0% found this document useful (0 votes)
84 views63 pages

A Guide To Primavera P6 Global & Project Data

This document provides information about global and project data in Primavera P6. It explains that Primavera P6 was designed as an enterprise project management system, even if it is used as a standalone tool. There is both global data, which can be shared across multiple projects, and project (embedded) data, which exists only within a single project. Global objects are linked to projects rather than embedded within them. The document discusses how global objects are included when exporting projects as .xer files, which can sometimes cause issues when importing files. It also provides examples of global versus project objects such as calendars and activity codes.

Uploaded by

Ahmed Sassi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
84 views63 pages

A Guide To Primavera P6 Global & Project Data

This document provides information about global and project data in Primavera P6. It explains that Primavera P6 was designed as an enterprise project management system, even if it is used as a standalone tool. There is both global data, which can be shared across multiple projects, and project (embedded) data, which exists only within a single project. Global objects are linked to projects rather than embedded within them. The document discusses how global objects are included when exporting projects as .xer files, which can sometimes cause issues when importing files. It also provides examples of global versus project objects such as calendars and activity codes.

Uploaded by

Ahmed Sassi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 63

A Guide to Primavera P6 Global &

Project Data
I‟ve always had difficulty explaining the concept of global and project
data to new users of Primavera P6 in my training courses. It‟s a bit too
much for some, and why should you even care? You seem to be able
to use Primavera P6 just fine without any knowledge of Global or
Project Data.

You can, but you can also get into trouble once you start moving data
around, especially back and forth between databases. If you‟ve
ever sent or received a Primavera P6 .xer file then this guide is for you.
It will help you to make sure your Primavera P6 project data is making
it to it‟s destination when you send a file. But it‟s also good knowledge
to have for any user of Primavera P6 Professional or EPPM.

Primavera P6 Global & Project Data


It‟s important to remember that Primavera P6 was initially designed as
an Enterprise project management system. Even though many of us
use Primavera P6 as a standalone tool, shunning all of the enterprise
bells and whistles, at it‟s core is a database initially designed for the
enterprise‟s needs. If Primavera P6 was truly a standalone tool, you‟d
find it to resemble a tool like Microsoft Project, where you deal with
files only and projects don‟t share data between them.

Primavera P6, both the Professional version and EPPM, have a more
complex data structure that enables them to be in the realm of
Enterprise software tools. The goal was to design a system that could
be used by an organization‟s many departments. So it would have to
be flexible enough to be configurable for each department‟s needs. But
also, the organization would want some over-arching corporate assets
that could be set up and available to any department.
With Primavera P6, a primary enterprise distinction is that we have this
concept of “Global” data objects and “Project” (or embedded) data
objects.

If you consider that any company that sets up Primavera P6 will want
to reuse and share data objects across their P6 projects, then you
have just revealed the difference between global and project objects.
Global objects can be shared and used on more than one project,
while embedded objects cannot.

Primavera’s Global Objects Are Linked And Not


Embedded in Projects
Going a bit deeper, we encounter how global data objects are actually
shared by multiple projects – it‟s a concept I call “linking”. By the
way, these concepts exist everywhere in databases, and are not
unique to Primavera P6….just sayin‟.

Global objects are P6 constructs that are used on or linked in to a


project, but never wholly become part of the project. For example,
a global Calendar exists in P6‟s database where it can be shared and
used on multiple projects. Thus, a global Calendar gets linked to a
project and used on Activities in that project, but the Calendar never
becomes wholly owned by the project nor is it embedded inside the
project.

The same concept always applies to Resources. A Resource can be


assigned to a project‟s activities, but the Resource (and it‟s associated
attributes, like Price/Unit hourly rate) are never embedded into a
project. That same resource can always be assigned to the activities of
another project at the same time, applying the linking concept or the
sharing of resources across projects.

When you start to thing about all of the many global objects that can be
linked to a large project, the list starts to look like this:

 Global Calendars
 Cost Accounts
 Global Activity Codes
 Project Codes
 Resources
 Roles
 Shift Calendar
 User Defined Fields
 etc.

Qualities of global objects is summarized in this list :

 global objects can be used on the activities of multiple projects.


 global objects exist outside of all projects.
 global objects are not deleted when their associated project(s) are
deleted.
 global objects can be left out during an import process.
It‟s import to understand Primavera P6‟s innate data linking concept
because it comes into play in a major way when you export and import
projects through .xer files. More on that soon.

