Long Term Control Plan Part 3 of 3
Long Term Control Plan Part 3 of 3
Prepared for
November 2016
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX III
CONTENTS
IV GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
CONTENTS
7.5.4 Single Line Diagrams and Preliminary Equipment Layout .................................. 7-5
7.5.5 Lighting................................................................................................................ 7-5
8 Instrumentation and Controls ............................................................................................... 8-1
8.1 Introduction ..................................................................................................................... 8-1
8.1.1 Existing Instrumentation and Control System .................................................... 8-1
8.2 Design Approach .............................................................................................................. 8-1
8.3 Control System Design Philosophy .................................................................................. 8-3
8.3.1 Equipment Control.............................................................................................. 8-3
8.3.2 Valve and Gate Control ....................................................................................... 8-3
8.3.3 Motor Control Centers ........................................................................................ 8-3
8.3.4 Adjustable Frequency Drives .............................................................................. 8-4
8.3.5 Power Monitors .................................................................................................. 8-4
8.3.6 Instruments and Transmitters ............................................................................ 8-5
8.3.7 Surge Suppressors............................................................................................... 8-5
8.3.8 Pilot-Light Colors ................................................................................................. 8-5
8.3.9 Equipment and Instrument Tag Numbers .......................................................... 8-5
8.3.10 PLC I/O signals ..................................................................................................... 8-5
8.4 Control System Operating Philosophy ............................................................................. 8-5
8.5 Remote Telemetry System............................................................................................... 8-6
8.6 Codes and Standards ....................................................................................................... 8-6
9 Odor Control ........................................................................................................................ 9-1
9.1 Introduction ..................................................................................................................... 9-1
9.2 Basis of Design ................................................................................................................. 9-1
9.2.1 Containment ....................................................................................................... 9-1
9.2.2 Conveyance ......................................................................................................... 9-1
9.2.3 Odor Control System Sizing ................................................................................ 9-2
9.2.4 Anticipated Odor Causing Compounds ............................................................... 9-2
9.3 Control Technology Selection .......................................................................................... 9-2
9.3.1 Biotowers ............................................................................................................ 9-3
9.3.2 Carbon Scrubbers................................................................................................ 9-4
9.4 Economic Evaluation ........................................................................................................ 9-6
9.5 Odor Control System Design Recommendations and Overview ..................................... 9-7
Appendix
A Preliminary Design Drawings
Tables
Table 1-1. Flow Scenarios .......................................................................................................................... 1-1
Table 1-2. Pump Operation ........................................................................................................................ 1-4
Table 2-1. Existing Pumps .......................................................................................................................... 2-2
Table 2-2. Grinder Selection ...................................................................................................................... 2-4
Table 2-3. Dry Weather Pump Selection .................................................................................................... 2-5
Table 2-4. Wet Weather Pump Selections ................................................................................................. 2-6
Table 3-1. Material Requirements for Structural Steel .............................................................................. 3-7
Table 5-1. HVAC Materials of Construction ............................................................................................... 5-3
Table 5-2. HVAC Outdoor Design Criteria .................................................................................................. 5-3
Table 5-3. Mechanical System Criteria ...................................................................................................... 5-4
Table 6-1. Plumbing and Fire Protection Materials of Construction ......................................................... 6-2
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX V
CONTENTS
Figures
Figure 2-1. Existing Screen Channels ......................................................................................................... 2-1
Figure 2-2. Suction and Discharge arrangement for Pump 2..................................................................... 2-2
Figure 2-3. Discharge header ..................................................................................................................... 2-3
Figure 2-4. Typical Grinder Installation ...................................................................................................... 2-4
Figure 2-5: Dry Weather Pump Selections ................................................................................................. 2-6
Figure 2-6. Wet Weather Pump Selections ................................................................................................ 2-7
Figure 7-1. Building Access Hatches and Vent Pipes ................................................................................. 7-4
Figure 9-1. Simplified Schematic of a Biotower System ............................................................................ 9-3
Figure 9-2. Photograph of a Biotower System ........................................................................................... 9-4
Figure 9-3. Schematic Dual Carbon Bed System ........................................................................................ 9-5
Figure 9-4. Photograph of a Dual Bed Carbon Scrubber ............................................................................ 9-5
VI GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
Acronyms and Abbreviations
AASHTO American Association of State Highway and Transportation Officials
ACGIH American Conference of Governmental Industrial Hygienists
ACH air changes per hour
ACI American Concrete Institute
AFD adjustable frequency drive
AISC American Institute of Steel Construction
ANSI American National Standard Institute
ASCE American Society of Civil Engineers
ASHRAE American Society of Heating, Refrigerating, and Air Conditioning
ASPE American Society of Plumbing Engineers
ASTM American Society for Testing and Materials
ATC automatic temperature control
Authority Greater New Haven Water Pollution Control Authority
AWWA American Water Works Association
BEP best efficiency point
BFE base flood elevation
CAIECC Connecticut Amendments to the International Energy Conservation Code
CFD computational fluid dynamics
cfm cubic feet per minute
CISPI Cast Iron Soil Pipe Institute
CMU concrete masonry unit
CSBC Connecticut State Building Code
CSO combined sewer overflow
DC direct current
DDC direct digital control
DFE design flood elevation
DLR device level ring
DWF dry weather flow
DX direct expansion
fps feet per second
FRP fiberglass reinforced plastic
ft2 square feet
ft3 cubic feet
GNHWPCA Greater New Haven Water Pollution Control Authority
gpm gallon(s) per minute
H2S hydrogen sulfide
HI Hydraulic Institute
HMI human-machine interface
hp horsepower
HSS hollow structural sections
HVAC heating, ventilation, and air conditioning
I&C instrumentation and controls
I/O input/output
IBC International Building Code
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX III
ACRONYMS AND ABBREVIATIONS
IV GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 1
Hydraulics
1.1 Introduction
The Long-Term Control Plan (LTCP) Update includes alternatives that control combined sewer overflow
(CSO) discharges from all CSO outfalls to meet a 2-year, 6-hour level of CSO control (zero discharges) by
2040. The LTCP Update includes short term, intermediate term, and long term improvements to meet
these stated goals. This Preliminary Design Report of the LTCP focuses on intermediate and long term
improvements at the Union Street Pump Station (Union). Preliminary Design Drawings are shown in
Appendix A of the report.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 1-1
SECTION 1 – HYDRAULICS
The design parameters and considerations in selecting pumps for the stations include;
1. Create maximum reliability, efficiency and redundancy for flows in the dry weather range since
flows in the dry weather range occur 98 percent of the time during a typical year.
2. Utilize extended shaft centrifugal pumps.
3. Maintain N+1 for dry weather and wet weather pumping conditions.
4. Consider space restrictions in existing station footprints.
5. Avoid cycling of flows at the East Street and Boulevard Pump Stations since these flows go
directly to the ESWPAF.
6. Select pumps to operate well within the pump manufacturers’ defined allowable operating
range (AOR) for both wet and dry weather conditions.
7. For high frequency flow capacities, select pumps to operate within the pump’s preferred
operating range (POR) as defined by the Hydraulic Institute Standards (HIS) to obtain high wire-
to-water pump efficiencies for both wet and dry weather conditions. For less frequent lower
flow capacities, size pumps for operation well within the candidate pump manufacturers’
defined allowable operating range (AOR).
8. Maintaining impeller tip speed to prevent accumulation of rags within the volute.
9. Maintaining scouring velocities in pump discharges to prevent grit accumulation.
10. Avoiding high VFD and corresponding pump speed turndown.
1-2 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 1 – HYDRAULICS
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 1-3
SECTION 1 – HYDRAULICS
The wet weather pumps would be sized to pump the maximum flows with one pump out of service.
Each wet weather pump would be rated at 17.5 mgd.
• Scenario 2 (five pumps, three large and two small): This scenario was similar to the previous with
one exception: The dry weather pumps were sized to pump the maximum dry weather flowrate
with one pump out of service. To achieve this, the pumps would cycle at the minimum dry weather
flowrate. The wet weather pumps are identical to those described above.
• Scenario 3 (five pumps, two large and three small): This scenario would require two pumps at 12.5
mgd and three pumps at 7.5 mgd. All pumps would be sized to pump together during wet weather.
This closely matches existing capacities and would not require modifications to the existing suction
piping. At max flow, the suction velocity in the existing 16-inch suction pipe is 7.5 feet per second
(fps), below the max velocity recommendation of 8 fps in Hydraulic Institute (HI) standards.
It was determined that Scenario 2 was the best option to meet the design flows. This scenario allows for
one of the dry weather pumps to meet the maximum dry weather flow with possible cycling (allowing
the second dry weather pump to be the N+1 pump), does not require replacement of the existing wall
pipes to meet maximum suction velocities, and allows for 480V service loads.
Table 1-2 shows the proposed pump operation under several flow regimes for the intermediate- and
long-term flow scenarios.
1-4 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 2
Process Mechanical
2.1 Introduction
This section describes the basis of the process mechanical design associated with improvements to meet
the intermediate and long-term flow scenarios and improve reliability of the station.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 2-1
SECTION 2 – PROCESS MECHANICAL
Downstream of the screen channels, the flow combines again. The flow then splits to the two sides of
the divided wet well. Sluice gates are located on the wet well influent channels and a sluice gate is
located on the wet well dividing wall.
There are four pumps currently installed; two on each side of the divided wet well. A small pump and
large pump are connected to the north wet well and a medium pump and large pump are connected to
the south wet well. An additional suction wall pipe is located on the south wet well for installation of a
fifth pump. The small pump has a 16-inch wall pipe, the large pumps have 24-inch wall pipes and the
medium pump and additional suction wall pipe are 20 inches.
Each pump listed in Table 2-1 is an extended shaft centrifugal pump manufactured by Fairbanks-Morse.
A gate valve is provided on the suction to each pump and a check valve and gate valve are provided on
the discharge of each pump. Figure 2-2 represents the suction and discharge arrangement for Pump 2.
All other pumps are typical.
A wye with a plug valve is provided on the discharge riser for each pump to allow maintenance to drain
and flush the risers, which have a tendency to collect grit when the pump is not operated. Figure 2-3
depicts the wye and plug valve on the riser for Pump 4.
2-2 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 2 – PROCESS MECHANICAL
The wet wells are ventilated through 10-inch diameter ducts on each side of the divided wet well. A fan
located in the screening room originally vented the ducts outside of the pump station. The fan has been
removed and the ducts currently vent to the atmosphere inside the screening room.
The pumps discharge to a 24-inch pipe that leaves the pump station from the south. Outside the pump
station, there is a flow meter before the force main crosses the rail lines to the east.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 2-3
SECTION 2 – PROCESS MECHANICAL
Coarse manual bar racks could be installed but they would require regular cleaning to remove collected
debris and could potentially cause backups into the system.
Channel grinders can be installed in the existing screen channels to protect the pumps from stringy
material and large objects. Two grinders would be installed, one in each channel, that would be able to
handle the long-term flow scenario. Bar racks can be installed above the grinder in the event a grinder
gets jammed. Flow would be able to pass over the top of the grinder while maintaining some level of
protection for the pumps. The existing channel ranges from 4 to 5 feet wide and the grinder is 54-inches
wide, a stainless steel mounting frame could be provided to make up the distance on either side of the
grinder. Wipes ready cutters would be provided to further reduce the size of materials preventing them
from reweaving at the pump intake.
A preliminary grinder selection is provided in Table 2-2.
Width 54-inches
Height 51.878-inches
Grinder Motor 5 HP
2-4 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 2 – PROCESS MECHANICAL
Number of pumps 2 2 2
NPSHA (ft) 42 -- 42
Motor (HP) 50
Model 12MN24E
Manufacturer Flowserve
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 2-5
SECTION 2 – PROCESS MECHANICAL
NPSHA (ft) 41 39
NPSH3 7.7
Model 16MW25B
Figures 2-5 and 2-6 display the selected pump system curves for the dry weather and wet weather
pumps.
Figure 2-5 shows the variable-frequency drive (VFD) curve for a single pump in operation. Under the
minimum dry weather flow (DWF), a single pump is operating outside the allowable operating range
(AOR); under this condition, the station would cycle. Under average DWF, a single pump is operating
2-6 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 2 – PROCESS MECHANICAL
within the preferred operating range (POR). Under maximum DWF, a single pump is operating within the
POR.
120
Union WWF Pumps
100
80
Head (ft)
WWF
60
40
20 DWF MAX
Intermediate
0
0 5000 10000 15000 20000 25000 30000
Flow (gpm)
900 RPM 810 RPM 720 RPM 630 RPM 540 RPM
AOR POR BEP Series12
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 2-7
SECTION 2 – PROCESS MECHANICAL
the wet wells will be evaluated using computational fluid dynamics (CFD) modeling to verify the
hydraulic efficiency and further physical testing may be required to model the existing wet well to
identify measures that can be taken to comply with HI standards.
HI also provides recommendations for retrofit designs of rectangular wet wells that would help improve
suction conditions. Recommendations are as follows:
• Inclusion of a baffle wall to minimize air entrainment due to falling liquid
• Setting the baffle wall below the maximum wet well level to allow any floatable material to pass
over the wall
• Inclusion of fillets below the pump intake
• Inclusion of baffles between the pump intakes
• Inclusion of fillets along the sides of the wet well to eliminate dead zones
2-8 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 3
Structural
3.1 Introduction
This section is intended to assess the building structure components of the Union Pump Station and
identify design criteria for the rehabilitation of the facility. It outlines proposed solutions to address
structural deterioration, deficiencies, and upgrades to incorporate architectural, process mechanical,
and MEP findings.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 3-1
SECTION 3 – STRUCTURAL
concrete foundation walls around the below-grade wet well and dry well areas. The above-grade
exterior elevations of the pump station structure is clad with brick veneer with a non-structural concrete
masonry unit (CMU) backup and an 8-inch CMU partition wall has been provided between the motor
room and the screen room.
The cast-in-place roof over the pump station structure is integral with a vehicular roadway above. A
bridge approach slab exists on the south side and is supported by the spandrel beam. A monorail crane
system supported by the roof structure is provided for maintenance of the four pumps in the dry well.
3-2 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 3 – STRUCTURAL
a. The dry well area concrete surfaces were in good condition. Minor leakage was noted through
the existing concrete foundation walls.
b. Structural steel braces have been provided to provide support or the pump motor shafts which
extend from the motor room above. The steel appears to be in good condition, but should be re-
coated for protection.
c. The stairs leading from the motor room down to the dry well are composed of galvanized steel
and in good condition. A new CMU wall will be necessary to isolate the stair from the drywell
area (see Section 4 – Architectural in this report).
4. Influent Channels: Two influent channels are located below the Screen Room, the channels are
constructed of reinforced cast-in-place concrete. Access to the influent channels was limited to
visual inspection from above.
a. The access covers could be removed to view the slide gates and concrete conditions on the
north and south ends. The gates and respective supports exhibit significant deterioration and
corrosion and will require concrete repair at channel walls when replaced. Deterioration and
corrosion of the channel structure outside of the slide gates was not observed, but with limited
access the concrete surfaces should be further reviewed. Concrete repairs will be necessary
around the gate structures. A protective coating should be applied to all channel concrete
surfaces.
5. Wet Well: The wet well is located outside of the northwest side of the Motor Room and is accessed
from the exterior of the Union Pump Station Structure. There are two surface mounted aluminum
access hatches provided above the wet well. Access to the wet well was limited to visual inspection
from above.
a. The two aluminum access hatches appear to be in good condition and have been replaced since
original construction. The safety grating provided below each hatch was bent and did not appear
to function as intended. Replace safety grating, or provide guardrails around the access hatches
b. The concrete surfaces within the wet well did not exhibit deterioration in areas that could be
observed, but the concrete does not appear to have a protective coating. A protective coating
should be applied to all concrete wet well surfaces.
6. Vehicular Roadway: The Roadway located directly above the Union Pump Station is also composed
of cast-in-place concrete.
a. The roadway bridge approach on the south side of pump station is also a concrete structure,
and is currently supported by steel brackets embedded into the building south elevation
spandrel beam. These brackets are intended to provide an expansion joint between the
structures. Leaks have developed from the roadway above allowing water infiltration into the
exterior wall assemblies and onto structural elements below. Corrosion of the steel support
brackets (5 locations) has occurred; leaks also expose the concrete structural elements to
deicing salts which will lead to deterioration. The extents of deterioration of the roadway
approach support brackets could not be determined due to the buildup of corrosion. At a
minimum the brackets should be cleaned of corrosion and protected with a coating system. The
roadway expansion joint assembly above should be replaced to minimize further structure
exposure to moisture and deicing salts infiltrating from above.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 3-3
SECTION 3 – STRUCTURAL
3-4 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 3 – STRUCTURAL
to allow hydrostatic pressures to equalize on either side of facility walls during the flooding event
allowing immediate return to service following cessation of flood waters. Specific floodproofing
locations are included in the Preliminary Design Drawings included in Appendix A.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 3-5
SECTION 3 – STRUCTURAL
Load cases that will be considered in detailed design of liquid holding basins are:
• All basins full of liquid, no backfill.
• Backfill and groundwater with empty tank
• Any tank cell empty or full in any combination.
• A fluid pressure of 62.4 pcf will be used for hydrostatic loads from ground water and flooding.
• A fluid pressure of 63 pcf will be used for process liquid in these basins, unless otherwise noted.
3.4.4 Concrete
Materials and design procedures for concrete are described below.
3.4.4.1 Materials
The following minimum requirements apply (concrete compressive strength at 28 days):
• Typical Concrete, unless otherwise noted 4,500 psi
• Concrete Fill, unless otherwise noted 3,000 psi
• Curbs and Sidewalks 3,000 psi
• Conduit Encasements and Pipe
(encasements not integral with foundation) 4,500 psi
• Precast Concrete 5,000 psi
Reinforcement:
• Conventional Steel: ASTM A615, Grade 60 (fy = 60 kilopounds per square inch [ksi])
3.4.5 Masonry
Materials and design procedures for masonry are described below.
3.4.5.1 Materials
The following requirements apply:
• Hollow concrete masonry units will conform to ASTM C 90 and will be normal- or medium-weight
units with a net area compressive strength of 1,900 psi.
• Mortar will conform to ASTM C 270, Type S.
3-6 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 3 – STRUCTURAL
• Grout will conform to ASTM C 476. Minimum 28-day compressive strength will be 2,000 psi.
• Steel reinforcement will conform to ASTM A615, Grade 60.
• Horizontal joint reinforcing steel will conform to ASTM A82.
3.4.6.1 Material
The material requirements for structural steel are listed in Table 3-1.
Pipes A53 B 35 60
A325 or
Bolts for Connections (1/2” to 1” diameter) - - 120
F1582
316, Cond.
Anchor Rods – Typical F593 40 80
CW
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 3-7
SECTION 3 – STRUCTURAL
runway shall be calculated as 20 percent of sum of rated capacity of crane and weight of hoist and
trolley. Lateral force shall be assumed to act horizontally at traction surface of a runway beam, in either
direction perpendicular to beam. Longitudinal force on crane runway beams shall be calculated as 10
percent of maximum wheel loads of crane. Longitudinal force shall be assumed to act horizontally at
traction surface of a runway beam in either direction parallel to beam.
3-8 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 4
Architectural
4.1 Introduction
This section assesses the architectural components of the Union Pump Station and presents the design
criteria for upgrades to the facility. The architectural assessment consisted of three tasks: interviewing
staff, visiting facility site, and reviewing available facility documentation. It outlines proposed solutions
to deficiencies found from building and code assessment completed. These recommendations are
intended to serve as preliminary guidance for the design of facility renovations.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 4-1
SECTION 4 – ARCHITECTURAL
4.3.3.2 Painting
The ground floor walls and ceilings are not painted. Equipment and piping is in need of painting. The
following solutions are recommended:
1. Surface prepare and paint walls and ceilings in all the ground floor rooms with a chemical resistant
epoxy paint system. If the insulation is added to the ceiling, then paint may not be necessary.
2. Epoxy paint floor of new restroom.
3. Surface prepare and paint piping, equipment, and supports in all the rooms with a chemical resistant
epoxy paint system.
See below on Lintels, Windows, and Doors for more details on painting.
4.3.3.3 Lintels
The lintels above doors and windows are rusted on the south wall of the Motor Room and Screen room
and the north wall of the Screen Room. The design will include the following:
1. Ventilate rooms to help remove moisture and fumes. Add new FRP louvers.
2. Seal around louvers.
4-2 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 4 – ARCHITECTURAL
4.3.3.4 Windows
Existing steel windows need replacement. The design will include the following:
1. Remove windows/plywood from three Screen Room and one west Motor Room openings, and
replace with CMU and brick. These windows are not on exterior of building but open into the
enclosed space under the bridge structure, so they are not needed.
2. Remove four windows from east Motor Room openings and replace with insulated translucent
panels with 8x8-inch grid pattern and aluminum frame. Paint existing steel lintels with a chemical
resistant epoxy paint system.
3. Seal around windows.
4.3.3.5 Doors
Doors to Screening Room are deteriorated and need replacement. The rollup door to the Motor Room
also needs replacement. Note, rollup doors are not considered an exit from the room, so the current
Pump and Motor rooms have only one exit. All other doors appear to be in good condition, but may be
replaced so all doors are new. The design will include the following:
1. Remove rollup door on south Motor Room wall and masonry above door to bottom of concrete roof
beam. Install new nominal 10-foot-high FRP double door and frame.
2. Monorail could be extended to run through the double door and have monorail seals on the doors.
3. Remove Screen Room south double door and single north door and replace with FRP doors and
frames with heavy duty stainless steel hardware.
4. Seal around doors.
5. See document sections for Stair Enclosure, Restroom, and Control Room for additional doors.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 4-3
SECTION 4 – ARCHITECTURAL
4-4 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 5
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 5-1
SECTION 5 – HEATING, VENTILATION, AND AIR CONDITIONING
A new heating/ventilating unit (HV-1) will be provided for the Screen Room. The unit will be located at
grade above the flood protection elevation. The unit will supply 12 air changes/hour (ACH) with 100
percent outside air in order to reduce the NFPA electrical classification from Class 1 Division 1 to Class 1
Division 2. The supply air will be tempered to minimum 55 degrees F during winter in order to protect
plumbing and water piping from freezing. The ventilation rate will be reduced to 6 ACH, as allowed by
NFPA 820 and whenever the outside air temperature is 50 degrees F or below, the space is unoccupied
and the combustible gas detector is 10 percent below the lower explosive limit of methane. The
heating/ventilating unit and exhaust fans will be provided with AFDs and a separate exhaust fan will be
provided to maintain proper temperature conditions for the pump motors during the summer months.
The heating/ventilating unit (HV-1) will be sized to provide tempered make-up air for wet wells through
screen room floor penetrations.
A separate heating/ventilating unit (HV-2) and exhaust fan will be will be provided for the Dry
Well/Motor Control Center (MCC) Room. The unit (HV-2) will be located on an elevated platform on the
east side of the building. The space will be heated and ventilated at a rate of 12 ACH with 100 percent
outside air. The supply air will be tempered to minimum 55 degrees F during winter in order to protect
plumbing and water piping from freezing.
5.3 Equipment
The specific type of equipment used on a particular building will be determined during detailed design
based on application. Roof or platform mounted equipment will be used where possible to preserve
floor space and to minimize equipment exposure to aggressive environments. The following types of
HVAC equipment may be utilized on this project.
5.4 Materials
Table 5-1 provides various material choices that may be used for HVAC systems depending on the type
of atmosphere in which equipment is installed. Specific materials will be selected during detailed design
to suit the application.
5-2 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 5 – HEATING, VENTILATION, AND AIR CONDITIONING
Ductwork Al
Process Non-corrosive
Equipment HPCS
Ductwork GS/Al
Non-process Non-corrosive
Equipment GS/Al
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 5-3
SECTION 5 – HEATING, VENTILATION, AND AIR CONDITIONING
Table Abbreviations:
AC – Air Conditioning G – Gas Heating Method
ACH – Air changes/hour OA – Outside Air
E – Electric
5.6 References
5.6.1 Codes
The HVAC design shall follow all applicable local, state, and federal codes and criteria. The following
codes will be used for the mechanical design of this project:
• 2016 Connecticut State Building Code
5-4 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 5 – HEATING, VENTILATION, AND AIR CONDITIONING
5.6.2 Standards
The following standards and guides will be used for the mechanical design of this project:
1. ASHRAE (American Society of Heating, Refrigerating and Air Conditioning Engineers)
2. SMACNA (Sheet Metal and Air Conditioning Contractors’ National Association)
3. ACGIH (American Conference of Governmental Industrial Hygienists) Industrial Ventilation Manual of
Recommended Practice
4. NFPA (National Fire Protection Association)
5.6.3 Miscellaneous
5.6.3.1 Calculation Software
• Heating and Cooling Load Analysis: Trane Trace 700
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 5-5
SECTION 6
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 6-1
SECTION 6 – PLUMBING AND FIRE PROTECTION
6.3.2 Materials
Table 6-1. Plumbing and Fire Protection Materials of Construction
Equipment or
Area Atmosphere (1) System Materials of Construction
Piping SS/GS/CU/AL/HCI/CU/CPVC
Process Corrosive
Equipment Coated GS/Al/SS/CU
Piping CU/BS/CI/DI
Process Non-corrosive
Equipment Coated GS/Al
Piping GS/BS/CU/DI/PVC
Administration Non-corrosive
Equipment GS/CS
6-2 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 6 – PLUMBING AND FIRE PROTECTION
6.5 References
6.5.1 Codes
The design of this project will be governed by the Connecticut State Building Code 2016 Edition,
Connecticut State Fire Safety Code 2005 (with amendments) and all adopted International Codes
including the International Plumbing and International Fire Codes.
6.5.2 Standards
The following standards and guides will be used for the plumbing and fire protection design of this
project:
• ANSI (American National Standard Institute)
• ASPE (American Society of Plumbing Engineers)
• ASTM (American Society for Testing and Materials)
• AWWA (American Water Works Association)
• CISPI (Cast Iron Soil Pipe Institute)
• IBC (International Building Code)
• IFC (International Fire Code)
• IPC (International Plumbing Code)
• NFPA (National Fire Protection Association)
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 6-3
SECTION 7
Electrical
7.1 Introduction
The electrical work at Union pump station will consist of adding a generator and automatic transfer
switch to supply backup power to the facility as well as new electrical service equipment, MCCs and
switchgear. The existing switchgear is over 55 years old, and will be replaced in its entirety. New pump
motors will be compatible with and controlled by adjustable frequency drives to provide precise control,
improve efficiency, and reduce power factor losses.
Architectural improvements to the site will be made so that the motor room is sealed and is not exposed
to Class I, Division 1 or 2 atmospheres. Most electrical equipment including the MCC, PLC, and
adjustable frequency drives (AFDs) will be placed in a climate controlled electrical room.
The sequence of construction will be scheduled in order to minimize down time and allow suitable
pumps to be available at all times, except for 4- to 8-hour shutdowns to transfer power and swap out
individual pumps.
Close coordination with the local utility United Illuminating (UI) will be required throughout this project,
as a new utility service will be provided for this facility.
The work required for this station is described in further detail below.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 7-1
SECTION 7 – ELECTRICAL
7-2 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 7 – ELECTRICAL
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 7-3
SECTION 7 – ELECTRICAL
The boarded window in the photograph is not a properly sealed window. Since the gasses from the wet
well below can escape into the motor room through this boarded window, the motor room, and
therefore the pump room, is classified as Class I, Division 1, and the equipment is not rated for this
environment.
Although the room is technically classified, it is not of immediate concern since the window is boarded
up, the wet well access hatches are usually closed, and very little if any air is getting in through the
boarded window. It is satisfactory to address this issue as a part of the upcoming project.
The solution is to replace the boarded up window with a concrete masonry unit wall.
7-4 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 7 – ELECTRICAL
Note the vent pipe shown in the lower left corner of the photo above. Per NFPA 820, Figure A.4.2.(c),
the area is classified Class I, Division 1 within three feet of the vent outlet, and is classified Class I,
Division 2 between a three and five foot radius of the vent. Fortunately, the west entrance to the motor
room is six feet from the vent, so the gasses expelled through this vent will not reach the door and affect
the classification of the room per NFPA 820.
The motor room, pump room, stairwell, and all new rooms created within motor room are unclassified
per NFPA 820.
The wet well is a Class I, Division 1 area. The screenings room above the wet well is a Class I, Division 1
area if it is ventilated at less than 12 ACH. The screenings room will be classified as Class I, Division 2 if
the room is ventilated at 12 or more ACH. There is a wet well vent near the north screenings room door.
However, the vent does not affect the area classification of the screenings room, as this room as already
classified.
7.5.5 Lighting
Existing lighting will be replaced with state-of-the-art LED type fixtures in all areas, including Class I,
Division 1 and Class I, Division 2 areas. LED frog-eye type emergency lighting fixtures will also be
provided.
Existing outdoor lighting fixtures will be replaced with metal halide or LED type fixtures. Where existing
lighting is insufficient, new lighting will be added.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 7-5
SECTION 8
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 8-1
SECTION 8 – INSTRUMENTATION AND CONTROLS
As detailed in the Process Mechanical Section, the new pumps at the Union Street Pump Station will be
adjustable speed. The AFDs for the pumps will be installed in the electrical/control room.
Power monitors will be provided in the new MCC for monitoring power consumption and quality.
In addition to hardwired signals, device level rings (DLRs) will be used for Pump Station PLC
communication with AFDs and power monitors to manage traffic on the control network.
Control system equipment will be powered from a true online double-conversion-type uninterruptable
power supply (UPS) unit to maintain reliable operation during power system disturbances and outages.
UPS unit will power the PLCs, operator interface terminals, and HMI operator workstation. UPS battery
backup will have enough capacity to energize the control system for 30 minutes after a power failure.
The low-battery alarm will be hardwired to the Plant PLC input/output (I/O) for monitoring. The panel
will be designed to automatically switch over to the line power upon UPS failure.
For powering loop powered instruments, redundant 24 V DC power supplies will be provided in the PLC
panel. The power supply failure alarm will be hardwired to the plant PLC I/O.
Electric or hydraulic actuation will be provided for all valves and gates. In general, electric actuators,
rated for the environment, will be used. If the actuator can potentially be submerged, hydraulic
actuation will be considered. Based on field observations, all gates and valves at the Union Pump Station
can be electrically actuated.
To complement process redundancy, the monitoring and control signals for redundant equipment (e.g.,
pumps, grinders, etc.) will be split between separate I/O modules and racks (if necessary)
The control systems for the new odor control system and the new generator system will be PLC/OIT
based. The package control systems will not be customized to use Allen-Bradley hardware if the system
vendor’s “standard” operating platform is different. Instead, gateways and/or protocol convertors will
be provided for digital connection to the Pump Station PLC System. The system supplier will program the
package PLCs. Hardwired I/O will be used for connecting critical monitoring and control signals from the
package systems to the Pump Station PLC System. The digital interface will be used for monitoring of
additional signals. Digital data interface requirements between the package systems and the Pump
Station PLC System will be further developed during design development and coordinated with the
package system vendors.
The sump pump control panel will be replaced. If new sump pumps are provided, a new control panel
will be specified. The panel will be mounted above the flood plain or in the control room
The existing pressure transducers for wet well level monitoring will be replaced with new non-fouling,
hydrostatic pressure type transmitters, designed specifically for wastewater applications. The
transmitters will be installed in stilling wells. As a backup to the level transmitters, high and low level
switches will be provided to operate the pumps upon failure of a transmitter.
A new electromagnetic flow meter will be provided for pump station flow monitoring. The meter will be
located in a vault outside the pump station and will provide analog flow signal to the Pump Station PLC.
Detailed change-out procedure will be developed so that the new I&C equipment can be installed and
tested prior to being put into operation. The design will allow the new Pump Station PLC System and the
existing control system to coexist for some time as the new system is brought online and the old system
is decommissioned. The pump station will remain operational during switchover.
Security camera system with DVR will be provided at the pump station. The location and quantity of
cameras will be determined during design development.
8-2 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 8 – INSTRUMENTATION AND CONTROLS
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 8-3
SECTION 8 – INSTRUMENTATION AND CONTROLS
• AUTO status of the ON/OFF/AUTO selector switch to the Pump Station PLC
• RUN status to the Pump Station PLC
• START and STOP control signals from the Pump Station PLC when the selector switch is in the AUTO
position
• Motor OVER LOAD alarm to the Pump Station PLC
• Individual FAIL alarms for the interlock signals that are hardwired to the MCC (for example, high
temperature, low-low level, high-pressure shutdown) to the Pump Station PLC, as required for the
specific application
8-4 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 8 – INSTRUMENTATION AND CONTROLS
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 8-5
SECTION 8 – INSTRUMENTATION AND CONTROLS
and equipment safety interlocks will stay active in this mode of operation. The process interlocks
will be bypassed.
• PLC Manual Control. This control level will provide the capability to manually control the process
equipment at the Pump Station OIT and HMI (for equipment controlled by the Pump Station PLC), or
the package system OIT (for equipment controlled by the package system PLC). All of the hardwired
equipment and personnel safety interlocks and some of the critical process interlocks with be active
in this mode.
• PLC Automatic Control. This will be the normal mode of operation. In this mode, the PLCs will
control the process equipment based on programmed control algorithms and functions, including
continuous closed-loop control and sequential control. Operator will select the operating
parameters and set points at the OITs or the HMI. All of the equipment and personnel safety
interlocks, as well as process interlocks, will be active in this mode.
• Plant SCADA Control. This supervisory control level will provide control of the pump station from
the East Shore WPAF. For example, the plant operators will be able to remotely change the
operating mode of the equipment from PLC Auto to PLC Manual. This will allow the operators to
Start/Stop the equipment and Open/Close the gates remotely from the plant. The available
interlocks in this mode will be the same as the PLC Manual Control mode mentioned above. It is
anticipated that this mode will be only be used occasionally if the operations staff is not able to
drive to the pump station in a timely manner. Normally, the pump station operation from the East
Shore WPAF will be limited to remote setpoints and operating parameter changes. A soft switch at
the plant HMI with password security will be provided to enable this mode of operation. The switch
to this mode will need to be carefully coordinated with the pump station operators.
8-6 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 8 – INSTRUMENTATION AND CONTROLS
− TR20.00.01, Specification Forms for Process Measurement and Control Instruments, Part 1:
General.
• National Electrical Code (NEC).
• National Electrical Manufacturers Association (NEMA):
− 250, Enclosures for Electrical Equipment (1,000 Volts Maximum).
− ICS 1, Industrial Control and Systems General Requirements.
• National Fire Protection Association (NFPA): 820, Standard for Fire Protection in Wastewater
Treatment and Collection Facilities.
Underwriters Laboratory, Inc. (UL): 508A, Standard for Safety, Industrial Control Panel
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 8-7
SECTION 9
Odor Control
9.1 Introduction
The Union Pump Station currently has no odor control. As part of this Long-Term Control Plan Update,
and as a result of the close proximity of the Union Pump Station to public areas and highly utilized
transportation routes, inclusion of odor control is recommended in order to mitigate odor complaints
associated with continued operation of the facility.
