W268.01 DLV FDR WWTP - & - Disposal Palembang

Download as pdf or txt
Download as pdf or txt
You are on page 1of 88

Water and Sanitation City Sewerage Grant

Activity 268.1 Detailed Engineering Design


Final Design Report Package A - Palembang
WWTP and Effluent Disposal
March 2015
INDONESIA INFRASTRUCTURE INITIATIVE

Water and Sanitation City Sewerage Grant


Activity 268.1 Detailed Engineering Design

Final Design Report Package A – Palembang


WWTP and Effluent Disposal

Consultant Report
March 2015
INDONESIA INFRASTRUCTURE INITIATIVE

This document has been published by the Indonesia Infrastructure Initiative (IndII), an
Australian Government funded project designed to promote economic growth in
Indonesia by enhancing the relevance, quality and quantum of infrastructure
investment.

The views expressed in this report do not necessarily reflect the views of the Australia
Indonesia Partnership or the Australian Government. Please direct any comments or
questions to the IndII Director, tel. +62 (21) 7278-0538, fax +62 (21) 7278-0539.
Website: www.indii.co.id.

ACKNOWLEDGEMENTS

This report has been prepared by MWH Australia Pty Ltd. who was engaged under the
Indonesia Infrastructure Initiative (IndII), an Australian Aid project managed by SMEC
on behalf of the Australian Government, as part of the Activity 268.1 Detailed
Engineering Design.

MWH Global

Jakarta, Date March 2015

© IndII 2014

All original intellectual property contained within this document is the property of the Indonesia
Infrastructure Initiative (IndII). It can be used freely without attribution by consultants and IndII partners in
preparing IndII documents, reports designs and plans; it can also be used freely by other agencies or
organisations, provided attribution is given.

Every attempt has been made to ensure that referenced documents within this publication have been
correctly attributed. However, IndII would value being advised of any corrections required, or advice
concerning source documents and/ or updated data.
QUALITY STATEMENT

PROJECT MANAGER DESIGN MANAGER

Shannon Trafford Steve Moore

REVISION SCHEDULE

Signature or Typed Name (documentation on file).


Rev
Date Description
No
Prepared by Reviewed by Approved by
A 09/05/2014 Issued for 30% A. Wilkie / J. R.Hoffman/ S.Trafford
Design Submission Mink C.Hare
B 13/08/2014 Issued for 50% A. Wilkie / S. Moore S.Trafford
Design Submission J. Mink / G.
Hadiardja
0 03/03/15 Final Design A. Wilkie / Rainer Hoffman S.Trafford
Submission J Mink

These reports have been prepared for use by the Indonesia Infrastructure Initiative under the
auspices of the SMEC Australia Pty Ltd. MWH Australia accepts no liability to any Contractor,
Third Party or Final Owner off the asset which is the subject of this report ore deliverable.
Table of Contents & Abbreviations

TABLE OF CONTENTS

ACRONYMS ........................................................................................................... VII


CHAPTER 0: EXECUTIVE SUMMARY........................................................................ 0-1
BACKGROUND AND INTRODUCTION ............................................................ 0-1
PERFORMANCE REQUIREMENTS ................................................................. 0-1
PROCESS CONFIGURATION ........................................................................ 0-2
HYDRAULIC DESIGN ................................................................................ 0-3
SITE DEVELOPMENT ................................................................................ 0-4
CHAPTER 1: INTRODUCTION ..................................................................................... 1
1.1 PURPOSE ....................................................................................... 1
1.1 RELEVANT PROJECT DOCUMENTS ........................................................ 1
1.2 PROJECT OBJECTIVES ........................................................................ 1
CHAPTER 2: KEY ASSUMPTIONS................................................................................ 3
2.1 KEY ASSUMPTIONS & CONSTRAINTS .................................................... 3
CHAPTER 3: PERFORMANCE REQUIREMENTS ............................................................ 4
3.1 POPULATION AND CATCHMENT DESCRIPTION ......................................... 4
3.2 FLOW VARIATIONS .......................................................................... 4
3.3 INFLUENT CHARACTERISTICS ............................................................... 5
3.4 EARLY OPERATION & TURNDOWN ....................................................... 6
3.5 EFFLUENT REQUIREMENTS ................................................................. 7
3.6 ODOUR ......................................................................................... 7
CHAPTER 4: FLOW MANAGEMENT............................................................................ 8
4.1 DESIGN CONDITIONS ........................................................................ 8
4.2 LOW FLOW OPERATION .................................................................. 10
CHAPTER 5: PROCESS DESIGN AND UNIT PROCESS DEVELOPMENT .......................... 13
5.1 PROCESS DESIGN OVERVIEW ............................................................ 13
5.2 INLET WORKS ............................................................................... 13
5.2.1 Performance Requirements ................................................... 13
5.2.2 Process Development ............................................................ 14
5.2.3 Design Description ................................................................. 15
5.3 SEPTAGE RECEIVAL ........................................................................ 17
5.3.1 Performance Requirements ................................................... 17
5.3.2 Process Development & Design Description.......................... 17
5.4 ANAEROBIC BAFFLED REACTOR (ABR)................................................ 18
5.4.1 Performance Requirements ................................................... 18

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report i
Status: FINAL
5.4.2 Process Development ............................................................ 18
5.4.3 Design Description ................................................................. 21
5.5 BIOLOGICAL TRICKLING FILTER AND BTF FEED PUMP STATION ................. 23
5.5.1 Performance Requirements ................................................... 23
5.5.2 Process Development ............................................................ 23
5.5.3 Design Description ................................................................. 24
5.6 SECONDARY CLARIFIER .................................................................... 26
5.6.1 Performance Requirements ................................................... 26
5.6.2 Process Development ............................................................ 26
5.6.3 Design Description ................................................................. 27
5.7 DISINFECTION ............................................................................... 28
5.7.1 Performance Requirements ................................................... 28
5.7.2 Process Development ............................................................ 28
5.7.3 Design Description ................................................................. 29
5.8 SOLIDS HANDLING ......................................................................... 31
5.8.1 Performance Requirements ................................................... 31
5.8.2 Process Development ............................................................ 32
5.8.3 Design Description ................................................................. 33
5.9 ODOUR TREATMENT ...................................................................... 34
5.9.1 Performance Requirements ................................................... 34
5.9.2 Process Development ............................................................ 34
5.9.3 Design Description ................................................................. 35
5.10 BIOGAS HANDLING ........................................................................ 38
5.10.1 Performance Requirements .................................... 38
5.10.2 Process Development .............................................. 38
5.10.3 Design Description ................................................... 40
5.11 SITE WASTE WATER PUMP STATION .................................................. 41
5.12 PLANT MAINTENANCE CONSIDERATIONS ............................................. 41
5.13 WWTP EXPANSION ....................................................................... 42
CHAPTER 6: ENVIRONMENTAL, SOCIAL & PERMIT REQUIREMENTS ......................... 43
6.1 ENVIRONMENT ............................................................................. 43
6.2 PERMITTING ................................................................................. 43
6.3 SOCIAL – INVOLUNTARY RESETTLEMENT.............................................. 43
CHAPTER 7: SITE DEVELOPMENT ............................................................................ 44
7.1 SITE LOCATION AND DESCRIPTION ..................................................... 44
7.2 SURVEY BENCHMARK AND DATUM .................................................... 44
7.3 FLOOD AND TIDAL RIVER LEVELS ....................................................... 44
7.4 GEOTECHNICAL INVESTIGATIONS ....................................................... 45
7.5 INCOMING FLOWS ......................................................................... 45
7.6 EFFLUENT DISCHARGE ..................................................................... 45

W268.01 City Sewerage DED


ii Palembang WWTP Final Detailed Design
Report Status: FINAL
Table of Contents & Abbreviations

7.7 SITE ACCESS AND SECURITY .............................................................. 45


7.8 FACILITY LAYOUT ........................................................................... 46
7.9 ON-SITE AMENITIES ....................................................................... 46
7.10 SITE WATER MANAGEMENT............................................................. 48
CHAPTER 8: UTILITIES ............................................................................................. 49
8.1 SITE / POTABLE WATER .................................................................. 49
8.2 TELECOMMUNICATIONS .................................................................. 50
8.3 ELECTRICAL POWER........................................................................ 50
CHAPTER 9: STRUCTURAL DESIGN REQUIREMENTS ................................................. 51
9.1 SEISMIC DESIGN ............................................................................ 51
9.2 FOUNDATION REQUIREMENTS .......................................................... 52
CHAPTER 10: ELECTRICAL DESIGN REQUIREMENTS ................................................. 54
10.1 ELECTRICAL POWER REQUIREMENTS .................................................. 54
10.2 STANDBY POWER PROVISIONS .......................................................... 55
10.2.1 Uninterruptible Power Supplies (UPS)..................... 55
10.3 ELECTRICAL EQUIPMENT INSTALLATION ............................................... 55
10.3.1 Motor Control Centres (MCC) and Cabinets............ 55
10.3.2 Variable Speed Drives (VSD’s) ................................. 56
10.3.3 Distribution board ................................................... 56
10.3.4 Cabling and Wiring Systems .................................... 56
10.3.5 Future and Spare Allowances .................................. 57
10.4 LOCATION OF ELECTRICAL EQUIPMENT ................................................ 57
10.5 SIZING OF ELECTRICAL SWITCH ROOM ................................................ 57
CHAPTER 11: PLANT CONTROL SYSTEM .................................................................. 59
11.1 PERFORMANCE REQUIREMENTS ........................................................ 59
11.2 COMMUNICATIONS ........................................................................ 59
11.3 CONTROL SYSTEM OVERVIEW ........................................................... 59
11.3.1 Objective .................................................................. 59
11.4 OPERATIONS SOFTWARE INTEGRATION ............................................... 60
11.5 CONTROL HIERARCHY ..................................................................... 60
11.6 CONTROL SYSTEM ARCHITECTURE AND HARDWARE ............................... 60
11.6.1 Programmable Logic Controllers (PLCs) .................. 60
11.6.2 HMI Operator Interface ........................................... 61
11.6.3 Intra-Plant SCADA Communications ........................ 61
CHAPTER 12: DESIGN STANDARDS .......................................................................... 62
12.1 MATERIALS OF CONSTRUCTION ......................................................... 62
12.1.1 Piping ....................................................................... 62
12.1.2 Other ........................................................................ 62

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report iii
Status: FINAL
12.2 CONCRETE CORROSION PROTECTION .................................................. 62
12.3 TANK AND CHANNEL COVERS ........................................................... 62
12.4 LIGHTING..................................................................................... 63
12.5 HOSE STATIONS ............................................................................ 63
CHAPTER 13: WORKS PACKAGING AND PROCUREMENT.......................................... 64
CHAPTER 14: REFERENCES ...................................................................................... 65

W268.01 City Sewerage DED


iv Palembang WWTP Final Detailed Design
Report Status: FINAL
Table of Contents & Abbreviations

LIST OF TABLES

Table 0-1: Sei Selayur WWTP Performance Requirement Summary.............................0-1

Table 3-1: WWTP Average Influent Flow and Load Summary .......................................... 4

Table 3-2: Key Transfer Pump Station Flows .................................................................... 5

Table 3-3: Design Wastewater Influent Characteristics.................................................... 6

Table 3-4: Effluent Quality Requirements ........................................................................ 7

Table 3-5: Hydrogen Sulphide Safe Working Levels ......................................................... 7

Table 4-1: WWTP Influent Flows....................................................................................... 8

Table 4-2: Minimum flow conditions to the WWTP ....................................................... 10

Table 4-3: Minimum flow conditions to the WWTP ....................................................... 11

Table 5-1: Performance Requirements – Inlet Works .................................................... 14

Table 5-2: Design Configuration Summary – Inlet Works ............................................... 16

Table 5-3: Performance Requirements – Septage Receiving Station ............................. 17

Table 5-4: Performance Requirements – Anaerobic Treatment .................................... 18

Table 5-5: Design Configuration Summary – Anaerobic Treatment ............................... 22

Table 5-6: Design Configuration Summary – Biological Trickling Filter .......................... 25

Table 5-7: Design Configuration Summary – BTF Feed Pump Station ............................ 26

Table 5-8: Design Configuration Summary – Secondary Clarifier ................................... 27

Table 5-9: Performance Requirements – Disinfection .................................................... 28

Table 5-10: Design Configuration Summary – Disinfection ............................................ 30

Table 5-11: Performance Requirements – Solids Handling ............................................ 32

Table 5-12: Process Unit Performance Requirements – Solids Handling ....................... 33

Table 5-13: Process Unit Performance Requirements – Odour Control......................... 34

Table 5-14: Design Summary – Odour Control ............................................................... 36

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report v
Status: FINAL
Table 5-15: Process Unit Performance Requirements – Biogas Handling ...................... 39

Table 5-16: Design Summary – Biogas Handling ............................................................. 40

Table 7-1: Key Estimated Operations Requirements ...................................................... 46

Table 8-1: Site and Potable Water Estimated Demands ................................................. 49

Table 9-1: Summary of Palembang Site Seismic Design Parameters (Ref. Indonesian
National Standard SNI 1726:2012) ................................................................................. 51

LIST OF FIGURES

Figure 0-1: Sei Selayur WWTP process flow diagram ....................................................0-2

Figure 4-1: Flow bypass operation under (a) normal operation and (b) low flow
commissioning operation ............................................................................................... 12

Figure 5-1: Anaerobic baffled reactor train flow schematic ........................................... 19

Figure 9-1: Spectral Response Acceleration Sa (g) Vs Period (sec.) ................................ 52

W268.01 City Sewerage DED


vi Palembang WWTP Final Detailed Design
Report Status: FINAL
Table of Contents & Abbreviations

ACRONYMS

ABR Anaerobic baffled reactor


ACPH Air changes per hour
ADB Asian Development Bank
ADWF Average dry weather flow
BoD Basis of Design
BOD Biochemical oxygen demand
BTF Biological trickling filter
CAPEX Capital expenditure estimate
COD Carbonaceous oxygen demand
CT Concentration x Time
DED Detailed engineering design
EIA Environmental impact assessment
EMP Environmental management plan
GIS Geographic information systems
HAZOP Hazard and operability study
HMI Human-Machine Interface
HRT Hydraulic retention time
I&C Instrumentation and controls
I/O Input / output signals
IEE Initial environmental examination
IndII Indonesia Infrastructure Initiative
LARP Land Acquisition and Resettlement Plan
LCS Local control stations
MCC Motor control centre
MLD Megalitre per day
MSMIP Metropolitan Sanitation Management Investment Project
O&M Operations and maintenance
OPEX Operating expenditure estimate
PDAM Water company
PDWF Peak dry weather flow
PLC Programmable Logic Controller
PWWF Peak wet weather flow
RFI Request for Information
SCADA Supervisory Control and Data Acquisition
SRT Solids retention time
TKN Total Kjeldahl Nitrogen
TSS Total suspended solids
UPS Uninterruptible Power Supplies
VFA Volatile fatty acids
VOC Volatile Organic Compounds
VSD Variable Speed Drive
VSS Volatile suspended solids
WW Wastewater
WWTP Wastewater treatment plant

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report vii
Status: FINAL
Executive Summary

Chapter 0: Executive Summary


BACKGROUND AND INTRODUCTION

The Government of Australia extended the Indonesia Infrastructure Initiative (IndII)


facility into phase 2 from July 2011 to June 2015. The city sewerage grant is a major
component of the Water Supply and Sanitation Program. The priority city sewerage
grant projects typically comprise trunk collector sewers, tertiary reticulation sewers,
property connections, pump stations, a wastewater treatment plant and an effluent
disposal pipeline to the nearest receiving water.

This Detailed Design Report has been prepared for the W268.1 – City Sewerage
Detailed Engineering Design (DED) Program (Package A – Palembang). Package A is
divided into the following sub-packages:
• Palembang (Sei Selayur) Wastewater Collections & Transfer System
• Palembang (Sei Selayur) Wastewater Treatment Plant & Effluent Disposal

This report has been generated to describe the detailed design for the Palembang (Sei
Selayur) Wastewater Treatment Plant & Effluent Disposal sub-package.

PERFORMANCE REQUIREMENTS

The design of the Sei Selayur wastewater treatment plant (WWTP) has been completed
in order to meet a series of performance requirements for plant flow and effluent
quality. A summary of pertinent performance requirements is given in the following
below.

Table 0-1: Sei Selayur WWTP Performance Requirement Summary


Parameter Units Value Remarks
Plant Flow
Average dry weather influent flow
MLD 20
(ADWF)
WWTP bypass to be initiated when
Maximum flow for full treatment L/s 800 flows exceed peak dry weather
flow (PDWF)
Flows above the maximum flow to
Maximum flow received from network. L/s 1300
full treatment are bypassed.
Key Plant Feed Characteristics
From collection system and
Feed biochemical oxygen demand (BOD) mg/L 350
septage
From collection system and
Feed total suspended solids (TSS) mg/L 450
septage
Effluent Treatment Target
pH 6-9 Provincial standard

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 0-1
Status: FINAL
BOD mg/L 50 Provincial standard
Suspended solids mg/L 100 Provincial standard
Fats, oil and grease mg/L 10 Provincial standard
Class II standard for the Musi
River has river quality standard for
this parameters. Value selected for
cfu/100
E. Coli 2,500 WWTP effluent is
mL
recommendations only and has not
been based on a receiving water
study.

