Detailed Feasibility Studies: Transmission Projects in Nepal

Download as pdf or txt
Download as pdf or txt
You are on page 1of 230

Task 1: Technical Assessment of Network

Improvements

Detailed Feasibility
Studies: Transmission
Projects in Nepal
Draft Feasibility Study Report
Transmission Projects in Nepal
Volume 1 (Report)

Volume 6
Monitoring and Evaluation

MCC-15-BPA-0032, MCC-16-CL-0002
Prepared for:
March 2017 Millennium Challenge Corporation
1099 14th Street NW, Suite 700
Washington, DC 20005-3550

MCC-16-CL-0002

Prepared by:
1320 North Courthouse Road, Suite 600
Arlington, VA 22201
Tel 703.387.2100, Fax 703.243.0953

December 6, 201
Feasibility Study:
Nepal Priority Transmission Projects

Volume 1: Technical Feasibility


Assessment

Prepared for:
Millennium Challenge Corporation
1099 14th Street, NW
Washington, DC 20005

MCC-15-BPA-0032, MCC-16-CL-0002

Prepared by:
Tetra Tech ES, Inc.
1320 N. Courthouse Road, Suite 600
Arlington, VA 22201

March 2017
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 1

1. INTRODUCTION ..................................................................................................................................... 6

1.1 TASK 1 OBJECTIVES ....................................................................................................... 7


2. APPROACH AND METHODOLOGY ......................................................................................................... 9

2.1 DATA COLLECTION AND REVIEW ....................................................................................... 9


2.2 POWER SYSTEM ASSESSMENT ........................................................................................ 10
2.3 SUBSTATIONS – ENGINEERING ASSESSMENT ...................................................................... 20
2.4 TRANSMISSION LINES - ENGINEERING ASSESSMENT ............................................................. 43
2.5 GEOTECHNICAL INVESTIGATION ...................................................................................... 58
2.6 OPERATIONS AND MAINTENANCE ................................................................................... 84
2.7 PROJECT COST ESTIMATES............................................................................................. 91
2.8 PROJECT PROCUREMENT PACKAGING .............................................................................. 98
2.9 RISK ASSESSMENT ..................................................................................................... 101
3. DETAILED FEASIBILITY ASSESSMENT ................................................................................................. 106

3.1 POWER SYSTEM ASSESSMENT ...................................................................................... 106


3.2 TRANSMISSION LINES AND SUBSTATIONS – DETAIL FEASIBILITY ASSESSMENT .......................... 176
4. IMPLEMENTATION SCHEDULE .......................................................................................................... 212

4.1 PROJECT PHASES ...................................................................................................... 212


4.2 IMPLEMENTATION ZONING .......................................................................................... 212
4.3 DURATION ASSUMPTIONS .......................................................................................... 213
4.4 SCHEDULE RISK AND CRITICAL PATH .............................................................................. 214
4.5 CRITICAL PATH ......................................................................................................... 214
4.6 PROJECT FLOAT ........................................................................................................ 214
5. CONTRACT PROCUREMENT PACKAGES ............................................................................................ 215

6. RESULTS, CONCLUSIONS, AND RECOMMENDATIONS ...................................................................... 219


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 2

Acronyms
ACSR Aluminum conductor steel reinforced
ADB Asian Development Bank
ASTM American Society for Testing and Materials
ATS Automatic transfer switch
AIS Air-insulated switchgear
BIL Basic insulation level
BOM Bill of Materials
BS British Standard
CF Base Case Counterfactual base case
CIF Compact Implementation Funding
CSA Canadian Standards Association
CT Current Transformer
DCPT Dynamic Cone Penetration Test
EHV Extra High Voltage
EIF Entry in force
EPC Engineering, procurement and construction
FACTS Flexible AC Transmission System
GIS Gas-Insulated Switchgear or geographic information system
HPP Hydropower plant
HVDC High Voltage Direct Current)
IACS International Annealed Copper Standard
IE Indian Electricity Rules
IEC International Energy Commission
IED Intelligent Electronic Devices
IEEE Institute of Electrical and Electronic Engineers
IFC International Finance Corporation
IFC Issued for construction
I/O Input/output
ION Brand name for Schneider Electric-Power & Energy Meter
IPP Independent power producer
IS Indian Standards
KfW The German Development Bank
LAN Local Area Network
LDC Load Dispatch Center
LiDAR Light Imaging Detection and Ranging
LRT Linear Routing Tool
MCC Millennium Challenge Corporation
MVAR Mega-Volt Ampere Reactive
NEA Nepal Electricity Authority
NPS Nominal pipe size
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 3

OHGW Overhead ground wire


OPGW Optical ground wire
OMCN Office of Millennium Challenge/Nepal
PGCIL Power Grid Power Corporation of India Ltd
PI Point of inflection
PSS®E Power Transmission System Planning Software
RMS Root mean squared
RTU Remote Terminal Units
SCADA Supervisory Control and Data Acquisition
SPT Standard Penetration Test
TOR Terms of reference
VDE German Standard
VT Voltage Transformer
WB World Bank
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 4

Executive Summary
The Millennium Challenge Corporation (MCC) is a US Government agency that provides aid to developing
countries in order to encourage economic growth. Nepal suffers from one of the worst electricity supplies
in South Asia. In December 2014, MCC selected Nepal as an eligible country and began work on developing
a program to stimulate its economic growth. The objective of MCC’s compact in Nepal is to reduce load
shedding by increasing the amount of power supplied to the national grid as well as facilitating increased
power trade between Nepal and India. The key areas of improvement are the transmission network,
extension of grid projects that can help transfer power from generating projects, and upgrades of existing
stations to supply electricity to locals who are living far from urban centers.

MCC selected Tetra Tech to perform a detailed feasibility analysis of proposed projects considering a
compact implementation period of five years (2018-2023). MCC’s due diligence contractor; WSP,
conducted a pre-feasibility assessment; its findings (WSP: Transmission Network Analysis (Final No 151-
09979-01) formed the basis of this detailed feasibility assessment. After assessing the feasibility of all
proposed MCC projects, Tetra Tech further defined and prioritized them. The feasibility assessment was
carried out through stakeholder engagement, site surveys, technical assessments, environmental and
social assessments, cost assessments, etc.

MCC compact projects include east-west transmission backbone; NR1, transmission network
reinforcements; NR3, NR4, cross-border electricity transmission; XB1 and generation pooling to the
national grid or Nepal/India Border; T2’, T3 and T8.

The following are key results of the technical feasibility assessment.


 The implementation of all projects under review will meet all compact objectives, including
reducing load shedding, increasing generation utilization, and maximizing power trade potential.
 With the implementation of the NR1 and XB1 projects, load shedding can be reduced up to 56%.
 With the implementation of the T8 project, electricity export potentials can be significantly
increased (290%), the overall generation utilization will increase to 83% in base case in 2023, and
increase to 75% in base case in 2030.
 T2’, T3, NR3, and NR4 are remote transmission projects. These projects enhance the remote area
transmission capacities, therefore, to accommodate increasing remote generation projects.
 Some roads and bridges in Nepal are not capable to carrying heavy equipment, due to this
constraints substation transformers are limited to single phase 55MVA transformers or three
phase 160MVA transformers.
 In the project implementation schedule, project float of 8 month is considered in the overall
schedule.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 5

The following are key recommendations of technical feasibility assessment.


 It is also recommended to model sub-transmission level system 132kV and 66kV to do the
power system assessment and evaluate the benefit to distribution level loads.
 It is recommended that the loop flow situation within these two tie lines be closely studied in
the detailed engineering stage with details from India’s network.
 It is recommended that all station access routes shall be surveyed by a logistics transporter
company for movement of transmission and other construction material.
 It is recommended that further more detailed geotechnical studies should take place during
detail design phase.
 To facilitate upcoming desktop routing study, Airborne LiDAR survey should be used for
transmission line routing.
 Considering the aggressive timeline for compact implementation, Tetra Tech recommends that
implementation be split into four engineering, procurement and construction (EPC) or design-
build packages based on geography.
 It is recommended that the EPC contractor be responsible for land acquisition, permitting,
resettlement, engineering, procurement, construction, testing, and commissioning and project
closeout.
 In order to manage the program, Tetra Tech recommends hiring a firm to provide program
supervision services including project management, technical oversight, environmental
monitoring, social safeguard services, construction oversight, procurement oversight and overall
financial monitoring.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 6

1. Introduction
Following the identification of power as a constraint to economic growth, the Government of Nepal
(GoN) submitted concept papers to MCC requesting funding for a diverse set of projects and activities in
the power sector. The Nepali electricity network suffers low throughput capacity, high losses, and
inability to evacuate power from supply sources, whether generation or imports. Consequently, the GoN
has proposed a program that will address this through critical investments in network infrastructure
(transmission lines and substations) to provide a stronger national transmission network.

Tetra Tech was retained by MCC to conduct a detailed feasibility study (DFS) of the proposed projects,
further refining the Pre-Feasibility Study by WSP.

The East-West Transmission Backbone


 NR1: 400 kV East-West Transmission Backbone

Transmission Network Reinforcements


 NR3: Upgrade of the Ilam-Inaruwa 132 kV transmission line
 NR4: Upgrade of the Balanch-Attariya 132 kV transmission line

Enabling Generation – Connecting Generation Pooling Points to the National Grid or Nepal/India Border
 T2’: Likhu Hub – New Khimti transmission line
 T3: New Tadhekani-Kusma transmission line
 T8: New Lamki substation and transmission line to the Nepal border

Cross-Border Electricity Transmission


 XB1: New Butwal 400 kV transmission line to the Nepal border

Note: The NR1.1 project, which includes the Dhalkebar substation and the Dhalkebar – Hetauda
transmission line upgrade to 400 kV, is already designed by private firm from India. So, NR1.1 is not part
of MCC compact projects and excluded from Detail Feasibility Study.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 7

1.1Task 1 Objectives
The primary objective of Task 1 of the DFS is to assess the technical feasibility of the proposed transmission
projects in Nepal.

Tetra Tech has provided a review of the technical feasibility and cost (+/- 20%) of each of the projects, as
shown in Table 1, by performing an engineering assessment and determining the specifications of
substations and transmission lines in accordance with relevant technical standards in Nepal, India and
other international standards. The assessment will include the determination of optimal configurations
and locations for both the transmission lines and the substations, and constraints and risks associated
with each projects. Whenever possible, recommendations will be made in order to optimize project
execution and reduce cost.

Following activities were performed for feasibility assessment:


 Power system analysis to determine technical feasibility, estimate power flows, and determine
power system losses for different scenarios
 Preliminary assessment of proposed developments
 Transmission line route selection and substation site selection
o Data gathering
o Site reconnaissance
o Walk down along routes (transmission line routes of NR4, NR3 and almost 50% of T8 were
drove down and all NR1, T2’, T3 were visited several time by helicopter.
o Stakeholder engagement
o Alternate route options analysis
o Participatory route selection workshops
o Geotechnical investigation
 Conceptual design of transmission line and substations
o Digital Terrain Model of potential transmission line route
o Substation layouts
 Risk assessment
 Detailed project cost estimates (to +/- 20 % accuracy)
 Project implementation schedule (overall and for each project)
 Recommendation of contract procurement packages
 Terms of reference (TOR) and cost estimates for the firm(s) to be hired following the compact’s
signing to produce tender documents for all engineering, procurement, and construction (EPC)
contract(s) (Annex B).
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 8

Table 1.1 Projects


Project Component Transmission Lines Substations
New Existing*
NR 1 400 kV, 270 km Lapsiphedi**
Lapsiphedi to Naubise (48 km) New Damauli
NR 1,
Naubise to New Hetauda (41 km) Naubise
XB1
Naubise to New Damauli (98 km) New Butwal**
New Damauli to New Butwal (84 km) New Hetauda***
XB1 New Butwal to Nepal/India border (23 km)
NR 3 132 kV, 110 km
Ilam* to Inaruwa* Ilam
Inaruwa
NR4 132 kV, 131 km
Balanch* to Attariya* Balanch
Attariya
T8 400 kV, 47 km
New Lamki to Nepal/India border New Lamki
T2’ 220 kV, 30 km
Likhu Hub to New Khimti* Likhu Hub New Khimti
T3 220 kV, 30 km
Tadhekani to Kusma* Tadhekani Kusma
Total 642 km 8 6
* Bay extensions will be provided at these existing substations.
** 220 kV system of these substations are funded by the Asian Development Bank.
*** 220 kV system of this substations is funded by the World Bank.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 9

2. Approach and Methodology


This section describes the approach and methodology employed for feasibility assessment.

2.1Data Collection and Review

Tetra Tech interacted with various government and non-government organizations in Nepal in order to
collect transmission system data and to understand other project developments taking place in the region.

Technical, environmental and financial details were gathered from various stakeholders. Table 2.1
illustrates the source and type of data collected Information.

Table 2.1 Data Collection


Sources Data/Information Collected
1 MCC / WSP / OMCN PSS®E files, due diligence report, power map and other
information relevant to the projects
2 Statistics Department Information related to gross domestic product growth rate,
population growth rate
3 Meteorological Department Information related to weather, wind speed, rainfall, snow fall,
isoceraunic level
4 Mining and Geotechnical Survey Geological map of Nepal
Department
5 NEA Project Planning Department Various information about existing and upcoming projects,
their associated transmission lines, generation, existing
substation details, drawings of existing substation, etc.
6 NEA Power Trade Department Information about power trades between India and Nepal
7 NEA Operation and Maintenance Information regarding maintenance schedules, fault levels, etc.
Department
8 NEA Financial Department Wheeling charges and tariff information
9 Data Collection from NEA Website Various tender documents, drawings, etc.
10 Data Collection from PGCIL Various drawings, technical specifications and other
information
11 NEA System Planning Department Only positive sequence data for short circuit analysis and
dynamic data of generating units for stability analysis
12 MCC/EPG Nepal Grid Code
Compliance & Power quality Requirements
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 10

All the above relevant data and reports were reviewed by technical leaders and engineers in further detail.
The collected data has formed the basis of the Detailed Feasibility Study. The missing information / any
gaps were further discussed with appropriate sources.

In order to achieve this objective of detail feasibility assessment, a number of meetings were held at the
beginning of the project, and great deal of data was obtained that are directly and indirectly related to
elements of this compact. In various meetings with NEA, transmission development and construction
managers, NEA managers of ADB projects, construction managers of NEA projects, and local
professionals, we understood NEA’s design approach and standards, the materials that have been used
to build Nepal’s network, transmission line construction constraints, the factors that might contribute to
construction delays, etc. We also met with other donors on Nepal’s electricity network development
and heard their experiences and points of views about project implementation. In parallel, we studied
many NEA tender documents in order to understand NEA’s desired technical specifications, contractor
scopes, and activities in NEA projects. We also visited all the MCC project sites and became familiar with
the climatic and terrain features of project areas.

2.2 Power System Assessment


The technical feasibility of the East-West Transmission Trunk Lines, Transmission Network
Reinforcements, and Transmission Extension Cords were evaluated by using PSS®E, a power system
analysis tool, employing the model developed previously by MCC’s due diligence consultants. The studies
were performed for the year of 2023 and the year of 2030 considering the timely generation and
transmission developments as described in the WSP due diligence report for the year of 2020 and the year
of 2025. For each year, two extreme power flow scenarios considering wet conditions with minimum
loading (“Wetmin”) and dry conditions with maximum loading (“Drypeak”) were considered.

2.2.1 Counterfactual Base Cases

For each study year, a set of “counterfactual base cases” (CF Base Cases) without any of the MCC projects
was created to demonstrate the base case situation without the MCC investment. In order to create
realistic (i.e., solvable) cases with no excessive overloads or voltage violations, the following are required:
power flow scenarios, reduction of loads (load shedding) and adjustment of import/exports from the
original cases provided by WSP. These load-shedding figures were later used to demonstrate the benefits
of the MCC projects. The following base case counterfactuals were created:

 2023 Drypeak
 2023 Wetmin
 2030 Drypeak
 2030 Wetmin
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 11

Note: the transmission project NR1.1 will be built by another donor. However, because it is part of Nepal’s
power system, was included at 400 kV in both the 2023 and 2030 scenarios.
The following techniques were used to create the aforementioned power flow scenarios. Please refer to
WSP Report.
 2023 Supply (generation) is based on WSP model generation for 2020 (implying a lag of 3 years)
 2023 Demand is based on WSP model demand for 2020 by feeder, scaled up by the factor of 7.5%
per year for 3 years (which equates to a 24.2% total increase over the three years)
 2030 Supply (generation) is based on WSP model generation for 2025 (implying a lag of 5 years)
 2030 Demand is based on WSP model demand for 2025 by feeder, scaled up by the factor of 7.5%
per year for 5 years (which equates to a 43.5% total increase over the five years)

The power flow cases provided by WSP included the following information. A complete set of network
elements is provided in Annex A.
 The transmission system above 132 kV was modeled in detail and some 66 kV and 33 kV buses
were included. The distribution system was not included.
 The loads were placed on the buses 66 kV and above.
 The load power factor was set to about 0.98 lagging.
 All the transformers were modeled as lossless (copper and iron losses are ignored)
 There are considerable number of switch shunts (capacitor banks and reactors) available in the
system (please refer to Annex A)
In the power flow models, the generator transformers were embedded into the generator model
and the transformer reactance was considered to be 15%.
 Most of the generators were consuming the reactive power (leading PF).

For the energy benefit studies, the provided models were used since there is no significant impact of
reactive power transfer of the system on the transmission system losses. For the cases used for the
technical benefit studies the following modifications were done.
 The load power factor was set to 0.85 lagging, which is a realistic value for typical system loads.
 The generator transformers were separated from the generator model by introducing the
generator terminal buses at 13.8 kV (a typical value).
 The generator transformer reactances were set to 10%, which is more realistic.
 The generator voltage set points were adjusted to within a realistic range of 1.05-0.95pu, in order
to maintain the leading power factors above 0.95.

Note: The modelling is adequate to determine the transmission level (66 kV and up) system upgrades
required to facilitate the MCC projects and to demonstrate the importance of the MCC projects with
respect to the Nepal transmission system performance. However, the sub transmission and distribution
level (66 kV and below) system upgrades needs to be evaluated at a later stage. It is also recommended
that to analyze actual benefit on MCC projects, further studies of sub-transmission system should be
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 12

completed. Furthermore, the losses estimated in the study are relevant to the transmission system only
and therefore considered as “transmission losses”.

Assumptions and Major Considerations

One of the major considerations is the power transfer capabilities of the tie lines to India. As agreed upon,
the following transfer limits were considered.

 Dhalkebar-Muzzaffarpur interconnector (1st tie line)


o Maximum of 700 MW in 2023
o Maximum of 1200 MW in 2030
 XB1 – second interconnector (considering 40%:60% power distribution between the first tie line
and XB1)
o Maximum of 1050 MW in 2023
o Maximum of 1800 MW in 2030.

The following assumptions were made:


 It was assumed that the power flows provided by the due diligence team accurately represent the
existing system and the system upgrades other than the MCC projects in Nepal Transmission
Network.
 It was not possible to obtain an equivalent model of the India power system. Therefore, the tie
line terminals were individually modeled without considering the transfer impedances between
the terminals. The power transfers were modeled as described above.

2.2.2 Scenarios with MCC Projects

Based on each base case built, the MCC projects were added to the system one by one as listed in Table
2.2, and the impact of each project was evaluated. In addition to that, one case with all the MCC projects
was also included for each base case.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 13

Table 2.2 Power Flow Scenarios Considered for Base Analysis


Case Supply/Demand Set of MCC Projects Included
1 2023 Drypeak CF Base Case
2 CF Base Case + NR1
3 CF Base Case + NR1 + XB1
4 CF Base Case + NR1+ XB1 + T2' + T3
5 CF Base Case + NR3
6 CF Base Case + NR4
7 CF Base Case + T8
8 CF Base Case + all MCC Projects
9 2023 Wetmin CF Base Case
10 CF Base Case + NR1
11 CF Base Case + NR1 + XB1
12 CF Base Case + NR1+ XB1 + T2' + T3
13 CF Base Case + NR3
14 CF Base Case + NR4
15 CF Base Case + T8
16 CF Base Case + all MCC Projects
17 2030 Drypeak CF Base Case
18 CF Base Case + NR1
19 CF Base Case + NR1 + XB1
20 CF Base Case + NR1+ XB1 + T2' + T3
21 CF Base Case + NR3
22 CF Base Case + NR4
23 CF Base Case + T8
24 CF Base Case + all MCC Projects
25 2030 Wetmin CF Base Case
26 CF Base Case + NR1
27 CF Base Case + NR1 + XB1
28 CF Base Case + NR1+ XB1 + T2' + T3
29 CF Base Case + NR3
30 CF Base Case + NR4
31 CF Base Case + T8
32 CF Base Case + all MCC Projects
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 14

2.2.3 Scenarios for Sensitivity Studies

Key scenarios were tested for sensitivity of the system in response to different supplies and demands.
The key scenarios were the base cases and the cases with all the MCC projects, as listed in Table 2.3.

Table 2.3 Power Flow Scenarios for Sensitivity Studies


Case Supply/Demand Set of MCC Projects Included
1 2023 Drypeak CF Base Case
8 CF Base Case + all MCC Projects
9 2023 Wetmin CF Base Case
16 CF Base Case + all MCC Projects
17 2030 Drypeak CF Base Case
24 CF Base Case + all MCC Projects
25 2030 Wetmin CF Base Case
32 CF Base Case + all MCC Projects

The above mentioned cases were used for the following sensitivity studies.

(1) Impact of Different Supply Scenarios


The generation dispatch of the cases described in Table 2.3 was selected considering a reasonable
expected growth rate in Nepal as described in Section Counter Factual Base Case. It was further tested for
the sensitivity to different supply (generation) scenarios by 2023 and 2030. As agreed upon, the following
two alternative supply scenarios were considered.

 Alternative Generation Scenario - 1, a higher supply forecast, which is based on the NEA plan in
the WSP due diligence report dated 15 July 2016.
 Alternative Generation Scenario - 2, a lower supply forecast, with 5 years additional lag.

Table 5 shows the different supply scenarios that were set up.

Please note that the Generation Distribution Zones mentioned below are different than Procurement
package zones.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 15

Table 2.4 Generator Dispatch for Different Supply Scenarios


Supply Forecast Generation Distribution by Zones (MW)
Case Generation Generation Zone 1 Zone 2 Zone 3 Zone 4 Zone 5 Zone 6
TOTAL
On-Line Available Far West Mid West West Central East Far East
Base cases:
2023 Drypeak 3,946 29% 35 4 402 331 282 104 1,158
2023 Wetmin 3,946 54% 63 7 736 606 516 190 2,118
2030 Drypeak 4,836 30% 35 4 584 331 298 176 1,428
2030 Wetmin 4,836 64% 75 9 1,268 720 648 382 3,102

Low Supply Cases:


2023 Drypeak 2,230 29% 58 - 243 127 181 38 647
2023 Wetmin 2,230 54% 107 - 452 236 337 72 1,204
2030 Drypeak 3,680 30% 63 7 414 264 283 73 1,104
2030 Wetmin 3,680 64% 134 14 884 563 605 155 2,355

High Supply Cases:


2023 Drypeak 4,907 29% 61 20 476 269 338 259 1,423
2023 Wetmin 4,907 54% 113 38 886 501 630 482 2,650
2030 Drypeak 9,735 30% 589 21 816 452 742 301 2,921
2030 Wetmin 9,735 64% 1,256 45 1,742 964 1,583 642 6,231

(2) Impact of Different Demand Forecast


As described in Sections 3 and 4 of the WSP due diligence report, a moderate demand forecast was used
in their studies, which equates to a growth rate of about 7.5% per year. To test sensitivity, it is necessary
to consider the variations in demand forecast as well. Therefore, the following sensitivity cases were
considered.

 Low forecast – demand growth at 5% per year


 High forecast – demand growth at 10% per year.

(3) Impact of Reduced Sales to India


A sensitivity case was run for both 2023 and 2030 in which “all MCC Projects” were included except XB1.
This case was run using the base analysis supply and demand forecasts (as described in Section 2.2.1).
Sales to India through other supply lines remained as modeled in the case with “all MCC Projects.”
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 16

2.2.4 Methodology – Technical Feasibility Study

The technical feasibility study was performed for the following cases.

Table 2.5 Power Flow Scenarios used for Technical Feasibility Studies
Supply/Demand Set of MCC Projects Included
2023 Drypeak CF Base Case
CF Base Case + all MCC Projects
2023 Wetmin CF Base Case
CF Base Case + all MCC Projects
2030 Drypeak CF Base Case
CF Base Case + all MCC Projects
2030 Wetmin CF Base Case
CF Base Case + all MCC Projects

The following studies were performed.

Power Flow Analysis and Loss Evaluation


The steady state power flow analysis was performed in PSS®E for the aforementioned power flow
scenarios to identify:

 Voltage violations and voltage stability issues


 Thermal overloads
 Steady state system instabilities (blown up cases) related to the project.

All the N-1 contingencies in the transmission network (132 kV and up) were considered in the analysis. In
addition to these, the following N-2 contingencies relevant to the MCC projects were also considered.

 NR1 trunk lines


o D/C transmission line from New Hetauda to Naubise
o D/C transmission line from Naubise to Lapsiphedi
o D/C transmission line from Naubise to New Damauli
o D/C transmission line from New Damauli to New Butwal.

 Apart from the abovementioned N-2 contingencies, we also considered the double circuit outages
of the all three tie lines (Dhalkebar, XB1 and T8). To do this, it was necessary to adjust the
imports/exports when one of these tie lines is out of service; therefore, these outages were
considered separately from the others.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 17

The study kept track of lower voltage violations in case these might signal the need for investment in
upgrades at the distribution voltage level. As in the Nepal grid code, voltages within 0.9 pu and 1.1 pu are
acceptable. However, for reporting purposes, the voltage violations beyond 0.95 pu and 1.05 pu were
considered and the mitigation measures evaluated only if the voltages moved beyond 0.9 pu and 1.1 pu.

The overloads of the transmission lines and transformers were monitored and for the overloads, the
mitigation measures such as adding parallel circuits were proposed.
A loss evaluation of the system expansions along with the related upgrades was performed for selected
power flow scenarios. For each power flow scenario, the followings were determined:

 System losses in MW before adding the project (at each voltage level and in each zone)
 System losses in MW after adding the project
o Losses related to the transmission components of the project
o Losses related to the rest of the system (at each voltage level and at each zone)
 Net impact in terms of losses.

2.2.5 Short Circuit Analysis

A short circuit analysis was performed to determine the maximum short-circuit levels in order to ensure
breaker ratings are not exceeded. The analysis was done for all the new stations as well as the existing
stations under system intact conditions. The impact on the system expansions are identified by comparing
against the short circuit levels before adding the expansions.
The following limitations were faced in the studies.
 No sequence impedance data of the Nepal system was available for the studies and only the
positive sequence impedances were available for the calculations. Therefore, only the three phase
fault levels can be calculated accurately. For the single phase fault level calculations, the negative
and zero sequence impedances are required.
 The short circuit contribution from Indian grid was unknown to the date on which the studies
were done and therefore the calculations were done without considering the contribution from
Indian grid. It is proposed to consider some short circuit contribution and add it into the results
of this analysis. The following short circuit contributions were added to the results of the short
circuit levels calculated.
o 400 kV buses – 15 kA
o 220 kV buses – 10 kA
o 132 kV buses – 5 kA

Because of the unavailability of zero sequence and negative sequence impedance data, only the three
phase short circuit levels were calculated. Note that for the generators, the zero sequence impedance is
usually smaller than the positive sequence impedance and therefore the single phase fault level would be
higher than the three phase fault levels. Furthermore, the calculations were done considering some
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 18

reasonable supply/demand scenarios for year 2023 and 2030. However, there is a possibility of having a
higher supply and hence a larger short circuit current. Therefore, it is necessary to consider an extra
margin from the calculated values when determining the breaker ratings. In order to cover these short
comings, a 30% margin was considered for the minimum breaker ratings.

2.2.6 Transient Stability Analysis

The transient stability analysis was performed for the aforementioned power flow scenarios considering
the critical contingencies related to the expansions. This included transmission line and generator outages
after a fault. The faults on the busses relevant to the MCC projects were considered. The following
dynamic performance issues were evaluated:

a. Rotor angle stability


b. Frequency stability and inertia requirements
c. Temporary over- and under-voltage
d. Dynamic reactive power requirements
e. Need for Special Protection Schemes (SPSs) such as cross tripping of generators
If any dynamic performance criteria violation was found, appropriate mitigation was investigated.

2.2.7 Methodology – Technical Benefit Study

A technical benefit study was done in PSS®E for all the cases described in Table 2.2 (Section 2.2.2). The
following procedure was followed for the evaluation of the technical benefits.

It was assumed that Nepal’s annual load patterns are represented by the dry and wet seasons. In order to
estimate the annual energy requirements, an equal number of months for the dry and wet seasons were
assumed– 6 months for the wet season and 6 months for the dry season.

The daily load profile of the Nepal system recorded in 2015 is shown in Figure 2.1. It was agreed to
consider a projected version of this load profile for 2023 and 2030, and the profile represented three
different loading conditions.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 19

Figure 2.1 2015 Daily Load Profile

Table 2.6 Nepal Load Profile, 2015


MW Hr/day MWh/day
Peak load 1385 4 5541
Base load 492 9.5 at 35.5% of peak 4672
Shoulder load 651 10.5 at 47% of peak 6837
Total 24 17050
Load factor = 0.51

It was assumed that the “Drypeak” scenarios represent the average loading in the Nepal system on a day
in the dry season and “Wetmin” scenarios represent the average loading in the Nepal system on a day in
the wet season. Considering the average loadings in these scenarios, the peak, shoulder and base load
cases were developed for the wet and dry seasons for 2023 and 2030.

For each power flow scenario the losses (in MWh) were calculated for the list of cases relevant to years
2023 and 2030 given in Section 2.2.2. In any of these cases, if the power flows were not solvable, the
following adjustments were made.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 20

 For the dry season cases, the loads were shed and the imports were adjusted until the load flow
is solvable. The amount of load reduction is considered as the energy not supplied (load shed).
 For the wet season, the exports were reduced and the generations were adjusted until the load
flow is solvable. The amount of export reduction is considered as the energy not supplied
(generation shed).

If the existing lines are heavily overloaded or very low/high voltages were observed in certain buses, the
local loads were reduced and these amounts were also considered as the energy not supplied (load shed).

The annual energy losses and the energy not supplied were calculated considering the daily values and
the duration of each season. The benefit of each MCC project was shown as the annual savings in energy
(MWh). The following information was derived for each scenario relevant to years 2023 and 2030:

 Annual MWh supply – with and without MCC project(s)


 Annual MWh consumption – with and without MCC project(s)
 Annual MWh loss – with and without MCC project(s)
 Annual load shedding in MWh – with and without MCC project(s)
 Annual import amounts in MWh – with and without MCC project(s)
 Annual export amounts in MWh – with and without MCC project(s)
 Annual generation shedding in MWh (lost exports) - with and without MCC project(s).

2.3 Substations – Engineering Assessment


Tetra Tech has performed feasibility level engineering for the substation proposed in MCC compact in
Nepal. Substation engineering assessment includes assessment of electrical, civil, structural, protection,
SCADA, telecommunication, environmental requirements. Tetra Tech has conducted different site
surveys, site selection assessment to study the feasibility of substation in the proposed area. Based on
the land selected, substation footprint and basic layout for each substation are created. This helped in
identifying the major equipment to be used. The major equipment are part of the Bill of Material (BOM)
which is required in providing the cost of the MCC compact varying from +/-20% range.

2.3.1 Substation Site Selection

The substation site selection process was based on a multi-criteria approach. The following criteria were
considered for substation site selection. While it is recognized that it is not always possible to find sites
that meet all the criteria, the site that met most of these criteria is selected.

 MCC/OMCN recommendations
 Space availability
o Space provision for ultimate layout
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 21

o Availability of laydown area


 Site condition
o Relatively flat sites with slopes no more than 1% to 2%
o Site elevation: preferably higher than the surrounding land
o Soil type
o not in a dense forest area, not located on a flood plain
o Proximity to imported fill
o proximity to distribution line for station service supply
o proximity to water supply
o Aviation routes
o Land cost
o Proximity to load centers (for stations serving load centers)
o Risk of security threat
 Environmentally-sensitive area adjacent to the site
o Wetlands
o Bird or wildlife habitants
 Community
o Proximity to local communities (noise, visual impact could be issues)
o Heritage sites
o Archeological sites
 Infrastructure
o Feasibility of year-round access
o Available access roads
o Nearby highway or major road (this is required to determine an internal access road)
o Nearest transport infrastructure (railway or highway)
o Accessibility for maintenance and emergency response (fire, ambulance)
o Pipelines

As a first step in the site selection process, a preliminary site visit was conducted for most of the proposed
sites along with other proposed sites. Each site was evaluated using the above criteria. There were three
different alternate locations were selected. The location best aligned with the site selection criteria – were
selected further for each new substation.

After the initial site selection evaluation, a second round of site visits was conducted to confirm which of
the short-listed sites are the most viable. As a next step, the site selection was finalized based upon space
availability for the ultimate layout. A final round of site visits was conducted to obtain geotechnical data
for the selected sites.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 22

The following provides a high-level summary of the site selection for each substation. Further details are
provided in Section 3 of this report.

New Hetauda Susbtation


The World Bank is developing a 220 kV substation and has purchased land for a 400 kV extension. For this
station, no desktop study or site visit was conducted as the site is already selected.

Naubise Substation
Initially, three alternatives sites were selected near Galcchi District. However, it was determined through
OMCN that NEA’s preference is to build the substation near Naubise District. Subsequently, site options
near Naubise were selected and evaluated.

New Damauli Substation


During the site visit, it was determined that the proposed sites have steeper slopes than what is
acceptable. Two additional alternative sites were then identified (one on farmland and one on a brick
factory site). After further evaluation of both sites, the farm land site was selected.

Lapsiphedi and New Butwal Substations


These stations have not gone through the site selection process as the land is already purchased by NEA
for the development of a 220 kV substation by the ABD and World Bank. For this reason, a desktop study
has not been completed.

New Lamki Substation


The New Lamki site selection process included a site visit and a desktop study to get acceptance from
different groups within the team (environmental, resettlement, etc.).

Tadhekani Substation
The first location selected during the desktop studies was found to be adequate during the site visits.

Likhu Hub Substation


A desktop study was conducted to determine an appropriate location for the substation. However, the
final location was chosen based on the fact that an independent power producer (IPP) is already
constructing a 132 kV substation. Based on discussion with NEA and IPP, the IPP has agreed to reserve
space for the 220 kV-132 kV substation on the land that they have already purchased.

Balanch, Attariya, Kusma, New Khimti, Ilam and Inaruwa Substations


These stations are NEA’s existing stations. No site selection was required for these stations.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 23

Table 2.7 provides a high-level summary of the site alternatives and selection criteria.

Table 2.7 Site Alternatives and Selection Criteria


Substation Alternative #1 Alternative #2 Alternative #3 Selected
New Hetauda N/A N/A N/A Site selected by NEA/World Bank.

Galcchi 27° 47' 55.72'' N 27° 47' 09.25'' N N/A Galchhi was initially proposed as an
84° 54' 53.79'' E 84° 56' 02.21'' E alternative for the Naubise site. These
alternatives were dropped after Naubise was
selected as final substation location.

Naubise 27° 43' 59.40'' N 27° 44' 09.15'' N N/A Alternative #1 was selected as it offers better
85° 06' 57.56'' E 85° 07' 13.77'' E land topography and a larger footprint.

New Damauli 27° 57’ 13.8” N 27° 56' 54.26'' N 27° 58’ 04.94” N Alternatives #1 and #2 are on steep slopes.
84° 17’ 10” E 84° 17' 54.20'' E 84° 17’ 33.97” E Alternative #3 is located on farmland and
offers better topography.
The selected site is alternative #3.

New Butwal 27° 34' 31.83'' N 27° 35' 46.27'' N 27° 35' 32.03'' N Three alternatives were proposed initially.
83° 41' 25.49'' E 83° 37' 25.78'' E 83° 41' 8.03'' E Alternative #1 was selected as it was found
that the ADB has already purchased this land
for its 220 kV substation.

Lapsiphedi N/A N/A N/A The substation is to be built adjacent to ADB’s


220 kV substation.

Tadhekani 28° 23' 40.43'' N 28° 26' 48.40'' N 28° 23' 25.69'' N Alternative #1 was selected as the other two
83° 25' 04.86'' E 83° 30' 10.98'' E 83° 26' 21.53'' E alternatives are not suitable from a
geotechnical and land topography
perspective.

Likhu Hub 27° 29' 58.74'' N 27° 29' 17.23'' N 27° 31' 36.84'' N Alternative #3 is the land purchased land by
86° 17' 18.95'' E 86° 18' 19.66'' E 86° 21' 25.32'' E an IPP. This site was selected.

New Lamki 28° 36' 55.50'' N N/A N/A This location was selected through site visits
81° 13' 39.13'' E and since all stakeholders agreed, no other
alternative sites were explored.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 24

Table 2.8 presents the final site locations.

Table 2.8 Final Substation Locations


Coordinates
Item Station North East
o ' " o ' "

1 New Hetauda 27 25 45.97 85 00 24.17


2 Naubise 27 44 0.12 85 06 59.63
3 New Damauli 27 58 04.80 84 17 37.11
4 New Butwal 27 34 31.83 83 41 25.49
5 Lapsiphedi 27 44 42.44 85 30 33.03
6 Ilam 26 52 36.30 87 55 32.69
7 Inaruwa 26 36 46.53 87 07 16.72
8 Attariya 28 48 19.40 80 33 11.15
9 Balanch (Chameliya) 29 41 06.52 80 39 0.47
10 Tadhekani 28 23 40.43 83 25 04.86
11 Kusma 28 14 34.16 83 38 55.76
12 New Lamki 28 36 55.50 81 13 39.13
13 Likhu Hub 27 31 36.84 86 21 25.32
14 New Khimti 27 29 41.69 86 05 54.28
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 25

2.3.2 Substation Design

The physical layout and configuration of any high-voltage substation is based on two underlying principles:

 COMS
o Constructability – practical design including provisions for future expansion with minimal
impact on the normal operation of existing components
o Operability – ensure substation operators can control substation components and
systems according to their precise design intent in any switching configuration, and
assuming extreme environmental conditions specific to the substation location
o Maintainability – of each individual substation component and of the substation yard in
general (vehicle access, snow clearing, etc.) with minimal impact on the normal operation
of other substation components
o Safety - of people who may come in contact with any substation component (starting at
the fence) intentionally or by accident.
 Reliability
o Substation must be able to operate with minimal or no interruptions in power flow under
various static (component failures) and dynamic (system transients) contingencies
o Due to cost impacts, each substation is evaluated individually based on its overall
importance to the power system, and criticality of loads/generators interconnected
through the substation.
o No Restriction of power transfer during the maintenance of one breaker

Each factor has a significant impact on the overall cost and size of the substation.

Bus bar Configuration


Substation reliability is most obviously reflected in the selected bus bar configuration.

The final selection was based on the following factors:

 Available land area and shape


 Effect of failure on the rest of the power system, such as overloads on adjacent substations or
transmission lines
 Critical loads and/or generators interconnected by the substation
 Estimated cost of components.

A comparative analysis of commonly used switching schemes is presented in Table 2.9, based on standard
IEEE 605 (Guide for Bus Design in Air Insulated Substations) and white paper titled “Reliability of
Substation Configurations” by Daniel Nack, Iowa State University. The failure rate shown is considering
substation buses and components only; line failures are not included. Cost in percent is given to illustrate
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 26

the cost relationship among the different bus arrangements with the Single Bus Single Breaker design as
the base. Relative footprints were compared in a similar manner.

Table 2.9. Comparison of the Different Busbar Schemes


Mean Time
Failure Between
Switching Relative Footpri
Rate Failures Remarks
Scheme Cost nt (m2)
(Failure/yr) (years)

Single Bus Single  Failure of the bus or any circuit breaker


Breaker (Figure 0.0489 20 100% 100% leads to the loss of the entire substation.
7)  Simple protection relaying schemes.
 Flexible operation.
 Allows for breaker maintenance.
 Breaker failure on bus side removes only
one line from service. The circuit can
rapidly be put back in service by closing
Breaker-and-a- 332 the tie breaker and connecting to the
Half 0.00301 145% 146% other bus.
(Figure 8)  One of the main buses can be taken out of
service at any time when conducting
maintenance.
 Protection and relaying can be involved
since the middle breaker must be
responsive to both associated breakers.
 Flexible operation. Double feed for each
circuit.
 Complex protection and relaying schemes.
 Requires only one breaker per circuit.
57  When a fault occurs, the splitting of the
Ring Bus
0.0174 125% 181% bus might lead to undesirable circuit
(Figure 9)
combinations.
 Limited number of circuit positions (4 to 6
is usually the maximum). When more
circuits are required, the circuit is usually
upgraded to a breaker-and-a half scheme.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 27

Mean Time
Failure
Switching Between Relative Footpri
Rate  Remarks
Scheme Failures Cost nt (m2)
(Failure/yr)
(years)
 Allows continuity of service to be
maintained a during circuit breaker
Main and N/A maintenance.
Transfer Bus N/A 140% 189%  Complex protection and relying schemes.
(Figure 10)  Failure of the bus or any circuit breaker
leads to the shutdown of the entire
substation.
 Very flexible. All circuit breakers can be
taken out for maintenance.
Double Bus –
176  Allows isolation of any bus or any breaker
Double Breaker 0.00567 190% 184%
without disrupting service.
(Figure 11)
 High cost since 2 breakers are used per
circuit.

