Concrete Bridge Designer S Manual
Concrete Bridge Designer S Manual
Concrete Bridge Designer S Manual
com
Concrete Bridge Designer’s Manual
i
www.EngineeringBooksPdf.com
www.EngineeringBooksPdf.com
Concrete
Bridge
Designer’s
Manual
E.Pennells
A Viewpoint Publication
iii
www.EngineeringBooksPdf.com
Frontispiece: Tarr Steps, Devon
Viewpoint Publications
Books published in the Viewpoint Publications series deal with all
practical aspects of concrete, concrete technology and allied subjects in
relation to civil and structural engineering, building and architecture.
iv
www.EngineeringBooksPdf.com
Preface
This book has grown from the need for a series of design guides for use in a
bridge design office. Its purpose is to help an engineer coping with the day to
day tasks of design, and to bring together in one volume some of the
information he needs to have close to hand.
Ideas have been collected from a wide range of sources and the author
acknowledges the contribution of numerous colleagues, particularly those at
E.W.H.Gifford and Partners.
Ernest Pennells first became involved in bridge design during the reconstruction
of numerous small railway overbridges to accommodate overhead
electrification of the London-Liverpool railway line.
His initial training with Contractors, and subsequent experience with Local
Authorities as well as Consulting Engineers, covered a diversity of types of
work: highways, buildings, heavy industrial construction and water-retaining
structures. But bridges became the dominant factor in the development of his
career.
In 1967 Mr. Pennells joined E.W.H.Gifford and Partners. He was their Resident
Engineer for the Braidley Road and Bourne Avenue bridges at Bournemouth,
which gained a Civic Trust Award, and commendation in Concrete Society
Awards. This was followed by a short tour in Chile representing the interests
of the practice. He was subsequently made
an Associate of the practice and became
responsible for several of their bridgeworks
contracts through all stages of design and
construction.
v
www.EngineeringBooksPdf.com
www.EngineeringBooksPdf.com
Contents
Merits of various forms of construction for piers, abutments Introductory note on other available methods.
and bank seats.
vii
www.EngineeringBooksPdf.com
Data sheets and illustrations
viii
www.EngineeringBooksPdf.com
60 Anchor blocks for external cables 91 Figures
61 Strand anchorages 92–93
CCL Systems Ltd Frontispiece Tarr Steps
PSC Equipment Ltd 1 Deck layout drawings 2
Stressed Concrete Designs E.W.H.Gifford and Partners
Losinger Systems 2 Bourne Avenue Bridge, Bournemouth 4
Simon BBRV E.W.H.Gifford and Partners
62 Strand anchorage forces 94 3 Layout of prestressing cables 5
63 Wire anchorages 95 4 Box construction applied to Calder Bridge 6
PSC Equipment Ltd E.W.H.Gifford and Partners
Simon BBRV 5 Interior of box deck under construction 7
64 Strand couplers 96 E.W.H.Gifford and Partners
E.W.H.Gifford and Partners 6 Precast beam-and-slab construction 8
CCL Systems Ltd 7 Precast construction applied to box-section deck 9
PSC Equipment Ltd 8 Controlled impact test
Losinger Systems British Steel Corporation
65 Shear in prestressed concrete 97 9 Mechanical splicing of reinforcement by swaging 64
66 Interface shear BE2/73 98 CCL Systems Ltd
67 Ultimate moments 99 10 Equipment for grouting 80
68 Prestressing ducts and saddles 100–101 PSC Equipment Ltd
PSC Equipment Ltd 11 Relationship between creep and time 82
E.W.H.Gifford and Partners 12 Temple of Bacchus 107
69 Differential shrinkage 102 13 Braidley Road Bridge, Bournemouth 108
70 Strand 103 E.W.H.Gifford and Partners
Bridon Wire 14 Precast concrete track for experimental tracked
71 Strand relaxation 104 hovercraft
Bridon Wire E.W.H.Gifford and Partners 109
72 Prestressed concrete references 105 15 Erecting beam for hovercraft track 110
73 Grillage force system 116 E.W.H.Gifford and Partners
74 Grillage analogy 117–118 16 Concrete cube results 122
75 Grillage interpretation 119 17 Plate pier design 123
76 Structural analysis references 120 18 Continuous beam 124
77 Trends in deck costs 133 19 Bending schedules 125
78 Economic span 134 20 Grillage 126
79 Economic depth—voided slab 135 21 Prestressing calculations 127
80 Abutments 136 22 Tender comparison
81 Hollow abutment 137 23 Comparison of equivalent concrete thickness of 131
82 Contract documents 140 decks bridge
83 Resident Engineer 146 24 Specimen rate for providing and installing 131
84 Section Resident Engineer 147 prestressing cable
85 Assistant Resident Engineer 148 25 Falsework for bridge deck 142
86 Inspectors 149 E.W.H.Gifford and Partners
87 Site meetings 150
88 Contract supervision references 151
ix
www.EngineeringBooksPdf.com
CHAPTER 1
The simplest form of bridge deck is a reinforced concrete Other methods of void forming have been tried, with
slab. It is, of course, only economic for short spans, and varying degrees of success. Formers have been built with
where such a slab is employed it is often connected timber frames overlain by tough cardboard, but the ability
monolithically with the abutment walls, forming part of of this type of former to maintain its shape after prolonged
a box or portal section. This arrangement leads to the exposure on a construction site is arguable.
more efficient utilization of the structure where the Any void former requires very secure fixing to prevent
proportions of height to span are favourable. flotation during concreting. The flotation force can be
Slabs play a part in many other forms of construction, substantial—even more so when combined with the
and where a slab is spanning between open spaced beams vibration used to compact the concrete. Fixing the void
or adjoining webs in a box deck which are spaced at to the reinforcement cage is not a wise procedure—some
intervals approximating to the width of a traffic lane, the engineers have suffered the embarrassment of having their
slab thickness will usually be 200mm (8in.), or reinforcement float with the void formers!
thereabouts. Assuming that the thickness has been kept Although there is no compulsion to use a cylindrical void,
to a modest dimension to suit the span, continuous and other shapes could be exploited to advantage in some
support is usually provided for solid slabs because they circumstances, the circle does allow the concrete to flow
have a limited capacity to span transversely between easily underneath the void. Any attempt to employ a wide
isolated bearings, and a simple rubber strip bearing is flat void could be disastrous for the concrete finish on the
adequate to cater for the small movements involved. soffit. The choice of dimensions for the spacing and depth
The thinnest possible slab is not necessarily the most of voids must make due allowance for the practicalities of
economic. It is worth investigating the relative costs of concreting, particularly when bearing in mind the space
concrete and reinforcement with various thicknesses of occupied by prestressing tendons, where they form part of
slab. Fluctuations in the costs of concrete and the deck construction. Due allowance for practical tolerances
reinforcement make it impossible to state a universal rule in construction should also be taken into account. For
for this, and the question is discussed further in the chapter reinforced concrete construction the recommended minimum
on economics. dimension for the concrete thickness above and below a
Once the depth of a cast-in-situ concrete deck slab circular void is 150mm (6in.), but for prestressed concrete
exceeds about 700mm or 28in., it becomes practical to construction this might be reduced to 125mm (5in.). Voids
introduce voids, thereby reducing the self weight and of other shapes require increased thicknesses. The spaces
material content of the deck. Various types of void former between voids should be not less than 200mm (8in.).
have been used. Spirally wound sheet metal was an early The saving achieved by introducing voids stems from
type. It has been known for voids to become full of water the reduction in self-weight. Forming the void is likely to
during construction, and the possibility of this taking place cost a similar amount to the actual concrete replaced, so
in a permanent structure cannot be overruled entirely even the resulting saving in materials consists of a saving of
if drainage holes are provided. This could result in reinforcement, which is reduced because the load due to
significant overstressing of the deck. With spirally-wound self weight is lower. In prestressed concrete the prestress
metal sheet it is only possible to produce a cylindrical required is further reduced as a result of the diminished
void so that, where it is necessary to change shapes, it area requiring precompression.
becomes essential to utilize an alternative material to form Other benefits arise from voided slab construction. It
the special shape required. becomes possible to introduce strong transverse diaphragms
The use of expanded polystyrene overcomes the within the depth of the deck, simply by stopping-off voids.
potential objection of water filling the void, since the Costs are also less sensitive to increases in depth than is
material consists of a series of small closed cells, resulting the case with solid construction, so that it becomes more
in very low porosity compared to the total volume attractive to vary the shape of the overall cross-section of
involved. The material has the further advantage of being a deck, introducing transverse cantilevers at the edges. This
readily cut, either by using a hot wire in the factory or, on not only gives economic benefits but also improves the
site, simply a hand saw. The latter may not give the appearance of a structure by lightening the edge and giving
smoothest result but is effective enough. an interesting profile to the soffit.
1
www.EngineeringBooksPdf.com
2
www.EngineeringBooksPdf.com
Figure 1 . Deck layout drawing.
In a wide bridge it is also worth while breaking up the necessary to accommodate suitable anchorages can
deck into a series of broad “spine” beams of voided slab impose restrictions on the eccentricity that can be achieved
construction, introducing linking slabs spanning at pier positions. If the construction joints for the span-
transversely to provide a connection between them and to-span connections are provided adjacent to the pier, the
to form a continuous deck surface. In addition to its affect prestressing anchorages force the cables down into the
on the appearance this arrangement introduces benefits deck to a lower level than that required by the cables
in construction. There are difficulties in building wide themselves, in order to achieve the necessary edge
decks, particularly where prestressing is involved. The clearances. To avoid this restriction it may become
relative movements between one part and another due to necessary to move the span-to-span construction joint
the elastic deformation on stressing, and the subsequent away from the piers.
shrinkage and creep, can result in awkward problems. With the construction joint within the span, the point
Trying to cater for relative movement during construction of connection becomes subject to deflection during the
and yet to achieve fully continuous behaviour in the course of construction and prestressing. This can be
completed deck can be particularly difficult with load- difficult to deal with in a manner consistent with obtaining
carrying diaphragms. By breaking up the width of the a good finish.
deck into distinct sections, each can be treated as a One disadvantage of serial construction is the
separate constructional problem, and the linking slabs constraint imposed on the constructional sequence. The
can then be concreted following the completion of all the work effort required from the differing trades in
main structural elements. contributing towards the progress of construction tends
Where this approach to construction is adopted, the to come in short, concentrated efforts that do not provide
transverse diaphragms should be kept within the width the continuity of work which is so desirable to achieve
of each spine element, and not taken across the linking optimum productivity.
slab. Supports are provided separately for each spine. There are also limits to the rate of construction which
The fact that a voided slab deck can be provided with can be achieved, and since serial construction demands
transverse diaphragms within its own depth allows a that erection proceeds sequentially, span by span, from
simple form of bridge pier to be utilized. A cantilevered the starting point, long construction periods become
diaphragm member can span up to 3 to 4m (or 10 to inescapable in the case of viaducts. To speed construction
14ft) depending on the proportions of the span and the it is sometimes necessary to produce a design requiring
width. With a plate pier 3 or 4m wide, plus cantilevered the construction of two spans at a time. The
edge slabs spanning 3 or 4m, the effective width of each disadvantage of this arrangement is that frictional losses
“spine” element could be up to 16m or 50ft, which is will be high at the end remote from the stressing point,
sufficient to accommodate a three-lane all-purpose road. which can only be the leading edge of construction. It is
The plate type of bridge pier is not only pleasing in inevitable that the effective prestress will differ at
appearance because of its simplicity of line, but is also adjoining piers (due to the different frictional losses).
straightforward to construct. It blends well with the lines The range of stresses that must be catered for during
of a deck of this type. design becomes a further constraint on achieving the
The economic change-over point between reinforced maximum economy in terms of the balance of forces on
and prestressed concrete construction in a voided slab a cross-section.
depends on the prevailing relative costs of concrete and
steel. The economic choice therefore changes in differing
circumstances, but is probably within the range of 20 to Beam-and-slab construction
25m or 65 to 80ft. That is to say, for spans of up to 20m
reinforced concrete is cheaper, between 20 and 25m Cast-in-situ construction using beams and slabs—as
further investigation is necessary, and above 25m commonly, adopted in building construction—is rarely
prestressed concrete should be the economic answer. used in bridges in the UK, other than locally within the
One important factor in the economy of a prestressed context of other forms of construction to provide
concrete deck is the layout of prestressing cables adopted. trimming around openings. Where beam-and-slab
It is fundamental to the efficiency of a cable that its profile construction is used, it invariably occurs in conjunction
should move through as great a height as possible, to with precast beam units. Early forms of such
give maximum eccentricities at both midspan and support. construction were based on the use of I-beams with slabs
Where twin cables are used between adjacent voids, the spanning transverely, as is common in steel construction.
maximum range of eccentricity is exploited by bringing Composite action between the precast unit and the deck
the cables from a parallel, side-by-side position at midspan slab then forms a T-section. A number of variants have
to a similar side-by-side position over the pier. The path been employed for the shape of the precast unit in an
followed by each cable, when viewed in cross section attempt to achieve the optimum economy in the design
through the deck, therefore describes an “X” through condition for the precast unit while it is acting
the length of the span, as shown in Figure 3. independently (i.e. during construction) as well as in the
Where a voided-slab deck is a continuous prestressed completed structure.
structure of more than three spans it becomes necessary To streamline construction, it can also be beneficial to
to use serial construction (see Data Sheet 57). This involves precast part of the slab itself. This usually means
building one or two spans at a time, coupling the precasting a sufficient thickness of slab to support the
prestressing cables for subsequent spans on to the end of dead weight of the full slab, and completing the thickness
those spans that are already built and stressed. The details with cast-in-situ concrete (see Figure 5).
3
www.EngineeringBooksPdf.com
Figure 2. Bourne Avenue Bridge, Bournemouth. Prestressed voided slab with reinforced concrete
side cantilevers, built using serial construction with couplers.
4
www.EngineeringBooksPdf.com
Figure 3. Layout of prestressing cables.
When railway modernization was in progress in the to those on the construction site, which must increase the
UK, with the accompanying change from steam to already substantial margins added to the direct cost.
electric and diesel motive power, the inverted-T bridge In many instances the cost of a cast-in-situ form of
deck became very popular. It provided a means of construction, as represented by the prices tendered by
constructing a bridge deck without recourse to falsework contractors, is cheaper than the precast alternative.
which could otherwise impinge unacceptably on railway Comparisons of this kind are difficult and can only be
clearances. Also, while steam traction was still common, valid where alternative designs of equal merit are used as
it had been desirable to have a bridge with a flat soffit, yardsticks. Even in a structure where the spans cover a
in order to avoid smoke traps which had the effect of range favourable for precasting, most practical bridge
worsening the deterioration of a structure by trapping decks have geometrical complications which demand
hostile elements in the exhaust from the locomotives and dimensional variations in the length of the units or their
thus promoting corrosive attack. A wide range of T- spacing, thus robbing the work of fabrication and
beams came on to the market, and steps were taken assembly of that repetitiveness which gives the prime
towards standardization, as it was felt that this would potential saving in precast construction.
produce economies. This development gave rise to the There are obvious limitations in the length and weight
marketing of rapidly-designed bridge decks. By the of precast units which can be transported, so that only
simple expedient of selecting the appropriate standard spans of less than 30m or 100ft can be dealt with by
units, and stacking them side by side on a drawing: using single precast beams.
“BINGO!”; the design was virtually complete. This It is sometimes possible to construct a precast deck in
procedure held considerable attractions for design offices a manner which results in continuity as regards imposed
with limited experience in bridge design. loading only. The adjustments which would be necessary
The use of bridge decks based on the use of during erection to counteract the deflection due to self
contiguously placed precast units still has a place in weight make it impracticable to achieve full continuity
particular circumstances where there are severe for the dead loading when precast beams are used. The
restrictions on temporary headroom during construction, effects of continuity are sometimes simulated by providing
where speed of erection is a prime consideration for the articulated joints within the span acting in conjunction
deck, or where safety requirements favour this approach. with cantilevers from the support. The drawback with
The current standard unit in the UK for this form of this solution is that the joints in a bridge deck invariably
construction is the M-beam, a particular version of an leak and, whereas the consequences of this can usually
inverted-T. There are also box sections and other types be concealed at the abutments, the siting of a joint within
of inverted-T on the market. Details of some types of the span usually leads to disfiguring staining on the
precast deck beams currently available are given on Data elevation. Unless the joint is successfully masked, it can
Sheet 1. also detract from the lines of the structure.
Where precast beam units are used in a bridge deck Where a bridge of precast beam construction consists
and the span is such that prestressing is the economic of several spans, the intermediate supports invariably
answer, the choice remains between pretensioning and require a portal frame, the cross member of this portal
post-tensioning. Where a small number of units are being usually being located below the deck. Although attempts
utilized, post-tensioning is likely to be more economic have been made to conceal the cross-head within the depth
because pretensioning requires a fairly elaborate set-up of the beam-and-slab construction, the resulting details
for fabrication. Such expense can only be justified where are complex, and are therefore unattractive.
the number of units to be produced is sufficient to gain
advantage from the fact that with pretensioning the
anchorages are re-usable through the fabrication of a Box-section decks
number of components.
It has often been argued that precasting should Precast construction has been applied to post-tensioned
represent the economic solution to most bridge problems. prestressed concrete box decks, but the circumstances
This impression arises from the relative simplicity of the where this is justified and provides an economic solution
constructional procedures on the site. Against this must are the exception rather than the rule. The arrangement
be set the fact that most forms of precast construction involves heavy handling on the site and a good deal of
involve more total work, and additional handling labour in forming joints.
operations are needed above those required to complete The precast solutions which have been adopted are
cast-in-situ forms of construction. It is also necessary to generally based on the use of segments which represent
finance the overheads at a precasting factory in addition the whole of the deck cross-section. These are precast in
5
www.EngineeringBooksPdf.com
Figure 4. Box construction applied to Calder Bridge.
short lengths which are then jointed by cast-in-situ There are a number of variations on the basic theme
concrete, usually in joints about 100mm (4in.) in of a box section. Not only is there a choice as to the
thickness. An alternative solution, in which precast number of cells which can be included but the soffit profile
segments represent only part of the cross-section of the can be varied, providing a haunch at the pier locations
deck, has been adopted where there were stringent where the bending moments tend to be higher. Nor is
limitations on the size of unit which could be handled on there any necessity for the web members to be kept
site (see Figure 6). Such a precast solution requires vertical. A number of boxes have been constructed with
extensive falsework to support the components until sloping outer webs, which gives an interesting profile to
jointing is complete and prestressing has been carried out. the bridge soffit. Whether or not this adds to the cost of a
The need for this falsework detracts from the potential structure is arguable in the light of the proportions of an
advantages of precasting and makes box construction individual deck but, where such a solution is appropriate,
generally better suited to cast-in-situ concrete work. the additional labour involved in forming the unusual
The natural flexibility of cast-in-situ concrete shape should be offset by reductions in material content
construction can be well exploited in a cellular type of necessary. Of course, where such shaping is introduced
deck. The external profile of the cross-section can be purely as a gimmick without having functional relevance
maintained, while variations in the relative positions of it must be expected to add to the cost.
webs, as well as their thickness, can be made to suit the The argument supporting the provision of sloping outer
geometry imposed on a structure by the highway layout. webs is that the width of the upper slab of a box deck is
6
www.EngineeringBooksPdf.com
Figure 5. Interior of box deck under construction. External prestressing cables located ready for stressing.
enforced by the width of the pavement to be carried. one, or possibly two, spans at a time from one end because
Although a box could be built with its outer webs on the of the rapidly accumulated friction within the length of
extremities of the section, it may be advantageous to limit the ducted cables. It is also likely that the dimensions of
the width of the box itself, thereby reducing the material the box, in terms of web thicknesses, will be dictated by
content. Providing transverse cantilevers at the edges of the concrete required to accommodate the prestressing
the deck is one significant step towards this, and sloping ducts and to cover them.
the outer webs can further reduce the width of the bottom The use of external prestressing cables removes these
slab, if the box is sufficiently deep to make this restrictions. The frictional losses accumulated along the
worthwhile. Whether or not such a shape is appropriate length of an external cable are very low, so that it becomes
depends on the width of the highway and the depth of possible to stress a number of spans at one time with
the box. quite modest losses. This can make a marked impact on
The bottom slab of a box has only to maintain the design of a multi-span structure. Not only does it
equilibrium with the prestressing cables at midspan. become possible to dispense with intermediate anchorage
Adjacent to the supports it has the primary function in positions for prestressing, which would be required with
resisting the reverse bending moments over the continuous serial construction, but the sequence of construction for
supports, and it is then a relatively simple matter to thicken the bridge can be freed from the strait-jacket of serial
the slab in this region without incurring the penalty of construction, demanding its span-by-span approach.
significantly increasing the bending moments due to self- It is unlikely that accumulated friction will limit the
weight. number of spans which can be constructed and prestressed
Where box construction is adopted another in a single operation. It is more likely that restrictions will
fundamental alternative presents itself: whether to provide arise from the prestressing equipment, in that it is necessary
internal or external prestressing cables. Internal cables to stress a cable by a series of bites, i.e. strokes of the jack,
are buried within ducts contained in the concrete forming and it is desirable to limit the load at which a further bite
the deck cross-section. External cables are suspended is commenced. This limitation arises from the fact that in
freely within the voids of the box, stressed in that commencing a fresh bite the prestressing jack must first
condition, and subsequently protected by a casing of overcome the resistance to withdrawal of the wedges, which
concrete, grout, or some other means. have locked-off temporarily at the end of the preceding
If internal prestressing cables are used and the structure bite. If a cable is to be stressed to 70% of its characteristic
has several spans, the same limitations arise that apply to strength, it is desirable that the last bite should commence
voided slab construction. That is to say, serial construction at a figure not higher than 65%, to allow for the overload
must be adopted because it is only possible to prestress due to withdrawal of the wedges, so that the length of
7
www.EngineeringBooksPdf.com
cable must be no more than that which will allow a single tend to prove the economic solution, even though
stroke of the jack to raise the cable through 5% of its alternatives may exist which are simpler to assemble and
characteristic strength. If the working stroke of the jack is which call for fewer man-hours to be worked on site.
