Introduction To Construction Dispute Resolution Pena-Mora Sosa McCone 2-1-2002
Introduction To Construction Dispute Resolution Pena-Mora Sosa McCone 2-1-2002
Introduction To Construction Dispute Resolution Pena-Mora Sosa McCone 2-1-2002
PREFACE ...................................................................... V
THE CONSTRUCTION INDUSTRY .............................................. 1
1.1 SOURCES OF CONFLICT AND DISPUTE ................................................... 3
1.2 ORGANIZATIONAL ISSUES ............................................................... 6
1.2.1 PARTICIPANTS AND PEOPLE ISSUES .............................................. 6
1.2.2 PROJECT STRUCTURE ........................................................... 7
1.2.3 PROCESS PROBLEMS .......................................................... 12
1.3 PROJECT UNCERTAINTY .............................................................. 13
1.3.1 EXTERNAL UNCERTAINTIES ................................................... 13
1.3.2 INTERNAL UNCERTAINTIES .................................................... 13
1.4 SUMMARY ............................................................................ 15
1.5 POINTS FOR DISCUSSION ............................................................. 16
1.6 REFERENCES ......................................................................... 17
1.7 ENDNOTES ........................................................................... 17
EVOLUTION OF DART ...................................................... 18
2.1 TRADITIONAL DISPUTE RESOLUTION IN CONSTRUCTION............................... 18
2.1.1 DETERMINATION BY THE DESIGN PROFESSIONAL .............................. 19
2.1.2 ARBITRATION ................................................................. 20
2.2 MODIFICATION OF THE TWO-STEP ADR APPROACH................................... 23
2.2.1 FIDIC’S ADR CONTRACT CONDITIONS ....................................... 24
2.2.2 WORLD BANK’S ADR CONTRACT CONDITIONS ................................ 25
2.2.3 CHEK LAP KOK AIRPORT’S DISPUTE RESOLUTION SYSTEM .................... 26
2.3 EVOLUTION OF THE PRESENT ADR METHODOLOGIES ................................. 29
2.3.1 DATA SUPPORTING THE EVOLUTION OF ADR ................................. 29
2.3.2 TWO CONCEPTUALIZATION MODELS OF DART................................ 31
2.4 THE STATE OF THE LEGAL CONSTRUCTION ARENA ................................... 35
2.5 SUMMARY ............................................................................ 38
2.6 POINTS FOR DISCUSSION ............................................................. 38
2.7 REFERENCES ......................................................................... 39
2.8 ENDNOTES ........................................................................... 42
STAGE 1: PREVENTION...................................................... 43
3.1 IMPORTANCE OF PREVENTION STAGE ................................................. 44
3.2 EQUITABLE RISK SHARING ............................................................ 45
3.2.1 ECONOMIC PRICE ADJUSTMENT ............................................... 47
3.2.2 GEOTECHNICAL BASELINE REPORT (GBR) .................................... 47
3.2.3 THIRD PARTY BENEFICIARY CLAUSE........................................... 49
3.3 ESCROW BID DOCUMENTS ............................................................ 49
3.4 PROJECT AWARD AND DELIVERY MECHANISM ......................................... 50
3.4.1 NEGOTIATED COMPRESSED PROCESS .......................................... 50
3.4.2 A+B BIDDING................................................................. 50
3.4.3 PEPC DELIVERY SYSTEM ...................................................... 51
3.4.4 “BRIDGING” THE DESIGN-BUILD GAP ......................................... 52
3.4.5 FRAME CONTRACT DELIVERY SYSTEM IN THE NETHERLANDS .................. 53
3.5 INCENTIVE PROGRAMS................................................................ 56
i
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION
ii
TABLE OF CONTENTS
iii
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION
iv
PREFACE
Leading construction experts have identified Productivity, Innovation, Cost Control,
Safety, and Litigation Expenses as critical areas in need of improvement in the
construction industry of this next century. In the United States alone, $60 billion are spent
every year on lawsuits, of which the construction industry accounts for nearly $5 billion.
The fact that these construction litigation expenditures have increased at an average rate
of 10% per year for the past ten years is one of the primary motivations for this book.
This reality has generated the need to develop new Dispute Avoidance and Resolution
Techniques (DART) with the aim of curving this cost spiral and improving productivity.
Fueled by this need, and as projects throughout the world continually achieve higher
levels of complexity, the field of construction dispute resolution has exploded with
innovative ways to prevent conflict and resolve disagreements. Companies have found
that in highly competitive markets, the resolution of disputes has become a key to forging
stronger and longer-lasting relationships with their clients. As a result, the construction
industry has been in the forefront of the development of DART. This book presents and
reviews a significant number of new and innovative ways to promote collaborative
environments and resolve disputes in construction. This includes some practical
applications of DART in the construction industry throughout a number of nations. The
aim is to provide the reader with data to support the successes or failures of these
techniques in multiple cultures.
In effort to ground the material in this book, some examples are presented of how the
material relates to current construction projects. These examples will be referred to as
cases. Not all the information specific to the project has been presented, as they are only
included to correlate theory with practice. They are also not included to illustrate either
effective or ineffective handling of dispute avoidance and resolution procedures. In
addition, some names or facts may have been changed for confidentiality reasons. Each
of the relevant chapters will open up with an introduction of facts to the case and leave
the reader with some questions to ponder while reading the chapter. At the end of each
chapter the case is revisited relating the chapter information to the project situation.
Content
This introductory book is divided in 12 chapters. The first chapter describes the
construction industry, focusing on its size, structure, relationships and sources of
conflicts. Chapter 2 presents a background for the evolution of construction DART. It
also presents a brief review of the reasons behind the apparent large number of disputes
in the construction industry, and identifies characteristics that make the construction
process adversarial in nature. The final section of Chapter 2 looks at two different
proposals for the organization of DART in the construction industry. It selects the
concept of the “Dispute Resolution Ladder” (DRL) to organize and present different
techniques found being used around the world.
Chapters 3 through 9 present the state of the art review of DART in the construction
industry following each of the stages of the DRL defined in Chapter 2. Chapter 3 reviews
techniques in the Prevention Stage with examples of mechanisms that can mitigate and
discourage disputes during the construction process. This chapter highlights the role the
owner plays in the introduction of dispute avoidance and resolution clauses in
construction contracts and as a promoter of honest communications between the parties to
the project. Chapter 4 reviews the concept of Partnering. Although not a Stage in the
v
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION
Dispute Resolution Ladder (DRL), Partnering was developed to change the adversarial
approach to the construction process, with the aim to improve job performance and
reduce conflict and confrontation. This concept integrates dispute resolution with other
communication and collaboration techniques that have resulted in a significant reduction
in the number of conflicts in those projects in which it is fully implemented. This chapter
introduces the essential phases of the system, and its key components.
Chapter 5 examines the Negotiation Stage in the process of dispute resolution in
construction. This chapter offers three different approaches to improve the outcomes of
negotiations: Step Negotiations, Structured Negotiations, and Facilitated Negotiations.
The introduction of neutral third parties begins in Chapter 6, with the Standing Neutral
Stage; a concept based on the incorporation of an unbiased, knowledgeable party as an
instrument to resolve disputes efficiently and effectively as soon as they develop. Chapter
7 examines the Non-Binding Phase of the DRL, covering Mediation, Advisory Opinion,
Fact-based Mediation, Minitrial, Summary Jury Trial, and Voluntary Settlement
Conference as the available DART techniques. A significant acceptance of non-binding
dispute resolution mechanisms is reflected in the number of variations that have
developed, as these procedures represent the last stage of the DRL in which the parties
have control over the outcome of the dispute.
Chapter 8 examines approaches where a third party issues a final award to settle the
dispute. These approaches correspond to the Binding Dispute Resolution Stage in the
DRL. Arbitration, the most common form of binding resolution procedure, is reviewed,
together with three other developments that can prove advantageous to a project that
might be inclined to minimize arbitration. Finally, as part of this review of DART in
construction, Chapter 9 looks at Alternative Litigation and Litigation as the last Stage in
the DRL. This Stage corresponds to a dispute resolution procedure of “last-resort,” and is
examined together with three techniques that can help reduce the amount of resources
spent on court proceedings (i.e., time and money).
Chapter 10 presents the concept of a Conflict Management Plan for projects. In all arenas
of construction, conflict is evident, but being able to quantify the degree of conflict is
challenging. Taking into consideration, the causes and results of the most common
conflict situations, a conflict management plan can be designed from the DART
presented in the previous chapters. The probability of conflict occurring is assessed along
with the impact that each conflict may have on the project. A preventative strategy is
developed to reduce the probability of conflict occurring and a resolution strategy is
planned to minimize the impact of conflict if it does occur. The resulting Conflict
Management Plan will help owners and contractors to evaluate the interactions among
participants and actively involve everyone in the dispute resolution process.
Following the presentation of all the material in the book, Chapter 11 analyzes a light rail
transit project in San Juan, Puerto Rico. This case study is included to promote discussion
on the methods to avoid claims and resolve disputes used in the project. This project
made use of preventative measures such as Partnering as well as a predefined dispute
resolution system. Analyzing this project allows the reader to envision how new and
innovative techniques can be implemented into the industry.
Finally, Chapter 12 gathers the conclusions of the book. First, it summarizes the DART
techniques. Second, it highlights the importance of alternative dispute resolution in
construction worldwide and how cultural conditions have affected the selection of the
DART, based on the examples presented throughout the book. Finally, this chapter
suggests areas for further study in the field of construction conflict, dispute avoidance,
and alternative resolution methodologies.
vi
PREFACE
Intended Audience
This introductory textbook is offered to both graduate and upper level undergraduate
students, as well as practicing professionals such as construction managers, design
engineers, and owners. Students should use this book to develop a basis of knowledge in
the area of dispute avoidance and resolution in the construction industry. We hope that
they will use this knowledge when they become practicing professionals or spark further
research in this area if they continue their graduate studies. Current practicing
professionals should compare this book with their current knowledge, keeping an open
mind in new techniques and whether they apply to their situation. This book is offered to
the professional community as the construction industry responds to its global reach,
where the conflicts are multinational. This book in no way serves as a substitute for
individual legal council provided by an attorney. Our competency in addressing these
issues stems from an international construction engineering and management background
with limited legal training in any specific country. Therefore, take no specific legal
advice from us, as none is offered. Your legal council, familiar with your individual
project situation, should advise you of your options.
Acknowledgements
The authors would like to acknowledge the following individuals for their technical
guidance in creating, revising and editing the book: Phil Helmes, Margaret Fulenwider,
Soád Kousheshi, Shounak Lahiri, Eduardo Witzke, Naz Majidi, Thomas Zgambo, Lara
El-Amm, and all the anonymous reviews that provided insightful comments on the drafts
of this book.
The authors would like to thank the National Science Foundation for their support to the
research that served as the basis for this book under the following grants: White House
PECASE Award, NSF CAREER Award CMS-9875557 and NSF IIS-9803251. We
would also like to thank the Central Artery and Third Harbor Tunnel Project, Tren
Urbano Project, InteCap Inc., Kajima Corporation, Shimizu Corporation, Draper
Laboratory, Ford Motor Company, Visteon Corporation, Microsoft Corporation, PenOp,
Modern Continental, Intel Corporation, and AT&T for their financial support to the
DaVinci Initiative (within which this book was born) and providing us access to their
personnel. Their contributions have been invaluable.
We would also like to thanks Joan McCusker for her tireless effort and support.
Feedback
Comments, constructive criticisms, and suggestions are welcome and encouraged.
Suggestions and contributions to make this book more relevant and useful to the intended
audience are greatly appreciated. Please contact Feniosky Pena-Mora at
[email protected].
viii
DEDICATION
Feniosky Pena-Mora:
A los pilares de mi vida:
• Mami, Mirtha Mora-Cepeda, por sembrar en mí una visión positiva cada vez
que tenía que conseguir algo muy importante. Siempre me decías: “Lo único que
puede ser es que tu ganes. Si tratas y no lo obtienes, te quedas igual – tu no lo
tenias como quiera. Si tratas y lo obtienes, ganas. Por tanto solo puedes ganar.”
• Papi, Ramón Peña-Salcedo, por siempre recordarme que mi único trabajo era
estudiar.
• Mi Adorada Esposa, Minosca Alcántara- Damirón (Minin), por quererme tanto
y apoyarme en todo lo que hago.
• Mis Hijos, Aramael, Amnahir, and Giramnah Peña-Alcántara, por que se que
ustedes serán mi orgullo y mi mejor trabajo.
To the pillars of my life:
• My Mother, Mirtha Mora-Cepeda, for planting in me a positive vision of life
whenever I wanted to get something important. You always said: “You can only
win. If you try and don’t get it, you stay the same – you don’t have it anyway. If
you try and get it, you win. You see, you can only win.”
• My Father, Ramón Peña-Salcedo, for always reminding me that my only job
was to study.
• My Beloved Wife, Minosca Alcántara- Damirón (Minin), for loving me so
much and providing me support in everything I do.
• My Children, Aramael, Amnahir, and Giramnah Peña-Alcántara, because you
will be my pride and my best work.
Carlos E. Sosa:
I have to acknowledge and appreciate the support and patience of my wife Cristina.
Throughout this race against time, Cristina has been both an inspiration and a challenging
voice that has kept me going, even at times when I felt the objective was unattainable. I
would also wish to thank my sister Daniela Sosa and my father Carlos Sosa. I wish to
dedicate this effort to my family, including those who will hopefully be joining us in the
near future.
D. Sean McCone:
This book is dedicated to all of my family for their love and caring. In particular, I would
like to express my sincere gratitude to my parents, Fran and Bob. Throughout my years,
you have given me the freedom and support that defines who I am. I hope that one day I
will be able to repay you for the priceless contribution you have bestowed upon me.
Carrie and Brett, thanks for all the encouragement. Kelly, thank you for your love and
support, and for enduring the frustration and stress I exuded on you during my extensive
studies.
ix
C H A P T E R
1
THE
CONSTRUCTION
In the United States alone, $60 billion are spent
every year on lawsuits, of which the construction
industry accounts for nearly $5 billion.
In 1995, companies from six different countries participate at different levels, with
different contractual relationships to build a Refinery. For the construction of this
Refinery in an Island in the Caribbean Sea (Figure 1), a British energy conglomerate
(CLIENT) hired an engineering and construction firm from the United States to serve as the
construction manager (CM). Among the many contracts for the Refinery, a Liquid
Nitrogen Gas facility had to be designed and built, for which the CM chose a design firm
from England (DESIGNER), and awarded it a two-year fast-track Design-Build package.
This design firm, a subsidiary of a German design and construction company, kept the
design in-house and divided the construction package in the usual work subdivisions (i.e.,
site work, foundations, civil, mechanical, electrical, and specialties). The DESIGNER
negotiated and awarded the contract for the foundations to an Italian contractor with
experience in similar projects, and the civil works contract 1 to a medium size company
KEY CONCEPTS
Sources of Conflict and Dispute ....................3 Organizational Issues ........................................ 6
Participants and People Issues .......................6 Project Uncertainty ........................................... 13
1
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION
from Venezuela. The Italians had recommended the Venezuelan company due to positive
past experiences in other large-scale projects. The total scheduled duration for these two
contracts was 18 months: ten months for the foundations and twelve for the civil works,
with a four-month overlap.
BRITISH
ENERGY
CONGLOMERAT
BID negotiations
and TECHNICAL ITALIAN CONTRACTOR
communications FOR FOUNDATIONS AND
during CIVIL WORKS LNG TANKS
construction
VENEZUELAN SUB-CONTRACTOR
ABOVE GRADE WORK PACKAGE CIVIL
WORKS (SUB-civil)
Looking a little closer at the structure, because of sub-contractor approval and bonding
requirements imposed by the CM, the British DESIGNER, and the Italian and Venezuelan
contractors agreed to have the foundations and civil works packages lumped as one
contract to be awarded to the Italians (GC). The latter in turn would subcontract out the
civil portion to the Venezuelan contractor (SUB). The contracts were drawn up following
this arrangement; nevertheless, communications lines were established as if the
Venezuelan SUB was working directly for the British DESIGNER.
Looking at the structure of this project, some important questions arise. Does this
arrangement provide any indication on how much conflict the project would encounter?
Is there anything about the project structure that would give an indication on how this
2
THE CONSTRUCTION INDUSTRY
project will handle conflicts? Does this project have mechanisms to handle uncertainty in
this project? Is there a process by which conflicts on this project will be handled?
At first sight, it seems that there are vast sources of construction conflicts and disputes,
but if you take a closer look you will see that most of the areas are the same, but
identified with different adjectives. This problem requires a set of labels or headings to
facilitate the comprehension of the reasons behind construction conflicts and disputes. On
this account, Howell et al. (1988 cited by Vorster, 1993) proposed a nomenclature of
elements that summarize four causes behind conflict in the construction environment:
• Incomplete scope definition
• Inappropriate contract type
• Poor communication
• Uncertainty
However, this classification can be further simplified in this book into to two main areas.
This arrangement gathers most of the information presented in Table 1 and Howell et
al.’s model, yet it permits a simpler cataloging of the ‘genesis’ of construction disputes.
This classification is presented herein to accurately group these areas of conflict.
This characterization has the additional contribution of supporting the notion that people
issues are related to the project structure and process problems. For example, certain
project structures align some of the participant’s objectives where as others do not. When
the parties’ objectives and interests are not compatible, their interpretations of contract
documents, terms and conditions can be divergent leading to discrepancies and conflicts.
In short, all of disciplines within an area are interrelated.
Confirming this notion of a relationship between objectives and disagreements, many
participants acknowledge the apparent conflict-prone nature of construction projects on
the incompatibility of the parties’ initial intents. Each construction party starts with a
different set of goals, correlating this information to the high tendency to conflict in this
4
THE CONSTRUCTION INDUSTRY
industry. Incompatible objectives are responsible for the frequent disagreements on how
to approach and complete a project, leading to adversarial attitudes. Table 3 illustrates the
results, when they asked owners and contractors to identify what constituted business
success for their companies in construction projects following a traditional Design-Bid-
Build approach.
CONTRACTORS OBJECTIVES
• Achieve profit and other financial gains.
• Satisfy client and generate repeat business.
• Manage cash flow.
• Limit long-term liability.
• Develop employees and create satisfaction.
• Optimize employment level within contractor organization.
CONTRACTORS’ AND OWNERS’ OBJECTIVES
• Complete the project within budget.
• Complete the project within schedule.
• Maintain a high level of quality.
• Execute the project safely, without wasted time or accidents.
• Minimize claims and litigation.
OWNERS OBJECTIVES
• Meet return on investment goal.
• Minimize plant operating and maintenance costs.
• Minimize plant downtime and outages.
• Achieve high product quality.
• Achieve product throughput capacity goals.
• Provide design flexibility to meet future demands.
• Minimize disruptions to existing operations.
• Avoid negative impact on environment and community.
• Reduce project cycle time.
• Exceed internal customer’s expectations.
As shown, only in a few responses the owner and contractor shared a set of objectives.
On the one hand, “the owner wishes to obtain maximum quality, functionality, and
capacity at a minimum cost.” On the other, “the contractor ...must achieve financial
goals that are advanced by expending the minimum resources required to meet a
minimum scope of work” (Howard et al., 1997). This limited alignment of objectives
fosters the development of conflicts and disputes.
After reviewing the reasons behind disputes in the construction, it appears that conflict is
an intrinsic aspect of this industry, as each project has its own set of organizational issues
and project uncertainty. These conditions also make each project unique, making the
development of a unique theory on the sources of conflict and dispute in construction a
challenging task. Therefore, it remains the responsibility of each project team to assess
their specific project characteristics to develop a joint, creative, and effective approach to
deal with and resolve conflicts before they can lead to disputes.
General characteristics of the major participants on the project, such as the owner, the
A/E, the contractor, and the CM, are reviewed here based on their interests, positions and
attitudes. Others that need to be considered but not mentioned here include
subcontractors, suppliers, unions, lawyers and financial institutions. Between these
participants, there are many sources of disputes. Misunderstandings often result in
conflict. All owners push for a job to be completed, as soon as possible, with exceptional
quality and minimal cost, but sometimes their expectations are too high. Even though a
contractor may be performing exceptionally compared to the industry standards, the
owner’s paranoia may harbor the feeling that contractor is not. As seen, people issues are
a major source of conflict. However, projects that encounter monumental challenges and
enormous conflicts can be overcome if the participants cooperate and communicate
effectively.
Owner
The owner is the inciting party for whom the project is developed. This party is also, in
most cases, the source of the financial resources that support the project. It is important to
notice the distinction between private and public owners, because the private owner’s
contracts operate differently from the public ones. The private owner may include
individuals, partnerships, corporations, or various combinations thereof. Most private
owners are the end users who have the facility built for their own use. Some others may
sell, lease or rent the facility to others for a profit. These differences of the owner’s
position in the “value system” (Porter 1985) may affect his/her strategy and, therefore,
his/her interests in a project. On the other hand, in the United States the public sector
owners are composed of local, state, or federal governmental bodies. Public projects are
paid for by appropriations, bonds, tax levies, or other forms of financing and are built to
meet some defined public need. It is interesting that public owners’ interests are largely
affected by the needs of the public they serve, who is usually not at the table when
conflicts occur. Another important point is that the public owner may be subject to
restrictions on delivery methods, such as a state law against public owners using design-
build. This may sometimes result in contractual relationships that contain unresolved
problems, or potential conflicts.
Architect/Engineer (A/E)
The A/E is the party that designs the work and often administers the construction phase
of the project on the behalf of the owner and in the absence of a CM. The A/E can occupy
a variety of positions with respect to the owner for whom the design is done. It is quite
common that the A/E acts as an independent designer under contract with the owner. In
some agencies that hold their own in-house designers, the A/E occupies a functional part
6
THE CONSTRUCTION INDUSTRY
of the owner’s organization. Meanwhile, the A/E may be affiliated with the contractor
when the owner contracts with a single party for both design and construction services.
Depending upon contracts and organizations, the A/E takes various positions as they
relate to both the owner and the contractor. In those cases, the A/E’s interests may differ
accordingly from project to project, however, some of his/her inherent interests, such as
safety and aesthetics, will not change.
There may be a number of ways to classify project delivery systems. The following seven
delivery systems were selected for review so that they can effectively show clear
distinctions between the participants’ roles, responsibilities, and relationships.
Project Phase
D/B is a delivery system where both design and construction functions are combined
under one contract. TKY can be categorized as one of the modification of D/B, which
packages design, construction, and short-term financing. DBO is an extension of the
TKY delivery process, but with O&M included over an extended period of time. BOT is
a further extension of the DBO model, including long-term financing. Those differences
in scope of the contracts are also anticipated to make distinction among each participant’s
relationship. The models of the project structure followed in these four delivery systems
are depicted in Figure 3. Project structures for TKY, DBO and BOT may be illustrated
similarly as the one for D/B, except for the differences of extra functional groups
involved in their teams, such as O&M forces and financing firms.
8
THE CONSTRUCTION INDUSTRY
Owner Owner
A/E
CM A/E
General
Contractor
Owner Owner
D/B Entity
CM A/E
Construction Design
Function Function
occupies the position of primary consultant and fiduciary to the owner. No formal
contract exists between the A/E and the contractor. However, despite no contractual
relationship, the informal relationship of communication exists between the A/E and the
contractor. The adversarial relationship may occur between them, because the contractor
has to act on orders from a contractually unauthorized source. From the nature of work
and selection base, the A/E’s interests may include profit, aesthetics, relationships,
quality, recognition, and otherwise.
The general contractor’s role usually starts from the bidding stage, so they play very little
or no part in the design phase. They take total charge of the site and construction of the
project. They coordinate and supervise the works of the subcontractors who actually
undertake most of the construction. They are responsible to the owner for the
construction in accordance with plans and desires of the A/E. They normally assume
responsibility for all site safety issues. In general, the contractor’s interests may include
profit, construction time, relationships, and reputation, although profit almost always
seems to be one of the top priorities. Construction time, or schedule, is also a key element
of the project especially in a situation that time becomes a cost item to the contractor.
Design-Build
The owner contracts singularly with the D/B team. The design function and construction
function are within one contractual team. The responsibility for design and construction
rests with one organization, and there exists only one contract to the owner. This is
usually a type of general contractor firm with design function. The design function can be
another firm, and the relationship is just as another subcontractor to the prime. Contrary
10
THE CONSTRUCTION INDUSTRY
to DBB, the owners may have more emphasis on schedules despite less control and more
uncertainty of cost. One of the disadvantages of the system is the loss of control over
design and flexibility in changes. The owner must be knowledgeable enough about
design and construction to establish the initial parameters, review proposals, and monitor
the process, which frequently require the help of an independent consultant.
Relationships differ even between the same participants of projects. For example, CM-
Trade Contractor relationship changes from the communicational one to the contractual
one when the owner shifts his/her risks to CM. The roles and positions may differ
significantly, even under the same relationships participants have. For example, one of
the A/E’s main interests in the DBB contract is to protect his own and the owner’s
interests, while, in the D/B contract, he/she plays the opposite role as the co-worker of the
contractor with the intent of bringing value to the D/B team instead of the owner. The
relationships between the CM and the A/E also show the differences between two
construction management systems. In PCM, both the CM and the A/E serves the owners
as agents and work together in a collaborative manner, while the CMR in practice
appears to be a GC and they may have adversarial relationships.
Since the roles and positions that every participant takes are regulated by the contract
they agreed on prior to the beginning of the project, different contract types lead to varied
positions and interests. Thus, the relationships and interests of participants become
extremely complex. It is quite possible that an owner has a fiduciary relationship with a
designer in a DBB project, while they have an adversarial relationship with the very same
designer in a different D/B project. Moreover, one participant may take two or more
distinct roles in a single project that adopts “innovative” hybrid delivery system. An
example of this is the Systems and Test Track Turnkey contract in the Tren Urbano
Project in Puerto Rico (Section 11.2), which includes design and construction of a
facility, operation system supply, O&M, and coordination/management of other D/B
facility contracts. In such a situation, conflicts due to interest inconsistency occur while
they have to collaborate on the same project under the relationships defined by their
contract protected by law.
Thus, information on relationships may help the project participants avoid their role and
responsibility confusions. This is especially important in a large-scale project, because
some participants may hold several different contracts and their roles and responsibilities
differ among those contracts. Surveys in American industry show that there is only a 35%
overlap between that which top managers expect their close subordinates to do, and that
which the subordinates themselves think they should do (Scott et al., 1990). This may
apply directly to owners and their relationships with contractors or contractors and their
relationships with subcontractors. Role confusion or misunderstanding is almost
inevitable, especially under competitive stresses in the context of a large-scale project.
Information on roles and relationships may also help in contract planning and formation
process, especially when a hybrid type of delivery system is under consideration. The
owners or project managers should check the interest inconsistency in allocating multiple
responsibilities and risks for hybrid systems.
Interrelated with the project structure are the process problems. The number and types of
process problems are endless. The sources of conflict relate to how the project is handled.
It focuses on contract administration, contract terms, project management and
inefficiencies therein. These process problems may be inherited from the choice of
project structure and they may be compounded by people issues.
There has been an abundance of material written on construction contracts. 2 This material
addresses formation of contracts, implementation of contracts, breech of contracts and
other related areas. When a conflict of interest arises, the first move each party makes is
to review the contract documents for direction. These documents are not always thorough
nor do they address every situation.
Contract Types
Directly relating to project structure is contract type. In this book, we will focus on
contract types as they differ on the “basis of payment.” For this reason the classification
of contract types will be based on this characteristic. Lump sum, unit price, guaranteed
maximum price, cost plus and fixed fee are all examples of different contract types. Each
of these contracts have advantages and disadvantages, and can create conflict. Some of
these contract types are sometimes synonymous with certain delivery systems, but make
no mistake they are different. Project structure and contract type should be chosen on a
project-by-project basis taking into consideration each individual situation.
The lump sum or fixed price contract is the most common type of contract. It is also the
most adversarial. The general contractor or design-build entity enters into a contract with
the owner for a fixed price. This type of contract compels the contractor to cut corners to
reduce costs and make a profit. On the owner’s side, it requires the owner to provide for
monitoring of the contract for quality and compliance as per the contract documents.
With this being the most common form of contract, you can see why the industry is
plagued with conflict and claims.
One the opposite end of the spectrum it a cost plus contract. The cost plus contract aligns
the objective of the owner and the constructor more so than a fixed price contract. In a
cost plus contract, the contractor will perform the work for the owner at the cost to
him/her plus a percentage for profit. This ensures that the contractor will not lose any
money, shifting more risk to the owner. Knowing this, there is the risk that a contractor
might take advantage of the situation, by inflating the costs and therefore increasing their
profit. In these cases, proper checks and balances need to be provided to ensure that cost
increases represent the reality of the project.
12
THE CONSTRUCTION INDUSTRY
A median between the two is a guaranteed maximum price (GMP). In a GMP contract,
the owner will reimburse the contractor for all the costs plus a profit up to a certain price.
The GMP contract has the benefit of having a fixed maximum price that the contractor
must respect, but still allowing the flexibility of being reimbursed for costs. In short, all
these contracting mechanisms try to achieve a balance between the objectives of each
participant in terms of risk allocation, quality, schedule and cost, among others.
External uncertainties are the result of external forces on the project. They are present in
all projects and range form inclement weather, to political risk, to acts of god. They are
usually accounted for through insurance policies, contract clauses or other forms of
mitigation. In most cases, there is not a person to blame. For example, securing a contract
with a government in a country that has a history of political chaos and government
overthrows might present the situation where the contract becomes void. After
completing half the work and not being compensated, how should the conflict be
resolved?
In other instances, Mother Nature seems to find her way onto every jobsite. Rain, snow,
wind, fog, extreme temperatures are just some of the factors that impact projects in a
negative manner. To combat these uncertainties, it is normal to insert contract clauses
that address these issues or identify schedule buffers according to the unworkable days.
There are was to proportionate the risks associated with most of the external
uncertainties, but they must be identified ahead of time and accounted for in order to
avoid conflicts on who is responsible and should pay for it.
design are present in all projects. However, their impact could be minimized with proper
monitoring and control the common statement heard in the construction industry “No
design is ever complete.”
Dissimilar to the disciplines in the organizational issues, technical and context
uncertainties are not interrelated. Political risks do not result from errors in design.
Incomplete scope definition does not breed inclement weather. This is different from the
organizational issues, as these characteristics are derived from the premise that these
uncertainties are present in every project.
The Liquid After reviewing the sources of conflict in the industry, revisit the LNG Tanks Project. We
have already identified the complex project structure, but where’s the conflict? After the
Nitrogen
job got under way, these separate communication and contractual arrangements resulted
Gas Tanks in total chaos. For example, the civil works contract between the British DESIGNER and
Project the Italian GC was never signed, a “detail” that became apparent only 2 years later when
lawyers began compiling the original documentation in preparation for a claim.
Presumably, the contract had been misplaced between Venezuela and Italy; hence, it was
never returned to the DESIGNER for signature.
British
DESIGNER
New
California York Italian
CM GC
Job
Venezuela
SUB
Moreover, halfway into the job neither party had a complete assessment of the status of
the design and the work completed. The SUB had invoiced 55% of the contract through
the GC, but only 30% was in place; major cash-flow problems were affecting the job, and
cost overruns were evident in every work item. At that point, the DESIGNER took over the
GC responsibilities, by forcing the Italian GC and the Venezuelan SUB into takeover
agreement. This agreement gave the DESIGNER the right to use all the material purchased
for the job and all the manpower and equipment the SUB had on site at that time. In
14
THE CONSTRUCTION INDUSTRY
addition, the GC and the SUB agreed to a provision that made them responsible for all
costs going forward concerning the civil works package. Therefore, the DESIGNER
effectively assumed total control over the project, without relieving the two contractors
from the cost risk of the project. In other words, the DESIGNER could finish the job with
whatever resources it considered necessary and charged them to the contract with the
Italian GC. Any cost over the original base-contract would still be the responsibility of the
contractors. Based on this arrangement, the DESIGNER brought more personnel from
England, provided additional financial resources, and finished the civil works one year
behind schedule.
Five months after the take over agreement, the Venezuelan SUB and the Italian GC
reconciled the jobsite and home-office files (formal and informal communications), and
proceeded to file a claim against the DESIGNER due to changed site conditions and
significant design modifications. This claim amounted in value to 100% of the original
contract cost and declared the takeover agreement invalid. The DESIGNER, in turn, filed a
counter-claim against the Italian GC for liquidated damages per the original “lumped”
contract and for extra costs incurred to finish the job according to the takeover
agreement. This counterclaim was worth double the original contract value.
Both claims for this project went to arbitration in New York, as per the contract terms,
sometime at the end of 1999, almost two years after the project was actually finished. By
mid 1999, the Venezuelan/Italian “team” had spent 3 percent of the original contract in
legal and consulting fees, and it was expected to spend another 3 to 8 percent before an
award through arbitration may be achieved. No information is available from the British
side, but the costs was estimated to be about the same, since both companies have
prepared separate arbitration claims using outside consultants. In other words, both
companies spent 6 percent of the original contract value, and expected another 6 to 16
percent in arbitration costs without knowing whether they will ever recover those
expenses. These costs are in addition to the economic and professional implications of
finishing a job one year behind schedule, with significant overtime costs and added
supervision.
1.4 SUMMARY
This case, although overly simplified for this introduction, provides a snapshot of some
of the conditions that are present nowadays in most large engineering and construction
projects: multi-party, multi-cultural, complex contractual arrangements, with
international arbitration clauses for dispute settlement. It also highlights the need for new
and innovative approaches to communication and contractual relationships, including
new ways to resolve disagreements without relying solely on arbitration or litigation. In
this example, we saw how inefficient communication and complex contractual
arrangements can result in poor job performance. Even though previous experiences in
other projects brought some of the team members together, their inability to overcome the
contractual framework resulted in claims and costs totaling over three times the original
contract value, leading to the following questions. Can these results be avoided? Can
attitude changes improve the overall job performance? Could the job have been saved
without the costly takeover if the parties had sacrificed a portion of the costs they are now
spending on arbitration? Are there mechanisms to improve communication regardless of
contract conditions?