What is An Embedded (Project) Object?


Some of the data objects in the list above can also be created as a
“Project” object. Let‟s look at Calendars again. A Calendar in P6 can
be created either as a Global Calendar (shareable on other projects) or
a Project Calendar, which then becomes embedded inside the project
you use it on. Project Calendars can‟t be shared or used on other
projects. No embedded object can.

Other examples include Project Layouts or Activity Codes. Here again,


you have the option to create either a Global Activity Code, or a Project
Activity Code.

Embedded object are wholly owned by the project. Embedded objects


in a project has these qualities:

 embedded objects cannot be used or linked to another project‟s


activities.
 embedded objects exists only inside the project and can be edited
only when the project is open.
 embedded objects are deleted along with the project.
 embedded objects are always imported with the project and
cannot be left out.

Exporting and Importing Primavera P6 Global


Objects
This where things can get messy.

If I want to export a project to an .xer or .xml file, and ensure you have
a complete record of the project, then during the export, all the bits of
linked Global objects have to come along for the ride. And that‟s why
happens. Included inside the .xer/.xml file are all of the Global
Resources, Calendars, Activity Codes, Cost Accounts, etc. that are
used in the project. So we now have a combination of Global data
objects and Project data objects in the same file. This isn‟t really a
problem on its own, as during the export this all happens automatically
and there is no way to alter what data goes into an export file from
Primavera P6 Professional.

However, it‟s on the importing of data from a .xer or .xml file that many
users usually run into trouble.
10 Primavera P6 Layouts You Must
Implement
It can get difficult to analyze the mountain of schedules you‟re
responsible for and our good friend Jerome Ijachi Odeh has recently
pulled together a list of 10 Must-Have Primavera P6 Layouts….ones
you probably should be using everyday.

So to help you take advantage of P6‟s powerful layout features


(like these ones we‟ve already told you about), here is a little sneak peek of
10 must-have Primavera P6 layouts you should be using in Primavera
P6 with the simple Grouping, Sorting, Filter and Column tools…since,
like yesterday. So let‟s get started!

Oh, and don‟t worry – we‟ll show you how to build each P6 layout step-
by-step.

Layout 1: Developing Schedules


For starters, when building a new schedule, make sure to use the
layout below to have all the key fields clearly visible and easy to
find. The Relationship tab in the Details pane is vital because it‟s used
to add logic relationships between activities in the schedule.

This layout is grouped by WBS and sorted by Activity ID.


Here is how to build the Layout:

1. Grouping

2. Sorting
3. Filter

No filter is applied in this layout so that all activities are displayed.

4. Columns

Layout 2: Analyzing Calendars


You need to make sure the right calendars are assigned to activities
when working with schedules because of the effect of calendars on
Total Float calculations and Activity Dates.

The layout used for analyzing calendars is grouped by Calendar


>WBS and sorted by Calendar as you can see below.

Here is how to build the Layout:

1. Grouping
2. Sorting

3. Filters

No filter is applied in this layout so that all activities are displayed.

4. Columns
Layout 3: Analysing Constraints
Constraints are mainly used for the Project Start milestones,
contractual milestones and external milestones. When reviewing
schedules from contractors make sure to check the constraints applied
in the schedule to ensure that constraints are not been used in place of
schedule logic to drive dates.

The layout used for analyzing constraints is grouped by Primary


Constraints >WBS and sorted by Activity ID as you can see below.
Here is how to build the Layout:
1. Grouping

2. Sorting
3. Filter

No filter is applied in this layout so that all activities are displayed.

4. Columns
11 Ways to Build a Cringe-
Worthy Primavera P6 Schedule

1. Link Only Half of Your Activities Together


Imagine trying to send an email from a computer that is not connected
to the network. Nowadays, if it‟s not connected, your PC isn‟t doing
much good. Now imagine a project schedule with 450 activities that
have no predecessor or successor relationships. Same idea.

A project schedule is really just a network of interconnected tasks put


into a thoughtful order of execution. Without the relationships, you
don‟t have a network. And you don‟t have an accurate Critical Path as
there is no path to an activity with missing relationships (or perhaps no
path from an activity if we‟re talking about open ends).

