Sukkur IBA University
Sukkur IBA University
Email: [email protected]
Web: www.iba-suk.edu.pk
1
1. Background
At Sukkur IBA University Community College Khairpur, different civil works for security
purpose (detailed in BOQ) are required to be done, so a tender is called for execution of
said work
2. General Terms and Conditions
2
2.12. Sukkur IBA, reserves the right to reject any or all Bids/ Offers without assigning any
reason or cancel the process at any time.
2.13. Sukkur IBA reserves the right to increase/ decrease the quantity of items / scope of
the work. Bidder has no right to challenge the decision.
3.1. For this tender PPRA’s Single stag-two envelope Procedure as per clause 36 (b)
for open competitive bidding is adopted. The bid shall comprise a single package
containing two separate envelopes. Each envelope shall contain separately the
financial proposal and the technical proposal;
3.1.2 Initially, only the envelope marked “TECHNICAL PROPOSAL” shall be opened;
3.1.4 The procuring agency shall evaluate the technical proposal, without reference to
the price and reject any proposal which do not conform to the specified
requirements;
3.1.5 During the technical evaluation no amendments in the technical proposal shall
be permitted;
3.1.6 The financial proposals of bids shall be opened publicly at a time, date and
venue announced after technical assessment and evaluation.
3.1.7 After the evaluation and approval of the technical proposal the procuring
agency, publicly open the financial proposals of the technically accepted bids
only. The financial proposal of bids found technically non-responsive shall be
returned un-opened to the respective bidders.
3
3.2.4 Description of material.
3.2.5. Completion schedule on Bar chart, Primavera or other software.
3.2.6 Technical proposal shall provide the details of company, complete factory details etc.
3.2.7. Financial Proposal of only those Bidders will be considered whose Technical Proposal
qualify.
3.2.8. Bidders must possess the valid PEC license in such category in which the total bid cost
falls, if not than his financial proposal will be rejected.
4
3.3.2. For each category the quoted prices must include all taxes, customs and freight
charges for delivery at the required locations at own risk and cost along with installation
and assembling.
3.3.3. As items are for educational institution, Sukkur IBA University thereof expects
significant educational and volume discounts from principal supplier.
Financial proposal of the bidders found technically non responsive will be returned
unopened.
3.3. 4. The Bidder shall furnish s earnest money equivalent to 2% of the total value of bid in
the form of Bank Draft issued by a scheduled bank of Pakistan in favor of “Sukkur IBA
University” along with financial proposal. No Bid shall be entertained without earnest
money. Earnest money of the successful bidder will be released after defect liability &
maintenance period.
4. Terms of Payment
5
1. FORM OF TENDER
Dear Sir,
1.1 Having inspected the SITE and checked all local conditions affecting the WORK, and
having also examined all Tender Documents including the Drawings, Instructions for
Tenderers, Conditions of CONTRACT, Special Conditions of CONTRACT, Specifications,
Bill of Quantities, for the above named WORK, we the undersigned offer to execute and
maintain the whole of the said WORK, in conformity with the said Tender Documents,
for the price as mentioned below:
As agreed upon under the CONTRACT or such other sums as may be ascertained in
accordance with the said CONDITIONS of CONTRACT.
1.2 We accept the above-mentioned Tender Documents as valid and binding including parts
not countersigned in full by us. This also includes all Appendices to the Form of Tender
attached hereto.
1.3 We confirm that we have satisfied ourselves about the SITE, climatic, traffic and all
other conditions in Pakistan in general and the SITE of the PROJECT, and related works
in particular, which influence, or may influence the work, and that we do not require
any further clarification and additional information thereto, and that we cannot raise
any claim for not knowing them.
1.4 We undertake to carry out such alterations, additions or curtailments of the WORK as
may from time to time be determined and ordered in writing, in accordance with the
CONTRACT, and at the rates in the Bill of Quantities.
6
1.5 The rates and prices which we have entered in the Bill of Quantities and Schedule, and
all information and data attached with our Tender are complete and without any
hidden or technical and/or financial reservations or implications. They have been duly
checked, and are correct in every aspect.
1.6 The rates and prices which we have entered in the Bill of Quantities and Schedule, are
firm and shall remain fixed for the entire duration of the CONTRACT, and are inclusive
of custom duties, sales tax, local and federal taxes, Iqra surcharge, insurance, port and
octroi charges, royalties, except change in direct taxes.
1.7 We attached herewith a Bid Bond for 2% of the contract in shape of Demand draft/ Pay
order by scheduled Bank of Pakistan
We agree that should we withdraw the offer within the aforesaid period, and/or fail to
sign the formal Agreement of CONTRACT, and/or fail to submit the Performance Bond;
the OWNER shall be at liberty to appropriate at his absolute discretion such aforesaid
Bid Bond.
1.10 If our Tender is accepted, we shall furnish a Performance Bond as per the format as in
Appendix II to these CONDITIONS of CONTRACT, from a Scheduled Bank which shall be
valid from the date of issue by the OWNER of the Letter of Award, till the expiry of the
PERIOD of MAINTENANCE in accordance with the CONDITIONS of CONTRACT.
1.11 We agree to pay all costs towards the preparation of the Agreement for the CONTRACT.
1.12 We further agree to abide by this Tender for a period of completion time from the date
of opening of this Tender, and we agree to be bound by this Tender for that period.
1.13 Until and unless the Agreement is signed, this Tender and the OWNER's written
acceptance thereof shall constitute a binding CONTRACT between us.
7
1.14 We understand that the OWNER is not bound to accept the lowest or any
Tender he may receive.
1.15 It is agreed that quoted rates includes all taxes, i-e Income tax, SST prevailing and
imposed by government now.
Designation_______________________________
Witness
Designation______________________________________
Address ______________________________________
8
2. INSTRUCTIONS TO TENDERERS
2.1.5 "WORK" means all supplies and performances, which are to be executed by the
CONTRACTOR in accordance with the CONTRACT. Insofar as to be understood
from the wording of the text, WORK also means the entirety of all or individual
components which are to be completed and maintained until finally accepted
within the scope of CONTRACT.
2.1.6 "CONTRACT" means the contractual agreement between the OWNER and
CONTRACTOR for the execution of the WORK and includes the following
documents:
.11 The Shop Drawings prepared by the CONTRACTOR and approved for
construction by the ARCHITECT and/or Client.
2.1.7 "CONTRACT PRICE" means the price as in the Tender, inclusive of all additions
or deletions foreseen in the CONTRACT, but without Liquidated Damages.
2.1.9 "TEMPORARY WORKS" means all temporary works of every kind, inclusive of
the materials therefore, required in or about the execution, completion and
maintenance of WORK until final acceptance. It also includes any material
becoming part of the completed WORK, and any performances therewith,
required and used only due to, or in consequence of, the construction
methods, construction stages etc.
2.1.11 "BILL OF QUANTITIES" - The term Bill of Quantities shall mean that part of the
CONTRACT documents under Section 5 outlining the quantities of the various
items of WORK to be performed under the various sections of the
Specifications, and the respective per unit prices for these items of work,
quoted for by the Tendered.
10
"SITE" - The "SITE" shall mean the “Sukkur IBA University IBA Community
College Khairpur”,
Where the WORK is to be executed.