Figure 2.2 Single Bus Bar Scheme


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 28

Figure 2.3 Breaker-and-a Half Busbar Scheme

Figure 2.4 Ring Bus Scheme


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 29

Figure 2.5 Main and Transfer Bus Scheme

Figure 2.6 Double Bus – Double Breaker Scheme


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 30

Figure 2.7 Mixed Double Bus – Single Breaker and Transfer Bus Scheme

As per the data collected, NEA’s existing substations use either a main and transfer bus arrangement or a
double bus single breaker arrangement, as shown in Figure 2.7. These configurations are not considered
reliable enough for the planned 400 kV bulk power substations for the following reasons:

 The system is vulnerable to the loss of circuit breakers as there is only one per line. If one circuit
breaker is lost, the tie breaker can be used to protect the line for which the circuit breaker has
failed. However, only one breaker can be lost before protection of the lines is compromised. If
the tie breaker cannot be used to protect the transferred line, the line has to be protected by a
protection element on the source side of the station. This means that the protection will be most
likely be on a second or third zone and will therefore be slower.
 The use of three buses leads to an increased foot print. At 400 kV this can lead to larger land
requirements. This is the case for most of the substations under consideration.

After a review and analysis of all the data obtained, the breaker-and-a-half scheme was selected for all
new 400 kV stations. In this scheme, three circuit breakers are used for controlling two circuits that are
connected between two bus bars. Either bus is designed to carry the entire station load in case the other
bus is lost due to fault, equipment failure, etc. Fault clearing can occur without affecting the continuity of
supply. In addition, the space requirement is less exhaustive and the configuration can be easily expanded.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 31

Selection of Equipment Insulation Levels and Minimum Design Clearances


The insulation levels selected for equipment have a direct impact on substation footprint and determine
most clearances including metal-to-metal and safe limits of approach. All equipment to be installed in the
substation must be rated to meet or exceed the selected insulation levels. The basic insulation level (BIL)
has been determined for each site based on IEC 60071 Parts 1 and 2, and the following factors:

 Rated maximum operating voltage


 Elevation above sea level
 Estimated pollution level.

Design clearances were selected based on the BIL level such that the minimum requirements outlined in
standard IEC 61936 Part 1 are met or exceeded. The following table summarizes the insulation levels and
clearances selected for all substations located at maximum 1000 m elevation above sea level, assuming a
low-to-medium level of pollution.

Table 2.10 Electrical Ratings


Type of Data Unit 400 kV 220 kV 132 kV
System System System
Nominal system voltage kV rms 400 220 132
Maximum continuous voltage kV rms 440 242 145.2
Minimum voltage kV rms 360 198 118.8
Fault level kA 50 40 40
Fault duration sec 1 1 1
Number of phases and wires - 3 ph, 3w 3 ph, 3w 3 ph, 3w
Power frequency Hz 50 50 50
BIL/full wave threshold kV peak 1425 1050 650
Substation main bus rating A 5000 4000 4000
Line rating A 3000 3000 3000
Auxiliary AC voltage V ac 415, 3 ph.
Auxiliary DC voltage V dc 220, 48
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 32

Table 2.11 Minimum Design Clearances (for All Substations below 1000 m from
Sea Level)
Clearance Type 400 kV 220 kV 132 kV
System System System
(mm) (mm) (mm)
Phase to earth (metal-to-metal) 3000 2100 1300
Phase to phase (metal-to-metal) 4200 2100 1300
Sectional clearance (center-to-center 6500 5000 4000
adjacent phases)
Finished grade to live part 7000 5000 4300
Road surface to live part 12000 10000 9000

Three substations are located above 1000 m sea level:

 Likhu Hub (220/132 kV), 1370 m; BIL correction factor calculated per IEC 60071 Part 2, Eq. 11:
1.18; adjusted BIL levels:
o 220kV: 1300 kV
o 132kV: 750 kV

Table 2.12 Design Clearances Adjusted to BIL level


220 kV 132 kV
Clearance Type System System
(mm) (mm)
Phase to earth (metal-to-metal) 2600 1500
Phase to phase (metal-to-metal) 2600 1500
Sectional clearance (center-to-center
5000 4000
adjacent phases)
Finished grade to live part 5000 4300
Road surface to live part 10000 9000

 Tadhekani (220/132 kV), 1100 m; BIL correction factor calculated per IEC 60071 Part 2, Eq. 11:
1.14, adjusted BIL levels:
o 220kV: 1300 kV
o 132kV: 750 kV
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 33

Table 2.13 Design Clearances Adjusted to BIL level


220 kV 132 kV
Clearance Type System System
(mm) (mm)
Phase to earth (metal-to-metal) 2600 1500
Phase to phase (metal-to-metal) 2600 1500
Sectional clearance (center-to-center
5000 4000
adjacent phases)
Finished grade to live part 5000 4300
Road surface to live part 10000 9000

 Lapsiphedi (400/220 kV), 1600 m; BIL correction factor calculated per IEC 60071 Part 2, Eq. 11:
1.22; adjusted BIL levels:
o 400 kV: 1800 kV
o 220 kV: 1300 kV

Table 2.14 Design Clearances Adjusted to BIL level


400kV 220kV
Clearance Type System System
(mm) (mm)
Phase to earth (metal-to-metal) 3700 2600
Phase to phase (metal-to-metal) 4900 2600
Sectional clearance (center-to-center
6500 5000
adjacent phases)
Finished grade to live part 7000 5000
Road surface to live part 12000 10000

Substation Layout Design


After the selection of a breaker switching scheme and the establishment of the design basis related to
insulation levels and clearances, the next step in the design process was to define the minimum
requirements and constraints for each substation. Some significant challenges had to be overcome:

 Available land area for placement of the substation is very constrained at most of the sites. This
is due to the geographic location of the substation or existence of adjacent infrastructure/built-
up areas. Ideally, substations must be located at sites with relatively flat slopes, no more than 1%
to 2%. Site grading represents a significant challenge for larger slopes. To minimize the economic
impact in such situations (moving large quantities of native soil, building retaining walls, non-
standard structures, etc.), gas-insulated switchgear (GIS) was selected for the following
substations:
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 34

o New Hetauda
o New Damauli
o Lapsiphedi
o Likhu Hub
o Tadakhani.

Using GIS results in an approximately 60% reduction of the required footprint and more efficient
use of limited space available than the air-insulated switchgear (AIS) substations.

 Based on the site visit observations and discussions with NEA managers, existing infrastructure in
Nepal is not adequate for transporting very heavy loads, most notably power transformers. A road
assessment study was conducted by the site team; it revealed that the size of the transformers
should not exceed 160 MVA in the best case locations, based on the 120 metric tons weight limit.
Auto-transformer instead of power transformer will be used for 400/220kV and 220/132kV which
are of less weight and lower cost than power transformer.

 For some substations, a different mitigating solution had to be used due to inadequate
infrastructure. Three single-phase transformer units operated as a parallel bank were required to
create the three-phase connections. Even in such circumstances, the bank power is limited to 160
MVA (approx. 55 MVA per single-phase unit) to reduce tank weights. Table 2.15 provides the
allowed transformer sizes based on the road study for respective substations. This approach
resulted in major design challenges related to the required space:
o Overall number of transformers had to be increased in order to meet power flow
requirements.
o Three single-phase transformer units operated as a parallel bank require a larger
containment footprint than a single three-phase unit of similar MVA rating.
o Limiting the capacity of the 400 kV stations based on transformer MVA ratings reduces
significantly the return on investment. At the detailed design stage, it would be worth
investing time in studying the road networks as well as possible upgrades in order to allow
the transport of larger equipment.
Table 2.15 Maximum Transformer Size for Each Site
Site Allowable Transformer
Likhu Hub 55 MVA, single phase transformers
Tadhekani 55 MVA, single phase transformers
Lapsiphedi 55 MVA, single phase transformers
New Damauli 160 MVA, Three phase transformer
Naubise 160 MVA, Three phase transformer
New Butwal 160 MVA, Three phase transformer
New Lamki 160 MVA, Three phase, phase shifter transformer
New Hetauda 160 MVA, Three phase transformer
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 35

The following subsections discuss in more detail the design of specific substation systems and
components.

Substation Buildings
The following buildings were considered for each new substation:

 A control building housing battery/chargers, AC/DC panels, protection and control panels, office
and washroom.
 Switchgear building at substations where GIS switchgear has been specified.
 A storage and maintenance building; spare parts for major equipment are intended to be housed
here if they are unsuitable for long-term outdoor storage. Space for water pumps has been
allocated in this building as well.
 A guard house.
 The substations will be manned. As such the following amenities are provided:
o Water treatment building
o Drinkable water tank
o Septic tank
o Living quarters
o Parking garages
o Firefighting water tank.

Living Quarters and Parking Garage Space


The parking garage size was obtained from the following drawings provided by NEA:

 CCPG-HDI-CP-CIV-01 OF 02
 CCPG-HDI-CP-CIV-02 OF 02
 CCPG-HDI-CP-STR-01 OF 02
 CCPG-HDI-CP-STR-02 OF 02.

These drawings show a five-car garage with overall dimensions of 28 m x 5 m.

The living quarters sizes were obtained from the bidding documents for the construction of the staff
quarters building in Dhalkebar substation (IFB number NIETTP/W/NCB-4.4/DSQB). According to the
drawings included with the bid package, a five apartment building has dimensions of 22 m x 8 m.

Given the dimensions above, a 40 m x 40 m fenced area has been provided adjacent to the substations
for the construction of living quarters and one garage.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 36

Substation Earthing
Each substation must be provided with a buried ground grid extending up to 1.5 m around the total fence
perimeter. The conductors must be of sufficient size to withstand the maximum considered fault currents,
as listed in the “Electrical Ratings” table. Due to significant cost impact from material and labor, the
amount of earthing material was estimated using the following approach.

The conductor quantities were approximated based on the overall substation footprint and based on
reference data available for similar substations. The typical ground potential rise limit at a substation is
3000 V, dependent on grid impedance and available fault current. The grid impedance is inversely
proportional to its overall footprint; typically, large substations can easily achieve low impedance due to
the ground grid area. Therefore, different mesh sizes were considered based on the overall dimensions of
the station. Table 17 presents a breakdown of the different mesh sizes considered for the substations. An
allowance of 25% of the total length of buried conductor was considered for above-grade connections to
equipment.

The following conductor sizes, per IEC 60228, were considered in the earthing bill of material:

 300mm2 CU conductors for the main ground grid and major outdoor equipment connections
 120 mm2 for fence earthing and indoor earthing.

Table 2.16 Ground Grid Dimensions Considered


Size of ground
Substation
grid mesh (m)
Likhu Hub 6x6
New-Hetauda 15 x 15
Lapsiphedi 6x6
Naubise 15 x 15
New Damauli 15 x 15
New Butwal 15 x 15
Tadhekani 6x6
New Lamki 15 x 15
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 37

Bus Selection
The substation layouts were developed considering a mixed use of strain and rigid bus in order to use
available space as efficiently as possible. For the air-insulated substations, only a limited amount of rigid
bus, mainly used for breaker bay interconnections in the breaker-and-a-half diameters, and around the
power transformers, were considered.

Due to limited space and tight clearances, rigid bus conductors were mostly considered for GIS
substations.

Rigid bus selection was based on the methods and parameters described in IEEE 605-2008 and ASTM
B317/B317-10. As is typical for high-voltage installations, span length and fault currents are the
determining factors. Therefore, 6” (152 mm) nominal pipe size (NPS) aluminum tubular bus was selected
for the 230 kV system, and 8” (203 mm) NPS bus for the 400 kV system. Bus material will be aluminum
alloy typically used in electrical application, code 6101, and temper T6, with rated conductivity of 56% of
IACS (International Annealed Copper Standard). This alloy provides an optimal balance between tensile
strength and conductivity. Alloy 6061-T6 (40% IACS) may be substituted to allow for maximum rigid bus
span lengths. The ampacity rating of these conductors will greatly exceed the 4000A design value of the
main bus.

The following conductors were considered for air-insulated substations:

 Main bus (5000A): 2 x 1250 mm2 ACSR, 76/19 Stranding per phase
 Feeder bus (3000A): 2 x 700 mm2 ACSR, 76/19 Stranding per phase.

Phase Shifting Transformer


GMR (an IPP) will build a dedicated 400 kV line from Upper Karnali hydropower plant (HPP) of 900 MW
capacity for export to India. ‘Free-Power’ of 12% (energy) of the Upper Karnali HPP is to be evacuated by
NEA from the Upper Karnali project. In order to evacuate the defined 12% of project capacity and control
the power flow, one 132 kV/132 kV, 160 MVA power shifting transformer is required to be installed at
New Lamki Substation.

Between Nepal and India’s interconnected power network system (except the proposed power-flow-
controlled dedicated tie line T8), there is one existing tie line (1st tie line) between Dhalkebar and
Muzzaffarpur . In addition, an XB1 tie line is proposed between New Butwal and Gorakhpur. With these
two tie lines between Nepal and India, depending on the system’s condition at the connection point, one
tie could run in an energy import mode, and the other tie line could run in an energy export mode.
Therefore, a loop flow would be created within these tie lines of the first tie line and XB1. A loop flow
within these two tie lines should be avoided. Since India power system data are not available at this time,
the loop flow situation cannot be simulated. It is recommended that the loop flow situation within these
two tie lines be closely studied in the detailed engineering stage with details from India’s network.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 38

However, in case a loop flow situation occurs within these two tie lines, two solutions should be further
investigated for engineering implementation.

 Phase shifting transformer: This is a popular power flow control method between two nodes in
an interconnected network. It creates a phase shift between the primary (source) and secondary
(load) sides, therefore regulating the load flow within the line.
 Back-to-back HVDC (high voltage direct current): The rectifier (conversion of AC to DC) and
inverter (conversion of DC to AC) are located in the same station. Back-to-back HVDC is used:
o To connect asynchronous high-voltage power systems or systems with different
frequencies
o To stabilize weak AC links
o To supply more active power where the AC system is already at the limit of its short-circuit
capability
o For grid power-flow control within synchronous AC systems.

Flexible AC transmission system (FACTS) devices: This is a modern trend in power flow control for AC
power networks. FACTS devices are installed in AC power systems to increase the power flow transfer
capability of the transmission systems and to enhance continuous control over the voltage profile. The
ability to control power rapidly can increase stability margins as well as the damping of the power system,
to minimize losses, to work within the thermal limits range, etc.

Substation Auxiliary Power Supply


The rating of the stations’ service transformer were selected based on transformer sizes typically seen in
the region:

 2 x 630 kVA for 400 kV substations


 2 x 300 kVA for 200 kV substations
 2 x 200 kVA for 132 kV substations
 A diesel generator set shall be provided to allow for black starts and to provide backup power
when no other sources are available. An 800 kVA generator set has been assumed for all
substations. It is assumed sufficient to provide power to all critical loads.

2.3.3 Protection Systems

Electrical protection schemes are intended to promptly, precisely and reliably isolate from service any
element of the power system when that element is subjected to an abnormal condition detrimental to its
effective operation, while leaving other unaffected elements in service and/or undamaged. The
protection schemes are designed so that they do not operate under load conditions or faults external to
the relevant zone.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 39

The protection system are designed based on the following:

 The power transformer and transmission line are protected by two protection schemes, identified
as Scheme A (Primary) and Scheme B (Backup). Multifunctional, software-based, digital relays
shall be specified for this purpose. Relaying for each scheme shall be selected from a different
manufacturer to minimize the possibility of common-mode software and hardware failure.
Common uses of current and voltage AC inputs shall be minimized.
 Each system is independently capable of detecting and isolating all faults on its respective
elements.
 The minimum protection scheme for short transmission lines consists of a pilot wire differential
or current differential through fiber optics or directional comparison relays with over-current and
earth fault relays as backup.
 The minimum protection scheme for long transmission kV lines consist of one protection distance
relay and carrier transfer trip with over-current and earth-fault relays as backup.
 The distance protection scheme should be a permissive under-reaching or blocking scheme with
protection zones 2 and 3 delayed trip.
 The distance protection relays are built-in facilities for fault locators, event recorders and
disturbance recorders.
 Out-of-step relays have been provided with both primary and backup protection to check the
operation of relays due to power swings.
 Each relay line terminal is provided with circuit breaker-failure protection for each circuit breaker.
 Each line terminal breaker includes single-pole tripping and three-pole tripping with single shot
auto-reclose.
 If the grid transformer with primary voltage is equal to or greater than 66 kV and is connected to
the distribution system, the high and low voltage sides of the transformer are connected in Wye
with neutral brought out for earthing.
 Power transformers will be equipped with on-load tap-changers (OLTC) and voltage regulator to
enable voltage regulation by varying the transformer ratio under load without interruption.
 Transformers will have winding thermal and oil level monitoring equipment and will be connected
to the station RTU/SCADA through fiber optic.
 A differential scheme is to be provided for all sizes of transformers with capacities above 5 MVA
with over-current and earth fault as backup.
 Over-current and earth-fault relays are to be provided for all capacity transformers with
directional features for parallel transformer operations.
 Restricted earth-fault relays have been provided for all transformers with capacities equal to or
higher than 30 MVA.
 Other protection requirements regarding gas-operated relays, and oil and winding temperature
protection are to conform to best industry practice.
 Critical features, such as protection operation or circuit breaker operation, are monitored by a
disturbance fault recorder.
 The two protection systems are supplied from separate current and voltage transformers.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 40

 Separate blocking switches for inputs and outputs of the protective relays are provided.
 Separate blocking switches for AC current, AC voltage, and DC are provided.
 Separately fused and monitored DC sources are used with the two protection systems.
 Protection system circuitry and physical arrangements are designed to minimize the possibility of
incorrect operations from personnel error.
 The protection system is equipped with breaker failure protection to protect the system when
the breaker fails to clear the fault. The time needed to clear the fault can be set depending on the
maximum permissible fault duration at that location. This can be achieved by using the transfer
trip signal transmitted to the remote ends via telecommunication systems if such a facility exists.
 The DC voltage supplied to the tripping coils of the breaker is fed from two separately fused and
monitored DC supplies.
 Any signal that opens remote breakers on the transmission system (Tt Signal – if any) can be
automatically removed when the main local disconnect switch opens.
 Low-impedance bus protection schemes will be one of the solutions to protecting the double-bus,
breaker-and-a-half scheme. These schemes will monitor all currents, as well as the positions of
breakers and isolators, and dynamically adjust their zones of protection for optimum selectivity
while the bus is being switched. They make it easier to accommodate added generation or expand
existing buses because it not necessary to change existing current transformers (CTs) or add slip-
on CTs as is sometimes required for high-impedance bus differentials.

2.3.4 Control, Metering, Telecommunication and SCADA

The engineering assessment for substations is based on following design criteria for control, metering,
telecommunication and SCADA.

 Telecommunication facilities are installed between the system operator at NEA’s load dispatch
center (LDC) and the generators, distributors and other users at their respective control centers
in order to ensure adequate monitoring and control of the grid and the exchange of information
during normal and emergency conditions. Such facilities will also be established between adjacent
grid substations.
 The communication and SCADA equipment installed at substations are compatible with those
installed by NEA at the remote end of the grid, including the LDC.
 A combination of communication media is used. These could be power line carriers, microwave
radio or fiber optics. Base radios, cellular phones and e-mail could serve as backup
communication.
 Fiber optical cables, where technically and economically feasible, are the preferred
communication media between NEA LDC and substations. Power line carriers or satellite
communication will be the communication media, where fiber optics is not practical.
 Two independent voice communication and two data transfer channels are installed, with one
serving as backup. These will be used only for operational purposes.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 41

 The remote terminal unit, which provides the NEA LDC with telemetry equipment facilities for
monitoring real time data and remote control at the connection point, are installed.
 The substation equipment is to have three levels of control as follows:
o Local, at the equipment for maintenance – the default position of the normal/ maintenance
switch is normal for remote operation from the control building or through SCADA.
o Remote, from the control panel – the local/remote switch on the control panel is on the
“local” position to enable control from the panel. In the “remote” position, the control is
remote through SCADA.
o Remote, from SCADA for breaker reclosing.

The following values and status will be monitored and metered:

 Voltage (phasors, true root mean squared (RMS) values, and symmetrical components), current
(phasors, symmetrical components, true RMS values), real, reactive, and apparent power, power
factor, demand, energy, and frequency. A separate intelligent electronic device (IED) shall be used
for metering purposes.
 The metering point will be located at the connection point; if this is not possible, a procedure
should be established to adjust the energy loss between the metering and connection points. The
location of the metering point and the procedure for adjusting losses, if necessary, shall be
specified in the connection agreement.
 Each power transformer in the grid substation shall have separate metering on the high-voltage
side and the low-voltage side.
 The auxiliary consumption of grid substations shall be measured on the primary side of the
auxiliary station service transformer. Energy supplied to the office and staff quarters shall be
measured separately and not be considered as auxiliary consumption.
 MW and MVAR four quadrant.
 Total harmonic distortion.
 Voltage and current harmonics.
 The meter shall require LAN + SCADA + local access.
 User-programmable oscillography.
 Trip circuit monitoring.
 DC supervision with time delay (100 msec.) on drop-out to prevent nuisance alarms.
 Programmable logic including non-volatile latches.
 VT fuse fail detection: this logic detects one, two, or three blown potential fuses.
 Status of all circuit breakers, disconnect switches, transformer tap positions, ATS position.
 Operating circuit breakers, disconnect switches, ULTC remotely and ATS remote control.
 Control cabinet with control switches, mimic diagram and meters (ION preferred) is provided.
 Annunciation system.
 Equipment to be provided with remote/maintenance switches, when in remote control through
the control panel or SCADA, when equipment is under local control.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 42

 Control panel to be provided with local /remote switches for equipment, when in local, control
from the control panel, when in remote, and control from SCADA.

The following key assumptions are made for SCADA design:

 The existing communication system supports the additional connection and has spares for single-
mode fiber connection available for integrating the new signal from new stations.
 There is an undergoing project by KFW that includes the construction of a new load dispatch
center, the installation of telecontrol systems, and the expansion of the related data transfer
system in the Nepalese transmission grid. As per recent communication with KFW, the SCADA
system which will be installed at LDC will get connected with all the existing 132kV and 66kV
station. KFW will ensure connections at LDC ends for connection of future 220kV and 400kV
stations. The project is delayed and revised schedule for completion of LDC is last quarter of 2018
now. Since the projects’ progress and schedule were delayed few times and possibility of more
delays in future, we assumed the existing SCADA system at the LDC will accommodate the new
SCADA signal from the new stations. We have included upgrading the existing energy
management system (Spectrum Power) and adding new SCADA/RTU (remote telemetry units)
panels in the existing LDC to incorporate the new SCADA signal and I/O from the new stations.
 The existing station has spare AC and DC station service circuits that can be used for the new
development.
 The control buildings at existing substations have space to house new panels.

2.3.5 Bridge study

After consulting with the concerned transportation officer in Nepal, it has been confirmed that all the
bridges along the National highway and feeder road are designed according to the AA Class loading. Class
AA loading comprise a track vehicle of 70 tonnes or wheeled vehicle of 40 tonnes to dimension and
track/axle spacing. Nose to tail distance between two vehicles is 90m on bridge. The maximum loads for
the wheeled vehicle shall be 20 tonnes for a single axle or 40 for bage of 2 axle spaced not more than 1.2
m centers.

Vehicle Dimensions:
The maximum dimensions of vehicles considered for design of roads in Nepal are as follows:
Maximum Width= 2.50 m
Maximum Height= 4.75 m
Maximum Length = 18.00 m
Maximum single axle load= 100 kN (10 ton)

General calculation:
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 43

If we require 10 ton per axle then


Total = 120 ton
Required axle = 12
Minimum spacing between axle= 1.2m
Length of the vehicle required = 12*1.2=14.4m
Letting 3m extra for vehicle body allowance= 14.4+3=17.4
This is under permissible limit of length of vehicle i.e. 18m
If we require 20 ton per axle then
Total = 120 ton
Required axle = 6
Minimum spacing between axle= 1.2m
Length of the vehicle required = 6*1.2=7.2m
Letting 3m extra for vehicle body allowance= 7.2+3=10.2
This is under permissible limit of length of vehicle i.e. 18m
Therefore loads upto 120 tonnes can be transported in Nepal.

Also, all station access routes shall be route surveyed by a logistics transporter company for movement of
transformer and other construction materials.

2.4 Transmission Lines - Engineering Assessment

2.4.1 Transmission Line Design Criteria

Design Criteria
The transmission line design was provided based on design criteria. The design criteria developed using
Nepal Electricity Act 2050, IEC standards, IEEE guidelines, ASTM, BS, CSA, VDE as other standards (such as
Indian Standard - IS) were not available. The design criteria outline the general design requirements, with
site-specific information for 132 kV, 220 kV and 400 kV transmission lines in Nepal.

The criteria include safety clearances for operating transmission lines, the weather and climatic conditions
applicable to areas of all the projects, and load and strength factors of materials. The climatic data
applicable to all the transmission line projects have been obtained from various sources such as NEA
tender documents, Ministry of Environment, Science and Technology, etc. They include parameters such
as temperatures, thickness of snow and/or ice, wind speed, seismic activities, Iso-Keraunic (lightening
activity) data, humidity, pollution and altitude above sea level. They also include major and important
weather cases, load factors and strength factors for structures, cable tension criteria, insulator swing
criteria, equipment and materials including conductors, overhead shield wires and insulators, tower types
for the project, and electrical vertical and horizontal external clearances.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 44

Paying attention to corona phenomenon in design of 400 kV transmission lines is important otherwise
corona losses, electrical field intensity at the edge or outside the right-of-way and radio and television
interference can become an issue. Corona in EHV transmission lines is a parameter of size of conductor
and sharpness of its surface curve, conductor surface smoothness, conductor age, transmission line area
elevation, humidity and precipitation. In MCC compact 400 kV transmission line designs we have utilized
a four bundle phase conductor which gives a proper conductor diameter to the design and we have
avoided high altitudes (above 2,000 m). Comprehensive corona calculations shall be conducted in detail
design stage to insure that the corona of 400 kV transmission lines are in acceptable range. In case any
action required there are available solutions to mitigate the corona. The most effective solution in terms
of technical and economic aspects is increasing the bundle spacing which is associated with very low cost
which won’t affect the feasibility of the project.

Design Codes and Regulations


The design of 132 kV, 220 kV and 400 kV transmission lines is based on both a deterministic approach and
a reliability approach. In the deterministic approach, the various clearances from transmission line
conductors to different features like traffic roads, pedestrian roads, railways, farms, etc. are referenced
from the Nepal Electricity Act. Indian Electricity Rules (IE) and IS have been used for the cases not covered
by the Nepal Electricity Act. Further, some deterministic approaches that were not found in the
abovementioned sources were adopted from CSA C22.3 No. 1. The reliability approach was adopted as
per IEC 60826, while each locality will use climate information specific to its area. The conditions outlined
in the deterministic approach are minimum design requirements for transmission line design, and the
reliability approach outlines additional extreme weather conditions and design requirements for the line.

In addition to these references, some other design codes and regulations have been followed for the
design of transmission lines. For details of design criteria, refer to Annex D.

2.4.2 Equipment and Material Selection

Selection of Phase Conductors


The phase conductors were selected based on the ampacity calculations per IEEE 738. The continuous
thermal ratings for single conductors have been calculated under project-specific operating conditions
and total line thermal ratings have been calculated.

Ampacity calculation is to verify conductor sufficiency for the target loads. However, it appears that the
load of NR1 lines are considerable lower than target loads in year 2030. However, by considering
transmission line life expectancy we concluded that even by considering the above fact, it is not
recommendable to change NR1 line conductors to a smaller sizes.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 45

Targ
2030 2033 2043 2053 2063 2073
NR1 T-Line et
name MV MV
MVA % % MVA % MVA % MVA % MVA %
A A
New
2177 371. 17.0 443. 20.3 793. 36.4 1420 65.25 2544 116.8 4556 209.2
Hetauda-
.53 97 8% 02 5% 39 4% .83 % .49 5% .80 6%
Naubise
Lapsiphedi 2177 456. 20.9 543. 24.9 973. 44.6 1742 80.03 3120 143.3 5588 256.6
-Naubise .53 2 5% 34 5% 04 9% .57 % .68 1% .66 5%
Naubise-
2177 543. 24.9 646. 29.7 1158 53.2 2074 95.27 3715 170.6 6653 305.5
New
.53 1 4% 84 1% .39 0% .51 % .12 1% .22 4%
Damauli
New
Damauli- 2177 781. 35.9 931. 42.7 1667 76.6 2987 137.1 5349 245.6 9579 439.9
New .53 99 1% 36 7% .93 0% .01 7% .27 6% .73 4%
Butwal

Annex D specifies the selected conductors for each transmission line.

Selection of Overhead Optical Ground Wire (OHGW)


Optical ground wire (OPGW) is designed to replace traditional overhead shield ground wires on the
transmission lines with the added benefits of containing optical fibers that can be used for
telecommunications purposes. OPGW, while providing electrical protection to transmission line
conductors by its steel wires, operates as the foundation for communication systems. OPGW has the
advantage of large capacity and high speed fiber optic wires laid over the long-distance transmission lines.
Hence, OPGW was considered for all transmission lines of this compact.

OPGW short-circuit capacity remains to be checked against the output of the PSS®E calculation on 132 kV,
220 kV and 400 kV transmission lines at this time. The following parameters were considered for the
selection of OPGW type:
 Cable tensile strength
 Sag characteristics
 NEA’s common practice.

For transmission line towers carrying two overhead ground wires, OHGW have been selected for the
second wire. For detailed specifications of selected OPGW and OHGW, refer to Annex D.

Selection of Insulators
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 46

Composite-type insulators were selected for 132 kV and 220 kV transmission lines, and porcelain or glass
(ball and socket) type insulators were selected for 400 kV transmission lines. The electrical and mechanical
properties for selected 132 kV, 220 kV and 400 kV insulators are specified Annex D.

The composite-type insulators are in the shape of fiber-reinforced rods that are used as insulator cores
and carry the mechanical loads. There are many advantages to these type of insulators:
 Low weight
 High mechanical strength
 Low maintenance requirements
 Shorter length allowing electrical clearances to be met easier
 Easy to transport and store.

These types of insulators are less pollution absorbent due to the hydrophobicity property of the silicone
rubber material. Thus, they are generally preferred in polluted areas (such as in coastal areas and in
proximity to industrial areas such as cement factories). Also, these types of insulators are more or less not
vulnerable to vandalism (such as shooting, stone throws, etc.).

On the negative side, the composite insulator’s performance is compromised at extra-high voltage
transmission lines. In those transmission lines, one of the mechanical failure modes of the insulators is a
failure process called brittle fracture, which is caused by stress-corrosion cracking of glass-reinforced
polymer rods. This causes the rapid aging of insulators and hence the traditional cap and pin insulators
are still the most favorable in transmission voltages above 230 kV.

Cap and pin type insulators attach to each other, forming an insulator string by inserting the ball of one
unit in the socket of the next unit and securing the connection with a locking key. The advantage of using
these types of insulators is that the insulator strings can form by using different numbers of basic units
and also if one unit in the string breaks, it can be replaced without discarding the entire string. Another
advantage of cap and pin insulators that is beneficial in hilly and mountainous areas is their relatively
higher weight in comparison to composite insulators. This additional weight increases the vertical load on
the tower and can cancel or alleviate insufficient weight spans.

Selection of Towers
Due to the cost and huge length of the lines, the best option is to use self-supporting lattice type
galvanized steel frame tower structures for 132 kV, 220 kV and 400 kV transmission lines. However, in
some urban areas or congested residential areas, compact design steel poles can be used.

The following types of towers have been used in 132 kV, 220 kV and 400 kV transmission lines. For more
details and tower drawings refer to Annex D.

 Suspension Towers
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 47

These towers are used in lines for straight-run or minor angle deviations of up to 2 degrees. These
type of towers are called “DA-type” for double-circuit line. The conductors on these types of
towers are supported by suspension (passing through) clamps. Suspension towers can be
designed to take larger angles (up to 10-15 degrees). These suspension towers are called running
angle/corner towers.
 Angle/Tension Towers
These towers are used at locations where the deviation angle exceeds 2 or 3 degrees or where
the towers are subjected to uplift loads. These towers are further classified as small angle towers
for deviation angles of 2 or 3 to 15 degrees (called B/DB), medium angle towers for deviation
angles of 15 – 30 degrees (called C/DC), and large angle towers for deviation angles of 30 to 60
degrees or in some tower family designs, 90 degrees (called D/DD). The conductors on these type
of towers are supported by tension (dead end) clamps.

 Dead End Towers


Dead-end towers (D/DD/DE) are used at line termination points and can hold a deviation angle of
about 30 to 60 degrees. They are also used as anti-cascading towers, which are used at certain
intervals in line routes to prevent the propagation of a failure.

Preparation of PLS-CADD and Terrain Model


The transmission line models were prepared using PLS-CADD software. It puts together all the data and
algorithms necessary for the layout and structural design of a transmission line. This software supports
transmission line design activities from line routing to developing construction documents and drawings.

Transmission line designers create a three-dimensional model (including terrain data and technical
information on transmission line components (structures, wires and conductors, etc.) and use this model
to develop the line design. Transmission lines in this environment are designed using interactive graphics
and optimum spotting or sagging algorithms.

This software utilizes different program modules in order to analyze and assist with the design and fine-
tune of routing and structures (including lattice towers and poles of different materials), conducting
various calculations such as sag and tension and structure spotting, and the production of construction
documents (such as plan and profile drawings, staking tables, stringing charts and bills of material).

Importing routing output into PLS-CADD and providing digital terrain model. The optimal corridors were
identified and imported in PLS-CADD. The file that was imported contained topographical data (geo-referenced
X, Y, Z data of the ground points in the form of Auto-Cad, Excel sheet or ASCII file). This file needed to include
feature codes (in detailed design when the survey data come from a LiDAR survey or detailed land survey,
feature codes will have to be included in the survey data). However, since detailed survey work is not intended
to be conducted for feasibility-level design, the survey data did not include feature codes in order to label broad
categories of terrain or obstacle points that have unique requirements together with obstacles elevation data.
These requirements include minimum code clearances to be met above or to the side of the points as well as
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 48

symbols to be used to display these points on the screen or final drawings. This three-dimensional labeled
model will be the transmission line corridors of the three-dimensional terrain model.

Fine-tuning of the line route in a given corridor. The fine tuning of the transmission line route in an optimal
corridor or in the presence of multi-criteria, the centerline is selected by locating the points of inflection (PIs)
in the corridor or slightly moving the PIs to improve line routes from a technical perspective without
compromising the environmental, social or resettlement criteria. Critical PIs are assumed to be fixed and other
PIs have been slightly changed in order to moderate sharp angles, steep slopes and inefficient line sections.
This determines the transmission line’s exact route and its centerline. Inserting PIs in a given corridor can be
done manually or automatically. The automatic positioning of PIs requires review and verification, and manual
fine tuning. Here, PIs were manually positioned due to the quality of feasibility-level survey data.

Tower Locations. After the centerline of the transmission lines is finalized, tower spotting is carried out.
The intermediate (suspension/tangent) structures are spotted in the line route based on the line design
criteria. The plan and profile drawings in Annex D provide the locations of all the towers along the
transmission lines.

Access Roads for Transmission Line and Towers. The transmission line routes were selected to be as close
as possible to roads and highways. However, if the route is far from the roads and highways, line material
will be carried to tower locations by other means than dedicated access roads. The traditional way of
transporting construction material, wherever access road is not available, is hiring porters and/or utilizing
animals. This method can be used by construction contractors for line projects. As a result no access road
needs to be considered for transmission line projects.

Right of Way
The right of way corridor is a particular parcel of land that should be kept clear so to ensure the safety of
people and their properties. It is also used to allow access to transmission lines for routine maintenance
work.

As per the Nepal Electricity Act, standard right of way widths for transmission lines are 18 m, 30 m and 46
m for 132 kV, 220 kV and 400 kV transmission lines, respectively.

It should be mentioned that right of way is not a constant value throughout the line route. It is
recommended that the right of way be calculated for each line section based on the actual sag of
conductors, width of tower cross arms, swing of insulator strings, conductors and safety clearance
between conductors, and adjacent objects at the detailed design stage.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 49

Based on the discussion with NEA officers in the Project and Planning Department, the standard right of
way widths in Nepal are as follows:

 400 kV double circuit line = 46.00 meters


 220 kV double circuit line = 36.00 meters
 132 kV double circuit line = 27.00 meters.

However, Nepal’s regulatory bodies have decided to decrease the right of ways to the values below and
NEA has recently adopted these widths for many projects. For this assessment, the following right of way
was used:

 400 kV double circuit line = 46.00 meters (no change)


 220 kV double circuit line = 30.00 meters
 132 kV double circuit line = 18.00 meters.

Preparation of Plan and Profile Drawings


After the PLS-CADD model was completed and thoroughly checked for errors and defaults, the plan and
profile drawings were prepared for all transmission lines. These drawings show transmission line routes
with aerial imagery and profile views showing structures, conductors and OPGWs with required ground
clearance.

Preparation of Bills of Material


Bills of material (BOM) for all transmission lines have been prepared and presented using the cost
estimate documents.

Assessment of Nepal’s Existing Transmission Infrastructure


Although there are no 400 kV transmission line in Nepal, there are some transmission lines built to 400 kV
design, and double circuit towers have been used for these lines. These towers have vertical configuration and
two overhead ground wires: galvanized steel on one side and OPGW on the other side. The conductors are of
ACSR type, which are commonly used in transmission lines around the world.

The 220 kV transmission lines consist of double circuit towers with vertical configuration and single ground
wires, either galvanized steel or OPGW cables and ACSR conductors.

Similar to 220 kV lines, the 132 kV lines have towers with vertical configuration and single ground wires,
either galvanized steel or OPGW cables and ACSR conductors.

Structural Design
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 50

The sample tower and foundation drawings received for existing transmission lines were used to estimate
the required steel weight and cost of the tower. Similarly, foundations from similar transmission lines in
the region were used to calculate the expected material quantities for the transmission line foundations.
Based on the examples available, six different soil conditions are considered for the 400 kV transmission
lines.

 Normal Dry Soil


 Normal Wet Soil
 Fully Submerged
 Wet Black Cotton
 Soft Fissured Rock
 Hard Rock

Further information on soil type and soil characteristics can be found in Geo Technical Reports (Annex E)

For the 220 kV and 132 kV transmission lines, four different soil conditions were considered based on the
examples available:

 Dense Sand or Stiff Clay (Type I)


 Medium Sand or Medium Clay (Type II)
 Loose Sand or Soft Clay (Type III)
 Hard Rock.

Assumptions were made with respect to the anticipated types of soil along the transmission line routes;
although a limited number of boreholes were drilled along the route of most transmission lines, these
assumptions must be validated based on more thorough soil investigation work at the detailed design
stage. As the number of boreholes drilled along the transmission line was not sufficient to provide
reliable, consistent data, each of the soil types was given an expected frequency of occurrence based on
the past experience of NEA staff. The assumed frequencies are:

Transmission line towers in hilly terrain:


 Hard rock: 40%,
 Submerged fissured rock: 40%,
 Normal dry soil 10%,
 Submerged loose soil: 10%

Transmission line towers in plain terrain:


 Normal dry soil: 35%,
 Normal wet soil: 10%,
 Submerged fissured rock: 30%
 Hard rock: 5%
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 51

 Wet black cotton soil: 20%.

Transmission line towers near river beds:


 Wet black cotton soil 70%,
 Normal dry soil: 10%,
 Normal wet Soil: 10%
 Submerged fissured rock: 10%

The above methodology provided the basis for calculating the expected material requirements for the
transmission lines. However, it must be understood that there is a very high degree of uncertainty
pertaining to the material required for the foundations. The actual conditions in the field may be
drastically different than what is assumed for this report and could add significant costs to the foundations
for the project. Contingency factors have been applied for this uncertainty as outlined in the risk section.

The risks below may result in increased foundation sizes and subsequent higher cost for the transmission
lines:
 Poor soil that would increase the size of the foundation footing.
 Poor soil that would not support shallow foundations. Design may need to be changed to a
deep foundation, such as a helical pile foundation.
 Sound bearing strata is deeper than expected, increasing the depth of footing or using piles
to reach the sound bearing strata.