150mm (6in.), this implies a limiting length of 200m or Economic designs make the best structural use of the
650ft where stressing is to be carried from one end only. material contained within the deck, and the non-working
Where a box section is cast-in-situ it is obviously parts of the structures are kept to a minimum. The
necessary for the section to be built up in a series of penalties to avoid are the provision of heavy webs at
operations. For deep boxes it may be necessary to cast the midspan, where shearing stresses are only nominal, and
bottom slab, webs and top slab separately. For shallower unnecessary areas of flange at points having nominal
sections the webs and top slab may be cast together. In a bending moments. For example, in many forms of precast
single-celled box there may be advantages in casting the construction it is necessary to provide a flange on the
bottom slab and webs together, and subsequently adding precast element in order to maintain stability prior to its
the top slab. Difficulties in securing the web forms make incorporation in the finished deck. In many beam sections
this arrangement unattractive for multi-celled boxes. this temporary top flange is stressed at low levels in the
To simplify the casting sequence in a long length of permanent structure but adds significantly to the self
deck, a considerable advantage can be gained from weight. In voided-slab construction the shape of the web
allowing the construction of the box itself to precede the is structurally inefficient and where significant depths are
concreting of such diaphragms and stiffeners as may be involved the amount of structurally-unnecessary material
necessary along its length. This arrangement enables the carried by such a section becomes substantial. In wide
formwork for the box to proceed without complications box construction the top flange is necessary throughout
due to the transverse reinforcement and formwork. Special to support the pavement, but the bottom of the box, which
attention must be paid to detailing the reinforcement for acts as a flange, is only nominally stressed at points away
the stiffeners and diaphragms if free movement of the from support or midspan locations. A source of self-
box formwork is to be attained. weight common to many forms of construction is the
The main limitation on the size of boxes at the lower concrete added to a section solely to protect the
end of the span range becomes the practicability of casting prestressing tendons.
a shallow box. It is necessary to work inside to strike and To achieve an economic solution it is necessary to assess
remove the formwork and, where external cables are used, critically any concrete which is included for non-structural
to thread and protect the prestressing cables. Where a box reasons. It is also essential to make the maximum use of
is to be built with re-usable timber forms the clear height those elements of the structure which are indispensable.
inside the deck should not be less than 900mm (3ft), which The prime example of this is the slab surface provided
implies a minimum overall depth of 1.2m (4ft). If external over the full width of the deck to support the road
cables are used and they are to be protected by a casing of pavement. For optimum structural efficiency this slab
cast-in-situ concrete, the headroom inside the box should member must be well utilized. It forms a natural flange
not be less than 1.5m (5ft). Lesser headrooms are acceptable to resist longitudinal bending, and the minimum thickness
where alternative forms of protection are provided. which it can practicably be given provides sufficient
capacity to span transversely between longitudinal
members that are spaced at about a width of one traffic
Optimum deck proportions lane apart.
To make the best structural use of longitudinal
In spite of the fact that a substantial proportion of on- members a prime consideration is that their number
site constructional costs in the UK are due to labour, should be kept to the minimum compatible with the
experience has shown that the forms of construction capacity of the deck slab. Since it is impossible to design
which require minimum material content are those which a beam of any type which is 100% structurally efficient,
8
www.EngineeringBooksPdf.com
Figure 7. Precast construction applied to box-section deck.
the idea of using a minimum number of longitudinal the minimum depth or may eliminate the use of falsework
members ensures the provision of the minimum of where the restrictions apply during construction. Access
structurally-surplus material in the deck. to the site, or the height of a deck above the ground can
The best use is made of the upper surface of a deck also be factors limiting the choice in extreme
slab spanning transversely by allowing it to make the circumstances.
maximum possible contribution to carrying the load In most cases several options remain. Appearances are
across the width of a deck. For example it can cantilever important and, assuming the deck to be well proportioned,
a significant distance beyond the outer members to the complimentary consideration is the form chosen for
support parapets, verges and part of the carriageway itself. the intermediate supports. Portal frames have little to
The presence of a verge lowers the intensity of loading, commend them in this respect—they add to the apparent
and transverse cantilevers of 3 to 4m or 10 to 14ft are overall depth of construction and interrupt the lines of
quite practical. Longitudinal members spaced at a width the deck. The plurality of numerous supporting columns
of one traffic lane apart are well within the capacity of a can add confusion to the general appearance beneath the
reinforced concrete slab about 200mm (8in.) in thickness. bridge, which may already be busy with traffic routes. If
This provides an economical layout whether the skew is present this confusion is compounded. To simplify
longitudinal members are the webs of a box-section, or the form of the supporting piers a deck structure must be
precast beams. of a type which has some capacity to span transversely as
A structure of the minimum depth is not necessarily well as longitudinally, thus replacing the cross-beam of a
the most economic. To achieve maximum economy the portal. This means using a voided-slab or box-type
balance of cost between the concrete and steel for structure.
reinforcing (or prestressing) needs examining. This matter For a long length of bridge or viaduct, there may be
is discussed further in the section on economics. For circumstances where the ground features admit a range
economic design the costs of approach roads also need to of options in terms of the number and dimensions of the
be taken into account, which may give rise to substantial individual spans. Obviously in such circumstances full
extra costs that are proportional to the deck thickness. advantage must be taken of the benefits of repetition by
Of course economy is not the sole consideration and a adopting an even spacing for the piers, although the end
slender structure is often preferred for the sake of spans should, if possible, be shorter than the intermediate
appearance. spans to achieve optimum structural economy. Where the
length of a structure is such that a large number of spans
becomes necessary, the rate at which it is practicable to
Selection of deck construct the bridge must be taken into consideration. If
serial construction is adopted it is unlikely that the rate
Physical constraints arising from the nature of the site of construction can exceed one span per month even after
may eliminate some solutions. Restrictions on the depth working has settled into a productive rhythm. Although
available for construction may demand a deck having the cheapest structure might be a voided slab with a span
9
www.EngineeringBooksPdf.com
of less than 30m or 100ft there could be a case for building Standard bridges
longer spans by using box construction so as to enable
the adoption of external prestressing to achieve a faster During recent years the Department of Transport has
rate of construction. Substructure costs often influence undertaken an extensive study of bridge standardization,
the economic layout. as a result of which it hopes to publish a range of detailed
For multi-span structures the preferred articulation is designs that are applicable to commonly recurring
to adopt full continuity. Serial construction introduces bridging problems associated with highway construction.
varying moments in adjoining spans as construction Although the forms of construction adopted for this
proceeds. These moments are subsequently modified by standardization are well known and proven bridge deck
shrinkage and creep, eventually converging on the values types, the task has nonetheless proved to be complex
which would occur in a structure built in the fully- because of the bewildering number of combinations of
continuous state. Because time is taken to achieve this factors controlling the basic geometry of a bridge. In view
situation a range of figures must be taken into account in of the fact that standard solutions can only be applied to
the calculations, adding to the margins of residual stress a small proportion of total bridging problems, the effort
to be provided and thereby adding to the material content required to resolve this difficulty, combined with the
in the deck. consequent cost of the exercise, raises questions as to
Where the choice of deck construction remains open, whether this approach to design standardization is
cast-in-situ concrete box construction will prove to be economically productive.
the most-economic solution for spans in excess of 35m. Standard precast beams are prominent in the standard
For spans of 30 to 35m or 100 to 115ft the box will be designs, which is likely to have the effect of strengthening
economic where a depth of not less than 1.2m (4ft) is their dominance of the scene where precast construction
acceptable. For spans of 25 to 30m a prestressed concrete is concerned. The incidence of precasting other than for
voided slab is the appropriate choice, changing to a standard beam sections has become rare in bridge
reinforced concrete voided slab at some point between building. Either this argues for economic advantages
25 and 20m or 80 and 65ft span. Where the depth of the having arisen from the use of standard sections, or it
deck is less than 700mm (about 28in.) a solid reinforced argues for conservatism in the design approach where
concrete slab is appropriate. precasting is concerned.
Data Sheet 2 summarizes the limiting dimensions and Cast-in-situ reinforced concrete slab decks and
spans for various types of deck construction. composite steel-and-concrete construction also figure in
Precast construction should be used where restrictions the range of standard designs prepared by the DTp, so
on the temporary headroom preclude the use of falsework that a choice of types of construction can be offered to
under the deck, where safety considerations demand the the contractor at tendering stage, enabling him to select
provision of a continuous soffit during construction by the type of construction best suited to his resources and
using contiguous precast beams, or where the speed of methods of working.
erection is a prime consideration.
10
www.EngineeringBooksPdf.com
Precast deck beams
Data sheet No 1
11
www.EngineeringBooksPdf.com
Data sheet No 1 Continued
12
www.EngineeringBooksPdf.com
Cast-in-situ concrete decks
Data sheet No 2
13
www.EngineeringBooksPdf.com
Bridge deck references
Data sheet No 3
14
www.EngineeringBooksPdf.com
CHAPTER 2
The sub-structure
Because of the close interaction between a bridge deck to this requirement occurs where the cross-section is given
and its supporting structure it is essential that the two be a triangular shape with the front face battered, resulting
considered together in formulating outline proposals, to in a sloping front to the abutment.
ensure that they are compatible. Ground conditions may Cantilevered reinforced concrete walls are probably
be such as to make some settlement of the foundations the most widely used form of construction for typical
inevitable, and where the magnitude of settlement highway bridges. They require simple formwork, but as
involved is substantial, this may rule out the use of the height increases, the reinforcement can become very
structural forms involving continuous spans or a heavy and the section thickness substantial.
torsionally stiff deck, because these would be unable to With increasing height it becomes economic to shape
accommodate large displacements at the points of the section of the wall stem in plan, creating a T, which
support. allows the use of wall panels of the minimum practical
The techniques of ground investigation by means of thickness in combination with cantilevered T-beams. This
boreholes are well known and widely practised. However, arrangement results in a reduction in the quantities of
it is important to realize that an investigation carried out concrete and reinforcement required but adds complexity
without proper supervision and understanding may be of to the formwork arrangements needed.
little value, and can even be positively misleading in ways The traditional counterfort wall employs T-ribs that
that may give rise to major problems during construction, extend right to the back of the footing, but at intermediate
or to the unsatisfactory performance of the completed heights this is not necessary—the T-ribs need only be
bridge. sufficiently deep to enable them to resist the shearing
The supervision of ground investigations needs to be forces involved, and to keep the amount of tension
in the hands of personnel who know the techniques of reinforcement required within reasonable limits. The
investigation well enough to differentiate between real resulting stub-counterfort wall provides an intermediate
difficulties and a lack of care on the part of the operatives, solution between the cantilever and the full counterfort,
and who are also able to identify the strata encountered and can be economic at heights which are appropriate to
during the investigation. In many instances the latter providing the necessary highway clearance.
requirement calls for little more than common sense, but Where types of wall involving more-complex
some subsoil formations present variations which may formwork requirements are to be utilized it is important
only be identifiable by trained geologists. Even so, the to keep the spacing between counterforts regular, so that
consequences of these differences may be very significant the formwork panels can be given the maximum amount
in terms of the design, construction and serviceability of of re-use without modification.
the foundations. For the bases of retaining walls it is often the shearing
Information regarding the allowable bearing capacities stresses that control the thickness of footing needed. This
of granular and cohesive soils is summarized on Data is particularly true as regards the recent requirements of
Sheet 4, Data Sheet 5 deals with the field identification the Department of the Environment (DoE) in its Technical
and classification of various types of soil, as required by Memorandum BE 1/73 which limits the shearing stress
CP2001, while Data Sheet 6 tabulates approximate in relation to the amount of main tension steel provided.
foundation pressures according to CP2004:1972. For large abutments where the ground is rising away
from the bridge spans there can be advantages in using a
hollow abutment. This consists of four walls forming a
Abutments box in plan and supporting a deck of simple cast-in-situ
reinforced concrete beam-and-slab construction. The front
Mass concrete construction is economic for retaining walls and side walls simply act as supports to the deck, while
of small height, but is not normally competitive with the rear wall retains the earth fill to the approach
alternatives in reinforced concrete at the height required embankments. The potential advantage of this
for a bridge abutment giving highway clearance. The arrangement is that the height of the retaining wall at the
simplicity of construction suggested by mass concrete is rear of the hollow abutment is much less than would be
offset by the need to taper the section in order to limit the required if the retaining wall were the front wall of the
quantities of materials involved. An interesting solution abutment.
15
www.EngineeringBooksPdf.com
The various types of abutments are illustrated on Data Transition slabs
Sheet 7, and their design is dealt with on Data Sheet 10.
The various modes of failure that may occur are discussed Opinions differ as to the merits of providing transition
on Data Sheet 9. slabs on the approaches to a bridge. Maintenance
problems have been known to arise with transition slabs,
but those who favour their use attribute this to poor
Piers original design or detailing. Where ground conditions are
such that the embankment supporting a road will settle
The choice of construction of a bridge deck will dictate significantly, depressions are liable to develop immediately
how much freedom exists in choosing the pier adjoining the ends of the bridge deck, giving a very poor
construction. If support is required at intervals across the riding characteristic to the carriageway. This in turn
full width of the bridge deck, some form of supporting increases the settlement as a result of pounding from traffic
wall or portal frame is called for. However, where a deck on the poorly-aligned section of road. This problem is
has within itself some capacity to span transversely at aggravated by providing rigid supports at the ends of the
intermediate-support positions by means of a diaphragm deck such as would occur if this element were piled. It is
within the depth of the deck, then a wider choice is also apparent that embankments of a substantial height
possible. will be subject to settlement within themselves, quite apart
Simplicity in the form of the pier not only has the merit from that of the supporting sub-grade, thus further adding
of providing easier, and therefore more-economical, to the problem.
construction but is also more likely to produce an A well-designed transition slab distributes the relative
attractive result. Complex shapes have been used with settlement between a bridge deck and the approach
success, but for every good example there are several poor embankments, thereby very much improving the riding
imitations and it is evident that piers of a complex shape characteristics of the pavement and eliminating the
should only be adopted after a careful investigation of recurring maintenance problems associated with the
their potential appearance. It is probably better to limit formation of depressions immediately behind rigid end
their use to situations where good modelling facilities supports to the deck.
enable a realistic representation to be made of the final
result. Although perspective sketches can be prepared,
they are frequently misleading because they can at best Piling
only represent the appearance from a single viewpoint.
One choice to be made in relation to the overall It often becomes necessary to employ piled foundations
articulation of a structure is whether the bearings should for bridgeworks where the ground near to the surface is
be placed at the heads or the feet of piers. A monolithic too soft to sustain spread footings or would be susceptible
connection between the head of a pier and the bridge to substantial settlement. In addition to providing a means
deck is undoubtedly a clean and tidy solution visually, of supporting the foundation loads, the use of piling can
but bearings at the foot of a pier require a chamber and make it possible for the other ground works (such as the
introduce associated drainage problems which usually construction of pile caps in the place of spread footings)
combine to create additional expense. There are also to be carried out at higher levels than might otherwise be
problems in providing stability for the pier during possible. This can be beneficial where the foundation is
construction, and for these reasons bearings at the heads to be built adjacent to a waterway or in waterlogged
of piers are usually preferred. ground.
The various types of pile that are available are listed
on Data Sheet 11. Data Sheets 12 and 13 give charts for
Banks seats the design of precast concrete and steel bearing piles
respectively according to the well-known Hiley pile-
Where no abutment is provided and the end of the bridge driving formula.
deck is supported at the head of a slope formed by a The choice of the type of pile to be used is influenced
cutting or embankment, the foundation may be a strip by ground conditions. Where rock or some other hard
footing, a buried skeletal abutment or a piled bank seat, bearing stratum occurs at an accessible depth, preformed
depending on the level of suitable founding strata. piles driven to provide end bearing can be an attractive
The choice of a bank-seat support usually follows from proposition. Steel H-piles are more easily driven, cut and
a designer’s wish to minimize the interruption to the flow extended than their reinforced concrete alternatives.
of lines of the deck. It is possible to detail such a However, it is self-evident that reinforced concrete is a
foundation in a way that enables the deck profile to more suitable material where corrosive conditions exist.
continue into the earthworks without the supporting Preformed piles can be driven at a rake of up to 1:4,
foundations being visible. To achieve this it is usually thereby absorbing horizontal forces without inducing
necessary to construct part of the bank seat with an edge substantial bending moments in the pile section. Loadings
profile to match that applied to the deck itself. With this in pile groups which include rakers can be assessed by
arrangement the movement joint in the deck is likely to the elastic centre method described in the Civil
pass through the parapet clear of the earthworks. Engineering Code of Practice No. 2: “Earth Retaining
Attention to draining this joint is therefore important in Structures”. To minimize the risk of high bending
order to avoid weathering defects. moments developing in piles, any arrangement adopted
Several types of bank seat are illustrated on Data Sheet 8. should be such as to avoid the intersection of all the pile
16
www.EngineeringBooksPdf.com
centre-lines at a single common point, because with such The construction of a diaphragm wall requires the
an arrangement the rotation of the pile cap about that excavation of a deep trench in short lengths, using a
point is possible. This risk is avoided by ensuring that the bentonite slurry to support the faces of the excavation
layout adopted produces intersections of centre-lines at where necessary. A prefabricated cage of reinforcement
no less than two well-separated points. is lowered into the excavation and concrete is placed by
Large-diameter piles are normally installed vertically, tremie. Each short length forms a panel, and the joints
but it is still possible to absorb horizontal loads although between panels introduce some measure of structural
these do give rise to bending in the pile. Methods of discontinuity into the wall. Precast wall panels have been
assessing the horizontal-load capacity of large-diameter used in some instances, and involve the use of a bentonite
piles have been developed which utilize the subgrade drilling mud which develops a strength appropriate to
resistance in combination with the stiffness of the pile. the surrounding ground.
