Example Problem RBI PSV - Rev1
Example Problem RBI PSV - Rev1
Vessel Design:
PRD Design:
Inspection 1
- Prior POFOD
Test result = Pass
Inspection interval (tinsp) = Inspection Date (1) – Install Date = 2005 – 2000 = 5 years
1.8
𝑝𝑟𝑑 𝑡𝑖𝑛𝑠𝑝 𝛽 5
𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 = 1 − 𝑒𝑥𝑝 [− ( ) ] = 1 − 𝑒𝑥𝑝 [− ( ) ] = 0.096
𝜂𝑚𝑜𝑑 17.925
𝑝𝑟𝑑 𝑝𝑟𝑑
𝑃𝑝,𝑝𝑟𝑖𝑜𝑟 = 1 − 𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 = 1 − 0.096 = 0.904 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
- Conditional POFOD
Test result = Pass; Effectiveness = B (Usually Effective) → Based on Table 7.8 CFpass =
0.7
𝑝𝑟𝑑 𝑝𝑟𝑑
𝑃𝑓,𝑐𝑜𝑛𝑑 = (1 − 𝐶𝐹𝑝𝑎𝑠𝑠 ) × 𝑃𝑝,𝑝𝑟𝑖𝑜𝑟 = (1 − 0.7) × 0.904 = 0.271 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
- Weighted POFOD
Test result = Pass; Effectiveness = B (Usually Effective) → Based on Table 7.9 equation
used is,
𝑝𝑟𝑑 𝑝𝑟𝑑 𝑝𝑟𝑑 𝑡𝑖𝑛𝑠𝑝 𝑝𝑟𝑑 𝑡𝑖𝑛𝑠𝑝
𝑃𝑓,𝑤𝑔𝑡 = 𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 − 0.2 ∙ 𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 ( ) + 0.2 ∙ 𝑃𝑓,𝑐𝑜𝑛𝑑 ( )
𝜂 𝜂
5 5
= 0.096 − 0.2 × 0.096 ( ) + 0.2 × 0.271 ( )
17.925 17.925
= 0.1057 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
Inspection 2
- Prior POFOD
Test result = Pass
Inspection interval (tinsp) = Inspection Date (2) – Install Date = 2010 – 2000 = 10 years
𝑝𝑟𝑑 𝑡𝑖𝑛𝑠𝑝 𝛽 10 1.8
𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 = 1 − 𝑒𝑥𝑝 [− ( ) ] = 1 − 𝑒𝑥𝑝 [− ( ) ] = 0.2951
𝜂𝑚𝑜𝑑 17.925
𝑝𝑟𝑑 𝑝𝑟𝑑
𝑃𝑝,𝑝𝑟𝑖𝑜𝑟 = 1 − 𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 = 1 − 0.2951 = 0.7049 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
- Conditional POFOD
Test result = Pass; Effectiveness = B (Usually Effective) → Based on Table 7.8 CFpass =
0.7
𝑝𝑟𝑑 𝑝𝑟𝑑
𝑃𝑓,𝑐𝑜𝑛𝑑 = (1 − 𝐶𝐹𝑝𝑎𝑠𝑠 ) × 𝑃𝑝,𝑝𝑟𝑖𝑜𝑟
= (1 − 0.7) × 0.7049
= 0.2115 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