The Union Pump Station processes that will receive odor control include an inlet chamber, two parallel
channels that include grinders, an outlet chamber and two wet wells.
9.2.1 Containment
The existing channels contain sections of grating that allow for comingling of sewage vapors with the
overlying room space that can then result in the release of sewage odors to the ambient atmosphere.
Containment of foul air to within the process area, i.e., within channels, will be achieved by replacing
the grating with solid panels to create a separate controlled headspace within the channels. Panels will
be designed using materials of construction resistant to corrosion e.g., fiberglass reinforced plastic (FRP)
or aluminum checker plate. Covers will be constructed using flat removable panels. The cover design will
facilitate easy removal of individual panels by two people. Each panel will not weight more than 100 lbs
and will have an integral nonskid surface. Lifting handles shall be provided on each panel. Each panel will
have gasketed joints to prevent fugitive air release.
As a result of the containment of foul air within the process channels, protection of concrete against
corrosion using either protective coatings or liners is recommended and will be included during detailed
design.
9.2.2 Conveyance
Foul air will be conveyed from within the contained process channels and wet wells by FRP ductwork. It
is anticipated that up to four foul air pickup locations will be designed, two associated with channels and
one for each wet well. Each foul air pickup location will include a flow balancing damper to facilitate
adjustment of flow for each pickup to design values. The foul air duct will connect to the covers through
a flanged connection to allow for easy removal. The duct will rise vertically up and then move
horizontally at a distance overhead ensuring clearance e.g., min 7 ft. The exact layout will be determined
during detailed design.
Allowance for air flow into the covered process channels and wet wells will be included in the design.
The relative locations of air entry and foul air extraction will be selected to achieve good overall air
movement within the enclosed process area and minimize development of “dead zones” or short-
circuiting.
The extraction of foul air will be achieved through use of a single exhaust fan constructed of FRP. A flow
balancing damper will be located at the fan inlet to allow for adjustment of overall system air flow. The
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 9-1
SECTION 9 – ODOR CONTROL
fan will convey captured foul air to an odor control system where the odorous compounds, primarily
hydrogen sulfide (H2S), are removed prior to release to the ambient atmosphere.
9-2 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 9 – ODOR CONTROL
9.3.1 Biotowers
In many ways, a biotower looks externally similar to a wet chemical scrubber, except that no hazardous
chemical addition is required. Figure 9-1 depicts a simplified schematic diagram of a biotower system.
Systems are pre-engineered, vendor-supplied systems made of fiberglass-reinforced plastic or high
density polyethylene shells. Biotowers use a biologically active media bed to absorb and oxidize odorous
compounds from the foul air stream. One of the primary technical advances associated with this
technology is the development of engineered inert media on which the biomass attaches. As the media
is inert, it is not compromised by the acidic environment within the biotower and has lifespans on the
order of 20 years. The media receives either constant recycle spray (bioscrubber) or intermittent once-
through spray humidification (biotrickling filter), depending on the vendor’s approach. The spray is also
the source of trace nutrients for the biological system. There are typically two potential sources of
water, potable or plant effluent. If potable water is used, then a supplemental nutrient supply
containing trace organics, nitrogen, phosphorous, and potassium is required. If plant effluent is
available, then supplemental nutrients are usually not required as the plant effluent water will contain
sufficient nutrients. For Union Pump Station, potable water and supplemental nutrients would be
required as plant effluent is not available.
Biotowers are usually designed in the form of a cylindrical arrangement such as those shown in
Figure 9-2.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 9-3
SECTION 9 – ODOR CONTROL
use of this type of impregnated carbon is not recommended for further consideration. Finally, there are
carbons available that have been processed in a manner that results in high selective adsorptive capacity
for H2S (e.g., order of magnitude higher than virgin activated carbon). The use of this type of high
capacity carbon is recommended for consideration as it will extend the useful life of the carbon
significantly thereby reducing O&M issues and costs associated with frequent media replacement.
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 9-5
SECTION 9 – ODOR CONTROL
Labor 40 $/hr
Excavation 15 $/CY
Backfill 35 $/CY
Allowance Costs
Equipment Installation 10 %
Field painting/finishes 1 %
Mechanical 8 %
Electrical 8 %
Instrumentation 5 %
Financial Factors
Discount Rate 7 %
Contractor Markups:
General Conditions 7 %
Contingency 30 %
9-6 GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX
SECTION 9 – ODOR CONTROL
GNHWPCA_LTCPUPDATE_UNIONPS_DRAFT_11302016.DOCX 9-7
Appendix A
Preliminary Design Drawings
1 2 3 4 5 6
GHTS RESERVED.
INDEX TO DRAWINGS
LL 2016. ALL RI
100 - UNION PUMP STATION
c CH2M HI
er
APVD
Seal
A
BY
NO. NO. NO. NO.
GENERAL MECHANICAL
APVD
S THE PROPERTY OF
100-G-001 UNION PUMP STATION INDEX OF DRAWINGS 100-M-201 UNION PUMP STATION 35 MGD CAPACITY
LL.
ON OF CH2M HI
LOWER PLAN
ew
100-G-002 UNION PUMP STATION ABBREVIATIONS
QC Revi
100-M-202 UNION PUMP STATION 35 MGD CAPACITY
100-G-003 UNION PUMP STATION ABBREVIATIONS AND UPPER PLAN
GENERAL LEGEND
100-M-301 UNION PUMP STATION 35 MGD CAPACITY
ZATI
CE,I
100-G-005 UNION PUMP STATION INSTRUMENTATION AND SECTION
TTEN AUTHORI
ONAL SERVI
CONTROL LEGEND - SHEET 1
ON
100-M-302 UNION PUMP STATION 35 MGD CAPACITY
SI
CHK
100-G-006 UNION PUMP STATION INSTRUMENTATION AND SECTION
REVI
CONTROL LEGEND - SHEET 2
THOUT THE W RI
100-G-007 UNION PUMP STATION ARCHITECTURAL AND
STRUCTURAL LEGEND
ELECTRICAL
DR
100-E-202 UNION PUMP STATION GROUND FLOOR PLAN
N,AS AN I
B (35 MGD CAPACITY)
E
100-G-017 ELECTRICAL LEGEND 3
J.OSOSKI
NCORPORATED HEREI
INSTRUMENTATION AND CONTROL
DATE
CIVIL
DSGN
100-N-601 UNION PUMP STATION PROCESS FLOW DIAGRAM
NO.
100-C-201 UNION PUMP STATION SITE PLAN
N W HOLE OR I
DEAS AND DESIGNS I
ON
STRUCTURAL
S NOT TO BE USED,I
100-S-201 UNION PUMP STATION FLOOD PROOFING
CUT
FLOOR PLAN 35 MGD CAPACITY
TY
NEW HAVEN,CONNECTI
LL AND I
100-A-201 UNION PUMP STATION LOWER LEVEL PLAN 35
MGD CAPACITY
CH2M HI
100-A-202 UNION PUMP STATION GROUND FLOOR PLAN 35
THI
MGD CAPACITY
HVAC
ON
NGS
EQUIPMENT SCHEDULES
ON PUM P STATI
100-H-202 UNION PUMP STATION 35 MGD CAPACITY
NDEX OF DRAW I
ON
EQUIPMENT PLATFORM PLAN
GENERAL
GROUND FLOOR PLAN
UNI
I
D
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 100-G-001
SHEET of
CL CENTERLINE ESC EROSION AND SEDIMENT CONTROL MC MODULATE-CLOSE PEP POLYETHYLENE PIPE
ABBREVIATIONS
GHTS RESERVED.
HDW HARDWARE
CLDI CEMENT LINED DUCTILE IRON EP EXPLOSION PROOF, EDGE OF MCC MOTOR CONTROL CENTER PEN. PENETRATION
HGL HYDRAULIC GRADE LINE
CLSF CONTROLLED LOW STRENGTH FILL PAVING HK HOOK MCJ MASONRY CONTROL JOINT PFC POUNDS PER CUBIC FOOT
A AMMETER, AMPERES, AWNINGS
CLG CEILING EQL EQUAL HGT HEIGHT MDO MEDIUM DENSITY OVERLAY PENTHOUSE
PH
AB, ABV ANCHOR BOLT, ABOVE
CLR CLEAR, CLEARANCE EQL SP EQUALLY SPACED HH HANDHOLE MECH MECHANICAL pH HYDROGEN ION CONCENTRATION
ABDN ABANDON
HID HIGH INTENSITY DISCHARGE
LL 2016. ALL RI
CLSM CONTROLLED LOW STRENGTH MATERIAL EQPT EQUIPMENT MFD MANUFACTURED PH PHASE
AC ACOUSTICAL, ACOUSTICAL CEILING CMP CENTRAL MONITORING PANEL HK HOOK MFR MANUFACTURER PI POINT OF INTERSECTION
ESC EROSION AND SEDIMENT CONTROL
AC ALTERNATING CURRENT
CMP CORRUGATED METAL PIPE HM HOLLOW METAL MGD MILLION GALLONS PER DAY PIT
ETM ELAPSED TIME METER PILOT TUBE TEST STATION
AC ASPHALTIC CONCRETE CMU CONCRETE MASONRY UNIT
EVC END OF VERTICAL CURVE HOA HAND-OFF-AUTO MH MANHOLE, MOUNTING HEIGHT PJF PREMOULDED JOINT FILLER
ACFL ACCESS FLOORING
c CH2M HI
CNTR COUNTER HOR HAND-OFF-REMOTE MIN MINIMUM
EW EACH WAY PL PLATE (STEEL)
ACI AMERICAN CONCRETE INSTITUTE
er
CO CLEANOUT, CARBON MONOXIDE HORIZ HORIZONTAL
APVD
EWC ELECTRIC WATER COOLER MISC MISCELLANEOUS PL PROPERTY LINE
Seal
A ACMU ACOUSTICAL CONCRETE MASONRY
COL COLUMN, COLOR HP HORSEPOWER
UNIT, ACOUSTICAL CMU EXH EXHAUST MJ MECHANICAL JOINT PLAM PLASTIC LAMINATE
CONC CONCRETE HPT HIGH POINT
ACP ACOUSTICAL PANELS EXP EXPANSION, EXPOSED MLO MAIN LUGS ONLY PLAS PLASTER, PLASTIC
BY
COND CONDENSATE HPU HYDRAULIC POWER UNIT
ACST ACOUSTICAL EXP AB EXPANSION ANCHOR BOLT MMDW DRY WEATHER MAXIMUM MONTH PLC PROGRAMMABLE LOGIC CONTROLLER
CONDTN CONDITIONED HR HOSE RACK, HANDRAIL
ACT ACOUSTICAL TILE EXP JT EXPANSION JOINT MMP MECHANICAL MOUNTING PANEL PLYWD PLYWOOD
CONN CONNECTION HV HOSE VALVE
AD AREA DRAIN EXST, EXIST EXISTING MMWW WET WEATHER MAXIMUM MONTH PNL PANEL
CONSTR CONSTRUCTION HVAC HEATING, VENTILATING AND
APVD
ADDL ADDITIONAL EXT EXTERIOR MO MANUAL OPERABLE, MASONRY OPENING PP POWER POLE
S THE PROPERTY OF
CONT CONTINUED, CONTINUOUS, CONTINUATION AIR CONDITIONING MP METAL PANEL P-P PUSH-PULL
LL.
ADJ ADJACENT
CONTR CONTRACTOR
ON OF CH2M HI
°F DEGREE FAHRENHEIT HWL HIGH WATER LEVEL MPU MULTIPURPOSE UNIT PPL POLYPROPYLENE LINED
ADW DRY WEATHER AVERAGE
ew
COORD COORDINATE
QC Revi
AFD ADJUSTABLE FREQUENCY DRIVE FACP FIRE ALARM CONTROL PANEL MS MANUFACTURER'S STANDARD PR PAIR
COP COPPER IC INTERRUPTING CAPACITY
AFF ABOVE FINISHED FLOOR FB FLAT BAR MSC MANUFACTURER SUPPLIED CABLE PRC POINT OF REVERSE CURVE
CP CENTER PIVOT ID INDUCED DRAFT, INSIDE DIAMETER PRCST PRECAST
AFG ABOVE FINISHED GRADE F, FU FUSE MSR GROUPED MOTOR CONTROL
CP-X CONTROL PANEL NO. X IE INVERT ELEVATION
ZATI
CE,I
F, FX FIXED MT MOUNT PREFAB PREFABRICATION
AG ACOUSTICAL, ACOUSTICAL GLASS,
CPLG COUPLING FAP FIRE ALARM PANEL I.F. INSIDE FACE
TTEN AUTHORI
PRES PRESSURE
ONAL SERVI
AIR GAP (FIXED) MTD MOUNTED
ON
CPRSR COMPRESSOR FC FLEXIBLE CONDUIT IG INSULATING, INSULATING GLASS PRI PRIMARY
SI
MTG MOUNTING
CHK
AGGR AGGREGATE
CPT CONTROL POWER TRANFORMER, CARPET IN INCH
REVI
FCA FLANGED COUPLING ADAPTER PRM PERMANENT REFERENCED MARKER
AHR ANCHOR MTS MANUAL TRANSFER SWITCH
CPVC CHLORINATED PVC FCL2 FREE CHLORINE RESIDUAL INCAND INCANDESCENT PROJ PROJECTION
J.HARGI
INFLUENT
THOUT THE W RI
CR CONTROL RELAY FCO FLOOR CLEANOUT INFL PROP PROPERTY
STEEL CONSTRUCTION MU MULCHING
CRS COLD ROLLED STEEL FCTY FACTORY INJS INJECTIONS
PS PLASTIC SHEET, POLYCARBONATE SHEET
AJ ADJUSTABLE MV MERCURY VAPOR
CRS CONSTRUCTION ROAD STABILIZATION FD FLOOR DRAIN INST INSTANTANEOUS PAINT SYSTEM
PS
AL ALUMINUM MWS MAXIMUM WATER SURFACE
CT CERAMIC TILE FDN FOUNDATION INSTM INSTRUMENT, INSTRUMENTATION
PSF POUNDS PER SQUARE FOOT
ALKY ALKALINITY
CT CURRENT TRANSFORMER INSUL INSULATION N NORTH, NEUTRAL
DR
CTR CENTER IP INLET PROTECTION, INSTRUMENTATION PANEL NA NON-AUTOMATIC
FF FINISHED FLOOR
N,AS AN I
AMRD ACOUSTICAL METAL ROOF DECKING PT POINT OF TANGENCY
B CTRD CENTERED IRRIG IRRIGATION NC NORMALLY CLOSED
E
FG FINISH GRADE, FLOAT GLASS
J.OSOSKI
ANDZ ANODIZE PT POTENTIAL TRANSFORMER
CTSK COUNTERSUNK FH FLAT HEAD ITG INSULATED TEMPERED GLASS NEUT NEUTRAL
APPROX APPROXIMATE PT PRESSURE TREATED
NCORPORATED HEREI
CU CUBIC FHY ITX ISOLATION TRANSFORMER
FIRE HYDRANT NG NATURAL GAS PTD PAPER TOWEL DISPENSER
APVD APPROVED
DATE
CU FT CUBIC FOOT FIG FIGURE IU INTAKE UNIT NGVD NATIONAL GEODETIC VERTICAL DATUM
ARCH ARCHITECTURAL PTN PARTITION
CU IN CUBIC INCH FL FLOW LINE IW IRRIGATION WELL NIC NOT IN CONTRACT
AR ANALOG RELAY PV PLUG VALVE
CUH COPPER TUBING, HARD DRAWN FLG FLANGE N.O. NORMALLY OPEN
AS AS SELECTED PVC POLYVINYL CHLORIDE
DSGN
JALOUSIE
NO.
CV CHECK VALVE FL FLOOR NO., # NUMBER
ASSY ASSEMBLY PVI POINT OF VERTICAL INTERSECTION
JA JAL-AWNING
N W HOLE OR I
CWR CABINET DOOR MOUNTED FLEX FLEXIBLE NOM NOMINAL PVMT PAVEMENT
GNS I
ATS AUTOMATIC TRANSFER SWITCH JB
J JUNCTION BOX
WASTE RECEPTACLE FLH FLAT HEAD NP NON-PROTECTED
AUTO AUTOMATIC JANITOR PVT POINT OF VERTICAL TANGENCY
JAN
S NOT TO BE USED,I
AVG AVERAGE JT JOINT
FNSH FINISH NTS NOT TO SCALE
CUT
AWW WET WEATHER AVERAGE QMM MAXIMUM 30 DAY FLOW
FOB FLAT ON BOTTOM K KEY GROUP, KEY INTERLOCK
QPI PEAK INSTANTANEOUS FLOW
TY
@ AT D DEEP, DRAIN
NEW HAVEN,CONNECTI
O2
CONTROL AUTHORI
FOT KIP THOUSAND POUNDS
d PENNY NAIL SIZE QPP PEAK PUMPING FLOW
O TO O OUT TO OUT
B BELL FP FIELD PANEL KIT KITCHEN QT
DA DUAL ACTION QUARRY TILE
OA OVERALL, ODOROUS AIR
BAL BALANCE FPM FEET PER MINUTE K-PL KICKPLATE
DAS DATA ACQUISTION SYSTEM OC ON CENTER
LL AND I
BETW BETWEEN FR FORWARD REVERSE KITCHEN SINK
DBA DEFORMED BAR ANCHOR KSK R RISER
BF BLIND FLANGE, BOTTOM FACE OC OPEN-CLOSE (O)
FRP FIBERGLASS REINFORCED PLASTIC KV KILOVOLTS R OR RAD
DBL DOUBLE RADIUS
OCA OPEN-CLOSE-AUTO
CH2M HI
BFV BUTTERFLY VALVE FSHS FOLDING SHOWER SEAT KILOVOLT AMPERES RA RETURN AIR
DC DIRECT CURRENT KVA
BL BASELINE OCR OPEN-CLOSE-REMOTE
FT FOOT OR FEET
THI
KVAR KILOVOLT AMPERES REACTIVE RC REINFORCED CONCRETE
DEG DEGREE OD OUTSIDE DIAMETER, OVERFLOW DRAIN
BFP BACKFLOW PREVENTER FTG FOOTING KILOWATT RCP REINFORCED CONCRETE PIPE
DET DETAIL KW
O.F. OUTSIDE FACE
ON
DN DOWN REINF REINFORCED, REINFORCING, REINFORCE
LOWER EXPLOSIVE LIMIT OPP OPPOSITE
BRK BRICK GC GROOVED COUPLING LEL
REQD
ON PUM P STATI
DO DISSOLVED OXYGEN REQUIRED
OSA OUTSIDE AIR
ONS
BRKR BREAKER GCMU GLAZED CONCRETE LF LINEAR FEET
DOL DIRECT-ON-LINE RESIL RESILIENT
OSC OPEN-STOP-CLOSE
ON
BSP BLACK STEEL PIPE MASONRY UNITS LG LONG
RFS ROLL-UP FIRE SHUTTER
DP, DPNL DISTRIBUTION PANEL OSD OPEN SITE DRAIN
ATI
BV BALL VALVE, BLOCK VENT LH LEFT HAND
GENERAL
BVC BEGINNING OF VERTICAL CURVE GFI GROUND FAULT INTERRUPTER LHR LEFT HAND REVERSE
OZ RH RODHOLE
DS DOWNSPOUT OUNCE
ABBREVI
GFR GROUND FAULT RELAY LLH LONG LEG HORIZONTAL
RHR RIGHT HAND REVERSE
DWG DRAWING
C CONDUIT, CASEMENT GH GREENHOUSE LLV LONG LEG VERTICAL P PROJECTED
RL RAIN LEADER
DWL DOWEL
°C DEGREE CELSIUS GL GLASS LNTL LINTEL P PILASTER, PIPE RLS RUBBER LINED STEEL
DELTA
C TO C CENTER TO CENTER GPD GALLONS PER DAY LONG LONGITUDINAL PAVT PAVER TILE RM ROOM
CAB CABINET GPH GALLONS PER HOUR LOS LOCK-OUT STOP PUSHBUTTON PB PUSHBUTTON SWITCH RO ROUGH OPENING
UNI
CB CATCH BASIN, CIRCUIT BREAKER GPM GALLONS PER MINUTE LP LIGHT POLE, LIGHTING PANEL, LOCAL PANEL PC POINT OF CURVE, PHOTOCELL ROL RAISE-OFF-LOWER
CC CENTER OF CIRCLE E EAST, EMPTY GPS GLOBAL POSITION SYSTEM LPT LOW POINT PC PRECAST CONCRETE PANEL RPM REVOLUTIONS PER MINUTE
CC CONTROL CABLE EA EACH, EXHAUST AIR GRTG GRATING LR LATCHING RELAY PCCP PRECAST CONCRETE CYLINDER PIPE
RR RIPRAP
CCP CENTRAL CONTROL PANEL EB, EBCT EMPTY BED CONTACT TIME GSB GYPSUM SOFFIT BOARD LR LOCAL-REMOTE PCV PRESSURE CONTROL VALVE
CCS CENTRAL CONTROL SYSTEM ECC ECCENTRIC GSP GALVANIZED STEEL PIPE LR LONG RADIUS PE PLAIN END
D CDF CONTROLLED DENSITY FILL EE EMERGENCY EYEWASH GV GATE VALVE LS LABORATORY SINK PED PEDESTAL, PEDESTRIAN
CE CONSTRUCTION ENTRANCE EDF EGG-SHAPED DIGESTER FACILITY GVL GRAVEL LT LEFT
CFM CUBIC FEET PER MINUTE EF EACH FACE, EXHAUST FAN GWB GYPSUM WALLBOARD LTG, LTS LIGHTS OR LIGHTING GENERAL NOTES:
CFS CUBIC FEET PER SECOND EFF EFFICIENCY, EFFICIENT LTX LIGHTING TRANSFORMER
GYP GYPSUM
1. THIS IS A STANDARD LEGEND SHEET.
CHEM CHEMICAL EFL EFFLUENT LWL LOW WATER LEVEL
H HIGH, HORN OR HOWLER THEREFORE, NOT ALL OF THE INFORMATION VERIFY SCALE
CHKD CHECKERED EIFS EXTERIOR INSULATION AND FINISH SYSTEM
H2S HYDROGEN SULFIDE SHOWN MAY BE USED ON THIS PROJECT. BAR IS ONE INCH ON
CI CAST IRON EL ELEVATION MA MANUAL-AUTO ORIGINAL DRAWING.
H.A.S. HEADED ANCHOR STUD
MI
MAS MASONRY 0 1"
CIP CAST IRON PIPE, CAST IN PLACE ELB ELBOW 2. CONTACT ENGINEER FOR ABBREVIATIONS
HC HOLLOW CORE WOOD
ELC ELECTRICAL LOAD CENTER MATL MATERIAL USED BUT NOT SHOWN ON THIS DRAWING. DATE NOVEMBER 2016
PRELI
CIP CULVERT INLET PROTECTION
HCL HYDROCHLORIC ACID
CISP CAST IRON SOIL PIPE ELEC ELECTRIC, ELECTRICAL MAX MAXIMUM PROJ 664626
HDNR HARDENER
CJ CONSTRUCTION JOINT ENGR ENGINEER MB MACHINE BOLT DWG
HDNS HARDNESS 100-G-002
CKT CIRCUIT EOP EDGE OF PAVEMENT MC MASONRY CLEARANCE
HDR HEADER SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/GEN/Dlv/100-G-002_664626.dgn
FILENAME:100-G-002_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 9:42:44 AM
1 2 3 4 5 6
GHTS RESERVED.
ABBREVIATIONS TG TEMPERED SECTION / DETAIL DESIGNATIONS DRAWING NUMBER DESIGNATION
TH TOP-HINGED
THD THREAD
RRUB RADIAL RUBBER
THK THICKNESS DRAWING NUMBER
RS RIGID STEEL
THRU THROUGH
100-S-201
LL 2016. ALL RI
RST REINFORCING STEEL ON DRAWING WHERE SECTION
SECTION (LETTER) OR
RT RIGHT TJB TERMINAL JUNCTION BOX OR DETAIL IS TAKEN:
DETAIL (NUMERAL)
TL TEFLON LINED PIPE
RTN RETURN DESIGNATION DRAWING NUMBER
REGENERATIVE THERMAL OXIDIZER T.O. TIME TO OPEN, TOP OF
RTO A 1 WHERE SHOWN
TOAE TIME OPEN AFTER ENERGIZATION
c CH2M HI
RUB RUBBER
65-S-301
TOC TOP OF CONCRETE
er
RUBC RUBBER CUSHIONED FLOORING
SEQUENTIAL NUMBER
APVD
Seal
A
RUBS RUBBER ESD CONTROL FLOORING TOC TOP OF CURB DRAWING NUMBER
R/W RIGHT OF WAY (REPLACED WITH A LINE
TOD TIME ON DELAY, TOP OF DUCT
IF TAKEN AND SHOWN SHEET TYPE
BY
TOTAL OXYGEN DEMAND
ON SAME SHEET) 0 GENERAL, DIAGRAMS, SCHEMATICS
S I-BEAM
TOF TOP OF FOOTING 1 DEMOLITION DRAWINGS
S SLOPE, SOUTH, SWITCH
TOG TOP OF GROUT, TOP OF GRATE SECTION 2 PLANS
SA SUPPLY AIR B 3 SECTIONS AND OR ELEVATIONS
APVD
T.O.P. TOP OF PARAPET SCALE
S THE PROPERTY OF
SATC SUSPENDED ACCUSTICAL TILE CEILING ON DRAWING WHERE SECTION 4 LARGE SCALED VIEWS
LL.
TOS TOP OF SLAB 5 DETAILS
65-S-201 IS SHOWN:
SB SEDIMENT BASIN
ON OF CH2M HI
TOW TOP OF WALL 6 SCHEDULES
ew
SC SHOWER CURTAIN, SOLID CORE WOOD DRAWING NUMBER(S)
QC Revi
TP TURNING POINT
SCADA SUPERVISORY CONTROL AND DATA ACQUISITION WHERE TAKEN
TR TRANSOM, TRUSS
SCC SOLID CORE DISCIPLINE
TRANS TRANSFORMER, TRANSITION
ZATI
SCFM STANDARD CUBIC FEED PER MINUTE G GENERAL
CE,I
SCHED SCHEDULE
TRANSV TRANSVERSE
DETAIL C CIVIL
TTEN AUTHORI
ONAL SERVI
TRD TREAD 2 L EROSION CONTROL
ON
SCU SPEED CONTROL UNIT SCALE ON DRAWING WHERE DETAIL
TS TEMPORARY SEEDING, TUBE STEEL S STRUCTURAL
SI
CHK
IS SHOWN:
REVI
SDP SUB-DISTRIBUTION PANEL A ARCHITECTURAL
TSHT THRESHOLD 65-S-201
F FIRE PROTECTION
SDWK SIDEWALK DRAWING NUMBER(S)
S
TSS
J.HARGI
P PLUMBING
WHERE TAKEN
THOUT THE W RI
SEC SECONDARY TOP OF STEEL
TST D PROCESS
SECT SECTION TTC TELEPHONE TERMINAL CABINET Y PIPING
DR
SH SHEET FACILITY
N,AS AN I
TX TRANSFORMER SCALE REFERENCE (eg: ELEVATIONS)
B SHA SURFACE HARDENING AGENT 100 - UNION PUMP STATOIN
E
J.OSOSKI
TYP TYPICAL
200 - EAST STREET PUMP STATION
SHS SOLIDS HANDLING SYSTEM
300 - BOULEVARD PUMP STATION
NCORPORATED HEREI
SIM SIMILAR
UON UNLESS OTHERWISE NOTED
DATE
SK SINK SECTION CALLOUT WHERE SECTION
UNO UNLESS NOTED OTHERWISE
SLR SEALER A IS ON THE SAME SHEET AND CUT
UPS UNINTERRUPTIBLE POWER SUPPLY
SMLS SEAMLESS EPOXY EXTENDS TO A FIXED LIMIT
USB UNIT SUBSTATION
DSGN
NO.
SOI SPRAY- ON INSULATION UVR UNDER VOLTAGE RELAY
N W HOLE OR I
SOLN SOLUTION
GNS I
SP SPACE OR SPACES, V VENT, VALVE
ON
GNHW PCA LONG TERM CONTROL PLAN
SECTION CALLOUT WHERE SECTION
S NOT TO BE USED,I
IS ON ANOTHER SHEET AND CUT
SPD SUMP PUMP DISCHARGE VC VERTICAL CURVE
EXTENDS THROUGHOUT ENTIRE SHEET
CUT
65-S-301 65-S-301
SPG SPACING VCP VITRIFIED CLAY PIPE
TY
NEW HAVEN,CONNECTI
SPLY SUPPLY VCT
CONTROL AUTHORI
SQ SQUARE VEL VELOCITY
SQ FT SQUARE FOOT, FEET VERT VERTICAL
VHC VOLATILE HYDROCARBONS 1 GRID LINE INDICATOR
LL AND I
SQ IN SQUARE INCH
SR SHORT RADIUS VIB VIBRATION
CH2M HI
SST STAINLESS STEEL VIN VINYL
1. PROJECT ELEVATIONS ARE BASED ON NAVD 88. EXISTING ELEVATIONS ARE
THI
SSC SUPERVISORY SET POINT CONTROL VINT, VT VINYL TILE 1 KEYNOTE NUMBER BASED ON NGVD 29. EXISTING DRAWINGS WERE USED AS BACKGROUNDS FOR
EXISTING BUILDINGS/STRUCTURES. EXISTING ELEVATIONS HAVE BEEN
ST STORM DRAIN VP VERTICAL PIVOTED
ON
SUSP SUSPENDED
ONS AND
W/ WITH
GENERAL LEGEND
ON PUM P STATI
SV SOLENOID VALVE
WC WATER COLUMN
SVIN SHEET VINYL
ON
WEASTRIP WEATHERSTRIP
SWBD SWITCHBOARD
WG WIRE, WIRE GLASS DESIGN DETAIL DESIGNATION
GENERAL
SYMM SYMMETRICAL
ATI
WHD WATTHOUR DEMAND METER
ABBREVI
T/ TOP OF WR WASTE RECEPTACLE DESIGN DETAIL
T&B TOP AND BOTTOM WRB
WR WATER RESISTANT GWB DESIGNATION 1234-567
WS WATER SURFACE, WATERSTOP, WELDED STEEL (NUMERAL)
T&G TONGUE AND GROOVE
WWF WELDED WIRE FABRIC SHOWN ON DESIGN
UNI
TA TRANSFER AIR
DETAIL DRAWING(S)
TAN TANGENT WWPH WET WEATHER PEAK HOUR
TB TERMINAL BOARD
NOTES:
TBG TUBING
TC TIME TO CLOSE 1. ALL DESIGN DETAILS ARE TYPICAL AND MUST BE USED IF DESIGN
D TC TURBIDITY CURTAIN DETAIL DESIGNATION IS NOT SHOWN
TCAD TIME CLOSE AFTER DE-ENERGIZATION
2. THE TERM STANDARD DETAIL, OR A FORM OF IT, IS SYNONYMOUS WITH DESIGN DETAIL.
TCAE TIME CLOSE AFTER ENERGIZATION THE DESIGN DETAILS REPRESENT THE CHARACTER AND NATURE OF THE WORK
TDH TOTAL DYNAMIC HEAD REQUIRED THROUGHOUT THE PROJECT. ALL ASSOCIATED WORK SHALL BE IN
TDR TIME DELAY RELAY ACCORDANCE WITH THE DESIGN DETAILS SHOWN WHETHER THE DETAILS ARE
TECH TECHNICAL
SPECIFICALLY REFERENCED OR NOT. GENERAL NOTES: VERIFY SCALE
MI
TEMP TEMPORARY, TEMPERATURE 0 1"
THEREFORE, NOT ALL OF THE INFORMATION
TF TOP FACE SHOWN MAY BE USED ON THIS PROJECT. DATE NOVEMBER 2016
PRELI
TFG TEMPERED FLOAT GLASS PROJ 664626
2. CONTACT ENGINEER FOR ABBREVIATIONS
USED BUT NOT SHOWN ON THIS DRAWING. DWG 100-G-003
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/GEN/Dlv/100-G-003_664626.dgn
FILENAME:100-G-003_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 9:42:50 AM
1 2 3 4 5 6
GHTS RESERVED.
INSTRUMENT IDENTIFICATION LINE LEGEND ABBREVIATIONS & LETTER SYMBOLS
INSTRUMENT IDENTIFICATION LETTERS TABLE
PRIMARY PROCESS
AC ALTERNATING CURRENT
FIRST-LETTER SUCCEEDING-LETTERS (CLOSED CONDUIT,
PARALLELING LINES AM AUTO-MANUAL
DASHED LINE INDICATES
LL 2016. ALL RI
PROCESS OR READOUT OR READOUT OR READOUT OR CL2 etc. CHLORINE (TYPICAL: USE STANDARD CHEMICAL
ALTERNATE FLOW STREAM)
LETTER INITIATING VARIABLE MODIFIER PASSIVE FUNCTION PASSIVE FUNCTION PASSIVE FUNCTION ELEMENT ABBREVIATIONS)
EXAMPLE SYMBOLS (2)
A ANALYSIS (+) ALARM SECONDARY PROCESS COD CHEMICAL OXYGEN DEMAND
BYPASS PROCESS CP-X CONTROL PANEL NO. X (X = FACILITY NUMBER)
B BURNER, COMBUSTION USER'S CHOICE (*) USER'S CHOICE (*) USER'S CHOICE (*)
DC DIRECT CURRENT
c CH2M HI
(A)
C USER'S CHOICE (*) CONTROL DO DISSOLVED OXYGEN
er
PROCESS (OPEN CHANNEL)
APVD
Seal
A D DENSITY (S.G.) DIFFERENTIAL FCL2 FREE CHLORINE RESIDUAL
CLARIFYING ABBREVIATIONS (A) TOTAL OF 2 SIGNALS FOS FAST-OFF-SLOW
E VOLTAGE PRIMARY ELEMENT, ANALOG SIGNAL
FOSA FAST-OFF-SLOW-AUTO
FIRST LETTER(S) SENSOR (4 TO 20 mAdc, ETC.)
BY
FOSR FAST-OFF-SLOW-REMOTE
BB
DISCRETE FP-W-X FIELD PANEL NO. WX (W = UNIT PROCESS NUMBER
SUCCEEDING LETTER(S) F FLOW RATE RATIO
FIT (ON/OFF, ETC.) X = PANEL NUMBER)
(FRACTION) CONNECTING LINES
FR FORWARD-REVERSE
UP-LL-UU
PNEUMATIC SIGNAL
APVD
G USER'S CHOICE (*) GLASS, GAUGE GATE HOA HAND-OFF-AUTO
S THE PROPERTY OF
VIEWING DEVICE FILLED SYSTEM SIGNAL HOR HAND-OFF-REMOTE
LL.