The techniques of constructing large-diameter bored piles
are best suited to cohesive soils. Granular layers near to the
surface can be successfully dealt with, but at greater depths Reinforced earth
the risks of the shaft sides collapsing become too great.
Piling adds to the cost of a bridge, so that the A rapidly-constructed and lighter form of retaining wall
practicability of providing traditional footings always construction has been developed in recent years which
merits careful investigation. Even where the soil will only is based on the use of facing panels that are stacked
permit low bearing pressures it is usually cheaper to without any attempt to provide fixity or bond with
provide extensive spread footings than to employ piles. adjacent units, but where each panel is tied back to the
earth fill by straps that are buried in the retained
embankment during construction. The facing to a
Groundworks reinforced earth wall can consist of concrete panels,
metal troughs or—more recently—lightweight panels of
For work within the ground, simplicity of construction fibre-reinforced concrete. The technique has been widely
can have considerable merits. A mass concrete foundation demonstrated on the Continent, and several examples
may be bulky, but is worth consideration as a means of have now been built in the UK. In addition to giving a
speeding construction in difficult ground conditions and lighter wall than could be achieved in traditional
it provides a firm base for continuing the work in reinforced concrete construction, this technique has the
reinforced concrete with the added complexities involved. merit of allowing construction to proceed on ground
In waterlogged ground the use of circular cofferdams filled which may not be suitable to form the foundation for a
with mass concrete minimizes the temporary works and conventional wall.
leads to the rapid completion of the work in the ground. Joints between the facing panels are usually made to
accept movements which may arise due to settlement,
and the flexibility of the finished construction makes it
Diaphragm walls highly tolerant to differential settlement without affecting
its structural integrity. The technique has been used for
For vertically-sided cuttings, such as those required for bridge abutments as well as free-standing walls. Some
lengths of sunken road, the work of excavation can often settlement is likely to occur, although this can be nominal
be minimized by using such constructional techniques as where ground conditions are firm. In circumstances where
contiguous bored piling or diaphragm-wall construction, the use of conventional abutments would involve
in place of conventional retaining walls. Since these extensive groundworks associated with foundations, it
techniques are usually associated with particularly- may be found that the use of reinforced earth could
difficult ground conditions, such as those arising with provide a solution which makes substantial savings by
over-consolidated clays, the design approach involves eliminating much of the groundworks.
consultation with authoritative experts.
17
www.EngineeringBooksPdf.com
Soil strength
Data sheet No 4
Granular soils
The bearing capacity of a granular soil is closely
related to its density. The more tightly compact the
soil is, the greater its capacity.
Cohesive soils
The ultimate bearing capacity qd per unit of area of a
continuous footing is
qdo=2·8qu(1+0·3B/L)
18
www.EngineeringBooksPdf.com
CP2001: Soil identification
Field identification and classification of soils Data sheet No 5
19
www.EngineeringBooksPdf.com
CP2004:1972 Approximate foundation pressures
Data sheet No 6
Presumed bearing values under vertical static loading
NOTE: These values are for preliminary design purposes only, and may need alteration upwards or downwards.
20
www.EngineeringBooksPdf.com
Abutments
Data sheet No 7
Mass concrete
Cantilever
Stub counterfort
Counterfort
Hollow abutment
21
www.EngineeringBooksPdf.com
Bank seats
Data sheet No 8
“Spillthrough” or “skeleton”
abutments are suitable where
spread footings are needed at a
level well below a bank seat. It is
often advantageous to design a
footing to offset the foundation in
relation to the bearings, because
the permanent horizontal loading
shifts the reaction.
22
www.EngineeringBooksPdf.com
Modes of failure
Data sheet No 9
Sliding
Foundation yield
Overturning
Slip circle
Structural failure
23
www.EngineeringBooksPdf.com
Abutment design
Data sheet No 10
Construction cases:
1 abutment self-weight+wing walls
www.EngineeringBooksPdf.com
Pile types
Data sheet No 11
Displacement piles
Replacement piles
25
www.EngineeringBooksPdf.com
Precast concrete piles
Data sheet No 12
26
www.EngineeringBooksPdf.com
Steel bearing piles
Data sheet No 13
27
www.EngineeringBooksPdf.com
Sub-structure references
Data sheet No 14
28
www.EngineeringBooksPdf.com
CHAPTER 3
Furnishings
Parapets hazard is weathering as a result of water staining. Even
where the parapet is non-corrosive, such as where it is of
The minimum function of a parapet is to prevent aluminium, if water running off the parapet is allowed to
pedestrians from accidentally falling from a bridge deck. run over the front face of the supporting upstand, this
In recent times it has become expected that they will also will lead to severe staining in time which will have a
provide some measure of similar protection for vehicles. disfiguring effect. The width of the supporting upstand
The requirement for a parapet to provide a safeguard therefore needs to be ample to accommodate the parapet
against a vehicle which is out of control plunging over post fixings and base plate, with a sufficient margin of
the edge of a bridge cannot be specified in terms of a width to ensure that the water drains into the bridge rather
static loading condition. The ability to absorb or redirect than over the front face.
the energy of an errant vehicle is a function of the The choice of fixings can also create hazards as regards
flexibility and constructional details of a parapet as much appearance. If some form of pocket is detailed it is possible
as on the nature and speed of the vehicle. Design for these pockets to become filled with water during the
regulations have therefore been based on the containment course of construction, and to give rise to frost damage
requirements in terms of a specified weight of a vehicle to the upstand. Even the introduction of anti-freezing
and its approach angle, and the assessment of suitable agents to prevent this does not always solve the problem.
parapet designs has become a matter of tests rather than Where a metal parapet is to be used a choice must be
design calculations. made between steel, which will then require painting (not
It would be impracticable to stipulate that a parapet only in the course of construction but as a regular item of
should be capable of containing any vehicle travelling at maintenance), and aluminium, which has gained
any speed. Requirements must be rationalized, and very widespread favour. Its colour is complementary to
few incidents have arisen in which vehicles have plunged concrete, and the absence of any need for routine
through parapets, although there is inevitably much maintenance in the form of painting is a significant
publicity in instances where this does occur with a advantage.
consequent loss of life. Data relating to the design of parapets are summarized
The selection of the type of parapet for a bridge is of on Data Sheet 15.
fundamental importance to its appearance. In fact, for
traffic users crossing a bridge the parapet is likely to be
the only indication that they are on a bridge structure. Expansion joints
The fundamental choice is between a solid concrete
parapet, usually surmounted by a single rail, and a more- Fundamental requirements for an expansion joint are
open metal parapet. Each can have visual merits that it should allow free movement of the structure under
depending on the general configuration of the bridge the influence of thermal, elastic and creep movements,
structure. In the case of a simple bridge that is required and that any constraining force that is applied should
to provide a single span over a single two-lane carriageway be easily absorbed by the structure. It should also provide
and with solid abutments, the short span will inevitably good riding quality for traffic passing over the joint,
be slender and may be visually weak by comparison with and it should either be waterproof or be associated with
the mass of the abutment wing-walls. A deep concrete drainage details which prevent any disfiguring
parapet can offset this, particularly if the parapet is weathering of the structure below the deck surface. The
continued as a distinctive element along the full length of joint should be serviceable and it should require the
the wing-walls as well as over the span. On the other minimum of maintenance. Since it is unlikely to last the
hand, if a three-span or four-span bridge is required over life of the structure it should also be replaceable without
a motorway to carry a local road, with consequent light prejudice to the viability of the structure, and at a
loading, it would seem inappropriate to introduce heavy moderate cost. Expansion joints not only have to cater
concrete parapets onto a structure which would otherwise for the surface of the main carriageway, but must also
be slender. make provision for movements in kerbs, verges and
Because it is very important to the finished appearance parapets.
of a bridge, the parapet and its supporting upstand merit However good an expansion-joint detail may be,
particular attention during detailing. The main potential the joint presents an interruption in the traffic surface
29
www.EngineeringBooksPdf.com
Figure 8. Controlled impact test on rectangular hollow-section barrier.
which is likely to give rise to noise in use, and to a problem or neoprene is exposed on the traffic face it can give rise
of some degree as regards maintenance. Where long to difficulties in the riding quality of the joint. At various
structures are constructed it is preferable to minimize the ranges of compression the upper surface will tend to
number of joints, accepting the need to cater for large change profile and therefore alter the riding
movements where they do occur rather than to have joints characteristics. In any event, some traffic noise must
at frequent intervals. The range of types of construction inevitably arise from the juxtaposition of two different
of bridge decks now in common use makes it feasible to riding surfaces. In some joints this potential difficulty has
produce long lengths of continuous structure. Even where been offset by introducing a series of steel members,
precast beams are being used which will not themselves breaking up the width of the compressible membrane into
be made continuous under added load, it is possible to narrow strips which are set below the traffic surface, so
detail the deck slab as a continuous member but with the that the running surface is provided by the steel members
provision of simple articulation joints at the deck-support themselves. These joints obviously become simpler as
locations. fewer membranes are needed to cater for reducing ranges
The mechanical type of expansion joint is used for large of movement, until only a single membrane is provided.
ranges of movement. Such a joint may be based on the Fillers based on foamed plastics are alternatives to the
use of opposing sets of finger plates which interlock to use of rubber or neoprene as compressible membranes.
provide a running surface throughout a range of Such fillers can be effective in joints catering for small
movement up to the length of the projecting fingers. This movements, provided that the filler material remains in
type of joint has been well proven over the years. Its compression at all stages of movement in the joint.
disadvantage is the need for heavy fixings because of the Although the filler is normally bonded to the supporting
cantilever action of the finger plates. With smaller ranges edges of the joint, and certain types of foam plastics are
of movement, however, the fingers can be shallower in capable of working in a stretched as well as a compressed
depth and in some instances may be partially supported state, adhesives do not usually show the degree of
by a flat plate on the opposing side of the joint, thereby reliability in service which would warrant relying on
reducing the cantilever and also the weight of the fixings tension across such a joint. Although the materials
needed. themselves may be capable of performing in this way, a
For lower ranges of movement several types of joint civil engineering site does not permit the close control of
are available that are based on the use of compressible workmanship which would be necessary to guarantee
neoprene or rubber membranes. If a wide strip of rubber results throughout long lengths of joint.
30
www.EngineeringBooksPdf.com
Because it is necessary to install the joint filler in a The choice is a matter of cost, but the capacity of rubber
state of compression, nosings must be established before bearings is limited to lower ranges of load and movement.
the installation of the filler. It is important to achieve a The service life of a bearing may not equal that of the
strong and true-to-line shoulder on each side of the joint. rest of the structure. It is important to make adequate
This may be done by using high-strength concrete or provision for inspection during the life of the structure
epoxy nosings. The latter have come into widespread use because any tendency for the capacity for movement to
in recent years, but difficulties have been experienced be restricted quickly leads to the deterioration of the
where the shape of the nosing results in high shearing structure, in the form of cracking and spalling. It is possible
stresses under the impact of vehicle wheels. It is important that the bearings will need to be replaced during the life
that the shoulders of the nosing should be square. of a bridge. This is obviously a fairly major operation,
Where the range of movement being catered for is very and it is not appropriate to prepare the details with a
small, flexible sealants may be used. There are a variety view to making simple replacement a prime requirement,
of types available on the market in the form of unless no resultant penalty of cost or serviceability will
polysulphides. Again, it is important that the shoulders arise. However, it is obviously appropriate to see that the
of the joints should be firm and true to line. details are such that replacement is possible without
For the smallest movements, perhaps associated with prejudicing the viability of the structure.
points where the deck support permits rotation without Many bearings contain steel components that are
translation, carriageway finishes can be continued over a susceptible to corrosion. A high standard of protective
joint in the structure. coating is appropriate on these because, within the context
Types of expansion joints form the subject of Data of the concrete structure, the need for painting
Sheet 16, and information relating to deck movements is maintenance does not generally arise, and it is therefore
collated on Data Sheet 18. unlikely that the paintwork on small components will be
given regular attention. In any event, to obtain access to
the bearings in order to repaint them would usually be
Bearings extremely difficult.
Further information regarding bearings is given on
The advent of PTFE (polytetrafluroethalene), giving low Data sheet 17.
frictional surface-to-surface contact, has meant that
mechanical types of bearings such as rollers and rockers
have largely been superseded. The working pressures that Waterproofing
PTFE can sustain are such that the design of bearings
gives contact areas well matched to the capacity of the Mastic asphalt is a long-established and widely used
concrete, and the sliding surfaces permit substantial material for waterproofing bridge decks. It provides a
movement without the need for enlarged bearing continuous membrane which can follow the shape of the
dimensions. bridge deck without difficulties. One disadvantage that
The objective of a bearing layout in a bridge deck is to it has, however, is that it requires good weather conditions
allow those movements which must take place as a result for successful laying. While a bridge deck is damp, laying
of thermal changes, creep, shrinkage and articulation of is delayed by the fact that the heat leads to the “blowing”
the structure to occur, while maintaining the deck in of the freshly laid material so that, during adverse weather
position. Restraints against longitudinal and lateral conditions, there may be lengthy periods during which it
movement must be provided, and bearing manufacturers is not possible to make progress with waterproofing,
have various details in their products to provide restraint which can cause embarrassment regarding the time
in certain directions while allowing specified movements. required to complete the works. Preformed bituminous
Some of these devices restrain movement in one direction sheeting is less sensitive to laying conditions but the
only while others are bi-directional. In some instances evaporation of moisture trapped on the deck surface can
the restraint is sensitive to direction and care must be cause the subsequent lifting or blowing of the sheeting.
taken to ensure that a pair of bearings do not act against Recent developments include the introduction of
one another in service conditions, and that they allow materials which are applied by spray. These bond directly
lateral as well as longitudinal movements to take place. to the deck surface, thereby preventing any migrant path
Rotations are accommodated by spherical or for water beneath the impermeable layer, such as can occur
cylindrical interfaces in a PTFE bearing, acting in with unbonded materials with the result that one weak
combination with a second, plane, sliding surface. Where spot allows the water to travel over large areas, finding
a cylindrical surface is adopted, it is essential that any set its way to the lowest corner of the deck where leaks
of bearings acting together along a single line of rotation develop.
should have a common axis—not only in plan, but also Sprayed material and bituminous sheeting require
in elevation. Where there is any doubt about the protection before the road pavement materials are added.
practicability of achieving the accurate setting of the This protection may take the form of sand asphalt or
bearings, spherical surfaces must be used in preference to concrete tiles.
cylinders. Some bearing manufacturers recommend this Several products are now marketed which are based on
as a matter of course. preformed sheets and combine a water barrier and a surface
Where small movements and rotations are to be that can withstand constructional traffic during completion
accommodated, it may be appropriate to use rubber of the road pavement, without requiring secondary protection.
bearings which permit movement by shear displacement. The drawback in using such materials is that they involve
31
www.EngineeringBooksPdf.com
special details wherever problems of shaping arise, as inevitably reservoir in which the water collects, discharging slowly
occurs at the edges of the bridge deck or where changes in on the downhill carriageway so that this pavement surface
camber occur across the width of the formation. does not dry out with the rest of the carriageway surface.
Where a bridge deck carries a dual carriageway with a This can present an icing hazard. Its prevention requires
continuous gradient (due to superelevation) from one side the introduction of a water barrier within the central
of the bridge deck to the other, problems can arise from reservation, together with filter drains in the finishes unless
the migration of water through the central reservation. these are formed of materials that are completely
The heavy finishes in the central reserve may act as a impermeable.
32
www.EngineeringBooksPdf.com
Parapets
Data sheet No 15
P1 Vehicle parapet with plinth 700mm high or more. P1 Vehicle parapet with plinth less than 700mm
For use on motorway under-bridges high. For use on motorway under-bridges.
P2 Vehicle pedestrian parapet. For use on P2 Vehicle pedestrian parapet. For use on road
all-purpose road bridges, the design speed bridges where speed is restricted to 48 km/h.
being stated.
33
www.EngineeringBooksPdf.com
Expansion joints
Data sheet No 16
34
www.EngineeringBooksPdf.com
Data sheet No 16 Continued
35
www.EngineeringBooksPdf.com
Bearings
Data sheet No 17
36
www.EngineeringBooksPdf.com
Deck movements
Data sheet No 18
Movements to be catered for at bearings and expansion joints arise
from the following causes.
37
www.EngineeringBooksPdf.com
CHAPTER 4
Loading
38
www.EngineeringBooksPdf.com
fixed along the line of support (as is commonly the case length allows several vehicles in line. A judgement may be
in a cellular or box deck) is subject to sharp peaks. Plotting made on the intervals between vehicles, based on the
the design bending moment along the length of a support information about stopping distances given in the Highway
will show the peak and illustrate how the area over which Code. BE 1/77 specifies design forces to cover these
the load is applied becomes significant in evaluating design conditions in anticipation of the requirements of BS 5400.
moments. It is therefore relevant to take the thickness of
finishes and the wheel contact area into account.
Settlement
39
www.EngineeringBooksPdf.com
Design regulations in the UK do not stipulate impact which should be expected from a bridge pier.
acceptable levels of vibration, but some guideline is given This is obviously more significant in a footbridge
in an appendix to CP 117, and BE 1/77 includes details structure, where the other strength requirements for a
of the requirements for footbridges. pier are low.
Several studies have been undertaken aimed at assessing Design regulations call for the provision of crash
human tolerance to vibration. Some of these results are barriers in front of bridge piers in most instances, giving
summarized on Data Sheets 33 and 34. The subject is some measure of protection.
complex but rarely becomes an important consideration
for bridge design.
Other design data
40
www.EngineeringBooksPdf.com
Highway dimensions
Data sheet No 19
41
www.EngineeringBooksPdf.com
Data sheet No 19 Continued
Carriageway widths are based on traffic
lanes of 3.650 m nominal width: 2 lanes
7.300 m; 3 lanes 11.000 m; for all classes
of road.
42
www.EngineeringBooksPdf.com
Traffic loading
Data sheet No 20
Centrifugal force:
This loading applies to local effects and shall not be taken into account in determining global effects
on the deck. Associated carriageway loading shall be assumed to consist of full HA loading on one
traffic lane and one third HA loading on remaining traffic lanes.
Collision loads on supports of bridges over highways (BS 5400: Part 1):
43
www.EngineeringBooksPdf.com
Load lanes to BS153
Data sheet No 21
44
www.EngineeringBooksPdf.com
Proposed load lanes for limit-state design
Data sheet No 22
45
www.EngineeringBooksPdf.com
HA loading to BS153/Tech memo BE1/77
Data sheet No 23
46
www.EngineeringBooksPdf.com
BS 5400: Part 2:1978 HA lane loads for limit-state design
Data sheet No 24
The loaded length is the length of the base of the positive or negative portion, as
the case may be, of the influence-line diagram for the member under
consideration.
Where the positive or negative portion of the base of the influence line consists of
separated parts, as for continuous construction, the maximum effect shall be
determined by considering any part or combination of separated parts, using the
loading appropriate to the length or the total combined length of the loaded
portions.
47
www.EngineeringBooksPdf.com
48
Data sheet No 25
Abnormal loads
www.EngineeringBooksPdf.com
The abnormal loading stipulated in BS 153 is applied to most public Some bridges are checked for special heavy vehicles which can range up
highway bridges in the UK: 45 units on motorway under-bridges, 37 1/2 to 466 tonnes gross weight. Where this is needed the gross weight and
units on bridges for principal roads and 30 units on bridges for other. trailer dimensions are stated by the authority requiring this special
roads. facility on a given route.
49
www.EngineeringBooksPdf.com
Wind loading
Data sheet No 27
50
www.EngineeringBooksPdf.com
Temperature stresses 1
Data sheet No 28
Annual minimum shade air temperatures Annual maximum air shade temperatures
at sea level in 120-year return period at sea level in 120-year return period
NOTE: For each 100m above sea level, the minimum shade temperature reduces by 0.5°C and the maximum shade temperature reduces by 1°C.
