B.C.A. - 5 Sem: Assignment: Unit-4 Job Sequencing
B.C.A. - 5 Sem: Assignment: Unit-4 Job Sequencing
-5th Sem
Assignment: Unit-4
Job Sequencing
Attempt all the questions:
1. Define the following:
i. General Assumption to solve Sequencing Problem iii. Sequencing
ii. Graphical Method iv. Johnson’s Method
2. Find the sequence that minimize the total elapsed time require to complete the jobs. Also
calculate idle time for each machine.
(i) (iv)
JOB 1 2 3 4 5 6 JOB A B C D E
Machine A 2 5 4 3 2 1 Machine I 10 12 8 15 16
Machine B 6 8 1 2 3 5 Machine II 3 2 4 1 5
(ii) Machine III 5 6 4 7 3
JOB 1 2 3 4 5 Machine IV 14 7 12 8 10
Machine I 4 9 8 6 5 (v)
Machine II 5 6 2 3 4 JOB A B C D
Machine III 8 10 6 7 11 Machine M1 18 17 11 20
(iii) Machine M2 8 6 5 4
JOB A B C D E F G Machine M3 7 9 8 3
Machine M1 12 6 5 11 5 7 6 Machine M4 2 6 5 4
Machine M2 7 8 9 4 7 8 3 Machine M5 10 8 7 8
Machine M3 3 4 1 5 2 3 4 Machine M6 25 19 15 12
(vi)
JOB 1 2 3 4 5 6 7
Machine M1 3 12 15 6 10 11 9
Machine M2 8 10 10 6 12 1 3
3. Use Graphical method to minimize the time required to process the following jobs on the
machines. Also calculate the total elapsed time require to complete the jobs and idle time for each
machine.
(i)
Job 1 Sequence A B C D E
Time (in hrs.) 6 8 4 12 4
Job 2 Sequence B C A D E
Time (in hrs.) 10 8 6 4 12
(ii)
Job 1 Sequence A C D B E F
Time (in hrs.) 20 10 10 30 25 15
Job 2 Sequence A C B D F E
Time (in hrs.) 10 30 15 10 15 20