Labour (Mazdoor) Required For Different Works Sr. No. Item Beldars Mazdoors Bhisti Mason

This document provides labor rates for various construction works including excavation, refilling excavated earth, laying PCC and RCC, masonry works, plastering, painting and other miscellaneous works. The rates are specified per item, type of labor required and unit of measurement (e.g. cubic meters, square meters etc.). A number of labor types are listed including beldars, mazdoors, bhistis and masons along with their productivity rates for different construction activities.

Uploaded by

Nikhil
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
80% found this document useful (5 votes)
7K views4 pages

Labour (Mazdoor) Required For Different Works Sr. No. Item Beldars Mazdoors Bhisti Mason

This document provides labor rates for various construction works including excavation, refilling excavated earth, laying PCC and RCC, masonry works, plastering, painting and other miscellaneous works. The rates are specified per item, type of labor required and unit of measurement (e.g. cubic meters, square meters etc.). A number of labor types are listed including beldars, mazdoors, bhistis and masons along with their productivity rates for different construction activities.

Uploaded by

Nikhil
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 4

Labour ( Mazdoor ) Required For Different Works

Sr. No. Item Beldars Mazdoors Bhisti Mason

Excavation in Foundations,trenches
1 etc. in ordinary soil including disposal 1/5.66 1/7.075 - -
up to 30 m and lift of 1.5 m

Refilling Excavated earth in


2 foundation, plinth,etc. including 1/9.43 1/14.15 1/56.6 -
consolidation in 15 cm layers

Disposal of surplus earth within a lead


3 - 1/2.83 - -
of 30 m

4 Laying P.C.C. 1/1.415 1/0.943 1/3.77 1/11.32

5 Laying R.C.C. 1/0.94 1/0.94 1/2.12 1/5.66

Centering and shuttering for flat Carpenter


6 1/2.4 - -
surfaces 1/2.4

Blacksmith
7 Reinforcement work R.C.C. 1/100 - -
1/100

Random Rubble masonry with blue


8 1/0.94 1/1.415 1/11.32 1/0.94
stone in foundation

1 st class brickwork in 1 : 4 cement


mortar in superstructure,partition wall,
9 - 1/0.629 1/5.66 1/1.258
junction of roof,parapet walls, string
course

Carpenter
10 Doors and Windows Frames 1/0.18 - -
1/0.09

Carpenter
11 Pannelled,glazed,etc. shutters 1/0.019 - -
1/0.005

Fixing 40 mm x 3 mm x 38 cm flat iron Blacksmith


12 1/36 - 1/36
holdfasts 1/36
Blacksmith Carpenter
13 Fixing 16 mm dia M.S.Rods 1/5.5 -
1/16.5 1/8.25

4 cm thick cement concrete flooring


14 1/10 1/13.33 1/40 1/8
laying ,mixing and finishing

12 mm thick plastering with any


15 - 1/13.33 1/40 1/13.33
mortat

white
White washing or colour washing ( 3
16 - 1/60 washer -
Coat)
1/60

Painter
17 Painting two coats on wood or steel - 1/5 -
1/3.33
Per Day

m3

m3

m3

m3

m3

m2

Kg.

m3

m3

m3 ( 4 door
frames 7.5 cm x
10 cm ) of 1.2 m
x 2.1 m size

m3 ( 4 shutters
40 mm thick 2.0
m x 1.15 m )

Per holdfasts
Per running m

m2

m2

m2

m2