Distribution Management Systems - Robert Uluski
Distribution Management Systems - Robert Uluski
Management Systems
Presented By:
Bob Uluski
Electric Power Research Institute
CRN Summit
Cleveland Ohio
July 20, 2011
•What is a DMS?
•Key Applications
•Planning, Procuring,
and Implementing a
new DMS
•Open discussion
2
What is a DMS?
• A Decision Support
System to assist the
control room and field
operating personnel with
the monitoring and
control of the electric
distribution system in an
optimal manner while
improving safety and
asset protection
3
What are the Major DMS Components?
4
Distribution Management System Components
SCADA provides the foundation
Field Devices
Switched Cap
Banks
Line regulators
Line switches
Real
Time Faulted circuit
Indicators
(FCIs)
Distribution DG, Energy
SCADA storage
Substation Switched
Cap Banks
Real
•Real time data
acquisition Time CBs, MODs
•Basic operational
alerts (alarms) Vreg/LTC
•Remote control
Subs secondary
•Tagging
equip
•Display real time
data
•Data archiving
Substation
Devices
5
Distribution Management System Components
DMS Applications Use SCADA Capabilities
Field Devices
Switched Cap
Banks
Line regulators
Line switches
Real
Time Faulted circuit
Indicators
(FCIs)
Advanced Distribution DG, Energy
Applications SCADA storage
Substation Switched
Cap Banks
Real
•Intelligent alarm •Real time data
processing acquisition Time CBs, MODs
•On-line power flow •Basic operational
alerts (alarms) Vreg/LTC
•State estimation
•Remote control
•Distribution model Subs secondary
•Tagging
•Switch order mgmt equip
•Display real time
•VVO data
•FLISR/ONR •Data archiving
Substation
•Contingency Analysis Devices
•DER Management
6
Distribution Management System Components
Interactions with Operational Support Systems
Field Devices
Near
Mobile Data Switched Cap
Advanced Real System Banks
Time,
Metering “day (MDS) Line regulators
after”
System
Line switches
(AMI) Switch orders,
R-T data
Real
Temp Time Faulted circuit
Model Indicators
updates
Outage (FCIs)
Substation Switched
Cap Banks
Real
•Intelligent alarm •Real time data
Time
Geographic processing acquisition CBs, MODs
“As •On-line power flow •Basic operational
Information engineered” •State estimation
alerts (alarms) Vreg/LTC
•Remote control
System (GIS) state of the
system
•Distribution model
•Tagging
Subs secondary
•Switch order mgmt equip
•Display real time
•VVO data
•FLISR/ONR •Data archiving
Substation
•Contingency Analysis Devices
•DER Management
7
The Distribution Management System
Field Devices
Near
Mobile Data Distribution Switched Cap
Advanced Real System Management Banks
Time,
Metering “day (MDS)
after” System Line regulators
System
Line switches
(AMI) Switch orders,
R-T data
Real
Temp Time Faulted circuit
Model Indicators
updates
Outage (FCIs)
Substation Switched
Cap Banks
Real
•Intelligent alarm •Real time data
Time
Geographic processing acquisition CBs, MODs
“As •On-line power flow •Basic operational
Information engineered” •State estimation
alerts (alarms) Vreg/LTC
•Remote control
System (GIS) state of the
system
•Distribution model
•Tagging
Subs secondary
•Switch order mgmt equip
•Display real time
•VVO data
•FLISR/ONR •Data archiving
Substation
•Contingency Analysis Devices
•DER Management
8
Combined DMS/OMS System
Field Devices
Near
Mobile Data Distribution Switched Cap
Advanced Real System Management Banks
Time,
Metering “day (MDS)
after” System Line regulators
System
Line switches
(AMI) Switch orders,
R-T data
Real
Temp Time Faulted circuit
Model Indicators
updates
Outage (FCIs)
Substation Switched
Cap Banks
Real
•Intelligent alarm •Real time data
Time
Geographic processing acquisition CBs, MODs
“As •On-line power flow •Basic operational
Information engineered” •State estimation
alerts (alarms) Vreg/LTC
•Remote control
System (GIS) state of the
system
•Distribution model
•Tagging
Subs secondary
•Switch order mgmt equip
•Display real time
•VVO data
•FLISR/ONR •Data archiving
Substation
•Contingency Analysis Devices
•DER Management
9
Typical Distribution Control Center a
Few Years Ago
10
Electronic Map Visualization
11
Current Trend in Control Center Design
12
• DMS Applications
– Basic Applications
– Advanced Applications
13
Advanced Display Capabilities
• Standard display
capabilities
Substation One-
Line Schematic
Trend line
Tabular
14
Advanced Display Capabilities
• Advanced display
capabilities
15
Advanced Display Capabilities
16
Highlighting abnormal sections of the
distribution feeders
17
Intelligent Alarm Processing
18
Data Archiving
• Data Archiving
– Store and retrieve data,
alarms, event logs, feeder
configuration changes, etc
– Allow access to data inside
and outside the control center
for studies etc.
