possible.
PAGE 10
.8 All panels shall have a consistent and matching paint finish. The final top
coat colour shall be light grey or manufacturer’s standard colour subject
to Employer representative’s approval.
.11 The equipment supplier shall submit detail of his painting system and
procedures for review and approval by the Employer’s Representative.
3.0 EXECUTION
3.1 INSTALLATION
.1 Distribution Panels
.2 Marshalling Cabinets
.1 When installing earth bars, ensure that the joint surfaces are clean before
tightening bolts of the correct size.
DISTRIBUTION PANELS, AUXILIARY BOARD AND
MARSHALLING CABINETS
SECTION 18010
PAGE 11
.2 Manufacturer shall provide information for unpacking and lifting safely, including
details of any special lifting and positioning devices, if necessary.
.3 On arrival at site, the consignment shall be checked against the delivery notes.
3.3 TESTS
.1 Type Tests
.2 Routine Tests
.1 Before the products leave the works, the manufacturer shall carry out the
relevant routine tests on the total assembly and on parts thereof when
delivered with time intervals and the results shall be recorded in a test
report.
PAGE 12
.1 Dimensions
PAGE 13
.4 Impact resistance test to BS 3900 Pt. E7. Paint shall not chip off.
.4 Site Tests
.1 Visual inspection
.3 Mounting of components.
.6 Earthing system.
Equip the Electrical Room (ER) with the following miscellaneous items: -
PAGE 14
.4 Earthing bar installation along the perimeter of the room connected to the
mainearthbed system.
.1 Provide training schedule and agenda and list of instructors from original
equipment manufacturer (OEM) and the trader contractor.
END OF SECTION
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.1 Manufacture, test at factory, deliver to site, install, test and commission 11kV
metalclad switchboards in accordance with the Contract Documents.
1.3 SUBMITTALS
.1 Tender Stage
.2 Type test certificates of circuit breakers, etc. to ASTA, UL, KEMA and
internationally recognised independent laboratory.
.2 Construction Stage
.5 Schematic/wiring diagrams
PAGE 2
.9 Nameplate information
.11 Full load heat rejection in Btu per hour of each switchboard
.12 Data on structural supports, metal thickness, surface finish, provisions for
lifting and foundations etc.
.4 Site Installation
.3 O&M manuals
.1 Except as modified by governing codes and by the Contract Documents, comply with
the latest applicable provisions and latest recommendations of the following:
PAGE 3
PAGE 4
PAGE 5
.4 Manufacturer shall have full parts back-up and normal (within 1 day) service
availability for equipment provided.
2.0 PRODUCT
.1 The design, manufacturing and testing of the equipment offered shall be strictly
in accordance with this specification and the current editions of the Standard
Specifications and Codes of Practice.
.2 The equipment shall be designed to include all possible provisions for the
safety of those concerned in the operating and maintenance thereof.
.1 Layouts of Equipment
periods and in the final operating conditions. Any queries in this regard
must be submitted in writing to the Engineer.
.3 Where special inspection and testing are required the cost shall be
in the contract price for the equipment and the contractor shall be
responsible for the arrangement of such inspections and testing.
PAGE 6
2.4 PAINTING
.1 General
.1 Cubicles which contain wiring and other apparatus and are assembled in
the works shall receive the external-finishing coat of paint in the works.
2.5 LABELS
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 7
.1 All equipment to be supplied in this contract shall be provided with clear and
concise descriptive labelling describing the function and the circuit number of the
apparatus concerned.
.2 In the case of open busbars, phase identification discs shall be fitted where
practical i.e. for strung busbars on the gantry beam below every string insulator
set and for solid busbars on post insulator support pedestals. These shall be
150mm diameter discs and shall be coloured red, yellow or blue according to
phase and shall be fitted to be visible from ground level.
.1 Where special tools are required for effecting adjustment, for dismantling
purposes or for maintenance, a full kit of such tools shall be provided.
.2 The cost of the special tools shall be deemed to have been included in the price
of the device for which they are required, unless specially listed.
.1 Motorised Operation
.3 Provision shall be made for locking the mechanism in the open or closed position
by means of padlocks.
.4 Control switches must be arranged to operate in one direction when closing and
in opposite direction when opening. The control switches must be spring return
position. An approved method of locking the control switches in the neutral
positions must be provided.
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 8
.6 In the event of the mechanism failing to latch in the closed position, the circuit
breaker shall be arranged to open at normal speed. Provision shall be made for
manual slow closing the circuit breaker for maintenance purposes, but it shall not
be possible to use this facility when the circuit breaker is in the 'SERVICE' position.
.1 The spring of spring operated mechanism shall be motor charged but it shall also
possible to charge the spring manually.
.2 The motor shall be operated from the substation battery supply, the voltage of
which shall be as specified.
.3 Two handle/lever for the manual charging of the spring shall be housed in the
mentioned toolbox.
.4 The spring release coil shall be suitable for operation from the substation battery
supply or any voltage between 80% and 120% of the nominal supply voltage
specified.
.5 The three phases of the circuit breaker shall be operated from a single drive
mechanism.
.6 Control of the spring close/open mechanism shall be possible from the local
control or from a remote source, depending on the position of the ‘local/remote’
selector switch.
.9 It shall be possible to charge the mechanism spring with the circuit breaker in
either the 'OPEN' or 'CLOSED' positions. It shall not be possible for the circuit
breaker to close unless the spring is fully charged. A visual indicating device,
preferably mechanical, shall be provided to indicate 'SPRING CHARGED' when
the spring is in a condition to close the circuit breaker and 'SPRING FREE' when
the spring is not in a condition to close the circuit breaker. If a charged spring is
released when the circuit breaker is closed, the circuit breaker shall not open and
neither shall such operation result in damage.
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 9
.10 The mechanism shall be fitted with a local manual spring release, preferably a
push button, covered to prevent inadvertent operation and provided with means for
padlocking. In addition, an electrical spring release shall be required as specified.
.11 Motor charging of the spring mechanism shall be fitted with DC motor. Re-
charging of the mechanism operating spring shall commence immediately and
automatically upon completion of each circuit breaker closure. The spring shall be
fully charged in not more than 15 seconds. On motor charged mechanisms an
emergency hand operated charging device shall be supplied.
.12 The shunt trip coils and closing spring release coils fitted in the circuit breaker shall
be rated at the DC voltage specified.
.1 Voltage Transformers
.1 Plug-in contacts shall be used and provision shall be made for locking the
voltage transformers in the service or withdrawn position. Shutters shall be
fitted to the spouts and shall open and shut automatically by the insertion of
the voltage transformer. The secondary winding earth connection shall be
made before the primary connections are made. The spout shutters shall
be painted yellow or red depending on whether they are connected to the
circuit side or the busbar side of the circuit breaker and labeled 'VOLTAGE
TRANSFORMER' in white letters. The enclosure for the voltage
transformer shall be appropriately labeled 'BUSBAR VT' or 'CIRCUIT VT' in
red letters.
.2 The ratio, burden and class of the voltage transformers required shall be
as specified. 11,000/110 volt 3 phase voltage transformers shall comply
with the requirements of IEC 60186.
PAGE 10
.7 The primary windings shall be connected to the busbar or feeder side of the
circuit breaker as specified through renewable fuses of adequate breaking
capacity with current limiting features. HRC type secondary fuses shall be
provided. These shall be so placed as not to be accessible to unauthorised
persons but shall be of suitable arrangement for safe removal and
replacement whilst the busbar is live.
.2 Current Transformers
.1 The ratio, burden and class of the current transformers required shall be
as specified in the technical data sheets.
.5 Each current transformer shall be equipped with 5P20, class 0.2 for
metering and class 1.0 for measurement and burden windings are
specified.
.6 The primary windings shall have a short time current rating of not less
than that of the associated circuit breaker.
.9 The tenderer shall ensure that the current transformers are suitable for
the protection relays or metering instruments with which they are to be
associated. Where the relays or instrument are to be supplied on a
separate contract the Engineer, on request, will provide the name of the
contractor concerned or the details of the relays or instruments.
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 11
.10 Current transformer circuits shall be earthed via a removable link in the
control panel and this shall be the only earth point.
.1 The control panel shall be mounted on top of the switchgear panel. Make
up of a separate cubicles for each main circuit. The final panel arrangement must
have a continuous and uniform appearance.
