MRP
MRP
MRP is the engine of any material planning software, computerized version of MRP IS Created 1977
MPS= HOW MANY END PRODUCT DO I NEED TO MAKE, FOR E-G- I AM MAKING CAR AND MARKETING
DEPT TELLS ME THAT YOU NEED TO MAUFACTURE 100 CARS, FOR 100 CARS.
BOM
Bill of Material tell me what do I need to make those 100 cars, one car need 5 tires and steering wheel
(BILL OF MATERIAL IS PRODCUT STRUCTURE What components we required to manufacture the
product) 100X5= 500 Tires
INPUT PROCESS
1.MPS-------------
3.Inventory----------
We required 500 tires but let supposed we have 200 in inventory so net requirement is 300 tires
OFF SETTING
Suppose we need the car in week 3 , so we plan the car manufacturing in week 2 and tires take 1 week
to come when order is placed , so I order tires in 1 week because supplier takes 1 week to supply the
tires. We order things according to our lead time
What to order
When to order
Aggregate planning
ANSWERS
Total working days = 19 + 20 + 21 = 60 Average daily production
= 500 60 = 8.3 units
Period 1 2 3 4 5 6
Planned 500
Inventory
Period 1 2 3 4 5 6
Planned Production
Planned 100
Inventory
Period 1 2 3 4 5 6 Total
Period 1 2 3 4 5 6 Total
Planned Production
Planned 500
Inventory
Solution:
Total Production= Ending Inventory – Opening Inventory
Total production= 5700 + 300 - 500= 5500 units
Period 1 2 3 4 5 6 Total
Period 1 2 3 4 Total
32
Forecast Demand 9 5 9 9
8 8 8 8 32
Planned Production
-1 2 1 0
Planned Inventory 0
Solution
Forecast demand total = 9+5+9+9= 32/4=8
Period 1 2 3 4 Total
32
Forecast Demand 9 5 9 9
9 9 9 9 36
Planned Production
0 4 4 4
Planned Inventory 0
There is a stockout of 1 unit in period one. The cost will be: Stockout cost: 1 $500 = $500
Carrying cost: 3 $50 = 150 Total cost: = $650 c. Total period inventory = 0 + 5 + 3 + 4 = 12
units The cost will be = $50 12 = $600 Since there are no stockouts this will be the total cost
of the plan.
Planned Production
Planned 100
Inventory
SOLUTION
a. Total production = 530 + 130 – 100 = 560
b. Daily production=560/70 = 8 units
c. The monthly production for May=(21x8) =168 units
d. The ending inventory for May=153 units
Week 1 2 3 4 5 6 Total
Planned Production
Projected 900
Backlog
Solution:
Total production= demand + opening backlog – ending backlog
= 3800 + 900 –200= 4500 units
Week 1 2 3 4 5 6 Total
3800
Forecast Demand 600 700 700 700 600 500
750 750 750 750 750 750 4500
Planned Production
750 700 650 600 450 200
Projected 900
Backlog
2.16 The opening backlog is 1100 units. Forecast demand is
shown in the following. Calculate the weekly
production for level production if the backlog is to be
increased to 1200 units.
Week 1 2 3 4 5 6 Total
Planned Production
Projected 1100
Backlog
Solution:
Week 1 2 3 4 5 6 Total
Month 1 2 3 4 Total
Working Days 20 24 12 19
Planned Production
Solution:
Total Production= Forecast demand + Ending Inventory-
Planned Inventory
Total production = 112,500 + 9000 – 11,500 = 110,000 units
Daily production= 110,000 75 = 1466.67 units
Number of workers required = 1466.67/14 = 104.76 105
Actual daily production=105 14= 1470 units
1470x20=2400, ………….
Month 1 2 3 4 Total
Working Days 20 24 12 19 75
112500
Forecast Demand 28,000 27,500 28,500 28,500
29400 35280 17640 27930 110250
Planned Production
12900 20680 9820 9250
Planned Inventory 11,500
2.18 For the following data, calculate the number of workers
required for level production and the resulting month-end
inventories. Each worker can produce 9 units per day, and the
desired ending inventory is 800 units. Why is it not possible to
reach the ending inventory target?
Month 1 2 3 4 5 6 Total
Working Days 20 24 12 22 20 19
Solution:
Month 1 2 3 4 5 6 Total
Working Days 20 24 12 22 20 19
Forecast Demand 2800 3000 2700 3300 2900 3200