A higher water table than anticipated and/or poor soil requiring the side slope of excavations to be
decreased and increasing the volume of excavation/fill required for the foundations.

2.4.3 Transmission Line Route Selection

Transmission Line Routing Approach


For transmission line routing, multi-criteria routing was used for all transmission lines and a Linear Routing
Tool (LRT) approach. The initial intent was to apply the LRT approach to all line routing; however, the
routes were later selected based on a combination of the multi-criteria approach as well as the use of
(LRT) models. For optimal line routing, consideration was given to social, environmental, economic and
engineering factors.

The LRT approach was applied at full scale to NR1 transmission lines. The outputs of the LRT model were
used in multi-criteria meetings and the required minor adjustments were applied to the suggested routes.
The multi-criteria meetings were attended by the task 1, 2 and 3 leaders, key members and local
professionals. Center lines were developed for each line corridor and the *.XYZ files as well as the aerial
images provided. The *.XYZ files were imported in PLS-CADD in order to develop a PLS model for each
line. Additional improvements were made on the PLS-CADD model to complete the transmission routing
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 52

selection process. Tower spotting was then carried out on these models. The outputs of this exercise –
plan and profile drawings – are shown in Annex D. For all other lines in this project we used multi-criteria
routing method to identify the centerline.

We proposed up to 3 alternative line routes for different lines (except for NR4 & T8) in this project. The
first alternative was due diligence proposed route, second alternative for NR1 was LRT based route and
for NR3 one alternative route was beside the river and another through the forest. The alternate line route
we have selected in the design is the most cost effective and having the least historical challenges (which
are minimum impact on the properties and natural resources).

Volume 2 of this report presents the details of routing using the LRT approach.

Multi-criteria and Participatory Line Routing


The following criteria/considerations were applied to transmission line routing at all stages of the
selection process:

 The route alignments, as far as practicable, were kept straight and short.
 Location of the angle points were approximated in order to determine the requirements for
angle/tension tower.
 Angles were kept as small as possible to avoid sharp direction changes.
 The route between one angle point to the adjacent angle point were appropriate with regards
to longitudinal and transversal slopes, and have an acceptable side profile.
 The route between angle points passes, as much as possible, through the land that is the
easiest and least expensive to acquire.
 The section lengths (distance between two consecutive angle points) were maintained as close
as possible to a multiplier of transmission line ruling span.
 The line sections avoid the following as far as possible:
o Buildings and dense settlements
o Conservation areas, national parks and environmentally sensitive areas (wildlife
habitat)
o Rivers and water bodies
o Traffic roads and highways
o Deep valleys, which may require extra-long spans
o Heavy forest areas or expensive land for rights of way
o Swampy areas
o Highly productive land and difficult terrain
 If crossing existing transmission lines, roads, railways, rivers, etc. is unavoidable, then the
crossing was kept as close to a right angle as possible.
 Proximity to access roads for construction, operation and maintenance work.
 Towers were located on geologically stable ground.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 53

The figures below show the final transmission line routes selected.

Figure 2.9 NR1- Naubise to Lapsiphedi 400 kV Transmission Line

Figure 2.10 NR1 - Naubise to New Hetauda 400 kV Transmission Line


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 54

The final route for the Naubise to New Hetauda line deviates from both NEA’s (which was developed
further by WSP) and LRT practices. The final line route was moved to the west in order to avoid high
elevation areas (2200 – 2300 m). The new route’s elevation is in the range of 1500 – 1600 m. This is an
important factor, especially for 400 kV lines, to minimize corona losses. The new line route was suggested
in the helicopter site visits with OMCN and MCC representatives, and was studied further in multi-criteria
line routing selection sessions.

Figure 2.11 NR1 - Naubise to New Damauli 400 kV Transmission Line

Figure 2.12 NR1 - New Damauli to New Butwal 400 kV Transmission Line
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 55

Figure 2.13 XB1 - New Butwal to Nepal/India border 400 kV Transmission Line

The XB1 line is routed from New Butwal substation to Rampuruwa Maheshpur (near the Nepal/India
border, N 27, 25, 57 E 83, 42, 28.6) based on the recommendation for MCC/OMCN.

Figure 2.14 NR3 - Ilam to Inaruwa 132 kV Transmission Line


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 56

Figure 2.15 T8 New Lamki to Nepal/India border 400 kV Transmission Line

This line follows the same route as the GMR line with small modifications in order to avoid houses as much
as possible.

Figure 2.16 T2’ - 220 kV Transmission Line from Likhu Hub to New Khimti:
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 57

Figure 2.17 T3 – 220 kV Transmission Line from Tadhekani to Kusma


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 58

2.5 Geotechnical Investigation

The objectives of the exploration work for this assignment were to determine the foundation types and
their safe bearing capacities while considering the soil strata. Here, a short geotechnical investigation
program on soil parameters and strata is considered to determine the safety of newly constructed 132 kV
tower foundations along the transmission line corridor.

2.5.1 General Geology and Geomorphology

The sites are located in the mountainous region of the middle part of Nepal, which is part of the Lesser
Himalayan Crystalline Group. The geological formation of the Group is igneous rocks, which contain mainly
Precambrian and probably Paleozoic formations with Augn, Gneisses and two Mica Granites mainly in the
Kuncha Group, with some in the Nawakot Group.

The project site is in a hilly area formed by residual and alluvial soil deposits with sandy gravels, pebbles,
cobbles and boulders, rock fragments with fines and rock mass in their textures around the vicinity of the
sites. The deposits are medium to very dense/hard in state. Moreover, the foundation structure on these
soil layers would be comparatively economical.

The data on epicenters and magnitude of the historical earthquakes show that Nepal is located in high-
hazard seismic zones. The substation and transmission line assessment has considered this criteria during
detail feasibility study.

2.5.2 Methodology

Field Work Procedures


At the time of investigation, a team of experts and workers with a helical hand auger, wash boring, percussion
drilling sets and other necessary equipment were mobilized to the site to make 150 mm diameter boreholes,
sampling and in-situ testing (e.g., Standard Penetration Tests (SPT) and Dynamic Cone Penetration Tests
(DCPT)).

Initially, the bore holes were advanced by auguring, wash boring, pit excavation, percussion drilling and
rotary drilling up to the required depths. Where applicable, SPTs and DCPTs were carried out at an interval
of 1.0 m up to required depth of investigation. These values will be presented in the borehole logs (Annex
E).
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 59

Method of Drilling
The borehole locations were drilled using the following methods:

 Auger Boring Method


This method is generally used in soft to stiff cohesive soils and semi cohesion less sandy soils
above the water table. A helical auger is used for boring and retrieving disturbed samples from
sub surface layers following the IS: 1498 Method
 Wash Boring Method
This system was developed for clayey and sandy soils only. Here, a boring pipe is driven manually
with water or bentonite slurry up to the required depth and the SPT values are recorded. The
retrieved disturbed samples are collected and preserved for identification and required
laboratory tests.
 Pit Excavation
Pit excavation is used when the soil layers are medium to dense sandy or gravelly layers with
cobbles, pebbles, small to medium size boulders, and weathered to fissured rock mass. Then, the
pit excavation method is widely used for digging and sampling of sub-surface layers while
conducting SPT/DCPT observations. Pit excavation should proceed by digging soil strata with the
help of mechanical tools such as shovels, picks, chisels, crow bars and hammers up to the
proposed foundation depth ( 3.5m) and then DCPT tests will be carried out in the lower depths.
 Percussion Drilling Method
This method is carried out using heavy chisel bits and bailers with casing. A heavy chisel bit is used
to chop the clayey to gravelly soil layers having pebbles to cobbles. The soil samples could be
retrieved from bailers and SPT tubes.
 Rotary Drilling Method
This method is employed by rotating the bit fixed at the lower end of the drill rod (i.e., barrel)
with drilling fluid, water or Bentonite slurry. The total weight of the rotary machine and its
accessories would be 3000 to 4000 kg. The transport, shifting and handling of the equipment is
quite difficult. When water courses, streams, rivers, etc. cannot be found in hilly and jungle areas
to produce the continuous flow of water needed for drilling works, this method is uneconomical
and not generally used in Nepal. However, this method could be adopted in the project area
where fissured and hard rocks are encountered.

Field Tests
The field tests were conducted using two methods:

Standard Penetration Tests (SPT): This consists of driving a split spoon sampler with an outside diameter
of 50 mm into the soil at the bottom of boreholes or pits. Driving is accomplished by dropping a hammer
weighing 63.5 kg from a height of 750 mm onto the drive head. First, the spoon is driven 150 mm into the
soil at the bottom of the boreholes/pits. It is then driven another 300 mm and the number of blows (N
values) required to drive this distance are recorded.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 60

Dynamic Cone Penetration Test (DCPT): This consists of using a hammer to drive a cone into the soil. The
number of blows needed to drive the cone a specified distance is the measurement of the dynamic cone
resistance.

A DCPT is performed using a 50.0 mm cone. The driving energy is given by a 63.5 kg hammer falling freely
from a height of 750.0 mm onto the drive head. It is then driven 300 mm and the number of blows (DCPrec
values) required to drive this distance is recorded.

The dynamic cone resistance value is converted into the SPT value and used for the analysis of bearing
capacity.

Sampling
Samples from the field can be retrieved in two ways as per soil profiles:

Disturbed Samples. Before any sample is taken, the boreholes/pits should be clear of loose disturbed soil
deposited during boring/excavation operations. The samples obtained by auguring/drilling or pit
excavation and SPT tubes are collected as representative disturbed samples for determining physical and
engineering properties. The samples thus obtained must be placed in airtight double plastic bags, labeled
properly for identification, and transported to the laboratory for analysis.

Undisturbed Sample. Here, soils are extracted by a thin wall tube (Shelby Tube) that is used to determine
strength and compressibility characteristics. The tube is pushed into the subsurface layers and the sample
is recovered mechanically. The tube is then sealed with wax and wrapped with airtight polythene sheets,
and then bound by adhesive tape and labeled. The tube is properly packed and transported to the
laboratory.

Laboratory Tests
The following laboratory tests shall be conducted for the retrieved soil samples to obtain the physical
and strength properties of the sub soil, as per IS & ASTM standards:

 Grain Size Distribution Analysis. Grain size distribution is determined by wet and dry
mechanical processes. Sieve analysis is carried out by sieving a soil sample through a set of
sieves, with the largest at the top and the smallest at the bottom. The soil retained in each
sieve is weighed and expressed as a percentage of the weight of the sample (see Annex D).
 Atterberg’s Limit. Liquid limits and plastic limits are determined on fine grained soils using
standard methods. Casagrande’s Plasticity Chart is used to classify the fine grained soil
according to the Unified Soil Classification System.
 Natural Moisture Contents, Bulk & Dry Density. The natural water content and bulk density
are determined from samples recovered through a split spoon sampler or barrels and the
corrected SPT values.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 61

 Specific Gravity Tests. The specific gravity test is conducted on soil samples that pass through
a 200 mm sieve. The density bottle method is widely used in laboratory tests for determining
the specific gravity value.
 Direct Shear Tests. Direct shear tests are conducted on representative disturbed samples
collected from boreholes. The samples are carefully molded to have almost the same
moisture contents using standard molds of 6.0 x 6.0 cm² cross-sectional areas and trimmed
to 2.5 cm high. Solid metal plates are placed on both surfaces of the samples to prevent the
dissipation of pore water during shearing. The direct shear test equipment is mechanically
operated and shearing should be applied at a more or less constant strain rate. The samples
are to be sheared at three different normal stress levels. The test results are presented in
terms of the failure of envelops to obtain the angle of internal friction and the cohesion
intercepts.
 Consolidation Tests. These tests are performed on disturbed samples of 75 mm diameter and
22 mm height as per laboratory requirements. Two-way drainages are provided and each
increment of load must be maintained for a sufficient period before primary consolidation is
reached.

Soil Types
After drilling or excavation, the retrieved soil samples can be found in different states in in-situ soil layers.
The general soil types as per their in-situ states are:

 Normal dry soil


 Wet soil
 Fully submerged soil
 Sandy soil
 Dry fissured rock
 Wet fissured rock
 Submerged fissured rock
 Hard rock

Site Description
The site description facilitates the categorization of different types of tower foundations following the
crude estimation of:
 Types of land
 Types of landscape
 Size of soil grains
 Rate of permeability
 Possibility of water courses nearer to the site location
 Probability of raising water table

Further, all the site locations will be explored as per site description following the above points.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 62

Bearing Capacity
The allowable safe bearing capacity, considering permissible settlement, is proposed in Annex E.

Type and Depth of Foundation


The type of foundation depends on types of soil, subsoil water level, and presence of surface water as per the
technical specifications:
 Normal dry/ wet soil foundation
 Fully submerged foundation
 Dry fissured rock foundation
 Wet fissured rock foundation
 Hard rock foundation

Different depths of foundation should be proposed from the original ground level. The bearing capacity of
soil at the boreholes for those depths is calculated as the square, mat or pile foundation as per requirements.
Generally, the technical specification recommended is to rest tower legs at 3.0 to 4.0 m depth ( 3.5m) from
ground level.

Recommendations
The following procedures are recommended for the project site locations:
 Soft to very stiff cohesive soils, sandy soils, and silty soil layers should be drilled by auger and wash
boring systems, and the samples retrieved and field observations made at required intervals.
 In sandy soils, gravelly sands, silty sands with fine gravels, and pebbles, the percussion drilling method
should be adopted if the location is accessible and lies in flat terrain.
 For soils having sandy gravels with pebbles, cobbles, and small to medium size boulders, pit
excavation should be carried out up to the required depth of foundation level and SPT/DCPT tests
should be taken to determine the allowable bearing capacity values.
 The rotary drilling method is not quite feasible for the soil investigation of tower foundations, but
could be done at some locations where its requirements will be fulfilled.
 There should be borehole testing for every 5 to 7 KM of Transmission line and 3 boreholes / stations
for detail design phase.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 63

2.5.3 Depth of Investigation

The required depth of investigation depends on many factors, including the type of structure and the
associated magnitude of the loading, the subsurface conditions and their variability, the depth of planned
excavation, and the types of foundations to be constructed.

In regards to the foundation loading, if a building will be founded on spread footing foundations, the
general practice is to investigate to a depth below the planned founding level equal to at least 2 to 3
times the footing width (noting however that the founding level and/or footing widths are not always
known at the time of investigation). If however weaker or compressible strata could exist at greater than
this depth (such as is often the case in the sensitive marine Champlain Sea clays) and could compress
under the loading from foundations or the weight of site grading fill and lead to foundation settlements,
then greater depth of investigation is required. The investigation should extend to at least sufficient
depth to investigate the most compressible (i.e., softest) portions of the deposit (which are generally the
upper few meters of the un-weathered clay, below the weathered surficial crust). If the grade on a site
will be raised (i.e., if underslab and/or landscaping fills will be placed on the site), the additional loading
will increase the stress level in the underlying clay over a significant depth. In this case, the investigation
should extend to sufficient depth to show that the preconsolidation pressure of the deposit is in excess
of the final stress level that will be achieved.

Where deep foundations (such as piles or caissons) may be required, the investigation should extend at
least to the bedrock surface.

Where a site is to be developed with a building and is underlain by generally cohesionless


(granular/sandy) soil, which extends below the groundwater level, the depth of investigation should be
sufficient to address the potential for seismic liquefaction.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 64

Figure 2.5.3
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 65

2.5.4 Complete Profile of Soil Investigation

Transmission Line Photograph

Figure 2.5.4 : New Butwal – India Border Transmission Line


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 66

Figure 2.5.4.1 : New Damauli – Naubise Transmission Line (Complete View)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 67

Figure 2.5.4.2: Damauli – Naubise Transmission Line Part – I


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 68

Figure 2.5.4.3 : Damauli – Naubise Transmission Line Part – II


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 69

Figure 2.5.4.4 : Lamki – India Border Transmission Line


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 70

Figure 2.5.4.5 : Naubise – Lapsiphedi Transmission Line


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 71

Figure 2.5.4.6 : Naubise – New Hetauda Transmission Line


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 72

Figure 2.5.4.7 : New Butwal – New Damauli Transmission Line


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 73

Figure 2.5.4.8 : Tadhekani – Kusma Transmission Line


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 74

Substation Photograph

Figure 2.5.4.9 : Lamki Substation


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 75

Figure 2.5.4.10: Lapsiphedi Substation (Zoom out)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 76

Figure 2.5.4.11: Lapsiphedi Substation (Zoom In)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 77

Figure 2.5.4.12 : Naubise Substation (Zoom Out)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 78

Figure 2.5.4.13: Naubise Substation (Zoom In)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 79

Figure 2.5.4.14: New Butwal Substation


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 80

Figure 2.5.4.15: New Damauli Substation (Zoom Out)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 81

Figure 2.5.4.16: New Damauli Substation (Zoom In)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 82

Figure 2.5.4.17: Tadhekani Substation (Zoom Out)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 83

Figure 2.5.4.18: Tadhekani Substation (Zoom In)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 84

2.6 Operations and Maintenance


The proper maintenance of transmission systems and substation not only improves reliability but also
generates revenue. Preventive or periodic maintenance is very relevant for keeping equipment
continuously in service. This forms the basis for “condition-based maintenance,” which helps in
providing advance information about the health of the equipment for planning for major
maintenance/overhauls.

2.6.1 Maintenance Strategy

The objective of the O&M strategy will be:


 To achieve system availability as specified by the regulator/system administrator at the most
economic cost
 To carry out periodic preventive maintenance so as to maximize the life of transmission lines
 To minimize the down time of the transmission lines for maintenance purposes.

The operation and maintenance of the transmission system shall be done in an efficient, coordinated
and economical manner, in compliance with the latest IE rules, safety regulations, grid code, Electricity
Act, CBIP Manual, Standards of Performance Regulation, and other applicable regulations and laws.

The maintenance philosophy to be adopted should cover both cold and hot line techniques so as to
maximize system availability.

Experienced and trained manpower should be deputed for O&M to carry out preventive maintenance
and condition monitoring of the transmission system. Also, all necessary tools and equipment will be
procured and kept in storage to reduce downtime. An adequate number of stores will be established
across the project area
Proven practices as described below shall be implemented:
 Routine patrolling of transmission lines at regular intervals.
 Visual inspection of insulator discs and jumpers.
 Lopping & chopping and bush clearance not involving tree cutting/crop compensation and right
of way problems.
 Inspection of foundations and completeness of tower members.
 Thermo-vision scanning.
 Replacement of missing/damaged tower members.
 Minor rectification/repair works not involving tower collapse or foundation failure under shut
down.
 Pre- and post-monsoon inspections.
 Special patrolling on tripping of the line.
 Repair of conductors.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 85

 Punctured insulator detection in insulator failure prone stretches on an as-needed basis without
availing shut down.
 Replacement of accessories like spacers and vibration dampers.
 Rectification in respect of conductor and earth-wire snapping not involving tower collapse.

Regular maintenance of each transmission line should be conducted to achieve the desired level of
performance. The maintenance activities must be predefined and the schedules developed in advance.
The scheduling of the regular maintenance shall be as under:

 Ground patrolling: For trimming of overgrown trees, liaise with locals to prevent the development
of plantations/structures that could infringe the statutory clearances, detection/ replacement of
stolen tower members and accessories, detection of displaced vibration dampers, spacers, etc.,
detection of hot spots/broken insulators/thermo vision scanning, soil erosion, rusting of tower
members, tower earthing, etc.
 Pre-monsoon patrolling: Inspect each of the tower locations that are not likely to be
approachable, or are vulnerable to water logging, soil erosion due to heavy flow of water, mid-
stream tower locations, revetments, etc.
 Post-monsoon patrolling: Inspect each of the locations that could not be visited during the
monsoon, checking for any damage to/exposure of the foundations, missing tower parts, damaged
revetments, and all others that are scheduled for regular ground patrolling.
 Pre/Post-winter/summer patrolling: In addition to the activities listed for regular ground
patrolling, intensive checks should be made for broken insulators, hot spots, tower earthing, and
live line washing of insulators.

2.6.2 Maintenance Schedule for Substation Equipment

Maintenance is defined as a combination of actions carried out to return/restore equipment to an


acceptable condition. Different types of maintenance being done on equipment are:

 Breakdown Maintenance: This maintenance is carried out when the equipment fails. It may be
appropriate for low-value items. However, for costly substation equipment, it is not desirable to
wait until a breakdown occurs, as it costs more to the utility as well as lessens power availability.
 Preventive Maintenance: This maintenance has been adopted by almost all utilities. In this type
of maintenance, equipment is inspected at a predetermined period, which is based on past
experience and also guidance from the manufacturer. This type of maintenance would require
specific periods of shutdown.
 Condition-Based Monitoring: This type of maintenance is used to assess the condition of the
equipment by carrying out tests. Some of the tests are done on-line and some off-line. However,
this type of maintenance would need sophisticated testing equipment and skills for analyzing the
test results.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 86

 Reliability Centered Maintenance: This is a recent technique based on the life cycle cost concept.
The decision to replace equipment is taken based on techno-economic considerations. Its
objective is to devise a system that does not need periodic maintenance and at the same time
predicts in advance possible equipment failures/problems.

2.6.3 Tentative Maintenance Schedule for Substation Equipment

Remarks /
Activity Date Condition Remedy with
Target date
Maintenance Schedules for ICT
Checking of bushing
oil level
Checking of oil level
in conservator
Checking of oil level
in OLTC conservator
Checking of cooler
oil pumps and fans
Manual actuation

Checking of oil leaks

Checking condition
of silica gel in
breather

Checking oil level in


oil seal of breather

Remarks / Remedy with


Sr. No. Activity Date Condition
Targeted date
2). CIRCUIT BREAKERS :

2.2 C Checking of oil leaks


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 87

Remarks /
Activity Date Condition Remedy with
Target date
Maintenance Schedules for ICT
3). CURRENT TRANSFORMER :

Checking of below
3.2 a
expansion/ oil level
B Visual inspection of CT for
oil leakage/ oil level and
cracks in insulator, etc.
4). CAPACITIVE VOLTAGE TRANSFORMERS :

4.1 d Checking of oil leaks

5) PROTECTION SYSTEMS :

Testing of DR/EL for time


5.1 a
synchronization
6). BATTERIES AND DC DISTRIBUTION SYSTEM :

Measurement of specific
A gravity and voltage of cell
with charger off

Checking electrolyte level


B and topping up with DM
water, if required
Checking of emergency DC
C
lighting
To control room
I Checking of any earth fault
(If E/F relay not provide)
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 88

2.6.4 Tentative O&M Expenses per Annum

Item Description Qty No of Annual


Unit Cost Month Charges

R&M – Building
R&M-Office maintenance & running Per
expenses Month
Per
R&M-Stores Month
R&M-Guest house including monthly Per
maintenance Month

Repair & Maintenance - other


R&M-Vehicles Including fuel Nos

Electricity Charges
Electricity-Office Nos
Gen set running exp Nos
Electricity-Stores Nos

Travelling & Conveyance


Railway tickets inland Nos
Local travel at outstation Lot
Travelling - Other expenses Lot
Caretaking and Support Staff
Caretaker for offices Nos
Cook/sweeper, etc. at guest house Nos
Manpower
O&M project in charge Nos
Commercial head Nos
Engineers Nos

Miscellaneous Expenses
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 89

Item Description Qty No of Annual


Unit Cost Month Charges
Management Meetings Nos
Audit Fees Nos
Legal Fees Nos
Safety Audit Nos

R&M - Plant & Machinery


R&M-Office equipment Lot
R&M-Towers Lot
DA Type No
DB Type No
DC No
DD No
R&M Tools & tackles
General maintenance resident
R&M land crop/way leave charges Yearly
R&M earth wire Kms
R&M Hardware Fittings
120 KN single I pilot string for 400
kV quad moose Nos
120 KN for single suspension string
for 400 kV quad moose Nos
2*160 KN double tension for 132 kV,
220 kV,400 kV quad moose Nos
1x160 kN single tension strings for
transposition tower Nos
R&M conductor & earthwire acce
Mid-span compression joint Nos
Repair sleeves for conductor Nos
T-Connector for transposition tower Nos
Quad vibration damper for 132 kV,
220 kV, 400 kV Nos
Quad rigid spacer for 132 kV, 220 kV
400 kV Nos
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 90

Item Description Qty No of Annual


Unit Cost Month Charges
Dead end clamp for tension towers
for 400 kV Nos
T-connector for dead end clamp Nos
Bundle spacer for ACSR moose Nos
EW accessories
Mid-span compression joint Nos
Repair sleeves Nos
Flexible copper Bond Nos
Vibration damper Nos
Earthwire suspension clamp Nos
Earthwire tension clamp Nos
R&M tower accessories Lot

R&M conductor Kms


R&M insulator
120 KN Nos
160 KN Nos

R&M OPGW & Fitting


OPGW conductor (24 Fiber) DWSM Kms
Tension – single Nos
Tension – double Nos
Suspension Nos
Down lead clamps Nos
Joint box Nos
OPGW holder bracket Nos
Vibration dampers Nos
Fiber optic distribution frame Nos
Per annum maintenance charges
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 91

As per the inputs obtained from NEA officials, NEA have their Routine Maintenance Schedule for Basic
Maintenance of Transmission Lines and Substations such as Patrolling of Transmission Lines, Periodical
Tree Cutting , Maintenance of Batteries , Verification of Leakages in SF6 Breakers .They do have the Basic
Tools & Equipments such as Oil Filtration Machines, Testing Equipments for Transformers CTs, Breakers,
Relays etc .They also have the line Construction Equipments for EHV Lines up to 220kV. As regards
Providing Training and Tools, we may include the provision in the Bid Specifications. We have made a
Provision of 5 % of the total material cost for special tools & Spares, in the cost Estimates.

2.7 Project Cost Estimates

Cost estimates for all MCC projects were prepared as follows:

NR-1: East-West 400kV Transmission Backbone


 400 kV double circuit transmission line with quad moose ACSR (hilly terrain in Central Nepal)
o New Butwal – New Damauli – 84 km
o New Damauli – Naubise – 98 km
o Naubise to New Hetauda- 41 km
o Naubise to Lapsiphedi- 48 km
 Five New 400 kV substations at
o New Hetauda
o Naubise
o New Damauli
o New Butwal
o Lapsiphedi

NR-3 Ilam- Inaruva 132 kV Network Reinforcement


 Ilam – Inaruwa double circuit 132 kV 110 km transmission line with single bison ACSR (mostly hilly
terrain in far eastern Nepal)
 2 new 132 kV Line bays at Ilam substation
 2 new 132 kV line bays at Inaruwa substation

NR-4 Balanch – Attariya 132kV Network Reinforcement


 Second circuit stringing on existing 132 kV Balanch – Attariya transmission line with single bear
ACSR (mostly hilly terrain in far western Nepal)
 1 x 132 kV line bay at Balanch substation
 1 x 132 kV line bay at Attariya substation

T3 Tadhekani-Kusma 220kV Network Reinforcement


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 92

 2 x 220 kV lines from Tadhekani to Kusma approximately 27 km, double-circuit transmission line
through hilly regions in western Nepal
 2 x, 220 kV-132 kV, 165 MVA transformers
 2 X 220 kV line bays at Kusma substation

T-2’ New Khimiti – Likhu Hub 220 kV Transmission Cord Extension


 New Khimti – Likhu Hub double circuit 220 kV 30 km transmission line with twin bison ACSR (hilly
terrain in eastern Nepal)
 220 kV substation at Likhu Hub
 2 X 220 kV line bays at New Khimti substation

T-8 New Lamki 400 kV Transmission Cord Extension


 New Lamki to Nepal/India border 400 kV 30 km double circuit transmission line with quad moose
ASCR (flat Terai terrain in western Nepal)
 New 400 kV Substation at Lamki

XB-1 400 kV Cross Border transmission Line


 New Butwal - Cross border 400 kV 30 km double circuit transmission line from with quad moose
ACSR (flat Terai terrain in central Nepal)

Key Assumptions
The estimates presented in this report are based on following data and assumptions:
 The unit prices for the project cost estimation are determined using the schedule of prices loaded
by Indian utilities and the costs of completed projects in India and Nepal.
 The price structure of contracts awarded by utilities in Nepal during 2011 and 2014-2015 for 132
kV and 220 kV transmission lines and 132 kV bays are used as references.
 The contracted rates for 220 kV and 400 kV substations and transmission lines in India during the
2011-2013 and 2015-2016 were considered.
 The effect of price inflation with respect to materials/equipment at the rate of 2% per annum for
materials supply and at the rate of 5 % per annum for services. (WPI – https://dbie.rbi.org.in
CPI – http://labourbureau.nic.in )
 The rates of conversion of Indian Rupees and Nepali Rupees to US Dollars used are 68 INR/USD
and 104 NRS/USD, respectively.
 The provision of contingencies was considered as 10% on the total project cost.
 The cost of administrative expenses, accounts and audit expenses, supervision costs, were
considered in this estimate.
 Interest during the construction is not considered in the estimate.
 Land costs, environmental and permit application costs are included.
 It should be pointed out that today’s prices exhibit a broad scattered range around the estimated
prices due to the current high fluctuation of the costs of raw materials (steel, copper, galvanizing
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 93

zinc, oil, etc.), the volatility of the USD exchange rate to other major currencies and the current
situation of contractors.

Methodology Adopted
The following were considered while preparing the cost estimates:

 Design criteria followed in the design of the transmission line and substation civil and electrical
works
 Terrain of the route of the transmission line and site of the substation
 Details of river crossings encountered in the route of transmission lines
 Results and recommendations from the survey and soil investigations conducted for the proposed
transmission lines and substations
 Type of tower configuration used and type of conductor and earth wire used in the construction
of the transmission line
 Switchyard equipment to be used in the switchyard area.

Quantity Calculations
The bills of materials for civil and electrical works of transmission lines and substations are shown in Annex
C. Quantities were based on the design drawings and the total cost estimate for each project was
calculated based on estimated quantities and cost rates as mentioned above.

Rate Analysis
The cost estimates of the civil and electrical works were based on the prevailing basic rates of materials,
equipment and labor. These rates were based on the Standard Schedule of Rates of Indian Utilities and
NEA.

Abstract of Cost
The abstract of the cost of civil and electrical works included expenditures incurred to date and the
provisions required for the balance work including the quantity, rates and amount of each of the items
included in the estimate.

The cost estimates were prepared after route verification of the transmission line, substation
transformation capacity, and BOM. The estimated environmental, social and resettlement costs of each
project were also considered after obtaining inputs from other disciplines.
The cost estimate for each project includes:

 Bill of quantities of major equipment and materials for transmission lines and substations
 Design and engineering cost
 Project management costs
 Services and works contractor cost
 Material and erection components
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 94

 Provision for contingencies


 Administrative costs
 Applicable taxes
 Route correction factor
 Additional foundation cost for extended chimney works
 Tower foundation protection cost
 Conductor length Multiplier (due to Sag)
 Contingency (Foundations)

The cost estimate includes inflation adjustment costs on materials as well as the erection component of
the projects. The cost estimate also provides compensation for land acquisition, damage to standing
crops, and the immovable property of land owners. For more details on compensation, refer to the
Volume 3, Task 3 (Resettlement) report.

For this purpose, the procedure used at NEA for estimating project costs was discussed and studied. The
routes have been finalized through desktop studies and during the studies, we identified five different
terrain types through which line route passes.

Accordingly, we developed a cost multiplier to observe feasibility-level routing inefficiency in each


transmission line. This has been considered as a route correction factor in the preparation of estimates.

Route Correction Factors

Table 2.17 Route Correction Factors


Sr. No Transmission line Route Correction factor
1 New Butwal – New Damauli 0.75
Line
2 New Damauli – Naubise Line 0.68
3 Naubise - New Hetauda Line No Change
Naubise - Lapsiphedi Line 0.8
5 Ilam- Inaruwa Line 0.85
6 Balanch – Attariya Line NA
7 New Khimti – Likhu Hub Line 0.82
8 Tadekhani – Kusma Line 0.78
9 New Lamki - India Border Line 0.9
10 Butwal - India Border Line 0.95

According to data collected from NEA, line construction works in hilly terrains require a certain number
of foundation chimney extensions. Extension are required when the largest tower’s unequal leg cannot
cover the difference in natural ground elevations at tower legs points. This added cost can reach 5-10%
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 95

of the line’s foundation cost depending on the harshness of its terrain. The following rates have been
applied to different lines for this matter.

Extended Chimney Added Cost Factor

Table 2.18 Extended Chimney Added Cost Factors


Sr. No Transmission line Extended Chimney Factor
1 NR3 1.08
2 T2’ 1.1
3 NR1 1.06
4 NR1; New Damauli – New Butwal 1.05
5 XB1 1
6 T3 1.1
7 T8 1

Data collected from NEA also suggest that in hilly areas, transmission line foundations need to be
protected by the construction of retaining walls in certain route slopes. This cost may vary from NRS
20,000 to NRS 40,000 per kilometer depending on the harshness of the terrain. The following additional
costs have been considered for different transmission lines to observe this cost factor.

Extended Foundation Protection Cost

Table 2.19 Extended Foundation Protection Cost


Sr. No Transmission line Foundation Protection Cost (NRS/km)
1 NR3 20,000
2 T2’ 35,000
3 NR1 15,000
4 NR1; New Damauli – New Butwal 13,000
5 XB1 0
6 T3 35,000
7 T8 0

Conductor Length Multiplier (Due to Sag):


This is an important consideration in the mechanical design of overhead lines. The conductor sag should
be kept to a minimum in order to reduce the conductor material required and to avoid extra pole height
for sufficient clearance above ground level. It is also desirable that tension in the conductor should be
low to avoid the mechanical failure of conductor and to permit the use of less strong supports
In an overhead line, the sag should be so adjusted that tension in the conductors is within safe limits.
The tension is governed by conductor weight, diameter and its mechanical properties such as coefficient
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 96

of thermal expansion, modulus of elasticity …, effects of wind, ice loading, temperature variations and
safety margins in different loading conditions which are to be applied to conductor tensioning criteria in
terms of maximum allowable percentage of its ultimate tensile strength.

Conductor length is never equal to transmission line route length and is always longer than the route
length by a certain percentage because of conductor sag. The conductor sag which is mainly a
parameter of its tension depends also on the ground profile on which transmission line stretches. As a
result conductor length is longer in mountainous and hilly terrains than in flat terrain. So the extra
percentage which shall be applied to line route will be higher in mountainous and hilly terrains
comparing to flat terrain. The following conductor length multipliers are applied to line routes in
different projects to observe the terrain difference in different projects’ route.

Project Particulars
Conductor Length Multiplier
(Due to Sag)
New Butwal – New Damauli Line 1.07
New Damauli – Naubise Line 1.08
NR1
Naubise - New Hetauda Line 1.09
Naubise - Lapsiphedi Line 1.08
NR-3 Ilam- Inaruwa Line 1.07
NR-4 Balanch – Attariya Line 1.07
T-2’ New Khimti – Likhu Hub Line 1.08
T-3 Tadekhani – Kusma Line 1.08
T-8 New Lamki - India Border Line No Change
XB-1 Butwal - India Border Line No Change
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 97

Contingency (Foundations)

This tables shows different contingency used for Transmission lines foundation design. Due to lack of
information on boreholes, additional contingency has been used in the cost estimate. These contingency
includes 10% overall contingency applied to all the projects.

*For Contingency basis, please refer to Transmission Line Geo Technical Risk Assessment in Section 2.9

Contingency
Project Particulars
Foundation (%)
New Butwal – New Damauli Line 50
New Damauli – Naubise Line 50
NR1
Naubise - New Hetauda Line 50
Naubise - Lapsiphedi Line 50
NR-3 Ilam- Inaruwa Line 50
NR-4 Balanch – Attariya Line NA
T-2’ New Khimti – Likhu Hub Line 50
T-3 Tadekhani – Kusma Line 50
T-8 New Lamki - India Border Line 40
XB-1 Butwal - India Border Line 40

Inflation Calculation
It is an overall rate of inflation worked out considering component of materials supply and services as
60:40. We have considered rate of inflation at the rate of 2% per annum for materials supply and at the
rate of 5 % per annum for services. Clubbing together, the annual rate of inflation would work out to (60
X 0.02) + (40 X 0.05 i.e. 61.2 + 42.0 = 103.2). Therefore rate of inflation on total contact cost is
considered @ rate of 3.2 % Per Annum. Compounded over the MCC Compact period of 5 years, it will
be a total of 17.06 % say 17 %.

Recommendation on Operation and Maintenance Activity Costs


Schedules of maintenance for transmission lines and substations were prepared as per standard practice
implemented in Nepal and India. The effects of terrain, environment and spares availability were taken
into consideration for this purpose. O&M costs were derived considering a life cycle of 50 years for
transmission lines and 30 years for substations. The engineer’s input was obtained regarding the Inventory
of spares to be maintained for transmission lines and substations, and the finalization of technical
specifications for equipment and materials. As per engineer’s inputs, following will be additional O&M
training required to maintain 400kV substations in Nepal.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 98

Following training will be required for employees in charge of maintaining the T Line and stations with the
help of material suppliers. Training will be integral part of all material supplier contractors:
 Training for 400kV and 220kV GIS
 Training on maintenance for the new 400kV equipment

We also assume that NEA already has the following elements / equipment:
 Preventive maintenance computer program. If not available in house.
 Nacelle trucks
 Thermographic testing equipment (Refer to Flir)
 RMS multi-function meter with 0.5% accuracy (Refer to Fluke). Should already be available has it
is the most basic maintenance tool.
 Megohmmeter (Refer to Fluke)
 Low Resistance Ohmmeter (Refer to Megger)
 Earth Resistance Meter (Refer to Megger has some models)
 Primary injection testing system like CPC 100 from Omicron
 Power factor meter (Fluke)
 Relay test set (Doble)
 Transformer Turn-Ratio Test Set (Megger)
 Purchase of recommended spares parts for the different 400kV equipment (breakers, switches,
CTs, PTs)

2.8 Project Procurement Packaging


This section describes our proposed methodology for packaging procurements for the MCC compact.
MCC’s compact consists of the following projects, which have been listed from the east to the west of the
country.

Table 2.20 MCC Compact Projects from the East to the West of Nepal
MCC
Voltage GIS /
Project Name project Remarks
(kV) AIS
title
Ilam substation upgrade 132 AIS NR3 Adding two line bays to existing
substation
Inaruwa substation upgrade 132 AIS NR3 Adding two line bays to existing
substation
Ilam – Inaruwa transmission line 132 - NR3 Double circuit transmission line
Likhu Hub substation 220/132 GIS T2’ New substation beside IPP’s 132 kV
substation
New Khimti substation upgrade 220 AIS T2’ Adding two line bays to existing
substation
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 99

Table 2.20 MCC Compact Projects from the East to the West of Nepal
MCC
Voltage GIS /
Project Name project Remarks
(kV) AIS
title
Likhu Hub – New Khimti transmission 220 - T2’ Double circuit transmission line
line
Lapsiphedi substation 400/220 GIS NR1 New substation beside ADB’s 220 kV
substation
Naubise substation 400/220 AIS NR1 New substation
New Hetauda substation 400/220 GIS NR1 New substation beside WB’s 220 kV
substation
New Damauli substation 400/220 GIS NR1 New substation
New Butwal substation 400/220 AIS NR1 New substation beside ADB’s 220 kV
substation
Lapsiphedi – Naubise transmission line 400 - NR1 Double circuit transmission line
New Hetauda – Naubise transmission 400 - NR1 Double circuit transmission line
line
Naubise - New Damauli transmission 400 - NR1 Double circuit transmission line
line
New Damauli - New Butwal 400 - NR1 Double circuit transmission line
transmission line
New Butwal – cross border 400 - XB1 Double circuit transmission line
transmission line
Tadhekani substation 220 GIS T3 New substation

Kusma substation upgrade 220 AIS T3 Adding two line bays to existing
substation
Tadhekani – Kusma transmission line 220 - T3 Double circuit transmission line

New Lamki substation 400/132 AIS T8 New substation

New Lamki – cross border transmission 400 - T8 Double circuit transmission line
line
Attariya substation upgrade 132 AIS NR4 Adding one line bay to existing
substation
Balanch substation upgrade 132 AIS NR4 Adding one line bay to existing
substation
Attariya – Balanch transmission line 132 - NR4 Adding second circuit to existing
transmission line
In summary, the MCC compact includes 8 new substations, 6 substation upgrades, and 10 transmission
lines from 132 kV to 220 kV and 400 kV, which are spread across the country. It is not feasible to award
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 100

all of these projects to one or two contractors and it would be better to package them as subprojects.
However, it is recommended that one Engineering firm be responsible for the full oversight for all
packages and to coordinate all packages.

There are different ways in which procurement could be packaged:


 Method # 1 – Packages are split according to their geographical location
 Method # 2 - Groupings are based on substation size and/or transmission line length
 Method # 3 – Groupings are based on voltage levels
 Method #4 – Groupings are based on technology (e.g., AIS or GIS) or type of equipment/material
 Method #5 – Groupings are based on power system parameters (their contribution to
improvements in power flow and technical losses) and economic factors (profitability and
sensitivity).

