NGCP - Procedures and Requirements For Energy Projects

Download as pdf or txt
Download as pdf or txt
You are on page 1of 17

DOE Energy Investment Forum

04 December 2015
Hotel Intercontinental, Makati City
Stronger transmission
for a stronger nation.

1. Procedures and Requirements


for Energy Projects

2. Transmission Development Plan


for Luzon Grid
Stronger transmission
for a stronger nation.
‰ The Philippine Grid Code provides, among others,-
• “..Grid Owner shall establish the procedure for the
processing of applications for connection ….”
• “..Grid Owner may disapprove an application for
connection…. if such will result in the Degradation
of the Grid”.

‰ The Open Access Transmission Service (OATS) Rules


mandates “..Transmission Provider and Prospective
Transmission Customer to comply with the processes
set out … for processing of new or modified
connection arrangement”

‰ ERC Resolution No. 16-2011, a Resolution Amending


the Definition and Boundaries of Connection Assets
Stronger transmission
for a stronger nation.

Application System Impact Study Facilities Study

• DOE clearance to • Conduct of • Conduct of


conduct of System System Impact Facilities Study
Impact Study Study (SIS) is
required

a. Letter of Intent a. SLD Facilities required at the


b. DOE Clearance b. Connection Scheme Connection per Module
c. Plant details c. Line and HV B18.3 of the OATS Rules.
d. Target commission equipment
date parameters Execution of Connection
e. Connection scheme d. Generator modelling Agreement within 30 days
parameters per B16 of the OATS Rules.
Stronger transmission
for a stronger nation.

Construction Pre-energization Readiness

• Connection • Conduct of Field • Customer to


Asset by the Tests issue “Statement
Customer • Submission of of Readiness to
• Required Grid Requirements Connect”
Upgrading prior to Pre- • Submission of
commissioning Evaluation
Request Form

Generator to follow Article Execution of Service


4.4 of the PGC and Section Agreement
B11 of the OATS Rules.
Other commercial
NGCP to undertake the compliance/s
requirements of Article 4.6
Stronger transmission
for a stronger nation.

Provisional
Final Approval to
Approval to Mandatory Tests
Connect
Connect
• NGCP to grant • Unit Capability • NGCP to issue
“Certification of Tests Certification of
Provisional Final Approval to
Approval to connect.
Connect”

Non-compliances may Conduct of on-line and


be allowed for minor off-line tests with NGCP
equipment only. as witness
Stronger transmission
for a stronger nation.

Connection Agreement
Service Agreements
Transmission Service Agreement
with NGCP
Metering Service Agreement

Compliances, • Technical requirements should be complied by the


Testing and proponent prior connection of power plant.
• Documentary requirements and compliances:
Commissioning
• Approved Energization Request Form
• Statement of Readiness to Connect
• Certificate of Technical Requirements Compliance
• Certificate of Provisonal/Final Approval to Connect
• Annex A 2.10 of the OATS Rule: Requirements as Generator
Commercial Customer shall be complied by the Transmission Customer
Operation 30 days before energization.

SIS and FS should have been completed at this time.


Stronger transmission
for a stronger nation.

TRANSMISSION CONNECTION ASSET (INCLUSION)


• Power Circuit Breaker, Surge Arrester, Disconnect Switch
including Protective Relays, Breaker Failure Relay and any other
multifunction protective devices and equipment.

TRANSMISSION CONNECTION ASSET (EXCLUSION)


• Communication equipment, SCADA and other equipment used
by the System Operator
• Meters and Metering Equipment for the Supply and Metering
Services
• Step-down transformer within the Grid
• Any transmission line
• Contributed Asset
Stronger transmission
g nation.
for a stronger

Power Delivery System Operator Metering Service


Service (PDS), (SO), Php/kW- Provider (MSP)
Php/kW-month month • Common Metering Charge -
• Recovers cost of conveying • Recovers cost of services cost of metering software,
electricity to or from the Grid by SO (e.g. communication, hardware, and related costs.
SCADA) to ensure safety, Uniform rate per meter.
• One rate per grid
power quality, stability, • Full Metering/ Meter Only
reliability and security of Charge- cost of metering
the Grid facilities. Different rate per
• P/kW rate approved delivery voltage and
annually by ERC ownership of CTs and PTs.