– Most DMS vendors support
interface to commercial data
management systems (e.g.,
OSI Soft PI)
19
Tagging Permits Clearance Management
20
Advanced DMS Applications
21
Distribution System Model
• Accurate distribution system model is essential element of DMS
(the “heart and soul”)
• Provides basis for graphical displays and advanced applications
– Network model
– member (Load) Model…..
22
Distribution System Model:
One Model – Two Parts
Physical Model
– Energized equipment Load Model
• wires, transformers, switches,
capacitor banks, voltage – member Load Profiles
regulators, distributed energy – Load-Voltage Sensitivities
resources
– Connections between equipment
23
Distribution System Physical Model
24
Distribution System Physical Model
25
Distribution System Physical Model
• Building and updating the physical model
– “Permanent” changes from GIS
– “Temporary” changes from SCADA and by operator entry
– Need to determine source of substation model (often this
information is not maintained via GIS)
– Planned alterations and additions
• Allows utility to enter information for work that is planned or
work in progress, but not yet energized – reduced latency
when work is energized
• Allows utility to consider work in progress when planning future
outage
26
member Load Model – Load Profile
Applications like on-line power flow (OLPF) require a means of
estimating the load at distribution service transformer Load Profile - Customer 1
• Not practical to send all AMI meter data for all meter 0.8
– Weekend 1
Customer 1
Estimate reactive power consumption at each transformer via
0.6
Customer 2
0.4
11
13
15
17
19
21
23
1
9
Hour of Day
27
member Load Model – Load Voltage Sensitivity
28
Distribution System Model – DMS Perspective
29
On Line Power Flow (OLPF)
• Similar to engineering analysis tool
– Engineering tool – peak load analysis
– OLPF – what’s happening in “near real time
• Calculates electrical conditions right now
(near real-time) at all points on the
distribution feeder
• Provides “visibility” in places where no
measurements exist …. alerts dispatcher to
trouble spots
• OLPF used by many DMS applications that
require up-to date electrical information
• Characteristics:
– 3 phase unbalanced
– Handles radial and “weakly-meshed” distribution
feeders
• “Study mode” - uses past or planned feeder
model in off line mode
30
On Line Power Flow (OLPF)
• Similar to engineering analysis tool
– Engineering tool – peak load analysis
– OLPF – what’s happening in “near real time
• Calculates electrical conditions right now
(near real-time) at all points on the
distribution feeder
• Provides “visibility” in places where no
measurements exist …. alerts dispatcher to
trouble spots
• OLPF used by many DMS applications that
require up-to date electrical information
• Characteristics:
– 3 phase unbalanced
– Handles radial and “weakly-meshed” distribution
feeders
• “Study mode” - uses past or planned feeder
model in off line mode
31
OLPF Study Mode
• “Off line” version of DMS power flow useful for
analyzing:
– Past events
– Upcoming (future) events
• Runs in background – does not impact real-time
(live) applications
• Specify time and date for which study is required
• Study mode estimates the load for past or future
events
• Potential use for all engineering analysis
32
Load Estimation for OLPF
Bus
Voltage
CB R
kW
kVAR
33
On Line Power Flow
• If you knew all the electrical impedances, could do a conventional power flow fairly easily
– Usually have a reasonably good idea of what the line impedance is
– Generally don’t know the impedance of every house –depends on which appliances are
on – changes all the time
Bus
Voltage
CB R X R X R X R X R X
XL XL XL XL
kW
kVAR RL RL RL RL
34
On Line Power Flow
Can use kW rating of distribution service transformers to estimate
the load:
– Split measurement from head-end of feeder in proportion to kW rating of the
transformer
Bus
Voltage
CB R
kW
25kW 1 kW 25kW 1 kW 25kW 1 kW 25kW 1 kW
4 kW
35
On Line Power Flow
This approach works well as long as all members have the same “load