The disputes in this case reached the settlement stage, and these questions remain
unanswered for this project. Thus, this book presents innovative procedures to promote
collaborative environments and resolve disputes in construction contracts. It also presents
specific uses and applications of DART across different countries, which have
implemented these techniques and used them within the realm of their own construction
industries. The contents in this book represent the state of the art in DART, and they
highlight how the industry is coping with some of the problems and project complexities
presented above. One of these alternative approaches, or a combination of them, might
have resolved the problems in the LNGT project before the takeover agreement. Even in
binding arbitration, this book presents certain techniques that could have improved the
chances for a “win-win” solution for the claims, at a lower cost to both parties.
These procedures can be used to answer and deal with some of the questions and issues
raised by either the LNG project or any other case throughout the world. Companies,
universities, professional associations, private groups, industry think tanks, and
government agencies have realized the cost implications of poor communication and
litigation in construction. The industry as a whole has realized that if legal costs continue
to grow unchallenged, productivity and technological innovation will continue to fall
further behind, limiting the construction industry’s role in the development and
improvement of our society.
16
THE CONSTRUCTION INDUSTRY
1.6 REFERENCES
[Conlin et al., 1996] Conlin, J., Langford, D.A.,and Kennedy, P., 1996. The
Relationship Between Construction Procurement Strategies and
Construction Contract Disputes Proceedings of CIB W92,
North Meets South, pp. 66-82. Durban, (January).
[Fenn et al., 1997] Fenn, Peter, Lowe, David, and Speck Christopher, (1997).
Conflict and Dispute in Construction. Construction
Management and Economics (1997) 15, p. 513
[Gordon, 1991] Gordon, Chris. (1991). “Compatibility of Construction
Contracting Methods with Projects and Owners” MS Thesis,
MIT, Cambridge.
[Howell et al., 1988]
1.7 ENDNOTES
1
This contract included all sub-base preparation, concrete, reinforcing and formwork to
be completed above grade for the two tanks (i.e. pile caps, gravel sub-base, slab-on-
grade, tank walls, and post-tensioning system).
2
One such book is: Collier, Keith. Construction Contracts. 3rd edition. Prentice-Hall Inc.
Upper Saddle River, NJ. 2001.
2
EVOLUTION OF DART
“...there has been a veritable explosion in the
development and use of new dispute resolution
techniques, particularly techniques for resolving
disputes at the job site during the course of
construction.”
(Groton, 1997)
KEY CONCEPTS
Two-Step DRL ..............................................18 Arbitration ........................................................ 20
Modification of the Two-Step .......................23 Evolution........................................................... 29
Current Legal State of the Industry................35
18
EVOLUTION OF DART
to organize dispute avoidance and resolution techniques for construction projects, and it
is further described in Section 2.3.2.
Negotiations
DETERMINATION
BY DESIGN
PROFESSIONAL
In this ladder, the design professional played the role of a first step in the process of
resolving disputes. The contractor submitted inquiries and disagreements to the design
professional representing the owner, and then expected prompt, knowledgeable, and
unbiased answers. If either the owner or contractor objected to the determination of this
third party, the matter usually escalated and it was left to arbitration. As discussed above,
and shown in Figure 5, negotiations were used to fill the “gap” between the first and
second step in the ladder. In this stage, either the owner or the contractor has become
involved to formally prevent conflicts and disagreement. An exception to this is perhaps
attempting to transfer project risks to the opposing party in an effort to limit individual
liabilities. Design-Build projects are based in part on this notion of reducing the owner’s
exposure to design problems, by assigning both the design and the construction
responsibility to only one party.
The second step in the ladder, Arbitration was the preferred alternative to litigation for
the resolution of construction disputes because it offered “...a limited process, a
relatively prompt hearing, privacy, informality, and above all, [an] informed judgment”
(Stipanowich, 1996). This is how arbitration became a “sine qua non of construction
contracting,” and gained popularity as a standard clause in most contracts. If the first step
of the ladder failed to resolve the dispute, arbitration procedures were usually delayed
until the project was completed. The two dispute resolution steps of the traditional
construction DRL, are discussed in more detail in the following two sections.
between the owner and the contractor. The decisions of the architect/engineer were
backed by their profound knowledge of the technical considerations of the project,
something that gave them the authority to resolve almost any matter related to their
‘creation’. The decisions of the design professional were usually not final nor binding on
the parties, but they provided a fast, knowledge-based, “objective” solution to jobsite
disputes.
Nevertheless, as contracts became larger, the technical complexities increased and the
number of parties expanded, the quantity, frequency, and size of project disputes also
increased. The dollar amount of contract disagreements became larger and delayed
completion time brought additional problems. Although it was often assumed by owners
that the evaluation of disagreements would always be conducted by their own on-site
agent (engineer or architect), the changes described eventually undermined the position
of the agents and they were finally considered not in the best position to propose or
evaluate the merits of an equitable settlement.
Among the major concerns that led this transformation was the possible conflict of
interest as the design professional was not truly neutral. A contractor seeking
compensation from the owner because of a contractual problem involving administration,
design, and/or contract interpretation elements was not likely to find an objective
decision originating from the agent, since this last was an actual part of the condition
being claimed (Stipanowich, 1996). Furthermore, in disputes regarding errors or
omissions in the contract, the design professionals frequently became a defendant, so
their role as an ‘unbiased third party resolver’ of disputes lost credibility. At that point
the owner was left to face what often were disputes that could not be settled by the people
they had assumed would be responsible of doing so during the project.
The role of the design professionals as the first step in the DRL has lost significance,
especially in large, complex projects where their decisions can be challenged in other
forms of binding adjudication, or where they can become a part of the dispute. Although
the design professional still remains the primary interpreter of design and specification
requirements, their role as a dispute resolution adjudicator has been reduced significantly.
Still, the benefits of having an unbiased, knowledgeable third party involved in the
resolution of construction disputes is still recognized by the industry (i.e., objectivity,
speed, decisions backed by technical know-how, and an understanding of the project) as
it will be demonstrated in further examples of third-party ADR techniques. Thus, it can
be argued that the concepts of Neutral Advisors (Section 6.1) and Dispute Review Boards
(Section 6.3) have been developed by the construction industry as substitutions and
improvements of the role played by the design professional in the traditional DRL.
2.1.2 ARBITRATION
This section presents two cases of early applications of arbitration as a dispute resolution
technique, together with the use of arbitration in the construction industry. The two cases
provide two important lessons for the use of arbitration in construction dispute resolution.
First, the Greek case shows how arbitration was implemented as a dispute resolution
system. Then, the use of arbitration in the Middle Ages in England shows how this
technique followed a path towards rigidity and formalization as its use increased just like
arbitration in construction during the past fifteen years.
20
EVOLUTION OF DART
(AIA), the Association of General Contractors (AGC), and the Chartered Institute of
Builders (CIOB) all incorporated arbitration as their only dispute resolution alternative.
International organizations like the World Bank and the Federation Internationale de
Ingenieurs-Conseils (FIDIC) also supported the use of this technique. However, with the
increasing acceptance of arbitration as a substitute for litigation, the technique began to
develop problems as it became more rigid and costly.
According to Stipanowich (1996), arbitration was “...subjected to the stresses and strains
borne by its expanded use.” Furthermore, as courts began to accept the system, they
proceeded to delegate in arbitrators the “...burden of almost the entire spectrum of civil
rights and remedies,” creating increasing demands for rules and procedures to
accommodate the expanding needs of the final users, something surprisingly similar to
the extinction of the “loveday” concept in Old England. In response to these demands,
arbitration was forced to adopt certain characteristics from civil litigation, such as
“extensive discovery, multi-party practice, awards of attorney fees, and written opinions
by the arbitrators” (Stipanowich, 1996). Due to these pressures and strains, arbitration
lost some of the features that had made it the preferred dispute resolution technique in the
construction industry: flexibility, privacy, decisions based on technical know-how, and
economy.
The problems experienced by arbitration are reflected in the results of an American Bar
Association (ABA) sponsored survey completed in the mid-1980’s. The study reviewed
the perceived advantages and disadvantages of arbitration in the resolution of
construction disputes, and its respondents, mostly construction attorneys, identified their
major concerns with this form of ADR. Table 5 summarizes the ABA results and
connects them to the features responsible for the initial popularity of arbitration in
construction.
Table 5 – Problems with Arbitration in ABA Survey 1988 and their connection to the
Features of Arbitration identified (Stipanowich 1996)
22
EVOLUTION OF DART
These concerns about arbitration within the ABA confirmed that the system had
developed some of the inherent problems of litigation due to its excessive use. In fact, the
views presented by points 4 and 5 above suggest that arbitration was being abused by the
disputants and their legal representatives, just as it happens in litigation. This is
exemplified by a study by Flood et al. (1993) on this subject in the UK, which concluded
that lawyers had “...essentially ‘juridified’ the field [of arbitration], making the
procedures rigid, costly and time consuming, with the many drawbacks attributed to
litigation.” Arbitration had become an adversarial procedure.
Examples of ancient Greece and England show how arbitration in construction evolved
into a pseudo-adjudicative and adversarial system with many of the features that had
made litigation the least preferred dispute resolution technique. In the next case a final
journey to ancient history is presented to illustrate how dispute resolution has been
carried out in Asia since the fourth century BC as a conciliatory practice focused in
maintaining the relationship between parties.
Confucian Philosophy
In the Far East, the concepts of resolving disputes by conciliation date back to the times
of Confucius (511-479 BC). The Chinese base their dispute resolution processes “...on
the Confucian view that the optimum resolution of a dispute should be attained by moral
persuasion and compromise instead of by sovereign coercion” (Chau, 1992). According
to Li (1970, cited by Chan E., 1997), the Chinese preference is to encourage people to
settle disputes amicably.
This philosophical approach is based in a common Asian tradition to seek “harmonious”
solutions that help maintain relationships over time. Judges and mediators are considered
the same in Asia, for what parties seek is a well-known go-between that is also familiar
with their disagreement. The idea is that the third party helps them bring an end to their
dispute while assisting in reaching a mutually agreeable solution. What they seek is a
solution with as little “loss of face” as possible. In Japan, the existence of a dispute may
itself cause a “loss of face,” and having to submit a dispute to a third party may represent
some sense of failure.
Under Confucius’ traditions, litigation is viewed as the last resource. Consider that China
has over 10 million mediators versus only 15,000 lawyers. Local People’s Mediation
Committees, with three to 10 members, mediate 7 million cases a year and they reach
agreement in 90% of the cases (Pierce, 1994). Discussion and compromise are always
preferred, and all adjudication procedures where a third party decides the matter are
considered adversarial in nature. In contrast, conciliation and mediation are always
favored, as informal, person-oriented approaches, unbound by the strict rules of highly
structured procedures. It is less important in Confucianism to be accurate in finding the
truth. What this philosophy truly considers important is to determine a common ground in
which parties can negotiate a settlement without ever disrupting their “harmonious
relationship” (Scott, 1995).
quest for improving their current effectiveness and ultimately their bottom lines when
dealing with conflict.
As described, the traditional dispute resolution ladder has experienced some problems as
the size and complexity of projects expanded. This section presents three examples that
illustrate how the ladder has been gaining “steps” as parties incorporate new ADR
techniques to bridge the gap between the design professional’s initial determination and
the binding arbitration stage.
The most frequently used form of international contract conditions for civil engineering
and construction projects comes from the Federation Internationale de Ingenieurs-
Conseils (FIDIC) - the Conditions of Contract for Works of Civil Engineering
Construction), also known as the “Red Book.” Until recently, this standard contract was
drafted under the assumption that construction claims should be set aside during the
work, and then resolved at the end of the project. Arbitration was the only alternative to
litigation if parties failed to agree with the architects/engineer’s determination 3, but it
could only be initiated after final completion of the project. Clearly, what the FIDIC was
using was the two-step traditional DRL described in Section 2.1.
The first edition of the Red Book in 1957 included a dispute resolution clause stating that
“...the arbitrator/s shall not enter on the reference [dispute] until after the completion or
alleged completion of the works unless the parties otherwise agree.”(FIDIC, 1957)
Claims, and the process to resolve them, were considered a distraction to the
construction, confirming the notion that the job came first, and that claims should be put
aside until the end of the project. More recently, however, there has been a trend to
address and resolve claims as early as possible. Molineaux (1995) suggests two important
reasons behind this new approach from the viewpoint of the owner:
1) “To avoid or lessen the origin of the claim, by taking the necessary actions in
response to the problem; for example, a design change to meet new subsurface
conditions; and
2) To monitor the alleged extra costs being incurred by the contractor for future
review and possible negotiation.”
Additionally, an early treatment of claims also means that owners can attempt to isolate
troubles from the rest of the project, which enhances flexibility and reduces their effect
on other activities. The 1987 Edition of the FIDIC contract had already taken into
consideration these developments, and addressed the need to resolve disputes during the
execution of the works by means other than arbitration. This Edition included a
requirement to attempt an “Amicable Settlement” before arbitration could actually start.
Clause 67.2 of the Red Book stated (FIDIC, 1987):
“Amicable Settlement – Where notice of intention to commence arbitration’s to
a dispute has been given in accordance with Sub-Clause 67.1, arbitration of
such dispute shall not be commenced unless an attempt has first been made by
the parties to settle such dispute amicably. Provided that, unless the parties
otherwise agree, arbitration may be commenced on or after the fifty-sixth day
after the day on which the notice of intention to commence arbitration of such
dispute was given, whether or not any attempt at amicable settlement thereof
has been made”
This clause is an encouragement for parties to resolve the dispute without recurring to
arbitration by making them wait considerably before arbitration can begin. This passage
24
EVOLUTION OF DART
is also an acknowledgment that there are other mechanisms available to deal with
problems between parties to a contract.
In terms of promoting early resolution of claims, the FIDIC reinforces the claims’
notification process. In the 1987 Red Book Edition, contractors are required to notify the
engineer within 28 days after the event giving rise to the claim is first noticed. From that
date forward, the contractor is required to keep updated files on all costs associated with
the claim, and to make the material available to the engineer for review, without requiring
from the engineer an acceptance of any liability. Failure to comply with these
requirements automatically reduces the amount the contractor can claim at a later date.
From his role of Chairman of the FIDIC Committee of Conditions of Contract, Seppala
(1991) identified three major advantages of the Federation’s procedure just described:
1) “The engineer can investigate the facts of a claim and its financial
consequences while the evidence is still fresh and available;
2) The owner receives a prompt notice of possible adjustment to the contract price;
and,
3) The earlier claims are identified, the sooner they may be resolved.”
The system makes both parties responsible, and creates an obligation to deal with
disputes in a timely and professional manner. In short, by preventing arbitration and
encouraging early claim notification the FIDIC has both introduced an ADR system and
promoted an expedite process that saves time and resources to the parties involved. Yet, a
point that is still missing is clause 67.2’s failure to describe what parties should do during
the waiting period before arbitration. Not clearing the article terms might only serve to
delay arbitration for almost two months.
Whereas the FIDIC has left open the possibility of using some form of alternative to
arbitration after the architect/engineer’s decision is rejected, the World Bank has gone a
step further and has actually recommended the use of a Dispute Review Board (DRB) as
the method to resolve construction disputes. In its May 1993 Standard Bidding
Documents, the World Bank suggests the following:
“In case of major projects, IBRD [World Bank] encourages employers to
consider introducing a dispute review board (DRB) into the contractual
settlement of dispute procedure ... Such a DRB could either replace the engineer
under Clause 67... or it could review the decisions made by the Engineer” (cited
by Molineaux, 1995).
For smaller contracts, the World Bank has also introduced the concept of an
“adjudicator” to function as the first step in the resolution of disputes:
“The adjudicator is the person appointed jointly by the employer and the
contractor to resolve disputes in the first instance. The adjudicator is …
required to provide a decision within 28 days. If no party submits the
adjudicator’s decision to arbitration within 28[days] of receipt the decision is
considered final and binding” (Molineaux, 1995).
These two conditions represent a significant improvement over the standard FIDIC
contracts in relation to dispute resolution procedures. Not only has the World Bank
recognized the existence of alternatives to arbitration - by recommending two options
depending on the size of the project, but also it has replaced the role of the designer in
small contracts as the first-instance resolver of disputes. In large contracts, the World
Bank has incorporated a dispute review board as a new step in the resolution process
between the designer and arbitration stages.
As a final example of the modified two-step DRL approach, this section presents an
actual case from Hong Kong. In this Asian country, construction contracts with the
government usually include a three-step dispute resolution process shown in Figure 6.
Just like in the two-step process, the design professional is responsible for the first
determination as to any disputes regarding the contract, and arbitration is the final
binding mechanism for settlement. However, a Mediation stage is added as an in-between
step, if the parties disagree with the design professional’s decision. In this case, mediation
is not mandatory, and the opposing party can refuse to participate in the mediation
procedures.
In the event mediation fails or one of the parties refuses to participate, the Hong Kong
government establishes that the dispute can be referred to arbitration, but only after the
conclusion of the project. In other words, the contract makes the completion of the works
a condition precedent to any final solution of disputes that may occur during construction,
just like the 1957 Edition of the FIDIC contract reviewed in Section 2.2.1.
1 2 3
ARCHITECT/ MEDIATION ARBITRATION
ENGINEER or
Supervising
Officer
For the construction of the Chek Lap Kok Airport, the government developed a specific,
modified dispute resolution system based on the three-step process described above.
During the negotiations between the Airport authority and the local contractors, the local
contractors exerted a great deal of pressure for a faster and more efficient dispute
resolution procedure than the one shown in Figure 6. The biggest hurdle in the
negotiations was a condition that “arbitration was only possible after the project’s
completion,” and the contractor insisted on a mechanism that could address the large
number of disagreements expected in a project of such complexity. The resulting dispute
resolution process is shown in Figure 7.
Two methods for dispute resolution were incorporated into the contract to satisfy
contractor’s demands regarding dispute resolution. Figure 7 shows these two methods,
which have been labeled here as A and B to help the reader.
26
EVOLUTION OF DART
Under method A, parties submitted to the engineer representing the Airport Authority a
Notice of Dispute as the first instance for resolution. Mediation followed if the
Engineer’s determination was not acceptable to one of the parties. Opposed to the
standard dispute resolution procedure (Figure 6), in this case mediation was mandatory
and had a time limit of 42 days before the parties escalated the dispute to the adjudication
stage. In addition, the Hong Kong government tightened this modified system by
requiring from the mediator 1) a final report on the findings 4, and 2) specific
recommendations to the parties involved.
1 2 3
ARCHITECT/ MEDIATION
ENGINEER or Mediator issues ADJUDICATION
A Supervising final report
Officer
Figure 7 - Dispute Resolution Process for Hong Kong’s Airport Core Program
If mediation failed, or one of the parties disagreed with the report, the matter was
submitted to an Adjudicator for binding determination. According to Fenn et al. (1998),
the selection of this adjudicator was handled through the Hong Kong International
Arbitration Center (HKIAC) and involved the following steps:
“Parties submitted to the HKIAC at least three names of people willing and able to
act as adjudicators;
The HKIAC combined these lists and returns them to the parties;
Each party ordered the combined list based on their preference, and
The HKIAC then appointed the individual with the highest rating.”
If parties failed to select an adjudicator the HKIAC could appoint one of its choices, from
the list, or from its registered adjudicators (arbitrators). Once appointed, the adjudicator
had the widest discretion permitted by the law to select the procedure and to ensure a just,
expeditious, and economical resolution of the dispute within 28 days. This adjudicator
acted as a Single Arbitrator (Section 8.3.1), and was required to provide a written
statement identifying the dispute, the reasons for the decision, and any admissions made
by the parties during the proceedings. The awards of the adjudicator were binding, but
could be appealed in arbitration after the completion of the project (Fenn et al., 1998).
Under method B (Figure 8), the contract incorporated the authority of a Dispute Review
Group (DRG), consisting of seven individuals. The DRG visited the construction site
once every three months and spent there four and a half days reviewing the project and
attending Quarterly Meetings between the contracting authority and the different
contractors in order to maintain current knowledge of the status of the works.
Arbitration Civil
Expert from Engineer
the People’s from the UK
Republic of
China
Technical Expertise
Figure 8 - Composition of the Dispute Review Group for the Chek Lap Kok Airport
Project, Hong Kong
An interesting aspect of the DRG is how it was organized in terms of expertise and
representation of each party in the project. Although modeled as a Dispute Review Board
(described in Section 6.3) in this case the contractors had no direct representation. Thus,
DRG was more like an Agency Review Board (Section 6.2) in which the Convenor
provided the legal background to any review and/or decision by the DRG. Arbitrators
from China represented the government, and at the same time were the experts in
arbitration procedures. The technical expertise to review construction and design issues
was provided by professionals from the UK. Although it is unclear how one method was
selected over the other for each claim, it appears that the larger contracts (i.e., Airport
Terminal Building) used the DRG, or method B.
Under both methods, A and B, arbitration was left as the final stage to resolve disputes, to
be used only after the project was completed. Arbitration awards in Hong Kong are
usually in writing, are signed by the arbitrator, and in most cases provide the reasons for
the award. Arbitration awards are final and can only be appealed when an issue of law is
in question. 5 The awards are enforceable in the same manner as a judgment.
28
EVOLUTION OF DART
For the construction of the Chek Lap Kok Airport contractors were able to modify the
standard dispute resolution clauses of the Government of Hong Kong and develop two
alternative approaches to address disputes more efficiently. By combining non-binding
techniques, like Mediation and an Owner Review Board, with more binding
determinations they were able to expedite processes and better document the project.
However, this case did not introduce a change in the requirement to finish the project
before being able to submit a claim to final arbitration.
To sum up, the examples presented above have shown how the traditional two-step DRL
(Section 2.1) has been modified with new techniques (i.e., Mediation, Dispute Review
Board, and Adjudication) added in between the designer’s determination and arbitration.
The World Bank contract and the Government of Hong Kong have actually replaced the
design professional by introducing the figure of a Standing Neutral to provide the initial
evaluation and recommendation on the conflict matter. The following section will present
the evolution of the two-step ADR model, portraying its expansion to include a number
of new ‘steps’ that offer the parties increased flexibility, reduced costs, and a better
chance to preserve their relationship.
Since the 1976 conference of the American Bar Association – known as the Pound
Conference, the growth in the use of ADR in the American court system has been
exponential. While in 1980 only 18 states had some type of ADR program as part of their
court system (Court-Annexed procedures), by 1990 all 50 states and the District of
Columbia had incorporated a program, and by 1993 more than 1,200 court-related ADR
programs were in place (Ide, 1993). This growth of ADR in the US court system has been
fueled by the success of Court-Annexed procedures in the early resolution of disputes.
For example, a mandatory ADR program 6 carried out by the Commercial Division of the
New York County Supreme Court achieved settlements in 52% of the cases, and
contributed to the resolution of the dispute in another 16% of the cases (Meade, 1997). In
other words, the ADR program positively affected 68% of the disputes in this Court.
Further use of ADR in the US is promoted by the Dispute Resolution Act of 1998, which
actually instructs Federal district courts to require all litigants in civil cases to consider
the use of alternatives to litigation. According to this bill, courts can direct parties to use
ADR at any point during the legal procedures, in an effort to expedite the resolution of
the matter and allow greater flexibility. The parties can now resort to ADR during
litigation, without giving up any advances made at the court level or losing their right to
continue with the court proceeding if ADR fails.
At the State level, for example, the Governor of New Jersey signed a bill during the first
quarter of 1998 that requires disputes in public construction projects to be submitted to an
alternative dispute resolution procedure before court litigation (DRT, 4/1998). The bill
recommends various specific ADR options such as mediation (Section 7.2), non-binding
arbitration (Section 7.4), or binding arbitration (Section 8.3). In this document, not only
has the government of New Jersey identified construction as a major source of civil
litigation, but also it has recognized the fact that DART can improve the resolution
process, increasing the chances for a faster, more efficient settlement of disputes with less
court appearances.
Two surveys by the American Bar Association further confirm the increasing use of
DART in construction. The first one, conducted as part of the ABA 1990-91 Forum on
the Construction Industry found arbitration to be the most frequently used form of ADR
in disputes with 81.5% of those surveyed having experience with the procedure
(Stipanowich et al., 1992). Many participants also reported the use of mediation, with
64.2% of the respondents having some experience with it, and 58.3% having mediated a
dispute in the last two years. In terms of the success of DART, the results of this survey
showed that 57.4% of cases resulted in full settlement, and in 8.4% of the cases a partial
settlement resulted. These results are similar to those obtained by the New York Supreme
Court as reported by Meade (1997) above. The second survey, conducted in 1993 by the
ABA Public Contract Law of the Alternative Dispute Resolution Committee, further
confirmed the increasing use of DART to resolve construction disputes. Arbitration was
still the most familiar method of dispute resolution among those surveyed, but mediation
was now rated as the most favorable approach (Stipanowich, 1994).
A 1994 study by the US National Transportation Board on dispute resolution methods
found that 22% of State transportation departments had incorporated dispute review
boards (Section 6.3), 63% used partnering (Chapter 4), 70% “empowered” field
personnel to handle disputes (Section 5.5), and 100% were willing to negotiate (Chapter
5) with the contractor (Civil Engineering, 1994). In April 1996, thirty-three of the most
influential US organizations and federal agencies in the construction industry signed a
declaration calling for the end of litigation in project disputes (ENR, 4/22/1996).
The numbers demonstrate how in the United States the use and popularity of ADR
extends beyond the field of public contracts and construction. An additional survey
conducted in 1997 by Price Waterhouse, Cornell University, and The Foundation for the
Prevention and Early Resolution of Conflict (PERC), revealed that 528 of the largest
corporations in the United States reported extensive use of ADR (Lipsky et al., 1997).
The results, summarized in Table 6, reflect the opinion of chief litigates, deputy counsels,
and corporate counsels of the corporations responding to the survey.
Table 6 - Summary of Results of Survey on the Use of ADR (Lipsky et al., 1997)
30
EVOLUTION OF DART
As shown above, mediation was the most favored ADR approach in this sample of
Corporate America. According to the answers provided, 88% of these corporations had
used mediation to resolve disputes in a number of fields (i.e., labor relations, employee
termination, drug testing, and lawsuits brought about by customers). Arbitration was the
second most favored ADR technique, with 79% claiming experience with this method.
Interestingly enough, the technique that combines mediation and arbitration (Med/Arb)
was the third most frequently used approach. Med/Arb (Section 8.1) has encountered
some resistance because of the two roles played by the third-party neutral and the type of
information that can and should be disclosed during mediation without affecting the
possible arbitration process.
In terms of the expected reduction in the use of Mediation and Arbitration shown in
Table 6, the survey attributes it to concerns declared by the respondents as to the
qualifications of the third parties involved in the procedures. Almost half expressed “...a
lack of confidence in the arbitrator” (Lipsky et al., 1997) and close to 30 say there are
not enough qualified arbitrators. With regards to mediators, 30% of responses raised the
issue of lack of confidence and 20% the problem with qualifications and experience. 7
The higher concerns expressed with regards to the arbitrators can be explained by the fact
that their decisions are final and binding, while the mediator does not even offer a
solution proposal.
The survey also revealed some other interesting aspects of ADR in American
corporations:
• Smaller companies were found to be more inclined to follow adjudicative
procedures. They make a very limited use of ADR.
• The selection of ADR methods was found to be related to the type of dispute
(DRT, 1/1999):
− Mediation is preferred to arbitration in all types of disputes except
international cases, where 50% of the respondents said they would use
arbitration, while only 43% would attempt mediation.
− In personal injury disputes, 60% have used mediation, but only a third have
used arbitration.
− In product liability cases, 40% have used mediation, versus only 24% that
have used arbitration.
− In long-standing relationships and contracts, 92% of the cases where
mediated.
These findings show how ADR provides a flexibility to select how disputes will be
addressed and resolved that is not found in the court system. Corporations are selecting
different ADR methods for each type of dispute, as ADR has allowed them to tailor their
approach to each specific case.
In response to this evolution of ADR methods, the construction industry has incorporated
to the traditional DRL numerous methodologies to avoid conflict and to resolve disputes
more creatively and efficiently. These changes have contributed to the creation of a
construction DART model. The authors of this book have identified two models of
conceptualization of DART that are presented in the following section.
This section provides a model for the organization and implementation of Dispute
Avoidance and Resolution Techniques (DART). Two different schemes for the
organization of construction DART are reviewed, and the Dispute Resolution Ladder
(DRL) has been chosen and implemented in the following chapters for all the techniques
found by this book. This selection is based on two features of this model; first, the DRL
model lends itself to practical applications and second, it gives a significant importance to
dispute prevention techniques by placing them as the first step in any successful system
of dispute resolution in construction.
Dispute Resolution
Conflict Management
32
EVOLUTION OF DART
Conflict Management
Non-Binding
Dispute Review Boards
Dispute Review Advisors
Negotiation
Quality Matters
Total Quality Management
Coordinated Project Information
Quality Assurance
Procurement Systems
Partnering
Dispute Resolution
Non-Binding Binding
Conciliation Adjudication
Executive Tribunal Arbitration
Mediation Expert Determination
Litigation
Negotiation
These notions are useful in the sense that they present an organized view of the different
steps involved in ADR and the various alternatives available. However, there is a
different approach that will prove to be eloquent in explaining the steps to follow.
LITIGATION
BINDING
NONBIDING
Usually, at the middle stages, (Standing Neutral and Non-Binding) third parties are
brought into the process and claims begin to depart from the job site level. The goal of
external participants is to help disagreements return to a lower stage in the ladder, by
identifying the real issues in dispute, finding a common ground between parties, helping
in the analysis of technical problems, and/or assisting parties improve communication.
Finally, as the parties get to the upper stages (i.e., binding and litigation), there is
decreased participation of those who are really involved in the project, and it becomes
less likely to invent alternative mechanisms to amicably solve the dispute, and the
process starts to see a dramatic increase in costs and hostility.
The six-step DRL is flexible enough that it allows the development of project-specific
DRL, something found in the two contracts of the FIDIC and the World Bank, where the
escalation did not include all the steps and allowed the parties to attempt an ADR
solution. The literature review also finds international applications of DART, with
interesting variations depending on culture.
An example of the diversities in DRL is provided by the Canadian Construction
Document Committee contract of 1994 (CCDC 2); a standard form of fixed-price terms
and conditions designed for projects with three basic participants: the owner, the design
or engineering consultant, and the contractor (i.e., Design-Bid-Build). The CCDC 2
provides a clear application of the modern DRL, recognizing some of the stages of the
process and highlighting the benefits and challenges of each one (Figure 12). In terms of
dispute resolution, the CCDC 2 contains specific provisions that make DART an integral
part of the contract.
34
EVOLUTION OF DART
LITIGATION
BINDING ARBITRATION
MEDIATION
NEGOTIATIONS
DESIGNER/ENGINEER
DETERMINATION
• “It is too expensive, in that costs often exceed the value of the claim.
• It is too slow.
• There is a lack of equality between the powerful wealthy litigant and the under-
resourced litigant.
• It is difficult to forecast both the cost and the length of litigation.
• It is incomprehensible to many litigants.
• It is too adversarial, and cases tend to be run by the parties with the rules of
court often ignored.” (Woolf, 1996)
These problems associated to costs, delays, uncertainty of outcome, complicated rules,
and lack of control over the process are affecting the way different industries are dealing
and solving their disputes without turning to the judicial system. In the specific field of
construction, Gould et al. (1998) have identified three factors that have influenced the
traditional dispute resolution procedures of this industry in the UK, moving it away from
litigation:
1) General dissatisfaction with arbitration.
2) An increase in the number of conflicts and disputes within the construction
industry.
3) International influence reflected in the worldwide movement towards alternative
dispute resolution methods.
These challenges faced by the construction industry of the UK have been equally found
as challenges in the United States. In a 1998 speech on the future of the construction
industry, Henry Michel, chairman emeritus of Parsons Brinckerhoff Inc., described the
current state of the American building industry as follows (Michel, 1995):
“We are members of the largest productive industry in this country and in the
world, and we are members of an ailing industry, a troubled industry. Consider
the following:
• The construction industry’s share of the gross domestic product [in the US] has
declined 20% in the past 20 years.
• Construction costs [in the US] have increased 60% more than inflation in the
past 10 years.
• We account [in the US] for 26% of the nation’s fatal accidents.
• Litigation expenditures [in the US] are increasing at 10% per year [for the past
ten yeas].” 8
Productivity, innovation, cost savings, safety, and litigation expenses are critical areas for
the future of the construction industry. It is in these areas that the industry must invest the
most to advance successfully into the next century 9. In the United States alone, $60
billion are spent every year on lawsuits, of which the construction industry accounts for
nearly $5 billion. Michel points out that for every $1 billion saved on litigation in
construction the industry could generate 40,000 new jobs, with the direct benefit of
reducing legal expenses for all parties.
The fact that litigation expenditures continue to increase year after year is astounding.
This book aims at providing information to the reader on ways in which these expenses
could be reduced. The problem of excessive litigation costs is reiterated in a paper written
by Bristow (1998), where an estimate of the legal costs associated with a hypothetical
lawsuit between a contractor and an owner are calculated and compared to the initial
claim amount. They included in their cost analysis, three basic items based on the
Canadian legal system: lawyer’s fees, trial costs (i.e., filing fees and expert witnesses),
36
EVOLUTION OF DART
and opportunity costs (i.e., time spent by key personnel in the litigation process). The
results of these calculations show that the cost of the procedure for the contractor
surpasses by almost 100% the original amount being claimed. The authors conclude that
the industry is “…being hampered by the tremendous amount of resources being utilized
in the litigation of claims.”