UNIT NUMBER
ISR INTRINSICALLY SAFE RELAY
ON OF CH2M HI
H HAND (MANUAL) HIGH HYDRAULIC SYSTEM SIGNAL
ew
LEL LOWER EXPLOSIVE LIMIT
QC Revi
I CURRENT (ELECTRICAL) INDICATE DATA LINK LOS LOCKOUT STOP
LR LOCAL-REMOTE
J POWER SCAN BUILDING OR
LOOP NUMBER MA MANUAL-AUTO
FACILITY BOUNDARY MC MODULATE-CLOSE
ZATI
CE,I
K TIME, TIME SCHEDULE TIME RATE CONTROL STATION
OF CHANGE PACKAGE SYSTEM NON-CONNECTING LINES MCC-X MOTOR CONTROL CENTER NO. X
TTEN AUTHORI
ONAL SERVI
UNIT PROCESS
EQUIPMENT MSC MANUFACTURER SUPPLIED CABLE
ON
NUMBER L LEVEL LIGHT (PILOT) LOW NC NORMALLY CLOSED
SI
CHK
REVI
M MOTION MOMENTARY MIDDLE, INTERMEDIATE SIMILAR PROCESS NO NORMALLY OPEN
OC OPEN-CLOSE(D)
J.HARGI
OCA OPEN-CLOSE-AUTO
THOUT THE W RI
O USER'S CHOICE (*) ORIFICE, RESTRICTION OCR OPEN-CLOSE-REMOTE
OO ON-OFF
P PRESSURE, VACUUM POINT (TEST)
OOA ON-OFF-AUTO
CONNECTION
OOR ON-OFF-REMOTE
Q QUANTITY INTEGRATE, ORP OXIDATION REDUCTION POTENTIAL
DR
R RADIATION RECORD OR PRINT PLC PROGRAMMABLE LOGIC CONTROLLER
N,AS AN I
B RIO REMOTE I/O UNIT
E
S SPEED, FREQUENCY SAFETY SWITCH
J.OSOSKI
RTU-X REMOTE TELEMETRY UNIT NO. X
ANALOG INPUT T TEMPERATURE TRANSMIT S A PROCESS INTERFACE SOF SLOW-OFF-FAST
NCORPORATED HEREI
U MULTI VARIABLE MULTI FUNCTION MULTI FUNCTION MULTI FUNCTION SS START-STOP
DATE
ANALOG OUTPUT
TCL2 TOTAL CHLORINE RESIDUAL
V VIBRATION, VALVE, DAMPER,
MECHANICAL ANALYSIS LOUVER TOC TOTAL ORGANIC CARBON
DISCRETE INPUT A D SIGNAL INTERFACE
X TOD TOTAL OXYGEN DEMAND
DSGN
NO.
W WEIGHT, FORCE WELL TURB TURBIDITY
DISCRETE OUTPUT
X X UNCLASSIFIED (*) X AXIS UNCLASSIFIED (*) UNCLASSIFIED (*) UNCLASSIFIED (*) VHC VOLATILE HYDROCARBONS
N W HOLE OR I
VIB VIBRATION
GNS I
Y EVENT, STATE Y AXIS RELAY, COMPUTE, A INTERFACE LETTER
ON
GNHW PCA LONG TERM CONTROL PLAN
D DESTINATION DRAWING NO.
S NOT TO BE USED,I
UNCLASSIFIED FINAL S SOURCE DRAWING NO.
CUT
CONTROL ELEMENT
TY
NEW HAVEN,CONNECTI
INTERFACE TO
(+) WHEN USED, EXPLANATION IS SHOWN ADJACENT TO INSTRUMENT SYMBOL. SEE ABBREVIATIONS AND LETTER SYMBOLS.
LL AND I
OR FROM PROCESS
(*) WHEN USED, DEFINE THE MEANING HERE FOR THE PROJECT.
EXTERNAL TO PROJECT
CH2M HI
GENERAL INSTRUMENT OR HAND SWITCHES AND
THI
PROCESS OR SIGNAL
FUNCTIONAL SYMBOLS INDICATING LIGHTS N LINE CONTINUATION N
C OO
FIELD MOUNTED YL ON AND OFF EVENT
LIGHTS
REAR-OF-PANEL
ON AND CONTROL
MOUNTED (OPERATOR
INACCESSIBLE) ON-OFF HAND SWITCH,
OO
MAINTAINED CONTACT
SELF CONTAINED VALVE & GENERAL NOTES
HS SWITCH (CONTROLLED
PANEL MOUNTED
DEVICE WILL RESTART
EQUIPMENT TAG NUMBERS
ON
(OPERATOR
ON RETURN OF POWER 1. COMPONENTS AND PANELS SHOWN WITH A SINGLE
LEGEND -SHEET 1
ACCESSIBLE)
ON PUM P STATI
AFTER POWER FAILURE). D-UP-LL-UU ASTERISK ( ) ARE TO BE PROVIDED AS PART OF A
PACKAGE SYSTEM.
ON
SS STOP-START HAND SWITCH
MCC MOUNTED 2. COMPONENTS AND PANELS SHOWN WITH A DOUBLE
GENERAL
SWITCHES (CONTROLLED AVRV AIR AND VACUUM RELEASE VALVE
DIVISION 26, ELECTRICAL.
DEVICE WILL NOT RESTART E EJECTOR
ON RETURN OF POWER G GATE
NSTRUM ENTATI
3. THIS IS A STANDARD LEGEND. THEREFORE, NOT ALL OF
AFTER POWER FAILURE). M MECHANICAL EQUIPMENT
THIS INFORMATION MAY BE USED ON THE PROJECT.
P PUMP
T TANK
UNI
LL LOOP NUMBER
UU UNIT NUMBER
I
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 100-G-005
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/GEN/Dlv/100-G-005_664626.dgn
FILENAME:100-G-005_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 9:42:46 AM
1 2 3 4 5 6
VALVE SYMBOLS
GHTS RESERVED.
MISCELLANEOUS SYMBOLS PUMP AND COMPRESSOR SYMBOLS
GATE PINCH PRESSURE RELIEF
CENTRIFUGAL PROGESSING
K AIR AND/OR PISTON PUMP
FFLCPLLLX PUMP (DRY PIT) CAVITY PUMP
VACUUM RELEASE XX
LL 2016. ALL RI
KNIFE GATE NEEDLE V PANEL CONTINUED XX
XX
VENT TO ON SAME OR OTHER
REGULATED SIDE ATMOSPHERE
DRAWING SUBMERSIBLE
BUTTERFLY SWING CHECK CENTRIFUGAL WET PIT COMPRESSOR
PRESSURE CONTROL PUMP OR TURBINE PUMP (CENTRIFUGAL) SUMP PUMP
XX
c CH2M HI
XX
GLOBE BALL CHECK AIR GAP
er
XX
APVD
PANEL OUTLINE RECIPROCATING OR
Seal
A PRESSURE REGULATION COMPRESSOR
PANEL NAME METERING PUMP
BACKFLOW (CLAY-TYPE) (PISTON)
BALL (POSITIVE DISPLACEMENT) XX
PREVENTER 120V 120 VOLT,
XX
BY
MULTI-PORT VALVE 60 HZ POWER
V T DRIP TRAP
(GATE VALVE SHOWN. FOR
VEE-BALL ROTARY
OTHER VALVE TYPES, PERISTALLIC
480V 480 VOLT, BLOWER OR FAN
APPROPRIATE VALVE PUMP
PIG INSERT POINT 60 HZ POWER DIAPHRAGM PUMP (CENTRIFUGAL)
SYMBOL SHOWN.) SEAT
APVD
TELESCOPING
SEAT PORT XX
S THE PROPERTY OF
PORTS ARE IMPLIED BY
XX
LL.
ECCENTRIC PLUG INDICATED FLOW PATTERN. PIG CATCH POINT
ON OF CH2M HI
XX AIR SET GEAR PUMP OR BLOWER
ew
S SAMPLE EJECTOR
(POSITIVE DISPLACEMENT)
QC Revi
XX = SUPPLY PRESSURE
DIAPHRAGM ANGLE GATE IN PSIG. XX
SELF CONTAINED
A
MUD AIR SUPPLY
PLUG
ZATI
XX: AS ADJUSTABLE SPEED
CE,I
CS-1 CONSTANT SPEED (SINGLE SPEED)
TTEN AUTHORI
ONAL SERVI
CS-2 CONSTANT SPEED (TWO SPEED)
ON
AP AIR PURGE SET
SI
CHK
REVI
RECEPTACLE
GATE SYMBOLS
THOUT THE W RI
FABRICATED RUPTURE DISK
SLUICE
SLIDE
STOP LOG
(VACUUM) FLOW STREAM IDENTIFICATION
S SEAL WATER SET
BUTTERFLY FLAP SHEAR RUPTURE DISK ALP AIR LOW PRESSURE PROCESS S SANITARY SEWER (GRAVITY)
DR
N,AS AN I
TV MONITOR ARV ACID RESISTANT VENT SC SUPPLEMENTAL CARBON
B TV
E
J.OSOSKI
FLEXIBLE CONNECTION BD BLOW DOWN SCS SUPPLEMENTAL CARBON SOLUTION
ACTUATOR SYMBOLS
NCORPORATED HEREI
BSD BLENDED SLUDGE SHC SODIUM HYPOCHLORITE
DATE
PNEUMATIC DIAPHRAGM AERATOR TV TV CAMERA
VALVE BYP BYPASS SMD SCUM DECANT
SPRING-OPPOSED, SINGLE MANUAL
POSITIONER
OR DOUBLE ACTING
DSGN
NO.
CA SODIUM HYDROXIDE / CAUSTIC SPD SUMP PUMP DRAIN / DISCHARGE
PNEUMATIC CYLINDER
N W HOLE OR I
RADIO ANTENNA
GNS I
SINGLE OR DOUBLE H HYDRAULIC CO CONDENSATE DRAIN SR SCRUBBER RECIRCULATION
ACTING ACTUATED DIAPHRAGM SEAL
S NOT TO BE USED,I
M DIFFERENTIAL D DRAIN (PLUMBING) SU SULFURIC ACID
ANNULAR DIAPHRAGM SEAL I
CUT
ELECTRIC MOTOR PRESSURE
DR DRAIN (PROCESS) TA TREATED AIR
TY
INTERLOCK, SEE
NEW HAVEN,CONNECTI
CONTROL AUTHORI
CONTROL DIAGRAMS
E/H
COMPOSITE SAMPLER FF FIRE SUPPRESSION FOAM TPSD THICKENED PRIMARY SLUDGE
S ELECTROHYDRAULIC SS
SOLENOID I
FO FUEL OIL TW TEMPERED WATER (POTABLE)
LL AND I
FLAME TRAP TWAS THICKENED WAS
VOICE COMMUNICATION FS FIRE SPRINKLER WATER
NOTE: XX: FO FAIL OPEN
CH2M HI
ON LOSS OF PRIMARY POWER FC FAIL CLOSED POINT
G NATURAL GAS (PROCESS) V VENT
FLP FAIL TO LAST POSITION
THI
(PNEUMATIC, ELECTRICAL, OR
HYDRAULIC)
GTO GRAVITY THICKENER OVERFLOW VR VAPOR RECOVERY
CALIBRATION COLUMN
ON AND CONTROL
TURBINE METER
BLIND FLANGE SCREW CONVEYOR ISD IMPORTED SLUDGE
WAS WASTE ACTIVATED SLUDGE
ON
LPS LOW PRESSURE STEAM
LEGEND -SHEET 2
ON PUM P STATI
STRAINER NG NATURAL GAS (PLUMBING)
SUBMERSIBLE MIXER
LEVEL DE
ON
ORFICE PLATE DENSITY METER
(BUBBLER TUBE)
NRCY NITRATE RICH RECYCLE
GENERAL
FLOW TUBE OA ODOROUS AIR
XX
GENERIC
ULTRASONIC OD OVERFLOW ROOF DRAIN
NSTRUM ENTATI
FILTER INTRINSIC SAFETY
FLOWMETER BARRIER/RELAY
OF OVERFLOW
ELECTROMAGNETIC LE
M LEVEL (ULTRASONIC)
FLOWMETER PULSATION
M PE PRIMARY EFFLUENT
DAMPENER
UNI
PSD PRIMARY SLUDGE
INLINE FAN
EXPANSION
RAS RETURN ACTIVATED SLUDGE
CHAMBER
D PIPING DESIGNATION
I
SIGHT INDICATOR RBSD RECYCLE BLENDED SLUDGE
RD ROOF DRAIN
SLUDGE
RAS
GRINDER RHG REFRIGERANT HOT GAS
VERIFY SCALE
MI
0 1"
IDENTIFICATION RL REFRIGERANT LIQUID NOTE:
DATE NOVEMBER 2016
PRELI
1. FOR EXISTING CIVIL YARD PIPING FLOW STREAM
RS REFRIGERANT SUCTION IDENTIFICATION, SEE CIVIL LEGEND. PROJ 664626
DWG 100-G-006
RTW RECIRCULATING TEMPERED WATER
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/GEN/Dlv/100-G-006_664626.dgn
FILENAME:100-G-006_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 9:42:41 AM
1 2 3 4 5 6
GHTS RESERVED.
GENERAL ARCHITECTURAL NOTES ARCHITECTURAL/STRUCTURAL LEGEND
1. UNLESS OTHERWISE INDICATED, PLAN DIMENSIONS ARE TO COLUMN GRID ON SYMBOL LEGEND
CENTERLINES, NOMINAL SURFACE OF MASONRY, FACE OF STUDS AND FACE OF
CONCRETE WALLS.
A NEW REFERENCE GRID INDICATOR
LL 2016. ALL RI
2. "FLOOR LINE" REFERS TO TOP ON CONCRETE SLABS. FINISH FLOORING IS
INSTALLED ABOVE THE FLOOR LINE. FOR DEPRESSED FLOORS AND CURBS,
SEE STRUCTURAL DRAWINGS. A EXISTING REFERENCE GRID INDICATOR
c CH2M HI
3. REPETITIVE FEATURES ARE NOT DRAWN IN THEIR ENTIRETY AND SHALL BE
COMPLETELY PROVIDED AS IF DRAWN IN FULL.
er
APVD
ROOM NAME ROOM NAME
Seal
A
4. WHERE DOOR IS LOCATED NEAR CORNER OF ROOM AND IS NOT LOCATED BY XX-101 101
ROOM IDENTIFIER
DIMENSION ON PLAN OR DETAILS, DIMENSION SHALL BE 3-INCHES FROM FACE OF OR
STUD (WALL) TO FACE OF ROUGH OPENING. DIMENSION SHALL BE 6" FROM FACE
BY
OF WALL TO EDGE OF ROUGH OPENING AT CONCRETE WALLS, 8" AT CMU WALLS. "XX" = FACILITY DOOR LETTER
INDICATOR
5. AT SOUND INSULATED WALLS, FULL HEIGHT PARTITIONS SHALL BE SEALED BOTH
101A
(IF SHOWN) ROOM NUMBER
SIDES WITH ACOUSTIC SEALANT; TOP, BOTTOM, INTERSECTION, DOOR FRAMES,
XX-
APVD
GLAZED OPENING FRAMES, AND OTHER PENETRATIONS. DOOR IDENTIFIER
S THE PROPERTY OF
LL.
6. LINE OF EXISTING GRADES, AS SHOWN ON THE BUILDING ELEVATIONS AND
ON OF CH2M HI
ew
SECTIONS ARE APPROXIMATE. THEY ARE AT THE BUILDING FACE, OR ON THE
QC Revi
SECTION END EXCEPT AS NOTED.
XXW-1 OR W-1 WINDOW IDENTIFIER
7. VERIFY ALL ROUGH-IN DIMENSIONS FOR EQUIPMENT PROVIDED IN THIS
CONTRACT, OR BY OTHERS.
ZATI
CE,I
8. REFER TO ARCHITECTURAL, STRUCTURAL, MECHANICAL, ELECTRICAL AND XXR-1 OR R-1 RELIGHT IDENTIFIER
TTEN AUTHORI
ONAL SERVI
ON
OTHER CATEGORIES OR DRAWINGS FOR ADDITIONAL NOTES.
SI
CHK
REVI
9. VERIFY SIZE AND LOCATION OF, AND PROVIDE: REQUIRED OPENINGS THROUGH
FLOORS AND WALLS, ACCESS DOORS, FURRING, CURBS, ANCHORS AND
XXL-1 OR L-1 LOUVER IDENTIFIER
THOUT THE W RI
MECHANICAL, ELECTRICAL AND OTHER EQUIPMENT.
DR
N,AS AN I
B SYMBOL LEGEND
E
J.OSOSKI
P-1 PRECAST PANEL IDENTIFIER
NCORPORATED HEREI
GRATING, SPAN DIRECTION INDICATED
DATE
1
EXTERIOR ELEVATION INDICATOR
CHECKERED PLATE XX-A-301
DSGN
NO.
QUANTITY AND
N W HOLE OR I
GROUT A
DIRECTION OF
GNS I
E
POINTERS AS
ON
1
GRANULAR FILL D B INTERIOR ELEVATION INDICATOR
S NOT TO BE USED,I
CUT
EARTH OR FINISH GRADE C
TY
NEW HAVEN,CONNECTI
LL AND I
CMU WALL (PLAN)
CH2M HI
CMU WALL (SECTION)
THI
DIRECTION OF SLOPE DOWN
MASONRY WALL
ACTIVE INACTIVE
XX-
BATT INSULATION
ON
INDICATES PAIR OF DOORS
ON PUM P STATI
STEEL
ON
F.EXT-X
ALUMINUM
GENERAL
"X" = NUMBER IN SPECIFICATIONS
PLYWOOD
GYPSUM WALLBOARD
CONTROL JOINT
ACOUSTICAL TILE
UNI
EXPANSION JOINT
WOOD, ROUGH CONTINUOUS
ARCHI
WOOD, ROUGH NON-CONTINUOUS
D RAILINGS
WOOD, FINISHED
POST
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 100-G-007
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/GEN/Dlv/100-G-007_664626.dgn
FILENAME:100-G-007_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 9:42:39 AM
1 2 3 4 5 6
GHTS RESERVED.
PIPE AND FITTING SYMBOLS VALVE SYMBOLS VALVE DESIGNATIONS
DOUBLE LINE SINGLE LINE DOUBLE LINE SINGLE LINE MANUAL VALVES AND CHECK VALVES
SINGLE LINE DOUBLE LINE
LL 2016. ALL RI
EXISTING PIPE REDUCING BUSHING
GATE
K K
NEW PIPE OR
UNION KNIFE GATE
c CH2M HI
V 500
BUTTERFLY OR
er
APVD
EXISTING PIPE TO BE ABANDONED
Seal
A
CAP
GLOBE OR VALVE DESIGNATION
BY
EXISTING PIPE TO BE REMOVED
BALL OR VALVE TYPE, SEE
ANCHOR
SPECIFICATIONS
WELDED JOINT
SEATING PORT
APVD
ELBOW, 90 DEGREE
S THE PROPERTY OF
LL.
ECCENTRIC PLUG OR
GROOVED END JOINT CONTROL VALVES
ON OF CH2M HI
ew
QC Revi
CROSS PLUG OR COCK OR
M
FLANGED JOINT
VALVE FUNCTION
NEEDLE OR
ZATI
CE,I
TEE
MECHANICAL JOINT &
TTEN AUTHORI
ONAL SERVI
ON
PROPRIETARY RESTRAINED JOINT
FV
SI
CHK
DIAPHRAGM OR
ELBOW, 45 DEGREE
REVI
UP-LL-UU
BELL & SPIGOT JOINT (LEADED)
UNIT NUMBER
J.HARGI
THOUT THE W RI
LOOP NUMBER
HUB & SPIGOT JOINT SWING CHECK OR
LATERAL
(RUBBER GASKET) UNIT PROCESS NUMBER
DR
GROOVED END ADAPTER FLANGE
N,AS AN I
X = NO. IN SPECS
B
S.CLARK
FLANGED COUPLING ADAPTER S SAMPLE
SELF-CONTAINED REGULATING VALVES
NCORPORATED HEREI
(RESTRAINING SYSTEM BY MFR)
MUD
DATE
RESTRAINED FLANGED
COUPLING ADAPTER SEE 4005-545 PRESSURE RELIEF
DSGN
NO.
PRV-UP-LL-UU
N W HOLE OR I
FLEXIBLE COUPLING AIR AND/OR VACUUM RELEASE
GNS I
REGULATED SIDE
ON
GNHW PCA LONG TERM CONTROL PLAN
S NOT TO BE USED,I
LOOP NUMBER
CUT
REGULATED SIDE
UNIT PROCESS NUMBER
NOTES:
TY
ELASTOMER BELLOWS EXP JOINT
NEW HAVEN,CONNECTI
LL AND I
2. SYMBOLS SHOWN HERE FOR SINGLE LINE FITTINGS ARE GENERIC ONLY. REFER TO PIPING SEATING PORTS ARE IMPLIED BY
INDICATED FLOW PATTERN.
SPECIFICATIONS FOR SPECIFIC END CONNECTIONS FOR SINGLE LINE PIPE AND FITTINGS.
CH2M HI
ELBOW DOWN
3. EXISTING PIPE AND EQUIPMENT IS SHOWN LIGHT-LINED AND/OR SCREENED.
THI
TELESCOPING
NEW PIPING AND EQUIPMENT IS SHOWN HEAVY-LINED.
TEE UP
CAL
3. LOCATION AND NUMBER OF PIPE HANGERS AND PIPE SUPPORTS SHOWN IS ONLY
ON
PNEUMATIC CYLINDER MANUAL
APPROXIMATE. CONTRACTOR SHALL DESIGN SUPPORTS AS SPECIFIED.
ON PUM P STATI
PROCESS M ECHANI
CONCENTRIC REDUCER
4. ALL JOINTS SHALL BE WATERTIGHT. WALL PIPES SHALL BE USED WHEREVER
ON
S SOLENOID
PIPING PASSES FROM A STRUCTURE TO BACKFILL.
GENERAL
ELECTRIC MOTOR THRUST PROTECTION AS SPECIFIED, UNLESS OTHERWISE NOTED. THRUST PROTECTION
SHALL BE ADEQUATE FOR TEST PRESSURES SPECIFIED.
UNI
SCREWED PIPING, SHALL BE PROVIDED WITH THRUST PROTECTION AS SPECIFIED,
UNLESS OTHERWISE NOTED.
PIPING DESIGNATION
8. NUMBER AND LOCATION OF UNIONS SHOWN ON DRAWINGS IS ONLY APPROXIMATE. PROVIDE
ALL UNIONS NECESSARY TO FACILITATE CONVENIENT REMOVAL OF VALVES AND
EXAMPLE: MECHANICAL EQUIPMENT.
D
16" RAS 9. WHERE A GROOVED END COUPLING IS SHOWN, IT SHALL BE THE RIGID JOINT TYPE, UNLESS
OTHERWISE SPECIFIED. WHERE A FLANGED COUPLING ADAPTER IS SHOWN, A STANDARD
FLANGE SHALL BE JOINED TO THE COUPLING ADAPTER.
16" RAS
MI
0 1"
PRELI
PROJ 664626
DWG 100-G-012
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/GEN/Dlv/100-G-012_664626.dgn
FILENAME:100-G-012_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 9:43:10 AM
1 2 3 4 5 6
GHTS RESERVED.
HVAC GENERAL NOTES ABBREVIATIONS SYMBOL LIST
TC TEMPERATURE/CO2 COMBINATION SENSOR
LWT LEAVING WATER TEMPERATURE BALL VALVE
AFS AIR FLOW MEASURING STATION
1. NOTES BELOW ARE NOT INTENDED TO REPLACE SPECIFICATIONS. SEE SPECIFICATIONS FOR REQUIREMENTS IN ADDITION TO
AC AIR CONDITIONING MD MOTORIZED DAMPER
GENERAL NOTES. WATER FLOW METER
ACC AIR COOLED CONDENSER UNIT (NO COMPRESSOR) MAU MAKE-UP AIR UNIT M
LL 2016. ALL RI
2. CONTRACTOR SHALL VISIT THE SITE AND BECOME INFORMED AS TO THE NATURE AND SCOPE OF WORK REQUIRED BY BALANCING VALVE
ACCU AIR COOLED CONDENSING UNIT MAX MAXIMUM
CONTRACT DOCUMENTS PRIOR TO BIDDING PROJECT. MBH THOUSAND BTU/HOUR
AD ACCESS DOOR AV
3. PROVIDE ALL REQUIRED MATERIALS, LABOR, EQUIPMENT, AND SERVICES NECESSARY FOR THE INSTALLATION OF THE WORK MIN MINIMUM AIR VENT, AUTOMATIC
AHU AIR HANDLING UNIT BUTTERFLY VALVE
AS SHOWN ON THESE DRAWINGS OR SPECIFIED BY THE BASE BUILDING DRAWING AND SPECIFICATIONS. MTS MINUTES
AL ALUMINUM DUCTWORK
4. REFER TO AND CAREFULLY CHECK ARCHITECTURAL, ELECTRICAL, PLUMBING, AND FIRE PROTECTION DRAWINGS AND DETAILS, MUW MAKE-UP WATER
AFF ABOVE FINISH FLOOR
NOTES, LOCATIONS WHERE WALLS, PARTITIONS, CEILINGS, AND OTHER SURFACES ARE FURRED, LOCATIONS OF SHAFTS, GATE VALVE MV AIR VENT, MANUAL
c CH2M HI
AMPS AMPERE MV MOTORIZED VALVE
SOFFITS, AND CONFLICTS WITH WORK OF OTHER TRADES, AND ARRANGE WORK ACCORDINGLY. FURNISH ALL OFFSETS, NEG NEGATIVE
BAL BALANCE
er
APVD
DAMPERS, CONNECTORS, ETC., REQUIRED TO MEET SUCH CONDITIONS. NG NATURAL GAS
Seal
A BD BAROMETRIC DAMPER ANGLE GATE VALVE
5. DUE TO SCALE OF DRAWINGS, ALL REQUIRED OFFSETS, DAMPERS, ETC., MAY NOT BE INDICATED. NO NUMBER PUMP
BDD DAMPER BACK DRAFT OR
6. COORDINATE DIFFUSERS LOCATIONS AND DUCT WITH LIGHTING FIXTURES AND SPRINKLER HEADS. SEE ARCHITECTURAL NRS NON-RISING STEM
BHP BREAK HORSEPOWER
DRAWINGS FOR EXACT LOCATIONS AND DETAILS OF PARTITIONS, SUSPENDED CEILINGS, AND SOFFITS. GLOBE VALVE
BMS BUILDING MANAGEMENT SYSTEM NTS NOT TO SCALE
BY
7. ALL DUCT PASSING THROUGH FIRE, SMOKE RATED OR SMOKE/FIRE RATED BARRIERS (WALLS, FLOOR) SHALL BE PROVIDED OA OUTSIDE AIR STRAINER
BTU BRITISH THERMAL UNIT
WITH FIRE, SMOKE OR SMOKE/FIRE DAMPERS. LOCATIONS OR RATED WALLS SEE ARCHITECTURAL DRAWINGS. CONTRACTOR OBD OPPOSED BLADE DAMPER ISOLATION VALVE (REFER TO SPECS FOR TYPE)
BTUH BRITISH THERMAL UNIT/HR
SHALL VERIFY QUANTITY OF ALL DAMPERS IN ACCORDANCE WITH FINAL CONTRACT DOCUMENTS. ALL REQUIRED SMOKE OCPD OVER CURRENT PROTECTION DEVICE
DWD DOUBLE WALL DUCTWORK H HUMIDISTAT/SENSOR
DETECTORS PROVIDED BY DIV 23 SHALL BE CONNECTED TO FIRE ALARM SYSTEM. OED OPEN END DUCT, TERMINATE WITH
C-C COLUMN ENCLOSURE TO COLUMN ENCLOSRE ANGLE GLOBE VALVE
8. CONTRACTOR SHALL OBTAIN AND PAY FOR ALL REQUIRED PERMITS AND ARRANGE FOR ALL REQUIRED INSPECTIONS IN STAINLESS STEEL BIRD SCREEN
C-W COLUMN ENCLOSURE TO WALL
APVD
ACCORDANCE WITH STATE AND LOCAL GOVERNING CODES. OS&Y OUTSIDE STEM & YOKE
S THE PROPERTY OF
CA COMBUSTION AIR O OCCUPANCY SENSOR
9. THE TERM "PROVIDE" SHALL MEAN "TO FURNISH, INSTALL, AND CONNECT COMPLETELY".
LL.
CENTRIF CENTRIFUGAL TWO WAY MOTORIZED
10. TURN OVER TO THE OWNER ALL MANUFACTURER'S WARRANTIES FOR EQUIPMENT AND MATERIALS PROVIDED. P PUMP
ON OF CH2M HI
CFM CUBIC FEET PER MINUTE CONTROL VALVE
PBD PARALLEL BLADE DAMPER
ew
11. WHERE THE CONTRACTOR PROPOSES TO USE AN ITEM OF EQUIPMENT OTHER THAN THAT SPECIFIED OR DETAILED ON THE
CO CLEAN OUT PRESSURE GAUGE WITH COCK VALVE
QC Revi
DRAWINGS WHICH REQUIRES ANY REDESIGN OF THE STRUCTURE, PARTITIONS, FOUNDATIONS, PIPING, WIRING OR ANY OTHER PEF PROCESS EXHAUST FAN
CW DOMESTIC COLD WATER PH PHASE
PART OF THE MECHANICAL, ELECTRICAL OR ARCHITECTURAL LAYOUT, ALL SUCH REDESIGN AND ALL NEW DRAWINGS AND
CV CONTROL VALVE PNL PANEL THREE WAY MOTORIZED
DETAILING REQUIRED THEREFORE, SHALL BE PREPARED AT THE CONTRACTOR'S EXPENSE AND ARE SUBJECT TO THE REVIEW
CMEU CEILING MOUNTED EVAPORATOR POS POSITIVE CONTROL VALVE
AND APPROVAL OF THE OWNER OR HIS AUTHORIZED REPRESENTATIVE. OWNER RESERVES THE RIGHT TO HAVE THE RETURN / EXHAUST GRILLE
CUH CABINET UNIT HEATER
ZATI
PRESS PRESSURE
CE,I
ARCHITECT OR ENGINEER OF HIS CHOICE PREPARE ANY REDESIGN WORK.
DB DRY BULB PRV PRESSURE RELIEF VALVE
12. CONTRACTOR SHALL COORDINATE ELECTRICAL REQUIREMENTS OF MECHANICAL EQUIPMENT WITH DIVISION 26.
TTEN AUTHORI
ONAL SERVI
DC DIRECT CURRENT PS PRESSURE SWITCH
13. ALL WORK SHALL BE DONE WITH LICENSED WORKMEN IN ACCORDANCE WITH STATE AND LOCAL GOVERNING AUTHORITIES. OS & Y T
ON
THERMOSTAT/SENSOR
DIAMETER PSIA POUNDS PER SQUARE INCH
14. BEFORE SELECTING MATERIAL AND EQUIPMENT, AND PROCESSING THE WORK, INSPECT AREAS WHERE MATERIAL AND
SI
CHK
DHW DOMESTIC HOT WATER HEATER ATMOSPHERE
EQUIPMENT ARE TO BE INSTALLED TO INSURE SUITABILITY AND CHECK NEEDED SPACE FOR PLACEMENT AND CLEARANCES.
REVI
DN DOWN PSIG POUNDS PER SQUARE INCH GAUGE P PRESSURE SENSOR
15. BEFORE CUTTING AND DRILLING INTO BUILDING ELEMENTS, INSPECT AND LAYOUT WORK TO AVOID DAMAGING STRUCTURAL
DP DEW POINT RA RETURN AIR MOTORIZED VALVE
J.HARGI
EA EXHAUST AIR RECIRC RECIRCULATING
THOUT THE W RI
16. CONTRACTOR RESPONSIBLE FOR REPAIR AND PAYMENT FOR ALL UTILITIES DAMAGE DURING CONSTRUCTION. DUCT WORK, DIRECTION OF FLOW
EAT ENTERING AIR TEMPERATURE RH RELATIVE HUMIDITY
17. CONTRACTOR TO CONFIRM DUCTWORK LOCATIONS, ELEVATIONS AND SIZES BEFORE ANY WORK IS STARTED. IF ANY SAFETY RELIEF VALVE (PRESS.)
EF EXHAUST FAN RPM REVOLUTIONS PER MINUTE
DISCREPANCIES ARE FOUNDED, NOTIFY ENGINEER BEFORE PROCEEDING WITH WORK. (SEE PAR. 48 "COORDINATION (PRESSURE & TEMPERATURE)
ESP EXTERNAL STATIC PRESSURE SA SUPPLY AIR WITH TURNING VANES. PROVIDE TURNING
DRAWINGS").
EWT ENTERING WATER TEMPERATURE SATT SOUND ATTENUATOR
18. FOLLOW MANUFACTURER'S RECOMMENDATIONS FOR INSTALLATION OF PROVIDED EQUIPMENT.
EUH ELECTRIC UNIT HEATER SCFM STANDARD CUBIC FEET/MINUTE QUICK CLOSING LEVER VALVE OTHERWISE NOTED
19. CONTRACTOR TO REPLACE ALL SUSPENDED CEILING TILES DAMAGED AS A RESULT OF HVAC SYSTEM INSTALLATION.
EXH EXHAUST
DR
SPECIFICATIONS OF CONTRACT DOCUMENTS AND INSPECTION OF FIELD CONDITIONS FOR DIVISION 23.
FD/AD FIRE DAMPER/ACCESS DOOR
N,AS AN I
22. HVAC PLANS, DETAILS AND ONE LINE DIAGRAMS SHOW THE GENERAL LOCATION AND ARRANGEMENT OF THE SYSTEM. THESE SCP SHORT CIRCUIT CIRCULATION PUMP
NEGATIVE PRESSURE DUCT
B FLG FLANGE SP STATIC PRESSURE
E
ARE DIAGRAMMATIC AND DO NOT SHOW ALL OFFSETS, HANGERS, ACCESS DOORS, ETC. WHICH THE CONTRACTOR MUST
J.OSOSKI
FCU FAN COIL UNIT STP STANDARD TEMP & PRESSURE
PROVIDE TO COMPLETE THE SYSTEM. GAS COCK CHANGE OF ELEVATION,
FMS FLOW MEASURING STATION SUP SUPPLY
23. ALL WORK IN INTERIOR FINISHED SPACES EXCEPT INDICATED IS TO BE CONCEALED ABOVE CEILING. PROVIDE ALL NECESSARY
NCORPORATED HEREI
DROP
FPM FEET PER MINUTE SV SOLENOID VALVE
CUTTING, PATCHING, REPAINTING AND/OR REPLACEMENT OF FINISHES AS REQUIRED TO PERFORM COORDINATE WITH OTHER
DEGREES FAHRENHEIT T&PV TEMP & PRESSURE RELIEF VALVE CHECK VALVE
DATE
DIVISIONS. LINED DUCTWORK
FPS FEET PER SECOND SFD/AD COMBINATION SMOKE/FIRE DAMPER
24. IF MANUFACTURER OF EQUIPMENT REQUIRES LARGER CAPACITY CIRCUITRY AND/OR EQUIPMENT THE CONTRACTOR SHALL
FS FLOW SWITCH TC TEST CONNECTION WITH ACCESS
PROVIDE SUCH CAPACITY AND/OR EQUIPMENT UNDER THIS CONTRACT AT NO COST TO THE OWNER.