Here’s how to fix it.


Leave no activity un-linked. That is, any activity that is a workable task
should have a predecessor and a successor. The only exceptions are
the project‟s first and last activities.

2. Don’t bother with Milestones


I don‟t know about you, but one of the very first things I look for when
I‟m shown a schedule are the milestones. It‟s the easiest way to get a
sense for major deadlines and startups. So when I don‟t see any, I get
confused and quick. Now think about the owner, client or project
sponsor. Milestones are a necessity for tracking to major deliverables,
the beginning or end of a project phase, or major events like materials
showing up or approvals.

How to fix it.


Pick out the big dates in your schedule and use P6‟s “Start Milestone”
or “Finish Milestone” activity type to highlight those events in your
project.

3. Being Vague Is Best


If you‟re really going for a project that‟s vague and ambiguous, then
you should consider using lots of one-word activity names to add some
mystery to what your crew is working on. Try some of
these descriptions:

 EC2030 – Fix
 M5860 – ASCMAC 24
 C3100 – Excavate

Maybe “Excavate” makes perfect sense in the context of that activity


being under the WBS element “Area 3, West end (10+320 to
10+430)”. But if you ever use P6‟s tools to regroup, filter or sort, you
may not always see the WBS, leaving that activity to any number of
interpretations you don‟t have time to consider.
Using too many abbreviations can have the same effect. Sometimes
more is best. Maybe your client doesn‟t know that “ASCMAC” stands
for Aluminized Corrugated Steel Metal Arch Culvert. (but maybe you
don‟t want to type it out 90 times either….I know. Typing can suck. Tip
below.)

Here’s how to fix it.


Be clear in your activity descriptions. Include a well-defined action on
ALL activities, and a location if you are repeating the same work
elsewhere. We‟ve already given you some tips on this. Spelling
counts! TIP: Don‟t forget about P6‟s “Find & Replace” feature. You can
use the CTRL+R key combo in the Activity Name column to replace an
abbreviation with a longer description throughout your schedule in a
few seconds.

4. Cost-Load Non-Resource Costs with


Resources
Why would you create a resource called “Cash” or “Interest” and
assign it to your activities? This is some sort of workaround that
sounds painful and confusing. It‟s true -P6 does not always shine when
it comes to managing costs, but some of the resources I‟ve seen are
just weird….like “Travel”.

Here’s how to fix it.


Stick to letting resources be resources. Use the Expenses area / tab to
track any fixed costs that are not resource related. If you need more
firepower, then I would recommend doing it right with a package like
Ares Prism or just plain old Excel.

5. Increment Activity IDs by 1’s


For those of you who know even a little about Primavera P6, you‟ll
probably remember the familiar ID numbering sequence “A1000,
A1010, A1020, A1030…etc.” It‟s pretty much accepted that a P6
schedule will increment by 10‟s to allow space to add extra activities
with numbers that fit in-between – A1015 for example.
No way to add activities in-between
When you increment by 1‟s, then you‟ve created a numbering system
that won‟t allow you to add activities in-between. So if you ever have to
add an activity into the sequence, you‟re going to rely on renumbering
ALL of your activities, which takes time and can be messy. Now some
of you just want P6 to work like Microsoft Project which automatically
renumbers when you add activities in-between. Sorry, we‟re all waiting
for that one.

The Fix.
Make sure to set your Activity ID numbering sequence on the Defaults
tab of your project to increment by 5‟s, 10‟s or 20‟s. 10‟s is the most
common setup. If your project is already built on a sequence
incremented by 1‟s or 2‟s, then highlight your Activities, right-click and
pick “Renumber Activity IDs” from the menu to renumber everything
properly. NOTE: this feature is present in versions 7 of Primavera P6
or later.

6. Go Activity Constraints Crazy


P6 is a scheduling engine, but some of us don‟t like to give the
software the control to schedule our work. It‟s a trust issue. Those
people usually go for the comfort of mass Activity Constraints to force
Activities to start or end on the best dates.

So why
bother with relationships if you plan to simply force every Activity to a
set of dates? Constraining %50 of your Activities seems to be an
effective way to get the dates you want….but it will cost you in the end.
With too many constraints, you lose the fluidity of the logic
dependencies (or maybe you didn‟t bother with logic in the first place).