.2 The panels shall be fabricated of steel of not less than 2mm thickness.
.3 The panel shall be capable of being extended at either end by the addition of
further cubicles.
.4 All relays and instruments shall be of the flush mounted type. Particulars of
relays and instruments required shall be as given in the technical data sheets.
The relay cases shall all be earthed.
.5 All relays and instruments must be labeled to indicate their exact function. Relay
type numbers only are insufficient.
.1 Electrical control of circuit must be possible from the local or remote position - a
control switch marked local/remote on or at the circuit breaker shall determine
whether control shall be from the breaker or from a remote source.
.2 Open/Close control switches on the control panel and at the circuit breaker must
be arranged to operate in one direction for a close operation and in the opposite
direction for an open operation. The switches must be spring return to the neutral
position after being operated.
.3 The control and selector switches must be robust and shall be to the satisfaction
of the Engineer.
PAGE 12
2.12 RELAYS
.1 All protective relay shall be of the flush mounting type and shall be contained in
dust-proof case with an interior finish of aluminium or other approved material.
Relays of the hand reset type shall be capable of being reset without the
necessity for opening the case.
.2 It shall not be possible to operate any relay by hand to ‘trip’ without opening the
case.
.3 All protective relays shall, except where otherwise approved, be provided with
double contacts independent of each other, for controlling duplicate tripping
circuits if necessary.
.5 High speed tripping relays shall be self latching and, unless otherwise specified,
the coil circuit shall be broken by self contained contracts.
.8 Distance protection relays (where specified) shall be of the numerical type with
fault recording. They shall have switched, stepped zone tripping characteristics
which depend on the proximity of the fault. The distance covered by each zone
and trip delay(except zone 1which shall be instantaneous) shall be widely and
independently variable. The protection system shall operate correctly under
changing fault conditions such as the remote operation of a fault thrower or
power swing and must provide definite stability for reserve faulting the first two
zones. A following zone shall be provided which shall be non-directional with an
adjustable (definite) time delay. The relay shall be suitable for remote signal
tripping acceleration or blocking. Unless otherwise specified, over current starting
shall be suitable. The range of impedance setting shall suit relatively short
lines/cables and shall be to the approval of the Engineer. Trapezoidal
characteristics are preferred.
.9 Inverse definite minimum time (I.D.M.T) over current relays (where specified)
shall be of the solid state or numerical type and have adjustable operating
settings from 40% to 400% of the normal full load secondary current, with an
adjustable time setting. These over current relays shall provide selectable
alternative time/current characteristics and high set definite time operation.
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 13
.10 I.D.M.T. earth fault relays (where specified) shall be of the solid state or
numerical type and have adjustable operating setting from 8% to 80% of the
normal full relays load secondary current, with an adjustable time setting, these
earth fault relays shall provide selectable alternative time current characteristics
and high set definite time operation.
.11 In cases where the individual over current and/or earth fault elements are
effectively combined into one relay, this relay shall still provide indication to
discriminate the reason the relay has operated (i.e.,I.D.M.T.) over current or
earth fault, high set over current or earth fault) and which phase has faulted.
.12 Restricted earth fault relays ( where required ) shall be instantaneous unless
otherwise specified. They shall be of the high impedance type and shall be stable
under transient and through-fault conditions.
.13 Where pilot wire feeder protection is specified, this may be required to match
existing equipment. Inter-tripping shall be effected by short circuiting the pilots. A
scheme which involves open circuiting the pilot wires will not be accepted. A
matching relay shall be supplied for use on the far end of the protected circuit.
Adequate transient protection shall be provided on the pilot wires (5kV) against
damage to any relays and/or relevant equipment.
.14 Biased Differential transformer Protection, (where specified) shall employ second
harmonic restraint to prevent operating during magnetization inrush, and shall not
required interposing CT’s for ratio correction.
.15 Pilot wire operated inter-trip receive (where specified) shall be provided with low
pass filters to prevent mal-operation as a result of imposed alternating voltages
of up to 5000 volts on the pilot wires. As a common pair of pilot wires will be
required for send and receive, contracts of the local inter-trip send relay must be
wired to open the local receive relay circuit. The master trip relay maybe used for
inter-trip send.
.16 All other relays specified, shall be to the approval of the Engineer.
.17 Relays that employ electronic sensing shall incorporate testing facilities to enable
the function of the relay to be tested without removing it from circuit, while the
primary circuit is on load.
.18 Power supplies for solid state relays must be provided with an alarm contact
which closes when the power supply fails. The primary sources of power shall be
the substation battery.
.19 Breaker fail current check required to initiate high speed back-up tripping
must be built into IDMT relay and shall be to the approval of the Engineer. The
AC circuit of the relay shall have instantaneous operating settings of 20 to 200%
of rated current and shall be continuously rated for at least twice rated current
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 14
and for 30 times rated currents for 2 seconds. The DC circuit of relay shall be
continuously rated for the maximum substation voltage. It must be possible to set
the time delay over a range from 100 milliseconds to 200 milliseconds, The
actual setting being determined after consultation with the Engineer. The
accuracy of the time relay must be within 5% over the working temperature
range.
.21 Provision shall be made for the supply, installation and commissioning
of
remote end pilot wire protection relays unless otherwise specified.
.1 Lamps indicating the switch condition shall be red for closed, green for open.
• The alarm scheme shall be such that whenever any circuit breaker is tripped for
any reason other than operation by means of control switch or a supervisory
control relay, a self-sealing, double-contact common alarm relay centrally
mounted on the control panel will operate. Cancellation of this alarm shall be by
means of a push-button in the sealing circuit of the common alarm relay. This
common alarm relay shall also be initiated by alarm relays such as trip circuit
supervision, if specified.
.1 The circuit breakers, isolators and earth switches shall be provided with all
necessary auxiliary and limit switches required for control, protection, interlocks,
alarm, local indication, supervisory indication and spares.
.2 Auxiliary switches must operate simultaneously with the main contacts (within =
20 milliseconds)
.3 The contacts of all auxiliary switches shall be adequately rated for the service
intended with a minimum rating of 10 amps continuous.
.4 Auxiliary switches shall be wired in series with the trip coil and special attention
shall be given to these to ensure correct timing and liberal rating for breaking
inductive currents.
.5 Auxiliary switches shall be wired in series with the close coil circuit and these
shall be liberally rated to suit the breaking of inductive currents.
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 15
.6 The auxiliary switches shall be easily accessible, even when the primary circuit is
‘live’.
.7 In order to provide for connections to remote alarm and indicating devices, each
circuit breaker shall be provided with spare voltage-free auxiliary switches directly
operated by the operating mechanism for the following:-
.9 These contacts shall be completely wired up to the terminal blocks in the low
voltage compartment.
.10 The characteristics of all control circuit devices and switching elements shall at
least be in accordance with IEC 60947-5-1.
.11 The rated thermal current (Ith) shall be 10A. The utilisation category AC 11 and DC
11 shall be as follows: -
.1 AC 116 - 48V 6A
110 - 127V 5A
.2 DC 116 - 48V 3A
100 - 127V 1A
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 16
.1 The low voltage compartment located at the front of the panel shall house the
following: -
.1 Protective relays
.2 Instruments
.3 Indicator lights
.5 Fuses
.6 Warning sign
.7 Circuit labels
.8 Secondary wiring
.9 Terminal blocks
.1 This contract includes the complete secondary wiring of all items of equipment
supplied on the contract. A secondary wiring compartment shall be provided along
the whole length of the switchboard. It shall be accessible at a suitable location
without having to intrude into any high voltage compartment. This compartment
shall be earthed.
.2 All multicore and low tension interconnecting cables, the installation, jointing and
termination of these shall be part of this Contract.
.4 All secondary cable in ducts and trenches shall be neat and orderly and to the
satisfaction of the Engineer. Cables shall not be allowed to hang freely for
distances in excess of 500mm, and shall be saddled to a rigid structure or
supported on cables trays as necessary.
.5 All terminal blocks for current transformers, relays and instrument connections
shall be neatly finished and readily accessible. Pinch type terminals in which the
screw bears directly on the wire strand will not be accepted. Each end of wire
shall be fitted with the crimp lug/connector suited to the type of terminal provided.