51
www.EngineeringBooksPdf.com
Temperature stresses 2
Data sheet No 29
In addition to the overall movement of bridge decks in
response to mean bridge temperature, stresses are set up with the
cross section due to changes in the temperature gradient as air
temperature and solar radiation vary through the day.
52
www.EngineeringBooksPdf.com
Temperature stresses 3
Data sheet No 30
53
www.EngineeringBooksPdf.com
Temperature stresses 4
Data sheet No 31
Maximum shade
temperature and
high solar radiation
Minimum shade
temperature and
high out-going radiation
Simplified temperature
criteria for use in the
absence of temperature
gradient calculation
54
www.EngineeringBooksPdf.com
Temperature stresses 5
Data sheet No 32
Thermal stresses
In a statically-indeterminate
structure the assessment of forces
arising from thermal stresses can
best be approached by allowing the
individual components of the
structure to adopt the deformed
shape suggested by the stress
gradient through the thickness of
the member, and then applying a
force system at the joint positions
to restore compatible slopes at all
joints.
55
www.EngineeringBooksPdf.com
Vibration 1
Data sheet No 33
56
www.EngineeringBooksPdf.com
Vibration 2
Data sheet No 34
The following method of assessing the vibration characteristics
of prismatic, symmetrical footbridge decks, simply supported
or continuous over up to three spans, and supported on
bearings which may be idealised as knife-edge supports, was
proposed by Technical Memorandum BE 1/77, and is
included in BS 5400: Part 2: Appendix C:
57
www.EngineeringBooksPdf.com
Bending moments
Data sheet No 35
58
www.EngineeringBooksPdf.com
Reactions
Data sheet No 36
59
www.EngineeringBooksPdf.com
Deflection
Data sheet No 37
60
www.EngineeringBooksPdf.com
Railway clearances
Data sheet No 38
61
www.EngineeringBooksPdf.com
Loading references
Data sheet No 39
62
www.EngineeringBooksPdf.com
CHAPTER 5
Reinforced concrete
Even where the main structural elements of a bridge deck The design moment for local wheel loads can be
are prestressed, there are parts of the structure which evaluated by using influence surfaces, such as those given
behave as reinforced concrete. by Adolf Pucher in “Influence surfaces for elastic plates.”
Design regulations relating to bridgeworks prior to the Alternatively Westergaard’s analysis of concentrated loads
appearance of BS 5400 called for design to be undertaken on slabs can be used, but the method only covers simply-
on an elastic basis and in the case of reinforced concrete, supported slabs so that the results must be adjusted to
provided that limitations on allowable stresses were allow for continuity.
observed, there was no requirement to check ultimate Pucher’s charts show influence surfaces for specific
resistance. sections within a slab, e.g. at midspan or at a support,
BS 5400 introduces the limit-state philosophy which each being represented by an individual chart. In many
means that strength calculations are approached on a cases it is possible to judge by examination the average
load-factor basis. One step in this direction had, in effect, value of the influence surface contours over the loaded
already been taken in earlier design requirements when area, but where these contours are closely spaced it may
limitations on deflections and crack control were become necessary to draw cross-sections of the influence
introduced as additional factors to consider, over and surface, in the manner described in the handbook.
above the limiting of the stresses in the constituent Any slab which forms part of the cross-section of
materials. longitudinal structural members, as in a beam-and-slab
Although calculations aimed at limiting cracking often or box deck, will be subject to a combination of stresses
have the effect of reducing the allowable stresses in the arising from the longitudinal bending of the deck, together
reinforcement, there are still benefits in employing with the local effects of concentrated loads on the slab
deformed bars, not only because they give better crack spanning as an individual member. These stresses are
control than plain bars but also because there are potential additive, but where the overall bending of the deck
economies due to the shorter lap lengths required. produces significant stresses this bending, in effect,
Differences in cost between plain and deformed bars are, prestresses the slab. It can therefore be considered as a
in any event, usually marginal so that these benefits are prestressed member when assessing coexistent local
well worth a minor premium in cost. bending stresses, provided that the whole slab section
In seeking economy when proportioning reinforced remains in compression under the combined loading.
concrete members it is well to remember that the most Distribution steel is not only needed to resist local
slender member does not necessarily result in the lowest stresses but also to control cracking due to shrinkage.
cost. The relative prices of steel and concrete need to be The extent to which this is likely to take place in a slab
taken into account in evaluating economic member sizes element depends on several factors, including the
although, of course, in many instances the additional concreting sequence adopted. In fact a high proportion
weight from the thicker sections may have an adverse of what is generally referred to as “shrinkage cracking”
effect on other elements forming the structure. An obvious is actually the thermal contraction which takes place
example is a reinforced concrete slab as a component of during the setting and curing of the concrete due to the
a more-complex deck structure. Considering the deck slab dissipation of the heat generated during setting. The
in isolation, an economic solution may well suggest a correct choice of a curing method to assist in the
thickness significantly greater than the minimum possible dissipation of this heat at an early stage in the setting
value, but the added dead load to be taken by the main action may therefore help to control such cracking.
structural elements of the deck would be a penalty which Nevertheless, whatever the precautions and sequence
would more than offset the savings in the cost of the slab. of concreting adopted, clearly some thermal contraction
A high proportion of deck slabs spanning up to 3.5m and subsequent shrinkage will take place, and the
(or 12ft) tend to be 200mm (8in.) thick. They not only reinforcement provided must be sufficient to control the
need to be designed for local wheel loads and other loads consequent cracking. This is particularly important at the
imposed directly on them, but also for effects arising from edge of a deck, where the cracks will be more visible and
the differential displacement of the members supporting exposed to weathering. Very large amounts of
the slab. This is true whether a cross-section is cellular or reinforcement are needed if an attempt is to be made to
in the form of open spaced beams, because each is subject eliminate all visible cracks, and a compromise is usually
to the distortion of the cross-section under localized loads. necessary. Twelve-millimetre (1/2in.) high-yield bars at
63
www.EngineeringBooksPdf.com
150mm (6in.) centres around the perimeter should be may be subjected in the loading history of a member, as
regarded as a minimum amount for even the thinnest well as the limiting tensile and compressive stresses which
section. For crack control the spacing of the reinforcement the reinforcement may be designed to resist.
is as important as the quantity provided, so that large
bars spaced well apart are unlikely to be effective.
Where applicable, UK design regulations relating to Detailing
bridges call for the calculations to be based on a modular
ratio of 15. Other national codes call for different values, The objective when detailing is to achieve a simple
some as low a ratio as eight. The discrepancy stems from arrangement of reinforcement which provides bars where
the fact that the elastic modulus for high-strength they are needed with the minimum of superfluous steel
concretes is, in fact, quite high but shrinkage and creep and without imposing restrictions on the formwork. A
have the effect of adjusting the relative stresses within simple arrangement of reinforcement means using
the concrete and the reinforcement. British design straight bars where possible to produce a layout of
regulations have taken the view that the calculations reinforcement which creates a readily identifiable pattern
should represent the long-term effect—i.e. after shrinkage that a steel fixer can easily memorize, thus enabling him
and creep have taken place—and stresses/which are to work without needing to make constant reference to
calculated using a modular ratio of 15 are representative the details. These objectives almost inevitably mean the
of this. Lowering of the modular ratio has the effect of use of a small number of different bars within an
increasing the calculated stresses in the concrete of a arrangement.
reinforced concrete section, thereby tending to require Putting reinforcement where it is needed sounds
slightly deeper members with marginally less obvious, but it is all too easy to detail arrangements of
reinforcement. reinforcement which take no sensible account of
Concern about fatigue in reinforced concrete sections tolerances that may reasonably be expected, either in bar
has recently led to the introduction of limitations on the bending or fixing. If a link passes round the full perimeter
total range of stress to which any given reinforcement of a column section and its dimensions are calculated from
64
www.EngineeringBooksPdf.com
the column size and cover required, without making any to be effective such lines need to coincide with the
allowance for tolerances, difficulties are likely to arise in construction joints, since cracks within monolithic
maintaining suitable cover to the reinforcement. concrete sections usually express their own opinion as to
There is often a conflict between the desire to adopt simple where a plane of weakness is, regardless of what the
arrangements and the need to minimize superfluous designer does in terms of reducing the reinforcement
reinforcement. Any attempt to restrict the reinforcement locally or providing rebates in the face of the section.
provided to the amounts theoretically required at closely
spaced sections within a member would lead to an
arrangement of reinforcement in which each reinforcing bar Design data
had its own individual dimensions and shape. There are,
however, points within a structure where there is a tendency Typical reinforced concrete details for bridgeworks are
to duplicate reinforcement. In a cellular deck, for instance, illustrated on Data Sheet 40. Some information
the junction between the web and slab members suggests concerning the design of diaphragms is presented on Data
the adoption of a detail in which the vertical reinforcement Sheet 41, and Data Sheet 42 deals similarly with the design
is bent into the plane of the slab reinforcement to provide of slabs linking spine beams.
anchorage. If this is done, then that reinforcement should Design may be undertaken either by employing
be arranged to contribute to the strength of the slab section, elastic-strain (so-called modular ratio) theory or a limit-
rather than simply to include it in addition to the state analysis based on load-factor methods. The
reinforcement already provided in the horizontal plane. principal formulae and data necessary for the
For an arrangement of reinforcement to be convenient application of these alternative theories are summarized
for construction it is essential that the constructional on Data Sheets 44 and 45 respectively. Modular-ratio
sequence and the location of construction joints are taken design can be facilitated by the use of various design
into account when deciding on the arrangement of steel. factors corresponding to the permissible working
For example, where the head of a wall is to provide support stresses in the concrete and the reinforcement and, for
for a slab, a simple reinforcement layout would provide a modular ratio of 15, these factors may be read from
an L-bar in the corner linking the wall to the slab. However, the chart forming Data Sheet 46: brief examples of the
during the process of constructing the wall, the bar is use of the chart are given on Data Sheet 47, which also
projecting through the plane of the face of the wall, which includes a chart that relates the stress in the
restricts the height of the wall formwork, and this can prove reinforcement to the bar spacing in order to achieve
costly. Where the members are sufficiently thick it is often adequate crack control.
possible to adopt alternative reinforcement layouts which The areas of various numbers and spacings of
allow the use of wall forms of any height. reinforcing bars of different sizes are tabulated on Data
Where long lengths of slab or wall are constructed Sheet 49, while Data Sheets 50 and 51 present details of
without joints, cracks will inevitably develop. If it is the requirements of BS 4466 for reinforcing bars of
important to control the positions of these cracks this preferred shapes and other permitted shapes,
can be attempted by creating lines of weakness. However, respectively.
65
www.EngineeringBooksPdf.com
Reinforced concrete details
Data sheet No 40
66
www.EngineeringBooksPdf.com
Diaphragm design
Data sheet No 41
Design of diaphragm fundamental importance to the structural integrity, and
its failure would be catastrophic.
The importance of diaphragms to the structural action
of the bridge deck varies with the form of construction
There can be dangers in relying on the results of
adopted. In some instances they act as little more than
sophisticated structural analyses to design diaphragms which
local trimmers stiffening what would otherwise be an
come into the latter category, because any assumptions made
unsupported edge of a deck slab; in other cases they
in the analysis which are not realised in the actual structure
stiffen the overall action of the deck, thereby improving
could adversely affect the loading conditions on such an
the load-sharing characteristics of the main structural
element. The independent assessment of diaphragm loading
elements. In either of these cases failure of a diaphragm
on the basis of simplified and conservative assumptions is
need not prejudice the stability of the deck. However,
therefore a worthwhile precaution.
in some forms of construction the diaphragm is of
The development of an I-section to resist bending For loading cases as ultimate conditions are
depends on shear lag considerations in the deck slabs. It approached the deck section cracks, thereby reducing
also gives rise to horizontal shear flow in the slabs, as the proportion of the cross-section available for the
illustrated at A. The bottom slab at a pier will be effective transfer of shear from the webs to the
subjected to biaxial compression at all stages in diaphragm. Adequate reinforcement is needed to
loading, and therefore well able to absorb this shear transfer the shear in this condition.
flow, but the top slab is subject to tension—particularly
at loads approaching ultimate conditions—and needs Shear in deck
significant reinforcement.
The pattern of cracking developed as ultimate conditions
are approached can affect the integrity of the I-section of
Shear in diaphragm the diaphragm where the reinforcement contributing to
its action has been spread outside the net width of the
The pattern of shear cracking likely to develop as diaphragm.
ultimate conditions are approached merits
examination, particularly in the light of any Torsion
penetrations made in the diaphragm for access or for
prestressing cables. Torsion adds to the shear flow in the slabs, which are
also subject to I-section horizontal shear, as well as to
shear in the webs.
67
www.EngineeringBooksPdf.com
Link slabs
Data sheet No 42
68
www.EngineeringBooksPdf.com
Principal moments
Data sheet No 43
b) Principal moments,
Mxy small; M1 and M2 have same sign.
c) Principal moments,
Mxy large; M1 and M2 have opposite signs.
69
www.EngineeringBooksPdf.com
Reinforced concrete: elastic design
Data sheet No 44
70
www.EngineeringBooksPdf.com
Reinforced concrete: limit-state design
Data sheet No 45
71
www.EngineeringBooksPdf.com
Reinforced concrete: factors for elastic design
Data sheet No 46
72
www.EngineeringBooksPdf.com
Design-factor examples
Data sheet No 47
Example 1.
Since moment=0.80 MN . m,
Therefore
Thus
fcb=8.2 N/mm2 and fst=177 N/mm2.
Also from Data Sheet 43,
j=0.863, so that la=0.863×950=820 mm.
Example 2.
(Illustrating the use of the accompanying crack-control chart.)
Assuming n=0.4, then
For fst of 150 N/mm2, from chart on Data Sheet 46, H=127 and
thus p=1.6/127. Therefore
and
Therefore
fcb=8.2 N/mm2 and fst=145 N/mm2.
73
www.EngineeringBooksPdf.com
Slab moments
Data sheet No 48
74
www.EngineeringBooksPdf.com
Reinforcement
Data sheet No 49
75
www.EngineeringBooksPdf.com
BS4466 preferred shapes
Data sheet No 50
76
www.EngineeringBooksPdf.com
BS4466 Other shapes
Data sheet No 51
77
www.EngineeringBooksPdf.com
Reinforced concrete references
Data sheet No 52
78
www.EngineeringBooksPdf.com
CHAPTER 6
Prestressed concrete
The idea of prestressing concrete was a natural anchors each strand independently using its own metal
progression following the introduction of reinforced barrel and wedge grip. It is this principle which forms
concrete. Whereas the latter set out to overcome the lack the basis of the majority of systems marketed for
of strength of concrete in tension by providing steel bars anchoring strand or wire cables today.
in those areas of the concrete susceptible to tensile stresses, One departure from the wedge principle for anchoring
the purpose of prestressing is to induce compression in wire is that in which the end of the wire is deformed into
the concrete which will oppose the tensile stresses that a button head, having a shape rather like the head of a
arise due to applied loading, thus ensuring that the whole knitting needle. This method is now marketed as the BBRV
concrete section remains in compression at all the stages system in the UK.
of its working life. Recommendations for the limiting One disadvantage of the threaded-bar and button-head
concrete stresses in precast and site-cast prestressed types of anchorage is the need to precalculate the length
concrete are tabulated on Data Sheet 53. of each tendon accurately in order to prepare the
One of the early motivations of the idea of prestressing anchorage. Exponents of these systems discount this
came from the thought of producing a simulated arch. complaint as a minor chore, however.
Whereas the cross-section of a natural arch remains in A fundamental requirement for prestressing tendons
compression due to the natural thrust which develops at is that they must be protected against corrosive attack in
the arch springings, prestressed concrete artificially order to maintain the integrity of the structure. Where
replaces the force line, which occurs naturally in an arch, the cables are contained within ducts inside a concrete
by a curved steel tendon which is under stress, thus giving section this protection is provided by pumping cement
rise to a comparable force system in the member. grout into the duct after prestressing has taken place.
Several types of prestressing tendon have been Where the tendons are external to the section other
employed. Steel bars and drawn wire were early materials, options become available, including providing an added
while in more recent years helically-spun stranded cables casing of concrete directly around the tendons, or using a
built up from cold-drawn wire have become the most polyvinylchloride coating to enclose the cable which has
commonly used type of tendon. been prepacked with grease.
Provided that the tendon force is effectively transmitted The anchorage is a significant part of the cost of a
to the concrete section, nothing dictates that the tendon prestressing tendon and where a substantial number
must be contained within the cross-section of the member. of similar units are to be fabricated there can be
Internal tendons are more common but the use of external advantages in stressing between anchorages that are
tendons can allow reduced dimensions to be adopted for external to the members themselves, tensioning the
the concrete member in circumstances where the size of tendons prior to casting the concrete in direct contact
the section is dictated by the need to accommodate the with them and thereby forming an immediate bond.
tendons themselves. This technique is known as pretensioning. On
Many patented anchorage systems are marketed for releasing the anchorages the force in the tendon is
each type of prestressing tendon. Where rolled steel bars transmitted to the concrete section by the bond which
threaded at the ends are used a nut bearing against an is developed between the tendon and the concrete.
anchor plate makes a simple anchorage assembly. One This approach to construction obviously requires the
of the earliest types of anchorage for multiple-wire cables use of a permanent prestressing bed where the re-
was that developed by Freyssinet. This is based on a usable anchorages are established, and therefore
tapering hollow cylinder within which the wires are involves precast concrete construction. The method
secured by a conical metal wedge designed to anchor, only becomes economic where the number of units to
simultaneously, each of the wires around its periphery. be produced is sufficient for the saving in the cost of
The method leads to the wires forming a natural circular anchorages (which would otherwise be built into each
grouping in cross section, thus fitting conveniently into individual unit) to offset the cost of handling precast
a circular duct. Magnel developed a system in which units, any loss of economy in the structural form of
each prestressing wire is independently wedged by a the members, the establishment costs at the
series of tapering plates. This allows the formation of a pretensioning bed, and the structural limitations of
cable of almost any size, contained within a rectangular pretensioning as opposed to post-tensioning in terms of
duct. The system developed in the UK by Gifford, design. To be worthwhile, substantial quantities of similar
79
www.EngineeringBooksPdf.com
Figure 10. Equipment for grouting prestressing cable ducts under pressure. High-speed mixer and
storage bin with continuous agitation.
80
www.EngineeringBooksPdf.com
calculations for severe temperature stresses must also be
prestressing force, then gives an effective eccentricity at
taken into account, demanding substantial residual
that point.
stresses under applied loads, it seems appropriate to
An alternative approach is to plot a diagram of Pe/EI
for the structure, the eccentricity e being measured from consider this width of support.
the centroid of the section in the first instance. The
diagram is then balanced at the points of continuity by
adjusting the indeterminate moments to give a compatible Serial construction
“moment-area” diagram, showing zero relative
displacement at the points of support in accordance with Some of the difficulties incurred when employing serial
“moment-area” methods. construction are discussed on page 3, and illustrated on
Data Sheet 57.
81
www.EngineeringBooksPdf.com
Figure 11. Relationship between creep and time.