"SITE" also means land on, under, in or through which the WORK are to be
executed or carried out, as well as all land or buildings provided by the OWNER
for the purpose of the CONTRACT, and furthermore, all terrain as may be
expressly designated in the CONTRACT as forming part of the SITE.
2.1.14 "Rupees" means Pakistani Currency Rupees. It is the currency basis of the
CONTRACT.
2.1.17 Words used only in the singular, also include the plural, and vice versa where
required by context.
2.2 General:
Only Contractors pre-qualified for the work are allowed to submit a Tender.
2.3 Confidentiality:
The Tenderer, whether or not he submits a Tender shall treat the details of the
Documents as strictly confidential.
12
2.14.1 Language
All entries are to be made in English and clearly in ink.
2.16.1 The Bill of Quantities must be fully priced in all items, and totaled as required.
2.16.2 All Schedules and Appendices of the Tender Documents must be properly
filled in, completed and signed as required.
2.16.3 All drawings, descriptions, time schedules and data to be supplied additionally
by the Tenderer must be in English.
The Bid Bond of the successful Tenderer will be released only after the Agreement of
CONTRACT has been signed and the Performance Bond has been deposited by him as
per Clause 3.13.
Project Director
Sukkur IBA University,
Airport Road,
Sukkur
The CLIENT shall have the right to adjust arithmetical errors in any Tender. If the
CLIENT/ ARCHITECT discover major errors and/or omissions in any Tender, he may
require the Tenderer to adjust the same, but in such cases the Tenderer will not be
permitted to change the basic rates. If any discrepancy is found, the relevant rates in
words so arrived at will be considered in assessing the Tender.
THE OWNER RESERVES THE RIGHT TO REJECT ANY TENDER WITHOUT GIVING ANY
REASON, OR TO ACCEPT ANY TENDER IN WHOLE OR IN PART AND DOES NOT BIND
HIMSELF TO ACCEPT THE LOWEST OR ANY TENDER AS PER RULES.
The Tenderer, whose Tender may be accepted will be required to send authorized
representatives at their own expense for necessary technical and contractual
discussions, as the case may be, for drafting the Agreement of CONTRACT.
The Tenderer whose Tender may be accepted will, after all discussions as in 2.25,
receive a Letter of Award of Work, after which Tenderer will be deemed to have been
awarded the Work, and all covenants of the CONTRACT Documents will be applicable
immediately on all parties concerned, until the formal Agreement of CONTRACT has
been signed.
The Tenderer who has been issued Letter of Award of Work will be required to enter
into the Agreement of CONTRACT, the form of which (subject to any necessary
adoptions), will be as set out in APPENDIX I to the Conditions of CONTRACT, within Ten
(10) days after issue of Letter of Award of Work.
The right is reserved to amend any of the Tender Documents or to issue additions to
them prior to the due date for submitting Tenders. All such amendments and/or
additions will be advised not later than 3 (Three) days before Tenders are due. It is
mandatory that the Tender shall include the latest amendment and/or additions to the
Tender Documents. The drawings mentioned in 2.5 of the Tender Documents as
revised during the aforesaid period shall be deemed to be Drawings referred to in the
CONTRACT upon which the sums named in the Tender are based.
15
When the Tenderer is informed of any amendment, addition or revision of the Tender
Documents, he is required to immediately acknowledge receipt of same to Consultant.
3. CONDITIONS OF CONTRACT
3.2.2 Specification
16
3.2.4 Extra Specification WORK
In the case of any class of WORK for which there are no specifications in the
Tender, such work is to be carried out in all respects as per the instruction and
requirement of the ARCHITECT and/or OWNER. 15% markup will be given to the
Contractor on prime cost of items of work which are not included in BOQ’s & the
OWNER has asked Contractor to perform. However, any job, which is required
by the OWNER to be done on daily work basis, shall be paid 25% extra to cover
the over head and for the coordination supervision on actual cost of material
and basic labor rates as below
Wherever the provision of any section of Specifications may conflict with any
agreements or regulations of any kind in force among members of any Trade
Associations, Union or Council which regulate or distinguished what work shall
or shall not be included in the work of any particular trade, CONTRACTOR must
make all necessary arrangements of his own to reconcile any such conflict of
provisions without recourse to the OWNER, ARCHITECT and/or CONSULTANT.
17
It is to be understood that prior to manufacture, fabrication or installation of
WORK under CONTRACT, Shop drawings shall be prepared and reproducible of
each submitted to ARCHITECT and/or OWNER for approval. No WORK will be
executed in any instance prior to approval by the ARCHITECT and/or OWNER of
any respective Shop drawings. ARCHITECT and/or OWNER’s approval, however,
shall not relieve CONTRACTOR of responsibility for accuracy, as such approval of
Shop drawings is only general and is not intended to serve as a check, and does
not relieve CONTRACTOR from furnishing the materials and performing the
WORK as required by Drawings and Specifications.
18
3.4 Record:
3.4.1 General
CONTRACTOR during progress of WORK, shall keep a careful record of
Drawings or all changes and corrections on Drawings. Upon completion
CONTRACTOR shall mark up a set of reproducible furnished by the ARCHITECT
and/or CONSULTANT, showing the WORK as actually constructed. These
drawings shall be delivered to the ARCHITECT and/or OWNER as a condition
of "Final Payment".
3.5.1 General
All types of materials, articles, or processes shall be of the respective kinds or
brands relating to kind, quality, function and characteristics required by the
Specifications or specified hereinafter. Where various kinds and brands are not
so specified they shall be the best obtainable for required purposes. Where a
specific item or type of material is specified in any portion of the Specifications
and/or followed by the words "or equivalent" or "as equal" or words of similar
intent, CONTRACTOR shall base his Bid Proposal upon said item or type of
material as specified. The CONTRACTOR may, however, submit a written
request, seeking permission to utilize a substitute item or material. The
CONTRACTOR shall handle and take care of all materials used by him in
performance of his WORK, whether furnished by him or by other parties; as such
materials are delivered at SITE, and shall pile, store, handle and protect them
from injury. He shall deliver all materials at such times and in such quantities as
will insure speedy and uninterrupted progress of WORK.
3.5.2 Samples
Where required in Specifications for various trades or otherwise required by
OWNER, samples of any materials to be used and of the finish to be applied in
the WORK, shall be submitted by the CONTRACTOR for approval. Samples of
all materials submitted for approval to the ARCHITECT and / or OWNER shall
be supplied, wherever reasonable, in duplicate, unless specified otherwise
elsewhere in this CONTRACT, each sample bearing a neatly typed label bearing
CONTRACTOR’s name, name of sub-Contractor or producer of materials, kind,
quality and finish or formula (where applicable, as in the case of liquids or
paints) intended use or location, date of submission. Written approval shall be
obtained prior to processing or fabrication of any materials for which samples
are submitted and all finished WORK shall conform thereto and/or comply with
characteristics of approved samples. In no instance shall approval of samples
relieve the CONTRACTOR of full compliance with any Specification requirement.