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 17
.6 The design of the wiring cleats/strapping shall be such that only limited pressure
can be transmitted to the wires. Wiring for current transformer circuits shall have
a conductor cross section of at least 2.5mm2, whilst control and voltage circuits
shall be 1.5mm2
.7 Each end of each wire or control cable connection shall be provided with a ferrule
bearing a number corresponding to that on the diagram of connections.
.8 All cables shall be marked with a number tag and the number shall correspond to
the cable number on the cable schedule.
.1 General
.1 All indoor switchgear shall be capable of operating under full load and
fault conditions.
.4 It shall be possible to set and reset all relays from a standing position in
front of the panel.
.6 All auxiliary wiring: Controls, CT’s VT’s, alarms and extra NO/NC contacts
shall be wired to control panel on top of switchgear panel.
.7 Doors shall have stops to prevent over swing when opening to prevent
interference with adjacent panels. The doors shall be suitably reinforced
to prevent distortion when open.
.8 All metal parts including door, relays, instruments, etc., mounted on the
switchgear shall be earthed through branch connections to the
switchboard earth bar.
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 18
.9 Frames of the draw-out circuit breakers shall be connected to the earth bar
through a substantial plug type contact.
.1 Circuit breakers of the vacuum type shall incorporate contacts designed to ensure
a long contact life at all currents up to the rated making and breaking current
switching conditions. Contacts materials having low current chopping levels are
preferred to minimise the occurrence of excessive over-voltages when switching.
.3 The breakers shall be capable of interrupting all currents from zero to the
full asymmetrical rated fault currents at maximum system voltage.
.4 All circuit breakers closing mechanism shall be of stored energy type and shall
be manually or electrically charged. The closing operation shall be initiated
mechanically or electrically. The electrical tripping circuit shall be isolated when
the circuit breaker is in the earthing position. The mechanical close and trip
facility shall be of the lockable pistol grip type arranged for spring return to
neutral.
.5 Circuit breaker spouts and sockets shall be such that all breakers of similar type
and current rating shall be interchangeable.
Note: It shall not be possible to insert a circuit breaker into a higher rated
circuit.
.6 Facilities shall be provided for padlocking the circuit breaker in the ‘racked in’
position.
.8 The main circuit isolating devices and all auxiliary circuit isolating devices
shall be self-aligning and accessible for maintenance. The main isolating
contacts shall be silver plated, self-cleaning and shall be mounted in
porcelain or cast resin bushings.
PAGE 19
.10 Means for measurement of contact erosion without major dismantling shall
be incorporated and an appropriate gauge shall be provided.
.11 Any one interrupter unit should be able to be removed without having to
remove either of those on the other two phases.
.12 Each circuit breaker shall be suitable for duty periods of 27,000 hours
minimum, operating within their rated duties and under the specified
conditions without requiring major repairs or replacements and with
minimum attendance. The operating duty cycle is 0-3 min. -CO-3 min. -CO.
The minimum endurance shall be: -
.13 It shall be possible to remove the circuit breaker completely from the panel
within the withdrawal distance. The circuit breaker truck shall have the
following:-
.4 Spring-charge indicator
.7 Trip counter
.8 A pair of handles
.14 The circuit breaker compartment shall be able to withstand internal pressures
arising from internal faults and it shall be incorporated with a pressure relief flap to
allow safe discharge of any excess pressure without endangering personnel within
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 20
the vicinity of the switchboard. The compartment shall be completely sealed from
the busbar and cable compartments.
.15 Contact material properties shall be such that the specified dielectric strength
across open contacts is obtained at all times.
.1 Each circuit breaker panel shall consist of a metal-clad enclosure with all the
required control and ancillary equipment.
.2 Guides and self-alignment main contracts shall endure that the circuit breaker
and fixed panel contracts are properly aligned and correctly made when the
circuit breaker is racked into service or earthing position.
.3 Movement of the circuit breaker into and out of the service or earthing positions
shall be by mechanical driving system, which shall ensure positive location
without any possibility of damage to contacts or insulation components.
.4 All auxiliary plugs and sockets for making and breaking the circuit of the circuit
breaker shall be self-aligning with guide pins and contacts. In order to achieve
interchangeability, the position and control circuit function of these contacts shall
be the same on all categories of circuit breaker panels of the same rating.
.5 The circuit breaker panel shall have defined indication, clearly visible from the
front of the panel, to show the following:-
- Circuit breaker open and closed, which shall be visible with the circuit
breaker in position applicable.
.1 The switches shall use low pressure SF6 gas for current interruption and shall
require no maintenance. The switch enclosure shall be mounted horizontally
within the cubicle and the position of the main and earthing contacts shall be
clearly visible from the front of the cubicle. The position indicator shall be placed
directly on the contact operating shaft. The switch enclosures shall be made of
cast epoxy resin.
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 21
.2 The switches shall be of the high operating frequency type in accordance with
IEC 60265-1 recommendations. They shall have three positions (closed, opened
and earthed) and shall be fully assembled and tested before leaving the factory.
The relative pressure of the SF6 inside the enclosure shall not exceed 0.5 bars
(500hPa).
The pole unit enclosure shall be of the “ sealed pressure system” type as defined
by IEC 62271-200 recommendations with a service life of at least 30 years. No
refilling of the gas is required over this period.
.4 This compartment shall also house the voltage indicators and the mechanical
‘fuse blown’ indicator for fuse-switch combination units.
.5 The compartment shall be accessible with the cables and busbars live, without
isolating the entire switchboard, and shall be designed for easy installation of
padlocks, key locks, auxiliary contacts, releases and the usual LV accessories.
The front cover of the operating mechanism shall be suitable for the application
of all symbols, mimic diagrams, nameplates and padlocking fixtures required by
the function implemented.
2.21 BUSBARS
.1 All busbars and droppers shall be of suitable cross sections with regard to
temperature rise at the specified altitude and of sufficient mechanical strength for
normal and fault conditions shall be fully insulated.
PAGE 22
.5 The busbar insulation system shall be continued as far as practicable into the
breaker and/or cable compartments up to the next current protective device.
.7 Busbars and connections shall be fully rated, braced and supported to withstand
the dynamic, thermal and dielectric stresses over the full length of the switchboard.
All busbar joints, splice plates and ends shall be silver plated to obtain self-aligning
high pressure contact.
.8 All bolted connections shall be made with high-tensile strength bolts effectively
secured against loosening.
.9 The busbar compartment shall be provided with pressure relief flaps that shall
positively and automatically open in a direction to discharge excess pressure
without endangering personnel within the vicinity of the switchboard in event of an
internal fault.
.2 The switchgear shall be fully interlocked against all possible mal-operation and
shall be so constructed to ensure that:-
- Operation of the circuit breaker is only possible in the service and earthed
position.
- It shall not be possible to rack the circuit breaker until the truck is properly
located in the panel at the approved position.
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 23
- The busbars shutters shall be painted red and circuit shutters shall be
painted yellow. All shutters shall be clearly labeled in letters of the largest
possible size, indicating ‘Cable’ and ‘Busbars’.
Note: All safety shutter shall be provided with suitable arrangements for
padlocking the shutter in a closed position.
2.23 INTERLOCKS
.1 An interlocking system, which ensures safe operation of the equipment under all
service conditions shall be provided. The system shall be non-defeatable.
.2 Mechanical interlocking shall be effective at the point where hand power is applied
so that stresses cannot be transferred to parts remote from that point.
.3 Mechanical means shall be provided so that the circuit breaker shall positively
select the intended position at all times.
.2 it is closed
PAGE 24
.2 The voltage-carrying part of the fixed gear shall be of the female type, while
the movable part of the switching device shall be of the male type.
PAGE 25
3.0 EXECUTION
.1 All equipment shall be packed in a manner such that they are adequately protected
against the tropical climatic conditions encountered during shipment and storage at
site. All fragile parts are to be packed separately in an approved manner. All
equipment shall be labeled for easy identification at site. On arrival at site, the
consignment shall be checked against delivery notes and stored indoors.
3.2 TESTS
.1 Type Tests
.2 Routine Tests
.1 Visual Inspection
.2 Dimension checks
PAGE 26
.18 Dielectric test shall be carried out on the control and auxiliary circuits at 2 x
Un + 1000V (AC) with a minimum of 1500V for 1 second.
.21 Voltage transformer ratio, polarity, phasing and phase rotation check.
