0% found this document useful (0 votes)
76 views5 pages

Work Standar Vapor Extractor

The document provides work procedures for operating a vapor extractor at a power plant. The vapor extractor helps prevent oil leaks by creating negative pressure in bearing pedestals. The summary outlines key steps for starting and stopping the vapor extractor safely, including checking equipment, monitoring pressure levels, and addressing any issues that arise. Safety precautions are emphasized, such as ensuring electrical safety and wearing proper protective gear.

Uploaded by

asri elektronik
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views5 pages

Work Standar Vapor Extractor

The document provides work procedures for operating a vapor extractor at a power plant. The vapor extractor helps prevent oil leaks by creating negative pressure in bearing pedestals. The summary outlines key steps for starting and stopping the vapor extractor safely, including checking equipment, monitoring pressure levels, and addressing any issues that arise. Safety precautions are emphasized, such as ensuring electrical safety and wearing proper protective gear.

Uploaded by

asri elektronik
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 5

IISM PT KPP #1.2 100MW Tgl :2012.10.23 Rev.

:0
Standard work
KPP Vapor Extractor Operation Guidance
Page:1/4
Procedure

Made By Achmad Gunawan Verified By

● Purpose Of Work : To prevent the oil from leaking out of the bearing pedestals, by making a
negative pressure.

● Summary work

Assortment Contents

Name and Place Of Work 1. Vapor Extractor Operation Procedure

Type : AC Motor driven vertical blower


Shaft Power : 0.75 kW
Important Equipment Speed : 3,000 rpm
Capacity : 5.5 m3/min
Pressure : 6.77 mbar

1. Problem : lube oil tank vapor fan trip


Quality
2. Cause : Pressure lube oil tank vapor ≧ -1 m BarG

Environment Contamination by leakage of motor bearing cooling lube oil

1. Safety Consideration
A. BRK input electrical shock caution
Important B. Work clothes curling caution due to the rotor
Check
2.Accident Case : Not Applicable
Safety
3.Near-Miss Case : Not Applicable

4.Fire Case : Not Applicable

5.Work Permit : Not Applicable

1. Check the service instrument status


Action
Before Work 2. Check Fan Vapor Extractor

Preparation
APD Helmet, safety shoes, work gloves, ear plug.
Equipment
Walky talky, valve handle, detector noise & vibration,
Required
IISM PT KPP #1.2 100MW Rev. :0
Standard work
KPP Vapor Extractor Operation Guidance
Page:3/4
Procedure

1. Vapor Extractor Operation (A: Control Room, B: Local)


Order Of Operations How To Work With Safety /
Environment

1)Check Before OP (B) BRK input


electrical shock
1. Check the voltage and frequency of the caution
electric source to be correct.
2. Check the rotating direction of the motor
to be correct.
3. Check for abnormal vibration, noise and
abnormal temperature rising of the motor.
4. Check BRK close

2) Vapor Extractor start

1.Control Room Start,


A. Control Room Auto start
- In operation, Lube oil Tank vapor Trip
- Pressure lube oil tank vapor ≧ -1 mBarG
B. Control Room Man’ start
- Graphic in DCS
Choose lube oil tank vapor fan
- Choose Sub window Man’ Then Start

3)Check After Vapor


Extractor start(Operation) Work clothes
curling caution
1. Check vibration or abnormal noises due to the rotor
2. Check pressure Lube oil tank vapor van if ≧
- 1 m BarG, Clean the lube oil vapor fan
(01/02 MAV10CP001)
IISM PT KPP #1.2 100MW Rev. :0
Standard work
KPP Vapor Extractor Operation Guidance
Page:3/4
Procedure

4) Vapor Extractor Stop

1.Control Room stop


Control Room Man’ stop
- Graphic di DCS
Choose Main Lube oil tank vapor fan
- In Sub window, Choose Man’ stop

Finish
Standard work IISM PT KPP #1.2 100MW Rev. :0
KPP Guidance
Vapor Extractor Operation Procedure Page:4/4

Vapor Extractor Operation Flow


Standard work IISM PT KPP #1.2 100MW Rev. :0
KPP Guidance
Vapor Extractor Operation Procedure Page:4/4