19
3.5.3 Inspection
For purpose of inspection OWNER and ARCHITECT and/or CONSULTANT and
their representatives shall, at all times, have access to WORK, wherever it is in
preparation or progress, and CONTRACTOR at his expense, shall provide proper
facilities for such access and for inspection; but such right of inspection and any
actual inspection, shall in no way relieve the CONTRACTOR from performance of
the WORK in accord with requirements of CONTRACT or from any other duty,
obligation or liability imposed upon him by the CONTRACT. The fact that
materials have been accepted at shop or wherever the WORK is in preparation
or progress shall not prevent its rejection under provisions hereto at building
either before or after its installation. If any such WORK should be covered up
without approval or consent of the ARCHITECT and/or CONSULTANT, it must, if
required by OWNER, and/or ARCHITECT and/or CONSULTANT, be uncovered for
examination at CONTRACTOR's expenses. Wherever so required by OWNER
and/or ARCHITECT and/or CONSULTANT shall render a detailed report of
condition of WORK in shop or at SITE.
OWNER and ARCHITECT, and all their authorized representatives, against any
claim, suits, damages and judgments, including Counsel fees and disbursements
incurred in defence of any action, of which they may be subjected or which they
may suffer by reason of any injury to persons or property resulting from
negligence or carelessness on part of the CONTRACTOR or his sub-Contractors,
agents or employees, in performance of WORK, or arising out of WORK
performed hereunder.
20
3.6.3 Emergencies: In any emergency affecting safety of life or of WORK or of
adjoining property, CONTRACTOR without special instruction or authorization
from OWNER or ARCHITECT and/or CONSULTANT, is hereby permitted to act at
his discretion, to prevent such threatened loss of injury, and he shall so act,
without appeal if so instructed / authorized.
3.6.6 Fire Provide: Adequate protection against fire hazards and observe all
care precautions against such hazards. ARCHITECT and/or OWNER shall be the
sole judge as to the adequacy or otherwise of such measures. Damage by fire
will be made good by the CONTRACTOR at his own expense.
3.7.1 General
Should CONTRACTOR desire to sublet any portion of the WORK, he shall make
such request to ARCHITECT and/or OWNER in writing, giving name and address of
proposed Sub-Contractor defining portion of WORK desired to be sublet. This
shall be done before CONTRACTOR in any manner obligates himself to any Sub-
Contractor.
21
as applicable.
3.8.1 General
If it shall appear to the ARCHITECT and/or OWNER that any WORK has been
executed with unsound, imperfect or unskilled workmanship, or if materials of
any articles provided by the CONTRACTOR for the execution of the WORK are
unsound or of a quality inferior to that contracted for, or otherwise not in
accordance with the CONTRACT, the CONTRACTOR, shall, on demand in writing
from the ARCHITECT and/or OWNER specifying the WORK or materials or
articles complained of, notwithstanding that, the same may have been
inadvertently passed, certified and paid for, forthwith rectify, or remove and
reconstruct the WORK so specified in whole or in part, as the case may require,
remove the articles or materials so specified and provide other proper and
suitable articles or materials at his own charge and cost. In the event of
CONTRACTOR's failing to do so, no payments shall be made for the same till
defects are rectified as per instructions of the ARCHITECT and/or OWNER, and in
case where rectification or removal of defects or materials is not possible and
work can be accepted otherwise, the rates for such items shall be reduced. In all
such cases the decision of OWNER shall be final and binding on the
CONTRACTOR.
3.9 Completion
3.9.1 Final Certificate of Completion
On completion of WORK the CONTRACTOR shall so notify the ARCHITECT and/or
OWNER in conducting inspections and any final tasks that may be prescribed by
the CONTRACT to determine successful completion of the WORK. CONTRACTOR
22
shall be furnished with a Certificate by the OWNER of such completion, but no
such Certificate shall be given, nor shall the WORK be considered to be complete
until CONTRACTOR shall have removed from the premises on which the WORK
shall be executed all surplus materials and rubbish, and cleaned off the SITE in,
upon or about which the WORK is to be executed or which he may have had
possession for the purpose of the execution thereof, nor until the WORK shall
have been certified by the ARCHITECT and/or OWNER whose certificate shall be
binding and conclusive against CONTRACTOR. If the CONTRACTOR shall fail to
comply with the requirements of this Clause as to removal of surplus materials
and rubbish, and cleaning off SITE on or before the date fixed for the Completion
of the WORK, OWNER, and/or ARCHITECT and/or CONSULTANT may, and at the
expense of CONTRACTOR order removal of materials and rubbish and disposal of
the same as they think fit to clean off such dirt as aforesaid, and CONTRACTOR
shall pay the amount of all expenses so incurred, and have no claim in respect of
any such surplus materials as aforesaid except for any sum actually realized by
the sale thereof. The "Period of Maintenance" of the WORK as specified in
Clause 3.17.4 of these Conditions shall commence from the date of issue of such
Final Certificate of Completion.
3.10 Payments
3.10.1 Interim Payments.
3.10.1.1General:
After verification of bill at site, its quality and quantity as per the specification,
entire satisfaction of CLIENT, within two weeks after bill submittal.
The OWNER shall have full power to reduce the rates for such items which have
not been properly carried out but can be accepted otherwise. The decision of
OWNER with respect to reduction of rates will be final and binding on the
CONTRACTOR. This will apply to such items also which might have been paid in
full earlier but defects are detected later.
23
3.10.5 Form of Payment
3.10.5.2 Interest: No interest will be paid to the CONTRACTOR or any body else,
on CONTRACTOR's Earnest Money, Security Retention, amounts of bills or any
other amounts of CONTRACTOR remaining with the OWNER for any period.
Interim Payments will be made after deduction of the Retention Money and the
like, as follows:
3.10.6.1 Security Retention: Deduction from the first and the following running
bills of the CONTRACTOR as Security Retention at 10% (Ten percent) of gross
amount of such running bills.
3.10.7.4 Release from Lien and Charge Release of Lien and Charge, according
to which there is no lien or charge from him or from a third party, on any
delivery or performance of the CONTRACT, in connection with the CONTRACT.
The final payment will be made after all the above documents and Final Bill of
the CONTRACTOR have been approved by the OWNER.
(0.1 %( point one percent) of Total Contract Price at the time of signing of
CONTRACT, per day or up to maximum of 10% (ten percent) of the contract
value)
OWNER may without prejudice to any other method of recovery deduct the
amount of such damages from any moneys in his hand due or which may
become due to the CONTRACTOR. The payment or deduction of such damages
shall not relieve CONTRACTOR from his obligations to complete the WORK, or
from his obligations and liabilities under this CONTRACT.
3.10.9 Escalation:
All prices and unit rates in the CONTRACT are fixed and shall remain unchanged
for the entire duration of the CONTRACT. If any Direct Tax is imposed by the
Government on any of the items included in the CONTRACT, rates shall be
adjusted accordingly, this does not include Indirect Tax this adjustment shall be
made only upon CONTRACTOR's furnishing to the OWNER sufficient
documentary evidence of the rate of tax per item.
3.11.1.5 Sub-letting
25
Has to the detriment of good workmanship or, in defiance of OWNER's and/or
ARCHITECT’s instructions to contrary, sub-let any part of the CONTRACT; or
sum for any WORK thereto or actually performed under this CONTRACT unless
and until ARCHITECT and/or OWNER will have certified in writing the
performance of such WORK and the value payable in respect thereof,
CONTRACTOR shall only be entitled to be paid the value so certified on the
completion of "Period of Maintenance".