Each of these methods of packaging has advantages and some of them have a number of disadvantages:
 The advantages of Method 1 are that the contractor’s logistics will be worked out more efficiently,
faster, and at less cost. Additionally, a sub-project with a smaller footprint will be managed more
effectively than one with geographically scattered elements. Further, local resources will be
better utilized by separating projects in this way.
 Large size projects require special project and construction management skills, and usually require
highly experienced international contractors (especially in Nepal), while small projects can be
efficiently managed by regional contractors (or even in the case of very small projects, by local
contractors). By separating small from large projects, regional or local contractors will have a
chance to engage in some of the packages, making small package tenders more competitive.
 For projects of different voltages, the design, procurement and construction approaches will also
differ. There are some criteria and phenomenon that are critical in 400 kV infrastructures that
normally do not need to be considered in 132 kV project (e.g., corona). On the other hand, not all
contractors are specialized in extra high voltage projects or have EHV equipment suppliers on
their active vendor list. Putting 400 kV projects in different packages from 132 and 220 kV projects
enables MCC to invite more contractors to the latter group of projects; these contractors may not
have the competence needed to design and construct 400 kV projects.
 Method 4 aims to take advantage of utilizing specialized contractors for certain technologies. This
will result in a more efficient design and more economical procurement and construction.
However, applying this method may contradict the other methods. For example, GIS substations
are scattered and awarding all of contracts to one bidder will require the coverage of a
geographically large area.
 Method 5 seeks to group projects with similar power system improvement ratings or similar
economic characteristics in the same package. In this way, those projects that are not approved
may be finally dropped and will go into the same package. Hence, removing them from the
compact won’t affect other packages. The disadvantages of this method, which is similar to
Method 4, is that it might produce projects that are not geographically proximate, or of similar
size or voltage. The disadvantages of this method are greater in construction work and outweigh
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 101

its advantages. Furthermore, if some of the projects in one package are dropped, the remaining
projects can be added to another package; this will not cause insurmountable problems.

In all of above mentioned methods we have put transmission lines and substations in same package.
Including both transmission lines and substations in the same package has some pros and cons however
we believe that its advantages are more. List of expected benefits and disadvantages of this packaging is
as per following:

Advantages:
 Ease of coordination at the interface of two infrastructures
 Ease of logistics of two projects
 Ease of transportation of material
 Geographical separation of contractors and keeping their jurisdictions exclusive
 Integration of responsibility of line and station components of a transmission project in one
contractor
 On-time commissioning and energization of the facility

Disadvantages:
 Construction of substations and lines are completely different professions and one contractor
might not have both skillset in-house (this is really true just for small contractors)

2.9 Risk Assessment


Please refer to Task 5 (Sustainability) for complete list of Risks.

Area Risk Solution Comments


Substation The existing station drawings Close coordination between MCA
downloaded from NEA website for Engineer and NEA/other donors’
different tender packages do not consultants or PMS. MCA is to facilitate
reflect consistent information. coordination by periodic coordination
meetings
SCADA Lack of information about the design MCA engineer to have close connection
of new LDC project and also existing with design firms or EPC contractors of
LDC which will have interface with these project. Periodic coordination
MCA’s substations. meetings with these firms will mitigate
this issue.
Transmission Increase in cost for civil works due to A detailed landslide analysis must be
line civil works possible landslide locations in the done and if required the alignment must
transmission line area be changed to avoid the landslide
location.
Substation There are several locations along the A detailed investigation should be done
access access routes to the substations prior to the start of the detailed design
where the water is flowing over the to clearly identify the
hazards/deficiencies and appropriate
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 102

roads and landslides occurring during mitigation measures shall be provided in


rainfall events. the design.
Geotechnical Geotechnical study for substations A detailed geotechnical report will need
investigation and and transmission lines was not to be completed prior to the detailed
foundation cost completed at the time of the material design stage to gain a clear
estimates during the feasibility understanding of soil conditions at each
stage. Estimated foundation site.
quantities may fall well outside the
anticipated +/- 20% range based on
actual geotechnical conditions at site.
Geotechnical A limited number of boreholes were A more extensive geotechnical Further details
investigation and drilled for the geotechnical investigation will be required prior to on Geo
foundation cost investigations on site. There is a starting detailed foundation design/ civil Technical Risk
reasonable chance that soil design to gain a reasonable are provided
conditions in the area could be understanding of the soil conditions to below.
significantly different from the results be expected at each station location and
given from the borehole data. along the transmission line route.

Addition of 2 PSTs in New Butwal


During the comment phase of the draft feasibility study, OMCN stated that phase shifting transformers
are required to control the power flow between New Butwal and India.

Given that the India power system model was not available, Tetra Tech was not able to study the
interactions between the Nepal and India networks to determine which solution, if required, would be
appropriate to prevent loop flows. As such, the PST was not added in the engineering documents.

However, Tetra Tech recommends that the addition of the phase shifting transformers be treated as a
risk and incorporated in the total capital cost requirements. According to the system studies, the
transfer capacity between Nepal and India would be of approximately 1800 MW divided into 2 lines. A
900 MVA phase shifting transformer would be added to each line.

Tetra Tech recommends that MCC obtain the detailed model of the Indian network in order to be able
to conduct a detailed study on the power transfers between Nepal and India. This study would allow to
determine if loop flows are anticipated and what the best mitigation solution is. Once the best solution
is identified, a final cost estimate can be completed in order to get a full picture of the project price.

Once the detailed modeling is complete, one of the mitigation options to loop flows could be to develop
standard operating procedures that would provide guidelines on how the national power control
centers of both countries would coordinate in order to avoid loop flows. The example of Bhutan could
be followed as it is already exporting power to India.

Addition of 2 new transformers and a 150MVAR capacitor bank in Inaruwa


System studies have revealed that the total installed transformer capacity at Inaruwa should be 480
MVA (3 x 160 MVA) and that an additional 150 MVAR capacitor bank would also be required. As of right
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 103

now, the total transformer capacity in the substation is 200 MVA. Two additional 160 MVA transformers
would need to be provided to meet the required capacity. This work is outside the scope of the MCC
compact.

Transmission Line Geotechnical Risks


To account for the lack of soil data at this stage, a contingency factor was applied to the costs of all
transmission line foundations. For transmission line foundations in hilly terrain, the soil found in the
boreholes gave a reasonable level of confidence that the foundations assumed for normal dry soil and
submerged loose soil would be sufficient, however, the bearing strength of the fissured rock was lower
than what was assumed in the design and hard rock was not found in any of the boreholes along the
transmission lines. As 80% of the foundations in hilly terrain was assumed to be hard rock or submerged
fissured rock, the results from the boreholes highlights the high level of uncertainty in the soil conditions.
Due to this level of uncertainty a contingency of 50% was applied to the cost of the transmission line
foundations in hilly terrain.

For transmission line foundations in plains terrain, the soil found in the boreholes gave a reasonable level
of confidence that the foundations assumed for normal dry soil, wet black cotton soil and normal wet soil
would be sufficient, however, the bearing strength of the fissured rock was lower than what was assumed
in the design and hard rock was not found in any of the boreholes along the transmission lines. As 40%
of the foundations in plains terrain was assumed to be hard rock or submerged fissured rock, the results
from the boreholes highlights the high level of uncertainty in the soil conditions. Due to this level of
uncertainty a contingency of 40% was applied to the cost of the transmission line foundations in hilly
terrain.

To reduce the level of uncertainty, a more thorough geotechnical study should be completed with a
sufficient number of boreholes drilled to a suitable depth. To reduce the contingency applied, it is
suggested to drill an additional borehole approximately every 5 to 10 kilometers of transmission line to a
minimum depth of ten meters below grade or until suitable bearing strata is intercepted.

Due to the remote location of some of the transmission lines, it may not be feasible to carry out a detailed
geotechnical study prior to the foundation design stage. In this case, it would be prudent to include a
large contingency in the foundation design to cover unexpected costs encountered during foundation
construction.

Substation Geo Technical Risk


Two boreholes were drilled at most substation sites to provide a general idea of the soil conditions at the
substation sites. This information was used to verify the safe soil bearing pressure used for the
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 104

preliminary design of foundations at site. As only limited information can be derived from two boreholes
and in some cases, the soil bearing capacity found was less than what was assumed for the foundation
quantities, a contingency factor was applied to the foundation costs to compensate for undersized
foundations and limited geotechnical information. The table below provides a brief description of the
situation found at each site and the contingency used:

Station Soil Type found Comparison between borehole results and Contingency
during borehole assumed soil conditions
drilling
Naubise Normal Dry Soil Foundation size for most yard foundations is 15%
acceptable, building foundation sizes are
expected to increase.
Tadhekani Normal Dry Soil Soil bearing capacity is high. Foundation sizes 5%
underlain by Sandy could be reduced. If dense gravels are
Soil and Dry Fissured shallow, excavation costs could increase.
Rock
New Normal Dry Soil Foundation size for most yard foundations is 20%
Damauli underlain by Sandy acceptable, building foundation sizes are
Soil expected to increase.
New Fissured Rock Soil bearing capacity is high. If dense gravels 10%
Hetauda underlain by or rock are shallow, excavation costs could
Submerged Fissured increase.
Rock
Likhu Hub Unknown N/A 40%
New Normal Dry Increase in most foundation sizes will be 40%
Butwal Soil underlain by Wet required to accommodate low soil bearing
Soil and Fully capacity at this site.
Submerged Soil
Lapsiphedi Wet Soil and Foundation size for yard foundations is 20%
Submerged Sandy Soil acceptable, building foundation sizes are
expected to increase.
New Lamki Normal Dry Soil Increase in most foundation sizes will be 40%
required to accommodate low soil bearing
capacity at this site.
New Khimti Unknown N/A 40%
Inaruwa Sandy Soil underlain Increase in foundation size will be required 25%
by Submerged Sandy for gantry foundations. Yard equipment
Soil foundations should be sufficient based on
borehole data.
Balanch Unknown N/A 40%
Kusma Unknown N/A 40%
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 105

Attariya Unknown N/A 40%


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 106

3. Detailed Feasibility Assessment


The key factor in engineering assessment is the understanding of compact objectives and MCC’s
standard approach to implementing such compacts. Furthermore, NEA’s standard line construction, and
operation and maintenance must be taken in consideration. This section provides details and results of
feasibility assessment of power system, substations and transmission lines.

3.1 Power System Assessment

As described in the methodology (Section 2), the main assessments were carried out using PSS®E power
system simulation software:

 Load Flow Study


 Short circuit study
 Technical Power Loss Study
 Dynamic Study
 Technical benefit analysis.

The details of the studies and the results are summarized in the following sub-sections.

3.1.1 Representation of MCC Projects in Power System Studies

The MCC compact enforcement includes projects in – NR1, XB1, NR3, NR4, T2’, T3 and T8 – are included
in the studies. The projects were modelled in PSS®E as follows.

NR1: High-Voltage Transmission Trunk Line


The 400 kV double circuit backbone Lapsiphedi - Naubise – Hetauda – New Damauli – New Butwal is shown
in Figure 3.1. The 160 MVA 400 kV/220 kV and 400 kV/220 kV transformers shown in the figure were
considered initially and the exact number of transformers required at each location was later evaluated
through power flow studies. It should be noted that in Lapsiphedi, there is no 220 kV station available in
the power flow cases provided WSP and the 400 kV substation was connected to the existing 132 kV
station using 400 kV/132 kV transformers. The same configuration was described in the WSP due diligence
report.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 107

400 kV
220 kV
132 kV

Figure 3.1 Single Line Diagram of NR1

XB1: Second Tie Line to India (from New Butwal to Gorakhpur)


A double circuit 400 kV line from New Butwal (Nepal) to Gorakhpur (India) was included in this project,
as shown in Figure 3.2.

400 kV
220 kV
132 kV

Figure 3.2 Single Line Diagram of XB1


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 108

NR3: Ilam-Inaruwa Transmission Line Project


A double circuit 132 kV transmission line from Inaruwa to Ilam was included in the project and the line
was connected to the existing stations, as shown in Figure 3.3.

400 kV
220 kV
132 kV

Figure 3.3 Single line diagram of NR3

NR4: Balanch-Attariya Transmission Line Project


One second circuit of the 132 kV transmission line to the existing circuit from Balanch hub to Attariya
was included in the project and the line connected to the existing stations, as shown in Figure 3.4.

400 kV
220 kV
132 kV

Figure 3.4 Single Line Diagram of NR4

T2’: New Khimti – Likhu Hub Transmission Line Project


A double circuit 220 kV transmission line from New Khimti to Likhu hub was included in the project and
the New Khimti end of the line was connected to the existing 220 kV substation; the other end of the line
was connected to a new 220 kV substation at Likhu, as shown in Figure 3.5. The 220 kV/132 kV
transformers at Likhu are also included in the project and the number of transformers required was
determined.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 109

400 kV
220 kV
132 kV

Figure 3.5 Single Line Diagram of T2'

T3: Tadhekani—Kusma Transmission Line Project


A double circuit 220 kV transmission line from Tadhekani to Kusma was included in the project and the
Kusma end of the line connected to the existing 220 kV substation; the other end of the line was connected
to a new 220 kV substation at Tadhekani, as shown in Figure 3.6. The 220 kV/132 kV transformers at
Tadhekani are also included in the project and the number of transformers required was determined.

400 kV
220 kV
132 kV

Figure 3.6 Single Line Diagram of T3

T8: New Lamki—Nepal/India Border Transmission Project


T8 is the third cross-border line added to the system. 88% of the generation in Upper Karnali is transferred
to India through T8 and the remaining 12% of the power is transferred to Nepal through the existing 132
kV substation at Limki. The power transfer is regulated using a phase shifting transformer connected
between the New Limki 400 kV bus and the 132 kV bus. The project is shown in Figure 3.7.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 110

Phase shifting TF

400 kV
220 kV
132 kV

Figure 3.7 Single Line Diagram of T8

3.1.2 Assumptions and Major Considerations

One of the major considerations is the power transfer capabilities of the tie lines to India. As agreed upon,
the following transfer limits were considered.

 Dhalkebar-Muzzaffarpur interconnector (1st tie line)


o Maximum of 700 MW in 2023
o Maximum of 1200 MW in 2030
 XB1 – second interconnector (considering 40%:60% power distribution between the first tie line
and XB1)
o Maximum of 1050 MW in 2023
o Maximum of 1800 MW in 2030.

The following assumptions were made:


 It was assumed that the power flows provided by the due diligence team accurately represent the
existing system and the system upgrades other than the MCC projects.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 111

 It was not possible to obtain an equivalent model of the India power system. Therefore, the tie
line terminals were individually modeled without considering the transfer impedances between
the terminals. The power transfers were modeled as described above.

3.1.3 Technical Feasibility Studies

The studies were performed for years 2023 and 2030 considering the counterfactual base cases (CF Base
Cases) and the cases with all the MCC projects included. The results are summarized below.

Additional Reactive Power Requirements under System Intact Conditions

The Nepal network (132 kV and below) needs major upgrades in order to handle the load forecast for
2030. The reactive power balancing was performed to obtain the maximum possible support from the
generators. However, most of these loads are far away from the generators and needs local reactive
power support. The issues reported in this section are not relevant to the MCC projects. The purpose of
this section is only to highlight the areas that require addition reactive power compensation.
A detailed reactive power compensation study needs to be done at a later stage including the details of
the sub-transmission and distribution system in order to determine the exact amount of reactive power
requirement and locations.

The identified issues are summarized below.


(1) In 2030 dry peak scenario, the voltages in the area of Hetauda, Karame, Patha, Parwani and N. Birgunj
drops significantly even under system intact conditions (i.e. no contingencies applied) as shown in
Figure 29. Note that this issue is not relevant to the MCC projects and just showing the inability of
existing network to supply the expected loads in 2030. It was required to add a significant amount of
reactive power support in order to solve the low voltage issues. The following changes were made.

 The capacitive range of the existing switch shunt at Patha was changed from 75 MVAR to 150
MVAR
 The capacitive range of the existing switch shunt at Parwani was changed from 75 MVAR to 180
MVAR
 New switch shunt of 150 MVAR was added at Hetauda 132 kV bus.
 The capacitive reactive power capability of the Bharatpu switch shunt was changed from 75 MVAR
to 150 MVAR

The resulted voltages after making the changes are shown in Figure 3.8. The voltages stayed above 0.9 pu
(Power Unit).
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 112

Figure 3.8 Low voltages in the area of Hetauda, Karame, Patha, Parwani and N. Birgunj in 2030
Drypeak Scenario
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 113

Figure 3.9 Voltage performance in the area of Hetauda, Karame, Patha, Parwani and N. Birgunj in
2030 DryPeak Scenario after adding some additional switch shunts

(2) The network around Inaruwa is heavily loaded in dry peak scenarios and having low voltage issues
under system intact and contingency conditions. About 150 MVAR of additional capacitive reactive
power compensation is required and the most suitable location was Inaruwa 132 kV bus (terminal of
NR3). A 150 MVAR switching shunt was added to this bus. Note that there is an existing switch shunt
at Inaruwa 220 kV bus and if required, this can be combined with the existing one and the tap changers
(if available) of 220kV/132 kV transformers can be used to control the 132 kV bus voltage.

(3) In 2030 dry peak scenario, the 66 kV network between Siuchata (bus # 610) and N. Bhakta (Bus # 614)
was heavily loaded and the power flow could not be solved even under system intact conditions. The
network reinforcements in 66 kV and lower network was not considered in this project and therefore,
the problem was simply solved by adding reactive power compensation at these buses. The capacitive
reactive power capacity of Siuchata switch shunt was increased to 500 MVAR in order to keep the
voltage near 1pu. The capacitive reactive power capacity of N. Bhakta switch shunt was increased to
150 MVAR in order to keep the voltage near 1pu. Note that this issue is also not relevant to the MCC
projects and just demonstrates the inability of existing network to supply the expected loads in 2030.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 114

3.1.4 Loss Evaluation

Table 3.1 provides a summary of losses in each zone, generation, total loads supplied, power import
from India and power export to India. In the wet min scenarios, the transmission losses reduced when
the MCC projects were added. For example, the transmission losses reduced from 3.3% to 2.8% in
2030 wetmin scenario.
Since the loadings in the dry peak cases with and without MCC projects are different, the losses cannot
be compared each other. For example in 2030 dry peak case, the losses were changed from 79.1 MW
to 176.7 MW when MCC projects are introduced. In this case, the loads supplied were almost doubled
and about 3000 MW was imported for India. Most of the losses were reported in zones 3, 4 and 5.
The losses in each voltage level in these zones are compared in Table 3.2 for 2030 Drypeak scenarios.
The 400 kV system losses are negligible compared to the other losses. Most of significant difference
between the losses were reported in the 132 kV system and the increased loads were responsible for
this.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 115

Table 3.1 Steady State Transmission Losses

Zone Losses (MW) T8 Project %


Nepal Nepal Loads Nepal Nepal Transmission
Zone 7 Losses
Case Name Zone 8 Total Loss Generation supplied Imports* Exports Generation Exports to
Zone Zone (Two tie
Zone 1 Zone 4 Zone 5 Zone 6 (Upper (MW) (MW) (MW) (MW) (MW)
2 3 lines to (MW) India (MW)
Karnali)
India)
CF 2023 Dry Peak 1 1.1 5.8 15.6 8.0 1.8 1.1 - 33.4 1016.6 1682.1 698.9 1.9%
MCC ALL 2023 Dry 1.1 2.1 14.2 26.7 13.8 4.7 4.1 0.3 66.7 1170.6 2573.4 1469.5 270 237 2.53%
Peak
CF 2023 Wet Min 2.9 0.8 5.8 23.4 7.2 2.2 0.5 - 42.3 1814.6 1287 485.3 2.3%
MCC ALL 2023 Wet 3.7 1.7 9.2 11.2 6.6 1.8 5.8 2.7 42.7 2385.9 1286.7 108 1164.5 900 786 1.71%
Min
CF 2030 Dry Peak 1.1 2.3 13.1 38.9 16.5 3.5 3.6 - 75.4 1286.7 2407.7 1196.4 3.0%
MCC ALL 2030 Dry 2.6 6.7 42.5 73.3 35.5 11.7 17.4 0.3 189.7 1433.1 4273.4 3030 270 237 4.25%
Peak
CF 2030 Wet Min 14.8 2.4 20.7 46.4 14.9 7.3 2.3 - 106.5 3231.3 2137.7 987.2 3.3%
MCC ALL 2030 Wet 16.4 3.4 34.5 32 23.8 9.8 15.9 2.8 135.8 4735.2 2136.7 108 2570.7 900 786 2.80%
Min
*Imports from T8 (Upper Karnali) included
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 116

Table 3.2 Losses in Zones 3, 4 and 5 for 2030 Drypeak Scenario


Case Name 400 kV 220 kV 132 kV 66 kV
CF 2030 Drypeak (MW) - 10.7 33.8 17.3
MCC ALL 2030 Drypeak (MW) 6.8 15 81.1 39.2

Estimation of line reactors to limit open circuit voltages

The requirement to have line reactors to limit the open circuit voltages of transmission lines was studied
using the Bergeron transmission line model in PSCAD (Electromagnetic transient simulation software).
The longest transmission lines of 400kV (127 km, Hetauda—Dhalke), 220kV (230 km, Kohalpur—New
Butwal) and 132kV (131 Km, Balanch—Ataria) were selected for the study.

Error! Reference source not found..10 shows the open circuit voltages of the 3 transmission lines
entioned above. The sending end voltages were set to 1.05 pu. The open circuit voltages observed at the
open end are less than 1.1pu in all cases. Therefore, no reactors are required during line energization.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 117

Figure 3.10 Open circuit voltages of longest transmission lines (400kV, 220kV and 132kV)

3.1.5 Steady State Contingency Analysis

The steady state contingency analysis was performed using “ACCC” utility in PSS®E for the N-1 and N-2
contingencies defined in the methodology.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 118

Required Number of Transformers in MCC Projects

First, the study was performed with the following transformers of the MCC projects included.

Table 3.3 Initial number of transformers considered at MCC projects


Rating
Project Station Transformer Number of TFs
(MVA)
New Butwal 400 kV/220 kV 160 2
New Damauli 400 kV/220 kV 160 2
NR1 Naubise 400 kV/220 kV 160 2
Hetauda 400 kV/220 kV 160 2
Lapsiphedi 400 kV/220 kV 160 2
NR3 Inaruwa 220 kV/132 kV 160 2
T2' New Khimti 400 kV/220 kV 160 2
Likhu Hub 220 kV/132 kV 160 2
T3 Tadhekani 220 kV/132 kV 160 2
T8 New Lamki One 400 kV/132 kV 160MVA phase shifting TF

The MCC transformer overloads reported from the studies are given in Table 3.5. There are significant
overloads reported for most of the transformers and it would be necessary to consider the following
number of transformers in order to avoid the overloads. Note that for the 400 kV/220 kV transformers at
New Butwal, the overloads under the N-2 contingency of New Butwal –Damauli 400 kV line were not
considered. It is not possible to transfer all imports (1800 MW) into the 220 kV system and therefore, a
reduction of imports /load shedding would be required under this contingency.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 119

Table 3.4 Required number of transformers to avoid overloads


Rating
Project Station Transformer Number of TFs
(MVA)
New Butwal 400 kV/220 kV 160 5
New Damauli 400 kV/220 kV 160 4
NR1 Naubise 400 kV/220 kV 160 3
Hetauda 400 kV/220 kV 160 3
Lapsiphedi 400 kV/220 kV 160 3
NR3 Inaruwa 220 kV/132 kV 160 3
New Khimti 400 kV/220 kV 160 3
T2'
Likhu Hub 220 kV/132 kV 160 3
T3 Tadhekani 220 kV/132 kV 160 2
T8 New Limki One 400 kV/132 kV 160MVA phase shifting TF

The steady state contingency analysis was repeated with the aforementioned modifications to the
number of transformers. The results are summarized in the next sections.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 120

Table 3.5 Overloads of Transformers of the MCC Projects (with initial number of transformers)
Overloaded Transformer
Worst Contingency
Bus-1 Bus-2 No
Project
Base Base CKT contingency MVA Rating
No Name kV No Name kV ID Powerflow Contingency % loading Overloads (%) of TF
32150 NEW DAMAULI 220 432150 NEW DAMAULI 400 1 2030_Wetmin (N-1): 32150-432150(2) 298.424 178.021 160.000
32150 NEW DAMAULI 220 432150 NEW DAMAULI 400 2 2030_Wetmin (N-1): 32150-432150(1) 298.424 178.021 160.000
34010 NEW BUTWAL 400 234010 NEW BUTWAL 220 2 2030_Drypeak (N-2): NR1_DAMUL_BUTWA 528.433 196.828 160.000
34010 NEW BUTWAL 400 234010 NEW BUTWAL 220 1 2030_Drypeak (N-2): NR1_DAMUL_BUTWA 528.433 196.828 160.000
41090 LAPSIPHEDI1 132 44050 LAPSIPHEDI4 400 2 2030_Drypeak (N-1): 41090-44050(1) 187.843 116.361 160.000
NR1
41090 LAPSIPHEDI1 132 44050 LAPSIPHEDI4 400 1 2030_Drypeak (N-1): 41090-44050(2) 187.843 116.361 160.000
44010 HETAUDA4 400 244010 HETAUDA 220 220 2 2030_Drypeak (N-1): 44010-244010(1) 188.109 123.244 160.000
44010 HETAUDA4 400 244010 HETAUDA 220 220 1 2030_Drypeak (N-1): 44010-244010(2) 188.109 123.244 160.000
42090 NAUBISE2 220 44040 NAUBISE4 400 1 2030_Wetmin (N-2): NR1_NAUB_LAPSE 156.332 - 160.000
42090 NAUBISE2 220 44040 NAUBISE4 400 3 2030_Wetmin (N-2): NR1_NAUB_LAPSE 156.332 - 160.000
61200 INARUWA 132 62020 INARUWA2 220 2 2030_Drypeak (N-1): 61200-62020(1) 233.200 130.501 160.000
NR3
61200 INARUWA 132 62020 INARUWA2 220 1 2030_Drypeak (N-1): 61200-62020(2) 233.200 130.501 160.000
51080 LIKHU HUB_ 132 51081 LIKHU 220 220 1 2023_Wetmin (N-1): 51080-51081(2) 211.464 105.562 160.000
51080 LIKHU HUB_ 132 51081 LIKHU 220 220 2 2023_Wetmin (N-1): 51080-51081(1) 211.464 105.562 160.000
T2'
52025 NEW KHIMTI22 220 54090 NEW KHIMTI4 400 1 2023_Wetmin (N-1): 52025-54090(2) 228.246 111.272 160.000
52025 NEW KHIMTI22 220 54090 NEW KHIMTI4 400 2 2023_Wetmin (N-1): 52025-54090(1) 228.246 111.272 160.000
31110 TADHEKANI 1 132 32020 TADHEKANI H. 220 2 2023_Wetmin (N-1): 31110-32020(1) 118.311 - 160.000
T3
31110 TADHEKANI 1 132 32020 TADHEKANI H. 220 1 2023_Wetmin (N-1): 31110-32020(2) 118.311 - 160.000
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 121

Diverged Power flow Cases for N-1 Contingencies


During the contingency analysis procedures, three contingencies diverged for the 2030 drypeak case that
could not be fixed and solved.

The first contingency that could not be fixed is the loss of the transmission line between buses 107 and
108. Figure 3.11 illustrates the system’s configuration during normal operating conditions. This diagram
illustrates that over half of the power required by the load at bus 107 is provided by the line between
buses 107 and 108. Furthermore, this diagram illustrates that the voltage at bus 107 is already close to
the lower operating limit of 0.9 pu during normal operating conditions. It was found that even though
there is alternative transmission path to bus 107, there is not enough voltage support available when the
system is heavily loaded. Therefore, the voltage at bus 107 quickly collapses and the power flow solution
diverges.

Figure 3.11 System configuration near transmission line 107-108 (1)

The second and third contingencies that could not be fixed are the loss of either one of the transmission
lines connecting buses 52010 and 62020. Figure 33 illustrates the system’s configuration during normal
operating conditions. This diagram illustrates that the double circuit transmission path between buses
52010 and 62020 provides the majority of the power coming into bus 62020. Furthermore, the system
voltages are already near the lower limit of 0.9 pu during normal operating conditions. It was found that
there is not enough voltage support on the Inaruwa side of the system when a single transmission line
between buses 52010 and 62020 is tripped. As the result, the system voltages collapse and the power
flow solution diverges.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 122

Figure 3.12 System configuration near transmission lines 52010-62020 (1) and (2)

The solution for all of these issues would be to add parallel lines to the lines tripped. Note that none of
these issues are related to the MCC projects.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 123

Transformer Loadings under N-1 Contingencies – MCC Projects


The loadings of the transformers of the MCC projects are given in Table 3.6 for N-1 contingencies. When the number of transformers are increased
to the aforementioned numbers, the transformer overloads stay within 120%.

Table 3.6 Loading of Transformers of the MCC Projects for N-1 Contingencies (with the proposed of transformers)
Overloaded Component
Worst Contingency
Bus 1 Bus 2 NO
Project CKT Contingency MVA rating
from ID Loading Overload (%)
Bus Name kV to Bus Bus Name kV Power flow Contingency
Bus (%)

34010 NEW BUTWAL 400 234010 NEW BUTWAL 220 1 2030 Dry Peak SINGLE 34010-234010(2) 100.8 0.0 160

34010 NEW BUTWAL 400 234010 NEW BUTWAL 220 2 2030 Dry Peak SINGLE 34010-234010(1) 100.8 0.0 160

34010 NEW BUTWAL 400 234010 NEW BUTWAL 220 3 2030 Dry Peak SINGLE 34010-234010(1) 100.8 0.0 160

34010 NEW BUTWAL 400 234010 NEW BUTWAL 220 4 2030 Dry Peak SINGLE 34010-234010(1) 100.8 0.0 160

34010 NEW BUTWAL 400 234010 NEW BUTWAL 220 5 2030 Dry Peak SINGLE 34010-234010(1) 100.8 0.0 160

41090 LAPSIPHEDI1 132 44050 LAPSIPHEDI4 400 1 2030 Dry Peak SINGLE 41090-44050(2) 85.0 0.0 160
NR1
41090 LAPSIPHEDI1 132 44050 LAPSIPHEDI4 400 2 2030 Dry Peak SINGLE 41090-44050(1) 85.0 0.0 160

41090 LAPSIPHEDI1 132 44050 LAPSIPHEDI4 400 3 2030 Dry Peak SINGLE 41090-44050(1) 85.0 0.0 160

44010 HETAUDA4 400 244010 HETAUDA 220 220 1 2030 Dry Peak SINGLE 44010-244010(2) 88.1 0.0 160

44010 HETAUDA4 400 244010 HETAUDA 220 220 2 2030 Dry Peak SINGLE 44010-244010(1) 88.1 0.0 160

44010 HETAUDA4 400 244010 HETAUDA 220 220 3 2030 Dry Peak SINGLE 44010-244010(1) 88.1 0.0 160

32150 NEW DAMAULI 220 432150 NEW DAMAULI 400 1 2030 Wet Min SINGLE 32150-432150(2) 87.9 0.0 160
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 124

Overloaded Component
Worst Contingency
Bus 1 Bus 2 NO
Project CKT Contingency MVA rating
from ID Loading Overload (%)
Bus Name kV to Bus Bus Name kV Power flow Contingency
Bus (%)

32150 NEW DAMAULI 220 432150 NEW DAMAULI 400 2 2030 Wet Min SINGLE 32150-432150(1) 87.9 0.0 160

32150 NEW DAMAULI 220 432150 NEW DAMAULI 400 3 2030 Wet Min SINGLE 32150-432150(1) 87.9 0.0 160

32150 NEW DAMAULI 220 432150 NEW DAMAULI 400 4 2030 Wet Min SINGLE 32150-432150(1) 87.9 0.0 160

61200 INARUWA 132 62020 INARUWA2 220 1 2030 Dry Peak SINGLE 61200-62020(2) 100.8 0.0 160

NR3 61200 INARUWA 132 62020 INARUWA2 220 2 2030 Dry Peak SINGLE 61200-62020(1) 100.8 0.0 160

61200 INARUWA 132 62020 INARUWA2 220 3 2030 Dry Peak SINGLE 61200-62020(1) 100.8 0.0 160

51080 LIKHU HUB_ 132 51081 220 1 2023 Wet Min SINGLE 51080-51081(2) 106.1 0.0 160

51080 LIKHU HUB_ 132 51081 220 2 2023 Wet Min SINGLE 51080-51081(1) 106.1 0.0 160

51080 LIKHU HUB_ 132 51081 220 3 2023 Wet Min SINGLE 51080-51081(1) 106.1 0.0 160
T2’
52025 NEW KHIMTI22 220 54090 NEW KHIMTI4 400 1 2023 Wet Min SINGLE 52025-54090(2) 111.3 0.0 160

52025 NEW KHIMTI22 220 54090 NEW KHIMTI4 400 2 2023 Wet Min SINGLE 52025-54090(1) 111.3 0.0 160

52025 NEW KHIMTI22 220 54090 NEW KHIMTI4 400 3 2023 Wet Min SINGLE 52025-54090(1) 111.3 0.0 160

31110 TADHEKANI 1 132 32020 TADHEKANI H. 220 1 2023 Wet Min SINGLE 31110-32020(2) 118.6 0.0 160
T3
31110 TADHEKANI 1 132 32020 TADHEKANI H. 220 2 2023 Wet Min SINGLE 31110-32020(1) 118.6 0.0 160
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 125

Transmission Line Loadings under N-1 Contingencies – MCC Projects

The ratings of the lines were determined based on the information given in Table 3.7. The transmission
line loadings are summarized in Table 30.

Table 3.7 Specified current ratings of transmission lines


Voltage Ampacity rating/phase

4xmoose ACSR
400kV
3143A/phase
2xBison ACSR
220kV
1285.4A/phase
NR3: 1xBison ACSR
642.7A
132kV
NR4: 1xBear ACSR
567.7A/phase

There is only one overload recorded in the contingency analysis. In NR4 project, the 132 kV line get an
overload of about 117% in 2030 scenarios due to the extra power generation in Balanch Hub. It is
recommended to re-conductor the 1 x Bear ACSR to HTLS (High Temperature Low Sag) conductor in
future when line load exceeds the 100% capacity of Bear ACSR in order to increase the power
transmission capacity of the line for N-1 contingency.

In NR1 project, the 400 kV lines are lightly loaded even under N-1 conditions. Therefore, there is a
possibility of using a lower rated line configuration for this project.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 126

Table 3.8 Loading of Transmission Lines of the MCC Projects for N-1 Contingencies

Voltage Rating Maximum Loading


MCC Project Monitoring Branch
(kV)
kA MVA MVA %

102 ATARIA 132.00 11020 BALANCH HUB 132.00 1


NR4 132 0.52 129.00 151.37 117.20%
102 ATARIA 132.00 11020 BALANCH HUB 132.00 2 132 0.52 129.00 151.37 117.20%
14035 N. LAMKI-I 400.00 24040 UP KARNALI 400.00 1 400 3.14 2177.53 900.08 41.34%
14035 N. LAMKI-I 400.00 24040 UP KARNALI 400.00 2 400 3.14 2177.53 900.08 41.34%
T8
14035 N. LAMKI-I 400.00 100111 BAREILLY 400.00 1 400 3.14 2177.53 789.20 36.24%
14035 N. LAMKI-I 400.00 100111 BAREILLY 400.00 2 400 3.14 2177.53 789.20 36.24%
32010 KUSMA2 220.00 32020 TADHEKANI H.220.00 1 220 1.29 489.65 188.79 38.56%
T3
32010 KUSMA2 220.00 32020 TADHEKANI H.220.00 2 220 1.29 489.65 188.79 38.56%
34010 NEW BUTWAL 400.00 70020 GORAKPHUR 400.00 1 400 3.14 2177.53 1713.57 78.69%
XB1
34010 NEW BUTWAL 400.00 70020 GORAKPHUR 400.00 2 400 3.14 2177.53 1713.57 78.69%
34010 NEW BUTWAL 400.00 432150 NEW DAMAULI 400.00 1 400 3.14 2177.53 829.43 38.09%
34010 NEW BUTWAL 400.00 432150 NEW DAMAULI 400.00 2 400 3.14 2177.53 826.43 38.09%
44010 HETAUDA4 400.00 44040 NAUBISE4 400.00 1 400 3.14 2177.53 351.21 16.13%
44010 HETAUDA4 400.00 44040 NAUBISE4 400.00 2 400 3.14 2177.53 351.21 16.13%
44010 HETAUDA4 400.00 54010 DHALKE4-NP 400.00 1 400 3.14 2177.53 367.30 16.87%
NR1
44010 HETAUDA4 400.00 54010 DHALKE4-NP 400.00 2 400 3.14 2177.53 367.30 16.87%
44040 NAUBISE4 400.00 44050 LAPSIPHEDI4 400.00 1 400 3.14 2177.53 581.50 26.70%
44040 NAUBISE4 400.00 44050 LAPSIPHEDI4 400.00 2 400 3.14 2177.53 581.50 26.70%
44040 NAUBISE4 400.00 432150 NEW DAMAULI 400.00 1 400 3.14 2177.53 563.89 25.90%
44040 NAUBISE4 400.00 432150 NEW DAMAULI 400.00 2 400 3.14 2177.53 563.89 25.90%
T2' 51081 220.00 52025 NEW KHIMTI22220.00 1 220 1.29 489.65 338.33 69.10%
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 127

Voltage Rating Maximum Loading


MCC Project Monitoring Branch
(kV)
kA MVA MVA %
51081 220.00 52025 NEW KHIMTI22220.00 2 220 1.29 489.65 338.33 69.10%
54010 DHALKE4-NP 400.00 70010 MUZZAFA 400.00 1 400 3.14 2177.53 1202.85 55.24%
Tieline1
54010 DHALKE4-NP 400.00 70010 MUZZAFA 400.00 2 400 3.14 2177.53 1202.85 55.24%
61010 ILLAM 132.00 61200 INARUWA 132.00 1 132 0.64 146.94 38.93 26.49%
NR3
61010 ILLAM 132.00 61200 INARUWA 132.00 2 132 0.64 146.94 38.93 26.49%

Overloads in Existing System under N-1 Contingencies

The overloads of the existing system transformers are given in Table 3.9. The overloads are not significant and the maximum loading is about
115%.

The overloads of the existing system transmission lines are given in Table 3.10. The mitigation measures are further discussed in the following
sections.