profile” (Fraction of peak load at given time and given day)
Bus
Voltage
CB Recloser
36
Using load profiles to estimate the load
1 1
0.8 0.8
0.6 0.6
0.4 0.4
0.2 0.2
0 0
1 6 11 16 21 1 6 11 16 21
Ho ur o f D ay Ho ur o f D ay
member #1 member #N
37
Load Estimation with Different Load
Profiles
• But if load profile is different for each member, method doesn’t work
• Load estimate = kW of distribution transformer x (fraction of peak load from
load profile) / total of all members
– member 2 gets a little more of the load estimate at hours 11 and 22
– member 1 gets a higher percentage of the load during hour 18
0.8
0.6 Customer 1
Customer 2
0.4
0.2
0
11
13
15
17
19
21
23
1
Hour of Day
38
Summary of Load Estimation Approach
• Obtain load profile for each member for given day (weekday,
weekend, special day) and season
• Determine percent of peak load for each member at given time of day
• Load Estimate For member “i” = (SCADA measurement from head
end of feeder) x (transformer rating for member “i”) x (Percent of peak
load from load profile for member “i”) / sum of ∑ (ratings of all
transformers)
39
Use of Meter Readings from AMI
• Can use meter readings from Advanced Metering Infrastructure (AMI) to:
– Create a load profile for each member/transformer based on yesterday’s AMI data
– Determine transformer load for selected members using nearly-real-time data for
selected members
Bus
Voltage
CB Recloser
Meter Data
Management
System
40
Switching Order Management
41
Switching Order Management
42
Switching Order Management
43
Switching Orders
Geographic versus Schematic Views
44
Switching Orders
Geographic versus Schematic Views
45
Off-Line Validation of Switch Orders
• Allows operator to single step
through switching order in Study
Mode
46
Automatic Generation of Switching Orders
• Some DMS include facility for
automatic generation of switching
orders based on established work
rules and practices
47
Volt-VAR Control and Optimization
48
DMS Conservation Voltage Reduction (CVR)
49
SCADA (Rule Based) Volt-VAR Control
Part 1: VAR Control (Power Factor
Correction)
Voltage Profile
124
122
120
VVO/CVR
Processor
118
116
RTU 0 0.25 0.5 0.75 1
P = 3846 kW
Q = 1318 kVAR
PF = .946
Losses = 96 kW
50
SCADA (Rule Based) Volt-VAR Control
Part 1: VAR Control (Power Factor
Correction)
Sample Rules:
1. Identify “candidate” cap banks for switching
• Cap bank “i” is currently “off”
• Rating of cap bank “i” is less than
measured reactive power flow at head end
VVO/CVR of the feeder
Processor
2. Choose the “candidate” cap bank that has the
lowest measured local voltage
RTU
3. Switch the chosen cap bank to the “ON” position
P = 3846 kW
Q = 1318 kVAR 1 2 N
PF = .946
Losses = 96 kW
51
SCADA (Rule Based) Volt-VAR Control
Part 1: VAR Control (Power Factor
Correction)
Voltage Profile
124
122
120
VVO/CVR
Processor
118
116
RTU 0 0.25 0.5 0.75 1
P = 3846 kW
Q = 1318 kVAR Chosen
cap bank
PF = .946
Losses = 96 kW
52
SCADA (Rule Based) Volt-VAR Control
Part 1: VAR Control (Power Factor
Correction)
Voltage Profile
124
122
120
VVO/CVR
Processor
118
116
RTU 0 0.25 0.5 0.75 1
P = 3880 kW
Q = 920 kVAR Chosen
cap bank
PF = .973
Losses = 91 kW
53
SCADA (Rule Based) Volt-VAR Control
Part 1: VAR Control (Power Factor
Correction)
Voltage Profile
124
122
120
VVO/CVR
Processor
118
116
RTU 0 0.25 0.5 0.75 1
P = 3920 kW
Q = 687 kVAR
PF = .985
Losses = 89 kW
54
SCADA (Rule Based) Volt-VAR Control
Part 1: VAR Control (Power Factor
Correction)
Voltage Profile
124
122
120
VVO/CVR
Processor
118
116
RTU 0 0.25 0.5 0.75 1
P = 3940 kW
Q = 532 kVAR
PF = .991
Losses = 88 kW
55
SCADA (Rule Based) Volt-VAR Control
Part 1: VAR Control (Power Factor
Correction)
Voltage Profile Before and After
124
122
120
VVO/CVR
Processor
118
116
RTU 0 0.25 0.5 0.75 1
P = 3940 kW
Q = 532 kVAR
PF = .991
Losses = 88 kW
56
SCADA (Rule Based) Volt-VAR Control
Part 2: Voltage Control (CVR)
RTU
57
SCADA (Rule Based) Volt-VAR Control
Part 2: Voltage Control (CVR)
Voltage Profile
124
122
120
VVO/CVR
Processor
118
116
RTU 0 0.25 0.5 0.75 1
58
SCADA (Rule Based) Volt-VAR Control