FT FEET FLEXIBLE CONNECTION (DUCTWORK)
DOOR BACKFLOW PREVENTER
25. SUPPORT DUCTWORK ABOVE SUSPENDED CEILING FROM CONSTRUCTION ABOVE AS CLOSE AS POSSIBLE TO BOTTOM OF
FTR FIN-TUBE RADIATION
DSGN
TEMP TEMPERATURE
NO.
SLABS, BEAMS, MAINTAINING HEADROOM AT ALL TIMES.
FT3 CUBIC FEET FD & AD
26. DO NOT SCALE DRAWINGS. CHECK EXISTING SPACE CONDITIONS AT THE JOB SITE. T THERMOSTAT
HOSE END DRAIN FIRE DAMPER WITH ACCESS DOOR
N W HOLE OR I
GA GAUGE TH TOTAL HEAT
27. DO NOT PENETRATE STAIR WALLS WITH ANY UTILITIES OR CONDUIT EXCEPT FOR UTILITIES SPECIFICALLY SERVING THAT STAIR.
GNS I
GPM GALLONS PER MINUTE TRA TRANSFER AIR
28. CONTROL CONTRACTOR PROVIDE ALL CONTROL DEVICES, EQUIPMENT, ACCESSORIES, VFD DRIVES, OTHER APPARATUS,
H HEAT CONTENT (BTU/lb) TRV RELIEF VALVE TEMP
CONTROL VALVES AND DAMPERS, ACTUATORS, SENSORS, ETC. AND ALL CONTROL WIRING RELATED TO FACILITY HOSE BIB BD
ON
MANAGEMENT SYSTEM (FMS). SEE SPECIFICATION SECTIONS 230900. TSP TOTAL STATIC PRESSURE BALANCING DAMPER
S NOT TO BE USED,I
30. PROVIDE FLEXIBLE JOINTS ON ALL PIPING AND DUCTWORK WHERE PENETRATING ALL BUILDING EXPANSION JOINTS. TYP TYPICAL FLEXIBLE CONNECTION (PIPING)
HP HORSEPOWER UH UNIT HEATER FLEXIBLE JOINT FD FIRE DAMPER / ACCESS DOOR
31. PROVIDE FLEXIBLE CONNECTIONS BETWEEN MECHANICAL EQUIPMENT AND DUCTWORK AND PIPING.
CUT
HT HEIGHT UN UNIT
32. PROVIDE MINIMUM OF 3' DUCT LINEAR AT EACH FAN-COIL UNIT BRANCH DUCT UNIT CONNECTION AND DUCT LINER FOR DUCT
TY
HZ CYCLES VD VOLUME DAMPER
NEW HAVEN,CONNECTI
FROM FAN-COIL UNIT TO SUPPLY DIFFUSERS (SEE DETAILS).
CONTROL AUTHORI
ID INSIDE DIAMETER VT VENT SD SMOKE DAMPER / ACCESS DOOR
33. PROVIDE VOLUME DAMPERS ON ALL BRANCHES OF DUCTWORK (SUPPLY, RETURN, EXHAUST).
IN INCHES VLV VALVE
34. PROVIDE FLEXIBLE DUCTWORK CONNECTION TO ALL CEILING SUPPLY DIFFUSERS. (MAXIMUM 3'-0" LONG).
KVA KILLOVOLT AMPERE VI VIBRATION ISOLATOR
35. REFER TO SPECIFICATION SECTION 078413 "THROUGH PENETRATION FIRESTOP SYSTEMS" FOR ALL MATERIALS AND METHODS CAP COMBINATION
KW KILOWATTS V VOLTS SF
FOR PENETRATION THROUGH FIRE AND SMOKE RATED ASSEMBLIES. FIRE & SMOKE DAMPER / ACCESS DOOR
LL AND I
L LENGTH W WATTS
36. ALL PENETRATIONS THRU WALLS, ROOF, AND FLOORS TO BE COORDINATED BEFORE SITE WORK EXECUTION WITH PIPE CONNECTION, BOTTOM
LAT LEAVING AIR TEMPERATURE WB WET BULB
STRUCTURAL ENGINEERS.
WG WATER GAUGE MOTORIZED DAMPER
37. THERMOSTAT AND TEMPERATURE SENSOR LOCATIONS TO BE COORDINATED WITH INTERIOR WALL LAYOUT, REFER TO LB POUNDS M OR MD
CH2M HI
LH LATENT HEAT WH WATER HEATER
ARCHITECTURAL PLANS. PIPE CONNECTION, TOP
WI WIDTH
38. CEILING DIFFUSER AND REGISTER LOCATIONS TO BE COORDINATED WITH CEILING GRID, LIGHTING & SPRINKLER LAYOUT.
THI
WT WEIGHT
REFER TO ARCHITECTURAL REFLECTED CEILING PLAN. BA BAROMETRIC DAMPER
39. PROVIDE MINIMUM OF 20' DUCT LINER AT EACH AIR HANDLING UNIT (SUPPLY AND RETURN CONNECTIONS). PIPE COUPLING (JOINT)
ON
47. WINGS: DETAIL MAJOR ELEMENTS, COMPONENTS, AND SYSTEM PF MECHANICAL EQUIPMENT AND MATERIALS IN
VOLUME DAMPER
RELATIONSHIPS WITH OTHER SYSTEMS, INSTALLATIONS, AND BUILDING COMPONENTS. SHOW SPACE REQUIREMENTS FOR
ON PUM P STATI
INSTALLATION AND ACCESS. INDICATE IF SEQUENCE AND COORDINATION ARE IMPORTANT TO EFFICIENT FLOW OF THE WORK. PIPE UNION, FLANGE
INCLUDE THE FOLLOWING.
HVAC LEGEND
OR
ON
THERMOMETER
NOTE: SOME SYMBOLS AND ABBREVIATIONS MAY OR PIPE UNION, SWEAT
A. PLANNED PIPING LAYOUT, INCLUDING VALVE AND SPECIALTY LOCATIONS AND VALVE-STEM MOVEMENT.
GENERAL
C. CLEARANCES FOR SERVING AND MAINTAINING EQUIPMENT, ACCESSORIES, AND SPECIALTIES, INCLUDING SPACE FOR PIPE ELBOW, TURNED DOWN TO EXISTING PIPING/DUCT
DISASSEMBLY REQUIRED BY PERIODIC MAINTENANCE.
MECHANICAL NOTE REFERENCE,
D. EQUIPMENT AND ACCESSORY SERVICE CONNECTIONS AND SUPPORT DETAILS. PIPE ELBOW, TURNED UP #
E. EXTERIOR WALL AND FOUNDATION PENETRATIONS. NUMBER INDICATES NOTE
UNI
I. FLOOR PLANS, ELEVATIONS, AND DETAILS TO INDICATE PENETRATIONS, FLOORS, WALLS, AND CEILINGS AND THEIR OF FLOW
RELATIONSHIP TO OTHER PENETRATIONS AND INSTALLATIONS.
J. REFLECTED CEILING PLANS TO COORDINATE AND INTEGRATE INSTALLATION OF AIR OUTLETS, LIGHT FIXTURES, UP PITCH UP IN DIRECTION
COMMUNICATION SYSTEMS, COMPONENTS, SPRINKLERS, AND OTHER CEILING-MOUNTED ITEMS. OF FLOW
FTR OR RP EQUIPMENT TAG
K. ACCESS DOOR AND ACCESS PANEL LOCATIONS, WITH FIRE-RATINGS REQUIRED TO MAINTAIN FIRE RATING OF
CONSTRUCTION, IN LOCATIONS AS REQUIRED FOR PROPER ACCESS FOR MAINTENANCE ADJUSTMENT, REPAIR AND EQUIPMENT TYPE DESIGNATION SD S SMOKE DETECTOR
REMOVAL OF ALL EQUIPMENT AND DEVICES. D
XX
L. SCALE: MINIMUM 1/4"=1'-0" FOR FLOOR PLAN, 3/8"=1'-0" FOR MECHANICAL ROOMS. TS T S TEMPERATURE SENSOR
D
XX
ACTIVE LENGTH (FT) / WATER FLOW RATE
48. ALL PENETRATIONS FOR THE INSTALLATION OF THE MECHANICAL SYSTEMS SHALL BE CAULKED AND SEALED FOR SMOKE AND XX PIPING FLEX CONNECTION (DUCTWORK)
(GPM)
FIRE AS REQUIRED.
49. LOCATE ROOF MOUNTED HVAC EQUIPMENT MORE 10 FEET FROM ROOF EDGE. PROVIDE HANDRAILS IF EQUIPMENT ON THE TOTAL LENGTH (FT), PROVIDE ENCLOSURE ROOF MOUNTED EXHAUST FAN
OR
ROOF LOCATED LESS 10 FEET FROM ROOF EDGE (SEE ARCHITECTURAL DRAWINGS) FROM WALL TO WALL OR WALL TO
50. CONTROL CONTRACTOR TO PROVIDE ALL CONTROL DEVICES, EQUIPMENT, ACCESSORIES, OTHER APPARATUSES, CONTROL COLUMN ENCLOSURE, ENCLOSURE
VERIFY SCALE
VALVES AND DAMPERS, ACTUATORS, SENSORS, ETC. AND ALL CONTROL WIRING AND LOW VOLTAGE POWER WIRING RELATED SURFACE SHALL MATCH ACTIVE LENGTH
TO CENTRAL DDC CONTROL SYSTEM. SEE SPECIFICATION SECTION 230900. ENCLOSURE SURFACE. BAR IS ONE INCH ON
ORIGINAL DRAWING.
MI
0 1"
PRELI
PROJ 664626
DWG 100-G-013
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/GEN/Dlv/100-G-013_664626.dgn
FILENAME:100-G-013_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 9:42:48 AM
1 2 3 4 5 6
GHTS RESERVED.
ONE-LINE DIAGRAM-1 ONE-LINE DIAGRAM-2 CONTROL DIAGRAM-1 CONTROL DIAGRAM-2
DRAWOUT AIR CIRCUIT BREAKER, LOW VOLTAGE DRAWOUT POWER CIRCUIT BREAKER, MEDIUM VOLTAGE PUSH-BUTTON SWITCH, MOMENTARY CONTACT, CAPACITOR
NORMALLY OPEN
LL 2016. ALL RI
CIRCUIT BREAKER, THERMAL MAGNETIC TRIP SHOWN, NON DRAWOUT FUSED SWITCH, MEDIUM VOLTAGE PUSH-BUTTON SWITCH, MOMENTARY CONTACT, BATTERY
400
3 POLE, UNO NORMALLY CLOSED
CIRCUIT BREAKER, STATIC TRIP UNIT, SENSOR AMP DRAWOUT FUSED SWITCH AND CONTACTOR, MEDIUM PUSH BUTTON SWITCH, MAINTAINED CONTACTS WITH LIMIT SWITCH, NORMALLY OPEN, CLOSES AT END
c CH2M HI
AS AT
or TRIP AND FRAME RATINGS SHOWN, 3 POLE, UNO VOLTAGE MECHANICAL INTERLOCK OF TRAVEL
er
AF AF
APVD
Seal
A
DRAWOUT FUSED SWITCH AND VACUUM CONTACTOR, LIMIT SWITCH, NORMALLY CLOSED, OPENS AT END
MEDIUM VOLTAGE OF TRAVEL
CIRCUIT BREAKER, MAGNETIC TRIP ONLY, TRIP
100/M
BY
RATING SHOWN, 3 POLE, UNO DRAWOUT VACUUM CONTACTOR, MEDIUM VOLTAGE 3 POSITION SELECTOR SWITCH MAINTAINED CONTACT TEMPERATURE SWITCH, OPENS ON TEMPERATURE RISE
CIRCUIT BREAKER WITH CURRENT LIMITING FUSES, MEDIUM VOLTAGE CABLE STRESS CONE TYPE TEMPERATURE SWITCH, CLOSES ON TEMPERATURE RISE
400
400 TERMINATION, OPEN TERMINATOR OR ELBOW
APVD
TRIP AND FUSE RATING INDICATED, 3 POLE, UNO OFF SELECTOR SWITCH - MAINTAINED CONTACT - CHART
S THE PROPERTY OF
HAND REMOTE
IDENTIFIES OPERATION WHEN NEEDED FOR CLARITY:
LL.
FLOAT SWITCH, NORMALLY OPEN, CLOSES ON
ON OF CH2M HI
DESCENDING LEVEL
ew
FUSED SWITCH, SWITCH AND FUSE CURRENT RATING SWITCH - LOAD BREAK, GROUP OPERATED,
POSITION
QC Revi
400 225 MEDIUM VOLTAGE
INDICATED, 3 POLE, UNO
CKT HAND OFF REMOTE X - CLOSED CONTACT
SWITCH, CURRENT RATING INDICATED, 3 POLE, UNO 1 X O O O - OPEN CONTACT FLOAT SWITCH, NORMALLY OPEN, CLOSES ON
100 2 O O X RISING LEVEL
ZATI
CE,I
SWITCH W/ARCING HORNS, MEDIUM VOLTAGE
TTEN AUTHORI
ONAL SERVI
FUSE, CURRENT RATING AND QUANTITY INDICATED
ON
60 (3)
DISCONNECTING FUSE - SOLID MATERIAL, TOGGLE SWITCH, ON-OFF TYPE PRESSURE SWITCH, NORMALLY CLOSED, OPENS ON
SI
CHK
REVI
MEDIUM VOLTAGE RISING PRESSURE
1
ON OFF
THOUT THE W RI
NEMA SIZE INDICATED, FVNR UNO MEDIUM VOLTAGE RISING PRESSURE
SELECTOR SWITCH, ON-OFF TYPE
M .REI
FUSE - EXPULSION, HOOK STICK OPERATED, FLOW SWITCH, CLOSES ON INCREASED FLOW
SINGLE POLE, MEDIUM VOLTAGE
AFD ELECTRONIC STARTER/SPEED CONTROL
RVSS = REDUCED VOLTAGE SOFT STARTER
FLOW SWITCH, OPENS ON INCREASED FLOW
DR
RVAT = REDUCED VOLTAGE AUTO TRANSFORMER TYPE
N,AS AN I
MUSHROOM HEAD PUSHBUTTON SWITCH NGR NEUTRAL GROUND CURRENT LIMITING RESISTOR
B RVRT = REDUCED VOLTAGE REACTOR TYPE
R.W OOD
TERMINAL BLOCK LUG
NCORPORATED HEREI
INDICATES COLOR
CABLE OR BUS CONNECTION POINT DELTA CONNECTION
DATE
T
TACHOMETER GENERATOR
GEN
K KEY INTERLOCK WYE GROUNDED CONNECTION, SOLID GROUND A INDICATING LIGHT - LETTER INDICATES COLOR
DSGN
A - AMBER G - GREEN S - STROBE
NO.
B - BLUE R - RED
N W HOLE OR I
SURGE ARRESTER (GAP TYPE) WYE NEUTRAL GROUND RESISTOR OR IMPEDANCE GFS GROUND FAULT SENSOR
C - CLEAR W - WHITE
GNS I
R or Z CONNECTION
S NOT TO BE USED,I
CUT
86 RELAY OR DEVICE, FUNCTION NUMBER AS INDICATED M MOTOR STARTER CONTACTOR COIL
TY
NEW HAVEN,CONNECTI
3 AC MOTOR, SQUIRREL CAGE INDUCTION - SEALED CONTACT
LL AND I
G GENERATOR, KW/KVA RATING SHOWN TIME DELAY RELAY, X INDICATES NUMERICAL ORDER
(1) X
IN CIRCUIT
500/625 POTENTIOMETER
SV
CH2M HI
VS BUSHING CURRENT TRANSFORMER, MULTI-RATIO SOLENOID VALVE, X INDICATES NUMERICAL ORDER
800/1200:5 X
AND QUANTITY INDICATED IN CIRCUIT
THI
V ANALOG METER WITH SWITCH - SCALE RANGE SHOWN
(3)
0-600V V = VOLTAGE KW = KILOWATTS CONTACT - NORMALLY OPEN RESISTOR
CAL LEGEND 1
E N
OPENS WHEN ENERGIZED AND TIMED OUT
GROUND TRANSFER SWITCH - LOW VOLTAGE MULTICONDUCTOR SHIELDED CABLE
ON
15 KVA
TIME DELAY RELAY CONTACT, OPENS WHEN DUPLEX RECEPTACLE
480-120/240V
GENERAL
AND PHASE INDICATED TIMED OUT
ELECTRI
SHIELDED ISOLATION TRANSFORMER TRANSFER SWITCH - MEDIUM VOLTAGE RELAY, WITH MECHANICAL LATCH
U
E N TERMINAL BLOCK, REMOTE
480-120V
POTENTIAL TRANSFORMER, VOLTAGE RATING TERMINAL BLOCK, INTERNAL FULLWAVE DIODE BRIDGE (AC TO DC)
AND QUANTITY INDICATED
(3)
FUSED TERMINAL BLOCK
MI
SPD SURGE PROTECTIVE DEVICE THERMOCOUPLE 0 1"
PRELI
PROJ 664626
DWG 100-G-015
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/GEN/Dlv/100-G-015_664626.dgn
FILENAME:100-G-015_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 9:42:43 AM
1 2 3 4 5 6
GHTS RESERVED.
POWER SYSTEM PLAN-1 POWER SYSTEM PLAN-2 FIRE ALARM SYSTEM PLAN AND RISER SOUND SYSTEM PLAN AND RISER
100/40
CONNECTION POINT TO EQUIPMENT SPECIFIED. BREAKER, SEPARATELY MOUNTED, CURRENT F FIRE ALARM STATION, MANUAL S SPEAKER, CONE TYPE, RECESSED IN CEILING, SEE
P
RACEWAY, CONDUCTOR,TERMINATION AND CONNECTION RATING INDICATED ARCHITECTURAL DRAWINGS FOR CEILING TYPE
LL 2016. ALL RI
IN THIS DIVISION. (100/40, 100 = FRAME SIZE; 40 = TRIP RATING)
3 POLE FIRE ALARM SYSTEM, AUTOMATIC SMOKE DETECTOR
MCC-A
MAJOR ELECTRICAL COMPONENT OR DEVICE - NAME S SPEAKER, CONE TYPE, WALL MOUNTED
OR IDENTIFYING SYMBOL AS SHOWN. 2
C CONTACTOR, MAGNETIC, NEMA SIZE INDICATED HD FIRE ALARM SYSTEM, AUTOMATIC, HEAT DETECTOR
c CH2M HI
S SPEAKER, CONE TYPE, SURFACE MOUNTED
er
APVD
30
Seal
A
PANELBOARD - SURFACE MOUNTED L LIGHTING CONTACTOR, CURRENT RATING INDICATED F FIRE ALARM BELL
LPXXA V VOLUME CONTROL, WALL MOUNT 5'-0" AFF
2
BY
PANELBOARD LETTER OR NUMBER STARTER, MAGNETIC NEMA SIZE INDICATED F FIRE ALARM HORN
FACILITY NUMBER S INTERIOR PAGING TRUMPET SOUND REPRODUCER
XX
WITH REMOTE AMPLIFIER, SURFACE MOUNTED
LP - LOW VOLTAGE PANEL CONVENIENCE RECEPTACLE - DUPLEX UNLESS NOTED FIRE ALARM HORN/STROBE LIGHT
DP - DISTRIBUTION PANEL 2 OTHERWISE
APVD
S THE PROPERTY OF
WP - WEATHERPROOF C - CLOCK HANGER
LL.
FIRE ALARM STROBE LIGHT M MICROPHONE OUTLET
TL- TWIST LOCK CRE - CORROSION RESISTANT
ON OF CH2M HI
ew
PANELBOARD - FLUSH MOUNTED GFCI- GROUND FAULT CIRCUIT INTERRUPTER
QC Revi
SUBSCRIPT NUMBER AT RECEPTACLE INDICATES CIRCUIT AIR DUCT DETECTOR S SOUND SYSTEM RACEWAY
ZATI
CE,I
240V RECEPTACLE FS FIRE SPRINKLER FLOW SWITCH S COMMUNICATION STATION
TTEN AUTHORI
ONAL SERVI
M MOTOR, SQUIRREL CAGE INDUCTION
ON
CONVENIENCE RECEPTACLE - QUADRUPLEX TS FIRE SPRINKLER TAMPER SWITCH SECURITY SYSTEM PLAN AND RISER
SI
CHK
REVI
THOUT THE W RI
M .REI
LPXXA HOME RUN - DESTINATION SHOWN DUPLEX CONVENIENCE RECEPTACLE - FLUSH IN FLOOR TELEPHONE SYSTEM PLAN AND RISER CS CONTROL STATION
DS
or EXPOSED CONDUIT AND CONDUCTORS* CONVENIENCE RECEPTACLE, PEDESTAL, DUPLEX TTC TELEPHONE TERMINAL CABINET DOOR SWITCH
DR
EP
N,AS AN I
or CONCEALED CONDUIT AND CONDUCTORS* L20R TELEPHONE RECEPTACLE FLOOR BOX EGRESS PUSHBUTTON
B G
20
R.W OOD
NOTE: RECEPTACLE, SPECIAL PURPOSE-NEMA CONFIGURATION
ALL UNMARKED CONDUIT RUNS CONSIST OF TWO NO. 12, ONE NO. 12 GROUND AND AMPERAGE INDICATED
TELEPHONE RECEPTACLE ELECTRONIC LOCK
NCORPORATED HEREI
CONDUCTORS IN 3/4" CONDUIT. RUNS MARKED WITH CROSSHATCHES INDICATE M = MAGENITIC
T THERMOSTAT
DATE
NUMBER OF NO. 12 CONDUCTORS. CROSSHATCH WITH SUBSCRIPT "G" INDICATES S = STRIKE
GREEN GROUND WIRE. T TELEPHONE SYSTEM RACEWAY
DSGN
NO.
CROSSHATCHES WITH BAR INDICATE NO.10 CONDUCTOR.
G
SIZE CONDUIT ACCORDING TO SPECIFICATIONS COMPUTER SYSTEM (DATA) PLAN AND RISER
N W HOLE OR I
MONITOR
GNS I
AND APPLICABLE CODE.
ELECTRIC UNIT HEATER CTC COMPUTER SYSTEM TERMINAL CABINET
S NOT TO BE USED,I
CUT
ELECTRIC AIR CONDITIONER VIDEO CAMERA
AC (SELF CONTAINED UNIT) PTZ = PAN/TILT/ZOOM
TY
NEW HAVEN,CONNECTI
CONDUIT DOWN COMPUTER NETWORK CONNECTION, FLUSH IN FLOOR
LL AND I
GROUND SYSTEM PLAN
CONDUIT, STUBBED AND CAPPED 1 or 1 LUMINAIRE, SEE SCHEDULE
COMBINED TELEPHONE/COMPUTER SYSTEM
CH2M HI
GROUND ROD
PLAN AND RISER
THI
CONDUIT TERMINATION AT CABLE TRAY 1 LUMINAIRE, SEE SCHEDULE
CAL LEGEND 2
(CCTV) AND DUPLEX CONVENIENCE RECEPTACLE IN TWO
FO FIBER OPTIC CONDUIT 1 FLOOD LIGHTS - AIM IN THE DIRECTION SHOWN
GANG BOX WITH BARRIER, 12" DOWN FROM CEILING
XXXX CONCRETE ENCASED DUCT BANK WHERE XXXX IS THE STANDBY LIGHTING UNIT, SURFACE MOUNTED, COMBINATION TELEVISION CABLE RECEPTACLE (TV)
ON
DUCT BANK NAME. SEE CIRCUIT AND RACEWAY SEE SCHEDULE AND DUPLEX CONVENIENCE RECEPTACLE IN TWO GANG
GENERAL
CONCEALED CONDUIT ROUTING AREA XX or EXIT LIGHTS - FILLED SECTION INDICATES LIGHTED FACE, CLOSED CIRCUIT TELEVISION RECEPTACLE, FLOOR BOX
ARROW INDICATES EGRESS DIRECTIONAL INDICATORS,
XX = FIXTURE NUMBER, SEE SCHEDULE
ELECTRI
CONDUIT ROUTING AREA TELEVISION CABLE RECEPTACLE, FLOOR BOX
a or SMALL LETTER SUBSCRIPT AT SWITCH AND LUMINAIRE
2a INDICATES SWITCHING. SUBSCRIPT NUMBER
CABLE TRAY
AT LUMINAIRE INDICATES CIRCUIT
MI
60/40 FUSED DISCONNECT SWITCH, CURRENT RATING INDICATED 0 1"
PRELI
3 POLE MD MOTION DETECTOR
PROJ 664626
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/GEN/Dlv/100-G-016_664626.dgn
FILENAME:100-G-016_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 9:42:38 AM
1 2 3 4 5 6
GHTS RESERVED.
ONE LINE PROTECTION RELAYING AND ONE LINE PROTECTION RELAYING AND GENERAL CIRCUIT CONDUCTOR AND CONDUIT IDENTIFICATION
ELEMENTARY DIAGRAMS-1 ELEMENTARY DIAGRAMS-2
52
LL 2016. ALL RI
51 or DEVICE FUNCTION NUMBER INDICATED,
SEE DEVICE TABLE POWER CIRCUIT CALLOUTS MULTICONDUCTOR POWER CABLE CIRCUIT CALLOUTS
DEVICE
FUNCTION DEVICE DESCRIPTION
[P1] [1/2"FLEX, 2#12,#12G] [P24] [1"C,3#8,3#14,1#10G] [PC1] [3/4"C,1 (3C#12,1#12G) TYPE 2]
NO.
CS [P2] [3/4"C,2#12,1#12G] [P25] [1"C,3#8,4#14,1#10G] [PC2] [3/4"C,1 (3C#10,1#10G) TYPE 2]
CONTROL SWITCH TRIP
c CH2M HI
T 21 IMPEDANCE/DISTANCE RELAY [P3] [3/4"C,3#12,1#12G] [P26] [1"C,3#8,5#14,1#10G] [PC3] [1"C,1 (3C#8,1#10G) TYPE 2]
er
APVD
Seal
A CS 25A AUTOMATIC SYNCHRONIZER [P4] [3/4"C,4#12,1#12G] [P27] [1"C,2#6, 1#10G] [PC4] [1 1/4"C,2 (3C#12,1#12G) TYPE 2]
CONTROL SWITCH CLOSE
C
25C SYNCH CHECK RELAY [P5] [3/4"C,5#12,1#12G] [P28] [1"C,3#6, 1#8G] [PC5] [1 1/2"C,2 (3C#10,1#10G) TYPE 2]
BY
43/CS 43-DEVICE FUNCTION NUMBER, [P6] [3/4"C,6#12,1#12G] [P29] [1"C,3#6, 2#14,1#8G] [PC1A] [3/4"C,1 (2C#12,1#12G) TYPE 2]
27 UNDERVOLTAGE RELAY
SEE DEVICE TABLE [P7] [3/4"C,7#12,1#12G] [P30] [1"C,3#6, 3#14,1#8G] [PC2A] [3/4"C,1 (2C#10,1#10G) TYPE 2]
32 REVERSE POWER RELAY
[P8] [3/4"C,8#12,1#12G] [P31] [1"C,3#6, 4#14,1#8G]
VS VOLTMETER SWITCH
40 GENERATOR LOSS OF EXCITATION RELAY [P9] [3/4"C,3#12,2#14,1#12G] [P32] [1"C,3#6, 5#14,1#8G]
APVD
S THE PROPERTY OF
[P10] [3/4"C,3#12,3#14,1#12G] [P33] [1"C,3#4,1#8G]
LL.
AS AMMETER SWITCH 43CSE AUTOMATIC POWER TRANSFER AND LOAD
ON OF CH2M HI
CONTROL MODE SEL. SWITCH [P11] [3/4"C,3#12,4#14,1#12G] [P34] [1 1/4"C,3#4,3#14,1#8G]
ew
QC Revi
[P12] [3/4"C,3#12,5#14,1#12G] [P35] [1 1/4"C,3#4,5#14,1#8G] EMPTY CONDUIT
A INDICATING LAMP-SWITCHBOARD TYPE 43CSX MODE SEL. SWITCH
[P13] [3/4"C,3#12,6#14,1#12G] [P36] [1 1/4"C,3#3, 1#6G]
INDICATING LAMP LENS COLORS [EC-1] [3/4"C,WITH PULL STRING]
46 GENERATOR CURRENT UNBALANCE RELAY [P14] [3/4"C,3#12,7#14,1#12G] [P37] [1 1/4"C,3#3, 3#14,1#6G]
INDICATED AS FOLLOWS:
ZATI
CE,I
[EC-2] [1"C,WITH PULL STRING]
49 THERMAL RELAY [P15] [3/4"C,2#10,1#10G] [P38] [1 1/4"C,3#2, 1#6G]
TTEN AUTHORI
ONAL SERVI
A - AMBER R - RED [EC-3] [1 1/4"C,WITH PULL STRING]
ON
B - BLUE W - WHITE 50GS INSTANTANEOUS OVERCURRENT DEVICE, [P16] [3/4"C,3#10,1#10G] [P39] [1 1/4"C,3#1, 1#6G]
SI
[EC-4] [1 1/2"C,WITH PULL STRING]
CHK
G - GREEN GROUND SENSOR [P17] [3/4"C,3#10,2#14,1#10G] [P40] [1 1/2"C,3#1, 3#14,1#6G]
REVI
[EC-5] [2"C,WITH PULL STRING]
[P18] [3/4"C,3#10,3#14,1#10G] [P41] [1 1/2"C,3#2/0, 1#4G]
THOUT THE W RI
[P19] [3/4"C,3#10,4#14,1#10G] [P42] [2"C,3#3/0, 1#4G]
[EC-7] [4"C,WITH PULL STRING]
51 TIME OVERCURRENT RELAY [P20] [3/4"C,3#10,5#14,1#10G] [P43] [2"C,3#4/0, 1#3G]
M .REI
A AMMETER [EC-8] [5"C,WITH PULL STRING]
51G TIME OVERCURRENT RELAY, GROUND FAULT [P21] [1"C,2#8,1#10G]
[P22] [1"C,3#8,1#10G]
W WATTMETER 51V TIME OVERCURRENT, VOLTAGE RESTRAINED
DR
N,AS AN I
F FREQUENCY METER 52CSX POWER CIRCUIT BREAKER CONTROL SWITCH ANALOG CIRCUIT CALLOUTS CONTROL CIRCUIT CALLOUTS MULTICONDUCTOR CONTROL CABLE CIRCUIT CALLOUTS
B
R.W OOD
59 OVERVOLTAGE RELAY [A1] [3/4"C,1 TYPE 3] [C1] [3/4"C,MSC] [CC5] [3/4"C,1-5C TYPE 1]
PF POWER FACTOR METER
NCORPORATED HEREI
60 VOLTAGE OR CURRENT BALANCE RELAY [A2] [1"C,2 TYPE 3] [C2] [3/4"C,2#14,1#14G] [CC7] [3/4"C,1-7C TYPE 1]
DATE
[A3] [1"C,3 TYPE 3] [C3] [3/4"C,3#14,1#14G] [CC9] [1"C,1-9C TYPE 1]
WH WATT-HOUR METER 65A ENGINE GOVERNOR, SPEED CONTROL
[A4] [1"C,4 TYPE 3] [C4] [3/4"C,4#14,1#14G] [CC12] [1"C,1-12C TYPE 1]
65A, MOP ENGINE GOVERNOR, SPEED CONTROL
[A5] [1 1/4"C,5 TYPE 3] [C5] [3/4"C,5#14,1#14G] [CC19] [1 1/2"C, 1-19C TYPE 1]
DSGN
MOTOR OPERATED POTENTIOMETER
NO.
ETM ELAPSED TIME METER
[A6] [1 1/4"C,6 TYPE 3] [C6] [3/4"C,6#14,1#14G] [CC25] [1 1/2"C,1-25C TYPE 1]
N W HOLE OR I
[A7] [1 1/2"C,7 TYPE 3] [CC37] [2"C,1-37C TYPE 1]
GNS I
65A, RL ENGINE GOVERNOR, SPEED CONTROL [C7] [3/4"C,7#14,1#14G]
RPM TACHOMETER RAISE/LOWER SWITCH [A8] [1 1/2"C,8 TYPE 3] [C8] [3/4"C,8#14,1#14G] [CCC1] [1-7C #12 TYPE 1]
S NOT TO BE USED,I
XD [A10] [2"C,10 TYPE 3] [C10] [3/4"C,10#14,1#14G]
CUT
65B, MOP ENGINE GOVERNOR, LOAD CONTROL
[A11] [2"C,11 TYPE 3] [C11] [3/4"C,11#14,1#14G]
PF MOTOR OPERATED POTENTIOMETER
TY
NEW HAVEN,CONNECTI
POWER FACTOR TRANSDUCER [A12] [2"C,12 TYPE 3]
CONTROL AUTHORI
65B, RL ENGINE GOVERNOR, % LOAD [A13] [2"C,13 TYPE 3] [C13] [3/4"C,13#14,1#14G]
TD TIME DELAY RAISE/LOWER SWITCH [A14] [2"C,14 TYPE 3] [C14] [3/4"C,14#14,1#14G]
LL AND I
[A15] [3/4"C,1 TYPE 4] [C15] [3/4"C,15#14,1#14G]
4 RELAY COIL, DEVICE FUNCTION NUMBER PER 65E AUTOMATIC POWER TRANSFER AND LOAD
[A16] [3/4"C,2 TYPE 4] [C16] [3/4"C,16#14,1#14G]
ANSI 37.2 - AMERICAN STANDARD MANUAL AND CONTROL, WOODWARD APTL
CH2M HI
[A17] [1"C,3 TYPE 4] [C17] [3/4"C,17#14,1#14G]
AUTOMATIC STATION CONTROL, SUPERVISORY
THI
AND ASSOCIATED TELEMETRY EQUIPMENT 65F AUTOMATIC GENERATOR LOADING [A18] [1 1/4"C,4 TYPE 4] [C18] [3/4"C,18#14,1#14G]
CONTROL, WOODWARD AGLC [A19] [1 1/4"C,5 TYPE 4] [C19] [3/4"C,19#14,1#14G]
90 VOLTAGE REGULATOR
TEST SWITCH CURRENT ELEMENT
CAL LEGEND 3
NOTES:
90, MOP ENGINE EXCITATION, POWER
1. FOR CABLE TYPES, SEE SPECIFICATIONS.
OPERATED POTENTIOMETER
TEST SWITCH POTENTIAL ELEMENT
2. CONDUIT SIZES ARE BASE ON THE AREA OF THW CONDUCTORS.
ON
90PF ENGINE EXCITATION, POWER
NEUTRAL CONNECTION FACTOR CONTROL 3. SIZING OF CONDUCTORS #1AWG AND SMALLER BASED ON AMPACITIES
GENERAL
90RL ENGINE EXCITATION, RAISE/ ON AMPACITIES AT 75 DEGREES C.