The effect of these large anchorage forces is not unlike reinforcement required and the resulting production of
that of driving a wedge into the structure, and the shape an arrangement so congested as to prevent good
of many prestressing anchorages encourages the analogy. concreting in that region, it is obviously even more
Several theories were developed as a basis for the design important that well-compacted concrete should support
of anchorages (Freysinnet, Guyon, Magnel, Bortsch, an anchorage than that the calculated area of
Bleich, Siever, Morsch, etc), producing significant reinforcement should be present.
differences in the results. The Cement and Concrete The fixing of closely-spaced reinforcement can usually
Association (C & CA) undertook a substantial series of be facilitated by detailing the steel in such a way that the
tests, presenting its findings in two research reports, the reinforcement required in the bottom of the deck to deal
first dealing with single anchorages and the second with with slab or diaphragm action can be fixed first.
group effects. These have formed a basis for most Anchorage-block reinforcement is then assembled on top
prestressed anchor-block design in the UK since that time. of this mat, followed by the top surface reinforcement
The prime requirement resulting from the calculations for the diaphragm or slab, which is assembled on top of
derived from these research reports is the need for heavy the bursting steel. The system of stirrups adopted must
reinforcement perpendicular to the axis of the prestressing permit this sequence.
cable and immediately behind the anchorage, to withstand For bursting steel itself many designers favour the use
the splitting forces arising from the wedge-like action of of a spiral immediately around the anchorage. This
the anchorage. follows from the development of an early form of
An additional requirement in the region of prestressing anchorage for small prestressing systems, which was
anchorages is the need to examine the way in which the constructed with fine-aggregate concrete inside a
forces disperse into the full section of the deck. For contiguously wound helix. The attraction of the spiral is
example, in a box-section deck groups of anchorages are its unquestionable effectiveness in all directions within
usually concentrated in concrete “anchor blocks” formed the plane of the splitting force, and the fact that it unites
by an enlargement of the web. The dispersal of these large a significant lump of concrete with the anchorage. Only
concentrated forces into the full cross-section gives rise in smaller stressing systems is this spiral adequate on its
to shearing and tensile stresses around the blocks. Each own, however, and a system of links, U-bars and straight
case requires individual assessment, assumptions being bars will often be needed to supplement the spiral. Where
made as to the flow of the forces, and reinforcement being conventional links are used care should be taken to detail
provided to cater for the shearing and tensile stresses that reinforcement to a shape which avoids a double thickness
result. Within the anchor blocks themselves the design of steel at the overlap closing the link. The close spacing
approach can be based on deep-beam theory. of reinforcement needed in an anchorage zone can be
The substantial amounts of reinforcement often prejudiced by employing avoidable laps of this kind.
necessary in the region of anchorages call for particular The design of anchor blocks forms the subject of
care in detailing. It is all too easy to adopt an arrangement Data Sheet 59 while Data Sheet 60 deals with anchor
of reinforcement which fits well on a drawing but proves blocks for external cables. Various types of anchorage
quite impossible to assemble on site. If there is a conflict for strand are illustrated on Data Sheet 61 and
between the need to provide the theoretical amount of appropriate design data are tabulated on Data Sheet
82
www.EngineeringBooksPdf.com
62. Data Sheet 63 illustrates some of the anchorage capacity is limited by flexural cracking, inclined tendons
systems that are available for prestressing methods that do not help.
use wire, and details of strand couplers are presented
on Data Sheet 64.
Ultimate moment of resistance
83
www.EngineeringBooksPdf.com
Prestressed concrete: elastic design
Data sheet No 53
The following mixes are selected as being the most appropriate for precast and
cast-in-situ work, respectively. Variations may be appropriate in particular jobs.
Compression in bending:
For HA loading 17.3 N/mm2
For HB loading 22.0 N/mm2
Tension (applied load) 0
Tension (prestress/dead load) 1 N/mm2
Shear : (see BE2/73 flow chart)
Tension 1 N/mm2
Site concrete
Compression in bending:
For HA loading 14.85 N/mm2
For HB loading 18.6 N/mm2
Working stresses:
84
www.EngineeringBooksPdf.com
Debonding
Data sheet No 54
Debonding/deflecting
One of the limitations on the design of pretensioned
units is that the arrangement of prestress which is most
effective at midspan, where some of the stresses induced
by prestressing are offset by the self-weight of the unit,
may produce unacceptable distributions of stress at the
support positions.
and thus
i.e., a = 11.55-8.3=3.25 m.
85
www.EngineeringBooksPdf.com
Parasitic forces
Data sheet No 55
86
www.EngineeringBooksPdf.com
Stress profile
Data sheet No 56
Effective eccentricity
of prestress
Stresses due to
prestress+self weight
87
www.EngineeringBooksPdf.com
Serial construction
Data sheet No 57
88
www.EngineeringBooksPdf.com
Loss of prestress
Data sheet No 58
89
www.EngineeringBooksPdf.com
Anchor block design
Data sheet No 59
Anchor block
Prestressing force=P0.
Crushing stress
Bursting force
Bursting reinforcement
where
90
www.EngineeringBooksPdf.com
Anchor blocks for external cables
Data sheet No 60
91
www.EngineeringBooksPdf.com
Strand anchorages
Data sheet No 61
92
www.EngineeringBooksPdf.com
Each prestressing system manufacturer
has his own stressing equipment. In
some circumstances there can be major
differences in the access to the jacking
point necessary, which may influence the
design details and/or the choice of
prestressing system employed.
93
www.EngineeringBooksPdf.com
Strand anchorage forces
Data sheet No 62
94
www.EngineeringBooksPdf.com
Wire anchorages
Data sheet No 63
A button-head.
95
www.EngineeringBooksPdf.com
Strand couplers
Data sheet No 64
96
www.EngineeringBooksPdf.com
Shear in prestressed concrete
Data sheet No 65
Zone A: High shear with nominal bending prestress Vp is taken into account for this condition.
Cracks do not develop up to failure, which may involve Zone C: High bending and shear
crushing or buckling of the web.
Cracks commence in the tension flange and extend up
into the web with increasing load. This can lead to
bending-shear failure as the reduced area of concrete in
Zone B: High shear with moderate bending compression is crushed. Shear cracks accelerate the
reduction of the effective concrete section.
Cracks develop in the web due to the principal tension
exceeding the tensile strength of the concrete. They
extend toward the flanges with increases in load.
Failure can occur due to shear-tension failure, or by
buckling of the web in compression.
Specimen calculation
Load case : 4 Beam section: Node 13
Shearing force per web S =0.26 MN
Overstress =25%
Sectional properties:
Interface width Ls =150 mm
Slab area A =0.493 m2
Height of slab c.g. above n.a. y =0.300 m
Moment of inertia of section I =0.086 m4
Longitudinal shearing force
=447 N/mm
Material properties:
Lesser cube strength of slab or beam ( 37.5) Uw=37.5 N/mm2
Permissible tensile strength of shearing reinforcement fs =175 N/mm2
Characteristic strength of reinforcement ( 425) fy =410 N/mm2
(Use 410 for high-yield steel, unless good reason)
Tensile stress at top of slab in hogging region ffc =—N/mm2
(assuming concrete uncracked)
Rules :
(i) Limiting longitudinal force
=478 N/mm
Rule (i) satisfied if > Q
(ii) Required steel in slab bottom excluding that for
coexistent bending
=436 mm2/m
Area of bottom reinforcement provided =900 mm2/m
Required steel cutting interface excluding that for
coexistent bending
(iii) Sagging region
=1606 mm2/m
98
www.EngineeringBooksPdf.com
Ultimate moments
Data sheet No 67
99
www.EngineeringBooksPdf.com
Prestressing ducts and saddles
Data sheet No 68
100
www.EngineeringBooksPdf.com
Data sheet No 68 Continued
101
www.EngineeringBooksPdf.com
Differential shrinkage
Data sheet No 69
Where a concrete section is
constructed in two stages involving
the placing of fresh concrete against
already mature material, differential
shrinkage will set up stresses in the
section, which may be significant. The
most obvious example of this is a
beam-and-slab deck.
102
www.EngineeringBooksPdf.com
Strand
Data sheet No 70
103
www.EngineeringBooksPdf.com
Strand relaxation
Data sheet No 71
For prestressed concrete the accepted procedure for 1000 hours. Relaxation is sensitive to stress and
design purposes is to allow for the relaxation of temperature, as is illustrated by the accompanying
prestressing steel on the basis of tests, taking the value graphs relating to British Ropes Dyform strand.
at 70% of the ultimate tensile strength and 20°C after
104
www.EngineeringBooksPdf.com
Prestressed concrete references
Data sheet No 72
105
www.EngineeringBooksPdf.com
CHAPTER 7
If man has always been as preoccupied with creature as well as for prestigous buildings. It might be
comforts as he is today it seems likely that his earliest appropriate to go to the expense and special effort of
efforts at producing a structure to span between cutting and transporting very large stones to create
supports would have been aimed at providing a roof impressive public buildings, but when it came to more
over his head, rather than at bridging a gap. Timber, utilitarian structures, such as bridges, a form of
vegetation and animal skins are likely materials to have construction had been needed which made use of the
formed his earliest attempts at a roof covering. Because more-readily-available small stones.
of the limited life of these materials the best evidence The circular arch form used by the Etruscans and
that remains as to these earliest techniques of Romans demanded a fixed relationship between rise and
construction is in the methods still adopted by primitive span. These peoples built barrel roofs as well as free-
peoples today. standing arches, to give long covered areas. It was also
A tree deliberately felled to provide a dry crossing of possible to form an intersection between barrel arches
a stream is presumed to have formed the first man-made crossing each other, but only where the intersecting barrels
bridge. As problems of transportation led to the adoption were of similar dimensions—otherwise problems of
of established routes and the heavy use of such crossings, stability would arise at the intersection. The circular arch
stone offered the prospect of a more durable material. therefore imposed severe limitations on the layout and
Its first application probably followed the use of appearance of buildings.
structural forms pioneered by heavy timbers; some Much Roman architecture still adhered to the
members standing on end (or stacked) to act as posts, traditions of columns and architraves adopted by the
while others were laid to span between these closely- Greeks. The arch seems to have been more extensively
spaced supports. used in bridge construction and in the creation of
Stone imposes severe limitations as to the distances that particular spectacles: triumphal arches and public
it will span in this way, not because of its tensile strength buildings. The fact that great men and national victories
but because of the practical limitations in the size of a single were commemorated by building arches reflects the
stone which can be cut and handled. The surviving heritage importance of such arches in the technology of the
of Greek and Egyptian architecture contains ample empire, almost amounting to the status of a national
examples of what has been achieved with this simple symbol.
structural form. Columns had to be closely spaced to restrict It was not until the 12th century that the concept of
beam action to short spans, and this had a constricting the Gothic arch was introduced, breaking away from the
effect on the layout of buildings, making it impossible to semi-circle, to adopt a form embodying a pointed apex.
achieve wide open spaces under the covering of a stone This change introduced flexibility into the relationship
canopy. The nearest approach was to adopt a colonnade between the span and the height of an arch, so that
of closely-spaced columns in two directions in the form of transepts could be created having a span differing from
a grid. Wide spaces could only be covered by using timber, the intercepted aisle. This gave a new degree of freedom
so that the development of techniques for jointing timbers in the planning of structures.
controlled progress in that respect. Pointed-arch forms also allowed greater spans, because
Despite their limitations, stone columns and architraves the horizontal thrust at the arch springing is of a lower
formed the basic structure for many magnificent buildings. magnitude than with the semi-circular form. This trend
Their durability cannot be questioned in the light of was further aided by the development of flying buttresses
examples that survive until today. Even in the UK, which which help to balance the horizontal forces. In this context
claims no special place in that architectural era, the well- the innovation of adding pinnacles to the buttresses might
known bridge at Tarr Steps in Devon represents a simple be regarded as an early example of prestressing—by
example of stone slab construction reputed to have been adding deadweight—aimed at stabilizing these complex
in service for up to 3,000 years (see Frontispiece). structural forms. Although these features were given
The development of the arch was a major elaborate decorative treatment by way of carving, their
breakthrough for construction using stone, now making prime function was (in most cases) structural rather than
it a material suitable for use in the construction of bridges ornamental.
106
www.EngineeringBooksPdf.com
When the processing of metals developed to the stage exploited in some framed girders by giving the compression
at which it could be applied to the construction of large boom an arch shape, the springings of the arch being tied
structures, its first use was based on the structural form together by a straight tensile member—the lower boom.
of an arch, reflecting the technology which had developed Stephenson’s design for the Conway Bridge represents an
from centuries of construction using stone. early suspension bridge, which was subjected to model
Iron Bridge in Shropshire is the first example of a metal testing as a means of proving the design.
bridge, which still stands as a monument to the skill and It was when mild steel was developed, offering a wide
craftsmanship of those who built it in 1799. The bridge range of rolled sections and plates, that truss and plate
at Coleport, built in 1818, is a further example. Both are girder forms were fully developed. Each of these forms
of arch construction, which is not the form best suited to found its best application within particular ranges of span.
metals. The early use of concrete shows yet another repetition
Cast iron, being weak in tension, tended to be used of the cycle associated with the introduction of new
primarily in compression members with only a limited materials, which start with the disadvantage of being
use for beam members. The development of wrought iron, applied to structural forms better suited to their
with its superior tensile qualities, opened the way for predecessors. It was inevitable that concrete should
further developments in structural form. initially be regarded as reconstituted stone and used in
The influence of earlier materials and the structural that context. People now knew the limitations of
forms to which they were applied have created pitfalls compression-only materials, and thus concrete had
for the designer as well as inhibiting the way in which obvious applications if the arch form were adopted.
a new material is first applied. The notorious weakness Reinforced concrete presented an opportunity to adopt
of cast iron in tension lured engineers into faulty design structural forms in parallel with those used for steel
in that, when early structures in wrought iron were sections, and the I-beam has become an established
built, great care was taken to test the strength of structural form utilized in reinforced and prestressed
members in tension but the phenomenon of buckling concrete structures. Some attempts were also made to
in long struts was not appreciated until accidents took build concrete structures of lattice girder form.
place. Because steel is produced by a rolling process, which
The capacity of wrought iron to accept tensile stresses gives long lengths of continuous members, the structural
opened the door to several new structural forms. Suspension forms that were created in steel were inevitably based on
cables became the tensile complement to the all- linear structural action. To provide adequate support for
compression arch. Frameworks were developed in which an area of floor or bridge deck it was necessary to create
some members acted in compression and others in tension. a grid with a primary, secondary, and sometimes tertiary
The well-known characteristics of the arch form were members spanning at right-angles to one another to cover
Figure 12. Temple of Bacchus. A remnant of the magnificence achieved with the simplest structural
forms.
107
www.EngineeringBooksPdf.com
Figure 13. Braidley Road Bridge, Bournemouth.
the area. But the potential merit of concrete is its ability forms were substantially influenced by earlier efforts at
to form shapes which can have a bi-directional structural building boxes in steel, where transverse stiffening
action, and to be moulded to give economy to suit those members and diaphragms are essential to prevent the box
two complementary actions. The voided slab or hollow buckling. In the case of concrete, however, experience has
box can be tailored to suit the varying requirements of shown that a satisfactory box structure can be achieved
relative longitudinal and transverse strengths at different without such stiffening diaphragms being needed,
points in a bridge deck, representing the effective use of resulting in substantial economies.
concrete in structural forms which are peculiarly its own The rate at which new materials become available for
and making optimum use of its inherent qualities. construction, and the parallel development of structural
The earliest efforts at building in concrete using box forms is accelerating rapidly. The column and architrave
108
www.EngineeringBooksPdf.com
and the arch each developed through a period somewhat in material would be to increase the range of application
excess of a millenium. Metal structures have been with us of cement-bound materials, rather than to extend the
for little more than a century and reinforced concrete has capability of existing structural applications. Even if
barely celebrated its jubilee. If this acceleration continues, fibre reinforcement were applied to conventional
structural engineers will have to foster a new flexibility in structural concrete construction, its impact on the
thought about structural form as they handle new materials. dimensions of beams and slabs would be only marginal.
However, fibre reinforcement makes it possible to
create very thin concrete sections compared with those
Future development
which can be formed with conventional reinforcement.
It is, of course, a good deal easier to review the past than to This opens up new possibilities for cement-bound facing
predict the avenues along which future development is likely panels which can be light in weight.
to take place. There is a natural tendency to feel that our A good deal of attention has also been given to the
methods of construction are well developed in the context possibility of developing prestressing tendons from non-
of the materials we have available. This has doubtless been corrosive materials. Although this might be useful in
the view of engineers of each generation. In fact the foregoing removing one cause for anxiety over the life of a
review seems to suggest that it is the availability of new prestressed structure, it would make no great impact on
materials which has paved the way for each break-through the design concept.
in constructional techniques, and that designers have been Turning attention to the structural forms adopted, it is
relatively slow to respond to each new material, and to find apparent that box construction has greatly increased in
the best use for it. popularity over recent years. Now that we have outgrown
There is limited scope for the exploitation of the tendency to provide complicated and unnecessary
concretes having significantly higher strengths than stiffeners at frequent intervals throughout a span, boxes
those available at present. The prime effect of utilizing are becoming progressively lighter in construction and
substantially stronger concrete would seem to be that this is likely to extend their range of application.
limitations on design would then be imposed by the The ribbon bridge has appeared on the scene in recent
requirements of stiffness rather than of strength. Fibre- years. This is a catenary of prestressed concrete forming
reinfored concrete is at present receiving a great deal what is, in effect, a stiff suspension cable. It has been
of attention, but it seems likely that the impact of this applied to footbridge construction, but although a ribbon
109
www.EngineeringBooksPdf.com
Figure 15. Erecting beam for hovercraft track.
highway bridge is theoretically possible, its appearance If we are to speculate on the future development of
is likely to be distressing. The marked sag is too suggestive structural forms, it is perhaps easier to imagine the
of imminent collapse to be acceptable. potential impact of new types of problem. The tracked
Some interesting work has been done on the possible hovercraft is a case in point: the requirement for long
applications of triaxial prestressing. We know that the lengths of elevated structure, narrow in width and
weakness of concrete as a material is due to its limited demanding very high standards of tolerance to admit the
tensile strength, so that if it can be maintained in a anticipated speed of vehicles of this type imposes severe
compressive state on all axes, its potential strength is demands on constructional tolerance. The experimental
very high. A cylindrical element of concrete can be track erected on the fens in East Anglia was based on
maintained in a state of triaxial precompression by pretensioned precast concrete box construction, for which
winding a tensioned wire around it, or by enclosing the a very high standard of tolerance was achieved.
concrete within a steel tube. This results in a member There is a good deal of excitement in being involved
that is capable of resisting very much higher axial forces with new developments, but this is not a goal to be pursued
than would be acceptable on a comparable cylinder of for its own sake. The rôle of the designer is to produce an
concrete not reinforced in one of these ways. Some work economic and pleasing solution rather than a novel one.
carried out in the USSR has considered the theoretical Concrete is firmly established as the principal material
possibilities of building trusses of concrete maintained for bridge construction in the short-span to medium-span
in triaxial compression by a spiral winding of wire. It is range. The prime effort of designers should be directed
hard to believe that a structure of this form would be toward ensuring that the structures we build do not
competitive with the alternative steel structure, however. detract from their environment.
110
www.EngineeringBooksPdf.com
CHAPTER 8
111
www.EngineeringBooksPdf.com
Approach to analysis loading case, in the light of the pattern of deformation
that is anticipated.
To design a structure which will give good service an The torsional resistance of a cellular deck results from
engineer needs to evaluate the forces and stresses two primary components, shear flow in the webs and
developed within its various components under service shear flow in the top and bottom slabs. A rectangular
conditions. This requires an appreciation of how the cell subjected to torsion develops shear flow of a pattern
structure is behaving, which may be aided by analogies which means that the vertical (web) members make a
with structures which will lend themselves to contribution to the torsional resistance which is equal to
mathematical solution. that afforded by the top and bottom slabs.
It is important for the designer to maintain the A grillage subjected to torsion develops a system of
realization that any mathematical analysis carried out is reacting forces consisting of three components.
an analogy that is not always truly representative of the
way in which the real structure would behave. Too great A torsional shear in the longitudinal members in
a reliance on the quantitative answers arising from some association with torsion in the transverse members.
form of mathematical analysis may be indicative of a lack A differential flexural shear in the longitudinal
of engineering judgement. members, due to non-uniform load sharing.
