Introduction To Construction Dispute Resolution Pena-Mora Sosa McCone 2-1-2002

Download as pdf or txt
Download as pdf or txt
You are on page 1of 213

INTRODUCTION TO

CONSTRUCTION DISPUTE RESOLUTION

FENIOSKY PEÑA-MORA, SCD., ASSOCIATE PROFESSOR, MIT


CARLOS E. SOSA, MSC., MIT
D. SEAN MCCONE, MSC., MIT
TABLE OF CONTENTS
TABLE OF CONTENTS ......................................................... I

PREFACE ...................................................................... V
THE CONSTRUCTION INDUSTRY .............................................. 1
1.1 SOURCES OF CONFLICT AND DISPUTE ................................................... 3
1.2 ORGANIZATIONAL ISSUES ............................................................... 6
1.2.1 PARTICIPANTS AND PEOPLE ISSUES .............................................. 6
1.2.2 PROJECT STRUCTURE ........................................................... 7
1.2.3 PROCESS PROBLEMS .......................................................... 12
1.3 PROJECT UNCERTAINTY .............................................................. 13
1.3.1 EXTERNAL UNCERTAINTIES ................................................... 13
1.3.2 INTERNAL UNCERTAINTIES .................................................... 13
1.4 SUMMARY ............................................................................ 15
1.5 POINTS FOR DISCUSSION ............................................................. 16
1.6 REFERENCES ......................................................................... 17
1.7 ENDNOTES ........................................................................... 17
EVOLUTION OF DART ...................................................... 18
2.1 TRADITIONAL DISPUTE RESOLUTION IN CONSTRUCTION............................... 18
2.1.1 DETERMINATION BY THE DESIGN PROFESSIONAL .............................. 19
2.1.2 ARBITRATION ................................................................. 20
2.2 MODIFICATION OF THE TWO-STEP ADR APPROACH................................... 23
2.2.1 FIDIC’S ADR CONTRACT CONDITIONS ....................................... 24
2.2.2 WORLD BANK’S ADR CONTRACT CONDITIONS ................................ 25
2.2.3 CHEK LAP KOK AIRPORT’S DISPUTE RESOLUTION SYSTEM .................... 26
2.3 EVOLUTION OF THE PRESENT ADR METHODOLOGIES ................................. 29
2.3.1 DATA SUPPORTING THE EVOLUTION OF ADR ................................. 29
2.3.2 TWO CONCEPTUALIZATION MODELS OF DART................................ 31
2.4 THE STATE OF THE LEGAL CONSTRUCTION ARENA ................................... 35
2.5 SUMMARY ............................................................................ 38
2.6 POINTS FOR DISCUSSION ............................................................. 38
2.7 REFERENCES ......................................................................... 39
2.8 ENDNOTES ........................................................................... 42
STAGE 1: PREVENTION...................................................... 43
3.1 IMPORTANCE OF PREVENTION STAGE ................................................. 44
3.2 EQUITABLE RISK SHARING ............................................................ 45
3.2.1 ECONOMIC PRICE ADJUSTMENT ............................................... 47
3.2.2 GEOTECHNICAL BASELINE REPORT (GBR) .................................... 47
3.2.3 THIRD PARTY BENEFICIARY CLAUSE........................................... 49
3.3 ESCROW BID DOCUMENTS ............................................................ 49
3.4 PROJECT AWARD AND DELIVERY MECHANISM ......................................... 50
3.4.1 NEGOTIATED COMPRESSED PROCESS .......................................... 50
3.4.2 A+B BIDDING................................................................. 50
3.4.3 PEPC DELIVERY SYSTEM ...................................................... 51
3.4.4 “BRIDGING” THE DESIGN-BUILD GAP ......................................... 52
3.4.5 FRAME CONTRACT DELIVERY SYSTEM IN THE NETHERLANDS .................. 53
3.5 INCENTIVE PROGRAMS................................................................ 56

i
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

3.5.1 COST/SCHEDULE INCENTIVE MATRIX ......................................... 57


3.5.2 SUBJECTIVE DETERMINATION OF FEE ......................................... 58
3.5.3 SUPERIOR TIME-MANAGEMENT ALLOWANCE .................................. 58
3.6 COMPETENT ENGINEERING AND DOCUMENTATION .................................... 59
3.6.1 CONSTRUCTABILITY ANALYSIS ................................................ 59
3.7 COST AND SCHEDULE CONTROL ...................................................... 59
3.7.1 COST STATEMENT SUBMITTAL ................................................ 61
3.7.2 CERTIFIED PAYROLL SUBMITTAL .............................................. 62
3.7.3 NEGOTIATED EQUIPMENT AND LABOR PRICING................................ 62
3.7.4 JOINT PROJECT SCHEDULING ................................................. 62
3.7.5 SCHEDULE AUDITS ............................................................ 63
3.7.6 AS-BUILT SCHEDULE SUBMITTAL ............................................. 63
3.7.7 FORWARD-PRICE CHANGE ORDERS ........................................... 64
3.7.8 RIGHT OF REFUSAL ON CHANGE-ORDER COST QUOTATIONS .................. 64
3.7.9 SUB-CONTRACTOR PAYMENT REQUIREMENTS ................................. 64
3.8 DISPUTE RESOLUTION CLAUSES ...................................................... 65
3.9 TRAINING AND DEVELOPMENT ........................................................ 65
3.10 SUMMARY ........................................................................... 66
3.11 POINTS FOR DISCUSSION............................................................ 67
3.12 REFERENCES ........................................................................ 68
3.13 ENDNOTES .......................................................................... 69
PARTNERING ................................................................ 71
4.1 DEFINITION AND BENEFITS OF PARTNERING........................................... 72
4.2 THE PARTNERING PROCESS .......................................................... 75
4.3 KEY COMPONENTS OF PARTNERING .................................................. 76
4.4 THE PARTNERING CONTINUUM ....................................................... 78
INTEL (PORTLAND, OREGON) ........................................................ 81
4.5 SUMMARY ............................................................................ 83
4.6 POINTS FOR DISCUSSION ............................................................. 84
4.7 REFERENCES ......................................................................... 84
4.8 ENDNOTES ........................................................................... 86
STAGE 2: NEGOTIATION .................................................... 87
5.1 THE FIELD OF NEGOTIATION ......................................................... 88
5.2 POSITIONS VERSUS INTERESTS ........................................................ 89
5.3 NEGOTIATION STYLES ................................................................ 91
5.4 PREPARATION ........................................................................ 92
5.5 STEP NEGOTIATION .................................................................. 93
5.6 STRUCTURED NEGOTIATIONS ......................................................... 94
5.7 FACILITATED NEGOTIATIONS/MEETINGS.............................................. 95
5.8 SUMMARY ............................................................................ 97
5.9 POINTS FOR DISCUSSION ............................................................. 98
5.10 REFERENCES ........................................................................ 98
5.11 ENDNOTES .......................................................................... 99
STAGE 3: STANDING NEUTRAL ............................................ 100
6.1 NEUTRAL ADVISOR .................................................................. 101
6.2 OWNER/AGENCY REVIEW BOARDS .................................................. 102
6.3 DISPUTE REVIEW BOARD ............................................................ 103
6.4 ON-CALL CONTRACTOR ............................................................. 106
6.5 SUMMARY ........................................................................... 107
6.6 POINTS FOR DISCUSSION ............................................................ 108
6.7 REFERENCES ........................................................................ 109
6.8 ENDNOTES .......................................................................... 109

ii
TABLE OF CONTENTS

STAGE 4:NON-BINDING DISPUTE RESOLUTION ............................ 110


7.1 IMPORTANCE OF NON-BINDING PHILOSOPHY ........................................ 111
7.2 MEDIATION .......................................................................... 112
7.3 CONCILIATION....................................................................... 117
7.4 ADVISORY ARBITRATION (NON-BINDING ARBITRATION).............................. 118
7.5 FACT-BASED MEDIATION ............................................................ 119
7.6 MINI-TRIAL OR EXECUTIVE TRIAL ................................................... 120
7.7 SUMMARY JURY TRIAL .............................................................. 120
7.8 VOLUNTARY SETTLEMENT CONFERENCE (RENT-A-JUDGE) ........................... 121
7.9 SUMMARY ........................................................................... 122
7.10 POINTS FOR DISCUSSION........................................................... 124
7.11 REFERENCES ....................................................................... 124
7.12 ENDNOTES ......................................................................... 126
STAGE 5: BINDING DISPUTE RESOLUTION ............................... 127
8.1 MEDIATION/ARBITRATION (MED/ARB) .............................................. 128
8.2 ADJUDICATOR/EXPERT DETERMINATION ............................................ 130
8.3 ARBITRATION ....................................................................... 131
8.3.1 SINGLE ARBITRATOR ......................................................... 134
8.3.2 BASEBALL ARBITRATION ..................................................... 135
8.4 SHADOW MEDIATION ................................................................ 136
8.5 SUMMARY ........................................................................... 137
8.6 POINTS FOR DISCUSSION ............................................................ 138
8.7 REFERENCES ........................................................................ 139
8.8 ENDNOTES .......................................................................... 140
STAGE 6: COURT ALTERNATIVES AND LITIGATION ........................ 141
9.1 THE FINAL STEP .................................................................... 142
9.2 DISCOVERY OF SITUATION ........................................................... 143
9.3 EFFECTIVE PRESENTATION .......................................................... 143
9.4 COURT APPOINTED EXPERTS ........................................................ 146
9.5 JUDGE PRO-TEM .................................................................... 147
9.6 TRIAL BY REFERENCE (REFEREE) .................................................... 147
9.7 SUMMARY ........................................................................... 149
9.8 POINTS FOR DISCUSSION ............................................................ 149
9.9 REFERENCES ........................................................................ 150
9.10 ENDNOTES ......................................................................... 150
CONFLICT MANAGEMENT PLAN ............................................ 151
10.1 CONFLICT MANAGEMENT PROCESS ................................................. 152
10.2 IDENTIFYING POSSIBLE CONFLICTS ................................................. 154
10.2.1 EFFECT OF DELIVERY SYSTEM ON IDENTIFYING CONFLICTS ................. 154
10.3 ANALYZING IDENTIFIED CONFLICTS ................................................ 156
10.3.1 PROBABILITY OF OCCURANCE .............................................. 156
10.3.2 IMPACT OF CONFLICT ...................................................... 160
10.3.3 COMBINED CONFLICT EXPOSURE ........................................... 161
10.4 DESIGNING THE MANAGEMENT PLAN ............................................... 163
10.4.1 PRIORITIZING AND DART IMPLEMENTATION ................................ 164
10.4.2 IDENTIFICATION: WHO IS RESPONSIBLE? .................................... 165
10.4.3 COST/BENEFIT ISSUES ..................................................... 165
10.4.4 CONTINGENCY PLAN ....................................................... 166
10.4.5 COMPUTER APPLICATIONS .................................................. 167
10.5 IMPORTANCE OF REVIEW ........................................................... 168
10.5.1 CONFLICT RESOLUTION INDEXES............................................ 168

iii
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

10.6 SUMMARY .......................................................................... 171


10.7 POINTS FOR DISCUSSION........................................................... 172
10.8 REFERENCES ....................................................................... 172
10.9 ENDNOTES ......................................................................... 173
CASE STUDY: TREN URBANO PROJECT .................................... 174
11.1 TREN URBANO PROJECT STORY ................................................... 175
11.2 PROJECT DESCRIPTION ............................................................ 176
11.3 PROCUREMENT STRATEGY ......................................................... 178
11.4 CONFLICT MANAGEMENT IN TREN URBANO ........................................ 180
11.4.1 PARTNERING ............................................................... 180
11.4.2 CHANGE ORDER PROCESS .................................................. 181
11.4.3 DISPUTE RESOLUTION CONTRACT LANGUAGE .............................. 182
11.5 ANALYSIS OF TREN URBANO COMPONENTS ......................................... 184
11.6 PARTNERING ANALYSIS IN TREN URBANO .......................................... 184
11.6.1 ENHANCE THE PROS OF DUPLICATION ...................................... 185
11.6.2 FORM A UNIFIED MANAGEMENT TEAM ..................................... 185
11.6.3 STTT CONTRACTOR’S FIDUCIARY RELATIONSHIP WITH OWNER ............ 186
11.6.4 AID NON-CONTRACTUAL RELATIONSHIPS ................................... 187
11.6.5 IMPROVE COMMUNICATION AND UNDERSTANDING BETWEEN THE MULTI-
CULTURES .......................................................................... 187
11.6.6 INITIAL MEETINGS .......................................................... 188
11.6.7 FOLLOW-UP MEETINGS ..................................................... 188
11.6.8 GENERAL ANALYSIS OF PARTNERING COMPONENTS ......................... 190
11.7 GENERAL ANALYSIS OF CONFLICT RESOLUTION .................................... 192
11.8 SUMMARY .......................................................................... 193
11.9 FURTHER DISCUSSION.............................................................. 194
11.10 REFERENCES ..................................................................... 194
11.11 ENDNOTES ....................................................................... 195
SUMMARY ................................................................. 196
12.1 INTERNATIONAL DART USE AND APPLICATIONS .................................... 198
12.2 AREAS OF FURTHER EXPLORATION IN DART ....................................... 199
12.3 REFERENCES ....................................................................... 201

iv
PREFACE
Leading construction experts have identified Productivity, Innovation, Cost Control,
Safety, and Litigation Expenses as critical areas in need of improvement in the
construction industry of this next century. In the United States alone, $60 billion are spent
every year on lawsuits, of which the construction industry accounts for nearly $5 billion.
The fact that these construction litigation expenditures have increased at an average rate
of 10% per year for the past ten years is one of the primary motivations for this book.
This reality has generated the need to develop new Dispute Avoidance and Resolution
Techniques (DART) with the aim of curving this cost spiral and improving productivity.
Fueled by this need, and as projects throughout the world continually achieve higher
levels of complexity, the field of construction dispute resolution has exploded with
innovative ways to prevent conflict and resolve disagreements. Companies have found
that in highly competitive markets, the resolution of disputes has become a key to forging
stronger and longer-lasting relationships with their clients. As a result, the construction
industry has been in the forefront of the development of DART. This book presents and
reviews a significant number of new and innovative ways to promote collaborative
environments and resolve disputes in construction. This includes some practical
applications of DART in the construction industry throughout a number of nations. The
aim is to provide the reader with data to support the successes or failures of these
techniques in multiple cultures.
In effort to ground the material in this book, some examples are presented of how the
material relates to current construction projects. These examples will be referred to as
cases. Not all the information specific to the project has been presented, as they are only
included to correlate theory with practice. They are also not included to illustrate either
effective or ineffective handling of dispute avoidance and resolution procedures. In
addition, some names or facts may have been changed for confidentiality reasons. Each
of the relevant chapters will open up with an introduction of facts to the case and leave
the reader with some questions to ponder while reading the chapter. At the end of each
chapter the case is revisited relating the chapter information to the project situation.

Content
This introductory book is divided in 12 chapters. The first chapter describes the
construction industry, focusing on its size, structure, relationships and sources of
conflicts. Chapter 2 presents a background for the evolution of construction DART. It
also presents a brief review of the reasons behind the apparent large number of disputes
in the construction industry, and identifies characteristics that make the construction
process adversarial in nature. The final section of Chapter 2 looks at two different
proposals for the organization of DART in the construction industry. It selects the
concept of the “Dispute Resolution Ladder” (DRL) to organize and present different
techniques found being used around the world.
Chapters 3 through 9 present the state of the art review of DART in the construction
industry following each of the stages of the DRL defined in Chapter 2. Chapter 3 reviews
techniques in the Prevention Stage with examples of mechanisms that can mitigate and
discourage disputes during the construction process. This chapter highlights the role the
owner plays in the introduction of dispute avoidance and resolution clauses in
construction contracts and as a promoter of honest communications between the parties to
the project. Chapter 4 reviews the concept of Partnering. Although not a Stage in the

v
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Dispute Resolution Ladder (DRL), Partnering was developed to change the adversarial
approach to the construction process, with the aim to improve job performance and
reduce conflict and confrontation. This concept integrates dispute resolution with other
communication and collaboration techniques that have resulted in a significant reduction
in the number of conflicts in those projects in which it is fully implemented. This chapter
introduces the essential phases of the system, and its key components.
Chapter 5 examines the Negotiation Stage in the process of dispute resolution in
construction. This chapter offers three different approaches to improve the outcomes of
negotiations: Step Negotiations, Structured Negotiations, and Facilitated Negotiations.
The introduction of neutral third parties begins in Chapter 6, with the Standing Neutral
Stage; a concept based on the incorporation of an unbiased, knowledgeable party as an
instrument to resolve disputes efficiently and effectively as soon as they develop. Chapter
7 examines the Non-Binding Phase of the DRL, covering Mediation, Advisory Opinion,
Fact-based Mediation, Minitrial, Summary Jury Trial, and Voluntary Settlement
Conference as the available DART techniques. A significant acceptance of non-binding
dispute resolution mechanisms is reflected in the number of variations that have
developed, as these procedures represent the last stage of the DRL in which the parties
have control over the outcome of the dispute.
Chapter 8 examines approaches where a third party issues a final award to settle the
dispute. These approaches correspond to the Binding Dispute Resolution Stage in the
DRL. Arbitration, the most common form of binding resolution procedure, is reviewed,
together with three other developments that can prove advantageous to a project that
might be inclined to minimize arbitration. Finally, as part of this review of DART in
construction, Chapter 9 looks at Alternative Litigation and Litigation as the last Stage in
the DRL. This Stage corresponds to a dispute resolution procedure of “last-resort,” and is
examined together with three techniques that can help reduce the amount of resources
spent on court proceedings (i.e., time and money).
Chapter 10 presents the concept of a Conflict Management Plan for projects. In all arenas
of construction, conflict is evident, but being able to quantify the degree of conflict is
challenging. Taking into consideration, the causes and results of the most common
conflict situations, a conflict management plan can be designed from the DART
presented in the previous chapters. The probability of conflict occurring is assessed along
with the impact that each conflict may have on the project. A preventative strategy is
developed to reduce the probability of conflict occurring and a resolution strategy is
planned to minimize the impact of conflict if it does occur. The resulting Conflict
Management Plan will help owners and contractors to evaluate the interactions among
participants and actively involve everyone in the dispute resolution process.
Following the presentation of all the material in the book, Chapter 11 analyzes a light rail
transit project in San Juan, Puerto Rico. This case study is included to promote discussion
on the methods to avoid claims and resolve disputes used in the project. This project
made use of preventative measures such as Partnering as well as a predefined dispute
resolution system. Analyzing this project allows the reader to envision how new and
innovative techniques can be implemented into the industry.
Finally, Chapter 12 gathers the conclusions of the book. First, it summarizes the DART
techniques. Second, it highlights the importance of alternative dispute resolution in
construction worldwide and how cultural conditions have affected the selection of the
DART, based on the examples presented throughout the book. Finally, this chapter
suggests areas for further study in the field of construction conflict, dispute avoidance,
and alternative resolution methodologies.

vi
PREFACE

Intended Audience
This introductory textbook is offered to both graduate and upper level undergraduate
students, as well as practicing professionals such as construction managers, design
engineers, and owners. Students should use this book to develop a basis of knowledge in
the area of dispute avoidance and resolution in the construction industry. We hope that
they will use this knowledge when they become practicing professionals or spark further
research in this area if they continue their graduate studies. Current practicing
professionals should compare this book with their current knowledge, keeping an open
mind in new techniques and whether they apply to their situation. This book is offered to
the professional community as the construction industry responds to its global reach,
where the conflicts are multinational. This book in no way serves as a substitute for
individual legal council provided by an attorney. Our competency in addressing these
issues stems from an international construction engineering and management background
with limited legal training in any specific country. Therefore, take no specific legal
advice from us, as none is offered. Your legal council, familiar with your individual
project situation, should advise you of your options.

About the Authors


Feniosky Peña-Mora (ScD., MIT) is an Associate Professor of Information Technology
and Project management in the Civil and Environmental Engineering Department's
Intelligent Engineering Systems Group at the Massachusetts Institute of Technology.
Prof. Peña-Mora current research interests are in information technology support for
collaboration, change management, conflict resolution, and process integration during
design and development of large-scale engineering systems. He is the leader of the Da
Vinci Agent Society Initiative at MIT that integrates his research interests. He is the
author of publications on computer-supported conflict resolution, computer-supported
engineering design and construction, project control and management of large-scale
engineering systems. One of his publications received the 1995 award for best paper
published in the ASCE Journal of Computing in Civil Engineering. He is also holder of a
1999 NSF CAREER Award and a 2000 White House PECASE (Presidential Early Career
Award for Scientists and Engineers) Award. He has been an invited speaker in numerous
conferences and symposiums including the 2001 National Academy of Engineering
Frontiers of Engineering Symposium. Prof. Peña-Mora has been a consultant for industry
and governments in Argentina, Colombia, Dominican Republic, Japan, Puerto Rico, and
the United States. He is the Chief Technology Officer for Peña Alcántara Consultants, a
consulting firm specializing in project management and information technology. He was
the Chief Technology Officer for inMeeting.com, an Internet company specializing on
managing rich collaborative sessions in heterogeneous devices for large-scale product
devlopment. In the Boston Central Artery/Third Harbor Tunnel Project, he was the Chief
Information Technology Consultant for the Project Director. There, he focused on
information technology support for change management and process integration during
the design and construction stages of this $13.6 Billion, decade long regional engineering
endeavor.
Carlos E. Sosa (MSc.., MIT) is a practicing professional in the field of Claim
Management and Dispute Resolution in Venezuela. After working with some of the
major contractors in Venezuela, in 1997 he began its own consulting firm dedicated to
offering Construction Management and Dispute Avoidance and Resolution Services to
contractors and developers. In 1999, he led the development and successful launch of
Venezuela’s first and most important Internet Construction Portal www.areazul.com,
together with the Venezuelan Construction Chamber. Currently he is working on
expanding the services offered by his firm throughout Latin America.

DRAFT 2/4/2017 2:32:00 PM vii


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

D. Sean McCone (MSc.., MIT) is a practicing professional in the construction


management and engineering profession. He completed his undergraduate studies at the
University of Illinois at Urbana-Champaign while working for Johnson, Mirmiran and
Thompson, a transportation-engineering firm in Baltimore, Maryland as a work/study
student. As an assistant program manager, he was involved in the management for the
design of over US$1 billion in capital improvements at the Baltimore Washington
International airport.

Acknowledgements
The authors would like to acknowledge the following individuals for their technical
guidance in creating, revising and editing the book: Phil Helmes, Margaret Fulenwider,
Soád Kousheshi, Shounak Lahiri, Eduardo Witzke, Naz Majidi, Thomas Zgambo, Lara
El-Amm, and all the anonymous reviews that provided insightful comments on the drafts
of this book.
The authors would like to thank the National Science Foundation for their support to the
research that served as the basis for this book under the following grants: White House
PECASE Award, NSF CAREER Award CMS-9875557 and NSF IIS-9803251. We
would also like to thank the Central Artery and Third Harbor Tunnel Project, Tren
Urbano Project, InteCap Inc., Kajima Corporation, Shimizu Corporation, Draper
Laboratory, Ford Motor Company, Visteon Corporation, Microsoft Corporation, PenOp,
Modern Continental, Intel Corporation, and AT&T for their financial support to the
DaVinci Initiative (within which this book was born) and providing us access to their
personnel. Their contributions have been invaluable.
We would also like to thanks Joan McCusker for her tireless effort and support.

Feedback
Comments, constructive criticisms, and suggestions are welcome and encouraged.
Suggestions and contributions to make this book more relevant and useful to the intended
audience are greatly appreciated. Please contact Feniosky Pena-Mora at
[email protected].

viii
DEDICATION
Feniosky Pena-Mora:
A los pilares de mi vida:
• Mami, Mirtha Mora-Cepeda, por sembrar en mí una visión positiva cada vez
que tenía que conseguir algo muy importante. Siempre me decías: “Lo único que
puede ser es que tu ganes. Si tratas y no lo obtienes, te quedas igual – tu no lo
tenias como quiera. Si tratas y lo obtienes, ganas. Por tanto solo puedes ganar.”
• Papi, Ramón Peña-Salcedo, por siempre recordarme que mi único trabajo era
estudiar.
• Mi Adorada Esposa, Minosca Alcántara- Damirón (Minin), por quererme tanto
y apoyarme en todo lo que hago.
• Mis Hijos, Aramael, Amnahir, and Giramnah Peña-Alcántara, por que se que
ustedes serán mi orgullo y mi mejor trabajo.
To the pillars of my life:
• My Mother, Mirtha Mora-Cepeda, for planting in me a positive vision of life
whenever I wanted to get something important. You always said: “You can only
win. If you try and don’t get it, you stay the same – you don’t have it anyway. If
you try and get it, you win. You see, you can only win.”
• My Father, Ramón Peña-Salcedo, for always reminding me that my only job
was to study.
• My Beloved Wife, Minosca Alcántara- Damirón (Minin), for loving me so
much and providing me support in everything I do.
• My Children, Aramael, Amnahir, and Giramnah Peña-Alcántara, because you
will be my pride and my best work.

Carlos E. Sosa:
I have to acknowledge and appreciate the support and patience of my wife Cristina.
Throughout this race against time, Cristina has been both an inspiration and a challenging
voice that has kept me going, even at times when I felt the objective was unattainable. I
would also wish to thank my sister Daniela Sosa and my father Carlos Sosa. I wish to
dedicate this effort to my family, including those who will hopefully be joining us in the
near future.

D. Sean McCone:
This book is dedicated to all of my family for their love and caring. In particular, I would
like to express my sincere gratitude to my parents, Fran and Bob. Throughout my years,
you have given me the freedom and support that defines who I am. I hope that one day I
will be able to repay you for the priceless contribution you have bestowed upon me.
Carrie and Brett, thanks for all the encouragement. Kelly, thank you for your love and
support, and for enduring the frustration and stress I exuded on you during my extensive
studies.

ix
C H A P T E R

1
THE
CONSTRUCTION
In the United States alone, $60 billion are spent
every year on lawsuits, of which the construction
industry accounts for nearly $5 billion.

INDUSTRY Paraphrasing Henry Michel (1998)

In 1995, companies from six different countries participate at different levels, with
different contractual relationships to build a Refinery. For the construction of this
Refinery in an Island in the Caribbean Sea (Figure 1), a British energy conglomerate
(CLIENT) hired an engineering and construction firm from the United States to serve as the
construction manager (CM). Among the many contracts for the Refinery, a Liquid
Nitrogen Gas facility had to be designed and built, for which the CM chose a design firm
from England (DESIGNER), and awarded it a two-year fast-track Design-Build package.
This design firm, a subsidiary of a German design and construction company, kept the
design in-house and divided the construction package in the usual work subdivisions (i.e.,
site work, foundations, civil, mechanical, electrical, and specialties). The DESIGNER
negotiated and awarded the contract for the foundations to an Italian contractor with
experience in similar projects, and the civil works contract 1 to a medium size company

CHAPTER LOOK AHEAD


WHAT IT IT? The construction industry is unlike any other industry in the world. The global market
encompasses over three trillion US dollars. The vast majority of construction projects are one-time
individualistic projects, never to be duplicated, developed in an open environment where variables such
as weather, soil, political, social and environmental conditions are difficult or impossible to control.
WHO IS INVOLVED? Participants in this industry include owners, engineers, governments, regulation
agencies, constructors, unions, suppliers, lawyers and financial institutions to name a few. Their roles
and objective in the construction industry vary based on their contractual relationships for each project.
WHY IS IT IMPORTANT? Conflict in this industry is inherent of the characteristics of this industry.
Industry size, complexity, uniqueness are conflict related characteristics. If we understand the
characteristics of the industry causing conflict, we are more apt to develop DART.
HOW TO APPROACH IT? Understand the organizational issues and project uncertainty that create conflict.
Evaluate the roles each participant plays in a construction project. Review the delivery systems that are
currently used today to define these relationships. Evaluate the contractual relationships that each
participant holds. Apply this knowledge to the projects, to help reduce potential conflict.

KEY CONCEPTS
Sources of Conflict and Dispute ....................3 Organizational Issues ........................................ 6
Participants and People Issues .......................6 Project Uncertainty ........................................... 13

1
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

from Venezuela. The Italians had recommended the Venezuelan company due to positive
past experiences in other large-scale projects. The total scheduled duration for these two
contracts was 18 months: ten months for the foundations and twelve for the civil works,
with a four-month overlap.

BRITISH
ENERGY
CONGLOMERAT

Construction Management contract for


Refinery Complex
GERMAN DESIGN
CONSTRUCTION
AMERICAN CONSTRUCTION
HOLDING COMPANY
MANAGER (CM)

BRITISH DESIGN BUILD (fast-track)


CONTRACTOR FOR LNG TANKS
(DESIGNER)

Formal Sub-contract Corporate bid and performance


agreement bonds for 100% of the work

BID negotiations
and TECHNICAL ITALIAN CONTRACTOR
communications FOR FOUNDATIONS AND
during CIVIL WORKS LNG TANKS
construction

Formal Letter of intent to form joint venture,


communications assuming 100% responsibility over
and payment cost and schedule for portion of
request to British work through corporate and personal

VENEZUELAN SUB-CONTRACTOR
ABOVE GRADE WORK PACKAGE CIVIL
WORKS (SUB-civil)

Figure 1- Diagram of Parties and Relationships for the LNGT Project.

Looking a little closer at the structure, because of sub-contractor approval and bonding
requirements imposed by the CM, the British DESIGNER, and the Italian and Venezuelan
contractors agreed to have the foundations and civil works packages lumped as one
contract to be awarded to the Italians (GC). The latter in turn would subcontract out the
civil portion to the Venezuelan contractor (SUB). The contracts were drawn up following
this arrangement; nevertheless, communications lines were established as if the
Venezuelan SUB was working directly for the British DESIGNER.
Looking at the structure of this project, some important questions arise. Does this
arrangement provide any indication on how much conflict the project would encounter?
Is there anything about the project structure that would give an indication on how this

2
THE CONSTRUCTION INDUSTRY

project will handle conflicts? Does this project have mechanisms to handle uncertainty in
this project? Is there a process by which conflicts on this project will be handled?

1.1 SOURCES OF CONFLICT AND DISPUTE


A number of causes of disputes in construction projects have been presented in literature.
However, a common source of conflict found is the fact that the majority of projects are a
one-time experience. Even when companies perform projects of a similar nature and for
the same client, differing site conditions, regulations, subcontractors, market conditions,
and team members modify the development of the contract.
Construction is significantly different from manufacturing, where the same goods are
produced a thousand times. Construction does not allow for the change of one variable
while holding the rest fixed in order to study its effects. Furthermore, in any given
project, different reasons for a particular dispute will be found depending on who is
asked, at what stage of the project the research is conducted, how the survey is
administered, or what documentation is available for review. That is why analyzing
construction projects post-factum adds complexity and makes the concluding task more
difficult.
The rationale behind the efforts to identify the sources of disputes in construction has
been the premise that if the origins of the “illness” can be identified, ways to “cure” the
industry from unnecessary litigation can be developed. In particular, Stipanowich (1996)
described the construction industry as the “…spearhead of experimentation with
mechanisms aimed at avoiding disputes by addressing the roots of controversy.” Table 1
summarizes seven different research efforts conducted during the past decade, and the
sources of disputes in construction projects they have identified.

Table 1 – Research on the Sources of Conflicts and


Disputes in the Construction Industry (Fenn et al., 1997)

Research Author Sources of Conflicts and Disputes in Construction


Bristow, 1998 Six Areas: unrealistic expectations; contract documents;
communications; lack of team spirit; and changes.
Conlin et al., 1996 Six Areas: payment; performance; delay; negligence;
quality; and administration.
Heath et al., 1994 Seven Areas: contract terms; payment; variations; time;
nomination; renomination; and information.
Hewit, 1991 Six Areas: change of scope; change conditions; delay;
disruption; acceleration; and termination.
Rhys Jones, 1994 Ten Areas: management; culture; communications; design;
economics; tendering pressures; law; unrealistic
expectations; contracts; and workmanship.
Semple et al., 1996 Four Areas: acceleration; access; weather; and changes.
Sykes, 1996 Two Areas: misunderstandings; and unpredictability.

DRAFT 2/4/2017 2:32:00 PM 3


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

At first sight, it seems that there are vast sources of construction conflicts and disputes,
but if you take a closer look you will see that most of the areas are the same, but
identified with different adjectives. This problem requires a set of labels or headings to
facilitate the comprehension of the reasons behind construction conflicts and disputes. On
this account, Howell et al. (1988 cited by Vorster, 1993) proposed a nomenclature of
elements that summarize four causes behind conflict in the construction environment:
• Incomplete scope definition
• Inappropriate contract type
• Poor communication
• Uncertainty
However, this classification can be further simplified in this book into to two main areas.
This arrangement gathers most of the information presented in Table 1 and Howell et
al.’s model, yet it permits a simpler cataloging of the ‘genesis’ of construction disputes.
This classification is presented herein to accurately group these areas of conflict.

Table 2 – Sources of Conflict and Dispute

Area Discipline Sources of Dispute

Internal/external organizational structure, delivery


Structure systems, inappropriate contract type, contract
documents, contract terms, law
Performance, quality, tendering pressures, payment,
delays, disruption, acceleration, administration,
Organizational Process
formal communication channels, information
Issues
sharing, reports and poor communication
Misunderstandings, unrealistic expectations, culture,
language, communications, incompatible objectives,
People
management, negligence, work habits, and lack of
team spirit
Change, variations, environmental concerns, social
External impacts, economics, political risks, weather,
Uncertainty regulations , and unforeseen site conditions
Incomplete scope definition, errors in design,
Internal
construction methods and workmanship

This characterization has the additional contribution of supporting the notion that people
issues are related to the project structure and process problems. For example, certain
project structures align some of the participant’s objectives where as others do not. When
the parties’ objectives and interests are not compatible, their interpretations of contract
documents, terms and conditions can be divergent leading to discrepancies and conflicts.
In short, all of disciplines within an area are interrelated.
Confirming this notion of a relationship between objectives and disagreements, many
participants acknowledge the apparent conflict-prone nature of construction projects on
the incompatibility of the parties’ initial intents. Each construction party starts with a
different set of goals, correlating this information to the high tendency to conflict in this

4
THE CONSTRUCTION INDUSTRY

industry. Incompatible objectives are responsible for the frequent disagreements on how
to approach and complete a project, leading to adversarial attitudes. Table 3 illustrates the
results, when they asked owners and contractors to identify what constituted business
success for their companies in construction projects following a traditional Design-Bid-
Build approach.

Table 3 – Owner-Contractor Objective Alignment (Howard et al., 1997)

CONTRACTORS OBJECTIVES
• Achieve profit and other financial gains.
• Satisfy client and generate repeat business.
• Manage cash flow.
• Limit long-term liability.
• Develop employees and create satisfaction.
• Optimize employment level within contractor organization.
CONTRACTORS’ AND OWNERS’ OBJECTIVES
• Complete the project within budget.
• Complete the project within schedule.
• Maintain a high level of quality.
• Execute the project safely, without wasted time or accidents.
• Minimize claims and litigation.
OWNERS OBJECTIVES
• Meet return on investment goal.
• Minimize plant operating and maintenance costs.
• Minimize plant downtime and outages.
• Achieve high product quality.
• Achieve product throughput capacity goals.
• Provide design flexibility to meet future demands.
• Minimize disruptions to existing operations.
• Avoid negative impact on environment and community.
• Reduce project cycle time.
• Exceed internal customer’s expectations.

As shown, only in a few responses the owner and contractor shared a set of objectives.
On the one hand, “the owner wishes to obtain maximum quality, functionality, and
capacity at a minimum cost.” On the other, “the contractor ...must achieve financial
goals that are advanced by expending the minimum resources required to meet a
minimum scope of work” (Howard et al., 1997). This limited alignment of objectives
fosters the development of conflicts and disputes.
After reviewing the reasons behind disputes in the construction, it appears that conflict is
an intrinsic aspect of this industry, as each project has its own set of organizational issues
and project uncertainty. These conditions also make each project unique, making the
development of a unique theory on the sources of conflict and dispute in construction a
challenging task. Therefore, it remains the responsibility of each project team to assess
their specific project characteristics to develop a joint, creative, and effective approach to
deal with and resolve conflicts before they can lead to disputes.

DRAFT 2/4/2017 2:32:00 PM 5


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

1.2 ORGANIZATIONAL ISSUES


As seen in the LNGT project, organizational structures can be very complex. Contractual
relationships and channels of communication created may be inefficient and create
conflict. The structure of a project can reduce or create conflict among the multiple
participants. To get a grasp on project structure lets first look at several different “pure”
project structures and delivery systems in order to identify participants, their roles, their
responsibilities, and their relationships. Next, we can identify potential conflicts in those
relationships, to evaluate how the delivery system affects the conflict situation, and
therefore, the negotiation process through changes in participants’ relationships.

1.2.1 PARTICIPANTS AND PEOPLE ISSUES

General characteristics of the major participants on the project, such as the owner, the
A/E, the contractor, and the CM, are reviewed here based on their interests, positions and
attitudes. Others that need to be considered but not mentioned here include
subcontractors, suppliers, unions, lawyers and financial institutions. Between these
participants, there are many sources of disputes. Misunderstandings often result in
conflict. All owners push for a job to be completed, as soon as possible, with exceptional
quality and minimal cost, but sometimes their expectations are too high. Even though a
contractor may be performing exceptionally compared to the industry standards, the
owner’s paranoia may harbor the feeling that contractor is not. As seen, people issues are
a major source of conflict. However, projects that encounter monumental challenges and
enormous conflicts can be overcome if the participants cooperate and communicate
effectively.

Owner
The owner is the inciting party for whom the project is developed. This party is also, in
most cases, the source of the financial resources that support the project. It is important to
notice the distinction between private and public owners, because the private owner’s
contracts operate differently from the public ones. The private owner may include
individuals, partnerships, corporations, or various combinations thereof. Most private
owners are the end users who have the facility built for their own use. Some others may
sell, lease or rent the facility to others for a profit. These differences of the owner’s
position in the “value system” (Porter 1985) may affect his/her strategy and, therefore,
his/her interests in a project. On the other hand, in the United States the public sector
owners are composed of local, state, or federal governmental bodies. Public projects are
paid for by appropriations, bonds, tax levies, or other forms of financing and are built to
meet some defined public need. It is interesting that public owners’ interests are largely
affected by the needs of the public they serve, who is usually not at the table when
conflicts occur. Another important point is that the public owner may be subject to
restrictions on delivery methods, such as a state law against public owners using design-
build. This may sometimes result in contractual relationships that contain unresolved
problems, or potential conflicts.

Architect/Engineer (A/E)
The A/E is the party that designs the work and often administers the construction phase
of the project on the behalf of the owner and in the absence of a CM. The A/E can occupy
a variety of positions with respect to the owner for whom the design is done. It is quite
common that the A/E acts as an independent designer under contract with the owner. In
some agencies that hold their own in-house designers, the A/E occupies a functional part

6
THE CONSTRUCTION INDUSTRY

of the owner’s organization. Meanwhile, the A/E may be affiliated with the contractor
when the owner contracts with a single party for both design and construction services.
Depending upon contracts and organizations, the A/E takes various positions as they
relate to both the owner and the contractor. In those cases, the A/E’s interests may differ
accordingly from project to project, however, some of his/her inherent interests, such as
safety and aesthetics, will not change.

General Contractor (GC)


The GC is the entity that is charged with the responsibility of actually putting
construction work in place and performs some or all of the actual work. The GC is the
entity that determines the means, methods, techniques, sequence, and procedures to direct
the actual construction activities. The subcontractors are responsible to the GC in the
same way that the GC is responsible to the owner. Therefore, in the interest of clarity and
simplicity here, the discussions on construction forces are confined to the GC. In
different contracts, there are a number of ways to price and pay for contracted services of
the contractors, which greatly influence one of their greatest interests, profit and risk
allocation. It must be noted that recent trends have been for a GC to subcontract all the
work for a project and not perform any of the actual work. For the purpose of this book
we define these general contractors as construction managers at risk.

Construction Manager (CM)


The CM may be design firms, contractors, or professional construction managers.
Construction management services range from mere coordination of contractors during
construction, to broad responsibilities over project planning and design, construction
scheduling, cost monitoring, and other management services. Depending upon the scope
of work determined by contracts, the CM may have several interests at a time, but most
of the times, some interests such as reputation remain at the center of the CM’s interest,
considering the nature of the professional services it provides.

Roles, Responsibilities, and Relationships


Based upon the characteristics of the major participants in a construction project, their
roles, responsibilities, and relationships need to be examined. To examine their
relationships however, it must be noted that there exists contractual relationships and
communicational relationships among the participants in projects. It is important to
maintain the clear distinction between these two types of relationships when we
scrutinize the project structures. There may not be a contractual link between the major
participants in a project, but only a communication link. This means that, although two
parties may sit at opposite ends of the negotiation table, a particular outcome may have to
be expressed through contracts held by a third party. The traditional design-bid-build
system, for example, places the owner in the middle of any conflict between the designer
and the contractor, who only have communicational relationship in the project. Thus, it is
critical to understand the contractual relationships and communicational relationships in
order to explore the negotiations that will occur as part of the administration of the
contract on a particular delivery system. The relationships need to be examined within a
delivery system for them to be accurately characterized.

1.2.2 PROJECT STRUCTURE

There may be a number of ways to classify project delivery systems. The following seven
delivery systems were selected for review so that they can effectively show clear
distinctions between the participants’ roles, responsibilities, and relationships.

DRAFT 2/4/2017 2:32:00 PM 7


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

• The Traditional Design-Bid-Build (DBB)


• Pure or Agency Construction Management (PCM)
• Construction Management at Risk (CMR)
• Design-Build (D/B)
• Turn-Key (TKY)
• Design-Build-Operate (DBO)
• Build-Operate-Transfer (BOT)
DBB has been the most frequently used delivery method, often called the “traditional”
approach. This assumes that design and construction of the project proceed in sequence,
awarding the construction contract after plans and specifications are completed. Most
references in this book are targeted toward the DBB delivery system unless noted
otherwise. In construction management, a construction manager plays a distinctive role to
perform as the owner’s agent or sometimes to take construction risks instead of the
owner. These two types of construction management, PCM and CMR, are expected to
illustrate the effect of risk shift among participants’ relationships. Recently some “new”
delivery systems packages such as D/B, TKY, DBO, and BOT have become popular.
These delivery systems focus on the concept of combining project phases into on one
contractual service. Figure 2 is included to define what we mean by “project phases”.

Project Phase

Scope of Design Construction Operation & Maintenance


Work

Financing Short-Term Financing Long-Term Financing

Figure 2 - Contractual Services (Gordon 1991)

D/B is a delivery system where both design and construction functions are combined
under one contract. TKY can be categorized as one of the modification of D/B, which
packages design, construction, and short-term financing. DBO is an extension of the
TKY delivery process, but with O&M included over an extended period of time. BOT is
a further extension of the DBO model, including long-term financing. Those differences
in scope of the contracts are also anticipated to make distinction among each participant’s
relationship. The models of the project structure followed in these four delivery systems
are depicted in Figure 3. Project structures for TKY, DBO and BOT may be illustrated
similarly as the one for D/B, except for the differences of extra functional groups
involved in their teams, such as O&M forces and financing firms.

8
THE CONSTRUCTION INDUSTRY

Owner Owner

A/E
CM A/E

General
Contractor

Sub Sub Sub Trade Trade Trade


Contractor Contractor Contractor Contractor Contractor Contractor

(a) Traditional Design-Bid-Build (b) Pure or Agency Construction Management

Owner Owner

D/B Entity
CM A/E
Construction Design
Function Function

Trade Trade Trade Sub Sub Sub


Contractor Contractor Contractor Contractor Contractor Contractor

(c) Construction Management At Risk (d) Design-Build

Contractual Relationship Communicational Relationship Internal Relationship

Figure 3 - Project Structures of Selected Delivery Systems

The Traditional Design-Bid-Build


The owner, the A/E, and the contractor are the three major participants in this structure.
The project proceeds sequentially, with design reaching full completion prior to
conducting bidding and the selection of a contractor.
In this structure, the owner contracts directly and separately with the contractor and the
designer. There are formal contractual relationships between the owner and the contractor
as well as between the owner and the designer. The owner selects and hires the A/E to
whom they may entrust responsibility for design and construction inspection. A lump
sum bid is commonly used in this delivery system for both public and private projects.
The lump sum and general contractor approach tends to set up a build-in adversarial
relationship between the owner and contractor. This typically results from the general
contractor’s principal interest in delivering the project below the lump sum amount to
achieve or increase profit or to encourage change orders or claims for the same reason.
The owner’s interest may vary depending upon projects, including quality and value of
product, delivery schedule, site safety, and environmental impact. However, they are
greatly influenced by the major assumption for this system that responsibility and risk are
allocated easily by segmenting tasks. The owner also has an emphasis on construction
costs that the DBB method pursues through a strong market competition.
The A/E completes the design and develops the general contract documents, interpreting
the owner’s needs. The general responsibilities beyond those are to administer the owner-
contractor contract, functioning as the owner’s agent. The owner and A/E are in more of
a collaborative position, because the A/E is typically selected on a qualification basis, and

DRAFT 2/4/2017 2:32:00 PM 9


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

occupies the position of primary consultant and fiduciary to the owner. No formal
contract exists between the A/E and the contractor. However, despite no contractual
relationship, the informal relationship of communication exists between the A/E and the
contractor. The adversarial relationship may occur between them, because the contractor
has to act on orders from a contractually unauthorized source. From the nature of work
and selection base, the A/E’s interests may include profit, aesthetics, relationships,
quality, recognition, and otherwise.
The general contractor’s role usually starts from the bidding stage, so they play very little
or no part in the design phase. They take total charge of the site and construction of the
project. They coordinate and supervise the works of the subcontractors who actually
undertake most of the construction. They are responsible to the owner for the
construction in accordance with plans and desires of the A/E. They normally assume
responsibility for all site safety issues. In general, the contractor’s interests may include
profit, construction time, relationships, and reputation, although profit almost always
seems to be one of the top priorities. Construction time, or schedule, is also a key element
of the project especially in a situation that time becomes a cost item to the contractor.

Pure or Agency Construction Management (PCM)


The owner is responsible for selecting and hiring the PCM as well as the A/E. The
owner’s interests may not be different from the ones in DBB, but the choice of a PCM as
an agent largely affects the owner’s interests. The owner appropriately selects the PCM
system, due to its advantages of great flexibility in the schedule and for changes, as well
as fiduciary relationship with the contractor both before and during construction, while
still providing market competition for most of the work (Gordon 1991). The role of A/E
remains much the same as in the traditional design-bid-build method, but the appearance
of a PCM affects the A/E’s roles. The A/E is forced to adjust their communication
network and their own responsiveness to accommodate the owner-PCM relationship. The
PCM does not hold any contracts with trade contractors, nor guarantees any sort of upset
price to the owner. For these reasons, the financial risk to the PCM is small but the risk of
loss of reputation is very high. Unlike other participants, the PCM in this system may
have greater interest on reputation and relationship at the expense of profit since most of
the time they have fixed fees. In this light, it is likely that the PCM could undertake the
facilitator/mediator role in negotiations when conflicts arise in a project.

Construction Management at Risk


This is often called construction management with a guaranteed maximum price (GMP).
Many owners want to reduce their risk by having the CM guarantee a total upset price for
the work, a GMP. With a GMP, the process becomes more like the traditional design-bid-
build process. This casts relationships into a status somewhere between that of the
traditional design-bid-build method and the pure construction management method. In
this system, the CM holds all of the trade contracts directly. The CM is responsible for
completing the project for a total sum equal to or less than the GMP. Their interest on
profit becomes more intensive as project costs approach the ceiling of GMP. This tends
to change the CM’s attitudes in negotiations during the course of the project.

Design-Build
The owner contracts singularly with the D/B team. The design function and construction
function are within one contractual team. The responsibility for design and construction
rests with one organization, and there exists only one contract to the owner. This is
usually a type of general contractor firm with design function. The design function can be
another firm, and the relationship is just as another subcontractor to the prime. Contrary

10
THE CONSTRUCTION INDUSTRY

to DBB, the owners may have more emphasis on schedules despite less control and more
uncertainty of cost. One of the disadvantages of the system is the loss of control over
design and flexibility in changes. The owner must be knowledgeable enough about
design and construction to establish the initial parameters, review proposals, and monitor
the process, which frequently require the help of an independent consultant.

Analyzing Delivery Methods


Given the roles, responsibilities, and relationships of major participants, Table 4
illustrates the differences of the relationships among the major participants in the four
delivery systems. Depending upon the delivery systems, participants form different
relationships: the contractual, communicational, or internal relationships.
Table 4 - Relationships among Participants

Owner- Owner- A/E- Owner- CM- CM-


A/E Contr. Contr. CM A/E Contr.
DBB K K C - - -
PCM K K - K C C
CMR K - - K C K
D/B K* I - - -
K: Contractual Relationship; C: Communicational Relationship; I: Internal Relationship; *:
Contractual Relationship between the Owner and the D/B Team

Relationships differ even between the same participants of projects. For example, CM-
Trade Contractor relationship changes from the communicational one to the contractual
one when the owner shifts his/her risks to CM. The roles and positions may differ
significantly, even under the same relationships participants have. For example, one of
the A/E’s main interests in the DBB contract is to protect his own and the owner’s
interests, while, in the D/B contract, he/she plays the opposite role as the co-worker of the
contractor with the intent of bringing value to the D/B team instead of the owner. The
relationships between the CM and the A/E also show the differences between two
construction management systems. In PCM, both the CM and the A/E serves the owners
as agents and work together in a collaborative manner, while the CMR in practice
appears to be a GC and they may have adversarial relationships.
Since the roles and positions that every participant takes are regulated by the contract
they agreed on prior to the beginning of the project, different contract types lead to varied
positions and interests. Thus, the relationships and interests of participants become
extremely complex. It is quite possible that an owner has a fiduciary relationship with a
designer in a DBB project, while they have an adversarial relationship with the very same
designer in a different D/B project. Moreover, one participant may take two or more
distinct roles in a single project that adopts “innovative” hybrid delivery system. An
example of this is the Systems and Test Track Turnkey contract in the Tren Urbano
Project in Puerto Rico (Section 11.2), which includes design and construction of a
facility, operation system supply, O&M, and coordination/management of other D/B
facility contracts. In such a situation, conflicts due to interest inconsistency occur while
they have to collaborate on the same project under the relationships defined by their
contract protected by law.

DRAFT 2/4/2017 2:32:00 PM 11


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Thus, information on relationships may help the project participants avoid their role and
responsibility confusions. This is especially important in a large-scale project, because
some participants may hold several different contracts and their roles and responsibilities
differ among those contracts. Surveys in American industry show that there is only a 35%
overlap between that which top managers expect their close subordinates to do, and that
which the subordinates themselves think they should do (Scott et al., 1990). This may
apply directly to owners and their relationships with contractors or contractors and their
relationships with subcontractors. Role confusion or misunderstanding is almost
inevitable, especially under competitive stresses in the context of a large-scale project.
Information on roles and relationships may also help in contract planning and formation
process, especially when a hybrid type of delivery system is under consideration. The
owners or project managers should check the interest inconsistency in allocating multiple
responsibilities and risks for hybrid systems.

1.2.3 PROCESS PROBLEMS

Interrelated with the project structure are the process problems. The number and types of
process problems are endless. The sources of conflict relate to how the project is handled.
It focuses on contract administration, contract terms, project management and
inefficiencies therein. These process problems may be inherited from the choice of
project structure and they may be compounded by people issues.
There has been an abundance of material written on construction contracts. 2 This material
addresses formation of contracts, implementation of contracts, breech of contracts and
other related areas. When a conflict of interest arises, the first move each party makes is
to review the contract documents for direction. These documents are not always thorough
nor do they address every situation.

Contract Types
Directly relating to project structure is contract type. In this book, we will focus on
contract types as they differ on the “basis of payment.” For this reason the classification
of contract types will be based on this characteristic. Lump sum, unit price, guaranteed
maximum price, cost plus and fixed fee are all examples of different contract types. Each
of these contracts have advantages and disadvantages, and can create conflict. Some of
these contract types are sometimes synonymous with certain delivery systems, but make
no mistake they are different. Project structure and contract type should be chosen on a
project-by-project basis taking into consideration each individual situation.
The lump sum or fixed price contract is the most common type of contract. It is also the
most adversarial. The general contractor or design-build entity enters into a contract with
the owner for a fixed price. This type of contract compels the contractor to cut corners to
reduce costs and make a profit. On the owner’s side, it requires the owner to provide for
monitoring of the contract for quality and compliance as per the contract documents.
With this being the most common form of contract, you can see why the industry is
plagued with conflict and claims.
One the opposite end of the spectrum it a cost plus contract. The cost plus contract aligns
the objective of the owner and the constructor more so than a fixed price contract. In a
cost plus contract, the contractor will perform the work for the owner at the cost to
him/her plus a percentage for profit. This ensures that the contractor will not lose any
money, shifting more risk to the owner. Knowing this, there is the risk that a contractor
might take advantage of the situation, by inflating the costs and therefore increasing their
profit. In these cases, proper checks and balances need to be provided to ensure that cost
increases represent the reality of the project.

12
THE CONSTRUCTION INDUSTRY

A median between the two is a guaranteed maximum price (GMP). In a GMP contract,
the owner will reimburse the contractor for all the costs plus a profit up to a certain price.
The GMP contract has the benefit of having a fixed maximum price that the contractor
must respect, but still allowing the flexibility of being reimbursed for costs. In short, all
these contracting mechanisms try to achieve a balance between the objectives of each
participant in terms of risk allocation, quality, schedule and cost, among others.

1.3 PROJECT UNCERTAINTY


Equally important as organizational issues are the uncertainties that are present in all
construction projects. Even if the correct delivery method is selected, all the process
problems have been eliminated and the people issues disappear, project uncertainty will
still exist. External uncertainties are those that must be accounted for, but they may not
be able to be directly controlled, as they are the result of external forces. Internal
uncertainties are unforeseen circumstances that we attempt to account for, but are often
unidentified because of lack of information. The area of project uncertainties is inherent
because of the characteristics of the industry.

1.3.1 EXTERNAL UNCERTAINTIES

External uncertainties are the result of external forces on the project. They are present in
all projects and range form inclement weather, to political risk, to acts of god. They are
usually accounted for through insurance policies, contract clauses or other forms of
mitigation. In most cases, there is not a person to blame. For example, securing a contract
with a government in a country that has a history of political chaos and government
overthrows might present the situation where the contract becomes void. After
completing half the work and not being compensated, how should the conflict be
resolved?
In other instances, Mother Nature seems to find her way onto every jobsite. Rain, snow,
wind, fog, extreme temperatures are just some of the factors that impact projects in a
negative manner. To combat these uncertainties, it is normal to insert contract clauses
that address these issues or identify schedule buffers according to the unworkable days.
There are was to proportionate the risks associated with most of the external
uncertainties, but they must be identified ahead of time and accounted for in order to
avoid conflicts on who is responsible and should pay for it.

1.3.2 INTERNAL UNCERTAINTIES

Internal uncertainties range from errors in design, to unforeseen site conditions to an


incomplete definition of scope. In large bureaucratic agencies and long duration projects,
internal uncertainties in terms of scope seem to be more prevalent. This is evident as
projects that start under one administration, who have defined the scope, may be changed
by the succeeding administration with a different agenda.
Unforeseen site conditions are a common source of disputes, even if this risk is allocated
in the contract documents. A finger pointing game results when lack of investigation on
both the part of the owner and the contractors result in. Examples of these include
unexpected contaminated soils or the bearing layer for foundations is deeper than
expected. Too many times “fast track” projects become engulfed in conflict because all
the parties are running in high gear and they overlook minor details that come back to
haunt them midway through a project. Not to mentions that errors and omissions in the

DRAFT 2/4/2017 2:32:00 PM 13


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

design are present in all projects. However, their impact could be minimized with proper
monitoring and control the common statement heard in the construction industry “No
design is ever complete.”
Dissimilar to the disciplines in the organizational issues, technical and context
uncertainties are not interrelated. Political risks do not result from errors in design.
Incomplete scope definition does not breed inclement weather. This is different from the
organizational issues, as these characteristics are derived from the premise that these
uncertainties are present in every project.

The Liquid After reviewing the sources of conflict in the industry, revisit the LNG Tanks Project. We
have already identified the complex project structure, but where’s the conflict? After the
Nitrogen
job got under way, these separate communication and contractual arrangements resulted
Gas Tanks in total chaos. For example, the civil works contract between the British DESIGNER and
Project the Italian GC was never signed, a “detail” that became apparent only 2 years later when
lawyers began compiling the original documentation in preparation for a claim.
Presumably, the contract had been misplaced between Venezuela and Italy; hence, it was
never returned to the DESIGNER for signature.

British
DESIGNER

New
California York Italian
CM GC

Job
Venezuela
SUB

Formal lines of communication

Informal lines of communications

Figure 4 – Worldwide Distribution of Participants with FORMAL & INFORMAL Lines


of Communication for the LNG Tank Project

Moreover, halfway into the job neither party had a complete assessment of the status of
the design and the work completed. The SUB had invoiced 55% of the contract through
the GC, but only 30% was in place; major cash-flow problems were affecting the job, and
cost overruns were evident in every work item. At that point, the DESIGNER took over the
GC responsibilities, by forcing the Italian GC and the Venezuelan SUB into takeover
agreement. This agreement gave the DESIGNER the right to use all the material purchased
for the job and all the manpower and equipment the SUB had on site at that time. In

14
THE CONSTRUCTION INDUSTRY

addition, the GC and the SUB agreed to a provision that made them responsible for all
costs going forward concerning the civil works package. Therefore, the DESIGNER
effectively assumed total control over the project, without relieving the two contractors
from the cost risk of the project. In other words, the DESIGNER could finish the job with
whatever resources it considered necessary and charged them to the contract with the
Italian GC. Any cost over the original base-contract would still be the responsibility of the
contractors. Based on this arrangement, the DESIGNER brought more personnel from
England, provided additional financial resources, and finished the civil works one year
behind schedule.
Five months after the take over agreement, the Venezuelan SUB and the Italian GC
reconciled the jobsite and home-office files (formal and informal communications), and
proceeded to file a claim against the DESIGNER due to changed site conditions and
significant design modifications. This claim amounted in value to 100% of the original
contract cost and declared the takeover agreement invalid. The DESIGNER, in turn, filed a
counter-claim against the Italian GC for liquidated damages per the original “lumped”
contract and for extra costs incurred to finish the job according to the takeover
agreement. This counterclaim was worth double the original contract value.
Both claims for this project went to arbitration in New York, as per the contract terms,
sometime at the end of 1999, almost two years after the project was actually finished. By
mid 1999, the Venezuelan/Italian “team” had spent 3 percent of the original contract in
legal and consulting fees, and it was expected to spend another 3 to 8 percent before an
award through arbitration may be achieved. No information is available from the British
side, but the costs was estimated to be about the same, since both companies have
prepared separate arbitration claims using outside consultants. In other words, both
companies spent 6 percent of the original contract value, and expected another 6 to 16
percent in arbitration costs without knowing whether they will ever recover those
expenses. These costs are in addition to the economic and professional implications of
finishing a job one year behind schedule, with significant overtime costs and added
supervision.

1.4 SUMMARY
This case, although overly simplified for this introduction, provides a snapshot of some
of the conditions that are present nowadays in most large engineering and construction
projects: multi-party, multi-cultural, complex contractual arrangements, with
international arbitration clauses for dispute settlement. It also highlights the need for new
and innovative approaches to communication and contractual relationships, including
new ways to resolve disagreements without relying solely on arbitration or litigation. In
this example, we saw how inefficient communication and complex contractual
arrangements can result in poor job performance. Even though previous experiences in
other projects brought some of the team members together, their inability to overcome the
contractual framework resulted in claims and costs totaling over three times the original
contract value, leading to the following questions. Can these results be avoided? Can
attitude changes improve the overall job performance? Could the job have been saved
without the costly takeover if the parties had sacrificed a portion of the costs they are now
spending on arbitration? Are there mechanisms to improve communication regardless of
contract conditions?
The disputes in this case reached the settlement stage, and these questions remain
unanswered for this project. Thus, this book presents innovative procedures to promote
collaborative environments and resolve disputes in construction contracts. It also presents
specific uses and applications of DART across different countries, which have

DRAFT 2/4/2017 2:32:00 PM 15


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

implemented these techniques and used them within the realm of their own construction
industries. The contents in this book represent the state of the art in DART, and they
highlight how the industry is coping with some of the problems and project complexities
presented above. One of these alternative approaches, or a combination of them, might
have resolved the problems in the LNGT project before the takeover agreement. Even in
binding arbitration, this book presents certain techniques that could have improved the
chances for a “win-win” solution for the claims, at a lower cost to both parties.
These procedures can be used to answer and deal with some of the questions and issues
raised by either the LNG project or any other case throughout the world. Companies,
universities, professional associations, private groups, industry think tanks, and
government agencies have realized the cost implications of poor communication and
litigation in construction. The industry as a whole has realized that if legal costs continue
to grow unchallenged, productivity and technological innovation will continue to fall
further behind, limiting the construction industry’s role in the development and
improvement of our society.

1.5 POINTS FOR DISCUSSION


1.1 The LNG Tank Project seemed to have a sub-optimal contract structure. What
alternative contractual agreements might have been more effective in avoiding
litigation?
1.2 When the project started having difficulties the constructors agreed to give up
control of the project but still take responsibility for the cost. What motivation did
they have for agreeing to these terms?
1.3 With all of the parties from various countries involved, why do you think they chose
New York for arbitration of the dispute?
1.4 With the construction industry being as extremely large, accounting for almost 20%
of all litigation expenditures in the United States, and increasing 10% annually, why
hasn’t more effort been put forth to curb these costs?
1.5 How important is dispute avoidance and resolution in the construction industry?
Relate this to other construction aspects such as safety, cost and schedule control, or
design efficiency?