How to fix it.


Let Primavera P6 do the scheduling for you. You set the following:

 Project Start Date


 Activities with duration estimates
 Order of execution (by adding relationships)

And once you hit F9 to schedule your project, P6 will calculate a start
and finish date for each activity. It‟s why you bought P6 in the first
place.

7. Calendars – Make Sure To Use Many


They say the more, the merrier! To get really merry, make sure to use
a lot of different Calendars throughout your project schedule. If you
have enough trouble with the equation “TF = LS – ES” then ensuring to
use multiple calendars will make your head spin when trying to figure
out why your Total Float values are off the chart. For example, you‟d
think Activity A below, would be on the Critical Path.

How to fix it.


Keep it simple and stick to 1 Project Calendar throughout your
schedule. Not practical? Then prepare for strange Total Float values in
your schedule. There are rumours that P6‟s Total Float calculations are
wrong in some instances where multiple calendars are used. We‟re
working on validating. Leave us a comment if you can help.
8. Use Some Loco Logic
I know you can sometimes make dates line up perfectly if you use
nothing but Start-to-Finish relationships and negative lags. But it
doesn‟t mean you should. Although there are 4 relationship types,
don‟t go loco trying to make sure you use them all in equal
parts. Things will get messy and your Critical Path will be where it
should. Keep it simple with good „old Finish-to-Start as much as
possible. The same applies to lags. We already know that lags and
leads are not clearly visible in schedules (although we‟ve showed you
how to find lag in your schedule), and they are often poorly
documented. Sometimes they are even misused to chew up float.

The fix.
Avoid all of those crazy logic options and stick to using Finish-to-Start
relationships with 0 lag or lead time. If you do, you will have the
cleanest Critical Path possible, assuming you‟re not guilty of #1 above
and are linking everything together.

9. Update Progress Here, There, and Everywhere


It‟s Tuesday at 1pm – progress update time! The same for next Friday
but only at 10am.

Timeliness not your thing? Details and decimal….meh.

Maybe you project controls is not for you, or at the meticulous process
of updating a schedule with progress. If your updates are sporadic and
spasmodic your project is going to suffer from giving everyone a major
headache and also from uncertainly of how much work has been done.

How to fix it.


Like the changing of the guard, you need to follow a consistent and
disciplined process to properly update your project. Pick a time and
update your project at that time every week (2-weeks / month).
Scrutinize every activity that was to be done and don‟t leave any out.
Primavera will push forward any work that wasn‟t done as planned. Be
impeccable in your updating.
10. Muck With The Bar Colors
Why are Critical Activities puce? (whatever puce is)

It‟s fun to tinker. And


man, can you make some ugly Gantt charts using the extensive
options provided in Primavera P6. But please don‟t.

How To Put It Back


Those standard P6 colors are so ingrained that changing them might
cause a riot. Find a layout that has the standard colors and use it.
Stay safe kids.
What are Level of Effort Activities for?
You might already know that Level of Effort activities are designed to
represent support work on a project. This is work that does not
contribute directly to the deliverables or outcome of the project, but
supports their progress. These are still important tasks, even critical to
the project, but are defined as supportive.

Examples of Level of Effort activities include:

 Customer Meetings
 Project Management tasks
 Maintenance of equipment
 Clerical work

These activities don‟t “earn” us much from an earned value


perspective. In Earned Value Management, any supportive-type Level
of Effort tasks are called “non-discrete” – which means that
measurement of these tasks is harder than say measuring a task to
install 12 lamp-posts.

How much project management did you do? VS. How many lamp
posts did you install?

You can see what the Defence Contract Management Agency has to
say about discrete tasks versus Level of Effort tasks and how they
relate to earned value.

As one Linkedin member recently commented “…if I cannot see it,


touch it, bump my hard hat on it or fall into it….it gives you NO
progress.“ And Level of Effort activities, in describing supportive-type
work, fall into that bucket.

What does Level of Effort mean?


The term Level of Effort could be reworded as – “to level out effort” OR
“to spread out the work”.

Since a Level Effort activity in Primavera P6 “summarizes” other


discrete activities, it spans the duration of multiple consecutive
activities, the result is similar to spreading out work over the duration of
those activities.
Level Of Effort – “to level out effort” OR “to spread out the work”.