Part 2: Voltage Control (CVR)
Voltage Profile
124
122
120
VVO/CVR
Processor
118
116
RTU 0 0.25 0.5 0.75 1
P = 3898 kW
Q = 508 kVAR
PF = .992
Losses = 88 kW
59
SCADA (Rule Based) Volt-VAR Control
Part 2: Voltage Control (CVR)
Voltage Profile
124
122
120
VVO/CVR
Processor
118
116
RTU 0 0.25 0.5 0.75 1
P = 3805 kW
Q = 508 kVAR
60
SCADA (Rule Based) Volt-VAR Control
Part 2: Voltage Control (CVR)
Voltage Profile
124
122
120
VVO/CVR
Processor
118
116
RTU 0 0.25 0.5 0.75 1
P = 3778 kW
Q = 492 kVAR
61
SCADA (Rule Based) Volt-VAR Control
Part 2: Voltage Control (CVR)
Voltage Profile Before and After
124
122
120
VVO/CVR
Processor
118
116
RTU 0 0.25 0.5 0.75 1
P = -41 kW (1.05%)
Q = -809 kVAR (61%)
62
Volt-VAR Optimization
63
Volt VAR Optimization (VVO) System Operation
Voltage Feedback,
Accurate load data Switch
Status
64
Volt VAR Optimization (VVO) System Operation
Real-Time
Cuts, jumpers, Updates
manual switching
IVVC requires an
accurate, up-to date
electrical model
65
Volt VAR Optimization (VVO) System Operation
OLPF calculates
losses, voltage
profile, etc
Powerflow
Results
66
Volt VAR Optimization (VVO) System Operation
Determines optimal
set of control
actions to achieve a
desired objective
Powerflow
Results
Alternative
Switching
Plan
67
Volt VAR Optimization (VVO) System Operation
Determines optimal
set of control
actions to achieve a
desired objective
Optimal
Switching
Plan
68
Predictive Fault Location
• Objective: Assist field crews in pinpointing
fault location
• Fault distance provided by protective relay
IEDs not accurate:
– Assumes homogeneous wire
size/arrangement
– Fault impedance unknown
• DMS Approach:
– “Reverse short circuit” analysis
• Obtain fault magnitude and type (A,
B, C, A-B, etc) from relay IED
• Determine possible fault locations
using DMS short circuit analysis tool
and associated feeder model
69
Fault Location Isolation & Service Restoration (FLISR)
70
Nature of the Problem
• When a permanent fault occurs, members on “healthy” sections of the
feeder may experience a lengthy outage
POWER RESTORED
Feeder
member Field TO memberS ON
FAULT Reports Crews
Fault Back to
Located HEALTHY SECTIONS
OCCURS Outage On-Scene Normal
OF FEEDER
Fault Investigation Time to Perform
Travel Time & Patrol Time Manual Switching Repair Time
45 – 75
minutes
71
FLISR Operation – Normal State
Net Load
= 1 MW
3
Substation #1 Net Load Net Load Substation #3
= 2.5 MW = 2 MW
1 2 6 7 8
72
FLISR Operation – A Fault Occurs
3 No
Substation #1 Fault
Fault
Substation #3
Fault
Current
1 2 6 7 8
Fault Fault No
Fault
73
CB Trips – Feeder De-energized
Fault Fault No
Fault
74
CB Recloses – Fault Still There
Substation #2
FDs at switches 1 and 2
5 remain picked up
Still no FLISR control
actions
4
3 No
Substation #1 Fault
Fault
Substation #3
Fault
Current
1 2 6 7 8
Fault Fault No
Fault
75
CB Trips Again – Feeder Deenergized
Circuit breaker trips and
locks out
Substation #2
Entire circuit de-energized
5
(dotted line)
FDs at switches 1 and 2
remain picked up
4
FLISR open/close logic
triggered
3 No
Substation #1 Fault
Substation #3
Fault
1 2 6 7 8
Fault Fault No
Fault
76
FLISR Step 1 – Identify Faulted Section
Faulted
3 No
Feeder
Substation #1 Fault
Substation #3
Section Fault
1 2 6 7 8
Fault Fault No
Fault
77
FLISR Step 2 – Isolate Faulted Section
Faulted
3 No
Feeder
Substation #1 Fault
Substation #3
Section Fault
1 2 6 7 8
Fault Fault No
Fault
78
FLISR Step 3 – Restore “Upstream” Section
Faulted
No
Feeder 3
Substation #1 Section
Fault
Substation #3
Fault
1 2 6 7 8
Fault No
Fault
79
FLISR Step 4 – Restore “Downstream” Section
(if possible)
3 No
Substation #1 Fault
Substation #3
Fault
1 2 6 7 8
Fault No
Fault
80
FLISR Step 4 – Restore “Downstream” Section
(if possible)
Fault No
Fault
81
FLISR Step 4 – Restore “Downstream” Load
(If Possible)
3 No
Substation #1 Fault
Substation #3
Fault
1 2 6 7 8
Fault No
Fault
82
FLISR Step 5 – Restore “Downstream” Load
(continued)
Now check available capacity on
Substation #2 Substation #3
Compare with pre-fault net load on
5 section 6-7
Net load exceeds available capacity!