Methods of analysis are evaluated by comparing the Torsional moments in the longitudinal members with
results with those given by laboratory tests carried out on associated flexure of the transverse members.
models. Considerable progress has been made towards
making models representative of prototype structures, but The torsional moments evaluated in the longitudinal
heavy reliance is still placed on measuring the deflected members by using a grillage are inevitably under-
shape under load because of the difficulties in attempting estimated: assuming the stiffnesses of transverse members
to measure strains, which may be more directly related to have been correctly evaluated, an appropriate amount of
the stresses developed. The fact that a good comparison is shear flow will develop in the webs. To this will be added
achieved between the displacements obtained on a the differential flexural shear reflecting the load-sharing
laboratory model and on an analytical mathematical model pattern of the longitudinal members. A grillage will only
does not, in itself, mean that they are both predicting the use the torsional stiffness of the longitudinal members to
same pattern of stresses. So the results of mathematical make up the deficiency in equilibrium. If use is made of
analyses still need to be approached with caution. these longitudinal torsions to evaluate the flow of shear
Grillage analysis is the most widely used in the top and bottom plates, this will inevitably give a
mathematical model, and the type of deck structure value which is less than that in the vertical webs, which
most difficult to represent in this way is a cellular must be equal in terms of force per unit perimeter.
deck, whether this is a voided slab or a box form of Stiffnesses assigned to transverse members of the
construction. The difficulties arise from the fact that grillage have a two-fold effect: they give rise to torsional
the grillage is two-dimensional only, whereas a cellular moments which can be used to evaluate the flow of shear
deck behaves in a three-dimensional manner. A in the top and bottom slabs, and they modify the bending
consideration of these differences can be a valuable moments in the longitudinal grillage members, inducing
aid to understanding both the cellular deck and the shears which represent the flow of shear within the webs
analytical limitations of a grillage. of the box. It is this which gives the grillage bending-
moment diagrams their characteristic saw-toothed shape.
In a grillage representing a multi-celled box the pattern
Torsion of torsion in the transverse members within the various
“bays” of the grillage shows the build-up of torsion from
There are fundamental differences between a grillage and the edges of the box inward. Intermediate longitudinal
a cellular bridge deck in relation to the forces and stresses members are influenced only by the change in torsion
which arise due to torsion. Elementary considerations of along a transverse member, on each side of the node at
equilibrium demand that a shearing stress in one plane which they intersect.
can only co-exist with a shearing stress of equal intensity In considering a particular cross-section of deck, the
in the complementary plane. In the case of a simple beam transverse members reflect the torsion on the basis of the
this means that shearing stresses of equal intensity are twist along that line. But the shear flow in the webs will
present over a vertical cross-section and in the be a product of the twist in the adjoining transverse
complementary horizontal plane. In the case of the top members also, which may be some distance away and
or bottom slab of a cellular deck, the implication is that possibly subject to a significantly different twist, because
shear flow arising from torsion is of equal intensity over of the deflected shape of the deck. To this extent the shear
both transverse and longitudinal sections through the flows evaluated are misrepresented.
deck, at any one point. By contrast with this there is no It follows that the transverse members are the better
interdependence between the longitudinal and transverse source of values for the torsion within a grillage. However,
torsional moments within a grillage. Balanced results can if shear flexibility has been incorporated in the grillage
only be achieved by carefully evaluating the sectional sectional properties this will have the effect of increasing
properties. To obtain accurate values for torsion using a the differential deflection between the longitudinal
grillage, which might be directly applied to the real members and, therefore, correspondingly increasing the
structure, it is necessary to re-assess the torsional twist in the longitudinal members connecting them. The
stiffnesses of the component members for each individual torsion in the transverse members is therefore overstated.
112
www.EngineeringBooksPdf.com
It has long been realized that grillages are not Sectional properties
particularly sensitive to torsion, in that variations in the
torsional stiffnesses assigned to the members make no In assigning stiffnesses to the grillage members it can
dramatic impact on the predicted behaviour of the grillage appear for many decks that the arbitrary division of the
in flexure—provided that the local “saw-tooth” effects deck into separate members by intersection lines at the
are ironed out when interpreting the results. This is just mid-points between the members will give an adequate
as well, because the grillage gives a poor representation result. In the case of a deck having sloping webs, however,
of the torsional moments present. Fortunately, these it is apparent that such an intersection line would result
moments are not difficult to evaluate by another means. in the outer members having very low moments of inertia,
This is less true when variations in the plan geometry with the position of the neutral axis changing abruptly
take place, either in the form of introducing skewed or from one member to another, whereas it has been
non-symmetrically arranged supports. In these cases it is demonstrated that such changes in the level of the neutral
more important to fit the torsional stiffnesses to the results. axis do not actually take place. Obviously the total
Clearly, the prime contributors to torsional stiffness stiffness should be correct, and this stiffness could be
are the top and bottom slabs. Where diaphragms are distributed in proportion to the respective areas of the
present within the depth of a deck, a consideration of members or purely as a matter of judgement.
membrane analogy for torsion will readily show that the Depending on the proportions of a structure, it may
flow of torsional shear in a diaphragm member is only be necessary to take shear lag into account in assigning
the difference in the flow of shear in the top and bottom stiffnesses to grillage members.
slabs as they cross the diaphragm. The torsional stiffness is evaluated from the opposing
shearing action of the top and bottom slabs, giving a
torsional constant of one-half of that which arises from
Grillage mesh considering the closed section as a thin-walled box.
This halving was found many years ago to best fit the
Where a bridge deck is formed of a small number of cells, experimental results, but no satisfactory explanation
it is appropriate to place the longitudinal grillage members has been given as to why this should be the case for a
along the axes of the web members. Where there are cellular deck when the full calculated figure is used for
sloping webs, the grillage members should be placed along other forms of construction. The explanation may be
the lines of intersection between the web and the top or in the equal contributions of torsion in the members,
bottom slab. and the adjusted shears in the intersecting members.
Excessive preoccupation with torsion might lead to
the conclusion that longitudinal members would best
be placed along the centre-lines of the cells, but in fact Shear lag
it is better to place such members along the web axes
to obtain the best representation of the transverse According to the basic assumptions of simple beam
flexural characteristics of the deck. The torsional values theory—where cross-sections remain plane after flexure—
included in the output are rarely directly applicable, in the distribution of stress across the top flange of a beam
any case. is constant. In a broad-flanged T- or I-section, this
For a multi-celled deck which approaches the assumption is not true except for sections which are far
characteristics of an orthotropic plate in its behaviour, from a point of contraflexure. At a point of contraflexure
there is no need to align the grillage members with the section is subjected to shearing force but no bending
individual webs. Suggested guide-lines for the selection moment. Zero moment implies that there is no direct stress
of the number of longitudinal grillage members are that in the flanges, while shear on the section indicates that
five or more members should be considered, and that the there are horizontal shearing stresses reducing in intensity
spacing of the longitudinal members should not exceed toward the extremities of the section. In the case of a
one-half of the width of a traffic lane, or one-and-a-half broad flanged I-section this means that the horizontal
times the overall depth of the deck, whichever is the lesser. shear flow diminishes to zero at the outer edges of the
Transverse grillage members must be placed along flange. Away from the point of contraflexure direct
the line of each diaphragm in a structure. Additional stresses are present because of the moment on the section,
transverse members are also needed to reflect the load- and the shearing stresses are modified. As with the case
sharing characteristics of the deck. The frequency of of simple bending theory for beams, the horizontal shear
these members should be such that the differences flow and direct stresses are inter-related, and what is
between the analytical model and the real structure do happening may be visualized in terms of the shear flow
not dominate the output, and thereby obscure injecting direct stresses into the flange. The build-up of
interpretation. West* has suggested that transverse these direct stresses resulting from the shear flow is not
members should be placed at intervals not exceeding uniform across the width of the wide flange, but produces
twice the spacing of the longitudinal members. In any stresses which tail off toward the extremities, until a
event, the adoption of less than five intermediate distance is attained that is far enough from the point of
transverse members produces results in which the contraflexure for the pattern of stresses to have reached
interpretation of the values at the intersection points of a balance which produces uniform direct stress. The effects
the grillage members could obscure the results. associated with this change of distribution of direct stress
are known as “shear lag.”
* See reference on Data Sheet 76. In order to assess the peak stresses in such a section,
113
www.EngineeringBooksPdf.com
the commonly adopted procedure is to calculate the suggests a change in the position of the neutral axis when
sectional properties on the basis of a reduced (so-called considering moments.
“effective”) flange width. CP 110 and CP 117
recommend methods of assessing this reduced width.
An exact assessment of the effects of shear lag involves Distortion
recourse to plate theory, because the effect is a function
of each particular loading case as well as of the plate When a concentrated load is applied over a single beam
dimensions. within the width of an open-spaced beam-and-slab deck,
With continuous bridge decks the effects of shear lag some load-sharing clearly takes place with adjacent
are most significant at the intermediate supports. The beams, but the member directly under the load obviously
recommendation of CP 110 (i.e. that the effective flange deflects more than the others, and the slab which provides
widths are assessed on the assumption of points of the transverse link between beams is therefore deformed.
contraflexure at distances of 0.7 of the span apart) can With a multi-celled box, similar deformations occur to
produce substantial errors at the support section. A the cross-section when the loads are applied over a single
reasonable compromise is to evaluate the effects of shear web, but the cross-section is now a closed frame and the
lag on the basis of the points of contraflexure which arise webs of a multi-celled box are not free to rotate in the
on a given structure under a uniformly distributed load way that is possible in a beam-and-slab deck, because
although, strictly speaking, these positions should be re- they are tied laterally, top and bottom. The pattern of
evaluated for each loading case. deformation and the resulting force system are akin to
Since shear lag reduces the effective stiffness of a those of a Vierendeel girder.
member in addition to modifying the distribution of The term “distortion” which is applied to this pattern
stresses across it, improved accuracy can be obtained of deformation can be misleading because it inevitably
from a grillage analysis if the “effective” sectional becomes associated with torsion, which is not necessarily
properties, arising from shear lag, are used in the grillage. the case. In fact, by considering a twin-celled box subjected
This may redistribute some moment away from those to distortion by a concentrated load over the central web
sections modified by shear lag, thereby reducing the it is evident that the force system which develops can be
resultant stresses. in equilibrium without imparting any torsional rotation
Where it is needed, a good picture of the distribution to the deck. Distortion is therefore essentially the effect
of stresses across the width of a plate can be obtained by of differential deflection between adjacent longitudinal
plotting those stresses which arise from the net “effective” “members”.
sectional properties, together with those arising from the Because of distortion, a cellular deck has a dual stiffness
gross sectional properties. The curved distribution of stress transversely. Circular bending across the deck results in
across the flange can then be sketched. direct tension and compression in the top and bottom
When applying shear lag to a box deck, the sectional slabs, thereby forming a couple to resist the bending
properties of the reduced section can imply a different moments. No distortion is involved. On the other hand,
neutral-axis position to that which applies to the gross where there is a transfer of shear across the deck, this
section. For a prestressed beam having varying sectional gives rise to distortion and the stiffness of the deck is
properties, it is well known that if the neutral axis now totally different from that which applies to circular
changes in level this, in itself, modifies the moment bending. Most real loading cases produce a combination
applied by the prestress. However, in the case of a change of these two effects. It is therefore essential that a grillage
in the position of the neutral axis due to shear lag, this should be capable of handling this duality of stiffness.
is not the case. In calculating the deflections of a beam, it is normal to
The forces produced by the prestress can be considered consider only those deformations which arise due to
as two separate elements: the horizontal force applied to bending. A full mathematical expression of the deflection
the deck and the bending moments produced by the cable in a beam includes the deformations arising as a result of
profile. In the case of a beam with varying sectional shear, in addition to those due to flexure. But shear
properties a change in the position of the neutral axis deformations are normally neglected because they are very
modifies the stresses produced by the horizontal force in small by comparison with those due to bending. To enable
the same way that a direct load on a column produces the transverse members of a grillage to take account of
varying stresses if the sectional properties change— the dual stiffnesses applicable to bending and to shear,
because of the changing eccentricity of the load at each grillage programs have been written that include the full
section. This analogy cannot be adopted in shear-lag deflection equations, including shear. It is therefore
calculations because differing rates of shear lag apply to possible to take account of the dual stiffness of a cellular
the horizontal load due to the prestress, and to the bending section by calculating a shear area for the transverse
moments. For the horizontal load, shear lag affects only members which would give the same rate of deformation
those regions adjacent to the anchorages where the as that which, in reality, arises from distortion.
horizontal force is applied. The fact that the stresses The calculation of this “effective shear area” is based
induced by bending moments arising from the vertical on assumptions of how the cross-section deforms. This
forces applied by changes in direction of the prestressing will, in fact, differ according to the loading case applied.
cable are subject to shear lag does not, in itself, modify In the case of a heavy load applied at one edge of a deck,
the stresses produced by the horizontal force. all the cells deform in a similar manner, including the
No adjustment is therefore needed to the stresses arising flexure of the webs themselves. In contrast, a heavy load
from axial prestress, even though the shear lag phenomena placed in the middle of the deck, which is such that the
114
www.EngineeringBooksPdf.com
force systems are in balance on each side of the point of a skewed deck, it is often sufficient to allow the orthogonal
application, means that the web under the load does not grillage members to represent the stiffness of the cellular
flex (because there is no moment in it). section, and to superimpose on this a diaphragm—usually
In the case of thin-webbed boxes, the presence or in a skewed direction—which is assigned a flexural stiffness
otherwise of flexure in the webs may significantly affect equal to its own nett dimensions, and a shear area equal to
the stiffness of the cell. The shear area assigned to the its actual cross-sectional area.
transverse members can therefore only approximate the It is within a skewed deck that the accurate assessment
distortional stiffness, but in most practical bridge-deck of the torsional stiffness becomes more significant as
sections the top and bottom slab elements are considerably otherwise the torsions introduced in the areas of skew
more flexible than the webs so this error is not serious. support will not be evaluated realistically.
Where there are variations in the shape of the cross- Variations in the plan geometry of a deck can introduce
section, such as sloping webs, which complicate the problems of tapering cells, which make the adoption of
assessment of the distortional flexibility, this can be assessed an orthogonal grillage impossible.
with the aid of a frame representing the cross-sectional In a majority of cellular structures diaphragm members
shape. The deformation of the frame under the load are contained within the depth of the deck. The force
provides a basis for assessing the “effective shear area”. systems resulting from the grillage at the intersections
Having obtained the grillage output, the force system between the diaphragm and the web members are not
arising from deformation is calculated by assuming that necessary directly applicable to these members themselves.
points of contraflexure develop midway between the webs, They represent the force field in the total deck and, in
and that the total shear from the grillage is shared between most instances, the web diaphragm members will not be
the top and bottom slabs in proportion to their stiffnesses. significantly affected by the torsions, which will be resisted
In designing reinforcement or determining the prestress by the top and bottom slabs. Any attempt to design an
required to cater for the forces developing around the intersection between such members for the torsion which
cross-section, the values are dominated by those forces a grillage analysis implies is transmitted through the
which arise from local wheel loads. These are best connection is therefore a mis-directed effort.
evaluated by applying Pucher’s* or a similar design
method for concentrated loads. The distortional stresses
are significant, but they are small in comparison with the Loading cases
results of local wheel loads.
In cases where cellular construction is used in separate In any structure which is prestressed the forces developed
sections within the cross-section of a deck, the sections by the prestressing force are intended to oppose those arising
being linked together by slabs which are made monolithic from applied loading. Whenever the geometry of the deck is
with the adjoining cellular elements, the distortional such that it will induce a complex system of forces, the
stresses arising in these linking slabs are also obtainable intensity of these resultant forces in the real structure will be
from a grillage analysis. In such cases the distortional reduced by the opposition between the prestress and the
stresses can be very much more prominent in the total applied loading. It is therefore of fundamental importance
design figures (see Data Sheet 42). to include the prestress as a loading case in any analysis.
In bridge decks having simple geometry it can be
sufficient to use the grillage merely to get a picture of the
Voided slabs distribution of moments across the width of the deck,
and then to resort to continuous-beam calculations to
When the method of “effective shear area” is applied to obtain the actual design figures.
a slab having circular voids, it is sufficient to assess the In many instances the optimum value can be obtained
deformation of the cross-section on the assumption of a from a grillage analysis by applying axle loads at intervals
simplified cross-section which has rectangular voids that along the span as individual loading cases which then
give slab and web thicknesses that are slightly greater form the basis of influence lines. The benefit to be obtained
than the actual minimum thicknesses at these locations. from this, as opposed to employing a full HB vehicle as a
loading case, is that any local effects can be more closely
identified and evaluated.
Skew In all cases it is recommended that the loads should be
applied to the longitudinal members forming the grillage
Because of the difficulties which arise in evaluating only, so that the transverse members reflect the forces
torsional parameters, the values obtainable for a grillage arising from distortion, without adding the complication
with members intersecting other than at right-angles are of the effects of local loads.
subject to error. The skewed deck should therefore be
constructed with an orthogonal grillage, apart from the
need to show the diaphragms in their real location. Data sheets
In many instances it is likely that the dominant difference
in stiffness between the diaphragm and the other parts of The force system employed in grillage analysis is
the deck is the increased shearing stiffness. Although illustrated on Data Sheet 73, while Data Sheet 74 is
difficulties inevitably arise from overlapping members within devoted to the use of a grillage to analyse a cellular deck.
The interpretation of the results obtained from an analysis
* See reference on Data Sheet 52. using a grillage is illustrated on Data Sheet 75.
115
www.EngineeringBooksPdf.com
Grillage force system
Data sheet No 73
116
www.EngineeringBooksPdf.com
Grillage analogy
Data sheet No 74
(1)
(2)
(3)
(4)
(5)
(6)
(7)
117
www.EngineeringBooksPdf.com
Data sheet No 74 Continued
(8)
(9)
118
www.EngineeringBooksPdf.com
Grillage interpretation
Data sheet No 75
119
www.EngineeringBooksPdf.com
Structural analysis references
Data sheet No 76
120
www.EngineeringBooksPdf.com
CHAPTER 9
Electronic calculators
The use of computers to undertake calculations is usually therefore expected to carry out those analytical tasks
associated with the need to process large quantities of previously undertaken by equipment remote from the
numerical data, as in the case of accounting systems, or office. However, the time required to prepare programs
to carry out complex mathematical manipulations using to deal with problems of such magnitude, and the
large quantities of data. For these reasons, in the initial potential restrictions imposed by the limited capacity of
development of computers much emphasis was placed desk-top machines, can make that approach difficult. A
on size and speed of operation. The complexity of the better way to utilize such a machine is to explore the
equipment and its mode of operation tended to restrict potential of having at hand equipment that is capable of
the use of computers to large problems only, where it dealing with programs specifically written to tackle the
was economic to make use of staff with very specialized problems encountered within a particular office, and to
knowledge of computer systems. However, computer present the results in a format convenient to that office.
languages have now become more orientated towards the One advantage of a programmed calculation is that it
non-specialized user, making computerized calculation gives output of a consistent format, however many times
increasingly attractive for certain types of engineering the calculations are carried out, whereas hand calculations
problems. Even so, this has generally been restricted to a may tend to become rather sketchy after a number of
basic structural analysis for a bridge deck, for example, repetitions. Simple diagrams can also be created as part
rather than the normal routines of engineering of the output, as aids to the interpretation of results or to
calculations. check the input data.