This exercise shows how the judicial system is no longer the most suitable and cost
effective way to resolve construction disputes. Fueled by this reality, together with the
fact that projects have become more complex and competition has increased, the
construction industry has been forced to develop and experiment with alternatives to
litigation in order to find cheaper and more effective ways to solve disputes. Thus, new
approaches have been designed to overcome the rigid and adversarial attitudes and
contract forms normally used in construction. These evolved to prevent the development
of conflicts during the execution of the project, and to help companies forge longer
lasting relationships with clients, designers, as well as subcontractors, while still solving
their disagreements. These new and innovative approaches and techniques are known as
Dispute Avoidance and Resolution Techniques (DART). 10
The changes in the construction industry are going beyond the application of an
alternative technique to court litigation (i.e., Mini-Trial or Arbitration). While the 80’s
saw the construction industry “...turned on itself – [as] each part of the construction
“team” started indulging in a seemingly unending orgy of risk-shifting, finger pointing,
and costly litigation” (ENR, 7/11/1994), the 1990s saw a revolution in the field of
construction dispute resolution, as the construction “team” has understood the negative
long-term effects of the approaches of the past decade. The team approach is being
redesigned, going from an adversarial system towards a collaborative environment in
which the limits are defined, but communication flows without unnecessary barriers.
Many project teams have developed radically new philosophies towards achieving the
project goals such as Partnering, Total Quality Management, and Risk Sharing. Some
industry experts claim that the industry is going back to the “old fashion way of doing
business”; when quality, service, and collaboration among parties were the norm, and
disagreements “...were settled on the jobsite at an informal meeting between the resident
engineer and the contractor on the basis of a handshake.” (Treacy, 1995).
In the international arena, the need to improve communication and limit the chances of
litigation is more evident. Large engineering endeavors are bringing together companies
with diverse cultural backgrounds, legal systems, labor laws, objectives, interests,
contractual agreements, competitive conditions, and priorities. Complicated
communication arrangements, changing conditions, and varying requirements are now
part of most large jobs. Therefore, in order to avoid having this diversity result in
disagreements, channels of communication must be developed, and a collaborative
environment for exchanges of information implemented.
The construction industry is suffering from an acute disposition to conflict and litigation.
Many contractors even take the strategy of bidding low and hope to make up their losses
in claims. This strategy makes disputes appear inevitable. Litigation expenses have
become a significant cost item for many projects, affecting productivity and damaging
business relationships. Professor Justin Sweet, of the University of California at
Berkeley, summarized this situation by saying:
“... a dispute-prone process such as construction will have the propensity to call
on the legal system to enforce contracts or obtain compensation for losses.
Participants ... must do all they can to avoid disputes, to seek to settle those that
do develop, and to be aware of the role law plays in the process.” (Sweet, 1994)
Based on this reality the construction industry has developed, during the past fifteen
years, a number of different mechanisms and methodologies to prevent, manage, and
2.5 SUMMARY
Conflicts have existed as long as human beings have interacted with each other.
Consequently, for centuries, civilizations have struggled to develop different ways to
manage and resolve disputes among its members and with other cultures. For some,
conflict resolution meant the difference between peace and war, for others mediation and
conciliation have simply become a way of living. A common feature in these approaches
to dispute resolution has been a tendency towards a dichotic and polarized way of
understanding the possible outcomes. The two alternatives have been an amicable
settlement or an openly adversarial approach that usually ended the relationship among
parties.
From the formalization of ancestral forms of dispute resolution, evolved the traditional
two-step resolution ladder, where determination by the design professional and binding
arbitration are the two poles of the model. However, as construction projects became
larger, multi-cultural, and more complex, the two-step Dispute Resolution Ladder (DRL)
has become a limited tool. The traditional model is often unable to meet the needs of the
project participants in an effective, timely and cost-efficient manner, without necessarily
jeopardizing the relationship between the parties involved.
Stemming from the limitations of the traditional two-step model, new approaches have
emerged trying to introduce alternative techniques to be used throughout the process of
conflict management. First, this chapter reviewed Fenn et al.’s ‘conflict continuum’ and
the way it served as a useful tool to divide multiple binding and non-binding strategies
across this spectrum. Second, the Dispute Resolution Ladder proposed by Findley (1997)
was chosen as the guide for the chapters to follow. The selection of this model to
organize the dispute avoidance and resolution techniques found by this book was based
on two characteristics of this model. First, this model has the advantage of lending itself
to practical applications, as clearly shown in the CCDC 2 contract. Second, the DRL
emphasizes the important role of prevention techniques in dispute resolution process for
construction projects. This prevention stage in the DRL is the focus of Chapter 3, where a
series of techniques designed to mitigate some of the common sources of disputes
discussed in this chapter are introduced together with some examples of their
implementations.
38
EVOLUTION OF DART
it implies a “loss of face.” How much influence does a contractor’s reputation have
in today’s society? How does this perception vary from private and public owners?
What about the owner’s reputation?
2.4 What role should professional organizations play in developing DART?
2.5 What role should large bureaucratic owners such as the World Bank (Section 2.2.2),
the Hong Kong government (Section 2.2.3), or the US Federal government play in
developing DART?
2.6 In the United States, conflicts arise in bidding situations when there is not
transparency in the bidding process. Can frame contracts, as described in Section
3.4.5, be effectively used in government procurements and still be fair? On what
basis should you select the contractor if a price is not predetermined, according to
the frame contracts? Are there other ways to incorporate objective alignment other
than frame contracts?
2.7 The revision of the Red Book (Section 2.2.1) aimed at addressing claims earlier in
the construction process. What are some advantages/disadvantages of addressing
conflicts during the process and after the process?
2.8 How important is it for the mediators/arbitrators/judges to have an
engineering/construction background? Can a reasonable and fair judgment be
reached if they do not have this technical expertise? How much credibility will their
decision carry?
2.9 Findley (1997) breaks down the DRL into six steps (Section 2.3.2). Does this
extension from the two-step DRL draw out the process or does it increase the
efficiency of handling claims? At what point are there too many steps in the DRL?
2.10 What are the differences between the CCDC 2 Contract DRL and the DRL in Figure
11 adopted from Findley, 1997 (Section 2.3.2)?
2.7 REFERENCES
[DRT, 1/1999] Dispute Resolution Times, (1999). New Law Authorizes ADR
Use in District Courts. p. 2. January
[DRT, 4/1998] Dispute Resolution Times, (1998). NJ Law Calls for ADR in
Public Construction Projects. p. 14 April
[ENR, 4/22/1996] Engineering News Record. The First Step is the Hardest. Vol.
236 (16). p. 114. April 22, 1996.
[ENR, 7/11/1994] McManamy, Rob. Industry Pounds Away at Disputes.
Engineering News Record. McGraw-Hill, New York. pp. 24-
27. July 11, 1994.
[Fenn et al., 1997] Fenn, Peter, Lowe, David, and Speck Christopher, (1997).
Conflict and Dispute in Construction. Construction
Management and Economics (1997) 15, p. 513
[Fenn et al., 1998] Fenn, Peter, O’Shea Michael, and Davies Edward (1998).
Dispute Resolution and Conflict Management in Construction
an International Review. E & FN Spon, London, ISBN 0-419-
23700-3
[FIDIC, 1957] FIDIC. Conditions of Contract for Works of Civil Engineering
Construction, First Edition, 1957.
[FIDIC, 1987] FIDIC. Conditions of Contract for Works of Civil Engineering
Construction, Fourth Edition, 1987 (reprinted in 1988 with
editorial amendments and reprinted in 1992 with further
amendments)
[Findley, 1997] Findley, Douglas. Construction Claims Preparation Under
ADR. 1997 AACE International Transactions C&C.01.1-
C&C.01.4. 1997.
[Flood et al., 1993] Flood J. and Caiger A. Lawyers and Arbitration: The
Juridification of Construction Disputes. Modern Law Review.
Vol 56. pp. 412-440. c Blackwell Publishing, 1993. Reprinted
with permission of Blackwell Publishing.
[Goudsmit, 1985] Goudsmit, J. J. Frame Contracts and the Closing of the Eastern
Scheldt. The International Construction Law Review Vol. 2 (2)
pp. 117-127. January 1985.
[Gould, et al.,1998] Gould, Nicholas and Cohen, Michael. ADR: Appropriate
Dispute Resolution in the U.K. Construction Industry. Sweet &
Maxwell, London. Vol. 17. April 1998.
[Groton, 1997] Groton, James. ADR in the Construction Industry. Dispute
Resolution Journal Vol. 52 (3) pp. 48-57, Summer, 1997.
[Ide, 1993] Ide III, William R., (1993). ADR: Giant Step Toward the
Future. Dispute Resolution Journal pp. 20-23, December
[King et al., 1994] King, Henry T., and Le Forestier, Marc A., (1994). Arbitration
in Ancient Greece. Dispute Resolution Journal. pp. 38-46
September
[Li, 1970] Li, V.H. The role of law in communist China. China Quarterly.
No. 44, October-December, pp 66-111.
40
EVOLUTION OF DART
[Lipsky et al., 1997] Lipsky, David B., and Seeber, Ronald, (1997). The Use of ADR
in U.S. Corporations: Executive Summary. Cornell University
School of Industrial and Labor Relations. Downloaded from the
web on April 25, www.irl.conell.edu
[Meade, 1997] Meade, Robert C., (1997). Commercial Division ADR: A
Survey of Participants. New York Law Journal p. 1. October 17
[Michel, 1998] Michel, Henry. The Next 25 Years: The Future of the
Construction Industry. Journal of Management in Engineering.
Pp. 26-28. September/October, 1998..
[Molineaux, 1995] Molineaux, Charles B., (1995). Settlements in International
Construction. Dispute Resolution Journal Vol. 50 (3) pp. 80-85.
Jul-Sep
[Moore, 1989] Moore, C. The Mediation Process. Jossey Bass, San Francisco.
1989.
[Overcash, 1998] Overcash, Allen. The Truth about Partnering. Limitations and
Solutions. Punch List Vol. 21 (2) August, 1998.
[Pierce, 1994] Pierce, Lemoine D., (1994). Mediation Prospers in China.
Dispute Resolution Journal pp.19-21. June
[Scott, 1995] Scott, Donahey M., (1995). Seeking Harmony. Technique
Dispute Resolution Journal. pp. 74-78. April-June
[Seppala, 1991] Seppala, Christopher. Contractor's Claims Under the FIDIC
Civil Engineering Contract, Fourth (1987) Edition II.
International Business Lawyer Vol. 19 (9). Pp. 457-460.
Q49October 1991.
[Stipanowich et al., Stipanowich, Thomas J. and Henderson Douglas, (1992).
1992] Settling Construction Disputes with Mediation, Mini-trial and
Other Processes. The ABA Forum Survey, Construction
Lawyer, April
[Stipanowich, 1994] Stipanowich, Thomas J., (1994). The Quiet Revolution in
Government Contracting: Dispute Avoidance and Resolution.
30 Procurement Lawyer 3
[Stipanowich, 1996] Stipanowich, Thomas J., (1996). Arbitration: Innovation and
Evolution in the United States Construction Industry. Wake
Forest Law Review Vol. 31 (1) pp. 65-182. Spring
[Sweet, 1994] Sweet, Justin. Legal Aspects of Architecture, Engineering and
the Construction Process. 5th ed. St. Paul: West Publishing
Company, 1994.
[Treacy, 1995] Treacy, Thomas B., (1995). Use of ADR in the Construction
Industry. Journal of Management in Engineering Vol. 11 (1) pp.
58-63. January/February, 1995.
[Woolf, 1996] Lord Woolf. Access to Justice: Final Report to the Lord
Chancellor on the civil justice system in England and Wales.
The Lord Chancellor's Department. July, 1996.
2.8 ENDNOTES
1
Solon’s legacy is the codification of the laws that defined Athens’s democratic
assembly (King et al., 1994).
2
The term “loveday” was used “…because the Quiet and Tranquility that should follow
the ending of the controversy” (Hurt, 1995).
3
Apparently, this has been the general thought among drafters of contracts and
construction law, since in every country reviewed as part of this book, arbitration was
found to be the standard for construction dispute resolution. In a number of these
countries, the arbitral proceeding was found to be contingent upon the completion of the
project.
4
Requiring a report from the mediator is a departure from the neutral facilitator role
normally assigned to this person. The fact that this project was very much under public
scrutiny might be the reason for wanting to have a written document explaining the
recommendations of the mediator.
5
The recent American Arbitration Association has incorporated this feature to the new
construction rules (See Section 8.3).
6
This program includes mediation before a trial date can be scheduled.
7
This problem of qualifications of the third party has been addressed in the 1996 revision
of the American Arbitration Association of the Arbitration Rules for construction
disputes.
8
For example, from 1983 to 1990 the number of construction arbitration cases filed with
the AAA grew from 2,675 to 5,440 (MacManamy, 1994), or approximately at an average
15% per year. From 1994 to 1996, the number of cases filed with the AAA grew at an
average of 8% per year (Fenn et al., 1998).
9
Thomas (1998) reports that litigation is discouraging engineering innovation and
technological advancement in construction projects. Consulting engineering firms are
unwilling to recommend creative designs “...out of fear of litigation-frenzied attorneys.”
10
For easier reading Dispute Avoidance and Resolution Techniques will be abbreviated
as DART.
42
C H A P T E R
3
STAGE 1:
PREVENTION
“For every $1 you spend on claims management
during the front-end of the project, you save at least
$20 to $25 in claims during construction.”
(Zack a, 1997)
KEY CONCEPTS
Risk Sharing ..................................................45 Escrow Bid Documents..................................... 49
Project Award and Delivery Systems ............50 Incentive Programs ........................................... 56
Engineering and Documentation ...................59 Cost and Schedule Controls .............................. 59
Dispute Resolution Clauses ...........................65 Training and Development ............................... 65
43
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION
project.
Realizing that these conflicts are going to occur is an important step in preparing a
conflict management strategy. After the realization that conflict will occur, the next step
is deciding how to prevent them. This case raises several questions. What effect does the
GMP have on the number of conflicts that may surface on the project? Is this the
appropriate delivery system? With numerous parties involved, how might they keep
misunderstandings at a minimum? How should the project risks be allotted?
44
STAGE 1: PREVENTION
risks are distributed more justly also sets the stage for greater communication and
interaction among the parties, resulting in more honest and productive negotiations when
unforeseen conditions become apparent. An example of the concept of Shared-Risks
between the owner and the contractor in a construction contract is summarized in Table
7.
Table 7 – Allocation of Project Risks under the Shared-Risk Approach (Findley, 1997)
PREREQUISITE RISKS
1 Adequacy of Project X Owner’s project
Financing
2 Adequacy of Labor X Can best assess
requirements
3 Permits and Licenses X Shared X Shared
4 Site access X Owner’s site
PERFORMANCE-
RELATED RISKS
1 Sufficiency of plans X Sets up the
Bidding process
2 Underestimation of X Estimate the contract
Costs
3 Owner furnished X Owner’s choice
material
4 Contractor Furnished X Responsibility
material identified in contract
5 Means and methods of X Area of expertise
construction
6 Delay in presenting X Could be the X Could be the claiming
problems claiming party party
7 Delay in addressing X Party receiving X Party receiving the
and solving problems the claim claim
8 Subsurface conditions X Owns the site
9 Worker and Site X Controls the execution
Safety
EXTERNAL EVENTS
RISKS
1 Governmental Acts X Shared – not X Shared – not
predictable predictable
2 Abnormal Adverse X Shared – not X Shared – not
Weather predictable predictable
3 Acts of God X Shared – not X Shared – not
predictable predictable
4 Cost escalation X Shared – not X Shared – not
predictable predictable
In this table, both parties share external events, which are usually the ones with the
greatest uncertainty, as they are not predictable. Contractors share risks that were usually
46
STAGE 1: PREVENTION
assigned to them exclusively, such as abnormal Adverse Weather conditions, but they
now also share the risks associated with Acts of Gods, easing some the owner's burden.
This type of distribution of risks meets Vega’s (1997) requirement that uncertainty must
be allocated seeking the benefit of all parties and not just an unfair allocation to limit
individual liabilities.
Considering the necessity to improve the distribution of risks in construction projects to
mitigate conflict, the following three contract clauses and methodologies have been
developed.
A clause that allows for controlled price escalation during the life of the project can help
reduce the amount of ‘guesswork’ performed by the contractor when pricing the job.
When contractors are forced in fixed cost contracts to assume 100% of the cost escalation
risk, the owner can be setting the stage for future disputes. In highly competitive markets,
when contractors are pressed to offer savings to their clients, contingency amounts are
usually the first ones to be taken out during contract negotiations. When price escalation
begins to affect the contractors' bottom line, claims tend to follow.
Zack (a, 1997) suggests that on projects over 3 years long or located in countries with
unstable economies, owners should provide in the contract methods to evaluate and
determine price escalation. By doing so, owners reduce uncertainties and limit the
contractor’s liabilities for price adjustment. The contract might set a limit to the price
escalation to be carried by the contractor, leaving anything above that number to the
owner. If significant increases in costs occur during the life of the project, the contract
already has a formula and the conditions to compensate the contractor, eliminating the
need for a claim. An agreement, prior to the existence of open conflict, on the level of
risk each party will assume and the mechanisms to apply if an unexpected price
escalation occurs, will significantly expedite the reviews and approvals, while reducing
costs and time implications.
An example of this occurred for the installation and maintenance of all the moving
walkways and escalators in a major airport. The cost of hiring mechanics that perform
this specialized work tends to fluctuate. Since the maintenance contract was for seven
years, the owner included a bid item to account for this fluctuation. This bid item was tied
to industry wage averages in this field. The result, the owner received six competitive
bids and the contracts had insurance that they if the cost of this labor increased, they
would be compensated for it.
Although research has found that unforeseen ground conditions are a primary source of
delays in construction projects, most owners only address this issue by transferring this
risk to the contractor. The Geotechnical report is provided to the bidders “for information
only” with a disclaimer to the effect that contractors may use that information but are
completely responsible for any interpretations of the data. On the other hand, most
contractors can not afford to make their own soil borings, nor can they hire a
Geotechnical consultant during bidding, so they end up relying solely on the information
provided by the owner. When unforeseen soil conditions are found, disagreements and
claims are common, as contractors will attempt to shift this risk back to the owner.
Because this type of dispute tends to happen at the beginning of the job, they usually
have a significant effect on the overall performance of the project, interfering with many
future disagreements and negotiations on other issues.
Geotechnical Baseline Reports (GBR) provide for a new way to present sub-surface soil
conditions and to distribute the associated risk. This Geotechnical report has an additional
section that includes not only an interpretation of the soil borings and test results but also
an outline of the possible subsurface conditions the contractor should expect to find. This
information is developed by the owner’s consultants and paid for by the owner. With this
information, the owner can require the contractor to include provisions to deal with any
of the possible conditions outlined in the GBR, effectively limiting his risks to anything
beyond those provisions. On the other hand, the contractor’s uncertainty concerning the
sub-surface conditions has now been limited to a set of defined possibilities. The
contractor is free to decide how to estimate and price the work more efficiently, confining
the risks to decisions within his control.
By making this additional information available to the contractors, the owner improves
their chances of getting a more competitive bid, and they establish a baseline to evaluate
and measure future claims on differing site conditions. By sharing the sub-surface risks
with the contractor, the owner reduces the likelihood of disputes on this issue, while at
the same time, it gives the contractor a tool to improve the assessment of the project
costs, schedule, and uncertainties.
48
STAGE 1: PREVENTION
Almost every construction project involves more than one contractor, and owners tend to
become the only responsible party to a number of contracts with different entities. When
one contractor causes delays, the owner usually becomes the defendant in more than one
claim as other contractors, affected by the performance of this one party, move against
the owner for relief. Single prime contracts can limit this situation from occurring, but as
jobs have become more complex, it is impossible to award the total project to only one
party.
In order to reduce this effect, Zack (a, 1997) recommends the use of a Third-Party
Beneficiary Clause in construction contracts. With this clause, owners are able to share
among all contractors and sub-contractors the risks of delays, by making each company
the “intended third-party beneficiary” of all other contracts. Through this clause, owners
can avoid claims that are not caused by them, and contractors can seek relief for delays
caused by other parties directly. Another benefit of this arrangement is that relationships
are less strained, as contractors are not fighting the owner over matters beyond his/her
control, and they can still search for compensation from the third party at fault.
By “freezing” the original bid documents, the project team creates a valuable source of
information to be accessed only when disagreements arise in issues such as productivity,
design details, and equipment selection. The advantages of putting the bid documents in
escrow are two-fold. First, it provides the basis for the review of any claim regarding how
an item was bid, how a detail was interpreted, or what productivity factors were used. For
example, if a change order requires additional excavation and disposal of excess soil,
parties can access the escrow documents and review equipment productivity rates, and
base costs for equipment rental and for disposal of excess material. Also, parties can
review the original quantity take-off performed by the contractor to determine whether
that specific excavation was considered or not in the original bid. Once this information
is determined and agreed by the parties, the respective mark-ups and fees can be
negotiated.
Second, the existence of this ‘as-bid’ database should deter any unfounded claims from
the contractor, since the original documents will not support them. This mechanism can
help prevent disputes and provide information to analyze disagreements faster, in
accordance with a set of variables that can be reviewed by both parties.
Another new approach towards contract award is based on the notion that in general,
owners want to finish their projects at the earliest possible date. Some public owners in
the United States are including in the bid package a line item referred to as “cost per
50
STAGE 1: PREVENTION
day.” Contractors are asked to provide, together with the pricing of all line items, the
schedule duration in days for the project (also known as time of performance). Then, to
obtain the total project cost of each contractor, the owner adds the construction costs (A-
term) and the number resulting from multiplying the “cost per day” of the owner by the
duration submitted by each contractor (B-term). The award is based on the lowest total
project cost.
This award mechanism provides two incentives for contractors that reduce the chances of
problems and disputes during construction. First, contractors are forced to review the
construction sequence in detail and present the shortest feasible construction schedule,
with the aim of keeping the B-term as low as possible. Second, contractors are
encouraged to finish within the time limit in order to realize the full amount of the bonus
(B-term); therefore, they should work with the owner and the design professionals to
resolve potential problems before they become disputes and delay the job. More than 100
projects have been bid and built in the US using this system, and all of them have been
completed on schedule (Zack a, 1997).
The use of Design-Build as a delivery system in the construction industry has grown
significantly as an owner-favored method, both in private and public sector projects. This
system provides the owner with a single-source of project responsibility and a single-
point of communication, so as to avoid the “finger-pointing” and “risk shifting” that often
takes place in other construction approaches such as Design-Bid-Build. Design-Build
projects are generally completed faster, usually with less administration costs for the
owner.
However, Design-Build is not a cure for all project delivery difficulties. Appelbaum
(1998) has identified the following problems with it:
• Loss of control over design by the owner, as they forfeit direct communication
with the designer.
• Selection of the design firm based on price rather than on qualifications.
• Less competition in the selection and award phases, as the owner is required to
compare “...apples to oranges, to bananas in order to choose a contractor,”
since each of the proposals might be different as they represent an interpretation
of what is sometimes very basic design and/or performance parameters.
• The final product is a mixture of owner-contractor objectives and
interpretations, but might fail to meet the original project criteria.
In other words, by transferring the design to the contractor, the owner generates a “gap”
between their objectives and the design process, which is responsible for the translation
of those objectives into plans and specifications. The owner is often left to choose from
three or more completely different proposals, none of which is one hundred percent
satisfactory. To correct these problems in the Design-Build delivery system, Kluenker
(1996) and Appelbaum (1998) propose the concept of “Bridging” to close the gap
between the owner and the design process, without loosing the many advantages of the
Design-Build system.
Bridging divides the Design-Build process into three phases (Kluenker, 1996). In the first
phase, the owner retains a design consultant who is responsible for developing a
conceptual design that satisfies the owner’s basic project needs. During this critical stage,
the owner has control over how his needs and objectives are translated into a very basic
design. Then, competing contractors prepare proposals based on this conceptual design
developed by the owner, complying with the specific requirements set forth in these
documents. The problem of having to compare apples to oranges is reduced, and the
selection can take into account, in addition to the price, the technical solutions proposed
to meet the criteria. Since the information contained in the conceptual design is limited,
the overall design responsibility remains with the design-builder.
In stage two, the design-build team completes the design and the drawings of the project,
while the design consultant acts as the owner’s representative, serving in a “pure agent
capacity” (Appelbaum, 1998). The consultant reviews working drawings to confirm
compliance with design requirements. There is no design responsibility overlap. In the
third stage, the contractor builds the project and the bridging consultant inspects work-in-
progress as the owner’s construction representative.
This system should overcome the disadvantages of the Design-Build delivery system
outlined above as follows:
• Owner’s loss of control over design: With the “bridging” consultant owners
have control of the portion of design that should be more important to them (i.e.,
schematic and conceptual design)
52
STAGE 1: PREVENTION
In order to design and build large-scale, time-consuming civil engineering projects, in the
1970’s the government of the Netherlands developed a type of project delivery system
that is still in use and is known as “Frame Contracts.” Under this scheme, parties start
with only a very broad definition of the works to be completed and accept to negotiate
partial contracts as the design problems emerge and engineers and architects propose
different solutions 1. According to Goudsmit (1985) 2, “...the philosophy of the frame
contract is that whereas a procedure for the negotiation of a price must be incorporated
in it, the real execution of the various stages of the works should only necessitate
agreement on the specification of such works as well as on the time period within which
such work should be completed.” In other words, parties agree on how they will negotiate
a price for works that will be fully defined in the future, with only a specified maximum
duration and some basic performance and quality criteria. The following example from
Belgium should clarify this concept and the reasons behind its development and
implementation.
“In 1975, the frame contract formula was selected by the Government [of
Belgium] for study/design and execution of a seaward expansion of the outer
port of Zeebrugge. The decision was influenced by the success on similar
maritime projects in the Netherlands.
Dutch experience has proved that it is almost impossible to formulate in
advance a ‘cut and dried’ study for projects which extend far beyond the
coastline ... It is also difficult to pre-determine the effects of such projects on the
behavior of beaches and seabed.
... the preparatory study was directed towards obtaining the fullest possible
information about the known or assumed behavior of the sea and the seabed.
But surprises always occur because not all of the sea’s reactions can be
predicted in advance,...This requires rapid adaptations of the design and
execution plans during the construction period without incurring costly delays
or protracted discussions on claims.
The frame contract, which defines general but strict rules and limits for quality
control, timing and prices, makes constant consultation possible between the
Government and contractors responsible for design. Accordingly, studies and
construction plans can be either amended or even changed as and when the
need arises during the course of the project to ensure the utmost efficiency and
completion on schedule.” (Ir R. Simoen, cited by Goudsmit, 1985).
Through the use of the Frame Contract parties in construction have been able to
effectively introduce the concepts of objective alignment, risk allocation, trust, and long-
term commitments to enhance efficiency and reduce conflict in large scale engineering
projects. By understanding the difference between “static agreements” (like the sale of a
house) and “relational contracts” such as construction projects (Overcash, 1998); and by
following this advice to concentrate more on the dynamics of the process than on its fixed
elements, the Frame Contract creates a resourceful environment to manage uncertainty
while designing and building large-scale projects. The benefits of this approach are not
limited to the cases in which environmental uncertainties create a time-related concern (a
typical worry in Nordic countries concerning the sea). Rather, they simply facilitate the
task of dealing with the unexpected by effectively acknowledging it as a natural part of
construction.
Among the most common delivery systems for construction projects in the United States,
Design-Build is the closest one to a Frame Contract. However, there are significant
differences between the traditional Design-Build and the Frame Contract, with regards to
key aspects of the contract and the criteria for the selection of the contractor. Table 8
summarizes these differences.
54
STAGE 1: PREVENTION
ASPECT OF
FRAME TRADITIONAL DESIGN-
THE
CONTRACT BUILD CONTRACT
CONTRACT
Only roughly defined. The owner
usually has a rough estimate, but
the design is not even schematic The total value of the contract is
Contract Value to allow for the development of a known, at least in the form of a
budget. Prices are negotiated as firm budget.
the design is completed and the
work is ready to be executed.
Only certain key dates are
Usually the owner sets the
specified, usually by stages. The
maximum duration and some key
contract will set a limit for the
milestones that must be met by
Schedule latest acceptable finish date.
the contractors. In the proposals,
Beyond that, the schedule
contractors include a schedule to
specifics are developed as the
perform each phase of the project.
project is defined.
The owner provides some form of
Only a broad definition of the
schematic or conceptual design.
problem exists, and a general
Design The contractors include in their
description of the works to be
Parameters proposals their initial
performed is included in the
interpretation of those
contract.
parameters.
Only a broad definition of how
the works are to function and
Specific owner requirements and
perform is included. Contractor
Design performance criteria is detailed in
know-how, new technologies,
Performance the tender documents and
and design decisions will
therefore in the contract.
determine the final performance
criteria for the project.
Contract focuses on the
relationship. Because there is
little definition at the award stage,
the contract sets limits that will
Terms and help guide the relationship and Varies from contract to contract,
Conditions the future definition of the but it is usually more formal.
project. Special emphasis is given
to the procedure to negotiate a
reasonable price for the works as
the design develops.
A balance allocation of risk is Varies from case to case, but one
incorporated in the contract in of the basic premises of design
Risk
order to manage the high degree build contracts was that most of
Allocation
of uncertainty at the beginning of the risks were assumed by the
the project. contractor.
ASPECT OF
FRAME TRADITIONAL DESIGN-
THE
CONTRACT BUILD CONTRACT
CONTRACT
Each owner will define the
The contract clearly defines
dispute resolution mechanism,
procedures to ensure that
but many fail to do so assuming
negotiations are completed and
that by awarding a Design Build
Dispute issues are resolved. Alternatives
contract all project risks have
Resolution are given to avoid disruptions
been assigned to the contractor
Clauses because of a failure to agree on a
and therefore problems will be
certain issue. Arbitration is the
solved within the contractors’
alternative of last resort.
scope of work.
As the project develops and parts The Design Build contractor has
of it are defined, the owner can control over 100% of the works
negotiate and issue partial under its scope of work. Some
Partial contracts to the Frame contractor. contracts might require
Contracts The owner can also incorporate subcontractor approval by the
new subcontractors if owner, but no separate partial
negotiations fail or certain contracts are issued as the design
technical expertise is required. develops.
Trust, previous experience,
quality of previous work, state of Price, proposed solution,
Selection
the art technology, financial schedule, experience and usually
Criteria
stability, willingness to assume price again.
risk, and reliability.
What the table shows, is that more flexibility is granted to the parties under the Frame
Contract, allowing them to tailor decision-making to the specific situations that emerge as
the project progresses. In the description of the Frame Contract the reader will find words
like rough, certain, broad, and general, which demonstrates its openness to change and
constant adaptation.
56
STAGE 1: PREVENTION
if the contractor has earned the incentive, and second, if the goals will be achieved based
on the progress made up to that point.
Three incentive approaches that encourage the alignment of the objectives of the different
parties and promote collaboration and cooperation during the execution of the project are
presented below. The first two incentive programs were identified by the Construction
Industry Institute (CII 114-1, 1998) during a recent study conducted by the organization.
The third program comes from an article by Zack (a, 1997).
In order to align owner and contractor objectives to improve timely completion of the
project within the stipulated budget allocation, owners can develop an incentive program
that rewards contractors when they meet cost and/or schedule goals. By addressing the
problems of cost overruns and schedule slippage’s through the incentive program the
owner increases his/her control over two important sources of disputes in construction,
and promotes a collaborative approach among the construction team. The owner profits
from meeting his/her planned schedule/cost projections, while the contractor shares in
part of the benefits. The following example shows a successful application of this type of
incentive program.
Howard et al. (1997) report that for a project worth over $100 Million to replace a
wastewater drainage system, the owner proposed the contractor a 15% share in the
benefits to be obtained from an improvement in the contractor’s performance. The owner
developed a value matrix for: “...cost underrun versus budget, dollar value for
completion before schedule date, and reduced owner overhead relative to the original
plan.”
As shown on Table 9, the contractor’s objectives can be aligned with those of the owner
in the categories defining the incentive. They represent for the contractor the only way to
acquire additional income from the execution of this project.
Table 9 – Objective Alignment through Incentive Program
According to Howard et al. (1997), in this instance the construction team was able to
surpass the owner’s cost and schedule goals, and the contractor earned an additional $3.5
Million as an incentive (3.5% of original contract amount).
In this example of an incentive program, the owner and the contractor agreed to have part
of the fee contingent on periodic engineering and/or construction performance
evaluations, executed by the owner. In a cost-plus-fee project, the contractor’s fee was
divided as follows: 15% of the fee was a fixed amount, 15% was based on actual man-
hours in engineering activities, 35% was tied to performance in engineering, and the
other 35% to performance in the construction phase (Howard et al., 1997). Then, in order
to process the request for payments for 70% of the fee, the owner completed quarterly
subjective evaluations of the contractor’s performance. A minimum score was set as a
payment requirement, and the contractor was able to recuperate any loss income from
previous months by exceeding a specified score with superior performance in the
following periods. The project was completed ahead of time and under budget.
This incentive program provided benefits to both the owner and the contractor. The
owner realized the project within the specified time and budget, while the contractor was
paid the full amount of its fee; it was able to adjust and correct any problems during the
execution thanks to the quarterly evaluations; it developed and maintained a good
relationship with the client during and after the project; and it spent less resources (i.e.,
field and office overhead staff and equipment rental) by finishing ahead of schedule.
Moreover, the owner and the contractor resolved all project disagreements at the site
level, without the need for the intervention of any third party.
According to study by CII (114-1, 1998), subjective evaluations of project performance
give the owner the ability to address areas that are not normally covered by the contracts.
For example, CII suggests that the owner can include “customer satisfaction feedback as
part of the incentive” package for the contractor. However, CII warns in the conclusions
of this 1998 study, that teams need “specific targets and milestones to aim at throughout
the total duration of the project, and an incentive totally dependent on a subjective
determination, will most likely result in failures.”
58
STAGE 1: PREVENTION
full bonus amount. This approach works in two ways, first, it is an incentive to finish on
time, and second, it is a disincentive to submit delay claims.