PROCESS CONFIGURATION

The configuration of the Sei Selayur WWTP will comprise of the following process
units:
• Inlet works
• Anaerobic baffled reactor (ABR)
• Biological trickling filter (BTF)
• Secondary clarifier
• Chlorine disinfection
• Sludge drying beds

This configuration is illustrated in a high level process flow diagram shown in.Figure 0-
1.

Figure 0-1: Sei Selayur WWTP process flow diagram

The inlet works will comprise of a automatically raked bar screen. An additional,
manually raked screen will be provided to treat flows when the automatically raked

W268.01 City Sewerage DED


0-2 Palembang WWTP Final Detailed Design
Report Status: FINAL
Executive Summary

screen is unavailable. The screens will remove large solid objects such as rags and
debris, protecting downstream equipment. The screened wastewater will flow through
a vortex style grit removal chamber to remove grit in the form of inert solid material,
preventing the build-up of grit in the ABR.

The ABR will be the primary means of removal of BOD load at Sei Selayur WWTP. It is
anticipated that the ABR will remove approximately 70% of influent BOD to the plant.
The ABR will consist of two trains, each consisting of three up-flow cells in series.

The flow will then pass through a trickling filter which will provide additional removal
of BOD. The combination of the anaerobic treatment and the biological trickling filter
will allow the plant to meet the BOD effluent target specified for the WWTP.

The flow will pass from the trickling filter to the secondary clarifier in order to ensure
adequate removal of total suspended solids. Flow not sent to the BTF will bypass the
clarifier and flow directly to the chlorine contact tank. Solids removed in the clarifier
operation will be returned to the ABR to be removed as part of the ABR solids removal
process.

Solids from the WWTP will be periodically removed from each ABR cell by means of a
sludge pump. The ABR design will incorporate a relatively high sludge age of 60 days,
which will produce a highly stable (low volatile solid content) solid waste stream. The
advantage of this is that the solids may be directly applied to sludge drying beds
without any further digestion, such as in sludge lagoons.

HYDRAULIC DESIGN

The wastewater collection network will gather flows from users throughout the
catchment and transfer flows to the WWTP via a single transfer pump station. The
transfer of flows to the WWTP will be subject to peaks, which must be managed. Flows
up to the design daily peak dry weather flow (PDWF) will receive full treatment at the
WWTP without bypassing. Above PDWF and up to the maximum capacity of the
network pump station a portion of the influent flow will overtop a fixed bypass weir at
the inlet works of the treatment plant and be transferred to the plant discharge via a
manually raked screen. When the flow received is at the maximum capacity of the
network pump station the instantaneous flow passed to the treatment process will
climb to 800 L/s.

During early operation of the WWTP, the load to the plant will be significantly below
the plant capacity as the collection system grows and more system connections are
made. The low load is expected to result in better WWTP performance in terms of BOD
removal, however, this may be required to be balanced with effluent pH, which may be
reduced due to nitrification in the trickling filter. To manage low loading, flow at the
inlet works may be split in early years of operation and a stream which bypasses the
ABR may be passed directly to the trickling filter and the ABR effluent may bypass the
trickling filter, effectively to operate the ABR and trickling filter and clarifier in parallel.
This bypass arrangement will allow the trickling filter heterotrophic operation to be
maintained and will allow the pH of the effluent stream to be maintained.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 0-3
Status: FINAL
SITE DEVELOPMENT

The wastewater treatment plant will be located on a 5.9 Ha site located along the Musi
River in the Kelurahan of Sei Selayur. The site is bordered by the PT Pupuk Sriwijaya
(Pusri) fertiliser plant to the west along Jalan Dr. Sutami, a police station and informal
settlements along the north and east, a timber mill along the south west and the Musi
River along the south. Approximately 0.24 Ha of the site was made unavailable for
WWTP facilities based on initial Land Acquisition and Resettlement Plan (LARP)
requirements.

The WWTP site is long and narrow (generally 80m – 100m wide) shaped like an “L”.
The main process units were laid out within the north-south portion of the site to allow
the process to be laid out in a linear fashion to minimise pipe lengths and to use the
natural grade of the site down to the river to assist gravity flow through the plant.

The east-west branch of the site will be used primarily for sludge drying. The waste
pump station / septage receiving facility will be located near to the primary site
entrance.

All facilities required for the final design capacity of the WWTP will be constructed in
the initial stage. Any future expansion of the WWTP capacity will require the purchase
of additional land.

The influent rising main will enter the site from the southern end of the western
boundary along Jalan Dr. Sutami. The WWTP effluent will be discharged to the
adjacent Musi River along the southern border of the site. Broad-order numerical
modelling was conducted to confirm effluent will be sufficiently dispersed from the
selected discharge location.

The primary site entrance for the WWTP will be provided on the far west edge of the
site along Jalan Dr. Ir. Sutami.

The WWTP will be equipped with the following security provisions:


• a security wall will be provided around the perimeter of the WWTP;
• a guard station at the primary and secondary site entrances; and
• lockable doors on all buildings and enclosures.

The following on-site amenities (and associated features) will be provided for the
WWTP:
• administration building & control room
• staff quarters
• guard station
• workshop & storage
• main switchroom

These facilities (except the main switchroom and guard house) will be primarily located
in the west end of the site so that they are close to the primary site entrance. The

W268.01 City Sewerage DED


0-4 Palembang WWTP Final Detailed Design
Report Status: FINAL
Executive Summary

guardhouse will be located at the primary site entrance. The main switchroom will be
located adjacent to the BTF and the pump stations to be adjacent to the key electrical
demands on the site.

Two sources were located and reviewed, which state the anticipated flood level of the
Musi River adjacent to the WWTP is around 3.7-3.75m MSL (sources: Desktop Study
Report for Geotechnical and Hydrogeological Investigations, Golder Associates, Feb
2014 and Strategy of Drainage and Flood Control in Palembang City, Eddy Santana
Putra, F.X. Suryadi, Kira Tarigan, Akhmad Bastari and Marlina Sylvia). The frequency
for this flood event is not available; therefore, a conservative approach has been
adopted and the WWTP has been designed to avoid inundation and submergence of
process units at the “flood” level of 3.75m MSL.

The site survey has indicated the WWTP site is generally flat ranging around 2.0 –
2.5 mEL. Site grading will require 1.5 – 3.5m fill to accommodate gravity flow through
WWTP and to bring plant above “flood” level. This may be a significant cost. The
geotechnical analysis will be finalised before the impact on the WWTP site is
confirmed.

If the frequency of flood events is known it may be practical to lower the site and
accept occasional inundation. Further investigation is being undertaken in an
attempt to locate and obtain relevant information for this purpose.
The bore logs show poor soils up to 15m depth and deep foundations (piles) will be
required for all major structures. The fill required to bring the site above the flood level
will also have an additional impact on the foundation design.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 0-5
Status: FINAL
Chapter 1: Introduction

Chapter 1: Introduction
1.1 PURPOSE

This Detailed Design Report has been prepared for the W268.1 – City Sewerage
Detailed Engineering Design (DED) Program (Package A – Palembang). Package A is
divided into the following sub-packages:
• Palembang (Sei Selayur) Wastewater Collections & Transfer System
• Palembang (Sei Selayur) Wastewater Treatment Plant & Effluent Disposal

This report has been generated to describe the detailed design for the Palembang (Sei
Selayur) Wastewater Treatment Plant & Effluent Disposal sub-package.

1.1 RELEVANT PROJECT DOCUMENTS

This document should be read in conjunction with the following documents:


• Collection System Detailed Design Report - Project Background

The Government of Australia extended the Indonesia Infrastructure Initiative (IndII)


facility into phase 2 from July 2011 to June 2015. The city sewerage grant is a major
component of the Water Supply and Sanitation Program. Under the phase 1 program,
IndII prepared wastewater management master plans for eight cities. Of these eight
cities, three are being considered for detailed engineering design: Cimahi, Makassar
and Palembang. The completed studies document sewerage schemes for the high
density areas of the cities and onsite sanitation for less dense areas. The priority
sewerage schemes of the master plans were developed further by the Asian
Development Bank under the Metropolitan Sanitation Management and Investment
Project (MSMIP) as part of its project preparation technical assistance for loan funding.
The priority sewerage projects typically comprise trunk collector sewers, tertiary
reticulation sewers, property connections, pump stations, a wastewater treatment
plant and an effluent disposal pipeline to the nearest receiving water.

The City Sewerage – DED includes detailed engineering designs and documentations
for the three cities under two packages:
• Package A – Palembang
• Package B – Makassar and Cimahi

This document pertains to Package A – Palembang.

1.2 PROJECT OBJECTIVES

The key objective of the Palembang (Sei Selayur) Wastewater Treatment Plant &
Effluent Disposal sub-package is to provide a detailed design package for a wastewater
treatment facility which can be included as part of a tender package for later
construction of the works.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 1
Status: FINAL
Palembang has no existing off-site sewerage systems. Many parts of the cities have
basic on-site systems such as septic tanks and pit latrines. Off-site sewerage systems in
general have never been considered in the past mainly because of the high cost of
construction and the difficulty in collecting revenue for the operation and
maintenance.

Drivers for creating an off-site sewerage system include the desire to eliminate public
health “hot spots” within the city which are mostly associated with poor sanitation
facilities and waterborne diseases and are prevalent in the lower socio-economic
areas; and to work towards meeting the Governor’s stated environmental objective of
making the Musi River a Class I or II river in terms of water quality. The implementation
of an effective citywide wastewater management strategy comprising a combination of
onsite sanitation, neighbourhood and centralised collection and treatment systems will
go a long way towards meeting these objectives. [Master Plan (IndII, 2011)]

This program will provide the design of a network for collection of wastewater from
nominated residential and commercial areas, a plant to treat the wastewater to a
nominated effluent quality level and an outfall system designed to minimise the impact
from the treated wastewater discharged from the plan on the receiving water body.
The detailed design for the collection system is presented in a separate report.

The design is undertaken in close consultation and collaboration with the city
governments and is expected to enhance their capacity and skills for sustainable future
wastewater management.

W268.01 City Sewerage DED


2 Palembang WWTP Final Detailed Design
Report Status: FINAL
2: Performance
Chapter 3: Key Assumptions
Requirements

Chapter 2: Key Assumptions


2.1 KEY ASSUMPTIONS & CONSTRAINTS

Design has been developed based on the following key assumptions and constraints:
• Wastewater flows and loads developed based on assumptions presented in the
Basis of Design reports and in this document. The collection system is to be
installed concurrently with the WWTP and therefore no wastewater flow
measurements or quality sampling was available.
• Provision of a collection system with connections upstream of septic tanks has
been adopted as a basis for review of loading development.
• Effluent quality BOD and TSS requirements are as cited in Master Plan.
Assume no other requirements than those identified in Table 3-4.
• Buildings on the WWTP site such as staff quarters, toilet blocks and guard
house to be designed by local designer.
• Environmental review and permitting by others.
• Water and power will be available for the site.
• Buildings including the saw mill kilns currently located on the allocated WWTP
site will be relocated as part of the LARP process.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 3
Status: FINAL
Chapter 3: Performance Requirements
This section outlines the performance requirements of the Sei Selayur WWTP
pertaining to the catchment operation, the subsequent peaking of flows entering the
WWTP, influent water quality and the required effluent water quality and odour
performance.

This chapter builds on information presented in the Basis of Design documents for the
collection and WWTP/effluent disposal systems (Annexes A & C).

3.1 POPULATION AND CATCHMENT DESCRIPTION

The Sei Selayur WWTP is designed to treat the sewerage flows collected in the
Palembang (Sei Selayur) collection and transfer system. The major flows and loads to
the WWTP, as defined in the Basis of Design documents, are summarised in Table 3-1.

Table 3-1: WWTP Average Influent Flow and Load Summary


Parameter Unit Value
(1)
Total domestic connections, Stage 1 connections 19,000
3
Total average domestic flow m /d 14,100
3
Total average commercial flow m /d 3,800
3
Total average infiltration flow m /d 2,100
(2)
Average dry weather flow to WWTP, ADWF MLD 20
(3)
Average influent BOD load to WWTP kgBOD/d 6,200
Average influent TSS load to WWTP kg/d 10,500
(4) 3
Additional allowance for septage flow m /d 112
(4)
Additional allowance for septage load kgBOD/d 675
1. Value per MSMIP Report, ADB 2013.
2. Includes 17.9 MLD sanitary flow and 2.1 MLD groundwater infiltration. Further details in collection system
design report.
3. Domestic BOD loading based on 5 people per domestic connection and 45 gBOD/p/day. Commercial BOD
load based on 500 mg/L.
4. Septage allowance included as agreed at the Basis of Design review meeting 29 January 2014 to increase
functionality of plant. Septage allowance assumes 20% of the 560 m3/d total city wide septage produced
(per Master Plan, IndII 2011) is brought to the WWTP. BOD concentration assumed to be 6,000 mg/L.

3.2 FLOW VARIATIONS

The flows defined above will be subject to fluctuation, caused by variation in the flows
of wastewater in the reticulation network due to factors such as weather conditions
and the behaviour of wastewater contributors.

The average dry weather flow (ADWF) represents the average flow from the
wastewater contributors in the collection area including steady groundwater
infiltration but without any contribution from wet weather events. The peak dry

W268.01 City Sewerage DED


4 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 3: Performance Requirements

weather flow (PDWF) represents the maximum flow anticipated from the collection
system due to daily and seasonal fluctuations in wastewater generation and not
including contributions from wet weather events. The peak wet weather flow (PWWF)
represents the maximum flow anticipated in the collection system including
contributions from wet weather events.

The wastewater collection network will gather flows from users throughout the
catchment and transfer flows to the WWTP via pump stations. The transfer of flows to
the WWTP will be subject to peaks, which must be managed. Flows up to the pump
capacities associated with the design daily peak dry weather flow (PDWF) will receive
full treatment at the WWTP without bypassing. Above PDWF and up to the maximum
capacity of the network pump station a portion of the influent flow will overtop a fixed
bypass weir at the inlet works of the treatment plant and be transferred to the plant
discharge via a manually raked screen. The management of peak flows as part of the
operation of the WWTP is discussed in further detail in Section 4.1 of this report.

Table 3-2: Key Transfer Pump Station Flows


Factor Flow (L/s) Remarks
Peak Dry Weather Flow 600 Represents peak diurnal flow
(PDWF) anticipated during an average dry
weather day at the design WWTP
capacity and the maximum flowrate
before the WWTP bypass weir begins
overtopping.
Peak Wet Weather Flow 1300 Maximum flow from transfer pump
(PWWF) station

3.3 INFLUENT CHARACTERISTICS

The Sei Selayur WWTP has been designed to receive influent sewage with contaminant
concentrations as defined in Table 3-3. The plant design was devised in conjunction
with the defined influent concentrations given below and the required effluent limits
outlined in Section 3.5.

Influent biochemical oxygen demand (BOD) was defined in the Basis of Design Report.
This value was used to derive the Total Kjeldahl Nitrogen (TKN) influent concentration
based on the assumed ratio of 4.5 kg BOD / kg TKN given the expected per capita loads
of BOD and TKN in standard domestic sewerage.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 5
Status: FINAL
Table 3-3: Design Wastewater Influent Characteristics
Parameter Unit Average Remarks
Value
Biochemical Oxygen mgBOD/L 350 Total influent flow including
Demand (BOD) sanitary flows and septage
received
Chemical Oxygen mg/L 700 Assumed ratio of COD:BOD is
Demand (COD) 2:1
pH 7.0 Design assumption
Temperature °C 25 Design assumption
Total Kjeldahl nitrogen mg/L 78 TKN concentration derived
using assumed loading ratio of
4.5 kg BOD/kgTKN in influent
wastewater.
Ammonia / TKN ratio - 0.75 Design assumption
Total suspended solids mg/L 410 Assumed ratio of BOD to TSS
is 1:1 for network flows and 3:1
for septage.
Volatile suspended - 0.8 Design assumption
solids to TSS ratio
(network flows)
Volatile suspended - 0.25 Design assumption
solids to TSS ratio
(septage flows)
Alkalinity mg/L as 200 Design assumption.
CaCO3
7
E.Coli (Faecal Coliforms) cfu/100 10 Design assumption
mL
Catchment sulphate mg/L as 50 Assumed value in the
2-
concentration SO4 catchment. This concentration
may be present as sulphide in
the inlet to the plant as
considered in the odour
treatment design.

3.4 EARLY OPERATION & TURNDOWN

The length of time until flow into a treatment plant matches the plant capacity is
dependent on the rate at which properties are connected to the collection system. A
slow rate of connection will mean the treatment plant will be operating below its
capacity, perhaps significantly below, for a number of years.

The anticipated rate of connection for the Sei Selayur collection system (based on rates
achieved in other cities in Indonesia) is 2,000 connections per year. Assuming also that
2,000 connections are completed prior to the WWTP start-up the initial ADWF has
been estimated to be 1.6 MLD with no assumed groundwater infiltration.

W268.01 City Sewerage DED


6 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 3: Performance Requirements

The management of the plant operation at low flows and loads, as expected in the
early years of plant operation, is discussed in Section 4.2.

3.5 EFFLUENT REQUIREMENTS

The effluent quality requirements for the Sei Selayur WWTP are listed in Table 3-4.
Table 3-4: Effluent Quality Requirements
Parameter Units Value Remarks
pH 6-9 Provincial standard
BOD mg/L 50 Provincial standard
Suspended solids mg/L 100 Provincial standard
Fats, oil and grease mg/L 10 Provincial standard
Class II standard for the Musi
River gives a river quality
standard for this parameter.
E. Coli cfu/100 mL 2,500 Value selected for WWTP
effluent is recommendation only
and has not been based on a
receiving water study.

