1.nodes: Node Design Conditions/Parameters Drawings / References

This document provides design conditions and references for 6 nodes in a propane and butane system. Node 1 involves receiving propane from a ship into storage. Node 2 receives butane from a ship into separate storage. Nodes 3 and 4 describe transferring propane and butane respectively from the Hamriyah storage tanks to the Sajaa plant using pumps. Node 5 concerns a glycol water system used to heat the propane and butane. Node 6 covers importing boil off gas from the propane storage tank using a compressor system.

Uploaded by

NK
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
59 views

1.nodes: Node Design Conditions/Parameters Drawings / References

This document provides design conditions and references for 6 nodes in a propane and butane system. Node 1 involves receiving propane from a ship into storage. Node 2 receives butane from a ship into separate storage. Nodes 3 and 4 describe transferring propane and butane respectively from the Hamriyah storage tanks to the Sajaa plant using pumps. Node 5 concerns a glycol water system used to heat the propane and butane. Node 6 covers importing boil off gas from the propane storage tank using a compressor system.

Uploaded by

NK
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

1.

Nodes
Node Design Conditions/Parameters Drawings / References
1. Propane unloading from ship - To receive Propane from ship into Propane Design Pr.= 275 psig (Unloading Lines-Insulated), 263 psig (Unloading SNOC-3000-PF-PR-PID-2191
storage tank T-2902 using ship pump [Propane loading arm is used for Lines-Uninsulated), 150 psig (Loading arm), (-)50 / 700 mmWC SNOC-3000-PF-PR-PID-2164
unloading Propane from the ship] (Propane Storage Tank) SNOC-3000-PF-PR-PID-2186
Design Temp.= 140 F (Unloading Lines-Insulated), 185 F (Unloading
Lines-Uninsulated), (-)50 F (Loading arm), (-)53.6 F (Propane Storage
Tank)
Op. Pr.= 3.95 psig
Op. Temp.= (-) 41 F
2. Butane unloading from ship - To receive Butane from ship into Butane Design Pr.= 275 psig (Unloading Lines-Insulated), 263 psig (Unloading SNOC-3000-PF-PR-PID-2191
storage tank T-2102 using ship pump [Butane loading arm is used for Lines-Uninsulated), 150 psig (Loading arm), (-)50 / 700 mmWC SNOC-3000-PF-PR-PID-2164
unloading Butane from the ship] (Butane Storage Tank) SNOC-3000-PF-PR-PID-2185
Design Temp.= 140 F (Unloading Lines-Insulated), 185 F (Unloading
Lines-Uninsulated), (-)50 F (Loading arm), 10.8 F (Butane Storage
Tank)
Op. Pr.= 3.44 psig
Op. Temp.= 23.3 F
3. Propane backflow to Sajaa storage - Transfer [backflow] of Propane from T- Design Pr.= FV/570 psig (Pump Discharge), Propane Heater (Cold SNOC-3000-PF-PR-PID-2186
2902 at Hamriyah to T-1102L A/B/C at Sajaa plant using pumps P-9111 Side) SNOC-3000-PF-PR-PID-2164
A/B/C [3x50%] Design Temp.= -53.6 / 185 F (Pump Discharge, Propane Heater (Cold SNOC-3000-PF-PR-PID-2166
Side) SNOC-3000-PF-PR-PID-2168
SNOC-3000-PF-PR-PID-2171
Op. Pr.= 439.5 psig SNOC-3000-PF-PR-PID-2170
Op. Temp.= -44.96 F (Pump discharge), 41 F (Propane Heater Outlet) SNOC-3000-PF-PR-PID-2176
SNOC-3000-PF-PR-PID-2180
SNOC-3000-PF-PR-PID-2190
SNOC-3000-PF-PR-PID-2174
4. Butane backflow to Sajaa storage - Transfer [backflow] of Butane from T- Design Pr.= FV/350 psig (Pump Discharge), Butane Heater (Cold Side) SNOC-3000-PF-PR-PID-2185
2102 at Hamriyah to T-1002L A/B/C at Sajaa plant using pumps P-9101 Design Temp.= 10.4 / 185 F (Pump Discharge, Butane Heater (Cold SNOC-3000-PF-PR-PID-2164
A/B/C [3x50%] Side) SNOC-3000-PF-PR-PID-2165
SNOC-3000-PF-PR-PID-2167
Op. Pr.= 281 psig SNOC-3000-PF-PR-PID-2171
Op. Temp.= 21.3 F (Pump discharge), 41 F (Butane Heater Outlet) SNOC-3000-PF-PR-PID-2170
SNOC-3000-PF-PR-PID-2177
SNOC-3000-PF-PR-PID-2178
SNOC-3000-PF-PR-PID-2179
SNOC-3000-PF-PR-PID-2181
SNOC-3000-PF-PR-PID-2190
SNOC-3000-PF-PR-PID-2174
5. Glycol water system - To receive Glycol water in V-9121 glycol water vessel Design Pr.= FV/438.5 psig (Glycol Water Vessel), SNOC-3000-PF-PR-PID-2169
and to circulate it to Butane / Propane heaters using pumps P-9121A/B FV/524 psig (Glycol Water Pumps, Propane/Butane Heater (Hot Side), SNOC-3000-PF-PR-PID-2167
[2x100%]. Cold water from Butane / Propane heaters is heated up again Glycol Water Air Heater) SNOC-3000-PF-PR-PID-2168
using air heater E-9121 before returning to V-9121 SNOC-3000-PF-PR-PID-2174
Design Temp.= (-)20 F / 185 F (Glycol Water Vessel), (-)53.6 F / 185 F
Propane/Butane Heater (Hot Side), Glycol Water Air Heater

