0% found this document useful (0 votes)
87 views3 pages

3.14 Housekeeping Check List

The document provides a housekeeping checklist for construction sites. It lists various points to check for different areas including general, structural fabrication, civil work, electrical installations, and stores. Items include ensuring walkways and work areas are clear, materials are properly stacked, welfare facilities are provided and maintained, and safety measures are followed.

Uploaded by

Aarti
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
87 views3 pages

3.14 Housekeeping Check List

The document provides a housekeeping checklist for construction sites. It lists various points to check for different areas including general, structural fabrication, civil work, electrical installations, and stores. Items include ensuring walkways and work areas are clear, materials are properly stacked, welfare facilities are provided and maintained, and safety measures are followed.

Uploaded by

Aarti
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

HOUSEKEEPING CHECKLIST

TPL UI / EHS / 3.14 Rev:0 Date: 01-Oct-17

Name of Site :
Inspected by :
Date :
S No. Points Observation Measures
GENERAL
Safe access provided to the job site
1
provided for all the workers
2 Separate scrap yard is allocated for the site.
Approaches to workstations, offices, stores,
3
batching plant are well laid and demarcated.
Site roads are kept clear of stacked material
4
for free & safe vehicular movement.
Heavy materials stacking are taken care of
5
to prevent slips, collapse and rolling
Walkways, aisles & all overhead workplaces
6
cleared of loose material.
Platforms and walkways free of oil / grease
7
or other slippery spillage
Collected scrap are brought down or
8
lowered down and not dropped from height.
Welfare facilities (toilet, drinking water, rest
9
room) provided & maintained
Signature: - Name: - Date: -
STRUCTURAL FABRICATION / ERECTION SITE
1 Walkways, passages kept clear of material.
Area and roads kept clear for manoeuvring
2
of cranes and material handling equipment.
Scrap, cut-pieces, welding electrode stubs,
3 hand-tools kept tidy in workarea and
disposed suitably.
The access road for the crane & hydra is
4
compact enough.
5 Scrap-bin available at site.
Welding cables, power cables routed
properly to avoid run-over by vehicle or
6
tripping hazards and obstruction to
personnel movement.
Compressed gas hoses routed properly in
7
the site.
Compressed gas cylinders and hoses kept
8
away from hot work and grinding work.
At least 1 metre on both sides of gantry rails
9
is kept clear of material.
Floor kept clear of water, oil spillage /
10
accumulation.
Signature: - Name: - Date: -

© TATA PROJECTS LIMITED, URBAN INFRASTRUCTURE Page 1 of 3


HOUSEKEEPING CHECKLIST

TPL UI / EHS / 3.14 Rev:0 Date: 01-Oct-17

S No. Points Observation Measures


CIVIL WORK AREA
All approach, aisle, ingress / egress to / from
1 site, excavated pits, ramps, walkways kept
clear of material debris tools etc.
Scaffolding material,(Pipes, bracing ,
2 clamps, etc.) shuttering boards, acrosspans
etc. are stacked properly at site.
Stacking of bricks, hollow blocks are done in
3
safe manner.
Nails removed from wooden planks / timber
4
and not protruding out.
Debris from demolition and excavated earth
5
cleared from site and accesses
All shuttering materials are removed after
6
de-shuttering is done.
Signature: - Name: - Date: -
ELECTRICAL INSTALLATIONS
Approach to DB, Panels, Switches kept
1
clear
Fire extinguishers installed at an easy
2
accessible location.
3 Weather protection for all the Panels.
Welding cables and power cables are routed
4
separately.
Routing of cables are done properly to avoid
5
obstruction & tripping hazards.
6 Floor of electrical sheds kept dry.
Rubber mats are in place at electrical
7
panels.
Signature: - Name: - Date: -
STORES
1 Walkways, entry and exits kept clear.
Materials placed on racks are safely
2
accessible.
Compressed gas cylinders are segregated
3
as full or empty and type of gas.
Vertically stored cylinders are secured /
4 chained to avoid toppling and horizontal
once guarded against rolling down.
Flammable storage areas are isolated from
5
store, office and work areas.
Cement bags are stacked in proper gradient
6
safely& stacked away from the wall.
Corrosive material (e.g. acids, alkalis) are
stored away from other material and kept on
7
collection trays to safeguard against
accidental leakage and MSDS displayed.

© TATA PROJECTS LIMITED, URBAN INFRASTRUCTURE Page 2 of 3


HOUSEKEEPING CHECKLIST

TPL UI / EHS / 3.14 Rev:0 Date: 01-Oct-17

S No. Points Observation Measures


Storing area for lifting tools & tackles, ropes,
8 wire ropes & PPE is dry, clean & free of
corrosive material
Easy accessibility to installed fire
9
extinguishers in store.

Signature: - Name: - Date: -

© TATA PROJECTS LIMITED, URBAN INFRASTRUCTURE Page 3 of 3