Can Level of Effort Activities be on the


Critical Path?
No. Level of Effort Activities should not appear on the Critical Path, nor
should they add any duration to the project.

How do I use Level of Effort Activities


in Primavera P6?
If you add a Level of Effort Activity in Primavera P6, it‟s most likely
because you want to track a resource and their time on a support task.

Level of Effort activities get their dates and durations from their
predecessors and successors. It‟s most common to assign a
predecessor with an SS relationship and a successor with an FF
relationship (however you aren‟t limited to those as in P3‟s
hammocks”). Then you assign a resource to the activity and his/her
effort is will be spread over the activity‟s duration.
How is a Level of Effort Activity’s
Duration calculated in Primavera P6?
The Level of Effort Activity gets it‟s start date from the Early Start date
of it‟s predecessor. It gets it‟s finish date from the Early Finish of it‟s
successor. Then it‟s own calendar is used to calculate the duration
between the start and finish dates.

All of this happens when you reschedule your project. After you
reschedule, the Level of Effort‟s duration will be calculated.

Of course, if any of the activities that a Level of Effort summarizes has


a change of duration, then after rescheduling P6 will calculate a new
duration for your Level of Effort.

How do I show my Level of Effort


Activities on the Gantt Chart? My Level
of Effort bars are not showing on the
Gantt Chart.
Simple, you‟ll just need to adjust the Gantt Bars settings in Primavera
P6. Right-click on the Gantt Chart, select Bars. Check on any entry
that is called “Remaining Level of Effort”. If you don‟t have an entry like
that, then go ahead and add one using the Add button. Set the
parameters a shown below. Make sure to set the Bar style as well.

Wrap-Up
Level of Effort activities are an essential component in building
complete schedules, for displaying and representing supportive, non-
discrete work. Make sure you familiar with them but don‟t overuse
them. Like most things in planning and scheduling, a little goes a long
way.
5 Tips to Improve Your Primavera P6
Activity Names
Newer versions of Primavera P6 and beyond allow many more
characters in the activity description field. Follow these 5 simple tips to
improve the overall quality of your schedule network and respective
activity descriptions.

1. Use an action word.


When adding an activity description you always want to add an action
word first. For construction related activities consider such words as
install, construct, place, or fabricate. For Engineering use action words
such as develop, issue, or incorporate. Make sure you follow the action
by the activity to be performed.

For example: “Install Lower Base Slab”.

2. Don’t abbreviate unless you absolutely have


to.
When developing your activity descriptions do your best to spell out
what you are trying to say.

For example instead of

“FREP lwr fndn concrete”

try

“Form, Rebar, Embed & Place lower foundation concrete.”

The more abbreviations your schedule contains, the greater potential


for confusion, particularly for those unfamiliar with the schedule or your
naming conventions.

3. Be descriptive!
The activity description needs to be as descriptive and detailed as
possible. For construction activities consider adding the location,
utilizing column references, direction, room numbers, and floor
elevation.

Example: “Install North Lower Base Slab Col 1 – Col 5, Floor 1”.

This type of description will give your reader vital information about
where this activity is physically located. Always assume that your
reader will not be using your code grouping & sorting when reading
yours schedule. Make sure each activity can stand on its own without
any coding headers.

4. Uniformity
Developing standard activity descriptions, similar to activity IDs, will
help standardize your schedule. Try to come up with a standard
structure that can be conveyed to the entire planning team. This is
especially good practice when working with multiple users in the same
program.

An example for an engineering schedule could be “*Action Word* –


*Deliverable* – *System*”. Below are some other examples to help
keep uniformity in the schedule.

Use the <Action Word> – <Deliverable> – <System> template.

1). Develop Mechanical Data Sheet – Horizontal Pump

2). Issue Piping Isometrics (Dwg #) – Cooling Water System

3). Issue RFQ (PO #) – Horizontal Pump

4). Award Purchase Order (PO #) – Horizontal Pump

5. Don’t scream!
THERE IS NO NEED FOR ALL OF YOUR ACTIVITIES
DESCRIPTIONS TO BE CAPTILIZED! For some reason there are
several planners that prefer to work in all-caps. Do us all a favor and
please turn the caps lock off. There is no need to scream and it adds
no value to the final product.
Schedule % Complete in Oracle
Primavera
Schedule % Complete is one of the many percent completes you have
in Primavera P6 and we‟re going to have a complete look at what it is
and how it is calculated. Two important products of maintaining
schedules are planned progress and actual progress of a given time;
you want to know how much you‟ve done so far and compare it with
how much you were supposed to do so far, in order to reach project
targets.

