VDC Execution Plan: XYZ Research Facility
VDC Execution Plan: XYZ Research Facility
For
0
Table of Content
Description Page
Executive Summary 2
Appendices 21
1
Executive Summary
The intent of this VDC Execution plan is to provide a framework that will let the Owner, Design
Professional, engineers, and Contractor deploy building information modeling (BIM) technology
and best practices on this project. This plan delineates roles and responsibilities of each party at
each phase, the scope and level of detail of information to be developed, data to be managed and
shared, processes defined, and software to be utilized.
Virtual Design and Construction (VDC) is a process for the project stakeholders to leverage data-
driven BIM deliverable to make more informed decisions about the design, performance, cost,
and/or schedule, through applied workflows and software tools.
The VDC Execution Plan should be considered a living document and can be developed and
refined throughout the project’s life cycle to ensure the project remains on schedule and meets
briefed requirements.
2
2. Project Schedule & Milestones
Design Stage
Owner, Architect,
Structural Consultant,
Design development phase
09-07-2021 09-08-2021 MEPFF Consultant,
LOD 200-300
General Contractor,
BIM Manager
Owner, General
Construction Documents
Phase
Contractor, Bim
10-08-2021 30-08-2021
Manager, Project
LOD 300 Complete
Manager
Construction Stage
Owner, General
Project close-out phase Contractor, Bim
13-09-2021 23-11-2021
LOD 500 Complete Manager, Project
Manager
3
Section 2: Key Project Contacts
The intent of the team is only to help clarify contractual obligations of the team members and
stakeholders. No portion of this is intended to redefine or override any contractual obligations each
party owes under their respective contracts.
1. BIM Roles and Responsibilities
This section is intended to cover the macro level major responsibilities of the team members.
2. Project Contacts
These are the primary management and technical contacts. These contacts should be used to seek
immediate resolution of projects coordination challenges.
Design Team
Structural
STR DEF CA [email protected] ##########
Consultant
4
Construction Team
Client
Client LMN California [email protected] ##########
representative
Priority / Goal /
Measurement
Primary Responsibility
Achieved if
5
Measurement Achieved if: Track code compliance through construction.
Builder / Report any code related issues to the team
● Energy consumption Contractor including costs to the project in both dollars and
projections are reduced time.
by >15% using the
model. Perform root-cause analysis on any code issues
Architect that cost the project during construction and
● No substantial code present the results to the team.
violations surface
during construction.
Ensure that strategies for energy consumption
MEP
reduction are taken from design to the real
Contractors
world. Report any deviations to the team.
Priority / Goal /
Measurement
Primary Responsibility
Achieved if
Measurement Achieved if: Builder / Track quantity and impact of RFIs and provide
Contractor competitive feedback to the project team.
● Change orders and RFIs
are reduced by 50% or MEP Track percentage of off-site fabrication. Inform
more from a traditional Contractors team on benefits and challenges encountered.
project.
Owner / Track and report to the team overall costs.
● 50% or more off-site Operator Provide this in comparison to historic cost data.
fabrication.
● See overall reduction in
gross sq. ft. cost
compared to traditional
project. See large
reduction in last minute
changes.
6
2. BIM Uses
After careful consideration the team has decided on a number of BIM uses on the project. These
uses are based on what stage of the project they are to be completely implemented.
LOD LOD LOD LOD LOD LOD LOD
-100 -200 -300 -350 -400 -500 -500
(Pre- (Sche (Desi (Cons (Fabr (Clos (Oper
desig matic gn tructi icatio eout) ation
n) Desig Devel on n/ &
n) opme Docu Const Mana
nt) ments ructio geme
Maturity BIM Uses
) n) nt)
Visualization Programming X X
Site Analysis X X
Design Reviews X X X
Design Authoring X X X
Record Modeling X X
COBie X X X X X X
a. Energy Analysis X X X
b. Structural Analysis X X X
c. Lighting Analysis X X
d. Mechanical Analysis X X
Disaster Planning X X X X
3D Coordination X X
7
Integrated Construction System Design X
Analyses
3D Control and Planning (Digital X
Layout)
Digital Fabrication (Supply chain
management)
Asset Management X
The use and deployment of the VDC Scorecard is a continuing process. Teams interested in the
benefits of the VDC Scorecard should closely coordinate its use with BIM representatives. The
VDC Scorecard covers 4 areas of VDC performance:
i. Planning
ii. Technology
iii. Adoption
iv. Performance.