26
3.11.3 Non-exercise by OWNER of his Rights
In any case in which any of the powers conferred upon OWNER by Clause 3.11.2
thereof shall have become exercisable and the same shall not be exercised, the
non exercise thereof shall not constitute a waive of any of the conditions thereof
and such powers shall notwithstanding be exercisable in the event of any future
case of default by the CONTRACTOR for which by any Clause or Clauses hereof
he is declared to pay compensation amounting to the whole of his Security
Retention, and the liability of the CONTRACTOR for past and future
compensation shall remain unaffected.
The CONTRACT shall not be assigned or sublet without written approval of the
OWNER. If CONTRACTOR shall assign or sublet his CONTRACT, or attempt to do
so, or become insolvent or commence insolvency proceedings or mark any
27
composition with his creditors, or attempt to do so, or if any bribe, gratuity, gift,
loan, reward or advantage, pecuniary or otherwise, shall either directly or
indirectly be given, promised or offered by the CONTRACTOR, or any of his
servants or agents to any officer or person in the employment of OWNER or
ARCHITECT and/or CONSULTANT in any way relating to their office or
employment, OWNER may thereupon by notice in writing, terminate the
CONTRACT and the Security Retention of the CONTRACTOR shall thereupon
stand forfeited and be absolutely at the disposal of the OWNER and the same
consequences shall ensue as if the CONTRACT had been rescinded under, and, in
addition, to recover or be paid for any WORK, actually performed under the
CONTRACT.
OWNER may terminate contractor for convenience which will mean that if the
OWNER decides to change its plan or is forced by the appropriate authority to
suspend work then the OWNER may terminate the contract for convenience and
so notify the CONTRACTOR etc.
3.12.1.1 Payment of Damages Should the WORK or any part thereof or all or
any of the Temporary Works or any part thereof or materials on SITE for
incorporation in the WORK be damaged or lost during the continuance of
insurance effected under Clause 3.12.1, any risk insured against, CONTRACTOR
shall proceed with utmost dispatch to make good the damage or loss aforesaid
and every sum of money received under the policy or policies shall be paid of
money received under the policy or policies shall be paid to OWNER and be paid
by OWNER to the CONTRACTOR in such installments as the OWNER shall upon
recommendation of ARCHITECT and/or CONSULTANT think proper and certify
having regard to the progress made by the CONTRACTOR in making good the
damage or loss aforesaid in and so far as such damage or loss ought in the
opinion of ARCHITECT and/or OWNER to be made good for the proper execution
of the WORK.
The CONTRACTOR must indemnify and keep indemnified the OWNER and the
ARCHITECT and/or CONSULTANT against all losses and claims for injuries or
damage to any person or any property whatsoever, which may arise out of or in
consequence of the construction and maintenance of the WORK and against all
claims, demands, proceedings, damages, costs, charges, and or in relation
thereto. The CONTRACTOR is not allowed to claim any personal liability for or
with regard to any matter or thing which can be made binding hereby for the
OWNER and/or ARCHITECT and/or CONSULTANT from either any member or
official nor from the OWNER, nor from the ARCHITECT and/or CONSULTANT.
3.12.4.2 Approved Insurers The CONTRACTOR shall insure against such liability
with Eastern Federal Insurance Co.ltd., Duly attested by EFU Head Office or
Adamjee Insurance Company. The insurance is to be maintained by
CONTRACTOR during the entire duration of the CONTRACT. CONTRACTOR shall
when require, produce to OWNER such policy or policies of insurance and the
receipt for payments of the current premiums.
30
3.12.5 Legal Remedy on CONTRACTOR's failure to Insure
If the CONTRACTOR shall fail to effect and keep in force the insurances referred
to in Clause 3.12.1 to 3.12.3 hereto, or any other insurance which he may be
required to effect under the terms of the CONTRACT, then in any such case,
OWNER may effect and keep in force any such insurance and pay such premium
or premiums as may be necessary for that purpose, and from time to time
deduct the amounts so paid by the OWNER as aforesaid from any monies due or
which may become due to the CONTRACTOR or recover the same as debt from
the CONTRACTOR.
3.14.1 General
CONTRACTOR shall conform in all respects with the provisions of all Federal,
Provincial and Local Laws, Rules and Regulations including all regulations and
bye-laws of all local or other duly constituted authority within Pakistan which
may be applicable to the execution of the WORK, and shall give all notices and
pay all fees required to be given or paid thereby and shall indemnify OWNER
against all penalties and liabilities incurred by reasons of any such provisions.
CONTRACTOR shall hold harmless, and indemnify, OWNER and ARCHITECT from
and against all claims and proceedings for or on account of infringement by
31
CONTRACTOR of any patent rights, designs, trademarks or brand names, or
other protected rights in respect of any constructional plant, machine, WORK,
process, or material used for the purpose of, or in connection with the
CONTRACT and from and against all claims, demands, proceedings, damages,
costs, charges, and expenses whatsoever in respect thereof or in relation
therewith.
Nothing contained in this CONTRACT shall in any way affect or impair, any rights
or remedies to which the OWNER may be entitled under law.
3.15.1 General
Variation of the form, quality or quantity of the WORK or any part thereof, can
be affected through a written order to the
CONTRACTOR signed to show the recommendations of the ARCHITECT and/or
CONSULTANT and the authorization of the OWNER. For the purpose, or if it
appears desirable to them for any reasons, they shall have the power to issue
following binding directives:
Item (2) CONTRACTOR's overheads, risk and profit in connection with the supply
as surcharged to (1) above.
Item (3) Insurance, all taxes, import duties and the like.
Item (4) all landings, clearance and transport costs in Pakistan as well as
expenditures for handling, storage and incorporation of materials into the
permanent WORK at SITE etc., inclusive of all required construction plant and
equipment and labour/staff costs, as well as of other SITE overheads, risks and
profit.
Item (5) all costs for incorporation of materials into the WORK completed
according to Bill of Quantities, Drawings and Specifications. Any material
deviating from Specifications and the individual Bill of Quantities must be
delivered on instruction of ARCHITECT and/or OWNER, and will be paid for the
above cost items as follows under variation order:
3.15.4.4 Variation exceeding 20% If the net effect of all variations (other than
those arising by reason of any Clause relating to variations in price of materials
and/or labour) shall be found on completion of the whole of the WORK to result
in a reduction or an addition greater than 20% (twenty percent) of the sum
named in the Tender, the amount of CONTRACT Price shall be amended by such
sums as shall be agreed upon between ARCHITECT and/or OWNER and
CONTRACTOR. In the event of disagreement, OWNER shall fix such sum as shall
in his opinion be reasonable and proper consideration being given to all material
and relevant factors including CONTRACTOR's own costs and overheads and his
decision shall be final and binding to CONTRACTOR.
3.16.1 General
CONTRACTOR shall, on the written order of OWNER, suspend the progress of the WORK
34
or any part thereof for such time or times and in such manner as OWNER may
consider necessary and shall during such suspension properly protect and secure
the WORK so far as is necessary in the opinion of ARCHITECT and/or OWNER or
as required under the CONTRACT.
