3.14 Housekeeping Check List
3.14 Housekeeping Check List
Name of Site :
Inspected by :
Date :
S No. Points Observation Measures
GENERAL
Safe access provided to the job site
1
provided for all the workers
2 Separate scrap yard is allocated for the site.
Approaches to workstations, offices, stores,
3
batching plant are well laid and demarcated.
Site roads are kept clear of stacked material
4
for free & safe vehicular movement.
Heavy materials stacking are taken care of
5
to prevent slips, collapse and rolling
Walkways, aisles & all overhead workplaces
6
cleared of loose material.
Platforms and walkways free of oil / grease
7
or other slippery spillage
Collected scrap are brought down or
8
lowered down and not dropped from height.
Welfare facilities (toilet, drinking water, rest
9
room) provided & maintained
Signature: - Name: - Date: -
STRUCTURAL FABRICATION / ERECTION SITE
1 Walkways, passages kept clear of material.
Area and roads kept clear for manoeuvring
2
of cranes and material handling equipment.
Scrap, cut-pieces, welding electrode stubs,
3 hand-tools kept tidy in workarea and
disposed suitably.
The access road for the crane & hydra is
4
compact enough.
5 Scrap-bin available at site.
Welding cables, power cables routed
properly to avoid run-over by vehicle or
6
tripping hazards and obstruction to
personnel movement.
Compressed gas hoses routed properly in
7
the site.
Compressed gas cylinders and hoses kept
8
away from hot work and grinding work.
At least 1 metre on both sides of gantry rails
9
is kept clear of material.
Floor kept clear of water, oil spillage /
10
accumulation.
Signature: - Name: - Date: -