Perform test on the three phase voltage transformer to show that
energising each primary winding produces an output from only the
correct phase secondary winding. Measure total burdens connected to
all voltage transformer circuits.
METALCLAD SWITCH BOARDS AND DISCONNECTING SWITCHES
SECTION 18011
PAGE 27
.24 Functional (sequence) test including all DC operated circuits over the
permissible DC voltage limits.
.4 Site Tests
.1 Upon delivery to site, check condition of panels and circuit breakers for
.1 Quantity
.3 Store indoors
PAGE 28
.8 Mounting of components.
.5 Dielectric test shall be carried out on the control and auxiliary circuits
at 2 x Un + 1000V (AC) with a minimum of 1500V for 1 second.
PAGE 29
PAGE 30
.1 The contractor shall obtain and prepare all necessary forms, documents and
drawings for submission and approval from local authority.
.2 The contractor shall obtain all endorsement from Employer’s Representative and
relevant parties.
.1 Provide training schedule and agenda and list of instructors from original
equipment manufacturer (OEM) and the Contractor.
END OF SECTION
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.1 Manufacture, test at Works, deliver to site, install and commission low voltage AC
switchboards, motor control centres and automatic transfer switches.
1.3 SUBMITTALS
.1 Tender Stage
.2 Construction Stage
.6 Schematic/wiring diagrams
.7 Control diagrams
PAGE 2
.11 Full load heat rejection in Btu per hour of each switchboard and
motor control centre
.12 Data on structural supports, metal thickness, surfaces finish and provisions
for lifting and foundations etc
.4 Site Installation
.3 O&M manuals
PAGE 3
PAGE 4
.20 BS EN 13601 Copper and Copper Alloys Copper Rod, Bar :2002
and Wire for General Electrical Purposes
.25 IEC 61641 Guide For Testing Under Conditions of Arcing Due
to Internal Fault
2.0 PRODUCTS
.1 Switchgear and controlgear shall be designed to minimise any risk of short circuit
and to ensure personnel and operational safety during all operating conditions,
inspections and maintenance. They shall also be so designed to allow safe
connection of main, control and auxiliary cables, and the equipping and
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 5
.2 The assemblies shall be suitable for continuous operation at full load for at least
40,000 hours without maintenance which would require the busbar and droppers to
be de-energized.
.3 Even under extreme conditions of major short circuits or mal-operations, there shall
be no danger to persons in the vicinity of the assembly.
.4 The Contractor shall carry out all short-circuit calculations, check the adequacy of
all equipment short-circuit ratings, provide the best protective device and
coordinate all protective devices in the system. Where computer software is used
for carrying out protection coordination exercise, the Contractor shall provide full
details of the software and shall be responsible for all results generated from the
software.
.1 General
.1 The LV switchboards and motor control centres shall be naturally cooled, self-
contained, metal-enclosed type, floor mounted, flush-fronted and suitable for
front and rear access and housing air circuit breakers, moulded-case circuit
breakers, ON/OFF switches, busbars, meters, protective relays, manually-
operated disconnecting switches, selector switches, indicating lamps, current
transformers, cable terminating boxes, anti-condensation heaters, padlocks,
interlocks and other necessary items of equipment. They shall be built to
comply with IEC 60439-1.
.3 All materials, used in the construction and for primary insulation shall be non-
hygroscopic and have fire retardant properties and halogen free as practical.
Insulating materials shall have a high resistance to tracking.
.4 The switchgear shall be suitable for mounting on a concrete floor or plinth. All
necessary foundation or fixing bolts, channel bases and rails shall be
provided.
.5 All operating devices shall be mounted for operation at the front of the
switchboard.
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 6
.7 The switchgear and motor control centres shall fit within the area designated
on the Contract Documents with the clearances as indicated.
.1 The enclosure structure shall be fabricated from rolled steel angle sections
and shall be self-supporting when assembled, uniform in height and depth
from front to back. Rigid construction shall be designed to withstand without
any sag, deformation or warping under the loads likely to be experienced
during normal operation, maintenance or maximum short-circuit conditions,
and shall comply with all requirements of IEC 60439-1 for normal mechanical
loads. Sheet steel used shall not be less than 2mm thick and anti-rust coated
steel plate. Welded cross-struts shall not be used.
.2 The front and rear covers of the switchboard shall be of hinged door type.
The front doors shall be provided with door latches; the rear doors shall be
provided with key locks. The doors shall be arranged to seal onto the board
frame by means of a non-perishable dust proof material. The sealing material
shall be synthetic rubber and not foam. Doors shall be effectively earthed to
the fixed enclosure by braided straps. Cover bolts or nuts shall be retained in
place when undone.
.3 The degree of protection for any assembly as per IEC 60529 shall be IP 41.
The floor shall not be considered as part of the enclosure.
.4 When the doors are opened, the degree of protection to all live parts shall be
at least IP20.
PAGE 7
.3 Anti-Condensation Heaters
.4 Temperature Rise
.1 The temperature rise limits as given in IEC 60439-1(all parts) shall not be
exceeded when the assembly is fully loaded.
.3 HRC fuses and associated fuse carriers shall only be accessible when they
are fully isolated or when they offer a degree of protection to live parts of at
least IP 20 when the fuses are inserted, withdrawn or during withdrawal.
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 8
.6 When a withdrawable unit has been removed from the assembly, the live parts
inside the fixed compartment shall be protected against touch, with a degree
of protection of at least IP 20. When shutters are fitted to comply with above
requirement, they shall be mechanically operated by the movement of the
withdrawable unit and not dependent on gravity. Each set shutters shall be
capable of being individually operated and able to padlock in the closed
position. Shutters covering busbars or droppers shall be marked ‘BUSBAR’
and shutters covering the incoming supply, ‘INCOMING SUPPLY’.
.8 Interlock systems shall be of a mechanical lever type and shall not rely on the
operation of springs or gravity.
.2 The whole busbar system, including the busbar conductors connecting the
main busbars to each outgoing unit, shall be arranged to withstand a short
circuit at any point.
.3 The switchgear shall be designed to withstand any external fault. In the event
of any internal arcing fault on a functional unit, the damage should be confined
to that unit, so that the busbars and all other functional units remain fit for
further service. However, the busbar conductors connecting the busbars to
the outgoing unit might be damaged by the internal arcing fault.
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 9
.4 The time value of the rated short-time withstand current shall be 1 second.
The value of the rated peak withstand current shall in no case be less than 2.2
times the rated rms value of the rated short-time withstand current with a
power factor not higher than 0.2.
.1 In motor starter units, the coordination between starter and protective device
shall comply with type '2' as specified in Sub-clause 7.2.5 of IEC 60947-4.
.3 The short circuit protection device inside each functional unit shall be
connected directly to the incoming supply from the busbars.
.8 Selection of Components
.4 Switching devices shall switch all phases or poles (i.e. 4-pole type for 3
phase + neutral systems). For balanced systems, the neutral pole current
rating shall not be less than as specified for the neutral busbar.
.5 The switching devices shall have padlock facilities in the 'OFF' position.
Mechanical & electrical interlock systems between incoming and sectionalizer
units shall be provided to prevent paralleling of transformers. Components
and devices such as ACBs and MCCBs selected for services as automatic
transfer switches shall comply to IEC 60947-6-1.
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 10
2.3 BUSBARS
.2 Busbars shall be coloured red, yellow and blue and black at appropriate points to
distinguish the phases and neutral. No tapes shall be used. The main busbars
shall be arranged in a horizontal plane and in the order, red, yellow, blue and
neutral phases from back to front. On each panel connections shall be red,
yellow, blue and neutral phases from left to right viewed from the front of the
panel.
.3 The phase and neutral busbars should be located in the top compartments of the
switchboard.
.4 The busbar system shall be readily accessible for inspection, construction and
maintenance duties without the requirement of additional equipment. In case of
a busbar short circuit, it shall be possible to clean or to replace the busbars and
the support system without stripping the assembly.
.5 In the busbar compartment the phase busbars may not be fully insulated.
However, each phase busbar shall be able to withstand at least an applied AC
test voltage of 2.5kV for a period of 60 seconds.
.6 The droppers shall have full segregation by insulated materials. The insulation
of the busbar jointing and branching points shall be of equal quality to that of the
main bars and shall be removable and easily replaceable for inspection.
