PSP P-2
PSP P-2
PSP P-2
PSP Paper – 1
S.2 A project manager may use _________ to make sure the clearly understand
what work is included in each of their work package.
A. The project scope statement
B. The contract documents
C. The detail Network Diagram
D. The WBS dictionary
S.3 To manage a project effectively, work should be broken down into small
pieces. Which of the following does not describe how far to decompose the
work?
A. Until it has meaningful conclusion
B. Until it cannot be logically subdivided further
C. Until it can be done by one person
D. Until it can be accurately estimated.
S.4 The work breakdown structure can be best thought of as an effective aid
for ___________ communications.
A. Project Team
B. Project Organisation
C. Senior management
D. Stakeholder
S.5 The WBS numbering system helps the project team to:
A. Integrate with the project management software.
B. Help in cost estimating each work package.
C. Identify the level in which each element could be found.
D. Assist us in preparation of sub-contractor packages.
PSP S1 AACEI-UAE
Page |2
A. Temporary in nature.
B. A start and a definite end.
C. A set of activities getting repeated at regular interval.
D. Having at least one critical path.
S.8 The type dependency that requires excavation be completed prior to the
start of the foundation concrete is called:
A. Discretionary dependency.
B. External dependency.
C. Task dependency.
D. Mandatory dependency.
S.11 Which of the following is the best project management tool to determine
the longest time for the project to be completed.
PSP S1 AACEI-UAE
Page |3
A. Resource Leveling.
B. Project duration estimation.
C. The Network Diagram.
D. The weighted average duration estimate.
S.14 The amount of time that an activity can be delayed from its early start
date without delaying project completion is called
A. total float
B. free float
C. interfering float
D. negative float
S.15 If your project will require redesign after completion of testing, which of
the following diagramming techniques would you use?
A. GERT
B. PERT
C. CPM
D. ADM
S.17 Management has informed you that the resources for your project will be
cut. Management wants to know how long the project will take if nine
PSP S1 AACEI-UAE
Page |4
resources per month are committed to your project. What is this activity
called?
A. Crashing
B. Floating
C. Leveling
D. Fast tracking
S.20 A detailed project schedule can be created only after creating the:
A. Project budget.
B. Work breakdown structure.
C. Project plan.
D. All of the above
S.21 Total slack is the amount of time a task can be delayed without delaying
the:
A. Project.
B. Completion date required by the customer.
C. Early start of its successor.
D. Project completion date.
S.22 A design must be completed before manufacturing can begin. What kind
of dependency is this?
A. Independent dependency
B. External dependency
C. Mandatory dependency
D. Discretionary dependency
PSP S1 AACEI-UAE
Page |5
S.24 A team member tells the project manager that their task will be delayed
four weeks. The project manager investigates and determines that the delay
will affect the project's completion date. Who should approve the change?
A. Management
B. Project manager
C. Team member
D. Functional manager
S.26 You have a project with the following tasks: Task 1 can start immediately
and has an estimated duration of four. Task 2 can start after Task 1 is
completed and has an estimated duration of eight. Task 3 can start after Task
2 is completed and has an estimated duration of five. Task 4 can start after
Task 1 is completed and has an estimated duration of eight. Task 5 has an
estimated duration of three and must take place concurrently with Task 3. It
can start after Tasks 4 and 2. What is the duration of the critical path of this
project?
A. 15 days
B. 18 days
C. 17 days
D. 12 days
PSP S1 AACEI-UAE
Page |6
S.29 Halfway through the execution phase of your project, a team member
alerts you to a potential cost overrun for a specific deliverable. What do you do
FIRST?
A. Determine the projected actual cost
B. Implement a change control process to track the change
C. Inform the customer
D. Determine the cause of the overage
S.30 The previous project manager informed management that all was well on
the project. However, the new project manager discovers that the project has a
CPI of .89. What does this mean?
A. At this time, it is expected that the total project will take 89% longer than
planned.
B. When the project is completed, 89% more than planned will have been
spent.
C. The project is only progressing at 89% of what was planned.
D. The project is only getting 89 cents out of every dollar invested.
S.31 You are asked to prepare a budget for completing a project that was
started last year and then shelved for six months. All the following would be
included in the budget EXCEPT?
A. Fixed cost
B. Sunk cost
C. Direct cost
D. Variable cost
S.32 You are trying to decide whether to lease or buy an item for your project.
The daily lease cost is US $150. To purchase the item, the investment cost is
US $2,000 and the daily cost is US $50. In how many days will the lease cost
be the same as the purchase cost?
A. 10 days
B. 15 days
C. 20 days
D. 25 days
PSP S1 AACEI-UAE
Page |7
C. 1.034
D. US $2,000
S.34 Which of the following BEST describes the meaning of the 50/50 rule?
A. Grant 50% progress A task begins and 50% upon completion
B. 50% of the work is done by 50% of the people on the project
C. Identify 50% of risks before you start to develop responses
D. A measure of Gantt chart review
S.35 Which estimating method tends to be MOST costly for creating a project
cost estimate?
A. Bottom up
B. Analogous
C. Parametric
D. 50/50 rule
S.36 The BEST description of costs that change with the amount of production
is:
A. Variable costs.
B. Fixed costs.
C. Direct costs.
D. Sunk costs.
S.38 As a project manager, you are presented with the following information
on the NPV for several potential projects. Which project is your BEST choice?