16
THE CONSTRUCTION INDUSTRY

1.6 REFERENCES

[Conlin et al., 1996] Conlin, J., Langford, D.A.,and Kennedy, P., 1996. The
Relationship Between Construction Procurement Strategies and
Construction Contract Disputes Proceedings of CIB W92,
North Meets South, pp. 66-82. Durban, (January).
[Fenn et al., 1997] Fenn, Peter, Lowe, David, and Speck Christopher, (1997).
Conflict and Dispute in Construction. Construction
Management and Economics (1997) 15, p. 513
[Gordon, 1991] Gordon, Chris. (1991). “Compatibility of Construction
Contracting Methods with Projects and Owners” MS Thesis,
MIT, Cambridge.
[Howell et al., 1988]

[Porter, 1985] Porter, M. (1985). Competitive Advantage, Free Press, New


York.
[Scott, 1995] Scott, Donahey M., (1995). Seeking Harmony. Technique
Dispute Resolution Journal. pp. 74-78. April-June
[Stipanowich, 1996] Stipanowich, Thomas J., (1996). Arbitration: Innovation and
Evolution in the United States Construction Industry. Wake
Forest Law Review Vol. 31 (1) pp. 65-182. Spring
[Sykes, 1996] Sykes, John. Claims and Disputes in Construction: Suggestions
for their Timely Resolution. Construction Law Journal. Sweet
& Maxwell. Vol. 12 (1) pp. 3-13

1.7 ENDNOTES

1
This contract included all sub-base preparation, concrete, reinforcing and formwork to
be completed above grade for the two tanks (i.e. pile caps, gravel sub-base, slab-on-
grade, tank walls, and post-tensioning system).
2
One such book is: Collier, Keith. Construction Contracts. 3rd edition. Prentice-Hall Inc.
Upper Saddle River, NJ. 2001.

DRAFT 2/4/2017 2:32:00 PM 17


C H A P T E R

2
EVOLUTION OF DART
“...there has been a veritable explosion in the
development and use of new dispute resolution
techniques, particularly techniques for resolving
disputes at the job site during the course of
construction.”
(Groton, 1997)

2.1 TRADITIONAL DISPUTE RESOLUTION IN CONSTRUCTION


Not so long ago, dispute resolution had two possible definitions for organizations
involved in construction. The first was for a design professional to render a non-binding
determination, the other was to proceed to binding arbitration. These were the only real
options, other than litigation, available to construction teams to unravel disagreements
during the execution of the project. All parties used negotiations to fill the gap between
these tools; however, they were mostly performed on the basis of experience, business
savvy, and opportunity, without any formal procedure that could promote both a faster
and more equitable settlement of the dispute. Litigation was considered too expensive
and time consuming, so arbitration became the industry standard as the alternative
binding procedure. Figure 5 shows the traditional two-step Dispute Resolution “Ladder”
(DRL) with the two resolution tools. This idea of a Dispute Resolution “Ladder” is used

CHAPTER LOOK AHEAD


WHAT IS IT? Throughout the years, ADR procedures have changed, evolved and grown into what is
currently used in the industry. Binding arbitration or the determination of a designer to resolve disputes
were logical steps, but weakness within these methods led to the development of numerous other
methods. Mediation, conciliation, and dispute review boards add flexibility in resolving disputes.
WHO IS INVOLVED? Most of the “new” procedures are not really new. Arbitration has been dated back to
Ancient Greece. The search for truth and a mutually acceptable solution evolved during the Confucian
era in ancient China. In the Netherlands, the concept of Frame Contracts incorporates objective
alignment and trust to reduce conflict. It goes to show, that DART have developed around the world.
WHY IS IT IMPORTANT? Problems can be solved with a particular technique, but does the answer make
sense if you don’t understand how the technique was derived. By looking at why these methods were
developed, it allows for enhanced implementation of these procedures.
HOW TO APPROACH IT? Review the traditional dispute resolution ladder and contemplate the pros and
cons. Study the development of the Six-step DRL and how it adds flexibility to the dispute resolution
process.

KEY CONCEPTS
Two-Step DRL ..............................................18 Arbitration ........................................................ 20
Modification of the Two-Step .......................23 Evolution........................................................... 29
Current Legal State of the Industry................35

18
EVOLUTION OF DART

to organize dispute avoidance and resolution techniques for construction projects, and it
is further described in Section 2.3.2.

Negotiations between the LITIGATION


parties attempted to resolve
the matter before reaching
arbitration. Arbitration
procedures usually
happened after final
completion
BINDING ARBITRATION

Negotiations

DETERMINATION
BY DESIGN
PROFESSIONAL

Figure 5 – Traditional Two-Step Dispute Resolution “Ladder” in Construction Projects

In this ladder, the design professional played the role of a first step in the process of
resolving disputes. The contractor submitted inquiries and disagreements to the design
professional representing the owner, and then expected prompt, knowledgeable, and
unbiased answers. If either the owner or contractor objected to the determination of this
third party, the matter usually escalated and it was left to arbitration. As discussed above,
and shown in Figure 5, negotiations were used to fill the “gap” between the first and
second step in the ladder. In this stage, either the owner or the contractor has become
involved to formally prevent conflicts and disagreement. An exception to this is perhaps
attempting to transfer project risks to the opposing party in an effort to limit individual
liabilities. Design-Build projects are based in part on this notion of reducing the owner’s
exposure to design problems, by assigning both the design and the construction
responsibility to only one party.
The second step in the ladder, Arbitration was the preferred alternative to litigation for
the resolution of construction disputes because it offered “...a limited process, a
relatively prompt hearing, privacy, informality, and above all, [an] informed judgment”
(Stipanowich, 1996). This is how arbitration became a “sine qua non of construction
contracting,” and gained popularity as a standard clause in most contracts. If the first step
of the ladder failed to resolve the dispute, arbitration procedures were usually delayed
until the project was completed. The two dispute resolution steps of the traditional
construction DRL, are discussed in more detail in the following two sections.

2.1.1 DETERMINATION BY THE DESIGN PROFESSIONAL

In “traditional” design-bid-build delivery methods, the resolution of construction disputes


has been the responsibility of the project architect/engineer for a long time. It was
considered logical that the design professional, who drafted drawings and contract
specifications, made determinations with regards to interpretations, and related conflicts

DRAFT 2/4/2017 2:32:00 PM 19


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

between the owner and the contractor. The decisions of the architect/engineer were
backed by their profound knowledge of the technical considerations of the project,
something that gave them the authority to resolve almost any matter related to their
‘creation’. The decisions of the design professional were usually not final nor binding on
the parties, but they provided a fast, knowledge-based, “objective” solution to jobsite
disputes.
Nevertheless, as contracts became larger, the technical complexities increased and the
number of parties expanded, the quantity, frequency, and size of project disputes also
increased. The dollar amount of contract disagreements became larger and delayed
completion time brought additional problems. Although it was often assumed by owners
that the evaluation of disagreements would always be conducted by their own on-site
agent (engineer or architect), the changes described eventually undermined the position
of the agents and they were finally considered not in the best position to propose or
evaluate the merits of an equitable settlement.
Among the major concerns that led this transformation was the possible conflict of
interest as the design professional was not truly neutral. A contractor seeking
compensation from the owner because of a contractual problem involving administration,
design, and/or contract interpretation elements was not likely to find an objective
decision originating from the agent, since this last was an actual part of the condition
being claimed (Stipanowich, 1996). Furthermore, in disputes regarding errors or
omissions in the contract, the design professionals frequently became a defendant, so
their role as an ‘unbiased third party resolver’ of disputes lost credibility. At that point
the owner was left to face what often were disputes that could not be settled by the people
they had assumed would be responsible of doing so during the project.
The role of the design professionals as the first step in the DRL has lost significance,
especially in large, complex projects where their decisions can be challenged in other
forms of binding adjudication, or where they can become a part of the dispute. Although
the design professional still remains the primary interpreter of design and specification
requirements, their role as a dispute resolution adjudicator has been reduced significantly.
Still, the benefits of having an unbiased, knowledgeable third party involved in the
resolution of construction disputes is still recognized by the industry (i.e., objectivity,
speed, decisions backed by technical know-how, and an understanding of the project) as
it will be demonstrated in further examples of third-party ADR techniques. Thus, it can
be argued that the concepts of Neutral Advisors (Section 6.1) and Dispute Review Boards
(Section 6.3) have been developed by the construction industry as substitutions and
improvements of the role played by the design professional in the traditional DRL.

2.1.2 ARBITRATION

This section presents two cases of early applications of arbitration as a dispute resolution
technique, together with the use of arbitration in the construction industry. The two cases
provide two important lessons for the use of arbitration in construction dispute resolution.
First, the Greek case shows how arbitration was implemented as a dispute resolution
system. Then, the use of arbitration in the Middle Ages in England shows how this
technique followed a path towards rigidity and formalization as its use increased just like
arbitration in construction during the past fifteen years.

Arbitration Experiences in Greece


In an article published in the Dispute Resolution Journal, King et al. (1994) described the
use of arbitration by the Greek city-states. The authors reported that by 500 BC
arbitration had reached almost universal acceptance throughout Greece, where it was

20
EVOLUTION OF DART

often used to resolve commercial problems between citizens, and as a diplomatic


resource between city-states. These early uses of arbitration provide an interesting
example of how alternative dispute resolution (i.e., arbitration) has been an integral part
in the evolution of human relationships. Furthermore, it appears that the reasons behind
the development of arbitration in Ancient Greece are also associated with flexibility,
privacy, and economy; the characteristics that allowed arbitration to become a pivotal
part of the Traditional DRL. The following case helps illustrate these observations.
According to the article, the Athenian democracy was rooted in the success of
commercial arbitrations conducted by Solon, a well-known Athenian lawmaker 1. At the
time, increasing social unrest required a prompt resolution of disputes; something that
Solon achieved by proposing knowledge-based, fast, and mutually beneficial resolutions
(sometimes the fallback was war). Just like some models in the present time (e.g., expert
determination and arbitration), the decisions of a third party neutral were final and not
eligible for appeal, as they were considered the judgment of city-state appointee to solve
the discords. These characteristics which made arbitration the dispute resolution system
in ancient Greece are also the some features that fostered its incorporation in the DRL of
the construction industry: fast solutions based on knowledge and experience, flexibility,
and finality.

Arbitration in Old England (602-1698)


Another case of ancient applications of arbitration is found in the history of Old England
from the Dark Ages to the end of the Middle Ages, where arbitration was a conciliatory
process used as a true alternative to litigation. Arbitration’s function was to reconcile the
parties and allow them to sustain long-lasting business relationships. Arbitration was
embodied in the medieval institution of the “loveday,” 2 and was essentially a form of
mediation .
“When two merchants found themselves in dispute …they went to a colleague,
and agreed to abide by his decision. In many trades, there was no need for
enforcement of awards at law. If a man failed to comply with an arbitral award,
[he/she] faced commercial ruin when his peers were no longer prepared to give
him credit or to deal in his goods. Chambers of Commerce and trade
associations played an active part in arbitration.”
Beresford Hartwell (1998)
However, as disputants began to use arbitration as a substitute to court litigation,
arbitration acquired some of the characteristics of the legal system; something that gave
raise to a pseudo-adjudicative variety of the technique that grew as the commercial
community used it more and more. Consequently, from the late Middle Ages through the
early modern period loveday arbitration changed, as potential abuses of the process and
evolving notions of community, competition, and individualism contributed to the
disappearance of arbitration as a conciliatory process (Yarn, 1995).
It can be seen from this how arbitration evolved from a purely conciliatory process to an
adjudicative system, as its use by the business community and the courts increased. This
evolution is similar to the one found in the arbitration of construction disputes today.

Arbitration in the Construction Industry


As mentioned in the traditional two-step ladder, if the parties failed to reach an agreement
with the design professional, the only alternative was binding arbitration. Arbitration
clauses became the standard in agreements between owners, designers, and contractors,
functioning as the dispute resolution technique instead of litigation. Standard contract
forms issued by professional associations like the American Institute of Architecture

DRAFT 2/4/2017 2:32:00 PM 21


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

(AIA), the Association of General Contractors (AGC), and the Chartered Institute of
Builders (CIOB) all incorporated arbitration as their only dispute resolution alternative.
International organizations like the World Bank and the Federation Internationale de
Ingenieurs-Conseils (FIDIC) also supported the use of this technique. However, with the
increasing acceptance of arbitration as a substitute for litigation, the technique began to
develop problems as it became more rigid and costly.
According to Stipanowich (1996), arbitration was “...subjected to the stresses and strains
borne by its expanded use.” Furthermore, as courts began to accept the system, they
proceeded to delegate in arbitrators the “...burden of almost the entire spectrum of civil
rights and remedies,” creating increasing demands for rules and procedures to
accommodate the expanding needs of the final users, something surprisingly similar to
the extinction of the “loveday” concept in Old England. In response to these demands,
arbitration was forced to adopt certain characteristics from civil litigation, such as
“extensive discovery, multi-party practice, awards of attorney fees, and written opinions
by the arbitrators” (Stipanowich, 1996). Due to these pressures and strains, arbitration
lost some of the features that had made it the preferred dispute resolution technique in the
construction industry: flexibility, privacy, decisions based on technical know-how, and
economy.
The problems experienced by arbitration are reflected in the results of an American Bar
Association (ABA) sponsored survey completed in the mid-1980’s. The study reviewed
the perceived advantages and disadvantages of arbitration in the resolution of
construction disputes, and its respondents, mostly construction attorneys, identified their
major concerns with this form of ADR. Table 5 summarizes the ABA results and
connects them to the features responsible for the initial popularity of arbitration in
construction.
Table 5 – Problems with Arbitration in ABA Survey 1988 and their connection to the
Features of Arbitration identified (Stipanowich 1996)

Problems reflected in ABA Results Arbitration Features


1. Problems regarding the speed and efficiency
of arbitration in larger cases, which made (Economy and Flexibility)
arbitration expensive.
2. Need to consider mechanisms to deal with
(Flexibility)
multi-party disputes.
3. Problems regarding the quality of construction (Economy, Knowledge-based
arbitrators. decisions, and Flexibility)
4. The need to support greater use of preliminary
hearings and pre-arbitration orders to organize (Economy)
and expedite the actual procedure.
5. The need to increase the power of the
arbitrator to order sanctions for delays and (Economy and Flexibility)
‘non-cooperation’.
6. Objections as to the appropriateness of a
written award by the arbitrator explaining the (Privacy)
reasons for the decision.

22
EVOLUTION OF DART

These concerns about arbitration within the ABA confirmed that the system had
developed some of the inherent problems of litigation due to its excessive use. In fact, the
views presented by points 4 and 5 above suggest that arbitration was being abused by the
disputants and their legal representatives, just as it happens in litigation. This is
exemplified by a study by Flood et al. (1993) on this subject in the UK, which concluded
that lawyers had “...essentially ‘juridified’ the field [of arbitration], making the
procedures rigid, costly and time consuming, with the many drawbacks attributed to
litigation.” Arbitration had become an adversarial procedure.
Examples of ancient Greece and England show how arbitration in construction evolved
into a pseudo-adjudicative and adversarial system with many of the features that had
made litigation the least preferred dispute resolution technique. In the next case a final
journey to ancient history is presented to illustrate how dispute resolution has been
carried out in Asia since the fourth century BC as a conciliatory practice focused in
maintaining the relationship between parties.

Confucian Philosophy
In the Far East, the concepts of resolving disputes by conciliation date back to the times
of Confucius (511-479 BC). The Chinese base their dispute resolution processes “...on
the Confucian view that the optimum resolution of a dispute should be attained by moral
persuasion and compromise instead of by sovereign coercion” (Chau, 1992). According
to Li (1970, cited by Chan E., 1997), the Chinese preference is to encourage people to
settle disputes amicably.
This philosophical approach is based in a common Asian tradition to seek “harmonious”
solutions that help maintain relationships over time. Judges and mediators are considered
the same in Asia, for what parties seek is a well-known go-between that is also familiar
with their disagreement. The idea is that the third party helps them bring an end to their
dispute while assisting in reaching a mutually agreeable solution. What they seek is a
solution with as little “loss of face” as possible. In Japan, the existence of a dispute may
itself cause a “loss of face,” and having to submit a dispute to a third party may represent
some sense of failure.
Under Confucius’ traditions, litigation is viewed as the last resource. Consider that China
has over 10 million mediators versus only 15,000 lawyers. Local People’s Mediation
Committees, with three to 10 members, mediate 7 million cases a year and they reach
agreement in 90% of the cases (Pierce, 1994). Discussion and compromise are always
preferred, and all adjudication procedures where a third party decides the matter are
considered adversarial in nature. In contrast, conciliation and mediation are always
favored, as informal, person-oriented approaches, unbound by the strict rules of highly
structured procedures. It is less important in Confucianism to be accurate in finding the
truth. What this philosophy truly considers important is to determine a common ground in
which parties can negotiate a settlement without ever disrupting their “harmonious
relationship” (Scott, 1995).

2.2 MODIFICATION OF THE TWO-STEP ADR APPROACH


The previous sections have shown how the two initial steps in the traditional dispute
resolution ladder have reached a point in which they no longer can successfully cope with
the growing needs and challenges of today’s construction environment. The industry has
been forced to look beyond the architects’ determinations and binding arbitration as the
sole mechanisms to solve professional and commercial disputes. The new instruments,
paradoxically, have tried to incorporate the lessons of ancient Asian philosophies, in a

DRAFT 2/4/2017 2:32:00 PM 23


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

quest for improving their current effectiveness and ultimately their bottom lines when
dealing with conflict.
As described, the traditional dispute resolution ladder has experienced some problems as
the size and complexity of projects expanded. This section presents three examples that
illustrate how the ladder has been gaining “steps” as parties incorporate new ADR
techniques to bridge the gap between the design professional’s initial determination and
the binding arbitration stage.

2.2.1 FIDIC’S ADR CONTRACT CONDITIONS

The most frequently used form of international contract conditions for civil engineering
and construction projects comes from the Federation Internationale de Ingenieurs-
Conseils (FIDIC) - the Conditions of Contract for Works of Civil Engineering
Construction), also known as the “Red Book.” Until recently, this standard contract was
drafted under the assumption that construction claims should be set aside during the
work, and then resolved at the end of the project. Arbitration was the only alternative to
litigation if parties failed to agree with the architects/engineer’s determination 3, but it
could only be initiated after final completion of the project. Clearly, what the FIDIC was
using was the two-step traditional DRL described in Section 2.1.
The first edition of the Red Book in 1957 included a dispute resolution clause stating that
“...the arbitrator/s shall not enter on the reference [dispute] until after the completion or
alleged completion of the works unless the parties otherwise agree.”(FIDIC, 1957)
Claims, and the process to resolve them, were considered a distraction to the
construction, confirming the notion that the job came first, and that claims should be put
aside until the end of the project. More recently, however, there has been a trend to
address and resolve claims as early as possible. Molineaux (1995) suggests two important
reasons behind this new approach from the viewpoint of the owner:
1) “To avoid or lessen the origin of the claim, by taking the necessary actions in
response to the problem; for example, a design change to meet new subsurface
conditions; and
2) To monitor the alleged extra costs being incurred by the contractor for future
review and possible negotiation.”
Additionally, an early treatment of claims also means that owners can attempt to isolate
troubles from the rest of the project, which enhances flexibility and reduces their effect
on other activities. The 1987 Edition of the FIDIC contract had already taken into
consideration these developments, and addressed the need to resolve disputes during the
execution of the works by means other than arbitration. This Edition included a
requirement to attempt an “Amicable Settlement” before arbitration could actually start.
Clause 67.2 of the Red Book stated (FIDIC, 1987):
“Amicable Settlement – Where notice of intention to commence arbitration’s to
a dispute has been given in accordance with Sub-Clause 67.1, arbitration of
such dispute shall not be commenced unless an attempt has first been made by
the parties to settle such dispute amicably. Provided that, unless the parties
otherwise agree, arbitration may be commenced on or after the fifty-sixth day
after the day on which the notice of intention to commence arbitration of such
dispute was given, whether or not any attempt at amicable settlement thereof
has been made”
This clause is an encouragement for parties to resolve the dispute without recurring to
arbitration by making them wait considerably before arbitration can begin. This passage

24
EVOLUTION OF DART

is also an acknowledgment that there are other mechanisms available to deal with
problems between parties to a contract.
In terms of promoting early resolution of claims, the FIDIC reinforces the claims’
notification process. In the 1987 Red Book Edition, contractors are required to notify the
engineer within 28 days after the event giving rise to the claim is first noticed. From that
date forward, the contractor is required to keep updated files on all costs associated with
the claim, and to make the material available to the engineer for review, without requiring
from the engineer an acceptance of any liability. Failure to comply with these
requirements automatically reduces the amount the contractor can claim at a later date.
From his role of Chairman of the FIDIC Committee of Conditions of Contract, Seppala
(1991) identified three major advantages of the Federation’s procedure just described:
1) “The engineer can investigate the facts of a claim and its financial
consequences while the evidence is still fresh and available;
2) The owner receives a prompt notice of possible adjustment to the contract price;
and,
3) The earlier claims are identified, the sooner they may be resolved.”
The system makes both parties responsible, and creates an obligation to deal with
disputes in a timely and professional manner. In short, by preventing arbitration and
encouraging early claim notification the FIDIC has both introduced an ADR system and
promoted an expedite process that saves time and resources to the parties involved. Yet, a
point that is still missing is clause 67.2’s failure to describe what parties should do during
the waiting period before arbitration. Not clearing the article terms might only serve to
delay arbitration for almost two months.

2.2.2 WORLD BANK’S ADR CONTRACT CONDITIONS

Whereas the FIDIC has left open the possibility of using some form of alternative to
arbitration after the architect/engineer’s decision is rejected, the World Bank has gone a
step further and has actually recommended the use of a Dispute Review Board (DRB) as
the method to resolve construction disputes. In its May 1993 Standard Bidding
Documents, the World Bank suggests the following:
“In case of major projects, IBRD [World Bank] encourages employers to
consider introducing a dispute review board (DRB) into the contractual
settlement of dispute procedure ... Such a DRB could either replace the engineer
under Clause 67... or it could review the decisions made by the Engineer” (cited
by Molineaux, 1995).
For smaller contracts, the World Bank has also introduced the concept of an
“adjudicator” to function as the first step in the resolution of disputes:
“The adjudicator is the person appointed jointly by the employer and the
contractor to resolve disputes in the first instance. The adjudicator is …
required to provide a decision within 28 days. If no party submits the
adjudicator’s decision to arbitration within 28[days] of receipt the decision is
considered final and binding” (Molineaux, 1995).
These two conditions represent a significant improvement over the standard FIDIC
contracts in relation to dispute resolution procedures. Not only has the World Bank
recognized the existence of alternatives to arbitration - by recommending two options
depending on the size of the project, but also it has replaced the role of the designer in
small contracts as the first-instance resolver of disputes. In large contracts, the World

DRAFT 2/4/2017 2:32:00 PM 25


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Bank has incorporated a dispute review board as a new step in the resolution process
between the designer and arbitration stages.

2.2.3 CHEK LAP KOK AIRPORT’S DISPUTE RESOLUTION SYSTEM

As a final example of the modified two-step DRL approach, this section presents an
actual case from Hong Kong. In this Asian country, construction contracts with the
government usually include a three-step dispute resolution process shown in Figure 6.
Just like in the two-step process, the design professional is responsible for the first
determination as to any disputes regarding the contract, and arbitration is the final
binding mechanism for settlement. However, a Mediation stage is added as an in-between
step, if the parties disagree with the design professional’s decision. In this case, mediation
is not mandatory, and the opposing party can refuse to participate in the mediation
procedures.
In the event mediation fails or one of the parties refuses to participate, the Hong Kong
government establishes that the dispute can be referred to arbitration, but only after the
conclusion of the project. In other words, the contract makes the completion of the works
a condition precedent to any final solution of disputes that may occur during construction,
just like the 1957 Edition of the FIDIC contract reviewed in Section 2.2.1.

1 2 3
ARCHITECT/ MEDIATION ARBITRATION
ENGINEER or
Supervising
Officer

Parties have Parties can request arbitration


28 days to 90 days after failing to agree
refer the through mediation, but not
matter to before the job is complete
mediation

Figure 6 - Standard Dispute Resolution Process for Government Construction Contracts


in Hong Kong

For the construction of the Chek Lap Kok Airport, the government developed a specific,
modified dispute resolution system based on the three-step process described above.
During the negotiations between the Airport authority and the local contractors, the local
contractors exerted a great deal of pressure for a faster and more efficient dispute
resolution procedure than the one shown in Figure 6. The biggest hurdle in the
negotiations was a condition that “arbitration was only possible after the project’s
completion,” and the contractor insisted on a mechanism that could address the large
number of disagreements expected in a project of such complexity. The resulting dispute
resolution process is shown in Figure 7.
Two methods for dispute resolution were incorporated into the contract to satisfy
contractor’s demands regarding dispute resolution. Figure 7 shows these two methods,
which have been labeled here as A and B to help the reader.

26
EVOLUTION OF DART

Under method A, parties submitted to the engineer representing the Airport Authority a
Notice of Dispute as the first instance for resolution. Mediation followed if the
Engineer’s determination was not acceptable to one of the parties. Opposed to the
standard dispute resolution procedure (Figure 6), in this case mediation was mandatory
and had a time limit of 42 days before the parties escalated the dispute to the adjudication
stage. In addition, the Hong Kong government tightened this modified system by
requiring from the mediator 1) a final report on the findings 4, and 2) specific
recommendations to the parties involved.

Parties have 28 Parties have 42


days to refer the days to resolve Adjudicator has 28 days to
matter to the matter issue a final and binding
mediation through determination from the time
mediation mediation fails

1 2 3
ARCHITECT/ MEDIATION
ENGINEER or Mediator issues ADJUDICATION
A Supervising final report
Officer

If either party objects to the


decision of the adjudicator,
they can submit the dispute
to arbitration, subject to the
completion of the work 4
DISPUTE ARBITRATION
B REVIEW Completion of the
GROUP works is required

Figure 7 - Dispute Resolution Process for Hong Kong’s Airport Core Program

If mediation failed, or one of the parties disagreed with the report, the matter was
submitted to an Adjudicator for binding determination. According to Fenn et al. (1998),
the selection of this adjudicator was handled through the Hong Kong International
Arbitration Center (HKIAC) and involved the following steps:
“Parties submitted to the HKIAC at least three names of people willing and able to
act as adjudicators;
The HKIAC combined these lists and returns them to the parties;
Each party ordered the combined list based on their preference, and
The HKIAC then appointed the individual with the highest rating.”
If parties failed to select an adjudicator the HKIAC could appoint one of its choices, from
the list, or from its registered adjudicators (arbitrators). Once appointed, the adjudicator
had the widest discretion permitted by the law to select the procedure and to ensure a just,
expeditious, and economical resolution of the dispute within 28 days. This adjudicator
acted as a Single Arbitrator (Section 8.3.1), and was required to provide a written
statement identifying the dispute, the reasons for the decision, and any admissions made

DRAFT 2/4/2017 2:32:00 PM 27


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

by the parties during the proceedings. The awards of the adjudicator were binding, but
could be appealed in arbitration after the completion of the project (Fenn et al., 1998).
Under method B (Figure 8), the contract incorporated the authority of a Dispute Review
Group (DRG), consisting of seven individuals. The DRG visited the construction site
once every three months and spent there four and a half days reviewing the project and
attending Quarterly Meetings between the contracting authority and the different
contractors in order to maintain current knowledge of the status of the works.

The Convenor, Chairman


Retired High Court Judge Legal Background
Government
Representation

Arbitration Civil Quantity Electrical/


Expert from the Engineer Surveyor from Mechanical
People’s from the UK the UK Engineer from
Republic of the UK
China

Arbitration Civil
Expert from Engineer
the People’s from the UK
Republic of
China

Technical Expertise

Figure 8 - Composition of the Dispute Review Group for the Chek Lap Kok Airport
Project, Hong Kong

An interesting aspect of the DRG is how it was organized in terms of expertise and
representation of each party in the project. Although modeled as a Dispute Review Board
(described in Section 6.3) in this case the contractors had no direct representation. Thus,
DRG was more like an Agency Review Board (Section 6.2) in which the Convenor
provided the legal background to any review and/or decision by the DRG. Arbitrators
from China represented the government, and at the same time were the experts in
arbitration procedures. The technical expertise to review construction and design issues
was provided by professionals from the UK. Although it is unclear how one method was
selected over the other for each claim, it appears that the larger contracts (i.e., Airport
Terminal Building) used the DRG, or method B.
Under both methods, A and B, arbitration was left as the final stage to resolve disputes, to
be used only after the project was completed. Arbitration awards in Hong Kong are
usually in writing, are signed by the arbitrator, and in most cases provide the reasons for
the award. Arbitration awards are final and can only be appealed when an issue of law is
in question. 5 The awards are enforceable in the same manner as a judgment.

28
EVOLUTION OF DART

For the construction of the Chek Lap Kok Airport contractors were able to modify the
standard dispute resolution clauses of the Government of Hong Kong and develop two
alternative approaches to address disputes more efficiently. By combining non-binding
techniques, like Mediation and an Owner Review Board, with more binding
determinations they were able to expedite processes and better document the project.
However, this case did not introduce a change in the requirement to finish the project
before being able to submit a claim to final arbitration.
To sum up, the examples presented above have shown how the traditional two-step DRL
(Section 2.1) has been modified with new techniques (i.e., Mediation, Dispute Review
Board, and Adjudication) added in between the designer’s determination and arbitration.
The World Bank contract and the Government of Hong Kong have actually replaced the
design professional by introducing the figure of a Standing Neutral to provide the initial
evaluation and recommendation on the conflict matter. The following section will present
the evolution of the two-step ADR model, portraying its expansion to include a number
of new ‘steps’ that offer the parties increased flexibility, reduced costs, and a better
chance to preserve their relationship.

2.3 EVOLUTION OF THE PRESENT ADR METHODOLOGIES


As new methodologies have been developed and implemented, the number of
approaches, techniques, and philosophies to deal with disputes in construction has grown
significantly, especially during the past several years. Moreover, because of the
uniqueness of each project and the differences in international practices, project teams to
suit their specific requirements, creating new and innovative approaches to dispute
resolution, constantly modify existing models. According to Groton (1997), “ ... there
has been a veritable explosion in the development and use of new dispute resolution
techniques, particularly techniques for resolving disputes at the job site during the course
of construction.”

2.3.1 DATA SUPPORTING THE EVOLUTION OF ADR

Since the 1976 conference of the American Bar Association – known as the Pound
Conference, the growth in the use of ADR in the American court system has been
exponential. While in 1980 only 18 states had some type of ADR program as part of their
court system (Court-Annexed procedures), by 1990 all 50 states and the District of
Columbia had incorporated a program, and by 1993 more than 1,200 court-related ADR
programs were in place (Ide, 1993). This growth of ADR in the US court system has been
fueled by the success of Court-Annexed procedures in the early resolution of disputes.
For example, a mandatory ADR program 6 carried out by the Commercial Division of the
New York County Supreme Court achieved settlements in 52% of the cases, and
contributed to the resolution of the dispute in another 16% of the cases (Meade, 1997). In
other words, the ADR program positively affected 68% of the disputes in this Court.
Further use of ADR in the US is promoted by the Dispute Resolution Act of 1998, which
actually instructs Federal district courts to require all litigants in civil cases to consider
the use of alternatives to litigation. According to this bill, courts can direct parties to use
ADR at any point during the legal procedures, in an effort to expedite the resolution of
the matter and allow greater flexibility. The parties can now resort to ADR during
litigation, without giving up any advances made at the court level or losing their right to
continue with the court proceeding if ADR fails.

DRAFT 2/4/2017 2:32:00 PM 29


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

At the State level, for example, the Governor of New Jersey signed a bill during the first
quarter of 1998 that requires disputes in public construction projects to be submitted to an
alternative dispute resolution procedure before court litigation (DRT, 4/1998). The bill
recommends various specific ADR options such as mediation (Section 7.2), non-binding
arbitration (Section 7.4), or binding arbitration (Section 8.3). In this document, not only
has the government of New Jersey identified construction as a major source of civil
litigation, but also it has recognized the fact that DART can improve the resolution
process, increasing the chances for a faster, more efficient settlement of disputes with less
court appearances.
Two surveys by the American Bar Association further confirm the increasing use of
DART in construction. The first one, conducted as part of the ABA 1990-91 Forum on
the Construction Industry found arbitration to be the most frequently used form of ADR
in disputes with 81.5% of those surveyed having experience with the procedure
(Stipanowich et al., 1992). Many participants also reported the use of mediation, with
64.2% of the respondents having some experience with it, and 58.3% having mediated a
dispute in the last two years. In terms of the success of DART, the results of this survey
showed that 57.4% of cases resulted in full settlement, and in 8.4% of the cases a partial
settlement resulted. These results are similar to those obtained by the New York Supreme
Court as reported by Meade (1997) above. The second survey, conducted in 1993 by the
ABA Public Contract Law of the Alternative Dispute Resolution Committee, further
confirmed the increasing use of DART to resolve construction disputes. Arbitration was
still the most familiar method of dispute resolution among those surveyed, but mediation
was now rated as the most favorable approach (Stipanowich, 1994).
A 1994 study by the US National Transportation Board on dispute resolution methods
found that 22% of State transportation departments had incorporated dispute review
boards (Section 6.3), 63% used partnering (Chapter 4), 70% “empowered” field
personnel to handle disputes (Section 5.5), and 100% were willing to negotiate (Chapter
5) with the contractor (Civil Engineering, 1994). In April 1996, thirty-three of the most
influential US organizations and federal agencies in the construction industry signed a
declaration calling for the end of litigation in project disputes (ENR, 4/22/1996).
The numbers demonstrate how in the United States the use and popularity of ADR
extends beyond the field of public contracts and construction. An additional survey
conducted in 1997 by Price Waterhouse, Cornell University, and The Foundation for the
Prevention and Early Resolution of Conflict (PERC), revealed that 528 of the largest
corporations in the United States reported extensive use of ADR (Lipsky et al., 1997).
The results, summarized in Table 6, reflect the opinion of chief litigates, deputy counsels,
and corporate counsels of the corporations responding to the survey.
Table 6 - Summary of Results of Survey on the Use of ADR (Lipsky et al., 1997)

Percent of Respondents Percent of Respondents who


ADR METHOD who had experience with expect to use this method of
this method of ADR ADR in the future
Mediation (Section 7.2) 88% 84%
Arbitration (Section 8.3) 79% 69%
Med/Arb (Section 8.1) 41% Data not available
Mini-trials (Section 7.6) 23% Data not available
Fact Finding (Section 7.5) 21% Data not available
Peer Review (Section 6.1) 11% Data not available

30
EVOLUTION OF DART

As shown above, mediation was the most favored ADR approach in this sample of
Corporate America. According to the answers provided, 88% of these corporations had
used mediation to resolve disputes in a number of fields (i.e., labor relations, employee
termination, drug testing, and lawsuits brought about by customers). Arbitration was the
second most favored ADR technique, with 79% claiming experience with this method.
Interestingly enough, the technique that combines mediation and arbitration (Med/Arb)
was the third most frequently used approach. Med/Arb (Section 8.1) has encountered
some resistance because of the two roles played by the third-party neutral and the type of
information that can and should be disclosed during mediation without affecting the
possible arbitration process.
In terms of the expected reduction in the use of Mediation and Arbitration shown in
Table 6, the survey attributes it to concerns declared by the respondents as to the
qualifications of the third parties involved in the procedures. Almost half expressed “...a
lack of confidence in the arbitrator” (Lipsky et al., 1997) and close to 30 say there are
not enough qualified arbitrators. With regards to mediators, 30% of responses raised the
issue of lack of confidence and 20% the problem with qualifications and experience. 7
The higher concerns expressed with regards to the arbitrators can be explained by the fact
that their decisions are final and binding, while the mediator does not even offer a
solution proposal.
The survey also revealed some other interesting aspects of ADR in American
corporations:
• Smaller companies were found to be more inclined to follow adjudicative
procedures. They make a very limited use of ADR.
• The selection of ADR methods was found to be related to the type of dispute
(DRT, 1/1999):
− Mediation is preferred to arbitration in all types of disputes except
international cases, where 50% of the respondents said they would use
arbitration, while only 43% would attempt mediation.
− In personal injury disputes, 60% have used mediation, but only a third have
used arbitration.
− In product liability cases, 40% have used mediation, versus only 24% that
have used arbitration.
− In long-standing relationships and contracts, 92% of the cases where
mediated.
These findings show how ADR provides a flexibility to select how disputes will be
addressed and resolved that is not found in the court system. Corporations are selecting
different ADR methods for each type of dispute, as ADR has allowed them to tailor their
approach to each specific case.
In response to this evolution of ADR methods, the construction industry has incorporated
to the traditional DRL numerous methodologies to avoid conflict and to resolve disputes
more creatively and efficiently. These changes have contributed to the creation of a
construction DART model. The authors of this book have identified two models of
conceptualization of DART that are presented in the following section.

2.3.2 TWO CONCEPTUALIZATION MODELS OF DART

This section provides a model for the organization and implementation of Dispute
Avoidance and Resolution Techniques (DART). Two different schemes for the
organization of construction DART are reviewed, and the Dispute Resolution Ladder

DRAFT 2/4/2017 2:32:00 PM 31


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

(DRL) has been chosen and implemented in the following chapters for all the techniques
found by this book. This selection is based on two features of this model; first, the DRL
model lends itself to practical applications and second, it gives a significant importance to
dispute prevention techniques by placing them as the first step in any successful system
of dispute resolution in construction.

Differentiation between conflicts and disputes


A first model of organization DART is proposed by Fenn et al. (1997) based on a
differentiation between conflicts and disputes in construction. You must first
acknowledge the construction industry exists within an adversarial society and conflict is
eminent. Fenn et al. (1997) argue that since it always will exist, conflict can be managed
as any other variable in construction. The goal is to manage the differences/conflicts
between parties to the point of preventing them from leading to a dispute. The rationale is
that organizations can learn from conflict, whereas disputes are not manageable by the
parties, and they require some form of final determination. By needing this determination
to resolve the dispute, this part of the process lends itself to be aided by the intervention
of a third-party.
Moore (1989, cited by Fenn et al., 1997) proposed a “conflict continuum,” on which the
“construction industry conflict continuum” is based and presented in Figure 9.

Dispute Resolution

Conflict Management

Conflict Informal Negotiation Arbitration Other


Avoidance Discussion ADR Litigation Action

Figure 9 - Construction Industry Conflict Continuum (Fenn et al., 1997)

In this continuum, a taxonomy that differentiates techniques is proposed based on their


usage to manage conflict or resolve disputes, also discriminating between non-binding
and binding ADR methods (Figure 10). This classification introduces means to manage
Organizational Issues and Project Uncertainty (Section 1.1) without delay, as these
features of construction can easily deteriorate and their negative effects can be
exponential if conflicts are not timely addressed and they evolve into disputes.

32
EVOLUTION OF DART

Conflict Management

Non-Binding
Dispute Review Boards
Dispute Review Advisors
Negotiation
Quality Matters
Total Quality Management
Coordinated Project Information
Quality Assurance
Procurement Systems
Partnering

Dispute Resolution

Non-Binding Binding
Conciliation Adjudication
Executive Tribunal Arbitration
Mediation Expert Determination
Litigation
Negotiation

Figure 10 - Proposed Taxonomy of ADR Techniques (Fenn et al., 1997).

These notions are useful in the sense that they present an organized view of the different
steps involved in ADR and the various alternatives available. However, there is a
different approach that will prove to be eloquent in explaining the steps to follow.

Six-step DRL: The stepped process of dispute resolution


This second categorization of DART uses six distinct stages in the evolution of
construction disputes. The stepped approach proposed by Findley (1997) is shown
graphically in Figure 11.
This theory recognizes conflict as an inherent part of construction projects. Based on that,
it proposes early mechanisms to prevent the escalation to a dispute. The underlying idea
is that the lower stages will facilitate the achievement of mutually beneficial solutions,
for as disagreements climb the stepladder; parties start to lose control over the eventual
outcome.

DRAFT 2/4/2017 2:32:00 PM 33


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

LITIGATION

BINDING

NONBIDING

STANDING NEUTRAL ↑ Increased expenses and


hostility.
↑ Less alternative mechanisms to
solve the dispute
NEGOTIATION ↑ Less participation of the team
directly involved in the project.
↑ Reduced flexibility and less
PREVENTION control over final outcome.

Figure 11 – Dispute Resolution Ladder (Findley, 1997)

Usually, at the middle stages, (Standing Neutral and Non-Binding) third parties are
brought into the process and claims begin to depart from the job site level. The goal of
external participants is to help disagreements return to a lower stage in the ladder, by
identifying the real issues in dispute, finding a common ground between parties, helping
in the analysis of technical problems, and/or assisting parties improve communication.
Finally, as the parties get to the upper stages (i.e., binding and litigation), there is
decreased participation of those who are really involved in the project, and it becomes
less likely to invent alternative mechanisms to amicably solve the dispute, and the
process starts to see a dramatic increase in costs and hostility.
The six-step DRL is flexible enough that it allows the development of project-specific
DRL, something found in the two contracts of the FIDIC and the World Bank, where the
escalation did not include all the steps and allowed the parties to attempt an ADR
solution. The literature review also finds international applications of DART, with
interesting variations depending on culture.
An example of the diversities in DRL is provided by the Canadian Construction
Document Committee contract of 1994 (CCDC 2); a standard form of fixed-price terms
and conditions designed for projects with three basic participants: the owner, the design
or engineering consultant, and the contractor (i.e., Design-Bid-Build). The CCDC 2
provides a clear application of the modern DRL, recognizing some of the stages of the
process and highlighting the benefits and challenges of each one (Figure 12). In terms of
dispute resolution, the CCDC 2 contains specific provisions that make DART an integral
part of the contract.

34
EVOLUTION OF DART

LITIGATION

BINDING ARBITRATION

MEDIATION

NEGOTIATIONS

DESIGNER/ENGINEER
DETERMINATION

Figure 12 - Dispute Resolution “Ladder” established in the CCDC 2 Contract

According to the CCDC 2 contract, disputes arising from interpretations of the


documents or from the execution of the works are to be referred for determination to the
design professional (consultant). The consultant then has a limited period of time to issue
a resolution regarding the dispute or disagreement. Negotiations between the disputants
are mandated if the decision of the designer/engineer is not acceptable to either party. As
part of this stage, the CCDC 2 requires the parties to “...provide, without prejudice,
disclosure of relevant facts, information and documents to facilitate the negotiations”
(Bristow, 1998), delineating the requirement for “Honest” negotiations as discussed in
Chapter 5.
As the CCDC 2 escalates, when negotiations fail to provide a settlement within 10 days
after they are formally initiated, either party must request the presence of the Mediator.
Mediation is a mandatory step before any other binding approach can be initiated, and the
parties must mutually select and appoint a mediator within 30 days after the contract is
awarded. Disputes must be resolved 10 working days after the mediator is brought. The
procedures can be extended by mutual agreement if the parties consider that progress is
being made through mediation. If the parties fail to mediate a solution, they can request a
confidential written opinion from the mediator, similar to a conciliation report.
This contract form is an important example of the use of different ADR mechanisms to
develop a Dispute Resolution Ladder tailored to the job requirements and assists the
disputing parties “reach a joint resolution of their dispute during the course of
construction so that the valuable business relationships can be preserved” (Groton,
1997). The CCDC 2 offers a lot of flexibility to the parties during the first three steps of
the ladder, but then sets strict time limits to encourage the parties to address the disputes
and approach a resolution. As the disputes moves up the ladder, the CCDC 2 becomes
less flexible and the rules governing the procedures are “explicit and far more
comprehensive” (Bristow, 1998).

2.4 THE STATE OF THE LEGAL CONSTRUCTION ARENA


In a report entitled “Access to Justice,” Lord Woolf (1996) concluded that the judicial
system in the United Kingdom had reached a level of over-saturation. He called for a
significant change in the litigation culture that dominates the legal scene in that country.
Woolf summarized the problems of the British judicial system as follows:

DRAFT 2/4/2017 2:32:00 PM 35


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

• “It is too expensive, in that costs often exceed the value of the claim.
• It is too slow.
• There is a lack of equality between the powerful wealthy litigant and the under-
resourced litigant.
• It is difficult to forecast both the cost and the length of litigation.
• It is incomprehensible to many litigants.
• It is too adversarial, and cases tend to be run by the parties with the rules of
court often ignored.” (Woolf, 1996)
These problems associated to costs, delays, uncertainty of outcome, complicated rules,
and lack of control over the process are affecting the way different industries are dealing
and solving their disputes without turning to the judicial system. In the specific field of
construction, Gould et al. (1998) have identified three factors that have influenced the
traditional dispute resolution procedures of this industry in the UK, moving it away from
litigation:
1) General dissatisfaction with arbitration.
2) An increase in the number of conflicts and disputes within the construction
industry.
3) International influence reflected in the worldwide movement towards alternative
dispute resolution methods.
These challenges faced by the construction industry of the UK have been equally found
as challenges in the United States. In a 1998 speech on the future of the construction
industry, Henry Michel, chairman emeritus of Parsons Brinckerhoff Inc., described the
current state of the American building industry as follows (Michel, 1995):
“We are members of the largest productive industry in this country and in the
world, and we are members of an ailing industry, a troubled industry. Consider
the following:
• The construction industry’s share of the gross domestic product [in the US] has
declined 20% in the past 20 years.
• Construction costs [in the US] have increased 60% more than inflation in the
past 10 years.
• We account [in the US] for 26% of the nation’s fatal accidents.
• Litigation expenditures [in the US] are increasing at 10% per year [for the past
ten yeas].” 8
Productivity, innovation, cost savings, safety, and litigation expenses are critical areas for
the future of the construction industry. It is in these areas that the industry must invest the
most to advance successfully into the next century 9. In the United States alone, $60
billion are spent every year on lawsuits, of which the construction industry accounts for
nearly $5 billion. Michel points out that for every $1 billion saved on litigation in
construction the industry could generate 40,000 new jobs, with the direct benefit of
reducing legal expenses for all parties.
The fact that litigation expenditures continue to increase year after year is astounding.
This book aims at providing information to the reader on ways in which these expenses
could be reduced. The problem of excessive litigation costs is reiterated in a paper written
by Bristow (1998), where an estimate of the legal costs associated with a hypothetical
lawsuit between a contractor and an owner are calculated and compared to the initial
claim amount. They included in their cost analysis, three basic items based on the
Canadian legal system: lawyer’s fees, trial costs (i.e., filing fees and expert witnesses),

36
EVOLUTION OF DART

and opportunity costs (i.e., time spent by key personnel in the litigation process). The
results of these calculations show that the cost of the procedure for the contractor
surpasses by almost 100% the original amount being claimed. The authors conclude that
the industry is “…being hampered by the tremendous amount of resources being utilized
in the litigation of claims.”
This exercise shows how the judicial system is no longer the most suitable and cost
effective way to resolve construction disputes. Fueled by this reality, together with the
fact that projects have become more complex and competition has increased, the
construction industry has been forced to develop and experiment with alternatives to
litigation in order to find cheaper and more effective ways to solve disputes. Thus, new
approaches have been designed to overcome the rigid and adversarial attitudes and
contract forms normally used in construction. These evolved to prevent the development
of conflicts during the execution of the project, and to help companies forge longer
lasting relationships with clients, designers, as well as subcontractors, while still solving
their disagreements. These new and innovative approaches and techniques are known as
Dispute Avoidance and Resolution Techniques (DART). 10
The changes in the construction industry are going beyond the application of an
alternative technique to court litigation (i.e., Mini-Trial or Arbitration). While the 80’s
saw the construction industry “...turned on itself – [as] each part of the construction
“team” started indulging in a seemingly unending orgy of risk-shifting, finger pointing,
and costly litigation” (ENR, 7/11/1994), the 1990s saw a revolution in the field of
construction dispute resolution, as the construction “team” has understood the negative
long-term effects of the approaches of the past decade. The team approach is being
redesigned, going from an adversarial system towards a collaborative environment in
which the limits are defined, but communication flows without unnecessary barriers.
Many project teams have developed radically new philosophies towards achieving the
project goals such as Partnering, Total Quality Management, and Risk Sharing. Some
industry experts claim that the industry is going back to the “old fashion way of doing
business”; when quality, service, and collaboration among parties were the norm, and
disagreements “...were settled on the jobsite at an informal meeting between the resident
engineer and the contractor on the basis of a handshake.” (Treacy, 1995).
In the international arena, the need to improve communication and limit the chances of
litigation is more evident. Large engineering endeavors are bringing together companies
with diverse cultural backgrounds, legal systems, labor laws, objectives, interests,
contractual agreements, competitive conditions, and priorities. Complicated
communication arrangements, changing conditions, and varying requirements are now
part of most large jobs. Therefore, in order to avoid having this diversity result in
disagreements, channels of communication must be developed, and a collaborative
environment for exchanges of information implemented.
The construction industry is suffering from an acute disposition to conflict and litigation.
Many contractors even take the strategy of bidding low and hope to make up their losses
in claims. This strategy makes disputes appear inevitable. Litigation expenses have
become a significant cost item for many projects, affecting productivity and damaging
business relationships. Professor Justin Sweet, of the University of California at
Berkeley, summarized this situation by saying:
“... a dispute-prone process such as construction will have the propensity to call
on the legal system to enforce contracts or obtain compensation for losses.
Participants ... must do all they can to avoid disputes, to seek to settle those that
do develop, and to be aware of the role law plays in the process.” (Sweet, 1994)
Based on this reality the construction industry has developed, during the past fifteen
years, a number of different mechanisms and methodologies to prevent, manage, and

DRAFT 2/4/2017 2:32:00 PM 37


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

resolve disputes without recurring to litigation. Furthermore, parties involved in


construction are continually experimenting with new ones to further mitigate the losses
implied in legal battles.

2.5 SUMMARY
Conflicts have existed as long as human beings have interacted with each other.
Consequently, for centuries, civilizations have struggled to develop different ways to
manage and resolve disputes among its members and with other cultures. For some,
conflict resolution meant the difference between peace and war, for others mediation and
conciliation have simply become a way of living. A common feature in these approaches
to dispute resolution has been a tendency towards a dichotic and polarized way of
understanding the possible outcomes. The two alternatives have been an amicable
settlement or an openly adversarial approach that usually ended the relationship among
parties.
From the formalization of ancestral forms of dispute resolution, evolved the traditional
two-step resolution ladder, where determination by the design professional and binding
arbitration are the two poles of the model. However, as construction projects became
larger, multi-cultural, and more complex, the two-step Dispute Resolution Ladder (DRL)
has become a limited tool. The traditional model is often unable to meet the needs of the
project participants in an effective, timely and cost-efficient manner, without necessarily
jeopardizing the relationship between the parties involved.
Stemming from the limitations of the traditional two-step model, new approaches have
emerged trying to introduce alternative techniques to be used throughout the process of
conflict management. First, this chapter reviewed Fenn et al.’s ‘conflict continuum’ and
the way it served as a useful tool to divide multiple binding and non-binding strategies
across this spectrum. Second, the Dispute Resolution Ladder proposed by Findley (1997)
was chosen as the guide for the chapters to follow. The selection of this model to
organize the dispute avoidance and resolution techniques found by this book was based
on two characteristics of this model. First, this model has the advantage of lending itself
to practical applications, as clearly shown in the CCDC 2 contract. Second, the DRL
emphasizes the important role of prevention techniques in dispute resolution process for
construction projects. This prevention stage in the DRL is the focus of Chapter 3, where a
series of techniques designed to mitigate some of the common sources of disputes
discussed in this chapter are introduced together with some examples of their
implementations.

2.6 POINTS FOR DISCUSSION


2.1 The construction industry has been labeled as “inherently inefficient.” What are the
reasons for this statement? How does this relate to conflicts, disputes and claims in
the industry?
2.2 The original two-step process (Section 2.1) assumes that the project is delivered
under the traditional design-bid-build procurement model. How would this change
for other delivery systems such as design-build, design-build-operate-transfer and
turnkey?
2.3 Old England and Confucian Philosophy (Section 2.1.2) incorporate the premise that
conflict was frowned upon in society. In England, if a party violated a non-binding
decision, the violator was publicly shunned. In China, if a conflict went to litigation

38
EVOLUTION OF DART

it implies a “loss of face.” How much influence does a contractor’s reputation have
in today’s society? How does this perception vary from private and public owners?
What about the owner’s reputation?
2.4 What role should professional organizations play in developing DART?
2.5 What role should large bureaucratic owners such as the World Bank (Section 2.2.2),
the Hong Kong government (Section 2.2.3), or the US Federal government play in
developing DART?
2.6 In the United States, conflicts arise in bidding situations when there is not
transparency in the bidding process. Can frame contracts, as described in Section
3.4.5, be effectively used in government procurements and still be fair? On what
basis should you select the contractor if a price is not predetermined, according to
the frame contracts? Are there other ways to incorporate objective alignment other
than frame contracts?
2.7 The revision of the Red Book (Section 2.2.1) aimed at addressing claims earlier in
the construction process. What are some advantages/disadvantages of addressing
conflicts during the process and after the process?
2.8 How important is it for the mediators/arbitrators/judges to have an
engineering/construction background? Can a reasonable and fair judgment be
reached if they do not have this technical expertise? How much credibility will their
decision carry?
2.9 Findley (1997) breaks down the DRL into six steps (Section 2.3.2). Does this
extension from the two-step DRL draw out the process or does it increase the
efficiency of handling claims? At what point are there too many steps in the DRL?
2.10 What are the differences between the CCDC 2 Contract DRL and the DRL in Figure
11 adopted from Findley, 1997 (Section 2.3.2)?

2.7 REFERENCES

[Beresford Hartwell, Beresford Hartwell, Geoffrey M., (1998). The Relevance of


1998] Expertise in Commercial Arbitration. " Arbitration Procedures:
Achieving Efficiency Without Sacrificing Due Process." Last
Update: 22 June. Paris. Downloaded from the web on April 5,
1999 www.ciob.org
[Bristow, 1998] Bristow, David. The New CCDC2: Facilitating Dispute
Resolution of Construction Projects. A paper delivered to the
Canadian Bar Association – Ontario. December, 1998.
[CCDC 2, 1994] Standard Construction Document. CCDC 2: Stipulated Price
Contract. Canadian Construction Documents Committee. June
1994.
[Chau, 1992] Chau, Kwok-Wing, (1992). Resolving Construction Disputes
by Mediation Hong Kong Experience. Journal of Management
in Engineering Vol. 8 (4) pp. 384-393 October, 1992.
[Civil Engineering,
Civil Engineering, (1994). State DOTs Tackle Problem
1994]
Projects. March 19

DRAFT 2/4/2017 2:32:00 PM 39


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

[DRT, 1/1999] Dispute Resolution Times, (1999). New Law Authorizes ADR
Use in District Courts. p. 2. January
[DRT, 4/1998] Dispute Resolution Times, (1998). NJ Law Calls for ADR in
Public Construction Projects. p. 14 April
[ENR, 4/22/1996] Engineering News Record. The First Step is the Hardest. Vol.
236 (16). p. 114. April 22, 1996.
[ENR, 7/11/1994] McManamy, Rob. Industry Pounds Away at Disputes.
Engineering News Record. McGraw-Hill, New York. pp. 24-
27. July 11, 1994.
[Fenn et al., 1997] Fenn, Peter, Lowe, David, and Speck Christopher, (1997).
Conflict and Dispute in Construction. Construction
Management and Economics (1997) 15, p. 513
[Fenn et al., 1998] Fenn, Peter, O’Shea Michael, and Davies Edward (1998).
Dispute Resolution and Conflict Management in Construction
an International Review. E & FN Spon, London, ISBN 0-419-
23700-3
[FIDIC, 1957] FIDIC. Conditions of Contract for Works of Civil Engineering
Construction, First Edition, 1957.
[FIDIC, 1987] FIDIC. Conditions of Contract for Works of Civil Engineering
Construction, Fourth Edition, 1987 (reprinted in 1988 with
editorial amendments and reprinted in 1992 with further
amendments)
[Findley, 1997] Findley, Douglas. Construction Claims Preparation Under
ADR. 1997 AACE International Transactions C&C.01.1-
C&C.01.4. 1997.
[Flood et al., 1993] Flood J. and Caiger A. Lawyers and Arbitration: The
Juridification of Construction Disputes. Modern Law Review.
Vol 56. pp. 412-440. c Blackwell Publishing, 1993. Reprinted
with permission of Blackwell Publishing.
[Goudsmit, 1985] Goudsmit, J. J. Frame Contracts and the Closing of the Eastern
Scheldt. The International Construction Law Review Vol. 2 (2)
pp. 117-127. January 1985.
[Gould, et al.,1998] Gould, Nicholas and Cohen, Michael. ADR: Appropriate
Dispute Resolution in the U.K. Construction Industry. Sweet &
Maxwell, London. Vol. 17. April 1998.
[Groton, 1997] Groton, James. ADR in the Construction Industry. Dispute
Resolution Journal Vol. 52 (3) pp. 48-57, Summer, 1997.
[Ide, 1993] Ide III, William R., (1993). ADR: Giant Step Toward the
Future. Dispute Resolution Journal pp. 20-23, December
[King et al., 1994] King, Henry T., and Le Forestier, Marc A., (1994). Arbitration
in Ancient Greece. Dispute Resolution Journal. pp. 38-46
September
[Li, 1970] Li, V.H. The role of law in communist China. China Quarterly.
No. 44, October-December, pp 66-111.

40
EVOLUTION OF DART

[Lipsky et al., 1997] Lipsky, David B., and Seeber, Ronald, (1997). The Use of ADR
in U.S. Corporations: Executive Summary. Cornell University
School of Industrial and Labor Relations. Downloaded from the
web on April 25, www.irl.conell.edu
[Meade, 1997] Meade, Robert C., (1997). Commercial Division ADR: A
Survey of Participants. New York Law Journal p. 1. October 17
[Michel, 1998] Michel, Henry. The Next 25 Years: The Future of the
Construction Industry. Journal of Management in Engineering.
Pp. 26-28. September/October, 1998..
[Molineaux, 1995] Molineaux, Charles B., (1995). Settlements in International
Construction. Dispute Resolution Journal Vol. 50 (3) pp. 80-85.
Jul-Sep
[Moore, 1989] Moore, C. The Mediation Process. Jossey Bass, San Francisco.
1989.
[Overcash, 1998] Overcash, Allen. The Truth about Partnering. Limitations and
Solutions. Punch List Vol. 21 (2) August, 1998.
[Pierce, 1994] Pierce, Lemoine D., (1994). Mediation Prospers in China.
Dispute Resolution Journal pp.19-21. June
[Scott, 1995] Scott, Donahey M., (1995). Seeking Harmony. Technique
Dispute Resolution Journal. pp. 74-78. April-June
[Seppala, 1991] Seppala, Christopher. Contractor's Claims Under the FIDIC
Civil Engineering Contract, Fourth (1987) Edition II.
International Business Lawyer Vol. 19 (9). Pp. 457-460.
Q49October 1991.
[Stipanowich et al., Stipanowich, Thomas J. and Henderson Douglas, (1992).
1992] Settling Construction Disputes with Mediation, Mini-trial and
Other Processes. The ABA Forum Survey, Construction
Lawyer, April
[Stipanowich, 1994] Stipanowich, Thomas J., (1994). The Quiet Revolution in
Government Contracting: Dispute Avoidance and Resolution.
30 Procurement Lawyer 3
[Stipanowich, 1996] Stipanowich, Thomas J., (1996). Arbitration: Innovation and
Evolution in the United States Construction Industry. Wake
Forest Law Review Vol. 31 (1) pp. 65-182. Spring
[Sweet, 1994] Sweet, Justin. Legal Aspects of Architecture, Engineering and
the Construction Process. 5th ed. St. Paul: West Publishing
Company, 1994.
[Treacy, 1995] Treacy, Thomas B., (1995). Use of ADR in the Construction
Industry. Journal of Management in Engineering Vol. 11 (1) pp.
58-63. January/February, 1995.
[Woolf, 1996] Lord Woolf. Access to Justice: Final Report to the Lord
Chancellor on the civil justice system in England and Wales.
The Lord Chancellor's Department. July, 1996.

DRAFT 2/4/2017 2:32:00 PM 41


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

[Yarn, 1995] Yarn, Douglas Hurt. Commercial Arbitration in Olde England


(602-1968). Dispute Resolution Journal, pp. 68-72, January
1995.

2.8 ENDNOTES

1
Solon’s legacy is the codification of the laws that defined Athens’s democratic
assembly (King et al., 1994).
2
The term “loveday” was used “…because the Quiet and Tranquility that should follow
the ending of the controversy” (Hurt, 1995).
3
Apparently, this has been the general thought among drafters of contracts and
construction law, since in every country reviewed as part of this book, arbitration was
found to be the standard for construction dispute resolution. In a number of these
countries, the arbitral proceeding was found to be contingent upon the completion of the
project.
4
Requiring a report from the mediator is a departure from the neutral facilitator role
normally assigned to this person. The fact that this project was very much under public
scrutiny might be the reason for wanting to have a written document explaining the
recommendations of the mediator.
5
The recent American Arbitration Association has incorporated this feature to the new
construction rules (See Section 8.3).
6
This program includes mediation before a trial date can be scheduled.
7
This problem of qualifications of the third party has been addressed in the 1996 revision
of the American Arbitration Association of the Arbitration Rules for construction
disputes.
8
For example, from 1983 to 1990 the number of construction arbitration cases filed with
the AAA grew from 2,675 to 5,440 (MacManamy, 1994), or approximately at an average
15% per year. From 1994 to 1996, the number of cases filed with the AAA grew at an
average of 8% per year (Fenn et al., 1998).
9
Thomas (1998) reports that litigation is discouraging engineering innovation and
technological advancement in construction projects. Consulting engineering firms are
unwilling to recommend creative designs “...out of fear of litigation-frenzied attorneys.”
10
For easier reading Dispute Avoidance and Resolution Techniques will be abbreviated
as DART.

