Mining Area - Plant & Infrastructure Mining Area Hndling Plant

The document outlines a work breakdown structure for a mining area project with multiple levels and areas including: mining area handling plant, coal receival and storage, primary and secondary crushing, stacking and reclaiming, sampling, load out, services distribution, infrastructure, temporary facilities, and EPCM. It breaks the project into areas, units, and sub-units with codes to track each element of work.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
440 views7 pages

Mining Area - Plant & Infrastructure Mining Area Hndling Plant

The document outlines a work breakdown structure for a mining area project with multiple levels and areas including: mining area handling plant, coal receival and storage, primary and secondary crushing, stacking and reclaiming, sampling, load out, services distribution, infrastructure, temporary facilities, and EPCM. It breaks the project into areas, units, and sub-units with codes to track each element of work.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

LEVEL 1 PRIME AREA

2 AREA
3 Unit
4 Sub Unit
3000 Mining Area - Plant & Infrastructure
3100 Mining Area Hndling Plant
3110
Mining Area - Handling Plant
OHP Site Development
3111 Bulk Earthworks
3112 OHP Internal Roadworks
3113 Drainage
3114 Creek Diversion
3120 Coal Receival & Storage
3121 Reinforced Earth Wall & ROM Base E/Wks
3122 ROM Bin
3130 Primary Crushing
3131 General Facilities & Building
3132 Equipment Chutework
3133 Mechanical Equipment
3140 Scalping & Product Screening
3141 General Facilities & Building
3142 Equipment Chutework
3143 Mechanical Equipment
3144 Conveyor - Primary Crusher Product MC01
3145 Conveyor - Product Screening Feed MC05
3146 Conveyor - Dust Collector Discharge
3147 Conveyor - Dust Transfer
3148 Dust Extraction Structure
3150 Secondary Crushing
3151 General Facilities & Building
3152 Equipment Chutework
3153 Mechanical Equipment
3154 Conveyor - Secondary Crushering Feed
3155 Conveyor - Secondary Crusher Feed
3156 Conveyor - Middlings Recycle
3157 Transfer Station
3160 Stacking / Reclaiming
3161 Conveyor - Fines Product MC07
3162 Conveyor - Fines Yard MC08
3163 Stacker, Fines
3164 Conveyor - Lump Product MC10
3165 Transfer Station TS 7/8
3166 Conveyor - Lump Yard MC11
3167 Stacker, Lump
3168 Reclaimer
3169 Conveyor - Product Reclaim MC14
3170 Sampling
3171 General Facilities & Building
3172 Equipment Chutework
3173 Mechanical Equipment
3174 Sample Preparation
3180 3175 Assay Laboratory
3176 Transfer Station TS 10/11
Train Loadout
3181 General Facilities
3182 Transfer Station TS 14/15
3200 3183 Conveyor - Load Out MC15
3210 3184 Train Loadout Bin & Chute
Mining Area C - OHP Services Distribution
3210 Electrical & Control Systems
3211 Process Control System
3212 Plant Process Control Room
3213 Plant Electrical Distribution
3214 Power Supply to Bores & Village
3215 Plant Substation
3220 3216 Crushing Substation
3217 Train Loadout Substation
13 3220 General Services
3221 Sewerage Treatment Plant & Reticulation
Page 1 of 3