Section 6 - 7 remains de-energized
4
End of FLISR operation
3 No
Net
Substation #1 Fault
Load = Substation #3
Fault 2 MW
1 2 6 7 8
Available
Capacity
Fault No
Fault
= 1 MW
83
Time Line Without and With FLISR
member Feeder
Fault Fault Back to
Reports
Located Normal
Occurs Outage
POWER RESTORED
45 – 75 TO memberS ON
minutes HEALTHY SECTIONS
POWER RESTORED
OF FEEDER
TO memberS ON
HEALTHY SECTIONS
OF FEEDER Feeder
Field
member Crews Back to
FAULT
Reports On-Scene Normal
OCCURS Outage
Patrol
Travel Time Time Repair Time
With
FLISR
5 – 10 15 – 30 5 - 10 1-4
minutes minutes Hours
minutes
1 to 5
minutes
84
FLISR with and without Large DG on
Distribution Networks
Substation #2
Earlier slide (no DG)
5
3 No
Substation #1 Fault
Fault
Substation #3
Fault
Current
1 2 6 7 8
Fault Fault No
Fault
85
FLISR with Large DG on Distribution Networks
3 No
Substation #1 Fault
Fault
Fault Substation #3
Fault
Current Current
1 2 6 7 8
86
FLISR with Large DG or Distribution Networks
3 No
Substation #1 Fault
Fault
Substation #3
Fault
Current
1 2 6 7 8
87
FLISR with Large DG or Distribution Networks
3 No
Substation #1 Fault
Substation #3
Fault
1 2 6 7 8
88
FLISR with Large DG or Distribution Networks
3 No
Substation #1 Fault
Fault
Fault Substation #3
Fault
Current Current
1 2 6 7 8
89
FLISR with Large DG or Distribution Networks
3 No
Substation #1 Fault
Substation #3
Fault
1 2 6 7 8
90
Opportunity – Islanding
5 MW DG Unit
3 No
Substation #1 Fault
Substation #3
Fault
1 2 6 7 8
Fault No
Fault
3 MW prefault
load
91
Opportunity – Islanding
Substation #2
Since DG rating exceeds pre-
fault load, can establish an
5
island fed by the DG unit
5 MW DG Unit
3 No
Substation #1 Fault
Substation #3
Fault
1 2 6 7 8
Fault No
Fault
3 MW prefault
load
92
Optimal Network Reconfiguration
• Goal: Identify changes in feeder
configuration that would improve overall
distribution feeder performance and
reliability
– optimize topology for steady state
operations…
93
Optimal Network Reconfiguration
• Goal: Identify changes in feeder
configuration that would improve overall
distribution feeder performance and
reliability
– optimize topology for steady state
operations…
Load
Transfer
Occurs
94
Optimal Network Reconfiguration
Courtesy of Telvent
95
Optimal Network Reconfiguration
(Load Balancing) – Sample Case
≈40% loss
reduction
96
Distribution Contingency Analysis (DCA)
97
Management of Distributed Energy Resources
98
Dispatch Training Simulator
99
Planning for a New DMS
Contents of the Plan
• Business case
• Needs analysis (functional requirements)
• Conceptual architecture
• Implementation strategy (Procurement, design/build,
Install, commission)
101
Overview of the Implementation Plan
102
What is a “Business Case”?