One way to reduce disagreements and disputes based on contract ambiguities is to carry
out constructability analysis. This analysis, performed during the planning, design, and
procurement phases, can mitigate problems and claims during construction. Moreover, it
can identify errors, omissions, and impractical details, which would have been uncovered
by the contractor or supplier, resulting in additional costs and delays for the project. In
Section 4.4 the application of the concept of constructability analysis is provided when
the example of Lean Construction is presented. In this case, the contractor assigns
structural engineers to work with the design team in order to improve the construction
details of the facility and helps expedite getting the structure off the ground.
90 days, the officer must review it with the contractor and submit a proposal for
‘amicable settlement’; then the parties have 60 days to negotiate a solution. If they fail to
resolve the matter after the 60 days, either party may proceed with arbitration after final
completion.
If claims develop
Negotiations to resolve and/or they remain Once claims
claims. Outstanding outstanding are
claims have to be reported
included subsequent and
SAL reports documented
Claims need to
be incorporated
into SAL report
If claim
exceeds 10%
of contract
90 days 60 days
With these requirements, the Italian Public Sector has established a procedure and
specific time periods for the negotiation of large claims. These claims will go through a
process of Structured Negotiations (Section 5.6), before arbitration can be utilized to
settle them. Moreover, by requiring that all claims be acknowledged and reported every
pay-period, this owner is promoting that the on-site representative and the contractor
meet and attempt to settle the claims to eliminate them from every SAL report (this type
of incentive to negotiate disputes during construction is reviewed in Section 5.5 under
Step Negotiations).
By assuming a pro-active approach like the Italian Public Sector, in the identification,
management and negotiation of disputes (i.e., costs and schedule changes), owners have
found ways to reduce litigation, encouraging the building team to attain the objectives
outlined in the famous cliché. Projects that fall out of schedule and/or miss budget
allocations are prone to disputes and confrontation. The following case provides a
concrete and successful application of the concept of owner intervention as a strategy for
dispute prevention in the Canadian construction industry.
60
STAGE 1: PREVENTION
In certain instances, owners have included as part of the contract a requirement that the
contractor submits a certified statement of all costs incurred in the project, before the
certificate of final completion is issued. With this information, the owner can evaluate
any “after-completion” claims the contractor might submit after receiving the certificate
and the retention moneys. More importantly, this requirement deters unfounded claims by
the contractor once he/she is clear from delivering the project.
These after-completion claims can become very complicated as data is scarce and job-site
people are no longer involved. Therefore, a certified cost report can provide important
information for a more accurate review and faster negotiation of any final settlements.
Owners can use certified payroll submittals by their contractors for two very important
aspects of the project. First, by keeping a record of actual labor expenses, owners will be
better prepared to analyze and negotiate any claims where labor costs are an issue.
Second, by tracking actual labor expenditures against a resource-loaded schedule, owners
have an additional tool to assess progress and identify delays. With this information the
owner can anticipate delays and approach the contractor with data he/she generated to
negotiate a remedial action plan.
Another way to gather information for faster dispute analysis and approval is for the
owners to negotiate with the contractor’s unit prices for equipment and labor before the
contract is awarded. With this information, owners can issue change orders and request
additional work while knowing the approximate cost implications of their decisions.
Moreover, contractors should provide more “honestly priced” change requests, since the
information has to be based on this schedule of values (Zack a, 1997).
In addition to equipment and labor prices, owners and contractors can agree on specific
unit prices for work items that will be typical for the type of project. For example, in a
renovation of an existing facility, both parties can agree on unit prices for items, such as
demolition, paint, clean up, and disposal of construction debris. These prices can then be
used as the project develops and unforeseen conditions require additional work.
Even though there are many nationally recognized equipment, labor, and work-item rate
schedules for costing, each job can vary significantly from the assumed conditions of
these sources of pricing information (Hoctor, 1989). Therefore, the parties should agree
to this information before hand and include it as part of the contract.
With the rates for equipment, labor, materials, and work items agreed upon before-hand,
parties can then concentrate on analyzing, for example, whether the crew-type or
equipment used were the most appropriate, whether the time used to complete the work
was not affected by other conditions, and whether the production rates used were
reasonable. Hence, the surprise factor (i.e., uncertainty) associated with change orders
that are priced after being executed can be eliminated.
Zack (a, 1997) suggests that “...success is more likely if people become stakeholders.”
This is especially true for the project schedule, and “...one way to see that all members of
the project team become stakeholders in the schedule is to provide for joint project
scheduling.”
Instead of having the contractor prepare and submit for approval the schedule, the owner,
the contractor, the major subcontractors, and the suppliers participate jointly in the
development of the baseline program for the project. This joint development eliminates
any schedule games (i.e., hidden float, change of sequence, front-loading) and forces
parties into communication and collaboration during the planning stages.
Once everyone agrees on the joint timetable, and the job begins, updates are prepared by
all parties and will represent the consensus of everyone involved in the project. Delays
can be identified and negotiated as parties complete the schedule updates jointly, since
now they all have a ‘stake’ in what is presented to senior management. Schedule reviews
and change order impacts are also performed together, thus reducing the chances of
62
STAGE 1: PREVENTION
future delay claims and disruption disputes by one of the parties. The following example
clarifies the application of this technique and some of the benefits it can generate.
Following the same logic as the Cost Statement Submittal (Section 3.7.1), owners can
request an as-built schedule from the contractor before issuing the certificate of final
completion and releasing the retention. As with the certified cost report, the as-built
schedule becomes the basis for review of any after-completion claims. By submitting a
schedule that reflects the actual construction sequence and total duration, the contractors
will be discouraged to submit, at a later date, delay claims that were not previously
shown. If the contractor has plans to present any delay claims at the end of the project,
they will have to address them in the as-built schedule, and they will be required to arrive
at a settlement prior to receiving the final completion certificate.
Impact or indirect costs like home office overhead, field staffing, or overtime work, that
can be associated to change order work beyond hard costs (i.e., labor, equipment, and
materials), have been identified as an additional source of disagreements in change order
pricing. To improve negotiations and reduce the amount of disagreements, owners and
contractors can agree beforehand on the guidelines and methods to determine and limit
these impact costs. Zack (a, 1997) suggests that a set of impact factors can be developed
for issues like “timing of changes, number of trades involved, effect on the schedule,
effect on office and field staffing, and the cumulative nature of the disruption.”
When change orders are priced and negotiated, owners and contractors will be able to
incorporate in the total amount, both hard costs and impact costs, and they will be able to
settle on a final adjustment to the contract value. Consequently, no further discussions or
claims will be required after these negotiations because the changes will include
everything (ENR, 9/11/1995). An example of a forward change order is presented in
Chapter 5.
When contractors price change orders, which in most cases is a contract obligation, they
usually include “reservation-of-right” language to allow themselves future requests for
additional time or money to complete the job. In other words, contractors include a
disclaimer such as “...further review is necessary in order to assess the impact this
change will have on the schedule’s sequence of activities and the overall project
duration” 5, with the intention of leaving the door open for future review. In fact, most
contractors feel the need to include such provisions in their change order cost proposals,
for they have not really completed a total assessment of the time and cost implications of
the change requested by the owner.
To overcome this situation, owners should allow contractors to refuse to quote the change
order if they can not guarantee zero-impact to the project duration. If the contractor sees a
possible delay arising from this change order, such delay will have to be identified and
negotiated before having the order executed. This technique has the added benefit of
forcing the on-site owner’s representative to deal with delay issues caused by the owner,
as they are identified, and change orders are issued for pricing and negotiation.
In order to guarantee that project funds reach subcontractors performing work for the
prime contractor, owners include in the contract special clauses to that effect. Under these
clauses, the owner establishes payment provisions for the prime contractor, which require
certification that the subcontractors are being paid for the work being invoiced. In
addition, if the prime contractor fails to pay the subcontractors in a timely and proper
manner, owners retain the right to make direct payments to subcontractors and deduct
64
STAGE 1: PREVENTION
those sums from future disbursements to the prime contractor. Therefore, owners can
assess the risk of disruption due to lack of payment to the subcontractors and act to lessen
the chances of delays without having any direct contractual relationship with the
subcontractors.
regards to partnering, Larson et al. (1997), identified the lack of understanding of the
partnered system as one of the main barriers for its successful implementation. All these
new systems and tools must be taught at all levels and understood by key players in order
to maximize their benefits. Some of them will even require special, dedicated training
before they can be effectively incorporated into the project.
Office Going back to the office-building project, to combat conflicts that arose from these issues
previously mentioned, the owner implemented some preventative measures. The owner
Building
selected a GMP style contract for a couple of reasons. As design was not complete and
Project change evident, a GMP allowed the flexibility of implementing these changes without
changing the upper ceiling cost. This is possible in a fixed price contract, but the majority
of changes will result in a price increase. In addition to a GMP, the owner proposed a
50/50 shared savings of the money under the GMP with the contractor. This incentive
kept the contractor honest when pricing changes and add-ons. The architect had to be
honest as well when specifying material, as they reviewed and negotiated long lead items
with he contractor.
With the numerous parties involved, a solid organizational structure kept
miscommunications to a minimum. The contractor set up a chain of command,
performing phone conversations with the owner on a daily basis. To reduce confusion
and increase communication on-site, the GC held daily meetings with all the
subcontractors. This brought everyone up to spend on what was going on throughout the
job. Those who attended had the authority to act of behalf of their company for the day-
to-day operations. If a minor problem came up a change in the schedule, it was resolve at
these meetings. Workarounds were scheduled and conflicts were resolved. In addition to
the daily meetings, an on-site inspector for the structural designer made is possible to get
instant clarification of the design. This was a major time saving measure as it cut out the
length “Request for Information” process typically used. The architect also visited the
site once or twice a week.
As mentioned, there was no flexibility in the schedule. In this respect, the owner included
large liquidated and real damages contractor if contractor did not deliver the product on
schedule. This US$ 100 million job was managed by the contractor with only 2
superintendents. Meetings everyday, 50/50 shared savings and the threat of liquidated
damages all aided in delivering this project on time and under budget.
3.10 SUMMARY
Early identification of possible areas of conflict for a specific project is the basic premise
of this first stage in the DRL. Prevention is based on the assumption that it is more
effective, less expensive, and less time consuming, to prevent conflicts from arising than
to solve them once they have progressed and escalated. The prevention stage allows the
owner to tailor a Dispute Avoidance and Resolution system, which recognizes the
possible sources of disputes of the project and provides procedures to resolve them;
reducing the chances of having disputes escalate to legal battles. Prevention enhances
interconnection between team members and increases collaboration throughout the
executive phase.
The vast array of dispute prevention mechanisms presented in this chapter confirms the
fact that this stage of the Dispute Resolution Ladder provides the greatest flexibility of
action to the parties, while in the long run reduces the cost and time required for conflict
resolution. This flexibility allows parties to choose among multiple DART, those that
best fit the needs and resources of a particular endeavor. Each group of prevention
66
STAGE 1: PREVENTION
3.8 Engineering document review is a crucial but often overlooked process. With faster
schedules and constant approaching deadlines, what are some ways to improve this
review process? Should the contractor be involved in the design stage and review
process? Can this be accomplished in the design-bid-build procurement model?
3.9 What should the owners’ role in the construction process be? If they take and active
role, how much does this open them up for liability if things go wrong and vice-
versa, if they do not take an active role?
3.10 “Some contractors underbid projects banking on the premises that they can make up
the deficit in change orders and claims.” Is this a valid statement? Is this strategy
generated by the contractors, or forced upon them by the competitive nature of the
industry and the owners? How does a public owner prevent this from happening?
3.12 REFERENCES
68
STAGE 1: PREVENTION
[Howard et al., 1997] Howard, William E., Bell, Lansford C., McCormick, and
Robert E., (1997). Economic Principles of Contractor
Compensation. Journal of Management in Engineering. Vol. 13
(5). pp. 81-89, Sep./Oct 1997.
[Kluenker, 1995] Kluenker, Charles. The Construction Manager as Project
Integrator. Journal of Management in Engineering, Vol. 12, No.
2, March/April 1996, pp. 17-20
[Larson et al., 1997] Larson, Erik, and Drexel, John, (1997). Barriers to Project
Management: Report from the Firing Line. Project Engineering.
Vol. 28 (1) pp. 46-52. March
[Miles, 1996] Miles, Robert. Twenty-First Century Partnering and the Role of
ADR. Journal of Management in Engineering Vol. 12 (3) pp.
45-55. May/June 1996
[Shen, 1997] Shen, L. Y., (1997). Project Risk Management in Hong Kong.
International Journal of Project Management, Vol. 15 (2). pp.
101-105. April
[Skelhorn, 1998] Skelhorn, Steve. Partnering to Success in Toronto (Sheppard
Subway, Toronto, Ontario). World Tunnelling and Subsurface
Excavation. Mining Journal Ltd. (UK).12/01/1998.
[Smith, 1995] Smith, John A., (1995). Construction ADR: You Get Out What
You Put In. Dispute Resolution Journal pp. 27-30. July
[Stipanowich, 1997] Stipanowich, Thomas. At the Cutting Edge: Conflict Avoidance
and Resolution in the US Construction Industry. Construction
Management and Economics. Vol.15 (6) pp. 505-512.
November, 1997.
[Vega, 1997] Vega, Arturo Olvera. Risk Allocation in Infrastructure
Financing. Journal of Project Finance Vol. 3 (2) pp. 38-42.
Summer, 1997
[Vorster, 1993] Vorster M. C., (1993). Dispute Prevention and Resolution.
Construction Industry Institute. Virginia Polytechnic Institute &
State University. Source Document 95. October
[Zack a, 1997] Zack, James G., (1997). Claims Prevention: Offense Versus
Defense. AACE. Vol. 39 (7) pp. 23-28. July
3.13 ENDNOTES
1
The total scope of work for a 10-year project to design and build a facility to control
floods in a region in the Netherlands under a Frame Contract System stated the following:
“The execution of works for the realization of the storm surge barrier in the mouth of the
Eastern Scheldt between the islands of Schuwen Duiveland and Noord Beveland, with
additional works in the municipalities of...” (Goudsmit, 1985).
2
The International Construction Law Review, originally published by Lloyd's of London
Press, now known as Informa Professional, a trading division of Informa UK Limited,
Gilmoora House, 57/61 Mortimer Street, London W1W 8HS. Tel: +44 (0)20 7453 2198
Fax: 020 7453 2274.
3
An author of this book was the Project Manager for the contractor in this project.
4
In a recent project, an author of this book found a significant difference between the
monthly schedule updates submitted to the owner and the actual as-built schedule kept by
the contractor. When questioned, the contractor explained that the submittal was a
payment requirement, and that he could not afford to have payments delayed because of a
disagreement on the sequence of construction or because it showed delays due to design
changes. According to the contractor, those problems were going to be addressed at a
later date.
5
Taken from a change order letter of a contractor to an owner in a project where an
author of this book participated in.
70
C H A P T E R
4
PARTNERING
“[Partnering is] a method of transforming
contractual relationships into a cohesive, project
team with a single set of goals and established
procedures for resolving disputes in timely and
effective manner.”
Larson (1995)
A museum in the Northeastern United States was losing money year after year and was in
danger of closing because it lacked the ability to attract new customers. The museum had
not under gone any recent capital improvement because of its lack of funding. This
museum is a publicly funded, not for profit organization. After a desperate plea from the
board of directors to the state government, $900,000 was allocated to cover construction
cost for an expansion project. The budget was not flexible and no additional money was
available from other sources. Since the money came from public funding, the delivery
system was restricted to design-bid-build so that a fair competition would be held and the
owner would receive a fair price.
To attract new customers, the expansion that was proposed included additional space for
artwork as well as cafeteria. A local designer proposed a custom artistically designed
addition, contrasting the existing bland 30-year old functional structure. The design
KEY CONCEPTS
Partnering Defined .........................................72 Partnering Process............................................. 75
Key Components ...........................................76 Partnering Continuum ....................................... 78
71
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION
specified glass and colored ceramics stone, large spans, exactly the opposite of what
existed, with the intent to change the image of the museum. As a result of the design-bid-
build process, the design and drawings were prepared without any involvement of the
contractor. The estimate submitted by the designer met the $900,000 budget requirement
on paper, but everyone involved up to this point focused more on the look than the reality
of cost and budget. The design was completed and publicly bid, under state regulations.
Bidders picked up drawings, and submitted bids, with the intention that the award would
go to the lowest bidder. Four bids came in at $1.2, $1.25, $1.4 $1.5 million. The
procurement process was successful in the sense there was ample competition and the
bids were relatively close for the design, but the money was not available to award the
project to the lowest bidder of $1.2 million.
At this point, the owner hired an additional consultant, knowledgeable in construction to
overcome the owner’s lack of familiarity with construction. With no extra money
available, how might the owner go about lowering the cost of constructing the design? If
the owner asks the designer to make changes to reduce the cost, should there be another
competition to decide the lowest bidder? Should it be awarded to the lowest bidder and
then value engineered with the designer? The second lowest bidder submitted a close
competitive bid, if the design is awarded, then changed can the bid be protested? How
might bringing together the designer and the contractor on the same team affect the price?
72
PARTNERING
74
PARTNERING
1997/1998). The facility was built under the supervision of the final user (i.e., tenant)
thanks to partnering between the State agency managing the project and the main
contractor. No special contracts were required to incorporate the tenant in the
construction process, as both the manager and the builder are benefiting from its input.
Both the Canadian example and the three US projects represent a few of the many
successful experiences of partnering in construction projects. The common themes in all
of them are improved communication, objective alignment, cooperation, and trust. The
following sections review the partnering approach in further detail presenting the phases
of its implementation, as well as its key components.
76
PARTNERING
“PARTNERING AGREEMENT
WE, THE BON FOUCA SUPERFUND PROJECT TEAM, COMMIT TO WORK TOGETHER WITH A
SPIRIT OF OPENNESS AND TRUST, AND TO RESPECT THE GOALS AND NEEDS OF THE
STAKEHOLDERS.
The Team Assessment is both a quality control mechanisms and a quality improvement
tool. As the project develops, new objectives can be added and original ones modified
through these review sessions. These sessions also foster communication. The meetings
and surveys should encourage a greater acceptance of the partnership philosophy, which
in turn should translate in greater benefits for the project. These follow-up sessions are
the basis for improving the system during the life of the project, and adapt the philosophy
to project and team conditions.
The Issue Resolution Process is a tool to help the partnership overcome disagreements
and disputes that will still develop during the project. Unresolved issues will undermine
the partnership, prevent parties from achieving the common objectives, and foster
adversarial positions that will increase the chances of litigation (see first example in
Section 4.4). Finally, the Job closeout review provides an opportunity for assessing the
benefits of partnership, and to develop improvement measurements for other projects.
During these meetings, participants can evaluate future opportunities for collaborative
work, and even establish a long-term set of objectives towards the execution of that work.
This project closeout further strengthens the use of partnering, as parties will learn from
their mistakes and improve its implementation.
Coalescence
(Synergistic Strategic
Partnering)
Collaboration
High (Value-Added
Integrated Team)
Cooperation
Potential (Collaborative)
Benefits of
Partnering
Partnering
Competition
(Adversarial)
Low
78
PARTNERING
Some degree of
Level of Trust Very high levels of
Little trust between trust, in order to
between Parties High degree of trust. trust. Transparent
the parties. work for the
interface.
common objectives.
Openness, honesty.
Extensive
Single points of Senior level
High degree of communication,
Level of contact within the “champions” from
communication. collaboration and
Communication organizations. both organizations
Multiple points of commitment from
Owner supervises foster
contact. all levels of the
contractor. communication and
organization.
remove “barriers.”
Integrated team of
client and contractor
Adversarial.
personal and Transparent
Primarily a
Improved resources. Team interface. Parties
Type of defensive position.
interpersonal creates separate share resources and
Relationship Coercive
relationships. organization for the cultures are
environment.
Cooperation. life of the project. integrated to fit the
Short-term focus.
Long-term focus applications.
multi-project, with
shared authority.
Joint sharing of
Limited risk Increasing risk liabilities over
Risk Sharing No shared risks.
sharing. sharing. failures and gains
from successes.
Procedures to
address and resolve
Responsibility is
Disputes are disputes are Problems are
shared among the
common; often established. addressed as a team
Probability of team, so problems
requires binding Solutions are found and resolved at the
Disputes and disagreements
dispute resolution through some expense of neither
are solved within the
methods to solve degree of party.
team before
them (win/lose). compromise and
becoming disputes.
cooperation
(win/win).
40% reduction in
15% reduction in
job-hours; 17%
equipment and
reduction in
Cost and schedule construction costs;
Schedule reduction overhead; 10%
overruns. Both 33% reduction in
Typical Project 10.5%; Cost improvement worker
sides finish the engineering rates;
Results reduction 16.3%; utilization rate; 10%
project without 100% acceptance
RFI turn-around 14 project costs; 100%
realizing their of risk by the
days Vs. 30-60 days success in meeting
objectives. owner with a low
budget and schedule;
fee charged by
50% reduction in
contractor.
engineering rework.
80
PARTNERING
might be behind the failure of this partnering arrangement, and the failure to align the
parties’ objectives and develop the necessary trust to resolve the initial problems.
Process
Owners Team
Facility Facility
Construction Operations
Team Teams
Client
Local Architectural
Project
Codes Team
Design/ Engineering
Authorities/ Const. Teams
State Codes
Utilities Consultants
Material &
Federal Equipment
Manufacturers
Agencies
Trades
Utility
Suppliers Independent
Testing
Agencies
Such high level of integration is exemplified by the fact that from the beginning of the
project, the construction team met regularly with the start-up teams and the client’s
facility operation group. Changes in the design were evaluated early on by the final users
of the facility, and their comments, suggestions, and requirements were incorporated into
the process. In addition, suppliers of major equipment and technology participated in the
design development phases in order to incorporate their knowledge and experience into
the final construction documents. 6 Furthermore, a cost control group served as the router
for all exchanges of information, tracking all communications between the design and
construction groups, which allowed them to provide management with real-time cost data
at any given time. With this cost information, the team was able to make informed
decisions on changes, and their implications in the long run with regards to the project
budget.
A company that has successfully implemented this delivery system is Hoffman
Construction Co., Portland, Oregon (ENR, 5/27/1996). In 1993 a Hoffman’s construction
team won Intel Corp.’s Pegasus Award for the “breakthrough success” in solving crucial
technical and building issues during the construction of a 435,000-sq-ft, $110 million
chip fabrication plant outside of Portland. The plant was built in only 14 months; two
months ahead of schedule. When asked about his secret, Hoffman’s project manager
responded (ENR, 5/27/1996):
“To start with, throw the linear approach out the window. We do everything
with a tremendous amount of concurrency. We are driving safety rates to
extremely low levels, even in a highly risky environment 7. We self-perform a
great deal of our work. We interact with organized and open-shop labor, often
on the same site. What we have tried is to create synergies and bypass
institutional barriers that keep [builders] from reaching their full potential....
new techniques come from understanding the design process and the owner’s
needs. [Missing] your client’s technology windows can cost owners billions of
dollars. You have to be dead right – or you’re simply dead.”
Hoffman is a full service construction company, and unlike other contractors who often
contract out most of the work, they have developed in-house capabilities in many areas to
meet project demands. Among the innovative techniques developed by Hoffman, is the
concept of Speed Engineering where the company integrates their in-house structural
engineers with the owner’s design team to develop the fastest solution for bringing the
structure off the ground and to meet the owner’s need for a faster design and construction
process of their facilities. Furthermore, they analyze material availability, structural
details for constructability, and building systems for pre-fabrication opportunities (See
Section 3.6.1, Constructability Analysis). Hoffman reports that project costs can be
lowered through the speed engineering process, but the emphasis is on timely, safe
completion (Hoffman, 1999).
In the Lean Construction Model, the basic concepts of Partnering have been fully
implemented along Partnering Continuum. The different groups evolve over the life of
the project as requirements change. The organization is shaped and reshaped according to
the project, and from the beginning, parties are able to align their objectives and redesign
the total work process. All of the costs associated with this system have been recovered
through partnering agreements and outstanding project performance (Miles, 1996). This
ultimate stage of partnering, Coalescing, has resulted in significant savings in time and
costs in the design and construction of a number of projects, helping both owners and
contractors achieve higher levels of productivity 8.
Museum Relating partnering to the Museum project, it can be seen that the principles of
Project Partnering, when applied correctly, can reduce and even eliminate an adversarial
situation. After the bids were analyzed, the owner’s consultant reviewed the design and
value engineered it with the designer and the owner. To be consistent with state
82
PARTNERING
regulations the owner went back to the two lowest bidders and asked for a reprice with
the design alternates. This method promoted fair competition comparing apples to apples,
in addition the owner asked for other suggestions to reduce the price to meet the strict
budget requirements. Both bidders concurred and thought it was fair. Bids were
submitted by the two lowest bidders, coming in at $1.0 and $1.6 million. The owner
awarded the project to the lowest bidder and the bid was not protested.
With the total construction costs still over the budget, the owner’s consultant
implemented partnering for the project. The contractor worked with the owner’s
consultant for further value engineer the addition. The contractor suggested eliminating
the basement, moving heating and ventilation systems to the roof, and some modification
to the curtain wall design. At the same time, the designer was approving the design
through the shop-drawing phase. Construction started before design was complete. The
project continued on schedule with changes being implemented on an ongoing basis. The
synergistic atmosphere allowed the owner the ability to make design and value
engineering changes, without sacrificing the quality of the structure.
The key concepts of partnering implemented included weekly meetings, openness and
commitment of all the parties involved to process. The consultant hired by the owner was
authorized to make decision on behalf of the owner whenever necessary. Upper level
management commitment was a major strength as well as cooperative field crew. Claims
and change orders where handled and resolved on a daily basis. Trade contractors were
involved in meetings to value engineer, especially HVAC contractor. As a result, the
project was completed on time and under budget by $10,000 ($890,000). At the end of
the project when the closeout phase occurred, the owner realized that the contract was
never signed, as everyone was so anxious to get underway and close in before winter.
The contract was signed at the end of the project.
4.5 SUMMARY
Partnering is a complete system of operation in the construction environment; hence, it is
not considered a stage in the DRL. However, the introduction of the concept of
Partnering was based on the consideration that many of the key principles of this system
of operation are congruent with those of the DRL; and thus can enhance the different
stages, even if the complete Partnering format is not being implemented. Partnering
fractures the common adversarial approach in construction projects and replaces it with
open communication, timely decisions, synergy, joint problem solving, and win/win
philosophy.
Among the multiple advantages of partnering are: reduced exposure to liability through
open communication, early problem identification and resolution; risk sharing; increased
productivity; better quality of work through the empowerment of workers; lower costs;
better cash flow; better decision making and commitment to resolving problems; and
better opportunity for a successful project. As Hunter et al. (1995) so eloquently said,
“…an ounce of partnering prevents a pound of problems.”
The Partnering Continuum establishes a direct relationship between the degree of
objective alignment between the parties to a project, and the potential benefits of
Partnering, where the Coalescence phase represents the greatest alignment of objectives
and offers the greatest benefits. Through the use of this continuum each project can
determine the level of objective alignment it has and/or desires, and from this estimate
the possible benefits that the system could provide. Nevertheless, despite its many
advantages, partnering can experience problems through its implementation associated to:
1) The demand it places on everyone committing to the partnering process.
2) The difficulty participants may have with taking the risk of trusting others.
3) The tendencies of many people to believe that conflicts can only be solved
through the win/lose approach.
4.7 REFERENCES
84
PARTNERING
4.8 ENDNOTES
1
To this effect, Groton (1997) concluded, “Partnering is both the overall philosophy for
dispute management and one of the tools for avoiding disputes.” In this book, partnering
is being considered as a philosophy.
2
See Chapter 5: Negotiation for more on win/lose and win/win negotiations.
3
See Chapter 5 for Position-Based versus Needs-Based Negotiations.
4
In parenBook is the equivalent level from the Ellison et al., 1995 model
5
A survey on barriers to partnering identified trust between parties as the most critical
aspect in the success of the implementation of this approach. Thirty one percent of
respondents considered the failure to build a true relationship of trust as a barrier to
partnering (Larson et al., 1997).
6
This concept of supplier involvement in the engineering process is behind the new
PEpC delivery system developed and proposed by the CII, and reviewed in Section 3.3.3.
7
Hoffman’s Lost Accident Rate per 200,000 works hours since 1994 has been 600% less
than the industry average (Hoffman, 1999).
8
Tesco Stores has reduced the capital costs of their stores by 40% since 1991; Needahm
Co., a construction company from Colorado, has been able to reduced project times and
costs by as much as 30%; Pacific Contracting of San Francisco, has increased their
annual turnover by 20% in 18 months with the same staff (CIOB, 1999).
86
C H A P T E R
5
STAGE 2:
NEGOTIATION
“there is a fixed-size cake to divide and each party
would rather have a bigger slice than a smaller
slice”
(Hill 1995)
KEY CONCEPTS
History of Negotiation ...................................87 Positions vs. Interests ........................................ 89
Styles .............................................................91 Structured Negotiations .................................... 94
Step Negotiations ...........................................93 Assisted Negotiation / Facilitation .................... 95
87
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION
88
STAGE 2: NEGOTIATION
GC: As you know, the schedule is very tight for this project and there is little float
available. Are there any other suppliers who can deliver on time?
SUB: Yes, but they are more expensive, more than the damages incurred by finishing
late.
GC: Although you are responsible for meeting the milestone, I understand your
dilemma. Let me see what I can do. I know some other suppliers that might be
able to help.
In this interest-based negotiation, the root of the conflict is uncovered, and a mutual
agreeable solution can be reached. Although the general contractor seems to have the
most power in this negotiation, the subcontractor has some as well. If the schedule begins
to slip because of this delayed finish, and they wind up in a court battle, it may take years
to award damages. In addition, the damages may not be sufficient to cover the actual
costs incurred by the contractor.
When the “Im’right you’re wrong!” position is abandon, it allows participants to address
the underlying concerns, which leads to the generation of alternatives that would not
seem readily apparent at first. In this fashion, Hollands (1989) 1 suggests that parties in a
construction disputes should not only consider needs or interests that are derived from the
contract documents, but parties should also look for alternatives that can solve the
disagreements without court intervention. After all, parties usually know and understand
the facts better than they can communicate to an arbitrator, judge, or jury. Therefore, they
should be able to develop a solution that incorporates and maximizes this knowledge. He
recommends that the following aspects be incorporated into the negotiation:
• “Substantive (e.g., money, time, long-term market);
• Procedural (e.g., confidentiality, protocol, administration);
• Psychological (e.g., need for respect, status, security, recognition).”
(Hollands, 1989)
The result of this positional bargaining is a “zero sum” solution. Even if perceived gains
do not have to equal perceived losses, any change in the proposed result will provide an
advantage to one party and a disadvantage to the other. Recognizing whether a particular
negotiation is zero or non-zero sum can be very important in planning for and actually
carrying out the negotiation, as dispute negotiations often seen as zero-sum, may have
non-zero sum aspects or alternative solutions (Boskey, 1993).
Negotiation parties often feel they are involved in a zero-sum situation in which court
proceedings are the only solution to the dispute. They believe “there is a fixed-size cake
to divide and each party would rather have a bigger slice than a smaller slice” (Hill,
1995). However, statistics from the American Arbitration Association show that few
business situations are zero-sum games and that by cooperating, business partners can
expand their markets and develop mutual benefits. For example, out of the 3,075 cases
that requested AAA mediation (i.e., a form of facilitated negotiations) in 1993, 1,136
were settled, 151 were closed, 293 were withdrawn, 644 were pending, and 851 were in
some other status at the end of the year (Langeland, 1995). In other words, over 50% of
the cases where closed through this form of aided negotiation where parties develop
solutions, which are acceptable to both parties (i.e., win/win or non-zero-sum), and only
28% proceeded to another form of dispute resolution.
It must be noted that sometimes interests based negotiations are not the best choice of
action. In the few disputes that are completely ‘cut and dry’, other approaches such as
rights or power can be used to resolve the dispute (Ury et al., 1988). More information is
presented in Chapter 9 on these types of disputes.
90
STAGE 2: NEGOTIATION
Competing Collaborating
Compromising
Avoiding Accommodating
Avoiding a situation or conflict is just how it sounds. Sometimes trivial problems are best
ignored. An example might be that the union workers are upset because there are only 20
bathrooms on-site instead of 22. At some point, the validity of a conflict must be
addressed, and usually this is done subconsciously. Imagine the number of erroneous
situations that could escalate into conflicts. Most project managers already spend too
much time on perceived problems that are not worth their time. On the other hand, a
legitimate concern from another participant that is avoided can have enormous
repercussions. If there were 20 bathrooms on-site, and no female bathrooms, the union
workers might have a legitimate complaint. This problem could easily be solved, but it
could also escalate quickly if avoided.
Competing is the style that most of the participants in the construction industry take. “I’m
not going to budge, because they will just take advantage of me.” This adversarial style
leads to litigation. Although the competing style is necessary, it is often misused. Think
about the issue of safety on the construction site, which is usually the responsibility of the
contractor. If a subcontractor approached the contractor and requested some leniency in
meeting certain safety requirements, what style should the contractor reply with? In this
situation if the contractor has responsibility for the site safety, the contractor should take
a competing style. On the other hand, it would be unwise for sub to continue with the
competing style. The worst time to use the competing style of negotiation is when you are
wrong or to compete for the sake of it.
Accommodating is the complete opposite of competing. This style focuses on
accommodating the interests and requests of the other side. This is usually the easiest
way to resolve a dispute. In many times when a party assumes responsibility for their
actions or mistakes, if they take on an accommodating style of negotiation they might
reach a mutually acceptable outcome even thought they are at fault. The exact opposite
can be true if a competing style is adopted by the party at fault. Accommodating another
party when applicable can develop trust among participants.
Compromising is when both or all of the participants give in on some points or interests
for the sake of acquiring others. Although this is usually not the optimal situation, it is
one in which all of the parties are willing to work together. Compromising works well
when both or all of the parties have valid complaints in a conflict. An example of this
might be adverse weather conditions. A contractor might ask for a 10-day time extension,
but the owner might feel that work could have continued through the weather. Both may
have a valid claim and a compromise of 6 days could be reached for the severe days.
