0% found this document useful (0 votes)
248 views5 pages

Pre-Commissioning Inspection / Calibration (Pressure Relief Valve) DN-M007-B

This document provides a checklist for pre-commissioning inspection and calibration of a pressure relief valve. The checklist includes items to inspect such as serial number, materials, sizes, settings, and location. It also lists calibration tests to perform including cold setting pressure, lift pressure, reset pressure, and leak testing. Technicians must complete the inspection and testing, ensure proper installation, and confirm the calibration certificate is stored.

Uploaded by

Rozh Sammed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
248 views5 pages

Pre-Commissioning Inspection / Calibration (Pressure Relief Valve) DN-M007-B

This document provides a checklist for pre-commissioning inspection and calibration of a pressure relief valve. The checklist includes items to inspect such as serial number, materials, sizes, settings, and location. It also lists calibration tests to perform including cold setting pressure, lift pressure, reset pressure, and leak testing. Technicians must complete the inspection and testing, ensure proper installation, and confirm the calibration certificate is stored.

Uploaded by

Rozh Sammed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Pre-Commissioning

Inspection / Calibration DN-M007-B


(Pressure Relief Valve)
Tag No.
Loop No
Equipment Description:
System No.
Sub System No
Location
Data Sheet.
Drawing Reference. Date Printed: @TagCheckDocCreatedDate@
Punch
No. Items to be Checked OK N/A
List
Required Data to be Noted:
Serial No. Body material:………………… Type / detail.   
Type and size Bellows material:……………… Type / detail.   
1 Orifice size Pilot or spring operated:…………… Confirm.   
Spring No. Tagging and Location correct: Yes / No   
Cold set pressure: Barg. Data sheet setting: Barg.   
Back pressure: Barg. Operating temperature: ºC.   
2 Verify equipment correct to data sheets / drawings / documentation   
Carry out calibration and recording of all data for the PRV/PSV as requested below and add any remarks /
3
comments on sheet 2 of 2 this form.   
4 Following satisfactory completion ensure that the PRV/PSV is installed at correct location on plant.   
5 Confirm that flange gaskets and bolting for inlet and outlet flanges are correct to piping specification.   
6 Ensure that calibration certificate is safely stored for future traceability.   
Ensure Lead seals / wire locking of the PSV / PRV is completed and during installation on plant is not
7
damaged / removed. (if tag is removed during transport /installation then retesting of PSV is required.   
Cold Setting Pressure : Leak Test :
Test medium Leak Test Pressure Barg.

8 Cold Set Pressure Barg. Duration Min. / Hour.   


Lifting Pressure Barg. Leak rate (Bubbles / Min).   
Reset Pressure Barg.   

Completed By Accepted By Comments / Remarks:


Signature:
Print Name:
Date:
Company:
Pre-Commissioning
DN-P-001B
Piping General Acceptance
Test Pack No.
Description:
System No.
Sub System No.
Location.
Drawing Reference.
The following checks are to be carried out as part of a P&ID ‘red line’ check when the
Workpack is offered at Ready For Commissioning stage and must include equipment,
instrumentation lines on Vendor packaged units as well as site installed equipment piping:
Punch
No. Items to be Checked OK N/A
List
Equipment, Piping and Instrumentation related to this workpack is accepted as Construction
1
Complete, installed / re-instated in accordance with the P & ID’s.   
2 Check all notes on each P&ID listed above and confirm system compliance.   
Confirm correct installation of relief valves interlock system and the interlock logic
3
demonstrated in both directions.   
Equipment, cabling and instrumentation on vendor packaged units is installed as per
4
(Vendor) documentation, correctly supported and hooked up to correct tie-in point   
All vendor preparation activities (pre-start checks, lubrication, alignments, loading of
5
software, function and safeguarding checks etc) have been completed and signed off.   
All construction (temporary) services and aids have been removed and fluids (hydrotest
6
water etc) drained down.   
Any joints broken after re-instatement check completion have been remade and witnessed
7
/ and signed off on disturbed joingt register   
8 Checksheets for other disciplines for the workpack have been completed and signed off.   
9 First fills for process equipment and vendor packages have been completed   
10 Any post construction ( operational ) flushing and sampling has been completed   
Confirm Sub-System is complete and ready for commissioning and Livening Up Notice has
11
been Issued.   
12 P&ID is marked up in to show ‘As built’ condition and attached to this certificate.   