103
Keys to Business Case Success
• Proposed DMS project must:
– Address significant business problem(s)
– Support important business driver(s)
– Provide monetary payback within an acceptable period to offset
the expenditure
104
Business Case Methodology
Needs Analysis
Results of Perform
Benefit/Cost Analyze Gather Operating
Sensitivity
Analysis Scenarios & Financial Data
Analysis
Benefit-Cost Analysis
Requirement Update
Final Report Management Specs & Business Case
Approval Technology & Cost/Benefit
Selection Expectations
105
Identifying Business Drivers
106
Identifying Business Drivers
• Typical Business Driver categories
– Workforce safety DMS projects can
contribute to each of
– Reduce O&M costs
these business driver
– member satisfaction categories
– Quality of service (reliability & power quality)
– Worker safety and productivity
– Proactive/direct response to regulatory compliance
– Energy efficiency
– Increased capacity utilization
– Support Demand Response activities
– Accommodate Distributed Energy Resources (e.g. PHEV, DER)
– Manage Electric vehicle charging
107
DMS Value Drivers
• Safety
• Reliability
• Efficiency
• Asset Utilization
• Maximize Use of Distributed Energy Resources
• Manage Electric Vehicle Charging Scenarios
108
Safety
109
Reliability
–Pinpoint fault
location
–Automatically
isolate fault
and restore
service to as
many members Substation #2
Close switch 4 to pick up
as possible 5
part of faulted feeder
FLISR logic stops here
3 No
Substation #1 Fault
Fault
1 2 6
Fault No
Fault
110
Efficiency
111
Asset Utilization
• Dynamic rating of
cables, transformers Base rating on
current
– Squeeze more “Real-time”
capacity out of conditions
and recent
existing assets history
– Defer capital
expenditures for
capacity addition
112
Maximize Use of DER
113
Manage Electric Vehicle Charging
Scenarios
• Enable/disable fast
charging based on
feeder conditions
• Manage Vehicle to
Grid (V2G) strategy
114
Needs Analysis –
Identifying Major Functional
Requirements for the DMS
DMS “Opportunity Matrix”
• Relates business needs to DMS application functions
Accommodate
Corporate Quality of Support Distributed Manage
profitability, service Increased Demand Energy Electric
e.g. O&M Customer (reliability & Energy capacity Response Resources (e.g. vehicle Workforce
costs satisfaction power quality) efficiency utilization activities PHEV, DER) charging safety
116
Discovery Meetings with
DMS Stakeholders
• Defined DMS needs for meeting the business drivers via series of interviews and workshops with key project stakeholders:
– Field and control center operations
– Engineering planning and design
– Protective relaying
– Restoration center (outage management)
– Communication engineering
– Information technology
• IT Standards, GIS, OMS, work management, mobile data
– SCADA engineering
– Engineering standards
– Smart metering
– member care
– DG connections
– Substation engineering
– Many others
117
Stakeholder Interviews – Items to Discuss
• Required DMS functions (must relate to the business case) – need to get to
the next level of detail
• Operational Needs – what level of DMS functionality is needed to address
operational needs and issues?
• Existing systems
– Will existing systems remain as separate standalone system, be
interfaced to the DMS, or be wholly incorporated in the DMS
– What are the available sources of information? Real time data (SCADA.
DA, AMI, external systems) and static data (GIS)
– Do existing independent systems require DMS data? (e.g. OMS requires
feeder outage data)
118
Request for Information (RFI)
• Objectives
– Obtain information (obviously)
• General info (financial and people resources, past
similar projects, etc)
• Standard offerings in areas of interest to the utility
• Handling of specific “tough spots” (GIS data quality,
cyber security, interfaces in general, etc.)