.7 The neutral bar may be not insulated in the busbar compartment but shall be
insulated at all other compartments with the same insulation level as the phase
busbars.
.8 The earth bar shall be located in the top or bottom compartment and in all cable
riser compartments of the switchboard and shall be easily accessible. Sufficient
connection points with adequate terminating facilities shall be provided for
terminating the cable earth leads. The earth bar shall be sized complying with
IEC 60439-1.
.1 Circuit breakers shall be of the air-break type suitable for indoor use and
withdrawable complete with all necessary instruments, transformers, closing and
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 11
tripping devices and protective instruments. They shall be easily accessible and
operable from the front and provided with padlocking facilities. Both phase and
neutral switching shall be required. Circuit breakers shall comply with IEC
60947-2 regarding their test performance and number of operating cycles, and
shall have a rated short-circuit making and breaking capacity specified in the
drawings and complying with IEC 60947-2 Table II. They shall be trip-free.
.2 Locking facilities shall be provided on the circuit breaker and control switch so
that, in any position, the circuit breaker can be prevented from being directly and
manually operated. Mechanical and electrical lockouts shall be provided to
prevent closing of the breaker after an overcurrent trip.
.3 All operating mechanisms shall have mechanical 'ON' and 'OFF' indicators.
'CLOSED', 'OPEN' and 'TRIPPED' indication lamps shall be provided. Hand
charged or motor charged spring mechanisms shall have mechanical indicators
to show 'SPRING CHARGED' and 'SPRING DISCHARGED'.
.4 All ACBs supplying loads from the main switchboards shall have motor charged
operating mechanisms, which shall be arranged so that release of the spring to
close the circuit breaker can only be done by deliberate action. It shall not be
possible for shocks to release the charged spring. Remote controlled switching
shall also be provided for motor charged operating mechanism ACBs.
.5 Closing and trip control switches shall turn clockwise for closing and anti-
clockwise for tripping and labelled 'OPEN-NEUTRAL-CLOSE' with spring return
to neutral.
.6 The shunt trip coil shall be operated by 240V AC supply unless otherwise stated
in the design drawings.
.3 The spring charged mechanisms cannot be discharged until they are fully
charged.
PAGE 12
.9 Facilities for operational tests of the circuit breaker shall be provided when in the
isolated or withdrawn position.
.10 Provide auxiliary contacts for remote monitoring of all incoming and
Sectionalizing breakers as well as all distribution breakers, on switchboards
supplied from the emergency power system.
.11 ACBs used for distribution on switchboards supplied from the emergency power
system shall have provision for remote operation (OPEN and CLOSE) for load
management.
.12 All protective relays and instruments shall be provided as shown in the design
drawings.
.13 Where specified in the design drawings, the circuit breakers shall have integral
solid-state trip units with built-in overcurrent and earthfault protection having
time-current characteristics. A combination of the following time-current curve-
shaping adjustments shall be provided: -
.1 Ampere setting.
.14 The solid-state trip-unit shall have a digital information system that provides
circuit current values and mode of trip indication (i.e. overload, short circuit, and
earth fault) with fault current levels displayed following an automatic trip
operation.
.15 All solid-state trip units shall be provided with test jacks for in-service functional
testing using a small hand-held test kit.
PAGE 13
.2 Inspections of all contacts (movable and fixed) shall be made from the
front without disconnecting the power cables or the linkages of the
operating mechanism. A manual slow opening and closing of the
contacts shall be provided for maintenance and inspection of the contacts
throughout the entire contact travel. Proper interlocks shall be provided
to prevent inadvertent transfer operation while in the maintenance/test
position.
PAGE 14
.3 Operating Mechanism
.4 Control System
.1 The control system shall direct the operation of the transfer switch via
wire connections to the operating mechanism. The connections of
auxiliary circuits shall be of the plug-and-socket type, which shall
permit the disconnection of the control module for maintenance.
.1 Relays provided in the control circuitry shall comply with the relevant
IEC and as far as possible be standardized. Relays shall be capable
of withstanding without damage 110% of the rated operating voltage.
PAGE 15
.8 Test switch.
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 16
.6 Spare Contacts
.1 Four (4) spare auxiliary contacts, two (2) closed with switch in
emergency position, and two (2) closed with switch in normal position.
.1 Moulded Case Circuit Breakers and Motor Circuit Protectors shall comply
with IEC 60947-2.
.3 The MCCB and MCP shall be so designed that when on tripped condition, the
circuit breaker cannot be switched on unless it has been reset by switching it to
the OFF position first. The operating condition (i.e. ON, OFF or TRIP) of the
circuit breaker shall be clearly indicated. The construction and operation of the
MCCB and MCP shall be such that if a fault occurs, all the poles of the breaker
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 17
shall operate simultaneously to isolate and clear the fault efficiently and safely
without any possible risk to the operator or to the installation.
.4 Each MCCB and MCP shall incorporate a 'trip free' mechanism to ensure the
breaker cannot be held closed under fault conditions. The operating mechanism
of the circuit breaker shall be hermetically sealed at the factory and all metallic
parts associated with the operating mechanism shall be treated against rust and
corrosion.
.5 Bolt-in type solid neutral links shall be provided and fitted in the same
compartment together with the phase poles.
.6 Means shall be provided to padlock the MCCBs and MCPs in the 'OFF'
position. Mechanical 'ON'/'OFF' indicator operating in conjunction with the rotary
type operating handle of the circuit breaker must be provided.
2.8 CONTACTORS
.1 Contactors shall be the holding coil type with an operating voltage derived
from
phase and neutral.
.2 The contactors shall be suitable for making and breaking at 0.35 power
factor the
stall current of the associated motors which shall be assumed equals 8 times
full
load current of the motors.
PAGE 18
.4 Contacts shall be renewable butt type, solid copper, hard silver faced, fully
shrouded main and auxiliary contacts and the designs shall be such as to ensure
effective freedom from contact bounce and sticking of the fixed and moving
portion of the magnet assembly.
.7 Magnets shall be fabricated from silicon alloy riveted electrical steel sheet
with
shaded poles. Magnet/armature assembly shall be fully floating and
self- aligning.
.8 Arc chutes and magnetic blow out coils shall be fitted where appropriate
and to
manufacturer's requirement.
.9 With reference to IEC 60947-4, motor starters and contactors shall conform to
the requirements of both uninterrupted duty and intermittent duty class 0.1 (12
operating cycles per hour), at rated operational current and shall have a
mechanical endurance level of 300,000 no-load operating cycles.
.10 The utilization category AC-3 (starting of squirrel-cage motors, switching off
motors during running) shall be applied. For motors in inching or reversing
rotating service, utilization category AC-4 shall be used.
.11 For special loads such as transformers, capacitors, lighting, etc. a suitable
current rating and utilization category shall be selected by the manufacturer and
in compliance to IEC 60947-4-1.
.12 Position indication of contactors shall be fitted on the front of the compartment
by clear red light for 'ON' and clear green light for 'OFF'. The indication lights
shall be of the long life, low power consumption type, e.g. multi segment LED or
neon.
.13 In addition to the required number of auxiliary contacts needed for the control
and indication circuits, each contactor and motor starter shall be provided with at
least one make and one break contact element, double gap, potential free, and
wired up to the auxiliary terminal block of the compartment.
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 19
.2 When analogue current transducers are required, they shall have an output
signal of 4-20mA.
.3 Accuracy class shall be in accordance with the design drawings. . The short-
circuit rating shall be at least 1 second if applied for short-circuit protection. The
wiring of the secondary circuits shall have a cross section of at least 2.5mm 2.
Secondary terminal shorting-links shall be provided for every current transformer.
.4 Secondary circuits of all current transformers shall be earthed.
.5 Undervoltage relay.
PAGE 20
.1 Where stated in the design drawings, the following measuring, indicating and
control devices shall be provided: -
.2 Kilowatt-hour meter
.3 Kilovar-hour meter
.4 Ammeter
.5 Voltmeter
.7 Indicating lamp
.8 Timer
.9 Control relay
.1 Provide the type of residual current devices indicated in the Contract Documents.
.4 For bus wiring and outgoing control circuits, individual terminals shall be provided
for each external conductor. These terminals shall be of the non-loosening,
wedge type construction, obviating the use of cable lugs.
