Stonehaven Inc.: Prepared by FAS-34: Working Group AH1
Stonehaven Inc.: Prepared by FAS-34: Working Group AH1
Case Analysis
21F630 – G Manasa
Batch: 2021-23
Q1. For this part of analysis, consider each department in the Gdansk factory “in isolation” –
that is, when doing the calculations, imagine for the moment that the rest of the production
system has no impact on the department you are considering. For the purposes of
calculations, material handling times may be assumed to be negligible, and you can ignore
variability in processing times. Also, it can be assumed that the leather sheets are
simultaneously released to the three stamping machines in the cutting department. Please be
sure to show your work and state your assumptions.
a) For the typical 100-pair batch, what is the daily capacity and manufacturing lead time
(MLT) for a steady state process, within each of the following departments :(i) Cutting (ii)
Stitching (iii) Lasting?
b) If the batch were size were reduced to 40 pairs, what would be the daily capacity and
MLT for a steady state process, within each of the following departments: (i) Cutting (ii)
Stitching (iii) Lasting?
a)
Average manufacturing throughput time per batch= Batch cycle time= 148.72 minutes/batch
Cutting Cycle time (Batches/day): 17.27
WIP=1 batch
Average manufacturing throughput time per batch= Batch cycle time= 27.8 minutes/batch
WIP=20 batches
Q2. Now consider the factory as a system and take into account interactions between the
departments. Please be sure to show your work and state your assumptions.
a) Assuming production is done in 100-pair batches, what is the factory’s daily capacity?