Activity 15: Individual: Activities/Assessments

Given a project with activities, their time estimates, predecessors, and maximum slack: 1) The earliest project completion is 35 months along the critical path of activities G-H-J. 2) The critical activities that cannot be delayed are G, H, and J. 3) The non-critical activities that can be delayed without delaying the project are A, B, C, D, E, F, and I.

Uploaded by

Joshua Lokino
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
120 views2 pages

Activity 15: Individual: Activities/Assessments

Given a project with activities, their time estimates, predecessors, and maximum slack: 1) The earliest project completion is 35 months along the critical path of activities G-H-J. 2) The critical activities that cannot be delayed are G, H, and J. 3) The non-critical activities that can be delayed without delaying the project are A, B, C, D, E, F, and I.

Uploaded by

Joshua Lokino
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Activities/Assessments:

Activity 15: Individual

Given the activities of a project; their optimistic (to), most likely (tm) and pessimistic (tp) time
estimates; and their immediate predecessors shown below:

ACTIVITIES IMMEDIATE ACTIVITY TIMES, MONTH MAXIMUM


SLACK,
PREDECESSOR MONTH

A - 1 4 13 5 3

B A 4 7 16 8 4

C A 2 2 2 2 3

D C 4 6 14 7 3

E - 1 3 5 3 9

F E 3 5 13 6 9

G - 7 10 13 10 0

H G 6 7 14 8 0

I B, D 1 1 1 1 3

J F, H, I 13 16 25 17 0

1. When is the earliest project completion?

G-H-J 10+8+17 35
Earliest completion time= 35 months

2. Which activities are critical (should not be delayed)?

A-B-I-J 5+8+1+17 31

A-C-D-I-J 5+2+7+1+17 32

E-F-J 3+6+17 26

G-H-J 10+8+17 35

The critical path are G – H – J, since it is the path that takes the longest time to finish.
3. Which activities are noncritical (can be delayed)?
The noncritical activities are the rest of the activities that are not critical. Therefore, the non-critical
activities are: A, B, C, D, E, F, and I.

4. How long can each of the activities be delayed without delaying the whole project (maximum
slack)?

A 3 MONTHS DELAY

B 4 MONTHS DELAY

C 3 MONTHS DELAY

D 3 MONTHS DELAY

E 9 MONTHS DELAY

F 9 MONTHS DELAY

G 0; CANNOT BE DELAYED

H 0; CANNOT BE DELAYED

I 3 MONTHS DELAY

J 0; CANNOT BE DELAYED