Although not always the most optimal solution, keep in mind that the alternative to
compromising on some of the trivial points is litigation.
Collaborating is one of the primary principles in Partnering. In collaborating, the
participants work together to design, develop and implement a solution that is acceptable
to all. This style of negotiation flourishes in a synergistic atmosphere. The downside of
this style is that it is rarely used. The delivery systems and contract selection do not
usually promote this atmosphere. An example of this is when a contractor and a designer
are brought in the project early to add their input and help steer the project based on their
expertise.
5.4 PREPARATION
Preparation for a negotiation cannot be stressed enough! To go into a negotiation without
doing your homework will only spell disaster. It can make valid claims seem invalid, fuel
personality conflicts, prolong the resolution process, frustrate others and ruin
relationships. When starting to prepare for a negotiation you should begin by figuring
out exactly what it is that you hope to achieve. What are your needs? In the same context,
one should also make a prediction as to what the other participant’s interests are.
Understand and identify where the might be conflict and plan accordingly.
When determining needs and interest, an objective determination can be made about your
BATNA (Fisher, 1991). The BATNA is the Best Alternative To a Negotiated Agreement,
in other words, the point at which a negotiator is willing to walk away from the
negotiations. Below this point, there is nothing that the other side can propose that is
better than not negotiating at all. For example, if an owner is negotiating with a set of
contractors for the lowest price on a quality guaranteed contract and has received a bid of
$100,000 (the BATNA); when negotiating with the next contractor, it would be worthless
to negotiate above this point. A BATNA is not something that the negotiator wishes for,
but it is rather determined by external factors. It should not be overly ambitious but
honestly the best alternative, for if things do not go as planed the result may be to accept
the BATNA. Once your BATNA has been identified, identify the BATNA for the other
parties involved.
Source of power are another aspect of negotiations that one can account for before the
negotiations begin. Examine the situation and identify what sources of power that each
side possesses. By doing so it will allow you to leverage your position in the negotiation
and come up with defenses against sources of power that the other side may have.
Once the BATNAs and sources of power are identified, one can begin to determine how
the negotiations might go. Develop a thorough list of needs and interests, prioritize them,
and do the same for the other side. Start to develop solutions to the problem that will be
92
STAGE 2: NEGOTIATION
acceptable to both sides. Make sure that these are optimistic but not too greedy. This
target solution is the aspiration point. Although you may have many great solutions to the
dilemma, keeping consistent with the win-win solution, one must be open to solutions
that are presented by the other side.
By preparing for the negotiation, the conflict will most likely be resolved faster and have
a more optimal result for all the parties involved. The following sections review three
important techniques designed to improve the negotiation process in the construction
industry and correct, “people issues and process problems” that might interfere with the
resolution of disputes at this DRL stage. These techniques, Structured Negotiations, Step
Negotiations, and Facilitated Negotiations, are presented in the following three sections.
When reading these sections keep in mind the theory of negotiation and how they might
apply.
Communication Lines
Level 3
Step 3
(e.g.,V.P. Level 3
Operations) (e.g., Senior
Management)
CONTRACTOR OWNER
ORGANIZATION ORGANIZATION
94
STAGE 2: NEGOTIATION
The advantages of structured negotiation are twofold. On the one hand, negotiations
become a formal procedure, in which a centralized structure is created to cope with the
dispute. The most important benefit is that people in dispute can control the process.
They can establish strict timetables for their agents to reach a settlement before calling
for a third party to solve the matter, and the third parties can be limited to the time they
have to reach a decision. The agents take every issue in dispute from its definition to a
resolution that is incorporated into the contract, identifying and leaving aside only those
issues in which they cannot come to an agreement.
The other advantage is that structured negotiations bring knowledgeable participants to
the table; a move that generally produces faster results, since the expert agents can draw
from their respective organizations all the legal, technical, and managerial information
required expediting the procedures and guaranteeing an effective outcome (Hoctor,
1989). In addition, by constantly interacting with experts, parties reduce the risk of
having to escalate the problem to a court, where a judge or jury will have a limited ability
to comprehend the problems. In short, by understanding underlying interests, managing
information, and then allocating time and resources, the experts involved in structured
negotiations increase the likeliness to achieve a win/win, non-zero sum solution.
Highway Negotiation played an important role in resolving the change order in the highway
Interchange interchange project. Looking at the sources of conflict for the highway interchange
Project project, one can see from Section 1.1 that even before the contractor started working on
the project, the potential for conflict in this contract was high. The delivery system
(Organizational Issue, Structure) of design-bid-build combined with incomplete design,
put the participants at an adversarial relationship from the start. Change, variations and
uncertainty (Uncertainty, External) impeded the steady flow of work. Ultimately, the
incomplete scope definition (Uncertainty, Internal) play the biggest role in defining the
conflict as there was a significant amount of work the contractor couldn’t plan for. In
terms of the possibility of negotiations on the project, the owner and the general
contractor had similar interests.
• The Owner wanted the contractor to do extra work.
• The Owner wanted zero impacts to the schedule.
• The Owner/Project Manager wanted to cap their exposed and risk level in the
area of schedule and cost.
• Both wanted a fair and equitable settlement.
• The Contracttor wanted quick resolution and payment
• The contractor was willing do the extra work and take on the risk.
For this reason, interest based negotiation was very successful in resolving these disputes,
although they could not all be resolved at the jobsite level. Both the owner and the
contractor used a combination of a collaborative/compromising strategy (Section 5.3) to
reach a solution. As mentioned earlier, the potential to impact other contracts made the
schedule an important interest to the owner. This is the reason behind the owner wanting
to cap their risk exposure to schedule delays. The milestones and completion date were
critical. The issue of cost was secondary to schedule, but also important because the
owner was a government agency. For this reason the owner requested a forward priced
change order (Section 3.7.7), guaranteeing that this price would hold once it is agreed
upon.
When this project was 80% complete, the owner had approved payment of $US 31
million and was still negotiating the rest of the contractor’s request one issue at a time.
An independent 3rd party was hired by the owner to verify the number submitted by the
contractor. The involvement of a 3rd party and the commitment to good faith, interest
96
STAGE 2: NEGOTIATION
based negotiations aided in the development of trust and helped facilitate an agreement.
The owner’s interests were met as the Contractor took on extra work, more risk,
promising zero schedule impacts, in return for fair compensation. By equitably
compensating the contractor, the contractor was satisfied and the owner capped their
exposure and locked in a budget based on the forward-priced change order.
5.8 SUMMARY
After the Prevention stage, which assumes that conflicts will exist and attempts to
minimize them, negotiation is the first stage that directly tries to solve the disputes. As
the second stage in the DRL, negotiation is a flexible stage in which parties have a high
degree of control over the possible outcomes. Thus, negotiation is considered the most
important tool available to manage and resolve construction disputes, and therefore
should be included as a standard resolution technique in contracts. Negotiations may
involve a third party facilitator that focuses on communication and development of
common grounds. The facilitator concentrates on the needs/interests of each party rather
than positions, and attempts to reach a non-zero-sum, win/win outcome that takes into
account matters internal and external to the contract that cannot be considered in the
binding stages of the DRL.
Step, Structured, and Facilitated Negotiations are three important techniques that can be
used throughout the negotiation process. The first two focus on the importance of
organizing and structuring the negotiation process in order to improve its results; the
third, focuses on the importance of facilitating the communication process among parties.
Step negotiation establishes a linear process for dispute resolution, assigning time limits
to each level of the parties’ organizations, moving upward along the hierarchy in the
negotiation process. Structured negotiation offers a formal procedure in which a
centralized structure is created to cope with the dispute, while allowing parties to
maintain control over it. The introduction of a participant with knowledge in the field lets
structured negotiation produce faster results, preventing disputes from escalating and
reaching litigation. This technique forces each party in a project to use all the resources
available to elucidate the problem before raising the matter to the next step. Finally the
facilitated negotiation/meeting is based on the notion that parties are not able to
communicate, and thus views the role of the facilitator as a vehicle to improve
communication in order to achieve an acceptable solution.
Depending on the objectives, strengths, and weaknesses of each particular project, parties
can decide which of these strategies to use. If lack of structure is a main weakness of the
project, step and structured negotiations might be the most helpful approaches to solve
the conflict. If lack of communication and understanding between the parties is the main
obstacle in the dispute resolution process, facilitated negotiation can become a valuable
tool. Mediation and conciliation, which are reviewed in Chapter 7, are also forms of
facilitated negotiations.
The following chapter reviews the role neutral third party agents can play in the
resolution of the usually complicated disputes in construction projects. Similar to the
initial determination by the design professional in the traditional DRL, which provides a
fast, objective, and knowledge-based solution, these third party agent techniques can aid
solve technical and contractual problems and allow the team to concentrate on
completing the project. Decisions suggested by the third party experts can also facilitate
negotiations and foster the settlement of disputes.
5.10 REFERENCES
98
STAGE 2: NEGOTIATION
5.11 ENDNOTES
1
The International Construction Law Review, originally published by Lloyd's of London
Press, now known as Informa Professional, a trading division of Informa UK Limited,
Gilmoora House, 57/61 Mortimer Street, London W1W 8HS. Tel: +44 (0)20 7453 2198
Fax: 020 7453 2274
6
STAGE 3:
STANDING
“...experienced and trusted construction
professionals with appropriate technical
background to address prevention and resolution of
NEUTRAL
disputes”
(ASCE, 1991).
For the construction of a $187 million state-of-the-art Land Level Transfer Facility in the
Northeastern United States, an Owner entered into an agreement with a design-build
Contractor. The facility was constructed for a subsidiary of a major defense Contractor
and replaced an aged facility to increase production capacity and capability. Upon refusal
of the first design-build Contractor to complete the final design and construction phases
of the project, the Owner subsequently entered into an lump sum agreement with a new
design-build Contractor. The new Contractor has claimed substantial damages arising
from inaccurate representation of marine subsurface conditions as reflected in the
preliminary design performed by the defaulting Contractor.
In the agreement between the Owner and the Contractor, no specific representations were
made regarding the site conditions. In fact, the scope of work in the agreement spells out
a design-build contract based on detailed performance criteria outlining the general
KEY CONCEPTS
Neutral Advisor .............................................101 Owner/Agency Review Boards ....................... 102
Dispute Review Boards .................................103 On-Call Contractors ........................................ 106
100
STAGE 3: STANDING NEUTRAL
configuration and characteristics of the facility, but the representation of the site
conditions is clearly not established. It does however contain a clause that provides for an
adjustment in price and/or performance period should the Contractor encounter unknown
surface, subsurface or latent physical conditions at the site differing materially from the
information provided by the Owner.
A third party neutral was retained by the insurance carrier’s counsel to assist in analyzing
the alleged design errors and misrepresentation of subsurface conditions resulting in the
claimed damages. These damages, which exceeded $50 million, represented additional
direct work, project delay and other consequential losses. Since this is a design-build
contract, there is not an independent designer or Owner’s agent to make a determination.
This case raises important questions such as, what services might the neutral provide?
What are the reasons for the insurance company’s selection of an independent report? Is
this type of analysis a reality check for both parties? Although the recommendations are
not binding among the parties, what affect might they have if the conflict escalates?
would centralize, organize, mediate, and resolve all of the requests and disputes over
corrective work, therefore reducing conflict.
The developer and the HOA select this Neutral Architect jointly, once the project is
completed and the requests have been collected by the HOA. Both parties should cover
the costs of this neutral to avoid affecting the impartiality of the process. Kemp (1998)
described his role as a Neutral Architect in a 95-unit residential project in California as
follows:
“The primary goal ...was to function as an intermediary between the home
owners and the developers in much the same way as a music conductor acts to
render a symphony to an audience. The written score and lyric represent the
scope of work. The orchestra and choir are the builder and subs. The task is to
interpret the scope of work so that both the composer and the audience are
satisfied with the result; at the same time making sure that the musicians are
team players from the beginning to end”
As the Neutral Advisor described above, this architect learns about the project, the scope
of work, and the disputes between the developer and the HOA and provides parties with
unbiased and knowledgeable solutions to their disagreements. This allows the corrective
work to proceed much faster and with significant savings for both parties.
Kemp (1998) suggests that the success of this DART approach is based on the fact that
the Neutral Architect represents to the parties the “ideals of impartiality and fair
dealing.” Impartiality allows this neutral to overcome the limitations that a design
professional, working directly for the owner, would normally encounter; thus, moving the
negotiation and resolution of the problem beyond the distrust and the adversarial stance
which often characterize the relationship between the developer and the home owner.
In reviewing the many positive contributions of the Neutral Advisor to the effective
resolution of conflict, parties to the construction must also take into consideration the
disadvantages and risks of this procedure that need to be monitored, which has been
summarized as follows:
• The decision is not binding to the parties. Therefore, disputes can continue to
affect job performance if a solution is not reached.
• The neutral might become “too” familiar with the job and the different parties to
the point that his decisions will no longer be respected.
• A Neutral Advisor that is not educated or inexperienced in making the proper
decision may hinder relations.
• The neutral over time might become partially biased towards one of the parties
of the construction team.
102
STAGE 3: STANDING NEUTRAL
claims and disputes with contractors working for the city. This Board is composed by
three members appointed by the Office of Construction with binding authority to issue
settlement for disputes submitted by contractors against the city. This Board functions as
a permanent arbitration panel.
Advantages of these Owner Review Boards include a second opportunity to review with
the owner unfavorable decisions made by the on-site representative, and the low costs
imposed on the contractor. With this DART, however, there can be a problem over the
partiality of the Board, since its members are employees of the owner and the contractor
has no representation. Due to this problem of partiality, the New York City Dispute
Review Board has been severely criticized by building organizations (Treacy, 1995),
which see the binding effect given to the decisions as an unacceptable feature in this
application of this technique, considering the composition of the Board.
In the same way that the Neutral Advisor was introduced to ameliorate many of the
limitations of the design architect/engineer, the Dispute Review Board discussed in the
following section attempts to solve the limitation of the Owner/Agency Review Board
associated with its compromised objectivity.
104
STAGE 3: STANDING NEUTRAL
The Board reviews the information gathered The contractor can accept the
at the presentations and sends a proposal by the Minister, or proceed
recommendation to the Minister, who them to submit its claim to arbitration or
advises the contractor on his/her decision litigation
Five interesting features of this version of the DRB in the Canadian public works sector
are worth highlighting:
1) The request to form the CDAB is received and reviewed by the Minister of
Public Works, and it is through that office that the decision to form the Board is
taken. This provides the procedure with the necessary official backing to
proceed. Using the Minister also appears to be a last minute effort to resolve the
dispute before choosing to form the Board. Officials are encourage to resolve
the dispute before they are submitted to the Minister for review, for the same
reasons outlined under the ADR technique of Step Negotiations (Section 5.5).
The Board is appointed when a dispute arises, and the Minister chooses to form it.
Therefore, the Board only deals with a specific dispute, and it is not part of the
whole project. This condition makes this type of Board different than a DRB,
which is incorporated into the job from the beginning, regardless of whether
there are any claims.
One person from each side is given the responsibility of presenting the cases.
Presentations to the Board are limited to a maximum of two and a half hours for each
side. This limitation should expedite the proceedings and limit the amount of
evidence presented by the parties. There is no time for expert testimony.
There are no formal rules to run the proceedings, and records of the discussions are
kept confidential. This adds flexibility to the process and encourages disputants
to present all the facts, without fear that they will be used in a binding procedure
(i.e., arbitration or litigation) if this step fails to achieve a resolution.
These features suggest that the Ministry of Public Works of Canada has in fact combined
two techniques from the DRL in the CDAB system. The CDAB is set up as a DRB but
operates more like an Executive Trial or Minitrial (Section 7.6). The time limitations and
the involvement of the Minister are characteristics that should encourage a faster
evaluation and resolution of matters. The Minister has the authority to evaluate and
propose alternative solutions to the contractor that the contract representatives may lack.
Despite successful applications of the DRB technique, its main disadvantage can be the
high cost of implementation, estimated to be between 0.5 and 1 percent of the
construction cost. Therefore, the application of this technique requires an evaluation of
the cost implications, for it could represent a considerable investment for both the owner
and the contractor. However, in larger-scale and complex projects, this technique has
resulted in significant savings in litigation and arbitration costs that surpass the costs of
its implementation (ASCE, 1997).
Land Level Getting back to the Land Level Transfer Facility, the insurance company contracted with
Transfer the neutral to review the claim for its validity as the Owner submitted a claim to the
Facility insurance company upon the receipt of the allegations from the Contractor. Two
registered professional engineers, familiar with ananlysis of similar construction disputes,
undertook the review. The third party neutral provided the following services:
• Review and analysis of geotechnical information contained in the 90 percent
design drawings and commissioned reports.
• Comparison of the geotechnical information available to bidders to reported
conditions encountered by the Contractor.
• Analysis of entitlement to additional compensation resulting from the alleged
changed conditions.
106
STAGE 3: STANDING NEUTRAL
6.5 SUMMARY
The Standing Neutral stage is based on a prompt, rational, on-site, and impartial review
of disputes by mutually accepted experts. This stage is an attempt to ameliorate the
disadvantages of using the design professional, who for years had been used as a neutral
and knowledgeable third party. All the techniques proposed in this stage share three
common denominators: third party involvement, unbiased decisions, and a
knowledgeable expert, all of which promote substantial cost savings and can eliminate
inefficient use of time and resources in litigation. Nevertheless, these techniques differ
across three different variables: the number of agents involved, the relationship of these
agents with the project (i.e., external or internal to the project), and the stage in which
they are introduced.
Table 11 - Summary of Characteristics of Different Standing Neutral Techniques
Owner Dispute
Standing Neutral Neutral On-Call
Review Review
Technique Advisor Contractor
Board Board
Number of Agents 1 Multiple Multiple 1 company
Relationship of the agent
External Internal External External
with the project
Towards the
From the end of the
When From the
Stage in which the agents beginning project.
conflicts beginning of
become involved of the Before
arise the project
project conflicts
arise
The different levels of each of these variables offer several advantages and
disadvantages. The introduction of only one agent has the advantage of reducing costs
and time, while increasing flexibility in the decision process. However, it suffers the
disadvantage of having decisions depend on the interpretation of only one person who
might fail to understand the multiple and complex issues involved in a dispute. In the
same manner, the introduction of the third party from the beginning of project offers the
benefit of an expert who is highly familiar with the project and its multiple facets, who
can collaborate not only to resolve disputes but also to address potential areas of
problems. This prevention feature of this stage in the Dispute Resolution Ladder is one of
its most important benefits. Nevertheless, the third party’s familiarity with the project can
result in loss of impartiality over time. This challenge, in combination with the fact that
having an expert throughout the project increments the costs of implementation of this
technique, represents the main drawbacks of having a third party neutral throughout the
complete project.
Finally, the greatest advantage of an external agent is their impartiality, which often
translates into greater trust from the parties. However, their strangeness with the members
of the project, specially those not involved in their selection, can be a double-edge sword,
and result in difficulties establishing trust, and communication among functional project
team members; thus, interfering with the possibility of gathering accurate information.
The advantages and disadvantages of the different levels of this stage, and how each of
these interact, need to be considered when deciding the most appropriate technique for
the specific characteristics of the project. The selection of the standing neutral technique
most fitting to the specific project will increase the chances of solving the dispute at this
stage or at least promote the clarification of technical issues that will increase the chances
of success. This clarification can help parties return to the negotiation table or proceed to
a higher stage in the DRL with some of the issues already resolved.
108
STAGE 3: STANDING NEUTRAL
6.7 REFERENCES
6.8 ENDNOTES
1
© ____CPR Institute for Dispute Resolution, 366 Madison Avenue, New York, NY
10017-3122; (212) 949-6490, www.cpradr.org. This excerpt from “Construction
industry ADR / Catherine Cronin-Harris. -- New York, NY : CPR Institute for
Dispute Resolution, c1994.” reprinted with permission of CPR Institute. The CPR
Institute is a nonprofit initiative of 500 general counsel of major corporations, leading
law firms and prominent legal academics whose mission is to install alternative dispute
resolution (ADR) into the mainstream of legal practice.
7
STAGE 4:NON-
BINDING
“I realized that the true function of a lawyer was to
unite parties ... A large part of my time during the
20 years of my practice as a lawyer was occupied
DISPUTE
in bringing about private compromises of hundreds
of cases. I lost nothing thereby – not even money,
certainly not my soul”
RESOLUTION
(Gandhi, cited by Ide, 1993)
A developer and a group of other investors purchased an old apartment building with the
intent to convert it into a condominium and sell the units. This 90-year-old building
consisted of 41 existing units. The developer assumed the role of a Construction
Manager. Various types of contracts were issued to various subcontractors including
fixed price, extra work order, cost plus, and unit price. Overall, the developer estimated
to make about US$ 6 million worth of repairs.
In doing this work, the developer had to prepare a document required by law called an
offering for prospective buyers. A designer inspected the building’s current condition and
KEY CONCEPTS
Mediation .......................................................112 Conciliation ..................................................... 117
Advisory Arbitration......................................118 Fact Based Mediation ..................................... 119
Mini-Trial ......................................................120 Voluntary Settlement Conference ................... 121
110
STAGE 4: NON-BINDING DISPUTE RESOLUTION
the developer then made representations as to exactly what they were going to do to the
building. These included the following items: repair the foundation, fix the façade, repair
the windows, replace the window frames, and replace the roof. Purchasers bought units
based on this document and other beautifully designed marketing brochures distributed
by the developer.
The developer completed the work, but the homeowners were displeased with the quality
of the units and asserted the developer had not finished the representations they had made
in the offering. The homeowners had noticed numerous defects in the construction such
as water leakage, code violations, and a poor heating system, but the leakage was the
issue that spearheaded the conflict. Poor oversight and a lack of strong management on
the part of the developer had led to a haphazard construction program and substandard
performance. Some subcontractors cut corners on lump sum contracts to save money
while others milked hours on extra work order contracts billed by the hour. The owner
caulked the windows, instead of replacing them as stated. Only patchwork was done on
the brick and where it should have been repointed. A cheaper roof was used and placed
over two existing layers, varying from the offering and violating state building codes.
In trying to resolve these issues, each participant took a hard position. On the developer’s
side, they felt that because they spent the US$ 6 million budgeted to improve it, that they
had met their obligations. In addition to this, they asserted that not all of the issues noted
by the homeowners stem from what the developers promised, and therefore they cannot
do anything about them. In response to the code violations, the developer argued that the
building inspector signed off on it. On the other side, the homeowners just wanted it
fixed. If it took $1 thousand or $10 million, they did not care as long as all the problems
were fixed. Even though many of the issues were the obligation of the developer, some
were not. Subsequently the homeowners association hired an attorney, and made a list of
inefficiencies. The lawyers in turn did not look at the obligations of the developer, but got
greedy and took the position that they wanted everything and more fixed. They had the
attitude that any jury would be sympathetic to a group of elderly senior citizens who were
abused by the big bag developer.
The parties are obviously at an impasse. Are the parties committed to resolving this
dispute effectively? Consider both of the positions, should either one of the participants
make concessions in order to reach a solution? What affect did the hiring of lawyers have
on the negotiations between them? How might a non-binding third party make each party
see the other side? Who should pay for a third party if needed?
the three risk management programs (Total Quality Management, DART, or Partnering)
had the lowest professional liability losses and insurance premiums in the industry. Based
on this study, firms with a TQM program have 31% lower professional liability losses
than those that do not. Those using DART have 19% lower losses, and firms with formal
partnering programs have 10% lower losses than those that do not.
These results support the efforts put forward by DPIC Cos. Inc., of Monterey, California,
to promote the use of DART among the 7,300 design professionals it insures in the US
and Canada (ENR, 7/11/1994). Since 1991, DPIC has been encouraging the use of formal
mediation program called “Mediation Works!” to resolve disputes by offering
policyholders a 50% reduction (capped at $12,500) in their deductible for claims resolved
using DART. The rationale behind the offer is that the program will reduce legal and
settlement expenses by preventing the “inevitable conflicts, which arise [in construction]
from becoming claims and lawsuits” (Hunter et al, 1995). 1
“Mediation Works!” has been a total success. During its first three years, DPIC
reimbursed a total of $4.3 million in deductibles to its clients, yet it was able to lower its
average legal expenses per closed claim from $22,000 to less than $18,000, and its
average loss per closed claim from $116,000 to $103,600. In 1993 alone, DPIC
reimbursed a total of $1.8 million on 236 claims (ENR, 7/11/1994). Simple calculations
can help understand the economic benefits of this program for DPIC:
Thus, in 1993 DPIC spent $1.8 million dollars in the implementation of “Mediation
Works!,” but was able to save a net average of $2 million dollars in legal and settlement
expenses, a 100% return on investment. Although these calculations do not consider any
direct costs associated with the implementation of the program, the benefits are large
enough to understand its success. Since 1991, the percentage of DPIC clients using
mediation in disputes has grown from 10% to 29% in 1995, and some local offices of
DPIC report that 40% of their cases are being mediated (Hunter et al., 1995).
7.2 MEDIATION
Construction attorneys generally perceive mediation to be the most effective approach for
achieving a wide range of goals, such as enhancing parties’ understanding of disputes,
112
STAGE 4: NON-BINDING DISPUTE RESOLUTION
MEDIATION ARBITRATION
114
STAGE 4: NON-BINDING DISPUTE RESOLUTION
Despite some obvious benefits like a general applicability to different industries, the
international community has only recently began to recognize formal mediation
procedures as an important tool for businesses. Analyzing the case of the United
Kingdom, it results evident that their use of mediation is still very limited compared to
the US. The two largest British providers of mediation service (ADR Group and CEDR)
each handle between eight and ten mediations per month or a total of 120 per year, by
contrast, JAMS/Endispute, Inc., the largest US ADR provider, handled 17,000 cases in
1995 (Coates, 1997). 2 Although these results do not specifically relate to construction,
they help illustrate the different levels of implementation of mediation in these countries.
In spite of its late-entrant status, the UK does provide a helpful international example of
the different applications of mediation in construction. Analyzing British engineering
cases, Gould et al.,(1998) identified a varied spectrum of mediation styles within the UK
construction industry. It included informal, facilitative (or facilitated), institutionalized,
and evaluative mediation (Figure 20).
Informal Institutionalized
Mediation Mediation
Facilitative Evaluative
Mediation Centre for Mediation
Dispute
Resolution
CEDR Institution
of Civil
Engineers
ICE
Figure 20 - Spectrum of Mediation Styles in use within the Construction Industry in the
United Kingdom
mediations is the expected improvement in the qualifications and expertise of the experts
and third party neutrals.
The last style of mediation in the spectrum identified by Gould et al. (1998), evaluative
mediation, occurs when the third party neutral, in addition to developing a common
ground for the settlement, also issues an opinion as to possible settlements based on the
information developed through the proceedings. In other words, if parties fail to mediate
a resolution, the mediator issues a recommendation on the case.
Another illustrative example of international applications of mediation of construction
disputes is found in Japan. In this case, the Japanese Construction Business Act requires
that construction contracts oblige the parties to address the following issues and include
them in writing in all construction contracts:
1) “How to deal with changes in construction schedule or contract amount, or
sharing and evaluation of loss where construction is changed or postponed or
canceled;
2) How to share and evaluate losses in case of Acts of God or other force majeure
events;
3) How to address changes in contract amounts or construction scope due to
changes in materials or services;
4) Sharing of the liability for damage to third parties;
5) Interest, penalty and other damages in case of delay in performance of
contractual obligations and other liabilities; and
6) Method of dispute resolution.”
(Fenn et al., 1998)
What Japanese authorities have identified is that, in the past, failure to include these
elements in a construction contract has usually led to unnecessary disputes.
In regards to the Japanese common procedures, both public and private
contractual forms in Japan generally include one of two types of dispute
resolution procedures [Figure 21]. In procedure A, both parties agree to solve
their disputes through a third party intermediary designated in the contract,
using either mediation or conciliation. If parties fail to reach a settlement, the
dispute is brought to the Construction Disputes Resolution Committee (CDRC),
similar to a Dispute Resolution Board. In procedure B, disputes are presented
and settled by the CDRC from the beginning of the project, and no party can
request arbitration before or during mediation or conciliation, unless there is a
joint agreement to that effect.
(Fenn et al., 1998)
In both procedures, parties can agree to arbitration once the disputes reach the committee.
Indeed, the Construction Disputes Resolution Committee was established by the
Construction Business Act to provide consultation, mediation and dispute resolution
through a number of regional and local committees located throughout the country.
116
STAGE 4: NON-BINDING DISPUTE RESOLUTION
Construction Arbitration
Procedure B:
Disputes
One-step
Resolution
process
Committee
In summary, the British and Japanese examples presented above, in conjunction with the
examples on the use of mediation in the US, all highlight the multiple benefits of
mediation as a tool to reduce the likelihood of advancing towards binding procedures or
litigation. Nevertheless, there are some drawbacks to the use of mediation, specifically in
relation to the exchange of confidential information, which may expose weak aspects of
each case and reveal possible trial strategies. In order to mitigate this problem, parties
should include strict limitations on the use of information developed through this non-
binding technique in the agreement to mediate. Also, the information provided to the
mediator should be classified as confidential, to avoid having it disclosed without
approval during the proceedings. This way the mediator still receives all the information
to attempt to develop common grounds for settlement, but with the condition that a
portion of it remains confidential as long as an agreement is not reached. Another risk of
mediation results from its increasing use. Many researchers and experts in the topic fear
that as mediation becomes the fallback dispute resolution technique for most construction
conflicts, it will lose its flexibility and harmonious nature, being at risk of suffering the
same destiny of arbitration.
7.3 CONCILIATION
Conciliation differs from mediation in that the neutral party evaluates the dispute and
then issues proposal for the resolution of the dispute that is presented to the parties for
approval or rejection. Conciliation’s non-adversarial nature attempts to improve business
relationships, and the AAA reports that 80% of the cases that attempt conciliation prior to
litigation are settled (Langeland, 1995).
In the UK, the evaluative form of mediation previously identified is in fact a conciliation
procedure, as the mediator is expected to provide the parties with a written assessment of
the dispute and a possible outcome. The engineering side of the construction business has
preferred conciliation over mediation, and the Institution of Civil Engineers (ICE) has
introduced this technique in their standard form of contract for engineering design work.
Moreover, in the most recent Design and Build contract form taken from ICE,
conciliation has been included as a mandatory step in the dispute resolution process.
In other parts of the world conciliation also receives important attention. The concept was
already a part of New Zealand’s “Conditions of Contract for Building and Civil
Engineering Construction” since 1987, in a process that followed some standard steps
and rules; among them:
• “The process is voluntary;
• The conciliator mediates between the two parties in order to identify common
grounds for a settlement;
• All discussions are confidential and information disclosed during the
procedures can not be used in other proceedings should conciliation fail to
achieve a settlement;
• Each party pays half of the costs of the conciliator;
• The conciliator may provide a non-binding written opinion as to the case and
the probable outcome if the case is resolved through arbitration or court
litigation.”
(Hollands, 1989)
New Zealand’s version of conciliation also added the following adjustments and
refinements to the Mediation procedure:
1) “Parties have ten working days to agree on conciliation, and choose a third
party neutral from the date of the request.
2) Once parties agree on using this procedure, and select a conciliator, they have
two months to reach a settlement or to have the conciliator issue a
determination. After that period, either party is free to proceed with arbitration.
3) The decision of the conciliator becomes binding if ten working days pass and no
party notifies the other in writing that it rejects the determination. So the non-
binding decision becomes automatically binding and final to the parties after the
specified period elapses.
4) A presiding judge may act as a conciliator if both parties agree to submit the
case to him/her in that form. If the procedure fails to produce an agreeable
solution, the judge remits the case to another judge for hearings and trial
proceedings.”
(Hollands, 1989)
Hollands (1989) comments on these older conditions saying they are “…more practical
and helpful...” with regards to outlining and defining the DART for the disputants, than
the more recent FIDIC provisions for Amicable Settlement.
118
STAGE 4: NON-BINDING DISPUTE RESOLUTION
into accepting the decision of the neutral. Furthermore, the presentations and the
procedures are relatively simpler than those for formal arbitration. Thus, this voluntary
negotiating tool can be easier to practice and more relaxed than the binding arbitration.
Together with some other DART like mediation and conciliation, this approach can be of
great help in complex disputes that combine technical and legal matters. Non-binding
arbitration can provide the framework for the fact-finding effort and the exchange of
information between the parties, while mediation can provide the communication and
cooperation tools required in developing a settlement. Again, because these procedures
are not binding, parties have more flexibility in defining and changing the role of the
third party based on the specific requirements and characteristics of the dispute. This
notion is supported by Beresford Hartwell (1998), who argued that in order for success to
occur; alternative dispute resolution procedures cannot always be confined to a readily
specified task:
“A mediator for example may need to have some ability to ascertain facts and to
ascertain them without having to rely entirely upon the parties, whose
objectivity is likely to be coloured. A fact finder may need some powers of
persuasion. Rigid categories and restrictions may well be an obstacle to a
realistic settlement” (Beresford Hartwell, 1998).
A simpler form of non-binding arbitration is known as the Advisory Opinion. It is very
similar to a Neutral Advisor (Section 6.1), except for the fact that the third party is not
incorporated into the project from the beginning. In other words, the neutral party only
starts to play a role when a dispute arises and parties decide to request an outside opinion.
Groton (1997) suggests this arrangement can bring disputes closer to reality, as the
neutral view encourages parties to focus on the issues and deal with the disputes before
they evolve into something larger with greater mutual implications.
120
STAGE 4: NON-BINDING DISPUTE RESOLUTION
Condo We can see the effect non-binding arbitration has on disputes by returning to the
Project Condominium project. When the homeowners association added a lawyer who adopted a
hard position, the negotiations between the parties began to fail. The owner recognized
and accepted responsibility for his actions and was willing to meet his obligations, but
this was not possible with the hard position taken by the homeowners. To prevent the
conflict from escalating to litigation, the developer hired a third party to help develop a
non-binding solution.