42
C H A P T E R

3
STAGE 1:
PREVENTION
“For every $1 you spend on claims management
during the front-end of the project, you save at least
$20 to $25 in claims during construction.”
(Zack a, 1997)

A large nationally based contractor teamed with a local, well-respected concrete


contractor to form a joint venture to construct a US$ 100 million office structure uniquely
designed. This project was designed and built on a fast track basis. The owner selected
the contractor though a round of negations. At 80 % design, the owner and the contractor
negotiated a guaranteed maximum price (GMP) of US$100 million. It was imperative
that the contractor finish on time. The owner was in the process of moving, and the
current office the owner occupied had already been sold and a departure date set.
With the GMP set with only 80% of the design being complete, the contractor understood
that there would be changes. As the job was underway, they were designing the upper
superstructure while garage construction was underway. Further complicating things, the
owner added a second architect while the steel was going up to handle only the interior
design. From experience, the owner was aware that large, fast track, multi-party projects
are conflict prone environments. Misunderstandings, incompatible objectives, change,
incomplete scope definition, performance and disruption were all encountered on this

CHAPTER LOOK AHEAD


WHAT IS IT? Preventing conflict before it happens. It presents techniques that focus on minimizing the
sources of conflict presented in this chapter. These techniques include risk sharing, escrow bid
documents, innovated project award and delivery systems, incentive programs, importance of
constructability analysis and documentation, cost/schedule controls, and contract implementation.
WHO IS INVOLVED? The owner is the most crucial participant in this stage. Decisions are made on how
the project should proceed before other participants are on board. The contractor’s staff will also benefit
from this information, especially the documentation, cost and schedule control and training sections.
The A/E should also be involved as a solid, well-reviewed design reduces conflict exponentially.
WHY IS IT IMPORTANT? The preventative stage is the most effective stage to resolve disputes. Although
the cost of implementing these techniques in this stage is sometimes viewed as additional costs, the
benefits usually far exceed the costs. Avoiding disputes before they start is always the best option.
HOW TO APPROACH IT? Review the sources of conflict in the construction industry. Keep an open mind
in applying new techniques to avoid conflict. Apply when designing the Conflict Mitigation Plan.

KEY CONCEPTS
Risk Sharing ..................................................45 Escrow Bid Documents..................................... 49
Project Award and Delivery Systems ............50 Incentive Programs ........................................... 56
Engineering and Documentation ...................59 Cost and Schedule Controls .............................. 59
Dispute Resolution Clauses ...........................65 Training and Development ............................... 65

43
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

project.
Realizing that these conflicts are going to occur is an important step in preparing a
conflict management strategy. After the realization that conflict will occur, the next step
is deciding how to prevent them. This case raises several questions. What effect does the
GMP have on the number of conflicts that may surface on the project? Is this the
appropriate delivery system? With numerous parties involved, how might they keep
misunderstandings at a minimum? How should the project risks be allotted?

3.1 IMPORTANCE OF PREVENTION STAGE


The prevention stage offers the greatest flexibility to design and create innovative ways
to improve communication and job performance by minimizing disagreements and
helping the project team resolve those problems that arise before they become disputes or
claims. The flexibility of this stage comes from the fact that the construction has not
actually begun at this time; hence, as Smith (1995) states, “...this is the only time the
owner has unilateral control over how to work with someone.” After the contract is
awarded and signed, the owner will have at least one partner in every decision, change, or
interpretation regarding the project (i.e., architect/engineer and/or contractor). Prevention
of disputes begins with a good design, comprehensive specifications, complete contract
documents, risk assessment, and other features of job organization. It includes tight and
consistent management of architectural design and engineering, risk sharing, incentive
programs, cost and schedule control, peer review, value engineering, and constructability
reviews.
This initial stage in the Dispute Resolution Ladder (DRL) offers a vast array of
techniques to promote dispute avoidance and encourage conflict resolution during
construction. The role of the owners are significant in this stage, since they have the
responsibility for the creation and introduction of a DRL that best fit the characteristics,
risks and conditions of the project. The owners must accept the fact that disagreements
will occur, and they must incorporate mechanisms in the contract to resolve them as
quickly and efficiently as possible as part of the Prevention Stage.
In terms of cost, some of the techniques in this stage represent additional expenses for the
owner and/or contractor. Most of them are based on existing practices that are upgraded
and adjusted to enhance the interaction between the team members (i.e., people issues)
and the exchange of project information (i.e., communication) through collaboration,
joint development, and updated project data. The use of dispute prevention techniques
will “...yield the harmony with the least cost,” Findley (1997). As an example, a
representative of a major US Public Works owner had this to say about the costs and
benefits of prevention techniques in his projects (Zack a, 1997):
“For every $1 you spend on claims management during the front-end of the
project, you save at least $20 to $25 in claims during construction.”
Consider that fifty percent of all construction claims submitted to the American
Arbitration Association (AAA) for resolution, fall under the US$50,000 value
(Stipanowich, 1997). It follows from the statement above that on average an owner
should spend $2,000 on prevention per dispute; a rather small amount compared to the
expenses required to achieve any type of resolution through binding procedures (i.e.,
arbitration). Therefore, the potential savings that can result from prevention measures
should encourage the complete building team (i.e., owner, designer, and contractor) to
incorporate them into the project.

44
STAGE 1: PREVENTION

This chapter presents twenty-three specific techniques to help prevent disputes in


projects. They have been organized based on the underlying principles that allow us to
consider them capable of preventing construction disputes.

3.2 EQUITABLE RISK SHARING


Unloading all of the construction risks on the contractor is an accepted trend in
construction contracts, “...but also as a practice that is not cost effective” (Findley,
1997). Research by the Center for Public Resources (CPR) in New York, has found that
“...many disputes arise when parties are forced to contest the adverse impacts of an
unreasonably allocated risk.” As contracts continually force contractors to assume risks
that are beyond their control, “...contractors have turned to litigation as a way to resolve
this inequality in the long term.” (Vorster, 1993)
In a recent study conducted on project risks, 85 construction contractors in Hong Kong
ranked how different project risks contributed to project delays. The results (starting with
the risk contributing to the largest delays) were as follows: (Shen, 1997)
1) Insufficient or incorrect design information,
2) Variations in ground and weather conditions,
3) Subcontractors’ manpower shortage,
4) Shortage of materials/plant resources,
5) Poor coordination with subcontractors,
6) Poor accuracy of project program,
7) Shortage of skills/techniques, and
8) Abortive works due to poor workmanship
As shown above, the study found that contractors included in the top-three contributors of
delays (i.e., possible sources of disputes), four conditions that fall beyond their initial
control: design problems, site conditions, weather, labor shortages and scarcity of
material. So, it is not surprising that change order requests relating to these four
conditions are among the most common causes of delays in construction. As presented in
Section 1.3, this book has identified that project uncertainty in the form of unexpected
sub-surface conditions, variations, changes in design, unrealistic expectations, and
weather, to name a few, are among the primary sources of disputes in construction
projects. This project uncertainty is translated into the risks each party has to assume,
either by choice or by contract, upon becoming a project team member.
In a paper on risk allocation in large infrastructure projects, it was concluded that:
“The general guiding principle of risk allocation should be that the different
parties involved should seek a multi-beneficial distribution of risk. A dominant
party that off-loads all project risks onto others is unlikely to enhance the
chances for a successful outcome.”
Vega (1997)
He further points out that a successful risk allocation is based on having the basic
concessions and project agreements right and understood by everyone; moreover, it is
based on clearly defined DART system (i.e., DRL) from the start (Vega, 1997).
By distributing the construction risks among the parties in a more balanced manner,
owners, designers, and contractors can manage the uncertainties more efficiently. As
more team members, with greater overall knowledge and experience, share project risks,
contingency costs carried by each party to cover them can be lowered. A project where

DRAFT 2/4/2017 2:32:00 PM 45


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

risks are distributed more justly also sets the stage for greater communication and
interaction among the parties, resulting in more honest and productive negotiations when
unforeseen conditions become apparent. An example of the concept of Shared-Risks
between the owner and the contractor in a construction contract is summarized in Table
7.
Table 7 – Allocation of Project Risks under the Shared-Risk Approach (Findley, 1997)

ITEM RISKS OWNER’S CONTRACTOR’S

Risk Reason Risk Reason

PREREQUISITE RISKS
1 Adequacy of Project X Owner’s project
Financing
2 Adequacy of Labor X Can best assess
requirements
3 Permits and Licenses X Shared X Shared
4 Site access X Owner’s site
PERFORMANCE-
RELATED RISKS
1 Sufficiency of plans X Sets up the
Bidding process
2 Underestimation of X Estimate the contract
Costs
3 Owner furnished X Owner’s choice
material
4 Contractor Furnished X Responsibility
material identified in contract
5 Means and methods of X Area of expertise
construction
6 Delay in presenting X Could be the X Could be the claiming
problems claiming party party
7 Delay in addressing X Party receiving X Party receiving the
and solving problems the claim claim
8 Subsurface conditions X Owns the site
9 Worker and Site X Controls the execution
Safety
EXTERNAL EVENTS
RISKS
1 Governmental Acts X Shared – not X Shared – not
predictable predictable
2 Abnormal Adverse X Shared – not X Shared – not
Weather predictable predictable
3 Acts of God X Shared – not X Shared – not
predictable predictable
4 Cost escalation X Shared – not X Shared – not
predictable predictable

In this table, both parties share external events, which are usually the ones with the
greatest uncertainty, as they are not predictable. Contractors share risks that were usually

46
STAGE 1: PREVENTION

assigned to them exclusively, such as abnormal Adverse Weather conditions, but they
now also share the risks associated with Acts of Gods, easing some the owner's burden.
This type of distribution of risks meets Vega’s (1997) requirement that uncertainty must
be allocated seeking the benefit of all parties and not just an unfair allocation to limit
individual liabilities.
Considering the necessity to improve the distribution of risks in construction projects to
mitigate conflict, the following three contract clauses and methodologies have been
developed.

3.2.1 ECONOMIC PRICE ADJUSTMENT

A clause that allows for controlled price escalation during the life of the project can help
reduce the amount of ‘guesswork’ performed by the contractor when pricing the job.
When contractors are forced in fixed cost contracts to assume 100% of the cost escalation
risk, the owner can be setting the stage for future disputes. In highly competitive markets,
when contractors are pressed to offer savings to their clients, contingency amounts are
usually the first ones to be taken out during contract negotiations. When price escalation
begins to affect the contractors' bottom line, claims tend to follow.
Zack (a, 1997) suggests that on projects over 3 years long or located in countries with
unstable economies, owners should provide in the contract methods to evaluate and
determine price escalation. By doing so, owners reduce uncertainties and limit the
contractor’s liabilities for price adjustment. The contract might set a limit to the price
escalation to be carried by the contractor, leaving anything above that number to the
owner. If significant increases in costs occur during the life of the project, the contract
already has a formula and the conditions to compensate the contractor, eliminating the
need for a claim. An agreement, prior to the existence of open conflict, on the level of
risk each party will assume and the mechanisms to apply if an unexpected price
escalation occurs, will significantly expedite the reviews and approvals, while reducing
costs and time implications.
An example of this occurred for the installation and maintenance of all the moving
walkways and escalators in a major airport. The cost of hiring mechanics that perform
this specialized work tends to fluctuate. Since the maintenance contract was for seven
years, the owner included a bid item to account for this fluctuation. This bid item was tied
to industry wage averages in this field. The result, the owner received six competitive
bids and the contracts had insurance that they if the cost of this labor increased, they
would be compensated for it.

3.2.2 GEOTECHNICAL BASELINE REPORT (GBR)

Although research has found that unforeseen ground conditions are a primary source of
delays in construction projects, most owners only address this issue by transferring this
risk to the contractor. The Geotechnical report is provided to the bidders “for information
only” with a disclaimer to the effect that contractors may use that information but are
completely responsible for any interpretations of the data. On the other hand, most
contractors can not afford to make their own soil borings, nor can they hire a
Geotechnical consultant during bidding, so they end up relying solely on the information
provided by the owner. When unforeseen soil conditions are found, disagreements and
claims are common, as contractors will attempt to shift this risk back to the owner.
Because this type of dispute tends to happen at the beginning of the job, they usually
have a significant effect on the overall performance of the project, interfering with many
future disagreements and negotiations on other issues.

DRAFT 2/4/2017 2:32:00 PM 47


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Geotechnical Baseline Reports (GBR) provide for a new way to present sub-surface soil
conditions and to distribute the associated risk. This Geotechnical report has an additional
section that includes not only an interpretation of the soil borings and test results but also
an outline of the possible subsurface conditions the contractor should expect to find. This
information is developed by the owner’s consultants and paid for by the owner. With this
information, the owner can require the contractor to include provisions to deal with any
of the possible conditions outlined in the GBR, effectively limiting his risks to anything
beyond those provisions. On the other hand, the contractor’s uncertainty concerning the
sub-surface conditions has now been limited to a set of defined possibilities. The
contractor is free to decide how to estimate and price the work more efficiently, confining
the risks to decisions within his control.
By making this additional information available to the contractors, the owner improves
their chances of getting a more competitive bid, and they establish a baseline to evaluate
and measure future claims on differing site conditions. By sharing the sub-surface risks
with the contractor, the owner reduces the likelihood of disputes on this issue, while at
the same time, it gives the contractor a tool to improve the assessment of the project
costs, schedule, and uncertainties.

Toronto Transit Commission (TTC) Case


The following case confirms the advantages that a balanced allocation of risks had in a
Canadian construction project, the construction of the Sheppard Subway twin tunnels in
Toronto. As reported by Skelhorn (1998), the Toronto Transit Commission (TTC), the
owner, has been successful in the implementation of the following DART:
1) Risk sharing for cost reductions and schedule acceleration:
a. The TTC bought and supplied the Tunnel Boring Machines (TBM),
removing the uncertainty about the type of equipment needed in the
contractors’ proposals. However, the TTC assigned the maintenance
responsibility and the operation of the machines to the contractor, and
included in the agreement with the TBM supplier a regular service and
supervision contract. In addition, the contractor was made responsible
for supplying the head dressings for the TBMs. Through the first 3.3
km. of tunnels; the “mechanical availability” of both machines had
exceeded 90%.
b. The tunnel precast concrete liners were bought and supplied by the
TTC to the contractor for installation. Although no additional
information on the reason for this purchase was provided, based on the
type of project and the other DART implemented by the TTC, it can be
inferred that this purchase limited the contractors risk as to this large
purchase of material, and allowed the owner more direct control over
the detailing and fabrication of the precast liners.
c. A Geotechnical Baseline Report was supplied to all the parties
performing design and/or work for the TTC, and so far the performance
of the TBMs has been as expected, as well as the wear of the head
dressings supplied by the contractor.
d. The TTC assumed the responsibility for surface conditions monitoring,
construction insurance, and quality control. However, the TTC made
everyone a stakeholder and linked the sensors on the TBMs to the
offices of the engineers, the contractor and the TBM supplier, forcing
everyone to focus on these critical aspects of the tunneling operation.
This real-time data is reported as being a great benefit to all parties,
since it provides immediate access to information on the machines for

48
STAGE 1: PREVENTION

“advisory and troubleshooting” purposes and for trend and scheduling


analysis. This data system had allowed timely responses by the
engineer-contractor team to settlement conditions, reducing the effects
of ground settlements beyond the set limits to only a few “isolated
incidents.”
2) On-site partnering (see Chapter 4) with scheduled off-site retreats to promote
communication and collaboration.
3) A Dispute Review Board (Section 6.3) to hear and resolve disagreements and
conflicts during construction effectively and efficiently, and to assess and
provide an opinion on potential areas of dispute.
As a result of the application of the risk sharing techniques, coupled with partnering and
the Dispute Review Board, the project was completed on schedule and the new subway
line is scheduled to begin operations in 2002. The Dispute Review Board visits the site
every quarter to receive an update on progress and offer advice on any potential disputes
(similar to what happened in Hong Kong – Section 2.2.3). So far, the Board is yet to be
asked formally to decide on any disputes. Disagreements are being addressed and
resolved promptly by the site personnel through partnering, with some level of informal
participation by the Dispute Review Board (Skelhorn 1998).

3.2.3 THIRD PARTY BENEFICIARY CLAUSE

Almost every construction project involves more than one contractor, and owners tend to
become the only responsible party to a number of contracts with different entities. When
one contractor causes delays, the owner usually becomes the defendant in more than one
claim as other contractors, affected by the performance of this one party, move against
the owner for relief. Single prime contracts can limit this situation from occurring, but as
jobs have become more complex, it is impossible to award the total project to only one
party.
In order to reduce this effect, Zack (a, 1997) recommends the use of a Third-Party
Beneficiary Clause in construction contracts. With this clause, owners are able to share
among all contractors and sub-contractors the risks of delays, by making each company
the “intended third-party beneficiary” of all other contracts. Through this clause, owners
can avoid claims that are not caused by them, and contractors can seek relief for delays
caused by other parties directly. Another benefit of this arrangement is that relationships
are less strained, as contractors are not fighting the owner over matters beyond his/her
control, and they can still search for compensation from the third party at fault.

3.3 ESCROW BID DOCUMENTS


In this form of preventive DART, the project team (owner/contractor) submits to a third
party neutral a full set of the documents used by the contractor to prepare the bid,
including information regarding pricing, production rates, equipment selection, and any
other aspect considered in finalizing the proposal. Confidential information such as mark-
ups and fees is not included. The project team reviews the documents before placing
them in custody, and agrees on both the procedures to access the information and how the
costs of safekeeping the documents will be shared. These documents remain confidential
under the escrow agreement, and parties can only access the information to resolve an
issue in dispute. Changes to the contract can be added to the escrow documents once they
are negotiated and signed by the parties, as well as any supplementary conditions that are
agreed to after the award.

DRAFT 2/4/2017 2:32:00 PM 49


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

By “freezing” the original bid documents, the project team creates a valuable source of
information to be accessed only when disagreements arise in issues such as productivity,
design details, and equipment selection. The advantages of putting the bid documents in
escrow are two-fold. First, it provides the basis for the review of any claim regarding how
an item was bid, how a detail was interpreted, or what productivity factors were used. For
example, if a change order requires additional excavation and disposal of excess soil,
parties can access the escrow documents and review equipment productivity rates, and
base costs for equipment rental and for disposal of excess material. Also, parties can
review the original quantity take-off performed by the contractor to determine whether
that specific excavation was considered or not in the original bid. Once this information
is determined and agreed by the parties, the respective mark-ups and fees can be
negotiated.
Second, the existence of this ‘as-bid’ database should deter any unfounded claims from
the contractor, since the original documents will not support them. This mechanism can
help prevent disputes and provide information to analyze disagreements faster, in
accordance with a set of variables that can be reviewed by both parties.

3.4 PROJECT AWARD AND DELIVERY MECHANISM


Four forms of innovative project awards and delivery mechanisms are presented below,
which recognize the possibility of disagreements in construction projects, and provide
specific tools to manage and deal with some of them more efficiently. These methods are
derived from the project structures previously mentioned in Section 1.2.2.

3.4.1 NEGOTIATED COMPRESSED PROCESS

In an effort to reduce the number of interpretations given to contract documents, which is


a major source of dispute, a new bidding method has been developed for Earthwork and
Tunneling jobs (Civil Engineering, 1995). Known as the Negotiated Compress Process,
this bidding-selection system divides the contract award in three steps. First, the owner
qualifies the contractors based on the type of work to be executed and their experiences.
Second, the selected contractors meet with the owner and designers to decide jointly on
the best type of equipment, a key variable in pricing earthwork and tunneling jobs, and
any other issue which might be considered critical to the execution of the project. Finally,
each contractor presents its bid, based on the agreed items, and the contract is awarded to
the lowest bidder.
According to Zack (a, 1997), this three-step bidding system provides for a more balanced
distribution of project risks since some of the uncertainty is reduced (i.e., the selection of
the equipment). In addition, the fact that this is a joint decision allows for significant
savings, during submittals and start-up, for all parties. Furthermore, it limits problems
associated with equipment, productivity, and schedule sequence during construction. The
costs associated with the pre-bid meetings are borne by the owner, who should benefit
from time/cost savings resulting from this early elimination of certain project
uncertainties.

3.4.2 A+B BIDDING

Another new approach towards contract award is based on the notion that in general,
owners want to finish their projects at the earliest possible date. Some public owners in
the United States are including in the bid package a line item referred to as “cost per

50
STAGE 1: PREVENTION

day.” Contractors are asked to provide, together with the pricing of all line items, the
schedule duration in days for the project (also known as time of performance). Then, to
obtain the total project cost of each contractor, the owner adds the construction costs (A-
term) and the number resulting from multiplying the “cost per day” of the owner by the
duration submitted by each contractor (B-term). The award is based on the lowest total
project cost.
This award mechanism provides two incentives for contractors that reduce the chances of
problems and disputes during construction. First, contractors are forced to review the
construction sequence in detail and present the shortest feasible construction schedule,
with the aim of keeping the B-term as low as possible. Second, contractors are
encouraged to finish within the time limit in order to realize the full amount of the bonus
(B-term); therefore, they should work with the owner and the design professionals to
resolve potential problems before they become disputes and delay the job. More than 100
projects have been bid and built in the US using this system, and all of them have been
completed on schedule (Zack a, 1997).

3.4.3 PEPC DELIVERY SYSTEM

This innovative delivery system was developed, based on the Engineering-Procurement-


Construction model, by the Construction Industry Institute (CII 130-1, 1998). It was
designed as a response to the increasing role major suppliers of equipment and material
are playing in the construction process. CII defined this delivery system as:
“PEpC (Procurement, Engineering, procurement, and Construction) is an
innovative project delivery system which makes it possible to utilize key supplier
expertise in all phases of the project life cycle by developing an advance
procurement strategy and by actually reaching a full commercial and
contractual agreement with suppliers of strategic procurement item and/or
systems prior to the principal engineering activities” (CII 130-1, 1998)
In other words, critical pieces of equipment and materials are negotiated and procured
before the actual engineering takes place, based on basic conceptual designs and detailed
performance requirements. With the suppliers on-board, the engineering process
incorporates their input, special requirements, and experience into the design. Among the
benefits this system brings to the construction process, CII highlights the following:
• Improved quality of the detail design.
• Improved system and facility performance.
• More equitable allocation of risk.
• Improved utilization of supplier core competencies.
• Reduction or elimination of redundant work.
• Reduced need for owners and contractors to maintain non-core competencies
that are more effectively maintained and delivered by suppliers.
As reviewed in Chapter 2, these benefits address areas that have been found to be sources
of conflict in the construction process (i.e., design quality, owner objectives, risk
allocation, and cost efficiency). Therefore, by improving these areas, the PEpC delivery
method can help prevent disputes from developing during the construction process, or at
least it can reduce the levels of uncertainty and risk in projects with highly specialized
equipment, systems, and/or technology.

DRAFT 2/4/2017 2:32:00 PM 51


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

3.4.4 “BRIDGING” THE DESIGN-BUILD GAP

The use of Design-Build as a delivery system in the construction industry has grown
significantly as an owner-favored method, both in private and public sector projects. This
system provides the owner with a single-source of project responsibility and a single-
point of communication, so as to avoid the “finger-pointing” and “risk shifting” that often
takes place in other construction approaches such as Design-Bid-Build. Design-Build
projects are generally completed faster, usually with less administration costs for the
owner.
However, Design-Build is not a cure for all project delivery difficulties. Appelbaum
(1998) has identified the following problems with it:
• Loss of control over design by the owner, as they forfeit direct communication
with the designer.
• Selection of the design firm based on price rather than on qualifications.
• Less competition in the selection and award phases, as the owner is required to
compare “...apples to oranges, to bananas in order to choose a contractor,”
since each of the proposals might be different as they represent an interpretation
of what is sometimes very basic design and/or performance parameters.
• The final product is a mixture of owner-contractor objectives and
interpretations, but might fail to meet the original project criteria.
In other words, by transferring the design to the contractor, the owner generates a “gap”
between their objectives and the design process, which is responsible for the translation
of those objectives into plans and specifications. The owner is often left to choose from
three or more completely different proposals, none of which is one hundred percent
satisfactory. To correct these problems in the Design-Build delivery system, Kluenker
(1996) and Appelbaum (1998) propose the concept of “Bridging” to close the gap
between the owner and the design process, without loosing the many advantages of the
Design-Build system.
Bridging divides the Design-Build process into three phases (Kluenker, 1996). In the first
phase, the owner retains a design consultant who is responsible for developing a
conceptual design that satisfies the owner’s basic project needs. During this critical stage,
the owner has control over how his needs and objectives are translated into a very basic
design. Then, competing contractors prepare proposals based on this conceptual design
developed by the owner, complying with the specific requirements set forth in these
documents. The problem of having to compare apples to oranges is reduced, and the
selection can take into account, in addition to the price, the technical solutions proposed
to meet the criteria. Since the information contained in the conceptual design is limited,
the overall design responsibility remains with the design-builder.
In stage two, the design-build team completes the design and the drawings of the project,
while the design consultant acts as the owner’s representative, serving in a “pure agent
capacity” (Appelbaum, 1998). The consultant reviews working drawings to confirm
compliance with design requirements. There is no design responsibility overlap. In the
third stage, the contractor builds the project and the bridging consultant inspects work-in-
progress as the owner’s construction representative.
This system should overcome the disadvantages of the Design-Build delivery system
outlined above as follows:
• Owner’s loss of control over design: With the “bridging” consultant owners
have control of the portion of design that should be more important to them (i.e.,
schematic and conceptual design)

52
STAGE 1: PREVENTION

• Owner’s loss of communication with the design professional: Through the


design professional, owners maintain direct communication with the design
process.
• Designer selection based on price: The “bridging” consultant can be selected
taking into account his/her qualifications. The conceptual design will benefit
from this, as the goals and objectives of the owner will be properly translated.
• Limitation of bidding and price competition: The existence of a conceptual
design will foster proposals from contractors, which are easier to compare and
select taking into account price as well as design, materials, and technical
solutions.
In terms of cost, the introduction of the “bridging” consultant in the Design-Build
equation should be close to zero (Appelbaum, 1998). First, the cost of design
development should be offset by a lower design cost in the Design-Build proposal, as
contractors will lower the design fee, now that they have a conceptual design to work
from. Second, the cost of the on-site representation should be covered by less change
orders and disagreements between the original design conditions developed, by the
owner, and design and details of the contractor.
“Bridging” helps ensure that owners using the Design-Build method receive a project that
meets their needs. This reduces the chances of job upsets, rework, and claims.
Furthermore, “bridging” should also expedite the submittal and design approval, as the
design-builder will have to perform less guesswork to interpret the project requirements.

3.4.5 FRAME CONTRACT DELIVERY SYSTEM IN THE NETHERLANDS

In order to design and build large-scale, time-consuming civil engineering projects, in the
1970’s the government of the Netherlands developed a type of project delivery system
that is still in use and is known as “Frame Contracts.” Under this scheme, parties start
with only a very broad definition of the works to be completed and accept to negotiate
partial contracts as the design problems emerge and engineers and architects propose
different solutions 1. According to Goudsmit (1985) 2, “...the philosophy of the frame
contract is that whereas a procedure for the negotiation of a price must be incorporated
in it, the real execution of the various stages of the works should only necessitate
agreement on the specification of such works as well as on the time period within which
such work should be completed.” In other words, parties agree on how they will negotiate
a price for works that will be fully defined in the future, with only a specified maximum
duration and some basic performance and quality criteria. The following example from
Belgium should clarify this concept and the reasons behind its development and
implementation.
“In 1975, the frame contract formula was selected by the Government [of
Belgium] for study/design and execution of a seaward expansion of the outer
port of Zeebrugge. The decision was influenced by the success on similar
maritime projects in the Netherlands.
Dutch experience has proved that it is almost impossible to formulate in
advance a ‘cut and dried’ study for projects which extend far beyond the
coastline ... It is also difficult to pre-determine the effects of such projects on the
behavior of beaches and seabed.
... the preparatory study was directed towards obtaining the fullest possible
information about the known or assumed behavior of the sea and the seabed.
But surprises always occur because not all of the sea’s reactions can be
predicted in advance,...This requires rapid adaptations of the design and

DRAFT 2/4/2017 2:32:00 PM 53


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

execution plans during the construction period without incurring costly delays
or protracted discussions on claims.
The frame contract, which defines general but strict rules and limits for quality
control, timing and prices, makes constant consultation possible between the
Government and contractors responsible for design. Accordingly, studies and
construction plans can be either amended or even changed as and when the
need arises during the course of the project to ensure the utmost efficiency and
completion on schedule.” (Ir R. Simoen, cited by Goudsmit, 1985).
Through the use of the Frame Contract parties in construction have been able to
effectively introduce the concepts of objective alignment, risk allocation, trust, and long-
term commitments to enhance efficiency and reduce conflict in large scale engineering
projects. By understanding the difference between “static agreements” (like the sale of a
house) and “relational contracts” such as construction projects (Overcash, 1998); and by
following this advice to concentrate more on the dynamics of the process than on its fixed
elements, the Frame Contract creates a resourceful environment to manage uncertainty
while designing and building large-scale projects. The benefits of this approach are not
limited to the cases in which environmental uncertainties create a time-related concern (a
typical worry in Nordic countries concerning the sea). Rather, they simply facilitate the
task of dealing with the unexpected by effectively acknowledging it as a natural part of
construction.
Among the most common delivery systems for construction projects in the United States,
Design-Build is the closest one to a Frame Contract. However, there are significant
differences between the traditional Design-Build and the Frame Contract, with regards to
key aspects of the contract and the criteria for the selection of the contractor. Table 8
summarizes these differences.

54
STAGE 1: PREVENTION

Table 8 - Differences between Frame and Traditional Design-Build Contracts

ASPECT OF
FRAME TRADITIONAL DESIGN-
THE
CONTRACT BUILD CONTRACT
CONTRACT
Only roughly defined. The owner
usually has a rough estimate, but
the design is not even schematic The total value of the contract is
Contract Value to allow for the development of a known, at least in the form of a
budget. Prices are negotiated as firm budget.
the design is completed and the
work is ready to be executed.
Only certain key dates are
Usually the owner sets the
specified, usually by stages. The
maximum duration and some key
contract will set a limit for the
milestones that must be met by
Schedule latest acceptable finish date.
the contractors. In the proposals,
Beyond that, the schedule
contractors include a schedule to
specifics are developed as the
perform each phase of the project.
project is defined.
The owner provides some form of
Only a broad definition of the
schematic or conceptual design.
problem exists, and a general
Design The contractors include in their
description of the works to be
Parameters proposals their initial
performed is included in the
interpretation of those
contract.
parameters.
Only a broad definition of how
the works are to function and
Specific owner requirements and
perform is included. Contractor
Design performance criteria is detailed in
know-how, new technologies,
Performance the tender documents and
and design decisions will
therefore in the contract.
determine the final performance
criteria for the project.
Contract focuses on the
relationship. Because there is
little definition at the award stage,
the contract sets limits that will
Terms and help guide the relationship and Varies from contract to contract,
Conditions the future definition of the but it is usually more formal.
project. Special emphasis is given
to the procedure to negotiate a
reasonable price for the works as
the design develops.
A balance allocation of risk is Varies from case to case, but one
incorporated in the contract in of the basic premises of design
Risk
order to manage the high degree build contracts was that most of
Allocation
of uncertainty at the beginning of the risks were assumed by the
the project. contractor.

DRAFT 2/4/2017 2:32:00 PM 55


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Table 8 - Differences between Frame and Traditional Design-Build Contracts (cont.)

ASPECT OF
FRAME TRADITIONAL DESIGN-
THE
CONTRACT BUILD CONTRACT
CONTRACT
Each owner will define the
The contract clearly defines
dispute resolution mechanism,
procedures to ensure that
but many fail to do so assuming
negotiations are completed and
that by awarding a Design Build
Dispute issues are resolved. Alternatives
contract all project risks have
Resolution are given to avoid disruptions
been assigned to the contractor
Clauses because of a failure to agree on a
and therefore problems will be
certain issue. Arbitration is the
solved within the contractors’
alternative of last resort.
scope of work.
As the project develops and parts The Design Build contractor has
of it are defined, the owner can control over 100% of the works
negotiate and issue partial under its scope of work. Some
Partial contracts to the Frame contractor. contracts might require
Contracts The owner can also incorporate subcontractor approval by the
new subcontractors if owner, but no separate partial
negotiations fail or certain contracts are issued as the design
technical expertise is required. develops.
Trust, previous experience,
quality of previous work, state of Price, proposed solution,
Selection
the art technology, financial schedule, experience and usually
Criteria
stability, willingness to assume price again.
risk, and reliability.

What the table shows, is that more flexibility is granted to the parties under the Frame
Contract, allowing them to tailor decision-making to the specific situations that emerge as
the project progresses. In the description of the Frame Contract the reader will find words
like rough, certain, broad, and general, which demonstrates its openness to change and
constant adaptation.

3.5 INCENTIVE PROGRAMS


According to Findley (1997), “Performance awards [incentive programs] strengthen the
project team members’ commitment to speed the project along.” In addition, incentive
programs aid in the process of aligning the contractors’ motivation and performance with
the owner’s objectives. As identified in Section 1.1, failure to achieve some degree of
objective alignment among the parties is one of the sources of conflict and dispute in the
construction process; therefore, incentive programs that promote the development of
common objectives for all the team members should help prevent and mitigate disputes in
projects.
Incentive programs can “...improve contractor performance by focusing efforts on areas
important to the owner” (Howard et al., 1997). Nevertheless, in order to benefit from this
greater alignment of objectives, the owner has to define attainable yet challenging goals
for the construction team. More importantly, the owner must continually evaluate the
performance of the contractor against the set goals, with the purpose of determining, first,

56
STAGE 1: PREVENTION

if the contractor has earned the incentive, and second, if the goals will be achieved based
on the progress made up to that point.
Three incentive approaches that encourage the alignment of the objectives of the different
parties and promote collaboration and cooperation during the execution of the project are
presented below. The first two incentive programs were identified by the Construction
Industry Institute (CII 114-1, 1998) during a recent study conducted by the organization.
The third program comes from an article by Zack (a, 1997).

3.5.1 COST/SCHEDULE INCENTIVE MATRIX

In order to align owner and contractor objectives to improve timely completion of the
project within the stipulated budget allocation, owners can develop an incentive program
that rewards contractors when they meet cost and/or schedule goals. By addressing the
problems of cost overruns and schedule slippage’s through the incentive program the
owner increases his/her control over two important sources of disputes in construction,
and promotes a collaborative approach among the construction team. The owner profits
from meeting his/her planned schedule/cost projections, while the contractor shares in
part of the benefits. The following example shows a successful application of this type of
incentive program.
Howard et al. (1997) report that for a project worth over $100 Million to replace a
wastewater drainage system, the owner proposed the contractor a 15% share in the
benefits to be obtained from an improvement in the contractor’s performance. The owner
developed a value matrix for: “...cost underrun versus budget, dollar value for
completion before schedule date, and reduced owner overhead relative to the original
plan.”
As shown on Table 9, the contractor’s objectives can be aligned with those of the owner
in the categories defining the incentive. They represent for the contractor the only way to
acquire additional income from the execution of this project.
Table 9 – Objective Alignment through Incentive Program

Owner Objectives Contractor Objectives Contractor Objective after


(Categories) before Incentive Program Incentive Program
Meet cost estimate, cash-
Complete the project under Meet cash flow, fee and
flow requirements and
budget (COST) maximize cost savings.
projected fee.
Complete project ahead of
schedule, even if it
Complete the project ahead Meet schedule datelines
represents some additional
of schedule (SCHEDULE) without additional costs.
costs, which would be
offset by the bonus.
Not concerned as long as
Collaborate with owner in
Reduce the owner overhead owner is able to respond
solving technical and
costs technically and
administrative problems to
(OVERHEAD) administratively to its
reduce overhead.
demands.

DRAFT 2/4/2017 2:32:00 PM 57


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

According to Howard et al. (1997), in this instance the construction team was able to
surpass the owner’s cost and schedule goals, and the contractor earned an additional $3.5
Million as an incentive (3.5% of original contract amount).

3.5.2 SUBJECTIVE DETERMINATION OF FEE

In this example of an incentive program, the owner and the contractor agreed to have part
of the fee contingent on periodic engineering and/or construction performance
evaluations, executed by the owner. In a cost-plus-fee project, the contractor’s fee was
divided as follows: 15% of the fee was a fixed amount, 15% was based on actual man-
hours in engineering activities, 35% was tied to performance in engineering, and the
other 35% to performance in the construction phase (Howard et al., 1997). Then, in order
to process the request for payments for 70% of the fee, the owner completed quarterly
subjective evaluations of the contractor’s performance. A minimum score was set as a
payment requirement, and the contractor was able to recuperate any loss income from
previous months by exceeding a specified score with superior performance in the
following periods. The project was completed ahead of time and under budget.
This incentive program provided benefits to both the owner and the contractor. The
owner realized the project within the specified time and budget, while the contractor was
paid the full amount of its fee; it was able to adjust and correct any problems during the
execution thanks to the quarterly evaluations; it developed and maintained a good
relationship with the client during and after the project; and it spent less resources (i.e.,
field and office overhead staff and equipment rental) by finishing ahead of schedule.
Moreover, the owner and the contractor resolved all project disagreements at the site
level, without the need for the intervention of any third party.
According to study by CII (114-1, 1998), subjective evaluations of project performance
give the owner the ability to address areas that are not normally covered by the contracts.
For example, CII suggests that the owner can include “customer satisfaction feedback as
part of the incentive” package for the contractor. However, CII warns in the conclusions
of this 1998 study, that teams need “specific targets and milestones to aim at throughout
the total duration of the project, and an incentive totally dependent on a subjective
determination, will most likely result in failures.”

3.5.3 SUPERIOR TIME-MANAGEMENT ALLOWANCE

In an attempt to reduce the duration of projects or at least increase the chances of


finishing on-time, some public owners in the US have introduced in their construction
contracts what is known as a Superior Time-Management Allowance incentive (Zack a,
1997). Under this system, contractors are offered a fixed bonus based on finishing the
project before the scheduled completion date, say 30 days ahead of schedule. This
amount is added to the contract price.
As the project proceeds, contractors can submit schedule changes and delay claims, but
the bonus remains tied to the original early completion date. In other words, if the
contractor submits a delay claim for a 30-day extension, the contractor would in effect
give up on collecting the bonus allowance. The same thing will happen if the job is
finished on or after the original completion date, regardless of any outstanding claims, or
any final arbitration awards.
The advantage of this system is that it discourages contractors from submitting time
extension claims. Contractors should be more willing to collaborate with the owner in the
resolution of problems, without turning them into additional time requests, to achieve the

58
STAGE 1: PREVENTION

full bonus amount. This approach works in two ways, first, it is an incentive to finish on
time, and second, it is a disincentive to submit delay claims.

3.6 COMPETENT ENGINEERING AND DOCUMENTATION


Poor contract documents, changes, and deficient design, are among the most common
sources of disputes in the construction industry (i.e., project uncertainty and process
problems). In fact, five out the seven papers presented in Section 1.1 (Table 1) found
these characteristics to be sources of disagreements and disputes in the industry.
Therefore, to reduce this type of uncertainty, owners should improve the documentation
by setting higher standards for their engineers and design professionals. The project
should benefit in the long run as fewer claims and erroneous interpretations will develop.

3.6.1 CONSTRUCTABILITY ANALYSIS

One way to reduce disagreements and disputes based on contract ambiguities is to carry
out constructability analysis. This analysis, performed during the planning, design, and
procurement phases, can mitigate problems and claims during construction. Moreover, it
can identify errors, omissions, and impractical details, which would have been uncovered
by the contractor or supplier, resulting in additional costs and delays for the project. In
Section 4.4 the application of the concept of constructability analysis is provided when
the example of Lean Construction is presented. In this case, the contractor assigns
structural engineers to work with the design team in order to improve the construction
details of the facility and helps expedite getting the structure off the ground.

3.7 COST AND SCHEDULE CONTROL


“On time and within budget” has to be one of the most common clichés in the
construction industry. Owners, designers, consultants and contractors commonly see
these two variables as the ultimate goals of the project. However, to control the costs and
the schedule of a project remains one of the most difficult activities to accomplish in any
construction project.
A dispute management technique used by the Public Sector in Italy, illustrates the notion
of cost and schedule control in the European continent (Fenn et al., 1998). This technique
is based on the requirement for contractors to report with monthly invoices any claims
regarding the performance of the works during that period (Figure 13). Every month,
before payment is made by the agency, the on-site representative completes a report
based on the works performed during that month. This report becomes the monthly
progress certificate (SAL), and it is given to the contractor for review and approval. If the
contractor does not report a claim that has become apparent in that period, the contractor
loses its rights to further compensation. In every report, the contractor must report any
new claims, as well as any outstanding ones from previous months.
This requirement forces the parties to acknowledge the existence of an outstanding issue
every pay-period, and forces them to address the matter. It also encourages an evaluation
by the parties as to whether the outstanding claim is affecting any additional parts of the
project since it has not been settled.
To further track the development and control the resolution of disputes in Public Works
in Italy, if a claim in the SAL report exceeds 10% of the contract value, the Italian law
requires immediate action by the head public official responsible for the project. Within

DRAFT 2/4/2017 2:32:00 PM 59


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

90 days, the officer must review it with the contractor and submit a proposal for
‘amicable settlement’; then the parties have 60 days to negotiate a solution. If they fail to
resolve the matter after the 60 days, either party may proceed with arbitration after final
completion.

Site Contractor SAL report is


Representative reviews and If no claims incoporated to
prepares approves SAL during period the request for
monthly report report progress
(SAL) payment

If claims develop
Negotiations to resolve and/or they remain Once claims
claims. Outstanding outstanding are
claims have to be reported
included subsequent and
SAL reports documented
Claims need to
be incorporated
into SAL report
If claim
exceeds 10%
of contract

Head Public Proposal for Negotiations to Arbitration can


Official must amicable settle be requested by
review claim settlement either party at
with contractor presented by the end of the
and site rep. owner to project for any

90 days 60 days

Figure 13 – Dispute Management Technique in Italian Public Sector Contracts

With these requirements, the Italian Public Sector has established a procedure and
specific time periods for the negotiation of large claims. These claims will go through a
process of Structured Negotiations (Section 5.6), before arbitration can be utilized to
settle them. Moreover, by requiring that all claims be acknowledged and reported every
pay-period, this owner is promoting that the on-site representative and the contractor
meet and attempt to settle the claims to eliminate them from every SAL report (this type
of incentive to negotiate disputes during construction is reviewed in Section 5.5 under
Step Negotiations).
By assuming a pro-active approach like the Italian Public Sector, in the identification,
management and negotiation of disputes (i.e., costs and schedule changes), owners have
found ways to reduce litigation, encouraging the building team to attain the objectives
outlined in the famous cliché. Projects that fall out of schedule and/or miss budget
allocations are prone to disputes and confrontation. The following case provides a
concrete and successful application of the concept of owner intervention as a strategy for
dispute prevention in the Canadian construction industry.

60
STAGE 1: PREVENTION

Air Canada Center Case


As reported in Engineering News Record (ENR 2, 2/15/1999), $50 million worth of
design and construction changes were introduced during the construction of the $265-
million Air Canada Centre after the facility was 45% complete. These changes, however,
did not disrupt the original construction schedule, and the facility was to open as planned.
A change in ownership of the arena triggered the modifications in the project, and
according to the construction manager, “the changes were very, very difficult to
implement because they were integrated throughout the entire building and affected the
whole fabric.” (ENR 2, 2/15/1999). How come an increase of almost 20% in the amount
of work did not affect the schedule? What was done to mitigate potential disputes and
delays as the changes were implemented?
The key in the success of the implementation of these changes appears to be the new
owner, who took an active role in the process. The goal was to make the changes without
modifying the original completion date or “going overboard on cost” (ENR 2,
2/15/1999). Both the contractor and the designer participated with the owner in the
definition of the changes and the procedure to implement them. The changes were not
imposed on any team member. So, when the change orders were issued, there was
already an agreement as to what and how they were going to be performed. Once the
changes were approved, the contractor introduced a separate night-crew for three months
to do the work, minimizing the impact on the rest of the construction.
By involving the complete project team in the decisions regarding the changes, the owner
was able to introduce significant changes in a controlled matter. The costs were high, but
the facility met the schedule deadline without any disputes as a result of the new work.
According to one project manager, “A big help was that once the owner charted a new
course, it stood by its decision” (ENR 2, 2/15/1999), encouraging every member to
assume the new responsibilities and negotiating the changes as they were defined, not
waiting until completion for a lengthy and troubled review. Although this was not a
formally partnered project (Chapter 4), key aspects of this system were introduced
through the involvement of the owner (i.e., team building, pro-active problem solving,
effective resolution of technical, and financial issues).
The following sections present techniques that can help owners and contractors assume a
pro-active approach as described in the Italian and Canadian examples above with
regards to cost, schedule and claims control. These techniques highlight the advantage of
establishing project information and guidelines to analyze and assign real costs to
changes and, once again, the importance of owner participation in the management and
control of the project’s costs and schedule.

3.7.1 COST STATEMENT SUBMITTAL

In certain instances, owners have included as part of the contract a requirement that the
contractor submits a certified statement of all costs incurred in the project, before the
certificate of final completion is issued. With this information, the owner can evaluate
any “after-completion” claims the contractor might submit after receiving the certificate
and the retention moneys. More importantly, this requirement deters unfounded claims by
the contractor once he/she is clear from delivering the project.
These after-completion claims can become very complicated as data is scarce and job-site
people are no longer involved. Therefore, a certified cost report can provide important
information for a more accurate review and faster negotiation of any final settlements.

DRAFT 2/4/2017 2:32:00 PM 61


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

3.7.2 CERTIFIED PAYROLL SUBMITTAL

Owners can use certified payroll submittals by their contractors for two very important
aspects of the project. First, by keeping a record of actual labor expenses, owners will be
better prepared to analyze and negotiate any claims where labor costs are an issue.
Second, by tracking actual labor expenditures against a resource-loaded schedule, owners
have an additional tool to assess progress and identify delays. With this information the
owner can anticipate delays and approach the contractor with data he/she generated to
negotiate a remedial action plan.

3.7.3 NEGOTIATED EQUIPMENT AND LABOR PRICING

Another way to gather information for faster dispute analysis and approval is for the
owners to negotiate with the contractor’s unit prices for equipment and labor before the
contract is awarded. With this information, owners can issue change orders and request
additional work while knowing the approximate cost implications of their decisions.
Moreover, contractors should provide more “honestly priced” change requests, since the
information has to be based on this schedule of values (Zack a, 1997).
In addition to equipment and labor prices, owners and contractors can agree on specific
unit prices for work items that will be typical for the type of project. For example, in a
renovation of an existing facility, both parties can agree on unit prices for items, such as
demolition, paint, clean up, and disposal of construction debris. These prices can then be
used as the project develops and unforeseen conditions require additional work.
Even though there are many nationally recognized equipment, labor, and work-item rate
schedules for costing, each job can vary significantly from the assumed conditions of
these sources of pricing information (Hoctor, 1989). Therefore, the parties should agree
to this information before hand and include it as part of the contract.
With the rates for equipment, labor, materials, and work items agreed upon before-hand,
parties can then concentrate on analyzing, for example, whether the crew-type or
equipment used were the most appropriate, whether the time used to complete the work
was not affected by other conditions, and whether the production rates used were
reasonable. Hence, the surprise factor (i.e., uncertainty) associated with change orders
that are priced after being executed can be eliminated.

3.7.4 JOINT PROJECT SCHEDULING

Zack (a, 1997) suggests that “...success is more likely if people become stakeholders.”
This is especially true for the project schedule, and “...one way to see that all members of
the project team become stakeholders in the schedule is to provide for joint project
scheduling.”
Instead of having the contractor prepare and submit for approval the schedule, the owner,
the contractor, the major subcontractors, and the suppliers participate jointly in the
development of the baseline program for the project. This joint development eliminates
any schedule games (i.e., hidden float, change of sequence, front-loading) and forces
parties into communication and collaboration during the planning stages.
Once everyone agrees on the joint timetable, and the job begins, updates are prepared by
all parties and will represent the consensus of everyone involved in the project. Delays
can be identified and negotiated as parties complete the schedule updates jointly, since
now they all have a ‘stake’ in what is presented to senior management. Schedule reviews
and change order impacts are also performed together, thus reducing the chances of

62
STAGE 1: PREVENTION

future delay claims and disruption disputes by one of the parties. The following example
clarifies the application of this technique and some of the benefits it can generate.

Nestle Chocolates Case


For the construction of an industrial plant in Cagua, Venezuela, the owner Nestle
Chocolates, Switzerland, and the contractor retained a scheduling consultant to develop,
update and control the schedule for the project 3. With the help and input of the
consultant, the parties generated a Master schedule that took into account both the critical
dates of the owner and the resources allocated by the contractor for the construction. As
the project began, each party assigned one engineer to follow the schedule, perform the
biweekly updates with the consultant, and present the results in the project meetings.
After two months into the job, a weekly joint scheduling meeting was organized to
review those areas that were behind schedule and to jointly resolve the problems causing
the delays. After each meeting, the consultant issued a report that presented the apparent
reasons for the delays and identified the responsible party. Since the schedule had
become a joint effort, these reports became a working tool for the team and helped solve
a number of problems without any discussions about claims.
Although the project had significant problems with regards to costs escalation and design
changes required by the home office of Nestle, the joint scheduling effort provided an
efficient tool to mitigate some of the effects of these changes. Both parties worked
together in analyzing each change and with the scheduling consultant determined the real
effects they had on the overall Master schedule. The project was completed one year
behind the original completion date, but no delay claims were filed at the end, since each
change was evaluated jointly and incorporated into the schedule as it occurred. The
consultant provided the necessary technical expertise, and gave the owner’s team a sense
of trust that allowed them to assume with the contractor the responsibility for the
schedule. The costs of developing the Master schedule and running the biweekly updates
were shared by both parties, even though in the tender documents, the contractor was
responsible for this activity.

3.7.5 SCHEDULE AUDITS

Monthly schedule updates are a common requirement in construction contracts. The


contractor presents, usually with the request for payment, a schedule update showing
progress made on the project. Two problems, however, can result from this approach.
First, the owner reviews schedule updates only once a month, so delays might be
identified as much as a month after they had become apparent. Second, the schedule may
become just another hurdle towards achieving payment, so it is assigned a secondary role
in the management of the project. 4
To avoid this, owners should first separate payment request, which can include an
updated schedule, from the ‘real’ schedule updates and reviews. The owners should
request weekly or biweekly schedule updates. Since most contractors generate not only
weekly lists of the activities that should be accomplished the following week but also a
list of the unfinished activities from the previous week, the requirement can be as simple
as to demand a copy of this information, in order to avoid generating additional
scheduling expenses for the contractor.

3.7.6 AS-BUILT SCHEDULE SUBMITTAL

Following the same logic as the Cost Statement Submittal (Section 3.7.1), owners can
request an as-built schedule from the contractor before issuing the certificate of final

DRAFT 2/4/2017 2:32:00 PM 63


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

completion and releasing the retention. As with the certified cost report, the as-built
schedule becomes the basis for review of any after-completion claims. By submitting a
schedule that reflects the actual construction sequence and total duration, the contractors
will be discouraged to submit, at a later date, delay claims that were not previously
shown. If the contractor has plans to present any delay claims at the end of the project,
they will have to address them in the as-built schedule, and they will be required to arrive
at a settlement prior to receiving the final completion certificate.

3.7.7 FORWARD-PRICE CHANGE ORDERS

Impact or indirect costs like home office overhead, field staffing, or overtime work, that
can be associated to change order work beyond hard costs (i.e., labor, equipment, and
materials), have been identified as an additional source of disagreements in change order
pricing. To improve negotiations and reduce the amount of disagreements, owners and
contractors can agree beforehand on the guidelines and methods to determine and limit
these impact costs. Zack (a, 1997) suggests that a set of impact factors can be developed
for issues like “timing of changes, number of trades involved, effect on the schedule,
effect on office and field staffing, and the cumulative nature of the disruption.”
When change orders are priced and negotiated, owners and contractors will be able to
incorporate in the total amount, both hard costs and impact costs, and they will be able to
settle on a final adjustment to the contract value. Consequently, no further discussions or
claims will be required after these negotiations because the changes will include
everything (ENR, 9/11/1995). An example of a forward change order is presented in
Chapter 5.

3.7.8 RIGHT OF REFUSAL ON CHANGE-ORDER COST QUOTATIONS

When contractors price change orders, which in most cases is a contract obligation, they
usually include “reservation-of-right” language to allow themselves future requests for
additional time or money to complete the job. In other words, contractors include a
disclaimer such as “...further review is necessary in order to assess the impact this
change will have on the schedule’s sequence of activities and the overall project
duration” 5, with the intention of leaving the door open for future review. In fact, most
contractors feel the need to include such provisions in their change order cost proposals,
for they have not really completed a total assessment of the time and cost implications of
the change requested by the owner.
To overcome this situation, owners should allow contractors to refuse to quote the change
order if they can not guarantee zero-impact to the project duration. If the contractor sees a
possible delay arising from this change order, such delay will have to be identified and
negotiated before having the order executed. This technique has the added benefit of
forcing the on-site owner’s representative to deal with delay issues caused by the owner,
as they are identified, and change orders are issued for pricing and negotiation.

3.7.9 SUB-CONTRACTOR PAYMENT REQUIREMENTS

In order to guarantee that project funds reach subcontractors performing work for the
prime contractor, owners include in the contract special clauses to that effect. Under these
clauses, the owner establishes payment provisions for the prime contractor, which require
certification that the subcontractors are being paid for the work being invoiced. In
addition, if the prime contractor fails to pay the subcontractors in a timely and proper
manner, owners retain the right to make direct payments to subcontractors and deduct

64
STAGE 1: PREVENTION

those sums from future disbursements to the prime contractor. Therefore, owners can
assess the risk of disruption due to lack of payment to the subcontractors and act to lessen
the chances of delays without having any direct contractual relationship with the
subcontractors.

3.8 DISPUTE RESOLUTION CLAUSES


As documented throughout Chapter 2, disagreements are a common trait of construction
projects, and they can lead to disputes and claims if not handled appropriately. Hence,
owners can go a long way towards mitigating their effects by including specific clauses in
the contract documents that identify and describe the way those disagreements will be
resolved. Owners have to address this issue of disputes and be prepared to manage them
in the most cost-effective way possible. According to Vorster (1993), contracts that leave
the dispute resolution process undefined, fail to provide alternatives to litigation.
Moreover, they may foster a faster evolution of simple job-site disagreements into
complicated disputes. The partnering approach to construction projects, reviewed in
Chapter 4, considers as one of its Key Components (Section 4.3) the early definition of a
dispute resolution system for these same reasons.
As part of this definition of a project specific DRL, parties should also proceed to select
by mutual agreement any third party neutral (i.e., facilitator, mediator, conciliator,
advisor, and dispute review board members) to avoid having disagreements that affect
their ability to choose the best candidate to help them resolve disputes.
By agreeing on the mechanism to resolve their disputes before they arise, parties, first are
providing the tools to the construction team to address and resolve disagreements before
they develop into disputes, and second, they are setting the stage for a more flexible
process, with greater trust, and fewer uncertainties, resulting in better overall job
performance (Vorster, 1993).

3.9 TRAINING AND DEVELOPMENT


Traditionally it was assumed that negotiation skills were inherited and that they could not
be trained. However, in recent years universities and professionals have begun to
examine the negotiation process in detail as described in the introduction of this chapter,
developing programs to improve the negotiation skills of individuals in both professional
and non-professional contexts.
People issues have been already identified as a source of disputes in construction.
Moreover, Miles (1996) states that although the lower steps in the corporate ladder
“...are the best able to make timely, informed decisions, they are generally not as skilled
in interpersonal relationships, negotiation, and dispute resolution.” Thus, it follows that
the development of personal skills through formal training in dispute prevention and
resolution, communication, and negotiation becomes a key ingredient of any successful
ADR program. As this knowledge moves down to the parties responsible of conducting
actual negotiations, the overall process will speed up because adversarial and adjudicative
approaches will less likely play a part in the resolution of problems.
In addition, new delivery systems like PEpC (Section 3.4), and innovative operating
philosophies like Partnering (Chapter 4) represent important changes in the mind-set of
the people in charge, so they require training. For example under a PEpC contract,
important purchases will be based on performance requirements rather than detailed
design information, completely changing the standard procurement procedure. With

DRAFT 2/4/2017 2:32:00 PM 65


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

regards to partnering, Larson et al. (1997), identified the lack of understanding of the
partnered system as one of the main barriers for its successful implementation. All these
new systems and tools must be taught at all levels and understood by key players in order
to maximize their benefits. Some of them will even require special, dedicated training
before they can be effectively incorporated into the project.

Office Going back to the office-building project, to combat conflicts that arose from these issues
previously mentioned, the owner implemented some preventative measures. The owner
Building
selected a GMP style contract for a couple of reasons. As design was not complete and
Project change evident, a GMP allowed the flexibility of implementing these changes without
changing the upper ceiling cost. This is possible in a fixed price contract, but the majority
of changes will result in a price increase. In addition to a GMP, the owner proposed a
50/50 shared savings of the money under the GMP with the contractor. This incentive
kept the contractor honest when pricing changes and add-ons. The architect had to be
honest as well when specifying material, as they reviewed and negotiated long lead items
with he contractor.
With the numerous parties involved, a solid organizational structure kept
miscommunications to a minimum. The contractor set up a chain of command,
performing phone conversations with the owner on a daily basis. To reduce confusion
and increase communication on-site, the GC held daily meetings with all the
subcontractors. This brought everyone up to spend on what was going on throughout the
job. Those who attended had the authority to act of behalf of their company for the day-
to-day operations. If a minor problem came up a change in the schedule, it was resolve at
these meetings. Workarounds were scheduled and conflicts were resolved. In addition to
the daily meetings, an on-site inspector for the structural designer made is possible to get
instant clarification of the design. This was a major time saving measure as it cut out the
length “Request for Information” process typically used. The architect also visited the
site once or twice a week.
As mentioned, there was no flexibility in the schedule. In this respect, the owner included
large liquidated and real damages contractor if contractor did not deliver the product on
schedule. This US$ 100 million job was managed by the contractor with only 2
superintendents. Meetings everyday, 50/50 shared savings and the threat of liquidated
damages all aided in delivering this project on time and under budget.

3.10 SUMMARY
Early identification of possible areas of conflict for a specific project is the basic premise
of this first stage in the DRL. Prevention is based on the assumption that it is more
effective, less expensive, and less time consuming, to prevent conflicts from arising than
to solve them once they have progressed and escalated. The prevention stage allows the
owner to tailor a Dispute Avoidance and Resolution system, which recognizes the
possible sources of disputes of the project and provides procedures to resolve them;
reducing the chances of having disputes escalate to legal battles. Prevention enhances
interconnection between team members and increases collaboration throughout the
executive phase.
The vast array of dispute prevention mechanisms presented in this chapter confirms the
fact that this stage of the Dispute Resolution Ladder provides the greatest flexibility of
action to the parties, while in the long run reduces the cost and time required for conflict
resolution. This flexibility allows parties to choose among multiple DART, those that
best fit the needs and resources of a particular endeavor. Each group of prevention

66
STAGE 1: PREVENTION

techniques addresses differently many of the sources of conflict in the construction


industry, previously defined in Chapter 2.
The importance of appropriately evaluating bids and creating good designs, the benefits
of adequate risk and uncertainty sharing, the role of the owner in reducing conflict among
parties, the relevance of incorporating mechanisms in the contract to help address areas of
possible conflict, and the positive valence of incorporating incentive programs to achieve
objective alignment and team building are among the most salient areas addressed by
these techniques. Clear and adequate communication among the parties, owner
involvement, and alignment of objectives are three crucial variables found to be common
denominators of the different prevention techniques.
Still, despite the multiple advantages of the prevention stage, investment on prevention is
not always an easy task. Prevention requires the recognition of a potential threat and a
commitment to avoid it, even if the negative consequences of the dispute have not yet
developed. The fantasy and “naïveté” of the parties involved, combined with inadequate
knowledge of the advantages of many prevention techniques, might drive owners and
constructors to believe “that the worse will never happen” to them, thus choosing not to
invest resources in this stage and planting the seed for future problems.
Between Prevention and the next stage of the DRL, Negotiation, Chapter 4 reviews the
concept of Partnering in construction projects. This system recognizes conflict as an
intrinsic aspect of this industry and establishes an approach to prevent it, and to solve
those disputes that do occur, strengthening lines of communication and collaboration that
foster win/win negotiations. Although Partnering is not a stage in the DRL, its basic
premises can be successfully applied to enhance the benefits of many dispute avoidance
and resolution techniques along then ladder.

