Answer On Question #51641, Management, Other
Answer On Question #51641, Management, Other
A (10,000) 10,000
Required:
Use 10% where cost of capital is not given especially in cases of NPV and IRR.
Solution:
i. Payback period.
In given problem we note the data of the task. The information is provided in the Table
In order to determine the payback period we apply the following method of calculation,
we divide the cash outlay (which is assumed to occur entirely at the beginning of the project) by
the amount of net cash flow generated by the project per year.
Thus, for the Project A the Payback period will be equal.
The table indicates that the real payback period is located somewhere between Year 1
and Year 2.
The table indicates that the real payback period is located somewhere after Year 3.
The table indicates that the real payback period corresponds to 1 year.
Accounting rate of return (ARR) method uses expected net operating income to be
generated by the investment proposal rather than focusing on cash flows to evaluate an
investment proposal. Under this method, the asset’s expected accounting rate of return (ARR) is
computed by dividing the expected incremental net operating income by the initial investment
and then compared to the management’s desired rate of return to accept or reject a proposal.
For the calculation we apply the following formula.
In first case for ARR depreciation will be deducted to cash flow. For the Project A cash in
flow 10,000 and depreciation is equal to 10,000, hence, the Profit = 0%.
Average profit
ARR =
Average investment
10,000
ARR = = 100%
10,000
Internal rate of return (IRR) method also takes into account the time value of money. It
analyzes an investment project by comparing the internal rate of return to the minimum required
rate of return of the company.
The internal rate of return is the rate at which an investment project promises to generate
a return during its useful life. The formula for IRR is:
Based on the above formula we can calculate the internal rate of return for each Project.
IRR for Project A
10,000
[ ] = 9900.99
(1 + 0.01)1
Since NPV is fairly close to zero at 64.7% value of r, therefore IRR ≈ 64.7%
The investment's IRR is must be less than 1%, which is the rate that makes the present
value of the investment's cash flows equal to zero. If we have the value of rate equal to 1%, then
we obtain the following result.
The investment's IRR is 37.55%, which is the rate that makes the present value of the
investment's cash flows approximately equal to zero.
22,032.307
PI = = 2.203
10,000
Now we make calculation for the Project C. As in previous part we create the Table.
Now we make calculation for the Project D. As in previous part we create the Table.
Where:
NPV – Net Present Value of the project;
CFt – cash flow in period t;
CF0 – cash flow at the initial moment. The initial cash flow is equal to investment capital (CF0 =
IC);
r – the discount rate.
Thus, we apply this formula for calculation the NPV for the first Project A. We obtain the
following result.
10,000
NPV = −10,000 + = −909.09
(1 + 0.10)1
We apply formula the same for calculation the NPV for the Project B. We obtain the
following result.
We apply the same formula for calculation the NPV for the Project C. We obtain the
following result.
We apply the same formula for calculation the NPV for the Project D. We obtain the
following result.
10,000 3,000 3,000
NPV = −10,000 + + + = −10,000 + 13824.19
(1 + 0.10)1 (1 + 0.10) 2 (1 + 0.10)3
= 3,824.19
https://www.AssignmentExpert.com