After reviewing the case and hearing both sides, the assisting third party estimated that
upwards of a half a million needed to be spent by the developer to meet his obligation,
almost a 10% of the original budget. An evaluation was made of the building and issues
were resolved on a case-by-case basis. To bring things into perspective for both parties
the third part look at what was promised, what was done and what the current condition
of obligation.
After five or six sessions and hours of research by the third party, about $50,000 in
billable hours, the parties grew apart. Homeowners wanted US$ 2 million although they
said money was not important and they really just wanted it fixed. The developer
proposed $500,000 in improvements. Mediation failed. Failure was attributed to the lack
of commitment of both of the parties, but more so on unrealistic expectations of the
homeowners. As noted in the chapter, commitment from both parties to develop a non-
zero sum solution is necessary for a successful outcome.
The case has now proceeded to litigation and both parties have effectively lost control
over the outcome. The cost of the third party attempt represents about 1% of the initial
budget. Both parties can only hope that attorney and court fees mirror this as the fight has
already lasted 10 years.
7.9 SUMMARY
The Non-Binding Dispute Resolution stage is crucial in the DRL, for it is the last
voluntary step before the conflict moves to Binding Arbitration and/or Litigation; stages
that result in increased use of economic and time resources, and relationship strains. Non-
binding procedures are characterized by higher levels of formality when compared to
previous stages in the DRL; however, they continue to preserve the flexibility of the
outcome, compared with the stages that follow. This chapter reviewed five important
techniques that can be used to effectively and efficiently resolve disputes: Mediation,
Conciliation, Advisory Arbitration, Fact-Based Mediation, Mini-Trial, Summary Jury
Trial, and Voluntary Settlement Conference.
Mediation has gained importance in the resolution of disputes in the last few years. It
rests in the following principles: the earlier the dispute is resolved, the less damage it
causes; the individuals involved in the dispute are the ones most capable of coming up
with the best solution to their problems; the parties involved in the dispute can best
preserve their future relationships without resorting to an adversarial process; and people
issues may impair the ability to communicate to resolve problems. The use of mediation
offers the parties multiple benefits, such as: the ability to remain involved in the
negotiation, the chance of having a third party neutral that can aid them develop solutions
they might not have considered otherwise, the possibility of arriving to a settlement faster
than in litigation, a significant cost reduction when compared to the litigation process, an
increased likelihood of safeguarding the relationship of functional teams, and the
opportunity for creative solutions and compromises (i.e., win/win).
Conciliation, another non-binding technique, resembles many of the principles of
mediation, with the addition that the third party issues a non-binding recommendation,
122
STAGE 4: NON-BINDING DISPUTE RESOLUTION
Flexibility: decreases along the continuum, less chances for win-win solutions
Third Party Role: moves from a facilitator of communications to a judge or jury with only
advisory opinion
7.11 REFERENCES
124
STAGE 4: NON-BINDING DISPUTE RESOLUTION
7.12 ENDNOTES
1
Although an attempt was made to contact DPIC directly to update the information from
the ENR and Dispute Resolution Journal articles, lack of response did not permit any
further investigation. However, the programs for promoting ADR were found throughout
DPIC’s website (www.dpic.com) signaling that the effort continues to be successful both
for the insurer, as well as for its clients.
2
ADR Group (www.adrgroup.co.uk), CEDR (www.cedr.co.uk), JAMS/Endispute, Inc.
(www.jamsadr.com).
3
The neutral advisor is either a retired judge (rent-a-judge) or a sitting judge in order to
guide the jurors in the legal considerations of the dispute (Zack b, 1997).
126
C H A P T E R
8
STAGE 5:
BINDING
“The future of arbitration is dependent on a
number of factors, probably the most important of
which is the quality of the arbitrators available to
DISPUTE
appoint”
(Crowter, 1999).
RESOLUTION
A publicly owned water agency that provides service to approximately 175,000 people in
the United States undertook a construction program to upgrade an existing reservoir near
an urban area. To assure that the water flowing into this reservoir was safe to drink, a
diversion facility to intercept and divert poor quality water and contaminants, generated
because of urbanization. This US$ 6 million Project consisted of four major components:
A Low Flow Barrier and Inlet Flume, a 48-inch Gravity Flow Reinforced Concrete
Pressurized Pipeline, a North Side pond and Two Wells and an 8-inch Pressurized
Pipeline.
An additional dimension of this Project is the recognition that the site lies in an
environmentally sensitive area, and is therefore subject to many environmental
KEY CONCEPTS
Mediation/Arbitration ....................................128 Adjudicator /Expert Determination ................. 130
Arbitration .....................................................131 Shadow Mediation .......................................... 136
127
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION
128
STAGE 5: BINDING DISPUTE RESOLUTION
actually the opposite as how this technique was design to work. That is why Hoellering
(1997) states that it is best when mediation and arbitration are used separate, since
“...each has its own purpose and ultimate morality.”
The Med/Arb notion is very popular in the East, given the Oriental tendency to seek a
harmonious solution that preserves the relationship rather than seeking what is legally
correct. Whereas most Westerners seek an unbiased judge with no prior knowledge of the
dispute, Asians look for a moderator who will not only end their dispute but also assist
them in reaching a mutually agreeable solution. A clear example is found in China, where
arbitration is combined with conciliation in the ongoing process of arbitration. An
arbitrator hears the evidence and attempts to conciliate the parties, but if it fails
immediately turns to arbitration.
In Australia, the Commercial Arbitration Act 1984 contains a special clause which
suggests the possibility of a “mediated” settlement between the parties before the
arbitration proceeding begins (Hollands, 1989). The Act states: 1
“Power to seek settlement of disputes otherwise than arbitration.
(1) Unless otherwise agreed in writing by the parties to an arbitration
agreement, the arbitrator or umpire shall have the power to order the parties to
a dispute which has arisen and to which the agreement applies to take such
steps as the arbitrator or umpire thinks fit to achieve a settlement of the dispute
(including attendance at a conference to be conducted by the arbitrator or
umpire) without proceeding to arbitration or (as the case requires) continuing
to arbitration.
(2) Where –an arbitrator or umpire conducts a conference pursuant to
subsection (1); and a) the conference fails to produce a settlement of the dispute
acceptable to the parties to the dispute, b) no objection shall be taken to the
conduct by the arbitrator or umpire of the subsequent arbitration proceedings
solely on the ground that the arbitrator or umpire had previously conducted a
conference in relation to the dispute.”
In other words, arbitrators are authorized by this Act to attempt to resolve the disputes by
means other than arbitration. The arbitrator is free to decide on the steps to arrive at a
resolution, including pre-trial conferences with the disputants. The parties in the dispute
must accept his/her decisions with regards to this stage, but both disputants must accept
any settlement. The second part of the clause, allows the “umpire” to proceed with
arbitration if the settlement conferences fail to develop an agreeable solution, without
having his/her powers affected in any way, because of the initial attempts to reach a
agreement.
The arbitrator first attempts to mediate a settlement between the parties. Then, if
unsuccessful, proceeds with binding arbitration. The double responsibility assigned to the
arbitrator, has also been questioned in Australia (Hollands, 1989). Mr. G. H. Golvan,
Barrister, referred to this problem as follows: 2
“...to permit an arbitrator to conduct a mediation conference without
prejudicing his entitlement to subsequently embark upon arbitration is a serious
anomaly in the Act. Arbitrators should be most cautious, if not reluctant, to
attempt to act in both capacities”
Hollands (1989) concludes though, that in Australia, this provision should be regarded in
a positive way, and that it is unlikely that arbitrators would “...breach the rules of natural
justice,” by hearing evidence and settlement proposals, or issuing final opinions on the
issues before the arbitration proceedings take place. On the contrary, this provision
encourages arbitrators to incorporate in the pre-trial motions, steps that are likely to
promote an early settlement of disputes. This includes exchanges of written expert
testimonies and written summaries of each claim to improve each party’s assessment of
the case in dispute, or deferment of arbitration date to give parties a time to review and
maybe attempt negotiation again.
BINDING
DECISION FOR
NOTICE OF APPOINTMENT THE REST OF
DISPUTE OF THE PROJECT.
ADJUDICATOR It can be submitted
to arbitration after
final completion.
130
STAGE 5: BINDING DISPUTE RESOLUTION
There are two interesting features worth noting in the application of this ADR technique
in the UK. First, this procedure is unilateral, so it can be initiated by one of the parties
without the consent of the other at any time during settlement negotiations, simply by
serving the seven-day notice shown in Figure 23. Once it is requested, the procedure is
designed to provide a solution in less than two months. Second, the decision of the
adjudicator is binding on the parties, but only for the remaining duration of the project,
and can be reversed through arbitration or litigation once the job is completed. In other
words, adjudication provides an interim decision, which if unacceptable to one of the
parties, can be reviewed and appealed in arbitration or court litigation. It would appear
that the objective of this ADR approach in the UK is to provide for a fast, but not final,
solution to the dispute in order to allow the job to continue without any further delays.
Adjudication “...is likely to provide a relatively cheap catalyst for settlement” as parties
will be encouraged to address the disputes and reach a settlement, before this procedure is
initiated (Staniforth et al. 1998).
Despite these advantages, the arbitration community has expressed their concerns
towards this dispute resolution method which is neither “...a fish nor fowl nor good red
herring” (Beresford Hartwell, 1998). Two problems are inherent in this procedure. First,
a reliable and knowledgeable adjudicator has to be found, agreed to, and appointed within
seven days. This timeframe might be too optimistic, especially since both parties have to
agree initially on the person to be appointed. However, this can be accomplished if a
roster of qualified adjudicators is pre-selected. Second, some professionals question the
ability of the adjudicator to provide just and reliable answers in less than two months,
considering that construction disputes can be very complex, with many issues and
technical evidence that would require from the Adjudicator certain familiarity with the
project in question. Since the Adjudicator is not incorporated in the project from the
beginning, he/she will depend on information gathered from both parties to assess the
issues and make a determination. This shortcoming could be handled by limiting the type
of disputes that the adjudicator could handle.
Because the Act has been in effect for just a few years, researchers suggest waiting to see
how the industry will respond to this system before issuing a final opinion as to the
strengths and weaknesses of Adjudication, but the introduction of this technique into a
legal framework is expected to promote the use of this ADR technique. In fact, a 1994
study by Fenn et al. (1994) revealed that this type of dispute resolution mechanism was
hardly ever used in the UK, however a similar report conducted in 1998 predicts a
significant increase in the use of the adjudicator in the resolution of construction disputes
(Gould et al., 1998).
Two additional examples of applications of this concept together with other DART are
presented in this book. First, the use of an Adjudicator was incorporated in the Dispute
Resolution Ladder of the World Bank for small projects in substitution for the design
professional. Second the Dispute Resolution Ladder for the Chek Lap Kok airport project
in Hong Kong incorporated this type of third party with binding authority if mediations
failed to provide a settlement. In this last application in Hong Kong, the decisions of the
adjudicator where binding on the parties only through the duration of the project, and
could be overturned by arbitration or litigation once the project was delivered, just like in
the UK application described above. No applications of this technique have been found in
the US yet.
8.3 ARBITRATION
According to the American Arbitration Association (AAA, 2000), arbitration is defined
as “...is referral of a dispute to one or more impartial persons for final and binding
132
STAGE 5: BINDING DISPUTE RESOLUTION
These procedures, each with a specific set of rules, are key in illustrating some of the
problems experienced with arbitration in the resolution of construction disputes. A
summary of the key aspects of each of these new rules follows (based on AAA, 1999). It
is instrumental to provide relevant information as to the changes introduced in response
to the apparent decline in the use of Arbitration 3 and the concerns expressed by the ABA
in the above referenced survey.
Fast Track Rules:
With specially designed procedures for small construction cases, these rules
apply to two-party disputes where no total claim or counterclaim exceeds
$75,000. The different features included are supposed to expedite the process
and not always require a physical encounter of the parties with the arbitrator.
Some fast track rules are:
o Parties select the arbitrator from a list of available professionals
supplied by the AAA. Selection must occur within seven days from
transmission of the roster.
o The award must be rendered within 60-day time limit from the day the
arbitrator is appointed, and seven calendar days from the close of the
hearings.
o Preliminary conferences are by telephone or other electronic channel.
o There are strict limits for information exchange and discovery. Also
there are limits on changes and extensions to avoid add-on claims and
schedule modifications.
o The AAA can also serve notices to the parties by telephone or fax to
expedite proceedings.
o For cases where no claim exceeds $10,000, the dispute is resolved with
a one-day ‘desk arbitration’ by submission of documents without
hearings, unless the parties or the arbitrator chooses to have them. In
this case the arbitrator serves without fee.
Regular Track Rules:
These rules govern all cases not covered by the Fast Track or Large
Track Rules. Regular track procedures are very similar to standard arbitration
rules for construction projects, but they have been upgraded to improve the
procedure in the areas of qualifications of the arbitrators, arbitrators’ authority,
and speed of the proceedings.
Regular track rules offer the arbitrator great amount of power to affect the final
results of the dispute. Other characteristics of this procedure are:
o Enhanced party input regarding arbitrator qualifications and other
needs.
o Parties can change claims and counterclaims before the hearings are
completed. After that, any different claim must receive arbitrator
approval.
o To decrease administrative costs and expedite the process parties may
only strike three names in single arbitrator cases and five names in
multi-arbitrator cases from roster of arbitrators.
o The arbitrator has the clear ability to direct the production of
information and the identification of any witnesses to be called.
o Arbitrators can control the order of proof, bifurcate proceedings,
exclude cumulative or irrelevant testimony, direct parties to focus on
relevant information, entertain motions to dispose of all or part of the
claim, make preliminary rulings or interlocutory orders, and/or request
offers of proof.
For small and simple cases, a single arbitrator instead of the panel of three experts
proposed in Section 8.3 can be used. Parties follow the same arbitration rules, but save
costs by having only one expert presiding over the hearings and deciding on the award.
The obvious disadvantage of having a single arbitrator is that the analysis and decision
making rests on one person. The three-member panel provides a “check and balances”
system that is not available in a single arbitration; therefore the savings should be
weighed against the risks of not having multiple viewpoints when reviewing questions
and issuing the award.
As described in Section 8.3, the AAA has introduced a fast-track, single-arbitrator system
to shorten the processing time of small and simple disputes. This system is for disputes
worth less than $75,000.00, which encompass 50% of the construction cases filed in
AAA for arbitration. A survey conducted by the AAA on over 2,100 projects between
1995 and 1997, to determine if this approach was resulting in actual benefits to the
disputants, concluded that the new fast track single-arbitrator procedures had reduced the
134
STAGE 5: BINDING DISPUTE RESOLUTION
average number of days to resolve a dispute by 33 days, from a previous average of 159
days (DRT, 1997/1998). This survey also found that the average time to appoint an
arbitrator from the day the case is filed had increased from 46 to 51 after the
implementation of the new system. This delay was associated with the fact that parties
have the option of selecting the single arbitrator by mutual consent from a list of
candidates, rather than having the AAA impose one as in the old procedures.
In this form of ADR, a single neutral arbitrator is chosen to preside over the dispute. Both
parties make a presentation of their cases, and propose their respective “best offer” for a
settlement. The arbitrator then selects one of the two proposals, and settles the dispute.
This type of ADR is called Baseball arbitration because it originated in the US Major
Leagues to resolve contract negotiations between owners and players regarding salary
conditions (Fizel, 1994).
The hearings under this approach are usually presentations, in which parties are limited as
to the amount of exhibits they can submit and the number of expert witnesses. These
characteristics result in a faster process and a binding decision. Furthermore, because the
arbitrator can only select one of the two options, parties are encouraged to present and
honest settlement to increase the likelihood that the arbitrator will select their option.
The main disadvantages of this approach are that it offers no flexibility and prohibits
alternative solutions. The arbitrator is limited to one of the two options presented by the
disputing parties. Baseball arbitration is an imperfect yet viable method for resolving
disputes. In the Major Leagues of Baseball this procedure has solved 9 out of 10 cases
(Fizel, 1994), without the need of conducting a full arbitration proceeding as outlined in
Section 8.3.
136
STAGE 5: BINDING DISPUTE RESOLUTION
Reservoir By reviewing the scenario in the Reservoir case, we can predict sources of conflict that
Project one might encounter in this project. Environmental concern (Uncertainty, External) is the
major source of conflict. The misunderstandings and possibly unrealistic expectations of
the owner (Organizational issues, People) also played a role in the dispute.
This case went to binding arbitration. The contractor presented his case with the
following argument.
1) The contractor based their bid price on modifying the access road.
2) The lack of this access resulted in their inability to complete the project in one
season, significantly impacting the cost.
The contractor calculated damages in excess of US$ 1.0 million. The owner presented his
case with the following argument.
1) The contractor did not request for widening this access road until after the
permits were issued.
2) The contractor was aware and involved during the request for use of this road, as
well as cognizant of the degree of environmental sensitivity.
3) The contractor has shown no proof that its bid was based on this access.
4) The allegation of the contractor’s bid price was based on this access was
unreasonable considering the representations made in the bid documents and
during the pre-bid meetings by the owner.
A single arbitrator decided this case. Using their impartial knowledge, the arbitrator
explored the facts and rendered a judgment in favor of the owner.
8.5 SUMMARY
Arbitration, the first binding step in the ladder, was initially introduced as an alternative
to Litigation, to ameliorate the disadvantages of this procedure associated with high costs,
time consumption, and strains in the relationship among the parties. However, as
Arbitration became a popular dispute resolution technique, it lost many of the qualities
that had supported its success: resembling more and more the litigation procedure, and
suffering from many of its limitations; increased formality, cost, and tension between
parties; and decreased control by the parties of the project and flexibility of outcome.
Arbitration represents a definite move away from the “win-win” approach, and thus
involves increased tension among parties, reduced communication, and an adversarial
stance. Information exchange becomes significantly compromised, and legal
representatives become the filters of such communication.
Nevertheless, despite the great resemblance between this stage and the final stage of
litigation, Arbitration continues to preserve some valuable and unique traits. Its main
advantage over litigation is the reliance on knowledgeable third party neutrals, with
recognized expertise in the construction field. This expertise facilitates his/her
understanding of technical and complex construction situations; thus, proving to be more
effective than litigation in those disputes that require significant understanding of
technical data, rather than in those where legal issues have become the center of the
dispute, for which litigation might serve as a more adequate procedure.
Through the years, Arbitration has become one of many Binding procedures, which are
often a modification of the initial form of Arbitration in an attempt to solve some of its
limitations, yet by doing so they have introduced a new set of challenges. Four of the
138
STAGE 5: BINDING DISPUTE RESOLUTION
8.7 REFERENCES
8.8 ENDNOTES
1
This Act is part of the Uniform Commercial Arbitration legislation in force in most
States and Territories of Australia (Hollands, 1989).
2
Speech given by Mr. G. H. Golvan, Barrister, to a Melbourne Forum of the Institute of
Arbitrators of Australia in 1985; cited by Hollands, 1989.
3
The problems with Arbitration in construction disputes are discussed in Section 2.2.2.
140
C H A P T E R
9
STAGE 6: COURT
ALTERNATIVES
“it is the judge-driven change to litigation culture
that is likely to lead the breakthrough”
Coates (1997)
AND LITIGATION
In the western United States, a hospital heating plant was in need of an upgrade before
the following winter season. This particular hospital was owned by a federal government
agency. After design was completed, it was competitively bid out in accordance with
federal regulations. The contract included the renovation of the heating plant as well as
some new additions to the plant. The work was estimated to cost US$ 45 million.
The contractor that was awarded the project was located in the northeastern United
States. It was the first time that they had ventured out side of their geographic region, to
bid work. Since they had no local office, their staff was sent to the site for the duration of
the project. During the construction phase of the project, problems relating to the design
and schedule began to arise. Typical of renovations projects, the scope of work came into
question. What exactly is required by the contract documents and what is not became a
gray area, which the owner and the contractor began to negotiate. The contractor
KEY CONCEPTS
Discovery of Situation .................................. 141 Effective Presentation ..................................... 143
Court Appointed Experts .............................. 146 Judge Pro-Tem ................................................ 147
Trial by referee .............................................. 147
141
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION
questioned the how the liquidated damages were assessed based on the schedule with
such problems. The owner refused to reveal how the liquidated damages were calculated.
The contract called for Step Negotiations, so that the conflict could be resolved at the
lowest level possible. With the upper level management of the contractor and the owner
so far away, the only effective negotiations were on-site. There was little oversight of the
project from the home office. As the differences increased, the negotiations began to
break down. Personality conflicts between the on-site representatives escalated the
conflict into the next stage of the dispute resolution ladder. This stage required both sides
to appoint an expert knowledgeable in the field of construction. Each selection had to be
approved by the other party. An unorthodox, binding mini-trial would then follow. Since
this was a federal contract, if this stage failed, the dispute would be resolved in a federal
court. An overburdened federal court system would be very likely not to uphold the
decision of the arbitrators.
Both parties in this dispute have valid claims and neither wanted to proceed to litigation.
There is no definitive right and wrong. How might a solid understanding of the facts help
resolve this dispute? What effect does the personality conflict have on the dispute? What
other reasons might have caused the negotiations to fail?
142
LITIGATION
notification initiates the conflict. It should be professional looking and include relevant
information describing the incident, the date discovered, what action the owner is
expected to take, the timeframe it should be resolved in and whether or not more
information will follow. An example of this is presented in Figure 24. Along with the
letter, the Contractor has attached a detailed breakdown of the labor equipment and
materials that will be needed to complete the work The owner’s obligation is to accept
the claim in good faith, objectively review it and make a prompt decision as to what
action they will take. If the owner cannot make a prompt decision for various reasons, it
is appropriate to send a courtesy letter stating the reason for delay. As we have learned
from this book, the impact conflicts can have on a project tend to escalate with time. If
either party fails to address the conflict when it arises, there is a greater probability that it
will escalate into a lawsuit.
144
LITIGATION
Meetings should be set up upon receipt of a major claim by either side. In preparation for
these meetings, facts and information should be gathered by both sides, in other words a
thorough discovery of the situation (Section 9.2) should be preformed. Authorized
representatives from all sides of the conflict should attend. It does not aid in the dispute
resolution process to send anyone who is not authorized to act on behalf of the
participant. One should prepare relevant information specifically tailored to the listening
party when presenting their interests. Research whom the presentation is for and prepare
accordingly. Is it a lawyer, a jury, the owner, an arbitrator, or is it the contractor? Know
the strengths and weaknesses of both sides and tailor your presentation to these. If there is
a personality conflict, ask that another representative attend.
All materials and documentation presented should be professional and not altered in
anyway. Keep this in mind when preparing project documentation on a daily basis. Any
comments that you do not want read aloud in court, do not write down. As a rule of
thumb, record only the events and facts and keep editorials/opinions to a minimum. The
same is true for presenting. Present only the facts, avoid accusations, and finger pointing.
A confident, professional performance is usually the most persuasive. In addition, all
material should be presented as soon as it is discovered. Do not hold back any
information. An effective way to present this information is in a formal report with an
executive summary in the front, followed by an appropriate assessment of the situation,
with exhibits such as contract documents, photographs, schedules, and bid information
attached as backup.
If the dispute does make it to court, a presentation in the form of expert testimony can be
one of the deciding factors in determining the award. Although expensive, these experts
bring validity to the claim. Most of the time, judges and juries are unfamiliar with the
construction industry and are forced to rely on the opinions given by these expert
witnesses. For instance, a waterproofing subcontractor waterproofed the walls with a
substance that did not meet the specifications in the design. A lawsuit resulting from a
leaking basement was filed. Validity can be brought to this claim by bringing in another
waterproofer (considered an expert) who states that the standard in the industry is to use
better quality materials and the original subcontractor should have known better.
A solid discovery of the facts and an effective presentation can reduce time in court,
accurately portray the facts, and aid in winning the case. For instance, if the conflict does
escalate to the courtroom, not all hope is lost that the process will be inefficient and
lengthy. In the following sections, three techniques review some of the different
procedures developed in the judicial system for use during court proceedings, which can
improve the litigation process: Court Appointed Experts (Section 9.4), Judge Pro-Tem
(Section 9.5), and Trial by Reference (Section 9.6). These techniques have been
developed by specific courts in an effort to expedite the resolution of civil disputes. They
also reinforce the idea that the construction industry must find ways to reduce the cost
and time impacts of litigation, even if the court proceeding is already underway.
146
LITIGATION
The problems of this process are associated with the selection of this common expert. If
the judge fails to select the best expert from the proposed options, the overall proceedings
will lack the technical depth required to resolve some of the more complicated issues.
More importantly, by having only one testimony, the outcome may depend on it too
much. Therefore, parties most pay close attention to the pre-selection process of the
experts and the presentation of the possible options to the court.
A variation of this approach is reported by Treacy (1995) in the Eastern District of New
York. This court offers disputants the possibility of reviewing the matter in dispute with
an impartial attorney with expertise in the area in question. This neutral helps parties
organize the issues in dispute, explore possible settlement options, and can provide upon
request an assessment of the likely outcome if the dispute in brought to trial. Treacy
(1995) identifies three benefits of this procedure. First, it helps parties organize and learn
about their respective cause before the trial. Second, it can be less expensive than full
discovery proceedings and pre-hearing motions. And third, the information is kept
confidential, since the court does not participate directly in the proceedings. So, parties
are free to develop an alternative solution with the help of the expert if they so desire
once they have fully understood the case and issues in dispute.
which is a branch of the Queen’s Bench Division of the High Court. Its purpose is to hear
cases that require “...prolonged examination of documents or accounts, or a technical
scientific or local investigation...” (Gould et al., 1998), around 80 % of the Official
Referees’ business is related to construction. Within the Court of the Official Referee, a
number of procedures have been developed to manage and expedite the settlement of its
cases: (Gould et al., 1998)
• “Holding regular pre-trial summon or meeting with the parties in order to
discuss and decide the manner in which the trial will take place.
• The use of timesaving written procedures.
• The use of a high level of computerization in the court to handle information and
documentation. In 1996, the “...first ‘paperless’ trial was conducted before one
of the Official Referees using a fully developed case management system..” 1
• Suggesting to parties to consider ADR before continuing with the court
proceeding, if they have not done so yet.”
Other examples of court initiatives to promote and use of dispute avoidance and
resolution techniques in the UK include: (Gould et al., 1998)
1) Since December 1993, disputants are required to inform the courts during pre-
trial meetings whether they have considered using alternative dispute resolution.
In addition, since 1995, attorneys are required to file a pre-trial summary stating
whether they reviewed with their clients alternative dispute resolution, and
whether they considered that all or part of dispute could be addressed through an
alternative technique.
2) A 1996 court direction gave judges an active role in the implementation of
DART by authorizing them to stop proceedings and encourage the
implementation of a DART (i.e., mediation), and to offer neutral evaluations of
the case.
These initiatives support the idea that the increase use of DART in the UK is fueled by
the court system. Two studies by public authorities, Lord Woolf and Latham (1994), have
provided the basis for the evaluation of litigation proceedings, and the introduction of
alternative practices, confirms that part of the DART “revolution” in the UK is coming
from within the judicial system. On this subject Coates (1997) concludes that “it is the
judge-driven change to litigation culture that is likely to lead the breakthrough” in the
implementation of DART.
Hospital Returning to the hospital heating plant, it can be seen that a solid discovery of the facts
Heating did not occur. When the contractor requested that the owner demonstrate how the
Plant liquidated damages were calculated, the owner refused. When the negotiations began on-
Project site, they failed in part due to the personality conflicts, but also to the fact that the
contractor’s presentation was ineffective.
When the next step of the DRL was reached, the contractor did not make the same
mistakes twice. The contractor and the owner both selected their experts. Unlike most
mini-trials, the contract allowed the experts to meet with their parties before the trial
where they would hear the cases presented by both sides. This unorthodox method
allowed for a thorough discovery of the facts by each of the experts for both sides. The
experts became intimately familiar with the claims of both sides. When the trial began,
the experts heard the claims by both sides and actively asked questions, probing the other
side. The experts then negotiated amongst themselves resolving each issue at hand.
148
LITIGATION
This method eliminated the personality conflicts that made negotiation impossible. In
addition is allowed for a solid discovery of the facts, a professional presentation of the
material, the opportunity for a win/win situation. In this case, there were no losers.
9.7 SUMMARY
Litigation is the final stage in the DRL. Although it is considered a costly, time
consuming, and less flexible procedure, it is not an unlikely outcome for many
construction projects. Litigation comes about when other DART have failed to work,
when arbitration clauses are not incorporated in the contract, and/or when the nature of
the conflict, characteristics of the dispute, or the relationship between parties, do not
allow for intermediate steps; for example, in those situations where legal issues, rather
than factual, are the main focus of the dispute. In this Stage of the Dispute Resolution
Ladder, a third party makes the final decision on the dispute.
A solid discovery of the situation and an effective presentation can soften the impacts of
litigation. A thorough understanding of the facts is necessary for all participants. This can
reduce the issues and can even resolve some of the areas of dispute. Start with reviewing
the contract, and then begin to investigate the dispute by requesting documents,
questioning participants, taking written accounts, and investigating the site. When
presenting this information, be confident and professional. Know the audience, select and
prepare accordingly.
Considering the many limitations of this stage, be preapared for a lengthy expensive
battle. This chapter proposes three procedures to attempt to overcome the many
challenges of litigation: Court Appointed Experts, Judge Pro-Tem, and Trial by
Reference. Although these three options within the litigation process offer the parties in
the dispute ways to save money and time, they fail to provide a flexible, cost-effective,
and fast option to resolve disputes, for they all happen in a court context. An important
advantage shared by the three options described above is the fact that the parties are
required to meet, communicate, and agree on certain issues in order to implement any of
them. This “forced” communication among the parties in preparation for, and during the
court hearings, could open the door to new settlement options, and can stop litigation, or
shorten the proceedings.
(Section 9.4) be the standard in the judicial systems throughout the world? Argue
the pros and cons.
9.7 Is Judge Pro-Tem (Section 9.5) any different from litigation? If so, how?
9.8 The majority of judges and juries do not have a construction or engineering
background, and lack technical expertise. Does this fact influence the decision in a
positive or a negative way? Why?
9.9 The issue of a knowledgeable deciding authority is addressed in the Trial by
Referee (Section 9.6) technique. By appointing this figure, what benefits do the
parties lose?
9.10 Are there any reasons that a dispute should go to trial and not be resolved by other
means?
9.9 REFERENCES
[Coates, 1997] Coates, Tom, (1997). ADR is (not) for Wimps. International
Commercial Litigation, Vol. 17 pp. 46-48. March, London.
Euromoney Institutional Investor PLC. 1997.
[ENR, 2/15/1999] Engineering News Record. Lightening up Litigiousness.
McGraw-Hill, New York. Vol.242 (7) p. 68 February 15, 1999.
[Findley, 1997] Findley, Douglas. Construction Claims Preparation Under
ADR. 1997 AACE International Transactions C&C.01.1-
C&C.01.4. 1997.
[Gould, et al.,1998] Gould, Nicholas and Cohen, Michael. ADR: Appropriate
Dispute Resolution in the U.K. Construction Industry. Sweet &
Maxwell, London. Vol. 17. April 1998.
[Latham, 1994] Latham, M. Constructing the Team: Final report of the
Government/Industry Review of Procurement and Contractual
Arrangements in the UK Construction Industry. HMSO
London. 1994.
[Murdoch et al.,
Murdoch, J and Hughes, W. Constuction Contracts: Law and
1992]
Management. E & FN Spon. p 372. 1992.
[Treacy, 1995] Treacy, Thomas B., (1995). Use of ADR in the Construction
Industry. Journal of Management in Engineering Vol. 11 (1) pp.
58-63. January/February, 1995.
[Zack b, 1997] Zack, James G., (1997). Resolution of Disputes: The Next
Generation. AACE Transactions. pp. 50-54.
9.10 ENDNOTES
1
Uff, 1996 cited by Gould, 1998.
150
C H A P T E R
10
CONFLICT
MANAGEMENT
“The general guiding principle of risk allocation
should be that the different parties involved should
seek a multi-beneficial distribution of risk. A
PLAN
dominant party that off-loads all project risks onto
others is unlikely to enhance the chances for a
successful outcome.”
Vega (1997)
KEY CONCEPTS
Conflict Management Process .......................152 Identifying Potential Conflicts ........................ 154
Analyzing Potential Conflict .........................156 Designing the Plan .......................................... 163
Review Process ..............................................168
151
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION
This contract is awarded on a negotiated cost basis, plus a fee. About 90% of the design
is completed and the contractor has been selected with the negotiated fee to be 3.5% of
the total construction costs.
The other sibling, Kelly, has advanced to the rank of senior procurement officer for the
state aviation administration. Her current project is a US$ 1.5 billion capital improvement
program that encompasses 19 different contracts ranging from US$ 20 to 400 million.
The contracts will be let at different times and almost all of the schedules are
interdependent. The majority of these contracts are fixed price, design-bid-build projects,
although some of these contracts have provision for operation and maintenance. This
capital program is fast-tracked to expedite the process. The projects are broken up into
different contracts so that design and construction of the overall program can overlap (i.e.
construction of certain parts of a project will be underway, while other parts of the same
project are still under design).
Each of these siblings are in charge of developing contract documents, in particular a
conflict management plan, for their upcoming projects. These two very different ‘owners’
have dissimilar projects, however both have a great likelihood of encountering some type
of conflict during the development of their projects and they are both concerned. How
should each of them go about planning to identify, avoid, monitor and control these
potential conflicts? How should Brock’s approach differ from Kelly’s approach? Could
they both use the same methodology? Are there restrictions on what DART each of them
could use?