3.6 ODOUR

The odour control and gas capture systems shall be designed to achieve a maximum
odour concentration of 15 OU at the nearest sensitive receptor, as caused by the
WWTP gas emission. A sensitive receptor shall be defined as one of the following:
• Medium/high density residential area
• School
• Hospital
• Community facility (e.g. park, place of worship, etc.)

The systems shall also be designed to provide a safe working environment above and
around covered process units. It is anticipated that hydrogen sulphide (H2S) gas will be
the main gaseous contaminant of interest. The Australian Guidelines for safe working
hydrogen sulphide levels are provided in Table 3-5.

Table 3-5: Hydrogen Sulphide Safe Working Levels


Long Term Exposure Limit Short Term Exposure Limit
Type of Gas
(8-hour, time weighted average) (15-mins)
Hydrogen sulphide (ppm) 10 15

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 7
Status: FINAL
Chapter 4: Flow Management
4.1 DESIGN CONDITIONS

This section outlines how variation in the influent flows and loads to the plant will be
managed. Note that the management of low flows and loads which are expected to be
encountered in early operation of the plant (directly following plant commissioning)
are discussed in Section 4.2.

The wastewater collection network will gather flows from users throughout the
catchment and transfer flows to the WWTP via transfer pump stations. The transfer of
flows to the WWTP will be subject to peaks, which must be managed. Flows up to the
pump station capacities associated with design daily peak dry weather flow (PDWF)
will receive full treatment at the WWTP without bypassing. Above PDWF and up to the
maximum capacity of the network pump stations a portion of the influent flow will
overtop a fixed bypass weir at the inlet works of the treatment plant and be
transferred to the plant discharge via a manually raked screen.

Further definition and quantification of the key design flows are described in Section
3.2

The transfer pump stations use fixed speed pumps. When the contributing flow from
the upstream collection system is less than the minimum pump capacity the pumps
will stop and wait for the flow to collect in the pump station wetwell. This will result in
repeated pump starts and periods of no flow into the WWTP. The operation of the
transfer pump stations is further defined in the collection & transfer system concept
design report.

The operation of the transfer pump stations feeding the WWTP is outlined in Table 3-2.
The resulting impact on the WWTP inlet flow splits is defined in Table 4-1.

Table 4-1: WWTP Influent Flows


Parameter Flow (L/s) Remarks
approximately equivalent to maximum
Flow at which WWTP bypass pump flow rate on an average dry
660 weather day (PDWF) plus 10% safety
weir begins overtopping
margin

Maximum transfer pump


1300 Refer Table 3-2
station flow
Maximum flow to full
800 At maximum transfer pump station flow
treatment
At maximum transfer pump station flow.
Maximum flow through Bypass sized to accommodate full
500 maximum pumped flow in the event of
WWTP bypass
complete WWTP failure.

W268.01 City Sewerage DED


8 Palembang WWTP Final Detailed Design
Report Status: FINAL
4: Site
Chapter 7: FlowDevelopment
Management

Flow management at the WWTP is designed to be predominantly passive, where


minimal operator input will be required.

The hydraulic design accommodates the full treatment capacity through the entire
process with the following exceptions:
• the BTF receives a constant pumped flow and is therefore not impacted by
flow peaks;
• the clarifier receives all flow from the BTF not recycled to the BTF inlet.

The hydraulic profile and process flow diagram for the plant are presented in Annex 3.

Inlet Works: Flows bypassing the WWTP will overflow a weir upstream of the inlet
flume and be diverted via a wet weather overflow channel to the river. This overflow
will pass through a manually raked screen. The manually raked screen will require
manual operation by plant staff. It is expected that the concentrations of contaminants
in this high flow will be low due to dilution incurred by high flows.

Anaerobic Baffled Reactors (ABR): Each ABR tank is designed to receive up to half of
the full flow from the inlet works. Weirs at the inlet works outlet evenly split flow
between the two tanks. Effluent leaves each cell of an ABR tank via a series of short
weirs and baffle walls. The large surface area of the ABR tanks will provide some level
of temporary attenuation of flow fluctuations; however, the duration of peak events is
not known so this attenuation cannot be quantified and it is assumed for the design
basis that the full peak flow will be passed through the tank.

Biological Trickling Filter (BTF): The BTF operation will utilise a constant feed flow to
the filter via a fixed speed pump. The BTF effluent will flow to the BTF recirculation
chamber of the BTF feed pump station. From here flow may either be returned to the
BTF feed pumps, to be recycled back through the BTF, or overflow a weir to be passed
forward in the plant operation.

The BTF feed pump speed is set such that the recycle ratio of the BTF is 1:1 under
ADWF conditions. The recycle ratio is defined as:

[recycled BTF effluent] : [feed to BTF feed pumps]

The BTF recycle rate will vary according to the flow into the BTF pump station from the
upstream process. As such, the operation will be self-regulating, with the BTF feed
pumps operating at a fixed flow. To achieve a 1:1 recycle ratio, the total duty BTF feed
pump capacity will be equal to 2 x ADWF.

Secondary Clarifier: The secondary clarifier will be designed to receive all of the BTF
effluent less the recycle flow back to the BTF. Flows above the maximum flow to the
BTF will bypass the clarifier and be sent directly to the Chlorine Contact Tank (CCT).
This will be passively controlled using weirs.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 9
Status: FINAL
Disinfection System: The disinfection system chlorine contact tank (CCT) will be
designed to treat all flows received from the clarifier and the bypass.

Effluent Disposal: The effluent disposal will be free discharging by gravity up to a flood
level (3.75mEL).

4.2 LOW FLOW OPERATION

The Sei Selayur collection and transfer system and WWTP will be developed
concurrently. As a result, the flow and load to the treatment plant is expected to
increase over time in accordance with the number of properties connected to the
reticulation network. The rate of connection is outlined in Section 3.4.

The WWTP is planned to be commissioned approximately one year into the connection
period. This will dictate the feed conditions as defined in Table 4-2, which outlines the
network flow upon commissioning, not including the septage loads. It is assumed the
septage flows will be equal to the ultimate septage loads.

Table 4-2: Minimum flow conditions to the WWTP


Parameter Units Value
Minimum Commissioning Flow MLD 1.65
Minimum Commissioning Load kgBOD/day 512

The anaerobic baffled reactor is expected to be under-loaded in early years of


operation. Under-loading improves the water quality of the tank discharge when
considering BOD concentration and will result in a low BOD load to the trickling filter.
Where the trickling filter is operated with a low BOD load, the aerobic process will tend
towards developing autotrophic bacteria, driving nitrification. Nitrification will
consume alkalinity and hence lower the pH of the wastewater. There is a risk that
under these conditions, the pH of the BTF effluent may move outside of the discharge
limits, defined for the plant.

In order to mitigate this risk, the treatment plant has been configured with two flow
diversions, described as follows:
• ABR Bypass: this bypass provides the ability for a portion of the flow from the
inlet works to be sent directly to the BTF. The configuration will pass raw
wastewater containing both BOD and TKN to the trickling filter allowing for the
BTF operation to be maintained even at the low flow case.
• BTF Bypass: this bypass provides the ability to direct anaerobic baffled reactor
effluent around the trickling filters directly to the disinfection system and
subsequently the river discharge. The effluent is expected to be suitable for
direct discharge due to the low loading of the anaerobic tanks.

A schematic of the low flow strategy is given in Figure 4-1. Note that all septage flow
will be sent to the ABR , and not included in the bypass to the BTF.

W268.01 City Sewerage DED


10 Palembang WWTP Final Detailed Design
Report Status: FINAL
4: Site
Chapter 7: FlowDevelopment
Management

The two required bypass flows will be initiated in commissioning of the WWTP. The de-
commissioning of the bypass flows will occur at a point where the plant performance
allows for normal plant operation.

In addition, it is recommended that one of the two ABR trains be operated in the early
years of plant operation. This will allow for the development of a microbial population
at low flows.

Table 4-3: Minimum flow conditions to the WWTP


Parameter Minimum Maximum Recommended Constraints
Plant Load Plant Load
(kg BOD/d) (kg BOD/d)
Removal of BTF 3300 4000
Bypass
Commissioning of 3300 4000 Recommended to occur
ABR No. 2 following the decommissioning
of the BTF bypass
Removal of ABR 3300 4000 Recommended to occur
Bypass greater than 6 months
following the commissioning of
ABR No. 2

This system of bypasses allows for all elements of the plant to be made operational
from commissioning.

Alkalinity correction has not been included in the detailed design. However, the
potential risk of low alkalinity and subsequently low pH in the plant effluent has been
identified as part of the detailed design of the WWTP. Influent design assumptions
have been made, as outlined in the BOD, in order to develop the WWTP design. It is
expected that the bypass arrangements described here will be sufficient to operate the
WWTP to meet the required licence conditions for effluent pH, in light of the influent
assumptions made.

Provision for alkalinity correction may be made in future operation of the plant in
order to address alkalinity issues caused due to variations from the design assumptions
used in this report. A number of options for the correction of alkalinity may be
considered in future such as caustic solution dosing or an appropriate equivalent.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 11
Status: FINAL
Anaerobic Baffled Reactor Bypass = nil

Trickling Filter / Provision


Provision for
for
Influent
Influent Anaerobic Disinfection
Disinfection //
Secondary Alkalinity
Alkalinity
== 20
20 MLD
MLD Baffled Reactor River
River Discharge
Discharge
Clarifier Correction
Correction

Septage
Septage Trickling Filter Bypass - nil
(a) Normal Operation

Anaerobic Baffled Reactor Bypass = 50% of Influent

Influent
Influent Trickling Filter / Provision
Provision for
for
Anaerobic Disinfection
== 1.65
1.65 Secondary Alkalinity
Alkalinity Disinfection //
Baffled Reactor River
MLD
MLD Clarifier Correction
Correction River Discharge
Discharge

Septage
Septage Trickling Filter Bypass

(b) Low Flow Operation

Figure 4-1: Flow bypass operation under (a) normal operation and (b) low flow
commissioning operation

W268.01 City Sewerage DED


12 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

Chapter 5: Process Design and Unit Process Development


This section addresses the development of the design of key process units of the Sei
Selayur WWTP.

5.1 PROCESS DESIGN OVERVIEW

The Sei Selayur WWTP will consist of the following unit processes:
• Inlet Works (Screening and Grit Removal)
• Anaerobic Baffled Reactors
• Biological Trickling Filter
• Secondary Clarifier
• Chlorine Contact Facility
• Odour Control Facilities
• Site Waste Return System

The overall process configuration is shown in the plant PFD (Drawing 200-G010 in
Annex D). The design development of each unit process is described in detail below.
The operational philosophy for the plant is outlined in the Operational Philosophy
(included in Volume 2.3 Part 3 of the specifications).

The process train has been developed to ensure ease of operation and low
maintenance requirements. However, provisions have been allowed for flexibility in
operation, potentially mitigating the risk associated with variation in plant conditions
which may arise during the commissioning and ongoing operation of the plant. These
provisions include recycle streams in the anaerobic baffled reactors and bypass flows
to allow flow management where the plant is operating at low loads, as described in
the following sections.

Design drawings referred to in the following sections are found in Annex D.

5.2 INLET WORKS

5.2.1 PERFORMANCE REQUIREMENTS

The inlet works consist of the following key elements:


• Wet weather bypass: provides bypassing of flows in excess of the plant
capacity directly to the river.
• Flow measurement: provides monitoring of the total flow into the WWTP.
• Inlet screening: removes rags, plastics, wood and grit (i.e. inorganic solids like
rocks, gravel, sand) from the wastewater before it enters the WWTP to protect
downstream equipment and prevent accumulation of excessive inert material
in the anaerobic tanks. Occasionally coarse screening (opening size > 20 mm) is
installed at the inlet to the plant to prevent large objects (i.e. boards,
carcasses) from entering the plant and damaging inlet pumps or preliminary

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 13
Status: FINAL
treatment equipment. Due to the enclosed nature of the collection system
and upstream pumping it is not anticipated that large objects will be able to
enter the system and coarse screening is not considered necessary.
• Grit removal: removes sand, gravel and other heavy solids from the raw
wastewater in order to protect downstream mechanical equipment from
abrasion, abnormal wear, and to reduce accumulation of inert material in
downstream processes.

The inlet works must accommodate the flows presented in Table 5-1.

Table 5-1: Performance Requirements – Inlet Works


Parameter Units Value Remarks
Minimum influent flow L/s 150 Not including periods of no flow
Maximum influent flow L/s 1300
Peak WWTP treatment At maximum transfer pump station
L/s 800
capacity flows.
At maximum transfer pump station
flow. WWTP bypass will be capable
Peak WWTP bypass
L/s 500 of receiving full maximum influent
capacity
flow in the event of complete
WWTP failure
Bar spacing mm 5-6 selected to protect BTF equipment

5.2.2 PROCESS DEVELOPMENT

Wet weather bypass: Wet weather flows in excess of the peak plant capacity will
overtop a long straight weir located upstream of the flume. The bypass will be
equipped with a manually cleaned coarse screen with a 10mm bar spacing. It is
expected that the concentrations of contaminants in this high flow will be low due to
dilution incurred by high flows.

Flow Measurement: Measurement of influent flow to the WWTP will be provided


using a rectangular flat bottom flume with upstream level sensor. The flume enables
flow to be measured manually in the event of instrument failure. A scale will be
mounted on the channel wall to enable visual estimation of inlet flow.

Inlet Screening: A screen opening of 5mm was selected to provide removal of inerts.

Mechanically raked barscreens will be provided for inlet screening. The screen consists
of a frame with vertical metal bars which is installed in the flow stream. Larger solids
will be captured on the bars while the remaining flow passes through. A mechanical
rake is lowered intermittently into the channel and is pulled up along the screen to
remove any materials collected on the screen. The rake deposits collected screenings
onto an adjacent screenings conveyor/compactor.

W268.01 City Sewerage DED


14 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

A cleaning rake cycle will be initiated by an upstream level switch indicating flow
through the inlet works.

The mechanically raked barscreen was selected for this application because there are
minimal parts requiring maintenance and all maintenance can be conducted without
requiring drainage of the channel.

The conveyor/compactor will be provided to simultaneously convey & compact


screenings removed from the barscreens and discharge the compacted screenings into
an adjacent waste bin. The conveyor/compactor will be called to run simultaneously
with the automatic screen raking system. Other systems such as conveyance sluices
were not considered due to large service water demands. The WWTP will not include a
recycled water system; therefore, all service water used on site will need to be
supplied from the potable water network.

An inlet screen bypass is provided around the mechanically raked barscreens in the
event of blinding of the screens due to unexpectedly high loading or failure of the
mechanical rake. The bypass will be equipped with a manually cleaned coarse screen
with a 10mm bar spacing.

Grit Removal: Grit removal was included to reduce the build-up of grit within the
anaerobic baffled reactors which would require periodic manual removal. Two options
for grit removal were considered: vortex grit chamber and horizontal grit chambers.
The horizontal grit chamber option was eliminated due to its inability to function
reliably over the wide range of flows anticipated; high headloss and the excessive wear
of submerged equipment increasing maintenance requirements. Vortex grit chambers
are energy efficient and require a small footprint. Headloss through a vortex system is
low. Vortex grit systems remove a high percentage of fine grit and have consistent
removal efficiency over a wide flow range. Although they have maintenance problems
with paddles collecting rags, the grit sump clogging and requiring high-pressure
agitation using water or air to loosen grit compacted in the sump, the chambers have
no submerged bearings or parts that require maintenance.

The grit vortex will include a system for removal of the grit to a grit bin. This will
include the required grit pump and grit classifier systems, as defined by the equipment
vendor.

5.2.3 DESIGN DESCRIPTION

The design configuration is summarised in Table 5-2.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 15
Status: FINAL
Table 5-2: Design Configuration Summary – Inlet Works
Parameter Units Value Remarks
Wet weather Bypass
Capacity L/s 500
Control mechanism - long straight weir 10m long
manually cleaned
Screening - 10mm bar spacing
barscreen
Flow Metering
Type - rectangular flume per AS3778.4.7-1991
Size (throat width /
mm 600 / 1200
length)
Inlet Screening
Mahr type screen or
Type mechanical barscreens
equivalent
Bar spacing mm 6
Number 2 each sized at 100%
peak instantaneous
Capacity (per screen) L/s 800
flow
1 no. screw
Screenings collection
conveyor/compactor
Screen Bypass
manually cleaned
Type
barscreen
Bar spacing mm 10
Number 1
peak instantaneous
Capacity L/s 800
flow
Grit Removal
Type - Vortex Chamber
Number 1
peak instantaneous
Capacity L/s 800
flow
Grit Collection grit pump & classifier

W268.01 City Sewerage DED


16 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

5.3 SEPTAGE RECEIVAL

5.3.1 PERFORMANCE REQUIREMENTS

The septage receiving station will include a septage screening channel to remove rags,
plastics, wood and a portion of grit (i.e. inorganic solids like rocks, gravel, sand) from
the septage before it enters the WWTP to protect downstream equipment and prevent
accumulation of excessive inert material in the anaerobic tanks.

The screened septage will drain to the adjacent grit settling chamber and then to the
site waste pump station. The waste pump station is described in Section 5.10.