Table 3.9 Overloads of non- MCC project transformers for n-1 contingencies (overloads above 100%)
Overloaded Transformer
Worst Contingency
MVA
Bus-1 Bus-2
Rating of
No Name Base kV No Name Base kV CKT ID Power flow Contingency % loading TF
108 BUTWAL-132 132 234010 NEW BUTWAL 220 1 2030 Dry Peak SINGLE 108-234010(2) 114.054 500
108 BUTWAL-132 132 234010 NEW BUTWAL 220 2 2030 Dry Peak SINGLE 108-234010(1) 114.054 500
114 DHALKE-132 132 52010 DHALKE2 220 1 2030 Dry Peak SINGLE 114-52010(2) 115.050 600
114 DHALKE-132 132 52010 DHALKE2 220 2 2030 Dry Peak SINGLE 114-52010(1) 115.050 600
122 SIUCH 132 610 SIUCHATA 66 1 2030 Dry Peak SINGLE 122-610(3) 112.783 200
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 128

122 SIUCH 132 610 SIUCHATA 66 2 2030 Dry Peak SINGLE 122-610(1) 109.991 200
122 SIUCH 132 610 SIUCHATA 66 3 2030 Dry Peak SINGLE 122-610(1) 109.102 200
130 N-BHAKTA-132 132 614 N-BHAKTA-66 66 1 2030 Dry Peak SINGLE 130-614(2) 102.509 100
130 N-BHAKTA-132 132 614 N-BHAKTA-66 66 2 2030 Dry Peak SINGLE 130-614(1) 102.509 100
130 N-BHAKTA-132 132 614 N-BHAKTA-66 66 3 2030 Dry Peak SINGLE 130-614(1) 102.509 100
52010 DHALKE2 220 54010 DHALKE4-NP 400 1 2030 Dry Peak SINGLE 52010-54010(2) 104.707 500
52010 DHALKE2 220 54010 DHALKE4-NP 400 2 2030 Dry Peak SINGLE 52010-54010(1) 104.707 500
52010 DHALKE2 220 54010 DHALKE4-NP 400 3 2030 Dry Peak SINGLE 52010-54010(1) 104.707 500

Table 3.10 Overloads of non-MCC project transmission lines for n-1 contingencies (overloads above 100%)
Overloaded Component
Worst Contingency NO
Bus 1 Bus 2 MVA
CKT Contingency Comments
Rating
from to ID Loading Overload (%)
Bus Name kV Bus Name kV Power flow Contingency
Bus Bus (%)
108 BUTWAL-132 132 31190 BAIRAHAWA 132 1 2030 Dry Peak SINGLE 108-31190(2) 121.487 - 159.130
108 BUTWAL-132 132 31190 BAIRAHAWA 132 2 2030 Dry Peak SINGLE 108-31190(1) 121.487 - 159.130
BHARATPU- -
112 132 159 N_BHARA 132 1 2030 Dry Peak SINGLE 112-159(2) 128.444 123.970
132
BHARATPU- -
112 132 159 N_BHARA 132 2 2030 Dry Peak SINGLE 112-159(1) 128.444 123.970
132
113 HETAUDA-132 132 40050 AMLEKHGUNJ 132 1 2030 Dry Peak SINGLE 113-40050(2) 123.658 - 186.000
113 HETAUDA-132 132 40050 AMLEKHGUNJ 132 2 2030 Dry Peak SINGLE 113-40050(1) 123.658 - 186.000
114 DHALKE-132 132 1115 MIRCHAY 132 1 2030 Dry Peak SINGLE 114-1115(2) 151.426 103.568 123.970
It is recommended to add another
114 DHALKE-132 132 1115 MIRCHAY 132 2 2030 Dry Peak SINGLE 114-1115(1) 151.426 103.568 123.970 circuit. This is not relevant to MCC
projects
114 DHALKE-132 132 1115 MIRCHAY 132 3 2030 Dry Peak SINGLE 114-1115(1) 151.426 103.568 123.970
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 129

Overloaded Component
Worst Contingency NO
Bus 1 Bus 2 MVA
CKT Contingency Comments
Rating
from to ID Loading Overload (%)
Bus Name kV Bus Name kV Power flow Contingency
Bus Bus (%)
SINGLE 52010- -
115 LAHAN 132 124 KUSHAHA 132 1 2030 Dry Peak 108.373 123.970
62020(1)
115 LAHAN 132 1115 MIRCHAY 132 1 2030 Dry Peak SINGLE 115-1115(2) 125.676 - 142.000

115 LAHAN 132 1115 MIRCHAY 132 2 2030 Dry Peak SINGLE 115-1115(1) 125.676 - 142.000
115 LAHAN 132 1115 MIRCHAY 132 3 2030 Dry Peak SINGLE 115-1115(1) 125.676 - 142.000
115 LAHAN 132 51070 RAJBIRAJ_ 132 1 2023 Dry Peak SINGLE 115-51070(2) 149.349 - 27.090 This is not relevant to MCC projects.
It is recommended to add a third
115 LAHAN 132 51070 RAJBIRAJ_ 132 2 2023 Dry Peak SINGLE 115-51070(1) 149.349 - 27.090 circuit.
SINGLE 52010- -
115 LAHAN 132 61200 INARUWA 132 1 2030 Dry Peak 105.068 123.970
62020(2)
116 DUHABI-132 132 61200 INARUWA 132 1 2030 Dry Peak SINGLE 116-61200(2) 106.559 - 228.000
116 DUHABI-132 132 61200 INARUWA 132 2 2030 Dry Peak SINGLE 116-61200(1) 106.559 - 228.000
ANARMANI- -
117 132 175 DAMAK 132 1 2030 Dry Peak SINGLE 117-175(2) 115.748 123.970
132
ANARMANI- -
117 132 175 DAMAK 132 2 2030 Dry Peak SINGLE 117-175(1) 115.748 123.970
132
118 MARSHYAN 132 159 N_BHARA 132 1 2030 Dry Peak SINGLE 119-158(1) 113.787 100.163 180.000
122 SIUCH 132 133 MATATRIT 132 1 2030 Dry Peak SINGLE 122-133(3) 118.948 - 228.000
122 SIUCH 132 133 MATATRIT 132 3 2030 Dry Peak SINGLE 122-133(1) 118.948 - 228.000

129 LAMOSANG 132 41100 BARABISE1 132 1 2030 Wet Min SINGLE 129-41100(2) 123.777 - 186.000
129 LAMOSANG 132 41100 BARABISE1 132 2 2030 Wet Min SINGLE 129-41100(1) 123.777 - 186.000
131 CHAPALI 132 41080 MULPANI 132 1 2030 Dry Peak SINGLE 131-41080(2) 105.242 - 159.130
131 CHAPALI 132 41080 MULPANI 132 2 2030 Dry Peak SINGLE 131-41080(1) 105.242 - 159.130
134 PARWANI-132 132 170 PATHA 132 1 2030 Dry Peak SINGLE 134-170(2) 116.735 - 142.000
134 PARWANI-132 132 170 PATHA 132 2 2030 Dry Peak SINGLE 134-170(1) 116.735 - 142.000
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 130

Overloaded Component
Worst Contingency NO
Bus 1 Bus 2 MVA
CKT Contingency Comments
Rating
from to ID Loading Overload (%)
Bus Name kV Bus Name kV Power flow Contingency
Bus Bus (%)
134 PARWANI-132 132 40060 SIMARA 132 1 2030 Dry Peak SINGLE 134-40060(2) 143.145 - 123.970 This overload is not a result of MCC
projects. It is recommended to
134 PARWANI-132 132 40060 SIMARA 132 2 2030 Dry Peak SINGLE 134-40060(1) 143.145 - 123.970 upgrade to a 3 CCT line.
134 PARWANI-132 132 41160 N BIRGUNJ 132 1 2030 Dry Peak SINGLE 134-41160(2) 172.191 - 123.970 This is not relevant to MCC projects.
Low voltage issues also observed in
- this area. Therefore it is
134 PARWANI-132 132 41160 N BIRGUNJ 132 2 2030 Dry Peak SINGLE 134-41160(1) 172.191 123.970
recommended to add a third circuit.
601 HETAUDA-66 66 602 KL-I-66 66 1 2030 Dry Peak SINGLE 601-602(2) 100.716 - 100.000
601 HETAUDA-66 66 602 KL-I-66 66 2 2030 Dry Peak SINGLE 601-602(1) 100.716 - 100.000
602 KL-I-66 66 610 SIUCHATA 66 1 2030 Dry Peak SINGLE 602-610(2) 107.511 - 77.000
602 KL-I-66 66 610 SIUCHATA 66 2 2030 Dry Peak SINGLE 602-610(1) 107.511 - 77.000
610 SIUCHATA 66 611 BALAJU-66 66 1 2030 Dry Peak SINGLE 610-611(1) 167.012 - 100.000 It is recommended to add another
circuit. This is not relevant to MCC
610 SIUCHATA 66 611 BALAJU-66 66 2 2030 Dry Peak SINGLE 610-611(2) 167.012 - 100.000 projects
610 SIUCHATA 66 616 NEW PATAN 66 1 2030 Dry Peak SINGLE 610-616(2) 194.686 104.275 100.000 This overload is not a result of MCC
projects. Outage of a single cct fom
New Patan to Siuchata results in
transmitting about 150 MW to
serve loads in New Patan and New
610 SIUCHATA 66 616 NEW PATAN 66 2 2030 Dry Peak SINGLE 610-616(1) 194.686 104.275 100.000 Baneswor. It is recommended to
upgrade to a 3 CCT line. That will
result in only 102% overload at the
outage of a single circuit.
- This overload is not a result of MCC
projects. Under the outage of s/c
line from DUMTEKU to K-3, the line
610 SIUCHATA 66 630 TEKU 66 2 2023 Dry Peak SINGLE 610-700(1) 139.517 100.000 from Teku to Siucha is overloaded
to transmit power to the loads at K-
3 and Teku. This line overload can
be resolved by upgrading the line
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 131

Overloaded Component
Worst Contingency NO
Bus 1 Bus 2 MVA
CKT Contingency Comments
Rating
from to ID Loading Overload (%)
Bus Name kV Bus Name kV Power flow Contingency
Bus Bus (%)
from Teku to Siucha to a double
circuit line.
610 SIUCHATA 66 700 DUMTEKU 66 1 2030 Dry Peak SINGLE 610-630(2) 127.238 - 200.000
- This overload is not a result of MCC
projects. The rating of this line is
only about 40 MVA. This overload
613 CHABEL 66 619 DEVIGHAT-66 66 1 2030 Dry Peak SINGLE 613-614(1) 159.824 40.000
can be resolved if this line is
reconductored to increase the
rating to about 60 MVA.
NEW -
614 N-BHAKTA-66 66 615 66 1 2023 Dry Peak SINGLE 615-616(1) 107.197 100.000
BANESWOR
- It is recommended to add another
NEW
615 66 616 NEW PATAN 66 1 2030 Dry Peak SINGLE 130-614(1) 152.158 100.000 circuit. This is not relevant to MCC
BANESWOR
projects
- This overload is not a result of MCC
630 TEKU 66 631 K-3 66 1 2030 Dry Peak SINGLE 610-630(2) 138.666 100.000 projects. It is recommended to
upgrade to a 2 CCT line.
631 K-3 66 700 DUMTEKU 66 1 2030 Dry Peak SINGLE 610-630(2) 127.295 - 200.000
SINGLE 40050- -
40050 AMLEKHGUNJ 132 40060 SIMARA 132 1 2030 Dry Peak 117.614 186.000
40060(2)
SINGLE 40050- -
40050 AMLEKHGUNJ 132 40060 SIMARA 132 2 2030 Dry Peak 117.614 186.000
40060(1)
SINGLE 41080- - Transfers all the power from NR1-
41080 MULPANI 132 41090 LAPSIPHEDI1 132 1 2030 Dry Peak 152.208 186.000
41090(2) Lapsehphedi to Mulpani. The
- outage of one circuit forces to
transmit over 300 MW in single
SINGLE 41080-
41080 MULPANI 132 41090 LAPSIPHEDI1 132 2 2030 Dry Peak 152.208 186.000 circuit that results in overload. It is
41090(1)
recommended to upgrade to a 3
CCT line.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 132

Voltage Violations
No over voltage violations were identified in the steady state contingency analysis. The low voltage (<0.9
pu) given in Table 3.11 were reported for the N-1 contingencies in the system. The 66 kV and 132 kV
networks in Zone 4 are the mostly stressed areas. None of these issues are related to the MCC projects.
Note that the network divergence issues and overloads discussed in the above sections were also
observed in the same areas. Therefore, it is expected that most of the under voltages will be solved when
the required lines upgrades are done. The additional shunt compensation requirements are discussed in
a later section.

Table 3.11 Low Voltage Violations for N-1 Contingencies


Worst Low Voltage
Bus Voltage
Case Contingency
(pu)
64090 DAMAK4 220.00 2030_Drypeak SINGLE 62020-64090(1) 0.881
612 LAINCHOU 66.000 2030_Drypeak SINGLE 610-611(1) 0.871
101 MAHENDRA 132.00 2030_Drypeak SINGLE 101-102(1) 0.863
105 LAMAHI 132.00 2030_Drypeak SINGLE 104-135(1) 0.890
107 SHIVPUR 132.00 2030_Drypeak SINGLE 104-135(1) 0.885
21070 GOHARI 132.00 2030_Drypeak SINGLE 104-135(1) 0.874
135 KUSUM 132.00 2030_Drypeak SINGLE 104-135(1) 0.875
21020 HAPURE_ 132.00 2030_Drypeak SINGLE 104-135(1) 0.869
41160 N BIRGUNJ 132.00 2030_Drypeak SINGLE 118-159(1) 0.880
112 BHARATPU-132132.00 2030_Drypeak SINGLE 118-159(1) 0.805
119 DAMAULI-132 132.00 2030_Drypeak SINGLE 118-159(1) 0.838
159 N_BHARA 132.00 2030_Drypeak SINGLE 118-159(1) 0.809
31200 KHUDI 132.00 2030_Drypeak SINGLE 118-159(1) 0.833
124 KUSHAHA 132.00 2030_Drypeak SINGLE 124-61200(1) 0.876
180 KATAIYA 132.00 2030_Drypeak SINGLE 124-61200(1) 0.865
611 BALAJU-66 66.000 2030_Drypeak SINGLE 610-611(1) 0.883
618 TRISHULI 66.000 2030_Drypeak SINGLE 610-611(1) 0.873
619 DEVIGHAT-66 66.000 2030_Drypeak SINGLE 610-611(1) 0.879
632 MAILUNG 66.000 2030_Drypeak SINGLE 610-611(1) 0.895
630 TEKU 66.000 2030_Drypeak SINGLE 610-630(2) 0.873
631 K-3 66.000 2030_Drypeak SINGLE 610-630(2) 0.879
700 DUMTEKU 66.000 2030_Drypeak SINGLE 610-630(2) 0.891
61160 ITHARI_ 132.00 2030_Drypeak SINGLE 61160-61200(1) 0.859
61170 DHARAN_ 132.00 2030_Drypeak SINGLE 61160-61200(1) 0.843
102 ATARIA 132.00 2030_Wetmin SINGLE 102-11020(1) 0.886
11040 DEEPAYAL 132.00 2030_Wetmin SINGLE 102-11020(1) 0.895
11050 BAJHANG 132.00 2030_Wetmin SINGLE 102-11020(1) 0.897
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 133

N-2 Outages
This section discusses the remedies for overloads resulting or worsened under n-2 contingencies.
Wherever the generation tripping is suggested, the recommendations are based only on making an
acceptable operating point and the economic aspects of tripping a particular generation unit over another
is not considered.

(1) D/C transmission line from Naubise to Lapsiphedi (MCC project: NR1)

400 kV
220 kV
132 kV

Figure 3.13 Outage of double circuit transmission line from Naubise to Lapsiphedi

The outage of Naubise to Lapsiphedi double circuit line forces the power coming from Barabise substation
(power coming from T2’) into the 132 kV system specially, under Wetmin conditions. In 2030 Wetmin
scenario, the 132 kV line from Mulpani to Lapsiphedi gets overloaded to about 113%. Note that for N-1
contingencies, this line gets overloaded to about 152%. All other overloads are below 110%. Therefore,
the outage of Naubise to Lapsiphedi double circuit line is not a concern.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 134

(2) D/C transmission line from New Damauli to New Butwal (MCC project: NR1)

400 kV
220 kV
132 kV

Figure 3.14 Outage of double circuit transmission line from New Butwal to New Damauli

The worst case is the outage of the double circuit line from New Butwal to New Damauli in 2030 Drypeak
scenario where the imports are at its maximum using the two tie lines. The outage requires the entire
import power from Gorkapur to be transmitted into the 220 kV system at New Butwal substation which
is about an increment of 1000 MW. It was not possible to obtain a converged power flow under these
conditions.

Recommendation:
Load shedding in order to have acceptable loading in 400kV/220kV transformers at the New Butwal
substation is recommended. Shedding of about 900 MW of loads on following buses resulted in acceptable
transformer loading: Bharatpu-132, Damauli-132, Butwal-132, Bairahawa, Shivpur, Hapure, Kusum and
Lamhi.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 135

(3) D/C transmission line from Naubise to New Damauli (MCC project: NR1)

400 kV
220 kV
132 kV

Figure 3.15 Outage of double circuit transmission line from New Damauli to Naubise

In 2030 Wetmin scenario, the loss of D/C line from new Damauli to Naubise results in transmitting about
additional 300 MW of power from the 220kV system. This results in overloading the 4 X 400kV/220kV
transformers at the New Damauli substation about 114%. If this overload is not acceptable, the generation
at New Damauli, Lekhnath, Lower Modi can be adjusted to control the overload.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 136

(4) D/C transmission line from Hetauda to Naubise (MCC project: NR1)

400 kV
220 kV
132 kV

Figure 3.16 Outage of double circuit transmission line from Hetauda to Naubise

Only few overloads as shown in Table 3.12 were reported for this contingency. The overloads stay below
120%. For most of the overloaded lines, N-1 outages show much larger overloads, which needs to be
mitigated. Therefore, the outage double circuit transmission line from Hetauda to Naubise is not a
concern.

Table 3.12. Overloads for outage of double circuit transmission line from Hetauda to Naubise
Overloaded Component
Worst
Worst Contingency
Bus 1 Bus 2 n-1
MVA Rating
CKT loading
to ID Loading (%)
from Bus Bus Name kV Bus Name kV Power flow Contingency
Bus (%)
114 DHALKE-132 132 1115 MIRCHAY 132 1 2030 Dry Peak (N-2): NR1_NAU_HETA 106.5 151 124

114 DHALKE-132 132 1115 MIRCHAY 132 1 2030 Dry Peak (N-2): NR1_NAU_HETA 106.5 151 124

114 DHALKE-132 132 1115 MIRCHAY 132 1 2030 Dry Peak (N-2): NR1_NAU_HETA 106.5 151 124

118 MARSHYAN 132 159 N_BHARA 132 5 2030 Dry Peak (N-2): NR1_NAU_HETA 118.5 114 180

610 SIUCHATA 66 616 NEW PATAN 66 3 2030 Dry Peak (N-2): NR1_NAU_HETA 110.7 195 100

610 SIUCHATA 66 616 NEW PATAN 66 3 2030 Dry Peak (N-2): NR1_NAU_HETA 110.7 195 100
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 137

(5) Tie line 1: D/C transmission line from Hetauda to Dhalkebar

Under maximum imports – 2030 Drypeak scenario


In this scenario, the tie line 1 is importing 1200 MW. The outage of the double circuit tie line requires the
load shedding of the about the same number of MWs. Loads in zone 5 and some of the loads in zone 6
were shed while keeping the maximum imports (1800 MW) in XB1. The total system loads were reduced
to about 3151 MW after about 1122 MW load shedding.

Under maximum exports – 2030 Wetmin scenario


In this scenario, the tie line 1 is exporting 1034 MW. The outage of the double circuit tie line requires the
generation to be tripped while ensuring the maximum exports from the second tie line. XB1 is exporting
about 1540 MW whereas the maximum exports is 1800 MW.

Some generation in Zone 5 (including T2’) and Zone 6 were tripped to ensure 1800 MW exports in XB1.
The total generation of the system was reduced to about 3943 MW after about 792 MW of generation
tripping.

2023 Drypeak scenario and 2023 Wetmin scenario also require similar strategies to keep an acceptable
operating point.

(6) XB1: D/C transmission line from New Butwal to Gorakhpur

Under maximum imports – 2030 Drypeak scenario


In this scenario, both tie line 1 and XB1 imports are at their maximum (XB1: about 1798 MW, tie line 1:
1200 MW). The outage of XB1 forces load shedding as the imports of the tie line 1 is also at its maximum.
Loads in zone 2, zone 3 and some of zone 4 were shed to resolve equipment rating violations and to limit
the imports from the tie line 1.

Under maximum exports – 2030 Wetmin scenario


In this scenario, XB 1 is exporting about 1540 MW and tie line 1 is exporting about 1034 MW. At the outage
of XB1, the tie line 1 exports can be increased to 1200 MW. The excess generation needs to be tripped in
this situation.

The generation at Zone2, Zone 3 and zone 4 were shed to maintain an acceptable operating point.
2023 Drypeak scenario and 2023 Wetmin scenario also require similar strategies to keep an acceptable
operating point.

For the outage of a tie line, it is necessary to have a special protection scheme to trip loads and generation
based on the conditions. A comprehensive study including the India system would be required to
determine the strategy.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 138

(7) D/C transmission line from New Lamki to Bareilly

The outage of New Lamki –Bareilly tie line requires the generation cross tripping. The only supply from T8
under this contingency is the 12% power to the Nepal system. It is assumed that the 12% supply in wet
season is 108 MW and for dry season is 32.4 MW.

Accordingly, in Drypeak scenario, about 237 MW of generation at Upper Karnali needs to be tripped. In
Wetmin scenario, about 792 MW of generation at Upper Kanali needs to be tripped.

(8) Mitigation of Steady State Power flow Issues

It is found that the existing Nepal network is not capable of supplying the loads expected by 2030. Line
upgrades and additional shunt compensation would be required to solve the issues identified in the above
sections. The following system upgrades were considered to mitigate these violations.

 One additional parallel circuit was considered for each of the lines given in the following table.
Note that only the 132 kV circuit between Mulpani and Lapsiphedi is directly relevant to the MCC
projects.

Table 3.13 Additional circuits required to mitigate overloads and network divergence issues
From Bus To Bus
Bus No Name kV Bus No Name kV
107 SHIVPUR 132 108 BUTWAL-132 132
114 DHALKE-132 132 1115 MIRCHAY 132
115 LAHAN 132 51070 RAJBIRAJ_ 132
134 PARWANI-132 132 40060 SIMARA 132
134 PARWANI-132 132 41160 N BIRGUNJ 132
610 SIUCHATA 66 611 BALAJU-66 66
610 SIUCHATA 66 616 NEW PATAN 66
610 SIUCHATA 66 630 TEKU 66
613 CHABEL 66 619 DEVIGHAT-66 66
615 NEW BANESWOR 66 616 NEW PATAN 66
630 TEKU 66 631 K-3 66
41080 MULPANI 132 41090 LAPSIPHEDI1 132
52010 DHALKE2 220 62020 INARUWA2 220
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 139

 As described in the above sections, the following switch shunts were considered to avoid low
voltages under system intact conditions.
o A switch shunt of 150 MVAR (capacitive) at Inaruwa 132 kV bus
o The capacitive range of the existing switch shunt at Patha was changed from 75 MVAR to
150 MVAR
o The capacitive range of the existing switch shunt at Parwani was changed from 75 MVAR
to 180 MVAR
o New switch shunt of 150 MVAR was added at Hetauda 132 kV bus.
o The capacitive range of the existing switch shunt at Bharatpu was changed from 75 MVAR
to 150 MVAR
o About 500 MVAR of switch shunts were required at Siuchata 66 kV bus. The capacitive
reactive power capacity of N. Bhakta switch shunt was increased to 150 MVAR. Note that
66 kV and 33 kV networks were not fully modelled in the power flow cases used and
therefore, this requirement needs to be re-evaluated in a later stage.

The contingency analysis was repeated after adding the aforementioned system upgrades. Table 3.14
shows the overloads obtained after adding the upgrades. There is only one line loaded to about 137 %
and all other overloads stays below 125%. It is necessary to evaluate these minor overloads carefully and
the low cost solutions such as re-dispatching the generators or re-conductoring can be used.

The low voltage violations in the system still remains the same. It is necessary to perform
comprehensive reactive power coordination study in the sub transmission and distribution system in
order to solve these issues.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 140

Table 3.14 Remaining overloads after adding the proposed upgrades


Overloaded Component NO
Worst Contingency
Bus 1 Bus 2 Contingency
CKT MVA rating
Overload
ID Loading (%)
from Bus Bus Name kV to Bus Bus Name kV Power flow Contingency
(%)
40050 AMLEKHGUNJ 132 40060 SIMARA 132 1 2030_Drypeak SINGLE 134-170(1) 137.0 121.3 186.0

118 MARSHYAN 132 159 N_BHARA 132 1 2030_Drypeak SINGLE 119-158(1) 113.0 0.0 180.0

108 BUTWAL-132 132 31190 BAIRAHAWA 132 2 2030_Drypeak SINGLE 108-31190(1) 120.8 0.0 159.1

108 BUTWAL-132 132 31190 BAIRAHAWA 132 1 2030_Drypeak SINGLE 108-31190(2) 120.8 0.0 159.1

108 BUTWAL-132 132 234010 NEW BUTWAL 220 2 2030_Drypeak SINGLE 108-234010(1) 114.2 0.0 500.0

108 BUTWAL-132 132 234010 NEW BUTWAL 220 1 2030_Drypeak SINGLE 108-234010(2) 114.2 0.0 500.0

112 BHARATPU-132 132 159 N_BHARA 132 2 2030_Drypeak SINGLE 112-159(1) 122.8 0.0 124.0

112 BHARATPU-132 132 159 N_BHARA 132 1 2030_Drypeak SINGLE 112-159(2) 122.8 0.0 124.0

113 HETAUDA-132 132 40050 AMLEKHGUNJ 132 2 2030_Drypeak SINGLE 113-40050(1) 114.5 0.0 186.0

113 HETAUDA-132 132 40050 AMLEKHGUNJ 132 1 2030_Drypeak SINGLE 113-40050(2) 114.5 0.0 186.0

114 DHALKE-132 132 52010 DHALKE2 220 2 2030_Drypeak SINGLE 114-52010(1) 102.8 0.0 600.0

114 DHALKE-132 132 52010 DHALKE2 220 1 2030_Drypeak SINGLE 114-52010(2) 102.8 0.0 600.0

115 LAHAN 132 1115 MIRCHAY 132 2 2030_Drypeak SINGLE 115-1115(1) 106.9 0.0 142.0

115 LAHAN 132 1115 MIRCHAY 132 3 2030_Drypeak SINGLE 115-1115(1) 106.9 0.0 142.0

115 LAHAN 132 1115 MIRCHAY 132 1 2030_Drypeak SINGLE 115-1115(2) 106.9 0.0 142.0

117 ANARMANI-132 132 175 DAMAK 132 2 2030_Drypeak SINGLE 117-175(1) 115.1 0.0 124.0

117 ANARMANI-132 132 175 DAMAK 132 1 2030_Drypeak SINGLE 117-175(2) 115.1 0.0 124.0

122 SIUCH 132 133 MATATRIT 132 3 2030_Drypeak SINGLE 122-133(1) 116.6 0.0 228.0

122 SIUCH 132 133 MATATRIT 132 1 2030_Drypeak SINGLE 122-133(3) 116.6 0.0 228.0

122 SIUCH 132 610 SIUCHATA 66 2 2030_Drypeak SINGLE 122-610(1) 113.5 0.0 200.0

122 SIUCH 132 610 SIUCHATA 66 3 2030_Drypeak SINGLE 122-610(1) 113.5 0.0 200.0
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 141

122 SIUCH 132 610 SIUCHATA 66 1 2030_Drypeak SINGLE 122-610(2) 118.3 0.0 200.0

131 CHAPALI 132 41080 MULPANI 132 2 2030_Drypeak SINGLE 131-41080(1) 106.2 0.0 159.1

131 CHAPALI 132 41080 MULPANI 132 1 2030_Drypeak SINGLE 131-41080(2) 106.2 0.0 159.1

134 PARWANI-132 132 170 PATHA 132 2 2030_Drypeak SINGLE 40050-40060(1) 157.5 0.0 142.0

134 PARWANI-132 132 170 PATHA 132 1 2030_Drypeak SINGLE 40050-40060(1) 157.5 0.0 142.0

602 KL-I-66 66 610 SIUCHATA 66 2 2030_Drypeak SINGLE 602-610(1) 111.8 0.0 77.0

602 KL-I-66 66 610 SIUCHATA 66 1 2030_Drypeak SINGLE 602-610(2) 111.8 0.0 77.0

610 SIUCHATA 66 616 NEW PATAN 66 2 2030_Drypeak SINGLE 610-616(1) 103.0 0.0 100.0

610 SIUCHATA 66 616 NEW PATAN 66 3 2030_Drypeak SINGLE 610-616(1) 103.0 0.0 100.0

610 SIUCHATA 66 616 NEW PATAN 66 1 2030_Drypeak SINGLE 610-616(2) 103.0 0.0 100.0

615 NEW BANESWOR 66 616 NEW PATAN 66 2 2030_Drypeak SINGLE 615-616(1) 100.2 0.0 100.0

615 NEW BANESWOR 66 616 NEW PATAN 66 1 2030_Drypeak SINGLE 615-616(2) 100.2 0.0 100.0

113 HETAUDA-132 132 41170 KAMANE 132 1 2030_Drypeak SINGLE 40050-40060(1) 122.7 0.0 159.1

113 HETAUDA-132 132 41170 KAMANE 132 2 2030_Drypeak SINGLE 40050-40060(1) 122.7 0.0 159.1

170 PATHA 132 41170 KAMANE 132 1 2030_Drypeak SINGLE 40050-40060(1) 110.5 0.0 159.1

170 PATHA 132 41170 KAMANE 132 2 2030_Drypeak SINGLE 40050-40060(1) 110.5 0.0 159.1

52010 DHALKE2 220 54010 DHALKE4-NP 400 2 2030_Drypeak SINGLE 52010-54010(1) 100.3 0.0 500.0

52010 DHALKE2 220 54010 DHALKE4-NP 400 3 2030_Drypeak SINGLE 52010-54010(1) 100.3 0.0 500.0

52010 DHALKE2 220 54010 DHALKE4-NP 400 1 2030_Drypeak SINGLE 52010-54010(2) 100.3 0.0 500.0

102 ATARIA 132 11020 BALANCH HUB 132 2 2030_Wetmin SINGLE 102-11020(1) 122.1 0.0 124.0

102 ATARIA 132 11020 BALANCH HUB 132 1 2030_Wetmin SINGLE 102-11020(2) 122.1 0.0 124.0

129 LAMOSANG 132 41100 BARABISE1 132 2 2030_Wetmin SINGLE 129-41100(1) 124.0 0.0 186.0

129 LAMOSANG 132 41100 BARABISE1 132 1 2030_Wetmin SINGLE 129-41100(2) 124.0 0.0 186.0

31110 TADHEKANI 1 132 32020 TADHEKANI H. 220 2 2030_Wetmin SINGLE 31110-32020(1) 118.1 0.0 160.0

31110 TADHEKANI 1 132 32020 TADHEKANI H. 220 1 2030_Wetmin SINGLE 31110-32020(2) 118.1 0.0 160.0

51080 LIKHU HUB_ 132 51081 220 2 2030_Wetmin SINGLE 51080-51081(1) 105.8 0.0 160.0
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 142

51080 LIKHU HUB_ 132 51081 220 3 2030_Wetmin SINGLE 51080-51081(1) 105.8 0.0 160.0

51080 LIKHU HUB_ 132 51081 220 1 2030_Wetmin SINGLE 51080-51081(2) 105.8 0.0 160.0

51081 220 52025 NEW KHIMTI22 220 2 2030_Wetmin SINGLE 51081-52025(1) 125.0 0.0 270.0

51081 220 52025 NEW KHIMTI22 220 1 2030_Wetmin SINGLE 51081-52025(2) 125.0 0.0 270.0

Sensitivity analysis - Lapsiphedi - New Khimti line at 220 kV

For the 2023 and 2030 scenarios considered, the Lapsiphedi - New Khimti line built by another donor will be at 400 kV level. Therefore, three
160 MVA 400 kV/132 kV transformers were used at Lapsiphedi. Initially it is expected that the Lapsiphedi - New Khimti line will be energized at
220 kV. Therefore, a sensitivity analysis was carried out to determine the transformer requirements at Lapsiphedi and the studies revealed that
THREE 160 MVA 400 kV/220 kV transformers would be required at Lapsiphedi.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 143

3.1.6 Short Circuit Analysis

The short circuit calculations were done to determine the breaker rating of the stations. The
calculations were done using the “ASCC” utility in PSSE. Note that only the positive sequence data is
available in the PSSE power flow cases and therefore, only the three phase short circuit currents were
calculated. In order to determine the worst possible fault current the following approach is used.
 It is assumed that the pre-fault voltages at all the bus bars are at the maximum steady state
value (i.e. 1.1 pu).
 The short circuit contribution of India was unknown to the date on which the studies were
done and therefore the calculations were done without considering the contribution of India.
Since the interconnections are at 400 kV system, the largest impact would be on the 400 kV
stations. The following currents were added to the calculated short circuit current based on
the voltage levels.
o 400 kV stations: 15 kA
o 220 kV stations: 10 kA
o 132 kV stations: 5 kA
For example, 15 kA at 400 kV is equivalent to the short circuit current of a 2000 MVA
generator. It is expected that the northern part of India is relatively weak and therefore this
assumption can be considered as pessimistic.
 The calculations were done considering the Wetmin and Drypeak powerflow scenarios in 2023
and 2030. The supply scenarios in these cases were considered as reasonable. However, there
is a possibility of having a higher supply and hence a larger short circuit current.
 Considering above two facts, it is necessary to consider an extra margin from the calculated
values when determining the breaker ratings. A 30 % margin was assumed while determining
the minimum breaker ratings in this analysis.

The maximum short circuit currents were calculated for all the stations in 132 kV and above. The
results are summarized in Table 3.15. The stations relevant the MCC projects are highlighted in the
following colors.

NR+XB1
NR3
NR4
T3
T8
T2'
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 144

Table 3.15 Maximum Short Circuit Currents


Short Circuit Contribution Min
breaker
rating
BusNo Bus Name Voltage Expected (with
Contribution Max SC 30%
2023 2030 Max from India* Current margin)
MVA kA MVA kA kA kA kA kA
101 MAHENDRA 132 357.7 1.6 404.5 1.8 1.8 5.0 6.8 9
102 ATARIA 132 882.8 3.9 1010.2 4.4 4.4 5.0 9.4 13
103 LAMKI 132 1794.9 7.9 1953.3 8.5 8.5 5.0 13.5 18

104 KOHALPUR 132 1492.7 6.5 1639.4 7.2 7.2 5.0 12.2 16

105 LAMAHI 132 1173.3 5.1 1310.5 5.7 5.7 5.0 10.7 14

106 JHIMRUK-132 132 805.8 3.5 891.8 3.9 3.9 5.0 8.9 12

107 SHIVPUR 132 1119.6 4.9 1260.4 5.5 5.5 5.0 10.5 14

108 BUTWAL-132 132 3788.5 16.6 4277.6 18.7 18.7 5.0 23.7 31

110 BARDGHAT 132 1482.7 6.5 1673.9 7.3 7.3 5.0 12.3 17
111 GANDAK-132 132 1047.4 4.6 1187.6 5.2 5.2 5.0 10.2 14
112 BHARATPU-132 132 2533.6 11.1 2771.9 12.1 12.1 5.0 17.1 23
113 HETAUDA-132 132 5281.7 23.1 5731.4 25.1 25.1 5.0 30.1 40
114 DHALKE-132 132 3702.4 16.2 4247.1 18.6 18.6 5.0 23.6 31
115 LAHAN 132 2052.3 9.0 2293.0 10.0 10.0 5.0 15.0 20
116 DUHABI-132 132 1878.7 8.2 2213.1 9.7 9.7 5.0 14.7 20
117 ANARMANI-132 132 1113.2 4.9 1253.4 5.5 5.5 5.0 10.5 14
118 MARSHYAN 132 3441.2 15.1 3768.3 16.5 16.5 5.0 21.5 28
119 DAMAULI-132 132 2109.9 9.2 2308.1 10.1 10.1 5.0 15.1 20
120 POKHARA 132 3258.4 14.3 3632.4 15.9 15.9 5.0 20.9 28
121 KL-II-132 132 4488.5 19.6 4886.0 21.4 21.4 5.0 26.4 35
122 SIUCH 132 5495.8 24.0 5949.2 26.0 26.0 5.0 31.0 41
123 BALAJU-132 132 4819.8 21.1 5220.6 22.8 22.8 5.0 27.8 37
124 KUSHAHA 132 1544.8 6.8 1804.6 7.9 7.9 5.0 12.9 17
125 KG-A-132 132 2494.8 10.9 2618.2 11.5 11.5 5.0 16.5 22
126 MODI-132 132 972.9 4.3 1057.4 4.6 4.6 5.0 9.6 13
127 KHIMTI-132 132 1047.4 4.6 1083.9 4.7 4.7 5.0 9.7 13
128 BHOTEKOS-132 132 1912.5 8.4 1992.7 8.7 8.7 5.0 13.7 18
129 LAMOSANG 132 3828.7 16.7 3994.6 17.5 17.5 5.0 22.5 30
130 N-BHAKTA-132 132 4766.7 20.8 5143.8 22.5 22.5 5.0 27.5 36
131 CHAPALI 132 4632.5 20.3 5020.2 22.0 22.0 5.0 27.0 36
133 MATATRIT 132 5850.2 25.6 6329.1 27.7 27.7 5.0 32.7 43
134 PARWANI-132 132 2686.3 11.7 3017.3 13.2 13.2 5.0 18.2 24
135 KUSUM 132 944.9 4.1 1058.7 4.6 4.6 5.0 9.6 13
142 MMMARS 132 2182.3 9.5 2346.7 10.3 10.3 5.0 15.3 20
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 145

Short Circuit Contribution Min


breaker
rating
BusNo Bus Name Voltage Expected (with
Contribution Max SC 30%
2023 2030 Max from India* Current margin)
MVA kA MVA kA kA kA kA kA
150 MIDMARS-132 132 2038.8 8.9 2159.8 9.4 9.4 5.0 14.4 19
151 N-MARSYA 132 3593.0 15.7 3965.9 17.3 17.3 5.0 22.3 30
157 CHANDRAN 132 2107.1 9.2 2342.4 10.2 10.2 5.0 15.2 20
158 LEKHNATH 132 3548.2 15.5 4020.0 17.6 17.6 5.0 22.6 30
159 N_BHARA 132 2647.9 11.6 2901.2 12.7 12.7 5.0 17.7 23
160 SYANGJA 132 2066.7 9.0 2241.9 9.8 9.8 5.0 14.8 20
170 PATHA 132 2800.6 12.2 3116.0 13.6 13.6 5.0 18.6 25
175 DAMAK 132 1734.8 7.6 1989.6 8.7 8.7 5.0 13.7 18
180 KATAIYA 132 1047.6 4.6 1193.1 5.2 5.2 5.0 10.2 14
181 BANSKOT 132 1962.6 8.6 2157.1 9.4 9.4 5.0 14.4 19
182 LOW_MOD 132 836.4 3.7 907.5 4.0 4.0 5.0 9.0 12
199 KAWASOTI 132 848.6 3.7 956.4 4.2 4.2 5.0 9.2 12
1115 MIRCHAY 132 2532.8 11.1 2817.9 12.3 12.3 5.0 17.3 23
1151 UDIPUR 132 1634.7 7.1 1735.7 7.6 7.6 5.0 12.6 17
2103 SINGATI 132 1790.3 7.8 1785.5 7.8 7.8 5.0 12.8 17
2104 SIPRING 132 1416.3 6.2 1425.7 6.2 6.2 5.0 11.2 15
11020 BALANCH HUB 132 742.6 3.2 1089.8 4.8 4.8 5.0 9.8 13
11040 DEEPAYAL 132 419.7 1.8 475.0 2.1 2.1 5.0 7.1 10
11050 BAJHANG 132 378.6 1.7 428.4 1.9 1.9 5.0 6.9 9
11060 BUDHI GHANGA 132 585.4 2.6 653.8 2.9 2.9 5.0 7.9 11
14030 N. LAMKI-NP 400 1764.7 2.5 1945.5 2.8 2.8 15.0 17.8 24
14035 N. LAMKI-I 400 3610.7 5.2 3685.6 5.3 5.3 15.0 20.3 27
14036 LAMKI-I 132 132 1794.9 7.9 1953.3 8.5 8.5 5.0 13.5 18
21010 NEPALGUNJ_ 132 706.3 3.1 793.9 3.5 3.5 5.0 8.5 12
21020 HAPURE_ 132 552.3 2.4 624.8 2.7 2.7 5.0 7.7 11
21030 SURKHET_ 132 883.9 3.9 987.5 4.3 4.3 5.0 9.3 13
21040 DAILEKH_ 132 574.0 2.5 645.8 2.8 2.8 5.0 7.8 11
21070 GOHARI 132 818.6 3.6 920.2 4.0 4.0 5.0 9.0 12
24010 N KOHALPUR-N 400 1879.9 2.7 2082.8 3.0 3.0 15.0 18.0 24
24040 UP KARNALI 400 4193.3 6.1 4034.1 5.8 6.1 15.0 21.1 28
31010 GULMI 132 1170.7 5.1 1269.8 5.6 5.6 5.0 10.6 14
31020 BURTIBANG 132 598.2 2.6 653.4 2.9 2.9 5.0 7.9 11
31050 KUSMA 1 132 3305.3 14.5 3528.5 15.4 15.4 5.0 20.4 27
31060 NEW MODI 132 3126.5 13.7 3367.9 14.7 14.7 5.0 19.7 26
31070 UPPER MODI A 132 2143.5 9.4 2264.7 9.9 9.9 5.0 14.9 20
31100 DANA1 132 1501.4 6.6 1680.4 7.4 7.4 5.0 12.4 17
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 146