Design and
Conflict Conflict Implement Monitor and
Identification Analysis Conflict Review Plan
Management
152
CONFLICT MITIGATION PLAN
tion
iga
L it
Dispute
Resolution
Ladder
tion
itra
Arb
iati on
Med
ng
ndi
Sta tral
Neu
tion
otia
Neg
Cumulative Effect
of Conflict
Project
Project Life Cycle
Life Cycle
Owners must be cognizant of the time at which the conflicts will occur. At any one point,
there could be numerous conflicts at different stages of the dispute resolution ladder. The
bottom half of Figure 26 shows the effect of multiple ongoing disputes as the project
progresses. The Conflict Management Plan must be able to handle such scenarios. For
example, there could be five potential change orders in negotiations while two others
have escalated to arbitration and the designer is evaluating four other proposed changes
as a neutral advisor. The notion of conflict space should be kept in mind throughout the
design process, especially when identifying possible conflicts, to be managed during the
development of the project.
This list encompasses the major sources of conflict in the construction industry, but a
individual project will not necessarily encounter all of these disputes. If the project does,
then that may be an indication that perhaps it was not a good project to undertake.
Identifying which of these conflicts have the potential to occur and have an impact on the
project is the hardest step in the process of designing a Conflict Management Plan.
Refering back to Chapter 1, we see that the selection of an appropriate delivery system
has a major influence over the type of conflicts that will arise in a given project. When
looking at the organizational structure and comparing the various relationships as shown
in Table 4, one may find that certain delivery systems are more prone to certain type s of
conflict situations. For example, if we take Stephenson’s (1996) construction conflicts,
we can identify which of them may be realize at the interfaces between the multiple
participants in an agency management delivery system (see Figure 27). One can eliminate
certain conflicts against the relationships among the owner, designer, CM and trade
contractor in a various situations if one selects a different delivery system. By doing this
exercise, one can find which conflicts are likely to surface according to the delivery
system selected.
154
CONFLICT MITIGATION PLAN
(CM-Trade Contractor
Owner-Trade Contrac
Owner-Designer
Owner-CM
1 Approval processes + +
2 Back-charges + +
3 Being a good off-site neighbor
4 Being a good on-site neighbor
5 Closing out the project +
6 Communicating with others
7 Constructibility +
8 Construction document quality + +
9 Contract interpretation + +
10 Cost growth + +
11 Decision making
12 Documents and documentation + + +
13 Equipment and material problems +
14 Financial matters
15 Inspecting and testing +
16 Issue, conflict, and problem resolution
17 Job management
18 Labor conditions +
19 Legal matters +
20 Maintaining regular project evaluations
21 Organization, authority, and responsibility
22 Paperwork and administrative work + + +
23 Payment processing
24 Personal quality and problems
25 Planning and scheduling +
26 Policies and procedures
27 Procurement of materials and equipment
28 Program conditions
29 Project cost structure
30 Quality management +
31 Regulatory agency matters + + +
32 Revision processing + + +
33 Safety +
34 Staff morale and attitudes
35 Staffing and personnel
36 Submittal processing + + +
37 Substitutions and alternates +
38 Time growth + +
39 Timely action
40 Training
41 User-group interaction + + + +
42 Value engineering
43 Warranty conditions
44 Weather conditions
45 Work-site condition + +
The conflicts in relationships presented in Figure 27 are just one example of what the
owner should be considering when identifying potential conflicts. A circle counts as two
points and a plus counts as one point. A detailed list of conflicts could be generated by
the company based on historical data or personal experience of the people involved in the
project.
156
CONFLICT MITIGATION PLAN
Organizational Issues
Following the potential areas of conflict in a project as presented in Table 2 (repeated in
Table 14), the first potential conflicts that should be explored are the Structure problems
in the area of Organizational Issues. This area addresses how the project is arranged,
delivered and contracted. To reduce the probability of a structural conflict the owner
should match the appropriate organization, delivery system and contract type
accordingly. When selecting the appropriate delivery system, it can be seen that certain
methods work better in certain situations. In a project where there is a solid, complete,
unambiguous design, the Design-Bid-Build is an excellent choice of delivery method. It
allows a fair competition among many bidders who know exactly what needs to be built.
Given these circumstances, contractors have little to misunderstand and the probability of
claims are minimal. In the case where the functional requirements have been set, but
design is not complete, and construction must begin, the selection of Design-Build might
be more appropriate.
Table 15 through Table 17 relate some common causes of conflict to the probability of
occurrence according to the project and its context. These generalizations begin to set
boundaries where conflict tends to exists. These boundaries were chosen to represent a
broad range of probability from low to high, which should be adjusted according to the
project.
The owner will begin to get a sense of the probability that conflict will occur by looking
at each of the sources of conflict, then rating them. The owner can do this on various
scales, but again, the results depend on how accurate the information is. In the early
stages, a simple high, medium, or low probability will begin to help for the management
plan. Owners, designers, and contractors can use numbers as more accurate, historical
information becomes available to them.
Once the structural conflicts have been analyzed, the focus is shifted to the Process
problems. Owners can expect this type of conflict when handling a larger project if they
have a small staff or have an inexperienced staff. For example, the processing of requests
for information or request for payment from the contractor when handled inefficiently
leads to claims.
Rounding out the Organizational Issues is the probability of encountering conflict based
on the interactions with People. Taking compatibility of objectives for an example, by
introducing profit sharing incentives, a contractor is more likely to ignore frivolous
claims. The probability that conflict will occur in this area is low when the participants’
objectives are aligned. The reverse of this situation is a fixed price, low bid scenario. As
the contractor starts to lose money, the probability of claims will be high, as the
contractor hopes to offset these loses.
Conflicts that arise from Organization Issues are vast and easily be predicted with a little
bit of logic and solid planning. The importance of a solid organizational structure with an
appropriate delivery system is paramount. Although some restrictions are put on various
delivery systems for certain owners, research and past experiences can curb these
limitations.
Uncertainty
The probability of certain types of Uncertainty, although an oxymoron, can be more
predictable than most Organizational Issues. For example, if a contractor planned to do
work in Vietnam they must account for time lost to weather during the rainy season.
158
CONFLICT MITIGATION PLAN
Based on historical records, statistics can determine the average amount of rain that the
contractor should account for. The same is true for earthquakes, floods, fires and other
instances. Insurance is one of the options used to mitigate these unforeseen, but
statistically predictable events. Other options include clauses in the contract for
uncertainty such as adverse weather conditions, differing site conditions or a shortage in
skilled labor.
Similar to the Organizational Issues, owners can look at the project circumstances and
determine the probability relating to the types of Uncertainty conflicts that will occur.
Looking at External uncertainty, environmental concerns in the world have been among
the forefront of controversy and have grown exponentially in the Untied States since the
passage numerous federal regulations in the 1970’s and 1980’s. Many owners found the
impediments to build waste disposal sites overbearing. The “Not in My Backyard”
philosophy has united communities and grassroots organizations who have repeatedly
stalled owners in costly legal zoning battles and court proceedings. An owner building a
waste disposal site should expect the probability of conflict to be high in the area of
Social Impacts, Changing Regulations, and Environmental Concerns. Not taking these
sources of conflict into consideration can be detrimental to a project.
Although rare in certain countries, political risks are highly probable in others. A perfect
example of this is the country of Afghanistan during the 20th century, particularly during
the Soviet invasion throughout the 1980’s. As much as 80 percent of the country eluded
effective government control. This included parts of major cities such as Herat and
Kandahar. The likelihood of political risks occurring on a project approached 100%. This
political instability in many third world countries is apparent and need to be taken into
consideration. The probability and impact of this source of conflict sometimes does not
offset the financial rewards, in these cases no development occurs. Take note that the
International Bank for Reconstruction and Development (IBRD) division of the World
Bank aims to promote projects with these circumstances, although excellent
opportunities, participants should be aware of the risks undertaken in these projects and
the probability that they will encounter conflict.
Table 18 provides a general gauge of the chances of encountering External Uncertainty
based on various project circumstances.
Concurrent with the probability of occurrence of a certain type of conflict is the impact
that the conflict may have on a project. The impact is independent of the probability of
occurrence, that is, the consequences of the conflict if it occurs would be the same if it
did or did not happen. Determining the impact of a conflict is just as important as
determining the probability of occurrence.
Some conflicts have a low probability of occurring but can have a significant impact on
the project, such as conflicts due to natural disasters, prolonged strikes or major
accidents. An example of this is the catastrophic failure of a 567-foot tall crane in the
construction of Miller Park on July 14, 1999 in Milwaukee, WI in the United States. The
stadium was designed to have a retractable roof. During the pick and placement of one of
the 450-ton roof sections, the crane failed dropping the roof section, killing three
ironworkers and effectively destroying ¼ of the completed stadium. This accident
impacted the schedule, increasing the duration by a full year, and caused over US$100
million of damage. A number of factors, including high winds and the management’s
drive to get the project done, were determined by the experts to have caused the failure.
Although the probability of conflicts due to this type of failure happening is very small,
the impact can be enormous.
At the same time, there are numerous other conflicts that are almost a given on a project.
The probability of them occurring approaches 100%, but the impact is almost negligent.
Problems are resolved on a daily basis through negotiations with on site personnel, but
they never escalate to the point of recognition. Issues such as scheduling, work-a-rounds,
and other accommodations made between various project participants on site, happen
daily. Impacts typically range from upset foreman to nasty letters from owners, but
overall the impact is negligent. Negotiation is the most common DART used to resolve
these types of conflicts, in particular step negotiations.
Quantifying impacts can be difficult. One way of doing so is to use historical data
relating to similar instances. Another is through experience and knowledge of the
industry. Initially, quantifying impact does not have to be 100% accurate, as each project
is different, but the idea is to get in the general range so that decisions can start to be
made about how much conflict the project is exposed to and what should be done to
prevent it. A list of examples are presented in Table 20.
160
CONFLICT MITIGATION PLAN
The last step in analyzing conflict is calculating the combined conflict exposure. This is
done by combining the probability of a conflict occurring with the impact that it may
have. The combined conflict exposure is based on the probability that conflict in general
or a specific type of conflict (c) will occur, P(c), and the resulting impact of the conflict
occurring L(c). Combined conflict exposure can be done at numerous levels of detail, but
the accuracy of this analysis is based on the amount of information available. Two
examples are presented to give the reader an idea of the level of detail that this analysis
can be performed. If little or no historical data is available, a crude system of high,
medium, low can be used and can be divided into more possibilities depending on the
amount of the information available.
For example, a homebuilder is considering constructing three new houses in a local
subdivision. The builder has identified the probability of miscommunication with trade
contractors as high. In addition, the impact of this source of conflict can be very high as
well. As the builder starts to list various sources of conflicts and relating the probability
that they will occur and the impact that each of these conflicts has, a combined risk
exposure table can be developed (Table 21). From this analysis, the builder begins to get
a sense of what conflicts need to be managed during the project and will be expanded
upon in the following section.
Another example where historical data is available presented in Figure 28. The bottom
half of the probability tree shown in Figure 28 performs this type of analysis of conflict
exposure on a macro level, or that conflict in general will occur. This analysis is based on
a $200 million project without any mitigation strategy. It predicts that there is a 40%
chance of encountering conflict that will result in a $25 million impact to the project.
There is a 50% chance that conflict on the project will result in a $5 million impact and a
10% chance that conflict on the project will have $1 million impact. In this case, it is
assumed that the probability that conflict will not occur at all is negligible. The overall
conflict exposure is therefore calculated to be $13.5 million.
The probabilities and impacts should be taken from past projects in the range of $150 -
$500 million, adjusting the impact accordingly as a percent of the total construction costs.
One could also attribute sources to the conflict and identify the impact associated with
these sources. Individual conflict exposure analysis would then be done on each source of
conflict. This involves more detail as there are usually several contributing sources
affecting the impact. Care must be taken so that they the impact is distributed properly
and not accounted for multiple times, unrealistically inflating the conflict exposure. By
calculating the conflict exposure that is derived from each source of conflict, the owner
can prioritize the sources of conflict that need to be addressed first, which will aid in
designing the Conflict Management Plan.
Risk Exposure
P(c) x L(c)
P(c) = 0.10
Large Problem 0.1 x 25 = 2.5 M
L(c) = $ 25 M
+ 2.5
P(c) = 0.20 + 1
Yes Medium Problem 0.2 x 5 = 1 M + 7
L(c) = $ 5 M = 10.5 M
P(c) = 0.70
Small Problem 0.7 x 1 = 7 M
L(c) = $ 1M
Partnering
P(c) = 0.40
Large Problem 0.4 x 25 = 10 M
L(c) = $ 25 M
+ 10
P(c) = 0.50 + 2.5
No Medium Problem 0.5 x 5 = 2.5 M + 1
L(c) = $ 5 M = 13.5 M
P(c) = 0.20
Minor Problems 0.1 x 1 = 1 M
L(c) = $ 1 M
After calculating the conflict exposure, the same type of analysis can be done to calculate
the conflict exposure with the application of various DART techniques. Again, based on
historical data, an owner can predict the amount of exposure they will face from a source
of conflict depending on what DART they implement. The top half of Figure 28 focuses
on overall project conflict with effective Partnering (Section 4.3) as the chosen DART. It
predicts that there is a 10% chance of encountering conflict that will result in a $25
162
CONFLICT MITIGATION PLAN
million impact to the project if Partnering is used. There is a 20% chance that conflict on
the project will result in a $5 million impact and a 70% chance that conflict on the project
will only have $1 million impact. Therefore, the overall conflict exposure is calculated at
$10.5 million.
In this situation, implementing Partnering reduced the conflict exposure by $3 million.
Depending on how much it costs to employ Partnering, one can determine whether this
DART should be used. The selection of the appropriate DART technique and the
cost/benefit analysis is discussed in further detail in the next section.
Once the conflict exposure is calculated for each of the identified potential conflicts, they
can be grouped into priority levels. They can be categorized into one of the following
three groups according to a pareto optimal categorization:
Group A: 10–20% of the top conflicts with high potential of realization, which
together account for roughly 60% or more of the total potential impacts the
project.
Group B: all activities not members of group A or C.
Group C: large percentage of the bottom conflicts in terms of potential of
realization, which account for 10% or less of the total potential impacts.
The conflict management plan can then be designed according to the priority. This is
discussed in more detail in the following section.
Now that the major sources of conflict have been identified and analyzed, it’s time to
look at which of these conflicts need attention. This can be done in numerous ways, but a
table incorporating the necessary information seems to work best. The first four columns
of Table 22 incorporate the information gathered in the analysis of the conflicts identified
(Section 10.3). The purpose of this table is twofold. First, it allows the prioritizing of
conflict based on the exposure. Next, it begins to assign appropriate prevention strategies
to address those potential conflicts. The management strategies used are those listed in
the Prevention Stage (Chapter 3) and cost is the cost associated with each. The use of
only prevention DART is because we are targeting conflicts before they occur.
Probability of
Occurrence
Occurrence
Prevention
Resolution
Procedure
Impact of
Exposure
Exposure
Reduced
Strategy
Strategy
Conflict
Conflict
Cost of
Source of Conflict
Organization
Delivery System
Contract Type
Contract
Documents
Contract Terms
Performance and
Quality
Payment Delays
Disruption
Administration
Formal Channels
Information
Sharing
Misunderstandings
/ Communications
Compatibility of
Objectives
Management
Negligence
164
CONFLICT MITIGATION PLAN
Once the preventative measures have been selected, a resolution procedure must be
designed so that when conflicts do arise, the conflicts are addressed and resolved. This
step in designing the Conflict Management Plan involves reviewing Stages 2 through 6
and comparing them with the characteristics of the project. In selecting an appropriate
resolution procedure, one must ponder numerous questions about the individual project.
How large is the project? What type of delivery system is used? How many parties are
involved? Who should initiate the process? What is the chain of command? How are
change orders handled? How crucial is the schedule? Should conflicts be resolved as
soon as possible, or at the end of the project?
All of these factors and more shape the decisions made in determining this step. If
schedule is of the utmost importance, an on-site representative or third party neutral can
deliver solutions instantly. In addition, include a clause that all appeals must be filed
when they arise and settled at the end of the job, and the fast track schedule will not be
hung up on conflicts. If the project is of an unusually large size, an impartial DRB might
be an alternative to a single neutral. There are pros and cons to every approach, as
outlined in each chapter, but the intent here is to identify which ones will be appropriate
to a given situation. In comparing these advantages and disadvantages with each project,
a resolution procedure should begin to take shape. It is now time to apply the knowledge
gained about the individual DART to a particular situation.
In addition to the application of DART, some other factors must be considered such as
cost, other party’s willingness to participate and clarity of procedure. The following
section addresses these factors in more detail.
This process starts with the identification of possible conflicts and an agreement on who
is responsible for addressing them first. Therefore, every party involved knows their role
and there are no surprises or excuses when the conflicts do arise. Agreement on
allocating the responsibility for conflicts upfront helps reduce and sometimes even
eliminate finger pointing.
This identification currently is done in a variety of ways. The most common of
addressing conflict has been in adding or modifying clauses contract. Another way is to
identify them in the Conflict Management Plan (a part of the contract documents) and
have each party sign the plan stating they are aware of and agree with their responsibility.
In either case, the contract should be reviewed for conflicting statements that create
ambiguities. These types of ambiguities (Organizational, Structural) often lead to
litigation, as both parties involved identify with the conflicting clause or document that
supports their claim. It is the owner’s responsibility to develop a contract with no
ambiguities. Confusion is reduced by eliminating them or defining which one takes
precedence over the other.
In addition to identifying who is responsible upfront, the importance of good
documentation cannot be stressed enough. A paper trail can be invaluable, when
reviewing what when wrong and aids in identifying who was responsible.
One thing that has not been mentioned before but is of great importance is the cost of
implementing these conflict resolution strategies. It is safe to say that resolution of any
conflict in construction is possible if cost is not an issue. With the invention of new and
innovate dispute and avoidance techniques mentioned throughout this book, one must
keep in mind that these techniques are only plausible if they bring value to the project. Is
a couple going to spend $20,000 on a partnering retreat with a contractor that is painting
their house? Of course not. The costs far exceed the benefits, but on a billion dollar
privately funded dam project, a $100,000 might be the best investment made if it helps
avoid or resolve a $100 million claim. The participants must keep this in mind when
designing the Conflict Management Plan.
One way to do this is by reviewing the combined conflict exposure developed when
analyzing the conflicts and compare them with the cost of the mitigation strategy
identified from the prevention stage. One should implement these techniques if the cost
of the mitigation strategy and the resultant conflict exposure is less then no management
strategy and its corresponding conflict exposure. Looking back at Figure 28, we can see
an example of this. The calculated conflict exposure if Partnering is implemented on this
project totals $ 10.5 M. On the other hand, if Partnering is not implemented the conflict
exposure increases to $13.5 M. Assuming that the cost of implementing Partnering on
this project is $0.5 M, it would make sense to do so. By applying Partnering to this
project, $11 M is expected to be spent on disputes (10.5 plus the 0.5 spent on Partnering)
compared to $13.5 M expected to be spent if nothing is done. In this case, it does make
sense to put into practice the DART, but in others, it might not. If the cost of
implementing Partnering were $3 M, it would not be optimal to do so.
If the data is not available to do this type of detailed analysis, one can use the high,
medium, low approach. Referring back to the example presented in Section 10.3.3, Table
21 can be recalculated to account for the result that Partnering will have on the various
sources of conflict. The cost of implementing this strategy can then be weighed against
this analysis.
This type of cost/benefit analysis should be done as a reality check when using these
strategies. The cost of installation for some DART is negligent, while others can grow to
be quite expensive. Keep in mind that cost does not merely mean monetary loss. Time
loss and overall stress can also be a factor. It does not take into account for unquantifiable
costs, such as the value of a good working relationship. Although some of these things
might not be able to be quantified as a monetary value, they should not be overlooked.
A contingency plan is nothing more than a list of options for both of the parties. These
options should outline the strengths and weaknesses that the Conflict Management Plan
has. As mentioned earlier, the cost of implementing various DART may exceed the
benefit. Therefore, by not implementing these DART everyone must be aware that they
166
CONFLICT MITIGATION PLAN
have conceded that conflict in this area may occur and no strategy is in place to prevent
them from happening or mitigate their impact if they do occur. The contingency plan
identifies these areas where conflict is expected to arise.
The contingency plan is also a backup in case of the unpredictable. In most cases, this is
litigation and at times, litigation is the best contingency plan. Without the threat of
litigation, some of the DART are not a viable option. Some participants out there would
like nothing more than to tie a dispute up in court for years, whether or not they think
they are going to win or lose. Dishonest owners who currently hold the money do not let
it go without a fight. For a contractor this could mean bankruptcy if the project is long
enough. In other instances, stubborn contractors feel that they are entitled to more then
they really deserve, causing stress for the owner.
In general, the contingency plan is one more step in the “What if?” process. By taking
this extra step, it keeps the participants from stumbling if a part of the Management Plan
does not work as anticipated.
Eventually the application of technology will aid in the process of designing a Conflict
Management Plan. Preliminary models are being developed and tested, incorporating the
information presented in this chapter. As research and development continues and more
data is gathered, accurate functional models will be generally available to analyze
different scenarios based on different variables and predict the amount of conflict that
will occur on a given project. Different scenarios would be easily entered and modeled
with minimal computation. An example of such a system can be in the DARTS system
developed by Fenisoky Peña-Mora and Tadatsugu Tamaki at the Massachusetts Institute
of Technology (Figure 29).
In this application, project circumstances are taken into account and then the user can
select different DART to minimize conflict on that project. Applications such as these
will allow the users to review numerous scenarios and assist the participants in refining
the Conflict Management Plan. This is especially important during and after the project is
underway.
168
CONFLICT MITIGATION PLAN
Satisfaction with the results Trends over negotiated amount over proposed
amount
As the project continues and relevant data is collected, it can be analyzed to identify
where conflict still exists. Looking back at Figure 25, this part of the review process of
identifying existing conflict completes the loop and begins the cycle of Conflict
Management process again. A more detailed description of this process is depicted in
Figure 30.
Information on
Potential Conflicts
Contract
Contract Contract
Contract Contract
Contract Contract
Contract
Planning
Planning Formation
Formation Administration
Administration Monitoring
Monitoring
Negotiation
Indexes
Agreement/
Perceived Conflicts Negotiation
Solution
Potential Conflicts
Brock Returning to the Brock and Kelly case, the siblings are facing the task of designing a
and Conflict Management Plan. Kelly identified the following as the major sources of conflict
Kelly’s in the $1.5 billion program.
Plan
Table 25 – Kelly’s Conflict Management Plan
Occurrence
Occurrence
Probability
Prevention
Impact of
Exposure
Exposure
Strategy
Strategy
Conflict
Conflict
Reduce
Cost of
of
Source of Conflict
By local regulation, Kelly was restricted to competitively bidding all of the contracts. To
align the objectives, reduce miscommunication and disruption she decided to invest in a
Partnering program. In addition to Partnering, she hired and independent Program
Manager to help handle the load of the projects that the government agency is taking on.
independent Quality Control inspectors were also assigned to the construction phase to
watch over the contractor. A clause was added in the contract that requires the contractor
to provide a Quality Assurance representative as well. Both of these personnel aim to
reduce the Performance and Quality conflicts. Following the preventions aspects of the
Plan, Kelly opted to use a DRB to resolve disputes that arise to reduce the impacts of
these disputes. This was not included in Table 25 because it applied to all of the sources
of conflict. The DRB panel will consist of 3 members, one appointed by each party and a
third jointly select by the appointees. Disputes can be submitted to the DRB at any time
during the project only after the parties have attempted at least three rounds of good faith
negotiations, with or without a mediator paid for by the owner. The DRB panel has the
power to issue binding solutions so as not to affect the schedule of other contracts.
Brock on the other hand, took a different route than Kelly. Not being too familiar with the
hotel development business, he hired reputable contractors experienced in building hotel
and added some incentive with shared savings. In addition, he hired a consultant
knowledgeable in the hotel development business for the first project. Although this
would cut into his profit a little, it would align the objective of the parties involved and
reduce his exposure to conflict. Various clauses were added to the contract to share the
risk of differing site conditions and adverse weather. Costly legal proceedings could
170
CONFLICT MITIGATION PLAN
Occurrence
Occurrence
Probability
Prevention
Impact of
Exposure
Exposure
Strategy
Strategy
Conflict
Conflict
Reduce
Cost of
of
Source of Conflict
10.6 SUMMARY
The conflict management plan is one of the most important but often overlooked steps in
the project. It should be conceived when planning begins and continue to be reviewed
and revised throughout the project life cycle. The Conflict Management Plan is
developed by identifying conflicts that might occur on the project, then analyzing the
impacts that each will have. After prioritizing these conflicts, dispute avoidance
techniques are applied to prevent the conflicts from occurring. Next, a resolution
procedure is designed; focusing on the impact of the conflicts, so when conflict does
occur the effects are minimal. All participants in the project should be involved
throughout the process or as they are brought onboard.
These plans are individually tailored to each project. The implementations of the DART
are done on a cost versus benefit basis. Although it is virtually possible to resolve every
conflict with money, it is not always effective. Quality of the final product and schedule
must be kept in mind when performing the cost/benefit analysis.
By designing the Conflict Management Plan, all the participants in the project are forced
to contemplate the conflict that they will encounter. This will allow the allocation of
responsibility for each one of these sources of conflict before it occurs. This upfront
distribution reduces ignorance and allows the responsible participant to effectively handle
conflicts.
10.8 REFERENCES
172
CONFLICT MITIGATION PLAN
10.9 ENDNOTES
none
11
CASE STUDY:
TREN URBANO
“…at the Construction Progress Meeting(s) or
partnering sessions at which the Claim is
considered, technical personnel of the parties,
PROJECT1
experienced in the discipline involved in the Claim,
will endeavor diligently and in good faith to
identify the issues involved, consider impartially the
countervailing positions, and achieve a resolution
of the Claim.”
(Rio Piedras Contract, 1997)
The Tren Urbano Project is a light rail transit line being developed in San Juan, Puerto
Rico. The first alignment of the project, Alignment 1 (Figure 32), is a 17.2-kilometer line
including 16 stations with maintenance facilities and operations and the administration
building. This first phase of the project was expected to be completed by November 2001
and to cost $1.5 billion. This project presents several peculiarities that made it perfect for
the analysis in this book. It is a large-scale project, with an innovative procurement,
multicultural and multiphase characteristics.
In this chapter, the history and a detailed description of the project are presented,
including the parties involved and their contractual relationships. Following the
KEY CONCEPTS
Project Description ........................................176 Procurement Strategy ...................................... 178
Conflict Management ....................................180 Analysis of Tren Urbano Components ............ 184
174
TREN URBANO
176
TREN URBANO
The project includes a maintenance and storage facility in the center of the alignment at
Las Lomas, which will also be the location of the system’s communications and train
control system. Tren Urbano will offer operator-attended automated service via a double-
track fixed guideway. The system will operate 20 hours per day, with vehicles providing
four-minute operating headways during the morning and evening peak hours. Roughly 55
percent of all Tren Urbano riders will arrive at the transit stations via bus or the privately
operated, non-subsidized público minivan service (private microbus public transportation
system). Given the importance of such intermodal transfers, Tren Urbano stations are
being designed to maximize integration of all modes, including pedestrians, públicos,
buses, taxis, and private automobiles. Five of the stations will have park and ride lots and
four will serve as transportation centers where the bus and público routes will be
interconnected with the rail system.
The Puerto Rico Highway and Transportation Authority will purchase 64 transit vehicles
for the Phase I line, with an option for another ten vehicles. The vehicles being built for
Tren Urbano, by Siemens Transportation Systems, are advanced technology stainless
steel heavy rail vehicles equipped with state-of-the-art AC three-phase propulsion
systems and advanced signaling, monitoring, and diagnosis systems. Traction supply will
be 750 V DC third rail, which was selected because it minimizes visual clutter and is less
vulnerable to storm and hurricane damage than overhead wire catenaries. The cars will
run as married pairs with seats for 72 passengers and a design capacity of 180 passengers
per car. Each train will consist of one or more married pairs coupled together, up to a
maximum train length of six cars. These will have a maximum speed in revenue service
of 100 km/hour (60 mph).
178
TREN URBANO
A summary of the hybrid delivery methods used in Tren Urbano can be seen Table 28.
Below the table are descriptions of how the Tren Urbano Project uses each of the delivery
methods.
Table 28 - Types of Procurement included in Tren Urbano Hybrid Approach
1) Turnkey Contractor. One entity develops and delivers the project to the owner as
one package. Essentially the owner buys the complete project from one
organization. In Tren Urbano, STT is responsible for the complete integrated
project.
2) Design-Build-Operate-Transfer (DBOT). The same entity designs, builds and
operates the project. In Tren Urbano, STT does the design, construction and
operations.
3) Pure or Agency Construction Management (at no risk). The owner holds the
contracts with the designer and contractor(s), but another agency manages the
contracts in behalf of the owner. In the Tren Urbano Project, GMAEC performs
construction management for the owner, but they do not hold contracts with any
of the designers, constructors or operators and therefore are not exposed to any
risk.
4) Multiple Prime Contractors. The owner first hires a designer, and then procures
several contractors. In the Tren Urbano Project, there are seven prime
contractors.
5) Design-Build (DB). The design and construction is procured as one entity and
the construction starts before the design is finished. Often the same entity or
partnership does both design and construction. In the Tren Urbano Project, the
civil contractors perform design together with construction.
The contractual layout of parties in the Tren Urbano Project using this hybrid delivery
method can be seen in Figure 33. It can be seen that the owner, the Tren Urbano Office,
has direct contracts with their consultants, the ASC’s and STT, and STT has no
contractual relationship with the ASC’s.
Consultants to
owner Tren Urbano Office
(GMAEC) (TUO)
USA
Siemens Transit
Team
(STT)
German/Other
Since the procurement strongly affects the formal and informal relationships between the
parties, it is important to carefully consider its implications.
11.4.1 PARTNERING
The design-build agreement for each section of the Tren Urbano project states (Rio
Piedras Contract, 1997):
“ To promote the development of effective working relationships among the
Contractor, key Subcontractors, the Authority’s Representative, the Contracting
Officer and the Authority, to promote cooperation and trust, and to achieve
common and individual objectives on a non-confrontational basis, the Authority
encourages the use of Partnering techniques during the course of the Contract.
Within thirty (30) days after the date of execution of the Contract, the parties
shall participate in a partnering workshop. The Contractor’s key on-site staff
and Authority personnel shall follow the initial workshop. Follow-up workshops
will be held periodically as agreed to by the Contractor and the Authority. The
Authority shall be periodically responsible for the expenses of conducting the
initial workshop and any follow-up workshops; provided, however, that each
participant shall be responsible for the cost incurred by the attendance and
participation of its own representatives. Facilitators for partnering workshops
shall be retained through the partnering program of the American Arbitration
Association. The parties will participate in partnering sessions with each other
and with other Project Contractors, as necessary, to facilitate the progress of
the work of the Project Contractors and to resolve disputes.”
180
TREN URBANO
The change order process is used to document, evaluate, negotiate, disposition and issue
change orders in Tren Urbano. The complete change order process is composed of four
major sub-processes – Initial Notice, Contractor Change Request, Authority Change
Request, Change Directive, and Change Order [Rio Piedras Contract, 1997]. For a
Change Order to occur not all of the sub-processes listed may be needed.
The Contractor Change Request process starts with the contractor submitting an Initial
Notice (IN) to the PRHTA/GMAEC that a change order is due (Figure 34). Within 10
days of the IN, the contractor must submit a complete estimate to complete the change
and an updated schedule of the change with documentation of its merit in the form of a
Contractor Change Request (CCR). Usually the CRR is not filed within 10 days and the
contractor, which is usually approved by the PRHTA/GMAEC, files an extension. Now
the Contract Manager together with Technical Services, Project Controls, and the legal
team of the owner (PRHTA/GMAEC) determines whether the CCR has any merit. If the
CCR has no merit, it is returned to the contractor; otherwise the CCR follows the Change
Notice (CN) or Change Directive (CD) process.
Initial Notice
submited by
contractor
10 days
If needed (usually)
request for
extension for
contractor to
submit CCR
Contractor
Contractor may
resubmit Initial No merit
Change
Notice Request
(CCR)
Avoided if possible
signature process
Merit to CCR 2-4 weeks
signature process
2-6 months
signature process
Difficult and long
negotiation process
Change Order
A CCR becomes a CD if it is determined that the contractor needs to start the work
immediately and the cost, time and technical impact evaluations will be negotiated after
the CD has been issued. This direction is avoided, as the negotiation process later
becomes more complicated and could be more costly for the PRHTA. After the CN or
CD has been approved, a Change Order (CO) must be negotiated and the cost, time and
technical issues must be approved.
The technical issues, cost, and time must be negotiated for both the CN and CD between
the PRHTA/GMAEC and the contractor. Usually the technical issues are quickly
resolved. There seems to be an inclination not to give the contractor schedule extensions
if possible, even it is means increasing payments to the contractor. The cost of the change
is usually what lengthens the negotiation process. On the PRHTA/GMAEC side, the
Contract Manager makes the final recommendation. Final approval occurs during the
signature process.
The signature process referred to is the procedure to obtain the signatures of a list of
project participants who must review and approve the package (Figure 34). The order in
which the signatures are received is not prescribed; however the list can be up to 10
people from the Contract Manager to the Secretary of Transportation. Initially the
Executive Officer (Director of the PRHTA) had the final signature, however in early
1998, the Secretary of Transportation signature became required as well. As the Secretary
has many other projects to oversee, to obtain his signature as well as the Executive
Director’s is a lengthy process. This may add time to an already lengthy process for
gathering signatures, for example a CN often takes 2-6 months to be approved. There the
signature process, as a sub-process of the change order process, can be a bottleneck. Now
the contractors and PRHTA/GMAEC must work together to avoid delays while the
change order is being processed.