DIODE
LOWER SWITCH
4. WHERE CIRCUITS ARE UNDERGROUND, DIRECT BURIED OR CONCRETE
ENCASED, MINIMUM CONDUIT SIZE SHALL BE 1".
ELECTRI
INSTRUMENTATION CABLE, SHIELDED
X = DEVICE NUMBER, WHEN THERE ARE MULTIPLE UNITS 5. FOR METRIC CONDUIT SIZES USE THE FOLLOWING CONVERSION:
1/2" = 16 mm 1/4" = 35 mm
3/4" = 21 mm 1 1/2" = 41 mm
NGR NEUTRAL GROUNDING RESISTOR
1" = 27 mm 2" = 53 mm
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 100-G-017
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/GEN/Dlv/100-G-017_664626.dgn
FILENAME:100-G-017_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 9:42:51 AM
1 2 3 4 5 6
GHTS RESERVED.
LL 2016. ALL RI
FOUL AIR DUCTWORK HEADER OUTLET
c CH2M HI
APVD
A
5 5
BY
HVAC UNIT
ODOR CONTROL PREFILTER
APVD
S THE PROPERTY OF
LL.
ON OF CH2M HI
ZATI
CE,I
TTEN AUTHORI
ONAL SERVI
SION
CHK
REVI
F.F. 10.95
THOUT THE W RI
N PART,FOR ANY OTHER PROJECT W I
7
DR
N,AS AN I
B
EBERS
NCORPORATED HEREI
RG SI
DATE
DSGN
NO.
HORIZONTAL (CROSS FLOW)
N W HOLE OR I
ODOR CONTROL SCRUBBER F.F. 12.95
GNS I
9
S NOT TO BE USED,I
CUT
TY
NEW HAVEN,CONNECTI
LL AND I
ODOR CONTROL
CH2M HI
ENCLOSURE FAN
THI
REUSE OF DOCUM ENTS:
C
EMERGENCY
GENERATOR
ON
13
ON PUM P STATI
ON
TE PLAN
VI
CI L
SI
UNI
NOTES:
D
15
1. BASE FLOOD ELEV. = 11.0
1"=10'
2. ALL ELEVATIONS SHOWN ARE NAVD 88 VERIFY SCALE
MI
0 1"
3. DESIGN RESILIENCY PROTECTION ELEV. = 14.0 UNION PUMP STATION SITE PLAN
N
PRELI
1"=10'-0" PROJ 664626
DWG 100-C-201
SHEET of
$PWURL
1
100-A-302
2
UP
STAIR
FRP DOOR
CMU WALL
1 HOUR FIRE BARRIER
1/4"=1'-0"
3
100-A-301
100-A-301
N
4
PUMP ROOM
5
SYSTEM
B
SPRINKLER
100-A-302
pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/AR/Dlv/100-A-201_664626.dgn FILENAME:100-A-201_664626.dgn
6
PLOT DATE:11/4/2016
DWG
DATE
PROJ
SHEET
0
ARCHI
TECTURAL GNHW PCA LONG TERM CONTROL PLAN
CONTROL AUTHORI
TY NO. DATE REVI
SION BY APVD
ORIGINAL DRAWING.
of
35 M GD CAPACI
TY
664626
NOVEMBER 2016
RG SI
EBERS DL M I
CHALEK
100-A-201
GHTS RESERVED.
CONC WALL TO
LL 2016. ALL RI
MATCH EXISTING
c CH2M HI
APVD
16'x8' ROLL-UP DOOR GENERATOR AND
A
DIESEL FUEL
(SEE SITE PLAN)
BY
A
APVD
100-A-301
S THE PROPERTY OF
LL.
EYEWASH
ON OF CH2M HI
ZATI
CE,I
TTEN AUTHORI
ONAL SERVI
ON
TYPE 316
SI
CHK
STAINLESS
REVI
STEEL HATCH
SCREEN ROOM ABOVE
THOUT THE W RI
DL M I
FRP GRATING,
DR
N,AS AN I
B
EBERS
NCORPORATED HEREI
RG SI
DATE
DSGN
NO.
N W HOLE OR I
DEAS AND DESIGNS I
ON
GNHW PCA LONG TERM CONTROL PLAN
S NOT TO BE USED,I
CUT
FRP DOOR, TYP
TY
NEW HAVEN,CONNECTI
LL AND I
CH2M HI
THI
CONTROL ROOM
1 HOUR FIRE
TY
ON PUM P STATI
BARRIER CMU
35 M GD CAPACI
ON
WALL
TECTURAL
UNI
RESTROOM
100-A-301
1/4"=1'-0"
VERIFY SCALE
MI
0 1"
1/4"=1'-0"
DATE NOVEMBER 2016
PRELI
PROJ 664626
DWG 100-A-202
SHEET of
GHTS RESERVED.
LL 2016. ALL RI
c CH2M HI
APVD
A
BY
TYPE 316 SST HATCH
APVD
S THE PROPERTY OF
TRAFFIC COATING, TYP
LL.
ON OF CH2M HI
ZATI
CE,I
SST FLASHING, TYP
TTEN AUTHORI
ONAL SERVI
SION
CHK
REVI
THOUT THE W RI
INSUL (R-19), TYP
4" FACE BRICK, TYP
DL M I
MOTOR SCREEN
CONTROL ROOM
ROOM ROOM
FRP DOOR, TYP
N,AS AN I
B CMU WALL, TYP
EBERS
NCORPORATED HEREI
RG SI
DATE
DSGN
NO.
N W HOLE OR I
DEAS AND DESIGNS I
ON
GNHW PCA LONG TERM CONTROL PLAN
S NOT TO BE USED,I
CUT
TY
NEW HAVEN,CONNECTI
LL AND I
PUMP
CH2M HI
ROOM
THI
REUSE OF DOCUM ENTS:
C
ON
TY
ON PUM P STATI
35 M GD CAPACI
ON
TECTURAL
UNI
SECTION
A 1/4"=1'-0"
100-A-201
100-A-202
1/4"=1'-0"
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 100-A-301
SHEET of
GHTS RESERVED.
LL 2016. ALL RI
c CH2M HI
APVD
A
BY
APVD
S THE PROPERTY OF
LL.
ON OF CH2M HI
SEAL ROAD
JOINTS, TYP
ZATI
CE,I
TTEN AUTHORI
ONAL SERVI
ON
SST FLASHING, TYP
SI
CHK
REVI
THOUT THE W RI
5" SPRAY-ON
4" FACE BRICK, TYP
INSUL (R-19),
TYP
DL M I
MOTOR
ROOM
N,AS AN I
B
EBERS
NCORPORATED HEREI
RG SI
DATE
DSGN
NO.
N W HOLE OR I
DEAS AND DESIGNS I
ON
GNHW PCA LONG TERM CONTROL PLAN
S NOT TO BE USED,I
CUT
TY
NEW HAVEN,CONNECTI
LL AND I
PUMP ROOM
1 HOUR FIRE
BARRIER CMU
CH2M HI
WALL
THI
STAIR
ON
TY
ON PUM P STATI
35 M GD CAPACI
ON
TECTURAL
UNI
SECTION
B 1/4"=1'-0"
100-A-201
100-A-202
1/4"=1'-0"
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 100-A-302
SHEET of
GHTS RESERVED.
B
100-D-301
LL 2016. ALL RI
c CH2M HI
APVD
A
BY
APVD
S THE PROPERTY OF
LL.
ON OF CH2M HI
CHANNEL
GRINDER
TYP 2
ZATI
CE,I
42"X42"
TTEN AUTHORI
ONAL SERVI
ON
SLUICE GATE 42"X42"
SI
CHK
SLUICE GATE
REVI
THOUT THE W RI
KL DI
N,AS AN I
B
S CLARK
NCORPORATED HEREI
36"X36" 36"X36"
SLUICE GATE SLUICE GATE
DATE
30"X48"
SLUICE GATE
DSGN
NO.
N W HOLE OR I
DEAS AND DESIGNS I
ON
GNHW PCA LONG TERM CONTROL PLAN
S NOT TO BE USED,I
CUT
TY
NEW HAVEN,CONNECTI
LL AND I
20"X16" RDCR 24"X16" RDCR 24"X16" RDCR 16"X12" RDCR
20"X12" RDCR
CH2M HI
THI
REUSE OF DOCUM ENTS:
C
8"
8"
TYP)
11 1/
TYP)
6 7/
A PUMP 5 PUMP 4 PUMP 3 PUMP 2 PUMP 1
-
3'
(
100-D-301
-
(
2'
ON
TY
ON PUM P STATI
35 M GD CAPACI
CAL
ON
LOW ER PLAN
PROCESS M ECHANI
VERIFY SCALE
LOWER PLAN
N
MI
1/4"=1'-0" 0 1"
PRELI
PROJ 664626
DWG 100-D-201
SHEET of
GHTS RESERVED.
B
100-D-301
LL 2016. ALL RI
c CH2M HI
APVD
A
BY
APVD
S THE PROPERTY OF
LL.
ON OF CH2M HI
CHANNEL
GRINDER
TYP 2
ZATI
CE,I
42"X42"
TTEN AUTHORI
ONAL SERVI
ON
SLUICE GATE 42"X42"
SI
CHK
SLUICE GATE
REVI
THOUT THE W RI
KL DI
N,AS AN I
B
S CLARK
NCORPORATED HEREI
36"X36" 36"X36"
SLUICE GATE SLUICE GATE
DATE
DSGN
NO.
N W HOLE OR I
DEAS AND DESIGNS I
ON
GNHW PCA LONG TERM CONTROL PLAN
S NOT TO BE USED,I
CUT
24" SS" SS
24"x16" WYE 24"x16" WYE 24"x12" WYE 24"x16" WYE 24"x12" WYE 24" BLIND FLANGE
TY
NEW HAVEN,CONNECTI
LL AND I
12" FCA
CH2M HI
16" FCA 16" FCA
12" CV
THI
REUSE OF DOCUM ENTS:
12" FCA
100-D-301
ON
TY
ON PUM P STATI
35 M GD CAPACI
CAL
ON
UPPER PLAN
PROCESS M ECHANI
VERIFY SCALE
UPPER PLAN
N
MI
1/4"=1'-0" 0 1"
PRELI
PROJ 664626
DWG 100-D-202
SHEET of
GHTS RESERVED.
LL 2016. ALL RI
c CH2M HI
APVD
A
BY
APVD
S THE PROPERTY OF
LL.
4"
ON OF CH2M HI
8"
5 1/
-3/
EXISTING BEAM
-
2'
3'
EL 19.45
ZATI
CE,I
EL 17.85
TTEN AUTHORI
ONAL SERVI
SION
CHK
EL 16.35
REVI
THOUT THE W RI
KL DI
EL 10.95
N,AS AN I
B
S CLARK
NCORPORATED HEREI
DATE
DSGN
NO.
16" GV 16" GV 16" GV
N W HOLE OR I
GNS I
(TYP) (TYP) (TYP)
S NOT TO BE USED,I
TO BE REPLACED
CUT
IN KIND
16" FLOW 16" FLOW 16" FLOW
TY
NEW HAVEN,CONNECTI
12" FLOW
LL AND I
CH2M HI
THI
PUMP 4 PUMP 3 PUMP 2 PUMP 1
PUMP 5
ON
TY
ON PUM P STATI
35 M GD CAPACI
CAL
ON
PROCESS M ECHANI
100-D-201, 100-D-202
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 100-D-301
SHEET of
$PWURL
1
2
PUMP 4
16" FCA
4'
-0" 4'
-0"
24"X16" RDCR
3
(
TYP) (
TYP)
16" GV
METER
16" FLOW
B
100-D-201, 100-D-202
1/4"=1'-0"
SECTION
4
42"X42"
SLUICE GATE
5
pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/100&space;-&space;Union&space;PS/PR/Dlv/100-M-302_664626.dgn FILENAME:100-M-302_664626.dgn
6
PLOT DATE:11/4/2016
DWG
DATE
PROJ
SHEET
0
PROCESS M ECHANI
CAL GNHW PCA LONG TERM CONTROL PLAN
UNI
ON PUM P STATION GREATER NEW HAVEN W ATER POLLUTI
ON
VERIFY SCALE
CONTROL AUTHORI
TY NO. DATE REVI
SION BY APVD
ORIGINAL DRAWING.
of
35 M GD CAPACI
TY
1"
SECTION
664626
NOVEMBER 2016
100-D-302
S CLARK KL DI
AZ
REUSE OF DOCUM ENTS: THI
S DOCUM ENT,AND THE IDEAS AND DESIGNS I
NCORPORATED HEREI N,AS AN I
NSTRUM ENT OF PROFESSIONAL SERVI
CE,IS THE PROPERTY OF c CH2M HI
LL 2016. ALL RI
GHTS RESERVED.
PRELI
MINARY – NOT FOR CONSTRUCTI
ON CH2M HI
LL AND I
S NOT TO BE USED,I
N W HOLE OR I
N PART,FOR ANY OTHER PROJECT W I
THOUT THE W RI
TTEN AUTHORIZATI
ON OF CH2M HI
LL.
1 2 3 4 5 6
GHTS RESERVED.
13.8 KV SERVICE FROM
UNITED ILLUMINATING COMPANY (UI)
LL 2016. ALL RI
1000 KVA
480V, 3Ø, 3W
G UNITED ILLUMINATING COMPANY SCOPE
(LOCATED 1000 KVA
c CH2M HI
OUTDOORS) 13.8 KV - 480V
3-PHASE
APVD
A
BY
E N ATS-1
1200A
CH2M / GNHWPCA SCOPE
APVD
S THE PROPERTY OF
LL.
1200 AF
ON OF CH2M HI
1000 AT
ZATI
CE,I
MCC-1, 480V, 3Ø, 60HZ, 1200A, 65 KAIC
TTEN AUTHORI
ONAL SERVI
SION
CHK
REVI
90 400 90 400 400 30 15 15 175 80 15
THOUT THE W RI
DPM
25 KVA
1 1 1 1 1 1 1
M .REI
480V - 208/120V
3-PHASE
SPD
N,AS AN I
B SUMP PUMP
R.W OOD
AFD AFD AFD AFD AFD
CONTROLLER
NCORPORATED HEREI
DATE
50 250 50 250 250 10 10 1 LP-1 1 1 1 3 1 1 100 KVA 50 KVA 1/4 1/4
DSGN
ODOR CONTROL
NO.
SUM P PUM P 1
SUM P PUM P 2
ST
N W HOLE OR I
VE
GATE VALVE
TYP OF 10)
M ATE)
M ATE)
HOI
DE GATE
STANDBY)
GNS I
NDER 1
NDER 2
NDER 1
NDER 1
NDER 2
NDER 2
PROTECTI
TYP OF 8)
NG
CHANNEL
CHANNEL
CHANNEL
CHANNEL
CHANNEL
CHANNEL
NG
M ETERI
CRANE/
DRUM 1
DRUM 2
DRUM 1
DRUM 2
PUM P 1
PUM P 2
PUM P 3
PUM P 4
PUM P 5
POW ER
CE
GHTI
ON
ESTI
ESTI
DEVI
HVAC
GRI
GRI
GRI
GRI
GRI
LP-
SLI
LI
S NOT TO BE USED,I
(
CUT
TY
NEW HAVEN,CONNECTI
LL AND I
NTS
CH2M HI
THI
REUSE OF DOCUM ENTS:
C
6"
15A GATE
UNUSABLE UNUSABLE UNUSABLE VALVE 1
SPACE SPACE SPACE 15A SLIDE
AGRAM AND
GATE 1
DIGITAL 400A 400A
15A GATE 15A GATE 15A GATE
ON
POWER PUMP 4 PUMP 5
VALVE 2 VALVE 5 VALVE 8
METERING FEEDER FEEDER
ON PUM P STATI
15A SLIDE 15A SLIDE 15A SLIDE
ON
GATE 2 GATE 4 GATE 6
ON
LP-1
M CC ELEVATI
15A GATE 15A GATE 15A GATE
208/120V
VALVE 3 VALVE 6 VALVE 9
CAL
1200AF/ 90A PUMP 1 15A SUMP 15A CRANE 15A SLIDE
SPARE
NE DI
72"
ELECTRI
1000AT
MAIN 90A PUMP 3 15A GATE
480V SIZE 1 SIZE 1
FEEDER VALVE 10
400A CHANNEL CHANNEL
400A SPARE 90A 15A SLIDE
PUMP 2 GRINDER 2 GRINDER 1
NGLE LI
FEEDER FEEDER GATE 8
FEEDER
SIZE 1 SIZE 1
SPARE HVAC FEED
CHANNEL CHANNEL
UNI
SIZE 1 25kVA
GRINDER 2 GRINDER 1
STARTER HVAC FEED 480-208/120V
DRUM 1 DRUM 2
XFMR
15A GATE 15A GATE
SI
SIZE 1 SIZE 1
HVAC FEED
VALVE 4 CHANNEL CHANNEL VALVE 7
SPD
15A SLIDE GRINDER 1 GRINDER 2 15A SLIDE ODOR
GATE 3 DRUM 1 DRUM 2 GATE 5 CONTROL
D
12"
VERIFY SCALE
20" 20" 20" 20" 20" 20" 20" 20" BAR IS ONE INCH ON
ORIGINAL DRAWING.
MI
0 1"
PRELI
MCC ELEVATION PROJ 664626
NTS
DWG 100-E-201
SHEET of
SHEET KEYNOTES
GHTS RESERVED.
1. PLACE FLOOR MOUNTED AFD'S AND ELECTRICAL
EQUIPMENT ON 1'-1" HIGH CONCRETE EQUIPMENT
PAD.
LL 2016. ALL RI
2. AFD SHALL FIT WITHIN THE AVAILABLE SPACE
SHOWN AND BE NO TALLER THAN 94-INCHES.
c CH2M HI
SHALL NOT BE MOUNTED MORE THAN 7'-6" ABOVE
APVD
THE FLOOR.
A
BY
1000 KVA GENERATOR
5. APPROXIMATE LOCATION OF EXISTING MAIN
WITH 3,000 GALLON
POWER TRANSFORMER. LOCATION OF NEW
SUB-BASE DIESEL
TRANSFORMER TO BE COORDINATED WITH UNITED
FUEL TANK
APVD
ILLUMINATING (UI).
S THE PROPERTY OF
6
LL.
6. 1000 KVA, 1200 KW GENERATOR IN
ON OF CH2M HI
WEATHERPROOF ENCLOSURE WITH 3,000 GALLON
SUB-BASE DIESEL FUEL TANK TO BE MOUNTED
OUTDOORS ON PAD WITH TOP OF PAD ELEVATION
TO BE 14.00 FEET. ACCESS PLATFORMS AND
STAIRS TO BE PROVIDED AS NEEDED.
ZATI
CE,I
TTEN AUTHORI
7. GRATING TO BE GROUNDED AND FLUSH WITH
ONAL SERVI
ON
FLOOR.
SI
CHK
REVI
8. NOT USED.
THOUT THE W RI
10. WALL-MOUNTED, BOTTOM OF AFD 36" ABOVE
M .REI
FINISHED FLOOR.
DR
N,AS AN I
TYP OF 2
B
R.W OOD
10
NCORPORATED HEREI
DATE
DSGN
NO.
N W HOLE OR I
GNS I
10
S NOT TO BE USED,I
CUT
TY
NEW HAVEN,CONNECTI
LL AND I
CH2M HI
5
THI
AFD-5 AFD-4 AFD-2 PLC
4 10 AFD-3
MCC-1
10 AFD-1
ATS-1 (FRONT)
TY)
4
ON PUM P STATI
35 M GD CAPACI
ON
NARY – NOT FOR CONSTRUCTI
CAL
ELECTRI
7 7 7 7
PUMP 5 PUMP 3 PUMP 1
PUMP 4 PUMP 2
250 50 50
250 250
UNI
(
RESTROOM
1/4"=1'-0"
VERIFY SCALE
MI
0 1"
PRELI
1/4"=1'-0"
PROJ 664626
DWG 100-E-202
SHEET of
LCP-X
GHTS RESERVED.
UNION PUMP STATION PLC PANEL
ETHERNET
OIT ETHERNET
RADIO
LL 2016. ALL RI
SWITCH
c CH2M HI
APVD
A
ANTENNA
BY
APVD
S THE PROPERTY OF
LL.
ON OF CH2M HI
ZATI
CE,I
HMI LCP-X LCP-X VFD-X (5)
TTEN AUTHORI
ONAL SERVI
ON
ODOR CONTROL GENERATOR
SI
CHK
SYSTEM PANEL CONTROL PANEL
REVI
THOUT THE W RI
M .REI
N,AS AN I
B
VASTAVA
PI
NCORPORATED HEREI
M M
DATE
R.SRI
FM
DSGN
NO.
N W HOLE OR I
M
S NOT TO BE USED,I
PUMP 1
CUT
PI
M M (50 HP)
TY
LE/LIT
NEW HAVEN,CONNECTI
M M
CONTROL AUTHORI
FM
LL AND I
WETWELL 1
M M
CHANNEL
CH2M HI
GRINDER
DRUM, TYP
THI
M-XXX-X-X
FM
M M
FROM SEWER
AGRAM
ON
PI
ON AND CONTROL
PUMP 3
ON PUM P STATI
M M M M
(50 HP)
M M M
ON
PROCESS FLOW DI
FM
NSTRUM ENTATI
CHANNEL
GRINDER
M-XXX-X-X PI
PUMP 4 M M
LE/LIT (250 HP)
UNI
FM
I
M
EXISTING
PUMP 5 FORCE MAINT
WETWELL (250 HP) TO EAST
PUMP STATION VERIFY SCALE
MI
0 1"
PRELI
PROCESS FLOW DIAGRAM PROJ 664626
SHEET of
GHTS RESERVED.
1. BASE FLOOD EL (BFE) = 11.00
LL 2016. ALL RI
MATCH EXISTING 3. PROJECTED SEA LEVEL RISE EL (SLR) = 14.00
c CH2M HI
SHALL CONFORM WITH THE FOLLOWING:
APVD
16'x8' ROLL-UP DOOR GENERATOR AND
A
DIESEL FUEL
a. AREA OF FLOOD RELIEF
BRICK VENEER (SEE SITE PLAN)
OPENINGS (Ao) = 2.5 in^2/1.0 ft^2
BY
6. AREAS IDENTIFIED FOR DRY FLOOD PROOFING
CMU WALL ABOVE DFE SHALL CONFORM WITH THE FOLLOWING:
APVD
APPROVED BY "AHJ".
S THE PROPERTY OF
EL +14.00 (SLR)
LL.
EYEWASH b. A BUILDING CODE COMPLIANT EXIT DOOR FROM
ON OF CH2M HI
NEW PERMITER EACH ISOLATED ROOM WITHIN THE DRY FLOOD
PROOF AREA SHALL BE PROVIDED.
CONC WALL
ZATI
CE,I
FLOOR
TTEN AUTHORI
EL +10.95
ONAL SERVI
ON
TYPE 316
SI
CHK
STAINLESS
REVI
EXST FDN WALL STEEL HATCH
SCREEN ROOM ABOVE
THOUT THE W RI
DRY FLOOD PROOFING PERMITER WALL
FRP GRATING,
DETAIL
DR
N,AS AN I
B
E
J.OSOKI
NCORPORATED HEREI
DATE
DSGN
NO.
BRICK VENEER
N W HOLE OR I
GNS I
NEW PERMITER
CMU WALL
S NOT TO BE USED,I
EL +14.00
CUT
FRP DOOR, TYP
TY
NEW HAVEN,CONNECTI
CONTROL AUTHORI
FLOOD VENT
T/ GROUND
LL AND I
FLOOR
0"M AX ABOVE
GROUND FLOOR
EL +10.95
CH2M HI
THI
EXST FDN WALL
CONTROL ROOM
NG FLOOR PLAN
NTS
ON
TYP
1 HOUR FIRE
TY
ON PUM P STATI
BARRIER CMU
GN
35 M GD CAPACI
ON
WALL
STANT DESI
UNI
CONCRETE WALL
RESTROOM
PERIMETER FLOOD
BARRICADE
MI
0 1"
1/4"=1'-0"
DATE NOVEMBER 2016
PRELI
WET FLOOD PROOF
AREA WITH FLOOD PROJ 664626
VENTS
DWG 100-S-201
SHEET of
Prepared for
November 2016
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX III
CONTENTS
Appendix
A Preliminary Design Drawings
Tables
Table 1-1. Flow Scenarios .......................................................................................................................... 1-1
Table 1-2. Pump Operation ........................................................................................................................ 1-4
Table 1-3. Summary of Force Main Velocities ........................................................................................... 1-5
Table 2-1. Existing Pumps .......................................................................................................................... 2-2
Table 2-2. Screening Design Criteria .......................................................................................................... 2-3
Table 2-3. Dry Weather Pump Selections .................................................................................................. 2-4
Table 2-4. Wet Weather Pump Selections ................................................................................................. 2-5
Table 3-1. Material Requirements for Structural Steel .............................................................................. 3-8
Table 5-1. HVAC Materials of Construction ............................................................................................... 5-3
Table 5-2. HVAC Outdoor Design Criteria .................................................................................................. 5-3
Table 5-3. Mechanical System Criteria ...................................................................................................... 5-4
Table 6-1. Plumbing and Fire Protection Materials of Construction ......................................................... 6-1
Table 9-1. Process Area Ventilation Rates ................................................................................................. 9-2
Table 9-2. Capital, O&M and NPV Assumptions ........................................................................................ 9-6
Table 9-4. Major Equipment, Design Criteria and Operating Conditions .................................................. 9-8
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX V
CONTENTS
Figures
Figure 2-1: Existing Grit Channels .............................................................................................................. 2-1
Figure 2-2: Existing Pumps ......................................................................................................................... 2-2
Figure 2-3: Existing Surge Suppressor ........................................................................................................ 2-3
Figure 2-4. Dry Weather Pump and System Curves ................................................................................... 2-5
Figure 2-5: Wet Weather Pump and System Curves ................................................................................. 2-6
Figure 9-1. Simplified Schematic of a Biotower System ............................................................................ 9-3
Figure 9-2. Photograph of a Biotower System ........................................................................................... 9-4
Figure 9-3. Schematic Dual Carbon Bed System ........................................................................................ 9-5
Figure 9-4. Photograph of a Dual Bed Carbon Scrubber ............................................................................ 9-5
Figure 9-5. Photograph of a Chemical Scrubber ........................................................................................ 9-6
VI GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
Acronyms and Abbreviations
AASHTO American Association of State Highway and Transportation Officials
ACGIH American Conference of Governmental Industrial Hygienists
ACH air changes per hour
ACI American Concrete Institute
AFD adjustable frequency drive
AISC American Institute of Steel Construction
ANSI American National Standard Institute
ASCE American Society of Civil Engineers
ASHRAE American Society of Heating, Refrigerating, and Air Conditioning
ASPE American Society of Plumbing Engineers
ASTM American Society for Testing and Materials
ATC automatic temperature control
Authority Greater New Haven Water Pollution Control Authority
AWWA American Water Works Association
BEP best efficiency point
BFE base flood elevation
CAIECC Connecticut Amendments to the International Energy Conservation Code
CFD computational fluid dynamics
cfm cubic feet per minute
cfph cubic feet per hour
CISPI Cast Iron Soil Pipe Institute
CMU concrete masonry unit
CSBC Connecticut State Building Code
CSO combined sewer overflow
DC direct current
DDC direct digital control
DFE design flood elevation
DLR device level ring
DWF dry weather flow
DX direct expansion
FEMA Federal Emergency Management Agency
fps feet per second
FRP fiberglass reinforced plastic
ft2 square feet
ft3 cubic feet
GNHWPCA Greater New Haven Water Pollution Control Authority
gpm gallon(s) per minute
H2S hydrogen sulfide
HI Hydraulic Institute
HMI human-machine interface
hp horsepower
HSS hollow structural sections
HVAC heating, ventilation, and air conditioning
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX III
ACRONYMS AND ABBREVIATIONS
IV GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 1
Hydraulics
1.1 Introduction
The Long-Term Control Plan (LTCP) Update includes alternatives that control combined sewer overflow
(CSO) discharges from all CSO outfalls to meet a 2-year, 6-hour level of CSO control (zero discharges) by
2040. The LTCP Update includes short term, intermediate term, and long term improvements to meet
these stated goals. This Preliminary Design Report of the LTCP focuses on long term improvements at
the Boulevard (Boulevard) Pump Station. Preliminary Design Drawings are shown in Appendix A of the
report.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 1-1
SECTION 1 – HYDRAULICS
The design parameters and considerations in selecting pumps for the stations include;
1. Create maximum reliability, efficiency and redundancy for flows in the dry weather range since
flows in the dry weather range occur 98 percent of the time during a typical year.
2. Utilize extended shaft centrifugal pumps.
3. Maintain N+1 for dry weather and wet weather pumping conditions.
4. Consider space restrictions in existing station footprints.
5. Avoid cycling of flows at the East Street and Boulevard Pump Stations since these flows go
directly to the ESWPAF.
6. Select pumps to operate well within the pump manufacturers’ defined allowable operating
range (AOR) for both wet and dry weather conditions.
7. For high frequency flow capacities, select pumps to operate within the pump’s preferred
operating range (POR) as defined by the Hydraulic Institute Standards (HIS) to obtain high wire-
to-water pump efficiencies for both wet and dry weather conditions. For less frequent lower
flow capacities, size pumps for operation well within the candidate pump manufacturers’
defined allowable operating range (AOR).
8. Maintaining impeller tip speed to prevent accumulation of rags within the volute.
9. Maintaining scouring velocities in pump discharges to prevent grit accumulation.
Avoiding high VFD and corresponding pump speed turndown.
1-2 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 1 – HYDRAULICS
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 1-3
SECTION 1 – HYDRAULICS
1.4.2.1 Boulevard
Boulevard currently has four pumps installed with no space for additional pumps. The existing pumps
have a rated capacity of 17.7 mgd. The stations firm capacity is 53.1 mgd and total capacity is 70.8 mgd.
Through conversations with pump station operators, the station pumps approximately 30 mgd during
peak flows. The pump station pumps to a 36-inch force main that joins the East Street force main
upstream of the harbor crossing.
The long-term flow scenario for Boulevard is 45 mgd. The minimum dry weather flow is 7.4 mgd, the
average dry weather flow is 12.5 mgd, and the maximum dry weather flow is 18.2 mgd.
The existing pumps do not have the capacity to meet the long-term pumping scenario with the largest
pump out of service (N+1 redundancy criteria). Several scenarios were investigated to meet the design
flows.
• Scenario 1: Four identical pumps installed in the existing pump station each rated at 15 mgd. A
single pump in service would be used for dry weather flows and three pumps in service, with one
pump in standby, would be used for the maximum wet weather flows. This scenario would have
trouble pumping the minimum dry weather flows without cycling.
• Scenario 2: Two dry weather pumps and three wet weather pumps. The dry weather pumps were
sized to efficiently pump the minimum flows to avoid cycling. To achieve this the dry weather pumps
were sized for 12.5 mgd and would require both pumps in service to meet the maximum dry
weather flowrate. Pump redundancy would be provided by one of the wet weather pumps which
would cycle at the dry weather flows in the event one of the dry weather pumps was out of service.
The wet weather pumps would be sized to pump the maximum flows with one pump out of service.
Each wet weather pump would be rated at 22.5 mgd. In order to install five pumps in the existing
station the two dry weather pumps are installed on a single suction header.
• Scenario 3: Three dry weather pumps and four wet weather pumps. The dry weather pumps are
sized similar to scenario 2 but they have a standby pump to meet N+1 redundancy criteria. Installing
seven pump requires the addition of a submersible pump station next to the existing station. The
dry weather pump would be installed in the submersible pump station and the wet weather pumps
would be installed in the existing pump station. Each wet weather pump would be rated at
15.00 mgd.
It was determined that Scenario 3 was the best option to meet the design flows. This scenario allows for
N+1 redundancy for both dry weather and wet weather pumping and efficiently handles the minimum
dry weather flows without cycling and peak wet weather flows.
Table 1-2 shows the proposed pump operation under several flow regimes for the Intermediate and
Long Term Flow Scenario.
1-4 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 1 – HYDRAULICS
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 1-5
SECTION 2
Process Mechanical
2.1 Introduction
This section describes the basis of the process mechanical design associated with improvements to meet
the intermediate- and long-term flow scenarios and improve reliability of the station.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 2-1
SECTION 2 – PROCESS MECHANICAL
The grit channels combine before entering the wet well. There are sluice gates located on the inlet to
each side of the wet well and a sluice gate on the wet well dividing wall.
The screenings and grit are conveyed to separate dumpsters in the pump station by belt conveyors.
Overhead doors allow for bin removal.
Each side of the wet well has two 30-inch suction wall pipes for total of four. Four pumps are currently
installed with no space for additional pumps. All four pumps are identical, as shown in Table 2-1. They
are manufactured by Goulds and are extended shaft vertical centrifugal pumps.
2-2 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 2 – PROCESS MECHANICAL
Grinder Motor 5 HP
Compactor Motor 3 HP
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 2-3
SECTION 2 – PROCESS MECHANICAL
Number of pumps 3 3 3
NPSHA (ft) 33 33 33
NPSH3 25 15 17
Model NP3356.736
Manufacturer Flygt
2-4 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 2 – PROCESS MECHANICAL
NPSHA (ft) 32 31
NPSH3 17 16
Model 12MF29A
Manufacturer Flowserve
Figures 2-4 and 2-5 show the system versus system curves containing the design points for dry and wet
weather pumps.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 2-5
SECTION 2 – PROCESS MECHANICAL
Figure 2-4 shows the variable-frequency drive (VFD) curves for two pumps in operation. Under the
minimum dry weather flow (DWF), a single pump is operating close to the Best Efficiency Point (BEP). A
single pump meets the average DWF just outside preferred operating range (POR), but within the
allowable operating range (AOR). Two pumps in operation meet the average DWF within the POR. Two
pumps are necessary to meet the DWF maximum flow with both pumps operating within the POR close
to the BEP.
350
Boulevard WWF Pumps
300
250
WWF
200
Head (ft)
150
100
50
DWF MAX DWF MAX One Harbor Crossing
0
0 10000 20000 30000 40000 50000 60000
Flow (gpm)
900 RPM 810 RPM 720 RPM 630 RPM 495 RPM
AOR POR BEP Design Points
2-6 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 2 – PROCESS MECHANICAL
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 2-7
SECTION 2 – PROCESS MECHANICAL
2-8 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 3
Structural
3.1 Introduction
This section is intended to assess the building structure components of the Boulevard Pump Station and
identify design criteria for the rehabilitation of the facility. It outlines proposed solutions to address
structural deterioration, deficiencies and upgrades to incorporate architectural, process mechanical, and
MEP findings.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 3-1
SECTION 3 – STRUCTURAL
concrete foundation walls around the below-grade wet well and dry well areas. The above-grade
exterior elevations of the pump station structure are clad with brick veneer with a non-structural
concrete masonry unit (CMU) backup. An 8-inch CMU partition wall has been provided between each of
the five rooms.