Completed By Accepted By Comments / Remarks:


Signature:
Print Name:
Date:
Company:

Page 1 of 1
Pre-Commissioning
DN-P002-B
Witnessed Joint Check
Test Pack No.
Description:
System No.
Sub System No.
Location.
Drawing Reference.
Punch
No. Items to be Checked OK N/A
List
1 State reason for request for Witnessed Joint:-   
Condition, rating of flanges, gaskets and fasteners to be checked and confirmed just prior to
2
assembly. Torqing, sequencing to be witnessed at assembly.   
3 Record Joint Identification Number:   
4 Confirm all NDT testing complete and accepted for flange/pipe welds.   
5 Joint previously hydrotested: Yes / No   
6 Joint previously subjected to leak test: Yes / No   
7 Fastening Method: Hydraulic / Manual Torque Wrench.   
8 Torque setting required.   
9 Bolt tension setting 1 ___________   
10 Bolt tension setting 2 ___________   
11 Confirm flange faces are parallel.   
12 Confirm flange raised faces / grooves clean, free from corrosion and undamaged.   
Confirm gasket new and size, rating, type correct in accordance with specification and code, clean and
13
undamaged.   
14 Confirm all studs / nuts new and correct to specification, clean, free from corrosion and undamaged.   
15 Check Studs / Nuts torqued in correct sequence to correct torque setting.   
16 Confirm no visible damage to gasket when joint completed.   
17 Confirm no excessive length of stud / bolt protruding through each nut.   

Completed By Accepted By Comments / Remarks:


Signature:
Print Name:
Date:
Company:

Page 1 of 1
Pre-Commissioning
DN-P003-B
Leak Test
Test Pack No.
Description:
System No.
Sub System No.
Location.
Drawing Reference.
No. Check Description N/A INIT DATE
Task description is available that specifies the method, media to be used , system
1
limits, acceptance criteria for the test and inerting requirement post testing
2 PIDs marked up with test circuit
Relief valve available. (If no, indicate why)
3
Valve number set at: __________________ BarG. / kPag
4 Flare system operational
5 JSA reviewed and requirements intiated
6 Flexible Hoses to be used rated for Relief Valve set pressure
7 Test gauges installed and correct scale for test
8 Flanges taped (HP Test)
9 Test area barricaded off, warning signs posted
10 No construction activities in the area
11 Blinds installed – Blinds list attached
12 All test isolations made – valves tagged
13 Adjacent systems vented if valve isolations applied
14 Safety review / walk of test area made – safe for testing
On completion of leak test, system has been inerted and placed under positive pressure
15
to specification.
Work Permit required.
16
Permit No.:
Test Results:
Test pressure achieved: BarG / kPag
Decay Test: Loss of (BarG / kPag) over hours
Comment on Decay Test:
System depressurized / made safe
All Test Blinds removed – Blinds list attached

Test has been completed as described on attached PIDs and is


ACCEPTABLE / NOT ACCEPTABLE (delete as appropriate and sign)

Remarks:

LEAK TEST LEAK TEST LEAK TEST


DESCRIPTION CARRIED OUT BY APPROVED BY ACCEPTED BY

Signature

Print Name
Date

Page 1 of 1
Pre-Commissioning
DN-S001-B
Structural Acceptance
Tag No.
Equipment Description:
System No.
Sub System No.
Location:
Drawing Reference.
Punch
No. Items to be Checked OK N/A
List
1 Confirm material certificates available.   
2 Confirm welding identification drawings available.   
3 Confirm weld history sheet complete / available.   
4 Confirm pre-heat / post weld heat treatment records complete / available.   
5 Confirm NDT records complete / available.   
6 a) MPI report   
7 b) UT report   
8 c) Load test certificate   

Completed By Accepted By Comments / Remarks:


Signature:
Print Name:
Date:
Company:

Page 1 of 1

You might also like