When a change order starts, a new negotiation process is beginning. The minimum
number of participants is two: the contractor and the owner (represented by the contract
manager of the section). For practical purposes, the submission of the initial notice (IN)
will be considered the start point of the negotiation (i.e.; the first step). This assumption
may not always be true: the contractor might call the contract manager to inform him of
the situation before an initial notice is filed, or the contract manager might have obtained
information concerning the problem beforehand. Therefore, in most of the cases the
negotiation process starts before the official submission of the IN, because the parties
have been preparing themselves for the negotiation for some time. This “preparation
time” is between two to ten weeks.
Despite delays that may occur, the change order process itself can deal with a given
problem and end up finding a solution. However, the owner is the one that finally
determines if the change order has merit or not. If the contractor does not feel satisfied
with the outcome of the process, he or she may ask for a revision of the decision. If this
happens, it is said that the contractor asserts a claim.
The Design-Build agreement for each section in the Tren Urbano Project has a whole
article dedicated to Claim and Dispute Resolution (Rio Piedras Contract, 1997). It states
the directives the parties shall follow to resolve claims and disputes.
Step Negotiations. If a claim is asserted by the Contractor of the Authority, the matter
shall be placed on the agenda of the next Construction Progress Meeting, and shall be
specifically identified as a Claim:
“…at the Construction Progress Meeting(s) or partnering sessions at which the
Claim is considered, technical personnel of the parties, experienced in the
182
TREN URBANO
discipline involved in the Claim, will endeavor diligently and in good faith to
identify the issues involved, consider impartially the countervailing positions,
and achieve a resolution of the Claim.”
These technical personnel have a maximum time of sixty (60) days to resolve the claim.
After that, the matter will then be submitted to the Contractor’s Project manager and the
Contracting Officer for resolution. If the Contractor’s Project manager and the
Contracting Officer are unable to resolve the matter within ten (10) workdays, either
party may then refer the Claim to the Contractor’s Project Executive and the Executive
Director. These senior executives shall meet within ten (10) workdays of such referral
and shall endeavor to resolve the Claim. If the Contractor’s Project Executive and the
Executive Director are unable to resolve the matter within such ten (10) workday’s
period, the Contracting Officer shall, within ten (10) workdays, issue a written
determination (a “Claim Determination”) to the Contractor describing the Authority’s
position with respect to the Claim. If the Contractor disagrees with a Claim
Determination issued by the Contracting Officer and gives written notice of such
disagreement to the Contracting Officer within ten (10) workdays after the date of the
“Claim Determination”, the Claim shall become a “Dispute”. Therefore, the contract
establishes five negotiation steps the parties shall exhaust before a Claim becomes a
Dispute. Figure 35 shows graphically the negotiation steps as a function of Time.
Dispute
ESCALATION OF CONFLICT
Claim
0 5 10 15 20
Time (weeks)
Figure 35 - Negotiation Steps required by Contract before a Claim becomes a Dispute
“At all time during the claim resolution process, the Contractor shall proceed
with the Work diligently, without delay, in accordance with the Contract, shall
otherwise comply with the Contract Documents.”
Dispute Review Board (DRB). In order to continue with the dispute resolution process a
DRB shall be established and shall consist of three members: One DRB member shall be
selected by each of the Authority and the Contractor. They each shall nominate three
individuals for membership to the DRB. Then, the Authority and the Contractor each
shall select one individual from the other’s list of nominees. The time horizon for this
procedure is a month and a half. The third member of the DRB shall be a qualified and
impartial Chairperson, who shall be selected by mutual agreement of the first two
members of the DRB within 21 days 3. Therefore, the foundation of the DRB may take
more than two months.
Processing Disputes. Within 45 to 60 days after receipt of a copy of the Contractor’s
request for a meeting and supporting statement, the Authority shall submit to the DRB
and the Contractor (i) the Authority’s response to the dispute, and (ii) any counterclaims
the Authority has relating to the dispute. Within 21 days after receipt of a counterclaim,
the Contractor shall submit to the DRB and the Authority a detailed statement setting
forth each factual and legal defense to the counterclaim. Within seven days after the date
of receipt of the Authority’s answer or the Contractor’s response to the Authority’s
counterclaim, whichever occurs later, the DRB shall set a date for an initial meeting on
the Dispute. Then, within 30 days after the close of the meeting(s) on a Dispute, the DRB
shall issue draft findings and recommendations to the Authority and the Contractor. Each
party shall notify the DRB of a miscalculation or other error in the draft within 14 days,
and the DBR has 14 days, after receipt of the parties’ responses to the draft, to submit its
final findings and recommendations to the Executive Director and the Contractor.
Finally, within 30 days after receipt of the DRB’s final findings and recommendations,
the Executive Director shall issue a written decision either accepting or rejecting the
DRB’s recommendations. Then, the estimated time that requires to process a dispute is
around six months.
Legal Action. Within 90 days after receipt of the Executive Director’s decision, the
Contractor may file a court action seeking a judicial resolution of the Dispute. If the
Contractor does not file suit within such 90-day period, the Executive Director’s decision
shall be final and binding, and any further judicial review shall be barred.
Hence, the contract establishes all the steps that the parties shall pass through in order to
search for a solution before reaching the ultimate step of escalation of conflict: litigation.
These steps give us a time frame for the negotiation: the claim resolution process may
last up to 20 weeks, and the dispute resolution process may last almost 6 months.
184
TREN URBANO
The management of Tren Urbano consists of several parties each with their own
objectives, priorities and set of tasks that may at times overlap. Under ineffective
partnering, the management would be inconsistent and competitive. On the other hand,
the different perspectives can provide checks and balances that can be superior to a
traditionally delivered project as the parties with different perspectives and aims can
complete the task more thoroughly. If a team building effort is initiated, overall
duplication of effort could also be minimized, as more information would tend to get
shared. Duplication, however, is not necessarily something to be avoided. The pros and
the cons must be evaluated based on the circumstances to meet the project objectives and
partnering could elicit these situations (Table 29).
Table 29 - Pros and Cons of Duplication
Pros Cons
Better quality check Extra cost and potentially extra time
More parties involved, better end product “All responsible, no one is”
Competition creates motivation Competition can create an adversarial
relationship
The Tren Urbano project aims at very high quality and, thus, chooses to have some tasks
overlap to ensure the highest quality at what is perceived as a small price. It is assumed
that effective partnering will overcome the obstacles of the cons (Section 11.5). These
cons include competitive adversarial relationships and the phenomenon that often
happens when too many entities are responsible for one task: one party assumes others
will be performing the task, the others assume the first party is doing it, so therefore no
one is. Hence, Tren Urbano relies on partnering in accomplishing its objectives, and
effective partnering becomes especially important.
An example of duplication is that Parsons Brinkerhoff (PB), who is part of the Siemens
group, performs much of the management functions in terms of interface between
systems to fixed facilities and interface between fixed facilities. The owner’s consultants,
the GMAEC, also perform schedule and design reviews of the ASCs’ work. Poor
partnering may cause inconsistent comments from the management team to the ASCs,
but with good effective partnering a more complete review can be provided than if only
one party was involved in the review process. Thus, the integration and collaboration
between GMAEC and PB will provide for a superior project.
In order for GMAEC and PB to partner effectively, it is required that PRHTA and STT
form a partnering bridge where PB and GMAEC can pass through as seen in Figure 36.
Partnering
PRHTA Bridge Siemens
GMAEC PB
For a more effective partnership between the owner, STT, and all other members of the
Tren Urbano Project, STT should be perceived as part of the owner’s management team.
This can be accomplished by strengthening the owner representative objectives and
priorities in the STTT contract.
The STTT contract characterizes the objectives and priorities for the STTT contractor in
line with two contrasting viewpoints, as owner representative and as pure contractor. This
occurs because the responsibilities of the STTT contractor include contractual obligations
as well as aligning objectives and interests with the owner (Table 30).
Table 30 Two perceptions of STT
For instance, the owner’s procurement strategy aim was to give the STTT contractor
incentives to make decisions on the design and construction and to act in the owner’s
interest (i.e., to reduce lifecycle costs), since they will be operating and maintaining the
project for five to ten years. On the other hand, the STTT contractor is responsible to
design and construct one of the civil facility sections and all the systems such as train
vehicles and control systems. These functions give incentives for the owner and the
STTT contractor to have a more traditional owner-contractor relationship.
186
TREN URBANO
It may be questionable whether this dual role is possible or if the perception of STT tends
to lean one-way or the other. Currently, many parties (TUI, 1997-8) actually perceive
STT primarily in a contractor role. This may be because STT does not have a direct input
and a binding mechanism for overseeing the ASCs such as a direct contract with the
ASCs, which could pull STT more in the owner representative direction.
Alternatively, it is important for STT to act more like an owner than a contractor in order
for the objectives and incentives to be aligned for effective partnering. Strong partnering
will give the STTT contractor more authority to perform management functions
effectively. Hence, the benefits of the turnkey contract can be gained as envisioned by the
federal turnkey demonstration project.
Aside from the important role partnering plays between the owner and STTT contractor,
partnering is equally important in Tren Urbano with the ASCs. ASCs partnering with the
owner can improve costs and schedule. Also, ASC partnering with STT is especially
important because there is no contract between them. If partnering breaks down, the
owner would stand between the various contractors, and the advantages of the turnkey
delivery method would deteriorate.
Partnering has been officially established in Tren Urbano through initial partnering
meetings. Initial meetings include conferences with each contractor separately, all
designers together and a conference with all principals of the project at a Quality Summit
in Oct. 1997. Partnering follow-up monthly meetings have also been held.
Partnering started out very promising with a series of initial meetings. They were held in
a neutral location for 2-3 days for each contract with the owner. A member of the
American Arbitration Association (AAA), an outsider to Tren Urbano, facilitated these
meetings. Risks, concerns, goals, objectives were discussed in small mixed groups. These
meetings fit the criteria for typical good-partnered projects. However, the benefits of
partnering will only hold true if the harder to measure, “soft”, criteria of partnering are
also met. The soft criteria include genuine effort of all parties to developing trusting
relationships. Then, only over time can the effectiveness of these initial meetings be
measured.
A quality summit (TUQS, 1997) was also held in a neutral location (i.e., a hotel) for the
purpose of all parties meeting each other and presenting how they planned to approach
the Tren Urbano Project in terms of quality design, construction and management. The
Tren Urbano Office, not a neutral facilitator, ran the meeting. Observations from this
partnering meeting pointed out different issues that needed attention in the Tren Urbano
Project. For example, the different parties mingled minimally between English-speaking
and Spanish-speaking participants. This could be an indicator that further work needed to
be done in cross-cultural relationships.
Observations from the quality summit also pointed out areas that needed more effort, for
example, the drive and belief in partnering by some of the alignment section contractors.
Observation from this meeting also pointed out that some human infrastructure was still
needed. Design/build/operate projects like Tren Urbano do not have the time to develop
personnel infrastructure like a design-bid-build then operate project because all personnel
is needed in a more compressed time. This becomes an issue, as partnering has to occur
concurrently with personnel being continuously added.
Although this conference was successful in delivering the message that quality was
important to the owner, and how parties intended to approach the project, it did not focus
on partnering issues appropriately. Thus, this meeting only had some factors of an
effective partnering meeting: a neutral location, and some emphasis on how each
organization would approach the project. To be an effective partnering meeting, a third
party should have facilitated the Quality Summit and it should focus on working together
in small groups instead of numerous presentations. Also, there needed to be more
interaction between parties.
Monthly “partnering” meetings have also been held with all the project principals (TUI,
1997-8). These meetings were a good initiative, but instead of working on the partnering
relationship, these meetings served as a way for the contractors to take a short cut to the
regular issue resolution process bringing their issues to the top management directly
without thorough analysis. The owner’s top management typically ran theses meetings
and other parties presented their status reports. Issues were resolved at these meetings,
but at a micro-management level. Therefore, in an effort to improve these meetings and
keep up the partnering spirit, the meetings are now being reduced to quarterly meetings.
By keeping the meetings several months apart, project participants could not wait until
the next meeting to resolve their issue as if the meetings were monthly. Thus, project
188
TREN URBANO
participants pursued other channels to resolve their issues and the partnering follow-up
meetings then could focus more on partnering relationship issues. Tren Urbano could
further improve these meetings by working on installing good communication processes
throughout the project and increasing the commitment to the partnering process.
All these partnering meetings and initiatives were good initial steps to implement an
effective partnering program. However, as expected, more has to be undertaken to
achieve the greater level of partnering effectiveness because of the additional challenges
of the project in terms of innovative procurement, multi-culture and multi-phase that
creates an environment where continual revision and improvement needs to occur.
Evaluation on Partnering
The evaluation of partnering in Tren Urbano shows that there were areas where good
steps toward partnering were taken such as the initial meetings, but some areas could be
improved upon, for example:
• A clear champion for partnering was not clearly identified in the pre-planning
stage.
• The initial partnering conferences were done well, but more faith and genuine
commitment needed to be elicited in the partnering process.
• Follow-up meetings could be improved if run by a third party.
• The need for and the value of partnering should have been emphasized and
explained better to all project participants.
More initial effort should have been put into the partnering venture. Once some
deterioration of partnering starts, it may become difficult to reverse. Additional meetings
should be hold in informal settings in order to gain better understanding of other parties’
cultures in a relaxed atmosphere. Another major lesson learned was all management
parties should form one united management team, otherwise STT would just be another
prime contractor and not all the benefits could be gained from the turnkey concept.
Partnering should occur at all levels. For example, field inspection occurs separately by
numerous parties. Partnering could help field inspection if teams were formed between
the numerous field inspectors. This could ensure complete inspection in all areas of the
work site whether the site was divided by location or by disciple. Partnering across many
entities can also help form an environment where champions for quality, cost, schedule
and partnering can foster. Champions can help lead a cause but can also create a clearer
and more structured organization. The organization is currently somewhat confusing as is
evident by the different perceptions of the organization chart by different entities. Tren
Urbano also tends to have elements of micro-management, and this creates inefficiencies
in the organization. One reason that micro-management starts could be that when
management foresees many uncertainties they tend to take control of the issues. A
trusting environment needs to be formed where delegation of responsibilities can occur.
The Tren Urbano project has many uncertainties and therefore more follow-up meetings
are needed to redefine the partnering objectives and aims. The partnering process also
needed to be evaluated more carefully earlier in the project to detect any decay of
partnering relationships. Earlier detection of symptoms could have led to a better
recovery. Today, the number of claims is increasing at a high rate and parties are starting
to prepare themselves in case of court battles. Partnering may be a challenge to repair at
this point in time. The partnering environment that still remains should be fostered until
after the construction is complete and until all claims are settled in good faith
negotiations. Then, a final evaluation of the Tren Urbano partnering efforts and results
can be done.
The lessons learned from Tren Urbano can be generalized in order to apply them to any
project, which uses an innovative delivery method in a multi-phase, multi-party, multi-
discipline, multi-culture environment.
The lessons learned could be divided in three categories: initial, operational and resulting
factors. The initial factors define how the remainder of the project will be carried out.
They are set at the beginning of the project, but their impact will not be seen until the end
of the project as they affect other factors. The operational factors occur throughout the
project. They are affected mostly by the initial factors, but can also be improved slightly
upon themselves. The resulting factors are mostly a product of the other factors. So
although, conflicts, quality, schedule and cost of the project are more directly linked to
the resulting factors, the initial and operational factors can have a larger impact than
expected. These factors can all be seen in Table 31 and a brief explanation of each factor
is given below.
Project Factors:
Initial Meetings: Start early with a full partnering initialization. Do whatever it takes,
especially if the delivery system relies on partnering to become effective. A little extra
time or money spent early on partnering may have a large pay-off later. Trust, as the key
ingredient of partnering, must be developed here because it will only be more difficult to
install later.
Education: Use experienced employees if possible, otherwise educate intensively in the
need and benefits of partnering and, of course, at the task at hand.
Numerous Cultures: Cultural differences must be recognized and special seminars with
played out examples of business differences may help parties see the differences before
they are in real situations and their relationship deteriorates.
Delivery Method: An innovative procurement is done to meet special project objectives
and can provide a fresh start for a new improved partnering relationship. But be careful,
there may be special challenges such as non-contractual relationships that need higher
commitment to partnering.
190
TREN URBANO
Turnkey Contractor
Delivery Method
Acting as Part Owner
Turnkey
D/B/O
Micro-
Multiple D/B
Unified Management Management
Construction
Team
Organizational Management
Issues Numerous Cultures
Multi-Phase
Effectiveness of Site Transfer
Multi-Professional
Champions Conflicts
Multi-Ethnic
Multi-Corporate
(uncertainties)
Benefits of Duplication
Operational Factors:
Follow-up Partnering Meetings: Follow-up meetings can prevent the initial trusting
partnering relationship from decaying.
Knowledge Transfer: Partnering can provide open communication for knowledge transfer
that is often needed between various cultures
Evaluations: Evaluate partnering throughout the project. Thus, if there seems to be
skepticism of partnering, this trend can be reversed immediately before becomes too
difficult to reverse. Use more ‘soft’ measures initially such as problem solving methods,
and evaluate ‘hard’ measures such as number of claims when it becomes relevant.
Champions for Objectives: There needs to be clear champions for quality, cost, schedule
and partnering itself. A confusing organization may be a sign that nobody knows who is
in charge of what and when. Party participants need to know who the champions are, and
the champions need adequate authority to be effective.
Benefits of Duplication: The amount of duplication in a particular delivery method must
be evaluated such as extra cost versus greater quality. How should parties with
overlapping tasks work together? Partnering processes must be put in place here to ensure
duplication does not lead to adversarial relationships and “all is responsible, nobody is”
syndrome. If the delivery system is some hybrid of multiple primes with similar tasks,
standardization with enforcement must occur.
Unified Management Team: Create a unified management team for highest effectiveness.
Certain relationships may need to be bridged by partnering in order for other entities to
work together effectively. Then partnering can occur at all levels.
Turnkey Contractor Acting as Part Owner: If a contractor is to perform tasks in the
owner’s interests as well as other tasks not as well aligned with the owner’s interests,
partnering can help pull the contractor to act more in the owner’s interest.
Resulting Factors:
Site Transfer Conflicts: Hand-over between contractors may prove to be tricky. If there is
no direct contractual link, the owner should oversee that the hand-over will be done in
good faith; otherwise the owner would have to monitor site hand-over in detail.
Micro-Management: If the owner remains in control, it must spend great number of
resources to oversee contractors in detail. Effective partnering will aid the process to
letting go of control and save on resources. It will also make the owner more confident to
use more innovative contracts for future projects. Trust must be developed so managers
can delegate responsibilities in an uncertain environment and to avoid micro-
management.
Claim Management: Claim management is important to improve costs, and schedule.
Claim management, however, cannot only be improved upon itself; first the factors
throughout the project, operational factors, must be improved upon through effective
partnering in order to greatly improve claim management. The partnering effort must be
emphasized after construction completion and all claims are settled.
192
TREN URBANO
• Manager have a lot of experience regarding conflict management and they feel
pretty confident about their negotiation skills: Project Managers, with more than
20 years of experience are reluctant to accept that they need help to deal with
conflicts. However, the facts show that frequently managers obey their emotions
and act irrationally in negotiation process. A tool that enhances their negotiation
skills might be useful.
• Decision-Makers are not aware of the long term effects of their actions: The
direct cost of a negotiation is always on the table. However, the hidden costs that
can be several times higher are difficult to take into consideration. Hence, the
short-term strategy generally prevailed over the long-term view.
11.8 SUMMARY
As newer and more innovative delivery methods are used in an increasing more global
market, partnering becomes especially important to convey a sense of collaboration to all
parties. Also, an innovative delivery method’s advantage over traditional projects may
ride on the assumption that effective partnering is in place. Therefore, in many projects
special attention should be given to partnering.
In summary, partnering is especially needed in innovative procured, multi-cultural, multi-
phase project. However, partnering can also be especially challenging because of the
numerous other issues that must be resolved that can easily overshadow partnering if
specific attention is not pointed towards partnering. Therefore, partnering has a singular
role in Tren Urbano. It has been implemented in terms of initial meetings with the owner
and each prime contractor and between all designers. A quality summit was also held
with all parties. Subsequently, follow-up partnering meetings have been held with the
principles of all parties involved in the Tren Urbano Project. Harpoth (1999) evaluated
the effect of partnering in Tren Urbano. She concluded that the amount of partnering
effort in the Tren Urbano Project is adequate for traditionally procured projects with few
uncertainties, but it was not enough for the challenge of Tren Urbano. Much greater
partnering effort is needed to receive the benefits of partnering.
Based on the insights received from the interviews and the data collected from the Rio
Piedras Contract, a set of conclusions and recommendations is proposed for the Tren
Urbano Project:
• Contract Language regarding conflict resolution is not the source of problems:
Tren Urbano contract language regarding conflict management includes the-
state-of-the-art dispute resolution techniques used in the construction industry.
The source of conflicts is the disagreement that might exist between the parties,
and this issue cannot be eliminated writing an article in the contract. Hence, the
competitive environment cannot be eliminated through a statement in the
contract.
• Inter-phase conflicts require additional efforts: Because of the characteristics the
Tren Urbano Project has, it is very important to think ahead of the possible
conflict that may arise between the current phase of the projects and its future
phases. For example, the operation and maintenance of following phase can be
awarded to a different entity.
11.10 REFERENCES
194
TREN URBANO
[TUQS, 1997] Tren Urbano Quality Summit, 10/6/97 & 10/7/97, San Juan,
Puerto Rico (1997).
11.11 ENDNOTES
1
The authors would like to acknowledge the help of research assistants Jorge A.
Giampaoli and Nina Harpoth for their contribution to the preparation of this case. Their
research and insights are the basis for the material presented in this case.
2
Prominent members of this group include Fred Salvucci, former Secretary of
Transportation for Massachusetts; Dr. Nigel Wilson and Ken Kruckemeyer of MIT;
Multisystems, Inc.
3
Note that in the Dispute Resolution Process the time is expressed in calendar days rather
than working days.
12
SUMMARY
“If your only tool is a hammer, then every problem
will look like a nail. When it comes to construction
industry, the main dispute resolution tool remains
the lawyer, and every disagreement still looks like a
lawsuit.”
(ENR, 2/15/1999)
This book on Dispute Avoidance and Resolution Techniques (DART) for construction
and engineering projects presents how this industry is reacting to the increasing
inefficient use of resources (e.g., monetary, time, and human) associated with the
resolution of disputes using the court system, and for that matter arbitration. More
importantly, it highlights that the industry has begun to realize that conflict is an
important variable in construction. Thus, managing and resolving conflict should be
added as a fourth key aspect to any project, together with Material, Labor, and
Equipment. An effort has to be made to deal with and manage this additional variable
efficiently and effectively. Parties must identify those characteristics that make their own
projects prone to disagreements and implement a DART system in order to prevent them
and/or mitigate their effects. Resources must be assigned to this task just as they are
dedicated to scheduling or cost control. Accordingly, a project that efficiently and
effectively manages its Material, Labor, Equipment, and Conflict will have much better
chances of resulting in a successful venture similar to ones presented within this book.
After the assessment presented in this book, it is clear that the parties in the LNGT
project presented in Case 1.1 failed to manage disagreements and find alternative ways to
resolve disputes. Instead, the Venezuelan SUB, the Italian GC, and the British
DESIGNER simply relied on contract terms to address the problems that developed
during the project execution. Thus, many years after the project was finished, they were
still involved in a large legal battle worth many times the original contract amount.
Arbitration - the only dispute resolution technique included in the contract costed both
parties more than 10% of the original contract value, and the final decision was in the
hands of a third party. Furthermore, proceedings were managed and controlled by an
agency external to both sides, located in a foreign country (i.e., US), who sets time
frames and rules, and controls information exchanges. Direct negotiations to solve the
claims were no longer encouraged, lawyers had taken over the dispute, and there was a
significant amount of uncertainty with regards to the potential outcome, at least in the
Venezuelan side.
The present work argues that the days of waiting until final completion to resolve
disagreements between contractors, design professionals, and owners (like in the LNG
case) are ending regardless of the location, type, or complexity of the project. Parties in
construction and engineering endeavors are realizing the benefits of assuming a proactive
role in dealing with conflicts and disputes. Parties are developing prevention techniques
that foster an equitable allocation of risk, communication, improved contracts, and
information flow addressing the basic characteristics of the industry that make it prone to
disagreements. Court systems have witnessed a trend towards new methods that help
overcome the difficulties of pre-trial hearings and motions during litigation. So, even
196
SUMMARY
when litigation is underway, the industry and the courts have produced innovative
practices (i.e., Court-Annexed Procedures) that can reduce the negative effects of legal
actions (e.g., cost, time, resources, and broken relationships). Parties have seen their roles
evolve from passivity and reaction to a dynamic, proactive attitude in the pursuit of
dispute avoidance and resolution. The benefits of this new approach (e.g., early
identification of problems, control over outcome, cost savings, and maintenance of
relationships) far outweigh the ones of the practice of waiting until the project is
completed.
The industry has made significant progress over the past decade in developing strategies
and techniques to curb the adversarial attitude that had become a standard in most
engineering and construction projects. Partnering and alternative dispute resolution
methods, such as structured negotiations, mediation, Med-Arb, mini-trials, and dispute
review boards have all become part of the industry. The use of these techniques has been
pivotal for parties to anticipate potential disagreements and has revolutionized the
traditionally defensive approach of the two-step Dispute Resolution Ladder reviewed in
Chapter 2.
This ‘quiet revolution’ (Stipanowich, 1996) in dispute resolution has changed the whole
scene of conflict in construction. The movement has placed emphasis on effective
communication, informality, win/win approaches, and conflict avoidance, overturning the
path of formalizing each process and legalizing design, relationships, information
disclosure, and even problem solving. This confirms Treacy’s (1995) point that the
industry is returning to “the old fashion way of doing business.”
Once understood that there is no unique formula to prevent or discourage disputes, the
attractiveness of DART and every dispute prevention or resolution system is that they can
be tailored to meet the specific needs and individual job characteristics of a given project
and a given building team. This flexibility is invaluable for the construction industry,
where each project is a new experience with new variables and different conditions.
Parties can customize procedures and rules to what they consider the weak aspects of the
project, helping to mitigate potential problems not covered in contract documents. The
six-step Dispute Resolution Ladder (DRL) is the most appropriate model to base and
design project actions based on specific project needs. However, this does not mean that
every project requires a six-step DRL. As it was shown in the example of the Hong Kong
Chek Lap Kok airport (Section 2.2.3), projects can have a three or a four-step DRL to
facilitate the resolution process, and they can even choose to have more than one DRL,
based on contract size, disputed amount, type, or source of disagreement.
Among the different stages of the DRL, this book considers the prevention stage as an
important asset which offers the greatest flexibility to the project, in terms of designing
and incorporating dispute avoidance and resolution techniques. Once disagreements are a
fact, Negotiation (Stage 2, Chapter 5) is identified as the most effective method to resolve
disputes in terms of time, costs, satisfaction, and minimization of further disputes,
communication, and enhancement of job relationships. Given the definite move away
from the adversarial approaches towards conflict avoidance and resolution, negotiation
will certainly become the primary tool to deal with disagreements. The fact that
Mediation, a form of facilitated negotiation, is becoming a highly favorable approach
within the industry, confirms this conclusion.
Just as Negotiation and Mediation, this book concludes that the most efficient and
effective ADR approaches utilize non-binding procedures, like Conciliation or Minitrials.
These procedures are reinforced by the incorporation of a neutral third party that
facilitates communication and/or helps resolve technical issues that might be part of the
dispute. The Second, Third and Fourth stages of the DRL are the key sets of techniques
available to avoid arbitration or litigation. Although these non-binding techniques might
fail to result in a 100% resolution of the dispute, partial settlements are also important in
mitigating the costs and time impacts. Furthermore, communication during these phases
can help clarify issues and might open the door to new solutions that might have been
overlooked during initial negotiations. The more adversarial approaches, Arbitration and
Litigation, are ranked last, and considered the most expensive and least efficient in the
DRL. The changes in the American Arbitration Association’ s (AAA) Construction
Arbitration Rules to make the procedure more flexible and efficient, together with the
emergence of binding techniques like Med-Arb and Shadow Mediation, support this
movement away from binding adjudicative procedures.
Another important finding of this assessment relates to the role owners (i.e., agencies,
private developers, and corporations) must play in the process of incorporating DART in
the construction process. It was demonstrated that owners must expect disagreements
during the construction process and should be prepared to manage and resolve them
before they become disputes. Owners’ participation in dispute prevention is critical. Also,
their role acquires relevance in areas like risk assessment and allocation, preparation of
documents, dispute resolution clauses, and cost and schedule control during all phases of
construction. Contract specifications reviewed as part of this book provide examples as to
this new role assigned to the owners (e.g., FIDIC, World Bank, CCDC, and Prevention
Stage).
198
SUMMARY
Also in the international arena, this book presents how cultural and market conditions can
affect the type of dispute mechanism preferred by constructors and owners in different
countries. The Netherlands’ case (i.e., Frame Contract) shows how a pragmatic culture
and an organized market discourage parties from engaging in adversarial relationships,
letting them rely on trust to guarantee long-term commitments. Countries have favored
certain types of ADR over others, as in the case of the Asian nations that have
incorporated mediation and conciliation in their standard DRL before more adjudicative
procedures. In Japan and Hong Kong, this book identified direct implementations of
mediation in government agencies that can relate to the cultural background and
traditions of ‘harmony’ and compromise. In the UK, more adversarial approaches such as
adjudication have been incorporated into law and are expected to gain more adepts, while
mediation has only recently become a recognized technique to resolve construction
disputes.
Ultimately, many of the problems associated with construction disputes are not limited to
particular geographic location or cultures. Disputes emerge whether the project is
conducted in New Jersey, Calcutta, or the Caribbean, and the ‘pandemic’ nature of
conflict in construction must be acknowledged, for one to properly manage it. Cultural
differences will have a bearing as to the DRL to use, but the nature of the project and the
participants will define the most appropriate system to use. For example, projects where
parties come from different cultural backgrounds, including different languages, most
address and foster from the beginning clear and continuous communication to reduce
problems. Facilitated negotiations with third party neutrals that are familiar with these
backgrounds will help overcome ‘people issues’ which can grow from this diversity.
apparent lack of interest towards this project philosophy in other parts of the
world. New barriers on the implementation of partnering could be identified.
• How the increasing use of mediation as a DART will affect the flexibility and
reduce the advantages it has over more binding approaches, such as: Arbitration.
The increasing use of this technique might lead to a formalization that could
hamper the advantages it currently holds.
• By defining the key characteristics and relationships in the most common
delivery systems (e.g., Design-Bid-Build, Design-Build, and Build-Operate-
Transfer) and the weaknesses of each one, specific dispute avoidance and
resolution systems can be designed and proposed as basis for each type of
project.
• Because third-party interventions appear to be among the key features of ADR
in construction, training programs should be developed to guarantee a level of
professionalism and to provide these agents with the necessary tools to address
and help resolve construction conflicts.
As a final note, it is important to understand that the Construction Dispute Avoidance and
Resolution Techniques as described in this book will likely change and evolve as new
methodologies are designed and successfully implemented; as new research uncovers
techniques already in use, but not reported, and as technology and innovation in
communications open the door to more collaborative environments of operation. The fact
that researchers are not able to replicate the construction process in order to study
different techniques, similar to manufacturing, adds to the need for creativity and
improvement of methods for each project. However, the following principles remain the
same:
• Adversarial approaches can lead to excessive inefficient waste of resources and
lost relationships.
• The industry has developed a significant quantity of techniques that are
alternatives to litigation for the resolution of construction disputes.
• Prevention of disputes is far more efficient than trying to resolve them.
• The nature of construction conflicts and disputes requires flexibility.
• Third party intervention to promote communication and/or resolve technical
issues address common sources of conflict in construction and therefore can be
highly effective.
• Creativity should take precedence over a prescribed list of accepted procedures.
Parties must learn about what techniques are available and choose and modify
those that best fit their needs.
In conclusion, in the past decade, dispute resolution in the construction industry has
evolved from private adjudication (i.e., arbitration) to voluntary techniques and
approaches based on communication and collaboration, aimed primarily at avoiding open
conflict and allowing the parties to develop a mutually agreeable settlement. This
evolution is common to the construction industries of a number of countries. No longer is
the only dispute resolution tool a lawyer. In fact, many DART still make use of this agent
(i.e., Minitrial and Settlement Conferences), but in a non-adversarial environment that
fosters the resolution of disputes faster, cheaper and without straining the relationships to
the point where no further work together is possible.
200
Mediation/Arbitrati
Voluntary
Mini-trial
Fact-Based
Advisory
Owner/Agency
Facilitated
Structured
Training
Dispute
Sub-Contractor
Right
Forward-Price
As-Build
Joint
Certified
Constructability
Competent
Superior
Subjective
Cost/Schedule
“Bridging”
Delivery
PEpC
Negotiated
Escrow
Third
Equitable
Geotechnical
Economic
Statement
Project
of
Party
Delivery
Technique
Summary Bid
Review
Resolution
Refusal
and
Time-
NON-BINDING
ARBITRATION
Quotations
Schedule
and
Incentive
Project
A+B
Step
Category Payroll
Schedule
Conciliation
On-Call
Mediation
STANDING
NEUTRAL
Neutral
NEGOTIATION
PREVENTION
Partnering
Cost
Control Risk
or
Price
the and
Documentation
Negotiations
and
Bidding
Award
Advisor
Contractor
Schedule
Audits
Programs
Jury
and on
Trial
Settlement
Arbitration
Negotiations/Meeti
Payment
Equipment
Management
Determination
Compressed
Baseline Report
on (Med./Arb.)
Executive
Mediation
Board
Review
Negotiations
Development
Clauses
Change-Order
Change
Scheduling
Submittal
Analysis
Engineering
Incentive
Design-Build
Mechanism
System
Documents
Beneficiary
Sharing
Adjustment and
(Non-
Orders
Boards
Matrix
Trial of
Clause
Gap
Cost
Conference
Binding
ngs
Requirements
Labor
Allowance
Fee
Process
(GBR) Pricing (Rent-
a-Judge)
Arbitration)
SUMMARY
12.3 REFERENCES