Short Circuit Contribution Min


breaker
rating
BusNo Bus Name Voltage Expected (with
Contribution Max SC 30%
2023 2030 Max from India* Current margin)
MVA kA MVA kA kA kA kA kA
31110 TADHEKANI 1 132 2321.5 10.2 2336.8 10.2 10.2 5.0 15.2 20
31130 KHUDI NOR. 1 132 2197.7 9.6 2620.9 11.5 11.5 5.0 16.5 22
31150 KIRTIPUR HUB 132 1729.7 7.6 1951.8 8.5 8.5 5.0 13.5 18
31170 UP. DARRAU1 132 1371.5 6.0 1512.2 6.6 6.6 5.0 11.6 16
31190 BAIRAHAWA 132 2273.1 9.9 2559.1 11.2 11.2 5.0 16.2 22
31200 KHUDI 132 1182.0 5.2 1289.0 5.6 5.6 5.0 10.6 14
32010 KUSMA2 220 4193.4 11.0 4457.3 11.7 11.7 10.0 21.7 29
32020 TADHEKANI H. 220 3157.2 8.3 3303.2 8.7 8.7 10.0 18.7 25
32040 DANA 220 3500.9 9.2 3692.5 9.7 9.7 10.0 19.7 26
32060 BHARATPUR2 220 5031.6 13.2 5924.0 15.5 15.5 10.0 25.5 34
32070 MARSYGANDI2 220 5930.0 15.6 7468.2 19.6 19.6 10.0 29.6 39
32130 UPPER DARAU 220 3945.2 10.4 4679.1 12.3 12.3 10.0 22.3 29
32150 NEW DAMAULI 220 6303.7 16.5 7432.7 19.5 19.5 10.0 29.5 39
32160 LEKNATH2 220 3627.8 9.5 4257.3 11.2 11.2 10.0 21.2 28
34010 NEW BUTWAL 400 5653.3 8.2 7011.5 10.1 10.1 15.0 25.1 33
40050 AMLEKHGUNJ 132 3520.6 15.4 3896.1 17.0 17.0 5.0 22.0 29
40060 SIMARA 132 2899.2 12.7 3237.1 14.2 14.2 5.0 19.2 25
41010 HARSIDDHI 132 4147.2 18.1 4477.0 19.6 19.6 5.0 24.6 32
41020 CHAPAGON 132 4174.9 18.3 4507.4 19.7 19.7 5.0 24.7 33
41030 BALHEPI HUB 132 1467.2 6.4 1511.5 6.6 6.6 5.0 11.6 16
41080 MULPANI 132 5280.4 23.1 5723.6 25.0 25.0 5.0 30.0 40
41090 LAPSIPHEDI1 132 5668.8 24.8 6176.0 27.0 27.0 5.0 32.0 42
41100 BARABISE1 132 4803.3 21.0 5053.1 22.1 22.1 5.0 27.1 36
41120 TRISHULI 3B1 132 3000.5 13.1 3015.3 13.2 13.2 5.0 18.2 24
41130 SAMUDARTAR 132 1123.2 4.9 1161.4 5.1 5.1 5.0 10.1 14
41140 CHILME1 132 1560.5 6.8 1582.1 6.9 6.9 5.0 11.9 16
41160 N BIRGUNJ 132 2086.0 9.1 2346.7 10.3 10.3 5.0 15.3 20
41170 KAMANE 132 3545.9 15.5 3910.6 17.1 17.1 5.0 22.1 29
42020 MATATRIT2 220 6622.7 17.4 7168.5 18.8 18.8 10.0 28.8 38
42030 TRISHULI 3B 220 4991.2 13.1 5042.2 13.2 13.2 10.0 23.2 31
42040 CHILME HUB 220 4021.0 10.6 4045.4 10.6 10.6 10.0 20.6 27
42090 NAUBISE2 220 6862.2 18.0 7566.9 19.9 19.9 10.0 29.9 39
42100 UPTRISHULI1 220 3945.5 10.4 3950.8 10.4 10.4 10.0 20.4 27
44010 HETAUDA4 400 7030.4 10.1 7879.8 11.4 11.4 15.0 26.4 35
44040 NAUBISE4 400 7885.9 11.4 8798.1 12.7 12.7 15.0 27.7 37
44050 LAPSIPHEDI4 400 7271.6 10.5 7974.7 11.5 11.5 15.0 26.5 35
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 147

Short Circuit Contribution Min


breaker
rating
BusNo Bus Name Voltage Expected (with
Contribution Max SC 30%
2023 2030 Max from India* Current margin)
MVA kA MVA kA kA kA kA kA
44060 BARABISE4 400 6329.3 9.1 6947.7 10.0 10.0 15.0 25.0 33
51040 TINGLA HUB 132 1257.6 5.5 1234.5 5.4 5.5 5.0 10.5 14
51050 JANAKPUR_ 132 1705.6 7.5 1911.3 8.4 8.4 5.0 13.4 18
51060 JALESWOR_ 132 1318.6 5.8 1472.5 6.4 6.4 5.0 11.4 15
51070 RAJBIRAJ_ 132 1493.2 6.5 1664.8 7.3 7.3 5.0 12.3 16
51080 LIKHU HUB_ 132 2749.3 12.0 3778.9 16.5 16.5 5.0 21.5 28
51081 220 2761.4 7.2 4431.0 11.6 11.6 10.0 21.6 29
51130 NEW KHIMITI1 132 781.6 3.4 1030.6 4.5 4.5 5.0 9.5 13
52010 DHALKE2 220 4638.6 12.2 5628.2 14.8 14.8 10.0 24.8 33
52020 NEW KHIMTI21 220 3196.0 8.4 5615.4 14.7 14.7 10.0 24.7 33
52025 NEW KHIMTI22 220 2864.0 7.5 5615.1 14.7 14.7 10.0 24.7 33
52030 UPPER_TAMA 220 3296.4 8.7 4182.3 11.0 11.0 10.0 21.0 28
52040 TAMAKO-3 220 2301.6 6.0 2553.6 6.7 6.7 10.0 16.7 22
54010 DHALKE4-NP 400 4961.7 7.2 5733.0 8.3 8.3 15.0 23.3 31
54090 NEW KHIMTI4 400 4788.8 6.9 5540.4 8.0 8.0 15.0 23.0 30
61010 ILLAM 132 1699.8 7.4 1881.6 8.2 8.2 5.0 13.2 18
61020 BHADRAPUR 132 879.6 3.8 987.1 4.3 4.3 5.0 9.3 13
61025 BIRATNAGAR 132 1446.6 6.3 1664.6 7.3 7.3 5.0 12.3 16
61030 PHIDIM 132 1367.8 6.0 1440.0 6.3 6.3 5.0 11.3 15
61040 KABELI 132 1189.1 5.2 1244.5 5.4 5.4 5.0 10.4 14
61050 PINASEGAHT 132 1072.1 4.7 1113.1 4.9 4.9 5.0 9.9 13
61090 KHANDBARI 220 1404.7 3.7 2263.7 5.9 5.9 10.0 15.9 21
61160 ITHARI_ 132 1145.6 5.0 1331.3 5.8 5.8 5.0 10.8 15
61170 DHARAN_ 132 922.9 4.0 1057.5 4.6 4.6 5.0 9.6 13
61200 INARUWA 132 2200.1 9.6 2704.0 11.8 11.8 5.0 16.8 22
61220 BANESHWOR1 132 418.8 1.8 462.3 2.0 2.0 5.0 7.0 10
62010 BASANTPUR 220 1617.1 4.2 2396.8 6.3 6.3 10.0 16.3 22
62015 BANESHWOR 220 1471.5 3.9 2307.5 6.1 6.1 10.0 16.1 21
62020 INARUWA2 220 2451.7 6.4 3096.7 8.1 8.1 10.0 18.1 24
62050 ARUN 3 NP_ 220 1221.9 3.2 2137.9 5.6 5.6 10.0 15.6 21
64090 DAMAK4 220 1857.0 4.9 2157.1 5.7 5.7 10.0 15.7 21
70010 MUZZAFA 400 3894.2 5.6 4591.7 6.6 6.6 15.0 21.6 29
70020 GORAKPHUR 400 3657.3 5.3 4957.6 7.2 7.2 15.0 22.2 29
100111 BAREILLY 400 2438.3 3.5 2835.8 4.1 4.1 15.0 19.1 25
140360 PSTF_BUS 132 1845.5 8.1 1918.2 8.4 8.4 5.0 13.4 18
234010 NEW BUTWAL 220 5496.3 14.4 6592.1 17.3 17.3 10.0 27.3 36
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 148

Short Circuit Contribution Min


breaker
rating
BusNo Bus Name Voltage Expected (with
Contribution Max SC 30%
2023 2030 Max from India* Current margin)
MVA kA MVA kA kA kA kA kA
234140 KHUDI 220 220 3144.8 8.3 5497.3 14.4 14.4 10.0 24.4 32
234150 MANANG 220 220 2125.2 5.6 3034.5 8.0 8.0 10.0 18.0 24
244010 HETAUDA 220 220 5968.1 15.7 6651.4 17.5 17.5 10.0 27.5 36
432150 NEW DAMAULI 400 6668.3 9.6 7895.9 11.4 11.4 15.0 26.4 35

Based on the short circuit analysis, at least 42 kA breakers are recommended for 132 kV stations of
MCC projects. For the 220 kV and 400 kV levels, the breaker ratings should be at least 39 kA and 37
kA respectively. Standard breaker ratings shall be selected based on these requirements.

3.1.7 Transient stability analysis

The objective of this study is to analyze the ability of the system to maintain the synchronism and the
stability after being subjected to a fault.

Methodology
The transient stability analysis were performed using PSSE dynamic simulation tools for the power
flow scenarios given in Table 3.16.

Table 3.16 Operating points selected for transient stability analysis


Case Supply/Demand Set of MCC Projects Included in this Case
8 2023 Drypeak Base Case + all MCC Projects
16 2023 Wetmin Base Case + all MCC Projects
24 2030 DryPeak Base Case + all MCC Projects
32 2030 Wetmin Base Case + all MCC Projects
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 149

Representation of loads
The loads were represented using the constant current model for active power and constant
admittance model for reactive power (default load model used in PSSE).

Dynamic representation of generators and auxiliary devices


For the existing devices (by 2016), the dynamic data provided by NEA were used in the transient
stability analysis. The generators listed in Table 3.17 were identified from the NEA database. Note that
the bus numbers of the NEA power flow cases and WSP provided powerflow cases were completely
different and the units were identified by matching the bus names.

Table 3.17. Generators identified from NEA database


Generators in power flows Identified from NEA dynamic data
Bus No Station ID BusNo-ID
106 JHIMRUK-132 132.00 1 6003-1
111 GANDAK-132 132.00 1 1002-1
111 GANDAK-132 132.00 2 1002-2
113 HETAUDA-132 132.00 2 1005-2
118 MARSHYAN 132.00 1 1001-1
121 KL-II-132 132.00 1 6004-1
126 MODI-132 132.00 1 6006-1
127 KHIMTI-132 132.00 1 1007-1
129 LAMOSANG 132.00 1 129-1
129 LAMOSANG 132.00 2 129-2
129 LAMOSANG 132.00 3 129-3
129 LAMOSANG 132.00 4 129-4
150 MIDMARS-132 132.00 1 1001-2
601 HETAUDA-66 66.000 1 1005-1
602 KL-I-66 66.000 1 1003-1
617 SUNKOSHI-66 66.000 1 6005-1
619 DEVIGHAT-66 66.000 1 6001-1
620 CHILIME-66 66.000 1 1006-1
622 INDRAWAT-66 66.000 1 6008-1
234140 KHUDI 220 220.00 1 6012-1
234140 KHUDI 220 220.00 2 6012-2

For the other devices, the generic dynamic device data were used as mentioned below.

Generators: Salient pole generator model. PSSE model – GENSAL


It is expected that most of the new generating stations would be hydro generators. For the hydro
generators (low speed & higher number of poles), the most suitable generator model is the salient
pole model (GENSAL). Usually, the inertia of hydro generators vary in the range of 2s to 4s regardless
of the size of the generators. As a mean value, an inertia of 3s was used and typical values were
selected for the other variables. All the model parameters are listed below.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 150

Table 3.18 Parameters used for PSSE GENSAL generator model


Constant Value
T’do 5.5 s
T’’do 0.036 s
T’’qo 0.1 s
H, Inertia 3.0 s
D, Speed damping 0.0 pu
Xd 0.63 pu
Xq 0.45 pu
X’d 0.25 pu
X’’d = X’’q 0.178 pu
Xl 0.1167 pu
S (1.0) 0.09
S (1.2) 0.29

No equivalents were provided for the India system and therefore, the India system was modeled using
three Thevenin sources connected at the end of three tie lines considered in the models. The short
circuit contribution of each source was kept at 15 kA. These sources are modeled using GENCLS in
PSSE. The PSSE models the units as voltage sources when the inertia of GENCLS model is zero.

Exciters: PSSE model – SEXS


The same exciter model with the same parameters has been used in the existing NEA database.
Therefore, the same model was used for the new generating stations as well. Note that there is a great
influence of the exciters on the transient stability of the system; however, at this stage it is difficult to
select different models for different generators without having much insight into the generation
(manufacturer, type, etc.). The generic exciter parameters are given below.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 151

Table 3.19. Parameters used for PSSE SEXS exciter model


Constant Value
TA/TB 0.05
TB 100 s
K 180
TE 0.5 s
EMIN 0
EMAX 4

Figure 3.17. Block diagram representation of PSSE SEXS exciter model

Power System Stabilizers: PSSE model – IEEEST


The need of power system stabilizers was determined by performing the small signal stability analysis
of the system. This analysis was performed using TGSSR – an in-house developed small signal stability
assessment tool.

The power system stabilizers were designed to improve the damping of a local and an inter area
oscillator mode of 0.9 Hz and 0.8 Hz respectively. Figure 3.18 shows the improvement of damping of
the generation speed oscillations for a 5 cycle 3 phase to ground fault occurred very close to the
Lapsiphedi 400 kV bus which was cleared by isolating the ckt 1 of the 400 kV transmission line from
Lapsiphedi to Naubise (Contingency 10, 2030 Wetmin scenario).
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 152

Figure 3.18 Effect of the PSS on damping of the generation oscillations for contingency 10
(2030 Wetmin scenario)

Table 3.11 lists the parameters of PSSE library model IEEEST type power system stabilizers on the
generators at Bus: 11020, id: 1 and Bus: 52030, Id: 1.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 153

Table 3.20 Parameters used for Power system stabilizers


Constant Generators:
Balanch Hub 132 kV bus (Bus #: 11020, Id ‘1’)
Upper Tama 220 kV bus (Bus #: 52030, Id ‘1’)
A1 0.02
A2 0
A3 0
A4 0
A5 0
A6 0
T1 0.06
T2 0.4
T3 0.06
T4 0.4
T5 10
T6 10
Ks 20
Lsmax 0.2
Lsmin -0.2
Vcu 0
Vcl 0

Turbine-Governor: PSSE model – HYGOV


A hydro governor model (HYGOV) model with the following parameters were used in the analysis.

Table 3.21 Parameters used for PSSE HYGOV turbine-governor model


Constant Value
R, permanent droop 0.05
r, temporary droop 0.4 s
Tr, governor time constant 7
Tf, filter time constant 0.05 s
Tg, servo time constant 0.5 s
+ VELM, gate velocity limit 0.1
GMAX, maximum gate limit 1.5
GMIN, minimum gate limit 0
TW, water time constant 1
At, turbine gain 1
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 154

Dturb, turbine damping 0.0


qNL, no power flow 0.1

List of contingencies
The list of contingencies comprised of 3 phase balanced faults occurred on transmission lines and
transformers close to major stations relevant to the MCC projects were considered in this analysis.
The fault was cleared by tripping the relevant transmission line or transformer. The fault duration was
considered to be 5 cycles (100ms). Table 3.22 shows the list of contingencies.

Table 3.22 List of contingencies used for dynamic simulation


Number Faulted bus Tripped Devices
(fault duration: 5 cycles)
1 NewButwal 400kV LNout: NewButwal- Gorakhpur
2 NewButwal 400kV LNout: NewButwal-KohalpurN
3 NewButwal 400kV 2WDout: NewButwal 400-220 kV
4 NewButwal 400kV LNout: NewButwal-NewDamauli
5 NewDamauli 400kV LNout: NewDamauli-Naubise
6 NewDamauli 220kV LNout: NewDamauli-Lekhnath
7 NewDaumuli 400kV 2WDout: NewDaumuli 400-220 kV
8 NewDamauli 220kV LNout: NewDamauli-Marsygandi
9 Naubise 400kV LNout: Naubise-Hetauda
10 Naubise 400kV LNout: Naubise-Lapsiphedi
11 Naubise 400kV 2WDout: Naubise 400-220 kV
12 Lapsiphedi 400kV LNout: Lapsiphedi-Barabise
13 Lapsiphedi 400kV 2WDout: Lapsiphedi 400-220 kV
14 Barabise 400kV 2WDout: Barabise 400-220 kV
15 Barabise 400kV LNout: Barabise-NewKhimti
16 NewKhimti 400kV 2WDout: NewKhimti 400-220 kV
17 NewKhimti 220kV LNout: NewKhimti-LikhuHub
18 NewKhimti 220kV 2WDout: NewKhimti 220 kV
19 LikhuHub 132kV 2WDout: LikhuHub 220-132 kV
21 Hetauda 400kV LNout: Hetauda-Dhalke
22 Hetauda 400kV 2WDout: Hetauda 400-220 kV
23 Hetauda 220kV LNout: Hetauda-Bharatpur
24 Hetauda 220kV 2WDout: Hetauda 220-132 kV
25 Hetauda 132kV LNout: Hetauda-KL-II
26 Hetauda 132kV LNout: Hetauda-Kamane
27 Hetauda 132kV LNout: Hetauda-Amelekhgunj
28 Hetauda 132kV LNout: Hetauda-NBhara
29 Dhalke 400kV 2WDout: Dhalke 400-220 kV
30 Dhalke 220kV 2WDout: Dhalke 220-132 kV
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 155

Number Faulted bus Tripped Devices


(fault duration: 5 cycles)
31 Dhalke 220kV LNout: Dhalke-NewKhimti
32 Dhalke 220kV LNout: Dhalke-Inaruwa
33 Dhalke 400kV LNout: Dhalke-Muzaffarpur
34 Inaruwa 220kV 2WDout: Inaruwa 220-132 kV
35 Inaruwa 132kV LNout: Inaruwa-Huhabi
36 Inaruwa 132kV LNout: Inaruwa-Ithari
37 Inaruwa 132kV LNout: Inaruwa-Khshaha
38 Inaruwa 132kV LNout: Inaruwa-Damak
39 Inaruwa 132kV LNout: Inaruwa-Lahan
40 Inaruwa 220kV LNout: Inaruwa-Basantpur
41 Inaruwa 132kV LNout: Inaruwa-Ilam
42 Ilam 132kV LNout: Ilam-Damak
43 Ilam 132kV LNout: Ilam-Phidim
44 Ilam 133kV 2WDout: Ilam 133-33 kV
45 Kusma 220kV LNout: Kusma-NewButwal
46 Kusma 220kV 2WDout: Kusma 220-132 kV
47 Kusma 220kV LNout: Kusma-Dana
48 Kusma 220kV LNout: Kusma-TadhekaniH
49 Tadhekani 220kV 2WDout: Tadhekani 220-132 kV
50 Ataria 132kV LNout: Ataria-Lamki
51 Ataria 132kV LNout: Ataria-Deepayal
52 Ataria 132kV LNout: Ataria-Mahendra
53 Ataria 132kV LNout: Ataria-BalanchHub
54 NLamki 400kV LNout: NLamki-UPKarnali
55 NLamki 400kV LNout: NLamki-Bareilly
56 NLamkiNP 400kV 2WDout: NLamkiNP 400-132 kV
57 NLamkiNP 400kV 2WDout: NKohalpurN 400-132 kV
58 NKohalpurN 400kV LNout: NLamkiNP-KohalpurN
59 Upper Tama Gen Terminal Upper Tama Generator
60 Khudi Gen Terminal Khudi Generator

Dynamic Study Results


The system was transiently stable for the set of contingencies listed in Table 3.22. The detailed system
responses under the list of contingencies are listed as an Annex A to the report.

Dynamic Voltage Performance


This section examines the transient recovery bus voltages of the system buses relevant to proposed
MCC projects. For the dynamic voltage performance, there is no straight forward criterion defined in
the Nepal grid code. The following performance criterion commonly used in North America was
adapted while analyzing the results.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 156

 Transient undervoltages after the fault clearance should remain above 0.7 pu and the voltage
should recover above 0.9 pu within 2 seconds from the fault occurrence.
 Transient overvoltages should remain below 1.3 pu for first 200 ms from the fault occurrence
and the voltage should recover below 1.1 pu after that.

The worst possible voltage responses observed at the stations relevant to the MCC projects are
summarized below.

MCC Project: NR1: High Voltage Transmission Trunk Line


For the faults in the NR1 project, the voltage recovers well within the criteria defined above, the
system performance is acceptable in the voltage stability point of view. The voltage recovery at each
station is shown below.
New Hetauda substation

Figure 3.19 Voltage recovery after being subjected to a fault at Hetauda 400 kV bus
(Contingency 21, 2030 Wetmin scenario).
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 157

New Damauli Substation

Figure 3.20 Voltage recovery after being subjected to a fault at New Damauli 400 kV bus
(Contingency 5, 2030 Wetmin scenario).
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 158

Naubise Substation

Figure 3.21 Voltage recovery after being subjected to a fault at Naubise 400 kV bus
(Contingency 10, 2030 Wetmin scenario)

Lapsiphedi Substation
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 159

Figure 3.22 Voltage recovery after being subjected to a fault at Lapsiphedi 400 kV bus
(Contingency 12, 2030 Wetmin scenario)

New Butwal Substation

Figure 3.23 Voltage recovery after being subjected to a fault at New Butwal 400 kV bus
(Contingency 4, 2030 Wetmin scenario)

MCC Project: NR3: Ilam—Inaruwa Transmission Line Project


In NR3 project, the system recovers well for the fault near Ilam. However for the fault near Inaruwa
substation, the voltage drops slightly below 0.7 pu while recovering in 2030 wetmin powerflow
scenario (outage of Inaruwa-Basantpur 220 kV circuit). Note that the Inaruwa-Basantpur 220 kV circuit
are heavily loaded in this powerflow scenario and the network divergence issues were also observed
near this area in the steady state analysis. It is expected that the slight dynamic voltage violation will
disappear when the steady state voltage performance in that area is improved.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 160

Ilam Substation

Figure 3.24 Voltage recovery after being subjected to a fault at Ilam 132 kV bus (Contingency
43, 2030 Wetmin scenario)

Inaruwa Substation
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 161

Figure 3.25 Voltage recovery after being subjected to a fault at Inaruwa 220 kV bus
(Contingency 40, 2030 Wetmin scenario)

MCC project NR4: Balanch—Attaria Transmission line project


For the faults in and near the NR4 project, the system recovers well. The worst reported voltage
recovery is shown below.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 162

Figure 3.26 Voltage recovery after being subjected to a fault at Ataria 132 kV bus (Contingency
53, 2030 Wetmin scenario)

MCC project: T2’: New Khimti – Likhu Hub Transmission Line Project
For the faults in and near the T2’ project, the system recovers well. The worst reported voltage
recoveries at the stations are shown below.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 163

New Khimti Substation

Figure 3.27 Voltage recovery after being subjected to a fault at New Khimti 220 kV bus
(Contingency 17, 2030 Wetmin scenario)
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 164

Likhu Hub Substation

Figure 3.28 Voltage recovery after being subjected to a fault at Likhu 132 kV bus (Contingency
19, 2030 Wetmin scenario)

MCC project: T3: Tadekhani—Kusma Transmission Line Project


For the faults in and near the T3 project, the system recovers well. The worst reported voltage
recovery is shown below.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 165

Figure 3.29 Voltage recovery after being subjected to a fault at Tadhekani 220 kV bus
(Contingency 49, 2030 Wetmin scenario)

T8: New Lamki—Nepal/India Border Transmission Project


For the faults in and near the T8 project, the system recovers well. The worst reported voltage
recovery is shown below.

New Lamki Substation

Figure 3.30 Voltage recovery after being subjected to a fault at New Lamki 400 kV bus
(Contingency 54, 2030 Wetmin scenario)
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 166

Electromechanical Oscillation Damping


The electromechanical oscillations of the system was analyzed using the transient stability results as
well as the small signal stability analysis. In general 3% to 5% damping is acceptable for the
electromechanical oscillations. Based on the small signal stability analysis of the system intact
conditions prior to the disturbances, the lowest damping of the electromechanical oscillations is about
7% and therefore, there is no concern about the damping of the oscillations. This performance was
also observed in the dynamic simulations. Some of the worst case electromechanical oscillations
observed in the system for the contingencies considered in the transient stability analysis are shown
below. The oscillations die down within 10 seconds.

Figure 3.31 Generator speed variations under contingency9 (2030 Drypeak)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 167

Frequency Stability
The system frequency stays within 49 Hz and 51 Hz, which is acceptable during the system
disturbances. Some of the worst case frequency responses are shown below.

Figure 3.32 Bus frequency variation under contingency 9 (2030 Drypeak)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 168

Figure 3.33 Bus frequency under contingency 5 (2030 Wetmin)

Figure 3.34 Bus frequency variation under contingency 9 (2023 Drypeak)


Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 169

Largest Generator Outage in Nepal


In 2030 Drypeak scenario, the generator at Khudi is supplying about 170 MW. The tie lines flows are
shown for the outage of the generator after a 3 phase fault at the terminal. The first tie line
(Dhalkebar) imports were increased by about 80 MW and XB1 imports were increased by about 73
MW. Note that the tie lines provide the entire power mismatch because fixed frequency voltage
sources were used to model the India system. In the real system, some power would be provided by
the local generators due to governor action and the rest is provided by the tie lines. Therefore the
case simulated can be considered as the worst case when considering the stresses on the tie lines and
the Nepal system. The system recovers well and the voltage performance of the system is good.

Figure 3.35 Tie line power transfers and voltages for the outage of Generator at Khudi - 2030
Dry Peak
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 170

Summary of Dynamic Analysis


The transient stability studies were performed using the dynamic data from NEA for the existing
generating stations and the generic models with typical parameters for the new generating stations.
All possible N-1 contingencies relevant to the MCC projects were considered in the analysis. The
system recovers well after the contingencies and there is no concern related to the dynamic voltage
performance, frequency stability of the electromechanically oscillations of the generators

3.1.8 Technical Benefits Study

An energy benefits study was performed to determine the benefits of eight different MCC project
scenarios in terms of load shedding, generation not utilized, and losses. Furthermore, sensitivity
studies were performed to determine the effects of different demand and supply forecasts along with
the impacts of the tie line connecting New Butwal and Gorakhpur (XB1).

Power flow cases were created using PSS®E to evaluate the energy benefits and sensitivity of each
scenario considered in this study. A power flow case was created for each scenario using different load
and supply forecasts depending on the year and season. The Nepal system load and generation were
balanced to ensure that the following constraints were met for each case:

 Transmission line limits. The load on each transmission line in the system was limited to 100%
of its MVA rating value defined in PSS®E. Local generation was shifted to try and alleviate
branch limit violations whenever possible. Generation reduction and load shedding were used
in cases where branch limit violations could not be eliminated by shifting generation.
 Bus voltage limits. The voltage at each bus in the system was limited to a value between 0.9
pu and 1.1 pu. Local shunt devices and tap changing transformers were used to eliminate
voltage violations whenever possible. Load shedding was used in cases where under voltage
violations could not be eliminated by local voltage control devices.
 Interchange limits. Power interchange between Nepal and India was limited to 700 MW
without XB1, 1750 MW with XB1 in the 2023 cases, 1200 MW without XB1, and 3000 MW with
XB1 in the 2030 cases. Furthermore, it was assumed that the existing tie line between
Dhalkebar and Musaffarpur carries 40% of the total interchange amount, while XB1 carries
60% of the total interchange amount in all cases where XB1 is in service.

Scenarios with MCC Projects


Tables 3.23 and 3.24 contain the annual energy figures for each MCC project scenario for 2023 and
2030, respectively. The results show that the XB1 tie line project has the greatest impact on reducing
load shedding in Nepal. In general, it was found that the load supplied for Drypeak cases and total
generation utilized for Wetmin cases are primarily constrained by the Nepal-India interchange limits.
The system’s transmission line and bus voltage limits did not have a significant impact on load
shedding and generation utilization for these power flow cases.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 171

Table 3.23 Annual Energy Figures for Different MCC Project Scenarios for 2023
Scenario Annual Annual Annual Annual Annual Annual Annual
Supply Consumption Loss Load Imports Exports Generation
(GWh) (GWh) (GWh) Shedding (GWh) (GWh) Not Utilized
(GWh) (GWh)
Counterfactual 12219.6 12986.5 377.0 3924.8 3571.1 2427.2 8482.5
NR1 12180.1 13012.2 272.7 3899.1 3570.2 2465.4 8522.0
NR1 + XB1 12604.9 15184.9 347.4 1726.4 5823.2 2895.8 8097.2
NR1 + XB1 + 15577.0 15313.5 400.3 1597.9 4911.2 4774.4 5125.1
T2’ + T3
NR3 12215.1 13004.9 350.3 3906.4 3570.8 2430.7 8486.9
NR4 12217.4 12985.1 373.7 3926.2 3570.8 2429.3 8484.7
T8 17097.5 13133.5 411.4 3777.8 3501.6 7054.1 3604.5
All Projects 20702.0 15349.6 351.7 1561.7 4670.0 9670.8 0.1

Table 3.24 Annual Energy Figures for Different MCC Project Scenarios for 2030
Scenario Annual Annual Annual Annual Annual Annual Annual
Supply Consumption Loss Load Imports Exports Generation
(GWh) (GWh) (GWh) Shedding (GWh) (GWh) Not Utilized
(GWh) (GWh)
Counterfactual 19305.1 18635.9 740.2 9452.7 4462.7 4391.7 12869.9
NR1 19650.8 19915.1 660.2 8173.5 5315.8 4391.3 12524.2
NR1 + XB1 23852.8 24923.8 1072.2 3164.7 10615.9 8472.6 8322.2
NR1 + XB1 + 26801.9 25025.7 1155.2 3062.9 9982.6 10603.5 5373.2
T2’ + T3
NR3 19305.1 19463.2 708.2 8625.4 5267.4 4401.2 12869.9
NR4 19285.6 19418.2 757.5 8670.3 5281.4 4391.2 12889.5
T8 24036.8 19636.7 809.0 8451.9 5297.2 8888.4 8138.2
All Projects 31710.2 25138.3 946.7 2950.3 9790.5 15415.7 464.8

Based on above two tables, it reveals that the NR1 and the tie line project between New Butwal and
Gorakphur (XB1) has the most significant impact on the reduction of load shedding in Nepal. The
annual load shedding (GWh) will be reduced to 44% of the level comparing with the base case without
the NR1 and XB1 project in 2023, and reduced to 33% of the level comparing with the base case
without the NR1 and XB1 project in 2030.

T8 tie line is critical important for the 900 MW Upper Karnali HPP generation project. With T8 project,
the overall generation utilization will increase to 83% from 59% in Base case in 2023, and increase to
75% from 60% in Base case in 2030. As the energy resources are distributed over the entire country in
different zones. Therefore, with all proposed MCC projects, the generation utilization can be increased
to 100% and 99% in 2023 and 2030 respectively.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 172

Impact of Different Supply Scenarios


The original cases prepared for the technical benefits study include a three- and five-year lag on
generation and transmission projects for 2023 and 2030, respectively. Two additional supply scenarios
were considered for the counterfactual and all MCC project cases to determine the impact of changes
in the supply forecast on the technical benefit results. The first supply scenario is a low supply scenario
that reduces the total generation available and transmission system capacity in Nepal by applying an
additional five-year lag to both base cases. The low supply cases for 2023 were created by first
removing all transmission projects with a commission date of 2020 except if the project provides
power to a radial load. The low supply cases for 2030 were created by simply scaling the generation
profile of the corresponding 2030 cases.

The second supply scenario is a high supply scenario that increases the total generation available and
transmission system capacity in Nepal by eliminating the lag associated with each case. The high
supply cases for both 2023 and 2030 were created by scaling the generation profile of each base case
to increase the overall system capacity. Furthermore, any out-of-service transmission system projects
with commission dates of 2025 were enabled in the 2030 high supply cases. Finally, it was found that
Zone 1 could not support the high supply generation figures for 2030, so an additional generator was
added to Lamki’s 132 kV bus to provide additional power in Zone 1.

Tables 3.25 and 3.26 contain the annual energy figures for the supply sensitivity scenarios along with
the base technical benefit results for 2023 and 2030, respectively. It was found that transmission line
capacity in Nepal was the primary limiting factor in both the low and high supply scenarios. In the case
of low supply scenarios, the elimination of transmission line projects increases the loading on other
transmission pathways in the system. In the case of high supply scenarios, the transmission system is
not capable of transmitting the additional generation available. For example, during the high supply
wetmin 2030 cases, there is a significant amount of generation not utilized despite the fact that there
is capacity available on the Nepal-India tie lines.

A particular situation important to note is the low supply wetmin scenario for the year 2023 with all
MCC projects. It was found that during peak and shoulder loads, there is some generation capacity
available and not utilized despite the fact that the system is importing power. In this case, importing
power to supply loads close to the tie lines is favored over using Nepal’s generation, as the system’s
infrastructure is unable to transmit the required power. It should also be noted that this does not
occur in the base or high supply cases.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 173

Table 3.25 Annual Energy Figures for the Supply Sensitivity Study for 2023
Scenario Annual Annual Annual Annual Annual Annual Annual
Supply Consumption Loss Load Imports Exports Generation
(GWh) (GWh) (GWh) Shedding (GWh) (GWh) Not Utilized
(GWh) (GWh)
Counterfactual
Low 5134.4 9885.2 231.5 7026.1 4982.3 0.0 8096.3
Base 12219.6 12986.5 377.0 3924.8 3571.1 2427.2 8482.5
High 13652.2 13802.6 435.8 3108.7 3145.4 2559.2 9312.5
All MCC Projects
Low 12147.6 14984.9 524.5 1926.4 8030.1 4668.2 1083.0
Base 20702.0 15349.6 351.7 1561.7 4670.0 9670.8 0.1
High 22852.4 15532.8 404.5 1378.5 3692.2 10607.3 112.4

Table 3.26 Annual Energy Figures for the Supply Sensitivity Study for 2030
Scenario Annual Annual Annual Annual Annual Annual Annual
Supply Consumption Loss Load Imports Exports Generation
(GWh) (GWh) (GWh) Shedding (GWh) (GWh) Not Utilized
(GWh) (GWh)
Counterfactual
Low 12178.4 17538.2 554.6 10550.4 6440.3 526.0 8096.9
Base 19305.1 18635.9 740.2 9452.7 4462.7 4391.7 12869.9
High 26610.3 24551.4 1332.6 3537.2 3698.9 4425.2 18596.7
All MCC Projects
Low 20275.3 21929.0 592.4 6159.6 9236.1 6990.0 0.0
Base 31710.2 25138.3 946.7 2950.3 9790.5 15415.7 464.83
High 35744.6 25293.9 1138.7 2794.7 3522.2 12834.1 9462.4

Impact of Different Demand Scenarios


The original cases prepared for the technical benefits study use a constant rate of 7.5% per year to
forecast the growth in Nepal’s demand. Two additional demand scenarios were considered for the
counterfactual and all MCC project cases to determine the impact of changes in the demand forecast
on the technical benefit results. The first scenario is a low demand growth scenario that uses a
constant growth rate of 5% per year. The second scenario is a high demand growth scenario that uses
a constant growth rate of 10% per year.

Tables 3.27 and 3.28 contain the annual energy figures for the demand sensitivity scenarios along with
the base technical benefit results for 2023 and 2030, respectively. The results from the demand
sensitivity study show that load shedding increases as the demand growth rate increases.
Furthermore, annual imports increase as the growth rate increases and annual exports decrease as
the growth rate decreases. These results were expected because as the demand increases, more of
Nepal’s generation must be used to supply the increasing demand and less is available for export to
India.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 174

Table 3.27 Annual Energy Figures for the Demand Sensitivity Study for 2023
Scenario Annual Annual Annual Annual Annual Annual Annual
Supply Consumption Loss Load Imports Exports Generation
(GWh) (GWh) (GWh) Shedding (GWh) (GWh) Not Utilized
(GWh) (GWh)
Counterfactual
Low 12086.0 12576.3 361.6 3182.4 3411.2 2559.2 8616.1
Base 12219.6 12986.5 377.0 3924.8 3571.1 2427.2 8482.5
High 12328.5 13258.6 365.1 4860.3 3570.7 2275.5 8373.5
All MCC Projects
Low 20702.1 14449.8 330.0 1308.9 4084.1 10006.4 0.0
Base 20702.0 15349.6 351.7 1561.7 4670.0 9670.8 0.1
High 20702.1 16298.7 372.9 1820.1 5367.5 9398.0 0.0

Table 3.28 Annual Energy Figures for the Demand Sensitivity Study for 2030
Scenario Annual Annual Annual Annual Annual Annual Annual
Supply Consumption Loss Load Imports Exports Generation
(GWh) (GWh) (GWh) Shedding (GWh) (GWh) Not Utilized
(GWh) (GWh)
Counterfactual
Low 18703.9 18881.4 752.5 6089.5 5242.5 4312.5 13471.1
Base 19305.1 18635.9 740.2 9452.7 4462.7 4391.7 12869.91
High 19924.6 20690.6 826.3 10819.6 5365.2 3772.9 12250.4
All MCC Projects
Low 31452.4 22708.0 852.8 2262.9 8293.5 16185.1 722.6
Base 31710.2 25138.3 946.7 2950.3 9790.5 15415.7 464.8
High 32074.1 27668.0 1081.4 3842.2 11255.8 14580.5 100.9

Impact of Reduced Interchange with India


The results from the MCC scenarios study indicate that the XB1 tie line project has the greatest impact
on reducing load shedding in Nepal. Cases including all MCC projects were run a second time with XB1
out of service to determine the impact of XB1 on the study results.

Tables 3.29 and 3.30 contain the annual energy figures for the XB1 sensitivity scenario along with the
base technical benefit results for 2023 and 2030, respectively. The results demonstrate that XB1 has
a significant effect on reducing both annual load shedding and generation not utilized.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 175

Table 3.29 Annual Energy Figures for the XB1 Sensitivity Study for 2023
Scenario Annual Annual Annual Annual Annual Annual Annual
Supply Consumption Loss Load Imports Exports Generation
(GWh) (GWh) (GWh) Shedding (GWh) (GWh) Not
(GWh) Utilized
(GWh)
Counterfactual 12219.6 12986.5 377.0 3924.8 3571.1 2427.2 8482.5
All MCC Projects 20702.0 15349.6 351.7 1561.7 4670.0 9670.8 0.1
All MCC Projects 18066.4 13687.3 276.7 3224.1 2951.3 7053.7 2635.7
Except XB1

Table 3.30 Annual Energy Figures for the XB1 Sensitivity Study for 2030
Scenario Annual Annual Annual Annual Annual Annual Annual
Supply Consumption Loss Load Imports Exports Generation
(GWh) (GWh) (GWh) Shedding (GWh) (GWh) Not
(GWh) Utilized
(GWh)
Counterfactual 19305.1 18635.9 740.2 9452.7 4462.7 4391.7 12869.91
All MCC Projects 31710.2 25138.3 946.7 2950.3 9790.5 15415.7 464.8
All MCC Projects 25438.2 20840.0 584.1 7248.6 5241.0 9255.1 6736.9
Except XB1

Based on above two tables, the study reveals that the XB1 project itself is critically important for all
MCC projects. With XB1 and all other MCC projects, annual load shedding (GWh) will reduce further
to 40% of the base case level compared with 82% of the base case level without XB1 in 2023, and to
31% of the base case level compared with 77% of the base case level without XB1 in 2030.

With XB1 and all other MCC projects, generation utilization will increase to 170% of the base case level
compared with 148% of the base case level without XB1 in 2023, and to 164% of the base case level
compared with 132% of the base case level without XB1 in 2030.

In addition, the technical benefit study was completed for NR1 +XB1 with 0.85 Power Factor. The
effect of power factor on system losses are negligible since the lines are not heavily loaded.

Original results:
Scenario Annual Annual Annual Annual Annual Annual Annual
Supply Consumption Loss Load Imports Exports Generation
(GWh) (GWh) (GWh) Shedding (GWh) (GWh) Not Utilized
(GWh) (GWh)
All 31710.2 25138.3 946.7 2950.3 9790.5 15415.7 464.8
Projects
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 176

Results with 0.85 power factor cases:


Annual Annual Annual Annual Annual Annual Annual
Supply Consumption Loss Load Imports Exports Generation
(GWh) (GWh) (GWh) Shedding (GWh) (GWh) Not Utilized
(GWh) (GWh)
All MCC 31755.8 24327.3 1021.1 3761.3 9816.4 16223.9 419.2
Projects

3.1.9 Power System Assessment Conclusion

Table 3.31 Power System Assessment Results


Project Study Results or Justifications
400 kV East-West NR1 project is the backbone transmission network; it enhances the Nepal
Transmission Trunk network’s transmission capacity. It provides the transmission backbone to transfer
Line - NR1 the remote energy to load centers and import/export energy from/to India.
XB1 XB1 is critically important within all MCC projects. It doubles the energy exchange
capability between Nepal and India. It greatly reduces the load shedding
requirement due to the increasing import capability, and greatly increases
generation utilization due to the increasing export capability.
T2’, T3, NR3, and NR4 T2’, T3, NR3, and NR4 are remote transmission projects. These projects enhance
the remote area transmission capacities, therefore, to accommodate increasing
remote generation projects.
T8 T8 is a dedicated transmission line project that will provide the transmission
network for the 900 MW Upper Karnali HPP generation project in which around
12% of project capability will be excavated by NEA.

