Status Report Example 021606110036 Status Report-Example

The monthly status report summarizes the Example Project's activities in November 2004. Overall status is yellow due to a deliverable being delayed. The budget is on track with no variance. Key plans for the next period include developing, reviewing, and accepting the delayed XYZ deliverable and reviewing all vendor deliverables. The project aims to provide modern electronic access to government programs while decreasing costs and increasing quality.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
1K views

Status Report Example 021606110036 Status Report-Example

The monthly status report summarizes the Example Project's activities in November 2004. Overall status is yellow due to a deliverable being delayed. The budget is on track with no variance. Key plans for the next period include developing, reviewing, and accepting the delayed XYZ deliverable and reviewing all vendor deliverables. The project aims to provide modern electronic access to government programs while decreasing costs and increasing quality.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 5

State of Minnesota

<project name> Project


Monthly Status Report (Example)
Project Name: Example Project Reporting Period: November, 2004

Project Manager: Name, Title


Project Owner: Name, Title
Project Sponsor: Name, Title

Executive Summary
Overall Status: Yellow

Green Yellow Red


Reason for Deviation
(Controlled) (Caution) (Critical)
Budget
Schedule Deliverable XYZ delayed

Scope External project deliverable strategy being redefined

Comments:

 Definition of the XYZ deliverable needs to be finalized. Content is currently being


generated. This important deliverable will need to be reviewed and updated for high quality.

Controls
Issue Status:

• A strategy needs to be established and agreed upon relative to responding to requests for
information associated with the project. This issue is being worked.
Change Status:

• XYZ deliverable due date changing from 3/7/2005 to 3/21/2005.


Risk Status:

• Risk: There is risk that the project accomplishments could lose their impact and the needed
momentum for the follow-on effort could be minimized if a transition plan to the next phase
is not defined and executed.
Mitigation: The following two activities are being initiated:
1.A communications plan is being developed and executed to support the
involvement of the Governor’s office and related legislative sponsorship.
2.A program portfolio for the follow-on effort is being generated. A transition work plan
will capture the recommendations of the project. Follow-on project initiatives will be
developed based on the recommendations of the project.

05/04/2011 Page 1 of 5
Monthly Status Report Template v 2.0 11/04/2002 Office of Technology Program Management Office
Budget

Budget Status as of 10/31/2004

Original Current Spent to Est. to Current


Expense Budget Budget Date Complete Forecast Variance
Labor
Internal 3,659,200 3,732,800 3,585,600 147,200 3,732,800 0
External 2,500,000 2,500,000 2,125,000 375,000 2,500,000 0
Hardware 0 0
Software 0 0
Other 0 0
Total $6,159,200 $6,232,800 $5,710,600 $522,200 $6,232,800 $0

Budgetary Comments:
• Burden rate of $100 per hour assumed for internal resources
• Spent to date is estimated based on a linier prorated over time algorithm

• Internal budget does not include steering committee member resources

• Increase in internal current budget is due to two additional weeks of deliverable generation

• Internal budget includes state resources deployed on the effort

05/04/2011 Page 2 of 5
Monthly Status Report Template v 2.0 11/04/2002 Office of Technology Program Management Office
Scheduled Milestones / Deliverables

Approved Current
Milestone Actual Status
Schedule Forecast
Start Project 6/1/2004 6/1/2004 Complete

Vendor RFP posted 6/19/2004 6/19/2004 Complete

Vendor selected 7/21/2004 8/8/2004 Complete

Vendor contract awarded 9/1/2004 9/25/2004 Complete

Program resources identified 9/9/2004 Complete

Steering Committee identified Complete

Phase I kick-off 10/8/2004 10/13/2004 10/13/2004 Complete

Communications Plan available 10/10/2004 10/10/2004 Accepted

Activity completed 12/8/2004 12/8/2004 Complete

Activity completed 12/8/2004 Complete

Activity completed 12/8/2004 12/15/2004 12/15/2004 Complete

DEF Deliverable available 12/29/2004 12/29/2004 Accepted

GHI Deliverable available 12/29/2004 120/29/2004 Accepted

Phase II kick-off meeting 1/1/2005 1/1/2005 Complete

Phase III kick-off meeting 1/6/2005 1/6/2005 Complete

JKL Deliverable available 2/3/2005 2/17/2005 In Review

XYZ Deliverable available 3/7/2005 3/21/2005 Redefined

Records Retention Plan executed 3/30/2005 Yellow

Project complete 3/31/2005 Green

Note: Bold milestones are key external project deliverable

05/04/2011 Page 3 of 5
Monthly Status Report Template v 2.0 11/04/2002 Office of Technology Program Management Office
Accomplishments & Plans

Accomplishments during this Reporting Period:


• Continued to execute the communications plan.

• Held several steering committee meetings. Reviewed and approved deliverable

• Subcommittee of the Steering Committee evaluated and categorized recommendations and


opportunities.

• Developed a work plan to schedule final update, review and acceptance of the project
deliverable.

Plans for the next Reporting Period:


• Develop, review and accept the XYZ deliverable.
• Review, update and accept all the vendor deliverable.

• Organize and archive all project materials.

• Execute the Records Retention plan.

• Start to initiate a transitional communications plan and program portfolio for the next steps
that can be handed off to the program office that will be recommended by the project.
• Continue to maintain the project control practices – steering committee meetings,
status reporting, issues management, change control, work plan, budget management,
document management and risk management.

05/04/2011 Page 4 of 5
Monthly Status Report Template v 2.0 11/04/2002 Office of Technology Program Management Office
Project Definition
Project Description
This section contains a brief description of the business need that drives the project.
The project will accomplish the following activities to support this vision:
 Broad description of activity
 Broad description of activity
Project Definition

Business  Providing modern, comprehensive and user-friendly electronic


Objectives access to government program.
 Decreasing the administrative cost of providing the service
while increasing the quality and efficiency.

Scope  Identify business transactions performed by the program,


documented in the form of a current business process model
 Identify information requirements of the business transactions
performed by the program, documented in the form of a data
flow diagram
 Identify technologies used by the program, documented in the
form of a current technology model
 Identify potential opportunities to improve efficiency and
effectiveness through the use of streamlined processes,

Assumptions  The program’s resources meet the requirements (skills,


experience and time commitment) specified in the “Roles and
Responsibilities” and “State FTEs” attachments to the
Statement of Work.
 Existing procedural and system documentation for all in-scope
businesses and systems will be available to the project team
very early in the project.
 The approach to this project is based on the vendor’s
methodology for organizational performance enhancement.
 It will be the State’s responsibility to review, verify, and confirm
the accuracy of the data provided to the project team by each
agency.

Dependencies  The Governor’s budget process


 Constraints governed by the Data Practices Act
 Constraints inherent in an aggressive project schedule

05/04/2011 Page 5 of 5
Monthly Status Report Template v 2.0 11/04/2002 Office of Technology Program Management Office