3-2 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 3 – STRUCTURAL
our understanding that the recommended repairs have yet to be incorporated and the
conditions may have further deteriorated.
Further structural analysis and field review will be needed for this area. Supplemental supports
should be installed below the generator room when repair work is being completed in the wet
well below. Concrete repairs should be completed on the top side and underside of the slab.
4. Blower Room: The Blower room is located on the west side of the pump station building and houses
motor control panels, chemicals and other mechanical equipment.
a. The concrete slab in the blower room exhibits significant deterioration totaling approximately
200 ft2. We suspect this is due to the chemicals stored in the room and an unprotected floor
surface. All deteriorated concrete on the floor slab should be repaired, a new chemical resistant
protective coating should be provided on all concrete and wall surfaces with in the chemical
storage area.
b. The chemical storage area within the blower room does not have walls or a curb for chemical
containment in the case of the spill. Containment walls should be added to this area. All walls
should be protected with a chemical resistant coating.
5. Dry Well: The dry well is located approximately 22 feet below the Motor Room and houses the
pumps for discharge from the adjacent wet well.
a. The dry well area concrete surfaces were in good condition and painted. Some leakage was
noted through the foundation walls. All active leaks should be sealed. Damaged areas shall be
re-coated.
b. The drains provided in the dry well floor are corroded. Replace existing drain bodies and grates.
c. A steel platform composed of galvanized framing and grating is provided for access to each of
the four pumps. Due to leaks at each of the pumps, the platform supports have been subjected
to moisture. Corroded stair and platform framing areas should be cleaned and protected with a
new coating system.
d. The pump pedestals and steel pipe supports are also subjected to moisture due to leaks around
the pump mechanism. All deteriorated areas of steel and concrete should be cleaned, repaired
and recoated with a protective coating system.
6. Screening Room: The screening room is the largest room in the Inlet Works building and provides
access to the influent, bar screen and grit collection channels:
a. The reinforced concrete floor in the screening room appears to be in good condition. The floor
appears to be constantly wet. The floor should be planned for sealants in joints at perimeter
walls and a protective coating system. This will protect the concrete structure and perimeter
walls.
b. At the time of the site visit, the aluminum gratings over channel openings were being replaced
with new composite grating. All channels shall receive a protective coating system over concrete
surfaces exposed to process fluids and moisture.
7. Wet Well: The wet well is located below the generator and blower rooms north of the dry well.
Access to the wet well is provided through a stairwell on the east side of the pump station building.
The stairs leading down to the wet well are composed of cast-in-place concrete.
a. The concrete stairs leading into the wet well were exhibiting deterioration, specifically along
embedded nosing plates. All nosing plates shall be removed and concrete steps shall be
repaired. A new chemical resistant protective coating should be provided over all steps.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 3-3
SECTION 3 – STRUCTURAL
b. The concrete foundation walls and framing within the wet well could not be reviewed up close.
Significant cracking and efflorescence on the ceiling below the generator room was noted.
c. The existing walls and framing in the wet well were not protected by a coating system. A new
protective coating shall be applied to all wet well concrete and steel surfaces.
d. The grating in the wet well could not be reviewed due to debris in the wet well. The debris
should be cleaned and all grating systems should be replaced in the wet well.
e. The railings along the steps were loose. Replace all railing systems in the wet well.
8. Garage and Exterior of Building:
a. The garage portion of the building is located on the west side of the pump station building, at
grade level and appears to be in good condition.
b. The exterior entrances and loading dock area on the west side of the pump station building is
approximately 4 feet-0 inches above grade. There was concrete deterioration noted at
embedded nosing plates on one of the two stairs. No sealants were provided along the brick
veneer/concrete interface, in cracks or at construction joints. Existing tread embedment plates
should be removed from all exterior stairs and the damaged concrete repaired. New
polyurethane sealant shall be provided along all walls, surface cracks and at construction joints.
c. The exterior brick veneer appears to be in good condition with the exception of the northwest
corner of the building. The brick veneer does not have control joints and has shifted from the
corner and cracked the foundation wall below. The damaged concrete wall should be repaired,
and the brick veneer should be rebuilt at the corner incorporating a vertical masonry control
joint.
d. There are three exterior steel framed stairs with metal grating treads and landings. The metal
treads are bent in several locations, and the grating at the landing has been covered with wood
decking boards. All landing grating and stair treads should be replaced with heavy duty
galvanized grating at each of the three locations.
3-4 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 3 – STRUCTURAL
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 3-5
SECTION 3 – STRUCTURAL
3.4.4 Concrete
Materials and design procedures for concrete are described below.
3-6 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 3 – STRUCTURAL
3.4.4.1 Materials
The following minimum requirements apply (concrete compressive strength at 28 days):
• Typical Concrete, unless otherwise noted 4,500 psi
• Concrete Fill, unless otherwise noted 3,000 psi
• Concrete Fill exposed to liquid 4,500 psi
• Curbs and Sidewalks 3,000 psi
• Conduit Encasements and pipe
(encasements not integral with foundation) 4,500 psi
Reinforcement:
• Conventional Steel: ASTM A615, Grade 60 (fy = 60 kilopounds per square inch [ksi])
3.4.5 Masonry
Materials and design procedures for masonry are as follows.
3.4.5.1 Materials
The following requirements apply:
• Hollow concrete masonry units will conform to ASTM C 90 and will be normal- or medium-weight
units with a net area compressive strength of 1,900 pounds per square inch (psi).
• Mortar will conform to ASTM C 270, Type S.
• Grout will conform to ASTM C 476. Minimum 28-day compressive strength will be 2,000 psi.
• Steel reinforcement will conform to ASTM A615, Grade 60.
• Horizontal joint reinforcing steel will conform to ASTM A82.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 3-7
SECTION 3 – STRUCTURAL
3.4.6.1 Material
The material requirements for structural steel are listed in Table 3-1.
Pipes A53 B 35 60
A325 or
Bolts for Connections (1/2” to 1” diameter) - - 120
F1582
3.4.7 Cranes
Cranes shall meet requirements of AISC Steel Construction Manual and ASCE 7. Unless noted otherwise,
vertical impact shall be 25 percent of maximum wheel load. Lateral force on crane runway shall be
calculated as 20 percent of sum of rated capacity of crane and weight of hoist and trolley. Lateral force
shall be assumed to act horizontally at traction surface of a runway beam, in either direction
perpendicular to beam. Longitudinal force on crane runway beams shall be calculated as 10 percent of
maximum wheel loads of crane. Longitudinal force shall be assumed to act horizontally at traction
surface of a runway beam in either direction parallel to beam.
3-8 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 4
Architectural
4.1 Introduction
This section assesses the architectural components of the Boulevard Pump Station and presents the
design criteria for upgrades to the facility. The architectural assessment consisted of three tasks:
interviewing staff, visiting facility site, and reviewing available facility documentation. It outlines
proposed solutions to deficiencies found from building and code assessment done. These
recommendations are intended to serve as preliminary guidance for the design of facility renovations.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 4-1
SECTION 4 – ARCHITECTURAL
building, and 375-gallon Diesel day tank in the Mechanical Room. No. 2 Diesel Fuel is a Class II
Combustible Liquid and irritant. The exempt amount of inside storage of diesel fuel is 120 gallons.
Rooms with diesel tanks over the exempt amount would be H-3 hazardous occupancies. This requires
fire separation from the rest of the building and sprinkler system. There is no containment for the inside
diesel tanks and battery storage. The Diesel day tank blocks required 3 feet-0 inches clear egress width.
No safety shower or eyewashes. There is an unused Bioxide tank in the Garage. There are two 55-gallon
drums of hydraulic fluid is in the Pump Room at El. 6. Hydraulic fluid is an irritant and not considered
hazardous by building code. The design will include the following components:
1. Limit the quantity of corrosive to 500 gallons to hazardous occupancy. The recommended odor
control system will be an activated carbon system to all chemical tanks and pumps related to odor
control will be demolished.
2. Provide containment for any chemical storage area. The containment has to contain largest tank and
needs to be resistant to chemical emersion.
3. Remove electrical equipment from room with any corrosive chemicals.
4. Remove the existing inside Diesel storage tank and provide new day tank integral with the exterior
emergency generator system. The emergency generator will be housed in a weatherproof
enclosure.
5. Provide containment for battery storage.
6. Provide leak detection in all chemical containments.
7. Provide emergency safety shower and eyewash in Blower Room. Add emergency eyewash at battery
storage and hydraulic fluid storage.
8. Add NFPA 704 Hazardous Material Signal signs at doors to chemical storage areas. Add Caution
Corrosive sign at door to corrosive chemical storage area. Add Warning Diesel Fuel sign at outside
Diesel storage tank.
9. Seal wall penetrations in Generator and Boiler rooms.
10. Demolish Bioxide tank in the Garage.
10. Provide new curbs for new and existing roof top HVAC.
11. Replace roof hatch with aluminum roof hatch with safety rails.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 4-3
SECTION 4 – ARCHITECTURAL
1. Remove all existing metal grating in Stair No. 2, wet well, and around west gates in Screening and
replace with FRP grating. Make all grating level with floor.
2. Surface prepare and paint grating supports with a chemical resistant epoxy paint system.
3. Remove all existing metal handrail in Stair No. 2, wet well and around west gates in Screenings and
replace with FRP handrail.
4. Remove 3 exterior metal stairs on north side and metal stair between Garage and Screening and
replace with FRP stairs and handrails.
5. Modify conveyer support and/or guard post at Garage exit stair to provide code required 3-foot
egress path.
6. Add limited headroom warning sign for low beams in Pump Room at El-12.
7. Add wall mounted handrail at south stair in Pump Room at El-12
4.3.2.6 Painting
The walls and ceilings are in need of repainting. Floors of Scrubber Area, Generator Room, Blower Room,
Mechanical Room, and Pump Room are cracked and spalling. Bottom of walls are deteriorating in
Screening, Stair No. 2 and Scrubber Area. Equipment and piping is in need of painting. The design will
include the following components:
1. Surface prepare and paint walls and ceilings in all the rooms with a chemical resistant epoxy paint
system.
2. After surface preparation and before painting the walls, patch holes and the base of the walls in
Screening, Stair No. 2 and Scrubber Area with 100% solid epoxy filler.
3. Remove spalling concrete and patch Scrubber Area, Generator Room, Blower Room, Mechanical
Room, and Pump Room floors.
4. Surface prepare and paint existing painted floor and Toilet floor with chemical resistant epoxy non-
skid paint system.
5. Surface prepare and paint piping, equipment, and supports in all the rooms with a chemical resistant
epoxy paint system, including exterior vent pipes.
4-4 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 5
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 5-1
SECTION 5 – HEATING, VENTILATION, AND AIR CONDITIONING
5.2.1 General
The existing heating and ventilation system in the Screen/Grit Works/Garage/Odor Control Room will be
completely demolished and a new make-up air unit (MAU) will be provided for the Screen/Grit
Works/Garage/Odor Control. The MAU may be located on the roof and will provide 12 air changes/hour
(ACH) with 100 percent outside air that will be provided in order to reduce the NFPA electrical
classification from Class 1 Division 1 to Class 1 Division 2. The supply air will be tempered to minimum 55
degrees F during winter in order to protect plumbing and water piping from freezing and ventilation
system will be reduced to 6 ACH, as allowed by NFPA 820 and whenever the outside air temperature is
50 degrees F or below, the space is unoccupied and the combustible gas detector is 10 percent below
the lower explosive limit of methane. The MAU and exhaust fans will be provided with VFDs and a
separate exhaust fan will be provided to maintain proper temperature conditions for the pump motors
during the summer months.
The 50 percent exhaust air during summer and 100 percent of exhaust air during winter (ambient
temperature is 50 degrees F or below) from the Screen/Grit Works/Garage/Odor Control will be treated
by the proposed odor control system.
The existing dual-fuel boiler is recommended to be replaced with a new duel-fuel boiler. The new boiler
and the accessories should be sized to meet the new heating requirement.
A split system DX air conditioning system is recommended for the Pump Room to handle the heat
dissipation from the VFDs, which will be located in this room.
A new heating and ventilation system will be recommended for the Screening Room to provide
tempered air into the space.
5.3 Equipment
The specific type of equipment used on a particular building will be determined during detailed design
based on application. Roof mounted equipment will be used where possible to preserve floor space and
to minimize equipment exposure to aggressive environments. The following types of HVAC equipment
may be utilized on this project.
5-2 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 5 – HEATING, VENTILATION, AND AIR CONDITIONING
5.4 Materials
Table 5-1 provides various material choices that may be used for HVAC systems depending on the type
of atmosphere in which equipment is installed. Specific materials will be selected during detailed design
to suit the application.
Ductwork Al
Process Non-corrosive
Equipment HPCS
Ductwork GS/Al
Non-Process Non-corrosive
Equipment GS/Al
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 5-3
SECTION 5 – HEATING, VENTILATION, AND AIR CONDITIONING
Table Abbreviations:
AC – Air Conditioning
ACH – Air changes/hour
E – Electric
G – Gas Heating Method
HW – Hot Water
OA – Outside Air
5-4 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 5 – HEATING, VENTILATION, AND AIR CONDITIONING
5.6 References
5.6.1 Codes
The HVAC design will follow shall follow all applicable local, state, and federal codes and criteria. The
following codes will be used for the mechanical design of this project:
• 2016 Connecticut State Building Code
• 2012 International Building Code
• 2012 International Mechanical Code
• 2012 International Energy Conservation Code
• 2005 Connecticut State Fire Safety Code
5.6.2 Standards
The following standards and guides will be used for the mechanical design of this project:
1. ASHRAE (American Society of Heating, Refrigerating and Air Conditioning Engineers)
2. SMACNA (Sheet Metal and Air Conditioning Contractors’ National Association)
3. ACGIH (American Conference of Governmental Industrial Hygienists) Industrial Ventilation Manual of
Recommended Practice
4. NFPA (National Fire Protection Association)
5.6.3 Miscellaneous
5.6.3.1 Calculation Software
• Heating and Cooling Load Analysis: Carrier E20-II Hourly Analysis Program (HAP)
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 5-5
SECTION 6
6.3.2 Materials
Table 6-1. Plumbing and Fire Protection Materials of Construction
Equipment or
Area Atmosphere (1) Materials of Construction
System
Piping SS/GS/CU/AL/HCI/CU/CPVC
Process Corrosive
Equipment Coated GS/Al/SS/CU
Piping CU/BS/CI/DI
Process Non-Corrosive
Equipment Coated GS/Al
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 6-1
SECTION 6 – PLUMBING AND FIRE PROTECTION
Piping GS/BS/CU/DI/PVC
Administration Non-Corrosive
Equipment GS/CS
6-2 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 6 – PLUMBING AND FIRE PROTECTION
6.5 References
6.5.1 Codes
The design of this project will be governed by the 2016 Connecticut State Building Code, Connecticut
State Fire Safety Code and all adopted International Codes including the International Plumbing and
International Fire Codes.
6.5.2 Standards
The following standards and guides will be used for the plumbing and fire protection design of this
project:
• ANSI (American National Standard Institute)
• ASPE (American Society of Plumbing Engineers)
• ASTM (American Society for Testing and Materials)
• AWWA (American Water Works Association)
• CISPI (Cast Iron Soil Pipe Institute)
• IBC (International Building Code)
• IFC (International Fire Code)
• IPC (International Plumbing Code)
• NFPA (National Fire Protection Association)
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 6-3
SECTION 7
Electrical
7.1 Introduction
The existing electrical service to this facility is 480 volt, 3-phase via a single transformer, terminating at
switchgear rated at 2500A. This service will need to be upgraded to a medium voltage service, as four
700 horsepower (hp) wet weather pumps are proposed for this project, and motors above 600 hp
generally require medium voltage service. Three 480 volt, 215hp dry weather pumps are also required
for this project.
The local electric utility that provides power to this facility is United Illuminating (UI). UI only offers 480
volt and below services and a 13.8kV service to its customers. UI does not provide a 4160-volt service, or
any other service between 13.8kV and 480 volts.
The electrical work at Boulevard Pump Station will consist of replacing the incoming distribution
switchgear, generator and an automatic transfer switch with 4160 volt rated equipment. A new 1200-
amp low voltage switchgear will also be added to feed the dry weather pump motors and 480 volt MCC.
The 480-volt motor control centers will also be replaced, as the existing electrical equipment will be over
30 years old by the time this project is implemented, and needs to be replaced in its entirety. New wet
weather pump motors will be compatible with and controlled by 4160-volt adjustable frequency drives
to provide precise control, improve efficiency, and reduce power factor losses. New dry weather pumps
will be controlled by new 480-volt adjustable frequency drives.
The construction sequence will be staggered so that all pumps may remain operable during
construction, and only short shutdowns are required to remove and install new pumps.
Electrical distribution equipment will be elevated 4 feet-0 inches above finish floor (AFF) to avoid
flooding while accounting for sea level rise concerns.
The work required for this station is described in further detail below.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 7-1
SECTION 7 – ELECTRICAL
currently located. This room will house all medium voltage switchgear and the automatic transfer
switch. Construction of this room will be sequenced so that the existing engine-generator can remain in
service as long as possible.
A 3000 kilovolt-amperes (kVA), 13.8 kV-4160 V transformer will be placed outdoors, mounted on a pad
near the existing transformer in the northeast corner of the building. Note that the GNHWPCA, not UI,
will be responsible for this transformer. The 4160 V secondary feeders will then return to a new 4160 V,
1200A arc flash rated switchgear, also located in the new medium voltage switchgear room. This 4160-
volt switchgear will feed the wet weather pump AFDs, and a 750 kVA, 4160-480V, 3-phase, 3-wire
transformer which will power a new 1200A low voltage switchgear.
outdoors, in front of the stairwell area at the east end of the pump station. The existing generator
controls and batteries are also located in the generator room.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 7-3
SECTION 7 – ELECTRICAL
7.4.2.3 Transformers
A new 3.0 MVA, 13.8 kV-4160 V, oil filled transformer and a 750 kVA 4160-480 V transformer will be
mounted on pedestals outdoors to the south of the existing transformer. The 750 kVA transformer may
be dry type or oil filled, and this will be determined in detailed design. The existing transformer will
remain in service until the new service is established.
7-4 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 7 – ELECTRICAL
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 7-5
SECTION 7 – ELECTRICAL
7.5.6 Lighting
Existing lighting will be replaced with state-of-the-art LED type fixtures in all areas, including Class I,
Division 1 and Class I, Division 2 areas. LED frog-eye type emergency lighting fixtures will also be
provided.
Existing outdoor lighting fixtures will be replaced with metal halide or LED type fixtures. Where existing
lighting is insufficient, new lighting will be added.
7-6 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 8
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 8-1
SECTION 8 – INSTRUMENTATION AND CONTROLS
8-2 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 8 – INSTRUMENTATION AND CONTROLS
between the package systems and the Pump Station PLC System will be further developed during design
development and coordinated with the package system vendors.
The sump pump control panel will be replaced. If new sump pumps are provided, a new control panel
will be specified. The panel will be mounted above the sea level rise protection elevation.
The hydraulic surge control valves will be replaced and a new control panel will be provided.
The existing bubbler systems, along with the associated compressors and receiver tanks will be replaced
by non-fouling, hydrostatic pressure type transmitters, designed specifically for wastewater
applications. The transmitters will be installed in stilling wells. As a backup to the level transmitters, high
and low level switches will be provided to operate the pumps upon failure of a transmitter.
New electromagnetic flow meters will be provided in the discharge line of each pump. The installation
will be coordinated with the new piping layout for better locations conforming to the upstream and
downstream straight pipe length requirements.
Detailed change-out procedure will be developed so that the new I&C equipment can be installed and
tested prior to being put into operation. The design will allow the new Pump Station PLC System and the
existing control system to coexist for some time as the new system is brought online and the old system
is decommissioned. The pump station will remain operational during switchover.
Security camera system with DVR will be provided at the pump station. The location and quantity of
cameras will be determined during design development.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 8-3
SECTION 9
Odor Control
9.1 Introduction
The Boulevard Pump Station has a crossflow scrubber that was originally designed for a total flow of
15,500 cfm and dual chemistry consisting of both sodium hypochlorite and sodium hydroxide for odor
removal. Although the system is in operation, it is unknown how much foul air is actually being
ventilated and only sodium hypochlorite is being added. Much of the supporting infrastructure such as
the chemical transfer pumps, have deteriorated and are no longer functioning. It is recommended that
this system be replaced.
The Boulevard Pump Station processes that require odor control include an inlet chamber, three parallel
channels that include bar screens, four aerated grit chambers and two wet wells. There are belt
conveyors that convey screenings and grit to two separate dumpsters located in the garage.
9.2.1 Containment
The existing channels contain sections of grating that are covered with mats to contain odors within the
channels. The inlet chamber is uncovered and allows for comingling of sewage vapors with the overlying
room space that can then result in the release of sewage odors to the ambient atmosphere. It is
recommended that all grating be replaced and that the inlet chamber be covered with solid panels to
prevent escape of raw sewage vapors into the overlying room space. Covers will be designed using
materials of construction resistant to corrosion (e.g., fiberglass reinforced plastic (FRP) or aluminum
checker plate). Covers will be constructed using flat removable panels. The cover design will facilitate
easy removal of individual panels by two people. Each panel will not weigh more than 100 lbs and will
have an integral nonskid surface. Lifting handles shall be provided on each panel. Each panel will have
gasketed joints to prevent fugitive air release.
As a result of the containment of foul air within the process channels, protection of concrete against
corrosion using either protective coatings or liners is recommended and will be included during detailed
design.
Grit and screenings are currently conveyed to the garage where they are discharged into open
dumpsters. As a result, the entire volume within the garage requires ventilation and odor control. It is
recommended that foul air capture hoods be installed over each dumpster to facilitate focused air
capture from the dumpsters thereby allowing for overall reduced foul air extraction rates from the
garage.
9.2.2 Conveyance
Foul air will be conveyed from within the contained process channels and wet wells by FRP ductwork. It
is anticipated that up to nine foul air pickup locations will be designed, three associated with channels,
four associated with the grit chambers and one for each wet well. Each foul air pickup location will
include a flow balancing damper to facilitate adjustment of flow for each pickup to design values. The
foul air duct will connect to the covers through a flanged connection to allow for easy removal. The duct
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 9-1
SECTION 9 – ODOR CONTROL
will rise vertically straight up and then move horizontally at a distance overhead ensuring clearance
(e.g., min. 7 feet). The exact layout will be determined during detailed design.
Allowance for air flow into the covered process channels and wet wells will be included in the design.
The relative locations of air entry and foul air extraction will be selected to achieve good overall air
movement within the enclosed process area and minimize development of “dead zones” or short-
circuiting.
The extraction of foul air will be achieved through use of a single exhaust fan constructed of FRP. A flow
balancing damper will be located at the fan inlet to allow for adjustment of overall system air flow. The
fan will convey captured foul air to an odor control system where the odorous compounds, primarily
hydrogen sulfide (H2S), are removed prior to release to the ambient atmosphere.
Total 17,000
9-2 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 9 – ODOR CONTROL
9.3.1 Biotowers
In many ways, a biotower looks externally similar to a wet chemical scrubber, except that no hazardous
chemical addition is required. Figure 9-1 depicts a simplified schematic diagram of a biotower system.
Systems are pre-engineered, vendor-supplied systems made of fiberglass-reinforced plastic or high
density polyethylene shells. Biotowers use a biologically active media bed to absorb and oxidize odorous
compounds from the foul air stream. One of the primary technical advances associated with this
technology is the development of engineered inert media on which the biomass attaches. As the media
is inert, it is not compromised by the acidic environment within the biotower and has lifespans on the
order of 20 years. The media receives either constant recycle spray (bioscrubber) or intermittent once-
through spray humidification (biotrickling filter), depending on the vendor’s approach. The spray is also
the source of trace nutrients for the biological system. There are typically two potential sources of
water, potable or plant effluent. If potable water is used, then a supplemental nutrient supply
containing trace organics, nitrogen, phosphorous, and potassium is required. If plant effluent is
available, then supplemental nutrients are usually not required as the plant effluent water will contain
sufficient nutrients. For Boulevard Pump Station, potable water and supplemental nutrients would be
required as plant effluent is not available.
Biotowers are usually designed in the form of a cylindrical arrangement such as the one shown in
Figure 9-2.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 9-3
SECTION 9 – ODOR CONTROL
use of this type of impregnated carbon is not recommended for further consideration. Finally, there are
carbons available that have been processed in a manner that results in high selective adsorptive capacity
for H2S (e.g., order of magnitude higher than virgin activated carbon). The use of this type of high
capacity carbon is recommended for consideration as it will extend the useful life of the carbon
significantly thereby reducing O&M issues and costs associated with frequent media replacement.
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 9-5
SECTION 9 – ODOR CONTROL
soda to facilitate dissolution of hydrogen sulfide into solution. Most have a stage with sodium
hypochlorite added to oxidize reduced compounds. Other chemistries can be used to remove
compounds, such as ammonia, that are less amenable to oxidation. Chemical scrubbers offer flexible
configurations with smaller foot prints than are typical of biofilters and biotowers. Figure 9-5 shows an
example. However, chemical scrubbers have the disadvantage that the cost to operate is proportional to
the hydrogen sulfide loading. Significant hydrogen sulfide loadings, such as would be present at the
headworks, can result in large operating costs. Nevertheless, chemical scrubbers are technically viable
for this application and are therefore included in the technology cost comparison. For this application, a
two stage dual chemistry chemical scrubber is recommended for consideration.
Labor 40 $/hr
9-6 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
SECTION 9 – ODOR CONTROL
Excavation 15 $/CY
Backfill 35 $/CY
Allowance Costs
Equipment Installation 10 %
Field painting/finishes 1 %
Mechanical 8 %
Electrical 8 %
Instrumentation 5 %
Financial Factors
Discount Rate 7 %
Contractor Markups:
General Conditions 7 %
Contingency 30 %
GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX 9-7
SECTION 9 – ODOR CONTROL
that the frequent turnover of air within the enclosed areas will prevent high concentrations of H2S from
accumulating, thus maintaining an inlet concentration of H2S to the odor control system well below the
25 ppmv threshold. Therefore, carbon is recommended as the odor control technology of choice.
Table 9-3. Capital, Annual O&M and NPV Evaluation
Technology Carbon Biotower Chemical Scrubber
Carbon type and replacement frequency High adsorptive capacity carbon, e.g., 0.3 g H2S/cc carbon;
24-month media replacement frequency
Odorous Air Fan One (1) fan, FRP construction with sound enclosure;
continuous operation
9-8 GNHWPCA_LTCPUPDATE_BOULEVARDPS_DRAFT_11302016.DOCX
Appendix A
Preliminary Design Drawings
1 2 3 4 5 6
GHTS RESERVED.
INDEX TO DRAWINGS
LL 2016. ALL RI
300 - BOULEVARD PUMP STATION
c CH2M HI
er
APVD
Seal
A
BY
NO. NO. NO. NO.
GENERAL ELECTRICAL
APVD
S THE PROPERTY OF
300-G-001 BOULEVARD PUMP STATION INDEX OF DRAWINGS 300-E-201 BOULEVARD PUMP STATION SINGLE LINE DIAGRAM
LL.
ON OF CH2M HI
ew
300-G-002 BOULEVARD PUMP STATION ABBREVIATIONS 300-E-202 BOULEVARD PUMP STATION MVSWGR-1 AND MCC-1
QC Revi
ELEVATIONS
300-G-003 BOULEVARD PUMP STATION ABBREVIATIONS
AND GENERAL LEGEND 300-E-203 BOULEVARD PUMP STATION FIRST FLOOR PLAN
ZATI
CE,I
300-G-005 BOULEVARD PUMP STATION INSTRUMENTATION AND
TTEN AUTHORI
ONAL SERVI
CONTROL LEGEND - SHEET 1
SION
CHK
300-G-006 BOULEVARD PUMP STATION INSTRUMENTATION AND
REVI
CONTROL LEGEND - SHEET 2
THOUT THE W RI
300-G-007 BOULEVARD PUMP STATION ARCHITECTURAL AND
STRUCTURAL LEGEND
DR
N,AS AN I
B
E
300-G-017 BOULEVARD PUMP STATION ELECTRICAL LEGEND 3
J.OSOSKI
NCORPORATED HEREI
CIVIL
DATE
300-C-201 BOULEVARD PUMP STATION SITE PLAN
DSGN
NO.
N W HOLE OR I
STRUCTURAL
S NOT TO BE USED,I
CUT
ARCHITECTURAL
TY
NEW HAVEN,CONNECTI
LL AND I
300-A-202 BOULEVARD PUMP STATION PLAN 45 MGD CAPACITY
CH2M HI
CAPACITY
THI
REUSE OF DOCUM ENTS:
MECHANICAL
C
300-M-201 BOULEVARD PUMP STATION 45 MGD CAPACITY PLAN
ON
300-M-302 BOULEVARD PUMP STATION 45 MGD CAPACITY
NGS
310-M-201 BOULEVARD DRY WEATHER PUMP STATION PLAN &
NDEX OF DRAW I
SECTION
ON
NARY – NOT FOR CONSTRUCTI
GENERAL
I
D
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 300-G-001
SHEET of
CL CENTERLINE ESC EROSION AND SEDIMENT CONTROL MC MODULATE-CLOSE PEP POLYETHYLENE PIPE
ABBREVIATIONS
GHTS RESERVED.
HDW HARDWARE
CLDI CEMENT LINED DUCTILE IRON EP EXPLOSION PROOF, EDGE OF MCC MOTOR CONTROL CENTER PEN. PENETRATION
HGL HYDRAULIC GRADE LINE
CLSF CONTROLLED LOW STRENGTH FILL PAVING HK HOOK MCJ MASONRY CONTROL JOINT PFC POUNDS PER CUBIC FOOT
A AMMETER, AMPERES, AWNINGS
CLG CEILING EQL EQUAL HGT HEIGHT MDO MEDIUM DENSITY OVERLAY PENTHOUSE
PH
AB, ABV ANCHOR BOLT, ABOVE
CLR CLEAR, CLEARANCE EQL SP EQUALLY SPACED HH HANDHOLE MECH MECHANICAL pH HYDROGEN ION CONCENTRATION
ABDN ABANDON
HID HIGH INTENSITY DISCHARGE
LL 2016. ALL RI
CLSM CONTROLLED LOW STRENGTH MATERIAL EQPT EQUIPMENT MFD MANUFACTURED PH PHASE
AC ACOUSTICAL, ACOUSTICAL CEILING CMP CENTRAL MONITORING PANEL HK HOOK MFR MANUFACTURER PI POINT OF INTERSECTION
ESC EROSION AND SEDIMENT CONTROL
AC ALTERNATING CURRENT
CMP CORRUGATED METAL PIPE HM HOLLOW METAL MGD MILLION GALLONS PER DAY PIT
ETM ELAPSED TIME METER PILOT TUBE TEST STATION
AC ASPHALTIC CONCRETE CMU CONCRETE MASONRY UNIT
EVC END OF VERTICAL CURVE HOA HAND-OFF-AUTO MH MANHOLE, MOUNTING HEIGHT PJF PREMOULDED JOINT FILLER
ACFL ACCESS FLOORING
c CH2M HI
CNTR COUNTER HOR HAND-OFF-REMOTE MIN MINIMUM
EW EACH WAY PL PLATE (STEEL)
ACI AMERICAN CONCRETE INSTITUTE
er
CO CLEANOUT, CARBON MONOXIDE HORIZ HORIZONTAL
APVD
EWC ELECTRIC WATER COOLER MISC MISCELLANEOUS PL PROPERTY LINE
Seal
A ACMU ACOUSTICAL CONCRETE MASONRY
COL COLUMN, COLOR HP HORSEPOWER
UNIT, ACOUSTICAL CMU EXH EXHAUST MJ MECHANICAL JOINT PLAM PLASTIC LAMINATE
CONC CONCRETE HPT HIGH POINT
ACP ACOUSTICAL PANELS EXP EXPANSION, EXPOSED MLO MAIN LUGS ONLY PLAS PLASTER, PLASTIC
BY
COND CONDENSATE HPU HYDRAULIC POWER UNIT
ACST ACOUSTICAL EXP AB EXPANSION ANCHOR BOLT MMDW DRY WEATHER MAXIMUM MONTH PLC PROGRAMMABLE LOGIC CONTROLLER
CONDTN CONDITIONED HR HOSE RACK, HANDRAIL
ACT ACOUSTICAL TILE EXP JT EXPANSION JOINT MMP MECHANICAL MOUNTING PANEL PLYWD PLYWOOD
CONN CONNECTION HV HOSE VALVE
AD AREA DRAIN EXST, EXIST EXISTING MMWW WET WEATHER MAXIMUM MONTH PNL PANEL
CONSTR CONSTRUCTION HVAC HEATING, VENTILATING AND
APVD
ADDL ADDITIONAL EXT EXTERIOR MO MANUAL OPERABLE, MASONRY OPENING PP POWER POLE
S THE PROPERTY OF
CONT CONTINUED, CONTINUOUS, CONTINUATION AIR CONDITIONING MP METAL PANEL P-P PUSH-PULL
LL.
