Project Managment Question Bank
Project Managment Question Bank
5 What are the constraints of Project Management? Time Scope Cost All the Above d
8 What are the phases of project management Project planning Project Scheduling Project Controlling All the Above d
16 The means of achireving the goals is called as Events Activities Rules Procedures b
17 _________ are broad guidelines for the enterprise Policies Plan Stratergy Procedures a
__________ specify the how to proceed in some
18 Policies Plan Stratergy Procedures d
situation.
An event represents a
noteworthy, significant and An event is an accomplishment
An event is either the start or
2 Which of the following aree properties of an event recognizable point in the project. occouring at an instantaneous All the above d
completion of an activity
Event act as a control pooint in a points in time
project
Greys them out and formats them A task field named Active is to NO
2 Setting tasks inactive Is the same as cancelling it All the above d
with strike through for when a task it is inactive
By default is 8 hrs and is used
The Hours er Day field in the Calendar Option for the is referred t when Start or Finish
3 when duration is entered in Days B & D is set to 24hrs per day b
project is less than 1 day
or weeks