3.11 POINTS FOR DISCUSSION


3.1 Defend or argue the opening quote of the chapter, “For every $1 you spend on
claims management during the front-end of the project, you save at least $20 to $25
in claims during construction.” Assuming this is true, is fast-tracking a project an
ingredient for making claims?
3.2 Escrow bid documents (Section 3.3) are said to be a “clean” set of documents, but
to what extent are they too clean? What information must be kept in this set? Should
this include ongoing documentation throughout the construction process?
3.3 How does a third party beneficiary clause (Section 3.2.3) reduce the risk of an
owner?
3.4 The four innovative project delivery systems presented (Section 3.4) are only a
small fraction of systems used. Cite others methods and their
advantages/disadvantages relating them to disputes and claims?
3.5 What legal recourse might an As-Built submittal schedule (Section 3.7.6) have?
What does this submittal deter the contractor from doing?
3.6 Does the right of refusal on change order (Section 3.7.8) increase or decrease the
number of conflicts between the owner and the contractor? Is it optimal to pin a
contractor to a zero-impact for the project duration?
3.7 In Case 3.2, it states, “the costs were high, but the facility met the scheduled
deadline.” Is it true that any schedule can be met if cost is not an issue?

DRAFT 2/4/2017 2:32:00 PM 67


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

3.8 Engineering document review is a crucial but often overlooked process. With faster
schedules and constant approaching deadlines, what are some ways to improve this
review process? Should the contractor be involved in the design stage and review
process? Can this be accomplished in the design-bid-build procurement model?
3.9 What should the owners’ role in the construction process be? If they take and active
role, how much does this open them up for liability if things go wrong and vice-
versa, if they do not take an active role?
3.10 “Some contractors underbid projects banking on the premises that they can make up
the deficit in change orders and claims.” Is this a valid statement? Is this strategy
generated by the contractors, or forced upon them by the competitive nature of the
industry and the owners? How does a public owner prevent this from happening?

3.12 REFERENCES

[Appelbaum, 1998] Appelbaum, Jeffrey. "Bridging" the Design-Build Gap. DPIC


Companies, Inc. Loss Prevention Library. Downloaded from
the web on March 3, 1999, www.dpic.com.
[CE, 1995]
Civil Engineering, (1995).

[CII 114-1, 1998] Construction Industry Institute. Innovative Contractor


Compensation. Research Summary. Report 114-1 September
1998.
[CII 130-1, 1998] Construction Industry Institute. Reforming Owner, Contractor
Supplier Relationships: A Project Delivery System to Optimize
Supplier Roles in EPC Projects. Research Summary. Report
130-1 September 1998.
[ENR 2, 2/15/1999] Engineering News Record. Sports Construction. Substitutions
at "Half Time" don't Delay Toronto Arena Job. McGraw-Hill,
New York. p. 19, Feb 15, 1999.
[ENR, 9/11/1995] Rosenbaum, David. Change Orders Organized. Engineering
News Record. McGraw-Hill, New York. Vol. 235 (11) p. 20.
September 11, 1995.
[Fenn et al., 1998] Fenn, Peter, O’Shea Michael, and Davies Edward (1998).
Dispute Resolution and Conflict Management in Construction
an International Review. E & FN Spon, London, ISBN 0-419-
23700-3
[Findley, 1997] Findley, Douglas. Construction Claims Preparation Under
ADR. 1997 AACE International Transactions C&C.01.1-
C&C.01.4. 1997.
[Hoctor, 1989] Hoctor, David,(1989). Techniques for the Resolution of Major
Construction Contract Disputes. Public Utilities Fortnightly
Vol. 123 (9) pp. 26-30. April 27

68
STAGE 1: PREVENTION

[Howard et al., 1997] Howard, William E., Bell, Lansford C., McCormick, and
Robert E., (1997). Economic Principles of Contractor
Compensation. Journal of Management in Engineering. Vol. 13
(5). pp. 81-89, Sep./Oct 1997.
[Kluenker, 1995] Kluenker, Charles. The Construction Manager as Project
Integrator. Journal of Management in Engineering, Vol. 12, No.
2, March/April 1996, pp. 17-20
[Larson et al., 1997] Larson, Erik, and Drexel, John, (1997). Barriers to Project
Management: Report from the Firing Line. Project Engineering.
Vol. 28 (1) pp. 46-52. March
[Miles, 1996] Miles, Robert. Twenty-First Century Partnering and the Role of
ADR. Journal of Management in Engineering Vol. 12 (3) pp.
45-55. May/June 1996
[Shen, 1997] Shen, L. Y., (1997). Project Risk Management in Hong Kong.
International Journal of Project Management, Vol. 15 (2). pp.
101-105. April
[Skelhorn, 1998] Skelhorn, Steve. Partnering to Success in Toronto (Sheppard
Subway, Toronto, Ontario). World Tunnelling and Subsurface
Excavation. Mining Journal Ltd. (UK).12/01/1998.
[Smith, 1995] Smith, John A., (1995). Construction ADR: You Get Out What
You Put In. Dispute Resolution Journal pp. 27-30. July
[Stipanowich, 1997] Stipanowich, Thomas. At the Cutting Edge: Conflict Avoidance
and Resolution in the US Construction Industry. Construction
Management and Economics. Vol.15 (6) pp. 505-512.
November, 1997.
[Vega, 1997] Vega, Arturo Olvera. Risk Allocation in Infrastructure
Financing. Journal of Project Finance Vol. 3 (2) pp. 38-42.
Summer, 1997
[Vorster, 1993] Vorster M. C., (1993). Dispute Prevention and Resolution.
Construction Industry Institute. Virginia Polytechnic Institute &
State University. Source Document 95. October
[Zack a, 1997] Zack, James G., (1997). Claims Prevention: Offense Versus
Defense. AACE. Vol. 39 (7) pp. 23-28. July

3.13 ENDNOTES

1
The total scope of work for a 10-year project to design and build a facility to control
floods in a region in the Netherlands under a Frame Contract System stated the following:
“The execution of works for the realization of the storm surge barrier in the mouth of the
Eastern Scheldt between the islands of Schuwen Duiveland and Noord Beveland, with
additional works in the municipalities of...” (Goudsmit, 1985).
2
The International Construction Law Review, originally published by Lloyd's of London
Press, now known as Informa Professional, a trading division of Informa UK Limited,

DRAFT 2/4/2017 2:32:00 PM 69


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Gilmoora House, 57/61 Mortimer Street, London W1W 8HS. Tel: +44 (0)20 7453 2198
Fax: 020 7453 2274.
3
An author of this book was the Project Manager for the contractor in this project.
4
In a recent project, an author of this book found a significant difference between the
monthly schedule updates submitted to the owner and the actual as-built schedule kept by
the contractor. When questioned, the contractor explained that the submittal was a
payment requirement, and that he could not afford to have payments delayed because of a
disagreement on the sequence of construction or because it showed delays due to design
changes. According to the contractor, those problems were going to be addressed at a
later date.
5
Taken from a change order letter of a contractor to an owner in a project where an
author of this book participated in.

70
C H A P T E R

4
PARTNERING
“[Partnering is] a method of transforming
contractual relationships into a cohesive, project
team with a single set of goals and established
procedures for resolving disputes in timely and
effective manner.”
Larson (1995)

A museum in the Northeastern United States was losing money year after year and was in
danger of closing because it lacked the ability to attract new customers. The museum had
not under gone any recent capital improvement because of its lack of funding. This
museum is a publicly funded, not for profit organization. After a desperate plea from the
board of directors to the state government, $900,000 was allocated to cover construction
cost for an expansion project. The budget was not flexible and no additional money was
available from other sources. Since the money came from public funding, the delivery
system was restricted to design-bid-build so that a fair competition would be held and the
owner would receive a fair price.
To attract new customers, the expansion that was proposed included additional space for
artwork as well as cafeteria. A local designer proposed a custom artistically designed
addition, contrasting the existing bland 30-year old functional structure. The design

CHAPTER LOOK AHEAD


WHAT IS IT? Partnering is a voluntary, non-binding process, in which all participants come together as a
team, focused on principles rather than rules, allowing trust to develop. Partnering has become much
more than an ADR technique, by developing into an alternative method of operating a business
relationship, a new philosophy in which two or more organizations make long-term commitments to
achieve mutual goals by entering into an agreement that requires a team-approach.
WHO IS INVOLVED? Partnering involves the participation of all parties. It is crucial for senior
management of these parties to be committed, as lack of commitment breed failure. At a project level,
participants should be trained on partnering philosophy. Each participant must clearly understand the
role played within the partnership and how their performance will influence the results of the efforts
WHY IS IT IMPORTANT? If trust is developed, a synergistic atmosphere results in which productivity
increases. This is opposite of the adversarial situation previously discussed and all too common in the
construction industry. If implemented correctly it can align objectives significantly, reducing conflict.
HOW TO APPROACH IT? Develop a strategy. Train the participants. Build the partnering atmosphere.
Implement strategy on-site. Hold meetings to review progress. Close-out and reflect on effectiveness.

KEY CONCEPTS
Partnering Defined .........................................72 Partnering Process............................................. 75
Key Components ...........................................76 Partnering Continuum ....................................... 78

71
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

specified glass and colored ceramics stone, large spans, exactly the opposite of what
existed, with the intent to change the image of the museum. As a result of the design-bid-
build process, the design and drawings were prepared without any involvement of the
contractor. The estimate submitted by the designer met the $900,000 budget requirement
on paper, but everyone involved up to this point focused more on the look than the reality
of cost and budget. The design was completed and publicly bid, under state regulations.
Bidders picked up drawings, and submitted bids, with the intention that the award would
go to the lowest bidder. Four bids came in at $1.2, $1.25, $1.4 $1.5 million. The
procurement process was successful in the sense there was ample competition and the
bids were relatively close for the design, but the money was not available to award the
project to the lowest bidder of $1.2 million.
At this point, the owner hired an additional consultant, knowledgeable in construction to
overcome the owner’s lack of familiarity with construction. With no extra money
available, how might the owner go about lowering the cost of constructing the design? If
the owner asks the designer to make changes to reduce the cost, should there be another
competition to decide the lowest bidder? Should it be awarded to the lowest bidder and
then value engineered with the designer? The second lowest bidder submitted a close
competitive bid, if the design is awarded, then changed can the bid be protested? How
might bringing together the designer and the contractor on the same team affect the price?

4.1 DEFINITION AND BENEFITS OF PARTNERING


This chapter provides a review of the concept of Partnering, which developed within the
construction industry as a response to the problems associated with the traditional
adversarial approach assumed by most parties in projects. The first popular use of
partnering dates from the mid-1980’s between a large chemical manufacturer and a
contractor. The first government agency to adopt partnering was the Army Corps of
engineers in 1988. The adversarial approach traditionally used in construction results in
poor communication and cooperation that leads to cost and schedule problems and
possibly arbitration or litigation.
Partnering is a complete system of operation in the construction environment; therefore it
is not considered a Stage of the Dispute Resolution Ladder (DRL). However, the
introduction of the concept of partnering in this book is based on the consideration that
many of the key principles of this system of operation are congruent and similar to those
principles that support the prevention and negotiation stages 1. Partnering promotes open
communications and exchanges of information, encourages collaboration, helps develop
trust among the parties, forms and supports the project team, aligns the objectives of team
members, and in general, improves the entire construction process by proposing a new
way in which team members interact and communicate at every level of the project
relationship. Partnering fractures the common adversarial approach in construction
projects by “…replacing deception with open communication, delays with timely
decisions, factionalism with synergy, litigation with joint problem-solving, and win/lose
with win/win 2” (Larson et al., 1997). Partnering, as a model of interaction and
communication between the parties, provides important additions to the DRL system,
which could expand and guide its implementation.
Partnering has caught the eye of the construction industry, and it currently seems to be
adopted faster than any other improvement process introduced in the industry. Partnering
has become much more than a Dispute Avoidance and Resolution Technique, by
developing into an alternative method of operating a business relationship, a new
philosophy in which two or more organizations make long-term commitments to achieve
mutual goals by entering into an agreement that requires a team-approach. Partnering is a

72
PARTNERING

voluntary, non-binding process, in which groups of people from different organizations


come together as a team focused on principles rather than rules, allowing trust to develop.
Studies by the Construction Industry Institute have shown that increased trust results in
improved productivity, which in turn reduces cost and schedule problems that lead to
litigation (AAA, 1996). Partnering changes the cultural and business framework in which
parties interact to complete a project.
Multiple definitions of partnering have been developed throughout the years by
researchers and industry organization. The Construction Industry Institute defines
partnering as follows:
“A long term commitment between two or more organizations for the purpose of
achieving specific business objectives by maximizing the effectiveness of each
participant’s resources. This requires changing traditional relationships to a
shared culture without regard to organizational boundaries. This relationship is
based on trust, dedication to common goals and an understanding of each
other’s individual expectations and values.”
(CII, 1991)
By developing common goals and an understanding of each parties’ needs and individual
objectives, parties involved in a project address some of the reasons behind construction
disputes identified in Chapter 2 (i.e., lack of objective alignment, unrealistic expectations,
poor communication, misunderstandings, and lack of team spirit). Cowan et al. (1992)
definition of partnering, stresses the importance of aligning the objectives, but adds the
requirement for dispute resolution mechanisms as a key in the partnering model:
“[partnering is] a method of transforming contractual relationships into a
cohesive, project team with a single set of goals and established procedures for
resolving disputes in timely and effective manner.”
In this definition, the importance of addressing procedures to resolve disputes focuses on
one of the organizational issues, in specific process problems, identified in Section 1.1, as
a characteristic that makes the construction industry prone to disputes. The need to
develop one set of goals for the entire building team focuses on the problem of objective
alignment reviewed in Chapter 1 as another source of conflict and dispute among
members of a project.
The review of these definitions of partnering brings about the similarity between this
system and the prevention stage in the DRL. Alignments of objectives, clear
communication, integration among team members, and incorporation of DART as part of
the relationship, are among others, core components of Partnering as well as of
Prevention.
The following excerpt from a sample Partnering specification developed by Groton
(1997) shows the level of commitment demanded from the parties, and the working
environment being pursued by this approach:
1) “Each party will function within the laws and statutes applicable to their duties
and responsibilities;
2) Each party will assist in the other’s performance;
3) Each party will avoid hindering the order’s performance;
4) Each party will proceed to fulfill its obligations diligently;
5) Each party will cooperate in the common endeavor of the contract.”
These levels of commitment are demonstrated in the following examples.

DRAFT 2/4/2017 2:32:00 PM 73


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Pedestrian Bridge (Sherbrooke, Quebec)


This commitment to a common endeavor, cooperation, and assistance between parties is
allowing the introduction of new concrete technology in Canada. A partnership between
Bouygues SA, the University of Sherbrooke, Quebec, and the US Army Corps of
Engineers has proposed the use of a 50,000 p.s.i. concrete mix known as Reactive
Powder Concrete (RPC) in a Canadian footbridge over the Magog River in Sherbrooke,
Quebec. Bouygues of France, developed RPC, and has used it in beams and pipes in
Europe, so far achieving 29,000-p.s.i. compressive strength. The Army Corps of
Engineers has used RPC in pipes, poles, beams, precast piles, and girders. Nevertheless,
according to ENR (9/9/1996), its use in the Canadian footbridge would be the first
application in a complete structure. The partners have agreed to a three-year study to
determine RPC’s conformity to codes, to lower the costs of the mix, now at about 10
times that of normal strength concrete, and to increase its use throughout the industry.
In this example, partnering is going beyond a single-project method for improving
relationships and communication. This partnering alliance is promoting technological
innovation in the field, as parties are sharing the risks associated with introducing the
RPC state of the art concrete technology in projects. Furthermore, this example shows a
long-term international association of private, public, and academic organizations with
significantly different objectives that through partnering are working together to develop
this technology.
The following three cases further confirm the benefits of partnering in construction
projects.

Central Artery and Tunnel (Boston, Massachusetts)


A study conducted by Gilleland et al. (1998) compared partnered and non-partnered
projects within the multi-billion dollar Central Artery and Tunnel Project in Boston. The
survey found that partnered projects outperformed non-partnered ones in each of the
following performance categories: Cost Growth, Schedule Growth, Number of Change
Orders, and Value Engineering Savings. When team members for these projects were
surveyed, 100% of Area Managers considered partnering to be beneficial, 75% of
Resident Engineers rated communication in their contracts as ‘excellent to good’, and
80% of the Project Managers described the resolution of issues as satisfactory. Team
members in the partnered projects considered that partnering led to fewer written
exchanges and more verbal agreements, which were honored by the parties. In addition,
communication was rated to be “excellent to good” by most respondents from various
sides (i.e., contracting agency, construction manager, and contractor).

Bus Garage (Cleveland, Ohio)


In the construction of the New Bus Garage in East Cleveland, Ohio, for the Regional
Transit Authority, partnering had similar results. Richard Mayer, project manager for the
job, stated that 98 % of the problems in the project that could have resulted in arbitration
or litigation were resolved at the lowest possible level with the help of partnering (DRT,
1998). This shows how one of the direct results of partnering is a reduction in litigation.
Problems are resolved at the jobsite level without the need of third party binding
decisions (i.e., arbitration and litigation).

Correctional Facility (San Diego, California)


In a 21-story facility in downtown San Diego, partnering has allowed the tenant of the
facility to participate in all aspects of construction and provide important input that
reduced rework and last minute change orders at the end of the project (DRT,

74
PARTNERING

1997/1998). The facility was built under the supervision of the final user (i.e., tenant)
thanks to partnering between the State agency managing the project and the main
contractor. No special contracts were required to incorporate the tenant in the
construction process, as both the manager and the builder are benefiting from its input.
Both the Canadian example and the three US projects represent a few of the many
successful experiences of partnering in construction projects. The common themes in all
of them are improved communication, objective alignment, cooperation, and trust. The
following sections review the partnering approach in further detail presenting the phases
of its implementation, as well as its key components.

4.2 THE PARTNERING PROCESS


The phases of a successful partnering process can be summarized as follows, based on
recommendations by the American Arbitration Association (AAA, 1996):
Phase One: A Long Term Strategy – Senior management defines a long-term
vision with supporting strategies and measurable goals and objectives.
Resources are allocated towards achieving the goals. Leadership, planning, and
partnering sessions are conducted to prepare the organization for the cultural
change. This phase also defines the level of commitment by senior management
to the partnering process. Failure of top-management to endorse and support this
long-term strategy has been previously identified as a barrier for successful
partnering
Phase Two: Training – Project participants receive specific training on
partnering and learn the strategy developed and set forth in the previous phase.
Each participant must clearly understand the role played within the partnership
and how his/her performance will influence the results of the efforts. Lack of
understanding of the strategy and the partnering process may result in parties
returning to the usual adversarial stance when relationships are strained due to
normal project disagreements.
Phase Three: Team Building – workshops and meetings are scheduled at a
neutral site to begin the team building process to develop trust and open
channels of communication. As part of this phase, participants develop the
Project Charter and the Issue Resolution Process, together with mechanisms and
procedures for continuous review. In this phase, the project team develops
common objectives (i.e., alignment). This phase should happen at the beginning
of the project, and should involve all key personnel.
Phase Four: On-site Implementation – Partnering activities reach a peak during
this phase. Key activities of this phase are:
o Regular partnering meetings.
o Biweekly or monthly assessment evaluation and feedback using the
Project Charter as the basis, to monitor the relationship and the level of
objective alignment.
o Use of the Issue Resolution Process to solve technical and financial
issues, adjusting it to meet new conditions that might develop through
project implementation.
o Promotion of innovation and creative problem solving.
Phase Five: Project Close-out – When partnering has been carried out correctly,
the results can be very beneficial to all parties as in the Central Artery project
described above. At close-out, parties should identify the successes and failures,

DRAFT 2/4/2017 2:32:00 PM 75


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

and the improvements made throughout the process to incorporate these


experiences into their individual as well as joint long term visions.
Each of these phases and activities which have been summarized above, are critical in the
success of the partnering effort, and therefore of the project. Partnering efforts that are
implemented only halfway will not achieve the levels of success reported by many
partnered projects.
The partnering process starts even before an actual project contract is awarded, as shown
in the first two phases. Partnering requires certain efforts from participants. These include
a long-term commitment to the principles of trust, communication, and collaboration, so
companies and agencies are required to establish long-term visions that support this
commitment and train their personnel in this new philosophy of operating a construction
project. The issue of training and development of human resources for the success of
partnering is critical, because of the significant changes this process incorporates into the
construction activity.

4.3 KEY COMPONENTS OF PARTNERING


The following are the minimum components of any successful partnering approach as
developed by the American Arbitration Association (AAA, 1996), because they provide
focus, follow-up, and accountability for all the team members:
Project Charter: This is the equivalent of a Mission Statement with a list of
common project goals. All parties sign the final version of the Project Charter
and the objectives, and it is posted throughout the job site, meeting rooms, and
offices. Figure 14 presents an example of an actual Project Charter for a project
with the Environmental Protection Agency (EPA) in the US.
Team Assessment: Biweekly or monthly meetings are scheduled with all parties
to review the status of the partnered relationship and the objectives. Written
surveys allow an assessment of the levels of trust, communication, and objective
alignment perceived by team members.
Issue Resolution Process: Critical in the process of developing the partnering
relationship is the definition of the system for “Issue Resolution.” Parties should
be committed to identify and resolve problems at the lowest possible levels of
the organization. Problems should never become disputes, but if they do, the
process to resolve them, and the tools available to the responsible parties should
be clearly defined (i.e., Dispute Resolution Ladder).
Job Closeout: Once the project is completed and no outstanding issues are
pending, parties should proceed with a review of their achievements through the
partnering process. The original Project Charter should be compared with the
actual results; successes and failures in the relationship should be identified and
understood by all parties; and improvement plans should be drafted for
implementation in future projects. This after-the-fact review enables the parties
to further develop the partnering concept and learn from their mistakes.
As a system, these key components support the partnership as follows. The Charter is the
blue-print for the relationship, parties become stakeholders of the joint objectives which
they have signed, and decisions and disagreements are always compared and measured
against this original set of guidelines and compromises. Through the development of the
Charter, common goals are defined between the parties, while they also become aware of
each other’s individual interests in the project. This will allow the building team to
conduct any negotiation based on these needs and goals, rather than contractual
requirements. 3

76
PARTNERING

“PARTNERING AGREEMENT
WE, THE BON FOUCA SUPERFUND PROJECT TEAM, COMMIT TO WORK TOGETHER WITH A
SPIRIT OF OPENNESS AND TRUST, AND TO RESPECT THE GOALS AND NEEDS OF THE
STAKEHOLDERS.

OUR TEAM IS FOUNDED ON PRINCIPLES OF:

TEAMWORK, MUTUAL RESPECT, OPENNESS, HONESTY, TRUST, PROFESSIONALISM,


UNDERSTAND ONE ANOTHER’S POSITIONS, WALKING THE TALK”

WITH THE OBJECTIVES OF:

• COMPLETING THE PROJECT ON SCHEDULE


• COMPLETING THE PROJECT WITHIN BUDGET
• DEVELOPING AND MAINTAINING GOOD COMMUNITY RELATIONS BY MINIMIZING
IMPACT TO THE COMMUNITY AT LARGE AND COORDINATING ACTIONS THROUGH
EPA HEAD
• PURSUING SHARED SAVINGS THROUGH VALUE ENGINEERING
• DEVELOPING AN MAINTAINING AN AWARENESS OF SAFETY – DAILY THROUGHOUT
THE PROJECT – IN ORDER TO ACHIEVE ZERO LOST TIME ACCIDENTS
• ESTABLISHING A FORTHRIGHT APPROACH TO MODIFICATIONS AND CLAIMS IN
ORDER TO AVOID LITIGATION
• REMEDIATING THE SITE IN ACCORDANCE WITH THE NATIONAL CONTINGENCY
PLAN
• IMPLEMENTING TOTAL QUALITY MANAGEMENT CONCEPTS, SPECIFICALLY IN
ADMINISTRATION, ENGINEERING, CONSTRUCTION, AND OPERATIONS
• PROVIDING CONTRACTORS THE OPPORTUNITY TO MAKE A REASONABLE PROFIT
• ENHANCING REPUTATIONS OF THE STAKEHOLDERS WITH RESPECT TO PUBLIC
PERCEPTION OF REMEDIATION/SUPERFUND EFFORTS

WE, THE UNDERSINGED, IN AN EFFORT TO ACHIEVE THE INTENT OF THE PARTNERING


PROCESS, COMMIT THE ABOVE PRINCIPLES AND OBJECTIVES.”

Project Charter signed and stamped by each stakeholders

Figure 14 – Sample Project Charter (Ellison et al., 1995)

The Team Assessment is both a quality control mechanisms and a quality improvement
tool. As the project develops, new objectives can be added and original ones modified
through these review sessions. These sessions also foster communication. The meetings
and surveys should encourage a greater acceptance of the partnership philosophy, which
in turn should translate in greater benefits for the project. These follow-up sessions are
the basis for improving the system during the life of the project, and adapt the philosophy
to project and team conditions.
The Issue Resolution Process is a tool to help the partnership overcome disagreements
and disputes that will still develop during the project. Unresolved issues will undermine
the partnership, prevent parties from achieving the common objectives, and foster
adversarial positions that will increase the chances of litigation (see first example in
Section 4.4). Finally, the Job closeout review provides an opportunity for assessing the
benefits of partnership, and to develop improvement measurements for other projects.

DRAFT 2/4/2017 2:32:00 PM 77


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

During these meetings, participants can evaluate future opportunities for collaborative
work, and even establish a long-term set of objectives towards the execution of that work.
This project closeout further strengthens the use of partnering, as parties will learn from
their mistakes and improve its implementation.

4.4 THE PARTNERING CONTINUUM


According to a CII report that surveyed more than 1,000 projects associated with this
type of relationships, the term “partnering” is being applied to a wide array of
management and contractual arrangements (Thompson et al., 1998). Partnering has
grown to include a number of different management approaches and contract
relationships, although some fall short of being a real partnered project. Thompson et al.
(1998), proposed the Partnering Continuum to address the many “shades” of partnering
forms found in the field, while Ellison et al. (1995) developed the Synergistic Strategic
Partnership Model to present these different levels of partnership. The continuum
proposed in Figure 15 is based on the degree of alignment of the individual objectives of
each of the parties involved.

Coalescence
(Synergistic Strategic
Partnering)
Collaboration
High (Value-Added
Integrated Team)

Cooperation
Potential (Collaborative)
Benefits of
Partnering
Partnering
Competition
(Adversarial)

Low

Low Degree of Objective High


Alignment

Figure 15 – Partnering Continuum (Thompson et al., 1998) 4

78
PARTNERING

Table 10 – Summary of Partnering Levels


(based on Thompson et al., 1998 and Ellison et al., 1995)

Project COMPETITION COOPERATION COLLABORATIV COALESCING


Characteristic (Adversarial) (Collaboration) E (Value-Added) (Synergistic)

One set of goals for a Total alignment of


successful project. objectives. Goals
Each side has well
Long-term goals and objectives are
defined objectives
Responsibilities Common objectives beyond single shared, including
and responsibilities.
and Objectives that are specific to application. cost information.
Objectives are not
the project. Typically includes Increased
common; might be
incentive for accountability.
conflicting.
exceeding project Autonomy in
goals. decision making.

Some degree of
Level of Trust Very high levels of
Little trust between trust, in order to
between Parties High degree of trust. trust. Transparent
the parties. work for the
interface.
common objectives.

Openness, honesty.
Extensive
Single points of Senior level
High degree of communication,
Level of contact within the “champions” from
communication. collaboration and
Communication organizations. both organizations
Multiple points of commitment from
Owner supervises foster
contact. all levels of the
contractor. communication and
organization.
remove “barriers.”

Integrated team of
client and contractor
Adversarial.
personal and Transparent
Primarily a
Improved resources. Team interface. Parties
Type of defensive position.
interpersonal creates separate share resources and
Relationship Coercive
relationships. organization for the cultures are
environment.
Cooperation. life of the project. integrated to fit the
Short-term focus.
Long-term focus applications.
multi-project, with
shared authority.

Joint sharing of
Limited risk Increasing risk liabilities over
Risk Sharing No shared risks.
sharing. sharing. failures and gains
from successes.

Procedures to
address and resolve
Responsibility is
Disputes are disputes are Problems are
shared among the
common; often established. addressed as a team
Probability of team, so problems
requires binding Solutions are found and resolved at the
Disputes and disagreements
dispute resolution through some expense of neither
are solved within the
methods to solve degree of party.
team before
them (win/lose). compromise and
becoming disputes.
cooperation
(win/win).

40% reduction in
15% reduction in
job-hours; 17%
equipment and
reduction in
Cost and schedule construction costs;
Schedule reduction overhead; 10%
overruns. Both 33% reduction in
Typical Project 10.5%; Cost improvement worker
sides finish the engineering rates;
Results reduction 16.3%; utilization rate; 10%
project without 100% acceptance
RFI turn-around 14 project costs; 100%
realizing their of risk by the
days Vs. 30-60 days success in meeting
objectives. owner with a low
budget and schedule;
fee charged by
50% reduction in
contractor.
engineering rework.

DRAFT 2/4/2017 2:32:00 PM 79


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

The characteristics of these different levels of partnering within the continuum as


compared to the standard adversarial approach, together with the improvements
introduced by each one, are presented and summarized in Table 10. Both models of the
continuum provide a partnering process, and they highlight the importance of objective
alignment within the building team.
In the Partnering Continuum, each of the three levels (shades) of partnering are based on
the degree of objective alignment achieved by the project team. The greater the alignment
of objectives and goals, the more benefits the parties will be able to achieve through
improved communication and collaboration, greater trust, risk sharing, and resolution of
disputes within the project team. Both models, by interrelating the different stages of the
Partnering continuum with the project characteristics, can serve as a guide for those
involved in construction, helping define the nature of the relationship, even if they do not
fully implement the Partnering systems. By comparing each level of Partnering with the
Competition Stage, in one or a series of projects, parties can determine the level of
objective alignment that can help them achieve their own needs. Parties can also compare
the expected project benefits versus the resources required to achieve the specific level, in
order to select the proper partnering stage. Furthermore, the continuum allows for a clear
definition of what to expect at each level of partnering to avoid misunderstandings and
erroneous expectations during implementation. The Key Components of Partnering
described in Section 4.3 represent the basic stage of partnering (i.e.,
Cooperation/Collaboration).
The following two cases show both extremes of the Partnering Continuum. In the first
example, parties returned to the Competition/Adversarial stage after attempting to
develop a partnering agreement. Apparently, their inability to resolve initial problems
with site conditions and design errors had an effect on the partnering approach. The
second example shows projects in the high-tech arena that have successfully reached the
Coalescing Stage.

Tomlinson Bridge (New Haven, CT)


The Tomlinson Bridge project in New Haven, Conn., is an example of a partnering
approach that failed victim to a claims battle between the State and the contractor, not
being able to overcome the Adversarial/Competition approach. The $87.7 million project
to replace a 69-year-old bridge was two years behind schedule; when the article appeared
in ENR (5/4/1998), because of numerous disputes over site conditions, contract drawings,
and removal of contaminated material. The Dept. of Transportation conceded that
partnering methods failed as the contractor encountered substantial obstructions during
demolition and significant errors in the drawings, which had delayed the project and
resulted in cost overruns. The issue resolution process in the partnering approach
apparently failed. It was speculated that the parties where not able to develop an initial
degree of trust 5. Both parties agreed that communications were strained despite the initial
attempts at partnering, making progress more difficult (ENR, 5/4/1998).
Further research on this case would be required to establish responsibilities, and learn
how the failure in the partnering approach contributed to the development of the claims.
In any case, one thing seems clear: the job had significant uncertainties with regards to
the site conditions that were not addressed by the owner at time of bid (i.e., risk sharing);
the owner knew from the beginning that at least two other structures had been there since
the 1800’s (ENR, 5/4/1998); contamination of the soil should have been expected, since
one of the reasons behind the project was the need to allow for larger oil tankers to access
the many refineries in the area. An unbalanced allocation risk (Section 3.2) by the owner

80
PARTNERING

might be behind the failure of this partnering arrangement, and the failure to align the
parties’ objectives and develop the necessary trust to resolve the initial problems.

Intel (Portland, Oregon)


This case shows how projects achieve a total alignment of risks and the benefits that
result. The design and construction of high-tech production facilities for companies like
Intel, is an example of complex large-scale engineering systems where partnering has
significantly changed the construction process. The Lean Construction Delivery System
Model (Miles, 1996; CIOB, 1999) illustrates the ways in which partnering has allowed
parties to maximize the resources of each team member. In this model the partnering
relationship overcomes the difficulties confronted by the Tomlinson Bridge project, by
moving the building team along the partnering continuum to a higher level of integration,
such as Coalescence and Synergistic.
The structure of one of these projects is shown in Figure 16. This structure is clearly a
departure from the typical pyramid shaped organization charts of construction jobs,
where each party sits underneath the client with clearly defined responsibilities and
contractual boundaries (i.e., LNGT Project, Chapter 1). Under this organization, all
parties were part of a whole, centered on the project and its objectives. All decisions were
based on the ultimate goal: the project. This project delivery system is based on
multitasking, multi-discipline, multi-functional working groups and partnering (Miles,
1996). Each working group makes joint decisions on the design based on constructability,
achievement of the design criteria, budget, schedule, and quality (CIOB, 1999).

Process
Owners Team

Facility Facility
Construction Operations
Team Teams
Client
Local Architectural
Project
Codes Team

Design/ Engineering
Authorities/ Const. Teams
State Codes
Utilities Consultants
Material &
Federal Equipment
Manufacturers
Agencies
Trades
Utility
Suppliers Independent
Testing
Agencies

Figure 16 – Structure of an Ultra-Fast Track High-Tech Design-Build Project


(Miles, 1996)

Such high level of integration is exemplified by the fact that from the beginning of the
project, the construction team met regularly with the start-up teams and the client’s

DRAFT 2/4/2017 2:32:00 PM 81


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

facility operation group. Changes in the design were evaluated early on by the final users
of the facility, and their comments, suggestions, and requirements were incorporated into
the process. In addition, suppliers of major equipment and technology participated in the
design development phases in order to incorporate their knowledge and experience into
the final construction documents. 6 Furthermore, a cost control group served as the router
for all exchanges of information, tracking all communications between the design and
construction groups, which allowed them to provide management with real-time cost data
at any given time. With this cost information, the team was able to make informed
decisions on changes, and their implications in the long run with regards to the project
budget.
A company that has successfully implemented this delivery system is Hoffman
Construction Co., Portland, Oregon (ENR, 5/27/1996). In 1993 a Hoffman’s construction
team won Intel Corp.’s Pegasus Award for the “breakthrough success” in solving crucial
technical and building issues during the construction of a 435,000-sq-ft, $110 million
chip fabrication plant outside of Portland. The plant was built in only 14 months; two
months ahead of schedule. When asked about his secret, Hoffman’s project manager
responded (ENR, 5/27/1996):
“To start with, throw the linear approach out the window. We do everything
with a tremendous amount of concurrency. We are driving safety rates to
extremely low levels, even in a highly risky environment 7. We self-perform a
great deal of our work. We interact with organized and open-shop labor, often
on the same site. What we have tried is to create synergies and bypass
institutional barriers that keep [builders] from reaching their full potential....
new techniques come from understanding the design process and the owner’s
needs. [Missing] your client’s technology windows can cost owners billions of
dollars. You have to be dead right – or you’re simply dead.”
Hoffman is a full service construction company, and unlike other contractors who often
contract out most of the work, they have developed in-house capabilities in many areas to
meet project demands. Among the innovative techniques developed by Hoffman, is the
concept of Speed Engineering where the company integrates their in-house structural
engineers with the owner’s design team to develop the fastest solution for bringing the
structure off the ground and to meet the owner’s need for a faster design and construction
process of their facilities. Furthermore, they analyze material availability, structural
details for constructability, and building systems for pre-fabrication opportunities (See
Section 3.6.1, Constructability Analysis). Hoffman reports that project costs can be
lowered through the speed engineering process, but the emphasis is on timely, safe
completion (Hoffman, 1999).
In the Lean Construction Model, the basic concepts of Partnering have been fully
implemented along Partnering Continuum. The different groups evolve over the life of
the project as requirements change. The organization is shaped and reshaped according to
the project, and from the beginning, parties are able to align their objectives and redesign
the total work process. All of the costs associated with this system have been recovered
through partnering agreements and outstanding project performance (Miles, 1996). This
ultimate stage of partnering, Coalescing, has resulted in significant savings in time and
costs in the design and construction of a number of projects, helping both owners and
contractors achieve higher levels of productivity 8.

Museum Relating partnering to the Museum project, it can be seen that the principles of
Project Partnering, when applied correctly, can reduce and even eliminate an adversarial
situation. After the bids were analyzed, the owner’s consultant reviewed the design and
value engineered it with the designer and the owner. To be consistent with state

82
PARTNERING

regulations the owner went back to the two lowest bidders and asked for a reprice with
the design alternates. This method promoted fair competition comparing apples to apples,
in addition the owner asked for other suggestions to reduce the price to meet the strict
budget requirements. Both bidders concurred and thought it was fair. Bids were
submitted by the two lowest bidders, coming in at $1.0 and $1.6 million. The owner
awarded the project to the lowest bidder and the bid was not protested.
With the total construction costs still over the budget, the owner’s consultant
implemented partnering for the project. The contractor worked with the owner’s
consultant for further value engineer the addition. The contractor suggested eliminating
the basement, moving heating and ventilation systems to the roof, and some modification
to the curtain wall design. At the same time, the designer was approving the design
through the shop-drawing phase. Construction started before design was complete. The
project continued on schedule with changes being implemented on an ongoing basis. The
synergistic atmosphere allowed the owner the ability to make design and value
engineering changes, without sacrificing the quality of the structure.
The key concepts of partnering implemented included weekly meetings, openness and
commitment of all the parties involved to process. The consultant hired by the owner was
authorized to make decision on behalf of the owner whenever necessary. Upper level
management commitment was a major strength as well as cooperative field crew. Claims
and change orders where handled and resolved on a daily basis. Trade contractors were
involved in meetings to value engineer, especially HVAC contractor. As a result, the
project was completed on time and under budget by $10,000 ($890,000). At the end of
the project when the closeout phase occurred, the owner realized that the contract was
never signed, as everyone was so anxious to get underway and close in before winter.
The contract was signed at the end of the project.

4.5 SUMMARY
Partnering is a complete system of operation in the construction environment; hence, it is
not considered a stage in the DRL. However, the introduction of the concept of
Partnering was based on the consideration that many of the key principles of this system
of operation are congruent with those of the DRL; and thus can enhance the different
stages, even if the complete Partnering format is not being implemented. Partnering
fractures the common adversarial approach in construction projects and replaces it with
open communication, timely decisions, synergy, joint problem solving, and win/win
philosophy.
Among the multiple advantages of partnering are: reduced exposure to liability through
open communication, early problem identification and resolution; risk sharing; increased
productivity; better quality of work through the empowerment of workers; lower costs;
better cash flow; better decision making and commitment to resolving problems; and
better opportunity for a successful project. As Hunter et al. (1995) so eloquently said,
“…an ounce of partnering prevents a pound of problems.”
The Partnering Continuum establishes a direct relationship between the degree of
objective alignment between the parties to a project, and the potential benefits of
Partnering, where the Coalescence phase represents the greatest alignment of objectives
and offers the greatest benefits. Through the use of this continuum each project can
determine the level of objective alignment it has and/or desires, and from this estimate
the possible benefits that the system could provide. Nevertheless, despite its many
advantages, partnering can experience problems through its implementation associated to:
1) The demand it places on everyone committing to the partnering process.

DRAFT 2/4/2017 2:32:00 PM 83


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

2) The difficulty participants may have with taking the risk of trusting others.
3) The tendencies of many people to believe that conflicts can only be solved
through the win/lose approach.

4.6 POINTS FOR DISCUSSION


4.1 What are the five phases of the partnering process (Section 4.2)? What stages are
most important for the success of the partnering agreement? Can an agreement work
if some of the stages are omitted?
4.2 One of the founding principles behind partnering is transparency and openness
(Section 4.3). Does this build a certain trust between the owner and the contractor?
Is it in the best interest of the owner or contractor to be open about all aspects of the
project, specifically mistakes or errors?
4.3 Partnering worked well for Hoffman construction (Section 4.4), who self-performs
the majority of their work. How is partnering affected when there are numerous
parties and sub-contractors involved?
4.4 Are the participants in the Partnering Agreement (Section 4.3) legally bound to this
commitment? Does this document have any bearing in a court of law?
4.5 How does partnering fit into the DRL proposed by Findley (Section 2.3.2)? Is this
agreement perpetual, including other projects, or does it end with a completed
project? How much credibility has the agreement lost for the rest of the project if a
dispute does reach litigation?
4.6 What options are available to the parties involved if the partnering agreement
doesn’t work as in Tomlinson Bridge project? What steps could be taken to help
deter an agreement from going south?
4.7 Should owners uses past partnering experiences as a means to pre-qualify designers
and constructors? What benefits would this method have? Does it create an
incentive for contractors to work at maintaining the partnering agreement?
4.8 If there are numerous parties involved and one does not actively participate, what
consequences might it have on the partnering agreement?
4.9 Pay now or pay later is a statement often associated with construction claims. What
are the differences between taking preventative measures and incentive programs?
Considering this concept, how much money should be invested in partnering? Are
there other sacrifices made by either party by entering into such an agreement?
4.10 Is partnering feasible for all projects? Does partnering work better depending on the
size or complexity of the project? How does partnering relate to the different
delivery systems (Section 1.2.2)?

4.7 REFERENCES

[AAA, 1996] American Arbitration Assiociation. Building Success for the


21st Century: A Guide to Partnering in the Construction
Industry. Dispute Avoidance and Resolution Task Force of the
American Arbitration Association. 1996.

84
PARTNERING

[CII, 1991] Construction Industry Institute. In Search of Partnering


Excellence. Special Publication 17-1, Partnering Task Force.
1991.
[CIOB, 1999] UK Department of the Environment, Transport and the
Regions. Rethinking Construction: The report of the
Construction Task Force to the Deputy Prime Minister, John
Prescott, on the scope for improving the quality and efficiency
of UK construction. July, 19
[Cowan et al., 1992] Cowan, C., Gray C., and Larson, E. (1992). "Project
Partnering."Project Management Journal, 22(4), 5-11.
[DRT, 1997/1998] Dispute Resolution Times, (1997/1998). AAA Partnering
Boosts Jail Project in San Diego. p. 7 Winter
[DRT, 1998] Dispute Resolution Times, (1998). AAA Cleveland VP Eileen
Vernon. Partnering Aids RTA Project in Ohio. p. 8 April
[Ellison et al., 1995] Ellison, David, and Miller, David, (1995). Beyond ADR:
Working Toward Synergistic Strategic Partnership. Journal of
Management in Engineering, Vol. 11 (6), pp. 44-54, ASCE
0742-597X. Nov-Dec, New York
[ENR, 5/27/1996] Daniel, Stephen. System Approach Pays Big Dividends.
Engineering News Record. McGraw-Hill, New York.Vol. 236
(21) p. 39. May 27, 1996.
[ENR, 5/4/1998] Angelo, William. Project Management, Partnering Goes Awry
on Connecticut Bridge Job. Engineering News Record.
McGraw-Hill, New York. p. 17, May 4, 1998.
[ENR, 9/9/1996] Engineering News Record. High-Strength Mix Tested.
McGraw-Hill, New York. p. 21, September 9, 1996.
[Groton, 1997] Groton, James. ADR in the Construction Industry. Dispute
Resolution Journal Vol. 52 (3) pp. 48-57, Summer, 1997.
[Hoffman, 1999 ] Hoffman Construction, (1999), Downloaded from the web on
April 11, www.hoffmanconstruction.com
[Hunter et al., 1995] Hunter Keith, and Hoening, James. Construction Dispute
Prevention Comes of Age. Dispute Resolution Journal pp. 53-
54, January 1995.
[Larson et al., 1997] Larson, Erik, and Drexel, John, (1997). Barriers to Project
Management: Report from the Firing Line. Project Engineering.
Vol. 28 (1) pp. 46-52. March
[Miles, 1996] Miles, Robert. Twenty-First Century Partnering and the Role of
ADR. Journal of Management in Engineering Vol. 12 (3) pp.
45-55. May/June 1996
[Thompson et al., Thompson, Paul J. and Sanders, Steve. Partnering Continuum.
1998] Journal of Management in Engineering. Vol. 14 (5).
September/October 1998.

DRAFT 2/4/2017 2:32:00 PM 85


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

4.8 ENDNOTES

1
To this effect, Groton (1997) concluded, “Partnering is both the overall philosophy for
dispute management and one of the tools for avoiding disputes.” In this book, partnering
is being considered as a philosophy.
2
See Chapter 5: Negotiation for more on win/lose and win/win negotiations.
3
See Chapter 5 for Position-Based versus Needs-Based Negotiations.
4
In parenBook is the equivalent level from the Ellison et al., 1995 model
5
A survey on barriers to partnering identified trust between parties as the most critical
aspect in the success of the implementation of this approach. Thirty one percent of
respondents considered the failure to build a true relationship of trust as a barrier to
partnering (Larson et al., 1997).
6
This concept of supplier involvement in the engineering process is behind the new
PEpC delivery system developed and proposed by the CII, and reviewed in Section 3.3.3.
7
Hoffman’s Lost Accident Rate per 200,000 works hours since 1994 has been 600% less
than the industry average (Hoffman, 1999).
8
Tesco Stores has reduced the capital costs of their stores by 40% since 1991; Needahm
Co., a construction company from Colorado, has been able to reduced project times and
costs by as much as 30%; Pacific Contracting of San Francisco, has increased their
annual turnover by 20% in 18 months with the same staff (CIOB, 1999).

86
C H A P T E R

5
STAGE 2:
NEGOTIATION
“there is a fixed-size cake to divide and each party
would rather have a bigger slice than a smaller
slice”
(Hill 1995)

A $US 380 million underground highway interchange needed to be built under an


existing mainline tunnel in a metropolitan city. The interchange project consisted of 4
lanes Northbound and 4 lanes Southbound. The contract for the project also included the
construction of: slurry walls; temporary decking and bridges; drilled shafts; cast-in-place
invert slab, walls, and roof system; support of excavation; groundwater control; paving;
underpinning of 14 mainline bents and 6 ramp bents supporting approximately 1,400 feet
of an existing elevated viaduct. The construction of ramps and connections to and from
two existing tunnels was also performed under this contract, along with all the associated
duct work. Major utility relocations, temporary facilities and service connections were
included as well.
This contract was a fixed price, publicly bid contract and scheduled to be completed in
3½ years. The major participants involved in this contract included the owner, a program

CHAPTER LOOK AHEAD


WHAT IS IT? Negotiation is aimed at resolving the problems when they surface, taking into consideration
each party’s interests to reach a win-win solution. The field of negotiation analyzes how participants
interact when a decision between two or more parties is made. The negotiation process entails preparing
for the negotiation, selection of an appropriate style, and commitment to reach an agreeable solution.
WHO IS INVOLVED? Negotiation, similar to that of Partnering, involves participants of all levels of
management. Specifically it focuses on providing the lower levels of management with the tools
necessary to resolve conflict. It also involves any third parties that are introduced to resolve disputes.
WHY IS IT IMPORTANT? If a mutually acceptable solution can be negotiated when a conflict arises, it
keeps it from escalating. Participants save time, money and even their relationship by addressing
conflicts at an early stage. The more educated the participants are in the theory of negotiation the easier
it is to reach an acceptable solution.
HOW TO APPROACH IT? Understand the difference between positions and interests. Review the different
styles available when negotiating and recognize how applicable they are in different contexts. Apply the
techniques learned to your individual situation. Implement one of the different negotiation techniques.

KEY CONCEPTS
History of Negotiation ...................................87 Positions vs. Interests ........................................ 89
Styles .............................................................91 Structured Negotiations .................................... 94
Step Negotiations ...........................................93 Assisted Negotiation / Facilitation .................... 95

87
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

manager (a representative of the owner), a general contractor, and a designer. It should be


noted that this contract was one of many integrated projects in the owner’s overall
construction program. This contract interfaced with 10 other contracts in this program.
The schedule of this contract was tied to each these contracts, making certain milestones
and final completion date of the essence.
Due to such a tight schedule, the contract was let before a solid final design was issued.
This led to 13 major design changes after the award of the bid, which revised more than
1000 plan sheets, some more than once. For example, one major design change being
considered that had not been part of this contract focused on whether to leave the tunnel
sections open or cover them over. Eventually it was decided to add the closure of the
tunnels to this contract. These changes resulted in an $US 86 million request for contract
increase by the contractor, a 21% price increase from the original contract!
Any project manager having to deal with these change orders will have some interesting
questions in their mind. Could the owner have set up the contract to allow for these
change orders before the contractor started work? Would these change orders be able to
be handled in a non-confrontational manner? Could these change orders be resolved
through simple negotiations between the owner or its representative and the contractor at
the jobsite? Should the general contractor take a hard position on some of the issues that
the owner would consider more important? What are the interests/positions of the owners
or the contractor? What sources of power does each of the participants have entering into
this negotiation? Are the interests of the owner and the contractor aligned in this project?

5.1 THE FIELD OF NEGOTIATION


The field of negotiation has made rapid advances since the 1970’s when its popularity
increased among the academic community. Currently all of the top business and law
school programs have courses that teach the theory of negotiation. Although the focus of
this book is not specifically to teach these theories, they are crucial in the steps taken to
resolve disputes in the construction industry. Most owners, contractors, and engineers do
not posses these skills, and therefore many disputes escalate when they could have been
avoided. An overview of these theories will be presented in this chapter, but it is
recommended that the reader indulge in outside readings by the experts in this field.
Susskind et al. (1987), Fisher et al. (1981), Ury et al. (1988) and Lewicki et al. (1985)
have all published books on resolving disputes through negotiation. Although they do not
directly address negotiation in the construction industry, the principles are generally the
same and they will build a solid basis of knowledge for the reader.
Negotiation is the most important tool available to manage and resolve disputes in
construction projects. This occurs after the Prevention stage (Chapter 3), which assumes
that conflicts will arise, and prepares the parties on how to manage them and mitigate
their effects. Negotiation represents the first stage where an attempt is made to resolve
the dispute. Here, parties are required to come together and arrive at an agreeable
settlement through communication. A successful negotiation should result in a solution
acceptable to both parties that will not harm their relationship. This implies collaboration,
trust, and common objectives (all ancient notions as it is presented in Chapter 2).
Another important benefit of negotiation relates to control over the outcome. When
parties resolve their disputes through negotiation, settlements result from a joint
agreement, essentially controlled by the parties, and generally inclined towards a win/win
outcome. Conversely, when a third party is given the responsibility of establishing the
facts and making a decision, the outcome will most likely be based only on the
interpretation of the contract, and therefore tend to produce a win/lose outcome.

88
STAGE 2: NEGOTIATION

5.2 POSITIONS VERSUS INTERESTS


A well-planned approach to negotiation should begin with the notions of partnering
explained in Chapter 4. From the building of teams to the final stages, parties should
attempt to resolve all disagreements through negotiations based on an honest exchange of
information. This dialogue addresses the underlying needs of each party, so at least some
of them are incorporated into the solution. In other words, negotiations should focus on
the individual and collective interests of the parties, instead of concentrating on positions.
A position might be, “He wants $100,000 for the change order now,” whereas the
underlying interests are, “Although he willing to do the extra work, he is low on cash and
cannot fund the work.” These interests are actually where the conflicts develop, but when
they turn into positions, parties lose sight of the underlying conflict at hand. By reverting
to interest-based negotiations, participants will be more willing to understand both sides
of the problem and develop a “non-zero sum” solution. A “zero sum” solution is when
every benefit received by one party is at the expense of the another.
Interest based negotiations are virtually non-existent in the construction industry, because
neither side wants to give up their true intentions, thinking that they will be cheated. This
all goes back to the level of trust that each party has for one another. The most common
approach to negotiations in the construction arena is "positional" bargaining, where each
party assumes a position, and then seeks to maintain it during negotiations. These
positions are chosen to be defended based on contract language and the law. They have
been elected as mere rationalizations and means to an end, but not as the end itself, and
are usually contradictory. Negotiations over positions can degenerate into an attempt
from each side to force the other to first abandon its position, turning the negotiation into
a purely “win/lose” proposition that inhibits innovation in the search for solutions.
Fisher et al. (1981) championed the theory of interest-based negotiation. Arguing over
positions is unwise, inefficient and it endangers an ongoing relationship. This type of
negotiation only gets more complicated when numerous parties are involved. “Needs-
based” (interest-based) negotiations look beyond positions to address each party’s actual
goals without engaging in a positional contest of will. Needs-based negotiations
encourage creative searches for alternative means to the real goals, and they do not
represent a surrendering of a given position.
Take these two examples of a simple negotiation between the general contractor and a
subcontractor that is unable to meet a milestone in the contract.
SUB: I will not be able to finish on time.
GC: You will finish as scheduled.
SUB: I need two extra weeks.
GC: You cannot have two weeks.
SUB: If I do not get two weeks, I will not be able to finish on time.
GC: No, you will finish according to the contract or we will collect damages and
replace you.
This position-based type of negotiation will go around in circles, until one of the parties
abandons their position, or they end up in court. From this dialogue, it is not clear why
they are even arguing. Looking at the same conflict from an interest-based negotiation,
one can see the differences.
SUB: I will not be able to finish on time.
GC: Why can you finish as promised? What are the reasons?
SUB: My supplier will not be able to deliver the materials until next week, causing me
to finish two weeks behind schedule.

DRAFT 2/4/2017 2:32:00 PM 89


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

GC: As you know, the schedule is very tight for this project and there is little float
available. Are there any other suppliers who can deliver on time?
SUB: Yes, but they are more expensive, more than the damages incurred by finishing
late.
GC: Although you are responsible for meeting the milestone, I understand your
dilemma. Let me see what I can do. I know some other suppliers that might be
able to help.
In this interest-based negotiation, the root of the conflict is uncovered, and a mutual
agreeable solution can be reached. Although the general contractor seems to have the
most power in this negotiation, the subcontractor has some as well. If the schedule begins
to slip because of this delayed finish, and they wind up in a court battle, it may take years
to award damages. In addition, the damages may not be sufficient to cover the actual
costs incurred by the contractor.
When the “Im’right you’re wrong!” position is abandon, it allows participants to address
the underlying concerns, which leads to the generation of alternatives that would not
seem readily apparent at first. In this fashion, Hollands (1989) 1 suggests that parties in a
construction disputes should not only consider needs or interests that are derived from the
contract documents, but parties should also look for alternatives that can solve the
disagreements without court intervention. After all, parties usually know and understand
the facts better than they can communicate to an arbitrator, judge, or jury. Therefore, they
should be able to develop a solution that incorporates and maximizes this knowledge. He
recommends that the following aspects be incorporated into the negotiation:
• “Substantive (e.g., money, time, long-term market);
• Procedural (e.g., confidentiality, protocol, administration);
• Psychological (e.g., need for respect, status, security, recognition).”
(Hollands, 1989)
The result of this positional bargaining is a “zero sum” solution. Even if perceived gains
do not have to equal perceived losses, any change in the proposed result will provide an
advantage to one party and a disadvantage to the other. Recognizing whether a particular
negotiation is zero or non-zero sum can be very important in planning for and actually
carrying out the negotiation, as dispute negotiations often seen as zero-sum, may have
non-zero sum aspects or alternative solutions (Boskey, 1993).
Negotiation parties often feel they are involved in a zero-sum situation in which court
proceedings are the only solution to the dispute. They believe “there is a fixed-size cake
to divide and each party would rather have a bigger slice than a smaller slice” (Hill,
1995). However, statistics from the American Arbitration Association show that few
business situations are zero-sum games and that by cooperating, business partners can
expand their markets and develop mutual benefits. For example, out of the 3,075 cases
that requested AAA mediation (i.e., a form of facilitated negotiations) in 1993, 1,136
were settled, 151 were closed, 293 were withdrawn, 644 were pending, and 851 were in
some other status at the end of the year (Langeland, 1995). In other words, over 50% of
the cases where closed through this form of aided negotiation where parties develop
solutions, which are acceptable to both parties (i.e., win/win or non-zero-sum), and only
28% proceeded to another form of dispute resolution.
It must be noted that sometimes interests based negotiations are not the best choice of
action. In the few disputes that are completely ‘cut and dry’, other approaches such as
rights or power can be used to resolve the dispute (Ury et al., 1988). More information is
presented in Chapter 9 on these types of disputes.

90
STAGE 2: NEGOTIATION

5.3 NEGOTIATION STYLES


Five strategies of negotiation are common in the field; avoiding, competing,
accommodating, compromising, and collaborating (Figure 17). Although they have been
worded and represented by different adjectives by different people, they still encompass
all the different styles that participants use. Each strategy is valuable in the construction
atmosphere depending on the situations. At the same time if they are used at the wrong
time, they can spiral a conflict into the courts rapidly.

Competing Collaborating

Compromising

Avoiding Accommodating

Figure 17 – Negotiation Strategies (Thomas, 1976)

Avoiding a situation or conflict is just how it sounds. Sometimes trivial problems are best
ignored. An example might be that the union workers are upset because there are only 20
bathrooms on-site instead of 22. At some point, the validity of a conflict must be
addressed, and usually this is done subconsciously. Imagine the number of erroneous
situations that could escalate into conflicts. Most project managers already spend too
much time on perceived problems that are not worth their time. On the other hand, a
legitimate concern from another participant that is avoided can have enormous
repercussions. If there were 20 bathrooms on-site, and no female bathrooms, the union
workers might have a legitimate complaint. This problem could easily be solved, but it
could also escalate quickly if avoided.
Competing is the style that most of the participants in the construction industry take. “I’m
not going to budge, because they will just take advantage of me.” This adversarial style
leads to litigation. Although the competing style is necessary, it is often misused. Think
about the issue of safety on the construction site, which is usually the responsibility of the
contractor. If a subcontractor approached the contractor and requested some leniency in
meeting certain safety requirements, what style should the contractor reply with? In this
situation if the contractor has responsibility for the site safety, the contractor should take
a competing style. On the other hand, it would be unwise for sub to continue with the
competing style. The worst time to use the competing style of negotiation is when you are
wrong or to compete for the sake of it.
Accommodating is the complete opposite of competing. This style focuses on
accommodating the interests and requests of the other side. This is usually the easiest

DRAFT 2/4/2017 2:32:00 PM 91


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

way to resolve a dispute. In many times when a party assumes responsibility for their
actions or mistakes, if they take on an accommodating style of negotiation they might
reach a mutually acceptable outcome even thought they are at fault. The exact opposite
can be true if a competing style is adopted by the party at fault. Accommodating another
party when applicable can develop trust among participants.
Compromising is when both or all of the participants give in on some points or interests
for the sake of acquiring others. Although this is usually not the optimal situation, it is
one in which all of the parties are willing to work together. Compromising works well
when both or all of the parties have valid complaints in a conflict. An example of this
might be adverse weather conditions. A contractor might ask for a 10-day time extension,
but the owner might feel that work could have continued through the weather. Both may
have a valid claim and a compromise of 6 days could be reached for the severe days.
Although not always the most optimal solution, keep in mind that the alternative to
compromising on some of the trivial points is litigation.
Collaborating is one of the primary principles in Partnering. In collaborating, the
participants work together to design, develop and implement a solution that is acceptable
to all. This style of negotiation flourishes in a synergistic atmosphere. The downside of
this style is that it is rarely used. The delivery systems and contract selection do not
usually promote this atmosphere. An example of this is when a contractor and a designer
are brought in the project early to add their input and help steer the project based on their
expertise.

5.4 PREPARATION
Preparation for a negotiation cannot be stressed enough! To go into a negotiation without
doing your homework will only spell disaster. It can make valid claims seem invalid, fuel
personality conflicts, prolong the resolution process, frustrate others and ruin
relationships. When starting to prepare for a negotiation you should begin by figuring
out exactly what it is that you hope to achieve. What are your needs? In the same context,
one should also make a prediction as to what the other participant’s interests are.
Understand and identify where the might be conflict and plan accordingly.
When determining needs and interest, an objective determination can be made about your
BATNA (Fisher, 1991). The BATNA is the Best Alternative To a Negotiated Agreement,
in other words, the point at which a negotiator is willing to walk away from the
negotiations. Below this point, there is nothing that the other side can propose that is
better than not negotiating at all. For example, if an owner is negotiating with a set of
contractors for the lowest price on a quality guaranteed contract and has received a bid of
$100,000 (the BATNA); when negotiating with the next contractor, it would be worthless
to negotiate above this point. A BATNA is not something that the negotiator wishes for,
but it is rather determined by external factors. It should not be overly ambitious but
honestly the best alternative, for if things do not go as planed the result may be to accept
the BATNA. Once your BATNA has been identified, identify the BATNA for the other
parties involved.
Source of power are another aspect of negotiations that one can account for before the
negotiations begin. Examine the situation and identify what sources of power that each
side possesses. By doing so it will allow you to leverage your position in the negotiation
and come up with defenses against sources of power that the other side may have.
Once the BATNAs and sources of power are identified, one can begin to determine how
the negotiations might go. Develop a thorough list of needs and interests, prioritize them,
and do the same for the other side. Start to develop solutions to the problem that will be

92
STAGE 2: NEGOTIATION

acceptable to both sides. Make sure that these are optimistic but not too greedy. This
target solution is the aspiration point. Although you may have many great solutions to the
dilemma, keeping consistent with the win-win solution, one must be open to solutions
that are presented by the other side.
By preparing for the negotiation, the conflict will most likely be resolved faster and have
a more optimal result for all the parties involved. The following sections review three
important techniques designed to improve the negotiation process in the construction
industry and correct, “people issues and process problems” that might interfere with the
resolution of disputes at this DRL stage. These techniques, Structured Negotiations, Step
Negotiations, and Facilitated Negotiations, are presented in the following three sections.
When reading these sections keep in mind the theory of negotiation and how they might
apply.