One inherent disadvantage in using a computer is the In this way the desk-top calculator represents a
inevitable delay between preparing the data relating to the computer which can be made to handle problems in the
problem and getting the result. Many organizations employ way that we choose, rather than one that has to take
the basis of sending data away to a computer bureau and advantage of whatever facilities happen to exist, as is the
are thus inevitably subjected to postal and processing delays case with bureaux programs. Data can be stored as a
before the answers are received. Another point is that problem progresses, and re-entered or modified for
programs available through bureaux have generally been subsequent stages in processing a problem. Methods of
designed for widespread use or to tackle a series of entering data to run a program can be modelled to suit
associated problems, and a particular program is therefore the particular needs of the user. A certain interaction
inevitably not written with the specific needs of an between the machine and the user can be established by
individual user in mind. Indeed, in some instances, arranging for the input data to be called for by a series of
programs leave much to be desired in terms of convenience questions from the machine, rather expecting the user to
for the user. be schooled in a particular sequence and format for
The increasing popularity in the use of terminals that entering data. This can be an aid to intelligent thought as
are linked from remote points to a single computer, on a the calculations proceed, as opposed to the blind entering
time-sharing basis, has removed some of the delay in of digits in a mechanical sequence.
processing results, but available programs are still of the Given these facilities, decisions must be made as to
generalized type with the inevitable limitations that this what types of problem should best be computerized to
imposes. The opportunity to write specific programs is give the maximum productive benefits. To be beneficial,
available when such terminals are used, but in practice a program must deal with calculations which either
this is not an attractive proposition for anything more involve a great deal of repetition (so that the machine
complex than minor calculations. Also the bulk of the relieves the engineer from the tedium of repetitive
data that must be entered can often require long periods arithmetical calculations), or of a complexity not readily
of time to be spent at the terminal by personnel whose dealt with by hand.
training and skills would be better used in other ways. Because design involves a large element of trial and error,
Desk-top computers are now reaching levels of there is ample scope for relieving the designer of the tedium
capability which make them adequate to process many of repetitive calculation. For example, in designing a
of the calculating requirements of a design office. The prestressed concrete beam it is necessary to calculate the
first reaction may be to feel that a desk-top computer is stresses in various sections at all stages of loading. In
121
www.EngineeringBooksPdf.com
Figure 16. Concrete cube results.
122
www.EngineeringBooksPdf.com
Figure 17. Plate pier design.
123
www.EngineeringBooksPdf.com
Figure 18. Continuous beam.
124
www.EngineeringBooksPdf.com
Figure 19. Bending schedules.
125
www.EngineeringBooksPdf.com
Figure 20. Grillage.
126
www.EngineeringBooksPdf.com
Figure 21. Prestressing calculations.
127
www.EngineeringBooksPdf.com
Figure 22. Tender comparison.
128
www.EngineeringBooksPdf.com
developing the design, adjustments may need to be made programmed calculations by adopting the approach of
to the sectional properties, to the prestressing force and analysing a section given by the engineer, rather than by
to its eccentricity—even assuming that the moments due trying to evolve design equations. In some cases it may
to the applied loading were correctly calculated initially. be possible to prepare a program that incorporates
There are other types of calculation where precise analysis automatic convergance on required output, but in many
can only be approached on a trial-and-error basis, such instances the intervention of the operator will be necessary
as evaluating the stresses in a column section that is subject to move toward the desired solution. Indeed the latter
to load which is eccentric about both axes. makes better use of the equipment because it means that
Accepting that much design is a matter of trial and the design process remains in the control of the engineer,
error, it is often possible to make the best use of who can then experiment with various solutions.
129
www.EngineeringBooksPdf.com
CHAPTER 10
Economic evaluation
Where the form of construction chosen for each Great emphasis has been placed at times on the
component of a bridge is functional, well proportioned potential economies arising from precasting, but prices
and appropriate for the conditions imposed by the layout obtained against contracts where both precast and cast-
and location of the structure, then it is likely that the in-situ designs have been prepared often suggest a different
overall solution is an economic one. The appropriateness story from the general climate of opinion at the time.
of various forms of construction to differing situations There are no permanent rules about the comparative
and ranges of span is a judgement usually attributed to costs of differing solutions for construction, because
experience. Economics are a fundamental consideration, changes take place in the relative cost and availability of
and involvement in the design and construction of varying labour and materials from one time to another, and
types of structure is the best means of developing a keen developments in constructional techniques or new
sense of their suitability in differing situations. It is not materials can also make a significant impact.
often that a detailed assessment has to be made of the In the UK alternative designs are seldom produced at
relative cost of alternatives, because most offices have a the tendering stage. Where this does happen the
fund of knowledge from which conclusions can be drawn opportunity has often been created by the original design
without the need to resort to specific calculations. having been poorly conceived. It is therefore a mistake to
Optimization calculations, whether for material base judgements on such incidents without a full
content or for cost, are more commonly a subject for knowledge of the circumstances.
debate in the academic sphere than among practical There are inevitable difficulties in forecasting the cost
engineers. It is certainly a waste of effort to carry out of civil engineering works, and these are aggravated
lengthy calculations on optimization for component parts during times of economic uncertainty or rapid inflation.
within a solution which is itself inappropriate. In most Quite apart from the general financial climate of the
engineering design situations there are myriad practical country, the rates adopted by contractors are obviously
constraints on the proportions and options open and, in influenced by their current work-load, so that keen pricing
any event, for the design of bridges of small to medium cannot be expected during a period when the construction
span there is only a limited choice of possible forms of industry is heavily committed.
construction. If there are difficulties about forecasting the overall
There is, however, a place for a calculated assessment cost of civil engineering works these problems are
of the relationship between the cost of alternatives, accentuated when it comes to identifying the cost of
whether such alternatives are differing constructional component parts within a contract. Costs in tenders
forms or for the optimum proportions within a given type submitted by several contractors frequently show marked
of structure. disparities in the sums of money assigned to individual
Some of the most commonly-quoted factors relating portions of the work, even where the total tender prices
to economy can yield disappointing results. It is often may be comparable. Bridge designers have always been
stated that contractors prefer methods of construction sensitive to this problem because the cost of the bridges
which are speedy to erect. Once committed to a project is commonly only part of the total cost of a highway
the contractor’s preferences are likely to be very much project. There may therefore be wide discrepancies
orientated in that direction, but this is not to say that he between the prices placed against bridgeworks by different
would give the best tender price for the solution which competitors, within overall tender prices which may be
offers the most rapid construction. close. There can also be widely differing rates against
Within a highway contract there may well be individual measured items on what appears to be comparable work
structures which are critical in terms of allowing access within separate contracts.
through a site, but differences in the overall cost on the A tenderer’s policy may involve putting large sums of
project which might result from the delayed or early money against certain sections of the work because they
completion of such a structure are unlikely to be reflected will be completed early and the money thus recouped at
in the costs attributed to it in the bills of quantities so an early stage in the contract, or because he anticipates
that, even where rapid erection is an important economic other financial benefits, perhaps as a result of anticipated
factor, evidence to support this may be hard to find. claims relating to that portion of the work. All such factors
130
www.EngineeringBooksPdf.com
Figure 23. Comparison of equivalent concrete thickness of bridge decks.
can distort data selected from tenders as a basis for the soffit formwork will therefore not invalidate the
building records of cost information. comparison although they will misrepresent the total
Whatever the difficulties may be, however, the problem cost. On the other hand an error in selecting the
still remains that the cost must be forecast and the designer correct rate for the reinforcement or the prestressing
has to make decisions about a choice of forms of equipment could seriously distort the picture, and
construction with a view to achieving an economic design. errors in the rate chosen for the concrete would also
In order to make valid cost comparisons between be significant.
alternative solutions there are two important factors to Having identified the significant rates, the degree of
guide any evaluation. These are that comparisons should sensitivity of the comparison to the sums of money put
be made on a common basis, and that significantly varying against them can be established, which usually leads to a
items should be identified so that they can be examined sound judgement as to the validity of the comparison.
more closely where necessary. For example, in making a Obviously, the greatest difficulty arises in making
comparison between the relative costs of box construction comparisons between work that is not similar. A
or of a voided slab, the soffit formwork will represent a comparison of the difference between deep spread footings
substantial proportion of the total cost, but the difference in difficult ground and the use of piling, would be sensitive
in the cost of the formwork required whichever form of to certain rates which therefore require detailed
construction is adopted will be negligible. Errors in pricing examination to confirm their reliability.
Figure 24. Specimen rate for providing and installing prestressing cable.
131
www.EngineeringBooksPdf.com
One must also be alert to the fact that similar items There can be other valuable guidelines to the
may demand significantly different rates within alternative economy of a form of construction, apart from direct
solutions. An obvious example is the formwork required calculations of cost. For example, the content of
to abutment wall construction if the options are between materials—concrete, reinforcement or prestressing
a plain surface for a cantilevered wall, and the shaping steel—expressed per unit area of bridge deck and
required to form counterforts. The rates for the formwork plotted against the span in the form of a graph is a
in such cases will be markedly different. useful guideline to economy; such a graph is illustrated
It is also important to identify an appropriate unit for in Figure 23.
making cost comparisons. It can be misleading to assume Data Sheets 77 to 81 give general guidance concerning
idealized conditions when making comparisons between economic evaluation. Data Sheet 77 is devoted to
alternatives. Most choices of this kind bring in their wake economic trends when using voided-slab or box decks
a number of peripheral issues, some of which may be while the general relationships between span and cost
significant in terms of cost. for various types of construction are illustrated on Data
It can be very satisfying to produce comparative estimates Sheet 78. Data Sheet 79 discusses the determination of
and to see figures purporting to demonstrate a particular the economic depth of a voided-slab deck, Data Sheet
conclusion, but with so many pitfalls involved in forecasting 80 is devoted to the relative costs of different types of
the cost of alternative forms of construction, perhaps the abutment construction, and Data Sheet 81 illustrates the
most important aspect of any economic assessment is a economic trends relating to hollow-abutment
proper evaluation of the validity of such figures. construction.
132
www.EngineeringBooksPdf.com
Trends in deck costs
Data sheet No 77
133
www.EngineeringBooksPdf.com
Economic span
Data sheet No 78
134
www.EngineeringBooksPdf.com
Economic depth—voided slab
Data sheet No 79
135
www.EngineeringBooksPdf.com
Abutments
Data sheet No 80
136
www.EngineeringBooksPdf.com
Hollow abutment
Data sheet No 81
The cost of the deck slab on the abutment is obviously Within the hollow construction the side-walls are
proportional to its area, except that any supports simple props, whereas behind the rear wall they act as
provided within the hollow abutment will be more retaining walls, becoming more expensive with
expensive as their height increases. increases in height.
137
www.EngineeringBooksPdf.com
CHAPTER 11
Contract documents
138
www.EngineeringBooksPdf.com
adopted he can send out enquiries to manufacturers Bills of quantities
before the main tenders are invited, make a selection of
specific types of bearing from several suppliers, and The Department of the Environment has published a
include in the documents a schedule of bearings from method of measuring quantities specifically related to
these several suppliers which may be used. In this way highways contracts: the “Method of measurement for
the main contractor is given a choice, commercial road and bridge works” (MMRB). The initial desire to
competition is maintained, but the difficulty is avoided produce a simplified bill with a small number of items is
of having bearings offered by the main contractor from to be applauded. At the same time the writers strayed
a source which is unknown or of a type which the from the underlying principle of the “Standard method
engineer does not feel best fits the circumstances. of measurement for civil engineering quantities”, which
is based on the initial premise that every item relates to
Conditions of contract completed work and includes all the materials, labour,
plant and other costs involved. The MMRB gives a
The Institution of Civil Engineers published in 1974 the detailed item coverage for each item within the bill of
fifth edition of the “General conditions of contract for civil quantities. If the writing of a particular bill requires the
engineering works”. These form the usual basis for contract introduction of items not included in the MMRB, then
documents in the UK. Where third parties are involved in new item coverage has to be written.
a contract it is often necessary to include additional The weakness of this system is that it is too easy to
conditions to meet their particular requirements. The most overlook detailed factors contributing to the overall
common of these parties are the statutory undertakers: cost. In the light of the number of revisions that have
electricity, gas, water and telephones. Other public bodies already had to be made it is apparent that this has been
may also be involved, such as British Rail, the National the case.
Trust and local authorities.
139
www.EngineeringBooksPdf.com
Contract documents
Data sheet No 82
140
www.EngineeringBooksPdf.com
CHAPTER 12
Contract supervision
The brunt of the work involved in supervising the written brief to be given to each member of the Resident
construction of bridgework falls on the Engineer’s Engineer’s staff. These briefs will require writing to suit
representative on the site, and it is important that he the actual staffing arrangements on individual contracts.
should have a clear understanding of what is expected in
this rôle. The obvious need for previous experience in the
practicalities of construction and an appreciation of the Training
design of the structures to be built are not necessarily of
themselves sufficient to equip an engineer to fulfill the Resident Engineer’s staff are often undertaking this work
rôle of Resident Engineer. Specific guidance should be for a limited period, in order to gain experience of
given to the person about to take up the appointment, construction. This aspect of the job should not be lost sight
and a written brief setting out the main functions of the of under the pressures of getting the job done. It is important
job can be a valuable aid. Obviously no document of this for the individual, for his employers and for the profession
type can be comprehensive, but it may provide a valuable as a whole that the experience gained should be of the greatest
starting point for anyone commencing in such an value. Engineering staff should therefore be given the
unfamiliar rôle. maximum opportunities to understand, and to partake in,
Specific details of the brief should be varied to suit the all aspects of administering the contract. Rigid job
scope and nature of the work, and the experience of the demarcation is an unnecessary evil in this respect. The
person appointed. The following notes assume the work functions outlined on Data Sheets 80 to 83 should be
consists of a substantially-sized contract involving a regarded as an ordered means of working as a team—not as
resident engineer’s staff of Section Engineers, Assistant a strait-jacket—within which a measure of flexibility can be
Engineers and Inspectors. accepted to advantage.
The objective of the Resident Engineer and his staff should One area of potential confusion on civil engineering sites
be to ensure that the works are completed in accordance is the question of responsibilities regarding safety. Under
with the contract documents, and to keep the Engineer the civil engineering contract between the contractor and
fully informed on all relevant matters. Their basic terms the employer, responsibility for the safety of all operations
of reference are the specification, contract drawings, on the site rests with the contractor. However, this does
conditions of contract and bill of quantities. If these NOT mean that the Engineer (and hence all the Resident
documents are contravened by the contractor or found Engineer’s staff) have no interest or responsibility in
to be in error, conflict or omission, the Engineer must be matters of safety. Under the professional contract between
referred to for guidance. the Engineer and the employer, the Engineer has a
The Resident Engineer should plan ahead and discuss responsibility to the employer to ensure the safe and
future work with the contractor’s agent to ensure that expeditious completion of the work. In turn, however,
the phasing of the works is properly planned to suit the this does NOT mean that the contractor can hand over
programme. This close collaboration between Resident his responsibility regarding safety to the Engineer.
Engineer and agent may also allow the consideration of The adequacy of temporary works, both as regards
design changes proposed by the contractor, and the design and construction, and the adoption of safe methods
submission of proposals to the Engineer for his approval. of working on the contract are of paramount importance.
The principal duties of the Resident Engineer are set For the Resident Engineer’s staff the implication is that
out on Data Sheet 83. Many of his responsibilities will the Resident Engineer must be informed of any case of
inevitably be delegated, wholly or in part, to members of suspected unsafe working or temporary works. Where
his staff, and they must each be given a clear picture of prompt action is needed, the guideline should be that work
what is expected of them. The job descriptions set out on must not be permitted to proceed in a manner considered
Data Sheets 84, 85 and 86 could form the basis for a to constitute a threat to the safety of persons. The Resident
141
www.EngineeringBooksPdf.com
Figure 25. Falsework for bridge deck.
Engineer is empowered to stop the job at any time, by and give brief details of any problems, physical, technical
issuing the necessary site instruction. or contractual, arising on the job. It should also note
visitors to site and any other points of interest to the
Engineer.
Checking temporary works A written report must be submitted regularly to the
Engineer, together with copies of all correspondence with
The checking of temporary works is done primarily to the contractor, of routine test results obtained on site,
check the safety of the permanent structures, but the and of all site instructions issued.
Engineer cannot escape his responsibility for care. He must
therefore satisfy himself that the contractor has a well-
worked-out scheme, even if he does not actually check Site meeting
the calculations for falsework.
Where detailed checking of complex proposals is The Resident Engineer should call and take minutes of
necessary, this should be done by the Engineer off the site meetings at monthly intervals. The general purpose
site. Other pressures may be too great for the Resident of such site meetings is to provide a regular opportunity
Engineer’s staff to undertake long and careful checking for the contractor and the Engineer to monitor jointly
of calculations, to give the approval urgently required by the progress of the contract, and to record items of
the contractor. contractual importance or interest. Such meetings are not
the occasion for raising or discussing points of detail, and
Resident Engineer’s reports the contractor should be dissuaded from any tendency to
do this.
The first site meeting should be used to establish the
The following extract is taken from “Civil engineering
intended pattern, and to advise everyone of the
procedure”.
contribution required of them. The following basic points
should be clarified and minuted.
Progress reports
The Engineer will maintain a check on progress through
reports submitted to him by the Resident Engineer. The contractor’s staff structure.
These reports must be in a form that will give the The levels of communication to be employed (i.e. the
Engineer a clear and concise picture of the progress acceptance of instructions).
made and the extent to which this is ahead of or behind The contractor’s safety officer.
the contractor’s programme; they should be Agreement as to site levels.
accompanied by such progress charts or diagrams as Written notification for inspections.
may be necessary for this purpose. If progress is behind Dayworks. (The Resident Engineer’s staff may sign for
programme on any items of work the report should hours for record purposes, but only the Resident
state the reasons for the delay and the steps which the Engineer can sign for payment.)
contractor is taking to remedy matters. Standing orders for material testing.
Signing of contracts.
Good handling and minutes of the site meeting will relieve Access to land.
the need for a good deal of verbiage in reports.
In addition to progress, reports should call for any A typical agenda for a site meeting is set out on Data
information needed from head office for the contract, Sheet 87.
142
www.EngineeringBooksPdf.com
Site instructions that the formation could be prejudiced unless
appropriate measures are taken.
All instructions given to the contractor should be The methods employed to place the concrete should
confirmed in writing, whether or not they have financial not only ensure that an appropriate rate of delivery can
implications. The instructions should be concise and be achieved but also that the placing and compaction can
unambiguous. Careless wording can be exploited by a be controlled. Where high lifts are being carried out within
contractor, apart from the possibilities of forms, trunking may be necessary to ensure that good
misunderstanding. access to the point at which the concrete is to be placed
All the relevant references (the drawing number, the can be maintained. The Engineer should also have played
specification clauses, the bill item number, and a clear his part by detailing the reinforcement in such a way that
statement of the part of the works affected) should be such access is possible. A choice also has to be made
noted on the instruction. This can save frustrating between the use of immersion or external vibrators.
searching at a later date, when one’s memory is blurred. Prestressing operations may be sensitive to the exact
When the instruction involves extra work not covered procedure adopted, in terms of making the result
by the drawings, the basis for payment should be stated compatable with the design calculations, so that the
on the instruction: i.e. as dayworks, at existing bill rates, Engineer will be very much concerned with how these
or at rates to be negotiated. operations are carried out. The grouting of prestressing
cables is an operation of critical importance to the
serviceability of the structure. A subsequent inspection
Variation orders of the results is often impossible and in any event, if defects
are found, the problem of suitable remedial action still
There are significant differences between the practices remains. Close control of the procedure is therefore the
adopted on building and civil engineering contracts in only way to ensure a satisfactory result.
respect of variation orders. Confirmation of the quality of materials fabricated or
For civil engineering contracts it is only necessary to manufactured off the site is usually undertaken by
issue a variation order for a significant departure from independent testing houses. This applies to reinforcement,
the works as shown on tender drawings, such as the prestressing strand and specialist equipment such as
omission or addition of items of work, or for substantial bearing, stressing anchorages and the like.
amendments to the quantity of measured work. Such
alterations will, in the first instance, be covered by site
instructions. The variation order follows as a definition Approvals
of the financial implications. It should state the
measurement and rates applicable for any additional During the currency of a contract, the Engineer must
work, arriving at a sum to be included in the final evaluate a number of proposals concerning the
account. It follows, therefore, that the variation order contractor’s method of dealing with the work, and the
will come after negotiations have taken place on rates materials he intends to use. On commencing the works
for the additional work. Also, new items added to the the contractor is required to produce a programme
bill of quantities should be covered by such variation setting out the sequence in which he intends to tackle
orders. the work and giving sufficient details to enable the
The Resident Engineer should draft variation orders Engineer to make a reasonable assessment of whether
where they are needed and pass them to the Engineer it is in fact an appropriate sequence of operations
who issues them. compatable with constructional requirements and that
can reasonably be achieved within the contract period.