The first thing to mention is that Schedule % Complete deals with


planned progress. As a result, it is calculated based on the Project
Baseline and the Data Date; it has nothing to do with the current
schedule.

The second thing is that this field is calculated differently for Activities
than for WBS Elements. This is the source of the most common
problems people have with this field.

Schedule % Complete for Activities


And now, let‟s start the story with how Schedule % Complete is
calculated for Activities. It‟s simple; just take a look at the following
figure.

When the Data Date is earlier than the Baseline Start date, Schedule
% Complete is zero, when it‟s after the Baseline Finish data, Schedule
% Complete is 100%. Otherwise, Schedule % Complete would show
what percentage of the Baseline duration is passed by the Data Date.
Here‟s a formula to calculate Activity Schedule % Complete:

Schedule % Complete(Act) = ( [Data Date] – [Baseline


Start] ) / ( [Baseline Finish] – [Baseline Start] )

The following diagram shows the Schedule % Complete of a single


Activity for different Data Dates:

And that‟s all for the activities; it has nothing to do with the current
schedule, the resource curves, the costs, etc. For Activities, Schedule
% Complete is strictly calculated based on:

1. Data Date
2. Activity‟s Baseline Start
3. Activity‟s Baseline Finish

Schedule % Complete for WBS


Elements
And now, the story of how Schedule % Complete is calculated for WBS
Elements. Let‟s start by reviewing 2 possible scenarios:

Scenario 1
How are these calculations possible? The Sample WBS Element has
three Activities, they all have Schedule % Completes greater than
zero, but the value for Sample WBS Element is 0! Before I reveal the
answer, here‟s a contrasting scenario.

Scenario 2

In this scenario, the Sample WBS Element has three Activities with
Schedule % Completes less than 50%, but the Schedule % Complete
of the WBS Element is 75%.

What is going on here? How is Schedule % Complete calculated in


each scenario?

A WBS Element‟s Schedule % Complete is calculated in a completely


different way. You might expect it to be the rollup value of the
underlying Activities (a weighted average for example). But, as in
scenario 2, the three Activity values which are all less than 50% could
never have a weighted average more than 50%.

As you saw before, the Schedule % Complete of the Activities is time-


based. However Schedule % Complete for WBS Elements is:

1. Depended project costs and…


2. Does not factor in any Activities‟ Schedule % Complete values

How Schedule % Complete is


Calculated for WBS Elements
When you assign resources and expenses to activities, each activity
will receive a calculated Total Cost. Resource assignment hours and
costs are, by default, spread uniformly over the duration of the activity
(but you may apply a Resource Curve to alter this). Oracle Primavera
will show you how costs are then planned for each day of the Activity.
These costs are aggregated to the WBS level, and the time-phased
cost of the WBS Element will be calculated automatically.

The Schedule %
Complete of the WBS Element will be the ratio of the Baseline Costs
before the Data Date to the Total Baseline Cost.
In the world of Earned Value, the costs before the Data Date are called
the Planned Value, or PV for short (Also called BCWS – Budgeted
Cost of Work Scheduled). The total baseline cost is called Budget At
Completion or BAC for short. We can now formulate the calculation of
Schedule % Complete for WBS Elements as:
Schedule % Completed (WBS) = PV / BAC
Please have this in mind that all the mentioned parameters are derived
from baseline and not from current schedule; the WBS bar shown in
these figures is the baseline schedule of the WBS Element and the
costs are the baseline costs of the WBS Element.

The following diagram shows Schedule % Complete of a sample WBS


Element for different Data Dates:
The above descriptions show that the Schedule % Complete of the
WBS Elements depend on the following:

1. Data Date
2. Baseline Costs before the Data Date (PV)
3. Total Baseline Costs (BAC)

To summarize, Schedule % Complete for Activities is based on time,


while its value for WBS Elements is based on costs.

