Function and Duties of Various Wings of SLDC, Patna: 1. Grid Operation (Shift Duty)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

FUNCTION AND DUTIES OF VARIOUS WINGS OF

SLDC, PATNA

1. GRID OPERATION (SHIFT DUTY):

 To monitor Grid Operation Round the Clock


 To co-ordinate with Grid S/s and DISCOMs for Planned &
Emergency Shutdown and also record message for the
shutdown.
 Preparation of Generation & Drawal schedule on day ahead
basis for GENCO & DISCOMs incorporating bilateral &
collective transaction and also taking into account power
allocation to DISCOMs from Central sector, Long term,
Medium term & short term power in consultation with State
generators, NBPDCL & SBPDCL and ERLDC.
 Responsible for optimum scheduling and dispatch of
electricity within the State, in accordance with the contract
entered by the DISCOMs (NBPDCL & SBPDCL) with the
licensees or the generating companies operating within the
State including Renewable energy based generation sources.
 To keep accounts of the quantity of electricity transmitted
through the State Grid.
 Responsible for carrying out real time operations for Grid
control, monitoring of data on real time basis and dispatch of
electricity within the State through secure & economic
operation of the State Grid in accordance with the Bihar
State Grid Code & Grid Standards.
 To exercise Supervision & Control over the Intra State
transmission system of BSPTCL
 To record and prepare any unusual events in the Grid
 Real- time monitoring of the Intra State Generating station &
transmission system operation
 checking that there is no gaming in the declaration of
availability by the Intra / Inter State Generating Stations
 revision of availability declaration and injection schedule of
the Generator
 Outage planning of Intra State Generators & intra state
transmission system
 switching instructions
 Facilitating transactions of power under short term and long
term intra state open access as approved by STU.

1
 Issuing No Objection Certificate/Standing Clearance for
inter-state open access transactions and facilitating the same
consequent upon the approval from Nodal RLDC.
 SLDC shall effect real time monitoring of difference
between generation and load of the area covered by each
islanded scheme in operation. In case of large deviation,
SLDC shall effect appropriate changes in area covered by an
islanding scheme by making operative or blocking the
tripping of lines through respective under frequency relays.
These changes have to be informed to ERPC/ERLDC as and
when implemented.
 SLDC shall effect real time monitoring of difference
between generation and load of the area covered by each
islanded scheme in operation. In case of large deviation,
SLDC shall effect appropriate changes in area covered by an
islanding scheme by making operative or blocking the
tripping of lines through respective under frequency relays.
 The In-charge of Grid Substations where under frequency
relays for islanding purposes are installed shall confirm to
SLDC through a numbered message, the status of UF relays
which are blocked / made operative as per latest system
conditions / changing loads. No alterations in Under
Frequency Relays (UFR) status/settings shall be made
without specific approval through a coded message from
SLDC. At the time of change in system status necessitating
blocking / operating of these relays, the shift engineer of LD
centre shall convey the changed requirement to respective
GSS and obtain confirmation that the relay status has been
suitably changed. It has to be ensured that due permission is
taken from ERLDC in respect of any such tripping of inter-
state lines and interconnection with ISTS.
 The power system operation is a dynamic situation, the
SLDC shall keep on monitoring the system status at least
once in every shift and ensure that status of UFRs be kept
suitably operative / blocked with correct settings as per
system requirements, so that in the event of major grid
disturbance, Islanding takes place smoothly.

2. Grid Operation (General Shift):

 To analyze and prepare grid report on daily basis pertaining


to Grid incidence & Grid disturbance and shut down in the

2
Intra State and Inter State transmission system. The grid
report should be submitted to MD / Transmission & CMD,
BSP(H)CL.
 To carry out system study for the Critical shutdown as well
as such shutdown affecting power supply in the Distribution
licensee area and if possible make an alternative
arrangement for supply of power through alternative
transmission lines before allowing for shutdown.
 To prepare daily report of power position, record schedule &
actual drawl of DISCOMs, schedule & actual injection of
power by the intra state generators for preparation of
monthly energy accounting & Deviation schedule of
DISCOMs & Intra State Generators and forward the same to
the Commercial wing of SLDC.
 To prepare daily & weekly report of power supply positions
and forward the same to MD / North, MD / South, MD /
Transmission & CMD / BSP(H)CL.
 To keep record of non compliance of directions of SLDC by
the Intra State Generators & DISCOMs/Open access
customers and deal the issues of non compliance of SLDC
directions with BERC in accordance with the provision of
Section 33 of EA 2003.
 To check the time drift and take appropriate action in
consultation with ERLDC and match the same with the intra
state generators for proper energy accounting and audit.
 In order to isolate and save healthy parts of the grid during
any disturbance, under frequency islanding schemes have to
be designed and developed based on system study and
simulating the conditions requiring isolation of a generator
from rest of the grid.
 SLDC shall make the islanding schemes in consultations
with ERPC and shall modify as per system requirement.
 SLDC shall formulate one or more sets or subsets of
islanding scheme(s) to prevent tripping of generating units
operating within the state.
 Such schemes shall be formulated in consonance with the
principles and guidelines decided by ERPC. ERLDC/SLDC
shall effect changes to any such islanding scheme, as may be
suggested by ERPC and ERLDC. These changes have to be
informed to ERPC/ERLDC and all affected users as and
when implemented
 To prepare regular MIS report