A. Project A with a NPV of US $95,000
B. Project B with an NPV of US $120,000
C. Project C with an NPV of US $20,000
D. Project D with an NPV of US $30,000
PSP S1 AACEI-UAE
Page |8
projects needs to be terminated. The cost benefits ratios for the four projects
are listed. Which would you select for termination?
A. 0.8
B. 1.0
C. 1.1
D. 10
S.41 You are a project manager for a small construction project. Your project
was budgeted for US $72,000 over a six week period. As of today, you've spent
US $22,000 of your budget to complete work that you originally expected would
cost US $24,000. According to your schedule, you should have spent US
$30,000 by this point. Based on these circumstances, your project could be
BEST described as:
A. Under budget.
B. Over budget.
C. On schedule.
D. CPI is less than 1.
S.42 A project manager is controlling the performance of the project when the
project controls manager indicates the project has a SPI of .76. Which of the
following BEST describes what this means?
A. You are over budget.
B. You are ahead of schedule.
C. You are only progressing at 76% of the rate originally planned.
D. You are progressing at only 24% of the rate originally planned.
S.43 A project manager is controlling the performance of the project when the
project controls manager indicates the project has a SPI of 0.76. Which of the
following BEST describes what this means?
A. You are over budget.
B. You are ahead of schedule.
C. You are only progressing at 76% of the rate originally planned.
D. You are progressing at only 24% of the rate originally planned.
PSP S1 AACEI-UAE
Page |9
PSP S1 AACEI-UAE
P a g e | 10
S.54 You are a project manager working on a project that requires 100 widgets
to be built in five weeks. You have just begun week three, with an overall
budget of US $10,000. To date, you have spent US $2,000 with 40 widgets
successfully built. What does the cost variance tell you in this circumstance?
A. The project is proceeding at 100% of the expected rate.
B. The project is US $2,000 under budget.
C. The project is on budget.
D. The project is getting US $2 of work for every dollar spent.
PSP S1 AACEI-UAE
P a g e | 11
S.56 A project has a payback period of nine months. What does this mean?
A. It will take the project nine months to start incurring costs.
B. The project will be completed in nine months.
C. The first nine months of the project will provide profit to the company.
D. It will take the project nine months to cover the investment and start
generating revenue.
S.58 A customer has requested a change that requires you to obtain new
equipment. You need to decide whether to lease or buy the equipment. The
daily lease cost is US $150. The cost of purchasing the item is US $2,000 for
the investment cost and US $50 for the daily cost. You will need to use the
item for about 12 days. What should you do?
A. Lease it.
B. Buy it and sell it at the end of 12 days to obtain the scrap value
C. Ask the customer for a US $2,000 change order.
D. Lease it for only seven days to try to save cost.
S.60 A project team budgeted US $3,000 for the work performed and has
spent US $4,000, to date. If they budgeted US $5,000 for the work scheduled,
what is the cost variance?
A. US -$1,000
B. US $2,000
C. US $1000
D. US -$2000
S.61 A manufacturing project has a SPI of .89 and a CPI of .91. What is the
BEST explanation for why this occurred?
PSP S1 AACEI-UAE
P a g e | 12
A. The equipment for the project was more expensive than expected.
B. At least one task has taken more time than expected.
C. Less experienced resources were used.
D. The project baseline was changed more than once.
S.64 During what time management process are the specific activities that
must be performed to produce the deliverables in the WBS identified and
documented?
A. Activity duration estimation
B. Schedule Development
C. Work package definition
D. Activity Definition
PSP S1 AACEI-UAE
P a g e | 13
S.69 In attempting to complete the project faster, the project manager looks at
the cost associated with crashing each task. The BEST approach to crashing
would also include looking at the:
A. The criticality and the risk impact of crashing each task.
B. Customer's opinion of what tasks to crash.
C. Owner’s opinion of what tasks to crash and in which order.
D. The project phase in which the task is due to occur in.
PSP S1 AACEI-UAE
P a g e | 14
Correct Answers
S.1 – C
S.2 – D
S.3 - C
S.4 - D
S.5 - C
S.6 - C
S.7 - D
S.8. - D
S.9. - B
S.10 - D
S.11. - C
S.12 - D
S.13 – D
S.14 – A
S.15. – A
S.16. – B
S.17. – C
S.18. – A
S.19. – D
S.20. – B
S.21. – D
S.22 – C
S.23 – A
S.24. – A
S.25 – B
S.26. – C
S.27 – B
S.28. – D
S.29 – D
S.30 – D
S.31 – B
S.32. – C
S.33 – B
S.34. – A
S.35. – A
S.36 – A
S.37. –D
S.38. –B
S.39. –A
S.40. – A
PSP S1 AACEI-UAE
P a g e | 15
S.41. –A
S.42. –C
S.43. –C
S.44. –C
S.45. –B
S.46. –C
S.47. –C
S.48. –D
S.49. –B
S.50. –B
S.51. –D
S.52. –C
S.53. –D
S.54. –B
S.55. –A
S.56. –D
S.57. –D
S.58. –A
S.59 –B
S.60. –A
S.61. –C
S.62. –C
S.63. –D
S.64. –D
S.65. –D
S.66. –C
S.67. –A
S.68. –A
S.69. –A
S.70. –D
PSP S1 AACEI-UAE