Microsoft Project Tutorial 5 CPM
Microsoft Project Tutorial 5 CPM
Mobilization
Start: Thu 11/11/21 ID: 2
Finish: Wed 11/17/21Dur: 5 days
Res:
Remove & Dispose Existing Building Remove Concrete Pavement Curb & Gutter
Start: Thu 11/18/21 ID: 3 Start: Thu 11/18/21 ID: 4
Finish: Mon 11/29/21Dur: 7 days Finish: Mon 11/29/21Dur: 7 days
Res: Res:
Grading
Start: Tue 11/30/21 ID: 5
Finish: Wed 12/8/21 Dur: 7 days
Res:
Rebar/Formwork
Start: Thu 12/30/21 ID: 8
Finish: Fri 1/7/22 Dur: 7 days
Res:
SOG
Start: Mon 1/10/22 ID: 9
Finish: Tue 1/11/22 Dur: 2 days
Res:
Finish Plumbing
Start: Mon 1/31/22 ID: 12
Finish: Tue 2/8/22 Dur: 7 days
Res:
Inspection - Plumbing
Start: Wed 2/9/22 ID: 13
Finish: Wed 2/9/22 Dur: 1 day
Res:
Finish Electrical
Start: Thu 2/10/22 ID: 14
Finish: Fri 2/18/22 Dur: 7 days
Res:
Inspection - Electrical
Start: Mon 2/21/22 ID: 15
Finish: Mon 2/21/22 Dur: 1 day
Res:
Roof TPO
Start: Tue 2/22/22 ID: 16
Finish: Fri 3/11/22 Dur: 14 days
Res:
Masonry
Start: Wed 4/13/22 ID: 23
Finish: Mon 5/2/22 Dur: 14 days
Res:
Dumpster Enclosure
Start: Fri 7/1/22 ID: 27
Finish: Fri 7/8/22 Dur: 5 days
Res:
Menu Board
Start: Mon 7/11/22 ID: 28
Finish: Fri 7/15/22 Dur: 5 days
Res:
Install Sign
Start: Mon 7/18/22 ID: 29
Finish: Tue 7/19/22 Dur: 2 days
Res:
Landscaping
Start: Wed 7/20/22 ID: 30
Finish: Thu 7/28/22 Dur: 7 days
Res:
Final Inspection
Start: Fri 7/29/22 ID: 31
Finish: Fri 7/29/22 Dur: 1 day
Res:
Project Complete
Page 1
Project: Project2 Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Date: Tue 12/7/21
Page 2