A C - Area/Units
LEVEL 1 ATTACHMENT i
2
Prime Area
Area Rev E
3 Unit
4 Sub-Unit
3300 3222 Water / Fire Services
3310 3223 Compressed Air
Mining Area C - Infrastructure
3310 Access Roads
3311 GNH to Perm Accom Intersection (Upgrade)
3312 Perm Accommodation to Mine Site
3320 3313 Mine Access Rd to AM Nitrate Facility
3314 GNH to Airstrip
3320 Administration / Workshop Complex
3321 Admin / Training / Emerg Services
3322 Workshops / Warehouse & Equipment
3330 3323 Tyre handling Facility
3324 Vehicles Washdown Facility
3330 HV Power Generation & Distribution
3331 HV O/H Line Subcontract
3340 Bulk Commodities & Fuel Storage
3341 HV/LV Fuel Storage & Dispensing
3350 Water Supply & Distribution
3351 Borefield - Mine Site
3352 Storage & Pumping - Mine Site
3353 Water Supply - Accommodation Village
3360 Accomodation Village
3361 Site Development / Drainage / Roads
3362 Village Complex
3370 Airstrip
3371 Airstrip
3372 Shelter / Ammenities / Carpark
3380 Communications
3381 Fibre Optic System (Telstra Interface)
3382 Communications
3600 3390 Mobile Equipment
3391 Mobile Equipment
Mining Area C - Temporary Facilities
3610 Temporary Structures
3611 Site Buildings & Facilities
3612 Site Office Infrastructure
3613 Site Office Computers, Equipment & Furniture
3620 Temporary Services / Utilities
3621 Communications / Phone / Fax / Courier
3622 Power Supply
3623 Water Supply
3624 Fuel Supply & Facilities
3625 Office Supplies & Reproduction
3626 Site Security Services
3627 Paramedical Services
3628 Office Cleaning & Maintenance
3629 Road Maintenance / Temporary Access Roads
3630 Temporary Minor Equipment
3631 Vehicles
3632 Plant Hire
3633 Inspection / Test Equipment
3640 Construction Village
3641 Village - Capital / Hire
3642 Village - Operation & Maintenance
3643 Village - Recoveries
3650 Contractors Mob & Demob
3651 Mobilisation
3652 Demobilisation
3660 Bulk Material Plant Establishment
3661 Batch Plant
3670 Miscellaneous
3700 3671 Safety Signage
3672 Safety Equipment
Mining Area C - EPCM
3710 Labour
Page 2 of 3

- Area/Units
VEL Prime Area
2 ATTACHMEI
3
4 Area Rev E
3711 Unit
3712 Sub-Unit
3713 Home Office Engineering & Drafting
3714 Home Office Management & Services
3715 Construction Management
3720 Commissioning
3721 HO Engineering Construction Support
3722 External Consultants
3730 Sub-Conultants - Home Office
3731 Sub-Conultants - Site
3732 Home Office Reimbursable Expenses at Cost
3733 Business Travel & Accommodation
3734 Insurances
3735 Licences, Permits & Government Charges
3736 Project Related Air Freight
3737 External Printing & Photocopying
3738 Overseas Project Related Telephone Calls
3740 Other Misc. Office Operating Expenses
3741 spare
3742 Home Office Reimbursable Expenses at Rates
3743 General Office Running Expenses
3744 Office Hire, Fitout & Outgoings
3745 General Computers
3746 CAD
3747 InRoads/PDS
3748 spare
3749 spare
3750 spare
3751 Lump Sum - Expenses
3752 Site Office Expenses
3753 General Office Costs (Stationary, Consumables)
3754 Office Equipment incl. Computers
3755 Travel & Accommodation
3756 Site Accommodation Costs & FBT
3757 Safety Supplies, Consumables & Awards
3758 Communication Eqpt & Charges
3759 Postage & Courier
3790 Photography & Videos
3791 Relocation, & Other Misc Expenses
3792 Overheads / Fee / Incentives
3793 Corporate Overheads
3794 Fee
3795 HSEC Incentive
3799 Schedule Incentive
3800 Capital Cost Incentive
3810 Advance Payments
3811 Mining Area Indirects
3812 Spares
3820 Start-Up & Consumable Spares
3821 Capital Spares
1822 Commissioning & Vendor Support
3900 Testing & Commissioning Support
3910 Vendor Representatives & Support
3911 Estimate Contingency
JEngineer's Contingency
Engineer's Contingency
113/091
Rey