Pulling Schedule % Complete together


for WBS and Activities
The following diagram shows Schedule % Complete of a sample WBS
Element with two Activities in different Data Dates.
The Proper Setup : Baselined and Cost-
loaded
Now let‟s see how Schedule % Complete works in action on a sample
Primavera P6 plan.

Since Schedule % Complete is based on both Project Baseline fields


and Earned Value Cost fields, to calculate it properly, your schedule
should:

 be cost-loaded at the Activity-level


 have a project baseline set

Examine the sample plan below. This plan has four WBS Elements in
two levels and seven Activities. Activities have sample durations and
relationships and you can see the current schedule in the Gantt chart.
Each Activity has a resource assignment and that‟s why we have costs
in the plan. Some Activities have uniform resource curves, while others
use At-Start, At-Finish or Bell-Shaped resource curves.
The project baseline is maintained and assigned. The baseline
schedule is shown by the yellow bars in Gantt chart. The current
schedule and the baseline are the same now.

Examining Schedule % Complete for


Activities
I will reschedule the plan for the second day, moving the Data Date
forward 1 day.
There are no actuals entered, but as we saw in Part 1, Schedule %
Complete has nothing to do with the current schedule or actual
data. The Schedule % Complete column shows the current values; for
example, take a look at A4:
The Data Date has passed half of the baseline schedule of A4, which
would be the Schedule % Complete of 50%.

Sometimes you have nonworking days in the schedule; in this cases,


those days would not be counted in passed and total baseline days (as
usual).
Schedule % Complete for WBS
Let‟s examine WBS E-2.

WBS E-2 has the following values:

 PV (Planned Value Cost column) = $240


 BAC (BL Project Total Cost column) = $400

The WBS Schedule % Complete is calculated as PV / BAC = $240 /


$400, or 60%.

How BAC and PV are calculated for


WBS?
1. BAC – Budget at Completion
BAC for the WBS Element E2 is the sum of the A6 and A7
BACs. Think of this as the sum of the Total Cost for each Activity (see
diagram above) but taken from the project baseline.

2. PV – Planned Value
Planned Value (PV) is bit trickier as it related to how your schedule is
cost-loaded in a time-phased manner.

The Activity Usage Spreadsheet, shown in bottom half of the screen


below, is handy for analysing planned value for Activities.
The bottom layout is set to show timephased values of
the Cumulative Planned Value Costs using the Activity Usage
Spreadsheet. Why use the Cumulative Planned Value Cost
field? Because it‟s essentially a running total. With that in mind, in this
view we can quickly see a running total PV for the WBS at any day in
the project.

Planned Value….elaborated
Planned Value taked into account Resource Curves. Let‟s explore
Activity A6.

A6 has a uniform curve and it has only two working days, $80 planned
for each one. $80 for the first day, and the cumulative value remains
80$ for the next two nonworking days, then increases to $160 in the
last day.

ActivityA7 has an “At Start” resource curve assigned. All of A7‟s


planned cost will be loaded to the first day and the cumulative value of
the next days would be the same.
No matter how the Activity planned values are distributed over time,
the WBS‟s planned values are the total of the Activities‟ planned
values.
The Data Date in the previous sample was the second day of the
project and PV of the last WBS Element is 240$ in that day. If we
change the Data Date to the sixth day, its PV would be $320. The
following figure shows the values with the Data Date set to day six of
the project.

When Things Don’t Add Up – A


Scenario using Resource Curves
Before wrapping up, let‟s look at a tricky scenario; I made some
changes and re-baselined the schedule. Check the values for WBS
E.1.1.
As you see, WBS E.1.1 and all of her underlying Activities have
costs. Two Activities have Schedule % Complete values that are
greater than zero and the WBS Element‟s value is still zero. Why?

I believe you can say; when Schedule % Complete of the WBS


Element is zero, you should expect that the PV is also zero. How is it
possible for the PV to be zero when Data Date has passed half of the
baseline duration? The answer is simple: the Activity costs are not
uniform…. because of Resource Curves.
All of these three activities‟ costs have “At Finish” curve. The following
figure is focused on the A2:
Many planners use Resource Curves in their schedules to properly
distribute labor hours and costs across an activity‟s duration. But keep
in mind that Resource Curves can cause scenarios like this one to
confuse and puzzle you, if you are calculating and finding strange
values for Schedule % Complete. Here‟s another reason to know your
schedule intimately.
The Essential Guide to Printing
Layouts in Primavera P6
Primavera P6 provides the ability to display project schedule
information using “Layouts”. Layouts are customizable views of project
information and are the primary method for printing Gantt Charts,
Profiles, Spreadsheets, and Trace Logic views. Schedules are tough to
read and all members of the project team can benefit from an easier
way to interpret their schedules. Did you know that you can customize
the display of schedule information by using the Layout Options Bar?