ADJ ADJACENT
CONTR CONTRACTOR
ON OF CH2M HI
°F DEGREE FAHRENHEIT HWL HIGH WATER LEVEL MPU MULTIPURPOSE UNIT PPL POLYPROPYLENE LINED
ADW DRY WEATHER AVERAGE
ew
COORD COORDINATE
QC Revi
AFD ADJUSTABLE FREQUENCY DRIVE FACP FIRE ALARM CONTROL PANEL MS MANUFACTURER'S STANDARD PR PAIR
COP COPPER IC INTERRUPTING CAPACITY
AFF ABOVE FINISHED FLOOR FB FLAT BAR MSC MANUFACTURER SUPPLIED CABLE PRC POINT OF REVERSE CURVE
CP CENTER PIVOT ID INDUCED DRAFT, INSIDE DIAMETER PRCST PRECAST
AFG ABOVE FINISHED GRADE F, FU FUSE MSR GROUPED MOTOR CONTROL
CP-X CONTROL PANEL NO. X IE INVERT ELEVATION
ZATI
CE,I
F, FX FIXED MT MOUNT PREFAB PREFABRICATION
AG ACOUSTICAL, ACOUSTICAL GLASS,
CPLG COUPLING FAP FIRE ALARM PANEL I.F. INSIDE FACE
TTEN AUTHORI
PRES PRESSURE
ONAL SERVI
AIR GAP (FIXED) MTD MOUNTED
ON
CPRSR COMPRESSOR FC FLEXIBLE CONDUIT IG INSULATING, INSULATING GLASS PRI PRIMARY
SI
MTG MOUNTING
CHK
AGGR AGGREGATE
CPT CONTROL POWER TRANFORMER, CARPET IN INCH
REVI
FCA FLANGED COUPLING ADAPTER PRM PERMANENT REFERENCED MARKER
AHR ANCHOR MTS MANUAL TRANSFER SWITCH
CPVC CHLORINATED PVC FCL2 FREE CHLORINE RESIDUAL INCAND INCANDESCENT PROJ PROJECTION
THOUT THE W RI
CR CONTROL RELAY FCO FLOOR CLEANOUT INFL PROP PROPERTY
STEEL CONSTRUCTION MU MULCHING
CRS COLD ROLLED STEEL FCTY FACTORY INJS INJECTIONS
PS PLASTIC SHEET, POLYCARBONATE SHEET
AJ ADJUSTABLE MV MERCURY VAPOR
CRS CONSTRUCTION ROAD STABILIZATION FD FLOOR DRAIN INST INSTANTANEOUS PAINT SYSTEM
PS
AL ALUMINUM MWS MAXIMUM WATER SURFACE
CT CERAMIC TILE FDN FOUNDATION INSTM INSTRUMENT, INSTRUMENTATION
PSF POUNDS PER SQUARE FOOT
ALKY ALKALINITY
CT CURRENT TRANSFORMER INSUL INSULATION N NORTH, NEUTRAL
DR
CTR CENTER IP INLET PROTECTION, INSTRUMENTATION PANEL NA NON-AUTOMATIC
FF FINISHED FLOOR
N,AS AN I
AMRD ACOUSTICAL METAL ROOF DECKING PT POINT OF TANGENCY
B CTRD CENTERED IRRIG IRRIGATION NC NORMALLY CLOSED
E
FG FINISH GRADE, FLOAT GLASS
J.OSOSKI
ANDZ ANODIZE PT POTENTIAL TRANSFORMER
CTSK COUNTERSUNK FH FLAT HEAD ITG INSULATED TEMPERED GLASS NEUT NEUTRAL
APPROX APPROXIMATE PT PRESSURE TREATED
NCORPORATED HEREI
CU CUBIC FHY ITX ISOLATION TRANSFORMER
FIRE HYDRANT NG NATURAL GAS PTD PAPER TOWEL DISPENSER
APVD APPROVED
DATE
CU FT CUBIC FOOT FIG FIGURE IU INTAKE UNIT NGVD NATIONAL GEODETIC VERTICAL DATUM
ARCH ARCHITECTURAL PTN PARTITION
CU IN CUBIC INCH FL FLOW LINE IW IRRIGATION WELL NIC NOT IN CONTRACT
AR ANALOG RELAY PV PLUG VALVE
CUH COPPER TUBING, HARD DRAWN FLG FLANGE N.O. NORMALLY OPEN
AS AS SELECTED PVC POLYVINYL CHLORIDE
DSGN
JALOUSIE
NO.
CV CHECK VALVE FL FLOOR NO., # NUMBER
ASSY ASSEMBLY PVI POINT OF VERTICAL INTERSECTION
JA JAL-AWNING
N W HOLE OR I
CWR CABINET DOOR MOUNTED FLEX FLEXIBLE NOM NOMINAL PVMT PAVEMENT
GNS I
ATS AUTOMATIC TRANSFER SWITCH JB
J JUNCTION BOX
WASTE RECEPTACLE FLH FLAT HEAD NP NON-PROTECTED
AUTO AUTOMATIC JANITOR PVT POINT OF VERTICAL TANGENCY
JAN
S NOT TO BE USED,I
AVG AVERAGE JT JOINT
FNSH FINISH NTS NOT TO SCALE
CUT
AWW WET WEATHER AVERAGE QMM MAXIMUM 30 DAY FLOW
FOB FLAT ON BOTTOM K KEY GROUP, KEY INTERLOCK
QPI PEAK INSTANTANEOUS FLOW
TY
@ AT D DEEP, DRAIN
NEW HAVEN,CONNECTI
O2
CONTROL AUTHORI
FOT KIP THOUSAND POUNDS
d PENNY NAIL SIZE QPP PEAK PUMPING FLOW
O TO O OUT TO OUT
B BELL FP FIELD PANEL KIT KITCHEN QT
DA DUAL ACTION QUARRY TILE
OA OVERALL, ODOROUS AIR
BAL BALANCE FPM FEET PER MINUTE K-PL KICKPLATE
DAS DATA ACQUISTION SYSTEM OC ON CENTER
LL AND I
BETW BETWEEN FR FORWARD REVERSE KITCHEN SINK
DBA DEFORMED BAR ANCHOR KSK R RISER
BF BLIND FLANGE, BOTTOM FACE OC OPEN-CLOSE (O)
FRP FIBERGLASS REINFORCED PLASTIC KV KILOVOLTS R OR RAD
DBL DOUBLE RADIUS
OCA OPEN-CLOSE-AUTO
CH2M HI
BFV BUTTERFLY VALVE FSHS FOLDING SHOWER SEAT KILOVOLT AMPERES RA RETURN AIR
DC DIRECT CURRENT KVA
BL BASELINE OCR OPEN-CLOSE-REMOTE
FT FOOT OR FEET
THI
KVAR KILOVOLT AMPERES REACTIVE RC REINFORCED CONCRETE
DEG DEGREE OD OUTSIDE DIAMETER, OVERFLOW DRAIN
BFP BACKFLOW PREVENTER FTG FOOTING KILOWATT RCP REINFORCED CONCRETE PIPE
DET DETAIL KW
O.F. OUTSIDE FACE
ON
DIR DIRECTION OPER OPERATOR
BOT BOTTOM GALV GALVANIZED LD COMBINATION LOUVER/DAMPER
DISCH DISCHARGE REFR REFRIGERATE, REFRIGERANT
ONS
BRKR BREAKER GCMU GLAZED CONCRETE LF LINEAR FEET
DOL DIRECT-ON-LINE RESIL RESILIENT
OSC OPEN-STOP-CLOSE
ON
BSP BLACK STEEL PIPE MASONRY UNITS LG LONG
RFS ROLL-UP FIRE SHUTTER
DP, DPNL DISTRIBUTION PANEL OSD OPEN SITE DRAIN
ATI
BV BALL VALVE, BLOCK VENT LH LEFT HAND
GENERAL
BVC BEGINNING OF VERTICAL CURVE GFI GROUND FAULT INTERRUPTER LHR LEFT HAND REVERSE
OZ RH RODHOLE
DS DOWNSPOUT OUNCE
ABBREVI
GFR GROUND FAULT RELAY LLH LONG LEG HORIZONTAL
RHR RIGHT HAND REVERSE
DWG DRAWING
C CONDUIT, CASEMENT GH GREENHOUSE LLV LONG LEG VERTICAL P PROJECTED
RL RAIN LEADER
DWL DOWEL
°C DEGREE CELSIUS GL GLASS LNTL LINTEL P PILASTER, PIPE RLS RUBBER LINED STEEL
DELTA
C TO C CENTER TO CENTER GPD GALLONS PER DAY LONG LONGITUDINAL PAVT PAVER TILE RM ROOM
CAB CABINET GPH GALLONS PER HOUR LOS LOCK-OUT STOP PUSHBUTTON PB PUSHBUTTON SWITCH RO ROUGH OPENING
CB CATCH BASIN, CIRCUIT BREAKER GPM GALLONS PER MINUTE LP LIGHT POLE, LIGHTING PANEL, LOCAL PANEL PC POINT OF CURVE, PHOTOCELL ROL RAISE-OFF-LOWER
CC CENTER OF CIRCLE E EAST, EMPTY GPS GLOBAL POSITION SYSTEM LPT LOW POINT PC PRECAST CONCRETE PANEL RPM REVOLUTIONS PER MINUTE
CC CONTROL CABLE EA EACH, EXHAUST AIR GRTG GRATING LR LATCHING RELAY PCCP PRECAST CONCRETE CYLINDER PIPE
RR RIPRAP
CCP CENTRAL CONTROL PANEL EB, EBCT EMPTY BED CONTACT TIME GSB GYPSUM SOFFIT BOARD LR LOCAL-REMOTE PCV PRESSURE CONTROL VALVE
CCS CENTRAL CONTROL SYSTEM ECC ECCENTRIC GSP GALVANIZED STEEL PIPE LR LONG RADIUS PE PLAIN END
D CDF CONTROLLED DENSITY FILL EE EMERGENCY EYEWASH GV GATE VALVE LS LABORATORY SINK PED PEDESTAL, PEDESTRIAN
CE CONSTRUCTION ENTRANCE EDF EGG-SHAPED DIGESTER FACILITY GVL GRAVEL LT LEFT
CFM CUBIC FEET PER MINUTE EF EACH FACE, EXHAUST FAN GWB GYPSUM WALLBOARD LTG, LTS LIGHTS OR LIGHTING GENERAL NOTES:
CFS CUBIC FEET PER SECOND EFF EFFICIENCY, EFFICIENT LTX LIGHTING TRANSFORMER
GYP GYPSUM
1. THIS IS A STANDARD LEGEND SHEET.
CHEM CHEMICAL EFL EFFLUENT LWL LOW WATER LEVEL
H HIGH, HORN OR HOWLER THEREFORE, NOT ALL OF THE INFORMATION VERIFY SCALE
CHKD CHECKERED EIFS EXTERIOR INSULATION AND FINISH SYSTEM
H2S HYDROGEN SULFIDE SHOWN MAY BE USED ON THIS PROJECT. BAR IS ONE INCH ON
CI CAST IRON EL ELEVATION MA MANUAL-AUTO ORIGINAL DRAWING.
H.A.S. HEADED ANCHOR STUD
MI
MAS MASONRY 0 1"
CIP CAST IRON PIPE, CAST IN PLACE ELB ELBOW 2. CONTACT ENGINEER FOR ABBREVIATIONS
HC HOLLOW CORE WOOD
ELC ELECTRICAL LOAD CENTER MATL MATERIAL USED BUT NOT SHOWN ON THIS DRAWING. DATE NOVEMBER 2016
PRELI
CIP CULVERT INLET PROTECTION
HCL HYDROCHLORIC ACID
CISP CAST IRON SOIL PIPE ELEC ELECTRIC, ELECTRICAL MAX MAXIMUM PROJ 664626
HDNR HARDENER
CJ CONSTRUCTION JOINT ENGR ENGINEER MB MACHINE BOLT DWG
HDNS HARDNESS 300-G-002
CKT CIRCUIT EOP EDGE OF PAVEMENT MC MASONRY CLEARANCE
HDR HEADER SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/GEN/Dlv/300-G-002_664626.dgn
FILENAME:300-G-002_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:17 AM
1 2 3 4 5 6
GHTS RESERVED.
ABBREVIATIONS TG TEMPERED SECTION / DETAIL DESIGNATIONS DRAWING NUMBER DESIGNATION
TH TOP-HINGED
THD THREAD
RRUB RADIAL RUBBER
THK THICKNESS DRAWING NUMBER
RS RIGID STEEL
THRU THROUGH
100-S-201
LL 2016. ALL RI
RST REINFORCING STEEL ON DRAWING WHERE SECTION
SECTION (LETTER) OR
RT RIGHT TJB TERMINAL JUNCTION BOX OR DETAIL IS TAKEN:
DETAIL (NUMERAL)
TL TEFLON LINED PIPE
RTN RETURN DESIGNATION DRAWING NUMBER
REGENERATIVE THERMAL OXIDIZER T.O. TIME TO OPEN, TOP OF
RTO A 1 WHERE SHOWN
TOAE TIME OPEN AFTER ENERGIZATION
c CH2M HI
RUB RUBBER
65-S-301
TOC TOP OF CONCRETE
er
RUBC RUBBER CUSHIONED FLOORING
SEQUENTIAL NUMBER
APVD
Seal
A
RUBS RUBBER ESD CONTROL FLOORING TOC TOP OF CURB DRAWING NUMBER
R/W RIGHT OF WAY (REPLACED WITH A LINE
TOD TIME ON DELAY, TOP OF DUCT
IF TAKEN AND SHOWN SHEET TYPE
BY
TOTAL OXYGEN DEMAND
ON SAME SHEET) 0 GENERAL, DIAGRAMS, SCHEMATICS
S I-BEAM
TOF TOP OF FOOTING 1 DEMOLITION DRAWINGS
S SLOPE, SOUTH, SWITCH
TOG TOP OF GROUT, TOP OF GRATE SECTION 2 PLANS
SA SUPPLY AIR B 3 SECTIONS AND OR ELEVATIONS
APVD
T.O.P. TOP OF PARAPET SCALE
S THE PROPERTY OF
SATC SUSPENDED ACCUSTICAL TILE CEILING ON DRAWING WHERE SECTION 4 LARGE SCALED VIEWS
LL.
TOS TOP OF SLAB 5 DETAILS
65-S-201 IS SHOWN:
SB SEDIMENT BASIN
ON OF CH2M HI
TOW TOP OF WALL 6 SCHEDULES
ew
SC SHOWER CURTAIN, SOLID CORE WOOD DRAWING NUMBER(S)
QC Revi
TP TURNING POINT
SCADA SUPERVISORY CONTROL AND DATA ACQUISITION WHERE TAKEN
TR TRANSOM, TRUSS
SCC SOLID CORE DISCIPLINE
TRANS TRANSFORMER, TRANSITION
ZATI
SCFM STANDARD CUBIC FEED PER MINUTE G GENERAL
CE,I
SCHED SCHEDULE
TRANSV TRANSVERSE
DETAIL C CIVIL
TTEN AUTHORI
ONAL SERVI
TRD TREAD 2 L EROSION CONTROL
ON
SCU SPEED CONTROL UNIT SCALE ON DRAWING WHERE DETAIL
TS TEMPORARY SEEDING, TUBE STEEL S STRUCTURAL
SI
CHK
IS SHOWN:
REVI
SDP SUB-DISTRIBUTION PANEL A ARCHITECTURAL
TSHT THRESHOLD 65-S-201
F FIRE PROTECTION
SDWK SIDEWALK DRAWING NUMBER(S)
Z BRYAN
TSS P PLUMBING
WHERE TAKEN
THOUT THE W RI
SEC SECONDARY TOP OF STEEL
TST D PROCESS
SECT SECTION TTC TELEPHONE TERMINAL CABINET Y PIPING
DR
SH SHEET FACILITY
N,AS AN I
TX TRANSFORMER SCALE REFERENCE (eg: ELEVATIONS)
B SHA SURFACE HARDENING AGENT 100 - UNION PUMP STATOIN
E
J.OSOSKI
TYP TYPICAL
200 - EAST STREET PUMP STATION
SHS SOLIDS HANDLING SYSTEM
300 - BOULEVARD PUMP STATION
NCORPORATED HEREI
SIM SIMILAR
UON UNLESS OTHERWISE NOTED
DATE
SK SINK SECTION CALLOUT WHERE SECTION
UNO UNLESS NOTED OTHERWISE
SLR SEALER A IS ON THE SAME SHEET AND CUT
UPS UNINTERRUPTIBLE POWER SUPPLY
SMLS SEAMLESS EPOXY EXTENDS TO A FIXED LIMIT
USB UNIT SUBSTATION
DSGN
NO.
SOI SPRAY- ON INSULATION UVR UNDER VOLTAGE RELAY
N W HOLE OR I
SOLN SOLUTION
GNS I
SP SPACE OR SPACES, V VENT, VALVE
ON
GNHW PCA LONG TERM CONTROL PLAN
SECTION CALLOUT WHERE SECTION
S NOT TO BE USED,I
IS ON ANOTHER SHEET AND CUT
SPD SUMP PUMP DISCHARGE VC VERTICAL CURVE
EXTENDS THROUGHOUT ENTIRE SHEET
CUT
65-S-301 65-S-301
SPG SPACING VCP VITRIFIED CLAY PIPE
TY
NEW HAVEN,CONNECTI
SPLY SUPPLY VCT
CONTROL AUTHORI
SQ SQUARE VEL VELOCITY
SQ FT SQUARE FOOT, FEET VERT VERTICAL
VHC VOLATILE HYDROCARBONS 1 GRID LINE INDICATOR
LL AND I
SQ IN SQUARE INCH
SR SHORT RADIUS VIB VIBRATION
CH2M HI
SST STAINLESS STEEL VIN VINYL
1. PROJECT ELEVATIONS ARE BASED ON NAVD 88. EXISTING ELEVATIONS ARE
THI
SSC SUPERVISORY SET POINT CONTROL VINT, VT VINYL TILE 1 KEYNOTE NUMBER BASED ON NGVD 29. EXISTING DRAWINGS WERE USED AS BACKGROUNDS FOR
EXISTING BUILDINGS/STRUCTURES. EXISTING ELEVATIONS HAVE BEEN
ST STORM DRAIN VP VERTICAL PIVOTED
ON
STRUCT STRUCTURE
SUBFL SUBFLOOR
ONS AND
W/ WITH
GENERAL LEGEND
SV SOLENOID VALVE
WC WATER COLUMN
SVIN SHEET VINYL
ON
WEASTRIP WEATHERSTRIP
SWBD SWITCHBOARD
WG WIRE, WIRE GLASS DESIGN DETAIL DESIGNATION
GENERAL
SYMM SYMMETRICAL
ATI
WHD WATTHOUR DEMAND METER
ABBREVI
T/ TOP OF WR WASTE RECEPTACLE DESIGN DETAIL
T&B TOP AND BOTTOM WRB
WR WATER RESISTANT GWB DESIGNATION 1234-567
WS WATER SURFACE, WATERSTOP, WELDED STEEL (NUMERAL)
T&G TONGUE AND GROOVE
WWF WELDED WIRE FABRIC SHOWN ON DESIGN
TA TRANSFER AIR
DETAIL DRAWING(S)
TAN TANGENT WWPH WET WEATHER PEAK HOUR
TB TERMINAL BOARD
NOTES:
TBG TUBING
TC TIME TO CLOSE 1. ALL DESIGN DETAILS ARE TYPICAL AND MUST BE USED IF DESIGN
D TC TURBIDITY CURTAIN DETAIL DESIGNATION IS NOT SHOWN
TCAD TIME CLOSE AFTER DE-ENERGIZATION
2. THE TERM STANDARD DETAIL, OR A FORM OF IT, IS SYNONYMOUS WITH DESIGN DETAIL.
TCAE TIME CLOSE AFTER ENERGIZATION THE DESIGN DETAILS REPRESENT THE CHARACTER AND NATURE OF THE WORK
TDH TOTAL DYNAMIC HEAD REQUIRED THROUGHOUT THE PROJECT. ALL ASSOCIATED WORK SHALL BE IN
TDR TIME DELAY RELAY ACCORDANCE WITH THE DESIGN DETAILS SHOWN WHETHER THE DETAILS ARE
TECH TECHNICAL
SPECIFICALLY REFERENCED OR NOT. GENERAL NOTES: VERIFY SCALE
MI
TEMP TEMPORARY, TEMPERATURE 0 1"
THEREFORE, NOT ALL OF THE INFORMATION
TF TOP FACE SHOWN MAY BE USED ON THIS PROJECT. DATE NOVEMBER 2016
PRELI
TFG TEMPERED FLOAT GLASS PROJ 664626
2. CONTACT ENGINEER FOR ABBREVIATIONS
USED BUT NOT SHOWN ON THIS DRAWING. DWG 300-G-003
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/GEN/Dlv/300-G-003_664626.dgn
FILENAME:300-G-003_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:17 AM
1 2 3 4 5 6
GHTS RESERVED.
INSTRUMENT IDENTIFICATION LINE LEGEND ABBREVIATIONS & LETTER SYMBOLS
INSTRUMENT IDENTIFICATION LETTERS TABLE
PRIMARY PROCESS
AC ALTERNATING CURRENT
FIRST-LETTER SUCCEEDING-LETTERS (CLOSED CONDUIT,
PARALLELING LINES AM AUTO-MANUAL
DASHED LINE INDICATES
LL 2016. ALL RI
PROCESS OR READOUT OR READOUT OR READOUT OR CL2 etc. CHLORINE (TYPICAL: USE STANDARD CHEMICAL
ALTERNATE FLOW STREAM)
LETTER INITIATING VARIABLE MODIFIER PASSIVE FUNCTION PASSIVE FUNCTION PASSIVE FUNCTION ELEMENT ABBREVIATIONS)
EXAMPLE SYMBOLS (2)
A ANALYSIS (+) ALARM SECONDARY PROCESS COD CHEMICAL OXYGEN DEMAND
BYPASS PROCESS CP-X CONTROL PANEL NO. X (X = FACILITY NUMBER)
B BURNER, COMBUSTION USER'S CHOICE (*) USER'S CHOICE (*) USER'S CHOICE (*)
DC DIRECT CURRENT
c CH2M HI
(A)
C USER'S CHOICE (*) CONTROL DO DISSOLVED OXYGEN
er
PROCESS (OPEN CHANNEL)
APVD
Seal
A D DENSITY (S.G.) DIFFERENTIAL FCL2 FREE CHLORINE RESIDUAL
CLARIFYING ABBREVIATIONS (A) TOTAL OF 2 SIGNALS FOS FAST-OFF-SLOW
E VOLTAGE PRIMARY ELEMENT, ANALOG SIGNAL
FOSA FAST-OFF-SLOW-AUTO
FIRST LETTER(S) SENSOR (4 TO 20 mAdc, ETC.)
BY
FOSR FAST-OFF-SLOW-REMOTE
BB
DISCRETE FP-W-X FIELD PANEL NO. WX (W = UNIT PROCESS NUMBER
SUCCEEDING LETTER(S) F FLOW RATE RATIO
FIT (ON/OFF, ETC.) X = PANEL NUMBER)
(FRACTION) CONNECTING LINES
FR FORWARD-REVERSE
UP-LL-UU
PNEUMATIC SIGNAL
APVD
G USER'S CHOICE (*) GLASS, GAUGE GATE HOA HAND-OFF-AUTO
S THE PROPERTY OF
VIEWING DEVICE FILLED SYSTEM SIGNAL HOR HAND-OFF-REMOTE
LL.
UNIT NUMBER
ISR INTRINSICALLY SAFE RELAY
ON OF CH2M HI
H HAND (MANUAL) HIGH HYDRAULIC SYSTEM SIGNAL
ew
LEL LOWER EXPLOSIVE LIMIT
QC Revi
I CURRENT (ELECTRICAL) INDICATE DATA LINK LOS LOCKOUT STOP
LR LOCAL-REMOTE
J POWER SCAN BUILDING OR
LOOP NUMBER MA MANUAL-AUTO
FACILITY BOUNDARY MC MODULATE-CLOSE
ZATI
CE,I
K TIME, TIME SCHEDULE TIME RATE CONTROL STATION
OF CHANGE PACKAGE SYSTEM NON-CONNECTING LINES MCC-X MOTOR CONTROL CENTER NO. X
TTEN AUTHORI
ONAL SERVI
UNIT PROCESS
EQUIPMENT MSC MANUFACTURER SUPPLIED CABLE
ON
NUMBER L LEVEL LIGHT (PILOT) LOW NC NORMALLY CLOSED
SI
CHK
REVI
M MOTION MOMENTARY MIDDLE, INTERMEDIATE SIMILAR PROCESS NO NORMALLY OPEN
OC OPEN-CLOSE(D)
THOUT THE W RI
O USER'S CHOICE (*) ORIFICE, RESTRICTION OCR OPEN-CLOSE-REMOTE
OO ON-OFF
P PRESSURE, VACUUM POINT (TEST)
OOA ON-OFF-AUTO
CONNECTION
OOR ON-OFF-REMOTE
Q QUANTITY INTEGRATE, ORP OXIDATION REDUCTION POTENTIAL
DR
R RADIATION RECORD OR PRINT PLC PROGRAMMABLE LOGIC CONTROLLER
N,AS AN I
B RIO REMOTE I/O UNIT
E
S SPEED, FREQUENCY SAFETY SWITCH
J.OSOSKI
RTU-X REMOTE TELEMETRY UNIT NO. X
ANALOG INPUT T TEMPERATURE TRANSMIT S A PROCESS INTERFACE SOF SLOW-OFF-FAST
NCORPORATED HEREI
U MULTI VARIABLE MULTI FUNCTION MULTI FUNCTION MULTI FUNCTION SS START-STOP
DATE
ANALOG OUTPUT
TCL2 TOTAL CHLORINE RESIDUAL
V VIBRATION, VALVE, DAMPER,
MECHANICAL ANALYSIS LOUVER TOC TOTAL ORGANIC CARBON
DISCRETE INPUT A D SIGNAL INTERFACE
X TOD TOTAL OXYGEN DEMAND
DSGN
NO.
W WEIGHT, FORCE WELL TURB TURBIDITY
DISCRETE OUTPUT
X X UNCLASSIFIED (*) X AXIS UNCLASSIFIED (*) UNCLASSIFIED (*) UNCLASSIFIED (*) VHC VOLATILE HYDROCARBONS
N W HOLE OR I
VIB VIBRATION
GNS I
Y EVENT, STATE Y AXIS RELAY, COMPUTE, A INTERFACE LETTER
ON
GNHW PCA LONG TERM CONTROL PLAN
D DESTINATION DRAWING NO.
S NOT TO BE USED,I
UNCLASSIFIED FINAL S SOURCE DRAWING NO.
CUT
CONTROL ELEMENT
TY
NEW HAVEN,CONNECTI
INTERFACE TO
(+) WHEN USED, EXPLANATION IS SHOWN ADJACENT TO INSTRUMENT SYMBOL. SEE ABBREVIATIONS AND LETTER SYMBOLS.
LL AND I
OR FROM PROCESS
(*) WHEN USED, DEFINE THE MEANING HERE FOR THE PROJECT.
EXTERNAL TO PROJECT
CH2M HI
GENERAL INSTRUMENT OR HAND SWITCHES AND
THI
PROCESS OR SIGNAL
FUNCTIONAL SYMBOLS INDICATING LIGHTS N LINE CONTINUATION N
C OO
FIELD MOUNTED YL ON AND OFF EVENT
LIGHTS
REAR-OF-PANEL
ON AND CONTROL
MOUNTED (OPERATOR
INACCESSIBLE) ON-OFF HAND SWITCH,
OO
SELF CONTAINED VALVE & GENERAL NOTES
ON
MAINTAINED CONTACT
HS SWITCH (CONTROLLED
PANEL MOUNTED EQUIPMENT TAG NUMBERS
LEGEND -SHEET 1
ACCESSIBLE)
AFTER POWER FAILURE). D-UP-LL-UU ASTERISK ( ) ARE TO BE PROVIDED AS PART OF A
PACKAGE SYSTEM.
ON
SS STOP-START HAND SWITCH
MCC MOUNTED 2. COMPONENTS AND PANELS SHOWN WITH A DOUBLE
GENERAL
SWITCHES (CONTROLLED AVRV AIR AND VACUUM RELEASE VALVE
DIVISION 26, ELECTRICAL.
DEVICE WILL NOT RESTART E EJECTOR
ON RETURN OF POWER G GATE
NSTRUM ENTATI
3. THIS IS A STANDARD LEGEND. THEREFORE, NOT ALL OF
AFTER POWER FAILURE). M MECHANICAL EQUIPMENT
THIS INFORMATION MAY BE USED ON THE PROJECT.
P PUMP
T TANK
LL LOOP NUMBER
UU UNIT NUMBER
I
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 300-G-005
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/GEN/Dlv/300-G-005_664626.dgn
FILENAME:300-G-005_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:24 AM
1 2 3 4 5 6
VALVE SYMBOLS
GHTS RESERVED.
MISCELLANEOUS SYMBOLS PUMP AND COMPRESSOR SYMBOLS
GATE PINCH PRESSURE RELIEF
CENTRIFUGAL PROGESSING
K AIR AND/OR PISTON PUMP
FFLCPLLLX PUMP (DRY PIT) CAVITY PUMP
VACUUM RELEASE XX
LL 2016. ALL RI
KNIFE GATE NEEDLE V PANEL CONTINUED XX
XX
VENT TO ON SAME OR OTHER
REGULATED SIDE ATMOSPHERE
DRAWING SUBMERSIBLE
BUTTERFLY SWING CHECK CENTRIFUGAL WET PIT COMPRESSOR
PRESSURE CONTROL PUMP OR TURBINE PUMP (CENTRIFUGAL) SUMP PUMP
XX
c CH2M HI
XX
GLOBE BALL CHECK AIR GAP
er
XX
APVD
PANEL OUTLINE RECIPROCATING OR
Seal
A PRESSURE REGULATION COMPRESSOR
PANEL NAME METERING PUMP
BACKFLOW (CLAY-TYPE) (PISTON)
BALL (POSITIVE DISPLACEMENT) XX
PREVENTER 120V 120 VOLT,
XX
BY
MULTI-PORT VALVE 60 HZ POWER
V T DRIP TRAP
(GATE VALVE SHOWN. FOR
VEE-BALL ROTARY
OTHER VALVE TYPES, PERISTALLIC
480V 480 VOLT, BLOWER OR FAN
APPROPRIATE VALVE PUMP
PIG INSERT POINT 60 HZ POWER DIAPHRAGM PUMP (CENTRIFUGAL)
SYMBOL SHOWN.) SEAT
APVD
TELESCOPING
SEAT PORT XX
S THE PROPERTY OF
PORTS ARE IMPLIED BY
XX
LL.
ECCENTRIC PLUG INDICATED FLOW PATTERN. PIG CATCH POINT
ON OF CH2M HI
XX AIR SET GEAR PUMP OR BLOWER
ew
S SAMPLE EJECTOR
(POSITIVE DISPLACEMENT)
QC Revi
XX = SUPPLY PRESSURE
DIAPHRAGM ANGLE GATE IN PSIG. XX
SELF CONTAINED
A
MUD AIR SUPPLY
PLUG
ZATI
XX: AS ADJUSTABLE SPEED
CE,I
CS-1 CONSTANT SPEED (SINGLE SPEED)
TTEN AUTHORI
ONAL SERVI
CS-2 CONSTANT SPEED (TWO SPEED)
ON
AP AIR PURGE SET
SI
CHK
REVI
RECEPTACLE
GATE SYMBOLS
THOUT THE W RI
FABRICATED RUPTURE DISK
SLUICE
SLIDE
STOP LOG
(VACUUM) FLOW STREAM IDENTIFICATION
S SEAL WATER SET
BUTTERFLY FLAP SHEAR RUPTURE DISK ALP AIR LOW PRESSURE PROCESS S SANITARY SEWER (GRAVITY)
DR
N,AS AN I
TV MONITOR ARV ACID RESISTANT VENT SC SUPPLEMENTAL CARBON
B TV
E
J.OSOSKI
FLEXIBLE CONNECTION BD BLOW DOWN SCS SUPPLEMENTAL CARBON SOLUTION
ACTUATOR SYMBOLS
NCORPORATED HEREI
BSD BLENDED SLUDGE SHC SODIUM HYPOCHLORITE
DATE
PNEUMATIC DIAPHRAGM AERATOR TV TV CAMERA
VALVE BYP BYPASS SMD SCUM DECANT
SPRING-OPPOSED, SINGLE MANUAL
POSITIONER
OR DOUBLE ACTING
DSGN
NO.
CA SODIUM HYDROXIDE / CAUSTIC SPD SUMP PUMP DRAIN / DISCHARGE
PNEUMATIC CYLINDER
N W HOLE OR I
RADIO ANTENNA
GNS I
SINGLE OR DOUBLE H HYDRAULIC CO CONDENSATE DRAIN SR SCRUBBER RECIRCULATION
ACTING ACTUATED DIAPHRAGM SEAL
S NOT TO BE USED,I
M DIFFERENTIAL D DRAIN (PLUMBING) SU SULFURIC ACID
ANNULAR DIAPHRAGM SEAL I
CUT
ELECTRIC MOTOR PRESSURE
DR DRAIN (PROCESS) TA TREATED AIR
TY
INTERLOCK, SEE
NEW HAVEN,CONNECTI
CONTROL AUTHORI
CONTROL DIAGRAMS
E/H
COMPOSITE SAMPLER FF FIRE SUPPRESSION FOAM TPSD THICKENED PRIMARY SLUDGE
S ELECTROHYDRAULIC SS
SOLENOID I
FO FUEL OIL TW TEMPERED WATER (POTABLE)
LL AND I
FLAME TRAP TWAS THICKENED WAS
VOICE COMMUNICATION FS FIRE SPRINKLER WATER
NOTE: XX: FO FAIL OPEN
CH2M HI
ON LOSS OF PRIMARY POWER FC FAIL CLOSED POINT
G NATURAL GAS (PROCESS) V VENT
FLP FAIL TO LAST POSITION
THI
(PNEUMATIC, ELECTRICAL, OR
HYDRAULIC)
GTO GRAVITY THICKENER OVERFLOW VR VAPOR RECOVERY
CALIBRATION COLUMN
ON AND CONTROL
TURBINE METER
BLIND FLANGE SCREW CONVEYOR ISD IMPORTED SLUDGE
WAS WASTE ACTIVATED SLUDGE
ON
PIPE CAP LPR LOW PRESSURE RETURN (CONDENSATE)
THERMAL FI
WEIR ROTAMETER
LEGEND -SHEET 2
STRAINER NG NATURAL GAS (PLUMBING)
SUBMERSIBLE MIXER
LEVEL DE
ON
ORFICE PLATE DENSITY METER
(BUBBLER TUBE)
NRCY NITRATE RICH RECYCLE
GENERAL
FLOW TUBE OA ODOROUS AIR
XX
GENERIC
ULTRASONIC OD OVERFLOW ROOF DRAIN
NSTRUM ENTATI
FILTER INTRINSIC SAFETY
FLOWMETER BARRIER/RELAY
OF OVERFLOW
ELECTROMAGNETIC LE
M LEVEL (ULTRASONIC)
FLOWMETER PULSATION
M PE PRIMARY EFFLUENT
DAMPENER
EXPANSION
RAS RETURN ACTIVATED SLUDGE
CHAMBER
D PIPING DESIGNATION
I
SIGHT INDICATOR RBSD RECYCLE BLENDED SLUDGE
RD ROOF DRAIN
SLUDGE
RAS
GRINDER RHG REFRIGERANT HOT GAS
VERIFY SCALE
MI
0 1"
IDENTIFICATION RL REFRIGERANT LIQUID NOTE:
DATE NOVEMBER 2016
PRELI
1. FOR EXISTING CIVIL YARD PIPING FLOW STREAM
RS REFRIGERANT SUCTION IDENTIFICATION, SEE CIVIL LEGEND. PROJ 664626
DWG 300-G-006
RTW RECIRCULATING TEMPERED WATER
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/GEN/Dlv/300-G-006_664626.dgn
FILENAME:300-G-006_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:26 AM
1 2 3 4 5 6
GHTS RESERVED.
GENERAL ARCHITECTURAL NOTES ARCHITECTURAL/STRUCTURAL LEGEND
1. UNLESS OTHERWISE INDICATED, PLAN DIMENSIONS ARE TO COLUMN GRID ON SYMBOL LEGEND
CENTERLINES, NOMINAL SURFACE OF MASONRY, FACE OF STUDS AND FACE OF
CONCRETE WALLS.