The septage receiving station must accommodate the flows presented inTable 5-3.

Table 5-3: Performance Requirements – Septage Receiving Station


Parameter Units Value Remarks
3
Design daily volume m /d 112
3
Volume per septage truck m 3
assumed 5min for truck
Estimated flow rate L/s 10
drain down
Bar spacing mm 20 & 10 Two screens in series

5.3.2 PROCESS DEVELOPMENT & DESIGN DESCRIPTION

A pull-out bay will be located next to the waste pump station for parking of septage
trucks during emptying. The pull-out bay will be provided with a drain to the waste
pump station for collection of spilled septage.

The septage truck discharge hoses will be set in the receiving chamber on the septage
screening channel. The screening channel will contain two manually cleaned coarse
screens in series with a 20mm and then 10mm bar spacing. Each screen will be
equipped with a drainage shelf on which screenings manually removed from the
screen can be placed to drain. Screened septage from the trough will drain by gravity
to the adjacent site waste pump station.

The screening trough will require visual inspection and manual cleaning of the screens
during septage unloading events.

The septage grit chamber provides a settling point to provide some reduction in grit
transferred to the ABRs. The grit chamber will require periodic manual removal of
accumulated grit.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 17
Status: FINAL
5.4 ANAEROBIC BAFFLED REACTOR (ABR)

5.4.1 PERFORMANCE REQUIREMENTS

An anaerobic baffled reactor has been designed as part of the WWTP in order to
remove BOD load from the influent wastewater. The process will form the primary
means of BOD removal, and is designed to remove a minimum of 70% of the BOD load
of the plant.

Anaerobic treatment relies on the growth of bacteria in the absence of oxygen to


remove a large fraction of the influent carbon load. Furthermore, the design of the
anaerobic baffled reactor will allow for the removal of solids load to the WWTP. Solids
fed to the plant will be a combination of volatile (VSS) and inert (ISS) suspended solids.
The anaerobic baffled reactor will remove solids through a combination of both the
organic destruction of a portion of the VSS and settling of a portion of the remaining
undigested solids. Hence, the anaerobic baffled reactor used in the WWTP will allow
for a reduction in both the BOD and TSS load to the plant.

The performance requirements set out for the anaerobic treatment are outlined in
Table 5-4, extracted from the basis of design.

Table 5-4: Performance Requirements – Anaerobic Treatment


Parameter Units Value Remarks
Design average flow MLD 20 ADWF
Peak instantaneous maximum WWTP
L/s 800
flow flow
Hydraulic retention
days 1.5 At ADWF
time (HRT)
Solids retention time
days >60
(SRT)
BOD removal %/w 70
SS removal %/w 70 Design assumption

5.4.2 PROCESS DEVELOPMENT

The primary function of the anaerobic treatment is to convert the BOD to biogas (a
mixture of carbon dioxide and methane) and water without the presence of oxygen.
The BOD removal achieved in anaerobic ponds is predicted to be 70% of the incoming
BOD load in a warm climate such as Indonesia.

The main advantage of an anaerobic treatment process is that it requires no power to


operate and produces a low quantity of excess bacteria cells, referred to as ‘sludge’.
The sludge which is produced will have a high sludge age, which is dictated by the

W268.01 City Sewerage DED


18 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

concentration of sludge in the tank, and will hence be highly stabilised. This will allow
for sludge to be transferred directly to a sludge drying bed, as described in Section 5.8.

Bioreactor configuration: The design used for the anaerobic treatment is an anaerobic
baffled reactor (ABR). The ABR configuration uses a series of 3 (no.) discrete tank
sections, referred to as cells. The orientation of feed and effluent points from each cell
forces the wastewater flow in an upward direction through each cell. As the biomass
population (sludge concentration) in each cell is established, the wastewater will be
forced to pass upward through a high concentration sludge blanket.

A schematic of the up-flow process is given in Figure 5-1.

Screened and
de-gritted flow
from Inlet Effluent to
Works BTF Pump
Station
Cell 1 Cell 2 Cell 3

Figure 5-1: Anaerobic baffled reactor train flow schematic

The up-flow design allows for a number of treatment advantages, including:


• the ability to maintain a high concentration of solids and a subsequent high
sludge age, due to the settling of sludge in each section,
• good contact between treated inflow and the anaerobic biomass, improving
treatment of the wastewater, and
• partial segregation of various anaerobic bacterial operation is expected to
improve the resilience of the process to shock loading (Foxon, et al, 2006).

The anaerobic digestion process will occur via a series of reactions, a high level
summary is as follows:
• Hydrolysis – breaking down long chain volatile fatty acids (VFAs) into smaller
chain molecules, such as monosaccharides (identified as the rate limiting step
of the process)
• Acetogenesis – converting intermediate products into acetate
• Methanogenesis – converting either acetate or intermediate acidic compounds
to methane and carbon dioxide.

The use of an anaerobic baffled reactor allows the above processes to be somewhat
segregated into various segments, generating a more efficient population tuned to a
specific process in various cells. This segregation will potentially allow for more rapid
completion of rate limiting digestion steps (Foxon, et al, 2006).

Design Modelling: The anaerobic baffled reactor design has been developed by means
of both process calculations and simulation modelling (Refer Annex E). The model was
developed using the BioWinTM software package developed by EnviroSim.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 19
Status: FINAL
Modelling was used to predict the performance of the plant with respect to BOD and
volatile suspended solids removal in each stage in order to confirm the performance of
each unit operation as predicted by process calculation. Specifically the modelling was
used to define the response of the ABR to changes in influent characteristics, relating
to pH and alkalinity.

Hydraulic Retention Time (HRT) Development: HRT of the bioreactor has been
developed as part of the detailed design. The original site concept utilised a 3 day HRT.
Review of literature has found operating examples of Australian wastewater treatment
plant operations where a HRT of 1.5 days has been shown to produce adequate
performance. The specification of a smaller HRT allows for a proportionally smaller
tank to be constructed, realising significant capital expenditure savings and a more
adaptable design given site area constraints. The use of a 1.5 day HRT was modelled
for operability and robustness using the BioWinTM software.

During periods of maximum flow into the plant (800 L/s), the sludge blanket is
expected to be lifted due to the increased upflow rate in each cell. It is anticipated that
during extended periods of high flow the solids capture performance of the ABR may
deteriorate.

Solids Retention Time (SRT) Development: The design SRT and solids concentration
values are outlined in Table 5-5.

The high SRT will allow for the production of more stable sludge with a lower
proportion of volatile solids. More stable sludge will allow for significant advantage in
the sludge removal process, in terms of sludge stability and volume. The more
complete digestion of sludge will increase sludge stability, avoiding the requirement of
any further sludge stabilisation process, such as a sludge lagoon, prior to sludge being
applied to sludge drying beds. Furthermore, smaller volumes of sludge will require
removal, due to the more complete digestion of volatile solids.

Hydraulic Recycle: The anaerobic baffled reactor design has allowed provision for a 10
ML/d recycle stream in each train to direct flow from the final cell of each train to the
inlet of the first cell of each train. This recycle has been included to improve the
stability of the anaerobic process in relation to shock loading and low pH influent. This
is predominantly important in mitigating risk associated with unknown pH and
alkalinity in the plant feed water.

Biogas capture: The anaerobic treatment process emits a biogas consisting of methane
and a number of odorous chemicals such as hydrogen sulphide and amines and
therefore the anaerobic tanks are often covered and the gas managed for safety and
health concerns. The biogas handling system is described in Section 5.10.

Sludge Pumps: A sloped floor will direct sludge in each cell of the ABR to a central
sludge low point. Sludge will then be drawn from the sludge low point via a suction line
to an externally mounted progressive cavity pump which will pump sludge to the
drying beds. Each cell will have a dedicated sludge pump. The pumps will be manually
operated as required to maintain sludge concentration in each cell. The frequency of

W268.01 City Sewerage DED


20 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

desludging events will be discussed in the final operations and maintenance manuals
which are to be completed.

At the point of commissioning of the Sei Selayur WWTP the inlet flow from the
network will be low, as discussed in the flow management section. However, the
septage flow has been assumed to be constant throughout the growth of the network,
as outlined in Table 5-3. Hence, the percentage of the plant flow and load which
originates as septage will be higher at the commissioning of the WWTP. Septage flow
will be directed to the inlet of the ABR, bypassing the inlet works grit removal
chamber. As such, grit associated with the septage flow will be captured in the ABR
solids blanket and subsequently removed via the ABR sludge pumps. During the early
operation, the proportion of the sludge made up by grit will be higher than expected
when the plant is operating at design capacity. Hence the sludge pumps will need to be
supplied with consideration of pumping abrasive sludge flows. Attention must be made
to the requirement for increased liner replacements given the progressive cavity pump
design proposed.

5.4.3 DESIGN DESCRIPTION

The anaerobic baffled reactor tanks will operate as two trains, each designed to treat
half of the plant design capacity. Weirs at the inlet works will divide the incoming flow
evenly between the trains. Flow will be fed into the bottom of the first cell of each ABR
train via a dedicated pipe from the inlet works.

Flow will pass an underflow baffle into the main volume of the first ABR cell. Flow will
then traverse the ABR cell, flowing upwards through a sludge blanket before passing an
overflow baffle wall at the far end of the first ABR cell. Flow will then be fed to the
bottom of the next cell via an underflow baffle. This process will repeat through all
three ABR cells. Flow will exit the third cell by exiting through outlet orifices into the
effluent channel. The outlet orifices will be submerged to prevent accumulated biogas
from leaking into the effluent channel.

The concentration of sludge is expected to decrease in each subsequent cell of the


ABR, with the highest solids load in the first cell. As described above, some segregation
of bacterial operation is expected in the ABR cells. The highest level of hydrolysis
activity is expected to occur in the first cell of the tank, where methanogenic activity is
expected to be favoured in later cells.

The process will accumulate sludge as BOD is removed. The sludge will be periodically
removed in order to maintain stable ABR operation.

The design dimensions of the anaerobic tanks are outlined in Table 5-5.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 21
Status: FINAL
Table 5-5: Design Configuration Summary – Anaerobic Treatment
Parameter Units Value Remarks
Type - Anaerobic Baffled in covered, reinforced
Reactors concrete tanks
No. of trains no. 2 both units each with
50% capacity

Design average flow, MLD 10 ADWF


per train

Peak flow, per train L/s 800 PDWF

Hydraulic retention days 1.5 At 20 MLD plant


time (HRT) design flow

Solids retention time days > 60


(SRT)

Solids concentration wt% Cell 1: 1.6 Biowin model output.


Cell 2: 1.4
Cell 3: 0.5
BOD removal % 70 Minimum design value
Biogas management Flare can be retrofitted as
part of future works
with energy recovery
facility
Number of cells per no. 3
train
Tank water depth m 4.5

Internal recycle MLD 10 1 x ADWF


flowrate per train
2
Total surface area m 6,700 including both trains

Predicted sludge kg dry 4165 at ADWF


production sludge
/day
3
Average daily sludge m 139 Assuming six-8hr
wasting wasted wasting events
per day fortnightly with sludge
wasting occurring at
2wt% solid
concentration.
Sludge pump design L/s 11 Assuming six-8hr
duty wasting events
fortnightly.

W268.01 City Sewerage DED


22 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

Solids Removal: The concentration of sludge within the anaerobic reactor will require
management during plant operation. Sludge removal will be periodically required from
the ABR tanks, as the biomass population increases over time. The build-up of sludge
will be monitored by the plant operational staff, given a sludge inventory
measurement which is detailed as part of the particular specification for operation,
testing and commissioning.

Sludge will be removed from each cell of the ABR by means of an external, fixed-speed,
progressive cavity pump. Solids will be removed via a manual operation of the sludge
pumps as detailed in the particular specification for operation, testing and
commissioning. When the concentration of sludge in each cell increases to a
predetermined level, a solids removal operation will be required.

It is anticipated that sludge will be removed from each cell on a fortnightly basis where
the ABR is operating at full design capacity, resulting in 6 sludge removal events per
fortnight. However, this frequency may be varied according to the prevailing
concentration of solids in each cell which will vary according to the load on the ABR. In
early years, the sludge removal operation will be less frequent.

Recycle Pumps: Each tank will be equipped with a fixed speed, submersible recycle
pump and recycle stream. Each recycle pump will be operated manually by plant
operations where there is a requirement given the operating conditions described
above.

ABR Isolation: Each anaerobic baffled reactor tank may be manually isolated using a
stop log at the inlet works. Either one or both tanks may be isolated. The ABR bypass
will allow for flow to be diverted directly to the trickling filter.

5.5 BIOLOGICAL TRICKLING FILTER AND BTF FEED PUMP STATION

5.5.1 PERFORMANCE REQUIREMENTS

The anaerobic baffled reactor is designed to remove 70% of the plant BOD load at full
plant capacity, resulting in a concentration of approximately 105 mg/L of BOD being
fed forward. The combination of the biological trickling filter (BTF) and the
downstream secondary clarifier shall complete the remaining required removal of BOD
to ensure the WWTP reliably achieves the plant target effluent condition. The BTF will
treat BOD in the ABR effluent via an aerobic process, converting organic material (BOD)
to CO2 and new cellular material. The BTF may also provide some nitrification under
certain conditions, converting ammonia to nitrates/nitrites and new cells.

5.5.2 PROCESS DEVELOPMENT

Number of Filters: The BTF operation will use one BTF, upstream of a clarifier process.
The design of the BTF unit operation has been amended from that presented in the
basis of design report, where two BTF units were proposed.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 23
Status: FINAL
The BTF design was completed considering the requirement for removing organic BOD,
where the major design parameter used was the organic loading of BOD per unit
volume of media which was specified as 0.5 kg BOD/m3.day. In review of the design of
the plant, and the design requirement for BOD removal, the organic loading rate at the
design condition has been amended to 1.0 kgBOD/m3.day. The higher loading is
possible as nitrification / de-nitrification reactions are not required to meet the target
effluent conditions. Empirical calculation of the required volume to allow for removal
of BOD has shown the revised loading rate to be appropriate. The plant design has
hence been amended to allow greater emphasis on solids removal by utilising one BTF
and a secondary clarifier. The secondary clarifier design is discussed in Section 5.6.

Flushing: The aerobic BOD removal will generate bacterial growth which will increase
the biofilm layer thickness present on the media. The biofilm layer must remain
sufficiently thin in order to maintain aerobic operation. In order to achieve this, the
system will undergo a periodic flush, nominally defined to occur daily. During a flush
the rotational speed of the distributor arm will be reduced, increasing the hydraulic
dose rate to the media which is defined with units of mm water per pass of the
distributor arm. The dose during normal operation has been specified as 30 mm/pass,
while the flush dose is defined as 300mm/pass. The increase in dose rate is intended to
remove excess solids build-up on the trickling filter media, which will then be passed
downstream.

Ventilation: The trickling filter will require forced airflow in order to maintain the
aerobic operation. This will be provided via a series of extraction points at the base of
the media bed structure, where air is drawn via the site odour control fans, drawing air
downwards through the media. The trickling filter shall incorporate a cover with air
inlets. The cover shall reduce the likelihood of any foul air emission from the top
surface of the media associated with the anaerobic baffled reactor effluent, which may
have a residual concentration of hydrogen sulphide. The ventilation rate shall be set to
a minimum required to achieve adequate distribution of air through the media, which
is predicted to exceed the air requirement of the biological reaction.

5.5.3 DESIGN DESCRIPTION

The design parameters used for the trickling filter are outlined in Table 5-6.

ABR effluent will flow via gravity from the ABR to the BTF feed pump station. The flow
from the BTF feed pumps to the filter media will be constant where the recycle rate
will vary to accommodate variation in flows from upstream processes. To achieve this,
the operating BTF feed pump will transfer a set flow to the rotating distributer arm and
hence onto the filter media. The flow leaving the filter will be directed back to the BTF
return well, as part of the BTF feed pump station. Flow will be passed via a non-return
flap valve from the BTF return well back to the BTF feed pump station wet well at a
rate which makes up the difference between the feed to the BTF pump station and the
flowrate of the BTF feed pumps. All flow which is not recycled will be passed
downstream to the outlet well. As such, minimal control will be required for the BTF
feed pump station operation.

W268.01 City Sewerage DED


24 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

Flow which enters the BTF pump station above the capacity of the BTF pumps (431L/s)
will bypass a weir and be diverted to the chlorine contact tank.

Table 5-6: Design Configuration Summary – Biological Trickling Filter


Parameter Units Value Remarks
Structure Type - Steel panel tank TBC
No. of trickling filters no. 1
3
Organic Loading kgBOD/m .day 1.0
3
Media volume m 2,100
Media depth m 5
Diameter m 23
At average
Recycle ratio ratio 1:1 trickling filter
influent flow
Operational
mm/pass 30
hydraulic dose
Flushing hydraulic
mm/pass 300
dose
Total required 3
Nm /min 126
airflow
Airflow empty bed
mins 16.7
contact time

BTF Feed Pump Station: The BTF will be fed via the BTF feed pump station. The design
parameters of the BTF feed pump station are outlined in

Table 5-7. The pumps will operate in a duty/duty/standby configuration. The pumps
will be sized to give a total flow of 463 L/s under normal operation with two pumps
operational.

