Pre-Commissioning Inspection / Calibration (Pressure Relief Valve) DN-M007-B
Pre-Commissioning Inspection / Calibration (Pressure Relief Valve) DN-M007-B
Page 1 of 1
Pre-Commissioning
DN-P002-B
Witnessed Joint Check
Test Pack No.
Description:
System No.
Sub System No.
Location.
Drawing Reference.
Punch
No. Items to be Checked OK N/A
List
1 State reason for request for Witnessed Joint:-
Condition, rating of flanges, gaskets and fasteners to be checked and confirmed just prior to
2
assembly. Torqing, sequencing to be witnessed at assembly.
3 Record Joint Identification Number:
4 Confirm all NDT testing complete and accepted for flange/pipe welds.
5 Joint previously hydrotested: Yes / No
6 Joint previously subjected to leak test: Yes / No
7 Fastening Method: Hydraulic / Manual Torque Wrench.
8 Torque setting required.
9 Bolt tension setting 1 ___________
10 Bolt tension setting 2 ___________
11 Confirm flange faces are parallel.
12 Confirm flange raised faces / grooves clean, free from corrosion and undamaged.
Confirm gasket new and size, rating, type correct in accordance with specification and code, clean and
13
undamaged.
14 Confirm all studs / nuts new and correct to specification, clean, free from corrosion and undamaged.
15 Check Studs / Nuts torqued in correct sequence to correct torque setting.
16 Confirm no visible damage to gasket when joint completed.
17 Confirm no excessive length of stud / bolt protruding through each nut.
Page 1 of 1
Pre-Commissioning
DN-P003-B
Leak Test
Test Pack No.
Description:
System No.
Sub System No.
Location.
Drawing Reference.
No. Check Description N/A INIT DATE
Task description is available that specifies the method, media to be used , system
1
limits, acceptance criteria for the test and inerting requirement post testing
2 PIDs marked up with test circuit
Relief valve available. (If no, indicate why)
3
Valve number set at: __________________ BarG. / kPag
4 Flare system operational
5 JSA reviewed and requirements intiated
6 Flexible Hoses to be used rated for Relief Valve set pressure
7 Test gauges installed and correct scale for test
8 Flanges taped (HP Test)
9 Test area barricaded off, warning signs posted
10 No construction activities in the area
11 Blinds installed – Blinds list attached
12 All test isolations made – valves tagged
13 Adjacent systems vented if valve isolations applied
14 Safety review / walk of test area made – safe for testing
On completion of leak test, system has been inerted and placed under positive pressure
15
to specification.
Work Permit required.
16
Permit No.:
Test Results:
Test pressure achieved: BarG / kPag
Decay Test: Loss of (BarG / kPag) over hours
Comment on Decay Test:
System depressurized / made safe
All Test Blinds removed – Blinds list attached
Remarks:
Signature
Print Name
Date
Page 1 of 1
Pre-Commissioning
DN-S001-B
Structural Acceptance
Tag No.
Equipment Description:
System No.
Sub System No.
Location:
Drawing Reference.
Punch
No. Items to be Checked OK N/A
List
1 Confirm material certificates available.
2 Confirm welding identification drawings available.
3 Confirm weld history sheet complete / available.
4 Confirm pre-heat / post weld heat treatment records complete / available.
5 Confirm NDT records complete / available.
6 a) MPI report
7 b) UT report
8 c) Load test certificate
Page 1 of 1