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 21
.5 They shall be constructed in such a way that direct contact between screw, bolt
or nut and conductor is avoided. For the termination of internal control wiring,
push-on connections with insulation support of the compression type may be
used.
.6 Terminals shall be identified in accordance with the related wiring diagram. The
layout shall be consistent and logical.
.7 As a standard, assemblies shall have facilities for the entry of cables and busbar
trunkings from the top. Busbar trunking and cable entries, clamping, supporting
and earthing facilities shall be provided suitable for the type, size and number as
specified. Coordinate phase configuration of all busbar trunking connection to
switchboards.
.9 Cable glands for lead sheathed or armoured single-core cables shall allow for the
insulation of the lead sheathing or armouring from the gland plate. Moreover, the
gland plates and the individual cable soldering cones or glands or single-core
cables shall be of non-magnetic material.
.1 Both ends of each conductor shall be provided with identification ferrules. The
ferrules shall be of insulating material which shall be unaffected by oil or
moisture. Characters shall be suitably marked in black. The ferrules shall be of
the continuous ring type, not of the slip-on type. Markings shall be in accordance
with the related manufacturer's drawings.
.2 For secondary wiring, PVC insulated interconnection wires shall be used. The
size and type of the wires to be selected shall be based on mechanical strength,
voltage levels and, especially for current circuits, on the prospective current
levels.
.3 The minimum allowable cross-sectional area of the wires shall be 1.0 mm2. Wires
with a cross section bigger 1.5 mm2 shall always be stranded.
PAGE 22
.5 Colour coding of secondary wiring shall be in accordance with IEC 60446. Earth
wires shall be green/yellow striped. Wiring between two terminals shall be
continuous. Joints or interconnections are not allowed.
.6 For the manufacturer's internal panel wiring, other than bus wires, no more than
2 wires shall be connected under one terminal connection. Bus wires shall have
only one wire connected to each terminal.
.10 To accommodate and support the secondary wiring, covered plastic channels,
insulated tubes or plastic strips shall be used.
.11 Secondary wiring shall never be mounted direct to metal. The filling factor for
channels shall not exceed 70%. Where supporting of a wire is not feasible, the
wire or part of it shall be as short as possible.
.12 Termination compartments for auxiliary and control cables shall have adequate
dimensions, with ample accommodation for the required number of terminals.
Two or more conductor terminations on one terminal are not acceptable.
.13 Metal cable glands suitable for the cables specified shall be included in the
supply of the assembly.
.14 There shall be adequate marshalling space between the cable glands and the
terminal blocks.
.15 All current transformer terminals shall be provided with shorting links. Other
terminals shall be provided with disconnecting links.
.16 Test terminals and plugs shall be provided at the front of the protective relay and
instrument panel.
PAGE 23
.1 For the purpose of remote monitoring and alarms additional auxiliary contacts
shall be provided for each circuit of the following: -
.1 Normal supply.
.2 Emergency supply.
2.16 EARTHING
.1 The equipment earth bar along the full length of the enclosure shall
consist of hard-drawn high conductivity copper. Where the substation
consists of 11kV switchgear, transformer and LV switchboard, the earth
bar shall be continuous along the full length of the substation. It shall be
connected to the main system earth bar at both ends using appropriate
size earthing bolts with nuts and spring washers. The cross-section of
the bar shall be sufficient to carry the rated short-time withstand current of
the switchgear for the allowable temperature rise and the time specified.
.1 Branch earth connections made from the equipment earth bar to the
components shall consist of adequately sized copper strips or
green/yellow striped PVC sheathed stranded copper conductor.
Termination lugs shall be of the compression type.
.1 All metal parts including door, relays, instruments, etc., mounted on the
switchgear shall be earthed through branch connections to the equipment
earth bar.
PAGE 24
.1 General
.1 Nameplates and their fixing materials shall be proven durable under the
service conditions specified for the switchboard, motor control centre and
automatic transfer switch. They shall be moisture and rodent proof and
provided with indelible inscriptions in the language specified.
.2 Labels
.1 Circuit labels shall be provided at the front and rear portion of the
switchgear, automatic transfer switch etc. in a prominent position.
.2 Each panel shall be provided with labels including, but not limited to, the
following: -
.3 Fuses.
.4 Instruments.
.5 Protective relays.
.6 Warnings
.3 Phase Marking
.1 All busbar and power cable terminals shall be provided with permanent
phase markings. No tapes are permitted.
.4 Material
.5 Fixing
PAGE 25
.6 Colour
.1 All metal structures and sheet steel shall be adequately protected against
corrosion. Preparation of surfaces for painting shall be made complying with BS
7079. All mill scale, loose rust and welding slag, shall be removed by hand tools
and the metal surfaces shall be cleaned free from dirt, oil, grease, wax and other
contaminants.
.4 All panels shall have a consistent and matching paint finish. The final top
coat colour shall be light grey or manufacturer's standard colour subject to
Employer Representative's approval.
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 26
3.0 EXECUTION
.1 Prior to installation ensure that the room is free from construction debris and that
all cable ladders, HV cables, LV cables and control cables have been properly
installed in the switchboard room and ready for eventual connection to the
switchboards motor control centre and automatic transfer switches.
.2 Install the switchboard, motor control centre and automatic transfer switches in
accordance with this specification, the manufacturer's instruction and within the
designated switchroom as shown in the design drawings.
.4 Install foundation channels such that they are flush with the floor.
.5 Positions bolt securely each panel of switchboard and motor control centre on
the foundation channel according to manufacturer's recommendations. All
switchboards and motor control centres shall be installed level and plumb.
Fronts shall be lined up and must present a neat and orderly appearance.
.6 When installing main busbar and earth bars ensure that the joint surfaces are
clean before tightening bolts of the correct size. Provide permanent phase
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 27
.7 For automatic transfer switches connect from auxiliary contact (closed before
switch returns to normal power) on transfer switch serving lift to each lift machine
room, which is served via the transfer switch. Terminate as and where required
by the lift vendor.
.8 For automatic transfer switches connect from auxiliary contact (closed before
switch moves to emergency position) on transfer switch serving lift to each lift
machine room, which is served via the transfer switch. Terminate as and where
required by the lift vendor.
.9 For automatic transfer switches connect from engine start contact on transfer
switch to emergency generator control panel.
.10 Insert withdrawable circuit breakers and check and adjust alignment. Check
alignment of auxiliary contacts.
.11 Complete and check inter-panel wiring and power and control wiring prior to pre-
commissioning.
.12 Upon completion of installation terminate all the respective, control cables, bus
ducts into the switchboard respective terminals.
.15 Certify that all the required tests have been performed and that the switchboards
and motor control centres are performing in accordance with the contract
requirements.
.16 Seal all the rear and top panel of the switchboard motor control centres and
automatic transfer switches using the prescribed seals.
.19 Records shall be kept of installation works and submitted to the Employer's
Representative.
.20 When terminating cable ensure that the joint surfaces are clean before tightening
bolts of the correct size with cable lugs.
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 28
.21 Padlock all the circuit breakers in the off-position and keep keys in the lockable
key cabinet.
.22 Carry out touch-up work on the paintwork of the switchboard, motor control
centre and automatic transfer switches and clean all surfaces.
.1 All power cable installation works shall be carried out after studying and
coordinating the recommendations of the cable manufacturer and the
switchboard, motor control centre and automatic transfer switch manufacturer.
.1 Switchboards, motor control centres, and auto transfer switches shall be packed
and delivered appropriately labelled in accordance with the manufacturer’s
recommendations. Each packing shall be provided with the respective label as
shown in the contract drawings for easy identification at site. All interconnecting
busbars, earth bars and insulation material/components etc. shall be packed
separately. They shall be securely packed to prevent any movement and
damage during transport and against tropical climatic conditions encountered
during shipment.
.3 Each switchboard, motor control centre and auto transfer switch shall be supplied
complete with: -
.1 Foundation channels
.2 Foundation bolts
.3 Interconnecting busbars and insulation materials, etc.
.4 Accessories
.4 On arrival at site, the consignment shall be checked against the delivery notes.
• On delivery to site, the switchboards motor control centre and automatic transfer
switches shall be stored indoor in a clean, dry and ventilated place. For
LOW VOLTAGE AC SWITCHBOARDS,
MOTOR CONTROL CENTRE AND ATS
SECTION 18012
PAGE 29
3.4 TESTS
.2 Routine Tests
.3 Special Test
PAGE 30
.1 Dimensions.