The pump station may be operated as duty/standby/standby in early years of


operation to take the low flow to the BTF into account. Where one pump is
operational, the flow is expected to be 350 L/s. This will give a recycle ratio upon plant
start-up of approximately 55:1.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 25
Status: FINAL
Table 5-7: Design Configuration Summary – BTF Feed Pump Station
Parameter Units Value
Number of Pumps no. 3
Pump configuration - duty / duty / standby
Pump station capacity two pumps
L/s 460
operating
Pump station capacity single pump
L/s 350
operating
Drive type - DOL

BTF Distributor Arm: The distributer arm will be motorised such that feed is evenly
distributed onto the plastic media. The BTF distributor will operate at a constant speed
except during an automated flush sequence, which will be programmed in the plant
control system to be completed at the set interval (default 24 hours, operator
adjustable).

When a flush sequence is called by the plant control system, the distributor arm motor
will slow to the rotational speed required to give the set flush pass rate 300 mm/pass
for set number of revolutions (default 1 revolution, operator adjustable).

The set-points required for this operation are to be set in commissioning; however, the
required frequency of the flush sequence may vary over the life of the filter as more
connections are made to the reticulation system, and the load on the unit operation
increases.

The operator may also manually hose down the distributor arm from the access
platform where there are blockages identified by means of observation as part of
regular maintenance checks.

5.6 SECONDARY CLARIFIER

5.6.1 PERFORMANCE REQUIREMENTS

A secondary clarifier has been included in the plant design in order to limit the risk of
the plant effluent solids concentration rising above the discharge limit. The secondary
clarifier will remove TSS from the plant flow downstream of the BTF. This process will
also decrease the effluent BOD, through the removal of organic solids.

5.6.2 PROCESS DEVELOPMENT

The use of the secondary clarifier process has been modelled as part of the process
modelling completed in Biowin, discussed previously. The BTF operation is primarily
focussed on the removal of BOD from the influent stream by means of an attached
growth aerobic process. While some volatile solids will be removed via digestion, the

W268.01 City Sewerage DED


26 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

process will incur the growth of biomass, adding to the aggregate solids. The overall
biological process poses a risk that the solids concentration may not be reduced in the
trickling filter.

The secondary clarifier will treat flows downstream of the BTF to ensure excess TSS is
removed, limiting the risk of failure of the TSS target. The clarifier design is anticipated
to remove both TSS and BOD, with BOD removal being achieved as organic solids are
removed.

5.6.3 DESIGN DESCRIPTION

The design will utilise one secondary clarifier unit.

The secondary clarifier design allows for an appropriate upflow rate and solid loading
to ensure the required capture of solids is maintained under design flows and loads.
The clarifier has been designed with an upflow rate of 1.40m/hr under average plant
flow conditions. The clarifiers will be sized to receive up to the full flow which is
treated by the BTF. Any flows above that which the BTF may treat (limited by the BTF
feed pump capacity) shall overflow the BTF pump station and bypass the clarifier
operation. As such, the clarifier may only be fed with BTF effluent. ABR effluent which
is not treated in the BTF will also bypass the clarifier operation.

The clarifier will be equipped with a Tow-Bro style sludge withdrawal system which will
traverse the clarifier floor driven by a fixed speed motor. The Tow-Bro style system
hydraulically removes the solids through a perforated hollow tube running from the
centre well to the outer wall of the tank providing uniform sludge removal across the
diameter of the tank bottom. The solids collection tube will be connected directly to
the suction header of an adjacent clarifier sludge pump station. The pump station will
utilise a duty/standby configuration.

The clarifier sludge stream, which is drawn via the clarifier sludge pumps, will be
directed to the ABR for wasting. The sizing parameters used for the secondary clarifier
are outlined in Table 5-8.

Table 5-8: Design Configuration Summary – Secondary Clarifier


Parameter Unit Value Comment
Number of clarifier units m/h 1
Diameter m 28
Maximum flow L/s 460 Equal to maximum
BTF capacity
Average upflow rate m/h 1.40 At ADWF
Maximum upflow at peak
m/h 2.71
flow
HRT at ADWF hours 2.69

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 27
Status: FINAL
Minimum HRT at peak flow hours 1.38
Side wall depth m 3.5
Solids removal
This sludge will be
Daily estimated clarifier kg dry sludge
2103 sent to the feed of
sludge production /day
the ABR
Approximation.
Solids stream to
Sludge concentration % dry solids 0.5
be transferred to
ABR.
24 x 30 minute
Sludge wasting events - wasting events
per day

The secondary clarifier will occupy the site directly to the south of the BTF.

5.7 DISINFECTION

5.7.1 PERFORMANCE REQUIREMENTS

The effluent quality requirements of the WWTP, presented in this report, define an
E.Coli limit of 2,500 cfu/100mL in the river discharge. Disinfection is predicted to be
required in order to meet this objective. The performance requirements of the
selected disinfection process are defined in Table 5-9.

Table 5-9: Performance Requirements – Disinfection


Parameter Units Value Remarks
Design average flow MLD 20 Average plant flow
Peak dry weather flow L/s 600 Represents peak diurnal flow
anticipated during an average
dry weather day at the design
WWTP capacity.
Estimated CCT inlet 6 Assuming 1 log reduction via
cfu/100ml 10
E. Coli concentration upstream processes
Plant effluent E. Coli
cfu/100ml 2,500 Outlined in Section 3.5
concentration limit
Required log log
3
reduction cfu/100ml

5.7.2 PROCESS DEVELOPMENT

Chlorine oxidation has been selected as the design basis for disinfection at the WWTP,
where chlorine is used to oxidise bacterial populations. The design is based on a Ct

W268.01 City Sewerage DED


28 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

approach, which specifies a minimum value for the product of the oxidant species
concentration and the contact time in the disinfection process, summarised as follows:

𝐶𝐶𝐶𝐶𝐶𝐶 𝑣𝑣𝑣𝑣𝑣𝑣𝑣𝑣𝑣𝑣𝑣𝑣 (𝑚𝑚3 ) 𝑚𝑚𝑚𝑚


𝐶𝐶𝐶𝐶 = 3 × 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 × 𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 � �
𝑚𝑚 𝐿𝐿
𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 � �
ℎ𝑟𝑟

Two methods of chlorine disinfection were considered using various forms of chlorine
as the disinfecting oxidant; breakpoint chlorination using free chlorine and
monochloramine. Free chlorine and monochloramine are similar chemicals which can
both be used as the oxidant in chlorine disinfection. Free chlorine, however; is a much
stronger oxidant and therefore to achieve a similar bacterial reduction has a lower
required Ct when compared to monochloramine.

In order to complete breakpoint chlorination, chlorine must be dosed firstly to exceed


the chlorine demand of constituents in the flow; including organic species demand and
ammonia demand, which react with free chlorine making it unavailable for
disinfection. Once the chlorine demand is met (the breakpoint), additional chlorine
must be dosed to provide a free chlorine residual, giving the required Ct value.

Chloramines, which can be in the form of monochloramine, dichloramine or


trichloramine, form when hypochlorite is added to water containing ammonia.
Chlorine attaches to the ammonia to form monochloramine. As more chlorine is added
to the water, the concentration of monochloramine increases while free ammonia
decreases.

Monochloramine is a less effective oxidant than free chlorine, and as such a higher Ct
value will be required to achieve the same level of bacterial reduction. However,
where a significant concentration of ammonia is present, the mass of chlorine required
to achieve breakpoint chlorination may be far greater than that required to achieve the
required monochloramine concentration. This means monochloramine is the most
chemically effective option.

The current design of the WWTP does not provide ammonia removal meaning that the
liquid flow into the chlorine contact channel will contain a portion of ammonia. Hence,
monochloramine has been identified as the most appropriate oxidant for disinfection
in this case.

The chlorination will be provided via dosing of sodium hypochlorite which has been
seen as a robust process in a range of chlorination facilities worldwide. Sodium
hypochlorite may be stored as a liquid phase chemical in bulk storage.

The disinfection process has been designed to treat all flows which are treated by the
WWTP.

5.7.3 DESIGN DESCRIPTION

The chlorination will be provided in the form of a chlorine contact tank (CCT).

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 29
Status: FINAL
Flow will enter the CCT into an inlet channel, where the flow will be slowed by an
energy dissipation structure. Sodium hypochlorite will be dosed into the CCT to achieve
the required concentration of residual monochloramine in the wastewater stream and
provide the required Ct value to achieve the treated wastewater quality, as outlined in
Table 5-10.

Sodium hypochlorite will be dosed by means of two disinfection dosing pumps,


operating in a duty/standby configuration. The dosing pumps will dose neat chemical
into a line of carrier water, which will dilute the chemical flow. The diluted chemical
will then be transferred to the chemical inlet location at the receiving chamber of the
CCT.

Following dosing, the flow will overtop a weir into the contact tank prior to passing an
underflow baffle. The baffles in the inlet structure are aimed minimising the risk of
poor mixing in the CCT.

Flow in the CCT will traverse a serpentine channel of approximately 120m in length. At
the tank outlet, the flow will pass an underflow baffle prior to overtopping an outlet
weir to an outlet compartment. Flow will discharge from the outlet compartment to
the Musi River.

Relevant design parameters of the CCT are outlined in Table 5-10.

Suspended solids in the effluent may impact on the performance of the disinfection
process. There is a risk associated with suspended solids that the chlorine dose
required to maintain adequate disinfection may increase.

The sodium hypochlorite storage tanks have been sized to allow for a total of 14 days
of onsite storage where the plant is operating under full design loads. This storage time
will be longer in early years of operation where the flows through the plant are lower.
The 14 day storage requirement is based on the supply of sodium hypochlorite being
readily available to replenish the plant supply within a number of days.

Table 5-10: Design Configuration Summary – Disinfection


Parameter Unit Value
Required E.Coli log count reduction Log 3
cfu/100ml
Disinfecting oxidant Monochloramine
Chlorine contact tank retention time At ADWF min 36
At minimum
min 56
Flow
At PDWF min 14
Design minimum Ct value mg.min/L 75

W268.01 City Sewerage DED


30 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

3
Chlorine contact tank volume m 580
Minimum required chloramine At ADWF mg/L 4.2
concentration
At inimum mg/L 2.7
Flow
At PDWF mg/L 10.8
Chlorine contact tank configuration Serpentine Tank
Number of serpentine passes no. 4
Sodium hypochlorite recommended mg/L 12.5
solution strength
Sodium hypochlorite dosing pump flow Minimum l/hr 83
required
Maximum l/hr 436

3
Expected fortnightly chemical usage m 45.4
Number of dosing pumps no. 2
Dosing pump configuration Duty/standby
Average carrier water flow L/hr 1220

5.8 SOLIDS HANDLING

5.8.1 PERFORMANCE REQUIREMENTS

The anaerobic treatment process will generate solids described as anaerobic sludge.
Removal of a portion of the stabilised sludge from the anaerobic baffled reactor is
required to prevent solids overloading which will reduce hydraulic retention time and
compromise the ABR performance. The sludge will settle in each of the three upflow
cells of each ABR. The settling process provides some concentrating of solids up to 2 to
5% dry solids; however, further sludge drying will be required.

The BTF will also accrue solids which will be partially captured in the secondary clarifier
process. Solids from the secondary clarifier are expected to be captured at relatively
low total solids concentration of approximately 0.5 wt% dry solids. The secondary
clarifier solids shall be returned to the ABR and subsequently removed to the sludge
drying beds with the ABR solids.

Sludge will be dried by means of sludge drying beds which will reduce the volume of
sludge and increase the dry solids concentration generating a solids product suitable
for disposal. The solids are expected to be dried to a solids content allowing the sludge
to be spadeable (approximately 15% solids by weight). Site specific data will be
required to determine an accurate estimate of the expected sludge drying
concentration, taking into account climatic conditions.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 31
Status: FINAL
After drying, the biosolids may be either disposed of at a local landfill or be beneficially
reused for landscaping or as a soil conditioner to improve and maintain productive
soils and to stimulate plant growth. At this stage of design, it is assumed sludge will be
disposed of via landfill. However, the current design will combine a high solids
stabilisation time in the ABR with solar drying. Hence, no design change is required to
the treatment plant process to facilitate biosolids reuse allowing a solids management
strategy to be developed once the plant is operational and a consistent solids
production is realised.

The performance requirements for the sludge handling system are outlined in
Table 5-11.

Table 5-11: Performance Requirements – Solids Handling


Parameter Units Value Remarks
ABR Sludge
Daily estimated ABR This estimate
sludge production kg dry sludge includes sludge
4165
/day produced in the
clarifier operation.
Sludge concentration % dry solids 2-5
Sludge wasting - 6 x 8hr events per
events fortnight
Sludge Drying
Expected dried sludge
% dry solids 15-40
concentration
Drying time days 14

5.8.2 PROCESS DEVELOPMENT

The major design parameter of the sludge drying beds is the area required, which is
dictated by the mass of solids produced by the WWTP. The majority of biological
removal at the WWTP is achieved via anaerobic treatment, which provides a
comparatively low production of solids, when compared with aerobic treatment.

The sludge drying beds will be equipped with a sand/gravel underdrain and decanting
gate for the removal of supernatant. This supernatant will be captured and transferred
to the site waste pump station and subsequently be returned to the inlet of the
anaerobic baffled reactors. The beds can be retrofitted with a lightweight roof
structure to prevent rain falling on the beds and re-wetting the dried sludge once
sludge production has neared the design conditions.

W268.01 City Sewerage DED


32 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

5.8.3 DESIGN DESCRIPTION

Sludge will be drawn from each ABR cell by operating the relevant sludge removal
pump. Stabilised sludge will be transferred to the sludge drying beds for solar drying
and storage prior to disposal to landfill.

Key sludge handling design specifications are summarised in Table 5-12. The design is
based on the use of sludge drying beds when the WWTP is operating at design
capacity, as specified in Section 3.1.

Table 5-12: Process Unit Performance Requirements – Solids Handling


Parameter Units Value Remarks
drying beds with
Dewatering, type under-drainage and
decanting
Percent dry solids to
% 3
dewatering for design
Sludge drying period days 14
Assuming sludge is
3 removed at 3 wt%
m /day 139
dry solids and
specific gravity of 1.
Sludge bed depth at
m 0.3
time of application
Minimum required
Ha 0.65
sludge bed area
Number of drying 4 beds per cell per
no. 24
beds event
3
Volume per bed m 81

Sludge wasting will be performed manually by the plant. Operator observations will be
required to ensure sludge is removed only when there is sufficient concentration of dry
solids in the base of ABR cell.

The distribution of sludge onto the drying beds will be performed using a distribution
manifold utilising manually operated valves located at each drying bed. The operator
will open the required valve to direct sludge to a specific drying bed. The design intent
is for several drying beds to be filled per desludging event then isolated for the set
drying time.

Sludge will then be removed from the drying beds and sent for disposal following the
minimum drying time, currently anticipated to be 14 days. The length of time required
for drying shall be confirmed during the initial years of the WWTP operation. The solids
concentration of the dried sludge, after various drying times may be determined by
total solids test performed in the site laboratory by drying a sample of sludge taken

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 33
Status: FINAL
from the drying bed. The sludge will be manually removed from each drying bed by
means of front-end loading tractor or equivalent and be removed from site by truck
movements.

5.9 ODOUR TREATMENT

5.9.1 PERFORMANCE REQUIREMENTS

The odour control and gas capture requirements of the WWTP are specified in Section
3.6. In order to achieve the gas capture requirements a series of odour control system
performance requirements have been estimated, as outlined in the Basis of Design and
summarised in Table 5-13.

Table 5-13: Process Unit Performance Requirements – Odour Control


Parameter Units Value Remarks
Odour Control
Ventilation and cover
systems to be
Minimum gas cover
% 95 designed to achieve -
capture efficiency
25 Pa under the
covers

10 Minimum 2 m above
Minimum vent stack
m tallest point of OCU
height (nominal) unit
Through discharge
Minimum discharge
m/s 15 cone; <9 m/s through
velocity
vent stack body
Media replacement
Odour treatment unit
Months 24 required every 24
design service life
months
Contaminant removal
efficiency
- Hydrogen sulphide >95 Based on typical
- Mercaptan >70 values achievable by
%
biological treatment
- Dimethyl sulphide >70 systems
- Ammonia >10
- VOC >30
Based on typical
Vent stack outlet odour values achievable by
ou <2,500
concentration biological treatment
systems

5.9.2 PROCESS DEVELOPMENT

Allowance has been made in the process design for the capture, removal and
treatment of foul air from the following process units:

W268.01 City Sewerage DED


34 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

Gases to odour treatment unit


• Inlet Works (inlet channels, mechanical screens, grit removal chamber)
• ABR Effluent Diversion Box
• BTF Feed Pump Station
• Biological Trickling Filter unit

Gases to flare and discharge


• Anaerobic Baffled Reactor (tanks, effluent channels)

Gas containment covers will be installed over the process units listed above to capture
gases released from the wastewater. Ventilation fans will be used to extract the
captured gases from under the covers and transfer the volume to an odour treatment
system or directly to a vent stack for discharge to the atmosphere.

A single odour treatment system will be provided to extract and treat gases captured
from the Inlet Works, ABR Effluent Diversion Box, BTF Feed Pump Station and the BTF
unit. The proposed odour treatment technology will be a biological Air Trickling Filter
(ATF) unit which provides up to 95% removal of odorous contaminants. Captured gases
will be extracted from the covered process units via fixed-speed duty/standby fans and
the treated air discharged via an elevated vent stacks to promote dispersion.