3.2 Transmission Lines and Substations – Detail Feasibility Assessment

3.2.1 NR1: Transmission Lines

The 400 kV East-West Transmission Backbone trunk line project will develop a new 270 km, 400 kV
double-circuit transmission line through hilly regions in central Nepal. The route for the first section
of the line is through New Hetauda – Naubise - New Damauli - New Butwal and the second section will
run from Naubise to Lapsiphedi.

The lengths of each section of transmission lines are:


 New Butwal substation to New Damauli substation – 84 km
 New Damauli to Naubise substation – 98 km
 Naubise Substation to New Hetauda substation – 41 km
 Naubise substation to Lapsiphedi – 48 km.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 177

Data Gathering Results


Data were collected from NEA managers of past and current projects, local consultants and
contractors, and World Bank and ADB employees:
 400 kV standard tower drawings
 Transmission line projects that are designed to connect to proposed substations in NR1
 Future requirements at all proposed substations in NR1
 Environmental and climatic data along the proposed transmission line and substations.

Site Visit Findings and Observations


We conducted site visits along the NR 1 route via helicopter. The proposed route goes through small
villages, agricultural land and over very hilly terrain. The crops grown in this area are mainly rice and
potatoes. The route also goes over some houses scattered over the hills. A section of the route passes
over forest land, which varies from dense vegetation to treeless patches. There is also a possibility
that the line would pass through grazing and pasture land. Nine river crossings were observed along
the route. The land near New Butwal substation is dry and flat.

The routing of this transmission line was difficult because of its hilly terrain. We tried to avoid steep
slopes, but they still can be found at some locations. In such situations the terrain commanded shorter
spans and thus required more towers. Detail designs of these lines (and all other lines in hilly terrain)
need to consider all of these problems and avoid such a harsh centerline. Line routing in the detailed
design stage (unlike in the detailed feasibility stage) will start with survey data that will have to come
from either a LiDAR survey or detailed land survey. Airborne LiDAR surveys have advantages such as
covering a wider corridor (which greatly facilitates the upcoming desktop routing practice), fast
operation and high accuracy levels, and hence is the preferred method. Furthermore, the airborne
LiDAR survey is more cost effective and more economical for long spans.

Survey data in the detailed design stage should include very precise information about ground points
in good density which will be suitable for detailed design. All the obstacles such as side slopes, trees
and their heights, existing transmission lines, roads with an identification of their class and width,
structures with type identifications, etc. will be labeled (this action is called feature coding). A desktop
line routing based on this survey data can avoid many problems. Furthermore, a detailed site
walk/drive down will eliminate the remaining problems. The final line route emerging from this
exercise will guarantee a smooth, efficient and cost-effective line spotting.

Assessment of Utilized Material in Existing Facilities


We collected data on existing transmission lines in Nepal from NEA, local engineering consulting
companies, and local contractors. This includes information on existing transmission line networks in
Nepal, the structure types used on these lines, the materials used, and their performance quality:
 Conductors
 Insulators
 Overhead shield wires
 Optical fiber ground wires
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 178

 Insulator string fittings


 Structure number boards
 Aerial markers.

Material used in 400 kV East-West Transmission Trunk Line


Full specifications of the materials used in the 400 kV east-west transmission trunk line are presented
in various specification documents in Annex D.

3.2.2 New Hetauda Substation

The New Hetauda 400 kV-220 kV substation is planned to be constructed adjacent to a 220 kV
substation that is under construction by the World Bank.

The substation will contain the following:


 2 x 400 kV bays for lines to Naubise
 2 x 400 kV bays for lines to Dhalkebar
 3 x 3 phase, 400 kV-220 kV, 160 MVA power transformers*
 Space for 2 x 3 phase, 400 kV-220 kV, 160 MVA future power transformers
 Space for 2 future 400 kV bays for lines to Budhi Gandaki.

* As per the due diligence report, 2 x 320 MVA transformers are to be provided at this station.
However, based on the site access constraints, the capacity of the power transformer is recommended
to be limited to 160 MVA. Also, based on the power system assessment results, only 3 x 160 MVA
transformers are required to meet the design criteria requirements (N-1).

The control building at this substation needs to house the following P&C and SCADA panels:
 18 protection panels
 9 control/mimic panels
 2 SCADA/RTU panels
 3 communication/teleprotection panels
 5 spare/dummy panels
 1 dynamic disturbance recorder.

New Hetauda Site: Option 1


The substation layout is presented in drawing 1661550400-DWG-E00011. The 400 kV switchgear is an
indoor GIS type with a breaker-and-a-half scheme. The 220 kV yard is AIS with a mixed double bus-
single breaker and transfer bus scheme. The new 220 kV bus bars are designed to be connected to the
220 kV bus bar of the adjacent 220 kV station. The 220 kV bus extensions are positioned for easy
installation and to connect two future 400 kV-220 kV, 160 MVA transformers.

1
These drawings are submitted as separate files owing to their large size (on average, over 250 MB).
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 179

The red polygon in Figure 3.36 shows the space reserved by NEA for the 400 kV extension. As can be
seen, the space required for the 400 kV extension is larger than the reserved space. As such, in order
to position the 400 kV extension immediately beside the 220 kV substation, the following work/actions
need to be completed:
 Re-routing of the east/west road north of the 220 kV substation as well as the north/south
road west of the 220 kV station
 Relocation of the residents within the area to be occupied by the 400 kV extension
 Demolition and relocation of the living quarters and office building already constructed in the
area available for the 400 kV extension
 Relocation of the water pond and ditch located in the area available for the 400 kV extension.

Figure 3.36 Overlay of the Available Space and the Design of the 400 kV Extension

New Hetauda Site: Option 2


Figure 3.37 presents an alternate substation placement considered in order to avoid relocation of the
residents to the west of the 220 kV substation. In this option, the 400 kV substation is constructed on
empty farmlands to the northwest of the 220 kV substation and the two substations are connected
through a double circuit, 220 kV transmission line. The analysis of the solution reveals the following:

 Requires the purchase of additional land when considering the 220 kV interconnection buses
and the transmission lines right of ways
 Purchasing the land for the transmission line right of way could potentially lead to the
relocation of some of the residents on the west side of the 220 kV station
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 180

 Potential for population unrest caused by the use of additional land and the perception of
poor project planning driven by the construction of two separate substations in close
proximity.

Given the substantial higher financial and social impact, this option is considered less feasible and
hence will not be pursued further.

Figure 3.37 Alternate Substation Placement Explored for New Hetauda

The location as shown in option 1 above was selected as the final site location. The discussions below
are specific to the selected option.

The civil work consists of realigning the irrigation ditch currently running across the site to the
perimeter of the site. The new ditch will follow the substation perimeter outside the fenced area and
then reconnect to the original alignment downstream to the west of the station. The topsoil (1 m
deep) inside the fenced area needs to be removed and backfilled with engineered fill in order to
stabilize the yard area. The top layer needs to be finished with electrical insulation stone while
maintaining a slope of 2 to 3% throughout the site. The existing conditions for this site are shown in
drawing 1661550400-DWG-C0001, while the final site grading and drainage plan are shown in drawing
1661550400-DWG-C0002.

The perimeter fence is composed of a compound wall with a barbed fence on top as well as one swing
gate for site access. A new access road into the substation from the E-W Highway needs to be
constructed and finished with sub base, base, and asphalt layers (see typical details in drawing 705-
1661550400-C-703) to handle heavy truck loads. The staff quarters need be connected to a water
supply system consisting of a water treatment system. The wastewater from the staff quarters is to
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 181

be collected and treated in a septic tank and septic bed system.

In conclusion, the analysis above reveals that it is feasible to build the 400 kV extension beside the
220 kV station if more land is purchased. The scope of supply will consist of the construction of the
440 kV extension as well as the extension of the 220 kV bus within the existing station.

3.2.3 Naubise Substation

The new 400kV-220kV Naubise substation is considered to contain:

 2 x 400 kV bays for lines to New Damauli


 2 x 400 kV bays for lines to New Hetauda
 2 x 400 kV bays for lines to Lapsiphedi
 2 x 220 kV bays for lines to Marsyangdi
 2 x 220 kV bays for lines to Matatirtha
 3 x 3 phase, 400 kV-220 kV, 160 MVA power transformers*
 Space for 2 x 3 phase, 400 kV-220 kV, 160 MVA future power transformers
 Space for 4 x 220 kV bays for lines to be constructed by IPPs.

* As per the due diligence report, 2 x 315 MVA transformers are to be provided at this station.
However, based on the site access constraints, the capacity of the power transformer is recommended
to be limited to 160 MVA. Also, based on the power system assessment results, only 3 x 160 MVA
transformers are required to meet the design criteria requirements (N-1)..

The control building at this substation needs to house the following P&C and SCADA panels:
 34 protection panels
 14 control/mimic panels
 2 SCADA/RTU panels
 3 communication/teleprotection panels
 5 spare/dummy panels.
 1 dynamic disturbance recorder.

The substation layout is presented on drawing 1661550400-DWG-E0100. The substation footprint is


optimized using a combination of strain and rigid bus at three different elevations to achieve the
breaker-and-a-half scheme. In order to further optimize the footprint use, all gantries are oriented in
order for the 400 kV lines to enter from the north and for the 220 kV lines to enter from the south. As
a result, only one bay of the two bay breaker-and-a-half arrangement is connected for the 400 kV
New-Hetauda lines. In order to maintain a similar level of reliability to that originally planned, an
additional breaker is added to connect the line bay to the second bus. This results in a double-bus
double breaker connected line bay arrangement that can be expanded to a breaker-and-a-half
arrangement by adding a third breaker and the associated disconnect switches.

Figure 3.38 presents the two locations considered for the Naubise station. The red polygon shows
the original location selected while the green polygon shows the final substation position.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 182

Figure 3.38 Planned Location (Red) and Selected Location (Green) for Naubise Substation – Latitude
27º44’0.12”N Longitude 85º6’59.63”E

Naubise Site Option 1 (Original Position)

The AIS substation is designed in order to allow its construction within the available land for Option 1
(207 m x 530 m).

This option was rejected following a more in-depth civil investigation. According to the civil analysis,
there is an elevation difference of approximately 60 meters between the highest and lowest points
of the station. A two step terrace design was studied but ruled out. In fact, the terrace design led to
increase the width of the station from 200m to 400m which also increased the civil and electrical
construction costs. The increased width was required in order to provide appropriate transition
distances between the different flat segments. It was not feasible to simply provide a retaining wall
given the 30m elevation difference between flat segments. A 3 to 1 slope was provided for slope
stability as per good engineering practices.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 183

Tetra Tech’s civil engineer went to site to further investigate and determine if the substation position
could be improved further. During the walkdown, the engineer was able to identify an area west of
the original position that was flatter and more favorable.

Naubise Site Option 2 (Final Position)


The final site location presents manageable elevations. However, the land is not already purchased
and parts of it are occupied. The land will need to be purchased and residents relocated.

There were flatter section to the north and south of the current location, so a split in the station to
the north and south with an access road in the middle was considered as an option. However during
the site visit it was noticed that an existing 132Kv transmission line was passing through the north
section of the split which rendered expansion to the north unfeasible.

The civil design consists of installing a retaining wall (1000 m long) around the perimeter of the site in
order to retain the excess backfill from the excavation at higher elevations and the new engineered
fill, which will be imported to create a relatively flat site. The topsoil (1.5 m deep) inside the fenced
area has to be removed and backfilled with engineered fill in order to achieve a good stable yard area.
The top layer has to be finished with electrical insulation stone and the final site grading has to have
a slope of 2 to 3% throughout the site. The existing conditions for this site are shown in drawing
1661550400-DWG-C0100 and the final site grading and drainage plan are shown in drawing
1661550400-DWG-C0101.

The existing access road into the station from Prithvi Highway is a mud access road that is not able to
withstand the load of the heavy trucks transporting the transformers. The road will be strengthened
by the addition of base and asphalt layers and by increasing its width to 6 m. The staff quarters has to
be connected to a water supply system which will also consist of a water treatment system. The
wastewater from the staff quarters will be collected and treated in a septic tank and septic bed system.
The yard and the staff quarters will be secured by installing a masonry wall and fence on top. A
perimeter fence will be installed on top of the retaining wall to restrict access into the site.
27°44'03.0"N 85°07'05.0"E

3.2.4 New Damauli Substation

The New Damauli 400 kV-220 kV substation is considered to contain:

 2 x 400 kV bays for lines to Naubise


 2 x 400 kV bays for lines to New Butwal
 4 x 3 phase, 400 kV-220 kV, 160 MVA power transformers*
 Space for 2 x 3 phase, 400 kV-220 kV, 160 MVA future power transformers
 Space for 2 x 400 kV bays for future line bays
 Space for 2 future 220 kV bays for lines to Lekhnath
 Space for 4 future 220 kV bays for lines from IPPs.
* As per the due diligence report, 2 x 315 MVA transformers are to be provided at this station.
However, based on the site access constraints, the capacity of the power transformer is recommended
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 184

to be limited to 160 MVA. Also, based on the power system assessment results, 4 x 160 MVA
transformers are required to meet the design criteria requirements (N-1).

The control building at this substation needs to house the following P&C and SCADA panels:
 24 protection panels
 12 control/mimic panels
 2 SCADA/RTU panels
 3 communication/teleprotection panels
 5 spare/dummy panels.
 1 dynamic disturbance recorder.

The yellow polygon in Figure 3.39 shows the space reserved for the substation. The available space is
an L-shaped area of 49 000m2 where the flat land is adequate for building a substation.

The substation layout is presented on drawing 1661550400-DWG-E0200. The 400 kV switchgear is


indoor GIS type with breaker-and-a half scheme. The 220 kV yard is AIS with breaker-and-a half
scheme. All 220 kV circuits are considered as part of the project scope. As such, only two of the three
breakers are provided for each breaker-and-a half diameter. The two breakers are provided in order
to allow connection to both buses.

Figure 3.39 Planned Location for New Damauli Substation – Latitude 27º58’4.80”N Longitude 84º17’37.11”E
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 185

The civil work involves removing the topsoil (1.5 m deep) inside the fenced area and backfilling with
engineered fill in order to achieve a good stable yard. The top layer has to be finished with electrical
insulation stone and the final site grading has to have a slope of 2 to 3% throughout the site. A new
430 m access road into the substation has to be built from the Chabdi Temple Road. This road has to
be finished with a sub base, base and asphalt layers (see typical details in Annex C) in order to handle
heavy truck loads. The existing conditions for this site are shown in drawing 1661550400-DWG-C0200
and the final site grading and drainage plan are shown in drawing 1661550400-DWG-C0201.

The new access road crosses a 6 m wide and 1.5 m deep stream. A system of culverts has to be installed
to handle the peak flows up to 1.5 m3/s where the road crosses the stream. The design plan details
for this road crossing are shown in drawing 1661550400-DWG-C0202.

The staff quarters must be connected to a water supply system that will consist of a water treatment
system. The wastewater from the staff quarters has to be collected and treated in a septic tank and
bed system. A perimeter compound wall and fence along with an access gate also have to be installed
around the substation to restrict the access to the site.

3.2.5 New Butwal Substation

The New Butwal 400 kV-220 kV substation is planned to be constructed adjacent to a 220 kV
substation that is under the ADB’s scope.

The substation is considered to contain the following:


 2 x 400 kV bays for lines to New Damauli
 2 x 400 kV bays for lines to the Indian border
 5 x 3 phase, 400 kV-220 kV, 160 MVA power transformers*
 Space for 2 x 3 phase, 400 kV-220 kV, 160 MVA future power transformers
 Space for 4 future 400 kV bays for lines to Kohalpur-Kaligandaki
 Space for 2 future 400 kV bays for lines to Gorakhpur India Border.

* As per the due diligence report, 2 x 315 MVA transformers are to be provided at this station.
However, based on the site access constraints, the capacity of the power transformer is recommended
to be limited to 160 MVA. Also, based on the power system assessment results, 5 x 160 MVA
transformers are required to meet the design criteria requirements (N-1).

The control building at this substation needs to house the following P&C and SCADA panels:
 24 protection panels
 6 control/mimic panels
 2 SCADA/RTU panels
 3 communication/teleprotection panels
 5 spare/dummy panels.
 1 dynamic disturbance recorder.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 186

The substation layout is presented in drawing 1661550400-DWG-E0900. The 400 kV and 220 kV
distributions are achieved by AIS. A 220 kV bus is provided in order to connect ADB’s 220 kV substation
to the 400 kV-220 kV substation. It is recommended that, in order to reduce the cost of the station,
that ADB’s 220 kV substation be designed starting from the secondary of the 400 kV-220 kV
transformers. This would allow removing the additional 220 kV bus that is redundant and reduces the
reliability of the system. It is also possible to extend the 220 kV bus to a breaker-and-a half scheme if
the appropriate breaker configuration is designed within ADB’s 220 kV substation. This allows a high
level of reliability to be maintained at the 220 kV side while re-using the bus that is already provided.

Upon completion of the projects under review in this study, there will be three lines interconnecting
Nepal to India; the existing tie line between Dhalkebar and Muzzaffarpur , the power flow controlled
dedicated tie line T8 between New Lamki and the Indian border, and XB1, the tie line proposed
between New Butwal and Gorakhpur. Depending on the system conditions at the interconnection
points, it is possible that one of the tie lines operates in energy export mode while another is operating
in energy export mode, therefore creating a loop flow between the two countries. These loop flows
are undesirable and need to be avoided. Since no detailed model is available for the Indian power
network at present, it is not possible to conduct simulations that can highlight potential loop flows. It
is therefore recommended that a complete model be obtained and that the potential for loop flows
between Nepal and India be studied at the detailed design stage.

However, the solutions listed below should be reviewed during detail design stage:
 Phase shifting transformer
 Back-to-back HVDC
 Flexible AC Transmission Systems (FACTS) devices.

The purple polygon in Figure 3.40 shows the space reserved by NEA and already acquired by ADB for
the 400 kV-220 kV substation, while the green polygon shows additional land available that has to be
purchased. Given that no information is available on the ADB 220 kV substation, it his assumed that it
will be constructed besides the 400-220 kV substation and that it will have an approximate dimension
of 120 m x 180 m. The approximate dimension is based on other 220 kV AIS stations that have been
designed as part of this project.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 187

Figure 3.40 Available Land for the New Butwal Substation – Latitude 27º34’35.25”N Longitude 83º41’25.62”E

At present, a 132 kV transmission line is situated in the middle of the selected site location (see Figure
3.41). According to the local experts consulted, the line will be redirected to avoid the station. If the
project goes forward, it is crucial that the relocation of the 132 kV line be completed before any work
can be started on the construction of the New Butwal substation.

Figure 3.41 132 kV Line on Future Site for New Butwal Station
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 188

The civil design consists of excavation and backfill of the existing soil to achieve a final site grading
with a slope of 2 to 3% throughout the site. The topsoil (1.5 m deep) inside the fenced area has to be
removed and backfilled with engineered fill in order to achieve a good stable yard area and the top
layer has to be finished with electrical insulation stone. The existing conditions for this site are shown
in drawing 1661550400-DWG-C0300 and the final site grading and drainage plan are shown in drawing
1661550400-DWG-C0301. There is a stream running through the site that will be backfilled inside the
substation and will be redirected to bypass the new substation.

A new access road into the substation has to be built from the E-W highway located to the north of
the site, and this will be finished to handle heavy truck loads. The staff quarters have be connected to
a water supply system, which also consists of a water treatment system. The wastewater from the
staff quarters must be collected and treated in a septic tank and bed system. A perimeter compound
wall and fence along with an access gate will also be installed around the substation to restrict the
access to the site.

3.2.6 Lapsiphedi Substation

Lapsiphedi is a 400 kV-220 kV substation planned to be constructed adjacent to a 220 kV substation


that is in ADB’s scope.

 2 x 400 kV bays for lines to Naubise


 2 x 400 kV bays for lines to Barabise
 9 x 400 kV-220 kV, 55 MVA single phase transformers*
 Space for 3 future 400 kV-220 kV, 55 MVA single phase transformers (future).
* As per the due diligence report, 2 x 275 MVA transformers are to be provided at this station.
However, based on the site access constraints, the capacity of the power transformer is recommended
to be limited to single phase 55 MVA. Also, based on the power system assessment results, 3 x 165
MVA transformers (3 x 55 MVA single phase transformers) are required to meet the design criteria
requirements (N-1).

The control building at this substation needs to house the following P&C and SCADA panels:
 18 protection panels
 6 control/mimic panels
 2 SCADA/RTU panels
 3 communication/teleprotection panels
 5 spare/dummy panels
 1 dynamic disturbance recorder.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 189

The red polygon in Figure 3.42 shows the space reserved for the substation. The available space is a
rectangle at the bottom of a valley that has dimensions of 70 m by 140 m. At present, there is no
information on the location of ADB’s 220 kV substation. It is therefore assumed that the substation
will be constructed beside the 400 kV-220 kV substation and that they will be connected via
underground 220 kV cables.

Figure 3.42 Available Land for Lapsiphedi Substation – Latitude 27º44’42.44”N Longitude 85º30’33.03”E

The substation layout is presented in drawing 1661550400-DWG-E0400. The 400 kV switchgear is


indoor GIS type with breaker-and-a half scheme. 220 kV cable termination structures are provided on
the 220 kV side of the power transformers. The 400 kV gantries for the Barabise lines are installed on
the outside of the substation fence in the inclined area in order to minimize the total substation
footprint.

The civil work involves removing topsoil (1.5 m deep) inside the fenced area and then backfilling with
engineered fill in order to achieve a good stable yard area. The top layer has to be finished with
electrical insulation stone and the final site grading has to have a slope of 2 to 3% throughout the site.
Since the site is in a valley, a retaining wall will be installed all around the perimeter of the site to
protect from any potential slope failures. The existing conditions at this site are shown in drawing
1661550400-DWG-C0400 and the final site grading and drainage plan is shown in drawing
1661550400-DWG-C0401.

The existing access road to the site from Sankhu- Bhotechour road is a narrow mud road that cannot
handle heavy truck loads. Therefore, the existing road from the village to the site (approximately 2.1
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 190

km) will be upgraded and expanded to a 6 m wide asphalt roads in order to carry heavy loads towards
the station. The existing road plan and details is shown in drawing 1661550400-DWG-C0402.

A new access road into the substation has to be built from this upgraded road, which will also be
finished to handle heavy truck loads. The staff quarters have be connected to a water supply system
which also consists of a water treatment system. The wastewater from the staff quarters must be
collected and treated in a septic tank and bed system. A perimeter fence has to be installed on top of
the retaining wall to restrict the access into the site.

3.3 NR3: Ilam-Inaruwa 132 kV Transmission Line and Substations

3.3.1 Transmission Lines

The NR 3 Ilam substation to Inaruwa substation project is the development of a new 110 km, 132 kV
double-circuit transmission line through hilly regions in eastern Nepal. The route for the first section
of the line goes north of Inaruwa substation to an area called Dharan and then east towards Ilam
through hilly terrain.

The due diligence report provided two proposed options for the first section of the line between
Dharan and Inaruwa. As per our assessment, a hybrid route between options 1 and 2 is the most
feasible route since it avoids most of the forest area on the one hand and large river of Koshi on the
other.

We conducted site visits along the proposed NR 3 route, which goes through flat land between
Inaruwa and Dharan, passing through small villages, agricultural land and some vegetated lands. From
Dharan to Ilam, the route goes through hills and mountains at a height of approximately 2000 ft. It is
observed that the main crops grown in this area are rice and tea plantations. Approximately two river
crossings were observed along the route. The Ilam substation is located in a valley surrounded by huge
mountains.

The routing of the 132 kV transmission line has been difficult between Dharan region and Ilam
substation because of hilly and sloping terrain. Although we have avoided the steep slopes as much
as possible, this problem still exists, but is expected to be avoided in detailed design stage.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 191

Data Gathering Results


We have collected data from various sources and site visits, as well as meetings with NEA employees
(managers of past and current projects, local consultants and contractors), and employees of the
World Bank and Asian Development Bank. We collected the following data:
 132 kV standard tower drawings
 Transmission line entering into the current Ilam and Inaruwa substations
 Future proposed transmission lines required to connect to these existing substations
 Environmental and climatic data along the proposed transmission line and substations.

Site Visit Findings and Observations


During the site visit, we learned that Ilam is an existing 132 kV/33 kV substation and Inaruwa, which
is under construction, will be a 220 kV/ 132 kV substation.

Material used in 132 kV Ilam - Inaruwa Transmission Line


Full specifications of the material used in 132 kV Ilam - Inaruwa transmission line have been presented
in various specification documents in Annex D.

3.3.2 Ilam Substation

Two 132 kV bays for new lines have to be added to the existing 132 kV/33 kV/11 kV substation. A
satellite picture of the substation is presented in Figure 36. The new 132 kV line is to enter from the
north of the substation.

At present, no electrical arrangement layouts are available for Ilam station. However, according to the
site visit previously conducted, there is sufficient land in the northern part of the substation to add
the required equipment for two additional 132 kV line bays.

Given the fact that no layout is available to create the bill of material, the required material for Ilam
is estimated to be the same as for Inaruwa.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 192

Figure 3.43 Existing Ilam Substation – Latitude 26º52’36.3”N Longitude 87º55’32.7”E

This substation expansion requires two protection panels, two control/mimic panels, modification of
the busbar protection panel (if any), a new fiber patch panel to terminate the new overhead line
OPGW signal cable, and modification of the existing SCADA/RTU panel to incorporate new I/O
(input/output) associated with substation expansion. It is assumed that the existing control room has
sufficient space for the addition of these new panels.

3.3.3 Inaruwa Substation

The construction work is in progress for this new 220 kV/132 kV substation. As a part of this project,
two 132 kV line bays are to be added to this substation. Figure 3.44 shows the substation’s location.

The substation layout is provided in drawing 1661550400-DWG-E2200. The layout demonstrates that
it is possible to add two 132 kV line bays to the east of the existing 132 kV bus. The new bays are
modelled on the existing bays to ensure homogeneity in the equipment used within the station.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 193

Figure 3.44 Existing Inaruwa Substation – Latitude 26º36’46.5”N Longitude 87º07’16.7”E

The line bay additions requires two protection panels, two control/mimic panels, modification of the
busbar protection panel (if any), a new fiber patch panel to terminate the new overhead line OPGW
signal cable, and modification of the SCADA/RTU panel to incorporate the new I/O associated with the
substation expansion. It is assumed that the existing control room has space for the addition of these
new panels.

The structural steel and foundation quantities were determined by assuming that the new station
equipment would be supported by steel structures and foundations that are similar to the existing
steel structures and foundations. A significant change in material quantities is not expected as the
drawings used for the steel structure and foundation bill of materials are from the existing Inaruwa
station.

It was confirmed that the foundations are in general conformance with the existing geotechnical
report prepared by Pashupati Drilling & Geo-Technical Services Pvt. Ltd. for the existing substation at
Inaruwa identified the following geotechnical information beneath the existing station:

 Site sits upon a deposit of loose to medium dense silty sand up to six meters deep
 This site is medium risk for soil liquefaction
 The top meter of soil is loose sands or soft clay and is not suitable to support foundations
 Minimum safe bearing capacity at 3 m below grade is 54 kPa for spread footings.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 194

3.4 NR4: Balanch-Attariya 132 kV Transmission Line and Substations

3.4.1 Transmission Line

The NR 4 Balanch substation to Attariya substation project comprises the upgrade of an existing 131
km, 132 kV double-circuit transmission line through hilly regions in western Nepal. This line is currently
strung with single circuit and the MCC project will design a second circuit on the existing tower using
the same single bear conductor. This new circuit will be on the east side of the transmission line.

During our site visits along the NR 4 route, we observed that the existing line goes through hilly terrain
crossing small villages, agricultural land and some vegetated lands. Five river crossings were observed
along the route.

There will be no deviation in design from that in the due diligence report.

Data Gathering Results


Data were collected from various sources and site visits, and meetings with NEA’s managers of the
design and construction of this project.

We collected the following data:


 132 kV standard tower drawings
 Existing transmission line entering into the Attariya and Balanch substations
 Environmental and climatic data along the proposed transmission line and substations

Assessment of Materials Used in Existing Facilities


We collected data on existing transmission lines that are entering into both Attariya and Balanch
substations from NEA, local engineering consulting companies, and local contractors. These data
include:
 Existing 132 kV line with single circuit, composed of lattice steel towers
 There is a single conductor per phase on this line
 There is a single overhead shield wire (OPGW) cable on top of the towers
 Cap and pin type insulators are used on this line.

The line passes through hilly areas and hence the towers should be capable of taking long spans and
have a good variety of body and leg extensions. The line is new and the conductor shiny, indicating
that it was recently strung.

We have not seen the earthing design of the towers, but feel that the earthing must have been difficult
because of the rocky terrain as observed along some parts of the route.

Towers for the Transmission Line


The existing towers on this line are double circuit self-supporting lattice type galvanized steel towers.
The line contains different types from a single family of towers. These include suspension type (DA-
type), angle type (DB & DC-type) and tension type (DD-type).
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 195

As per our assessment and site visit, the towers seem to be in good shape and they were recently
installed. These towers have provisions to support three phases on both side of the towers and one
OHGW/OPGW at the top of the tower.

The outline drawings and specifications of this towers have been prepared and presented in drawing
number 705-1661550400-TS-E3061 in Annex D.

Conductors for the Transmission Line


As per our assessment, the conductor that is currently on this transmission line is a single bear
conductor. The same conductor will be installed on the second circuit of this transmission line. The
specifications for this conductor type are prepared in drawing number 705-1661550400-TS-E3063 in
Annex D.

Insulators for the Transmission Line


As per our assessment, the insulators used on the existing circuit are porcelain type insulators. The
same type of insulators will be used on the second circuit of the transmission line. Unfortunately, we
were unable to find specifications for this insulator type, but general specification of such insulators
are provided in document number 705-1661550400-TS-E3062 in Annex D.

3.4.2 Balanch Substations

One 132 kV line bay is to be added to the existing Balanch substation. Figure 3.45 shows the
substation’s location.

The substation’s layout is shown in drawing 1661550400-DWG-E2400. The layout shows that space to
add a 132 kV bay is available beside the already existing Attariya line bay. The new bay is modelled on
the existing bays in order to maintain homogeneity in the equipment used in the station.

This substation expansion requires one protection panel, one control/mimic panel, modification of
the busbar protection panel (if any), a new fiber patch panel to terminate the new overhead line
OPGW signal cable, and modification of the SCADA/RTU panel to incorporate the new I/O associated
with the substation expansion. It is assumed that the existing control room has space for the addition
of these new panels.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 196

Figure 3.45 Existing Balanch Substation – Latitude 29º41’06.5”N Longitude 80º39’00.5”E

The structural steel and foundation quantities were determined assuming that the new station
equipment would be supported by the same steel structures and foundations as at the Hetauda
station. A significant change in material quantities is not expected as the drawings used for the steel
structure and foundation bill of materials are from the existing Inaruwa station.

3.4.3 Attariya Substations

One 132 line bay is to be added to the existing Attariya substation. Figure 3.46 shows the substation’s
location.

The substation’s layout is shown in drawing 1661550400-DWG-E2600. According to information


obtained from site a walk down, there is no remaining space inside the fence of the substation to add
a 132 kV line bay. However, the land to the south of the station is owned by NEA and the space is
available for expansion. As such, the south fence needs to be moved approximately 10 meters further
south. As a result, the ground grid needs to be extended and additional civil work is required.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 197

Figure 3.46 Existing Attariya Substation – Latitude 28º48’19.4”N Longitude 80º33’11.2”E

The existing substation will be expanded to accommodate new equipment and structures. The civil
design will follow the existing grades and slopes to maintain consistency with the station. This
substation expansion will require one protection panel, one control/mimic panel, modification of
busbar protection panel (if any), a new fiber patch panel to terminate the new overhead line OPGW
signal cable, and modification of the SCADA/RTU panel to incorporate the new I/O associated with the
substation expansion. It is assumed that the existing control room has space for the addition of these
new panels.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 198

3.5 T3: Tadhekani-Kusma 220 kV Transmission Line and Substations

3.5.1 Transmission Line

The T3 Tadhekani substation to Kusma substation project is a new development of approximately 27


km, 220 kV double-circuit transmission line through hilly regions in western Nepal. This line is to
connect new hydro generation plants in the surrounding area of Tadhekani substation to the national
grid. Tadhekani substation’s location is different from that suggested in the due diligence report, as it
must be located at or close to the geographic center of the hydro power generation projects. This
double circuit 220 kV line is so routed to pass near Rahughat substation (or Beni Hub). The route from
Tadhekani substation goes south-east towards Kusma substation through hilly terrain.

A site visit was conducted by air together with MCC/OMCN and its new proposed location was
accepted. Multi-criteria routing was conducted and the optimum route for the transmission line
chosen. The proposed route was finalized (as far as feasibility-level design is concerned) after
considering all environmental, social and engineering factors; the new route will pass close to the
Rahughat substation (or Beni Hub).

Data Gathering Results


We collected data from various sources and site visits, and held meetings with NEA managers, local
consultants and contractors:
 220 kV standard tower drawings
 Existing transmission line entering the Kusma substations
 Information about hydro power generators near the proposed Tadhekani substation’s
location
 Environmental and climatic data along the proposed transmission line and substations.

Assessment of Materials Used in Existing Facilities. We collected some data on new hydropower
generation near the proposed Tadhekani substation site. The substation location selected is close to
the new hydro facilities.

Materials Used in 220 kV Tadhekani – Kusma Transmission Line


Full specifications of the materials used in this transmission line have been presented in various
specification documents in Annex D.

3.5.2 Tadhekani Substation

The Tadhekani 220 kV-132 kV substation is planned to be constructed adjacent to a 132 kV substation
under ADB’s scope.

The substation is considered to contain the following:


 2 x 220 kV bays for lines to Kusma
 2 x, 220 kV-132 kV, 165 MVA transformers (6 x 55 MVA single phase transformers)*
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 199

 Space for one 165 MVA transformer (3 x 55 MVA single phase transformer).
* As per the due diligence report, 2 x 200 MVA transformers are to be provided at this station.
However, based on the site access constraints, we recommend that the capacity of the power
transformer be limited to single phase 55 MVA. Also, based on the power system assessment results,
2 x 165 MVA transformers (6 x 55 MVA single phase transformers) are required to meet the design
criteria requirements (N-1).

The control building at this station needs to house the following P&C and SCADA panels:
 14 protection panels
 5 control/mimic panels
 2 SCADA/RTU panels
 3 communication/teleprotection panels
 5 spare/dummy panels.
 1 dynamic disturbance recorder.

The red polygon in Figure 3.47 shows the space reserved for the substation. The available space has
approximate dimensions of 100 m x 250 m. According to the available information, the land remains
to be acquired.

Figure 3.47 Available Land for Tadhekani Substation – Latitude 28º23’40.4”N Longitude 83º25’04.9”E
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 200

The substation layout is presented in drawing 1661550400-DWG-E0700. The 220 kV switchgear is


indoor GIS type with breaker-and-a half scheme. A bus is provided on the 132 kV of the transformers
in order to connect to ABB’s 132 kV substation. It is recommended that the 132 kV substation designer
use the 132 kV bus provided in the 220 kV-132 kV substation within the designed bus scheme. The
single bus can be incorporated in the design of an appropriate double bus scheme in order to provide
greater reliability.

The control building will house all protection and control, telemetry, SCADA/communication panel,
RTUs, batteries, DC systems, AC systems and battery chargers, etc.

The civil design consists of removing the topsoil (1.5 m deep) inside the fenced area and backfilling
with engineered fill in order to achieve a good stable yard area. The top layer has to be finished with
electrical insulation stone and the final site grading has to have a slope of 2 to 3% throughout the site.
The existing site conditions for this site are shown in drawing 1661550400-DWG-C0700 and the final
site grading and drainage plan is shown in drawing 1661550400-DWG-C0701.

A new access road into the substation has to be built from the existing mud road to the north of the
Myagdi River. This road has to be finished with a sub base, base and asphalt layers (see typical details
in 1661550400-DWG-C702) to handle heavy truck loads. In addition to the new access road, a new
bridge has to be constructed to cross the Myagdi River, this bridge has to have a span of 60 m and the
road has to be 6m wide. The plan details for this road and bridge are shown in drawing 1661550400-
DWG-C0702.

The existing road from Beni to Tadhekani substation is a mud road of 4 m wide that passes through
several river bends where landslides have been observed. This 20 km road has to be upgraded to a 6
m wide asphalt road and the potential landslide locations must be strengthened to prevent landslides.
The existing road plan and details are shown in drawing 1661550400-DWG-C0703.

There are several locations where small streams flow over the road and at these locations a culvert
has to be added. This is required to prevent erosion of the road during major storms. The location of
landslides and river crossings are identified in drawing 1661550400-DWG-C0704.

The staff quarters must be connected to a water supply system that will also consist of a water
treatment system. The wastewater from the staff quarters has to be collected and treated in a septic
tank and bed system. A perimeter compound wall and fence along with an access gate also need to
be installed around the substation to restrict the access to the site.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 201

3.5.3 Kusma Substation

Two 220 kV line bays have to be added to the existing Kusma station. Figure 3.48 shows the
substation’s location.

The substation’s layout is shown in drawing 1661550400-DWG-E2500. The layout shows that space to
add two 220 kV bays is available north of the existing 220 kV bus. The new bays are modelled on the
existing bays in order to maintain homogeneity in the equipment used in the station.

Figure 3.48 Location of Existing Kusma Substation – Latitude 28º14’34.2”N Longitude 83º38’55.8”E
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 202

3.6 T8: Nepal-India Border Line and New Lamki Substation

3.6.1 Transmission Line

The T8 New Lamki substation to the Nepal-India border project is a new development of
approximately 23 km of 400 kV double-circuit transmission line. This line is designed from New Lamki
substation to the Nepal/India border to export 88% of the power generated in the Upper Karnali hydro
generation plant to India and also will be used for importing power from India in dry season.

The route from New Lamki substation goes south-west towards the border. We conducted a site visit
and selected the proposed New Lamki substation’s location. We also reviewed GMR’s line route from
New Lamki substation to the border and found that this is an optimal route. However, a more detailed
study has been conducted to further optimize the route. This line route meets technical,
environmental and resettlement criteria, and hence has been selected as the final feasibility level
design of the line.

Assessment of Existing Facilities


Lamki is a large 132 kV substation that sits on a very large piece of land that has been acquired by NEA.
Currently construction work is going on in the substation to change its busbar design from single to
double. The control building is just large enough for the existing 132 kV facility; there is no room for
extension. Substation operators do not have the skills required to operate a transmission substation
and cannot appreciate even the functions of the existing panels.

This substation’s land can easily accommodate a new 400 kV substation. However, since this station
is surrounded by houses and other structures, taking a double-circuit 400 kV line in and out will
precipitate resettlement and is thus not feasible. Therefore, in coordination with OMCN, we have
selected another location for the new Lamki 400 kV substation. This location is far from populated
land and is closer to existing 132 kV and 400 kV lines. This location will be very convenient for 400 kV
lines for loop-in loop-out connection as the GMR line passes near this location.

Materials Used in T8 New Lamki – Nepal/India Border 400 kV Transmission Line


Full specifications of the material used in this transmission line are presented in various specification
documents in Annex D.

Data Gathering Result


We collected data from various sources and site visits, and held meetings NEA staff of existing Lamki
substation, local consultants and contractors.

We collected the following data:


 400 kV standard tower drawings
 Information on future transmission lines entering into New Lamki substation
 Coordination of the last structure before the border crossing
 Environmental and climatic data along the proposed transmission line and substations.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 203

3.6.2 New Lamki Substation

The new 400 kV-132 kV New Lamki substation is considered to contain:


 4 x 400 kV bays for lines to the India border
 4 x 132 kV bays for lines
 One 400 kV-132 kV, 160 MVA phase shifting transformer*
 Space for 4 future 400 kV bays for lines to Kohalpur/Surkhet and Attariya
 Space for 2 future 400 kV bays for lines to Bareilly.

*GMR, an independent power producer, will be building a dedicated 400 kV line in order to transfer
900 MW of power from Upper Karnali to India. Twelve percent (12%) of this generation has to be
evacuated to Nepal. To control the power flow of 12%, a 132 kV-132 kV phase shifting transformer
will be installed.

Additional spaces for two phase shifting transformers and four 400 kV-220 kV transformers are
provided in order to allow for future expansion of the station.

The control building at this station needs to house the following P&C and SCADA panels:
 26 protection panels
 10 control/mimic panels
 2 SCADA/RTU panels
 3 communication/teleprotection panels
 5 spare/dummy panels.
 1 dynamic disturbance recorder.