The extra cost including demurrage (if any) incurred by CONTRACTOR in giving
effect to OWNER's instructions under this Clause shall be borne and paid by the
OWNER unless such suspension is:
(2) Necessary for the proper execution of the WORK for any reason whatsoever
or by reason of weather conditions affecting the safety or quality of the WORK,
or by some default on WORK, or by some default on the part of CONTRACTOR,
or
(3) Necessary for the safety of the WORK or any part thereof.
The time allowed for carrying out the WORK as entered in the CONTRACT shall be
180 days and be reckoned from the date of issue of Letter of Award. The WORK
shall throughout the stipulated period of the CONTRACT be processed with all
due diligence (time being deemed to be the essence of the CONTRACT).
3.17.4.2 If, for any material or equipment supplied by CONTRACTOR, the OWNER
is entitled to a guarantee or warrantee by manufacturer or supplier, the validity
of which is greater than 24 (twenty-Four) months, CONTRACTOR shall be bound
to ensure the realization of all such guarantees or warrantees, until the expiry of
their validity.
3.18.1 The CONTRACT shall be and be deemed to be a Pakistani CONTRACT and shall
accordingly be governed by and construed according to the laws for the time
being in force in Pakistan. Should any more Conditions of CONTRACT be lacking
in legal effectiveness on account of ambiguity or for any other reason
whatsoever the same shall not impair the validity of any other conditions or of
the CONTRACT as a whole. Any conflict which cannot be resolved mutually will
be referred for arbitration under the arbitration Act. In case of default or conflict
the Chairman of Client shall be the Arbitrator and his decision shall be final and
binding.
3.18.2 if any or differences of any kind whatsoever shall arise between the ARCHITECT /
CONSULTANT and CONTRACTOR in connection with or arising out of the
CONTRACT, or the carrying out of the WORK (whether during the progress of the
WORK or after the termination, abandonment or breach of the CONTRACT), it
shall in the first place be referred to and settled by OWNER who within a period
of ninety (90) days after being requested to do so, shall give written notice of
his decision to the CONTRACTOR. Such decision in respect of every matter so
referred shall be final and binding upon the CONTRACTOR until the completion
36
of the WORK and shall forthwith be given effect to by the CONTRACTOR, who
shall proceed with the WORK with all due diligence.
3.19.1 Any notice be given to the CONTRACTOR under the terms of the CONTRACT shall
be served, by sending the same to the CONTRACTOR's Head Office as well as to
his local Site Office, by Registered Mail, or to leave it at the Head Office and the
local Site Office against receipt.
3.19.2 Any notice to be given to the OWNER and/or CONSULTANT by the CONTRACTOR
is to be sent to him by Registered Mail (as in Clause 3.19.1), or to be left against
receipt.
3.19.3 Simultaneously with the sending of notice, as aforesaid, copies thereof shall be
dispatched to the CONTRACTOR, the OWNER and CONSULTANT as the case may
be.
3.20 PHOTOGRAPHS
3.20.1 Contractor should put the photographs of all fabrication / manufacturing process
of all items
3.21.1 Shortly after issue of the Letter of Award of the CONTRACT, the ARCHITECT
and/or OWNER will require a meeting with the CONTRACTOR at OWNER’s office
at Karachi/Sukkur, to discuss equipment methodology and scheduling of WORK
and other similar matters which may be pertinent for the execution of the
WORK.
37
3A. SPECIAL CONDITIONS OF CONTRACT
(Blank spaces to be filled in by the Tenderer)
Subject Provision
38
3A.8.b Deduction of Mobilization 20% (Twenty percent) of the Gross
Advance value of the first and subsequent
Interim running payments until the
Mobilization Advance has been wholly
recovered.
39
3I. APPENDIX ‘I’ TO THE CONDITIONS OF CONTRACT
AGREEMENT
THIS CONTRACT (“Contract”) is made at Sukkur this ____ day of ______, 2021 by and between:
1. Sukkur IBA University
AND
2. M/S___________________________________________
Sukkur IBA University and M/S_____________________ are collectively referred hereto as the “Parties” and
individually as the “Party”.
WHEREAS:
1. Sukkur IBA University intends to get the work done of “Repair and Maintenance work of Masjid Shareef
at IBA Community College Khairpur”.
2. M/S _________________ represents that it has the requisite experience and expertise to undertake to do
the work, “Repair and Maintrnance work of Masjid Shareef at IBA Community Khairpur”. (“Project”),
SUKKUR IBA University and M/S_____________________. Consider it expedient to enter into this
Contract to set out the terms and conditions for the construction by
M/S_______________________________.
NOW THEREFORE:
In consideration of the mutual covenants and agreements contained herein, SUKKUR IBA and
M/S ____________________________, agree as follows:
1. In this Contract words and expressions shall have the same meanings as are respectively assigned to
them in the “Conditions of Contract” annexed hereto as per tender documents
3. In consideration of M/S __________________ carrying out the Project in accordance with the Terms of
Contract and Scope of Work, Sukkur IBA University shall make payment to M/S
_________________________ for the work done, as per the rates of BOQ.
4. M/S ___________________________________ shall commence the said work with THREE days of the
receipt of employers written order to proceed, and shall complete the work on or before the date stated
in the work order, the maintenance of rate of progress which will result in completion of the works within
the time specified in the tender is an essential feature of this contract. The Contractor agrees to proceed
with all due diligence and care to take all precautions to ensure completion in accordance with the
specified time, and shall not to lag at any stage.
5. Before start of work, the “Contractor”, shall submit the work completion schedule.
6. M/S ___________________________ agrees to wok completion schedule and also submit supply of
items in details and time.
7. M/S __________________________ agrees to provide samples all fixtures and fittings and other items,
and final sample approved and certified at site for final approval of the Client prior to execution of
reaming quantities.
8. Shop drawings must be submitted before execution of any activity, get its approval from the client and
Consultants.
9. M/S _________________________ agrees to abide by the BOQ, specifications and drawings complete in
all respects.
10. M/S ___________________________ shall be solely responsible for the Project and other works and
services set out in this Contract.
11. Liquidated damages in case of non completion of the work or for delay, must be 0.1% of contract amount
per day or part of day up to maximum of 10% of contract amount for whole work as finalized by the
OWNER.
40
12. Retention money would be @10% of gross amount of work done is to be deducted from the bill.
13. Completion period of the work in all respects i-e its functioning is 06 (Six Months)
16. If the performance of the Project is delayed, with reference to the Project Execution Schedule, on
account of M/S ________________________________ default, by FOUR (04) weeks, Sukkur IBA
University shall have the right to terminate this Contract.
18. Following documents shall be deemed to form and be read and construed as part of this agreement.
a) The conditions of contract.
b) Specification
c) The drawings.
d) Bill of quantities (BOQ).
16. This agreement shall not stand discharged on any account, but shall remain binding on the contractor.
IN WITNESS WHEREOF, this Contract is executed at Sukkur as of the day and year hereinabove, first written.
41
PERFORMANCE BOND
INSTITUTE OF BUSINESS GUARANTEE NO. :
ADMINISTRATION, DATE : _______________
SUKKUR AMOUNT : RS_____________
EXPIRY DATE : _______________
THIS BOND is executed at _______________ on this ____day of _____ 2021 by _____________, having
its registered Office at __________________ (hereafter called the “Surety” which expression shall
include its successors and assign) and M/S____________________., whose registered Office is
______________________________ (hereafter called the “Contractor” which expression shall include
its successors and permitted assigns) in favor of Sukkur IBA University, Sukkur hereafter called the
“Employer” which expression shall include its successors and permitted assigns).