Under the current design intent, no treatment shall be provided for gases captured in
the ABR tanks and effluent channel. The ABR gases will be flared to remove flammable
components (predominantly methane) and discharged directly via an elevated vent
stack to promote dispersion.

5.9.3 DESIGN DESCRIPTION

The following cover types and materials are proposed for the covered process units:
• Inlet Works – flat, trafficable, chequered-plate aluminium or GRP covers
• ABR Tanks – arc-span GRP cover or similar
• ABR Effluent Diversion Box – GRP/concrete roof with aluminium hatches
• BTF Feed Pump Station – concrete roof with aluminium hatches
• BTF unit – arc-span/domed GRP covers or similar

Access hatches or removable cover sections will be provided on the covers to allow for
inspection and operator access under the cover, where required. The location and size
of access hatches are identified on the corresponding General Arrangement drawings.

All covered process units will be provided with corrosion-resistant lining to minimise
the impact of sulphuric acid corrosion from hydrogen sulphide (H2S) presence in the
headspace. A Hazardous Area Classification exercise has been completed for all
covered spaces. All electrical and mechanical equipment located under the covers will
need to be suitably rated and constructed of corrosion resistant materials, as per the
outcomes of the Hazardous Area Classification.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 35
Status: FINAL
Air inlet and extraction points will be located such that fresh air will enter the covers
and sweep across the covered headspace to prevent ventilation dead-zones. Flow
control dampers will be provided on each extraction point to allow for flow balancing.
For the BTF unit, distribution air will be drawn through the roof via air inlets and
extracted from an air plenum section at the bottom of the tower via four extraction
points. The location and number of air inlet and extraction points are identified on the
corresponding General Arrangement and P&ID drawings.

A set of duty/standby ventilation fans will operate continuously at a fixed speed to


extract gases from the headspace of the covered process units via field ductwork. The
ventilation fans shall be direct drive type fans constructed from GRP for corrosion
resistance. The ventilation fans will maintain a negative pressure under the covers of at
least -25 Pa to prevent gases from escaping through gaps in the covers.

The ATF unit will be based on a multi-stage, once-through biological media filter
technology. The ATF unit will be a column containing wetted media beds with
immobilised bacteria population. Pollutants in the extracted air come into contact with
the liquid layer on the media surface and are degraded by autotrophic and/or
heterotrophic bacteria. The ATF column will contain separate autotrophic bed(s) for
hydrogen sulphide removal and heterotrophic bed(s) for organic compound removal.
The ATF will be sized based on a minimum 12 seconds empty bed contact time (EBCT)
and target removal efficiencies The ATF will require a single-pass nutrient supply to
maintain its biological activity. This will be supplied via the secondary clarifier effluent
or potable water service. The liquid purged from the ATF column will be acidic (pH 1-2)
and shall be drained to the site waste pump station and subsequently returned to the
head of works.

The vent stacks will be designed to be nominally 13 m tall (minimum 10 m or 2 m


above the tallest point of the ATF tower, whichever is higher). The vent stack will be
fitted with a discharge cone to increase discharge velocity to >15 m/s and promote gas
dispersion. The vent stacks will also be fitted with anti-vermin mesh.

The specific key design parameters for the odour treatment systems are specified in
Table 5-14.

Table 5-14: Design Summary – Odour Control


Parameter Units Value Remarks
Odour Control
Treatment technology Biotrickling Filter
Facilitated by a set of
Fixed speed,
Operating mode - duty/standby ventilation
continuous
fans

W268.01 City Sewerage DED


36 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

Parameter Units Value Remarks


• Differential
pressure gauge on
ATF media beds
Installed instruments - • Fan discharge low
flow switch
• Fan failure alarm to
control room
Based on 15 ACPH for
Inlet Works, 6 ACPH for
ABR Effluent Diversion
Ventilation flow rate m3/hour 13,700 Box and BTF Feed Pump
Station, and 7,560 m3/hr
distribution air flow for
BTF
100 (average)
Inlet H2S concentration ppm
5801 (peak)

Inlet DMS 13 (average)


ppm
concentration 261 (peak)
Estimated based on
Inlet Mercaptans 0.7 (average) historical sampling data
ppm
concentration 1.31 (peak) for similar sites and
processes
Inlet Ammonia 0.7 (average)
ppm
concentration 1.51 (peak)

Inlet VOC 11 (average)


ppm
concentration 431 (peak)
Air temperature °C 20 to 46
Air relative humidity % 75 to 100
Empty bed contact time seconds >12
Nutrient water To be confirmed by
L/hour 1,500
requirement Vendor design
To be confirmed by
Number of ATF tower Number 1
Vendor design
ATF column diameter m 4.5 Based on preliminary
column sizing; to be
ATF column height m 11.0 confirmed by Vendor
design
Preliminary power
Ventilation fan power
kW 10 requirement for individual
rating
fan

1. The peak H2S concentrations are expected to be observed intermittently in the early operating years, where
sewage residence times may be in excess of 50 hours. The actual gas-phase H 2S concentration will be dependent
on, amongst other things, the nature and extent of turbulence and the ventilation rate at the point where
wastewater contacts air. At this point, there is a percentage of equilibrium value which indicates the percentage
of the maximum equilibrium concentration of hydrogen sulphide which actually enters the gas phase. The
percentage equilibriums assumed for this project are between 13% (quiescent surface) and 50% (inlet works,
turbulent pump station).

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 37
Status: FINAL
5.10 BIOGAS HANDLING

5.10.1 PERFORMANCE REQUIREMENTS

The anaerobic treatment process within the ABR emits a biogas consisting of methane
and a number of odorous chemicals such as hydrogen sulphide and amines. Due to this
emission, anaerobic process units are often covered and the gas managed for safety
and health concerns. When they are not covered, anaerobic process units are designed
to facilitate the generation of a scum layer or crust.

The methane within the biogas is highly flammable and, if contained, must be
managed appropriately for safe operation of the WWTP. The flammable biogas can be
used to generate power or create a hot water supply; however, these facilities are
complex and expensive and require significant operation and maintenance inputs and
experience. In the future, once the plant is operational, gas quality and production can
be monitored to assess the viability and design criteria for an energy recovery system.

In lieu of use of the biogas, it will need to be disposed of by either venting to the
atmosphere or by discharging through a flare. Venting provides a simple, low
maintenance option, but provides no treatment of the odours other than through
dilution and no reduction in the emitted greenhouse gasses. Flaring increases the
quantity of mechanical equipment requiring maintenance on-site, but reduces odours
and the emission of methane gas which is a key greenhouse gas.

In all cases, the design of the ABR and biogas piping must meet standards that
determine the hazardous classification of the headspace, the areas outside of the
covers, and of the biogas piping route and fixtures. This classification directly impacts
the electrical protection requirements of all power and control elements within the
area.

5.10.2 PROCESS DEVELOPMENT

A high level qualitative assessment was conducted of the three options for biogas
handling: crust layer, venting and flaring. The relative advantages and disadvantages of
these options are presented below:
• Natural crust layer:
o Advantages:
 Lowest capital and O&M costs
 No biogas handling skills/health & safety procedures required
o Disadvantages:
 No control over emissions
 Not suitable for retrofit for power generation facility
• Venting:
o Advantages:
 Low O&M costs
 Suitable for retrofit for power generation facility
 Covered tanks minimise visual impact of plant

W268.01 City Sewerage DED


38 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

o Disadvantages:
 High capital
 Biogas handling skills/ health & safety procedures required
 No treatment of odorous emissions
• Flaring:
o Advantages:
 Treatment of odorous and greenhouse gasses
 Suitable for retrofit for power generation facility
 Covered tanks minimise visual impact of plant
o Disadvantages:
 Highest capital and O&M costs
 Biogas handling skills/health & safety procedures required

The design has proceeded on the basis of flaring the biogas for odour and greenhouse
gas emission control. Covering the reactors will result in concentration of the
flammable biogas and will require the operations staff to become familiar with
operation of the reactor and the associated health and safety procedures.

The primary risk associated with the combustible biogas is the possibility of explosions.
Explosions, like fire, require three elements: fuel, oxygen, and an ignition source.
Combustible biogas will ignite only within a specific range of fuel/oxygen mixtures. Too
little or too much biogas will not ignite. These conditions are defined as the Lower
Explosive Limit (LEL) and the Upper Explosive Limit (UEL). Any amount of gas between
the two limits is explosive. The LEL and UEL gas concentrations are defined by a
percent of total volume, with the balance as normal air. The predominant combustible
gas within the biogas mixture is methane which has an LEL of 5.0% and UEL of 15.0%.

During normal operation, the airspace within the covered ABR will contain no fresh air
and the biogas will be safely above the UEL. Maintenance operations which will require
access within the ABR will require a safety operation to displace the methane rich
biogas with a neutral gas such as nitrogen.

The performance requirements for the biogas handling system are outlined in
Table 5-15.

Table 5-15: Process Unit Performance Requirements – Biogas Handling


Parameter Units Value Remarks
At design capacity,
assuming 700 mg/L COD
Estimated average
3 in influent, 70% COD
daily methane m /d 3,500
removal in ABR and a
production
methane yield of
0.40 m3/kg COD
Estimated biogas
% CH4 55
quality
Working pressure
kPa 3.0
under cover

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 39
Status: FINAL
Parameter Units Value Remarks
Emergency relief Setting for emergency relief
kPa 3.3
pressure fittings on ABR cover
Methane Lower
% 5 percent of total volume,
Explosive Limit (LEL)
with the balance as normal
Methane Upper air
% 15
Explosive Limit (UEL)
Maximum gas piping
m/s 3.5 to minimise losses
velocity
Clear zone around min distance between flare
m 15
flare and the nearest structure

5.10.3 DESIGN DESCRIPTION

Biogas will be extracted from one point from each of the six ABR cells. Each extraction
point will be equipped with an isolation valve, sampling/purge point, condensate trap,
and flame arrestor. The extraction lines will feed into a common header for each tank.
Each header will be equipped with an isolation valve before the headers are joined to
enable a single tank to be taken out of service.

An emergency pressure/vacuum relief with flame arrestor will be fitted on the cover of
two of the three cells to protect the system against overpressure. The gas headspace is
common across all three cells. A pressure gauge and transmitter will be fitted on each
tank for monitoring and alarming of system pressure.

The above grade biogas piping will be constructed of 316 stainless steel for impact and
corrosion resistance. The ductwork will be sloped to allow condensation from the
moist biogas to drain either back to the ABR or to a low point with drain on the
common duct to the flare.

The below grade ductwork will be HDPE.

The design summary for the biogas handling system is outlined in Table 5-16.

Table 5-16: Design Summary – Biogas Handling


Parameter Units Value Remarks
ABR Covers
Designed for
Leak-tight domed
Cover type - overpressure and
GRP cover
vacuum conditions
Biogas Piping
Extraction points per
no. 1
cell

W268.01 City Sewerage DED


40 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 5: Process Design and Unit Process
Chapter 7: Site Development
Development

Parameter Units Value Remarks


Pipe material – above for corrosion and
- stainless steel
grade impact resistance
Duct material – below
- HDPE
grade
Flare
Open flame
Flare type -
candlestick style
Number of flares no. 1
Flare sizing nm3/d TBC

5.11 SITE WASTE WATER PUMP STATION

A site waste system has been included in the Sei Selayur WWTP to transfer waste flows
to the head of the works. The waste system will essentially comprise of a pump station
with two submersible pumps operating in a duty/standby configuration.

The site waste water pump station will operate two major functions; to collect waste
from various sources throughout the WWTP and received septage and transfer the
flow to the inlet works.

Site waste flows will be collected from the following areas:


• Supernatant from grit classifier washpress (Screening clarifier wastewater to
be returned directly to the inlet works)
• Drainage liquor from sludge drying beds
• Raw wastewater from site amenities building
• Drainage from site bunds

The waste pump station will include two submersible waste transfer pumps operating
in a duty/standby configuration.

The waste pump station wet well will include an emergency overflow to an adjacent
storm drain.

5.12 PLANT MAINTENANCE CONSIDERATIONS

Key plant maintenance considerations include:


• ABR cell cleanout
• Equipment item maintenance across site

Further key maintenance considerations will be added during the completion of


detailed design.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 41
Status: FINAL
5.13 WWTP EXPANSION

The WWTP has been designed to accommodate necessary treatment operations within
the limited site area available. Expansion of the WWTP has not been considered at this
stage of design. As per the Master Plan documentation, expansion to a higher capacity
ultimate configuration will require additional land availability.

W268.01 City Sewerage DED


42 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 6: Environmental, Social & Permit
Chapter 7: Site Development
Requirements

Chapter 6: Environmental, Social & Permit Requirements


6.1 ENVIRONMENT

The initial environmental examination (IEE) conducted for the ADB confirmed the
project is not a new incursion to an ecologically untouched area.

An environmental impact assessment (EIA) will be conducted concurrently with the


detail design by another consultant appointed by IndII. Regular liaison will be
undertaken with the EIA consultant to identify any potential adverse environmental
impacts resulting from the design.

No requirements for the DED design have been identified from the EIA at the time of
issue of this report.

6.2 PERMITTING

The statutory and regulatory requirements relevant to this project as identified by the
IEE conducted for the ADB include:
• environmental permit and AMDAL report prior to any bidding or procurement
process
• discharge permit in the initial months of WWTP operation

Further details on permitting requirements shall be provided by the environmental


consultant.

6.3 SOCIAL – INVOLUNTARY RESETTLEMENT

Development and implementation of the Land Acquisition and Resettlement Plan


(LARP) will be by others.

There are informal settlements within the nominated site boundary. An allowance of
2400m2 (0.24 Ha) (100m2 per person for 15 people and 300m2 per business for 3
businesses) within the northwest corner of the site has been requested by the AMDAL
consultant at the meeting with BAPPEDA in Palembang 05 February 2014 for relocation
of displaced persons. Design of any development within this allowance will be by
others.

A timber mill adjacent to the WWTP site includes kilns constructed within the
nominated site boundary. The area is estimated to encompass 0.4 Ha. During a
subsequent meeting with IndII it was confirmed that this area can be used for the
WWTP facilities and all existing structures within the WWTP site boundary shall be
demolished as part of the construction works.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 43
Status: FINAL
Chapter 7: Site Development
7.1 SITE LOCATION AND DESCRIPTION

The wastewater treatment plant will be located on a 5.95 Ha site located along the
Musi River in the Kelurahan of Sei Selayur. The site is bordered by the PT Pupuk
Sriwijaya (Pusri) fertiliser plant to the west along Jalan Dr. Sutami, a police station and
informal settlements along the north and east, a timber mill along the south west and
the Musi River along the south.

As noted in Section 6.3 - Social – Involuntary Resettlement the following area on the
site were reserved due to resettlement concerns:
• approximately 0.24 Ha within the northwest corner relocation of persons
displaced on site

7.2 SURVEY BENCHMARK AND DATUM

The survey was conducted on the Geographic Coordinate System WGS-84. Further
details to be provided in final survey documentation.

7.3 FLOOD AND TIDAL RIVER LEVELS

No official flood or tidal river level information has been provided for the WWTP site.
Unofficial and anecdotal information has therefore been used to provide a basis for the
design.

Two sources were found which state the anticipated flood level of the Musi River
adjacent to the WWTP is around 3.7-3.75m MSL (sources Desktop Study Report for
Geotechnical and Hydrogeological Investigations, Golder Associates, Feb 2014 and
Strategy of Drainage and Flood Control in Palembang City, Eddy Santana Putra, F.X.
Suryadi, Kira Tarigan, Akhmad Bastari and Marlina Sylvia). The frequency for this flood
event is not available; therefore, a conservative approach has been adopted and the
WWTP has been designed to avoid inundation and submergence of process units at the
“flood” level.

The site survey has indicated the WWTP site is generally flat ranging around 2.0 –
2.5 mEL. Site grading will require 1.5 – 3.5m fill to accommodate gravity flow through
WWTP and to bring plant above “flood” level. This may be a significant cost. The
geotechnical investigation must be finalised before the impact can be confirmed.

If the frequency of the “flood” event is know it may be practical to lower the site and
accept occasional inundation.

The report Strategy of Drainage and Flood Control in Palembang City, Eddy Santana
Putra, F.X. Suryadi, Kira Tarigan, Akhmad Bastari and Marlina Sylvia has further data
on tidal levels in the Musi River including:

W268.01 City Sewerage DED


44 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 7: Site Development

• Wet season:
o highest water level: +3.7 m MSL
o average high tide: +2.0 m MSL
o lowest water level: +1.8 m MSL
• Dry season:
o highest water level: +1.2 m MSL
o average water level: +0.0 m MSL
o lowest water level: ‐1.2 m MSL

7.4 GEOTECHNICAL INVESTIGATIONS

Geotechnical report is included as Annex F.

7.5 INCOMING FLOWS

The influent pressure main will enter the site from the southern end of the western
boundary along Jalan Dr. Sutami. Further information on the incoming sewer collection
system can be found in the collection and transfer design report.

7.6 EFFLUENT DISCHARGE

WWTP effluent will be discharged to the adjacent Musi River along the southern
border of the site. The discharge is approximately 2km downstream of the nearest
water treatment plant intake. Broad-order numerical modelling was conducted to
confirm effluent will be sufficiently dispersed from the selected discharge location. The
modelling report is included in Annex 8.

The modelling indicated the discharge will be well dispersed. No diffusers will be
required on the discharge pipework which will terminate at a simple headwall which
will be fitted with a non-return valve.