– Create “short list” for DMS procurement (10 vendors -> 3 bidders)
– Did not request budgetary pricing – in general this is meaningless at
RFI stage
119
Request for Information (RFI)
• RFI contents
– Overview of functional technical requirements
– Questions, Questions, more questions
• RFI process
– Send RFI to vendors
– Read vendor responses (“Tell Me” phase)
– Vendor demonstrations (“Show Me” phase)
– “Show Me” phase changed opinions developed during “Tell
Me’ phase
120
• Develop “Conceptual” Architecture
– Goal is to identify high level “technical” features of the DMS
(e.g. requirement for primary and independent backup control
center)
– Should not unnecessarily restrict the vendor in this area – let
them be creative within reason
• e.g. allow use or “virtualization” for the training/development
environment where performance and reliability are not mission
critical
121
Centralized vs. Decentralized
• Refers to the location where the main logic resides under normal
circumstances
– Does not refer to the input/output location
– Does not refer to the human machine interface location
122
Alternatives
123
Centralized Architecture
Main Logic
Resides here
124
Substation Centered Architecture
Main Logic
Resides here
125
Fully Distributed Architecture
Main Logic
Resides here
126
Hybrid DMS Architecture
COMPLEXITY
COMPLEXITY
Centralized
Substation
Centered
Distributed
Static Fixed set
System of rules
Milliseconds Minutes
SPEED
128
Other Considerations
Substation-
Criteria Centralized Distributed
Centered
Small # of geographically
High % of feeders All feeders at selected
# of DA Feeders automated substations automated
dispersed feeders
automated
Can tolerate some Can tolerate some
Nothing happens without
Operator Visibility operator being informed
control actions without control actions without
operator notification operator notification
Availability of
VVO, FLISR, ONR VVC, FLISR, DFA FLISR
commercial products
129
Architecture by Application
Substation-
Application Centralized Distributed
Centered
FLISR
Volt VAR Control (rule based)
Volt VAR Opt (model based)
Adaptable VVO
Dynamic Volt-VAR Control
Optimal Network Reconfiguration
Fault Anticipator
Equipment Condition Monitoring
130
Centralized DMS Architecture
AMI Network
and Interface Distribution
Field Devices
OMS
GIS
Peer-Peer
Field
Devices
Data
EMS/SCADA
Warehouse Distribution
Network
Control Center
consoles
Substation
RTUs DMS
131
“Bolt-On” Configuration
• Substation inputs and outputs handled via EMS/SCADA
• Field (feeder) inputs handled directly by DMS (DNP/IP)
Vendor 1 Vendor 2
EMS/SCADA DMS
Secure ICCP
FIELD
AUTOMATION
NETWORK
132
Redundant, Location Agnostic Design
• Dual redundant architecture – Fully redundant DMS installed at primary and backup control centers
• “Location Agnostic” Design: Operator consoles and DMS servers installed at different locations
(remote data center concept)
133
DMS Interfaces – Essential for effective deployment
Illustrates the
importance of
external interfaces to
the DMS
implementation
project
134
Interface functional requirements
Interface Data Elements Returned to DMS On demand results, interval transformer demand, energized status
Interface Function Description The DMS interface to AMI/MDMS must be capable of requesting and receiving on
demand reads, obtaining outage event information, provide an ability to query
historical data from AMI/MDMS,
Preferred Integration Method Publish-subscribe: web services or XML using Java Message Service (JMS)
Latency Requirements 30 seconds or less for on demand pinging of up to 100 meters, 15 minute and hourly for
transformer readings and interval load profile reads, 30 seconds for on demand
energized state requests.
135
Interface Standards
e.g. MultiSpeak
136
Implementation Plan
• The implementation strategy should be divided into the
following key activities:
– Procurement
– Design and Test
– Installation
– Implementation and Commissioning
– Sustainment
138
Main objectives for the DMS implementation strategy
• Ensure that the DMS is designed, implemented, tested, installed and commissioned in
accordance with utility’s requirements
• Ensure that the Vendor completes all contractual obligations to utility’s satisfaction.
• Ensure that electric utility personnel are fully trained in design, maintenance, and
operation of all aspects of the system so that utility company can be as self-sufficient
as possible in the future.
• Should not have to depend on the vendor and outside consultants for day-to-
day DMS “sustenance”.
139
Contents of the Implementation Strategy
• Identifies strategies for implementing the DMS facilities that satisfy the functional and architectural
requirements
• “Multi-Stage” approach versus “Single-Stage” approach
• Provides a roadmap for implementing and maintaining the system.
• Relationships with other projects
• Identifies a strategy for implementing the new system without disrupting ongoing operations
• Summarize the role of Electric Utility personnel and its Subject Matter Experts (consultants) during
each activity
• Provide a rough estimate of the level of effort required during each activity.