5.5 STEP NEGOTIATION


A way to structure negotiations that encourages the resolution of disagreements at the
lowest possible organizational level is to establish a contract requirement for Step
Negotiations. Under this approach, the representative of each party directly involved with
the issues must first address problems, within a limited timeframe. If parties fail to settle
the dispute in the time stipulated, they must endorse the problem to their immediate
superior, who will then attempt an agreeable settlement based on the advancements of the
first step. If this level does not succeed either, the matter is raised to a higher echelon in
the organization (Figure 18).
Step negotiations force each level of the firm to use up, within time limits, all the
resources available to elucidate the problem without raising the matter to the next step.
An example of this type of incentive is found in the Canadian Public Works arena
(Section 6.2), where contracts require that before the Agency Review Board can be
incorporated into the dispute, the agents must submit the matter to the Minister of Public
Works. The Ministry reviews the attempts made to achieve a resolution, and then has the
option of settling the case with the contractor. This contract encourages contract
administrators to assume a role in the resolution of disputes, rather than relying
exclusively on the Board.

DRAFT 2/4/2017 2:32:00 PM 93


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Communication Lines

Level 3
Step 3
(e.g.,V.P. Level 3
Operations) (e.g., Senior
Management)

Level 2 Step 2 Level 2


(e.g., Project (e.g., Project
Manager) Representative

Level 1 Step 1 Level 1


(e.g., Field Supervisor (e.g., Architect or
or Project Engineer) Engineer)

CONTRACTOR OWNER
ORGANIZATION ORGANIZATION

Figure 18 – Diagram of Step Negotiations showing Levels and Communication Lines

5.6 STRUCTURED NEGOTIATIONS


On a recent Florida case cited by Kane (1992), litigation began to threaten a power plant
contract dispute in excess of $20 million. The example describes how the Utility and the
contractor set up a structured negotiation process that took place over a 12-month period.
Upper management accepted an honest, open airing of the facts in the dispute with a
commitment towards good-faith negotiations. After many meetings, and a thorough
allocation of resources including time, money, and people, a settlement was finally
reached without a lawsuit being filed. This case was resolved in one third of the time
usually needed to conclude a dispute of this magnitude using court proceedings. The
average civil case in the state court takes 14 months to reach a conclusion, while at a
federal level it takes 7-11 months from filing to disposition. In the United States, the
number of civil cases that are more than 3 years old in district courts had risen in 1992 to
over 28,000 cases (Treacy, 1995).
Hoctor (1989) provides a clear view of the steps involved in the structured approach used
in this case:
1) Each side chooses to be represented by a person knowledgeable in the resolution
of construction contract disputes. These agents must have the authority to make
decisions and accept settlements in order to move the negotiation process along.
2) The items in dispute are given to these agents for the purpose of reaching a final
settlement binding on the owner and the contractor.
3) Items upon which agents cannot reach an agreement are set aside. For these
items, parties may mutually choose a neutral third party to decide the matter.
This person can either adjudicate the item in dispute or choose a fourth person
with greater expertise in the area in dispute for a decision.
4) The resolution of each item is documented, and a contract change administered
for each. The contractor and owner are both bound by the results of the
agreement.

94
STAGE 2: NEGOTIATION

The advantages of structured negotiation are twofold. On the one hand, negotiations
become a formal procedure, in which a centralized structure is created to cope with the
dispute. The most important benefit is that people in dispute can control the process.
They can establish strict timetables for their agents to reach a settlement before calling
for a third party to solve the matter, and the third parties can be limited to the time they
have to reach a decision. The agents take every issue in dispute from its definition to a
resolution that is incorporated into the contract, identifying and leaving aside only those
issues in which they cannot come to an agreement.
The other advantage is that structured negotiations bring knowledgeable participants to
the table; a move that generally produces faster results, since the expert agents can draw
from their respective organizations all the legal, technical, and managerial information
required expediting the procedures and guaranteeing an effective outcome (Hoctor,
1989). In addition, by constantly interacting with experts, parties reduce the risk of
having to escalate the problem to a court, where a judge or jury will have a limited ability
to comprehend the problems. In short, by understanding underlying interests, managing
information, and then allocating time and resources, the experts involved in structured
negotiations increase the likeliness to achieve a win/win, non-zero sum solution.

5.7 FACILITATED NEGOTIATIONS/MEETINGS


Facilitated negotiations assume that parties are not always able to communicate their
needs and interests effectively. This inability usually results in parties focusing on
positions, and viewing the process as something they will either win or lose. Berman
(1995) states that parties on two sides of an issue tend not to be objective and open-
minded, therefore becoming adversarial and vague in their interactions. Facilitated
negotiations propose a way to improve communications by inviting a neutral third party
with knowledge on negotiation, who concentrates on the issues rather than on reaching a
settlement. The facilitator will refrain from making judgments or recommendations, but
he/she will play a key role in facilitating a smooth evolution of the sessions.
Since construction disputes are usually technically complex and involve a large number
of documents, parties can easily conceal the reality, by adopting a position of “convenient
listeners” (Berman, 1995). In other words, parties can be tempted to pay only attention to
the things that benefit them. According to Berman (1995), the facilitator can help surpass
this barrier by dividing the negotiations into two phases:
1) Understanding the Issues: the facilitator concentrates on making sure both
parties understand their own claims, as well as those of the opposing party. This
clear definition and understanding of issues will prove beneficial when parties
engage in the second phase.
2) Exploring of Alternatives: With a clear understanding of facts and issues, the
facilitator helps the parties develop creative solutions and evaluate the different
implications of potential outcomes. They together explore various settlement
strategies in search for a win/win outcome.
If after these two phases a settlement is not achieved, new alternatives are explored until
the parties decide to forego negotiation and move to a different level of dispute
resolution.
The facilitator plays the important role as a channel of communication and a translator of
position into common grounds for settlement, in this form of negotiation. For these
reasons, the American Arbitrator Association (AAA, 1996) established that agents should
have the following attributes:

DRAFT 2/4/2017 2:32:00 PM 95


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

• A facilitator must be trusted by both parties. He/she must be seen as an


impartial, confident viewpoint in the process.
• He/she must have a basic understanding of construction, in order to understand
the sometimes-complex issues in dispute.
• Strong communication, social, and listening skills will be needed to provide a
proper channel for interaction.
• The agent must have solid organizational skills, to help parties understand and
manage the large amounts of information usually associated with construction
claims.
• Ideally, facilitators should also have some knowledge of ADR and arbitration, to
communicate to the parties the implications of not reaching an agreement under
his/her supervision.
It is important to note that the AAA offers a roster of facilitators for construction disputes
that have been selected based on meeting these conditions.

Highway Negotiation played an important role in resolving the change order in the highway
Interchange interchange project. Looking at the sources of conflict for the highway interchange
Project project, one can see from Section 1.1 that even before the contractor started working on
the project, the potential for conflict in this contract was high. The delivery system
(Organizational Issue, Structure) of design-bid-build combined with incomplete design,
put the participants at an adversarial relationship from the start. Change, variations and
uncertainty (Uncertainty, External) impeded the steady flow of work. Ultimately, the
incomplete scope definition (Uncertainty, Internal) play the biggest role in defining the
conflict as there was a significant amount of work the contractor couldn’t plan for. In
terms of the possibility of negotiations on the project, the owner and the general
contractor had similar interests.
• The Owner wanted the contractor to do extra work.
• The Owner wanted zero impacts to the schedule.
• The Owner/Project Manager wanted to cap their exposed and risk level in the
area of schedule and cost.
• Both wanted a fair and equitable settlement.
• The Contracttor wanted quick resolution and payment
• The contractor was willing do the extra work and take on the risk.
For this reason, interest based negotiation was very successful in resolving these disputes,
although they could not all be resolved at the jobsite level. Both the owner and the
contractor used a combination of a collaborative/compromising strategy (Section 5.3) to
reach a solution. As mentioned earlier, the potential to impact other contracts made the
schedule an important interest to the owner. This is the reason behind the owner wanting
to cap their risk exposure to schedule delays. The milestones and completion date were
critical. The issue of cost was secondary to schedule, but also important because the
owner was a government agency. For this reason the owner requested a forward priced
change order (Section 3.7.7), guaranteeing that this price would hold once it is agreed
upon.
When this project was 80% complete, the owner had approved payment of $US 31
million and was still negotiating the rest of the contractor’s request one issue at a time.
An independent 3rd party was hired by the owner to verify the number submitted by the
contractor. The involvement of a 3rd party and the commitment to good faith, interest

96
STAGE 2: NEGOTIATION

based negotiations aided in the development of trust and helped facilitate an agreement.
The owner’s interests were met as the Contractor took on extra work, more risk,
promising zero schedule impacts, in return for fair compensation. By equitably
compensating the contractor, the contractor was satisfied and the owner capped their
exposure and locked in a budget based on the forward-priced change order.

5.8 SUMMARY
After the Prevention stage, which assumes that conflicts will exist and attempts to
minimize them, negotiation is the first stage that directly tries to solve the disputes. As
the second stage in the DRL, negotiation is a flexible stage in which parties have a high
degree of control over the possible outcomes. Thus, negotiation is considered the most
important tool available to manage and resolve construction disputes, and therefore
should be included as a standard resolution technique in contracts. Negotiations may
involve a third party facilitator that focuses on communication and development of
common grounds. The facilitator concentrates on the needs/interests of each party rather
than positions, and attempts to reach a non-zero-sum, win/win outcome that takes into
account matters internal and external to the contract that cannot be considered in the
binding stages of the DRL.
Step, Structured, and Facilitated Negotiations are three important techniques that can be
used throughout the negotiation process. The first two focus on the importance of
organizing and structuring the negotiation process in order to improve its results; the
third, focuses on the importance of facilitating the communication process among parties.
Step negotiation establishes a linear process for dispute resolution, assigning time limits
to each level of the parties’ organizations, moving upward along the hierarchy in the
negotiation process. Structured negotiation offers a formal procedure in which a
centralized structure is created to cope with the dispute, while allowing parties to
maintain control over it. The introduction of a participant with knowledge in the field lets
structured negotiation produce faster results, preventing disputes from escalating and
reaching litigation. This technique forces each party in a project to use all the resources
available to elucidate the problem before raising the matter to the next step. Finally the
facilitated negotiation/meeting is based on the notion that parties are not able to
communicate, and thus views the role of the facilitator as a vehicle to improve
communication in order to achieve an acceptable solution.
Depending on the objectives, strengths, and weaknesses of each particular project, parties
can decide which of these strategies to use. If lack of structure is a main weakness of the
project, step and structured negotiations might be the most helpful approaches to solve
the conflict. If lack of communication and understanding between the parties is the main
obstacle in the dispute resolution process, facilitated negotiation can become a valuable
tool. Mediation and conciliation, which are reviewed in Chapter 7, are also forms of
facilitated negotiations.
The following chapter reviews the role neutral third party agents can play in the
resolution of the usually complicated disputes in construction projects. Similar to the
initial determination by the design professional in the traditional DRL, which provides a
fast, objective, and knowledge-based solution, these third party agent techniques can aid
solve technical and contractual problems and allow the team to concentrate on
completing the project. Decisions suggested by the third party experts can also facilitate
negotiations and foster the settlement of disputes.

DRAFT 2/4/2017 2:32:00 PM 97


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

5.9 POINTS FOR DISCUSSION


5.1 What is ‘positional bargaining’? What is ‘needs-based’ negotiation? Are these
negotiation styles adversarial or collaborative? What different types of outcomes
usually result from these strategies?
5.2 Negotiations are often complex and tense situations. What are the consequences of a
party that will not compromise or collaborate? Do the parties have to enter into
negotiations only under good faith?
5.3 What are the major advantages of Structured Negotiations (Section 5.6)?
5.4 Who should be directly involved in the negotiations? What role should they play?
How effective are Step Negotiations (Section 5.5) if there are “weak links” in the
steps, in terms of personnel? By involving more people does the process become
more or less efficient?
5.5 Step Negotiations (Section 5.5) assume that personnel at the lowest level have the
authority to make critical decisions. What are the ramifications if the upper echelon
disagrees with their decision? Does these implications intimidate the initial
personnel to aviod making a decision?
5.6 Negotiations, concurrent with DART, focuses on aligning common interests
between the two parties. In what atmosphere is resolution most likely, competing,
avoiding, compromising, accommodating, or collaborating?
5.7 Negotiation has become an essential skill in the construction industry. Should this
negotiation training be a requirement for a large-scale project, or part of a partnering
agreement? Would this avoid Facilitated Negotiations/Meetings (Section 5.7)?
5.8 Negotiation theory suggests that parties should not settle for any thing less than
their BATNA (Section 5.4). Does this mean that all cases will precede to litigation
as suggested in these zero-sum situations?
5.9 A controlled structure and a forum for knowledgeable individuals are the major
advantages in structured negotiation. What are some additional advantages?
5.10 In most cases, the outcome of non-binding negotiation is not permissible in
following litigation? Is this just? What are the implications? Does this allow for
negotiators to be more open in order to reach an agreement?

5.10 REFERENCES

[AAA, 1996] American Arbitration Assiociation. Building Success for the


21st Century: A Guide to Partnering in the Construction
Industry. Dispute Avoidance and Resolution Task Force of the
American Arbitration Association. 1996.
[Berman, 1995] Berman, Gary S., (1995). Facilitated Negotiation, An Effective
ADR Technique. Dispute Resolution Journal pp. 18-29. April-
June
[Boskey, 1993] Boskey, James B., (1993). Blueprint for Negotiations. Dispute
Resolution Journal pp. 8-19. December
[Fisher, 1981] Fisher, Roger, Getting to yes : negotiating agreement without
giving in / Boston: Houghton Mifflin, 1981.

98
STAGE 2: NEGOTIATION

[Hill, 1995] Hill, Richard, (1995). Non-Adversarial Mediation. Dispute


Resolution Journal pp. 43-46. July
[Hoctor, 1989] Hoctor, David,(1989). Techniques for the Resolution of Major
Construction Contract Disputes. Public Utilities Fortnightly
Vol. 123 (9) pp. 26-30. April 27
[Hollands, 1989] Hollands, David S. FIDIC Provision for Amicable, Settlement
of Disputes. International Construction Law Review. Issue 1.
pp. 33-43. 1989
[Kane, 1992] Kane, Christopher. Mitigation Construction Contract Disputes.
Public Utilities Fortnightly. Vol. 130 (1). pp. 11-12. July 1992.
[Langeland, 1995] Langeland, Erik, (1995). The Viability of Conciliation in
International Dispute Resolution. Dispute Resolution Journal
pp. 34-41. July
[Lewicki et al., 1985] Lewicki, Roy. Negotiation : readings, exercises, and cases /
Homewood, Ill. : R.D. Irwin, 1985.
[Susskind et al., Susskind, Lawrence. Breaking the impasse : consensual
1987] approaches to resolving public disputes / New York : Basic
Books, c1987.
[Thomas, 1976] Thomas, Kenneth. Handbook of Industrial and Organizational
Psychology. Chicago. Rand McNally College Pub. Co., 1976.
[Treacy, 1995] Treacy, Thomas B., (1995). Use of ADR in the Construction
Industry. Journal of Management in Engineering Vol. 11 (1) pp.
58-63. January/February, 1995.
[Ury et al., 1988] Ury, William. Getting disputes resolved : designing systems to
cut the costs of conflict / San Francisco : Jossey-Bass, 1988.

5.11 ENDNOTES

1
The International Construction Law Review, originally published by Lloyd's of London
Press, now known as Informa Professional, a trading division of Informa UK Limited,
Gilmoora House, 57/61 Mortimer Street, London W1W 8HS. Tel: +44 (0)20 7453 2198
Fax: 020 7453 2274

DRAFT 2/4/2017 2:32:00 PM 99


C H A P T E R

6
STAGE 3:
STANDING
“...experienced and trusted construction
professionals with appropriate technical
background to address prevention and resolution of

NEUTRAL
disputes”
(ASCE, 1991).

For the construction of a $187 million state-of-the-art Land Level Transfer Facility in the
Northeastern United States, an Owner entered into an agreement with a design-build
Contractor. The facility was constructed for a subsidiary of a major defense Contractor
and replaced an aged facility to increase production capacity and capability. Upon refusal
of the first design-build Contractor to complete the final design and construction phases
of the project, the Owner subsequently entered into an lump sum agreement with a new
design-build Contractor. The new Contractor has claimed substantial damages arising
from inaccurate representation of marine subsurface conditions as reflected in the
preliminary design performed by the defaulting Contractor.
In the agreement between the Owner and the Contractor, no specific representations were
made regarding the site conditions. In fact, the scope of work in the agreement spells out
a design-build contract based on detailed performance criteria outlining the general

CHAPTER LOOK AHEAD


WHAT IS IT? A neutral third party is incorporated into the project to evaluate and resolve disagreements,
when and if they arise. They aim to provide objective and unbiased feedback by a knowledgeable
professional in a timely matter.
WHO IS INVOLVED? These neutral third parties include Neutral Advisors, Owner/Agency Review Boards,
Dispute Resolution Boards, and On-call Contractor to name a few. Although there are many variations
of a neutral third party, they all have the same objectives.
WHY IS IT IMPORTANT? The capacity of the design professional to provide unbiased feedback was
undermined by his/her relationship with the owner. The Standing Neutral stage in the DRL was
introduced to substitute the design architect/engineer, with the aim of providing the parties with the
possibility of resolving conflicts with a neutral and unbiased professional.
HOW TO APPROACH IT? Review the relationships among the participants previously presented and
understand their objectives. Apply this knowledge to the desire to resolve disputes in a timely, efficient
manor, while still having control over the outcome. Assess the pros/cons for each of the neutral third
party options. Select an appropriate third party neutral DART.

KEY CONCEPTS
Neutral Advisor .............................................101 Owner/Agency Review Boards ....................... 102
Dispute Review Boards .................................103 On-Call Contractors ........................................ 106

100
STAGE 3: STANDING NEUTRAL

configuration and characteristics of the facility, but the representation of the site
conditions is clearly not established. It does however contain a clause that provides for an
adjustment in price and/or performance period should the Contractor encounter unknown
surface, subsurface or latent physical conditions at the site differing materially from the
information provided by the Owner.
A third party neutral was retained by the insurance carrier’s counsel to assist in analyzing
the alleged design errors and misrepresentation of subsurface conditions resulting in the
claimed damages. These damages, which exceeded $50 million, represented additional
direct work, project delay and other consequential losses. Since this is a design-build
contract, there is not an independent designer or Owner’s agent to make a determination.
This case raises important questions such as, what services might the neutral provide?
What are the reasons for the insurance company’s selection of an independent report? Is
this type of analysis a reality check for both parties? Although the recommendations are
not binding among the parties, what affect might they have if the conflict escalates?

6.1 NEUTRAL ADVISOR


The neutral advisor is actually a mediator with technical know-how, hired by the parties
to help resolve problems before they escalate to complex disputes. According to the CPR
Institute for Dispute Resolution, this advisor is a “pre-selected neutral to serve the
parties as a dispute resolver throughout the construction process” (Cronin-Harris,
1994) 1. The neutral advisor or on-site neutral, as it is also known, is jointly chosen by the
parties based on his/her experience in that particular type of construction project.
As the job begins, the neutral advisor becomes familiar with the plans and specifications
of the project by reviewing the documents and attending project meetings that take place
during the course of the job. When conflicts arise, the on-site neutral can gather the
parties to work out solutions. The neutral advisor does not make decisions for the parties
or impose final solutions. Instead, they work with the parties to develop an agreeable
settlement for all stakeholders, looking for a win-win solution to the arising problems.
The costs of the on-site neutral are usually shared equally by the major parties to the job,
with no changes in the contract price.
The neutral advisor can be understood as a party taking the place of the architect or
engineer in the DRL. If properly implemented, the neutral can provide resolution advice
with regards to actual disputes, but the parties can also use them as a consultant for
number of activities. This includes analysis of potential problems before they become
disputes, guidance in the interpretation of certain contract documents, and in general,
advise the parties on any subject for which they require an opinion from a third party to
help them arrive at a decision. In their role as a consultant, the neutral advisor can help
with early identification of possible sources of conflict, serving as an important figure in
the prevention of disputes.
The Neutral Architect, a variation of this concept of the Neutral Advisor, has been
successfully developed to address post-construction disputes in merchant housing
projects (Kemp, 1998). In this type of project, each individual home owner usually
identifies problems for what they consider to be defective work after the homes are
delivered and requests from the developer their immediate correction. Some of these
requests are accepted by the developer as being part of the guarantee or within the scope
of work, but others are disputed as being beyond what was “sold” to the homebuyer.
Additional problems arise when work has to be scheduled and performed inside occupied
units. According to Kemp (1998), these conditions make litigation between developers
and homeowners associations (HOA) a likely outcome. The use of a Neutral Architect

DRAFT 2/4/2017 2:32:00 PM 101


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

would centralize, organize, mediate, and resolve all of the requests and disputes over
corrective work, therefore reducing conflict.
The developer and the HOA select this Neutral Architect jointly, once the project is
completed and the requests have been collected by the HOA. Both parties should cover
the costs of this neutral to avoid affecting the impartiality of the process. Kemp (1998)
described his role as a Neutral Architect in a 95-unit residential project in California as
follows:
“The primary goal ...was to function as an intermediary between the home
owners and the developers in much the same way as a music conductor acts to
render a symphony to an audience. The written score and lyric represent the
scope of work. The orchestra and choir are the builder and subs. The task is to
interpret the scope of work so that both the composer and the audience are
satisfied with the result; at the same time making sure that the musicians are
team players from the beginning to end”
As the Neutral Advisor described above, this architect learns about the project, the scope
of work, and the disputes between the developer and the HOA and provides parties with
unbiased and knowledgeable solutions to their disagreements. This allows the corrective
work to proceed much faster and with significant savings for both parties.
Kemp (1998) suggests that the success of this DART approach is based on the fact that
the Neutral Architect represents to the parties the “ideals of impartiality and fair
dealing.” Impartiality allows this neutral to overcome the limitations that a design
professional, working directly for the owner, would normally encounter; thus, moving the
negotiation and resolution of the problem beyond the distrust and the adversarial stance
which often characterize the relationship between the developer and the home owner.
In reviewing the many positive contributions of the Neutral Advisor to the effective
resolution of conflict, parties to the construction must also take into consideration the
disadvantages and risks of this procedure that need to be monitored, which has been
summarized as follows:
• The decision is not binding to the parties. Therefore, disputes can continue to
affect job performance if a solution is not reached.
• The neutral might become “too” familiar with the job and the different parties to
the point that his decisions will no longer be respected.
• A Neutral Advisor that is not educated or inexperienced in making the proper
decision may hinder relations.
• The neutral over time might become partially biased towards one of the parties
of the construction team.

6.2 OWNER/AGENCY REVIEW BOARDS


Some public owners with large and long duration projects, like the Corps of Engineers in
the US, have established in-house review boards to hear disputes that cannot be resolved
at the site level. The Board is usually composed of senior officials of the public agency
with authority to make determinations on contract matters. It reviews either unresolved
issues with the contractor or appeals of decisions of the contract representatives;
moreover, the Board attempts to resolve these issues with the contractor in a simple and
informal atmosphere.
Another form of application of this technique has been implemented by the City of New
York, which established a City Dispute Review Board in 1990 to review and settled

102
STAGE 3: STANDING NEUTRAL

claims and disputes with contractors working for the city. This Board is composed by
three members appointed by the Office of Construction with binding authority to issue
settlement for disputes submitted by contractors against the city. This Board functions as
a permanent arbitration panel.
Advantages of these Owner Review Boards include a second opportunity to review with
the owner unfavorable decisions made by the on-site representative, and the low costs
imposed on the contractor. With this DART, however, there can be a problem over the
partiality of the Board, since its members are employees of the owner and the contractor
has no representation. Due to this problem of partiality, the New York City Dispute
Review Board has been severely criticized by building organizations (Treacy, 1995),
which see the binding effect given to the decisions as an unacceptable feature in this
application of this technique, considering the composition of the Board.
In the same way that the Neutral Advisor was introduced to ameliorate many of the
limitations of the design architect/engineer, the Dispute Review Board discussed in the
following section attempts to solve the limitation of the Owner/Agency Review Board
associated with its compromised objectivity.

6.3 DISPUTE REVIEW BOARD


Dispute Review Boards (DRBs) play the same role of the individual Neutral Advisor
reviewed in Section 6.1, but in the form of a panel which utilizes “...experienced and
trusted construction professionals with appropriate technical background to address
prevention and resolution of disputes” (ASCE, 1997).
This definition by the American Society of Civil Engineers (ASCE, 1997) incorporates
two important ideas that are the basis of the success of this DART approach:
1) Since construction disputes are usually technical rather than legal, construction
professionals should be involved, and
2) These experts should be involved to prevent as well as resolve disputes.
The roots of the DRB can be found in the traditional role of the architect/engineer as the
owner’s representative and in the arbitration panel. The design professional had been the
logical dispute resolution agent for the construction industry. However, because their
independence is no longer taken for granted as projects and disputes have become larger
and more complex, this notion of an independent and technically qualified board has
developed as an alternative. The idea of having a Board rather than a single individual
comes from the arbitration panel, which encourages unbiased recommendations from the
experts by providing a system for ‘checks and balances’. The inherent objectivity of the
DRB reduces the limitation of other DART, such as the design professional and/or the
Owner/Agency Review Board.
The DRB comes into existence by agreement of the parties at the beginning of the project
and usually the costs are shared equally between the owner and the contractor. Usually, it
is composed of at least three members, two of which are chosen by each party to the
contract, while the third member is appointed by the first two. During construction,
whether or not there are any disputes, the Board visits the site and meets with the site
representatives of all parties, owner/employer, main contractor(s), sub-contractor(s) and,
if necessary, important suppliers of goods to the project. The Board may also attend
monthly job meetings, depending on the initial agreement between the parties and the
level of involvement desired.
Through these meetings and regular site visits, the Board develops a good understanding
of the project, its progress, and the parties involved in the contract. “This real time

DRAFT 2/4/2017 2:32:00 PM 103


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

knowledge of the project’s progress provides, an understanding that is nearly impossible


to recreate during arbitration or litigation once the project is finished” (Kane, 1992). So,
when an actual dispute arises, the Board convenes very quickly to hear and settle it as
soon as possible, based on this real time knowledge of the project. The Board can also
advise parties on areas or issues with potential to become disputes, so they are addressed
and settled before the actual disagreement takes place.
In terms of the results of this dispute resolution technique, ASCE reports “...that a total
of $3.2 billion worth of work was completed or under construction in the period 1975 to
1991 [using DRB], with 81 disputes heard and none taken to litigation” (ASCE, 1997),
and according to ENR (8/26/1991) similar construction projects without a DRB do not
exhibit these same levels of performance.

Contract Dispute Advisory Board (Canada)


The following case taken from the Canadian government shows an interesting
modification of the Dispute Resolution Board technique. In 1987 the Ministry of Public
Works and Government Services of Canada established the figure of the Contract Dispute
Advisory Board to handle and resolve contractual disagreement between the Ministry and
any contractor/consultant. The Contract Advisory Board is basically a DRB with non-
binding authority to review and recommend solutions to the disputants (Figure 19). This
board has three members: one neutral Chairman, one representative of the Ministry, and
one member selected by the contractor/consultant. Bristow (1998) reports that the success
rate in resolving disputes has been 88 %, especially for large, multi-party and multi-issue
disputes, which are common at the Ministry.

104
STAGE 3: STANDING NEUTRAL

Contractor/Consultant requests to the Minister the


constitution of a CDAB to review and settle a
pending claim

Minister Reviews the request and Minister can negotiate a


determines whether it is necessary to form settlement with the
the CDAB contractor/consultant

The contractor gets eight weeks to prepare


and submit in writing to the Ministry copies
of all documents supporting the claim

The Ministry gets four weeks to


review the documents and
prepare its case

Both parties make their respective


presentations to the Board

The Board reviews the information gathered The contractor can accept the
at the presentations and sends a proposal by the Minister, or proceed
recommendation to the Minister, who them to submit its claim to arbitration or
advises the contractor on his/her decision litigation

Figure 19 - Contract Dispute Advisory Boards DART Procedure

Five interesting features of this version of the DRB in the Canadian public works sector
are worth highlighting:
1) The request to form the CDAB is received and reviewed by the Minister of
Public Works, and it is through that office that the decision to form the Board is
taken. This provides the procedure with the necessary official backing to
proceed. Using the Minister also appears to be a last minute effort to resolve the
dispute before choosing to form the Board. Officials are encourage to resolve
the dispute before they are submitted to the Minister for review, for the same
reasons outlined under the ADR technique of Step Negotiations (Section 5.5).
The Board is appointed when a dispute arises, and the Minister chooses to form it.
Therefore, the Board only deals with a specific dispute, and it is not part of the
whole project. This condition makes this type of Board different than a DRB,
which is incorporated into the job from the beginning, regardless of whether
there are any claims.
One person from each side is given the responsibility of presenting the cases.
Presentations to the Board are limited to a maximum of two and a half hours for each
side. This limitation should expedite the proceedings and limit the amount of
evidence presented by the parties. There is no time for expert testimony.
There are no formal rules to run the proceedings, and records of the discussions are
kept confidential. This adds flexibility to the process and encourages disputants

DRAFT 2/4/2017 2:32:00 PM 105


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

to present all the facts, without fear that they will be used in a binding procedure
(i.e., arbitration or litigation) if this step fails to achieve a resolution.
These features suggest that the Ministry of Public Works of Canada has in fact combined
two techniques from the DRL in the CDAB system. The CDAB is set up as a DRB but
operates more like an Executive Trial or Minitrial (Section 7.6). The time limitations and
the involvement of the Minister are characteristics that should encourage a faster
evaluation and resolution of matters. The Minister has the authority to evaluate and
propose alternative solutions to the contractor that the contract representatives may lack.
Despite successful applications of the DRB technique, its main disadvantage can be the
high cost of implementation, estimated to be between 0.5 and 1 percent of the
construction cost. Therefore, the application of this technique requires an evaluation of
the cost implications, for it could represent a considerable investment for both the owner
and the contractor. However, in larger-scale and complex projects, this technique has
resulted in significant savings in litigation and arbitration costs that surpass the costs of
its implementation (ASCE, 1997).

6.4 ON-CALL CONTRACTOR


Another type of project neutral that can help resolve conflicts is an On-call Contractor.
As jobs approach the completion mark, small change orders are often necessary to meet
last minute requirements by the user. At that time, the main contractor is usually less
willing to perform minor change orders and is only interested in obtaining both the
completion certificate and the release of the retention moneys. If the contractor is
“forced” to perform these change orders, delay claims and additional costs can slow the
completion and strain the relationships.
As a way to prevent these last minute confrontations, Zack (a, 1997) suggests that owners
proceed to hire an “on-call” contractor to perform these additional work orders. The
owner and this new contractor can develop a separate schedule to control these activities,
leaving the main contractor free to finish the original scope of work. Special attention
should be given to this new contractor, so as to avoid any type of interference with the
one finishing the job.
Although this option of the on-call contractor has been included here as part of the
Standing Neutral Stage, it can also be considered a Dispute Prevention Mechanism
(Chapter 3) since this contractor will actually help prevent last-minute disagreements
between the owner and the main contractor. Furthermore, it will increase the chances for
a smooth completion and job closeout process.

Land Level Getting back to the Land Level Transfer Facility, the insurance company contracted with
Transfer the neutral to review the claim for its validity as the Owner submitted a claim to the
Facility insurance company upon the receipt of the allegations from the Contractor. Two
registered professional engineers, familiar with ananlysis of similar construction disputes,
undertook the review. The third party neutral provided the following services:
• Review and analysis of geotechnical information contained in the 90 percent
design drawings and commissioned reports.
• Comparison of the geotechnical information available to bidders to reported
conditions encountered by the Contractor.
• Analysis of entitlement to additional compensation resulting from the alleged
changed conditions.

106
STAGE 3: STANDING NEUTRAL

• Verification of costs determined to be compensable and preparation of an


estimate to support settlement negotiations.
• Analysis of project progress schedule to assess the alleged impact of the
changed conditions and quantification of the Contractor acceleration efforts and
supplemental costs.
They produced an expert report on its findings and opinion on the above issues. They
asserted that the Contractors claim for damages relating to the alleged differing site
conditions did not meet the standard of proof and should have been rejected. In addition,
the neutral added that the claim was inflated based on inaccurately reported quantities by
the Contractor. This report influenced the positions of both parties and the dispute settled
in subsequent negotiations.

6.5 SUMMARY
The Standing Neutral stage is based on a prompt, rational, on-site, and impartial review
of disputes by mutually accepted experts. This stage is an attempt to ameliorate the
disadvantages of using the design professional, who for years had been used as a neutral
and knowledgeable third party. All the techniques proposed in this stage share three
common denominators: third party involvement, unbiased decisions, and a
knowledgeable expert, all of which promote substantial cost savings and can eliminate
inefficient use of time and resources in litigation. Nevertheless, these techniques differ
across three different variables: the number of agents involved, the relationship of these
agents with the project (i.e., external or internal to the project), and the stage in which
they are introduced.
Table 11 - Summary of Characteristics of Different Standing Neutral Techniques

Owner Dispute
Standing Neutral Neutral On-Call
Review Review
Technique Advisor Contractor
Board Board
Number of Agents 1 Multiple Multiple 1 company
Relationship of the agent
External Internal External External
with the project
Towards the
From the end of the
When From the
Stage in which the agents beginning project.
conflicts beginning of
become involved of the Before
arise the project
project conflicts
arise

The different levels of each of these variables offer several advantages and
disadvantages. The introduction of only one agent has the advantage of reducing costs
and time, while increasing flexibility in the decision process. However, it suffers the
disadvantage of having decisions depend on the interpretation of only one person who
might fail to understand the multiple and complex issues involved in a dispute. In the
same manner, the introduction of the third party from the beginning of project offers the
benefit of an expert who is highly familiar with the project and its multiple facets, who
can collaborate not only to resolve disputes but also to address potential areas of
problems. This prevention feature of this stage in the Dispute Resolution Ladder is one of
its most important benefits. Nevertheless, the third party’s familiarity with the project can

DRAFT 2/4/2017 2:32:00 PM 107


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

result in loss of impartiality over time. This challenge, in combination with the fact that
having an expert throughout the project increments the costs of implementation of this
technique, represents the main drawbacks of having a third party neutral throughout the
complete project.
Finally, the greatest advantage of an external agent is their impartiality, which often
translates into greater trust from the parties. However, their strangeness with the members
of the project, specially those not involved in their selection, can be a double-edge sword,
and result in difficulties establishing trust, and communication among functional project
team members; thus, interfering with the possibility of gathering accurate information.
The advantages and disadvantages of the different levels of this stage, and how each of
these interact, need to be considered when deciding the most appropriate technique for
the specific characteristics of the project. The selection of the standing neutral technique
most fitting to the specific project will increase the chances of solving the dispute at this
stage or at least promote the clarification of technical issues that will increase the chances
of success. This clarification can help parties return to the negotiation table or proceed to
a higher stage in the DRL with some of the issues already resolved.

6.6 POINTS FOR DISCUSSION


6.1 What qualifications should a third party, such as a neutral advisor (Section 6.1),
possess? When should they be selected and by who?
6.2 What are the differences between a Neutral Architect and a Neutral Advisor
(Section 6.1)? In what setting has a Neutral Architect been typically used?
6.3 Is the cost of a neutral (Section 6.1) covered by his/her performance? Does this vary
based on the scale of the project?
6.4 What are the major advantages of replacing the designer/architect (Section 2.1.1)
with a neutral (Section 6.1) in the DRL? Review the disadvantages list at the end of
Section 6.1? Do these differ from the disadvantages of using a designer/architect?
6.5 How does the Owner/Agency Review Board (Section 6.2) vary from the higher
levels of Step Negotiations (Section 5.5)? If the board is comprised of the owner’s
representatives is it really a neutral entity?
6.6 Graduating from the Owner/Agency Review Board (Section 6.2) to the Dispute
Review Board (Section 6.3) what benefits are realized? Contrast these benefits with
a single Neutral (Section 6.1)?
6.7 What level of involvement in the project should the Dispute Review Board (Section
6.3) take? Should they be involved in prevention of conflicts as well as resolution of
claims?
6.8 Taking a closer look at the Contract Dispute Advisory Board (Case 6.1), is this in
effect a mini-trial? How does this differ from actual litigation? How is a CDAB
structured compared to a DRB (Section 6.2)?
6.9 The inclusion of an On-call Contractor (Section 6.4) in the contract opens the door
to questions as to who is responsible for what. Does this clause complicate conflicts
or resolve them? What could be done to ensure the latter?
6.10 When should the On-Call Contractor (Section 6.4) come on board the project, in the
end or the beginning? What implications might it have if the On-Call Contractor
performed all the owner directed change orders?

108
STAGE 3: STANDING NEUTRAL

6.7 REFERENCES

[ASCE, 1997] Technical Committee on Contracting Practices of the


Underground Technology Research Council. Avoiding and
Resolving Diputes During Construction: Successful Practices
and Guidelines. ASCE. 1997.
[Bristow, 1998] Bristow, David. The New CCDC2: Facilitating Dispute
Resolution of Construction Projects. A paper delivered to the
Canadian Bar Association – Ontario. December, 1998.
[Croain-Harris, 1994] Construction industry ADR / Catherine Cronin-Harris. -- New
York, NY : CPR Institute for Dispute Resolution, c1994.
[ENR, 8/26/1991] McManamy, Rob. Quiet Revolution Brews for Settling
Disputes. Engineering News Record. McGraw-Hill, New York.
pp. 21-23 August 26, 1991.
[Kane, 1992] Kane, Christopher. Mitigation Construction Contract Disputes.
Public Utilities Fortnightly. Vol. 130 (1). pp. 11-12. July 1992.
[Kemp, 1998] Kemp, Jack, (1998). Dispute Resolution Using a Neutral
Architect. Punch List Vol. 20 (4) Winter
[Treacy, 1995] Treacy, Thomas B., (1995). Use of ADR in the Construction
Industry. Journal of Management in Engineering Vol. 11 (1) pp.
58-63. January/February, 1995.
[Zack a, 1997] Zack, James G., (1997). Claims Prevention: Offense Versus
Defense. AACE. Vol. 39 (7) pp. 23-28. July
[Zack b, 1997] Zack, James G., (1997). Resolution of Disputes: The Next
Generation. AACE Transactions. pp. 50-54.

6.8 ENDNOTES

1
© ____CPR Institute for Dispute Resolution, 366 Madison Avenue, New York, NY
10017-3122; (212) 949-6490, www.cpradr.org. This excerpt from “Construction
industry ADR / Catherine Cronin-Harris. -- New York, NY : CPR Institute for
Dispute Resolution, c1994.” reprinted with permission of CPR Institute. The CPR
Institute is a nonprofit initiative of 500 general counsel of major corporations, leading
law firms and prominent legal academics whose mission is to install alternative dispute
resolution (ADR) into the mainstream of legal practice.

DRAFT 2/4/2017 2:32:00 PM 109


C H A P T E R

7
STAGE 4:NON-
BINDING
“I realized that the true function of a lawyer was to
unite parties ... A large part of my time during the
20 years of my practice as a lawyer was occupied

DISPUTE
in bringing about private compromises of hundreds
of cases. I lost nothing thereby – not even money,
certainly not my soul”

RESOLUTION
(Gandhi, cited by Ide, 1993)

A developer and a group of other investors purchased an old apartment building with the
intent to convert it into a condominium and sell the units. This 90-year-old building
consisted of 41 existing units. The developer assumed the role of a Construction
Manager. Various types of contracts were issued to various subcontractors including
fixed price, extra work order, cost plus, and unit price. Overall, the developer estimated
to make about US$ 6 million worth of repairs.
In doing this work, the developer had to prepare a document required by law called an
offering for prospective buyers. A designer inspected the building’s current condition and

CHAPTER LOOK AHEAD


WHAT IS IT? Non-binding dispute resolution procedures result in a mutually agreeable solution with the
help of a third party. The procedures are still flexible, but more structured than previous stages. Parties
can enter the proceedings voluntarily and select the third party by mutual consent. Other times the
contract dictates that participants must enter this stage before proceeding up the DRL. This stage
includes Mediation, Conciliation, Advisory Arbitration, and various forms of mock trials.
WHO IS INVOLVED? Mediators, Retired Judges and Experts along with the participants, are involved in
this stage. Services provided in this stage can be done by organizations such as the American
Arbitration Association and the International Chamber of Commerce.
WHY IS IT IMPORTANT? This stage allows for one last attempt at reaching a solution with the participants
still able to have control over the outcome. Flexibility over the outcome is the major advantage.
Awards are not based solely on monetary awards. Costs start to become an issue, although they are still
significantly less than litigation.
HOW TO APPROACH IT? Understand the significance of non-binding. Choose the appropriate non-binding
DART technique based on the individual project circumstances. Follow the necessary processes.

KEY CONCEPTS
Mediation .......................................................112 Conciliation ..................................................... 117
Advisory Arbitration......................................118 Fact Based Mediation ..................................... 119
Mini-Trial ......................................................120 Voluntary Settlement Conference ................... 121

110
STAGE 4: NON-BINDING DISPUTE RESOLUTION

the developer then made representations as to exactly what they were going to do to the
building. These included the following items: repair the foundation, fix the façade, repair
the windows, replace the window frames, and replace the roof. Purchasers bought units
based on this document and other beautifully designed marketing brochures distributed
by the developer.
The developer completed the work, but the homeowners were displeased with the quality
of the units and asserted the developer had not finished the representations they had made
in the offering. The homeowners had noticed numerous defects in the construction such
as water leakage, code violations, and a poor heating system, but the leakage was the
issue that spearheaded the conflict. Poor oversight and a lack of strong management on
the part of the developer had led to a haphazard construction program and substandard
performance. Some subcontractors cut corners on lump sum contracts to save money
while others milked hours on extra work order contracts billed by the hour. The owner
caulked the windows, instead of replacing them as stated. Only patchwork was done on
the brick and where it should have been repointed. A cheaper roof was used and placed
over two existing layers, varying from the offering and violating state building codes.
In trying to resolve these issues, each participant took a hard position. On the developer’s
side, they felt that because they spent the US$ 6 million budgeted to improve it, that they
had met their obligations. In addition to this, they asserted that not all of the issues noted
by the homeowners stem from what the developers promised, and therefore they cannot
do anything about them. In response to the code violations, the developer argued that the
building inspector signed off on it. On the other side, the homeowners just wanted it
fixed. If it took $1 thousand or $10 million, they did not care as long as all the problems
were fixed. Even though many of the issues were the obligation of the developer, some
were not. Subsequently the homeowners association hired an attorney, and made a list of
inefficiencies. The lawyers in turn did not look at the obligations of the developer, but got
greedy and took the position that they wanted everything and more fixed. They had the
attitude that any jury would be sympathetic to a group of elderly senior citizens who were
abused by the big bag developer.
The parties are obviously at an impasse. Are the parties committed to resolving this
dispute effectively? Consider both of the positions, should either one of the participants
make concessions in order to reach a solution? What affect did the hiring of lawyers have
on the negotiations between them? How might a non-binding third party make each party
see the other side? Who should pay for a third party if needed?

7.1 IMPORTANCE OF NON-BINDING PHILOSOPHY


The Non-Binding Dispute Resolution Stage is the last phase in which the parties still
have control over the outcome of the dispute and can participate in the development of an
agreeable settlement in conjunction with a third, neutral party. In the next two stages,
Binding Dispute Resolution and Litigation, all decisions reached by the third party will
be mandatory and will imply strict procedures and rules for their implementation. The
non-binding dispute resolution stage has become popular as it facilitates the meetings of
the parties, approaching them to a non-zero sum result. Procedures are still flexible, and
parties can still enter the proceedings voluntarily and select the third party by mutual
consent.
The increasing importance of non-binding dispute resolution methods is supported by a
benchmark survey of 200 of the top 500 design firms in the US, conducted by the
Johnson & Higgins Construction Group with the aid of Arthur Andersen (ENR,
1/15/1996). This study showed that engineering and design firms that use at least one of

DRAFT 2/4/2017 2:32:00 PM 111


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

the three risk management programs (Total Quality Management, DART, or Partnering)
had the lowest professional liability losses and insurance premiums in the industry. Based
on this study, firms with a TQM program have 31% lower professional liability losses
than those that do not. Those using DART have 19% lower losses, and firms with formal
partnering programs have 10% lower losses than those that do not.
These results support the efforts put forward by DPIC Cos. Inc., of Monterey, California,
to promote the use of DART among the 7,300 design professionals it insures in the US
and Canada (ENR, 7/11/1994). Since 1991, DPIC has been encouraging the use of formal
mediation program called “Mediation Works!” to resolve disputes by offering
policyholders a 50% reduction (capped at $12,500) in their deductible for claims resolved
using DART. The rationale behind the offer is that the program will reduce legal and
settlement expenses by preventing the “inevitable conflicts, which arise [in construction]
from becoming claims and lawsuits” (Hunter et al, 1995). 1
“Mediation Works!” has been a total success. During its first three years, DPIC
reimbursed a total of $4.3 million in deductibles to its clients, yet it was able to lower its
average legal expenses per closed claim from $22,000 to less than $18,000, and its
average loss per closed claim from $116,000 to $103,600. In 1993 alone, DPIC
reimbursed a total of $1.8 million on 236 claims (ENR, 7/11/1994). Simple calculations
can help understand the economic benefits of this program for DPIC:

Table 12 – Insurance: Mediation Costs/Benefits

Average savings in legal expenses per claim:


from $ 22,000 to $18,000 $ 4,000
Average savings in losses per claim:
from $116,000 to $103,600 $ 12,400
Total average savings by DPIC per claim through mediation:
$ 4,000 plus $ 12,400 $ 16,400
Total reimbursement costs of deductibles to clients: (1993)
$ 1.8 million in 236 cases ($ 7,630)
Average net savings for DPIC per claim $ 8,770
Average total net savings for DPIC in 1993 $ 2.0 million

Thus, in 1993 DPIC spent $1.8 million dollars in the implementation of “Mediation
Works!,” but was able to save a net average of $2 million dollars in legal and settlement
expenses, a 100% return on investment. Although these calculations do not consider any
direct costs associated with the implementation of the program, the benefits are large
enough to understand its success. Since 1991, the percentage of DPIC clients using
mediation in disputes has grown from 10% to 29% in 1995, and some local offices of
DPIC report that 40% of their cases are being mediated (Hunter et al., 1995).

7.2 MEDIATION
Construction attorneys generally perceive mediation to be the most effective approach for
achieving a wide range of goals, such as enhancing parties’ understanding of disputes,

112
STAGE 4: NON-BINDING DISPUTE RESOLUTION

opening channels of communication between disputants, minimizing future


disagreements, and reducing the cost and duration of dispute. In fact, mediation typically
requires relatively less money and time. The American Arbitration Association stated that
nearly half of the mediations reported to them are conducted in two days or less and
fewer than 10% take more than six days (Macneil et al., 1994). More than 50% cost
$3,000 or less, and fewer than 10% cost more than $20,000. The mediator is the figure
that aids parties in achieving these goals by promoting an open discussion of the facts
that have lead to the disagreement while serving as a guide for clear and honest
communication. This approach is crucial for the mediation process, specially considering
that this DART could be the last step prior to the Arbitration or Litigation stages, which
often results in a win-lose resolution.
An important aspect of mediation is that parties must be able to understand both sides of
the problem to develop a non-zero sum solution. That is precisely why pre-hearing
statements include 1) a narrative of the facts to let the mediator understand the
background of the dispute; and 2) a description of each individual dispute with facts,
contractual provisions, issues of law, and damages. Procedures then continue with an
exchange of statements between parties and the mediator, something that allows sides to
determine if they are mediating the same dispute.
The exchange of statements usually starts with all parties meeting jointly in a caucus with
a mediator. Being a skilled communicator and interpreter, this third party neutral is
capable to quickly identify the strengths and weaknesses of the case at hand. During the
meeting, each party’s advocate is asked to present a brief summary of their case. The
mediator then recaps the presentations and the parties break up for individual meetings
with the mediator. The private caucuses have three objectives:
1) They allow parties to reveal things they did not want to state in front of the
adversary.
2) They provide a space for the mediator to ‘play devil’s advocate’ and present
new scenarios.
3) They allow each party to realistically assess settlement possibilities and
opportunities.
The mediator then goes back and forth between the parties in an effort to develop an
acceptable settlement for the dispute. Throughout the process, a mediator plays the role
of a facilitator, a translator of the positions each party wants to explore without formally
committing to them. In a way, mediation is simply an extension of a negotiated
settlement, but one in which confidentiality is maintained throughout the process, and an
offer is not such until it is made through the mediator.
The AAA (AAA, 2000) summarizes some of the benefits of mediation as follows:
• “Reduces the hostility between the parties and helps them to engage in a
meaningful dialogue on the issues at hand;
• opens discussions into areas not previously considered or…developed;
• communicates positions or proposals in understandable …terms;
• probes and uncovers additional facts and the real interests of parties;
• helps each party to better understand the other parties’ views and evaluations of
a particular issue, without violating confidences;
• narrows the issues and each party’s positions, and deflates extreme demands;
• gauges the receptiveness for a proposal or suggestion;
• explores alternatives and searches solutions;
• identifies what is important and what is expandable;

DRAFT 2/4/2017 2:32:00 PM 113


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

• prevents regression or raising of surprise issues; and


• structures a settlement to resolve current problems and future parties’ needs.”
Another significant and often overlooked aspect of mediation is that not all cases settle
for monetary damages. In mediation parties can agree to numerous social and/or
monetary obligations and commitments that can meet the needs and interests of all the
parties; opening the door for win-win solutions. For example, a contractor may agree to
settle a dispute by performing additional work at cost. In contrast, courts can only provide
limited types of settlements, which often reduce the options available to the parties such
as money damages, injunctive relief, and declamatory judgments.
Mediation is a flexible technique and its only role is to guide parties towards dispute
resolution. A mediator has no binding authority to render decision on any matter. For this
reason, real zero-sum disputes are not to be handled through mediation and neither should
constitutional issues or any case in which legal precedent must be set (Meyer, 1995).
The characteristics of mediation have allowed this technique to gain popularity in the
United States as an alternative to arbitration and litigation. The 1997 edition of the
American Institute of Architects’ construction contract forms recommends mediation to
solve disputes before arbitration can be pursued. Similarly, the new standard form of
agreement and general conditions between the owner and contractor for lump-sum
projects of the AGC includes “...a menu of alternative dispute resolution [which] starts
out with direct discussions between the parties and then moves to mediation” (ENR
2/14/1998). The reasons for this popularity are well founded. Meyer (1995) estimates that
timely mediation can save 80% of court and counsel costs, and “...[Construction]
industry studies indicate a 90% success rate [for mediation] in resolving disputes” (ENR
2/14/1998). This is mostly because of the fact that mediation offers a contextual
alternative to litigation without compromising any side’s strategy or real interests. This
data puts mediation in a competitive advantage against other methods of ADR.
A joint effort by Cornell University, Price Waterhouse, and the Foundation for the
Prevention and Early Resolution of Conflict (PERC) established the differences between
mediation and arbitration (Table 13) as ADR mechanisms. The comparison is based on
the views expressed in a survey by legal counsels of large US corporations.
Table 13 - Mediation and Arbitration Differences (Lipsky et al., 1997)

MEDIATION ARBITRATION

Predominantly triggered by parties. Predominantly triggered by contract.


Slightly less experience with the process,
Widespread experience with the process.
although still widespread.
Used in most types of disputes. Used in a narrow set of disputes.
Extensive growth expected. Growth will be limited if at all.
Parties perceive gain in process control. Parties uneasy about control of arbitration.
Arbitrators come primarily from private
Wide variety of sources for mediators.
providers.
Some uneasiness about qualifications of
Less confidence in arbitrators.
mediators.
Usage in some industries much higher than
Used in almost all industries.
others.

114
STAGE 4: NON-BINDING DISPUTE RESOLUTION

Despite some obvious benefits like a general applicability to different industries, the
international community has only recently began to recognize formal mediation
procedures as an important tool for businesses. Analyzing the case of the United
Kingdom, it results evident that their use of mediation is still very limited compared to
the US. The two largest British providers of mediation service (ADR Group and CEDR)
each handle between eight and ten mediations per month or a total of 120 per year, by
contrast, JAMS/Endispute, Inc., the largest US ADR provider, handled 17,000 cases in
1995 (Coates, 1997). 2 Although these results do not specifically relate to construction,
they help illustrate the different levels of implementation of mediation in these countries.
In spite of its late-entrant status, the UK does provide a helpful international example of
the different applications of mediation in construction. Analyzing British engineering
cases, Gould et al.,(1998) identified a varied spectrum of mediation styles within the UK
construction industry. It included informal, facilitative (or facilitated), institutionalized,
and evaluative mediation (Figure 20).

Informal Institutionalized
Mediation Mediation

Facilitative Evaluative
Mediation Centre for Mediation
Dispute
Resolution
CEDR Institution
of Civil
Engineers
ICE

Figure 20 - Spectrum of Mediation Styles in use within the Construction Industry in the
United Kingdom

In informal mediation, one of the parties incorporates a third party in an effort to


begin/resume the negotiations, or break up a deadlock. This technique is commonly used
in many dispute resolution processes, and sometimes the mediator is a common
acquaintance or a recognized professional within the industry. Thus, sometimes all that it
takes is a telephone call or brief intervention for the “mediator” to reestablish the talks.
In facilitative mediation, the third party mediator helps parties communicate and
exchange information, but refrains from issuing an opinion as to the interests or a
possible settlement. The mediator is not an arbitrator, and they have no power to impose
a solution upon the parties. The role of the mediator is simply to promote communication,
identify common grounds between the parties, and mediate a settlement.
Institutionalized mediation is in fact a facilitated mediation that is formally administered
by an organization dedicated to ADR. With the increasing demand for mediation in the
UK, private organizations like the Center for Dispute Resolution have been established to
provide, manage, and organize mediation procedures. An advantage of institutionalized

DRAFT 2/4/2017 2:32:00 PM 115


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

mediations is the expected improvement in the qualifications and expertise of the experts
and third party neutrals.
The last style of mediation in the spectrum identified by Gould et al. (1998), evaluative
mediation, occurs when the third party neutral, in addition to developing a common
ground for the settlement, also issues an opinion as to possible settlements based on the
information developed through the proceedings. In other words, if parties fail to mediate
a resolution, the mediator issues a recommendation on the case.
Another illustrative example of international applications of mediation of construction
disputes is found in Japan. In this case, the Japanese Construction Business Act requires
that construction contracts oblige the parties to address the following issues and include
them in writing in all construction contracts:
1) “How to deal with changes in construction schedule or contract amount, or
sharing and evaluation of loss where construction is changed or postponed or
canceled;
2) How to share and evaluate losses in case of Acts of God or other force majeure
events;
3) How to address changes in contract amounts or construction scope due to
changes in materials or services;
4) Sharing of the liability for damage to third parties;
5) Interest, penalty and other damages in case of delay in performance of
contractual obligations and other liabilities; and
6) Method of dispute resolution.”
(Fenn et al., 1998)
What Japanese authorities have identified is that, in the past, failure to include these
elements in a construction contract has usually led to unnecessary disputes.
In regards to the Japanese common procedures, both public and private
contractual forms in Japan generally include one of two types of dispute
resolution procedures [Figure 21]. In procedure A, both parties agree to solve
their disputes through a third party intermediary designated in the contract,
using either mediation or conciliation. If parties fail to reach a settlement, the
dispute is brought to the Construction Disputes Resolution Committee (CDRC),
similar to a Dispute Resolution Board. In procedure B, disputes are presented
and settled by the CDRC from the beginning of the project, and no party can
request arbitration before or during mediation or conciliation, unless there is a
joint agreement to that effect.
(Fenn et al., 1998)
In both procedures, parties can agree to arbitration once the disputes reach the committee.
Indeed, the Construction Disputes Resolution Committee was established by the
Construction Business Act to provide consultation, mediation and dispute resolution
through a number of regional and local committees located throughout the country.

116
STAGE 4: NON-BINDING DISPUTE RESOLUTION

Procedure A: Mediation or If both parties agree


Two-step Conciliation
process using third
party

Construction Arbitration
Procedure B:
Disputes
One-step
Resolution
process
Committee

Figure 21 - Dispute Resolution Procedures in Standard Japanese Contracts

In summary, the British and Japanese examples presented above, in conjunction with the
examples on the use of mediation in the US, all highlight the multiple benefits of
mediation as a tool to reduce the likelihood of advancing towards binding procedures or
litigation. Nevertheless, there are some drawbacks to the use of mediation, specifically in
relation to the exchange of confidential information, which may expose weak aspects of
each case and reveal possible trial strategies. In order to mitigate this problem, parties
should include strict limitations on the use of information developed through this non-
binding technique in the agreement to mediate. Also, the information provided to the
mediator should be classified as confidential, to avoid having it disclosed without
approval during the proceedings. This way the mediator still receives all the information
to attempt to develop common grounds for settlement, but with the condition that a
portion of it remains confidential as long as an agreement is not reached. Another risk of
mediation results from its increasing use. Many researchers and experts in the topic fear
that as mediation becomes the fallback dispute resolution technique for most construction
conflicts, it will lose its flexibility and harmonious nature, being at risk of suffering the
same destiny of arbitration.

7.3 CONCILIATION
Conciliation differs from mediation in that the neutral party evaluates the dispute and
then issues proposal for the resolution of the dispute that is presented to the parties for
approval or rejection. Conciliation’s non-adversarial nature attempts to improve business
relationships, and the AAA reports that 80% of the cases that attempt conciliation prior to
litigation are settled (Langeland, 1995).
In the UK, the evaluative form of mediation previously identified is in fact a conciliation
procedure, as the mediator is expected to provide the parties with a written assessment of
the dispute and a possible outcome. The engineering side of the construction business has
preferred conciliation over mediation, and the Institution of Civil Engineers (ICE) has
introduced this technique in their standard form of contract for engineering design work.
Moreover, in the most recent Design and Build contract form taken from ICE,
conciliation has been included as a mandatory step in the dispute resolution process.
In other parts of the world conciliation also receives important attention. The concept was
already a part of New Zealand’s “Conditions of Contract for Building and Civil

DRAFT 2/4/2017 2:32:00 PM 117


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Engineering Construction” since 1987, in a process that followed some standard steps
and rules; among them:
• “The process is voluntary;
• The conciliator mediates between the two parties in order to identify common
grounds for a settlement;
• All discussions are confidential and information disclosed during the
procedures can not be used in other proceedings should conciliation fail to
achieve a settlement;
• Each party pays half of the costs of the conciliator;
• The conciliator may provide a non-binding written opinion as to the case and
the probable outcome if the case is resolved through arbitration or court
litigation.”
(Hollands, 1989)
New Zealand’s version of conciliation also added the following adjustments and
refinements to the Mediation procedure:
1) “Parties have ten working days to agree on conciliation, and choose a third
party neutral from the date of the request.
2) Once parties agree on using this procedure, and select a conciliator, they have
two months to reach a settlement or to have the conciliator issue a
determination. After that period, either party is free to proceed with arbitration.
3) The decision of the conciliator becomes binding if ten working days pass and no
party notifies the other in writing that it rejects the determination. So the non-
binding decision becomes automatically binding and final to the parties after the
specified period elapses.
4) A presiding judge may act as a conciliator if both parties agree to submit the
case to him/her in that form. If the procedure fails to produce an agreeable
solution, the judge remits the case to another judge for hearings and trial
proceedings.”
(Hollands, 1989)
Hollands (1989) comments on these older conditions saying they are “…more practical
and helpful...” with regards to outlining and defining the DART for the disputants, than
the more recent FIDIC provisions for Amicable Settlement.

7.4 ADVISORY ARBITRATION (NON-BINDING ARBITRATION)


In this non-binding dispute resolution procedure, parties select a third neutral player and
then jointly and/or separately present the facts of their dispute. The arbitrator then
proceeds to issue a non-binding decision or opinion as to the possible outcome if the
dispute were brought before a judge or a jury.
The more complete form of this approach follows all the stages of arbitration, but it
includes an advisory opinion for the parties as the final award. This procedure is known
as Advisory Arbitration or Non-Binding Arbitration, and it can be an efficient way to put
the parties in a position to evaluate a likely outcome of binding proceedings and provide
them an opportunity to negotiate a settlement.
The procedure is very similar to a Mini-Trial (Section 7.6), with the benefit that the
parties have an opinion from a neutral third participant. It could be said that the advisory
arbitration is actually arbitration in every sense, except that it does not bind the parties

118
STAGE 4: NON-BINDING DISPUTE RESOLUTION

into accepting the decision of the neutral. Furthermore, the presentations and the
procedures are relatively simpler than those for formal arbitration. Thus, this voluntary
negotiating tool can be easier to practice and more relaxed than the binding arbitration.
Together with some other DART like mediation and conciliation, this approach can be of
great help in complex disputes that combine technical and legal matters. Non-binding
arbitration can provide the framework for the fact-finding effort and the exchange of
information between the parties, while mediation can provide the communication and
cooperation tools required in developing a settlement. Again, because these procedures
are not binding, parties have more flexibility in defining and changing the role of the
third party based on the specific requirements and characteristics of the dispute. This
notion is supported by Beresford Hartwell (1998), who argued that in order for success to
occur; alternative dispute resolution procedures cannot always be confined to a readily
specified task:
“A mediator for example may need to have some ability to ascertain facts and to
ascertain them without having to rely entirely upon the parties, whose
objectivity is likely to be coloured. A fact finder may need some powers of
persuasion. Rigid categories and restrictions may well be an obstacle to a
realistic settlement” (Beresford Hartwell, 1998).
A simpler form of non-binding arbitration is known as the Advisory Opinion. It is very
similar to a Neutral Advisor (Section 6.1), except for the fact that the third party is not
incorporated into the project from the beginning. In other words, the neutral party only
starts to play a role when a dispute arises and parties decide to request an outside opinion.
Groton (1997) suggests this arrangement can bring disputes closer to reality, as the
neutral view encourages parties to focus on the issues and deal with the disputes before
they evolve into something larger with greater mutual implications.