WHEREAS the contractor by an agreement which shall be signed between the employer of the one part
and the contractor of the other part (hereafter called the “Contractor” has agreed commissioning,
adjusting, balancing & maintenance of certain works as therein mentioned viz Sukkur IBA University
__________________________________ (hereafter called the “Works” in conformity with the
precisions of the said contract.
AND WHEREAS one of the conditions of entering into contract Agreement is that the contractor shall
provide to the Employer a performance Bond in the sum of Rs. ____________
(Rupees__________________________________) for due fulfillment of the contract.
AND WHEREAS, the surety has agreed to give to the employer this performance Bond on the terms and
conditions mentioned hereinafter.
NOW THERFORE, THIS BOND WITNESSETH:
1. That the contractor shall duly perform and observe all the terms, provisions, conditions,
stipulations and his obligations container in the contract according to the true purport, intent
and meaning thereof or as may be determined by the Employer who shall be the Sole Judge in
the matter.
2. In the even of default being committed by contractor of which the Engineer shall be the sole
exclusive Judge, the surety shall satisfy and discharge within three days after demand of all the
damages sustained by the employer on account of the default of the contractor, as may
whatsoever to the contractor and without any question whatsoever and whether or not the
contractor disputes his liability in respect thereof and whether or not any arbitration or occur
case is pending in respect of dispute.
3. That the liability of the surety under this performance Bond shall be up to the amount
Rs. ________/- (Rupees ______________________________________________________________)
and this Bond shall become null and void if the contractor has carried out the works and also performed
his obligation strictly in accordance with the contract to the full satisfaction of the engineer, who will be
sole and exclusive judge to determine whether or not the contractor has carried the works and fulfilled
his obligation in accordance with the contract.
42
4. The Engineer can complete that portion of the works, which the contractor has not commenced
or not satisfactory executed, up to the amount of the performance Bond, at the Expense of the
surety.
5. No alteration in the term of the said contract made by agreement between the Employer and
the contractor or in the extent or nature of the works to be executed there under and no
allowance of time by the Employer or the Engineer under the said contract nor any forbearance
or forgiveness in or in respect of any matter or thing concerning the said contract on the part of
the Employer or the Engineer shall in any way release the surety from any liability under this
Bond
6. That the payment under this Bond shall be made by surety in the name of the Employer and a
receipt issued by the Employer shall discharge surety from his liability to the Employer under
this Bond.
7. That any notice or demand under this Bond may be made by the Employer and may be left at
surety address mentioned herein or at any changed address as may be communicated by Surety
to the Employer in writing against receipt of the Employer, or the said notice of demand may be
sent by registered post Surety addressed as afore said and shall be deemed to have been at the
time when it should have been delivered in due course of the post and a corticated signed by
the Employer that the envelop containing the notice was posted shall be conclusive.
8. Our obligations under this guarantee shall at all times within the validity period of this
guarantee not exceed the Guaranteed Amount of Rs. _____________/- (Rupees
________________________________________________________) and that this guarantee
shall remain valid up to xx-xx-xxxx. Claim of outstanding dues if any, under this guarantee
must be received by us during business hours on or before xx-xx-xxxx. Should we receive
no claim from you on or before xx-xx-xxxx, our liability under this guarantee will become
null and void whether this original Guarantee is returned to us or not
43
MOBILIZATION ADVANCE GURANTEE
Guarantee No. :
Date :
Amount :
Expiry :
Contract :
Contractor :
Surety :
To :
AND whereas the Owner has agreed to pay the Contractor an amount of Rs:_______________
/-(Rupees _____________________) being 10% percent of the accepted Contract
price as Mobilization Advance against an irrevocable Guarantee for actual losses (Except
Opportunity Cost) suffered and determined by you not exceeding the amount of
Rs:_______________ /-(Rupees_________________________) or any part thereof which
may be outstanding against the Contractor without any reference to the Contractor or any
other person whosever and this Guarantee shall not be affected by Owners granting time
extension or any other indulgence to the said M/S
_______________________________________ .
We ______________Bank( the “Surety”) in consideration of your having awarded the Contract
to the Contractor M/S__________________________, do hereby undertake and guarantee
irrevocably and unconditionally on demand by the Owner to pay forthwith the Owner the
amount of advance up to and not exceeding Rs.___________/-
(Rupees_____________________________________________________ ) or any part thereof
which may be outstanding against the Contractor without any reference to the Contractor or
any other person whosever and this Guarantee shall not be affected by Owners granting time
extension or any other indulgence to the said
M/s___________________________________________________________
The amount of this Guarantee shall be reduced progressively as the recoveries towards the
advance are affected by the Owner from the Contractor through their running bills in
accordance with the terms of the said agreement and our liability at no time shall exceed the
amount of Rs. /-(Rupees ) or the balance
recoverable amount as may be certified by you as the case may be and your certified to the
effect shall be conclusive and binding upon us we agree to keep the Guarantee valid and in full
44
force from this date up to the time of deduction made by the Owner by way of advance have
equaled the amount of this Guarantee.
NOW THE CONDITION of the above written BOND is such that.
a) If the Owner shall certify in writing that entire mobilization advance has been recovered
from the Contractor or
b) If upon the written certificate of the Owner stating that the mobilization advance or any
part thereof is due to the Owner under the Contract such sum not exceeding the
amount of the above written bond as the Owner demand in writing.
Then either in case of the Owner certifying clause (a)hereinabove or where the Owner has
enforced this bond under clause (b) hereinabove and has received the requisite payment from
us this obligation shall be null and void otherwise it shall be and remain in full force and
mobilization advance is made or in the terms of the Contract or the conditions on which the
mobilization advance is made or in the extent and nature of the works shall in any release the
surety from any liability under the above written bond.
This Guarantee is binding on us and our successors in interest our obligations hereunder shall
be as if we are principal debtor and shall be under unconditional and continuing obligation and
will remain in force notwithstanding any time extension given indulgence forbearance shown
or any amendments or alterations made in the obligation or the terms conditions and
covenants between the Owner and the Contractor and / or any Contract documents.
NOTWITHSTANDING any thing contained herein before our liability under this guarantee is
restricted to Rs._______________ /-(Rupees,_________________________) and in
time up to xx.xx.xxxx .This Guarantee is valid up to xx.xx.xxxx all claims under this guarantee
must be received by the Bank in writing on or before the said expiry date i.e. xx.xx.xxxx, within
banking ours where after no claim of whatsoever nature will be entertained and our Bank will
be relieved from all liabilities of this Guarantee whether the original Guarantee Instrument is
returned to us or not.
Moreover, this Guarantee is governed by and shall be construed in accordance with, the laws
of Pakistan provided that such laws do not contradict the Islamic Sharia’h.
45
GENERAL SOURCE OF SUPPLY OF MATERIAL/ GENERAL NOTES
1. Bricks in Pacca brick works used is sub structure will be from Rahim Yar Khan (A-I
Quality, approved by Client)
2. Bricks in face brickwork will be from Lahore. (A-I Quality, approved by Client).
3. Fine aggregate (Hill sand) will be from Bholari quarry.
4. Coarse aggregate (Crush stone, Ballast) will be from Ubbhan Shah.
5. Deformed Steel from Karachi (60 grade steel by Amereli) will be used, no any rust will
be allowed, and at site steel must be covered with plastic covers to save it from
humidity/moisture.