7.7 SITE ACCESS AND SECURITY

The primary site entrance for the WWTP will be provided on the far west edge of the
site along Jalan Dr. Ir. Sutami.

The following vehicles will require access to the WWTP once operational:
• Septage tankers
• Chemical delivery truck
• Maintenance vehicles (crane, truck)
• Personnel vehicles

Temporary access will also be required during construction for construction vehicles
and equipment delivery. This access is anticipated to be provided from the future
primary site entrance and the unsealed road to the lumber mill along the southern
west boundary.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 45
Status: FINAL
The WWTP will be equipped with the following security provisions:
• a security wall will be provided around the perimeter of the WWTP;
• a guard station at the primary site entrance; and
• lockable doors on all buildings and enclosures.

7.8 FACILITY LAYOUT

The WWTP site is long and narrow (generally 80m – 100m wide) shaped like an “L”.
The main process units were laid out within the north-south portion of the site to allow
the process to be arranged in a linear fashion to minimise pipe lengths and to locate
the final process unit adjacent to the river.

The east-west branch of the site will be used primarily for sludge drying. The waste
pump station / septage receiving facility will be located near the primary entrance to
minimise the incursion on septage trucks into the site.

All facilities required for the final design capacity of the WWTP will be constructed in
the initial stage. Any future expansion of the WWTP capacity will require the purchase
of additional land.

7.9 ON-SITE AMENITIES

The extent of staff support facilities is a direct function of the number of people based
at the plant. The plant staffing requirements are estimated in Table 7-1.

Table 7-1: Key Estimated Operations Requirements


Parameter Value
9am – 5pm, 7 days per week
Operator shifts
(no regular evening coverage required)
Number of Operators 4 Operators, 2 shifts – total 8 Operators
on-site housing will be provided for operations and
Emergency coverage maintenance staff; therefore, emergency coverage will be
available 24/7
all Operators will be located at the WWTP thus no operation or
monitoring capabilities are required off-site
Remote operation central control room will be provided with monitoring (and
some minimal control) of major units and alarms only, all other
monitoring and control will be local to equipment

The following on-site amenities (and associated features) will be provided for the
WWTP:

Administration building & control room

W268.01 City Sewerage DED


46 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 7: Site Development

The administration building & control room will include the following features:
• 1 no. air conditioned office for head operator
• 1 no. general indoor office area with desks, chairs, space for paper files,
computers, and telephones for remaining operation staff
• 1 no. meeting room for up to 10 people
• 1 no. men’s water closet with lockers, toilet, sink and shower facilities
• 1 no. women’s water closet with lockers, toilet, sink and shower facilities
• 1 no. room with bench and sink for laboratory testing

Staff quarters

The staff quarters will include the following features:


• 1 no. prayer room
• 5 no. air conditioned 100m2 living quarters each including:
o 1 no. living room
o 1 no. kitchen
o 1 no. water closet with toilet, sink and shower
o 2 no. bedrooms

Guard station

Each guard station will include the following features:


• 1 no. 10m2 hut including:
o 1 no. water closet with toilet and sink

Workshop & storage

The workshop and storage building will include the following features:
• 1 no. general indoor office area with desk, chair, space for paper files,
computer and telephone
• 1 no. open plan workshop area
• 1 no. storage room
• 1 no. water closet with lockers, toilet, sink and shower facilities

Main switchroom

The main switchroom building will include the following features:


• 1 no. open plan switchroom including:
o Main switchboard
o Site controls panel
o Adjacent outdoor slab for temporary generator

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 47
Status: FINAL
These facilities (except the main switchroom and guard house) will be primarily located
in the northwest corner of the site so that they are located close to the primary site
entrance.

The guardhouse will be located at the primary site entrance.

The main switchroom will be located adjacent to the BTF and the pump stations to be
adjacent to the key electrical demands on the site.

These building requirements will be supplied to a separate designer for building layout
and design (including architectural requirements, power supply, potable water supply,
fire water supply, telecommunications and wastewater facilities).

7.10 SITE WATER MANAGEMENT

Site water will be discharged to the Musi River. Further site water management details
(including design flood levels and surface water discharge arrangements) will be
established in the next stage of detail design.

W268.01 City Sewerage DED


48 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 8: Utilities

Chapter 8: Utilities
External utility services that will be needed at the plant site include site / potable
water, telecommunications and electrical power.

8.1 SITE / POTABLE WATER

No recycled water facilities will be provided as part of the WWTP to supply water for
process equipment. Therefore, potable water will be required for all water demands
on site. A summary of the water demands at the site are presented in Table 8-1.

Table 8-1: Site and Potable Water Estimated Demands


Water Demand Flow Remarks
Requirements
Process Water
Screenings Washer/Compactor 50 L/m at 2 bar, general operation
4-8 times per day for a
duration of 5min
Grit chamber agitation water TBC to be confirmed with vendor
Chlorine Dosing Station 20 L/m initial estimate
General Site
Fire Hydrants TBC
Safety Shower / Eyewash Stations 1.5 L/s Australian Standard
AS4775(2007). Required at
below 5.5 bar (550 kPa)
Hose Stations 4 L/s (4x1 L/s) Design assumption of 4 hose
points operable
concurrently.
Personnel Use
Toilet and shower facilities 3.5 L/s
Staff Housing 925 L/d based on 185 L/p/day and 5
persons per household
TOTAL DEMAND 310 L/m at 2 bar

PDAM will supply site / potable water for the WWTP. Coordination with the local
authority will be the responsibility of the contractor.

The water supply will most likely come from Jalan Dr. Sutami along the west edge of
the site. A double check valve will be installed at the connection point to prevent
backflow into the main potable water line.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 49
Status: FINAL
The local authority will be consulted during the application process to confirm if there
are any additional requirements for the connection.

Additional storage and pumping facilities may be required on site if sufficient pressure
and / or flow cannot be supplied by the water supply network.

8.2 TELECOMMUNICATIONS

Coordination with the local authority will be the responsibility of the contractor. The
telecommunications connection will most likely come from Jalan Dr. Sutami along the
west edge of the site.

8.3 ELECTRICAL POWER

PLN will be the likely supplier of electricity for the WWTP. Coordination with the local
authority will be the responsibility of the contractor. The power connection will most
likely come from Jalan Dr. Sutami along the west edge of the site.

W268.01 City Sewerage DED


50 Palembang WWTP Final Detailed Design
Report Status: FINAL
9: Structural
Chapter 10: Electrical Design
Design Requirements
Requirements

Chapter 9: Structural Design Requirements


9.1 SEISMIC DESIGN

Palembang geotechnical parameters; Ss and S1 have been extracted from SNI


1726:2012 Figures 9 and 10. Site Classification is as per Geotechnical Report, Section
7.5.

Table 9-1: Summary of Palembang Site Seismic Design Parameters (Ref. Indonesian
National Standard SNI 1726:2012)
Parameter Value Description/Ref.
Site Classification E Soft Ground as per Draft Geotechnical
Report (Section 7.5)
I 1.25 Importance Factor
Ss 0.275 Mapped Maximum Considered Earthquake
(MCER), 5% damped, spectral response
acceleration parameter at short period
S1 0.175 Mapped Maximum Considered Earthquake
(MCER), 5% damped, spectral response
acceleration parameter at a period of 1 s
Ri 2 Response modification factor, impulsive
mass
Rc 1 Response modification factor, convective
mass
Fa 2.42 Short-period site coefficient
Fv 3.275 Long-period site coefficient (1 second)
SMS 0.666 The MCER, 5% damped, spectral response
acceleration parameter at short period
adjusted for site class effects
SM1 0.573 The MCER, 5% damped, spectral response
acceleration parameter at a period of 1 s
adjusted for site class effects
SDS 0.444 Design, 5% damped, spectral response
acceleration parameter at short period
adjusted for site class effects
SD1 0.382 Design, 5% damped, spectral response
acceleration parameter at a period of 1 s
adjusted for site class effects

Note:- For simplicity all the piled structures are given the same Importance Factor.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 51
Status: FINAL
Figure 9-1: Spectral Response Acceleration Sa (g) Vs Period (sec.)

9.2 FOUNDATION REQUIREMENTS

The flooding and geotechnical conditions are discussed in Sections 7.3 and 7.4
respectively.

It is anticipated, that most belowground pipelines plus utilities and services can be
installed without the need for special foundations whilst the following structures can
be supported on relatively shallow footings (in conjunction with compacted subgrade
and site grading):
• All buildings (presupposing these will be a single storey)
• Septage receival facility and site waste pump station
• Clarifier sludge pump station
• Sludge drying beds.

Due to the presence and depth of the underlying soft soils and the proximity to the
groundwater table, shallow footings are not suitable for major and/or settlement-
sensitive structures and pipelines due to the significant settlement that will occur
under the applied loads (even after a 12 month pre-loading period). These structures
and pipelines include the following:
• Inlet works
• Odour control facility (OCF) support slab
• Anaerobic baffled reactors (ABR)
• ABR effluent diversion box
• Biological trickling filter (BTF)
• BTF feed pump station
• Clarifier
• Disk filter (Makassar only)
• Chemical storage and dosing facility
• Chlorine contact tank (CCT)
• Connecting pipelines between ABR, BTF, clarifier, CCT and effluent outlet.

W268.01 City Sewerage DED


52 Palembang WWTP Final Detailed Design
Report Status: FINAL
9: Structural
Chapter 10: Electrical Design
Design Requirements
Requirements

Deep foundations comprising either driven precast concrete piles (such as Wika spun
piles) or driven open tubular steel pipe sections are required. It has been determined,
based on an assessment of these options, that there are uncertainties regarding the
suitability of driven concrete piles with regard to durability, high potential for excessive
driving stress during installation, and the adequacy of these piles to accommodate
lateral loads.

Accordingly, the DED has been prepared based on the use of driven open tubular steel
pipes acting as piled foundations for major and/or settlement-sensitive structures and
pipelines.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 53
Status: FINAL
Chapter 10: Electrical Design Requirements
10.1 ELECTRICAL POWER REQUIREMENTS

All equipment provided will be selected and designed for suitable operation and
connection to the station power supply as follows:
• Nominal voltage between phases – 380 V
• System highest phase voltage - 418 V (i.e. plus 10%)
• System lowest phase voltage - 357 V (i.e. minus 6%)
• Nominal voltage between phase & neutral - 220 V
• Number of phases - 3
• Fundamental Frequency - 50 Hz
• Control and instrumentation Voltage - 24VDC

Estimated load requirements are detailed below:

LOAD POWER DUTY LOAD MCC TYPE


EQUIPMENT VOLTAGE EFFICIENCY UTILISATION ESSENTIAL INSTALLED DEMAND OPERATIONAL DEMAND
DESCRIPTION RATING FACTOR FACTOR MODULE OF
NUMBER FACTOR LOAD
TYPE LOADS

V kW in dec. cos phi in dec. kW kVA A kW kVA A


SC-15-01 Screen No.1 Raking Drive 380 1.50 0.8 0.8 0.95 1 DOL Duty Y 1.88 2.34 3.56 1.78 2.23 3.38
SC-15-02 Screen No.2 Raking Drive 380 1.50 0.8 0.8 0.95 1 DOL Duty Y 1.88 2.34 3.56 1.78 2.23 3.38
CM-15-01 Screening Conveyor/Compactor 380 3.00 0.8 0.8 0.95 1 DOL Duty Y 3.75 4.69 7.12 3.56 4.45 6.77
MX-15-01 Vortex Grit Chamber Mixer 380 0.37 0.7 0.8 0.95 1 DOL Duty Y 0.53 0.66 1.00 0.50 0.63 0.95
PF-15-01 Grit Pump 380 4.00 0.8 0.8 0.95 1 DOL Duty Y 5.00 6.25 9.50 4.75 5.94 9.02
GC-15-01 Grit Classifier 380 0.37 0.7 0.8 0.95 1 DOL Duty Y 0.53 0.66 1.00 0.50 0.63 0.95
PF-21-01 ABR Recycle Pump No. 1 380 1.50 0.8 0.8 0.95 1 DOL Duty Y 1.88 2.34 3.56 1.78 2.23 3.38
PF-21-02 ABR Recycle Pump No. 2 380 1.50 0.8 0.8 0.95 1 DOL Duty Y 1.88 2.34 3.56 1.78 2.23 3.38
PF-25-01A ABR Sludge Pump - ABR Tank No. 1, Cell 1 380 7.50 0.9 0.8 0.95 1 DOL Duty Y 8.33 10.42 15.83 7.92 9.90 15.04
PF-25-01B ABR Sludge Pump - ABR Tank No. 1, Cell 2 380 7.50 0.9 0.8 0.95 1 DOL Duty Y 8.33 10.42 15.83 7.92 9.90 15.04
PF-25-01C ABR Sludge Pump - ABR Tank No. 1, Cell 3 380 7.50 0.9 0.8 0.95 1 DOL Duty Y 8.33 10.42 15.83 7.92 9.90 15.04
PF-25-02A ABR Sludge Pump - ABR Tank No. 2, Cell 1 380 7.50 0.9 0.8 0.95 1 DOL Duty Y 8.33 10.42 15.83 7.92 9.90 15.04
PF-25-02B ABR Sludge Pump - ABR Tank No. 2, Cell 2 380 7.50 0.9 0.8 0.95 1 DOL Duty Y 8.33 10.42 15.83 7.92 9.90 15.04
PF-25-02C ABR Sludge Pump - ABR Tank No. 2, Cell 3 380 7.50 0.9 0.8 0.95 1 DOL Duty Y 8.33 10.42 15.83 7.92 9.90 15.04
PF-30-01 BTF Feed Pump No.1 380 45.00 0.9 0.8 0.95 1 SS Duty Y 50.00 62.50 94.96 47.50 59.38 90.21
PF-30-02 BTF Feed Pump No.2 380 45.00 0.9 0.8 0.95 0 SS Standby Y 0.00 0.00 0.00 0.00 0.00 0.00
PF-30-03 BTF Feed Pump No.3 380 45.00 0.9 0.8 0.95 1 SS Duty Y 50.00 62.50 94.96 47.50 59.38 90.21
ME-35-01 Trickling Filter Distributor Arm Motor 380 2.20 0.8 0.8 0.95 1 VSD Duty Y 2.75 3.44 5.22 2.61 3.27 4.96
ME-40-01 Clarifier Scrapper Motor 380 0.75 0.7 0.8 0.95 1 DOL Duty Y 1.07 1.34 2.03 1.02 1.27 1.93
PF-45-01 Clarifier Sludge Pump 1 380 5.50 0.9 0.8 0.95 1 DOL Duty Y 6.11 7.64 11.61 5.81 7.26 11.03
PF-45-02 Clarifier Sludge Pump 2 380 5.50 0.9 0.8 0.95 0 DOL Standby Y 0.00 0.00 0.00 0.00 0.00 0.00
PVM-60-01 Chlorine Dosing Pump 1 380 0.75 0.7 0.8 0.95 1 DOL Duty Y 1.07 1.34 2.03 1.02 1.27 1.93
PVM-60-02 Chlorine Dosing Pump 2 380 0.75 0.7 0.8 0.95 0 DOL Standby Y 0.00 0.00 0.00 0.00 0.00 0.00
FN-80-01 Odour Control Facility Foul Air Fan No. 1 380 11.00 0.9 0.8 0.95 1 DOL Duty Y 12.22 15.28 23.21 11.61 14.51 22.05
FN-80-02 Odour Control Facility Foul Air Fan No. 2 380 11.00 0.9 0.8 0.95 0 DOL Standby Y 0.00 0.00 0.00 0.00 0.00 0.00
ME-89-01 Biogas Flare 220 1.00 1 0.8 1.00 0.9 Feeder Duty Y 1.00 1.25 5.68 0.90 1.13 5.11
PF-80-01 Odour Control Facility - Feed Water Pump 380 0.75 0.7 0.8 0.95 1 DOL Duty Y 1.07 1.34 2.03 1.02 1.27 1.93
PF-90-01 Waste Return Pump No. 1 380 7.50 0.9 0.8 0.95 1 DOL Duty Y 8.33 10.42 15.83 7.92 9.90 15.04
PF-90-02 Waste Return Pump No. 2 380 7.50 0.9 0.8 0.95 0 DOL Standby Y 0.00 0.00 0.00 0.00 0.00 0.00
UPSDB-01 UPS Distribution Board Administration Building 220 4.00 1 0.8 1.00 0.9 Feeder Duty Y 4.00 5.00 22.73 3.60 4.50 20.45
DB-01 Lighting and Small Power Distribution Board Switchroom Building 380 5.00 1 0.8 1.00 0.5 Feeder Duty Y 5.00 6.25 9.50 2.50 3.13 4.75
DB-02 Lighting and Small Power Distribution Board Administation Building 380 10.00 1 0.8 1.00 0.5 Feeder Duty Y 10.00 12.50 18.99 5.00 6.25 9.50
DB-03 Lighting and Small Power Distribution Board Staff Housing 380 10.00 1 0.8 1.00 0.5 Feeder Duty Y 10.00 12.50 18.99 5.00 6.25 9.50
DB-04 Lighting and Small Power Distribution Board Workshop 380 10.00 1 0.8 1.00 0.5 Feeder Duty Y 10.00 12.50 18.99 5.00 6.25 9.50

TOTAL 239.9 299.9 474.6 211.9 264.9 419.5

W268.01 City Sewerage DED


54 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 10: Electrical Design Requirements

PF kVAR Bank
kW kVA Amp WITH NO Target PF
CORRECTION Required

Station Total Installed Demand 240 300 475 0.80 0.93 65.66

Station Total Operational Demand (Nominal) 212 265 420 0.80 0.93 58.00

10.2 STANDBY POWER PROVISIONS

Wastewater flows through the main portion of the WWTP and effluent discharges by
gravity. A power failure will have the following impact on the process:
• Inlet works: minimal impact on flow, manual screen cleaning required,
reduced grit removal efficiency
• Anaerobic baffled reactors: no impact on the treatment capability of the
anaerobic treatment process, sludge removal not available
• Biological trickling filter: filter off line
• Clarifier: no impact on flow through the clarifier, sludge removal not available
• Chlorine contact tank: no impact on flow through tank, no disinfection
• Effluent disposal: no impact on flow

A temporary portable standby generator can be located adjacent to the switchroom


and should be sized to accommodate the estimated minimum permanent electrical
load for the entire treatment plant of 300 kW (375 kVA). The MCC is provided with
portable generator connection panel to which temporary cables from the generator
can be terminated in the event of mains power failure. The cables required for this
temporary connection will need to be provided along with the generator set.