3
 SLDC shall upload following reports on its website
(a) Annual and monthly grid reports containing annual
and monthly supply position for Grid Sub-Stations.
(b) Weekly reports containing weekly power supply
position for the BSPTCL Grid.
(c) Daily state power availability from all sources
including supply position report
(d) Daily outage status report for transmission lines and
generating units.

 Event information from SLDC to Utilities:

(a) Any operations planned to be carried out on the


instructions of ERLDC which may have an impact
on the State system and which shall be reported by
ERLDC to SLDC in advance, shall be brought to
the notice of concerned users of State.
(b) SLDC shall also send report to its Discoms, if due to
any failure or trippings, the power supply is affected
by 20% of the schedule or in 20% of the area served
by the licensee.
(c) In the event of a grid disturbance, SLDC shall issue
a flash report to the DISCOMs, followed by a
detailed report in the following manner (Grid
Disturbance Category is defined in Appendix-I):

(i) Grid disturbance category - A (major


disturbance):
Flash report within a period of six (6) hours
followed by a detailed report within ten (10)
working days.
(ii) Grid disturbance category - B (moderate
disturbance): Flash report within a period of
five (5) hours followed by a detailed report
within a period of seven (7) working days.
(iii) Grid disturbance category - C (minor
disturbance): Flash report within a period of
four (4) hours followed by a detailed report
within a period of four (4) working days

3. Commercial wing of SLDC:

4
To keep records of the power & energy transacted through the
intra state grid of BSPTCL including power injected by the
State Generators & supplied to DISCOMs.
 To collect weekly meter data from all the interface meters
with the DISCOMs, State Generators & CTU for preparation
of Deviation schedule.
 To prepare Monthly Energy Accounting and Weekly
Deviation Schedule of DISCOMs & Intra State Generators.
 To decide meter location at interface points with DISCOMs,
Intra State Generators, Open Access Customer(s).
 Preparation of ARR of the SLDC for determination of fees
& charges of SLDC and filing before BERC for approval in
consultation with the finance wing of the BSPTCL
 Approval of Short term open access as per BERC Open
Access Regulations as amended time to time and collection
of open access charges.
 Creation of State UI Pool for collection and disbursement of
payment based on the weekly Deviation schedule of Intra
state generators & DISCOMs and reconciliation of payments
on weekly basis.
 To prepare and raise bills to the DISCOMs, Open Access
customer & Intra State Generators towards SLDC fees &
charges.

4. Unified Load Dispatch Centre (ULDC):

 To operate and maintained the hardware & software in


ULDC
 To modify / design modified database to accommodate
integration of new RTU and to accommodate different
operational requirement
 To validate data in regular interval to ensure correct display
of data
 To take back up of the system and to restore the system in
the event of system crash.
 To generate report from the real time system to study the
cause of the system disturbance
 To monitor and analyze the PMU data installed in the
BSPTCL Grid S/s & PSS of DISCOMs (if any)
 To coordinate with ERLDC for restoration of online data in
case system failure

5
 Maintenance of ULDC infrastructure, Hardware & Software
for ULDC functional requirement
 To coordinate with Telecommunication for maintenance &
monitor data communication from field RTU’s location to
SLDC end
 Design & Maintenance of Website & Intranet of ULDC,
SLDC & Company HQ of BSPTCL
 Development of customized Software & Applications
 Implementation and Maintenance of Communication system
for LAN & WAN connectivity under ULDC project of
BSPTCL
 Design and maintenance of Knowledge Portal (Detailed
content map for Knowledge Portal is enclosed)
 Technology management, Patch management, Information
Security implementation as per policy & procedure.

5. Telecommunication:

 To maintain and establish Voice / Data communication &


PLCC from end to end GSS to Company HQ level
 Planning, Engineering, Design, Installation &
Commissioning of RTUs and to provide communication
channel from RTU location to Company HQ and all related
activities to perform successful communication.
 To operate and maintain RTU & communication equipments
with all accessories at field level to Company HQ level.
 Commissioning & maintenance of hot line communication.