These 4 areas are further divided into 10 Dimensions:
i. Objective vi. Maturity
ii. Standard vii. Coverage
iii. Preparation viii. Integration
iv. Process ix. Quality
v. Organization x. Quantity
Under each dimension, there are 49 Measures that will be evaluated quantitatively or
qualitatively. Furthermore, the VDC Scorecard is being continuously validated and refined with
the intent to continuously align with the industry practice
8
Section 4: Collaboration Procedures
1. Collaboration Strategies
For general project correspondence and milestone/phase BIM deliverable, the Project Team will
use BIM 360 Glue & BIM 360 Docs as a means of sharing and storing information.
During the design phase, BIM-related files utilized by the Design Team will be shared through
the common project site managed by the Design Teams BIM Manager. During the construction
phase, BIM-related files may be shared utilizing either the Construction Teams Managers,
selected A/E site or through BIM 360 Docs.
Design Phase:
● The qualifications, experience, and previous success in BIM coordination of the Proposed
BIM Manager and the Design Team shall be a part of the evaluation factors for BIM
Manager Selection.
● The Design Team shall be responsible for providing a fully coordinated and assembled BIM
in a collaboration software format (Navisworks or approved) as well as separate copies of
each technical discipline model in the original software authoring tool, as well as a 2D plan
set, derived from the assembled BIM, for construction.
10
Construction Phase:
● It is the General Contractors responsibility to assure that all major trades are modeled and
used for clash detection, construction phasing, and installation coordination.
● The General Contractors fabrication BIMs shall be coordinated with the Design BIM. Any
conflicts to the Design BIM that need to be made prior to fabrication and construction shall
be reported to the Design Team in the form of a Request for Information (RFI). Clash
reports may also be issued by the General Contractor as background information for RFI’s
and submittals.
2. Meeting Procedures
The following are examples of meetings that should be considered.
Meeting Type Project Frequency Participants Location
Stage
11
3. Model Delivery Schedule of Information Exchange for Submission and Approval
Information File File One-Time Delivered Model Model Native File
Exchange Or by File Software File Type Exchange
Sender Receiver
Frequenc Type
y
2D Arch Shop Architech BIM One time 02-07- Arch AutoCAD .dwg -
Dwg Manager 2021
& Arch
Modeller
2D Str Shop Structural BIM One time 05-07- STR AutoCAD .dwg -
Dwg Consultan Manager 2021
t & STR
Modeller
2D MEPFF Shop MEP BIM One time 06-07- MEPFF AutoCAD .dwg -
Dwg Consultan Manager 2021
t & MEPFF
Modeller
3D STR STR BIM One time 20-07- STR Revit .rvt .IFC/NWD
Modeller Manager, 2021
GC
3D Arch Arch BIM One time 22-07- Arch Revit .rvt .IFC/NWD
Modeller Manager, 2021
GC
3D MEPFF MEP BIM One time 30-07- MEPFF Revit .rvt .IFC/NWD
Modeller Manager, 2021
GC
Federated Model BIM Owner, One Time 30-08- Central Revit .rvt .IFC/NWD
Manager GC 2021 File
12
4. Interactive Workspace
13
● Publication and Document Issue:
i. Alongside other project documentation, exported data and 2D electronic drawings produced
from the BIMs shall be stored in the Published Area of the project CDE, once formally
checked, approved and authorized in accordance with the project review procedures.
ii. Revision/Issues control shall follow the document control systems established for the project.
A record of all issued deliverable shall be maintained in both soft-copy and hard-copy where
appropriate.
iii. Information within BIM are interdependent and changes in one view may affect other views.
As such the BIM and all associated views shall be treated as the master project data and once
published become uncontrolled documents as they leave the BIM environment and are
published in a non-editable format.
● Archiving:
i. Archiving of all approved output data from the BIM shall be stored in the archive section in
the CDE, including published, superseded, and Record BIM and documents, and data.
ii. Additionally, at key stages of the design process, a complete version of the model, exported
data and associated drawing deliverable shall be copied into an archive location. Project
history should be maintained for knowledge, regulatory and legal requirements.
14
1. Quality Control Checks:
The following checks should be performed to assure quality.