- Weighted POFOD
Test result = Pass; Effectiveness = B (Usually Effective) → Based on Table 7.9 equation
used is,
𝑝𝑟𝑑 𝑝𝑟𝑑 𝑝𝑟𝑑 𝑡𝑖𝑛𝑠𝑝 𝑝𝑟𝑑 𝑡𝑖𝑛𝑠𝑝
𝑃𝑓,𝑤𝑔𝑡 = 𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 − 0.2 ∙ 𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 ( ) + 0.2 ∙ 𝑃𝑓,𝑐𝑜𝑛𝑑 ( )
𝜂 𝜂
10 10
= 0.2951 − 0.2 × 0.2951 ( ) + 0.2 × 0.2115 ( )
17.925 17.925
= 0.2851 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
= 1.0002 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑦𝑒𝑎𝑟
149.52
(3.464837× )
𝑃𝑓,𝐵𝐷 = (0.0312881 × 3.06 ∙ 10−5 × 1 × 1) × 𝑒 155
= 2.71 × 10 −5 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑦𝑒𝑎𝑟
180
(3.464837× )
𝑃𝑓,𝐿𝑂 = (0.0312881 × 3.06 ∙ 10−5 × 1 × 1) × 𝑒 155
= 5.35 × 10 −5 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑦𝑒𝑎𝑟
149.52
(3.464837× )
𝑃𝑓,𝐸𝐹 = (0.0312881 × 3.06 ∙ 10−5 × 1 × 1) × 𝑒 155
= 2.71 × 10 −5 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑦𝑒𝑎𝑟
𝑝𝑟𝑑
𝑃𝑓,𝑓𝑖𝑟𝑒 = 0.0184 × 0.0004 × 1.0002 = 7.3615 × 10−6 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑦𝑒𝑎𝑟
𝑝𝑟𝑑
𝑃𝑓,𝐵𝐷 = 0.092 × 0.1 × 2.71 ∙ 10−5 = 2.4913 × 10−7 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑦𝑒𝑎𝑟
𝑝𝑟𝑑
𝑃𝑓,𝐿𝑂 = 0.092 × 0.01 × 5.35 ∙ 10−5 = 4.9242 × 10−8 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑦𝑒𝑎𝑟
𝑝𝑟𝑑
𝑃𝑓,𝐸𝐹 = 0.092 × 0.08 × 2.71 ∙ 10−5 = 1.993 × 10−7 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑦𝑒𝑎𝑟
Inspection 1
- Prior POFOD
Test result = No Leak
Inspection interval (tinsp) = Inspection Date (1) – Install Date = 2005 – 2000 = 5 years
𝑝𝑟𝑑 𝑡𝑖𝑛𝑠𝑝 𝛽 5 1.6
𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 = 1 − 𝑒𝑥𝑝 [− ( ) ] = 1 − 𝑒𝑥𝑝 [− ( ) ] = 0.1509
𝜂𝑚𝑜𝑑 15.5
𝑝𝑟𝑑 𝑝𝑟𝑑
𝑃𝑝,𝑝𝑟𝑖𝑜𝑟 = 1 − 𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 = 1 − 0.1509 = 0.8491 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
- Conditional POFOD
