The document discusses compliance requirements for a water supply project in Polgahawela, Sri Lanka. It addresses two client comments, confirming that design calculations and drawings have been submitted according to BS5395-3 standards, and that a method statement will be separately submitted for painting compliance.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
24 views1 page
Compliance Statement: Va Tech Wabag LTD
The document discusses compliance requirements for a water supply project in Polgahawela, Sri Lanka. It addresses two client comments, confirming that design calculations and drawings have been submitted according to BS5395-3 standards, and that a method statement will be separately submitted for painting compliance.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1
COMPLIANCE STATEMENT
POLGAHAWELA, POTHUHERA AND ALAWWA INTEGRATED WATER
Project SUPPLY PROJECT Client NATIONAL WATER SUPPLY & DRAINAGE BOARD, SRI LANKA
Location POLGAHAWELA, SRI LANKA
Submission of handrail sample and the company profile of schaupub Doc. Title Technik limited to utilize at WTP and Intake. Commented Doc. Rev No. 0 No.
Comments Ref : PD/PPAIWSP/ General /2021/C/712 , dated 17th May, 2021
Sl No Client Comments WABAG reply
The design calculation report and
drawing shall be carried out as Design calculation and drawing are attached 1. BS5395-3. As per OSHAS minimum for your checking as per BS5395-3 and outer diameter of rails shall be 1.5” provided Rail diameter is 38 mm. to 2”. The method of statement shall be Method of statement will be submitted 2. submitted for painting compliance separately. requirement of clause 1.10 Vol