7.5 FACT-BASED MEDIATION


This form of DART is a combination of Advisory Opinion and Mediation. When parties
agree to use this approach, they select a mediator who proceeds to conduct a complete
assessment of the facts and issues in dispute between the parties. The mediator analyzes
each party’s point of view and reviews all the evidence and documents generated by the
case. Once this information is processed, the mediator issues confidential and detailed
reports to each party, where he/she outlines the potential costs of litigation, the probable
outcomes of a suggested binding procedure, and a settlement recommendation for the
case (Groton, 1997).
An interesting feature of this non-binding procedure is that each report given to the
parties is different from the other, except for the “bottom-line, dollar recommendation”
Groton (1997). The mediator does not provide a unique solution for the disputes, but
he/she explores in each report to the parties possible alternatives for a settlement. The
dollar settlement is common for it is part of the mediator’s assessment of the probable
outcome if the dispute is taken to a binding procedure.
After this point, the mediator has hopefully been able to identify common grounds for a
settlement, and he/she can proceed to mediate the talks between the two parties. The
mediator retains the capacity to issue new recommendations and opinions via separate
reports as the negotiations move forward. The mediation aspect of this procedure
involves the same techniques described in Section 7.2.

DRAFT 2/4/2017 2:32:00 PM 119


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

7.6 MINI-TRIAL OR EXECUTIVE TRIAL


As all the other DART approaches mentioned in this chapter, the Mini-Trial is a
voluntary, private, non-binding procedure that helps senior management understand the
issues in dispute, assess the risks of proceeding with a binding approach, and hopefully
negotiate a settlement agreeable to all parties.
In 1991 the American Bar Association defined this DART approach as follows (cited by
Stipanowich, 1996):
“Mini-Trial is a private process in which counsel for the opposing parties
present their cases in condensed form in the presence of designated
representatives for each side who have authority to settle the dispute. Usually,
an independent and impartial third party “advisor” is also present. After the
presentation, the parties’ representatives meet to discuss settlement prospects.
At some point, the third party advisor may offer certain non-binding conclusions
regarding the probable adjudicated outcome of the case and may assist in
negotiation”
Groton (1997) also defines the Mini-Trial as “... a brief presentation of each side’s ‘best
case’ arguments in the presence of principal executives of both parties, whose efforts are
usually facilitated by a third party neutral,” offering a simpler explanation to the
procedures involved in this non-binding and conciliatory technique.
The advantages of this approach are the achievement of non-binding results, an effective
mutual participation, guaranteed privacy, and an overall control over the process.
Additionally, this system is relatively cheaper than litigation or arbitration, even though
proceedings are carried out as if the case was being presented in front of a court or
arbitration panel. This makes it possible for managers to assess the strengths and
weaknesses of their case and those of the opposing party, facilitating the decision to
develop a settlement proposal.
The role of the third party neutral in the Mini-Trial is critical as in the other cases, since
they are responsible for providing both parties with a thorough assessment of each case.
Only then can they truly help the parties develop a solution acting somewhat like a
mediator.

7.7 SUMMARY JURY TRIAL


A variation to the Mini-Trial is that instead of having company executives as the
members of the panel parties, should include professionals with expertise in the specific
field in dispute. This panel would resemble a Dispute Review Board (Section 6.3) in
terms of the knowledge and neutrality of its members, with the difference that these
would be working in front of representatives of both firms with the capacity to accept or
reject a resolution. Moreover, the presentations would take place at a stage in the dispute
process in which the next available options are binding arbitration or litigation. This
alone should encourage representatives to design and accept a resolution based on the
presentations.
This alternative dispute resolution method is very similar to a Mini-Trial, with the
difference that a counsel from each party makes presentations in front of a “rented” jury
of six people. Zack (b, 1997) describes the Summary Jury Trial as follows:
“Attorneys for both parties are each given 1 hour to summarize their case
before a “rented” jury of six people ...After the case summaries have been

120
STAGE 4: NON-BINDING DISPUTE RESOLUTION

presented, the [neutral advisor 3] provides a short explanation of the law


concerning the issues in dispute, and the jury retires to the jury room. The jury
tries to reach a consensus opinion on the case. Failing that, individual juror
views are presented anonymously.”
Among the advantages of this technique, as outlined by Zack (b, 1997), the one-hour
limitation on presentations forces attorneys to focus on the issues and leave aside
complex legal issues and irrelevant evidence. This time frame also prevents the
introduction of excessive evidence or the use of witnesses and experts, which greatly
reduces costs when compared to court litigation. The matter is presented, and a decision
is reached, in a matter of one or two days at the most. Finally, an important benefit is that
decisions are not binding to the parties, yet they provide management with a valuable
insight as to the strengths and weaknesses of their respective cases. This insight might
result in new approaches to the negotiation and eventually into a satisfactory settlement.
In a nutshell, the results of this procedure provide disputants with an understanding of
“how a potential jury will react to the case” (Zack b, 1997) but without actually taking
the dispute to court. The non-binding decision of the jury, if reached, can improve the
chances for a negotiated settlement to be achieved.

7.8 VOLUNTARY SETTLEMENT CONFERENCE (RENT-A-JUDGE)


In this form of ADR, a retired judge acts as a neutral facilitator/mediator between the two
parties during the negotiations. This is a fast and inexpensive approach for parties to
reach an agreement under a legal framework, rather than through private negotiations.
The judge or magistrate is selected by mutual agreement of both disputants. Parties are
free to select a judge with significant experience in the field of construction, both in
managing complex cases and in determining and issuing decisions. The judge’s prior
experience in construction disputes provides added benefits to this form on non-binding
DART. In addition, parties are able to schedule conferences and follow-up meetings with
the selected judge without the administrative and/or legal formalities of arbitration or
litigation. This characteristic provides for a faster process.
Among the responsibilities of the judge are: 1) running the proceedings very much as a
court process; 2) guiding the parties with regards to legal issues in the dispute; 3)
suggesting tentative compromises; and 4) issuing advisory settlements subject to approval
by the parties (Zack b, 1997). Treacy (1995) reports that in the Eastern District of New
York, courts allowed this settlement judge to act as a mediator between the parties,
following the procedures described in Section 7.2 to promote communication and
develop common grounds in which to build an agreement. In order to maintain
confidentiality during these conferences, the information developed through mediation is
not allowed in court if a settlement is not reached and the case proceeds to litigation.
Some courts have implemented a similar procedure for pre-trial motions and discovery in
an effort to shorten the duration of the actual hearings. These court appointees known as
Special Masters or Settlement Judges are appointed by the court to control the discovery
process and resolve common pre-trial disputes. In these proceedings, the court is involved
in setting the responsibilities of the Master and reviewing the award. The costs of the
Master are determined by the judge, who also determines how they will be shared by the
disputants. In the Eastern District of New York, this technique has been used in cases,
which involved large sums of money, and the dispute is very complex (Treacy, 1995).
The Master brings into the proceedings experience in the construction field and usually
more flexibility in terms of schedule.

DRAFT 2/4/2017 2:32:00 PM 121


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Condo We can see the effect non-binding arbitration has on disputes by returning to the
Project Condominium project. When the homeowners association added a lawyer who adopted a
hard position, the negotiations between the parties began to fail. The owner recognized
and accepted responsibility for his actions and was willing to meet his obligations, but
this was not possible with the hard position taken by the homeowners. To prevent the
conflict from escalating to litigation, the developer hired a third party to help develop a
non-binding solution.
After reviewing the case and hearing both sides, the assisting third party estimated that
upwards of a half a million needed to be spent by the developer to meet his obligation,
almost a 10% of the original budget. An evaluation was made of the building and issues
were resolved on a case-by-case basis. To bring things into perspective for both parties
the third part look at what was promised, what was done and what the current condition
of obligation.
After five or six sessions and hours of research by the third party, about $50,000 in
billable hours, the parties grew apart. Homeowners wanted US$ 2 million although they
said money was not important and they really just wanted it fixed. The developer
proposed $500,000 in improvements. Mediation failed. Failure was attributed to the lack
of commitment of both of the parties, but more so on unrealistic expectations of the
homeowners. As noted in the chapter, commitment from both parties to develop a non-
zero sum solution is necessary for a successful outcome.
The case has now proceeded to litigation and both parties have effectively lost control
over the outcome. The cost of the third party attempt represents about 1% of the initial
budget. Both parties can only hope that attorney and court fees mirror this as the fight has
already lasted 10 years.

7.9 SUMMARY
The Non-Binding Dispute Resolution stage is crucial in the DRL, for it is the last
voluntary step before the conflict moves to Binding Arbitration and/or Litigation; stages
that result in increased use of economic and time resources, and relationship strains. Non-
binding procedures are characterized by higher levels of formality when compared to
previous stages in the DRL; however, they continue to preserve the flexibility of the
outcome, compared with the stages that follow. This chapter reviewed five important
techniques that can be used to effectively and efficiently resolve disputes: Mediation,
Conciliation, Advisory Arbitration, Fact-Based Mediation, Mini-Trial, Summary Jury
Trial, and Voluntary Settlement Conference.
Mediation has gained importance in the resolution of disputes in the last few years. It
rests in the following principles: the earlier the dispute is resolved, the less damage it
causes; the individuals involved in the dispute are the ones most capable of coming up
with the best solution to their problems; the parties involved in the dispute can best
preserve their future relationships without resorting to an adversarial process; and people
issues may impair the ability to communicate to resolve problems. The use of mediation
offers the parties multiple benefits, such as: the ability to remain involved in the
negotiation, the chance of having a third party neutral that can aid them develop solutions
they might not have considered otherwise, the possibility of arriving to a settlement faster
than in litigation, a significant cost reduction when compared to the litigation process, an
increased likelihood of safeguarding the relationship of functional teams, and the
opportunity for creative solutions and compromises (i.e., win/win).
Conciliation, another non-binding technique, resembles many of the principles of
mediation, with the addition that the third party issues a non-binding recommendation,

122
STAGE 4: NON-BINDING DISPUTE RESOLUTION

offering disputants information on the possible outcome if the case continues to


arbitration or litigation.
Advisory Arbitration, also known as non-binding arbitration, follows all the standard
procedures of Arbitration, yet it includes, as the final award, an advisory opinion as to the
possible outcome if the case is presented to an arbitrator. Although this technique pays
less attention to helping the parties communicate with one another, the advisory opinion
can foster a new stage of negotiation where a settlement can be achieved without
proceeding to binding arbitration. Fact-Based Mediation is a non-binding technique that
combines the principles of Advisory Opinion and Mediation. The mediator assesses the
facts and issues in dispute and then presents a different report to each party, where he/she
outlines the potential costs of litigation, the probable outcomes of a binding procedure,
and a settlement recommendation for the case. In Mini-Trial, each party presents its case
to upper management and to a third neutral party. The presentation of the case helps
management understand the issues in dispute, assess the risks of proceeding with a
binding approach, and hopefully negotiate a settlement. A modification of the Mini-Trial
is the Summary Jury Trial in which the counsel for each party makes presentations to a
rented jury. This technique, as well as the Voluntary Settlement Conference (Rent-a-
Judge), allows the parties to see how a potential jury or judge would react to the
arguments being presented. In both of these two procedures, the parties issue an advisory
settlement for approval and acceptance.
In the face of dispute, it would be unrealistic and ineffective to try to apply all of the
techniques previously described. As discussed in earlier chapters, parties involved in a
non-binding conflict resolution process must think about their needs, objectives,
relationship with the opposing party, and the facts of the case before choosing the most
appropriate technique. The techniques presented in this chapter can be organized in a
continuum (Figure 22), beginning with less formality putting more emphasis on the
parties ability to solve the dispute, and continuous effort to achieve a win-win outcome,
to increased formality, legal representation, and confrontation between parties. This
continuum depicts the trajectory that if followed would lead towards the next stages in
the DRL: Binding Arbitration and/or Litigation, if conflicts are not effectively resolved in
this stage. Chapter 8 introduces the Binding Stage, addressing both its strengths and
limitations, as the last step in the DRL, before disputes proceed to Litigation.

Advisory Fact-Based Jury Trial


Mediation Conciliation Arbitration Mediation Minitrial and Rent-a-
Judge

Flexibility: decreases along the continuum, less chances for win-win solutions

Formality: increases as the techniques required more predefined steps

Third Party Role: moves from a facilitator of communications to a judge or jury with only
advisory opinion

Costs: expenses should be expected to increase as the procedures become more


complex

Figure 22 – Continuum of Non-binding Dispute Resolution Techniques

DRAFT 2/4/2017 2:32:00 PM 123


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

7.10 POINTS FOR DISCUSSION


7.1 In mediation (Section 7.2), what should be the role of an insurance company such as
DPIC? What are their interests? Do they have justification to be involved at this
stage? Is their presence beneficial to other parties involved?
7.2 What are the major advantages and disadvantages of mediation (Section 7.2)?
Compare these with previous DART mentioned in this book. How do they differ?
7.3 Is non-binding mediation (Section 7.2) adversarial or collaborative? Does this stage
in the DRL allow parties to change their position as new facts are presented and a
better understanding of the situation is realized?
7.4 How important is the idea that not all settlements need be in terms of monetary
damages (Section 7.2)? Discuss implications of this concept?
7.5 How critical is the need in the United States for a centralized dispute resolution
entity such as the CEDR (Section 7.2)? Should this be a public or private entity or a
partnership of both?
7.6 What are the disadvantages associated with conciliation (Section 7.3)? In what
situations should this method be used? Is conciliation placed at the appropriate step
in the DRL?
7.7 There are numerous variations of non-binding DART. When are there too many?
Should it be the responsibility of the owner to select the processes to be used before
the bid is awarded, or should they be jointly selected after the award of the contract,
before a dispute or after a dispute?
7.8 How valuable is an Advisory Opinion (Section 7.4) to the participants? Might this
opinion deter them from proceeding to litigation? Is it more or less valuable
depending on the qualifications of the arbitrator?
7.9 Can non zero-sum solution be reached through Fact-Based Mediation (Section 7.5)?
Is this ‘reality check’ a useful step, or does it just add time to the process?
7.10 As we move up the DRL, the technical expertise and construction experience of the
selected or appointed neutral seems to decline. What effect does this have on the
outcome? How might one participant change their case to appeal to such
individuals?

7.11 REFERENCES

[AAA, 2000] American Arbitration Assiociation. A Guide to Mediation and


Arbitration for Business People 2000.
[Beresford Hartwell, Beresford Hartwell, Geoffrey M., (1998). The Relevance of
1998] Expertise in Commercial Arbitration. " Arbitration Procedures:
Achieving Efficiency Without Sacrificing Due Process." Last
Update: 22 June. Paris. Downloaded from the web on April 5,
1999 www.ciob.org
[Coates, 1997] Coates, Tom, (1997). ADR is (not) for Wimps. International
Commercial Litigation, Vol. 17 pp. 46-48. March, London.
Euromoney Institutional Investor PLC. 1997.

124
STAGE 4: NON-BINDING DISPUTE RESOLUTION

[ENR, 1/15/1996] Schriener, Judy. Partnering, TQM, ADR Lower Insurance


Costs. Engineering News Record. McGraw-Hill, New York.
Vol. 236 (2) p.16. January 15, 1996.
[ENR, 2/14/1998] Engineering News Record. Contracts, New AGC Contract has
Owner Input. McGraw-Hill, New York. Vol. 240 (7) p. 14
February 16, 1998.
[ENR, 7/11/1994] McManamy, Rob. Industry Pounds Away at Disputes.
Engineering News Record. McGraw-Hill, New York. pp. 24-
27. July 11, 1994.
[Fenn et al., 1998] Fenn, Peter, O’Shea Michael, and Davies Edward (1998).
Dispute Resolution and Conflict Management in Construction
an International Review. E & FN Spon, London, ISBN 0-419-
23700-3
[Gould, et al.,1998] Gould, Nicholas and Cohen, Michael. ADR: Appropriate
Dispute Resolution in the U.K. Construction Industry. Sweet &
Maxwell, London. Vol. 17. April 1998.
[Groton, 1997] Groton, James. ADR in the Construction Industry. Dispute
Resolution Journal Vol. 52 (3) pp. 48-57, Summer, 1997.
[Hollands, 1989] Hollands, David S. FIDIC Provision for Amicable, Settlement
of Disputes. International Construction Law Review. Issue 1.
pp. 33-43. 1989
[Hunter et al., 1995] Hunter Keith, and Hoening, James. Construction Dispute
Prevention Comes of Age. Dispute Resolution Journal pp. 53-
54, January 1995.
[Langeland, 1995] Langeland, Erik, (1995). The Viability of Conciliation in
International Dispute Resolution. Dispute Resolution Journal
pp. 34-41. July
[Lipsky et al., 1997] Lipsky, David B., and Seeber, Ronald, (1997). The Use of ADR
in U.S. Corporations: Executive Summary. Cornell University
School of Industrial and Labor Relations. Downloaded from the
web on April 25, www.irl.conell.edu
[Macneil at al., 1994] MacNeil, Ian, Richard Speidel and Thomas Stipanowich.
"Federal Arbitration Law: Agreements, Awards and Remedies
Under the Federal Arbitration Act." Little, Brown and
Company. Vol. 3, Ch. 33. 1994.
[Meyer, 1995] Meyer, Judith, (1995). Mediation Works…With the Least
Damage done to the Parties’ Egos and Pocketbooks. Dispute
Resolution Journal pp. 44-47. April
[Treacy, 1995] Treacy, Thomas B., (1995). Use of ADR in the Construction
Industry. Journal of Management in Engineering Vol. 11 (1) pp.
58-63. January/February, 1995.
[Zack b, 1997] Zack, James G., (1997). Resolution of Disputes: The Next
Generation. AACE Transactions. pp. 50-54.

DRAFT 2/4/2017 2:32:00 PM 125


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

7.12 ENDNOTES

1
Although an attempt was made to contact DPIC directly to update the information from
the ENR and Dispute Resolution Journal articles, lack of response did not permit any
further investigation. However, the programs for promoting ADR were found throughout
DPIC’s website (www.dpic.com) signaling that the effort continues to be successful both
for the insurer, as well as for its clients.
2
ADR Group (www.adrgroup.co.uk), CEDR (www.cedr.co.uk), JAMS/Endispute, Inc.
(www.jamsadr.com).
3
The neutral advisor is either a retired judge (rent-a-judge) or a sitting judge in order to
guide the jurors in the legal considerations of the dispute (Zack b, 1997).

126
C H A P T E R

8
STAGE 5:
BINDING
“The future of arbitration is dependent on a
number of factors, probably the most important of
which is the quality of the arbitrators available to

DISPUTE
appoint”
(Crowter, 1999).

RESOLUTION
A publicly owned water agency that provides service to approximately 175,000 people in
the United States undertook a construction program to upgrade an existing reservoir near
an urban area. To assure that the water flowing into this reservoir was safe to drink, a
diversion facility to intercept and divert poor quality water and contaminants, generated
because of urbanization. This US$ 6 million Project consisted of four major components:
A Low Flow Barrier and Inlet Flume, a 48-inch Gravity Flow Reinforced Concrete
Pressurized Pipeline, a North Side pond and Two Wells and an 8-inch Pressurized
Pipeline.
An additional dimension of this Project is the recognition that the site lies in an
environmentally sensitive area, and is therefore subject to many environmental

CHAPTER LOOK AHEAD


WHAT IS IT? Arbitration as defined by the American Arbitration Association is “…referral of a dispute
to one or more impartial persons for final and binding determination. Private and confidential, it is
designed for quick, practical, and economical settlements.”
WHO IS INVOLVED? The most important part of Arbitration is the arbitrators. Knowledge, skill and
experience of the arbitrators heavily influence the outcome. A panel of three arbitrators, one selected
by each party and a third selected mutually, is common in the industry. A list of qualified arbitrators by
region is provided by the AAA.
WHY IS IT IMPORTNAT? Decisions are impartial, decisions are final and binding on the parties, and
decisions are issued by knowledgeable experts in the field in dispute. For these reasons Arbitration has
become the most popular dispute resolution technique.
HOW TO APPROACH IT? If a non-binding solution cannot be reached, follow the appropriate steps
outlined in the contract to reach a binding decision. Review your contract for the appropriate
procedures. If arbitration is the selected option, file the necessary forms and select a knowledgeable
arbitrator. Prepare your case relevant to the conflict.

KEY CONCEPTS
Mediation/Arbitration ....................................128 Adjudicator /Expert Determination ................. 130
Arbitration .....................................................131 Shadow Mediation .......................................... 136

127
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

constraints. The construction constraints were outlined in the Technical Provisions


Specification – Special Environmental Concerns.
“The urban runoff diversion system passes through sensitive environmental
areas which the construction will disrupt and/or impact. Permits for
construction by the Authority and its agents have been issued by the U.S. Dept.
of Interior Fish and Wildlife service, U.S. Army Corps of Engineers, and the
California State Fish and Game Dept. Permit copies have been included in
Appendix B. By submitting a bid for the project award, the Contractor agrees he
has read and understands the permits’ conditions and these provisions, and
agrees to comply with these provisions at all times. …The permitted time
constraints are as follows: No vegetation clearing from February 1 to
September 30; No work of any kind, form March 15 to July 21; Work activity
emitting greater than 60 dBA is not permitted from March 1 to March 15, and
July 22 to September 30.”
This contract was a fixed price, publicly issued contract and scheduled to be completed in
480 days after Notice to Proceed (September 11, 1997). The major participants involved
in this contract include the owner, a general contractor, and a designer. A pre-bid
conference was held to clarify any ambiguities in the design or questions/concerns that
the contractors might have. Liquidated damages were set at US$ 1,000 per day.
The contractor proceeded to start the work by widening a temporary access road for
equipment and was immediately stopped by the owner. The widening of the road would,
which was not in the permits, impacts 35 feet of the environmentally sensitive area. The
contractor submitted a delay claim, and they proceeded to arbitration.
This project raises some critical questions. If you were the contractor, would you ask for
clarification of the environmental permits at the pre-bid meeting? Should you have a
backup plan for construction if your methods are limited by unforeseeable
circumstances? How might these environmental constraints affect the construction
schedule? What role should the owner play in reviewing the contractor’s schedule?

8.1 MEDIATION/ARBITRATION (MED/ARB)


The least adversarial binding DART, Med/Arb, combines non-binding mediation with
binding arbitration. In this technique the parties select a mediator and agree that the very
same third party neutral will become arbitrator if they fail to reach a mediated settlement
within a specific time frame.
However, the picture gets more complicated. As parties engage in Med/Arb negotiations,
they need to understand that there are basic differences between traditional mediation and
this innovative technique, especially because some conventional benefits of mediation are
lost in Med/Arb cases. First, litigants lose the freedom to walk away from the process
once they decide to proceed. Each party agrees to a stipulation confirming that if
mediation does not succeed, the arbitrator retains jurisdiction to render a final and
binding award.
Second, participants will find some problems associated to the disclosure of information
during the mediation stage. Since the same third party could eventually become the
arbitrator, each side will be careful to divulge confidential information that could later be
used against them in the arbitration stage. Hence, parties may withhold information
during mediation and limit the effectiveness of this initial stage and the chances for
success. More importantly, parties may fail to take advantage of the benefits of mediation
because arbitration is just around the corner. If this were the case, the effects would be

128
STAGE 5: BINDING DISPUTE RESOLUTION

actually the opposite as how this technique was design to work. That is why Hoellering
(1997) states that it is best when mediation and arbitration are used separate, since
“...each has its own purpose and ultimate morality.”
The Med/Arb notion is very popular in the East, given the Oriental tendency to seek a
harmonious solution that preserves the relationship rather than seeking what is legally
correct. Whereas most Westerners seek an unbiased judge with no prior knowledge of the
dispute, Asians look for a moderator who will not only end their dispute but also assist
them in reaching a mutually agreeable solution. A clear example is found in China, where
arbitration is combined with conciliation in the ongoing process of arbitration. An
arbitrator hears the evidence and attempts to conciliate the parties, but if it fails
immediately turns to arbitration.
In Australia, the Commercial Arbitration Act 1984 contains a special clause which
suggests the possibility of a “mediated” settlement between the parties before the
arbitration proceeding begins (Hollands, 1989). The Act states: 1
“Power to seek settlement of disputes otherwise than arbitration.
(1) Unless otherwise agreed in writing by the parties to an arbitration
agreement, the arbitrator or umpire shall have the power to order the parties to
a dispute which has arisen and to which the agreement applies to take such
steps as the arbitrator or umpire thinks fit to achieve a settlement of the dispute
(including attendance at a conference to be conducted by the arbitrator or
umpire) without proceeding to arbitration or (as the case requires) continuing
to arbitration.
(2) Where –an arbitrator or umpire conducts a conference pursuant to
subsection (1); and a) the conference fails to produce a settlement of the dispute
acceptable to the parties to the dispute, b) no objection shall be taken to the
conduct by the arbitrator or umpire of the subsequent arbitration proceedings
solely on the ground that the arbitrator or umpire had previously conducted a
conference in relation to the dispute.”
In other words, arbitrators are authorized by this Act to attempt to resolve the disputes by
means other than arbitration. The arbitrator is free to decide on the steps to arrive at a
resolution, including pre-trial conferences with the disputants. The parties in the dispute
must accept his/her decisions with regards to this stage, but both disputants must accept
any settlement. The second part of the clause, allows the “umpire” to proceed with
arbitration if the settlement conferences fail to develop an agreeable solution, without
having his/her powers affected in any way, because of the initial attempts to reach a
agreement.
The arbitrator first attempts to mediate a settlement between the parties. Then, if
unsuccessful, proceeds with binding arbitration. The double responsibility assigned to the
arbitrator, has also been questioned in Australia (Hollands, 1989). Mr. G. H. Golvan,
Barrister, referred to this problem as follows: 2
“...to permit an arbitrator to conduct a mediation conference without
prejudicing his entitlement to subsequently embark upon arbitration is a serious
anomaly in the Act. Arbitrators should be most cautious, if not reluctant, to
attempt to act in both capacities”
Hollands (1989) concludes though, that in Australia, this provision should be regarded in
a positive way, and that it is unlikely that arbitrators would “...breach the rules of natural
justice,” by hearing evidence and settlement proposals, or issuing final opinions on the
issues before the arbitration proceedings take place. On the contrary, this provision
encourages arbitrators to incorporate in the pre-trial motions, steps that are likely to
promote an early settlement of disputes. This includes exchanges of written expert

DRAFT 2/4/2017 2:32:00 PM 129


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

testimonies and written summaries of each claim to improve each party’s assessment of
the case in dispute, or deferment of arbitration date to give parties a time to review and
maybe attempt negotiation again.

8.2 ADJUDICATOR/EXPERT DETERMINATION


This binding resolution consists on parties agreeing to refer their differences to an expert,
and to be bound by the decision of that authority. This expert will make his/her own
inquiries and inspections into the matter, and will not rely upon the parties to select and
present evidences to their arguments. The award by the expert, although binding, will
normally be enforced as a contract, without the benefits of the direct enforcement that
many countries have available for arbitration awards. The following example exhibits the
application of this technique in the context of the UK’s construction industry.
In 1994, a report by Sir Michael Latham (Latham, 1994) on the state of construction
procurement and contractual arrangements in the construction industry of the UK
suggested the need for “expert adjudicators” with wide ranging powers to review and
resolve construction disputes. This recommendation addressed the most important
characteristics of a dispute 'resolver' in the construction industry – the need to be fast,
decisive, and binding.
As a response to the conclusions issued by the Latham report, legislation in the UK has
introduced the concept of the construction adjudicator. Part II of the Housing Grants,
Construction, and Regeneration Act 1996 introduced the right for parties to construction
contracts to call upon Adjudicators to solve disputes. This Adjudicator combines some of
the features of the procedure we have identified as Expert Determination (Section 8.2)
with some of Arbitration (Section 8.3). Figure 23, shows the dispute resolution procedure
introduced by this Act, and the time-frame in which a resolution of the construction
dispute should be expected.

BINDING
DECISION FOR
NOTICE OF APPOINTMENT THE REST OF
DISPUTE OF THE PROJECT.
ADJUDICATOR It can be submitted
to arbitration after
final completion.

7 days 28 days, which can be extended


once for another 14 days if the
parties agree to do so

Figure 23 - Adjudicator Procedure for Dispute Resolution

130
STAGE 5: BINDING DISPUTE RESOLUTION

There are two interesting features worth noting in the application of this ADR technique
in the UK. First, this procedure is unilateral, so it can be initiated by one of the parties
without the consent of the other at any time during settlement negotiations, simply by
serving the seven-day notice shown in Figure 23. Once it is requested, the procedure is
designed to provide a solution in less than two months. Second, the decision of the
adjudicator is binding on the parties, but only for the remaining duration of the project,
and can be reversed through arbitration or litigation once the job is completed. In other
words, adjudication provides an interim decision, which if unacceptable to one of the
parties, can be reviewed and appealed in arbitration or court litigation. It would appear
that the objective of this ADR approach in the UK is to provide for a fast, but not final,
solution to the dispute in order to allow the job to continue without any further delays.
Adjudication “...is likely to provide a relatively cheap catalyst for settlement” as parties
will be encouraged to address the disputes and reach a settlement, before this procedure is
initiated (Staniforth et al. 1998).
Despite these advantages, the arbitration community has expressed their concerns
towards this dispute resolution method which is neither “...a fish nor fowl nor good red
herring” (Beresford Hartwell, 1998). Two problems are inherent in this procedure. First,
a reliable and knowledgeable adjudicator has to be found, agreed to, and appointed within
seven days. This timeframe might be too optimistic, especially since both parties have to
agree initially on the person to be appointed. However, this can be accomplished if a
roster of qualified adjudicators is pre-selected. Second, some professionals question the
ability of the adjudicator to provide just and reliable answers in less than two months,
considering that construction disputes can be very complex, with many issues and
technical evidence that would require from the Adjudicator certain familiarity with the
project in question. Since the Adjudicator is not incorporated in the project from the
beginning, he/she will depend on information gathered from both parties to assess the
issues and make a determination. This shortcoming could be handled by limiting the type
of disputes that the adjudicator could handle.
Because the Act has been in effect for just a few years, researchers suggest waiting to see
how the industry will respond to this system before issuing a final opinion as to the
strengths and weaknesses of Adjudication, but the introduction of this technique into a
legal framework is expected to promote the use of this ADR technique. In fact, a 1994
study by Fenn et al. (1994) revealed that this type of dispute resolution mechanism was
hardly ever used in the UK, however a similar report conducted in 1998 predicts a
significant increase in the use of the adjudicator in the resolution of construction disputes
(Gould et al., 1998).
Two additional examples of applications of this concept together with other DART are
presented in this book. First, the use of an Adjudicator was incorporated in the Dispute
Resolution Ladder of the World Bank for small projects in substitution for the design
professional. Second the Dispute Resolution Ladder for the Chek Lap Kok airport project
in Hong Kong incorporated this type of third party with binding authority if mediations
failed to provide a settlement. In this last application in Hong Kong, the decisions of the
adjudicator where binding on the parties only through the duration of the project, and
could be overturned by arbitration or litigation once the project was delivered, just like in
the UK application described above. No applications of this technique have been found in
the US yet.

8.3 ARBITRATION
According to the American Arbitration Association (AAA, 2000), arbitration is defined
as “...is referral of a dispute to one or more impartial persons for final and binding

DRAFT 2/4/2017 2:32:00 PM 131


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

determination. Private and confidential, it is designed for quick, practical, and


economical settlements.” This definition highlights three important characteristics of
arbitration, which have made it the most common ADR technique throughout the world
and across a wide array of industries:
• Decisions are impartial;
• Decisions are final and binding on the parties; and
• Decisions are issued by knowledgeable experts in the field in dispute.
Observing these characteristics of the proceeding, the AAA also asserts that arbitrators
should be selected based on the following basic attributes (AAA, 2000):
• Impartiality and objectivity;
• Dispute management skills;
• Experience with arbitration proceedings; and
• A strong academic background and professional or business credentials.
Because of the essential role played by the arbitrator, the issue of qualifications has been
raised by a number of arbitration institutions throughout the world. Harold Crowter,
Chairman of the Chartered Institute of Arbitrators in the UK, commented on the matter
by saying: “The future of arbitration is dependent on a number of factors, probably the
most important of which is the quality of the arbitrators available to appoint” (Crowter,
1999). Myers (1994) complements this argument adding that as disputes become more
complex, arbitrators will have to assume more active and fundamental role in the
proceedings in order to guarantee efficiency and speed in the process to save time and
expenses.
In construction, arbitration is typically conducted by a panel of three arbitrators; one
selected by each side and the third by mutual agreement or by the organization
administering the proceedings, usually the AAA. Parties may establish within their own
contracts the size and organization of the arbitration panel, as well as any special rules
they wish to include as part of their dispute resolution procedure. Parties may also choose
before hand the organization that will administer the proceedings, the location, and the
codes and regulations that will be followed. As discussed in Section 2.1.2, arbitration has
been the preferred alternative dispute resolution technique after the design professional’s
determination in the traditional two-step DRL.
In order to adapt arbitration to the needs of the construction industry for a “speedier and
more efficient process than litigation” (AAA, 1999), the AAA modified its construction
arbitration rules in 1996, updated in 1997 for consistency with the AIA documents, and
amended again in January 1999 and July 2001. These changes originated partly because
of the findings of the ABA survey presented in Chapter 1, but also in response to a
continuous decline in filings of construction cases in the AAA since 1991. Between 1983
and 1990, the annual number of AAA construction cases grew from 2,675 to 5,440. Since
1991 however, the number of cases continually declined through 1994, when it reached
3,564 cases. Part of the decline was attributed to less construction due to the recession of
those years, but AAA also recognized that companies were finding other solutions for
their construction disputes (i.e., minitrials, mediation, neutral advisors, or dispute review
boards) (ENR, 7/11/1994). The new organization divided arbitration cases into three
possible procedures:
• Fast Track Rules for cases up to $75,000;
• Regular Track Rules for all other cases, and
• Large Complex Track Rules for cases involving in excess of $1,000,000.

132
STAGE 5: BINDING DISPUTE RESOLUTION

These procedures, each with a specific set of rules, are key in illustrating some of the
problems experienced with arbitration in the resolution of construction disputes. A
summary of the key aspects of each of these new rules follows (based on AAA, 1999). It
is instrumental to provide relevant information as to the changes introduced in response
to the apparent decline in the use of Arbitration 3 and the concerns expressed by the ABA
in the above referenced survey.
Fast Track Rules:
With specially designed procedures for small construction cases, these rules
apply to two-party disputes where no total claim or counterclaim exceeds
$75,000. The different features included are supposed to expedite the process
and not always require a physical encounter of the parties with the arbitrator.
Some fast track rules are:
o Parties select the arbitrator from a list of available professionals
supplied by the AAA. Selection must occur within seven days from
transmission of the roster.
o The award must be rendered within 60-day time limit from the day the
arbitrator is appointed, and seven calendar days from the close of the
hearings.
o Preliminary conferences are by telephone or other electronic channel.
o There are strict limits for information exchange and discovery. Also
there are limits on changes and extensions to avoid add-on claims and
schedule modifications.
o The AAA can also serve notices to the parties by telephone or fax to
expedite proceedings.
o For cases where no claim exceeds $10,000, the dispute is resolved with
a one-day ‘desk arbitration’ by submission of documents without
hearings, unless the parties or the arbitrator chooses to have them. In
this case the arbitrator serves without fee.
Regular Track Rules:
These rules govern all cases not covered by the Fast Track or Large
Track Rules. Regular track procedures are very similar to standard arbitration
rules for construction projects, but they have been upgraded to improve the
procedure in the areas of qualifications of the arbitrators, arbitrators’ authority,
and speed of the proceedings.
Regular track rules offer the arbitrator great amount of power to affect the final
results of the dispute. Other characteristics of this procedure are:
o Enhanced party input regarding arbitrator qualifications and other
needs.
o Parties can change claims and counterclaims before the hearings are
completed. After that, any different claim must receive arbitrator
approval.
o To decrease administrative costs and expedite the process parties may
only strike three names in single arbitrator cases and five names in
multi-arbitrator cases from roster of arbitrators.
o The arbitrator has the clear ability to direct the production of
information and the identification of any witnesses to be called.
o Arbitrators can control the order of proof, bifurcate proceedings,
exclude cumulative or irrelevant testimony, direct parties to focus on
relevant information, entertain motions to dispose of all or part of the
claim, make preliminary rulings or interlocutory orders, and/or request
offers of proof.

DRAFT 2/4/2017 2:32:00 PM 133


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

o Arbitrators have the explicit authority to make interim protective


measures.
o The arbitrator is admonished to provide a ‘concise’, written breakdown
of the award. If requested, arbitrators can also provide a written
explanation of the award.
o The arbitrator can correct any clerical, typographical, technical, or
computational errors in the award upon the request. However, the
merits of the award are final.
Large, complex case rules:
A supplement to the Regular Track Rules, the AAA rules for complex cases
allow the parties to tailor the norms to the specific needs of the case in hand.
However, the AAA increases its involvement in these cases, and any
modification must be made before the selection of the arbitration panel. The
$1,000,000 limit for the utilization of Large Case Rules excludes fees, interest,
and attorney costs. Some important features of these rules are :
o Hearings will be scheduled in blocks of days.
o The AAA is required to conduct an administrative conference with the
parties to: a) obtain additional information about the dispute; b) review
and discuss parties’ views regarding the qualifications of the
arbitrators; c) collect each party’s conflict statement in writing; d)
introduce the use of mediation or other non-adjudicative methods.
o Arbitrators are required to have a minimum of ten years experience,
with a strong reputation for impartiality, patience, good judgment,
integrity and attentiveness.
o Three arbitrators are the norm, unless parties agree otherwise.
o Once arbitrators are selected, parties and panel must meet to review
various issues such as the scheduling of hearings, extend of discovery,
prospective witnesses, undisputed facts, and the possible use of non-
adjudicative methods.
o Arbitrators will direct the production of documents and limit discovery.
A common feature of these three sets of rules is that they try to make arbitration
more flexible and less costly. In any case, the industry continuously emphasizes
the development of alternative methods to simplify the dispute resolution
process. The following two sections, Single Arbitrator and Baseball Arbitration,
are a good example of these developments.

8.3.1 SINGLE ARBITRATOR

For small and simple cases, a single arbitrator instead of the panel of three experts
proposed in Section 8.3 can be used. Parties follow the same arbitration rules, but save
costs by having only one expert presiding over the hearings and deciding on the award.
The obvious disadvantage of having a single arbitrator is that the analysis and decision
making rests on one person. The three-member panel provides a “check and balances”
system that is not available in a single arbitration; therefore the savings should be
weighed against the risks of not having multiple viewpoints when reviewing questions
and issuing the award.
As described in Section 8.3, the AAA has introduced a fast-track, single-arbitrator system
to shorten the processing time of small and simple disputes. This system is for disputes
worth less than $75,000.00, which encompass 50% of the construction cases filed in
AAA for arbitration. A survey conducted by the AAA on over 2,100 projects between
1995 and 1997, to determine if this approach was resulting in actual benefits to the
disputants, concluded that the new fast track single-arbitrator procedures had reduced the

134
STAGE 5: BINDING DISPUTE RESOLUTION

average number of days to resolve a dispute by 33 days, from a previous average of 159
days (DRT, 1997/1998). This survey also found that the average time to appoint an
arbitrator from the day the case is filed had increased from 46 to 51 after the
implementation of the new system. This delay was associated with the fact that parties
have the option of selecting the single arbitrator by mutual consent from a list of
candidates, rather than having the AAA impose one as in the old procedures.

8.3.2 BASEBALL ARBITRATION

In this form of ADR, a single neutral arbitrator is chosen to preside over the dispute. Both
parties make a presentation of their cases, and propose their respective “best offer” for a
settlement. The arbitrator then selects one of the two proposals, and settles the dispute.
This type of ADR is called Baseball arbitration because it originated in the US Major
Leagues to resolve contract negotiations between owners and players regarding salary
conditions (Fizel, 1994).
The hearings under this approach are usually presentations, in which parties are limited as
to the amount of exhibits they can submit and the number of expert witnesses. These
characteristics result in a faster process and a binding decision. Furthermore, because the
arbitrator can only select one of the two options, parties are encouraged to present and
honest settlement to increase the likelihood that the arbitrator will select their option.
The main disadvantages of this approach are that it offers no flexibility and prohibits
alternative solutions. The arbitrator is limited to one of the two options presented by the
disputing parties. Baseball arbitration is an imperfect yet viable method for resolving
disputes. In the Major Leagues of Baseball this procedure has solved 9 out of 10 cases
(Fizel, 1994), without the need of conducting a full arbitration proceeding as outlined in
Section 8.3.

CN Oil Refinery Project (Venezuela)


During the construction of a Refinery Complex for Heavy Crude Oil in Venezuela, the
Mechanical, Structural Steel and Equipment Erection Contractor (Contractor)
experienced significant disruptions due to unforeseen labor conditions in the Industrial
Complex where the Refinery was located. The total number of Man-hours grew from a
bid estimate of 1,500,000 to 3,000,000 man-hours spent and the project was completed in
26 months instead of the 18 originally planned.
Among the labor conditions experienced by the Contractor during the execution of the
works were:
• Labor strikes during labor contract negotiations with Refinery Owner
• Shortage of skilled labor
• Overcrowding and trade stacking
• Extensive overtime and shift work
The contract between the Contractor and the Engineering Procurement and Construction
Consortium (EPC) specifically excluded labor strikes in the Force Majeure Clause, which
stated:
“Force Majeure means events or circumstances after the Effective Date which are
unforeseen at the time of execution of the Contract and beyond the control of the party
claiming Force Majeure… and which renders the execution of the obligations
impossible… including acts of governmental authority, acts of God, fires, floods,
earthquakes, explosions, riots, war, rebellion and sabotage, but excluding lack or shortage

DRAFT 2/4/2017 2:32:00 PM 135


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

of labor, strike or boycotts caused by Contractor’s or its Subcontractors’ own


workforces…”
The impact of the labor disruptions caused a significant deviation in the financial results
of the Contractor, who repeatedly requested an adjustment in the contract amount from
the EPC with no positive results.
Because the contract required that any disputes be settled via arbitration after project
completion, the Contractor hired an independent auditor halfway in the job to perform an
Independent Third Party Review of the project. The objective of this review was to have
an objective snapshot of the conditions under which the contractor was required to work,
for future use during negotiations and/or arbitration. The benefits of carrying out this
review at that time it was performed were:
• Objective analysis and review of project status, performed by an expert in the
field of claim management.
• All documentation was gathered and organized with one file structure for future
use at the end of the job.
• Key variables for measuring the impact on job productivity were established for
the remainder of the job.
• A separate cost structure was set-up to monitor and record cost deviations
incurred because of the conditions affecting the job.
In terms of the cost of the Third Party Report, the Contractor spent approximately
US$20,000 on a project worth US $30 million. In other words, less 0.07% of the original
contract amount for a document that is now helping settle a claim of approximately US
$20,000,000 in value to the Contractor (2 million Man-hours at US$20 each).
Currently, the Contractor and the EPC are in negotiations attempting to settle their
differences and close the contract before having to go to arbitration in Switzerland. The
Independent Third Party Report is proving to be an invaluable tool and reference guide
for both parties. Although the amounts are significant and the parties are far from
agreeing on the final number, the information gathered halfway on the job by this third
party and the organization that was established then is helping to clear the path towards
an agreement.

8.4 SHADOW MEDIATION


In this last form of binding ADR, parties proceed with arbitration but retain a mediator
(Section 7.2) who sits through the proceedings and reviews the information submitted to
the arbitrators. As the cases are presented before the arbitration panel and issues are
defined through the discovery phase, parties can request that parts of the dispute be
removed from arbitration, in order to attempt to settle them through mediation. If parties
agree, they can actually stop the arbitration and submit the whole case to mediation. In
addition, the “shadow mediator” can also recommend possible settlement options or areas
of common ground where parties could negotiate a solution faster than through
arbitration and possibly in better terms for both disputants.
Although this procedure increases the cost of the proceedings by incorporating the
mediator, it provides some flexibility to the arbitration process, in that it allows the
parties to stop the binding approach and settle the dispute faster through mediation. By
having two different parties running the procedures in this system (i.e., arbitration and
mediation), this technique overcomes the problems discussed in Section 8.1 with regards
to the dual role assigned to the arbitrator in the Med/Arb technique.

136
STAGE 5: BINDING DISPUTE RESOLUTION

Reservoir By reviewing the scenario in the Reservoir case, we can predict sources of conflict that
Project one might encounter in this project. Environmental concern (Uncertainty, External) is the
major source of conflict. The misunderstandings and possibly unrealistic expectations of
the owner (Organizational issues, People) also played a role in the dispute.
This case went to binding arbitration. The contractor presented his case with the
following argument.
1) The contractor based their bid price on modifying the access road.
2) The lack of this access resulted in their inability to complete the project in one
season, significantly impacting the cost.
The contractor calculated damages in excess of US$ 1.0 million. The owner presented his
case with the following argument.
1) The contractor did not request for widening this access road until after the
permits were issued.
2) The contractor was aware and involved during the request for use of this road, as
well as cognizant of the degree of environmental sensitivity.
3) The contractor has shown no proof that its bid was based on this access.
4) The allegation of the contractor’s bid price was based on this access was
unreasonable considering the representations made in the bid documents and
during the pre-bid meetings by the owner.
A single arbitrator decided this case. Using their impartial knowledge, the arbitrator
explored the facts and rendered a judgment in favor of the owner.

8.5 SUMMARY
Arbitration, the first binding step in the ladder, was initially introduced as an alternative
to Litigation, to ameliorate the disadvantages of this procedure associated with high costs,
time consumption, and strains in the relationship among the parties. However, as
Arbitration became a popular dispute resolution technique, it lost many of the qualities
that had supported its success: resembling more and more the litigation procedure, and
suffering from many of its limitations; increased formality, cost, and tension between
parties; and decreased control by the parties of the project and flexibility of outcome.
Arbitration represents a definite move away from the “win-win” approach, and thus
involves increased tension among parties, reduced communication, and an adversarial
stance. Information exchange becomes significantly compromised, and legal
representatives become the filters of such communication.
Nevertheless, despite the great resemblance between this stage and the final stage of
litigation, Arbitration continues to preserve some valuable and unique traits. Its main
advantage over litigation is the reliance on knowledgeable third party neutrals, with
recognized expertise in the construction field. This expertise facilitates his/her
understanding of technical and complex construction situations; thus, proving to be more
effective than litigation in those disputes that require significant understanding of
technical data, rather than in those where legal issues have become the center of the
dispute, for which litigation might serve as a more adequate procedure.
Through the years, Arbitration has become one of many Binding procedures, which are
often a modification of the initial form of Arbitration in an attempt to solve some of its
limitations, yet by doing so they have introduced a new set of challenges. Four of the

DRAFT 2/4/2017 2:32:00 PM 137


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

techniques presented in this chapter, in addition to Arbitration. Med-Arb introduces


mediation as a prior step to arbitration, yet sustains that the same expert will serve as the
mediator and the arbitrator throughout the process. This role change has been the focus of
concern to those involved in Arbitration. Shadow Mediation follows the same principles
of Arbitration with the added figure of a mediator, who witnesses the arbitration process,
and identifies possible areas for mediation that can be withdrawn from the arbitration
process. The Adjudicator consists of an expert neutral-third-party, who performs a similar
role than the Neutral Advisory, with the added attributes of being able to perform fact
finding and issue a binding solution. Lastly, in Baseball Arbitration each party presents
their “best case” and the arbitrator chooses the final settlement among those two options.
The first two techniques represent an attempt to increase mediation during binding
procedures, when compared to the traditional arbitration; the last two aim for a rapid
closure of the dispute, paying less attention to enhancing the communication among the
parties, moving dramatically away from a win-win solution. Chapter 9 will review the
final stage in the DRL: Litigation, in which the win-lose approach is the basis of this
procedure. This chapter will address a number of techniques that can help reduce the
limitation of litigation.

8.6 POINTS FOR DISCUSSION


8.1 What are the basic major differences between traditional mediation (Section 7.2)
and binding Mediation/Arbitration (Section 8.1)? Are there other differences that
are pros or cons for this method?
8.2 Discuss the intentions of Mediation and Arbitration. Can they effectively be
incorporated in to a single solution such as Mediation/Arbitration (Section 8.1)?
What is lost, what is gained? In what cultures does Mediation/Arbitration work
best?
8.3 In the United Kingdom, an Adjudicator (Section 8.2) is appointed by the request of
either party. What problems does this pose if the other party doesn’t approve?
8.4 Does an interim decision made by an Adjudicator (Section 8.2) carry any weight or
does it just buy time for the parties to finish the job before diving into litigation?
What effect does the semi-binding decision have on the process?
8.5 Is the Binding Arbitration (Section 8.3) really the last step? Can a contractor/owner
still file suit after they have received a binding decision? Why or why not?
8.6 The AAA revised the rules for construction arbitration in 1996 (Section 8.3). How
are they tailored to the current trends in DART? Was this a sensible move for the
AAA considering the declining number of cases they were involved in?
8.7 Over time Binding Arbitration (Section 8.3) has come to closer and closer to
resembling litigation. Will they eventually become one in the same? If not, what
defining attributes will keep them separate?
8.8 Who should cover the costs associated with Binding Arbitration (Section 8.3)?
8.9 Can a democratic government, such as the US, impose contractors to submit to
binding arbitration before filing for litigation?
8.10 What are some advantages and disadvantages of having a Single Arbitrator (Section
8.3.1)? Multiple Arbitrators (Section 8.3.2)? A Shadow Mediator (Section 8.4)?

138
STAGE 5: BINDING DISPUTE RESOLUTION

8.7 REFERENCES

[AAA, 2000] American Arbitration Assiociation. A Guide to Mediation and


Arbitration for Business People 2000.
[Beresford Hartwell, Beresford Hartwell, Geoffrey M., (1998). The Relevance of
1998] Expertise in Commercial Arbitration. " Arbitration Procedures:
Achieving Efficiency Without Sacrificing Due Process." Last
Update: 22 June. Paris. Downloaded from the web on April 5,
1999 www.ciob.org
[Crowter, 1998] Crowter, Harold, (1998). Chartered Institute of Arbitrators.
Chairman's Address Member Lunch, Butchers Hall. June 23,
London. Downloaded from the web on April 5, 1999
www.cioa.org
[DRT, 1997/1998] Dispute Resolution Times, (1997/1998). AAA Partnering
Boosts Jail Project in San Diego. p. 7 Winter
[ENR, 7/11/1994] McManamy, Rob. Industry Pounds Away at Disputes.
Engineering News Record. McGraw-Hill, New York. pp. 24-
27. July 11, 1994.
[Fenn et al., 1994] Fenn, P., and Gould, N., (1994). Dispute Resolution in the
United Kingdom Construction Industry. October 1994.
University of Kentucky. p 1-17.
[Fizel, 1994] Fizel, John L., (1994). Play Ball Baseball Arbitration After 20
Years, Construction Dispute Prevention Comes of Age. Dispute
Resolution Journal pp. 42-47, June
[Gould, et al.,1998] Gould, Nicholas and Cohen, Michael. ADR: Appropriate
Dispute Resolution in the U.K. Construction Industry. Sweet &
Maxwell, London. Vol. 17. April 1998.
[Hollands, 1989] Hollands, David S. FIDIC Provision for Amicable, Settlement
of Disputes. International Construction Law Review. Issue 1.
pp. 33-43. 1989
[Latham, 1994] Latham, M. Constructing the Team: Final report of the
Government/Industry Review of Procurement and Contractual
Arrangements in the UK Construction Industry. HMSO
London. 1994.
[Myers, 1994] Myers, James. Task Force, Survival Kit for Complex
Construction Arbitration in the 1990's. Dispute Resolution
Journal. pp 53-57. September 1994.
[Staniforth et al., Staniforth, Alison and Taylor Kathryn, (1998). Building and
1998] Engineering Disputes: Reasons to be Worry Part II. Credit
Control Hutton. Vol. 19 (2) pp. 12-13. 1998.

DRAFT 2/4/2017 2:32:00 PM 139


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

8.8 ENDNOTES

1
This Act is part of the Uniform Commercial Arbitration legislation in force in most
States and Territories of Australia (Hollands, 1989).
2
Speech given by Mr. G. H. Golvan, Barrister, to a Melbourne Forum of the Institute of
Arbitrators of Australia in 1985; cited by Hollands, 1989.
3
The problems with Arbitration in construction disputes are discussed in Section 2.2.2.

140
C H A P T E R

9
STAGE 6: COURT
ALTERNATIVES
“it is the judge-driven change to litigation culture
that is likely to lead the breakthrough”
Coates (1997)

AND LITIGATION

In the western United States, a hospital heating plant was in need of an upgrade before
the following winter season. This particular hospital was owned by a federal government
agency. After design was completed, it was competitively bid out in accordance with
federal regulations. The contract included the renovation of the heating plant as well as
some new additions to the plant. The work was estimated to cost US$ 45 million.
The contractor that was awarded the project was located in the northeastern United
States. It was the first time that they had ventured out side of their geographic region, to
bid work. Since they had no local office, their staff was sent to the site for the duration of
the project. During the construction phase of the project, problems relating to the design
and schedule began to arise. Typical of renovations projects, the scope of work came into
question. What exactly is required by the contract documents and what is not became a
gray area, which the owner and the contractor began to negotiate. The contractor

CHAPTER LOOK AHEAD


WHAT IS IT? Litigation is the final step in the Dispute Resolution Ladder. At this stage, both parties
have lost all control over the outcome. Awards are based on monetary compensation, where one side
wins and the other loses. However, even if a dispute proceeds to litigation, there still are some possible
options to improve the situation, including a solid discovery and an effective presentation.
WHO IS INVOLVED? At times, the court may appoint an outside third party to listen and decide the case.
These individuals may include experts in the field of construction, retired judges, or lawyers.
Otherwise, this process involves lawyers, a judge and/or a jury. Expert witnesses are needed to explain
the situation to a judge or jury unfamiliar to the construction process.
WHY IS IT IMPORTANT? Although not the focus of this book, litigation influences the whole dispute
resolution spectrum. The cost of litigation and time required for a decision has been the driving force
behind the development of DART. In addition to this, there are certain steps that can be taken to prepare
for litigation that are also needed in other dispute resolution methods.
HOW TO APPROACH IT? Review the facts from both sides. Take time and evaluate the other side’s
position as well as your own, noting the strengths and weaknesses. Prepare an effective presentation.

KEY CONCEPTS
Discovery of Situation .................................. 141 Effective Presentation ..................................... 143
Court Appointed Experts .............................. 146 Judge Pro-Tem ................................................ 147
Trial by referee .............................................. 147

141
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

questioned the how the liquidated damages were assessed based on the schedule with
such problems. The owner refused to reveal how the liquidated damages were calculated.
The contract called for Step Negotiations, so that the conflict could be resolved at the
lowest level possible. With the upper level management of the contractor and the owner
so far away, the only effective negotiations were on-site. There was little oversight of the
project from the home office. As the differences increased, the negotiations began to
break down. Personality conflicts between the on-site representatives escalated the
conflict into the next stage of the dispute resolution ladder. This stage required both sides
to appoint an expert knowledgeable in the field of construction. Each selection had to be
approved by the other party. An unorthodox, binding mini-trial would then follow. Since
this was a federal contract, if this stage failed, the dispute would be resolved in a federal
court. An overburdened federal court system would be very likely not to uphold the
decision of the arbitrators.
Both parties in this dispute have valid claims and neither wanted to proceed to litigation.
There is no definitive right and wrong. How might a solid understanding of the facts help
resolve this dispute? What effect does the personality conflict have on the dispute? What
other reasons might have caused the negotiations to fail?

9.1 THE FINAL STEP


Although not an alternative dispute resolution technique (DART), Litigation has been
included as the last stage in the Dispute Resolution Ladder (DRL) for two reasons. First,
it is one of the methods available to resolve disputes, although not the most effective and
efficient one. Second it is reviewed to be able to assess a number of techniques that have
been developed within this stage that can lead to faster and more effective trials.
“Litigation can be productive if it helps define legal and factual issues, building a
foundation for fair and expeditious settlements, but ...a decade or more may pass before
there is any resolution of a dispute by the courts, leaving no one a winner.” (ENR,
2/15/1999). In other words, the settlement of disputes in this stage will always involve
one party losing its case, and another one winning. A court award that results in neither
party winning at the expense of the other one (i.e., win/win) is not foreseeable in the near
future. In litigation, there is limited flexibility to develop compromises and solutions that
can maintain business relationships, and improve job-site productivity. Costs in this stage
are high, and the resolution of the disputes can take a significant amount of time and
resources. Therefore, litigation should be avoided by implementing one of the many
DART reviewed in the previous chapters, or a combination of them in a DRL system.
However if one must go to litigation, many things should be considered when pondering
litigation. Has a thorough discovery of the situation been performed? Is there enough
evidence to support the claim? Are the resources available to engage in a trial? In what
court system will this case be tried? Has an attorney been selected? If not, how should
one be selected? Will this be a bench trial or a jury trial? How long will the trial take and
what are the ramifications of a lengthy trial? Are there any previously decided cases
similar this one? Are their any other options?
This chapter addresses some of these questions and provides some alternative options
developed by courts in the United States.

142
LITIGATION

9.2 DISCOVERY OF SITUATION


One-step that is important in presenting a case is a solid discovery of the dispute. The
basis of the discovery is a thorough understanding of the facts. This is necessary for all
participants, so that everyone is on the same page. At times, this discovery does not occur
until conflict reaches litigation because parties in an adversarial relationship are always
hesitant to present documents or divulge information that may be detrimental to their
argument, unless ordered to do so. This discovery of information can sometimes even
resolve the dispute. As more information is uncovered, one side may realize that their
claim or position is incorrect or unsubstantiated. Therefore, discovery itself can be a
method that can avoid or resolve a dispute.
The first step of the discovery process is to thoroughly review and understand the
contract. The contract is the ‘handbook’ for the project. If drafted properly, the contract
will outline the responsibilities for all the parties involved. After this, investigation of the
dispute begins. This process takes time and persistence to get the necessary information.
Various methods of discovery are used. The main modes of investigation used in the
construction industry are requests for documents, questioning participants, written
accounts, and site investigations and testing. The request for documents can be the most
valuable, but are also probably the hardest to obtain. Contract documents are already in
the hands of both parties, but daily logs and personal project diaries are tougher to obtain.
The same is true for depositions and written accounts. The basic facts of the dispute will
probably not change much from person to person, but getting a participant to admit a
mistake or take responsibility for a mistake is a challenge. In addition to documents and
statements, site investigation is also important. For example, quantity disputes can be
resolved by surveying the site. Numerous other performance related disputes can be
resolved by site investigation and testing.
Going back to previous DART identified in this book, Escrow bid documents (Section
3.3) is a prevention technique can be used to make the discovery process easier. This set
of clean documents can provide valuable information as to how the job was bid, reducing
the tendency of misrepresentation on behalf of the contractor. In effect, a number of
valuable documents are readily available should a dispute arise. An added benefit of
having a third party review these documents is that the information irrelevant to the
situation remains confidential to both parties.
It should be mentioned that both sides are not entitled to every piece of information. A
conversation between each party and their lawyer is privileged material. That is, the
attorney and their client are the only ones entitled to this information.

9.3 EFFECTIVE PRESENTATION


Following a through discovery is an effective presentation. Whether it be in court, before
an arbitrator or with the other party, the ability to present your understanding of the facts
in a logical, timely, persuasive manner is vitally important. This skill leads back to the
fundamentals described in Chapter 5: Negotiation. By selecting an appropriate strategy
and understanding both sides of the argument, it will help you present your side
effectively. Even a valid claim can be denied if the claimant does an inadequate job of
presenting their case.
The effective presentation of a claim usually starts when the contractor files a claim with
the owner. This claim should be a written notice with all the necessary information
required by the contract and delivered to the owner in accordance with the contract. This

DRAFT 2/4/2017 2:32:00 PM 143


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

notification initiates the conflict. It should be professional looking and include relevant
information describing the incident, the date discovered, what action the owner is
expected to take, the timeframe it should be resolved in and whether or not more
information will follow. An example of this is presented in Figure 24. Along with the
letter, the Contractor has attached a detailed breakdown of the labor equipment and
materials that will be needed to complete the work The owner’s obligation is to accept
the claim in good faith, objectively review it and make a prompt decision as to what
action they will take. If the owner cannot make a prompt decision for various reasons, it
is appropriate to send a courtesy letter stating the reason for delay. As we have learned
from this book, the impact conflicts can have on a project tend to escalate with time. If
either party fails to address the conflict when it arises, there is a greater probability that it
will escalate into a lawsuit.