9
Stronger transmission
for a stronger nation.

• Ten 10-year program for


Major expansion,

VOL 1
reinforcement, and
Network
rehabilitation of the
Development Transmission System

Operations &
• Annually updated and
Maintenance

VOL 2
submitted to DOE for
approval and
Metering integration to its PDP
and PEP

System
VOL 3 • Reference plan for
Operations NGCP’s CAPEX
application with the
ERC for approval
Stronger transmission
for a stronger nation.

1. Receive Inputs from the DOE


a. System Peak Demand
Forecast 4. Presentation of the
b. Generation Capacity Addition Proposed TDP to
Line-up stakeholders
DOE, TransCo, GMC, PEMC,
DUs, GenCos and other
2. Coordination with Customers customers/stakeholders
and other Stakeholders

5. Submission of the TDP Final


3. Preparation of the TDP
Report to the DOE
Updating the system
requirements for the next ten
(10) years
Planning criteria based on Phil Grid Code
Stronger transmission
for a stronger nation.

1. Load growth

2. Generation Entry

3. Congestion Alleviation

4. System Reliability

5. Power Quality

6. Island Interconnection
ERC-Approved Projects Completed

San Esteban-Laoag, 230 kV T/L, Legend:


120km, 300MVA, 2015
500 kV
230 kV
Capacity additions to the existing
substations: 115 kV
• Laoag 69 kV
• Bantay
• San Esteban
• La Trinidad
• Bayombong
• Botolan
• Limay
• Concepcion
• Mexico
• Cabanatuan
• San Rafael
• San Jose
• Dasmariñas
• Batangas
• Tayabas
• Labo
• Naga Lumban – Bay, 230 kV T/L,
• Daraga 40km, 1200MVA, 2015
ERC-Approved Projects Ongoing

Tuguegarao – Lal-lo, 230 kV T/L,


64km, 300MVA, 2018 *
Legend:

500 kV
Santiago – Tuguegarao, 230 kV T/L, 230 kV
118km, 300MVA, 2017
Ongoing capacity additions and 115 kV
new substations:
69 kV
• La Trinidad
• Ambuklao
• Binga Ambuklao – Binga – San Manuel, 230 kV T/L,
• Balingaeo (new) 51km, 1100MVA, 2018
• San Manuel
• Santiago
• Gamu
• Tuguegarao
• Antipolo (new)
• Batangas
• Gamu

Calaca – Dasmariñas, 500 kV T/L,


58km, 4704MVA, 2019 *

* Provisional Approval for advance


implementation
Proposed Projects Legend:
North Luzon 230 kV
Loop, 160km, 500 kV
300MVA, 2023 230 kV
115 kV
69 kV
La Trinidad – Sagada –
San Esteban, 230kV T/L,
142km, 600MVA, 2024

Nagsaag-Santiago, 500 kV T/L,


140km, 2850MVA, 2022
Western 500 kV Backbone
– Stage 2, 174km,
2850MVA, 2030

Hermosa – San Jose, 500 kV


T/L, 82km, 4704MVA, 2019
Alaminos – Taguig, 500 kV T/L,
Mariveles – Hermosa, 500 kV 73km, 2850MVA, 2025
T/L, 55km, 4704MVA, 2019

Pagbilao EHV S/S,


Bataan-MM/Cavite Submarine
Option 1 – 230 kV to Pasay 3000MVA, 2017
Option 2 – 500 kV to Dasmariñas

Batangas-Mindoro Interconnection Project,


230 kV T/L, 48km (OH), 25km (submarine),
300MVA, 2022
SAN JOSE
Proposed Projects
New Substations for
MARILAO Metro Manila
• Navotas
CAMARIN
• Pasay
• Marilao
• Camarin
SAN MATEO • San Mateo
• Antipolo
• FBGC
QUEZON • Taguig
NAVOTAS ANTIPOLO
DOÑA IMELDA

PACO TAYTAY

PASAY
FBGC

TAGUIG
TAGU
TAG IG EHV
GU
Option 1 – 230 kV to Pasay
Option 2 – 500 kV to Dasmariñas

LAS PIÑAS
Legend:
MUNTINLUPA 500 kV
230 kV
Stronger transmission
for a stronger nation.

End of Presentation