Test result = No Leak (Pass); Effectiveness = B (Usually Effective) → Based on Table 7.8
CFpass = 0.7
𝑝𝑟𝑑 𝑝𝑟𝑑
𝑃𝑓,𝑐𝑜𝑛𝑑 = (1 − 𝐶𝐹𝑝𝑎𝑠𝑠 ) × 𝑃𝑝,𝑝𝑟𝑖𝑜𝑟
= (1 − 0.7) × 0.8491
= 0.2547 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
- Weighted POFOD
Test result = No Leak (Pass); Effectiveness = B (Usually Effective) → Based on Table 7.9
equation used is,
𝑝𝑟𝑑 𝑝𝑟𝑑 𝑝𝑟𝑑 𝑡𝑖𝑛𝑠𝑝 𝑝𝑟𝑑 𝑡𝑖𝑛𝑠𝑝
𝑃𝑓,𝑤𝑔𝑡 = 𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 − 0.2 ∙ 𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 ( ) + 0.2 ∙ 𝑃𝑓,𝑐𝑜𝑛𝑑 ( )
𝜂 𝜂
5 5
= 0.1509 − 0.2 × 0.1509 ( ) + 0.2 × 0.2547 ( )
15.5 15.5
= 0.1576 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
Inspection 2
- Prior POFOD
Test result = Leak (Fail)
Inspection interval (tinsp) = Inspection Date (2) – Install Date = 2010 – 2000 = 10 years
𝑝𝑟𝑑 𝑡𝑖𝑛𝑠𝑝 𝛽 10 1.6
𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 = 1 − 𝑒𝑥𝑝 [− ( ) ] = 1 − 𝑒𝑥𝑝 [− ( ) ] = 0.391
𝜂𝑚𝑜𝑑 15.5
𝑝𝑟𝑑 𝑝𝑟𝑑
𝑃𝑝,𝑝𝑟𝑖𝑜𝑟 = 1 − 𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 = 1 − 0.391 = 0.6089 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
- Conditional POFOD
Test result = Leak (Fail); Effectiveness = B (Usually Effective) → Based on Table 7.8
CFpass = 0.7 and CFfail = 0.95
𝑝𝑟𝑑 𝑝𝑟𝑑 𝑝𝑟𝑑
𝑃𝑓,𝑐𝑜𝑛𝑑 = 𝐶𝐹𝑓𝑎𝑖𝑙 ∙ 𝑃𝑓,𝑝𝑟𝑖𝑜𝑟 + (1 − 𝐶𝐹𝑝𝑎𝑠𝑠 ) × 𝑃𝑝,𝑝𝑟𝑖𝑜𝑟
= 0.95 × 0.391 + (1 − 0.7) × 0.6089
= 0.5541 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
- Weighted POFOD
Test result = Leak (Fail); Effectiveness = B (Usually Effective) → Based on Table 7.9
equation used is,
𝑝𝑟𝑑 𝑝𝑟𝑑
𝑃𝑓,𝑤𝑔𝑡 = 𝑃𝑓,𝑐𝑜𝑛𝑑 = 0.5541 𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑑𝑒𝑚𝑎𝑛𝑑
𝝅𝒅𝟐𝒏
𝑨𝒏 =
𝟒
3.14 × 0.252
𝐴𝑠𝑚𝑎𝑙𝑙 = = 0.049 𝑖𝑛2
4
3.14 × 12
𝐴𝑚𝑒𝑑𝑖𝑢𝑚 = = 0.786 𝑖𝑛2
4
3.14 × 42
𝐴𝑙𝑎𝑟𝑔𝑒 = = 12.571 𝑖𝑛2
4
3.14 × 162
𝐴𝑟𝑢𝑝𝑡𝑢𝑟𝑒 = = 201.143 𝑖𝑛2
4
3.14 𝑥 82
𝐴𝑚𝑎𝑥8 = = 50.286 𝑖𝑛2
4
𝑙𝑏 𝑙𝑏. 𝑓𝑡 1.014+1
0.61 𝑙𝑏𝑓 1.014 𝑥 51 𝑙𝑏𝑚𝑜𝑙 𝑥 32.2 2