• Change management and training strategy
• Scheduling and budgeting
140
Procuring a new DMS
Approaches to System Procurement
142
Approaches to System Procurement
143
Prepare RFP & Bid Evaluation Method
An Overview of the Process
144
Request for Proposal (RFP)
• Overall objectives
– Obtain firm fixed pricing
– Obtain information to compare proposals from the
proponents and pick a winner
– Lay foundation for DMS Contract
145
Request for Proposal (RFP)
• Terms of Reference
– Commercial terms and conditions
– Instructions to bidders
– Functional/technical requirements
– Questionnaire (lots of questions)
146
Request for Proposal (RFP)
Commercial terms and conditions
147
Additions to standard
Commercial terms and conditions
– Right to use system and make changes without
voiding warranty
– Disclosure of interfaces
– Availability of source code
– Right to move software to replacement hardware
– Right to make copies of documentation
– Complicated definition of “Acceptance”
– Milestone payments
– Many others
148
Request for Proposal (RFP)
• Terms of Reference
– Instructions to bidders
• Format of proposal Requirement to have consistent
• Pricing forms format and content simplifies
review process
• Table of compliance
– Allows Vendor to concisely indicate where
they comply or take exception
149
Sample Table of Compliance
(Blank form)
150
Sample Table of Compliance
(With vendor entries)
151
Request for Proposal (RFP)
• Terms of Reference
– Questionnaire
• Prepare questions seeking clarification on specific issues
pertaining to the proposal
• Guideline: At least one question per specification section
• Questionnaire responses become part of statement of
work/contract for winning vendor
152
Request for Proposal (RFP)
• Terms of Reference
– Functional/technical requirements
• Technical description of requirements for
equipment, software, services
• Focus on “what” is needed, not solution
• Provide enough detail to avoid confusion. But
don’t over-specify
153
Contents of Technical Specification
154
Contents of Technical Specification
155
Contents of Technical Specification
156
Contents of Technical Specification
157
Contents of Technical Specification
158
Contents of Technical Specification
Training
– Summary of required training needed to enable utility to achieve desired level of system
support capability
– General approach to training (train the trainer, versus vendor handles all training)
– Training location
159
Training
• Categories:
Programmers, database & display builders,
dispatchers, maintenance technicians, installation
teams
– Train the trainer?
– Informal hands-on dispatcher training
– Delay formal dispatcher training
– On-the-job training of programmers
(6 mo - 12 mo)
160
Contents of Technical Specification
161
Contents of Technical Specification
– Project management
– Project meetings
– Maintenance prior to and following acceptance
– System installation
– Expert assistance during installation and checkout of advanced
applications
162
Bid Evaluation Process
Bid Evaluation
• Cross functional evaluation team
• Develop scoring methodology in advance of bids arriving (avoid
bias in weighting factors used for scoring)
• Scoring categories
– Functional & Technical
– Commercial
– Bid demonstration
– Risk
– Pricing
164
Bid demonstrations
• Presentation included functional demonstration of key application functions (GIS data conversion,
model building, OLPF, VVO, FLISR)
• Bidders convert the data as needed, built company specific models and displays, demonstrated
DMS application functions using these models
165
Sample score-sheet
166
Bid Evaluation Stages
167
Evaluation Methodology – Weighting Factors
General Proponent
Responsibilities
QA and Testing
Documentation and
Training
Sustainment
System Architecture
End-End Integration
Hardware Characteristics
Software Characteristics
Performance, expansion,
reliability
IT Standards
168
Scoring Summaries
169
Contract Negotiation
• Create statement of work based on winning proposal and clarifications received during bid
evaluation
– Updated TOR wording only where the bidder proposed alternatives or took
exception during bid evaluation process
– Allows you to essentially maintain control of the contract wording
170
Designing Building and
Implementing the System
Design, Configuration and Testing
• General organization and Project Management
– Single point of contact
– Core team with representatives of affected parties
• Design input and review
• Testing
– Type testing
– Functional and performance testing
– Integrated system testing
• Training and Documentation
– Prepare you for self sufficient O&M
172
Barriers to Successful
Implementation
Barriers to Successful deployment
• Lack of accurate data for modeling
– No record of construction details for overhead conductors
• Conductor arrangement needed to compute line reactance, for
example
• Can assume default conductor arrangement
– Incorrect records of phasing
• EPRI researching techniques to identify phase
– Lack of standard models for members and loads
• EPRI Load/Voltage Modeling Initiative
– Lack of information on substations in GIS
– Lack of information about secondary circuits in GIS
• Vendors can do some consistency checks
174
Barriers to Successful deployment
175
Barriers to Successful deployment
• Lack of reliable, near real-time, two way communication
facilities
– Is AMI communications network the answer?
– Need failsafe design for local controllers (revert to standalone local
control if communications fail)
176
More Barriers to Successful
Deployment
• Lack of support for advanced distribution applications
– Lack of field proven advanced applications
– Vendor offerings not fully developed
• Lack of industry standard interfaces (CIM, MultiSpeak)
• Management of distributed energy resources
• Others???
177
Questions and Discussion
Bob Uluski
EPRI
Technical Executive
[email protected]
215-317-9105
178