Measurement Sheet #9 (VO)
Measurement Sheet #9 (VO)
Measurement Sheet #9 (VO)
Schedule No.4 Payment Plan (1st Oct, 2021 to 31 Oct, 2021) For Installation Services
Measurement Sheet No. 09 (VO)
1 2 3 4 5 6 10
Clearing and grubbing of the complete site area as per Drawings &
F.1.1 Lot 1 Appendix i 1.000 1.000
Specifications as approved by the Engineer.
ii. Using fill material excavated from the other foundations on Site. Cu.m. 4000 Appendix iii 2,908.761 2,908.761
Schedule No.4 Payment Plan (1st Oct, 2021 to 31 Oct, 2021) For Installation Services
Measurement Sheet No. 09 (VO)
1 2 3 4 5 6 10
F.3.D
Providing & Fixing hot dip galvanized steel brackets (hangers),
cable trays, channels in the cable trenches type 1,2,3 & 4 including
fixer and all accessories complete as per specification and
drawings approved by the Engineer. Lot 1
Design, Manufacture, Supply, Installation, Testing and Commissioning of Plant for 500/220/132 kV Faisalabad
West Substation
Measurement Sheet No.09 (VO)
Reference Documents:
Boq. Item No. F.3.C.2 Appendix - (CI) Item Detailed Breakdown 1.
Design, Manufacture, Supply, Installation, Testing and Commissioning of Plant for 500/220/132 kV Faisalabad
West Substation
Measurement Sheet No.09 (VO)
Reference Documents:
Boq. Item No. F.3.C.2 Appendix - (CJ) Item Detailed Breakdown 1.
Design, Manufacture, Supply, Installation, Testing and Commissioning of Plant for 500/220/132 kV Faisalabad
West Substation
Measurement Sheet No.09(VO)
Reference Documents:
Boq. Item No. F.3.C.4 Appendix - (CK) Item Detailed Breakdown 1.
Design, Manufacture, Supply, Installation, Testing and Commissioning of Plant for 500/220/132 kV Faisalabad
West Substation
Measurement Sheet No.09 (VO)
Reference Documents:
Boq. Item No. F.3.B.2 Appendix - (CE) Item Detailed Breakdown 1.
Design, Manufacture, Supply, Installation, Testing and Commissioning of Plant for 500/220/132 kV Faisalabad
West Substation
Measurement Sheet No.09 (VO)
Reference Documents:
Boq. Item No. F.3.B.3 Appendix - (CF) Item Detailed Breakdown 1.
3 Trench Pad L.m 484.269 484.269 100.00% 40% 0.000 193.552 193.552
4 Trench Walls L.m 484.269 484.269 100.00% 40% 0.000 193.552 193.552
Design, Manufacture, Supply, Installation, Testing and Commissioning of Plant for 500/220/132 kV
Faisalabad West Substation
Measurement Sheet No.09 (VO)
Reference Documents:
Boq. Item No. F.3.A.3 Appendix - ( CB ) Item Detailed Breakdown 1.
Item Description RCC Cable Trench Type -3 Actual Length As per Drawing As per Measurement Sheet No. 09 Approved Trench Length (L.m) 150.720
Weightage
Executed Percentage Total
Total Length Length Completed (%) Length claimed
Sr. Length Previous
No. Actual Actual Percentage (%) (D) claimable QTY Todate
Description Unit No L W H (A) No (B) (C) (F)
(E)
1 Excavation and Levelling L.m 150.720 150.720 100.00% 5% 0.000 7.268 7.268
2 Lean concrete L.m 150.720 150.720 100.00% 10% 0.000 14.536 14.536
3 Trench Pad L.m 150.720 150.720 100.00% 40% 0.000 58.144 58.144
4 Trench Walls L.m 150.720 150.720 100.00% 40% 0.000 58.144 58.144
Design, Manufacture, Supply, Installation, Testing and Commissioning of Plant for 500/220/132 kV Faisalabad
West Substation
Measurement Sheet No.09 (VO)
Reference Documents:
Boq. Item No. F.3.A.4 Appendix - (CC) Item Detailed Breakdown 1.
Item Description RCC Cable Trench Type -4 Actual Length As per Drawing As per Measurement Sheet No. 09 Approved Trench Length (L.m) 256.225
Weightage
Executed Percentage Total
Total Length Length Completed (%) Length claimed
Sr. Length Previous
Actual Actual Percentage (%) (D) Todate
No. claimable QTY (F)
Description Unit No L W H (A) No (B) (C) (E)
1 Excavation and Levelling L.m 256.225 256.225 100.00% 5% 0.000 12.755 12.755
2 Lean concrete L.m 256.225 256.225 100.00% 10% 0.000 25.510 25.510
3 Trench Pad L.m 256.225 256.225 100.00% 40% 0.000 102.040 102.040
4 Trench Walls L.m 256.225 256.225 0.000 100.00% 40% 0.000 102.040 102.040