Glorietta 1 - Popeyes Glorietta - Hotworks
Glorietta 1 - Popeyes Glorietta - Hotworks
Glorietta 1 - Popeyes Glorietta - Hotworks
Ground floor, Glorietta 2, Ayala Center, Makati City Tel: (02) 955-1128
Please email to: [email protected]
Work Permit
Dear Merchant,
Kindly email filled-up permit to [email protected]. Please use the following format as the name your file and
email: Building number_Merchant_Work Permit. (Example: Glorietta 1_Art Supplies Store Work Permit). Please note that validity of
permit is only 1 week.
Fire Watch Personnel: MASTY DIAZ / JAIME AGONOY Welder: JOUVER SUMILE / FRANCO NINO PASCUA
Approved by:
Name
Signature
Comments
1. Dedicated fire watch personnel must be at job site 30 minutes before and after scheduled hot work.
a. A Fire Watch will be deployed BY ADMIN to the merchant / contractor during the hot works with corresponding
Fee of 1,800.00 per night per fire watcher.
2. At least one (1) 20 lbs ABC fire extinguisher should be available at the work area.
3. The should be no combustible materials and if there are, they should be covered with metal sheet or non-combustible
cover. Appropriate ventilation should be provided when working with flammable gas.
4. The contractor and the project Engineer/Supervisor shall make sure that there will be no damage to the surrounding
area.
5. Any damage to the surrounding area caused by negligence shall be charged to the contractor.
6. Contractor must clean-up the area after work.
7. Hot work permit should be filed every day for the whole duration of the work.
1. All permits shall be accomplished and submitted prior to work commencement, in case of urgent/emergency works,
Glorietta BE/SE shall have the discretion of approval.
2. Workers shall accomplish a “signed” Job Hazard Analysis (JHA) that will cover all activities stated in this permit and shall
be submitted to Glorietta BE/SE prior to Hot Work Permit application or for urgent cases, prior to the commencement of
work. Absence of JHA means non-approval of work mobilization.
SAMPLE FORM:
Activity: ______________________________________
3. All works to be done shall not cause damage to exceed utility capacities of the leased area or building and shall
comply with pertinent government and safety regulations in accordance with the Glorietta House Rules and
Regulations and Construction Guidelines.
4 Painting or spraying shall be done when building is not operational and air-conditioning system is off. Th
5. Building Administration has the right to confiscate the materials and equipment which are used for painting or
spraying.
6. Any work which affects adjacent tenants/common areas should be subjected for work stoppage.
7. If merchants/workers continue to defy work stoppage or orders, BE/SE has the right to confiscate materials or
equipment to effect the stoppage.
8. Tampering of work permits without the authorization of BE/SE and other authorized representative will
automatically render the work permit void.
9. Damages caused by construction works or any procedures of the like will not render Glorietta liable.
10. Any person who shall be caught smoking within the building construction area shall be banned entry to building
and shall be fined as specified in the Construction Guidelines.
11. Use of common utility has corresponding charges to be determined by the Building Administration.