The red polygon in Figure 3.49 presents the location considered for the New Lamki substation. The
selected site has sufficient flat land available to fit an AIS station.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 204

Figure 3.49 Available Land for New Lamki Substation – Latitude 28º36’55.5”N Longitude 81º13’39.1”E

A new location for the New Lamki substation, near Pahalmanpur, has recently been proposed by the
secretary of the Ministry of Energy. This new location is shown in Figure 3.50. Upon evaluation, it was
determined to be unfeasible. This location is 32 km away from the original location, which means that
an additional 64 km (line in/line out) of lines would be required.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 205

Figure 3.50 Additional Proposed Location for New Lamki

The substation layout is presented in drawing 1661550400-DWG-E0800. For three of the 400 kV lines,
only one line of the two-line breaker-and-a half diameter is connected. As such, the middle breaker
and a disconnect switch are provided in order to allow connecting to the second bus and to maintain
the reliability of the 400 kV supply. A single bus arrangement is provided for the 132 kV side. A single
bus is deemed sufficient given the fact that the reliability of the link is limited by the fact that only a
single phase shifting transformer is to be provided.

The civil design includes removing the topsoil (1.5 m deep) inside the fenced area and backfilling with
engineered fill in order to achieve a good stable yard area. The top layer will be finished with electrical
insulation stone and the final site grading will have a slope of 2 to 3% throughout the site. The existing
site conditions for this site are shown in drawing 1661550400-DWG-C0800 and the final site grading
and drainage plan is shown in drawing 1661550400-DWG-C0801.

A new access road into the substation from the E-W Highway situated to the south of the site has to
be built and finished to handle heavy truck loads. The staff quarters must be connected to a water
supply system which consists of a water treatment system. The wastewater from the staff quarters
has to be collected and treated in a septic tank and bed system. The substation has to be surrounded
by a compound wall and fence to restrict access into the station.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 206

3.7 T2’: Likhu Hub-New Khimti Transmission Line and Substations

3.7.1 Transmission Line

The T2’ Likhu Hub to the New Khimti project is a new development of approximately 25 km of 220 kV
double-circuit transmission line. This line has been designed to run from Likhu Hub substation to New
Khimti substation. This project will help new hydro generating plants to bring energy into the national
grid. As per our assessment and investigation, there are five registered Likhu hydro projects in the
surrounding area. All of these plants need to connect to the national grid. Therefore, it was decided
that these projects will connect to Likhu substation and will step up the voltage and connect to the
New Khimti substation.

After a comprehensive desktop study, we made a site visit to possible locations for Likhu substation
and the line route to New Khimti substation. As mentioned in the section on substation site selection,
one of the IPPs proposed a location that is close to their power house and substation. Although the
proposed land area is small, this is the only flat land on this scale in the project area, and by choosing
a GIS design for the substation, the substation layout can be accommodated on this land. Based on
this location, the line route was determined in the optimal corridor that was developed using multi-
criteria routing. The line route developed is close to the corridor suggested by the due diligence team.

Data Gathering Results


We collected data from various sources and site visits, and held meetings with IPPs, NEA managers of
past and current projects, local consultants and contractors.

We collected the following data:


 220 kV standard tower drawings
 Information on hydro power plants that need to connect to Likhu substation
 Environmental and climatic data along the proposed transmission line and substations.

Assessment of Materials Used in Existing Facilities


We visited the proposed Likhu substation site, which is at the end of the point of the transmission line
from New Khimti to Likhu Hub substation. We met with the IPP and reviewed their plan for the 132
kV substation. This IPP also has a detailed plan to upgrade the existing roads and build a new road to
this location for shipping their equipment. Aside from this, there is no other facility in the area and no
assessment has been conducted.

Materials Used in T2’ Likhu Hub – New Khimti 220 kV Transmission Line
Full specifications of the materials used in this transmission are presented in various specification
documents in Annex D.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 207

3.7.2 Likhu Hub Substation

The Likhu Hub 220 kV-132 kV substation is planned to be constructed adjacent to a 132 kV substation
under being built by an IPP.

The substation is considered to contain the following:


 2 x 220 kV bays for lines from New Khimti
 3 x 220 kV-132 kV, 165 MVA transformers (9 x 55 MVA single phase transformers) *
 Space for one future, 220 kV-132 kV, 165 MVA transformer (3 x 55 MVA single phase
transformers)
 1 x 132 kV / 11 kV for local distribution / small power evacuation transformer
 Space for 4 future 220 kV bays for lines to Tingla and IPPs
 Space for 2 future 132 kV bays for lines to IPP generators.**

*Based on the site access constraints, the capacity of the power transformer is recommended to be
limited to single phase 55 MVA. Also, based on the power system assessment results, 3 x 165 MVA
transformers (9 x 55 MVA single phase transformers) are required to meet the design criteria
requirements (N-1).

**The number of 132 kV line bays has been reduced to 2 since the IPP is already building the 132 kV
bays in their substation.

The control building at this station needs to house the following P&C and SCADA panels:
 18 protection panels
 6 control/mimic panels
 2 SCADA/RTU panels
 3 communication/teleprotection panels
 5 spare/dummy panels
 1 dynamic disturbance recorder.

Figure 3.52 shows the space reserved for the substation based on discussions with the IPP building
the 132 kV substation. The IPP has agreed to reserve space for the 220 kV-132 kV substation on the
land that they have already purchased.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 208

Figure 3.52 Available Land for Likhu Hub Substation after Discussions with IPP

The substation layout is presented in drawing 1661550400-DWG-E0500. The 220 kV switchgear is


indoor GIS type with a breaker-and-a half scheme. The area available does not allow for the
construction of living quarters and all related buildings. The land available to the north of the IPP’s
132 kV substation will have to be used. The available land is surrounded by the light blue polygon in
Figure 3.53.

A single 132 kV bus with two line bays is provided in the 220 kV substation in order to connect to the
IPP’s 132 kV substation or any other load as required. A single 132kV bus is provided because it is not
possible to build two bus bars in the space provided. At the detailed design stage, it is recommended
to coordinate the design of the 220 kV substation with the IPP’s 132 kV substation in order to optimize
the layout of both stations. With the station layout of the 132 kV station, it might be possible to extend
the existing 132 kV bus in order to add a second bus and optimize the space being used.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 209

Figure 3.53 Available Land for Living Quarters at Likhu Hub

The civil design consists of removing the top layer of loose gravel and then backfilling with excavated
soil from the hill to the west of the station. The top 0.5 m of the substation will be backfilled with
engineered fill in order to achieve a good stable yard area. The top layer needs to be finished with
electrical insulation stone and the final site grading needs to have a slope of 2 to 3% throughout the
site. A retaining wall needs to be built to the west and south of the site to prevent any potential slope
failure. An access road into the substation needs to be built from the 132 kV access road located to
the north of the site. This road will be finished to handle heavy truck loads. The existing conditions at
this site are shown in drawing 1661550400-DWG-C0500 and the final site grading and drainage plan
is shown in drawing 1661550400-DWG-C0501.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 210

The staff quarters need to be constructed to the north of the existing 132 kV station and need to be
connected by a walkway to the new station. They must also be connected to a water supply system
that also consists of a water treatment system. The wastewater from the staff quarters needs to be
collected and treated in a septic tank and bed system. A perimeter fence needs to be installed on top
of the retaining wall to the west and south and on top of a compound wall to the east and north in to
restrict access into the site.

3.7.3 New Khimti Substation

Two new 220 kV line bay are to be added to the existing New Khimti substation. The 220 kV lines are
to be connected to GIS breakers. Figure 3.54 shows the substation’s location.

Figure 3.54 Planned Location for New Khimti – Latitude 27º29’41.7”N Longitude 86º05’54.3”E

The substation layout is shown in drawing 1661550400-DWG-E0600-SH1. Two future bays for lines
are available in the original layout and are now being used for the Likhu hub line. The line will enter
from the north of the station and underground cables will connect the line bays to the GIS breakers.
According to the drawings obtained, the 220 kV GIS will be a double bus – single breaker with bypass
arrangement.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 211

The substation expansion will require two new protection panels, two new control/mimic panels,
modification of the busbar protection panel (if any) to incorporate new line CTs, a new fiber patch
panel to terminate the new overhead line OPGW signal cable, and modification of the SCADA/RTU
panel to incorporate the new I/O associated with the substation’s expansion. We assume that the
control room will have adequate space to accommodate these new panels.

3.8 XB1: New Butwal to Nepal-India Border Transmission Line

3.8.1 Transmission Line

The XB1 New Butwal substation to the Nepal/India border is a new development of an approximately
23 km, 400 kV double-circuit transmission line. This line is to export power to India. The route from
the New Butwal substation goes almost south towards the Nepal-India border.

We recently received information on the border crossing point and revised the line route to approach
this point. For routing of this transmission line, we utilized multi-criteria routing and considered all
environmental, social and engineering factors.

Assessment of Materials Used in Existing Facilities


This line is a new line and no existing facility is found relevant to this line.

Materials Used in XB1 New Butwal – Nepal/India Border 400 kV Transmission Line
Full specifications of the material used in this transmission line are presented in various specification
documents in Annex D.

Data Gathering Results and Site Visit Findings and Observation


The 220 kV substation of New Butwal is an ADB-funded project. We met with ADB and NEA staff for
this project. We understand that the land has been purchased but could not find data for the design
of this substation. However, we did find a land map from NEA’s manager of the 220 kV project.

We collected the following data:


 A land map showing the purchased land and its size. The substation location is not shown on
the land map; however, we located it using information collected during the site visit
 400 kV standard tower drawing
 Information about future transmission lines entering into the New Butwal substation
 Environmental and climatic data along the proposed transmission line and substation.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 212

4. Implementation Schedule
The schedule shown in Annex F represents the proposed timeline for the MCC projects on a month-
to-month basis. The timeline begins when the feasibility study is submitted and runs through to the
end of the compact period (five years from the date of signing). It is assumed that a more detailed
schedule will be developed once the project moves into future phases.

The schedule has been developed in Primavera P6 and Microsoft project. Also, the working file in
Microsoft project is shared in the Annex F.

Please refer to Annex F for Implementation schedule.

4.1 Project Phases

The first phase – project development and planning – consists of the project definition, the compact
negotiation and signing, compact implementation funding, formation of MCA entity, compact entry
into force. This phase is expected to last 18-24 months.

The second phase of the project is for advanced work, which would occur approximately 3 months
into the project, after the approval of MCA board. This phase is expected to take 18 months and would
comprise the following activities:

 Award of engineer; will manage all the following activities


 Preparation of tender documents
 Submission and evaluation of bids.
 Award of turnkey EPC vendor(s)
 Completion of environmental and geotechnical assessments
o Design surveys completed
o Land acquisition
o Permitting.
o Preliminary and Detail Design

The first and second phases are common to all projects. The third phase, implementation, is divided
into the four zones (see below) and consists of the procurement, construction, and commissioning
components of the project. This phase is expected to be 60 months in duration after EIF.

4.2 Implementation Zoning


To accommodate the required timeline, Tetra Tech has proposed that the implementation phase be
divided into four zones, with each being awarded to a single EPC vendor. The zones are defined as
follows (their durations can be found in Annex F).
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 213

The specific projects included for each zones can be found under section 2.8 – Project Procurement
Packaging.

4.3 Duration Assumptions


In order to meet the required timeline certain assumptions during the construction period have been
taken into account, these assumptions are as follows:

Zone A EPC Contractor


 Transmission Line – Foundation Construction - 20 Crews ( or Gangs) consisting of 15-20
workers per crew
 Transmission Line – Foundation Construction - 20 Crews ( or Gangs) consisting of 15-20
workers per crew
 Transmission Line – Stringing - 2 Crews (or Gangs) consisting of 45-50 workers per crew

 Substation – 1 Substation construction crew per station, with all zone stations be
constructed simultaneously

Zone B EPC Contractor


 Transmission Line – Foundation Construction - 5 Crews ( or Gangs) consisting of 15-20
workers per crew
 Transmission Line – Foundation Construction - 5 Crews ( or Gangs) consisting of 15-20
workers per crew
 Transmission Line – Stringing - 1 Crew (or Gang) consisting of 45-50 workers

 Substation – 1 Substation construction crew per station, with all zone stations be
constructed simultaneously

Zone C EPC Contractor


 Transmission Line – Foundation Construction - 8 Crews ( or Gangs) consisting of 15-20
workers per crew
 Transmission Line – Foundation Construction - 8 Crews ( or Gangs) consisting of 15-20
workers per crew
 Transmission Line – Stringing - 2 Crews (or Gangs) consisting of 45-50 workers per crew

 Substation – 1 Substation construction crew per station, with all zone stations be
constructed simultaneously

Zone D EPC Contractor


 Transmission Line – Foundation Construction - 15 Crews ( or Gangs) consisting of 15-20
workers per crew
 Transmission Line – Foundation Construction - 15 Crews ( or Gangs) consisting of 15-20
workers per crew
 Transmission Line – Stringing - 2 Crews (or Gangs) consisting of 45-50 workers per crew
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 214

 Substation – 1 Substation construction crew per station, with all zone stations be
constructed simultaneously

4.4 Schedule Risk and Critical Path


We estimate that the project can be completed within a minimum of 60 months. However, this
assumes that advanced funds are released to complete advanced work prior to implementation phase.
There are a number of risks that may potentially impact this duration. These have been accounted for
by adding additional time to the scheduled activities. Some of the identified risks are:

 Availability and reliability of existing information and studies


 Interface among stakeholders (i.e., MCA, EPC vendors, local governments)
 Availability of materials and labor
 Weather interferences, such as the monsoons.

4.5 Critical Path


The critical path is driven by the Zone A transmission line and in particular the construction of the
tower foundation, the tower erection, and the stringing of the line.

4.6 Project Float


Float has been identified for each of the 4 zones. In addition to the stated float for each of the Zone,
it is our understanding that for projects of this nature permission to construct may be granted during
the monsoon season. Our current timeline assumes no work will occur during this time, thus allowing
up to an additional 8 months of float if access was granted during all years of construction. Excluding
the monsoon season the float for each of the identified zones is as follows:

 Zone A EPC Contractor - ~ 8 Months


 Zone B EPC Contractor - ~ 7 Months
 Zone C EPC Contractor - ~ 7 Months
 Zone D EPC Contractor - ~ 5 Months

** Float is calculated from the time of energization to the end of the compact period
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 215

5. Contract Procurement Packages


Section 2.8 described the methodology used for suggested procurement packages and mentions the
advantages and disadvantages associated with them.

Zone A EPC Contractor


Projects include:
 NR1: Transmission line between New Damauli and Naubise
 NR1: New Damauli substation work
 NR1: Transmission line between New Damauli and New Butwal
 NR1: New Butwal 400 kV substation work (400 kV switchyard, transformers and 400 &
220 kV transformer bays) to connect to ADB’s 220 kV substation
 XB1: Transmission line Between New Butwal substation and Nepal/India border
 T8: New Lamki 400 kV substation
 T8: 400 kV Transmission line between New Lamki substation and Nepal/India border

Zone B EPC Contractor


Projects include:
 T3: 220 kV Transmission line between Tadhekani and Kusma
 T3: 220 kV Tadhekani substation work
 T3: 220 kV Kusma substation upgrade work
 NR4: Adding one circuit to the existing transmission line
 NR4: Upgrading (adding one line bay) to Balanch substation
 NR4: Upgrading (adding one line bay) to Attariya substation

Zone C EPC Contractor


Projects include:
 NR1: Naubise 400 kV substation work
 NR1: 400 kV Lapsiphedi substation upgrade (400 kV switchyard, transformers and 400 &
220 kV transformer bays) to connect to ADB’s 220 kV substation
 NR1: 400 kV New Hetauda substation upgrade (400 kV switchyard, transformers and 400
& 220 kV transformer bays) to connect to WB’s 220 kV substation
 NR1: Transmission line between Naubise to Lapsiphedi
 NR1: Transmission line between Naubise to New Hetauda

Zone D EPC Contractor


Projects include:
 T2’: 220 kV Likhu Hub substation work
 T2’: 220 kV New Khimti upgrade
 T2’: Likhu Hub to New Khimti 220 kV transmission line
 NR3: Upgrading (adding two line bays) to Ilam substation
 NR3: Upgrading (adding two line bays) to Inaruwa substation
 NR3: Ilam to Inaruwa 220 kV transmission line
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 216

Implementation schedule for this packaging have been provided which shows different floats for
different packages depending on their size. In case more float is desired and if lower package capital
cost is preferred an alternative packaging including 5 packages could be suggested. The scope of
packages would be then as per below:

Zone A EPC Contractor:


Projects include:
 NR1: Naubise 400 kV substation work
 NR1: Transmission line between New Damauli and Naubise
 NR1: New Damauli substation work
Zone B EPC Contractor:
Projects include:
 T3: 220 kV Transmission line between Tadhekani and Kusma
 T3: 220 kV Tadhekani substation work
 T3: 220 kV Kusma substation upgrade work
 NR4: Adding one circuit to the existing transmission line
 NR4: Upgrading (adding one line bay) to Balanch substation
 NR4: Upgrading (adding one line bay) to Attariya substation
Zone C EPC Contractor:
Projects include:
 NR1: 400 kV Lapsiphedi substation upgrade (400 kV switchyard, transformers and 400 &
220 kV transformer bays) to connect to ADB’s 220 kV substation
 NR1: 400 kV New Hetauda substation upgrade (400 kV switchyard, transformers and 400
& 220 kV transformer bays) to connect to WB’s 220 kV substation
 NR1: Transmission line between Naubise to Lapsiphedi
 NR1: Transmission line between Naubise to New Hetauda
Zone D EPC Contractor:
Projects include:
 T2’: 220 kV Likhu Hub substation work
 T2’: 220 kV New Khimti upgrade
 T2’: Likhu Hub to New Khimti 220 kV transmission line
 NR3: Upgrading (adding two line bays) to Ilam substation
 NR3: Upgrading (adding two line bays) to Inaruwa substation
 NR3: Ilam to Inaruwa 220 kV transmission line
Zone E EPC Contractor:
Projects include:
 NR1: Transmission line between New Damauli and New Butwal
 NR1: New Butwal 400 kV substation work (400 kV switchyard, transformers and 400 &
220 kV transformer bays) to connect to ADB’s 220 kV substation
 XB1: Transmission line Between New Butwal substation and Nepal/India border
 T8: New Lamki 400 kV substation
 T8: 400 kV Transmission line between New Lamki substation and Nepal/India border
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 217

5.1 Execution of Packages

Data collected from NEA project managers, other donors, consultants and contractors active in Nepal’s
power sector yielded the following observations. The current model of NEA’s execution of a project is
to provide a preliminary design for transmission lines and proceed to the tendering stage with a
preliminary design, select a contractor and leave the rest to the contractor. The contractor’s scope in
this model includes a wide range of activities from the check survey, finalization of line route, land and
right of way acquisition and to project construction. This model has been more or less followed by
other donors; ADB, WB etc., although some of them are changing this approach because of the
problems they have experienced.

Although this model has some advantages, it results in significant changes to transmission line routes
and contract values and quantities. Since the line route is finalized by the contractor, the areas
affected by transmission line rights of way cannot be identified in advance of the contractor’s work.
So resettlement is carried out by the contractor while procurement and construction logistics are
being completed. Resettlement is not easy and requires a long process of official work. Delays in
resettlement introduce major problems to project construction; this is the main reason for almost all
of the transmission line projects not being constructed on schedule or within budget. As a matter of
fact, right of way acquisition and the procurement and construction of works are not of the same
nature and cannot be managed in the same time frame.

Many of our data sources who are active players in the power sector believe that the design should
be developed in more detail before assigning a contractor to the job. However, there are some
concerns with this approach. Lack of confidence in this method can be summarized as:

 Although further design development will help in identifying more land owners who will be
affected by line construction, an incomplete detailed design will not make a real change in
project implementation.
 A long gap between the time owners are compensated and lines are constructed will not really
free up the line right of way and sometimes will attract more people to come and build
structures in the right of way.
 A transmission line check survey is inseparable from the contractor’s construction work. So,
no contractor will take responsibility for construction if the check survey is taken out of the
contractor’s scope.
 Contractors don’t feel ownership for the detailed designs that have been provided by others
and do not have much confidence in a detailed design that has been provided without being
engaged in actual site conditions.
 As far we can determine, construction work goes more smoothly and faster when an EPC
model is adopted.

In these circumstances, it appears that a feasible fusion of the above methods will resolve or minimize
the problems listed here. The method we propose for the MCC compact projects would realistically
combine the advantages of the two methods above while avoiding their disadvantages.
Details and steps of our proposed package execution are as follows:
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 218

 One engineer will be hired to provide services for all MCC compact sub-projects.
 EPC contractors will be hired for sub-projects or zones as defined above. The selection of EPC
contractors should comply with the FIDIC yellow book (design-build) and hence a pre-
qualification process is required.
 EPC contractors must have adequate capacity (either in-house or as a subcontractor or joint
venture) to carry out the Environmental and Social Impact Assessment, Resettlement Action
Plan, and Resettlement Implementation.
 EPC contractors must be capable of conducting full-scale survey works (LiDAR or land survey)
and geo-technical assessments for their respective zones, either by themselves or through
competent subcontractors.
 Pre-qualification of bidders will be conducted for two group of sub-projects. This pre-
qualification will help determine which groups of bidders will be invited to prepare EPC bids
for all the sub-projects and which groups will be invited to Zones B and D tenders only.
 The bidders can bid on multiple zones and successful bidders may be awarded more than one
zone. However, Zone A and Zone C contracts will not be awarded to the same bidder.

The following points justify this set up and note its pros and cons:

 By having two EPC contractors on the design of NR1, there will be some degree of natural
competition between them. Their work will be compared with each other. Innovative
solutions for one package can be used in another package. If an issue arises with one EPC
contractor, there is will be another one as back up. However, intensive coordination is needed
between the EPC contractors in order to maintain consistency in design and remove design
variety. The engineer will play a critical liaison role between the two EPC contractors.
 NR1 has four substations and approximately 280 km of transmission lines, so it is better to
have two EPC contractors work on it. If MCC depends on only one, there is risk of project
delay, compromise on quality and lack of resources. In other words, NR1 is a critical part of
the compact and MCC shouldn’t rely on one contractor. Having two EPC contractors on NR1
provides a plan B in case the first contractor encounters serious problems.
 There is also a risk of poor coordination between the two EPC contractors, which may result
in unwanted design variations between two parts of NR1, XB1 and T8 in terms of different
equipment, ratings and design details. In order to mitigate this risk, the engineer should
provide close oversight on the designs of these two contractors, and their interface.
 Funds of the “E” part and “PC” parts will be released in two stages. “E” funds will be released
(approximately 10% of total the EPC value) in the compact implementation funding (CIF)
period in order to enable the EPC contractor to start working on the “E” portion of the work
(preliminary and detailed design of the respective projects).
 No procurement or construction work is to be done in the CIF stage. However, all the services,
including surveys, geotechnical assessments, preliminary and detailed design, vendor design,
issuing shop drawings by vendors, and issued for construction (IFC) packages shall be
completed by entry into force (EIF).
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 219

6. Results, Conclusions, and Recommendations


In conclusion, all projects included in MCC compact will meet the project objective of decreasing load
shedding, increasing generation utilization and maximize power trade between Indian and Nepal.

The key results / recommendation of power system assessment are following:

 The technical benefit analysis reveals that the XB1 tie line project is of critical importance for
Nepal because it will double the exchange capability between Nepal and India. As a result,
load shedding is greatly reduced and generation utilization is increased. NR1 is also of great
importance as it provides the transmission network backbone that enhances the network’s
transmission capacity. It provides the transmission backbone to transfer remote energy to
load centers and to import/export energy from/to India. In fact, the combined effect of the
NR1 and XB1 projects is a reduction of load shedding to 33% of its original value.
 Based on the short circuit analysis, at least 42 kA breakers are recommended for 132 kV
stations of MCC projects. For the 220 kV and 400 kV levels, the breaker ratings should be at
least 39 kA and 37 kA respectively. Standard breaker ratings shall be selected based on these
requirements.
 The transient stability studies were performed using the dynamic data from NEA for the
existing generating stations and the generic models with typical parameters for the new
generating stations. All possible N-1 contingencies relevant to the MCC projects were
considered in the analysis. The system recovers well after the contingencies and there is no
concern related to the dynamic voltage performance, frequency stability of the
electromechanically oscillations of the generators.
 For the outage of a tie line, it is necessary to have a special protection scheme to trip loads
and generation based on the conditions. A comprehensive study including the India system
would be required to determine the strategy.
 Load shedding in order to have acceptable loading in 400kV/220kV transformers at the New
Butwal substation is recommended. Shedding of about 900 MW of loads on following buses
resulted in acceptable transformer loading: Bharatpu-132, Damauli-132, Butwal-132,
Bairahawa, Shivpur, Hapure, Kusum and Lamhi.
 The power flows provided by WSP included the transmission system (400 kV, 220kV and 132
kV) in detail. Only some parts of sub-transmission system (33kV and 66 kV) was included and
the distribution system was not modelled. Furthermore, most of the loads were directly
placed at the transmission levels busses. It was found that the 132 kV and 66 kV system
included in the model is not capable of supplying the demand expected by 2030. There are
significant number of 132 kV and 66 KV line upgrades identified from the studies.
Furthermore, a significant amount of reactive power compensation at these voltages would
be required. In order to determine the reactive power compensation required at each bus, a
reactive power coordination study needs to be carried out considering proper distribution
feeders. The 66kV and 33 kV network needs to be included and the loads should be placed at
the feeders. It is also necessary to properly model the tap changing transformers with the
voltage regulators. Furthermore, the generators needs to be placed at the right locations
connected with their feeder lines.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 220

 MCC projects are only in transmission and there is no significant impact on the distribution
and sub-transmission systems. The distribution and sub-transmission systems should be
planned such that they are capable of transferring power as well as maintaining voltage. A
condition precedent to EIF could be developed to ensure a distribution master plan is
developed.In the power flow studies the Indian network was not included and the studies
were done considering Thevenin voltage sources at the end of each tie line. The third tie line
is going to be connected for the upper Karnali generation through T8 project and there is a
phase shifting transformer to regulate the 12% of power coming in to the Nepal network.
Therefore, there is no concern about that tie line. However, tie line 1 and tie line 2 (XB1) are
electrically coupled through both India and Nepal. Therefore, the distribution of the total
power exchange between the two tie lines is a concern. The simple model used in this analysis
assumed a 40:60 percent distribution between the two tie lines. The natural distribution of
power can only be identified by modelling the India system in detail (at least northern part of
India). The natural distribution can be controlled to some extent by changing the generation
dispatch. If it is not possible, it would be required to regulate the power transfer of one of the
tie lines by means of one of the followings.
o Phase shifting transformer
o Back to back HVDC
o Thyristor Controlled Series Capacitors (TCSC)
 Another concern would be the interarea electromechanical oscillations between the two
systems during the disturbances. These oscillations can also be controlled by some of the
power regulating devices described above. The tie line power transfer capability also depends
on the strength of the northern part of India at which the tie lines are connected. Therefore,
it would be necessary to perform a more detailed study including the India system in order to
determine the power transfer capabilities and the factors limiting them.
 It is recommended that the loop flow situation within these two tie lines be closely studied
in the detailed engineering stage with details from India’s network.

The key results / recommendation of Substation and Transmission Line design are following:
 The MCC compact consists of 8 new substations, upgrades of 6 existing substations, and
approximately 620 km of transmission lines. The feasibility study demonstrates that difficult
terrain and the size of available land are the main constraints in implementing the proposed
projects. Except for the XB1, T8 and New Lamki projects, which are located in the Terai plain
region, the remaining transmission lines and substations are located in mountainous areas.
Because of the specific geographical features of Nepal, the terrains can become subject to
landslide, seismic and flood hazards.
 There were many challenges faced during site selection process. Main challenge was to find
sufficiently big and flat terrain required for a typical substation. As such, GIS option was
explored to decrease the station footprint and more civil work was required to solve elevation
difference in the station.
 The assessment of the substation design reveals that the infrastructure constraints Nepal will
have a significant impact on the overall project cost.
 Considering the above constraints, a new, improved approach should be adopted for the
implementation of MCC projects. Their design and construction will be supported by advanced
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 221

geotechnical studies.
 Further geotechnical studies will need to be completed in detail design phase. It is
recommended that the borehole testing should be occur for every 5 to 10 KM of Transmission
line and 3 boreholes / stations and 3+ boreholes for bigger station for detail design phase.
 A LiDAR survey will offer fast and precise survey data production for wide areas, thus
guaranteeing a good transmission line routing. The design criteria provided are based on the
observed land conditions as well as professional, international, modern and well developed
standards aimed at organizing and harmonizing the design activities. The use of PLS-CADD
adds to the accuracy of line design by eliminating all the destructive and/or eroding factors
that cannot be detected without the use of finite element and non-linear analysis methods.
In order to complement the design documentation, we recommend that MCC develop a
comprehensive quality assurance plan for both the construction and operation phases of the
projects.
 An assessment of the road conditions presented in the section 2.3, revealed that no
equipment larger than a 160 MVA, 3 phase transformer can be transported to most
substations, while more remote areas are limited to single phase, 55 MVA transformers. This
limitation leads to an increase in the amount of transformers required, which inflates the size
of substation layouts. This further compounds the space limitation problem on the selected
substation sites and has the following consequences:
o Lower power handling capacity for a given footprint
o Lower capacity for substation expansion
o Increased overall project cost.

The following are key results / recommendation for contract procurement packages:

 In order to meet compact end date, Tetra Tech has recommended to divide contract
procurement packages in four zones. These packages should be awarded to a single EPC
vendor.
 Tetra Tech recommends one Engineer entity to provide services to all MCC vendors.
 There are several resettlement risks which can impact the project schedule and these risks are
further explained in Task 5.
 During construction phase, it is recommended that more than one construction crew work on
transmission line routes.
 The current implementation schedule includes 8 months of float in activities and in addition
there will be possible monsoon season float which can be utilized upon getting approvals from
National Government.
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 222

Annex C
Conceptual Drawings and Bills of Material for
Substations

The following files have been submitted as standalone documents owing to their size (over 250 MB
each):

Substation File Title File Number


EA Station Layout EA Station layout 1661550400-DWG-E0001
Protection SLD 1661550400-DWG-E0021-SH1-
1661550400-DWG-E0021-SH2-
Ultimate Stage 1661550400-DWG-E0023-SH1
1661550400-DWG-E0023-SH2
New Hetauda P&C Communication Block 1661550400-DWG-E0022-
Substation Diagram
Civil Drawing 1661550400-DWG-C0001-A
1661550400-DWG-C0002-A
EA / P&C BOM General Nepal EA/P&C BOM
Structural BOM 1661550400-BOM-S2074-A
Civil BOM General BOM will be attached at the end
EA Station Layout 1661550400-DWG-E0100
Protection SLD 1661550400-DWG-E0121-SH1
1661550400-DWG-E0121-SH2

Ultimate Stage 1661550400-DWG-E0123-SH1


1661550400-DWG-E0123-SH2
Naubise
P&C Communication Block 1661550400-DWG-E0122
Substation
Diagram
Civil Drawing 1661550400-DWG-C0100-A
1661550400-DWG-C0101-A
EA / P&C BOM General Nepal EA/P&C BOM
Structural BOM 705-1661550400-BOM-S2071-A
Civil BOM General BOM will be attached at the end
EA Station Layout 1661550400-DWG-E0200
Protection SLD 1661550400-DWG-E0221-SH1
1661550400-DWG-E0221-SH2
New
Ultimate Stage 1661550400-DWG-E0223-SH1
Damauli
1661550400-DWG-E0223-SH2
P&C Communication Block 1661550400-DWG-E0222
Diagram
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 223

Substation File Title File Number


Civil Drawing 1661550400-DWG-C0200-A
1661550400-DWG-C0201-A
EA/P&C BOM General Nepal EA/P&C BOM
Structural BOM 705-1661550400-BOM-S2073
Civil BOM General BOM will be attached at the end
EA Station Layout 1661550400-DWG-E0900
Protection SLD 1661550400-DWG-E0321

Ultimate Stage 1661550400-DWG-E0323


P&C Communication Block 1661550400-DWG-E0322
New Butwal Diagram
Civil Drawing 1661550400-DWG-C0300-A
1661550400-DWG-C0301-A
EA / P&C BOM General Nepal EA/P&C BOM
Structural BOM 705-1661550400-BOM-S2076-A
Civil BOM General BOM will be attached at the end
EA Station Layout 1661550400-DWG-E0400
Protection SLD 1661550400-DWG-E0421
Ultimate Stage 1661550400-DWG-E0423
P&C Communication Block 1661550400-DWG-E0422
Lapsiphedi Diagram
Substation Civil Drawing 1661550400-DWG-C0400-A
1661550400-DWG-C0401-A
EA / P&C BOM General Nepal EA/P&C BOM
Structural BOM 705-1661550400-BOM-S2077
Civil BOM General BOM will be attached at the end
EA Station Layout N/A
Protection SLD N/A
P&C Communication Block N/A
Diagram
Ilam
Civil Drawing N/A
EA/P&C BOM General Nepal EA/P&C BOM
Structural BOM 705-1661550400-BOM-S2081
Civil BOM General BOM will be attached at the end
Station Layout 1661550400-DWG-E2200
Protection SLD 1661550400-DWG-E2221
P&C Communication Block N/A
Inaruwa Diagram
Substation Civil Drawing N/A
EA / P&C BOM General Nepal EA/P&C BOM
Structural BOM 705-1661550400-BOM-S2080-A
Civil BOM General BOM will be attached at the end
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 224

Substation File Title File Number


Station Layout 1661550400-DWG-E2400
Protection SLD N/A
P&C Communication Block N/A
Diagram
Balanch
Civil Drawing N/A
EA/P&C BOM General Nepal EA/P&C BOM
Structural BOM 705-1661550400-BOM-S2082-A
Civil BOM General BOM will be attached at the end
Station Layout 1661550400-DWG-E2600
Protection SLD 1661550400-DWG-E2621
P&C Communication Block N/A
Diagram
Attariya
Civil Drawing N/A
EA/P&C BOM General Nepal EA BOM
Structural BOM 705-1661550400-BOM-S2083-A
Civil BOM General BOM will be attached at the end
Station Layout 1661550400-DWG-E0500
Protection SLD 1661550400-DWG-E0521
Ultimate Stage 1661550400-DWG-E0523-SH11661550400-
DWG-E0523-SH2
P&C Communication Block 1661550400-DWG-E0522-A
Diagram
Likhu Hub
Civil Drawing 1661550400-DWG-C0500-A
1661550400-DWG-C0501-A
EA/P&C BOM General Nepal EA/P&C BOM-Likhu Hub
Structural BOM
705-1661550400-BOM-S2075-A
Civil BOM General BOM will be attached at the end
Station Layout 1661550400-DWG-E0600-SH1
1661550400-DWG-E0600-SH2
Protection SLD N/A
P&C Communication Block N/A
New Khimti: Diagram
Civil Drawing N/A
EA/P&C BOM General Nepal EA/P&C BOM
Structural BOM 705-1661550400-BOM-S2079
Civil BOM General BOM will be attached at the end
Station Layout 1661550400-DWG-E0700-A
Protection SLD 1661550400-DWG-E0721-A
Tadhekani Ultimate Stage 1661550400-DWG-E0723-A
P&C Communication Block 1661550400-DWG-E0722-A
Diagram
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 225

Substation File Title File Number


Civil Diagram 1661550400-DWG-C0700-A
1661550400-DWG-C0701
EA/P&C BOM General Nepal EA/P&C BOM
Structural BOM 705-1661550400-BOM-S2072
Civil BOM General BOM will be attached at the end

Station Layout 1661550400-DWG-E2500


Protection SLD N/A
P&C Communication Block N/A
Diagram
Kusma
Civil Drawing N/A
EA/P&C BOM General Nepal EA/P&C BOM
Structural BOM 705-1661550400-BOM-S2082-A
Civil BOM General BOM will be attached at the end
New Lamki Station Layout 1661550400-DWG-E0800
Protection SLD 1661550400-DWG-E0821-SH1
1661550400-DWG-E0821-SH2
Ultimate Stage 1661550400-DWG-E0823-SH11661550400-
DWG-E0823-SH2
P&C Communication Block 1661550400-DWG-E0822
Diagram
Civil Drawing 1661550400-DWG-C0800-A
1661550400-DWG-C0801-A
EA/P&C BOM General Nepal EA/P&C BOM
Structural BOM 705-1661550400-BOM-S2078-A
705-1661550400-BOM-S20xx-A T8
Civil BOM General BOM will be attached at the end
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 226

Annex D
Conceptual Drawings and Bills of Material for
Transmission Lines

The following files have been submitted as standalone documents owing to their size (over 250 MB
each):

File Number
1661550400-DWG-E9009-A-132kV
1661550400-DWG-E9010-A-132kV
1661550400-DWG-E9011-A-132kV
1661550400-DWG-E9012-A-132kV
1661550400-DWG-E9023-A-132kV
132 kV 1661550400-DWG-E9024-A-132kV
drawings 1661550400-DWG-E9036-A-132kV
1661550400-DWG-E9037-A-132kV
1661550400-DWG-E9038-A-132kV
1661550400-DWG-E9039-A-132kV
1661550400-DWG-E9040-A-132kV
1661550400-DWG-E9051-A-132kV
220 kV 1661550400-DWG-E9005-A-220kV
drawings 1661550400-DWG-E9006-A-220kV
1661550400-DWG-E9007-A-220kV
Conceptual 1661550400-DWG-E9008-A-220kV
Design 1661550400-DWG-E9025-A-220kV
1661550400-DWG-E9026-A-220kV
1661550400-DWG-E9030-A-220kV
1661550400-DWG-E9031-A-220kV
1661550400-DWG-E9032-A-220kV
1661550400-DWG-E9033-A-220kV
1661550400-DWG-E9034-A-220kV
1661550400-DWG-E9001-A-400kV
1661550400-DWG-E9002-A-400kV
1661550400-DWG-E9003-A-400kV
1661550400-DWG-E9004-A-400kV
400 kV
1661550400-DWG-E9027-A-400kV
drawings
1661550400-DWG-E9028-A-400kV
1661550400-DWG-E9029-A-400kV
1661550400-DWG-E9052-A-400kV
1661550400-DWG-E9001-A-400kV
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 227

File Number
1661550400-DWG-E9041-A
1661550400-DWG-E9042-A
General 1661550400-DWG-E9043-A
drawings 1661550400-DWG-E9044-A
1661550400-DWG-E9045-A
1661550400-DWG-E9053-A
Transmission 1661550400-DWG-E9014-A Inaruwa
Line PP 1661550400-DWG-E9015-A Tadhekani-Kusma
drawings 1661550400-DWG-E9016-A New Khinti-Likhu Hub
1661550400-DWG-E9017-A New Lamki
1661550400-DWG-E9018_A_Sheets View New Butwal
1661550400-DWG-E9019_Sheets View New Butwal-Damauli
1661550400-DWG-E9020-A New Damauli-Naubise
1661550400-DWG-E9021-A_Sheets View Naubise-New Hetauda
1661550400-DWG-E9022-A Naubise-Lapsiphedi
Structure List NR1-Damaul-Naubise_StructureList
Structure List - Naubise to Lapsiphedi NR1
Structure List - Nr1 New Butwal to New Damauli
Structure List - T3 Tadhekani- Kusma sub
Structure List - XB1 New Butwal
Structure List NR1 Naubise to New Hetauda
Structure List NR3 - Ilam Inaruwa
Structure List t2 New Khimti-Likhu Hub
T8_Structure List New Lamki
Technical 705-1661550400-DBM-E0001-A_Design Criteria Final
Specifications 705-1661550400-TS-E3061-A_TowerSpec_final
705-1661550400-TS-E3062-A_Insulators_Final
705-1661550400-TS-E3063-A_CondOPGWOHSW_Fina
Report 705-1661550400-REP-E3061-A - Ampacity report_Final
Transmission 705-1661550400-BOM-S20xx-A XB1 New Butwal-India Border
Line 705-1661550400-BOM-S20xx-A T8 New Lamki-India Border
Foundation 705-1661550400-BOM-S20xx-A T3 Tadhekani-Kusma
BOM 705-1661550400-BOM-S20xx-A T2’ New Khimti-Likhu Hub
705-1661550400-BOM-S20xx-A NR3 Inaruwa-Ilam
705-1661550400-BOM-S20xx-A NR1 New Hetauda-Naubise
705-1661550400-BOM-S20xx-A NR1 Naubise-Lapsiphedi
705-1661550400-BOM-S20xx-A NR1 Damauli-New Butwal
705-1661550400-BOM-S20xx-A NR1 Damauli-Naubise
705-1661550400-BOM-S2084-B T8 New Lamki-India Border
705-1661550400-BOM-S2091-B T2' New Khimti-Likhu Hub
Feasibility Study: Nepal Priority Transmission Projects
Technical Feasibility Assessment
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Page 228

For Information/Clarifications
David Keith – [email protected] – +1-7033802582
Rakesh Kumar Goyal – [email protected] – +91-9871055119
1320 North Courthouse Road, Suite 600
Arlington, VA 22201
Tel 703.387.2100, Fax 703.243.0953

You might also like