144
LITIGATION

Figure 24 – Example of a Proposed Change in the CA/T Project

Meetings should be set up upon receipt of a major claim by either side. In preparation for
these meetings, facts and information should be gathered by both sides, in other words a
thorough discovery of the situation (Section 9.2) should be preformed. Authorized
representatives from all sides of the conflict should attend. It does not aid in the dispute
resolution process to send anyone who is not authorized to act on behalf of the
participant. One should prepare relevant information specifically tailored to the listening
party when presenting their interests. Research whom the presentation is for and prepare
accordingly. Is it a lawyer, a jury, the owner, an arbitrator, or is it the contractor? Know
the strengths and weaknesses of both sides and tailor your presentation to these. If there is
a personality conflict, ask that another representative attend.

DRAFT 2/4/2017 2:32:00 PM 145


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

All materials and documentation presented should be professional and not altered in
anyway. Keep this in mind when preparing project documentation on a daily basis. Any
comments that you do not want read aloud in court, do not write down. As a rule of
thumb, record only the events and facts and keep editorials/opinions to a minimum. The
same is true for presenting. Present only the facts, avoid accusations, and finger pointing.
A confident, professional performance is usually the most persuasive. In addition, all
material should be presented as soon as it is discovered. Do not hold back any
information. An effective way to present this information is in a formal report with an
executive summary in the front, followed by an appropriate assessment of the situation,
with exhibits such as contract documents, photographs, schedules, and bid information
attached as backup.
If the dispute does make it to court, a presentation in the form of expert testimony can be
one of the deciding factors in determining the award. Although expensive, these experts
bring validity to the claim. Most of the time, judges and juries are unfamiliar with the
construction industry and are forced to rely on the opinions given by these expert
witnesses. For instance, a waterproofing subcontractor waterproofed the walls with a
substance that did not meet the specifications in the design. A lawsuit resulting from a
leaking basement was filed. Validity can be brought to this claim by bringing in another
waterproofer (considered an expert) who states that the standard in the industry is to use
better quality materials and the original subcontractor should have known better.
A solid discovery of the facts and an effective presentation can reduce time in court,
accurately portray the facts, and aid in winning the case. For instance, if the conflict does
escalate to the courtroom, not all hope is lost that the process will be inefficient and
lengthy. In the following sections, three techniques review some of the different
procedures developed in the judicial system for use during court proceedings, which can
improve the litigation process: Court Appointed Experts (Section 9.4), Judge Pro-Tem
(Section 9.5), and Trial by Reference (Section 9.6). These techniques have been
developed by specific courts in an effort to expedite the resolution of civil disputes. They
also reinforce the idea that the construction industry must find ways to reduce the cost
and time impacts of litigation, even if the court proceeding is already underway.

9.4 COURT APPOINTED EXPERTS


A variation derived from the concept of expert testimony is using a court appointed
expert instead of a judge to decide the case. Because in many construction disputes the
conflict revolves around a technical question, which requires an opinion from a qualified
witness, an expert witness appointed by the court to decide the case, can significantly
lower the costs for all parties. This DART is similar to court appointed arbitration with an
expert as an arbitrator. According to Zack (b, 1997), this approach starts with a definition
of the issues that will require expert testimony and a cost-sharing plan to cover these
expenses. Then, both parties present two or three possible experts to the court, and the
judge selects one per issue. The experts work for the court, but the disputants cover the
costs.
The benefits of implementing this technique are obvious in terms of costs, since both
parties are sharing the expenses of only one expert testimony per issue. In addition, Zack
(b, 1997) points out that the duration of the hearings is substantially reduced by making
the parties agree before hand on the issues that require expert testimony and by
eliminating testimonies from two or more experts from each party that might be
conflicting.

146
LITIGATION

The problems of this process are associated with the selection of this common expert. If
the judge fails to select the best expert from the proposed options, the overall proceedings
will lack the technical depth required to resolve some of the more complicated issues.
More importantly, by having only one testimony, the outcome may depend on it too
much. Therefore, parties most pay close attention to the pre-selection process of the
experts and the presentation of the possible options to the court.
A variation of this approach is reported by Treacy (1995) in the Eastern District of New
York. This court offers disputants the possibility of reviewing the matter in dispute with
an impartial attorney with expertise in the area in question. This neutral helps parties
organize the issues in dispute, explore possible settlement options, and can provide upon
request an assessment of the likely outcome if the dispute in brought to trial. Treacy
(1995) identifies three benefits of this procedure. First, it helps parties organize and learn
about their respective cause before the trial. Second, it can be less expensive than full
discovery proceedings and pre-hearing motions. And third, the information is kept
confidential, since the court does not participate directly in the proceedings. So, parties
are free to develop an alternative solution with the help of the expert if they so desire
once they have fully understood the case and issues in dispute.

9.5 JUDGE PRO-TEM


In an effort to expedite getting the dispute to trial, parties may agree to have the courts
appoint a temporary judge to preside over the trial. This judge has to be an attorney, and
he/she gets all the powers of a presiding judge for the specific case. Litigation then
follows all stipulated court proceedings. In the United States, most States authorize this
procedure, and the temporary judge maintains jurisdiction over the case until a final
determination is reached, including any post-trial procedures.
By having a judge who is independent from court schedules, parties can initiate the
proceedings faster and schedule all the other hearings and motions with more flexibility.
This represents an advantage considering that the average court resolution process in the
US takes between 2 to 5 years (Findley, 1997). A disadvantage according to Zack (b,
1997), at least in the United States, is the need to give up the right to a jury trial in case of
disagreements with the award by the temporary judge.

9.6 TRIAL BY REFERENCE (REFEREE)


In this procedure, the court appoints a neutral expert to preside over the complete trial or
specific sections of the proceedings. This expert does not have to be a lawyer, and the
court upon appointment sets the authority of the expert and the rules of the procedure.
The expert presents the legal and technical findings to the court, and the court issues
judgment. The expert’s report is binding, but it can be appealed.
This procedure provides for a faster procedure and privacy during discovery. In highly
complex cases, it allows the courts to select an expert with the technical knowledge
required to understand the issues and provide a faster ruling than that of a judge in a
standard court proceeding. The disadvantages are that trial costs are not reduced, since
both parties still have to prepare for trial, and the decisions are not final and can result in
appeals and re-trials.
In the UK, the Court of the Official Referee (Gould et al., 1998) is an example of this
procedure that has been incorporated and developed into a separate and specialized
section of the judicial system. Most construction disputes are presented at this court,

DRAFT 2/4/2017 2:32:00 PM 147


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

which is a branch of the Queen’s Bench Division of the High Court. Its purpose is to hear
cases that require “...prolonged examination of documents or accounts, or a technical
scientific or local investigation...” (Gould et al., 1998), around 80 % of the Official
Referees’ business is related to construction. Within the Court of the Official Referee, a
number of procedures have been developed to manage and expedite the settlement of its
cases: (Gould et al., 1998)
• “Holding regular pre-trial summon or meeting with the parties in order to
discuss and decide the manner in which the trial will take place.
• The use of timesaving written procedures.
• The use of a high level of computerization in the court to handle information and
documentation. In 1996, the “...first ‘paperless’ trial was conducted before one
of the Official Referees using a fully developed case management system..” 1
• Suggesting to parties to consider ADR before continuing with the court
proceeding, if they have not done so yet.”
Other examples of court initiatives to promote and use of dispute avoidance and
resolution techniques in the UK include: (Gould et al., 1998)
1) Since December 1993, disputants are required to inform the courts during pre-
trial meetings whether they have considered using alternative dispute resolution.
In addition, since 1995, attorneys are required to file a pre-trial summary stating
whether they reviewed with their clients alternative dispute resolution, and
whether they considered that all or part of dispute could be addressed through an
alternative technique.
2) A 1996 court direction gave judges an active role in the implementation of
DART by authorizing them to stop proceedings and encourage the
implementation of a DART (i.e., mediation), and to offer neutral evaluations of
the case.
These initiatives support the idea that the increase use of DART in the UK is fueled by
the court system. Two studies by public authorities, Lord Woolf and Latham (1994), have
provided the basis for the evaluation of litigation proceedings, and the introduction of
alternative practices, confirms that part of the DART “revolution” in the UK is coming
from within the judicial system. On this subject Coates (1997) concludes that “it is the
judge-driven change to litigation culture that is likely to lead the breakthrough” in the
implementation of DART.

Hospital Returning to the hospital heating plant, it can be seen that a solid discovery of the facts
Heating did not occur. When the contractor requested that the owner demonstrate how the
Plant liquidated damages were calculated, the owner refused. When the negotiations began on-
Project site, they failed in part due to the personality conflicts, but also to the fact that the
contractor’s presentation was ineffective.
When the next step of the DRL was reached, the contractor did not make the same
mistakes twice. The contractor and the owner both selected their experts. Unlike most
mini-trials, the contract allowed the experts to meet with their parties before the trial
where they would hear the cases presented by both sides. This unorthodox method
allowed for a thorough discovery of the facts by each of the experts for both sides. The
experts became intimately familiar with the claims of both sides. When the trial began,
the experts heard the claims by both sides and actively asked questions, probing the other
side. The experts then negotiated amongst themselves resolving each issue at hand.

148
LITIGATION

This method eliminated the personality conflicts that made negotiation impossible. In
addition is allowed for a solid discovery of the facts, a professional presentation of the
material, the opportunity for a win/win situation. In this case, there were no losers.

9.7 SUMMARY
Litigation is the final stage in the DRL. Although it is considered a costly, time
consuming, and less flexible procedure, it is not an unlikely outcome for many
construction projects. Litigation comes about when other DART have failed to work,
when arbitration clauses are not incorporated in the contract, and/or when the nature of
the conflict, characteristics of the dispute, or the relationship between parties, do not
allow for intermediate steps; for example, in those situations where legal issues, rather
than factual, are the main focus of the dispute. In this Stage of the Dispute Resolution
Ladder, a third party makes the final decision on the dispute.
A solid discovery of the situation and an effective presentation can soften the impacts of
litigation. A thorough understanding of the facts is necessary for all participants. This can
reduce the issues and can even resolve some of the areas of dispute. Start with reviewing
the contract, and then begin to investigate the dispute by requesting documents,
questioning participants, taking written accounts, and investigating the site. When
presenting this information, be confident and professional. Know the audience, select and
prepare accordingly.
Considering the many limitations of this stage, be preapared for a lengthy expensive
battle. This chapter proposes three procedures to attempt to overcome the many
challenges of litigation: Court Appointed Experts, Judge Pro-Tem, and Trial by
Reference. Although these three options within the litigation process offer the parties in
the dispute ways to save money and time, they fail to provide a flexible, cost-effective,
and fast option to resolve disputes, for they all happen in a court context. An important
advantage shared by the three options described above is the fact that the parties are
required to meet, communicate, and agree on certain issues in order to implement any of
them. This “forced” communication among the parties in preparation for, and during the
court hearings, could open the door to new settlement options, and can stop litigation, or
shorten the proceedings.

9.8 POINTS FOR DISCUSSION


9.1 What are the various methods involved in the discovery process (Section 9.2)?
What are the cost implications of each? What are the roles of the participants in the
discovery?
9.2 How might a through discovery (Section 9.2) promote a settlement before the trial
begins?
9.3 What constitutes an effective presentation (Section 9.3)? How might one improve
their presentation?
9.4 What are the major disadvantages of litigation?
9.5 What is the difference between a court appointed expert (Section 9.4) and an
arbitrator?
9.6 Construction accounts for a solid amount of litigation throughout the world. To
reduce tying up judges in these civil disputes, should court appointed experts

DRAFT 2/4/2017 2:32:00 PM 149


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

(Section 9.4) be the standard in the judicial systems throughout the world? Argue
the pros and cons.
9.7 Is Judge Pro-Tem (Section 9.5) any different from litigation? If so, how?
9.8 The majority of judges and juries do not have a construction or engineering
background, and lack technical expertise. Does this fact influence the decision in a
positive or a negative way? Why?
9.9 The issue of a knowledgeable deciding authority is addressed in the Trial by
Referee (Section 9.6) technique. By appointing this figure, what benefits do the
parties lose?
9.10 Are there any reasons that a dispute should go to trial and not be resolved by other
means?

9.9 REFERENCES

[Coates, 1997] Coates, Tom, (1997). ADR is (not) for Wimps. International
Commercial Litigation, Vol. 17 pp. 46-48. March, London.
Euromoney Institutional Investor PLC. 1997.
[ENR, 2/15/1999] Engineering News Record. Lightening up Litigiousness.
McGraw-Hill, New York. Vol.242 (7) p. 68 February 15, 1999.
[Findley, 1997] Findley, Douglas. Construction Claims Preparation Under
ADR. 1997 AACE International Transactions C&C.01.1-
C&C.01.4. 1997.
[Gould, et al.,1998] Gould, Nicholas and Cohen, Michael. ADR: Appropriate
Dispute Resolution in the U.K. Construction Industry. Sweet &
Maxwell, London. Vol. 17. April 1998.
[Latham, 1994] Latham, M. Constructing the Team: Final report of the
Government/Industry Review of Procurement and Contractual
Arrangements in the UK Construction Industry. HMSO
London. 1994.
[Murdoch et al.,
Murdoch, J and Hughes, W. Constuction Contracts: Law and
1992]
Management. E & FN Spon. p 372. 1992.

[Treacy, 1995] Treacy, Thomas B., (1995). Use of ADR in the Construction
Industry. Journal of Management in Engineering Vol. 11 (1) pp.
58-63. January/February, 1995.
[Zack b, 1997] Zack, James G., (1997). Resolution of Disputes: The Next
Generation. AACE Transactions. pp. 50-54.

9.10 ENDNOTES

1
Uff, 1996 cited by Gould, 1998.

150
C H A P T E R

10
CONFLICT
MANAGEMENT
“The general guiding principle of risk allocation
should be that the different parties involved should
seek a multi-beneficial distribution of risk. A

PLAN
dominant party that off-loads all project risks onto
others is unlikely to enhance the chances for a
successful outcome.”
Vega (1997)

A brother and a sister growing up in a construction business atmosphere both progressed


in life taking different directions. Brock, the eldest, followed the example of his father
and took over control of the family business in real estate development. His sister Kelly
opted to work for the procurement office of the state government.
Brock has decided to venture into the hotel development business, a new area for him and
the company. In the past, the family construction company has billed approximately US$
40 million in construction costs. The projects typically range from US$ 1 to $10 million
and include department and retail stores with an occasional restaurant. Funded partly by
the developer and the rest by banks, the upcoming hotel project is estimated to cost
US$20 million. Although new to the hotel business, the banks are willing to fund this
project because Brock’s reputation is excellent and he rarely loses money on a project.

CHAPTER LOOK AHEAD


WHAT IS IT? A Conflict Management Plan looks at each project individually to establish a set of criteria
for manageing conflicts. It assesses how much conflict one will encounter, how severe each conflict
might be, then presents cost effective ways to avoid conflict and curb these disputes. Similar to the
contract documents it should be complete, unbiased, understood, and accepted by all parties involved.
WHO IS INVOLVED? Throughout the life cycle of a project, the owners, the owner’s representatives,
designers, lawyers, and contractors are responsible for designing, reviewing and revising it accordingly.
No one person or entity should be responsible for developing this plan alone.
WHY IS IT IMPORTANT? Designing a conflict management plan compels the owner to contemplate the
conflicts that might arise. This will allow the owner to allocate responsibility and develop a plan to
handle discrepancies. By doing this upfront and with each subsequent review, everyone involved has
agreed to follow this plan, reducing the push for lengthy, costly court proceedings.
HOW TO APPROACH IT? Assess the project situation by identifying the sources of conflict that might
occur. Analyze the severity and impact each of these conflicts might have. Match the conflict with a
corresponding DART, to reduce or avoid the conflict. Draft the plan. Review and revise it as needed.

KEY CONCEPTS
Conflict Management Process .......................152 Identifying Potential Conflicts ........................ 154
Analyzing Potential Conflict .........................156 Designing the Plan .......................................... 163
Review Process ..............................................168

151
INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

This contract is awarded on a negotiated cost basis, plus a fee. About 90% of the design
is completed and the contractor has been selected with the negotiated fee to be 3.5% of
the total construction costs.
The other sibling, Kelly, has advanced to the rank of senior procurement officer for the
state aviation administration. Her current project is a US$ 1.5 billion capital improvement
program that encompasses 19 different contracts ranging from US$ 20 to 400 million.
The contracts will be let at different times and almost all of the schedules are
interdependent. The majority of these contracts are fixed price, design-bid-build projects,
although some of these contracts have provision for operation and maintenance. This
capital program is fast-tracked to expedite the process. The projects are broken up into
different contracts so that design and construction of the overall program can overlap (i.e.
construction of certain parts of a project will be underway, while other parts of the same
project are still under design).
Each of these siblings are in charge of developing contract documents, in particular a
conflict management plan, for their upcoming projects. These two very different ‘owners’
have dissimilar projects, however both have a great likelihood of encountering some type
of conflict during the development of their projects and they are both concerned. How
should each of them go about planning to identify, avoid, monitor and control these
potential conflicts? How should Brock’s approach differ from Kelly’s approach? Could
they both use the same methodology? Are there restrictions on what DART each of them
could use?

10.1 CONFLICT MANAGEMENT PROCESS


Talk with anyone in the construction industry and ask them is there a project you have
completed without any conflict? The answer 100% of the time will be no. Somehow,
conflict creeps into every project, even ones that are self performed. Conflict has been
defined in many ways, but generally, it is any action or circumstance resulting from
incompatible or opposing needs. Managers in all area of business recognize that conflict
exists, but the successful managers are the ones that implement strategies to avoid,
control and monitor conflict in their projects. This is no different in the construction
industry. These managers follow a number of common steps when developing a
successful strategy to achieve these objectives. These steps are:
• Conflict Identification
• Conflict Analysis
• Design and Implementation of a Conflict Management Plan
• Monitoring and Review of the Conflict Management Plan

Design and
Conflict Conflict Implement Monitor and
Identification Analysis Conflict Review Plan
Management

Figure 25 – Conflict Management Process

152
CONFLICT MITIGATION PLAN

A Conflict Management Plan looks at each project individually to establish a set of


criteria for managing conflicts. It assesses how much conflict you will encounter, how
severe each conflict might be, then presents cost effective ways to avoid conflict, mitigate
the impacts of the conflict that occur and resolve any disputes.
To understand the importance of a Conflict Management Plan one must understand how
conflicts escalate during the life cycle of a project. As we know, various kinds of
problems continuously arise during the course of a project. At any one time during the
lifecycle of a project, there can be a number of ongoing problems, disputes, negotiations
or conflicts. Some misunderstandings escalate up the “ladder” to cause more conflicts,
influencing the conflicting parties for some period. Therefore, the amount of cumulative
conflict is influenced by not only the amount of conflicts, but also by how these conflicts
arise and are resolved.

Figure 26 – Conflict Space

Conflict “Space” in Project


Degree of
Conflict

tion
iga
L it
Dispute
Resolution
Ladder
tion
itra
Arb

iati on
Med
ng
ndi
Sta tral
Neu
tion
otia
Neg

Cumulative Effect
of Conflict

Project
Project Life Cycle
Life Cycle

Owners must be cognizant of the time at which the conflicts will occur. At any one point,
there could be numerous conflicts at different stages of the dispute resolution ladder. The
bottom half of Figure 26 shows the effect of multiple ongoing disputes as the project
progresses. The Conflict Management Plan must be able to handle such scenarios. For
example, there could be five potential change orders in negotiations while two others
have escalated to arbitration and the designer is evaluating four other proposed changes
as a neutral advisor. The notion of conflict space should be kept in mind throughout the
design process, especially when identifying possible conflicts, to be managed during the
development of the project.

DRAFT 2/4/2017 2:32:00 PM 153


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

10.2 IDENTIFYING POSSIBLE CONFLICTS


To address conflicts on a project, we must first accept that conflict occurs even in the
best-managed project and identify what kind of conflict a project may encounter. To help
identify the conflicts that surface in a project, review the common sources of conflict in
Section 1.1, accepting these as the major sources of conflict on any given project.

Table 14 – Sources of Conflict and Dispute

Area Discipline Sources of Dispute

Internal/external organizational structure, delivery


Structure systems, inappropriate contract type, contract
documents, contract terms, and law.
Performance, quality, tendering pressures, payment,
delays, disruption, acceleration, tendering pressures,
Organizational Process
administration, formal communication channels,
Issues
information sharing, reports, and poor communication.
Misunderstandings, unrealistic expectations, culture,
language, communications, incompatible objectives,
People
management, negligence, work habits, and lack of
team spirit.
Change, variations, environmental concerns, social
External impacts, economics, political risks, weather,
regulations, uncertainty, and unpredictability.
Uncertainty
Incomplete scope definition, errors in design,
Internal unforeseen site conditions, construction methods, and
workmanship.

This list encompasses the major sources of conflict in the construction industry, but a
individual project will not necessarily encounter all of these disputes. If the project does,
then that may be an indication that perhaps it was not a good project to undertake.
Identifying which of these conflicts have the potential to occur and have an impact on the
project is the hardest step in the process of designing a Conflict Management Plan.

10.2.1 EFFECT OF DELIVERY SYSTEM ON IDENTIFYING CONFLICTS

Refering back to Chapter 1, we see that the selection of an appropriate delivery system
has a major influence over the type of conflicts that will arise in a given project. When
looking at the organizational structure and comparing the various relationships as shown
in Table 4, one may find that certain delivery systems are more prone to certain type s of
conflict situations. For example, if we take Stephenson’s (1996) construction conflicts,
we can identify which of them may be realize at the interfaces between the multiple
participants in an agency management delivery system (see Figure 27). One can eliminate
certain conflicts against the relationships among the owner, designer, CM and trade
contractor in a various situations if one selects a different delivery system. By doing this
exercise, one can find which conflicts are likely to surface according to the delivery
system selected.

154
CONFLICT MITIGATION PLAN

(CM-Trade Contractor
Owner-Trade Contrac
Owner-Designer

Owner-CM
1 Approval processes + +
2 Back-charges + +
3 Being a good off-site neighbor
4 Being a good on-site neighbor
5 Closing out the project +
6 Communicating with others
7 Constructibility +
8 Construction document quality + +
9 Contract interpretation + +
10 Cost growth + +
11 Decision making
12 Documents and documentation + + +
13 Equipment and material problems +
14 Financial matters
15 Inspecting and testing +
16 Issue, conflict, and problem resolution
17 Job management
18 Labor conditions +
19 Legal matters +
20 Maintaining regular project evaluations
21 Organization, authority, and responsibility
22 Paperwork and administrative work + + +
23 Payment processing
24 Personal quality and problems
25 Planning and scheduling +
26 Policies and procedures
27 Procurement of materials and equipment
28 Program conditions
29 Project cost structure
30 Quality management +
31 Regulatory agency matters + + +
32 Revision processing + + +
33 Safety +
34 Staff morale and attitudes
35 Staffing and personnel
36 Submittal processing + + +
37 Substitutions and alternates +
38 Time growth + +
39 Timely action
40 Training
41 User-group interaction + + + +
42 Value engineering
43 Warranty conditions
44 Weather conditions
45 Work-site condition + +

Scores of Each Realtionship 9 11 31 (36)


Scores of Each Delivery System (87)
Normalized Scores 0.10 0.13 0.36 (0.41)
Total of Normalized Scores (1.00)

Figure 27 – Potential Conflicts in Relationships for Agency Construction Management


Delivery System (conflict list from Stephenson, 1996)

DRAFT 2/4/2017 2:32:00 PM 155


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

The conflicts in relationships presented in Figure 27 are just one example of what the
owner should be considering when identifying potential conflicts. A circle counts as two
points and a plus counts as one point. A detailed list of conflicts could be generated by
the company based on historical data or personal experience of the people involved in the
project.

10.3 ANALYZING IDENTIFIED CONFLICTS


After studying the sources of potential conflict, one can begin to analyze them. This
analysis should include the probability that these conflicts might occur, and the impact
that each of these might have on the project.
Each of these sources of conflict has different probabilities of occurrence and impact
depending on the project. Say for instance, you have an owner and a contractor that have
worked together in the same geographic region for several years; chances are that the
probability of misunderstandings, unrealistic expectations and poor communication are
low. Compare this situation to an owner who ventures into a neighboring state or country
working with an unfamiliar contractor, the probability of occurrence for the same sources
of conflict are higher. This varying outcome is also true for the impact of conflict as well.
For example take two similar light rail projects, one delivered Design-Bid-Build and one
delivered Design-Build, and then introduce a design change halfway through
construction. Typically, the impact will be greater on the DBB project as the flexibility to
change the design is considerably lost without a significant impact once the owner
awarded the project to the contractor based on the lowest bid. The designer and the
contractor will need to work closely together in incorporating the changes. In addition,
the designer may not have the resources available to handle these changes after
completion of design, because personnel have moved on to new projects. The Design-
Build delivery method would typically offer greater flexibility in changing the design
after construction begins, because the designer and the contractor are on the same team
and their priorities for this project will be aligned, minimizing these impacts.
Going back to the characteristics of the construction industry (Section 1.1), no two
projects are exactly the same. For this reason, a conflict management plan should be
developed for each project based on the individualistic conditions. The circumstances that
surround the project affect the probability that certain conflicts will arise and the impact
that they may have. There is no standard way to evaluate conflict, although there have
been attempts, it must be done on a project-by-project basis. As with all studies and
predictions, the results are only as reliable as the data entered by the user. The “owner”
should complete a thorough discovery of the project circumstances in order to determine
an accurate prediction. In this situation, the word ‘owner’ collectively represents the
owner, owner’s consultant or other authorized representative. The following sections aim
to identify the probability an owner will encounter certain conflict and the impact each
may have. Both are equally important in determining the conflict that needs to be
managed.

10.3.1 PROBABILITY OF OCCURANCE

The probability an owner, contractor, subcontractor or designer will encounter conflict in


general on a project is a given. With this understood the questions they need to ask are;
what types of conflicts will they encounter? Can they reduce the probability that these
conflicts will arise? To do this we will begin to look at the common sources of conflict
and the circumstances that affect their probability of occurrence. This important, yet often
overlooked step is the start in creating a Conflict Management Plan.

156
CONFLICT MITIGATION PLAN

Organizational Issues
Following the potential areas of conflict in a project as presented in Table 2 (repeated in
Table 14), the first potential conflicts that should be explored are the Structure problems
in the area of Organizational Issues. This area addresses how the project is arranged,
delivered and contracted. To reduce the probability of a structural conflict the owner
should match the appropriate organization, delivery system and contract type
accordingly. When selecting the appropriate delivery system, it can be seen that certain
methods work better in certain situations. In a project where there is a solid, complete,
unambiguous design, the Design-Bid-Build is an excellent choice of delivery method. It
allows a fair competition among many bidders who know exactly what needs to be built.
Given these circumstances, contractors have little to misunderstand and the probability of
claims are minimal. In the case where the functional requirements have been set, but
design is not complete, and construction must begin, the selection of Design-Build might
be more appropriate.
Table 15 through Table 17 relate some common causes of conflict to the probability of
occurrence according to the project and its context. These generalizations begin to set
boundaries where conflict tends to exists. These boundaries were chosen to represent a
broad range of probability from low to high, which should be adjusted according to the
project.

Table 15 – Probability of Encountering Structure Conflict

Source of Conflict Probability of Occurrence


Low: Small projects, knowledgeable/experienced owner
Organization
High: Larger projects, numerous participants
Low: A system that aligns objectives and properly allocates risk
Delivery System
High: Adversarial ‘Cookie cutter’ system, unmatched for project
Low: Solid, proven contracts used on similar projects
Contract Type
High: Standard, highly specialized or unreviewed contracts
Contract Low: Standard, universally accepted plans and specifications, CSI
Documents High: Specialized specifications, high end CADD systems req’d
Low: Fair reasonable allocation of risk
Contract Terms
High: Unfair, unreasonable allocation of risk favoring one party

The owner will begin to get a sense of the probability that conflict will occur by looking
at each of the sources of conflict, then rating them. The owner can do this on various
scales, but again, the results depend on how accurate the information is. In the early
stages, a simple high, medium, or low probability will begin to help for the management
plan. Owners, designers, and contractors can use numbers as more accurate, historical
information becomes available to them.
Once the structural conflicts have been analyzed, the focus is shifted to the Process
problems. Owners can expect this type of conflict when handling a larger project if they
have a small staff or have an inexperienced staff. For example, the processing of requests
for information or request for payment from the contractor when handled inefficiently
leads to claims.

DRAFT 2/4/2017 2:32:00 PM 157


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Table 16 – Probability of Encountering Process Conflict

Source of Conflict Probability of Occurrence


Performance and Low: Cost-Plus, quality driven projects, inspection staff
Quality High: Competitive bids award to lowest bidder, bad reputation
Low: Payment clauses in contract and payment bonds
Payment Delays
High: Lack of qualified staff on owner’s side
Low: Backup plans or alternative approaches available
Disruption
High: Poor planning, strict schedule, no flexibility
Low: Qualified, adequate staff
Administration
High: Unqualified, inadequate or overworked staff
Low: Backed by contract, circular integration
Formal Channels
High: Vertically integrated with numerous steps
Information Low: Open web based system, documentation is crucial
Sharing High: Closed, non-documented random system

Rounding out the Organizational Issues is the probability of encountering conflict based
on the interactions with People. Taking compatibility of objectives for an example, by
introducing profit sharing incentives, a contractor is more likely to ignore frivolous
claims. The probability that conflict will occur in this area is low when the participants’
objectives are aligned. The reverse of this situation is a fixed price, low bid scenario. As
the contractor starts to lose money, the probability of claims will be high, as the
contractor hopes to offset these loses.

Table 17 – Probability of Encountering People Conflict

Source of Conflict Probability of Occurrence


Misunderstandings / Low: Previous experience with participants
Communications High: Language barriers, unwillingness to communicate
Compatibility of Low: Incentives, shared profit built into the contract
Objectives High: Adversarial relationships
Low: Long distinguish solid managers
Management
High: Inexperienced participants
Low: Solid history that demonstrates ‘reasonable care’
Negligence
High: Past history of negligence

Conflicts that arise from Organization Issues are vast and easily be predicted with a little
bit of logic and solid planning. The importance of a solid organizational structure with an
appropriate delivery system is paramount. Although some restrictions are put on various
delivery systems for certain owners, research and past experiences can curb these
limitations.

Uncertainty
The probability of certain types of Uncertainty, although an oxymoron, can be more
predictable than most Organizational Issues. For example, if a contractor planned to do
work in Vietnam they must account for time lost to weather during the rainy season.

158
CONFLICT MITIGATION PLAN

Based on historical records, statistics can determine the average amount of rain that the
contractor should account for. The same is true for earthquakes, floods, fires and other
instances. Insurance is one of the options used to mitigate these unforeseen, but
statistically predictable events. Other options include clauses in the contract for
uncertainty such as adverse weather conditions, differing site conditions or a shortage in
skilled labor.
Similar to the Organizational Issues, owners can look at the project circumstances and
determine the probability relating to the types of Uncertainty conflicts that will occur.
Looking at External uncertainty, environmental concerns in the world have been among
the forefront of controversy and have grown exponentially in the Untied States since the
passage numerous federal regulations in the 1970’s and 1980’s. Many owners found the
impediments to build waste disposal sites overbearing. The “Not in My Backyard”
philosophy has united communities and grassroots organizations who have repeatedly
stalled owners in costly legal zoning battles and court proceedings. An owner building a
waste disposal site should expect the probability of conflict to be high in the area of
Social Impacts, Changing Regulations, and Environmental Concerns. Not taking these
sources of conflict into consideration can be detrimental to a project.
Although rare in certain countries, political risks are highly probable in others. A perfect
example of this is the country of Afghanistan during the 20th century, particularly during
the Soviet invasion throughout the 1980’s. As much as 80 percent of the country eluded
effective government control. This included parts of major cities such as Herat and
Kandahar. The likelihood of political risks occurring on a project approached 100%. This
political instability in many third world countries is apparent and need to be taken into
consideration. The probability and impact of this source of conflict sometimes does not
offset the financial rewards, in these cases no development occurs. Take note that the
International Bank for Reconstruction and Development (IBRD) division of the World
Bank aims to promote projects with these circumstances, although excellent
opportunities, participants should be aware of the risks undertaken in these projects and
the probability that they will encounter conflict.
Table 18 provides a general gauge of the chances of encountering External Uncertainty
based on various project circumstances.

Table 18 – Probability of Encountering External Uncertainty

Source of Conflict Probability of Occurrence


Change Low: Solid, well thought out design
High: Cursory thought process and planning
Environmental Low: Environmentally conscious projects
Concerns High: Projects within environmentally sensitive areas
Social Impacts Low: Site zoned for proper use in a consistent area
High: Environmentally sensitive projects
Political Risks Low: Work in areas with stable, well developed governments
High: Newly developed governments or history of instability
Weather High or Low probability of inclement or disastrous weather
based on historical data
Regulations Low: Documented, court proven and tested regulations
High: New, unclear or constantly changing regulations
Consistent with External Uncertainty, participants can reasonably expect Internal
Uncertainty depending on the surrounding situation.

DRAFT 2/4/2017 2:32:00 PM 159


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Table 19 – Probability of Encountering Internal Uncertainty

Source of Conflict Probability of Occurrence


Incomplete Scope Low: Well documented, unambiguous scope
Definition High: Inexperienced owners, lack of planning
Errors in Design Low: Well reviewed contract documents, reputable designer
High: Inexperienced, overworked designers
Unforeseen Site Low: Open, above ground projects with adequate investigation
Conditions High: Lack of subsurface investigation for all participants
Construction Low: Proven traditional methods used in construction
Methods High: Experimental, unproven methods, specialty equipment

Overall, the probability of encountering conflict is based of individual project


characteristics. Once probabilities of certain conflicts are determined, one can begin to
look the impact that each of these sources of conflict will have on the project and
determine if they warrant a DART.

10.3.2 IMPACT OF CONFLICT

Concurrent with the probability of occurrence of a certain type of conflict is the impact
that the conflict may have on a project. The impact is independent of the probability of
occurrence, that is, the consequences of the conflict if it occurs would be the same if it
did or did not happen. Determining the impact of a conflict is just as important as
determining the probability of occurrence.
Some conflicts have a low probability of occurring but can have a significant impact on
the project, such as conflicts due to natural disasters, prolonged strikes or major
accidents. An example of this is the catastrophic failure of a 567-foot tall crane in the
construction of Miller Park on July 14, 1999 in Milwaukee, WI in the United States. The
stadium was designed to have a retractable roof. During the pick and placement of one of
the 450-ton roof sections, the crane failed dropping the roof section, killing three
ironworkers and effectively destroying ¼ of the completed stadium. This accident
impacted the schedule, increasing the duration by a full year, and caused over US$100
million of damage. A number of factors, including high winds and the management’s
drive to get the project done, were determined by the experts to have caused the failure.
Although the probability of conflicts due to this type of failure happening is very small,
the impact can be enormous.
At the same time, there are numerous other conflicts that are almost a given on a project.
The probability of them occurring approaches 100%, but the impact is almost negligent.
Problems are resolved on a daily basis through negotiations with on site personnel, but
they never escalate to the point of recognition. Issues such as scheduling, work-a-rounds,
and other accommodations made between various project participants on site, happen
daily. Impacts typically range from upset foreman to nasty letters from owners, but
overall the impact is negligent. Negotiation is the most common DART used to resolve
these types of conflicts, in particular step negotiations.
Quantifying impacts can be difficult. One way of doing so is to use historical data
relating to similar instances. Another is through experience and knowledge of the
industry. Initially, quantifying impact does not have to be 100% accurate, as each project
is different, but the idea is to get in the general range so that decisions can start to be
made about how much conflict the project is exposed to and what should be done to
prevent it. A list of examples are presented in Table 20.

160
CONFLICT MITIGATION PLAN

Table 20 – Examples of Impact on the Project

Source of Conflict Impact on Project


Weather Low: Construction ‘friendly’ environment
High: Area prone to natural disasters
Errors in Design Low: Well reviewed contract documents, reputable designer
High: Inexperienced, overworked designers
Unforeseen Site Low: Open, above ground projects with adequate investigation
Conditions High: Lack of subsurface investigation for all participants
Construction Low: Proven traditional methods used in construction
Methods High: Experimental, unproven methods, specialty equipment

10.3.3 COMBINED CONFLICT EXPOSURE

The last step in analyzing conflict is calculating the combined conflict exposure. This is
done by combining the probability of a conflict occurring with the impact that it may
have. The combined conflict exposure is based on the probability that conflict in general
or a specific type of conflict (c) will occur, P(c), and the resulting impact of the conflict
occurring L(c). Combined conflict exposure can be done at numerous levels of detail, but
the accuracy of this analysis is based on the amount of information available. Two
examples are presented to give the reader an idea of the level of detail that this analysis
can be performed. If little or no historical data is available, a crude system of high,
medium, low can be used and can be divided into more possibilities depending on the
amount of the information available.
For example, a homebuilder is considering constructing three new houses in a local
subdivision. The builder has identified the probability of miscommunication with trade
contractors as high. In addition, the impact of this source of conflict can be very high as
well. As the builder starts to list various sources of conflicts and relating the probability
that they will occur and the impact that each of these conflicts has, a combined risk
exposure table can be developed (Table 21). From this analysis, the builder begins to get
a sense of what conflicts need to be managed during the project and will be expanded
upon in the following section.

Table 21 – General Conflict Exposure

Source of Conflict (c) Probability of Impact of Combined


Occurrence P(c) Occurrence L(c) Conflict Exposure

Miscommunication High Very High High

Performance/Quality High Med Med-High

Management Med Med Med

Contract Type Low Low Low

Another example where historical data is available presented in Figure 28. The bottom
half of the probability tree shown in Figure 28 performs this type of analysis of conflict

DRAFT 2/4/2017 2:32:00 PM 161


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

exposure on a macro level, or that conflict in general will occur. This analysis is based on
a $200 million project without any mitigation strategy. It predicts that there is a 40%
chance of encountering conflict that will result in a $25 million impact to the project.
There is a 50% chance that conflict on the project will result in a $5 million impact and a
10% chance that conflict on the project will have $1 million impact. In this case, it is
assumed that the probability that conflict will not occur at all is negligible. The overall
conflict exposure is therefore calculated to be $13.5 million.
The probabilities and impacts should be taken from past projects in the range of $150 -
$500 million, adjusting the impact accordingly as a percent of the total construction costs.
One could also attribute sources to the conflict and identify the impact associated with
these sources. Individual conflict exposure analysis would then be done on each source of
conflict. This involves more detail as there are usually several contributing sources
affecting the impact. Care must be taken so that they the impact is distributed properly
and not accounted for multiple times, unrealistically inflating the conflict exposure. By
calculating the conflict exposure that is derived from each source of conflict, the owner
can prioritize the sources of conflict that need to be addressed first, which will aid in
designing the Conflict Management Plan.

Risk Exposure
P(c) x L(c)

P(c) = 0.10
Large Problem 0.1 x 25 = 2.5 M
L(c) = $ 25 M
+ 2.5
P(c) = 0.20 + 1
Yes Medium Problem 0.2 x 5 = 1 M + 7
L(c) = $ 5 M = 10.5 M

P(c) = 0.70
Small Problem 0.7 x 1 = 7 M
L(c) = $ 1M

Partnering

P(c) = 0.40
Large Problem 0.4 x 25 = 10 M
L(c) = $ 25 M
+ 10
P(c) = 0.50 + 2.5
No Medium Problem 0.5 x 5 = 2.5 M + 1
L(c) = $ 5 M = 13.5 M

P(c) = 0.20
Minor Problems 0.1 x 1 = 1 M
L(c) = $ 1 M

Figure 28 – Calculating Conflict Exposure

After calculating the conflict exposure, the same type of analysis can be done to calculate
the conflict exposure with the application of various DART techniques. Again, based on
historical data, an owner can predict the amount of exposure they will face from a source
of conflict depending on what DART they implement. The top half of Figure 28 focuses
on overall project conflict with effective Partnering (Section 4.3) as the chosen DART. It
predicts that there is a 10% chance of encountering conflict that will result in a $25

162
CONFLICT MITIGATION PLAN

million impact to the project if Partnering is used. There is a 20% chance that conflict on
the project will result in a $5 million impact and a 70% chance that conflict on the project
will only have $1 million impact. Therefore, the overall conflict exposure is calculated at
$10.5 million.
In this situation, implementing Partnering reduced the conflict exposure by $3 million.
Depending on how much it costs to employ Partnering, one can determine whether this
DART should be used. The selection of the appropriate DART technique and the
cost/benefit analysis is discussed in further detail in the next section.
Once the conflict exposure is calculated for each of the identified potential conflicts, they
can be grouped into priority levels. They can be categorized into one of the following
three groups according to a pareto optimal categorization:
Group A: 10–20% of the top conflicts with high potential of realization, which
together account for roughly 60% or more of the total potential impacts the
project.
Group B: all activities not members of group A or C.
Group C: large percentage of the bottom conflicts in terms of potential of
realization, which account for 10% or less of the total potential impacts.
The conflict management plan can then be designed according to the priority. This is
discussed in more detail in the following section.

10.4 DESIGNING THE MANAGEMENT PLAN


After assessing the probability of occurrence and degrees of impact that certain conflicts
cause, it is time to develop a preliminary plan to mitigate these sources of conflict. The
owner develops this preliminary plan based on their assessment of the project
circumstances and their exposure to the identified source of conflict. In preparing for this
planning, the owner must explore a range of options carefully weighing each one for the
criteria of cost and benefit, keeping in mind which technique can better handle the
conflict. The participants that the owner can allocate the management of certain conflicts
to can be anyone of the stakeholders previously named in Section 1.2.1, such as the
owner, designer, or contractor. In addition, other participants such as insurance
companies or financial institutions services can handle certain conflicts more effectively.
The following are the steps that need to be done when designing the plan:
• Prioritize the sources of conflict.
• Implement DART to avoid/prevent conflict using techniques in Stage 1 and
Partnering.
• Implement DART to resolve conflict, using techniques in Stages 2 through 5.
• Identify each participant’s role.
• Perform a Cost/Benefit Analysis of the Conflict Management Plan.
• Develop a contingency plan.
• Review with all participants and update as necessary.
After reading the previous chapters in this book, one should be aware of the different
stages of dispute resolution. To optimize the Conflict Management Plan, apply these
stages in order to reduce the probability conflict will occur and the impact that it will
have. Keep in mind that not all of the stages will be used in a single project. As stated
repeatedly, the Prevention Stage is the best opportunity to address conflict.

DRAFT 2/4/2017 2:32:00 PM 163


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

10.4.1 PRIORITIZING AND DART IMPLEMENTATION

Now that the major sources of conflict have been identified and analyzed, it’s time to
look at which of these conflicts need attention. This can be done in numerous ways, but a
table incorporating the necessary information seems to work best. The first four columns
of Table 22 incorporate the information gathered in the analysis of the conflicts identified
(Section 10.3). The purpose of this table is twofold. First, it allows the prioritizing of
conflict based on the exposure. Next, it begins to assign appropriate prevention strategies
to address those potential conflicts. The management strategies used are those listed in
the Prevention Stage (Chapter 3) and cost is the cost associated with each. The use of
only prevention DART is because we are targeting conflicts before they occur.

Table 22 – Example of a Mitigation Plan List

Probability of
Occurrence

Occurrence

Prevention

Resolution
Procedure
Impact of

Exposure

Exposure
Reduced
Strategy

Strategy
Conflict

Conflict
Cost of
Source of Conflict

Organization
Delivery System
Contract Type
Contract
Documents
Contract Terms
Performance and
Quality
Payment Delays
Disruption
Administration
Formal Channels
Information
Sharing
Misunderstandings
/ Communications
Compatibility of
Objectives
Management
Negligence

164
CONFLICT MITIGATION PLAN

Once the preventative measures have been selected, a resolution procedure must be
designed so that when conflicts do arise, the conflicts are addressed and resolved. This
step in designing the Conflict Management Plan involves reviewing Stages 2 through 6
and comparing them with the characteristics of the project. In selecting an appropriate
resolution procedure, one must ponder numerous questions about the individual project.
How large is the project? What type of delivery system is used? How many parties are
involved? Who should initiate the process? What is the chain of command? How are
change orders handled? How crucial is the schedule? Should conflicts be resolved as
soon as possible, or at the end of the project?
All of these factors and more shape the decisions made in determining this step. If
schedule is of the utmost importance, an on-site representative or third party neutral can
deliver solutions instantly. In addition, include a clause that all appeals must be filed
when they arise and settled at the end of the job, and the fast track schedule will not be
hung up on conflicts. If the project is of an unusually large size, an impartial DRB might
be an alternative to a single neutral. There are pros and cons to every approach, as
outlined in each chapter, but the intent here is to identify which ones will be appropriate
to a given situation. In comparing these advantages and disadvantages with each project,
a resolution procedure should begin to take shape. It is now time to apply the knowledge
gained about the individual DART to a particular situation.
In addition to the application of DART, some other factors must be considered such as
cost, other party’s willingness to participate and clarity of procedure. The following
section addresses these factors in more detail.

10.4.2 IDENTIFICATION: WHO IS RESPONSIBLE?

This process starts with the identification of possible conflicts and an agreement on who
is responsible for addressing them first. Therefore, every party involved knows their role
and there are no surprises or excuses when the conflicts do arise. Agreement on
allocating the responsibility for conflicts upfront helps reduce and sometimes even
eliminate finger pointing.
This identification currently is done in a variety of ways. The most common of
addressing conflict has been in adding or modifying clauses contract. Another way is to
identify them in the Conflict Management Plan (a part of the contract documents) and
have each party sign the plan stating they are aware of and agree with their responsibility.
In either case, the contract should be reviewed for conflicting statements that create
ambiguities. These types of ambiguities (Organizational, Structural) often lead to
litigation, as both parties involved identify with the conflicting clause or document that
supports their claim. It is the owner’s responsibility to develop a contract with no
ambiguities. Confusion is reduced by eliminating them or defining which one takes
precedence over the other.
In addition to identifying who is responsible upfront, the importance of good
documentation cannot be stressed enough. A paper trail can be invaluable, when
reviewing what when wrong and aids in identifying who was responsible.

10.4.3 COST/BENEFIT ISSUES

One thing that has not been mentioned before but is of great importance is the cost of
implementing these conflict resolution strategies. It is safe to say that resolution of any
conflict in construction is possible if cost is not an issue. With the invention of new and
innovate dispute and avoidance techniques mentioned throughout this book, one must
keep in mind that these techniques are only plausible if they bring value to the project. Is

DRAFT 2/4/2017 2:32:00 PM 165


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

a couple going to spend $20,000 on a partnering retreat with a contractor that is painting
their house? Of course not. The costs far exceed the benefits, but on a billion dollar
privately funded dam project, a $100,000 might be the best investment made if it helps
avoid or resolve a $100 million claim. The participants must keep this in mind when
designing the Conflict Management Plan.
One way to do this is by reviewing the combined conflict exposure developed when
analyzing the conflicts and compare them with the cost of the mitigation strategy
identified from the prevention stage. One should implement these techniques if the cost
of the mitigation strategy and the resultant conflict exposure is less then no management
strategy and its corresponding conflict exposure. Looking back at Figure 28, we can see
an example of this. The calculated conflict exposure if Partnering is implemented on this
project totals $ 10.5 M. On the other hand, if Partnering is not implemented the conflict
exposure increases to $13.5 M. Assuming that the cost of implementing Partnering on
this project is $0.5 M, it would make sense to do so. By applying Partnering to this
project, $11 M is expected to be spent on disputes (10.5 plus the 0.5 spent on Partnering)
compared to $13.5 M expected to be spent if nothing is done. In this case, it does make
sense to put into practice the DART, but in others, it might not. If the cost of
implementing Partnering were $3 M, it would not be optimal to do so.
If the data is not available to do this type of detailed analysis, one can use the high,
medium, low approach. Referring back to the example presented in Section 10.3.3, Table
21 can be recalculated to account for the result that Partnering will have on the various
sources of conflict. The cost of implementing this strategy can then be weighed against
this analysis.

Table 23- Conflict Exposure after Implementing Partnering

Source of Conflict (c) Probability of Impact of Combined


Occurrence P(c) Occurrence L(c) Conflict Exposure

Miscommunication Low High Med

Performance/Quality Med Med Med

Management Low Med Med

Contract Type Low Low Low

This type of cost/benefit analysis should be done as a reality check when using these
strategies. The cost of installation for some DART is negligent, while others can grow to
be quite expensive. Keep in mind that cost does not merely mean monetary loss. Time
loss and overall stress can also be a factor. It does not take into account for unquantifiable
costs, such as the value of a good working relationship. Although some of these things
might not be able to be quantified as a monetary value, they should not be overlooked.

10.4.4 CONTINGENCY PLAN

A contingency plan is nothing more than a list of options for both of the parties. These
options should outline the strengths and weaknesses that the Conflict Management Plan
has. As mentioned earlier, the cost of implementing various DART may exceed the
benefit. Therefore, by not implementing these DART everyone must be aware that they

166
CONFLICT MITIGATION PLAN

have conceded that conflict in this area may occur and no strategy is in place to prevent
them from happening or mitigate their impact if they do occur. The contingency plan
identifies these areas where conflict is expected to arise.
The contingency plan is also a backup in case of the unpredictable. In most cases, this is
litigation and at times, litigation is the best contingency plan. Without the threat of
litigation, some of the DART are not a viable option. Some participants out there would
like nothing more than to tie a dispute up in court for years, whether or not they think
they are going to win or lose. Dishonest owners who currently hold the money do not let
it go without a fight. For a contractor this could mean bankruptcy if the project is long
enough. In other instances, stubborn contractors feel that they are entitled to more then
they really deserve, causing stress for the owner.
In general, the contingency plan is one more step in the “What if?” process. By taking
this extra step, it keeps the participants from stumbling if a part of the Management Plan
does not work as anticipated.

10.4.5 COMPUTER APPLICATIONS

Eventually the application of technology will aid in the process of designing a Conflict
Management Plan. Preliminary models are being developed and tested, incorporating the
information presented in this chapter. As research and development continues and more
data is gathered, accurate functional models will be generally available to analyze
different scenarios based on different variables and predict the amount of conflict that
will occur on a given project. Different scenarios would be easily entered and modeled
with minimal computation. An example of such a system can be in the DARTS system
developed by Fenisoky Peña-Mora and Tadatsugu Tamaki at the Massachusetts Institute
of Technology (Figure 29).

Figure 29 – DART Simulator Screen

DRAFT 2/4/2017 2:32:00 PM 167


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

In this application, project circumstances are taken into account and then the user can
select different DART to minimize conflict on that project. Applications such as these
will allow the users to review numerous scenarios and assist the participants in refining
the Conflict Management Plan. This is especially important during and after the project is
underway.

10.5 IMPORTANCE OF REVIEW


Sometimes going overboard on a plan not only increases the dollar costs of a
management plan, but can ruin relationships, slow the project and lead to litigation
quicker than having no plan at all. This is where review and acceptance of the plan by all
the parties involved becomes important. For instance if a project has all six steps in the
dispute resolution ladder, a contractor might be hesitant to bid on the job. If the claim
goes all six steps, it might take years to receive money on a valid claim, possibly putting
the contractor out of business.
Forcing a dispute resolution plan on a party forms an adversarial relationship from the
start. From what we have seen, this leads to the lack of participation from the other
parties, a key element in resolving conflicts. By including all the participants in the final
decision of what conflict management plan to adopt, the interests become aligned and all
are more willing to faithfully participate.
This review of the Conflict Management Plan should be done at various stages in the life
cycle of a project such as planning, design, pre-bid meeting, award of bid, at project
milestones, and project close-out. In the planning stage an initial concept should be
developed, and refined in the design stage to be almost complete. Reviewing the plan
during the pre-bid meetings (if any are held) provides opportunity to engage the
contractors in the process as well as alert them to how conflicts will be handled before
they bid on a project. When the award is made, the plan should be review thoroughly
with all the parties involved. This review has two major objectives; inform all the parties
involved, and make them a partner of the process. By making them a partner in the
process, they are jointly responsible for the design of this plan, therefore, when conflict
arises they are more apt to particiapte without protest.
Another important step at the project close-out is the overall review and effectiveness of
the plan. If the plan did not work, ask the question, “Why?” Review the cost of each
strategy that was implemented. This information will prove useful when designing the
Conflict Management Plan for the next project.

10.5.1 CONFLICT RESOLUTION INDEXES

By using a conflict resolution index, it is easier to determine whether the Conflict


Management Plan is working. A conflict resolution index takes into account certain data
from the project that is quantifiable and returns a rating for the Conflict Management
Plan. These indexes may include the number of negotiation, number of change orders,
frequency of change orders, duration of negotiations, number of parties affected,
satisfaction with result of change orders among others.

168
CONFLICT MITIGATION PLAN

Table 24 – Proposed Indexes for Conflict Resolution


(adopted from Pena-Mora et al., 2001)

Indexes Data Examples

Number of Negotiations Number of negotiations taken place during the


change order process

Frequency of negotiations Project duration over number of negotiations.

Duration of negotiations in project Total days of negotiations

Number of negotiations steps Maximum number of negotiations steps in


negotiation

Number of parties affected in Number of negotiations over one issue


negotiations

Satisfaction with the results Trends over negotiated amount over proposed
amount

Innovativeness or uniqueness of the Differences from conventional results (e.g.


outcome of negotiation integrated bargaining results over distributed
ones)

As the project continues and relevant data is collected, it can be analyzed to identify
where conflict still exists. Looking back at Figure 25, this part of the review process of
identifying existing conflict completes the loop and begins the cycle of Conflict
Management process again. A more detailed description of this process is depicted in
Figure 30.

Information on
Potential Conflicts

Contract
Contract Contract
Contract Contract
Contract Contract
Contract
Planning
Planning Formation
Formation Administration
Administration Monitoring
Monitoring

Negotiation
Indexes

Agreement/
Perceived Conflicts Negotiation
Solution

Potential Conflicts

Figure 30 – Review Process (Pena-Mora et al., 2001)

DRAFT 2/4/2017 2:32:00 PM 169


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

This iterative process, if executed correctly, will reduce conflict on a project.

Brock Returning to the Brock and Kelly case, the siblings are facing the task of designing a
and Conflict Management Plan. Kelly identified the following as the major sources of conflict
Kelly’s in the $1.5 billion program.
Plan
Table 25 – Kelly’s Conflict Management Plan

Occurrence

Occurrence
Probability

Prevention
Impact of

Exposure

Exposure
Strategy

Strategy
Conflict

Conflict
Reduce
Cost of
of
Source of Conflict

High Med High Program Manager 10 Low-


Organization
Med
Performance and Low High High QC Inspectors 5 Med
Quality
(Life Cycle Costs)
Disruption Low Med Med Weekly Meetings 1 Low
Information High Low Med Web Based 1 Low
Sharing System
Misunderstandings High Low Med Weekly Meetings Included Low
/ Communications above
Compatibility of Med Med Med Partnering 10 Low
Objectives

By local regulation, Kelly was restricted to competitively bidding all of the contracts. To
align the objectives, reduce miscommunication and disruption she decided to invest in a
Partnering program. In addition to Partnering, she hired and independent Program
Manager to help handle the load of the projects that the government agency is taking on.
independent Quality Control inspectors were also assigned to the construction phase to
watch over the contractor. A clause was added in the contract that requires the contractor
to provide a Quality Assurance representative as well. Both of these personnel aim to
reduce the Performance and Quality conflicts. Following the preventions aspects of the
Plan, Kelly opted to use a DRB to resolve disputes that arise to reduce the impacts of
these disputes. This was not included in Table 25 because it applied to all of the sources
of conflict. The DRB panel will consist of 3 members, one appointed by each party and a
third jointly select by the appointees. Disputes can be submitted to the DRB at any time
during the project only after the parties have attempted at least three rounds of good faith
negotiations, with or without a mediator paid for by the owner. The DRB panel has the
power to issue binding solutions so as not to affect the schedule of other contracts.
Brock on the other hand, took a different route than Kelly. Not being too familiar with the
hotel development business, he hired reputable contractors experienced in building hotel
and added some incentive with shared savings. In addition, he hired a consultant
knowledgeable in the hotel development business for the first project. Although this
would cut into his profit a little, it would align the objective of the parties involved and
reduce his exposure to conflict. Various clauses were added to the contract to share the
risk of differing site conditions and adverse weather. Costly legal proceedings could

170
CONFLICT MITIGATION PLAN

bankrupt a small developer such as Brock, so a binding Mediation/Arbitration clause was


added to reduce the impact of the conflict if it occurs.

Table 26 – Brock’s Conflict Management Plan

Occurrence

Occurrence
Probability

Prevention
Impact of

Exposure

Exposure
Strategy

Strategy
Conflict

Conflict
Reduce
Cost of
of
Source of Conflict

Compatibility of High High High Shared Saving variable Low


Objectives
Performance and Med High Med- Hire Reputable 0 Low-
Quality High Contractors Med
(Life Cycle Costs)
High Med Med- Shared Savings & variable Low-
Miscommunication
High Consultant Med
Med Med Med Consultant 1% of Low
Administration
costs

10.6 SUMMARY
The conflict management plan is one of the most important but often overlooked steps in
the project. It should be conceived when planning begins and continue to be reviewed
and revised throughout the project life cycle. The Conflict Management Plan is
developed by identifying conflicts that might occur on the project, then analyzing the
impacts that each will have. After prioritizing these conflicts, dispute avoidance
techniques are applied to prevent the conflicts from occurring. Next, a resolution
procedure is designed; focusing on the impact of the conflicts, so when conflict does
occur the effects are minimal. All participants in the project should be involved
throughout the process or as they are brought onboard.
These plans are individually tailored to each project. The implementations of the DART
are done on a cost versus benefit basis. Although it is virtually possible to resolve every
conflict with money, it is not always effective. Quality of the final product and schedule
must be kept in mind when performing the cost/benefit analysis.
By designing the Conflict Management Plan, all the participants in the project are forced
to contemplate the conflict that they will encounter. This will allow the allocation of
responsibility for each one of these sources of conflict before it occurs. This upfront
distribution reduces ignorance and allows the responsible participant to effectively handle
conflicts.

DRAFT 2/4/2017 2:32:00 PM 171


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

10.7 POINTS FOR DISCUSSION


10.1 If there is not a Conflict Management Plan, where do the parties turn for
information if a dispute arises? What role does the contract play if a Conflict
Management Plan is developed?
10.2 Do the sources of conflict overlap with each other? Are there certain sources of
conflict that are interrelated?
10.3 When analyzing the possibility that a conflict might occur, where might an owner
go to get information on this? Would this change if this were the owner’s first
project? How might an inexperienced owner determine the probability that conflict
might occur?
10.4 What are the differences between probability of occurrence and impact of the
conflict? Can they be combined into one entity?
10.5 Could the impact of a conflict be standardized across all projects, i.e. would the
predicted impact of rain, earthquakes, and miscommunication affect all the
projects the same or does it vary from project to project? Is this true for all conflict
types?
10.6 How accurate should the probability and impact information be to design a
Conflict Management Plan? How does this relate when weighing the costs versus
benefits?
10.7 When would an owner incur costs for designing a Conflict Management Plan?
What are the effects of the timing in which the owner incurs these costs? Should
the contractor contribute money to the design and development of the Conflcit
Management Plan?
10.8 What are the benefits of assigning risk and conflict responsibility to the
appropriate parties before construction begins? Are there any drawbacks?
10.9 Discuss the importance of reviewing and revising the Conflict Management Plan.
Does this create any problems? Is there any incentive for parties to actively review
this plan or is this something that will only come up in the case of a dispute, after
the fact?
10.10 Why include a contingency plan? Should this contingency plan be hard to
implement? What might be some obstacles if a contingency plan is implemented?

10.8 REFERENCES

[Pena-Mora et al., Pena-Mora, Feniosky and Tamaki, Tadatsugu (2001). Effect of


2001] Delivery Systems on Collaborative Negotiations for Large-
Scale Infrastructure. ASCE Journal of Management in
Engineering, Vol. 17 (2), April 2001.
[Stephenson, 1996] Stephenson, R. (1996). Project Partnering for the Design and
Construction Industry. Wiley. New York. 1996.
Pfleeger, Shari Lawrence. Software engineering: Theory and
Practice. Upper Saddle River, NJ. Prentice Hall. 2001.

172
CONFLICT MITIGATION PLAN

Jalote, P. An integrated approach to software engineering. New


York. Springer. 1997.
Braude, Eric J. Software engineering: An object-oriented
perspective. New York. Wiley. 2001.

10.9 ENDNOTES
none

DRAFT 2/4/2017 2:32:00 PM 173


C H A P T E R

11
CASE STUDY:
TREN URBANO
“…at the Construction Progress Meeting(s) or
partnering sessions at which the Claim is
considered, technical personnel of the parties,

PROJECT1
experienced in the discipline involved in the Claim,
will endeavor diligently and in good faith to
identify the issues involved, consider impartially the
countervailing positions, and achieve a resolution
of the Claim.”
(Rio Piedras Contract, 1997)

The Tren Urbano Project is a light rail transit line being developed in San Juan, Puerto
Rico. The first alignment of the project, Alignment 1 (Figure 32), is a 17.2-kilometer line
including 16 stations with maintenance facilities and operations and the administration
building. This first phase of the project was expected to be completed by November 2001
and to cost $1.5 billion. This project presents several peculiarities that made it perfect for
the analysis in this book. It is a large-scale project, with an innovative procurement,
multicultural and multiphase characteristics.
In this chapter, the history and a detailed description of the project are presented,
including the parties involved and their contractual relationships. Following the

CHAPTER LOOK AHEAD


WHAT IS IT? The Tren Urbano Project is a light rail transit line being developed in San Juan, Puerto
Rico. It is a large-scale project, with an innovative procurement, multicultural and multiphase
characteristics. This first phase of the project was expected to be completed by November 2001 and to
cost $1.5 billion
WHO IS INVOVLED? Key participants for this project include: Puerto Rico’s Department of Transportation
and Public Works (DTPW), Parsons DeLeuw, Inc., Federal Transit Administration, Siemens Transit
Team, Daniel, Mann, Johnson and Mendenhall (DMJM) and Frederic R. Harris, Inc.
WHY IS IT IMPORTANT? This project presents several peculiarities that made it perfect for the analysis
and application of the material presented in this book.
HOW TO APPROACH IT? Understand the project circumstances. Identify the potential conflicts. Analyze
the potential conflicts. Design a conflict Mitigation Plan. Review and revise the plan based on project
data.