Checks Definition Responsible Software Frequency
Party Program(s)
15
or duplicated elements and the
reporting process on non-
compliant elements and
corrective action plans
v. Clash Detection/Coordination:
i. It is the Design/Construction Teams responsibility to conduct and manage an adequate and
thorough Clash Detection process so that all major interference between building
components will have been detected and resolved before construction. It shall be the goal of
the Design/Construction Teams to reduce the number of changes during construction due to
major building interference to zero before construction starts.
ii. The Design/Construction Teams BIM Managers shall assemble a composite BIM from all of
the BIM data of each design discipline for the purpose of performing a visual check of the
building design for spatial and system coordination. Vertical shafts should also be reviewed
to ensure that adequate space has been allocated for all of the vertical mechanical systems
and that all of the shafts line up floor to floor. Prior to each scheduled coordination meeting,
an updated clash report will be issued by the Design/Construction Teams BIM Manager to
the project team.
iii. On a multistory project, the BIM may need to be split on a level by level basis for MEPF
coordination. If a floor is particularly large, it may also need to be split by zones to reduce
16
file size. Typically, 3D clash detection /coordination continues on a single floor until
building systems are fully coordinated, and then continues on up to the next floor level.
iv. Coordination software (Navisworks or other approved software) shall be used for
assembling the various design BIM to electronically identify, collectively coordinate
resolutions, and track and publish interference reports between all disciplines. The technical
disciplines shall be responsible for updating their BIM data to reflect the coordinated
resolution.
v. The Project Team shall review the model and the Clash Reports in coordination meetings on
a regular as-needed basis throughout the design phases until all spatial and system
coordination issues have been resolved.
vi. During the construction phase, the accuracy of fabrication models shall be verified and
approved, prior to submittal and fabrication. Fabrication contractors shall submit their BIM
to the Construction Teams BIM Manager for integration and Clash Detection /coordination
and resolution.
vii. Internal Clash Resolution – The Design Team and Subcontractors who are responsible for
multiple scopes of work are expected to coordinate the clashes between those scopes prior to
providing those models to the Construction Teams BIM Manager for spatial and system
coordination.
viii. Spatial Coordination: Verification and tracking of resolved conflicts of all trade coordination
issues which could result in change orders or field conflicts shall be provided to Client
during project milestone dates, and should be fully resolved before construction start.
17
Section 7: Model Structure
1. File Naming Structure:
The team projects that the following master files will be generated during the project. All names
of master files, and all other data should be maintained as follows
FILE NAMES
Architectural Model ARCH-
Civil Model CIV-
Mechanical Model MECH-
Plumbing Model PLU-
Electrical Model ELE-
Structural Model STR-
Energy Model ENE-
Construction Model CONST-
Coordination Model COORD-
2. Model Structure:
The models are to be separated as shown below. This is for completion of 3D modelling.
Clash Federated
Building 1 STR ARCH MEPFF Coordinati model
on
Clash Federated
Building 2 STR ARCH MEPFF Coordinati model
on
18
Section 8: Project Deliverable
The team should familiarize themselves with these requirements before any BIM work is
commenced. Item covered by the Standard Include:
● COBie / IFC data requirements
● Native format
● Minimum data attributes
● Use of Standard folder structure
● Collection of extended data into the Standard folder structure
● Specific quality reports for model data and laser scan data
● Specific versions of software
● Specific model structure requirements
● Specific use of URLs within the BIM data
These standards must be followed by all team members.
Estimated
Project Stakeholders
Project Stage / Milestone Description of Delivery Delivery
Involved
Date
Design Stage
Owner, Architect,
Design development Preliminary submittal of IFC, Structural Consultant,
phase COBie, Revit, and Navisworks 09-08-2021 MEPFF Consultant,
LOD 200-300 data for review. General Contractor,
BIM Manage
Formal submittal of
construction documents and
Construction BIM data. All 2D and 3D Owner, General
Documents Phase building data produed on the Contractor, Bim
30-08-2021
project in both native format, Manager, Project
LOD 300 Complete IFC, and COBie spreadsheets. Manager
All design level attribute data
will be complete.
19
Construction Stage
Signature Page
Team members agree to use BIM to enable improved workflows for subject project. Model data
will be authored, maintained, shared, and documented as outlined in this VDC Execution Plan.
Team Member Company Name Signature Date
Client Client LMN
GC GC ABC
Architect Arch XYZ
Structural
STR DEF
Consultant
MEP Consultant MEP MEP
BIM Manager UVW UVW
Project Manager FGH FGH
Client
Client JKL
representative
Lead Q/C QC QC
20
Appendices
1. Project Schedule/Timeline
2. Cumulative work graph
3. Clash detection report
4. RFI format
21
22
23