JSA For Electrical Work TCF3-Haradh

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6
At a glance
Powered by AI
The document discusses job safety analysis (JSA) for electrical works and hot works including potential hazards and controls.

Potential hazards during mobilization include lack of site awareness, interaction with vehicles, and adverse road conditions. Controls include safety induction, explanation of JSA, traffic management training, and following speed limits.

When setting up the work area, ensure adequate lighting, clear access, good housekeeping, and proper welfare facilities like drinking water, toilets, and prayer areas.

JOB SAFETY ANALYSIS

FOR
JOB TITLE:
ELECTRICAL WORKS
TCF-3 Haradh

JSA DATE: December 08th, 2020 REVISION: 0 (Ref: TAFGA/JSA/015)

Safety helmet, Face Shield/Welding Glasses, Safety shoe, Ear protection, Dust Mask, Full
List of PPE’s for Each Person
body harness, Gloves as per job, FRC as per job.

Personnel Involved: Maintenance Engineer, Supervisor, Electrical / Mechanical workers

Control Measures in Place:

Barricades, Warning signs, Fire extinguisher, Canopy/Fire proof, Blanket, Machine should be in good working condition.

Prepared by: Reviewed by: Approved by:

Asad Ullah Muhammad Rafiq Saudi Aramco PMT


Corp. HSE Manager Project Manager
TAMIMI Global Co. Sign & date_________________ Sign & date_________________
Risk Assessment Index
(Risk Rating is bases on 5X5 Risk Matrix)

Likelihood Associated Risk Level

5 Very High 5A 5B 5C 5D 5E
4 High 4A 4B 4C 4D 4E
3 Medium 3A 3B 3C 3D 3E
2 Low 2A 2B 2C 2D 2E
1 Very Low 1A 1B 1C 1D 1E
A B C D E
Severity / (Very Low) (Low) (Medium) (High) (very High)
Consequences

Labels: High Risk

Medium Risk

Low Risk
JSA FOR HOT WORKS
JOB TITLE:

Step Task/Activity Description POTENTIAL ACCIDENTS OR Risk Hazard Controls


HAZARDS Rating
No
1 Mobilization of Manpower  Lack of site awareness 3C  Manpower will be transported to the site using buses
and equipment on the site that meet Saudi Aramco standard, A/C working, Safety
belt fitted for each passenger.
 Require Safety Induction to new workers prior to start
any work in the site. Moreover Safety talk shall be
conducted to explain JSA with all participants before
work on daily basis.
 Train all employees on TCF traffic management plan
and requirements.
 Interaction with Light & heavy  Follow speed limit 80kmph on temporary access road,
Vehicles 40kmph on internal project access road and 20kmph on
site.
 Head lights to be turn on when on the move.
 Hazard lights to be turn on when vehicle is temporary
stopped along the side of the highway.
 No reverse parking allowed for all equipment and
vehicle to be parked “Drive in / Drive out” system.
 No worker will be allowed to walk on the project
roads.

 Adverse Road condition  Not to take any unwanted risk during shifting.
 Plan ahead for the route and always be alert for any
consequences.
 Get a map and use and use alternative route for better
road condition.
 Presence of mind while behind the wheel and expect
the unexpected. Make eye contact with other
commuters.
JSA FOR HOT WORKS
JOB TITLE:

Step Task/Activity Description POTENTIAL ACCIDENTS OR Risk Hazard Controls


HAZARDS Rating
No
 Intrusion  Vehicle/equipment check prestart, First aid kit,
warning triangle, spare tire, jack & communication
device.

 Barricade the area with hard barricade/grill.

2 Set up work area  Lighting is not enough 3C  Prior to start of work we have to ensure there is adequate
light.

 Congestion of work area  The access area clear of any sort of obstruction

 Slips , Trip and Fall  Good housekeeping to ensure all around the area

3 Welfare provision  Heat stress 2C  Cool drinking water station shall be available with regular
water supply
 Sanitary waste  Toilet facilities with proper disposal of sanitary waste
 Hand wash facilities

 General waste  General waste to be collected in designated area and


deposed properly
 No proper prayer area  Prayer area shall be provided with proper signs. No prayer
allowed in non-designated areas in site
 Improper parking
 Proper parking area shall be provided
4 Transformer testing  Test voltage from test equipment 3C  Panel to be LOTO’ed, Lead Engineer to verify zero energy.
trapped charges  Keep persons clear of live test equipment. Only authorized
 Inadvertent contact with test persons in the work area.
voltages
JSA FOR HOT WORKS
JOB TITLE:

Step Task/Activity Description POTENTIAL ACCIDENTS OR Risk Hazard Controls


HAZARDS Rating
No
 Electric shock  Use insulated gloves by all involved.
 Slips trips and falls  Make sure the grounding is properly done.
 Use proper signs and barricades
 Clear the area surrounding access
 Watch the edges of the panel and be sure they do not touch
the wires in the panel box
 Should have emergency push stop buttons or equally
effective means to cut all the test supplies if there is an
emergency.
4 Electrical Equipment Repair  Arc flash 3C  Identify & confirm the switch gear feeding electrical power to
& Maintenance  Electrocution the equipment.
 Burns  Make sure the panels are properly isolated and LOTO
 Fire applied.
 Improper closure of panel  Personnel should wear FRC when working.
 Personnel should wear heavy duty gloves as per the work
requirement.
 All electrical portable tools should be double insulated and
inspection color coded.
 Keep the area free of unwanted materials and combustibles.
 Acquire proper permit with required counter signature from
all relevant parties.
 Make sure the panel is properly and safely closed before
restarting the power supply.

7 Housekeeping  Uncleaned area 2C  Promptly clean and dispose all the debris from work.
 Scattered materials  Keep the materials in a tidy manner during and after work
 Trips  Do not keep extension cords in a scattered manner, if
passing through walking aisles or road proper protection to
take wither lift it over head or keep inside the sleeve.