Inspection Test Plan For Concrete Blinding Work: Approved Method Statement
Inspection Test Plan For Concrete Blinding Work: Approved Method Statement
Inspection Test Plan For Concrete Blinding Work: Approved Method Statement
REVIEW OR
ITEM DESCRIPTION OF INSPECTION & SPECIFICATION REF / PROCEDURE /
VERIFYING RECORD FREQUENCY INITIATE REVIEW APPROVAL APPROVAL BY
No. TEST DRAWINGS CHECKLIST
CONSULTANTS
1.0 Submission
Drawing of substructure above Project Specifications & Approved shop drawing Technical Mgr / Sr. Project
1.1 NA Prior to work commencement Draftsman The Engineer (Hold)
blinding Drawings submittal QAQC Mgr Manager
Blinding concrete mix design & Trial Project Specifications & Technical Mgr / Sr. Project
1.2 Cube test result Approved Transmittal Prior to work commencement Sr.QA/QC Eng. The Engineer (Hold)
mix Drawings QAQC Mgr Manager
Const Mgr /
Method Statement for concrete Project Specifications & Sr. Project
1.3 NA Technical Submital Prior to work commencement Sr.QA/QC Eng. Technical Mgr / The Engineer (Hold)
blinding Drawings Manager
QAQC Mgr
Materials related to concrete blinding Project Specifications & Technical Engineer / Sr. Project
1.4 _ Approved Material submittals Prior to work commencement QAQC Mgr The Engineer (Hold)
application Drawings Architect Manager
2.0 Construction
Compaction below blinding area done Project Specifications & Approved Technical submital Approved Third Technical Mgr / Sr. Project
2.1 Test Result & IR Each area prior to blinding appliction The Engineer (Hold)
and test results passed Drawings and IR party lab. QAQC Mgr Manager
MEP clearance to start concrete Project Specifications & Approved Method Sr. Project
2.3 Mep clearance format Each area prior to blinding appliction MEP Engineer QAQC Eng The Engineer
obtained Drawings Statement Manager
1 of 2 CSC-2080-ITP-005, REV 0
INTEGRATED MANAGEMENT SYSTEM FORMAT Document #:PM-F-02-Rev B
REVIEW OR
ITEM DESCRIPTION OF INSPECTION & SPECIFICATION REF / PROCEDURE /
VERIFYING RECORD FREQUENCY INITIATE REVIEW APPROVAL APPROVAL BY
No. TEST DRAWINGS CHECKLIST
CONSULTANTS
The Engineer
Project Specifications & Approved Method Site Engineer/
2.5 Anti termite applied as per specification Visual inspection Each area prior to blinding appliction QAQC Eng QC Engineer
Drawings Statement forman
( survelliance)
The Engineer
Project Specifications & Approved Method Site Engineer/
2.5 Curing for concrete surface Visual inspection After initial setting of concrete work QAQC Eng QC Engineer
Drawings Statement forman
( survelliance)
2 of 2 CSC-2080-ITP-005, REV 0