PAGE 31
.4 Impact resistance test to BS 3900 Pt. E7. Paint shall not chip-
off.
.5 Site Tests
.1 Visual Inspection
PAGE 32
.7 Mounting of components.
PAGE 33
.4 A 5 mm thickness and 1000 mm width rubber mat in front and at the back of the
entire length of the switchboard, motor control and automatic transfer switch.
.7 Earthing bar installation along the perimeter of the room connected to the main-
earth bed system.
.1 Provide training schedule and agenda and list of instructors from original
equipment manufacturer (OEM) and the supply contractor.
PAGE 34
END OF SECTION
EARTHING SYSTEM
SECTION 18013
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.1 Provide low impedance earthing systems and connections for equipment earthing in
accordance with the Contract Documents.
1.3 SUBMITTALS
.1 Tender Stage
.2 Construction Stage
.4 Construction/working/shop drawings
.4 Site Installation
PAGE 2
.3 O&M manuals
.1 Except as modified by the Contract Documents, comply with the latest applicable
provisions and latest recommendation of the following: -
PAGE 3
2.0 PRODUCT
2.1 GENERAL
.4 Exothermic welds
• Testing joints
• Earth chamber
.2 For the bored pile reinforcement bars in the core area of the building, they will be
interconnected with a conductor loop to obtain a low resistance to earth.
.3 Earth Conductor
.1 Earth conductor laid in the earth or soil shall be bare type. Earth conductor shall
2
be soft drawn copper stranded wire of not less than 95mm . Allowance of five (5)
percent slack shall be provided before casting the concrete floor slab.
EARTHING SYSTEM
SECTION 18013
PAGE 4
.2 PVC copper conductor shall be green in colour. If PVC copper conductor used
as neutral earth, it shall be black in colour.
.4 If PVC covered copper tape is used as neutral earth, it shall be black in colour.
.5 Exothermic Welding
.1 Exothermic welding connections shall be provided for all buried connections and
connection between copper stranded wire to steel reinforcement bar. The
method of welding shall be as follows: -
.1 Install the portion of copper conductor into a mould and fire the
powder in the crucible, which produce a super- heated flow of
molten copper into the mould.
.1 The system earthing shall be installed complying with the following criteria: -
PAGE 5
.3 Earthing of Main Columns. The main structural columns shall be bonded with
exothermically weld and earthing leads will be taken to the above pits.
.2 All earthing of trunking, cable trays, cable ladders, conduits, junction boxes,
lighting fittings, general socket outlets, equipment.
.2 The building earth-bed system shall consist of continuous loop connection of the
respective pile cap locations using buried bare copper stranded wire and exothermically
welded. The disconnection of earthing conductors from the earth-bed shall only be made
at the earth bars. All earth points shall be flushed to column surface for connection to
respective services.
.3 The groups of earthing points shall be interconnected with each other with a copper tape
to which all electrical plant and metal work is bonded. Connections to the earth
2
electrodes shall be by means of 95mm PVC insulated green copper cables. Each
earthing strip shall be extended by 25 x 3mm Hard Drawn High Conductivity copper
tapes connecting the non current carrying metal work of all ancillary apparatus supplied
EARTHING SYSTEM
SECTION 18013
PAGE 6
under the works to the main earth bar. It shall be installed at a height of 300mm above
floor finishes level.
.4 Separate earth bar shall be provided for the building system earth. The method of
connection shall permit convenient disconnection by means of a tool for the purpose of
measurement and testing of earth loop impedance. No other joints should be allowed; if
the copper tape or stranded conductor is not adequate to complete the loop, exothermic
welds shall be used to joint two sections.
.5 Earth connections shall run in approved positions and fixed in an approved manner
generally in square and symmetrical line using gunmetal saddles of appropriate size for
securing tapes at intervals not exceeding 900 mm. The copper tapes shall be supplied in
long unbroken lengths to avoid unnecessary jointing, unless otherwise, all joints shall be
exothermic welded.
.6 The mating surfaces of all tapes at joints etc. shall be tinned before clamping and the
joints shall be tinned, riveted and soldered. All connections to electrical apparatus shall
be made by a bolted connection in a visible and accessible position.
.7 All joints in exposed sections shall be protected against corrosion and the ingress of
moisture by the application of two coats of an approved anti corrosion paint.
.8 The earthing systems shall include for measuring, making off, cutting, fitting and erecting,
the supply of necessary clamps and rag bolts complete with all fixing screws and rivets
for fixing and jointing the copper tape including the necessary lugs, installation material
and the use jointers tools.
.9 The earth connection for all sections of the installation shall be electrically continuous
throughout.
.10 All transformer and generator set neutral connections shall be brought directly and
connected to the plantroom main earth bars by exothermic welds such that
disconnection of the neutral can only be made at the individual transformers and
generator set. Neutral earthing conductors shall be insulated to distinguish from
frame earth conductors. Clear distinction shall be provided.
2.4 EARTHING POINTS (IF EARTH BED SYSTEM USING PILECAP NOT APPLICABLE)
.1 Each earthing point shall comprise and extensible type 15mm diameter hard drawn, solid
copper rod with internal screw and socket joint, hardened steel tip, driving head and
connector clamp.
.2 The combined resistance of the earth electrodes shall be less than one ohm and the
requirements of local authorities and/or utility providers shall take precedence.
.3 Contractor shall carry out soil resistivity tests on site and to ascertain the location and
number of earth points required, and allowance for such tests shall be made in the
Contract. The Contract sum for earthing shall cover any number of points or method
required achieving the required earthing resistance. The testing shall be carried out to the
EARTHING SYSTEM
SECTION 18013
PAGE 7
satisfaction of the Employer’s Representative with a digital four-pole earth tester and
other relevant testing apparatus to be provided by the Contractor.
.4 Where more than two (2) electrodes are driven to form a group, the heads of the
electrodes in the group shall be bonded to each other by means of copper tape, laid at a
depth of 600mm in the ground.
.5 Where group conditions are favourable for the use of rods in parallel to form a group, the
distance between the rods should be at least equal to twice the driven length.
.6 Earth chamber c/w cover shall be provided. The Contractor shall include for the driving of
all earth electrodes, connecting to the main earth bar and testing to the satisfaction of the
Employer’s Representative.
.1 A looped earth conductor shall act as the main earth bar installed within the
electrical rooms or plantrooms. The main earth bar shall be sized to carry the
rated short-circuit current without creating any fire risk.
.2 Minimum two (2) copper tape conductor shall be extended in separate route from
the main earth bar to the equipment earth bar in each switchgear, transformer,
switchboard, motor control centre, generator set and other frame earth.
.3 Conductors from the main earth bar shall be provided as indicated in the design
drawings.
.3 Where equipment earth bars are provided e.g. switchgear, main switchboards,
motor control centres, the respective circuit protective conductors shall be
connected to them. The sizes of circuit protective conductors shall be in
compliance with BS 7671.
PAGE 8
.3 Install bonding jumper across flexible conduit from transformer enclosure to rigid
conduit.
.4 Generator Set
.1 Where busbar trunking routes to switchboard, the integrated earth bar in the
busbar trunking shall be extended to the earth bar on the switchboards.
.2 Where busbar trunking are served via cable tap boxes; earth conductors from
earth bar in the busbar trunking shall be extended to equipment earth bar of
switchboard.
.3 All busbar trunking tap-offs and fuse devices shall have earth connection within
them for positive connection to earth bar of the busbar trunking.
.6 Cables
.1 Cable armour, cable metallic sheath, enclosures, frames, fittings and other metal
non-current-carrying parts that are to serve as earthing conductors shall be
effectively bonded where necessary to assure electrical continuity and the capacity
to conduct safely any fault current likely to be imposed on them. The armour or
metallic sheath of 3-core or 4-core cables shall be earthed at both ends. Any
nonconductive paint, enamel, or similar coating shall be removed at threads,
contact points, and contact surfaces or be connected by means of fittings so
designed as to make such removal unnecessary.
.7 Cable Trays
.1 Metallic paint systems shall not be used as principal earth return path in full
length. Separate earth conductor shall be provided.