6. DG cement (Manufactured at Dera Ghazi Khan) will be used in all construction work.
Proper and adequate steps must be taken for curing.
7. New Steel/marine ply shuttering will be used for RCC work in, columns, and beams.
8. Up to plinth level Sulpahte Resistant Cement (DG) will be used
9. All material to be used will be laboratory tested along with authentication certificate
and finally selected by the client/ Consultant.
10. Use of vibrator is must in every RCC work.
11. Before execution of any activity, shop drawings must be submitted for its
approval, then execution, if required sample should be prepared for approval.
12. Batch plant/ Semi Auto mixers shall be used in cementing work.
13. Before start of work proper work schedule for completion on Bar Chart, or on
any software based planning schedule for whole project must be submitted, along with
this a fortnightly schedule to monitor and evaluate the progress of work.
14. Qualified and Experienced engineer must be available at site.
15. You must establish site office along with site material testing lab for material
testing.
16. All safety measures for Staff, Surrounding property etc must be taken as asked
by Client.
Name of firm/Contractor: _____________________________________
Date: ____________________________________________________
46
Repair and Maintenance work of Masjid Shareef @ IBA Community College
Khairpur Mirs.
SUMMARY
S.N DESCRIPTION AMOUNT
1 CIVIL WORK
2 PLUMBING WORK
3 ELECTRICAL WORK
TOTAL AMOUNT Rs:
47
Repair and Maintenance work of Masjid Shareef
at IBA Community College Khairpur Mirs.
Sr. Description Unit Quantity Rate Amount Remarks
A) CIVIL WORK
DISMENTLING: Dismantling of Old PCC
Floor & Roof treatment at least or avg:
1 thickness as 3''-9" Depth and removing
Material Shifted away from site up to lead
1.5 Km. Cft 4,950
DISMENTLING: Dismantling of existing BM
wall for making washrooms and removing
2
of same Material and Shifted away from
site up to lead 1.5 Km. Cft 36
EXCAVATION:
Excavation for foundation in any type of
3 soil 5' depth from NGL i/c dewatering as
per specification and shifting of excavated
earth lead upto 1.5km. Cft 321
BACKFILLING:
4 Back Filling With River sweet Sand as per
specification and directed by Site Incharge. Cft 412
Stone Soling: P/L 6'' thick layer size of
5 stone 2" to 3' and voids filled with fine
powder (Khaka) and compaction as per
instruction of Site Incharge. Cft 20
6 Plain & Reinforced Concrete
49
Plaster: Providing and applying 1:4 cement
plaster with thickness in two layers (12mm+
13mm) on interior/exterior surfaces using O.P.
Cement/SR, as directed by Engineer at any
height and level including the cost of supply &
fixing 8" wide expanded metal lath at the
junction of structural member and block wall,
9 making chamfered edges as desired, rounding
of corners at junctions and making drip courses
stops, groves, corner and stop beads wherever
required, including scaffolding, preparation,
treatment, curing, etc. Complete in all respects
and conforming to the requirements of
drawings, specifications as per instruction of
engineer Sft 2151
10 FLOORING & SPECIAL FINISHES
Tile In Toilet Area : P/L of Ceramic tile
300mmx600mm (Master) i/c pond as
required, light color on walls and dark color
on floor with all necessary allied as base
10.1
beds, mortar ratio 1:3, filling by grouting
and spacer for proper lining and complete
in all respects as per instruction of Site
Incharge.
Floor Sft 40
Walls Sft 252
MARBLE: Providing & Fixing of full body
Marble (Ziarat White Marble/Equivalent)
600mmx300mmx12mm, including 1" thick
base in 1:3 cement sand ratio, washing,
cleaning and grouting/filling by white
cement and also providing 1"-1 1/2"
10.2 Marble Strip for proper lining on every 4ft
width etc. complete in all respect using
approved grouting etc and proper grinding
with complete polish in shape of smooth
finish and complete in all respect as per
drawing and specifications and /or directed
by the Engineer Incharge. Sft 5385
11 CONVENTIONAL ROOF TREATMENT
Proper cleaning of surface completely, then
Screeding 3" thick 1:3:6 for proper
maintain slope, laying of water proofing
membrane sheet 4mm thick/Bituline trpica
-onduline group) than 2'' thick CC topping
1:2:4 & dividing in panels (4' X 4') and 1/2"
gap b/w panel to panel and filling of cavity
with bitumen 10/20 grade as per
instruction of Site Incharge Sft 4007
50
GIRDERS: Providing and Fixing Girders
(Battala Co) in Ceiling Size 4"x 8" and 5Kg
Weight of per/Rft, Red oxide & two Coat
Oil paint and re-construct same portion of
12
wall as removed/dismantled to fix girder in
proper position by using Jacks for fixing of
Girders under fixed slab etc as per
instruction of Site Incharge.
Girders 4"x8"- weight 5Kg/Rft Rft 322
T-IRON : Providing and laying of T-Iron
3"x1-1/2": P/L T-Iron having weight of 1
13
kg/Rft -Battala as per direction of Site
Incharge Rft 80
Roof Tile: Providing and laying of Roof tile
6"x12": P/L of roof tiles with proper way
14
and over grouting with cement mortar 1:4
as per instruction of Site In charge. Sft 65
PLASTIC EMULSION PAINT: Providing and
laying of Plastic Emulsion (03 Coats of ICI
Dulux or Equivalent) i/c filling by wall putty,
15
primer for base coat and applying 03 coats
with fully finish as per instruction of Site
Incharge.(Walls+Roofs) Sft 8035
16 ENAMEL PAINT
Providing and laying of Enamel Paint of
Girders and T-Iron i/c proper coat of red
16.1
oxide coat,03 coats of Oil Paint with proper
finish as per instruction of Site Incharge. Sft 2824
Providing and laying of Enamel Paint of
Doors and windows (03 Coats of ICI Dulux
or Equivalent) i/c filling by wall putty,
16.2
primer for base coat and applying 03 coats
with fully finish as per instruction of Site
Incharge. Sft 1135
Weather Shield: Providing and applying
three coats of Weather Shield and shade
including scrabing, cleaning, preparation of
17 surface applying a coat of primer
preparation of base etc. Complete in all
respect as instructed and approved by
engineer.
