The second feature due to the length of the barrette piles is that the cages are necessarily
prefabricated in 5 sections, which must be assembled directly in the excavation. Each
segment is held from the top by means of horizontal tubes slipped through the loops. A
second section may then be coupled to the first. The auscultation tubes are nested and
welded. The coating of steel is provided through cable ties. Before each run, concrete
spacers pads are in placed to ensure the concrete cover of 7cm. The elements are coupled
and then step by step down. The last section of the reinforcement cage does not play
structural role but simply serves as hanger. Indeed, the barette piles are not made from the
raft level but from the natural terrain at 32NVP. The last section cage will therefore be torn
during the general excavations.
Finally a concrete column is slided down, in the barrette pile, section by section to the bottom
of the excavation, and we proceed to the concreting from the bottom, through mixer trucks.
During the excavation, the part of the concrete barrette pile that is above raft level is
demolished