The Layout Options Bar is used to create customized layouts that fulfill
your project reporting requirements. The Layout Options Bar is located
in the Activities Window.

The Layout Options Bar enables you to customize/incorporate the


following (in addition to other options):

 Bars
 Columns
 Table Font & Row
 Group & Sort
 Filters

This Primavera P6 training tutorial addresses the procedures for


printing the Layouts once you have customized them to your needs.

Step 1: Open the layout that you want to print using the Layout
Options Bar. The layout displayed below is: X – Current vs. Baseline
Bars. This layout includes the Activity Table on the left and the Gantt
chart on the right. The Gantt chart includes both current and baseline
bars. Click the Print Preview icon on the toolbar (see yellow arrow).
Step 2: In the Print Preview Dialog Box, you can use the toolbar at the
top left to access various print/view options.
Step 3: We will access the “Page Setup” option, which is the first icon
from the left. “Page Setup” consists of 5 tabs, and we will review each
of those tabs. The first tab is the Page tab, which can be used to select
page orientation, scaling and paper size.
Step 4: The Margins tab allows you to establish the top, bottom, left
and right margins.
Step 5: The Header tab enables you to select the appearance of the
Header. You can divide the header (see yellow arrow) into up to 5
sections and can control the contents of each section. You can also
identify on which pages you would like to include the Header, as well
as the height of the Header. In our example, we will divide the Header
into 3 sections. We will put a logo in the first section, insert the Project
Name & Layout Name in the second section, and the Date/Time in the
third section.

To insert the logo into section 1, click the drop-down list for section 1
and select Picture (see red arrow below),
Step 6: Use the browse button to select the filename of the logo (see
yellow arrow) . Click the Apply button on the right to preview the layout
with the new modifications. Notice that the logo is barely visible (see
green arrow below) because the Header height is only .25.
Step 7: Increase the Header height to 1 and click Apply to view the
result. Notice that the logo is now more prominent.
Step 8: Let‟s work on the 2nd Section of the Header. Currently, the
2nd section is set to display the Layout Name (see Red arrow). We
would like to display the Project Name in addition to the Layout Name
and would also like the Project Name to be displayed as red text.
Step 9: In section 2, select Text/Logo (see yellow arrow) to identify the
desired contents. Click the drop-down list at the bottom left to pick
Project Name (see red arrow).
Step 10: Use the text formatting tools to format the text for the
contents of section 2 (see red arrow). Click the Apply button to view
the results. You can see that the text for Project Name has been set to
red using the text formatting tools.
Step 11: We will let Section 3 of the Header reflect Date/Time (see red
arrow).
Step 12: The Footer Tab works exactly as the Header tab.
Step 13: The Options tab will be available if your Layout includes a
Gantt chart, Profile, Spreadsheet, or Trace Logic. You can identify the
Timescale Start and Timescale Finish. These can be predefined dates
or you can specify a custom date. We have selected DD (Earliest Data
Date) for the Timescale Start and PF (Latest Project Finish) for the
Timescale Finish. Of course, you‟ll want to ensure you descrunch the
Gantt chart if you‟re printing it with this trick.

Notice the other print options that can be selected. We will explore
those options with the subsequent images.
Step 14: The preview displayed below depicts printing the Gantt chart,
only without the Activity Table.
Step 15: The preview below selects to print the Activity Table, displays
all columns on the Activity Table, as well as the Gantt chart.
Step 16: The preview below displays only those Activity Table columns
visible on the layout versus all columns.
Step 17: This preview displays only the Activity Table (ie. No Gantt
chart).
Step 18: View the finished product. Use arrows on the toolbar to
navigate through the preview. Use the print setup & print icons to
establish printer options. You can also publish the layout to an HTML
file (red arrow identifies the print preview dialog box options).

You might also like