10.2.1 UNINTERRUPTIBLE POWER SUPPLIES (UPS)

UPS systems will be provided within the MCC in the main electrical switchroom
building to ensure that all key instrumentation, controller, and communications system
remain functional during mains power outage for a minimum of two hours. The UPS
status will be monitored from the plant SCADA system. The UPS will be supplied with a
rectifier unit to allow the plant control and instrumentation equipment to be supplied
at 24 VDC secure supply.

10.3 ELECTRICAL EQUIPMENT INSTALLATION

10.3.1 MOTOR CONTROL CENTRES (MCC) AND CABINETS

Where possible, electrical cabinets will be installed indoors to avoid the influences of
weather and vermin. Locating cabinets outdoors can cause early deterioration to
equipment and in turn, reduce operability and installation life.

Where electrical cabinets are installed outdoors, cabinets and enclosures will be
suitably rated weather-proof to Ingress Protection (IP) 56.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 55
Status: FINAL
Where MCC and electrical cabinets are installed indoors, cabinets will be suitably rated
to Ingress Protection (IP) 41.

The plant MCC is located in the electrical switchroom. The MCC is to be provided with
incoming and outgoing breakers, energy meter, distribution boards, controls and
motor starters etc. as shown in the single line diagram. The MCC shall additionally
include master PLC, I/Os, UPS, 240/24V DC power supply unit in a separate
compartment.

All equipment selections shall be applicable to the installed environment, including


manufacturers recommended ambient temperature operating ranges, manufacturers
installation and segregation requirements.

10.3.2 VARIABLE SPEED DRIVES (VSD’S)

Variable Speed Drives (VSD’s) will be used for the BTF distributor arm only.

The use of VSD’s has been minimised where not required for efficient operation of
equipment to reduce capital costs, including the costs associated with VSD units,
cabling, programming, harmonic mitigation equipment, additional switchroom space
and air conditioning requirements

VSDs are typically rated to operate at a maximum nominal ambient temperature of 40º
C to 50º C for maximum operational optimisation. During summer ambient peaks it is
possible that the building within the plant can achieve or exceed the nominal ambient
temperatures for equipment operation. Forced ventilation (air conditioning) is
recommended within rooms where VSD’s are installed to ensure equipment reliability
and mitigate potential failures to process equipment.

10.3.3 DISTRIBUTION BOARD

The Distribution boards shall be provided for the following areas and applications:
• UPS DB for Administration Building
• Lighting and Small Power DB for Switchroom Building
• Lighting and Small Power DB for Administration Building.
• Lighting and Small Power DB for Staff Housing.
• Lighting and Small Power DB for Workshop.
• Process DBs (to be designed and supplied by respective process vendor and
located near to the process area)
Except for process DBs, all DBs are located inside the building.

10.3.4 CABLING AND WIRING SYSTEMS

To achieve a high rating of conductance within the electrical system, all cables will
have copper conductors of circular cross-section and sized as required for equipment
operation. Cables will be installed with suitable mechanical protection and wiring
enclosures to mitigate the environmental influence and vermin.

W268.01 City Sewerage DED


56 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 10: Electrical Design Requirements

Cables will be permanently identified by a unique reference number to assist with


identification and troubleshooting.

Single core, phase coloured PVC insulated, multi-stranded, copper conductor cables of
minimum sizes according to the following table shall be used for wiring in the
assembly.
• Power cables, 2.5 mm³
• Control cables, 1.5 mm²
• Instrument cables, 0.5 mm²

10.3.5 FUTURE AND SPARE ALLOWANCES

Provisions have been made in the design for future installation of additional electrical
equipment due to plant expansions or upgrades. MCC’s and cabinets have been
designed with provisional allowances for future equipment installations and minor
upgrades.

Associated conduit and wiring systems into and out of the electrical room include
provision of spare space within conduits/cable tray networks and within wiring
trenches.

All future spare allowances will be within the nominal vicinity of 25% spare capacity.

10.4 LOCATION OF ELECTRICAL EQUIPMENT

The design and installation of electrical equipment will aim to achieve, wherever
possible, reasonable vicinity to the specific equipment to minimise electrical cable
reticulation and enhance plant operability. Distribution boards supplied by the process
vendors shall be located near the respective process area to reduce the length of
distribution cables.

10.5 SIZING OF ELECTRICAL SWITCH ROOM

The electrical switchroom building will make provisions for installation of the plant
MCC with all necessary switchgear and control gear equipment required (as shown in
the Single Line Diagram) for the plant operation and distribution, including allowances
for future equipment.

This could be achieved through designing the switchroom with a spare capacity
allowance of 25%, or spare space allowance adjacent to the building to allow future
expansion. The option of designing the spare capacity would be preferred as this will
reduce the impacts to future construction.

Sufficient clearance shall be provided around the MCC for ease of maintenance with a
minimum of 600mm clearance from any obscurities when a cabinet door is opened at
90 degrees, for example.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 57
Status: FINAL
Should the Power Supply Authority decide to provide a High Voltage (HV) supply to the
plant instead of Low Voltage (LV), then a suitable sized transformer shall be supplied
and installed by the Contractor within the correct vicinity to the switchroom, adhering
to any clearance or safe distance requirements set by the governing standards. The
power supply availability and the limit of scope definition shall be verified by the
Contractor with the Power Supply Authorities

W268.01 City Sewerage DED


58 Palembang WWTP Final Detailed Design
Report Status: FINAL
11: Plant
Chapter 12: DesignControl System
Standards

Chapter 11: Plant Control System


11.1 PERFORMANCE REQUIREMENTS

The plant operation will be based on the philosophy of a manned plant, with operators
being housed at the plant during non-business hours and on weekends. Therefore, no
offsite monitoring will be required for the WWTP plant.

The plant control system will be provide a moderate level of automation and not a full
autonomous operation. The system will require minimal operator intervention under
normal conditions with regular manual operator interaction required.

Reliable Programmable Logic Controllers (PLCs) will be implemented, In this


application, redundant PLC processors are not required. Process systems will be
designed with emergency manual backup controls.

The control system shall be configured and programmed to:


• Provide functionally, inclusive of all local indication and control requirements
• Interface to a Supervisory Control and Data Acquisition (SCADA) workstation
located onsite.

11.2 COMMUNICATIONS

A local area Ethernet network will provide communications to a fixed Human-Machine


Interfaces (HMI’s)) workstations throughout the plant.

11.3 CONTROL SYSTEM OVERVIEW

11.3.1 OBJECTIVE

The key objective of the control system is to provide the ability to efficiently and safely
control and monitor the treatment plant both locally, and remotely. This includes the
following:

Local control objectives:


• Start-up of equipment
• Shut down the equipment
• Respond to alarms
• Setpoint and control adjustments
• Process monitoring
• Perform automated control sequences

Remote control objectives:


• All of the above

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 59
Status: FINAL
11.4 OPERATIONS SOFTWARE INTEGRATION

The SCADA system will provide performance monitoring data, such as accumulated
equipment run-times, process tending etc. to an asset management/logging system.
The data interface and data access protocols will be defined during the design phase.

11.5 CONTROL HIERARCHY

The plant control system will provide the following basic hierarchy of control from the
field devices to the control room:
• Local manual control mode of individual equipment and sub-systems. This
mode is operated from the Local Control Stations (LCS) located within close
proximity to the plant equipment such as pump motors etc.
• Remote manual control mode (only available on selected equipment) of
individual devices and sub-systems through the plant SCADA system. This
mode will mainly be used for periodic maintenance, testing, and short term
operation and will be available through any of the HMI operator workstations
when the applicable LCS’s have been set to ‘Remote’ mode.
• Remote automatic control mode (only available on select equipment), based
on operator-entered set-points and logic sequencing.

11.6 CONTROL SYSTEM ARCHITECTURE AND HARDWARE

The following are the key hardware components of the plant control system with a
functional description of each of the components:

11.6.1 PROGRAMMABLE LOGIC CONTROLLERS (PLCS)

The WWTP will be controlled by a centralised/master PLC with remote PLC I/O clusters.
The master PLC will be programmed to provide automatic sequencing and control of
the select equipment, monitor status, and initiate alarms.

The master PLC will be independent of the HMI. Should the HMI be unavailable, or
unattended, the PLC will continue to operate on the basis of the last entered set-
points. The PLC will operate over a ring Ethernet network via a series of managed ‘hub’
switches, to allow access to the network through various locations on the plant. The
PLC will be specified to include programming software, spare PLC hardware
components, and operator training.

The PLCs supplied by each process vendor shall have the compatibility to interface to
the master PLC located in the electrical switchroom building. The individual process
vendor supplied PLC & I/Os shall be located within a reasonable vicinity of their
respective process area. The vendor PLC I/O equipment can be installed within the
same cabinet as the process vendor distribution board, but shall be installed within a
dedicated compartment/tier to maintain segregation and shall be installed as per
manufacturer’s requirements.

W268.01 City Sewerage DED


60 Palembang WWTP Final Detailed Design
Report Status: FINAL
11: Plant
Chapter 12: DesignControl System
Standards

The master PLC, I/Os and converter switches located in the switchroom shall be
mounted in a separate IP 20 compartment within the MCC. A double General Purpose
Outlet (GPO) shall be supplied in this cubicle to allow charging of programmer’s
laptops and or ancillary equipment during programming or maintenance.

The general control system architecture drawing details the main components of the
control system. Any further details shall be confirmed by the contractor in accordance
with the manufacturer and respective vendor packages.

11.6.2 HMI OPERATOR INTERFACE

A HMI (Human-Machine Interface) will provide a graphical interface between the


operator and the equipment. The HMI will provide alarm logging, trending, and
historical database logging.

A HMI will be located within the electrical switchroom building, and a main
engineering HMI workstation via desktop computer will be located within the plant
administration building.

To ensure security and reliability, the HMI workstations will not be used as general-
purpose computers and will have no connection to the Internet, and will not have
general-purpose office software such as Microsoft Office.

11.6.3 INTRA-PLANT SCADA COMMUNICATIONS

Communications between fixed SCADA nodes, including the HMI workstations and the
PLC and remote I/O clusters, will be via Ethernet CAT5/6 cable within the building and
up to 50 meter distances. Between locations greater than 50 meters, multimode
Ethernet over fibre optic cable will be provided. The fibre optic cable will provide
redundancy and reduce cabling across large spans between the plants communication
system architecture and provides optimal opportunities for expansion for future
applications.

The communication between the process vendor PLCs and the master PLC in the
electrical switchroom is via fibre optic cables.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 61
Status: FINAL
Chapter 12: Design Standards
12.1 MATERIALS OF CONSTRUCTION

12.1.1 PIPING

The proposed piping materials within the WWTP site are as follows:
• Below grade pressure lines and all gravity lines:
o > 600mm diameter: MSCL
o 300mm-600mm diameter: DICL
o < 300mm diameter: HDPE
• Above grade pressure lines:
o ≥ 100mm diameter: DICL
o < 100mm diameter: PVC

The site will potentially experience significant differential settlement; therefore, pipe
materials which have good flexibility and resistance to sheer are required.

12.1.2 OTHER
• Penstocks to be 316 stainless steel.
• Handrailing, stairways and associated supports to be hot dipped galvanised.

12.2 CONCRETE CORROSION PROTECTION

Protection/isolation of concrete surfaces against biogenic sulphuric acid


attack/corrosion will be required in the inlet works, ABRs and BTF feed pump station.
The surfaces to be protected will include all channel and tank wall internal surfaces
above the minimum operating water level and the roof slab soffit. Available options
are summarised below.

Commonly used isolation coatings in this application are solventless epoxy or polyuria
coatings. Cast-in high density polyethylene protective liners have also been adopted in
some structures and the application of a calcium aluminate based mortar layer which
inhibits the bacterial activity necessary to produce sulphuric acid has also been
popular, especially with rehabilitation and protection of deteriorated concrete surfaces
from such attack and it’s use is gaining popularity in some new structures.

The above options are considered the most appropriate isolation methods having
considered aspects such as local practices, application constraints, environmental
factors, service life etc.

12.3 TANK AND CHANNEL COVERS

Open decking will be aluminium grating except in potentially corrosive areas in which
case the decking will be fiberglass grating.

W268.01 City Sewerage DED


62 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 12: Design Standards

The inlet works will be fitted with closed decking consisting of GRP covers and foul air
extraction offtakes. Decking will be set in pieces not more than 1200mm wide by the
width of the opening with hinged (flush surface mounted to prevent trip hazard) lifting
rings to allow hand insertion for lifting. The covers will be fitted with hinged access
hatches where required.

The ABR tanks will be covered with air tight, moulded GRP sections designed to
accommodate an internal working pressure of 3kPa, supplied and installed by specialist
supplier/Contractor. Cover access hatch positions and details are to be finalised at the
next detail design phase.

The BTF feed pump station will be fitted with a concrete cover with aluminium
hatches.

12.4 LIGHTING

Local area lights will be provided at each process area, including at the top deck level.
One light located nearest the light switch will be placed on a photovoltaic cell to turn
on at dark. The remaining lights will be manually turned on and off.

Site lighting will be placed along the main entrance roads. These site lights will be
placed on photovoltaic cells to activate at dark.

The power supply to area lights will be from the lighting distribution board located
inside the electrical switchroom building.

All lighting and associated equipment selections should be applicable to the installed
environment, including manufacturer’s recommended ambient temperature operating
ranges, manufacturer’s installation and segregation requirements and a min IP56
rating.

12.5 HOSE STATIONS

Hose stations will be provided in process areas at a spacing of not more than 15 meter.
Each hose station will be 1-1/2” diameter with a coupler for a 3/4-inch hose. Hose
racks will be provided at each hose station. Isolation valves will be provided at the rise
to each hose station.

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 63
Status: FINAL
Chapter 13: Works Packaging and Procurement
An issued for construction (IFC) set of the DED drawings and documentation has been
generated for input to a tender package and subsequent issue to the selected
Contractor. The works for the WWTP shall be procured as follows:
• Specifications and concept drawings will be generated as part of the IFC
package for Contractor design and construction of:
o Foundations
o Site services and utilities (including drinking water, fire water, power
supply, gas, telecommunications and site sewerage for WWTP
buildings). Contractor also responsible for coordination with local
authorities.
o Permanent yard piping
o Construction methods for permanent works
o Permanent buildings (including covers on sludge drying beds) and
associated architectural works, building services and building permits
arranged.

The Contractor will be required to make any required adjustments of detailed designed
structures and pipework to suit exact requirements of selected equipment and fittings.

Final layout of permanent roads and drainage within WWTP site determined by
Contractor (to match access requirements for buildings) based on road and drainage
engineering requirements defined in DED drawings and documentation.

Temporary works sites (including areas for Contractor’s plant and equipment and
storage of plant, equipment and materials) determined by Contractor.

W268.01 City Sewerage DED


64 Palembang WWTP Final Detailed Design
Report Status: FINAL
Chapter 14: References
• Asian Development Bank (ADB) Metropolitan Sanitation Management
Investment Project Draft Final Report (Revised) – ADB TA 7993, January 2013;
• Asian Development Bank (ADB) Technical Review of the IndII Wastewater
Investment Master Plan for Palembang (2011): Wastewater Treatment and
Sludge Management, November 2012;
• Asian Development Bank (ADB) Initial Environmental Examination, Palembang
City Off-Site Wastewater Collection System and Treatment (including
Environmental Management Plan), January 2013;
• IndII Wastewater Investment Master Plan Package II, Activity W004:
Palembang, Volume 4 Final Feasibility Study (& Annexs), September 2011;
• IndII Wastewater Investment Master Plan Package II, Activity W004:
Palembang, Volume 1 - Final Master Plan (& Annexs), August 2011;
• IndII Wastewater Investment Master Plan Package II, Activity W004:
Palembang, Volume 2 - GIS Drawings, August 2011.
• Foxon, KM., Buckley, CA., Brouckaert, CJ., Dama, P., Mtembu, Z., Rodda, N.,
Smith, M., Pillay, S., Arjun, N., Lalbahadur, T., Bux, F., February 2006 The
evaluation of the anaerobic baffled reactor for sanitation in dense peri-urban
settlements. Water Research Commission Report Number 1248/01/06 ISBN: 1-
77005-371-9

W268.01 City Sewerage DED


Palembang WWTP Final Detailed Design Report 65
Status: FINAL

You might also like