KEY CONCEPTS
Project Description ........................................176 Procurement Strategy ...................................... 178
Conflict Management ....................................180 Analysis of Tren Urbano Components ............ 184

174
TREN URBANO

presentation of the background material, a hypothetical analysis is given to provoke


thought and promote discussion. This analysis focuses on the material presented
throughout this book. Keeping this in mind, read the information presented and how it
relates to the techniques that are available for dispute avoidance and claim management.
Our goal is to familiarize the reader with real-life applications of DART, so they may
apply them to their current or future situations.

11.1 TREN URBANO PROJECT STORY


In 1989, Puerto Rico’s Department of Transportation and Public Works (DTPW)
proposed to construct a light-rail system called Tren Urbano. Parsons DeLeuw, Inc. was
contracted to develop the conceptual design. In January 1993, a new executive team took
charge of the DTPW and its Highway and Transportation Authority (PRHTA), to review
the light-rail concept developed by their predecessors. This included a team of Puerto
Rican engineering, architectural, and project management consultants, who joined forces
with some of the best-known transit development and design experts in mainland United
States 2.
In February of that same year the Federal Transit Administration designated Tren Urbano
as one of four turnkey demonstration projects in the nation. The new DTPW team re-
thought the Tren Urbano concept from the ground up and decided to set their sights on a
world-class transit system that would be a model of advanced technology, quality design,
and innovative project management (DTOP, 2000). In January 1994, they submitted a
successful bid for Federal assistance to the U.S. Congress.
In April 1994, the Department of Transportation and Public Works signed a $42-million
contract for General Management and Architectural and Engineering Consultant
(GMAEC) services. The contract was with a joint venture composed of two leading
transportation infrastructure development firms from the U.S. mainland and two Puerto
Rican firms. The U.S. partners in the GMAEC contract were Daniel, Mann, Johnson and
Mendenhall (DMJM) and Frederic R. Harris, Inc. The Puerto Rican firms were Eduardo
Molinary and Associates (architects) and Barret and Hale and Associates (consulting
engineers).
These four firms, together with more than 20 subcontractors, made up the GMAEC,
which employed over 150 professionals representing diverse engineering, design,
architecture, and project management specialties. The consortium moved into their
project offices in October 1994. There they have worked hand-in-glove with the Highway
and Transportation Authority’s project oversight team, now organized as the Tren Urbano
Office (TUO). The primary mission of TUO at this early stage was to carry out the
planning and environmental permitting process, to develop partial plans and systems
specification, and to structure a procurement process and assist the DTPW/HTA in
carrying it out.
The Final Environmental Impact Statement (FEIS) was approved for publication in
November 1995. On February 1996, the FTA approved it and issued a Record of
Decision. Shortly thereafter, on March 1996, the DTPW/HTA signed a $307.5 million
Full Funding Grant Agreement with the Federal Transit Administration. This agreement
authorized the Tren Urbano to be included in the U.S. Department of Transportation
budget presented to the congress each year for the next six years. The groundbreaking for
the Phase I alignment was celebrated on August 2, 1996.

DRAFT 2/4/2017 2:32:00 PM 175


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

11.2 PROJECT DESCRIPTION


The Tren Urbano traverses three central municipalities of the San Juan Metropolitan
Area: Bayamón, Guaynabo, and San Juan. About 60% of the alignment passes through
three of San Juan’s most densely populated urban centers: Río Piedras, Hato Rey, and
Santurce (Figure 31 and Figure 32).
The population densities within one-half mile of the alignment range from 10,000 to
20,000 people per mile2. Over 30% of the total regional employment, nearly 150,000
jobs, will be located within a third of a mile of the Phase I corridor. The project was
designed to be 17.2 kilometers in length and have 16 stations, each one 138 meters in
length, capable of servicing six-car trains. Ten stations will be elevated; four will be at or
below grade in an open cut, and two will be underground. The system begins on elevated
track in Bayamón, transitions to at-grade as it leaves the central business district of that
municipality, continues at-grade through Guaynabo and into Río Piedras, descends into a
tunnel section through most of Río Piedras, and finally returns to elevated trackway
through Hato Rey.

Figure 31 - The Tren Urbano Master Plan.

176
TREN URBANO

Figure 32 - Map of Tren Urbano Phase I alignment showing contract segments.

The project includes a maintenance and storage facility in the center of the alignment at
Las Lomas, which will also be the location of the system’s communications and train
control system. Tren Urbano will offer operator-attended automated service via a double-
track fixed guideway. The system will operate 20 hours per day, with vehicles providing
four-minute operating headways during the morning and evening peak hours. Roughly 55
percent of all Tren Urbano riders will arrive at the transit stations via bus or the privately
operated, non-subsidized público minivan service (private microbus public transportation
system). Given the importance of such intermodal transfers, Tren Urbano stations are
being designed to maximize integration of all modes, including pedestrians, públicos,
buses, taxis, and private automobiles. Five of the stations will have park and ride lots and
four will serve as transportation centers where the bus and público routes will be
interconnected with the rail system.
The Puerto Rico Highway and Transportation Authority will purchase 64 transit vehicles
for the Phase I line, with an option for another ten vehicles. The vehicles being built for
Tren Urbano, by Siemens Transportation Systems, are advanced technology stainless
steel heavy rail vehicles equipped with state-of-the-art AC three-phase propulsion
systems and advanced signaling, monitoring, and diagnosis systems. Traction supply will
be 750 V DC third rail, which was selected because it minimizes visual clutter and is less
vulnerable to storm and hurricane damage than overhead wire catenaries. The cars will
run as married pairs with seats for 72 passengers and a design capacity of 180 passengers
per car. Each train will consist of one or more married pairs coupled together, up to a
maximum train length of six cars. These will have a maximum speed in revenue service
of 100 km/hour (60 mph).

DRAFT 2/4/2017 2:32:00 PM 177


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

11.3 PROCUREMENT STRATEGY


The FTA’s Turnkey Demonstration Program is evaluating turnkey and design/build
procurement methods for fixed guideway transit projects. The goal is to determine
whether these alternative procurement strategies can expedite project development,
reduce project costs, and more rationally allocate project risks and rewards between
public transit entities and their private sector partners. The unique turnkey plus
design/build strategy developed for Tren Urbano Phase I has shaved nearly two years off
the project timeline. Tren Urbano is the national model demonstrating how these
alternative approaches to transit system procurement can deliver top quality services and
time saving. To ensure quality control, optimize technology transfer, the participation of
local firms, and accelerate the start of construction, the DTPW divided the Phase I project
into six design/build contracts for civil structures and one System and Test Track
Turnkey (STTT) Contract. The STTT Contract provides for:
• Construction of two stations and 2.6 km of test track, the maintenance and
storage facility, and the operations and control center,
• Delivery of train vehicles and systems,
• Systems integration, and
• System operations and maintenance for a minimum of five years.
As a result of dividing the alignment into segments, the DTPW was able to see
preliminary construction activities get underway in August 1996. By the end of 1997 the
Puerto Rico Highway and Transportation Authority had executed all contracts required
for the design and construction of the Tren Urbano. Table 27 summarizes key data on the
alignment segment and turnkey contracts.
Table 27 - The STTT and Alignment Section Contracts at a Glance

Contract Stations Length Consortium Contract


Facilities Km Value
($ Millions)
STTT Torrimar, Martínez 2.6 Siemens Transit 612.5
Contract Nadal, Maintenance Team
Facility, Operations
Control Center.
Bayamón Bayamón, Deportivo 2.9 Grupo Metro 71.5
San Juan
Río Jardines 1.7 Redondo – 37.9
Bayamón Entrecanales
Centro Las Lomas, San 2.5 Redondo – 74.1
Médico Francisco, Centro Entrecanales
Médico
Villa Cupey 1.9 Redondo – 71.8
Nevárez Entrecanales
Rio Rio Piedras, 1.8 Grupo Kiewit 245.3
Piedras Universidad (KKZ/CMA)
Hato rey Piñero, Domenech, 3.6 Redondo – 125.8
Roosevelt, Hato Rey, Entrecanales
Sagrado Corazón

178
TREN URBANO

A summary of the hybrid delivery methods used in Tren Urbano can be seen Table 28.
Below the table are descriptions of how the Tren Urbano Project uses each of the delivery
methods.
Table 28 - Types of Procurement included in Tren Urbano Hybrid Approach

Types of Procurement Party Also referred to as


1 Turnkey Siemens Transit Team
Turnkey Contractor
2 DBOT (STT)
3 Construction Management
GMAEC Owner’s Consultants
(at no risk)
4 Multiple Primes Alignment Section
Civil Contractors
5 Design-Build Contractors (ASC)

1) Turnkey Contractor. One entity develops and delivers the project to the owner as
one package. Essentially the owner buys the complete project from one
organization. In Tren Urbano, STT is responsible for the complete integrated
project.
2) Design-Build-Operate-Transfer (DBOT). The same entity designs, builds and
operates the project. In Tren Urbano, STT does the design, construction and
operations.
3) Pure or Agency Construction Management (at no risk). The owner holds the
contracts with the designer and contractor(s), but another agency manages the
contracts in behalf of the owner. In the Tren Urbano Project, GMAEC performs
construction management for the owner, but they do not hold contracts with any
of the designers, constructors or operators and therefore are not exposed to any
risk.
4) Multiple Prime Contractors. The owner first hires a designer, and then procures
several contractors. In the Tren Urbano Project, there are seven prime
contractors.
5) Design-Build (DB). The design and construction is procured as one entity and
the construction starts before the design is finished. Often the same entity or
partnership does both design and construction. In the Tren Urbano Project, the
civil contractors perform design together with construction.
The contractual layout of parties in the Tren Urbano Project using this hybrid delivery
method can be seen in Figure 33. It can be seen that the owner, the Tren Urbano Office,
has direct contracts with their consultants, the ASC’s and STT, and STT has no
contractual relationship with the ASC’s.

DRAFT 2/4/2017 2:32:00 PM 179


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Line Legend: Puerto Rican Department of


Solid: Transportation
Management by and Public Works
contract or (PRDTPW)
legislation
Dashed: No
contractual
Relationship, only Puerto Rican Highway and Other Puerto Rican
management Transportation Authority Public Works and
(PRHTA) Authorities

Consultants to
owner Tren Urbano Office
(GMAEC) (TUO)
USA

Siemens Transit
Team
(STT)
German/Other

ASC ASC ASC ASC ASC


ASC
(Redondo- (Redondo- (Redondo- ASC (Entrecanales/ (Redondo/
(ICA-MMSJ)
Entrecanales) Entrecanales) Entrecanales) (KKZ/CMA) Redondo) Perini)
Mexican/Puerto
Puerto Rican/ Puerto Rican/ Puerto Rican/ USA Spanish/Puerto Puerto Rican/
Rican
Spanish Spanish Spanish Rican USA

Figure 33 – Organizational Chart for Tren Urbano

Since the procurement strongly affects the formal and informal relationships between the
parties, it is important to carefully consider its implications.

11.4 CONFLICT MANAGEMENT IN TREN URBANO


Three major items must be mentioned regarding conflict management in Tren Urbano,
the Partnering Implementation, the Change Order Process, and the Dispute Resolution
Contract Language.

11.4.1 PARTNERING

The design-build agreement for each section of the Tren Urbano project states (Rio
Piedras Contract, 1997):
“ To promote the development of effective working relationships among the
Contractor, key Subcontractors, the Authority’s Representative, the Contracting
Officer and the Authority, to promote cooperation and trust, and to achieve
common and individual objectives on a non-confrontational basis, the Authority
encourages the use of Partnering techniques during the course of the Contract.
Within thirty (30) days after the date of execution of the Contract, the parties
shall participate in a partnering workshop. The Contractor’s key on-site staff
and Authority personnel shall follow the initial workshop. Follow-up workshops
will be held periodically as agreed to by the Contractor and the Authority. The
Authority shall be periodically responsible for the expenses of conducting the
initial workshop and any follow-up workshops; provided, however, that each
participant shall be responsible for the cost incurred by the attendance and
participation of its own representatives. Facilitators for partnering workshops
shall be retained through the partnering program of the American Arbitration
Association. The parties will participate in partnering sessions with each other
and with other Project Contractors, as necessary, to facilitate the progress of
the work of the Project Contractors and to resolve disputes.”

180
TREN URBANO

11.4.2 CHANGE ORDER PROCESS

The change order process is used to document, evaluate, negotiate, disposition and issue
change orders in Tren Urbano. The complete change order process is composed of four
major sub-processes – Initial Notice, Contractor Change Request, Authority Change
Request, Change Directive, and Change Order [Rio Piedras Contract, 1997]. For a
Change Order to occur not all of the sub-processes listed may be needed.
The Contractor Change Request process starts with the contractor submitting an Initial
Notice (IN) to the PRHTA/GMAEC that a change order is due (Figure 34). Within 10
days of the IN, the contractor must submit a complete estimate to complete the change
and an updated schedule of the change with documentation of its merit in the form of a
Contractor Change Request (CCR). Usually the CRR is not filed within 10 days and the
contractor, which is usually approved by the PRHTA/GMAEC, files an extension. Now
the Contract Manager together with Technical Services, Project Controls, and the legal
team of the owner (PRHTA/GMAEC) determines whether the CCR has any merit. If the
CCR has no merit, it is returned to the contractor; otherwise the CCR follows the Change
Notice (CN) or Change Directive (CD) process.

Initial Notice
submited by
contractor

10 days

If needed (usually)
request for
extension for
contractor to
submit CCR

Contractor
Contractor may
resubmit Initial No merit
Change
Notice Request
(CCR)

Avoided if possible
signature process
Merit to CCR 2-4 weeks
signature process

Change Notice Change


(CN) Directive

2-6 months
signature process
Difficult and long
negotiation process

Change Order

Figure 34 - Process for Contractor Request for Change (CCR)

DRAFT 2/4/2017 2:32:00 PM 181


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

A CCR becomes a CD if it is determined that the contractor needs to start the work
immediately and the cost, time and technical impact evaluations will be negotiated after
the CD has been issued. This direction is avoided, as the negotiation process later
becomes more complicated and could be more costly for the PRHTA. After the CN or
CD has been approved, a Change Order (CO) must be negotiated and the cost, time and
technical issues must be approved.
The technical issues, cost, and time must be negotiated for both the CN and CD between
the PRHTA/GMAEC and the contractor. Usually the technical issues are quickly
resolved. There seems to be an inclination not to give the contractor schedule extensions
if possible, even it is means increasing payments to the contractor. The cost of the change
is usually what lengthens the negotiation process. On the PRHTA/GMAEC side, the
Contract Manager makes the final recommendation. Final approval occurs during the
signature process.
The signature process referred to is the procedure to obtain the signatures of a list of
project participants who must review and approve the package (Figure 34). The order in
which the signatures are received is not prescribed; however the list can be up to 10
people from the Contract Manager to the Secretary of Transportation. Initially the
Executive Officer (Director of the PRHTA) had the final signature, however in early
1998, the Secretary of Transportation signature became required as well. As the Secretary
has many other projects to oversee, to obtain his signature as well as the Executive
Director’s is a lengthy process. This may add time to an already lengthy process for
gathering signatures, for example a CN often takes 2-6 months to be approved. There the
signature process, as a sub-process of the change order process, can be a bottleneck. Now
the contractors and PRHTA/GMAEC must work together to avoid delays while the
change order is being processed.
When a change order starts, a new negotiation process is beginning. The minimum
number of participants is two: the contractor and the owner (represented by the contract
manager of the section). For practical purposes, the submission of the initial notice (IN)
will be considered the start point of the negotiation (i.e.; the first step). This assumption
may not always be true: the contractor might call the contract manager to inform him of
the situation before an initial notice is filed, or the contract manager might have obtained
information concerning the problem beforehand. Therefore, in most of the cases the
negotiation process starts before the official submission of the IN, because the parties
have been preparing themselves for the negotiation for some time. This “preparation
time” is between two to ten weeks.

11.4.3 DISPUTE RESOLUTION CONTRACT LANGUAGE

Despite delays that may occur, the change order process itself can deal with a given
problem and end up finding a solution. However, the owner is the one that finally
determines if the change order has merit or not. If the contractor does not feel satisfied
with the outcome of the process, he or she may ask for a revision of the decision. If this
happens, it is said that the contractor asserts a claim.
The Design-Build agreement for each section in the Tren Urbano Project has a whole
article dedicated to Claim and Dispute Resolution (Rio Piedras Contract, 1997). It states
the directives the parties shall follow to resolve claims and disputes.
Step Negotiations. If a claim is asserted by the Contractor of the Authority, the matter
shall be placed on the agenda of the next Construction Progress Meeting, and shall be
specifically identified as a Claim:
“…at the Construction Progress Meeting(s) or partnering sessions at which the
Claim is considered, technical personnel of the parties, experienced in the

182
TREN URBANO

discipline involved in the Claim, will endeavor diligently and in good faith to
identify the issues involved, consider impartially the countervailing positions,
and achieve a resolution of the Claim.”
These technical personnel have a maximum time of sixty (60) days to resolve the claim.
After that, the matter will then be submitted to the Contractor’s Project manager and the
Contracting Officer for resolution. If the Contractor’s Project manager and the
Contracting Officer are unable to resolve the matter within ten (10) workdays, either
party may then refer the Claim to the Contractor’s Project Executive and the Executive
Director. These senior executives shall meet within ten (10) workdays of such referral
and shall endeavor to resolve the Claim. If the Contractor’s Project Executive and the
Executive Director are unable to resolve the matter within such ten (10) workday’s
period, the Contracting Officer shall, within ten (10) workdays, issue a written
determination (a “Claim Determination”) to the Contractor describing the Authority’s
position with respect to the Claim. If the Contractor disagrees with a Claim
Determination issued by the Contracting Officer and gives written notice of such
disagreement to the Contracting Officer within ten (10) workdays after the date of the
“Claim Determination”, the Claim shall become a “Dispute”. Therefore, the contract
establishes five negotiation steps the parties shall exhaust before a Claim becomes a
Dispute. Figure 35 shows graphically the negotiation steps as a function of Time.

Dispute
ESCALATION OF CONFLICT

Claim
0 5 10 15 20
Time (weeks)
Figure 35 - Negotiation Steps required by Contract before a Claim becomes a Dispute

According to the Contract:

“At all time during the claim resolution process, the Contractor shall proceed
with the Work diligently, without delay, in accordance with the Contract, shall
otherwise comply with the Contract Documents.”
Dispute Review Board (DRB). In order to continue with the dispute resolution process a
DRB shall be established and shall consist of three members: One DRB member shall be
selected by each of the Authority and the Contractor. They each shall nominate three
individuals for membership to the DRB. Then, the Authority and the Contractor each
shall select one individual from the other’s list of nominees. The time horizon for this
procedure is a month and a half. The third member of the DRB shall be a qualified and
impartial Chairperson, who shall be selected by mutual agreement of the first two

DRAFT 2/4/2017 2:32:00 PM 183


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

members of the DRB within 21 days 3. Therefore, the foundation of the DRB may take
more than two months.
Processing Disputes. Within 45 to 60 days after receipt of a copy of the Contractor’s
request for a meeting and supporting statement, the Authority shall submit to the DRB
and the Contractor (i) the Authority’s response to the dispute, and (ii) any counterclaims
the Authority has relating to the dispute. Within 21 days after receipt of a counterclaim,
the Contractor shall submit to the DRB and the Authority a detailed statement setting
forth each factual and legal defense to the counterclaim. Within seven days after the date
of receipt of the Authority’s answer or the Contractor’s response to the Authority’s
counterclaim, whichever occurs later, the DRB shall set a date for an initial meeting on
the Dispute. Then, within 30 days after the close of the meeting(s) on a Dispute, the DRB
shall issue draft findings and recommendations to the Authority and the Contractor. Each
party shall notify the DRB of a miscalculation or other error in the draft within 14 days,
and the DBR has 14 days, after receipt of the parties’ responses to the draft, to submit its
final findings and recommendations to the Executive Director and the Contractor.
Finally, within 30 days after receipt of the DRB’s final findings and recommendations,
the Executive Director shall issue a written decision either accepting or rejecting the
DRB’s recommendations. Then, the estimated time that requires to process a dispute is
around six months.
Legal Action. Within 90 days after receipt of the Executive Director’s decision, the
Contractor may file a court action seeking a judicial resolution of the Dispute. If the
Contractor does not file suit within such 90-day period, the Executive Director’s decision
shall be final and binding, and any further judicial review shall be barred.
Hence, the contract establishes all the steps that the parties shall pass through in order to
search for a solution before reaching the ultimate step of escalation of conflict: litigation.
These steps give us a time frame for the negotiation: the claim resolution process may
last up to 20 weeks, and the dispute resolution process may last almost 6 months.

11.5 ANALYSIS OF TREN URBANO COMPONENTS


The Tren Urbano case presents many opportunities to discuss the strategy associated with
this project. The following analysis is taken from an imaginary independent consulting
firm. Their recommendations may or may not be in line with what actually happened as
the project progressed. As mentioned before, the analysis is presented to provoke thought
and discussion on the Tren Urbano project. This analysis is not presented to illustrate
either effective or ineffective handling of the project. Keeping this in mind, we ask the
readers to form their own opinions as they progress through the following sections.

11.6 PARTNERING ANALYSIS IN TREN URBANO


Effective partnering in Tren Urbano is very important in order to reap the benefits of its
procurement objectives. Five reasons why partnering is especially needed in Tren
Urbano, and projects like Tren Urbano, are outlined below:
• Enhance the Pros of Duplication
• Form a Unified Management Team
• STTT Contractor’s Fiduciary Relationship With Owner
• Aid non-contractual relationships

184
TREN URBANO

• Improve communication and understanding between the multiple cultures on the


project

11.6.1 ENHANCE THE PROS OF DUPLICATION

The management of Tren Urbano consists of several parties each with their own
objectives, priorities and set of tasks that may at times overlap. Under ineffective
partnering, the management would be inconsistent and competitive. On the other hand,
the different perspectives can provide checks and balances that can be superior to a
traditionally delivered project as the parties with different perspectives and aims can
complete the task more thoroughly. If a team building effort is initiated, overall
duplication of effort could also be minimized, as more information would tend to get
shared. Duplication, however, is not necessarily something to be avoided. The pros and
the cons must be evaluated based on the circumstances to meet the project objectives and
partnering could elicit these situations (Table 29).
Table 29 - Pros and Cons of Duplication

Pros Cons
Better quality check Extra cost and potentially extra time
More parties involved, better end product “All responsible, no one is”
Competition creates motivation Competition can create an adversarial
relationship

The Tren Urbano project aims at very high quality and, thus, chooses to have some tasks
overlap to ensure the highest quality at what is perceived as a small price. It is assumed
that effective partnering will overcome the obstacles of the cons (Section 11.5). These
cons include competitive adversarial relationships and the phenomenon that often
happens when too many entities are responsible for one task: one party assumes others
will be performing the task, the others assume the first party is doing it, so therefore no
one is. Hence, Tren Urbano relies on partnering in accomplishing its objectives, and
effective partnering becomes especially important.
An example of duplication is that Parsons Brinkerhoff (PB), who is part of the Siemens
group, performs much of the management functions in terms of interface between
systems to fixed facilities and interface between fixed facilities. The owner’s consultants,
the GMAEC, also perform schedule and design reviews of the ASCs’ work. Poor
partnering may cause inconsistent comments from the management team to the ASCs,
but with good effective partnering a more complete review can be provided than if only
one party was involved in the review process. Thus, the integration and collaboration
between GMAEC and PB will provide for a superior project.

11.6.2 FORM A UNIFIED MANAGEMENT TEAM

In order for GMAEC and PB to partner effectively, it is required that PRHTA and STT
form a partnering bridge where PB and GMAEC can pass through as seen in Figure 36.

DRAFT 2/4/2017 2:32:00 PM 185


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Partnering
PRHTA Bridge Siemens

GMAEC PB

Figure 36 - Partnering Bridge in Tren Urbano

From this partnering bridge, cross-organizational partnerships can form a unified


management that will improve the organization. This unified management is necessary in
order to create a common management strategy and implementation. This is especially
necessary in Tren Urbano because of the numerous parties involved in various
contractual relationships that must work together on tasks that often overlap. Lack of a
unified management team can cause such things as conflicting directives. Also, it can
lead to further uncertainty in the project, as parties would have less knowledge of other
parties who are not directly in the management chain of command.

11.6.3 STTT CONTRACTOR’S FIDUCIARY RELATIONSHIP WITH OWNER

For a more effective partnership between the owner, STT, and all other members of the
Tren Urbano Project, STT should be perceived as part of the owner’s management team.
This can be accomplished by strengthening the owner representative objectives and
priorities in the STTT contract.
The STTT contract characterizes the objectives and priorities for the STTT contractor in
line with two contrasting viewpoints, as owner representative and as pure contractor. This
occurs because the responsibilities of the STTT contractor include contractual obligations
as well as aligning objectives and interests with the owner (Table 30).
Table 30 Two perceptions of STT

As Owner Representative As Contractor

• Operations and Maintenance for 5-10 • Design and construction of systems


years gives incentives to reduce and vehicles (Major cost component of
lifecycle costs the STTT contract)
• Oversees the ASCs interface with each • Design and Construction of one fixed
other & interface with systems alignment section
• Reviews ASCs’ design & schedule
• Partnering with PRHTA/GMAEC

For instance, the owner’s procurement strategy aim was to give the STTT contractor
incentives to make decisions on the design and construction and to act in the owner’s
interest (i.e., to reduce lifecycle costs), since they will be operating and maintaining the
project for five to ten years. On the other hand, the STTT contractor is responsible to
design and construct one of the civil facility sections and all the systems such as train
vehicles and control systems. These functions give incentives for the owner and the
STTT contractor to have a more traditional owner-contractor relationship.

186
TREN URBANO

It may be questionable whether this dual role is possible or if the perception of STT tends
to lean one-way or the other. Currently, many parties (TUI, 1997-8) actually perceive
STT primarily in a contractor role. This may be because STT does not have a direct input
and a binding mechanism for overseeing the ASCs such as a direct contract with the
ASCs, which could pull STT more in the owner representative direction.
Alternatively, it is important for STT to act more like an owner than a contractor in order
for the objectives and incentives to be aligned for effective partnering. Strong partnering
will give the STTT contractor more authority to perform management functions
effectively. Hence, the benefits of the turnkey contract can be gained as envisioned by the
federal turnkey demonstration project.

11.6.4 AID NON-CONTRACTUAL RELATIONSHIPS

Aside from the important role partnering plays between the owner and STTT contractor,
partnering is equally important in Tren Urbano with the ASCs. ASCs partnering with the
owner can improve costs and schedule. Also, ASC partnering with STT is especially
important because there is no contract between them. If partnering breaks down, the
owner would stand between the various contractors, and the advantages of the turnkey
delivery method would deteriorate.

11.6.5 IMPROVE COMMUNICATION AND UNDERSTANDING BETWEEN THE


MULTI-CULTURES

Tren Urbano is being built in a multi-cultural environment as numerous parties are


brought together by the delivery method. The multi-cultural environment can be viewed
from several angles: multi-ethnical, multi-corporate, and multi-professional. In addition,
Tren Urbano is concurrently in different development phases: planning for the next
alignments, design and construction of Phase I alignment and preparation for operations
and maintenance of Phase I. These multi-cultural and multi-phase categories may
overlap, for example, the contract managers tend to be Puerto Rican and the design
managers tend to be mostly North American. Hence, often the Puerto Rican versus North
American issues are translated into design versus construction issues. This is important
because each culture has its own way of conducting business and when combined with
other cultures, parties may be less at ease, and the working relationship poses additional
challenges.
For instance, a management team, which has worked solely with construction
management, sees the need to cut the design review cycle down to improve the schedule
of a design-build project. This may, however, cause rift with the design managers
because designers consider a shorter deign review cycle as a compromise to the design
quality. Each profession champions their work and may easily overshadow other
professions’ objectives. Likewise, among ethnic cultures, the contract language may be
interpreted differently based on what is common in contractual relationships in the
different home culture leading to many discrepancies and disputes.
These are examples for how the differences in culture can cause strains in the already
complex set of relationships defined by the procurement strategy. Effective partnering
can ease and/or prevent these strains. Effective partnering requires trust in the other
parties; and with cultural differences, the partnering process becomes additionally
challenging. This makes communication and understanding of other participants’
objectives and priorities even more challenging. Effective partnering can improve
communication and understanding needed for a smooth project.

DRAFT 2/4/2017 2:32:00 PM 187


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Partnering has been officially established in Tren Urbano through initial partnering
meetings. Initial meetings include conferences with each contractor separately, all
designers together and a conference with all principals of the project at a Quality Summit
in Oct. 1997. Partnering follow-up monthly meetings have also been held.

11.6.6 INITIAL MEETINGS

Partnering started out very promising with a series of initial meetings. They were held in
a neutral location for 2-3 days for each contract with the owner. A member of the
American Arbitration Association (AAA), an outsider to Tren Urbano, facilitated these
meetings. Risks, concerns, goals, objectives were discussed in small mixed groups. These
meetings fit the criteria for typical good-partnered projects. However, the benefits of
partnering will only hold true if the harder to measure, “soft”, criteria of partnering are
also met. The soft criteria include genuine effort of all parties to developing trusting
relationships. Then, only over time can the effectiveness of these initial meetings be
measured.
A quality summit (TUQS, 1997) was also held in a neutral location (i.e., a hotel) for the
purpose of all parties meeting each other and presenting how they planned to approach
the Tren Urbano Project in terms of quality design, construction and management. The
Tren Urbano Office, not a neutral facilitator, ran the meeting. Observations from this
partnering meeting pointed out different issues that needed attention in the Tren Urbano
Project. For example, the different parties mingled minimally between English-speaking
and Spanish-speaking participants. This could be an indicator that further work needed to
be done in cross-cultural relationships.
Observations from the quality summit also pointed out areas that needed more effort, for
example, the drive and belief in partnering by some of the alignment section contractors.
Observation from this meeting also pointed out that some human infrastructure was still
needed. Design/build/operate projects like Tren Urbano do not have the time to develop
personnel infrastructure like a design-bid-build then operate project because all personnel
is needed in a more compressed time. This becomes an issue, as partnering has to occur
concurrently with personnel being continuously added.
Although this conference was successful in delivering the message that quality was
important to the owner, and how parties intended to approach the project, it did not focus
on partnering issues appropriately. Thus, this meeting only had some factors of an
effective partnering meeting: a neutral location, and some emphasis on how each
organization would approach the project. To be an effective partnering meeting, a third
party should have facilitated the Quality Summit and it should focus on working together
in small groups instead of numerous presentations. Also, there needed to be more
interaction between parties.

11.6.7 FOLLOW-UP MEETINGS

Monthly “partnering” meetings have also been held with all the project principals (TUI,
1997-8). These meetings were a good initiative, but instead of working on the partnering
relationship, these meetings served as a way for the contractors to take a short cut to the
regular issue resolution process bringing their issues to the top management directly
without thorough analysis. The owner’s top management typically ran theses meetings
and other parties presented their status reports. Issues were resolved at these meetings,
but at a micro-management level. Therefore, in an effort to improve these meetings and
keep up the partnering spirit, the meetings are now being reduced to quarterly meetings.
By keeping the meetings several months apart, project participants could not wait until
the next meeting to resolve their issue as if the meetings were monthly. Thus, project

188
TREN URBANO

participants pursued other channels to resolve their issues and the partnering follow-up
meetings then could focus more on partnering relationship issues. Tren Urbano could
further improve these meetings by working on installing good communication processes
throughout the project and increasing the commitment to the partnering process.
All these partnering meetings and initiatives were good initial steps to implement an
effective partnering program. However, as expected, more has to be undertaken to
achieve the greater level of partnering effectiveness because of the additional challenges
of the project in terms of innovative procurement, multi-culture and multi-phase that
creates an environment where continual revision and improvement needs to occur.
Evaluation on Partnering
The evaluation of partnering in Tren Urbano shows that there were areas where good
steps toward partnering were taken such as the initial meetings, but some areas could be
improved upon, for example:
• A clear champion for partnering was not clearly identified in the pre-planning
stage.
• The initial partnering conferences were done well, but more faith and genuine
commitment needed to be elicited in the partnering process.
• Follow-up meetings could be improved if run by a third party.
• The need for and the value of partnering should have been emphasized and
explained better to all project participants.
More initial effort should have been put into the partnering venture. Once some
deterioration of partnering starts, it may become difficult to reverse. Additional meetings
should be hold in informal settings in order to gain better understanding of other parties’
cultures in a relaxed atmosphere. Another major lesson learned was all management
parties should form one united management team, otherwise STT would just be another
prime contractor and not all the benefits could be gained from the turnkey concept.
Partnering should occur at all levels. For example, field inspection occurs separately by
numerous parties. Partnering could help field inspection if teams were formed between
the numerous field inspectors. This could ensure complete inspection in all areas of the
work site whether the site was divided by location or by disciple. Partnering across many
entities can also help form an environment where champions for quality, cost, schedule
and partnering can foster. Champions can help lead a cause but can also create a clearer
and more structured organization. The organization is currently somewhat confusing as is
evident by the different perceptions of the organization chart by different entities. Tren
Urbano also tends to have elements of micro-management, and this creates inefficiencies
in the organization. One reason that micro-management starts could be that when
management foresees many uncertainties they tend to take control of the issues. A
trusting environment needs to be formed where delegation of responsibilities can occur.
The Tren Urbano project has many uncertainties and therefore more follow-up meetings
are needed to redefine the partnering objectives and aims. The partnering process also
needed to be evaluated more carefully earlier in the project to detect any decay of
partnering relationships. Earlier detection of symptoms could have led to a better
recovery. Today, the number of claims is increasing at a high rate and parties are starting
to prepare themselves in case of court battles. Partnering may be a challenge to repair at
this point in time. The partnering environment that still remains should be fostered until
after the construction is complete and until all claims are settled in good faith
negotiations. Then, a final evaluation of the Tren Urbano partnering efforts and results
can be done.

DRAFT 2/4/2017 2:32:00 PM 189


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

11.6.8 GENERAL ANALYSIS OF PARTNERING COMPONENTS

The lessons learned from Tren Urbano can be generalized in order to apply them to any
project, which uses an innovative delivery method in a multi-phase, multi-party, multi-
discipline, multi-culture environment.
The lessons learned could be divided in three categories: initial, operational and resulting
factors. The initial factors define how the remainder of the project will be carried out.
They are set at the beginning of the project, but their impact will not be seen until the end
of the project as they affect other factors. The operational factors occur throughout the
project. They are affected mostly by the initial factors, but can also be improved slightly
upon themselves. The resulting factors are mostly a product of the other factors. So
although, conflicts, quality, schedule and cost of the project are more directly linked to
the resulting factors, the initial and operational factors can have a larger impact than
expected. These factors can all be seen in Table 31 and a brief explanation of each factor
is given below.
Project Factors:
Initial Meetings: Start early with a full partnering initialization. Do whatever it takes,
especially if the delivery system relies on partnering to become effective. A little extra
time or money spent early on partnering may have a large pay-off later. Trust, as the key
ingredient of partnering, must be developed here because it will only be more difficult to
install later.
Education: Use experienced employees if possible, otherwise educate intensively in the
need and benefits of partnering and, of course, at the task at hand.
Numerous Cultures: Cultural differences must be recognized and special seminars with
played out examples of business differences may help parties see the differences before
they are in real situations and their relationship deteriorates.
Delivery Method: An innovative procurement is done to meet special project objectives
and can provide a fresh start for a new improved partnering relationship. But be careful,
there may be special challenges such as non-contractual relationships that need higher
commitment to partnering.

190
TREN URBANO

Table 31 – Summary of Issues/Lessons Learned

Project (Initial) Resulting


Operational Factors
Factors Factors
Partnering
Follow-up Meetings
Commitment
Partnering Claim
Evaluations
Issues Education Management
Knowledge Transfer
Initial Meeting

Turnkey Contractor
Delivery Method
Acting as Part Owner
Turnkey
D/B/O
Micro-
Multiple D/B
Unified Management Management
Construction
Team
Organizational Management
Issues Numerous Cultures
Multi-Phase
Effectiveness of Site Transfer
Multi-Professional
Champions Conflicts
Multi-Ethnic
Multi-Corporate
(uncertainties)
Benefits of Duplication

Operational Factors:
Follow-up Partnering Meetings: Follow-up meetings can prevent the initial trusting
partnering relationship from decaying.
Knowledge Transfer: Partnering can provide open communication for knowledge transfer
that is often needed between various cultures
Evaluations: Evaluate partnering throughout the project. Thus, if there seems to be
skepticism of partnering, this trend can be reversed immediately before becomes too
difficult to reverse. Use more ‘soft’ measures initially such as problem solving methods,
and evaluate ‘hard’ measures such as number of claims when it becomes relevant.
Champions for Objectives: There needs to be clear champions for quality, cost, schedule
and partnering itself. A confusing organization may be a sign that nobody knows who is
in charge of what and when. Party participants need to know who the champions are, and
the champions need adequate authority to be effective.
Benefits of Duplication: The amount of duplication in a particular delivery method must
be evaluated such as extra cost versus greater quality. How should parties with
overlapping tasks work together? Partnering processes must be put in place here to ensure
duplication does not lead to adversarial relationships and “all is responsible, nobody is”
syndrome. If the delivery system is some hybrid of multiple primes with similar tasks,
standardization with enforcement must occur.

DRAFT 2/4/2017 2:32:00 PM 191


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

Unified Management Team: Create a unified management team for highest effectiveness.
Certain relationships may need to be bridged by partnering in order for other entities to
work together effectively. Then partnering can occur at all levels.
Turnkey Contractor Acting as Part Owner: If a contractor is to perform tasks in the
owner’s interests as well as other tasks not as well aligned with the owner’s interests,
partnering can help pull the contractor to act more in the owner’s interest.
Resulting Factors:
Site Transfer Conflicts: Hand-over between contractors may prove to be tricky. If there is
no direct contractual link, the owner should oversee that the hand-over will be done in
good faith; otherwise the owner would have to monitor site hand-over in detail.
Micro-Management: If the owner remains in control, it must spend great number of
resources to oversee contractors in detail. Effective partnering will aid the process to
letting go of control and save on resources. It will also make the owner more confident to
use more innovative contracts for future projects. Trust must be developed so managers
can delegate responsibilities in an uncertain environment and to avoid micro-
management.
Claim Management: Claim management is important to improve costs, and schedule.
Claim management, however, cannot only be improved upon itself; first the factors
throughout the project, operational factors, must be improved upon through effective
partnering in order to greatly improve claim management. The partnering effort must be
emphasized after construction completion and all claims are settled.

11.7 GENERAL ANALYSIS OF CONFLICT RESOLUTION


The following paragraphs show the most important insights learned from the interviews
and a summary of the data collected regarding conflicts in the Rio Piedras Section of the
Tren Urbano.
Insights from the Interviews:
• Conflicts and Disputes are inherent to the construction business and they cannot
be eliminated: The issues described above, such as the competitive environment
associated to the construction industry, are imbedded in the business. Therefore,
the goal is to learn from the conflicts and to escalate lowest possible step in the
“Dispute Resolution Ladder”.
• Owner and Contractor are disagreeing concerning how the project is running:
This is a clear example of how negotiations are interrelated and they cannot be
analyzed individually. The main reason why this disagreement exists is because
each party has completely different point of view of the reality. From the owner
side, this Rio Piedras contract is doing better than the rest. Then, the owner has
the tendency to see this contract as a good one. On the other hand, from the
Contractor point of view, the project is running far below their standards. Then,
they have no reasons to believe that the project is OK.
• Mitigation Actions are most effective if taken early: Managers, based on their
experience, realized how important the early actions are. The general procedures
for partnering implementation described in Section 11.6 emphasize the necessity
of early adoption. Once the competitive atmosphere is embedded in the project it
becomes almost impossible to facilitate and/or enhance communication between
the parties.

192
TREN URBANO

• Manager have a lot of experience regarding conflict management and they feel
pretty confident about their negotiation skills: Project Managers, with more than
20 years of experience are reluctant to accept that they need help to deal with
conflicts. However, the facts show that frequently managers obey their emotions
and act irrationally in negotiation process. A tool that enhances their negotiation
skills might be useful.
• Decision-Makers are not aware of the long term effects of their actions: The
direct cost of a negotiation is always on the table. However, the hidden costs that
can be several times higher are difficult to take into consideration. Hence, the
short-term strategy generally prevailed over the long-term view.

11.8 SUMMARY
As newer and more innovative delivery methods are used in an increasing more global
market, partnering becomes especially important to convey a sense of collaboration to all
parties. Also, an innovative delivery method’s advantage over traditional projects may
ride on the assumption that effective partnering is in place. Therefore, in many projects
special attention should be given to partnering.
In summary, partnering is especially needed in innovative procured, multi-cultural, multi-
phase project. However, partnering can also be especially challenging because of the
numerous other issues that must be resolved that can easily overshadow partnering if
specific attention is not pointed towards partnering. Therefore, partnering has a singular
role in Tren Urbano. It has been implemented in terms of initial meetings with the owner
and each prime contractor and between all designers. A quality summit was also held
with all parties. Subsequently, follow-up partnering meetings have been held with the
principles of all parties involved in the Tren Urbano Project. Harpoth (1999) evaluated
the effect of partnering in Tren Urbano. She concluded that the amount of partnering
effort in the Tren Urbano Project is adequate for traditionally procured projects with few
uncertainties, but it was not enough for the challenge of Tren Urbano. Much greater
partnering effort is needed to receive the benefits of partnering.
Based on the insights received from the interviews and the data collected from the Rio
Piedras Contract, a set of conclusions and recommendations is proposed for the Tren
Urbano Project:
• Contract Language regarding conflict resolution is not the source of problems:
Tren Urbano contract language regarding conflict management includes the-
state-of-the-art dispute resolution techniques used in the construction industry.
The source of conflicts is the disagreement that might exist between the parties,
and this issue cannot be eliminated writing an article in the contract. Hence, the
competitive environment cannot be eliminated through a statement in the
contract.
• Inter-phase conflicts require additional efforts: Because of the characteristics the
Tren Urbano Project has, it is very important to think ahead of the possible
conflict that may arise between the current phase of the projects and its future
phases. For example, the operation and maintenance of following phase can be
awarded to a different entity.

DRAFT 2/4/2017 2:32:00 PM 193


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

11.9 FURTHER DISCUSSION


11.1 Incorporating the knowledge of a delivery systems (Chapter 1), how reasonable
was the procurement strategy of the FTA (Section 11.3)?
11.2 Review the organizational chart (Figure 33). What problems, if any do you see?
Is this structure similar to the LNGT case (Chapter 1)? Compare the successes of
the two projects. What are the major differences?
11.3 What role does each of the participants play in the organizational chart (Figure
33)? Can any roles be eliminated or combined?
11.4 Is the change order process (Section 11.4.2) to complex? Why allot only 10 days
to submit a CCR, when the entire process can take as long as 6 months?
11.5 Which processes in the Six Step DRL (Section 2.3.2) are represented in this
project? Are there any other techniques that were implemented in this project?
11.6 Would such a change order process (Section 11.4.2) work in a small-scale civil
engineering project? If so why? If not, are there any parts of the system that
would?
11.7 What avenues does a contractor have if the owner feels the proposed CN does not
have merit (Section 11.4.3)? Is this a fair process? Relating this to the importance
of a neutral (Chapter 5), should a third party have been included in this stage?
11.8 Keeping in mind the partnering process (Chapter 4), did the partnering process
(Section 11.6) align the interests of the contractors and owners? Who in particular
did the owner target?
11.9 The STTT contract was procured as a turnkey project. How did this affect this
procurement partnering process (Section 11.6.3)? How does this relate to the
typical design-bid-build partnering process (Chapter 4)?
11.10 To what extent did the multi-cultural differences cause conflict? As construction
globalization becomes more frequent, what role will these differences play in the
future? Were these differences handled appropriately in this case?

11.10 REFERENCES

[DTOP, 2000] Puerto Rico’s Department of Transportation and Public Works


home page (http://www.dtop.gov.pr/english/tu/history.htm)
(2000).
[Harpoth, 1999] Harpoth, Nina. Effective Partnering in an Innovative Procured,
Multi-Cultural Project, MS Thesis. MIT Deaprtment of Civil
and Environmental Engineering. 1999.
[Rio Piedras Rio Piedras Design-Build Agreement, Phase I of Tren Urbano,
Contract, 1997] Contract No. AC-500083, Rio Piedras Contract: Alignment
Section 7, Puerto Rico Highways and Transportation Authority.
[TUI, 1997-8] Tren Urbano Interviews with Project Participants, (1997-8).
Tren Urbano Office and Siemens Transit Team Office, San
Juan, Puerto Rico.

194
TREN URBANO

[TUQS, 1997] Tren Urbano Quality Summit, 10/6/97 & 10/7/97, San Juan,
Puerto Rico (1997).

11.11 ENDNOTES

1
The authors would like to acknowledge the help of research assistants Jorge A.
Giampaoli and Nina Harpoth for their contribution to the preparation of this case. Their
research and insights are the basis for the material presented in this case.
2
Prominent members of this group include Fred Salvucci, former Secretary of
Transportation for Massachusetts; Dr. Nigel Wilson and Ken Kruckemeyer of MIT;
Multisystems, Inc.
3
Note that in the Dispute Resolution Process the time is expressed in calendar days rather
than working days.

DRAFT 2/4/2017 2:32:00 PM 195


C H A P T E R

12
SUMMARY
“If your only tool is a hammer, then every problem
will look like a nail. When it comes to construction
industry, the main dispute resolution tool remains
the lawyer, and every disagreement still looks like a
lawsuit.”
(ENR, 2/15/1999)

This book on Dispute Avoidance and Resolution Techniques (DART) for construction
and engineering projects presents how this industry is reacting to the increasing
inefficient use of resources (e.g., monetary, time, and human) associated with the
resolution of disputes using the court system, and for that matter arbitration. More
importantly, it highlights that the industry has begun to realize that conflict is an
important variable in construction. Thus, managing and resolving conflict should be
added as a fourth key aspect to any project, together with Material, Labor, and
Equipment. An effort has to be made to deal with and manage this additional variable
efficiently and effectively. Parties must identify those characteristics that make their own
projects prone to disagreements and implement a DART system in order to prevent them
and/or mitigate their effects. Resources must be assigned to this task just as they are
dedicated to scheduling or cost control. Accordingly, a project that efficiently and
effectively manages its Material, Labor, Equipment, and Conflict will have much better
chances of resulting in a successful venture similar to ones presented within this book.
After the assessment presented in this book, it is clear that the parties in the LNGT
project presented in Case 1.1 failed to manage disagreements and find alternative ways to
resolve disputes. Instead, the Venezuelan SUB, the Italian GC, and the British
DESIGNER simply relied on contract terms to address the problems that developed
during the project execution. Thus, many years after the project was finished, they were
still involved in a large legal battle worth many times the original contract amount.
Arbitration - the only dispute resolution technique included in the contract costed both
parties more than 10% of the original contract value, and the final decision was in the
hands of a third party. Furthermore, proceedings were managed and controlled by an
agency external to both sides, located in a foreign country (i.e., US), who sets time
frames and rules, and controls information exchanges. Direct negotiations to solve the
claims were no longer encouraged, lawyers had taken over the dispute, and there was a
significant amount of uncertainty with regards to the potential outcome, at least in the
Venezuelan side.
The present work argues that the days of waiting until final completion to resolve
disagreements between contractors, design professionals, and owners (like in the LNG
case) are ending regardless of the location, type, or complexity of the project. Parties in
construction and engineering endeavors are realizing the benefits of assuming a proactive
role in dealing with conflicts and disputes. Parties are developing prevention techniques
that foster an equitable allocation of risk, communication, improved contracts, and
information flow addressing the basic characteristics of the industry that make it prone to
disagreements. Court systems have witnessed a trend towards new methods that help
overcome the difficulties of pre-trial hearings and motions during litigation. So, even

196
SUMMARY

when litigation is underway, the industry and the courts have produced innovative
practices (i.e., Court-Annexed Procedures) that can reduce the negative effects of legal
actions (e.g., cost, time, resources, and broken relationships). Parties have seen their roles
evolve from passivity and reaction to a dynamic, proactive attitude in the pursuit of
dispute avoidance and resolution. The benefits of this new approach (e.g., early
identification of problems, control over outcome, cost savings, and maintenance of
relationships) far outweigh the ones of the practice of waiting until the project is
completed.
The industry has made significant progress over the past decade in developing strategies
and techniques to curb the adversarial attitude that had become a standard in most
engineering and construction projects. Partnering and alternative dispute resolution
methods, such as structured negotiations, mediation, Med-Arb, mini-trials, and dispute
review boards have all become part of the industry. The use of these techniques has been
pivotal for parties to anticipate potential disagreements and has revolutionized the
traditionally defensive approach of the two-step Dispute Resolution Ladder reviewed in
Chapter 2.
This ‘quiet revolution’ (Stipanowich, 1996) in dispute resolution has changed the whole
scene of conflict in construction. The movement has placed emphasis on effective
communication, informality, win/win approaches, and conflict avoidance, overturning the
path of formalizing each process and legalizing design, relationships, information
disclosure, and even problem solving. This confirms Treacy’s (1995) point that the
industry is returning to “the old fashion way of doing business.”
Once understood that there is no unique formula to prevent or discourage disputes, the
attractiveness of DART and every dispute prevention or resolution system is that they can
be tailored to meet the specific needs and individual job characteristics of a given project
and a given building team. This flexibility is invaluable for the construction industry,
where each project is a new experience with new variables and different conditions.
Parties can customize procedures and rules to what they consider the weak aspects of the
project, helping to mitigate potential problems not covered in contract documents. The
six-step Dispute Resolution Ladder (DRL) is the most appropriate model to base and
design project actions based on specific project needs. However, this does not mean that
every project requires a six-step DRL. As it was shown in the example of the Hong Kong
Chek Lap Kok airport (Section 2.2.3), projects can have a three or a four-step DRL to
facilitate the resolution process, and they can even choose to have more than one DRL,
based on contract size, disputed amount, type, or source of disagreement.
Among the different stages of the DRL, this book considers the prevention stage as an
important asset which offers the greatest flexibility to the project, in terms of designing
and incorporating dispute avoidance and resolution techniques. Once disagreements are a
fact, Negotiation (Stage 2, Chapter 5) is identified as the most effective method to resolve
disputes in terms of time, costs, satisfaction, and minimization of further disputes,
communication, and enhancement of job relationships. Given the definite move away
from the adversarial approaches towards conflict avoidance and resolution, negotiation
will certainly become the primary tool to deal with disagreements. The fact that
Mediation, a form of facilitated negotiation, is becoming a highly favorable approach
within the industry, confirms this conclusion.
Just as Negotiation and Mediation, this book concludes that the most efficient and
effective ADR approaches utilize non-binding procedures, like Conciliation or Minitrials.
These procedures are reinforced by the incorporation of a neutral third party that
facilitates communication and/or helps resolve technical issues that might be part of the
dispute. The Second, Third and Fourth stages of the DRL are the key sets of techniques
available to avoid arbitration or litigation. Although these non-binding techniques might
fail to result in a 100% resolution of the dispute, partial settlements are also important in

DRAFT 2/4/2017 2:32:00 PM 197


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

mitigating the costs and time impacts. Furthermore, communication during these phases
can help clarify issues and might open the door to new solutions that might have been
overlooked during initial negotiations. The more adversarial approaches, Arbitration and
Litigation, are ranked last, and considered the most expensive and least efficient in the
DRL. The changes in the American Arbitration Association’ s (AAA) Construction
Arbitration Rules to make the procedure more flexible and efficient, together with the
emergence of binding techniques like Med-Arb and Shadow Mediation, support this
movement away from binding adjudicative procedures.
Another important finding of this assessment relates to the role owners (i.e., agencies,
private developers, and corporations) must play in the process of incorporating DART in
the construction process. It was demonstrated that owners must expect disagreements
during the construction process and should be prepared to manage and resolve them
before they become disputes. Owners’ participation in dispute prevention is critical. Also,
their role acquires relevance in areas like risk assessment and allocation, preparation of
documents, dispute resolution clauses, and cost and schedule control during all phases of
construction. Contract specifications reviewed as part of this book provide examples as to
this new role assigned to the owners (e.g., FIDIC, World Bank, CCDC, and Prevention
Stage).

12.1 INTERNATIONAL DART USE AND APPLICATIONS


Regarding the international scenario, DART is receiving increasing attention worldwide.
Examples presented in this book ranged from prevention techniques like risk sharing in a
tunneling project in Canada to mediation and conciliation experiences in Hong Kong, to
the introduction of the ‘adjudicator’ figure in the British legal system for construction
disputes to expedite resolution of conflict. As an additional illustration of this exploding
awareness, the AAA now has expanded beyond US borders to provide ADR services
throughout the globe. As of May 1999, 53 arbitration and mediation agreements have
been reached between the AAA and ADR institutions in other countries (see Appendix
A). The organization now arranges training for arbitrators and mediators, and claims to
have been instrumental in promoting the spread of ADR, helping other countries develop
national arbitration acts and ADR organizations.
The international activities of the AAA, and the growth it has experienced in its foreign
caseload support some interesting conclusions:
• Although Arbitration remains the primary dispute resolution technique utilized
throughout the world, Alternative Dispute Resolution has achieved worldwide
recognition and it is being used more and more by the business community to
solve disputes without litigation.
• The inclusion of mediation together with arbitration as the primary ADR
services offered by the AAA, confirms the shift towards non-binding procedures
for dispute resolution worldwide.
• Agreements of cooperation and collaboration are creating an international
standard for ADR, and at the same time a network of organizations that will
allow a faster and a more effective resolution of disputes and dissemination of
new ADR techniques as they are developed.
• Collaboration between these organizations should encourage international
corporations to continue solving their disputes through the implementation of
DART.

198
SUMMARY

Also in the international arena, this book presents how cultural and market conditions can
affect the type of dispute mechanism preferred by constructors and owners in different
countries. The Netherlands’ case (i.e., Frame Contract) shows how a pragmatic culture
and an organized market discourage parties from engaging in adversarial relationships,
letting them rely on trust to guarantee long-term commitments. Countries have favored
certain types of ADR over others, as in the case of the Asian nations that have
incorporated mediation and conciliation in their standard DRL before more adjudicative
procedures. In Japan and Hong Kong, this book identified direct implementations of
mediation in government agencies that can relate to the cultural background and
traditions of ‘harmony’ and compromise. In the UK, more adversarial approaches such as
adjudication have been incorporated into law and are expected to gain more adepts, while
mediation has only recently become a recognized technique to resolve construction
disputes.
Ultimately, many of the problems associated with construction disputes are not limited to
particular geographic location or cultures. Disputes emerge whether the project is
conducted in New Jersey, Calcutta, or the Caribbean, and the ‘pandemic’ nature of
conflict in construction must be acknowledged, for one to properly manage it. Cultural
differences will have a bearing as to the DRL to use, but the nature of the project and the
participants will define the most appropriate system to use. For example, projects where
parties come from different cultural backgrounds, including different languages, most
address and foster from the beginning clear and continuous communication to reduce
problems. Facilitated negotiations with third party neutrals that are familiar with these
backgrounds will help overcome ‘people issues’ which can grow from this diversity.

12.2 AREAS OF FURTHER EXPLORATION IN DART


This section is directed to students and researchers as areas to pursue to gather more in
depth information in the subject. The following areas of further research and exploration
are recommended based on the findings of this work:
• Review how the changes in the Construction Arbitration Rules of the AAA have
affected the procedures and what the response of the industry has been to these
revisions.
• Incorporation of new communication technologies into conflict management and
dispute resolution systems. New methods of dispute resolution are more and
more based on methods of communication between parties and third-party
intermediaries. With the advent of the Internet as a revolutionary
communication channel, further research will need to shed light into the effects
this new tool will have in the future deployment of ADR.
• In-depth review of international applications of DART in construction projects
through the rules, conditions and experiences of ADR associations throughout
the world, focusing on non-binding procedures like mediation and conciliation,
to provide further understandings as to how culture and background can affect
the implementation of these techniques.
• Throughout the review of the literature, the authors found a significant large
quantity of applications of alternative dispute resolution in fields other than
construction. A review of these applications in Health, Labor, Insurance, and
Sports might provide insight as to other techniques that might be applicable to
construction.
• Little information on partnering experiences was found beyond the US, Canada
and the UK. More research could shed light as to the reasons behind this

DRAFT 2/4/2017 2:32:00 PM 199


INTRODUCTION TO CONSTRUCTION DISPUTE RESOLUTION

apparent lack of interest towards this project philosophy in other parts of the
world. New barriers on the implementation of partnering could be identified.
• How the increasing use of mediation as a DART will affect the flexibility and
reduce the advantages it has over more binding approaches, such as: Arbitration.
The increasing use of this technique might lead to a formalization that could
hamper the advantages it currently holds.
• By defining the key characteristics and relationships in the most common
delivery systems (e.g., Design-Bid-Build, Design-Build, and Build-Operate-
Transfer) and the weaknesses of each one, specific dispute avoidance and
resolution systems can be designed and proposed as basis for each type of
project.
• Because third-party interventions appear to be among the key features of ADR
in construction, training programs should be developed to guarantee a level of
professionalism and to provide these agents with the necessary tools to address
and help resolve construction conflicts.
As a final note, it is important to understand that the Construction Dispute Avoidance and
Resolution Techniques as described in this book will likely change and evolve as new
methodologies are designed and successfully implemented; as new research uncovers
techniques already in use, but not reported, and as technology and innovation in
communications open the door to more collaborative environments of operation. The fact
that researchers are not able to replicate the construction process in order to study
different techniques, similar to manufacturing, adds to the need for creativity and
improvement of methods for each project. However, the following principles remain the
same:
• Adversarial approaches can lead to excessive inefficient waste of resources and
lost relationships.
• The industry has developed a significant quantity of techniques that are
alternatives to litigation for the resolution of construction disputes.
• Prevention of disputes is far more efficient than trying to resolve them.
• The nature of construction conflicts and disputes requires flexibility.
• Third party intervention to promote communication and/or resolve technical
issues address common sources of conflict in construction and therefore can be
highly effective.
• Creativity should take precedence over a prescribed list of accepted procedures.
Parties must learn about what techniques are available and choose and modify
those that best fit their needs.
In conclusion, in the past decade, dispute resolution in the construction industry has
evolved from private adjudication (i.e., arbitration) to voluntary techniques and
approaches based on communication and collaboration, aimed primarily at avoiding open
conflict and allowing the parties to develop a mutually agreeable settlement. This
evolution is common to the construction industries of a number of countries. No longer is
the only dispute resolution tool a lawyer. In fact, many DART still make use of this agent
(i.e., Minitrial and Settlement Conferences), but in a non-adversarial environment that
fosters the resolution of disputes faster, cheaper and without straining the relationships to
the point where no further work together is possible.

200
Mediation/Arbitrati
Voluntary
Mini-trial
Fact-Based
Advisory
Owner/Agency
Facilitated
Structured
Training
Dispute
Sub-Contractor
Right
Forward-Price
As-Build
Joint
Certified
Constructability
Competent
Superior
Subjective
Cost/Schedule
“Bridging”
Delivery
PEpC
Negotiated
Escrow
Third
Equitable
Geotechnical
Economic
Statement
Project
of
Party
Delivery
Technique
Summary Bid
Review
Resolution
Refusal
and
Time-
NON-BINDING
ARBITRATION
Quotations
Schedule
and
Incentive
Project
A+B
Step
Category Payroll
Schedule
Conciliation
On-Call
Mediation
STANDING
NEUTRAL
Neutral
NEGOTIATION
PREVENTION
Partnering
Cost
Control Risk
or
Price
the and
Documentation
Negotiations
and
Bidding
Award
Advisor
Contractor
Schedule
Audits
Programs
Jury
and on
Trial
Settlement
Arbitration
Negotiations/Meeti
Payment
Equipment
Management
Determination
Compressed
Baseline Report
on (Med./Arb.)
Executive
Mediation
Board
Review
Negotiations
Development
Clauses
Change-Order
Change
Scheduling
Submittal
Analysis
Engineering
Incentive
Design-Build
Mechanism
System
Documents
Beneficiary
Sharing
Adjustment and
(Non-
Orders
Boards
Matrix
Trial of
Clause
Gap
Cost
Conference
Binding
ngs
Requirements
Labor
Allowance
Fee
Process
(GBR) Pricing (Rent-
a-Judge)
Arbitration)
SUMMARY

12.3 REFERENCES

[ENR, 2/15/1999] Engineering News Record. Lightening up Litigiousness.


McGraw-Hill, New York. Vol.242 (7) p. 68 February 15, 1999.
[Stipanowich, 1996] Stipanowich, Thomas J., (1996). Arbitration: Innovation and
Evolution in the United States Construction Industry. Wake
Forest Law Review Vol. 31 (1) pp. 65-182. Spring
[Treacy, 1995] Treacy, Thomas B., (1995). Use of ADR in the Construction
Industry. Journal of Management in Engineering Vol. 11 (1) pp.
58-63. January/February, 1995.

DRAFT 2/4/2017 2:32:00 PM 201

You might also like