Frame 5 Schedule

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

DISMANTLING OF GT GE Frame 5

S.No Activities involved Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20


1 Isolation of system
2 Gate pass & Safety induction
3 Issuance of PTW
4 Dismantle CO2 system
5 Dismantle Fuel Oil system
6 Support in oil and diesel draining
and transfering to Gully sucker
7 Dismantle the filter house

8 Dismantle the air inlet duct and


elbow
9 Dismantle the stack

10
Dismantle local control compartment
11 Dismantle cooling tower & piping
12 Dismantle accessory compartment as
one unit

Remove necessary piping


13 instrumentation and electrical to the
turbine compartment
14 Dismantle gas turbine as one unit
15 Decouple load gear with Turbine
16 Disconnect all electrical connection to
generator
17 Disconnect Cooling system to
generator
18 Remove Generator as one unit
19 Remove all connections to MCC
20 Remove MCC Compartment
21 Remove all pipework, I beam etc.