TOR - Process and Procedure Audit - NGCP
TOR - Process and Procedure Audit - NGCP
A. RATIONALE
The NGCP has the crucial task of delivering safe and reliable electricity
throughout the archipelago, a responsibility formerly held by the
National Transmission Corporation (TransCo). Incorporated in 2008,
the private corporation won in the bidding for the franchise to operate
and maintain the country’s transmission network. The fifty-year
franchise provides NGCP with the right to operate, maintain, expand
and further develop the country’s power transmission system which
involved with more than 21,000 circuit kilometers of lines, 20,000
transmission towers, and 140 substations.
The WESM was established by the DOE, in accordance with the EPIRA,
to facilitate a competitive market environment in the Philippine
electricity industry. The market operator, a non-stock and non-profit
organization with equitable representation from electric power
industry participants, was constituted by the DOE in November 2003
to operate the WESM in the interim. It is headed by Board of Directors
whose members are independent of government and of the market
participants.
Republic Act No. 9136, otherwise known as the Electric Power Industry
Reform Act (EPIRA) requires that WESM market operations be
transferred to an independent entity that is separate from its governing
body. As jointly endorsed by the market participants and the
Department of Energy (DOE), market operator will take on this role
and pursue the WESM objectives of having a transparent, fair,
competitive, and reliable market for the trading of electricity
throughout the Philippines.
As the Central Registration Body (CRB) for the retail electricity market,
market operator plays a pivotal role in fostering competition in the
Philippine electricity sector. Under the existing legal framework for
Retail Competition and Open Access (RCOA), electricity end-users
become part of the contestable market upon reaching the applicable
contestability demand threshold. After being certified by the ERC,
these contestable customers are given option to secure their supply
from a licensed retailer of their own choosing duly licensed by the ERC.
As CRB, market operator maintains a registry of these contestable
customers and their current suppliers, tracks the market transactions
made by their suppliers on their behalf, and effect customer-switching
in the retail market.
In accordance with Clause 1.5 of the WESM Rules, the market operator,
through an Independent Reviewer, has conducted four (4)
Independent Operational Audits of the Systems and Procedures on
Market Operations since 2009 up to 2013.
B. OBJECTIVE
C. SCOPE OF WORK
The Review shall cover NGCP’s operations for Luzon, Visayas and
Mindanao. The review shall cover procedures, processes and systems
being employed by NGCP through its organizational units but not
limited to the following:
▪ SCADA/EMS Division;
Further, the Review shall cover the relevant interfaces of the SO with
the market operator and its customers which include generators,
private distribution utilities, electric cooperatives, government-owned
utilities, economic zones, industries, and directly connected
companies.
Market Operator
Input Output
Processes
Load forecasts (RTD,
Load Forecasting
Energy Management DAP, WAP)
System (EMS) Snapshot Scheduling and DAP, RTD and RTX
Pricing schedules
Outage Schedules
Contingency List WAP, DAP, RTD and
Scheduling and
Transmission Limits and RTX schedules and
Pricing
Security Limits Prices
Reserve Requirements
WAP, DAP, RTD and
Transmission Network Scheduling and
RTX Schedules and
Model Pricing
Prices
Updating of the MNM used in
System Notices on
Market Network dispatch and
Network Configuration
Model (MNM) scheduling
The Commission and the ERC shall have full access to any
information, data, documents or working records acquired or used
by the Consultant during the project.
3. Security
3. Confidentiality
4. Intellectual Property
E. RESPONSIBILITIES OF ERC
The ERC shall facilitate the subject Process and Procedure Review by
providing the following:
F. TIMELINES/DELIVERABLES
The project shall be completed within one hundred eighty (180) days,
commencing from the date of receipt of the NTP by the Consultant.
Outputs/Deliverables Timeline
Conduct Kick-off meeting
Within five (5) days from the date of
receipt of the NTP
Output: Minutes of the Meeting
Delivery of Work Plan (Inception Report)
Within fourteen (14) days from the date of
receipt of the NTP
Output: Inception Report
Conduct of Clarificatory Meetings
Within sixty (60) days from the date of the
receipt of the NTP
Output: Minutes of the Meeting
Comments/Recommendations on the
Clarificatory meetings Within ninety (90) days from the date of
the receipt of the NTP
Output: Issues Paper/Report
On-site inspection
Within one hundred twenty (120) days
from the date of the receipt of the NTP
Output: Field Inspection Report
Submission of Initial/Draft Report on the
system operations process and procedure
review and inspection activities
Within one hundred fifty (150) days from
assessments/observations
the date of the receipt of the NTP
Output: Report on Observations and
Findings
Submission of Final Report for the system
operations process and procedure review Within one hundred eighty (180) days
from the date of the receipt of the NTP
Output: Final Report
3. Documentation
G. QUALIFICATION REQUIREMENTS
▪ Knowledgeable in fields of
accountancy, economics, finance,
law, engineering or other related
disciplines to undertake the tasks
required for this consultancy
services.
Education
Lead Consultant: At least an MA/MS
Educational attainment in law, degree holder, PhD will be an
accounting, economics, finance, advantage.
engineering and/or related fields, with
strong background in regulatory Experts: At Least BS/BA degree
practices. holder, MS/MA an advantage.
H. MODE OF PROCUREMENT
J. PAYMENT SCHEME/SCHEDULE
K. LIQUIDATED DAMAGES
L. RESERVATION CLAUSE
CRITERIA/PARTICULARS POINTS
I. Applicable Experience of the Firm 50
Prior involvement in reports or studies
related to asset valuation
II. Qualification of Officers, Key/Organic 30
Personnel who may be assigned for
the study
Education, training and years of
professional experience
III. Current Workload relative to job 20
capacity
GRAND TOTAL 100
Hurdle Rate 70
Note: only the top five (5) ranked consultancy firms with at least 70% rating based
on the short-listing criteria will be invited to submit the Technical and Financial Proposals.
Knowledge in fields of accountancy, economics, finance, law, engineering or other related disciplines to
A) 10%
undetake the tasks
Consultancy Services for the Process and Procedure Review of the National Grid Corporation of the Philippines (NGCP)
Exposure in electricity industry particularly on the regulatory reset of Electricity Distrbution utilities under the
C)
Performance Based Regulation - 10%
Yes 100 10%
No 0 10%
Records of previous engagement and quality of performance in similar projects (attached copy of proof of
A)
engagement)
C) Must have trainings on the different procurement process or other similar relevant trainings