False Ceiling Check List

This document is a checklist for inspecting a suspended false ceiling during and after installation. It lists items to check before installation such as approved drawings and materials. During installation it lists structural and aesthetic items to check such as wall channel installation, panel alignment and gaps. The checklist is to be signed off by contractors and CBRE representatives once all observations are addressed.

Uploaded by

Raja gopal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
492 views1 page

False Ceiling Check List

This document is a checklist for inspecting a suspended false ceiling during and after installation. It lists items to check before installation such as approved drawings and materials. During installation it lists structural and aesthetic items to check such as wall channel installation, panel alignment and gaps. The checklist is to be signed off by contractors and CBRE representatives once all observations are addressed.

Uploaded by

Raja gopal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Remove Watermark Wondershare

PDFelement

Checklist for Suspended False Ceiling

Client Inspection Report No

Consultant Date

Vendor
Package Civil finishes
Description of Work Suspended false ceiling
Wing Dwg.Ref.No Rev Inspection Request
Floor Inspected by By Time
Details :
Location
Sl. No Description YES NO NA Remarks

Before Installation
1 Has the method statement been approved
Check for completion of plastering of walls and the above ceiling
2
services works
A. Electrical
B. HVAC
C. Sprinkler
D. Fire Alarm
E. Public Address
F. Access Control & CCTV
G. Light Fixture Supports (if any)
3 Is the approved drawings available for reference.
Check the availability of approved material. Whether the mock up for
4
suspended ceiling has been executed.

5 Check the availability of installation aids and skilled manpower

During Installation

1 Check the levels of the suspended ceiling transferred on to the walls.

2 Check the installation of wall channels as indicated in the drawing

3 Check if the fixing of the suspenders is as per specifications.

4 Check the fixing & alignment of carriers.


5 Check the rigidity of grid for suspended ceiling.
6 Check the painting at panel surface and tile edge.
7 Check for fixing of panels as shown in dwg
8 Check the levels for true horizontal alignment.

9 Check the provision for fixing of A/C grills & electrical fittings.

10 Check the matching of joints, closure of gaps & uniform finish.

Observations if any :

Above Observations have been attended & completed YES NO NA

CBRE
Contractor Civil Contractor Quality Contractor Safety CBRE Safety Client Representative
Representative
Signature
Name
Date
Time
Distribution Original : CBRE - QS cc : Vendor
Format No. F021-QC-Ch-023/Rev01/Oct2013