Op. Pr.= 66.7 psig (Pump Discharge)


Op. Temp.= 50 to 94.3 F (Pump discharge), (-)34.2 F to 10.2 F

1 of 3
Node Design Conditions/Parameters Drawings / References
(Propane Heater Outlet-Glycol), 25 F to 34 F (Butane Heater Outlet-
Glycol), 19.8 F to 64.6 F (Glycol Water air heater inlet), 40.3F to 94.1 F
(Glycol water Air heater outlet)

6. Import Propane BOG Compressor system - Propane circuit - To receive boil Design Pressure: SNOC-3000-PF-PR-PID-2186
off propane gas from T-2902 in suction of 2 stage BOG Compressor K- a. 85 psig (Propane Gas Purge drum), (Propane Product SNOC-3000-PF-PR-PID-2188
9310, compress and condense this propane and return the liquid propane to Chiller – 3-Tube Side) E003737-01-101 Sht 1 to 6/7
-T2902 SNOC-3000-PF-PR-PID-2190
b. 150 psig (Propane Product Chiller – 1/2/3 Shell Side)
c. 370 psig (Propane Product Chiller – 1/2-Tube Side)
Compressor Package
d. FV/450 psig (Suction Separator, Low Stage Compressor,
High Stage Compressor, Lube Oil Separator, Secondary Oil
Coalescer, BOG Condenser)
Design Temp:
e. (-) 50 F / 165 F (Propane Gas Purge drum), (Propane
Product Chiller – 3-Tube Side)
f. (-) 5 F / 165 F (Propane Product Chiller – 2 Shell Side)
g. (-) 45 F / 165 F (Propane Product Chiller – 3 Shell Side)
h. 10 F / 165 F (Propane Product Chiller – 1/2-Tube Side)
Compressor Package
i. (-20) F / 300 F (Suction Separator, Low Stage Compressor,
High Stage Compressor, Lube Oil Separator, Secondary Oil
Coalescer, BOG Condenser)

Op. Pr.= 344 psig (Propane Compressor Package outlet), 49.3 psig
(Propane Chiller 3 – tube side inlet)
Op. Temp.= 131 F (Compressor Package outlet), 18.5 F (Propane
Chiller 3 – tube side inlet), -58.1 F (To Propane Tank)
7. Import Butane BOG Compressor system - To receive boil off Butane gas Design Pressure: SNOC-3000-PF-PR-PID-2185
from T-2102 in suction of 2 stage BOG Compressor K-9210, compress and a. 85 psig (Butane Gas Purge drum), (Butane Product Chiller – SNOC-3000-PF-PR-PID-2187
condense this Butane and return the liquid propane to -T2102 2-Tube Side) E003737-02-101 Sht 1 to 5/6
SNOC-3000-PF-PR-PID-2190
b. 150 psig (Butane Product Chiller – 1/2 Shell Side)
c. 265 psig (Butane Product Chiller – 1-Tube Side)
Compressor Package
d. FV/225 psig (Suction Separator, Compressor, Lube Oil
Separator, Secondary Oil Coalescer, BOG Condenser)
Design Temp:
e. 10 F / 165 F (Butane Gas Purge drum), (Butane Product
Chiller – 2-Tube Side)
f. 165 F (Butane Product Chiller – 1 Shell Side, Tube Side)
g. (-)5 F / 165 F (Butane Product Chiller – 2 Shell Side)
h. 10 F / 165 F (Butane Product Chiller –2-Tube Side)

2 of 3
Node Design Conditions/Parameters Drawings / References
Compressor Package
i. (-20) F / 300 F (Suction Separator, Compressor, Lube Oil
Separator, Secondary Oil Coalescer, BOG Condenser)

Op. Pr.= 344 psig (Propane Compressor Package outlet), 49.3 psig
(Propane Chiller 3 – tube side inlet)
Op. Temp.= 131 F (Compressor Package outlet), 51.4 F (Butane
Chiller 2 – tube side inlet), 16.8 F (To Butane Tank)

3 of 3