.8 Cable Trunkings
.1 Metallic paint system shall not be used as principal earth return path. Separate
link earth conductor shall be provided in the form of copper tape of minimum 35
mm sq. size.
EARTHING SYSTEM
SECTION 18013
PAGE 9
.1 Install bare copper bonding jumper between underfloor duct sections on both
sides of expansion joint using pressure type lugs with embedding type-bonding
screws.
.1 All raised floors shall be electrically bonded for grid earthing purpose.
.2 25mm² PVC insulated earth cables and connectors from opposite ends of raised
floor shall be connected to panel board serving that area.
.1 All socket outlets, switches and lighting luminaries shall be earthed by means of
a green/yellow PVC covered copper protective conductor.
.2 Install bonding jumpers between outlet box and socket outlet earthing terminal
except where contact device is provided for earthing purposes.
.3 Motors shall use the armours of the power supply cables as protective earth
conductors. Approved glands shall be provided for bonding. The armours shall
be sized to carry the prospective short-circuit currents. If the cross section of the
armour is inadequate, a separate protective conductor shall be used.
PAGE 10
.1 Main telephone terminal board and riser terminal boards shall be earthed by
installing a bare copper tape riser between the building service earth and the last
riser terminal board. The design, routing and location of the telecommunication
earth riser, terminal bar and earth connections shall be similar to that of the
distribution earthing system. At each terminal riser board, one (1) copper wire
from the telephone riser earth shall terminate at the riser terminal board. The
method of bonding shall be similar to that of the distribution earth system.
.3 Facilities for the connection of the earth of electronic equipment at every floor
shall be provided for connection of earth conductors.
.1 Label all the various types of earth at every floor. All the earth connection terminals and
earth test points shall be correctly labelled. Identification plates shall be white bakelite
plates with black engraved upper case letters enclosed by black border with bevelled
edge.
3.0 EXECUTION
3.1 TESTS
PAGE 11
.3 Sufficient prior notice shall be served to the Architect / Engineer for the
inspection of the welding of reinforcement extension prior to concreting of the pile
cap. Prior to testing, the methodology for testing shall be submitted to the
Architect / Engineer for approval. No testing is permitted without approval of
testing procedures.
.5 The earth resistance at each bore pile shall be of the order of 3 ohms or less.
Should the resistance reading of any of the bored piles before concreting of pile
cap exceeds 3 ohms, additional bonding to the other starter bars of the bored pile
shall be provided, if instructed by the Architect / Engineer, to achieve lower
resistance to earth.
.2 Site Tests
.1 All site tests shall comply with the requirements of BS 7430 and BS 7671.
.3 Visual Inspection
PAGE 12
.5 Continuity Test
END OF SECTION
LIGHTNING SYSTEM
SECTION 18014
PAGE 1
1.0 GENERAL
1.1 DESCRIPTION
.1 Provide all labour, materials and items of service required for the completion of a
functional and unobtrusive lightning protection system in accordance with the Contract
Documents.
.1 All materials, equipment and components for a safe and durable lightning protection
system in accordance with IEC 62305, BS 6651 and BS 7430.
1.3 SUBMITTALS
.1 Tender Stage
.2 Construction Stage
.4 Site Installation
PAGE 2
.3 O&M manuals
.1 Except as modified by the Contract Documents, comply with the latest applicable
provisions and latest recommendation of:
PAGE 3
2.0 PRODUCT
2.1 GENERAL
.4 Test Joints
LIGHTNING SYSTEM
SECTION 18014
PAGE 4
.5 Earth Terminations
.6 Connections and bonding to external metallic curtain wall, parapet railing and
metallic parts located on the roofs and the sides of building.
• Air terminations shall be firmly secured by suitable fixing bolts, screws and clamps to
establish good electrical continuity from lightning rods to roof conductors and to ensure
that they are securely held in position under the influence of mechanical stresses during
the passage of lightning currents. Roof conductors shall be secured by suitable clamps 1
meter apart. Part of the building structure, roof, parapet railing, metallic curtain walls and
other exposed metallic parts, etc. shall act as lightning air terminations. Special
consideration shall be given in the installation of air termination system in view of the
height of the building and the requirements of an aesthetically pleasing appearance but
without compromising inspection, performance and maintenance requirements.
.1 The number of down conductor connecting the air termination and/or down conductor
shall be provided as shown in the design tender drawings. Down conductors shall be
brought straight down to its own earth termination with the least looping possible so as to
prevent unduly high electrical stresses during the passage of lightning currents. Each
down conductor, in the form of 95 mm sq. PVC copper cables indicated in the tender
drawings, shall be secured firmly by clamp to the bar within the building column at 1
meter intervals from the point of roof conductor connection to the earth termination and
shall be able to withstand mechanical stresses during the passage of lightning current.
For building height of more than 60 meter, tap-off points in the form of 25 m X 3 mm
copper tapes shall be provided at intervals indicated in the tender drawings, connecting
the metal parts of the building façade to each of the vertical down conductors. Such
connection shall protect against the in-direct flashing on the building.
.1 All external metal parts shall be effectively bonded to the lightning protection system.
Where metal parts are long, e.g. service pipes, metal sheaths, ladders, etc. bonding shall
be provided at their extremities. Attention shall be given to the bonding of metallic curtain
wall to prevent side flashing while acting as air termination.
2.5 CORROSION
.1 All materials selected for the lightning protection system shall offer resistance to
corrosion. Care has to be given to the contact of dissimilar metals such as copper and
aluminium. Proper friction-welded bimetallic connectors shall be provided.
PAGE 5
.1 Each down conductor shall be provided with a test joint in such a position that, while not
inviting unauthorised interference, it is convenient for use during testing. The down
conductor used to connect the test joint and the earth termination shall be of copper and
of the same dimensions as the upper down conductor.
2.8 MATERIAL
.1 All materials and components shall be similar to those used for the purpose of system
earthing.
.1 General
.3 Surge Protection Devices for MSB, SSB & DB shall be under one manufacturer
to ensure products compatibility.
.4 Third party test report on the let-through voltage and kA rating per phase is
mandatory to be submitted for performance review approval.
.2 Surge Diverters for Main Switch Boards(MSB), Essential Main Switch Boards (EMSB)
and AMF Board
.1 Surge Diverters for MSB, EMSB and AMF shall require minimum rating of
200kA(8/20us) per phase c/w status display and multiple redundant modes.
.2 Surge Diverters shall provide full mode protection (L-N, L-E & N-E)
.3 Surge Diverters shall have let through voltage less than 800V p (L-N,L-E & N-E),
when tested at 6kV (1.2/50us) and 3kA (8/20us) combination wave as per IEEE
C62.41 1999 and BS 6651: 1999 cat C test.
PAGE 6
.1 Surge Diverters for SSB shall require minimum rating of 80kA (8/20us) per
phase c/w status indicators.
.2 Surge Diverters shall provide full mode protection (L-N, L-E & N-E)
.3 Surge Diverters shall have let through voltage less than 600Vp (L-N, L-E & N-E),
when tested at 6kV (1.2/50us) and 3kA (8/20us) combination wave as per IEEE
C62.41 1999 and BS 6651: 1999 cat B test.
.1 Surge Diverters for DB shall require minimum rating of 40kA (8/20us) per phase
c/w status indicators.
.2 Surge Diverters shall provide full mode protection (L-N, L-E & N-E)
.3 Surge Diverters shall have let through voltage less than 600Vp (L-N, L-E & N-E),
when tested at 6kV (1.2/50us) and 3kA (8/20us) combination wave as per IEEE
C62.41 1999 and BS 6651: 1999 cat B test.
3.0 EXECUTION
3.1 INSTALLATION
• The installation of all conductors and components shall be a such a manner that the
completed work is unobtrusive and does not detract the appearance of the building but
without compromising inspection, performance and maintenance requirements that are
necessary during the life of the building.
.3 The design of the lightning protection system shall not only ensure the protection of the
buildings from downward flashes but upward flashes as well taking into consideration the
building height and high ceramic level experience at the location. The design shall
employ the Faraday Cage Principle to protect people and equipment within the building.
No side flashing shall be allowed.
3.2 TEST
.1 Site Tests
.1 All site tests shall comply with the requirements of BS 7430 and BS 7671.
.2 Visual Inspection
PAGE 7
.3 Continuity Test
END OF SECTION