Inspection Test Plan For Concrete Blinding Work: Approved Method Statement

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 2

INTEGRATED MANAGEMENT SYSTEM FORMAT Document #:PM-F-02-Rev B

INSPECTION TEST PLAN FOR CONCRETE BLINDING WORK Date: 12-08-2010

Name of the Project: KIZAD LIFESCIENCE PARK


Name of the Client: CNBC
Name of the Consultant: ECG
Name of Contractor China State Construction Engineering Corporation (ME) L.L.C

REVIEW OR
ITEM DESCRIPTION OF INSPECTION & SPECIFICATION REF / PROCEDURE /
VERIFYING RECORD FREQUENCY INITIATE REVIEW APPROVAL APPROVAL BY
No. TEST DRAWINGS CHECKLIST
CONSULTANTS

1.0 Submission

Drawing of substructure above Project Specifications & Approved shop drawing Technical Mgr / Sr. Project
1.1 NA Prior to work commencement Draftsman The Engineer (Hold)
blinding Drawings submittal QAQC Mgr Manager

Blinding concrete mix design & Trial Project Specifications & Technical Mgr / Sr. Project
1.2 Cube test result Approved Transmittal Prior to work commencement Sr.QA/QC Eng. The Engineer (Hold)
mix Drawings QAQC Mgr Manager

Const Mgr /
Method Statement for concrete Project Specifications & Sr. Project
1.3 NA Technical Submital Prior to work commencement Sr.QA/QC Eng. Technical Mgr / The Engineer (Hold)
blinding Drawings Manager
QAQC Mgr

Materials related to concrete blinding Project Specifications & Technical Engineer / Sr. Project
1.4 _ Approved Material submittals Prior to work commencement QAQC Mgr The Engineer (Hold)
application Drawings Architect Manager

2.0 Construction

Compaction below blinding area done Project Specifications & Approved Technical submital Approved Third Technical Mgr / Sr. Project
2.1 Test Result & IR Each area prior to blinding appliction The Engineer (Hold)
and test results passed Drawings and IR party lab. QAQC Mgr Manager

Setting out lines, levels, Dimensions,


shape and size as per approved construction drawings/ Approved Method a.Survey Report Sr. Project
2.2 Statement
Each area prior to blinding appliction Site Engineer QAQC Eng The Engineer (Hold)
drawings and within tolerance Setting Out Drawings b.Inspection request Manager
acceptable

MEP clearance to start concrete Project Specifications & Approved Method Sr. Project
2.3 Mep clearance format Each area prior to blinding appliction MEP Engineer QAQC Eng The Engineer
obtained Drawings Statement Manager

1 of 2 CSC-2080-ITP-005, REV 0
INTEGRATED MANAGEMENT SYSTEM FORMAT Document #:PM-F-02-Rev B

INSPECTION TEST PLAN FOR CONCRETE BLINDING WORK Date: 12-08-2010

Name of the Project: KIZAD LIFESCIENCE PARK


Name of the Client: CNBC
Name of the Consultant: ECG
Name of Contractor China State Construction Engineering Corporation (ME) L.L.C

REVIEW OR
ITEM DESCRIPTION OF INSPECTION & SPECIFICATION REF / PROCEDURE /
VERIFYING RECORD FREQUENCY INITIATE REVIEW APPROVAL APPROVAL BY
No. TEST DRAWINGS CHECKLIST
CONSULTANTS

Thickness of blinding concrete


The Engineer
maintained as per drawings & Finishing Project Specifications & Approved Method Site Engineer/ Sr. Project
2.4 Blinding Checklist Each area prior to blinding appliction QAQC Eng
heights marked on the formwork and Drawings Statement forman Manager
( survelliance)
joints flush and tight

The Engineer
Project Specifications & Approved Method Site Engineer/
2.5 Anti termite applied as per specification Visual inspection Each area prior to blinding appliction QAQC Eng QC Engineer
Drawings Statement forman
( survelliance)

Concrete delivery, slump and The Engineer


Approved Method a.Concrete
2.6 temperature checked and comply with Mix design approval Visual inspection Each delivery of concrete truck QAQC Eng QC Engineer
Statement technician
Project specs. ( survelliance)

Concrete cubes for compressive Project Specifications & Approved Method


2.7 Report - Concrete test result Each pour of concrete Third party lab. QAQC Eng QC Engineer The Engineer (Hold)
strength testing Drawings Statement

The Engineer
Project Specifications & Approved Method Site Engineer/
2.5 Curing for concrete surface Visual inspection After initial setting of concrete work QAQC Eng QC Engineer
Drawings Statement forman
( survelliance)

Prepared & Reviewed By: Approved By:

Name: Name: Name:


Construction Manager QA-QC Representative Project Manager/ Sr. project Manager

Date: …………………….. Date: …………………….. Date: …………………

2 of 2 CSC-2080-ITP-005, REV 0