2 𝑙𝑏𝑓. 𝑠 2 1.014−1
𝑊𝑚𝑒𝑑𝑖𝑢𝑚 = 𝑥 0.786 𝑖𝑛 𝑥 634.7 2 √( )( )
1 𝑖𝑛 𝑓𝑡. 𝑙𝑏𝑓 1.014 + 1
1545 𝑥 580.67 𝑜𝑅
𝑙𝑏𝑚𝑜𝑙. 𝑜𝑅
= 7.938 𝑙𝑏/𝑠
𝑊𝑛 = 𝑚𝑖𝑛[𝑊𝑛 ; 𝑊𝑚𝑎𝑥8 ]
3.4 Total Amount of Fluid Available for Release
• Inventory Fluid Mass
𝑚𝑎𝑠𝑠𝑐𝑜𝑚𝑝 = 𝜌𝑙 × 𝐿𝑖𝑞𝑢𝑖𝑑 𝑉𝑜𝑙𝑢𝑚𝑒
- Equipment volume = πr2t = 3.14 x (8.14/2)^2 x 30 = 1559.7 ft3
- Assumed: Liquid volume = Equipment volume = 1559.7 ft3
𝑙𝑏
𝑚𝑎𝑠𝑠𝑐𝑜𝑚𝑝 = 33.61 3 × 1559.7 𝑓𝑡 3 = 52,420.913 𝑙𝑏
𝑓𝑡
• Additional Mass
𝑚𝑎𝑠𝑠𝑎𝑑𝑑,𝑛 = 180 ∙ 𝑚𝑖𝑛[𝑊𝑛 ; 𝑊𝑚𝑎𝑥8 ]
→ Example for Fire Overpressure Scenario, Medium (1 in) Release Hole Area:
𝑚𝑎𝑠𝑠𝑎𝑑𝑑,𝑚𝑒𝑑𝑖𝑢𝑚 = 180 ∙ 𝑚𝑖𝑛[7.938; 513.313] = 1,428.864 𝑙𝑏
→ Example for Fire Overpressure Scenario, Medium (1 in) and Large (4 in) Release Hole
Area:
𝐴𝐼𝑁𝐿
𝐶𝐴𝑖𝑛𝑗,𝑚𝑒𝑑𝑖𝑢𝑚 = 𝑎 (𝑟𝑎𝑡𝑒𝑛 )𝑏 = 125.2(5.95)1 = 745.39 𝑓𝑡 2 = 69.25 𝑚2
𝐴𝐼𝑁𝐿
𝐶𝐴𝑖𝑛𝑗,𝑙𝑎𝑟𝑔𝑒 = 𝑎 (𝑚𝑎𝑠𝑠𝑛 )𝑏 = 57.72(28,565)0.75 = 126,827.23 𝑓𝑡 2 = 11,782.635 𝑚2
= $6,315 + 0 + 0 + 0
= $6,315
• Stuck Open Leakage
𝑪𝒔𝒐 𝒔𝒐
𝒍 = 𝑪𝒊𝒏𝒗 + 𝑪𝒆𝒏𝒗 + 𝑪𝒔𝒅 + 𝑪𝒑𝒓𝒐𝒅
𝒔𝒐
• Risk of PRD failure to open associated with Blocked Discharge overpressure demand case
𝑝𝑟𝑑 𝑝𝑟𝑑 𝑝𝑟𝑑
𝑅𝑖𝑠𝑘𝑓,𝐵𝐷 = 𝑃𝑓,𝐵𝐷 ∙ 𝐶𝑓,𝐵𝐷 = (2.4913 × 10−7 ) × $695,359.77 = $0.173
• Risk of PRD failure to open associated with Liquid Overfilling overpressure demand case
𝑝𝑟𝑑 𝑝𝑟𝑑 𝑝𝑟𝑑
𝑅𝑖𝑠𝑘𝑓,𝐿𝑂 = 𝑃𝑓,𝐿𝑂 ∙ 𝐶𝑓,𝐿𝑂 = (4.9242 × 10−8 ) × $708,614.98 = $0.035
• Risk of PRD failure to open associated with Electrical Power Failure overpressure demand
case
𝑝𝑟𝑑 𝑝𝑟𝑑 𝑝𝑟𝑑
𝑅𝑖𝑠𝑘𝑓,𝐸𝐹 = 𝑃𝑓,𝐸𝐹 ∙ 𝐶𝑓,𝐸𝐹 = (1.993 × 10−7 ) × $695,359.77 = $0.139
8. RISK CATEGORY
PoF Level Determination
• Risk of Fail to Open Failure Mode (taken from highest risk of all the overpressure scenario)
PoF = 7.3615×10-06 failure/year → Level 1
CoF = $1,238,869 → Level D
Risk Category = 1-D (Medium)
• Risk of Leakage Failure Mode
PoF = 0.169 failure/year → Level 5
CoF = $25,805 → Level A
Risk Category = 5-A (Medium)