Sft 4836
18 ALUMINIUM DOORS
51
Providing, and fixing of aluminum Glass
Doors as per Drawing/approval anodized
PAK aluminum alloy extruded Deluxee
section, with netted Shutter dull natural
finish, Deluxee but not less than 2mm thick
section with 6mm Glazing or its equivalent
make as indicated on the drawings with
frame of grade as specified above using
stainless steel screw, including (6mm) with
clear glass imported ( from Saudi Arabia )
including ,heavy duty aluminum handles,
hinges, gaskets, silicon filling, all around
completing specification and to the entire
satisfaction of the Engineer.(Including
Dismantling of Existing) Sft 151
19 Windows/Doors (Deodar wood)
Providing and Fixing 1.5'' thick first class
window/ Door (Deodar wood) with
wooden FRAME Painted or polished
approved quality of Oxidized hinges, Brass
Screw, Tower Bolts, other Hardware of
Brass i/c Iron hold fasts, complete in all
respect as per drawing/Specification or
Directed By Engineer. Sft 78
Plinth Protection: Comprising of 6'' thick
1:4:8 and 2" CC topping divided into panels
20
with Glass Strips and brick masonry 9" thick
as per drawing/instruction of site Incharge. Sft 180
Manholes: Construction of Brick masonry
Manhole (600x600mm) including
excavation,backfilling,6"thick Lean 1:4:8
bed 1:2:4 ,Brick Masonry 9" thick, Plaster
21
1:4(internal+ external)removing surplus
excavated material, RCC cover with
nominal steel as per direction of site
Incharge. Nos 2
Total Amount of Civil Work (Rs.)
52
Repair & Maintenance work of Masjid Shareef
at IBA Community College Khairpur Mirs.
Sr. Description Unit Quantity Rate Amount Remarks
B Plumbing Work
1 Providing and Laying (UPVC) pipe; including
all supports, fittings, markings, joints,
complete the piping installation approved By
Engineer Dadex Nikasi-Pushfit Rubber Ring
Socket Joint/Master-UPVC
4" dia Rft 100
2 Eastern Water Closet-PORTA
S/I white glazed fireclay European W.C with
Flush Tank(Sonex) & P-trap etc i/c all water
supply pipes, CP angles valves, CP
connectors,UPVC drainage pipe connecting to
the nearest manhole as per specification of
Site Incharge. Nos 2
CP Angle valve/tee cock for flush tank/cistern
water inlet (Sonex/Master) Nos 2
CP connectors with nuts and fittings Nos 2
Single bibcock(Sonex/Master) Nos 2
3 Wash Basin PORTA
S/I of white glazed fireclay hand wash basin,
complete with all water supply pipes, waste
fittings, trap, plug and chain and CP Water
mixer/Basin Mixer-Sonex and Drainage line 2"
to the nearest floor trap. Nos 2
CP Tee valves for wash basin hot and cold
water inlet Nos 4
Waste Pipe Nos 2
Basin Mixer Sonex approved from Site
Incharge Nos 2
4 COLD WATER INSTALLATION
PPR piping as per DIN 8077-8078, PN20 with
welded joints: i/c all supports, fittings PN25,
markings, painting materials, firestops,
expansion joints, consumables and other
required materials to complete the piping
installation as per instruction of Site Incharge.
DADEX Ploydex
PPR pipe 20mm Rft 30
PPR pipe 25mm Rft 15
25mm Gate Valve ARS brass Nos 1
5 HOT WATER INSTALLATION
PPR piping as per DIN 8077-8078, PN20 with
welded joints: i/c all supports, fittings PN25,
markings, painting materials, firestops,
expansion joints, consumables and other
53
required materials to complete the piping
installation as per instruction of Site Incharge.
DADEX Ploydex
PPR pipe 20mm Rft 30
PPR pipe 25mm Rft 15
25mm Gate Valve ARS brass Nos 1
Roof drain/Spouts complete with all respect.
4" dia i/c 3ft pipe having 4" dia with complete
6 finish as per instruction of Site Incharge Nos 6
Floor waste SS Jali 6" dia for proper drain of
7 water Nos 4
Total Amount of Plumbing works (Rs.)
54
C ELECTRICAL WORK
S# Description Quantity Unit Rate Amount Remarks
Providing & installation of gang switch CLIPSAL (E-Series)
1 10A , 220 V , 4-Gang Switch Unit 10 No.
2 10 A , 220 V , 3 Gang Switch Unit 10 No.
3 10 A , 220 V , 2 Gang Switch Unit 8 No.
4 10 A , 220 V , 1-Gang Switch Unit 5 No.
5 Fan Dimmer (Regulator) 12 No.
6 Internationa Switch Socket (Dimmer) 10 No.
7 20A Switch socket for AC 4 No.
ELECTRICAL WIRING (Pakistan cables)
Supply & installation of wiring of light
point with 2x1.5 +1.5 sq.mm single core
1 12 No.
PVC pipe /duct in 25mm dia Size of PVC
Conduit
2 Same as above but point to point 12 No.
Supply & installation of wiring of light
3 point with 2x2.5 sq.mm single core PVC 10 No.
in 25mm dia Size of PVC Conduit
4 Same as above but point to point 5 No.
Supply & installation of wiring of light
5 point with 2x4 sq.mm single core PVC in 4 No.
25mm dia Size of PVC Conduit
6 Same as above item but point to point 3 No.
Providing & wiring of 13 Amps 3 pin
power socket outlet wired with
7 5 No.
3x2.5mm2 in 25mm dia Size of PVC
Conduit
8 Same as above item but outlet to outlet. 4 No.
Wiring of 20A switch socket unit For
AC from DB to first outlet with following
9
size of wires in 25mm dia PVC conduit
as shown on drawings.
2x6 Sq.mm Cu/PVC + ECC 1x4 Sq.mm
a 4 No.
Cu/PVC
Same as above item but wiring from
b 4 No.
outlet to outlet.
Providing , Supply & Installation of below items complete in all
respects.
Exhaust Fan 12" Square, 100 % copper (Pak
1 3 No.
Fan / GFC Fans)
2 LED Saver 11W with 15000h life (Phillips) 8 No.
LED Tube Light (Phillips Master ) 50000h Life
10 No.
with complete accessories
Digital Wall clock for Masjid as already
3 1 Nos
installed at Sukkur IBA Mosque.
Water Dispenser (Orient/Homage/Super
Asia/Dawlance) i/c Bottle 19ltr and wooden
4 1 Nos
Base for dispenser) as per instruction of Site
Incharge.
55
Providing , Supply & Installation DB(Distribution Board) complete in
all respects.
Supply, Installation, testing &
commissioning of following Distribution
Boards as shown on drawing made with 14
SWG sheet steel housing including all
installation accessories such as Rawal bolt
etc. Complete in all respects.
Note: (Refer Single Line Diagram)
1) All the DB should be front accessible and
maintainable.
2) Cost of Lighting Control Relays & Power
Supplies should be Included in Distribution
Boards .
3) The transportation and placement of DBs
unto dedicated location is also included in
the work scope, complete in all respects
including leveling, grouting etc.
4) Laser engraved tags required as mention
in SLDs
5) Space for circuit tagging required with
permanent installation on protective sheet
1 via rivets
6) 20% space required in DB for future
provision
7) Tin platted Imported Cu bus bar with
heat shrink color coded sleeves to be used.
8) Hindged protective metallic door
required with knob/handle.
9) Braided Door earth required.
10) Lockable handle required for main door.
11) As-built drawing pocket.
12) Cable hanging arrangement.
3 Pole - 100 A Adjustable breaker
(ABB/Terrsaki/Schneider)
3-Pole , 20/32 A Brekaer = 5 Pcs
2-Pole , 16/20/32 A Breaker = 8 Pcs
Single Pole, 10/16/20/32 A Breaker = 16 Pcs
Minimum One Year Warranty Required
from date of successful commissioning on
site.
Main DB 1 Nos
Total Amount
56