It may be necessary to ask the contractor to supply
Methods of working additional information about the plant and labour he
intends using on those parts of the work where there
There are a number of operations during the construction may be doubt as to the practicability of completing
of a bridge where the method of working that is adopted the items within the time assigned within the
may be critical, not only in terms of ensuring the smooth programme. At this early stage of the contract it is not
progress of the work, but also because the soundness of reasonable to assume that such a programme can be
the end product may be prejudiced if a wrong approach an exact instrument. Physical circumstances may
is taken. It is normally because of this latter possibility change and the contractor is constantly having to
that the Engineer takes a particular interest in the balance available resources of labour, plant and
question of the methods of working adopted, since a materials against his intended progress, so that it
contractor will himself have progress very much in mind frequently becomes necessary to recast a programme
when making his own decisions, and should be at least as work proceeds.
as well informed as the Engineer on the issue. For The responsibility of the Engineer in examining this
example, during excavation there is the possibility of initial programme is therefore limited to checking that
disturbance to the adjoining ground. In particular, when the contractor’s intended sequence in no way conflicts
ground-water problems exist either in the form of with the requirements of the design, or any restrictions
artesian pressure or a high standing-water table, the on the contract such as the availability of land, the
Engineer will want to be satisfied that the contractor maintenance of traffic routes through the site, and the
will deal with this effectively, bearing in mind the fact phasing of associated work being carried out by, for
143
www.EngineeringBooksPdf.com
example, public utilities which may not be under the direct It is often assumed that if a beam of this type is capable of
control of the main contractor. sustaining a certain bending moment and shearing force it is
It may be necessary to make clear to the contractor therefore adequate to support the associated loads—a false
the limited nature of the Engineer’s assessment of the conclusion. This situation is aggravated by any tendency for
programme at this stage. In the event of difficulties arising the support conditions to produce an eccentricity of load in
in the course of the contract, which lead to the disruption relation to the axis of the web, a condition quite common in
of the contractor’s working arrangements, negotiations falsework. The remedy is to provide adequate bracing of the
on such questions as an extension of time or compensatory member or to introduce web stiffeners at the points of
payment may focus on this initial programme. In giving concentrated load or reaction, or both.
his consent the Engineer may therefore find it prudent to The temporary nature of falsework structures means
point out to the contractor that this does not bestow on that they are normally supported on improvised
his initial programme the status of a mathematical foundations. These are liable to settle in most instances,
instrument which might be used to re-evaluate the contract this settlement not necessarily being uniform. For certain
period by the adjustment of variables within the equation. types of structure this behaviour may be significant in
At the time of submitting his programme, the the way that the loads are distributed within the
contractor will usually give some indication of the temporary structure, and local overloading can lead to
intended methods of construction he will employ relating distortion and even to failure. Fork-heads at the tops of
to bridges. Whether at this stage or later in the contract, scaffold poles can easily be loaded in an eccentric manner
detailed proposals for the falsework and formwork should and become susceptible to failure by bending or buckling.
be submitted for the Engineer’s approval. A sensible Such details of seatings and connections within
appraisal of these proposals is of prime importance if the falsework are a fruitful field for finding deficiencies to
Engineer wishes to retain control over the quality of the which attention must be paid.
finished work. Although in theory, it may be possible to
allow a contractor to proceed with the construction of
elements of the work and then to make judgements about Formwork
their finished quality, either accepting or condemning
them, it is rarely possible to justify the condemning of a In studying proposals for formwork which is intended to
significant item of work and to have it pulled down simply provide a high standard of finish, attention needs to be
because one is disappointed with the quality. To justify concentrated particularly on the joints, whether they are
such measures the work usually has to be defective rather the joints between adjacent plywood panels, between
than merely disappointing. To ensure the quality of the abutted shutter panels, at corners, or between the forms
end product it is necessary to keep abreast of all the and the work previously cast. If the resulting concrete is
contractor’s intended ways of working to achieve it, either to be sound, without “boney” patches or discoloration,
as regards the temporary works and materials to be then the formwork must prevent any loss of grout or
incorporated, or the methods of working to be adopted. moisture from the mix during placing. All the joints must
The prime requirement for falsework is obviously that therefore be grout-tight and remain so under the vibration
it should be stable under the loads which will be imposed that results during the placing and compacting of the
on it during construction. Its deformation under load is concrete. Positive and preloaded connections are necessary
also important so that the works can be completed to line to achieve this and the spacing adopted must be such that
and level within acceptable tolerances. The basic principles the panel is stiff enough to resist any deformation between
involved in falsework construction are much the same as the points at which it is held. If props are used, these
the structural principles involved elsewhere, but added must extend back to something which is rigid.
problems arise from the temporary nature of the structure. If all these jointing details are given proper attention
Many of the joints are less positive than would be the case then the major source of defects will have been taken
in a permanent structure. The alignment of beams seated care of. Provided that the shutter surface is in a reasonable
on scaffolding poles cannot, by the nature of the structure, condition, modern release agents are such that difficulties
comply with the same tolerances expected from a from bad striking are relatively rare nowadays.
connection between beam and column in permanent works. Where some form of profiled relief is provided in the
Unhappily it is often the case that where these tolerances surface by planting timber or plywood block-outs on the
are likely to arise the structure is particularly sensitive to face of the form, the interface between the making-out
variations, but this is not often appreciated by the operatives pieces and the surface of the form must be sealed to
on site, and is even overlooked quite frequently by prevent the grout gaining access between the two surfaces.
falsework designers and engineers. If this is not done, spalling of the concrete edge and a
A high proportion of the failures of falsework are due progressive movement of the block-out away from the
to oversights in relation to the susceptability of temporary original face of the form will occur.
structures to problems of this type. It should be a salutary The remaining point to consider in order to achieve a
thought that almost all the failures of bridge structures satisfactory finish is to make proper arrangements for
take place during the period of construction, and that a terminating the height of concrete placed at one time.
high proportion of these failures result directly from The inclusion of a grout-check provides a means by which
failures of the falsework. the concrete can be finished off to a clean line. Where the
In examining falsework failures a number of recurring top surface of the concrete being placed is to be a finished
themes arise. The sensitivity of rolled steel I-sections to the surface a grout-check can only be provided as a temporary
buckling of the web under direct load is frequently overlooked. measure while the concrete is being placed, and must be
144
www.EngineeringBooksPdf.com
removed at the end of the operation so that the top surface If the contractor’s and the Resident Engineer’s staffs
can be finished with a float. To achieve a good line on are prepared to discuss difficulties as they arise and to
this upper surface it is either necessary to use forms made seek agreement on the course of action to be taken, then
to the true height or, after removing the grout-check, to disputes can be minimized. It is usually possible to agree
employ a string line as a guide to which the finisher can on the course of action needed to resolve a difficulty, even
work in producing the finished top edge. if the question of the responsibility for costs cannot be
agreed at the time. But if this spirit of co-operation can
be fostered it usually has the effect of paving the way for
Disputes the easier settlement of claims as well as achieving
agreement for physical action on the site.
During the progress of the contract, issues inevitably arise Where both parties are prepared to agree that it is
over which the contractor and the Engineer have differing desirable to minimize areas of dispute, then such interests
points of view. Such difficulties may take the form of are usually best served by arranging the maximum personal
circumstances which the contractor regards as disruptive contact and discussion of issues, prior to the establishment
and not necessarily foreseeable, or requirements for of a written record in the form of correspondence or
additional work, or delays due to operations outside of minutes of discussions. Correspondence without prior
the direct control of the contractor, or disputes over the discussion generally has the effect of widening any areas
standard of work being produced. of dispute.
Those responsible for supervision have to decide An open and constructive approach toward the
whether or not a contractor’s requests for additional settlement of differences requires that both parties should
payment or for an extended time for completion are be experienced engineers, confident of what they are doing
reasonable within the terms of the contract. and enjoying the confidence of their superiors. An
The rôle of the Resident Engineer in this respect should excessive reliance on correspondence in disputes generally
be to seek to minimize any areas of disagreement. This task indicates that the parties are more interested in
involves clearly identifying those issues over which differences establishing their own positions than in seeking
can arise, giving prompt instructions where these are agreement. At worst, this degenerates into an endless
necessary to resolve a difficulty and, where differences still debate on the significance of the conditions of contract,
remain, keeping a record of work in progress, instructions leading to the distressing spectacle of those who should
issued and discussions between the parties involved. be engineers acting out the rôle of amateur lawyers.
145
www.EngineeringBooksPdf.com
Resident Engineer
Data sheet No 83
The principal routine duties of the Resident Engineer aided, where appropriate, by
his staff are as follows.
1. To organise and phase the duties of his staff to suit the construction programme.
2. To supervise the permanent work to ensure that it is executed to the correct line and
level, and that the materials and workmanship comply with the specification.
3. To execute or supervise tests carried out at the site, and to inspect materials and
manufacture at source other than that which may be carried out by the Engineer’s
head office staff.
9. Where the Contractor claims payment for additional work, to agree with the
Contractor and record all relevant circumstances, including the cost of labour and
materials, seeking agreement on matters of fact before any question of principle has
to be decided by the Engineer or an arbitrator.
10. To record and check the progress of the work against the programme.
11. To measure, in agreement with the Contractor’s staff, the quantities of work executed,
and to check daywork and other accounts for interim and final payments due to the
Contractor so that they may be certified by the Engineer.
12. To examine methods proposed by the Contractor for executing the work, and
temporary works, to ensure the safe and satisfactory execution of the permanent
work.
13. To redesign work to the extent that this may be delegated by the Engineer.
14. To record on drawings prepared for the purpose, the actual level and nature of
all foundations, the strata encountered in excavation, and full details of any
deviations from the working drawings which have been made during the execution
of the work.
15. To observe the behaviour of the finished works, recording movements, settlements,
etc.
16. To keep all the Resident Engineer’s staff fully informed on matters which may
affect their work, including copies of the relevant site instructions and
correspondence.
146
www.EngineeringBooksPdf.com
Section Resident Engineer
Data sheet No 84
3. To monitor the Contractor’s programme for his section, advising the Contractor
and the Resident Engineer of potential bottlenecks.
4. To draft site instructions for any required variations from, or in addition to,
the contract documents, and to pass them to the Resident Engineer.
5. To agree, for record purposes only, the hours and quantities involved in any
part of the works for which the Contractor claims additional payment, and to
make recommendations to the Resident Engineer as to whether such payment
is due.
8. To keep a daily diary of dealings with the Contractor and other items of
interest.
147
www.EngineeringBooksPdf.com
Assistant Resident Engineer
Data sheet No 85
1. To check the correctness of the basic setting-out drawing for the contract
relative to existing ground features.
9. To keep a daily diary of the weather, the setting-out he has checked, any
points of contention with the Contractor, and other items of major interest,
plus details of his own hours of attendance on the site.
10. To keep other Resident Engineer’s staff informed on matters which may
influence their work.
12. To undertake any other work requested by the Section Resident Engineer.
148
www.EngineeringBooksPdf.com
Inspectors
Data sheet No 86
1. To check the workmanship and materials for conformity with the drawings,
specification and site instructions, and to inform the Section Resident
Engineer and the Contractor where this is not achieved.
2. To note site instructions and any other relevant directives onto the drawings
used in inspection, to ensure that they are taken into account during an
inspection.
3. To check the reinforcement against the drawings and to inform the Section
Resident Engineer and the Contractor of any discrepancies. This inspection
must be carried out prior to the erection of any formwork which would
impede access to the steel.
4. To prepare a written list of any points which may require attention, in
conjunction with an engineer, where the Contractor has asked for an
inspection. To pass the list to the Contractor’s foreman. To check that these
points have been rectified or agreed before this part of the works is covered
(by concreting, erecting formwork, or earthworks as the case may be),
unless the Section Resident Engineer advises him that relaxation of
requirements has been agreed. A copy of this list should be passed to the
Section Resident Engineer.
5. To attend during concreting, to ensure that the workmanship is satisfactory
and to observe the formwork. To check the workability of the concrete.
6. To inspect the concrete when the forms are struck, to note any defects and
to inform the Section Resident Engineer.
7. To attend operations where full records are required: e.g. piling,
prestressing, grouting, etc.
8. To check the levels of the foundations after placing the blinding concrete (or
earlier if extra digging is involved) and to inform the Section Resident
Engineer of any significant discrepancies. To agree levels with the
Contractor’s Quantity Surveyor where extra digging is involved.
9. To keep a daily diary recording the weather, the work in progress,
inspections carried out, concrete placed, movements of key plant, points of
special difficulty or contention, other items of special interest, and his own
hours of attendance on the site.
10. To note the hours worked on any item designated as daywork, or any other
work which may involve extra cost, and to inform the Section Resident
Engineer.
11. To note minor variations which may affect payment and to notify the
Section Resident Engineer.
12. To record the ground conditions in foundations on the layout drawings.
13. To notify the Section Resident Engineer of any accidents on site, and record
these in his diary.
14. To keep record drawings marked with the dates when concreting takes
place.
15. To keep a record of the Contractor’s staff and the sub-contractors on site.
16. To ensure that general disciplines such as the curing and protection of fresh
concrete, the provision for traffic through the site, and safe working
conditions are maintained. These can best be kept under control by requiring
items in this category to be put in order before inspecting for concreting.
17. To keep other Resident Engineer’s staff informed on matters which may
affect their work.
18. To report daily, in person, to the Section Resident Engineer.
19. To undertake any other work requested by the Section Resident Engineer.
20. To supervise routine tests where requested.
149
www.EngineeringBooksPdf.com
Site meetings
Data sheet No 87
The agenda for a typical site meeting should be on the following lines:
The Contractor should report on the progress achieved since the last meeting,
giving reasons for an unexpectedly poor or good performance, and drawing
attention to any items which may affect future performance relative to the
programme. His report should also give details of:
1. The labour and principal plant on the site, together with the changes
planned for the coming month.
2. Any changes in site staff (from Section Foreman and Section Engineers
upward).
3. The names of sub-contractors to be employed on any part of the works,
together with a description of the work they are to undertake.
4. Any claims for additional payment not accepted by the Resident
Engineer. The grounds for the claim should be stated briefly.
Salient points of the Agent’s report should be submitted in writing to the site
meeting for inclusion in the record.
Questions concerning the Agent’s report present an opportunity to plug any
gaps in his submission.
150
www.EngineeringBooksPdf.com
Contract supervision references
Data sheet No 88
151
www.EngineeringBooksPdf.com
APPENDIX A
Notation
152
www.EngineeringBooksPdf.com
APPENDIX B
Metric units
153
www.EngineeringBooksPdf.com
154
www.EngineeringBooksPdf.com
APPENDIX C
155
www.EngineeringBooksPdf.com
156
www.EngineeringBooksPdf.com
157
www.EngineeringBooksPdf.com
158
www.EngineeringBooksPdf.com
Subject index
Abutments, 15, 16, 21–24, 28, 136, 137 Creep, 39, 82, 89
Anchorage:
force, 90, 94 Data sheets (see list on page viii)
system, 92–93, 95 Debonding, 80, 85
Anchor block, 81, 82, 90–93 Decimal conversion, 153–154
Arch, 79, 106, 109 Deflected tendons, 85
Area: Deflection, 60
of reinforcement, 75 Diaphragm, 1, 67, 81
of strand, 103 Diaphragm wall, 17, 28
Articulation, 10, 88 Dimensions:
strand, 103
reinforcement, 75–77
Beam: carriageway, 41–42
precast, 5, 11–12, 110, 111, 105 Distortion, 114, 117–118
deflection, 60 Drawing, 2, 138, 140
moment, 58 Ducts (see Prestressing)
reaction, 59 Dyform (see Strand)
Beam-and-slab construction, 4, 11–12
Bearing capacity, 15, 18, 20 Eccentricity, 80, 86, 87
Bearings, 31, 36, 37 Economy, 10, 14, 63, 131, 133–137
Bending: Effective width of flange, 113, 117–118
dimensions, 75–77 Elastic design, 70, 72, 84
schedules, 76, 77, 125 Expansion joint, 29, 33–34, 37, 155 et seq
Bending moments: Finishes, 31, 151
beam, 58 Finite elements, 111
slab, 69, 74 Finite strip, 111
traffic lane, 49 Flange, effective width of, 113, 117–118
transverse, 69, 74
Bond, 7 Force, anchorage, 90, 94
Box (see also Beam): Formwork, 144
deck analysis, 114, 117–118, 120 Foundation, 15, 17, 18, 20, 28
deck construction, 2, 5–8, 11–14, 108, 133, 134 Friction, 7, 89
Cable (see Strand and Prestressing) Grillage analysis, 111, 116, 119, 120, 126
Calculator, 121 Grouting, 7, 80
Carriageway dimensions, 41–42
Cellular deck (see Box and Voided slab) Harped tendons, 80, 85
Chart (see list of Data Sheets on page viii) Hollow abutment, 21, 137
Composite construction, 4, 11–12
Concentrated loads, 43, 74 Inclined webs, 6, 8, 9
Construction joints, 4, 9, 65, 66
Continuous:
Joints:
beam, 124
construction, 4, 9, 65, 66
deck construction, 9, 86–88 expansion, 29, 34–35, 37
Contract:
documents, 138, 139, 140, 151
supervision, 141–145, 146–151 Limit-state design, 63, 65
Cost comparison, 9, 131, 133–137 Link slabs, 13, 68
Cover (see Reinforcement) Load distribution, 111, 120
Couplers, 3, 96 Load-factor method, 71
Crack control, 63, 70, 73 Loading:
HA, HB, HC, 38, 46–49
159
www.EngineeringBooksPdf.com
lanes, 44, 45 Slab:
combinations of 43, 81, 115 deck, 1, 63
link, 13, 68
Modular-ratio method, 64, 65, 70 moments, 74
Moment (see Bending moment) Soil, 18, 19
Multiple span, 9, 10 Specification, 138, 140
Standard bridges, 10, 155 et seq
Notation, 152 Strand:
anchorages, 79, 85, 94
Parapets, 29, 30, 33, 155 et seq couplers, 3, 96
Parasitic factors, 80, 86 properties, 103, 104
Piers, 16, 123 Strain, 71
Piles, 16, 25–27 Stress distribution, 114
Precast beam, 5, 11–12, 56, 57 Structural analysis, 111
Prestressing:
anchorage, 79 Technical memoranda, 15, 155 et seq
anchor block, 81 Temperature effects, 39, 51–55, 62
cable, 4, 79, 132 Temporary works, 142–145, 151
calculations, 97–99, 127 Tender, 128, 130
design, 79, 84, 97, 98 Torsion, 112, 120
ducts, 80, 100–101 Traffic lanes, 44, 45
external, 7, 9, 83, 108 Transition slabs, 16
losses, 81, 89 Transmission length, 85
saddles, 100–101 Transverse moments, 69, 74
Principal moments, 69
Principal tension, 97 Ultimate moment of resistance, 83, 99
Ultimate shear, 97
Railway clearances, 61 Ultimate strength, 71, 99, 122
References, 14, 28, 62, 78, 105, 120, 151
Reinforced earth, 17
Reinforcement: Vehicle, HA, HB, HC, 46–49
areas, 75 Viaduct, 9, 14
arrangement, 64, 66, 73 Vibration, 39, 56, 57, 62
properties, 70–72 Voided slab:
schedules, 76, 77, 125 decks, 3, 13, 68, 133–135
Relaxation, 104 distortion, 115, 117–118
Retaining walls, 15, 21, 23, 28, 136 Void formers, 1, 3
160
www.EngineeringBooksPdf.com
Author index
120 Sawko, F.
78 Faber, J. 14, 120 Swann, R.A.
161
www.EngineeringBooksPdf.com