A NEW REFERENCE GRID INDICATOR
LL 2016. ALL RI
2. "FLOOR LINE" REFERS TO TOP ON CONCRETE SLABS. FINISH FLOORING IS
INSTALLED ABOVE THE FLOOR LINE. FOR DEPRESSED FLOORS AND CURBS,
SEE STRUCTURAL DRAWINGS. A EXISTING REFERENCE GRID INDICATOR
c CH2M HI
3. REPETITIVE FEATURES ARE NOT DRAWN IN THEIR ENTIRETY AND SHALL BE
COMPLETELY PROVIDED AS IF DRAWN IN FULL.
er
APVD
ROOM NAME ROOM NAME
Seal
A
4. WHERE DOOR IS LOCATED NEAR CORNER OF ROOM AND IS NOT LOCATED BY XX-101 101
ROOM IDENTIFIER
DIMENSION ON PLAN OR DETAILS, DIMENSION SHALL BE 3-INCHES FROM FACE OF OR
STUD (WALL) TO FACE OF ROUGH OPENING. DIMENSION SHALL BE 6" FROM FACE
BY
OF WALL TO EDGE OF ROUGH OPENING AT CONCRETE WALLS, 8" AT CMU WALLS. "XX" = FACILITY DOOR LETTER
INDICATOR
5. AT SOUND INSULATED WALLS, FULL HEIGHT PARTITIONS SHALL BE SEALED BOTH
101A
(IF SHOWN) ROOM NUMBER
SIDES WITH ACOUSTIC SEALANT; TOP, BOTTOM, INTERSECTION, DOOR FRAMES,
XX-
APVD
GLAZED OPENING FRAMES, AND OTHER PENETRATIONS. DOOR IDENTIFIER
S THE PROPERTY OF
LL.
6. LINE OF EXISTING GRADES, AS SHOWN ON THE BUILDING ELEVATIONS AND
ON OF CH2M HI
ew
SECTIONS ARE APPROXIMATE. THEY ARE AT THE BUILDING FACE, OR ON THE
QC Revi
SECTION END EXCEPT AS NOTED.
XXW-1 OR W-1 WINDOW IDENTIFIER
7. VERIFY ALL ROUGH-IN DIMENSIONS FOR EQUIPMENT PROVIDED IN THIS
CONTRACT, OR BY OTHERS.
ZATI
CE,I
8. REFER TO ARCHITECTURAL, STRUCTURAL, MECHANICAL, ELECTRICAL AND XXR-1 OR R-1 RELIGHT IDENTIFIER
TTEN AUTHORI
ONAL SERVI
ON
OTHER CATEGORIES OR DRAWINGS FOR ADDITIONAL NOTES.
SI
CHK
REVI
9. VERIFY SIZE AND LOCATION OF, AND PROVIDE: REQUIRED OPENINGS THROUGH
FLOORS AND WALLS, ACCESS DOORS, FURRING, CURBS, ANCHORS AND
XXL-1 OR L-1 LOUVER IDENTIFIER
THOUT THE W RI
MECHANICAL, ELECTRICAL AND OTHER EQUIPMENT.
DR
N,AS AN I
B SYMBOL LEGEND
E
J.OSOSKI
P-1 PRECAST PANEL IDENTIFIER
NCORPORATED HEREI
GRATING, SPAN DIRECTION INDICATED
DATE
1
EXTERIOR ELEVATION INDICATOR
CHECKERED PLATE XX-A-301
DSGN
NO.
QUANTITY AND
N W HOLE OR I
GROUT A
DIRECTION OF
GNS I
E
POINTERS AS
ON
1
GRANULAR FILL D B INTERIOR ELEVATION INDICATOR
S NOT TO BE USED,I
CUT
EARTH OR FINISH GRADE C
TY
NEW HAVEN,CONNECTI
LL AND I
CMU WALL (PLAN)
CH2M HI
CMU WALL (SECTION)
THI
DIRECTION OF SLOPE DOWN
MASONRY WALL
ACTIVE INACTIVE
ON
XX-
BATT INSULATION
STEEL
ON
F.EXT-X
ALUMINUM
GENERAL
"X" = NUMBER IN SPECIFICATIONS
PLYWOOD
GYPSUM WALLBOARD
CONTROL JOINT
ACOUSTICAL TILE
EXPANSION JOINT
WOOD, ROUGH CONTINUOUS
ARCHI
WOOD, ROUGH NON-CONTINUOUS
D RAILINGS
WOOD, FINISHED
POST
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 300-G-007
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/GEN/Dlv/300-G-007_664626.dgn
FILENAME:300-G-007_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:29 AM
1 2 3 4 5 6
GHTS RESERVED.
PIPE AND FITTING SYMBOLS VALVE SYMBOLS VALVE DESIGNATIONS
DOUBLE LINE SINGLE LINE DOUBLE LINE SINGLE LINE MANUAL VALVES AND CHECK VALVES
SINGLE LINE DOUBLE LINE
LL 2016. ALL RI
EXISTING PIPE REDUCING BUSHING
GATE
K K
NEW PIPE OR
UNION KNIFE GATE
c CH2M HI
V 500
BUTTERFLY OR
er
APVD
EXISTING PIPE TO BE ABANDONED
Seal
A
CAP
GLOBE OR VALVE DESIGNATION
BY
EXISTING PIPE TO BE REMOVED
BALL OR VALVE TYPE, SEE
ANCHOR
SPECIFICATIONS
WELDED JOINT
SEATING PORT
APVD
ELBOW, 90 DEGREE
S THE PROPERTY OF
LL.
ECCENTRIC PLUG OR
GROOVED END JOINT CONTROL VALVES
ON OF CH2M HI
ew
QC Revi
CROSS PLUG OR COCK OR
M
FLANGED JOINT
VALVE FUNCTION
NEEDLE OR
ZATI
CE,I
TEE
MECHANICAL JOINT &
TTEN AUTHORI
ONAL SERVI
ON
PROPRIETARY RESTRAINED JOINT
FV
SI
CHK
DIAPHRAGM OR
ELBOW, 45 DEGREE
REVI
UP-LL-UU
BELL & SPIGOT JOINT (LEADED)
UNIT NUMBER
THOUT THE W RI
LOOP NUMBER
HUB & SPIGOT JOINT SWING CHECK OR
LATERAL
(RUBBER GASKET) UNIT PROCESS NUMBER
DR
GROOVED END ADAPTER FLANGE
N,AS AN I
X = NO. IN SPECS
B
S.CLARK
FLANGED COUPLING ADAPTER S SAMPLE
SELF-CONTAINED REGULATING VALVES
NCORPORATED HEREI
(RESTRAINING SYSTEM BY MFR)
MUD
DATE
RESTRAINED FLANGED
COUPLING ADAPTER SEE 4005-545 PRESSURE RELIEF
DSGN
NO.
PRV-UP-LL-UU
N W HOLE OR I
FLEXIBLE COUPLING AIR AND/OR VACUUM RELEASE
GNS I
REGULATED SIDE
ON
GNHW PCA LONG TERM CONTROL PLAN
S NOT TO BE USED,I
LOOP NUMBER
CUT
REGULATED SIDE
UNIT PROCESS NUMBER
NOTES:
TY
ELASTOMER BELLOWS EXP JOINT
NEW HAVEN,CONNECTI
LL AND I
2. SYMBOLS SHOWN HERE FOR SINGLE LINE FITTINGS ARE GENERIC ONLY. REFER TO PIPING SEATING PORTS ARE IMPLIED BY
INDICATED FLOW PATTERN.
SPECIFICATIONS FOR SPECIFIC END CONNECTIONS FOR SINGLE LINE PIPE AND FITTINGS.
CH2M HI
ELBOW DOWN
3. EXISTING PIPE AND EQUIPMENT IS SHOWN LIGHT-LINED AND/OR SCREENED.
THI
TELESCOPING
NEW PIPING AND EQUIPMENT IS SHOWN HEAVY-LINED.
TEE UP
ON
THE SAME AS SHOWN FOR ADJACENT STRAIGHT RUN OF PIPE.
LATERAL DOWN
CAL
BOULEVARD PUM P STATI
MANUAL 3. LOCATION AND NUMBER OF PIPE HANGERS AND PIPE SUPPORTS SHOWN IS ONLY
PNEUMATIC CYLINDER
APPROXIMATE. CONTRACTOR SHALL DESIGN SUPPORTS AS SPECIFIED.
PROCESS M ECHANI
CONCENTRIC REDUCER
4. ALL JOINTS SHALL BE WATERTIGHT. WALL PIPES SHALL BE USED WHEREVER
ON
S SOLENOID
PIPING PASSES FROM A STRUCTURE TO BACKFILL.
GENERAL
ELECTRIC MOTOR THRUST PROTECTION AS SPECIFIED, UNLESS OTHERWISE NOTED. THRUST PROTECTION
SHALL BE ADEQUATE FOR TEST PRESSURES SPECIFIED.
16" RAS 9. WHERE A GROOVED END COUPLING IS SHOWN, IT SHALL BE THE RIGID JOINT TYPE, UNLESS
OTHERWISE SPECIFIED. WHERE A FLANGED COUPLING ADAPTER IS SHOWN, A STANDARD
FLANGE SHALL BE JOINED TO THE COUPLING ADAPTER.
16" RAS
MI
0 1"
PRELI
PROJ 664626
DWG 300-G-012
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/GEN/Dlv/300-G-012_664626.dgn
FILENAME:300-G-012_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:32 AM
1 2 3 4 5 6
GHTS RESERVED.
ONE-LINE DIAGRAM-1 ONE-LINE DIAGRAM-2 CONTROL DIAGRAM-1 CONTROL DIAGRAM-2
DRAWOUT AIR CIRCUIT BREAKER, LOW VOLTAGE DRAWOUT POWER CIRCUIT BREAKER, MEDIUM VOLTAGE PUSH-BUTTON SWITCH, MOMENTARY CONTACT, CAPACITOR
NORMALLY OPEN
LL 2016. ALL RI
CIRCUIT BREAKER, THERMAL MAGNETIC TRIP SHOWN, NON DRAWOUT FUSED SWITCH, MEDIUM VOLTAGE PUSH-BUTTON SWITCH, MOMENTARY CONTACT, BATTERY
400
3 POLE, UNO NORMALLY CLOSED
CIRCUIT BREAKER, STATIC TRIP UNIT, SENSOR AMP DRAWOUT FUSED SWITCH AND CONTACTOR, MEDIUM PUSH BUTTON SWITCH, MAINTAINED CONTACTS WITH LIMIT SWITCH, NORMALLY OPEN, CLOSES AT END
c CH2M HI
AS AT
or TRIP AND FRAME RATINGS SHOWN, 3 POLE, UNO VOLTAGE MECHANICAL INTERLOCK OF TRAVEL
er
AF AF
APVD
Seal
A
DRAWOUT FUSED SWITCH AND VACUUM CONTACTOR, LIMIT SWITCH, NORMALLY CLOSED, OPENS AT END
MEDIUM VOLTAGE OF TRAVEL
CIRCUIT BREAKER, MAGNETIC TRIP ONLY, TRIP
100/M
BY
RATING SHOWN, 3 POLE, UNO DRAWOUT VACUUM CONTACTOR, MEDIUM VOLTAGE 3 POSITION SELECTOR SWITCH MAINTAINED CONTACT TEMPERATURE SWITCH, OPENS ON TEMPERATURE RISE
CIRCUIT BREAKER WITH CURRENT LIMITING FUSES, MEDIUM VOLTAGE CABLE STRESS CONE TYPE TEMPERATURE SWITCH, CLOSES ON TEMPERATURE RISE
400
400 TERMINATION, OPEN TERMINATOR OR ELBOW
APVD
TRIP AND FUSE RATING INDICATED, 3 POLE, UNO OFF SELECTOR SWITCH - MAINTAINED CONTACT - CHART
S THE PROPERTY OF
HAND REMOTE
IDENTIFIES OPERATION WHEN NEEDED FOR CLARITY:
LL.
FLOAT SWITCH, NORMALLY OPEN, CLOSES ON
ON OF CH2M HI
DESCENDING LEVEL
ew
FUSED SWITCH, SWITCH AND FUSE CURRENT RATING SWITCH - LOAD BREAK, GROUP OPERATED,
POSITION
QC Revi
400 225 MEDIUM VOLTAGE
INDICATED, 3 POLE, UNO
CKT HAND OFF REMOTE X - CLOSED CONTACT
SWITCH, CURRENT RATING INDICATED, 3 POLE, UNO 1 X O O O - OPEN CONTACT FLOAT SWITCH, NORMALLY OPEN, CLOSES ON
100 2 O O X RISING LEVEL
ZATI
CE,I
SWITCH W/ARCING HORNS, MEDIUM VOLTAGE
TTEN AUTHORI
ONAL SERVI
FUSE, CURRENT RATING AND QUANTITY INDICATED
ON
60 (3)
DISCONNECTING FUSE - SOLID MATERIAL, TOGGLE SWITCH, ON-OFF TYPE PRESSURE SWITCH, NORMALLY CLOSED, OPENS ON
SI
CHK
REVI
MEDIUM VOLTAGE RISING PRESSURE
1
ON OFF
THOUT THE W RI
NEMA SIZE INDICATED, FVNR UNO MEDIUM VOLTAGE RISING PRESSURE
SELECTOR SWITCH, ON-OFF TYPE
FUSE - EXPULSION, HOOK STICK OPERATED, FLOW SWITCH, CLOSES ON INCREASED FLOW
SINGLE POLE, MEDIUM VOLTAGE
AFD ELECTRONIC STARTER/SPEED CONTROL
RVSS = REDUCED VOLTAGE SOFT STARTER
FLOW SWITCH, OPENS ON INCREASED FLOW
DR
RVAT = REDUCED VOLTAGE AUTO TRANSFORMER TYPE
N,AS AN I
MUSHROOM HEAD PUSHBUTTON SWITCH NGR NEUTRAL GROUND CURRENT LIMITING RESISTOR
B RVRT = REDUCED VOLTAGE REACTOR TYPE
R.W OOD
TERMINAL BLOCK LUG
NCORPORATED HEREI
INDICATES COLOR
CABLE OR BUS CONNECTION POINT DELTA CONNECTION
DATE
T
TACHOMETER GENERATOR
GEN
K KEY INTERLOCK WYE GROUNDED CONNECTION, SOLID GROUND A INDICATING LIGHT - LETTER INDICATES COLOR
DSGN
A - AMBER G - GREEN S - STROBE
NO.
B - BLUE R - RED
N W HOLE OR I
SURGE ARRESTER (GAP TYPE) WYE NEUTRAL GROUND RESISTOR OR IMPEDANCE GFS GROUND FAULT SENSOR
C - CLEAR W - WHITE
GNS I
R or Z CONNECTION
S NOT TO BE USED,I
CUT
86 RELAY OR DEVICE, FUNCTION NUMBER AS INDICATED M MOTOR STARTER CONTACTOR COIL
TY
NEW HAVEN,CONNECTI
3 AC MOTOR, SQUIRREL CAGE INDUCTION - SEALED CONTACT
LL AND I
G GENERATOR, KW/KVA RATING SHOWN TIME DELAY RELAY, X INDICATES NUMERICAL ORDER
(1) X
IN CIRCUIT
500/625 POTENTIOMETER
SV
CH2M HI
VS BUSHING CURRENT TRANSFORMER, MULTI-RATIO SOLENOID VALVE, X INDICATES NUMERICAL ORDER
800/1200:5 X
AND QUANTITY INDICATED IN CIRCUIT
THI
V ANALOG METER WITH SWITCH - SCALE RANGE SHOWN
(3)
0-600V V = VOLTAGE KW = KILOWATTS CONTACT - NORMALLY OPEN RESISTOR
ON
TIME DELAY RELAY CONTACT, NORMALLY CLOSED,
ON
15 KVA
TIME DELAY RELAY CONTACT, OPENS WHEN DUPLEX RECEPTACLE
480-120/240V
GENERAL
AND PHASE INDICATED TIMED OUT
ELECTRI
SHIELDED ISOLATION TRANSFORMER TRANSFER SWITCH - MEDIUM VOLTAGE RELAY, WITH MECHANICAL LATCH
U
E N TERMINAL BLOCK, REMOTE
480-120V
POTENTIAL TRANSFORMER, VOLTAGE RATING TERMINAL BLOCK, INTERNAL FULLWAVE DIODE BRIDGE (AC TO DC)
AND QUANTITY INDICATED
(3)
FUSED TERMINAL BLOCK
MI
SPD SURGE PROTECTIVE DEVICE THERMOCOUPLE 0 1"
PRELI
PROJ 664626
DWG 300-G-015
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/GEN/Dlv/300-G-015_664626.dgn
FILENAME:300-G-015_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:24 AM
1 2 3 4 5 6
GHTS RESERVED.
POWER SYSTEM PLAN-1 POWER SYSTEM PLAN-2 FIRE ALARM SYSTEM PLAN AND RISER SOUND SYSTEM PLAN AND RISER
100/40
CONNECTION POINT TO EQUIPMENT SPECIFIED. BREAKER, SEPARATELY MOUNTED, CURRENT F FIRE ALARM STATION, MANUAL S SPEAKER, CONE TYPE, RECESSED IN CEILING, SEE
P
RACEWAY, CONDUCTOR,TERMINATION AND CONNECTION RATING INDICATED ARCHITECTURAL DRAWINGS FOR CEILING TYPE
LL 2016. ALL RI
IN THIS DIVISION. (100/40, 100 = FRAME SIZE; 40 = TRIP RATING)
3 POLE FIRE ALARM SYSTEM, AUTOMATIC SMOKE DETECTOR
MCC-A
MAJOR ELECTRICAL COMPONENT OR DEVICE - NAME S SPEAKER, CONE TYPE, WALL MOUNTED
OR IDENTIFYING SYMBOL AS SHOWN. 2
C CONTACTOR, MAGNETIC, NEMA SIZE INDICATED HD FIRE ALARM SYSTEM, AUTOMATIC, HEAT DETECTOR
c CH2M HI
S SPEAKER, CONE TYPE, SURFACE MOUNTED
er
APVD
30
Seal
A
PANELBOARD - SURFACE MOUNTED L LIGHTING CONTACTOR, CURRENT RATING INDICATED F FIRE ALARM BELL
LPXXA V VOLUME CONTROL, WALL MOUNT 5'-0" AFF
2
BY
PANELBOARD LETTER OR NUMBER STARTER, MAGNETIC NEMA SIZE INDICATED F FIRE ALARM HORN
FACILITY NUMBER S INTERIOR PAGING TRUMPET SOUND REPRODUCER
XX
WITH REMOTE AMPLIFIER, SURFACE MOUNTED
LP - LOW VOLTAGE PANEL CONVENIENCE RECEPTACLE - DUPLEX UNLESS NOTED FIRE ALARM HORN/STROBE LIGHT
DP - DISTRIBUTION PANEL 2 OTHERWISE
APVD
S THE PROPERTY OF
WP - WEATHERPROOF C - CLOCK HANGER
LL.
FIRE ALARM STROBE LIGHT M MICROPHONE OUTLET
TL- TWIST LOCK CRE - CORROSION RESISTANT
ON OF CH2M HI
ew
PANELBOARD - FLUSH MOUNTED GFCI- GROUND FAULT CIRCUIT INTERRUPTER
QC Revi
SUBSCRIPT NUMBER AT RECEPTACLE INDICATES CIRCUIT AIR DUCT DETECTOR S SOUND SYSTEM RACEWAY
ZATI
CE,I
240V RECEPTACLE FS FIRE SPRINKLER FLOW SWITCH S COMMUNICATION STATION
TTEN AUTHORI
ONAL SERVI
M MOTOR, SQUIRREL CAGE INDUCTION
ON
CONVENIENCE RECEPTACLE - QUADRUPLEX TS FIRE SPRINKLER TAMPER SWITCH SECURITY SYSTEM PLAN AND RISER
SI
CHK
REVI
THOUT THE W RI
LPXXA HOME RUN - DESTINATION SHOWN DUPLEX CONVENIENCE RECEPTACLE - FLUSH IN FLOOR TELEPHONE SYSTEM PLAN AND RISER CS CONTROL STATION
DS
or EXPOSED CONDUIT AND CONDUCTORS* CONVENIENCE RECEPTACLE, PEDESTAL, DUPLEX TTC TELEPHONE TERMINAL CABINET DOOR SWITCH
DR
EP
N,AS AN I
or CONCEALED CONDUIT AND CONDUCTORS* L20R TELEPHONE RECEPTACLE FLOOR BOX EGRESS PUSHBUTTON
B G
20
R.W OOD
NOTE: RECEPTACLE, SPECIAL PURPOSE-NEMA CONFIGURATION
ALL UNMARKED CONDUIT RUNS CONSIST OF TWO NO. 12, ONE NO. 12 GROUND AND AMPERAGE INDICATED
TELEPHONE RECEPTACLE ELECTRONIC LOCK
NCORPORATED HEREI
CONDUCTORS IN 3/4" CONDUIT. RUNS MARKED WITH CROSSHATCHES INDICATE M = MAGENITIC
T THERMOSTAT
DATE
NUMBER OF NO. 12 CONDUCTORS. CROSSHATCH WITH SUBSCRIPT "G" INDICATES S = STRIKE
GREEN GROUND WIRE. T TELEPHONE SYSTEM RACEWAY
DSGN
NO.
CROSSHATCHES WITH BAR INDICATE NO.10 CONDUCTOR.
G
SIZE CONDUIT ACCORDING TO SPECIFICATIONS COMPUTER SYSTEM (DATA) PLAN AND RISER
N W HOLE OR I
MONITOR
GNS I
AND APPLICABLE CODE.
ELECTRIC UNIT HEATER CTC COMPUTER SYSTEM TERMINAL CABINET
S NOT TO BE USED,I
CUT
ELECTRIC AIR CONDITIONER VIDEO CAMERA
AC (SELF CONTAINED UNIT) PTZ = PAN/TILT/ZOOM
TY
NEW HAVEN,CONNECTI
CONDUIT DOWN COMPUTER NETWORK CONNECTION, FLUSH IN FLOOR
LL AND I
GROUND SYSTEM PLAN
CONDUIT, STUBBED AND CAPPED 1 or 1 LUMINAIRE, SEE SCHEDULE
COMBINED TELEPHONE/COMPUTER SYSTEM
CH2M HI
GROUND ROD
PLAN AND RISER
THI
CONDUIT TERMINATION AT CABLE TRAY 1 LUMINAIRE, SEE SCHEDULE
ON
COMBINATION CLOSED CIRCUIT TELEVISION RECEPTACLE N EQUIPMENT NEUTRAL BUS
XXXX CONCRETE ENCASED DUCT BANK WHERE XXXX IS THE STANDBY LIGHTING UNIT, SURFACE MOUNTED, COMBINATION TELEVISION CABLE RECEPTACLE (TV)
ON
DUCT BANK NAME. SEE CIRCUIT AND RACEWAY SEE SCHEDULE AND DUPLEX CONVENIENCE RECEPTACLE IN TWO GANG
GENERAL
CONCEALED CONDUIT ROUTING AREA XX or EXIT LIGHTS - FILLED SECTION INDICATES LIGHTED FACE, CLOSED CIRCUIT TELEVISION RECEPTACLE, FLOOR BOX
ARROW INDICATES EGRESS DIRECTIONAL INDICATORS,
XX = FIXTURE NUMBER, SEE SCHEDULE
ELECTRI
CONDUIT ROUTING AREA TELEVISION CABLE RECEPTACLE, FLOOR BOX
a or SMALL LETTER SUBSCRIPT AT SWITCH AND LUMINAIRE
2a INDICATES SWITCHING. SUBSCRIPT NUMBER
CABLE TRAY
AT LUMINAIRE INDICATES CIRCUIT
MI
60/40 FUSED DISCONNECT SWITCH, CURRENT RATING INDICATED 0 1"
PRELI
3 POLE MD MOTION DETECTOR
PROJ 664626
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/GEN/Dlv/300-G-016_664626.dgn
FILENAME:300-G-016_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:23 AM
1 2 3 4 5 6
GHTS RESERVED.
ONE LINE PROTECTION RELAYING AND ONE LINE PROTECTION RELAYING AND GENERAL CIRCUIT CONDUCTOR AND CONDUIT IDENTIFICATION
ELEMENTARY DIAGRAMS-1 ELEMENTARY DIAGRAMS-2
52
LL 2016. ALL RI
51 or DEVICE FUNCTION NUMBER INDICATED,
SEE DEVICE TABLE POWER CIRCUIT CALLOUTS MULTICONDUCTOR POWER CABLE CIRCUIT CALLOUTS
DEVICE
FUNCTION DEVICE DESCRIPTION
[P1] [1/2"FLEX, 2#12,#12G] [P24] [1"C,3#8,3#14,1#10G] [PC1] [3/4"C,1 (3C#12,1#12G) TYPE 2]
NO.
CS [P2] [3/4"C,2#12,1#12G] [P25] [1"C,3#8,4#14,1#10G] [PC2] [3/4"C,1 (3C#10,1#10G) TYPE 2]
CONTROL SWITCH TRIP
c CH2M HI
T 21 IMPEDANCE/DISTANCE RELAY [P3] [3/4"C,3#12,1#12G] [P26] [1"C,3#8,5#14,1#10G] [PC3] [1"C,1 (3C#8,1#10G) TYPE 2]
er
APVD
Seal
A CS 25A AUTOMATIC SYNCHRONIZER [P4] [3/4"C,4#12,1#12G] [P27] [1"C,2#6, 1#10G] [PC4] [1 1/4"C,2 (3C#12,1#12G) TYPE 2]
CONTROL SWITCH CLOSE
C
25C SYNCH CHECK RELAY [P5] [3/4"C,5#12,1#12G] [P28] [1"C,3#6, 1#8G] [PC5] [1 1/2"C,2 (3C#10,1#10G) TYPE 2]
BY
43/CS 43-DEVICE FUNCTION NUMBER, [P6] [3/4"C,6#12,1#12G] [P29] [1"C,3#6, 2#14,1#8G] [PC1A] [3/4"C,1 (2C#12,1#12G) TYPE 2]
27 UNDERVOLTAGE RELAY
SEE DEVICE TABLE [P7] [3/4"C,7#12,1#12G] [P30] [1"C,3#6, 3#14,1#8G] [PC2A] [3/4"C,1 (2C#10,1#10G) TYPE 2]
32 REVERSE POWER RELAY
[P8] [3/4"C,8#12,1#12G] [P31] [1"C,3#6, 4#14,1#8G]
VS VOLTMETER SWITCH
40 GENERATOR LOSS OF EXCITATION RELAY [P9] [3/4"C,3#12,2#14,1#12G] [P32] [1"C,3#6, 5#14,1#8G]
APVD
S THE PROPERTY OF
[P10] [3/4"C,3#12,3#14,1#12G] [P33] [1"C,3#4,1#8G]
LL.
AS AMMETER SWITCH 43CSE AUTOMATIC POWER TRANSFER AND LOAD
ON OF CH2M HI
CONTROL MODE SEL. SWITCH [P11] [3/4"C,3#12,4#14,1#12G] [P34] [1 1/4"C,3#4,3#14,1#8G]
ew
QC Revi
[P12] [3/4"C,3#12,5#14,1#12G] [P35] [1 1/4"C,3#4,5#14,1#8G] EMPTY CONDUIT
A INDICATING LAMP-SWITCHBOARD TYPE 43CSX MODE SEL. SWITCH
[P13] [3/4"C,3#12,6#14,1#12G] [P36] [1 1/4"C,3#3, 1#6G]
INDICATING LAMP LENS COLORS [EC-1] [3/4"C,WITH PULL STRING]
46 GENERATOR CURRENT UNBALANCE RELAY [P14] [3/4"C,3#12,7#14,1#12G] [P37] [1 1/4"C,3#3, 3#14,1#6G]
INDICATED AS FOLLOWS:
ZATI
CE,I
[EC-2] [1"C,WITH PULL STRING]
49 THERMAL RELAY [P15] [3/4"C,2#10,1#10G] [P38] [1 1/4"C,3#2, 1#6G]
TTEN AUTHORI
ONAL SERVI
A - AMBER R - RED [EC-3] [1 1/4"C,WITH PULL STRING]
ON
B - BLUE W - WHITE 50GS INSTANTANEOUS OVERCURRENT DEVICE, [P16] [3/4"C,3#10,1#10G] [P39] [1 1/4"C,3#1, 1#6G]
SI
[EC-4] [1 1/2"C,WITH PULL STRING]
CHK
G - GREEN GROUND SENSOR [P17] [3/4"C,3#10,2#14,1#10G] [P40] [1 1/2"C,3#1, 3#14,1#6G]
REVI
[EC-5] [2"C,WITH PULL STRING]
[P18] [3/4"C,3#10,3#14,1#10G] [P41] [1 1/2"C,3#2/0, 1#4G]
THOUT THE W RI
[P19] [3/4"C,3#10,4#14,1#10G] [P42] [2"C,3#3/0, 1#4G]
[EC-7] [4"C,WITH PULL STRING]
51 TIME OVERCURRENT RELAY [P20] [3/4"C,3#10,5#14,1#10G] [P43] [2"C,3#4/0, 1#3G]
A AMMETER [EC-8] [5"C,WITH PULL STRING]
51G TIME OVERCURRENT RELAY, GROUND FAULT [P21] [1"C,2#8,1#10G]
[P22] [1"C,3#8,1#10G]
W WATTMETER 51V TIME OVERCURRENT, VOLTAGE RESTRAINED
DR
N,AS AN I
F FREQUENCY METER 52CSX POWER CIRCUIT BREAKER CONTROL SWITCH ANALOG CIRCUIT CALLOUTS CONTROL CIRCUIT CALLOUTS MULTICONDUCTOR CONTROL CABLE CIRCUIT CALLOUTS
B
R.W OOD
59 OVERVOLTAGE RELAY [A1] [3/4"C,1 TYPE 3] [C1] [3/4"C,MSC] [CC5] [3/4"C,1-5C TYPE 1]
PF POWER FACTOR METER
NCORPORATED HEREI
60 VOLTAGE OR CURRENT BALANCE RELAY [A2] [1"C,2 TYPE 3] [C2] [3/4"C,2#14,1#14G] [CC7] [3/4"C,1-7C TYPE 1]
DATE
[A3] [1"C,3 TYPE 3] [C3] [3/4"C,3#14,1#14G] [CC9] [1"C,1-9C TYPE 1]
WH WATT-HOUR METER 65A ENGINE GOVERNOR, SPEED CONTROL
[A4] [1"C,4 TYPE 3] [C4] [3/4"C,4#14,1#14G] [CC12] [1"C,1-12C TYPE 1]
65A, MOP ENGINE GOVERNOR, SPEED CONTROL
[A5] [1 1/4"C,5 TYPE 3] [C5] [3/4"C,5#14,1#14G] [CC19] [1 1/2"C, 1-19C TYPE 1]
DSGN
MOTOR OPERATED POTENTIOMETER
NO.
ETM ELAPSED TIME METER
[A6] [1 1/4"C,6 TYPE 3] [C6] [3/4"C,6#14,1#14G] [CC25] [1 1/2"C,1-25C TYPE 1]
N W HOLE OR I
[A7] [1 1/2"C,7 TYPE 3] [CC37] [2"C,1-37C TYPE 1]
GNS I
65A, RL ENGINE GOVERNOR, SPEED CONTROL [C7] [3/4"C,7#14,1#14G]
RPM TACHOMETER RAISE/LOWER SWITCH [A8] [1 1/2"C,8 TYPE 3] [C8] [3/4"C,8#14,1#14G] [CCC1] [1-7C #12 TYPE 1]
S NOT TO BE USED,I
XD [A10] [2"C,10 TYPE 3] [C10] [3/4"C,10#14,1#14G]
CUT
65B, MOP ENGINE GOVERNOR, LOAD CONTROL
[A11] [2"C,11 TYPE 3] [C11] [3/4"C,11#14,1#14G]
PF MOTOR OPERATED POTENTIOMETER
TY
NEW HAVEN,CONNECTI
POWER FACTOR TRANSDUCER [A12] [2"C,12 TYPE 3]
CONTROL AUTHORI
65B, RL ENGINE GOVERNOR, % LOAD [A13] [2"C,13 TYPE 3] [C13] [3/4"C,13#14,1#14G]
TD TIME DELAY RAISE/LOWER SWITCH [A14] [2"C,14 TYPE 3] [C14] [3/4"C,14#14,1#14G]
LL AND I
[A15] [3/4"C,1 TYPE 4] [C15] [3/4"C,15#14,1#14G]
4 RELAY COIL, DEVICE FUNCTION NUMBER PER 65E AUTOMATIC POWER TRANSFER AND LOAD
[A16] [3/4"C,2 TYPE 4] [C16] [3/4"C,16#14,1#14G]
ANSI 37.2 - AMERICAN STANDARD MANUAL AND CONTROL, WOODWARD APTL
CH2M HI
[A17] [1"C,3 TYPE 4] [C17] [3/4"C,17#14,1#14G]
AUTOMATIC STATION CONTROL, SUPERVISORY
THI
AND ASSOCIATED TELEMETRY EQUIPMENT 65F AUTOMATIC GENERATOR LOADING [A18] [1 1/4"C,4 TYPE 4] [C18] [3/4"C,18#14,1#14G]
CONTROL, WOODWARD AGLC [A19] [1 1/4"C,5 TYPE 4] [C19] [3/4"C,19#14,1#14G]
ON
90 VOLTAGE REGULATOR
TEST SWITCH CURRENT ELEMENT
ON
90PF ENGINE EXCITATION, POWER
NEUTRAL CONNECTION FACTOR CONTROL 3. SIZING OF CONDUCTORS #1AWG AND SMALLER BASED ON AMPACITIES
GENERAL
90RL ENGINE EXCITATION, RAISE/ ON AMPACITIES AT 75 DEGREES C.
DIODE
LOWER SWITCH
4. WHERE CIRCUITS ARE UNDERGROUND, DIRECT BURIED OR CONCRETE
ENCASED, MINIMUM CONDUIT SIZE SHALL BE 1".
ELECTRI
INSTRUMENTATION CABLE, SHIELDED
X = DEVICE NUMBER, WHEN THERE ARE MULTIPLE UNITS 5. FOR METRIC CONDUIT SIZES USE THE FOLLOWING CONVERSION:
1/2" = 16 mm 1/4" = 35 mm
3/4" = 21 mm 1 1/2" = 41 mm
NGR NEUTRAL GROUNDING RESISTOR
1" = 27 mm 2" = 53 mm
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 300-G-017
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/GEN/Dlv/300-G-017_664626.dgn
FILENAME:300-G-017_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:22 AM
1 2 3 4 5 6
GHTS RESERVED.
LL 2016. ALL RI
36" FOUL AIR 9
14
15
DUCTWORK (TYP) 14
c CH2M HI
APVD
A 7
13 ODOR CONTROL FAN
VALVE CHAMBER
12
BY
11 SOUND ENCLOSURE
10 9 9
.5
7
8
APVD
5
S THE PROPERTY OF
79
. 07
.
LL.
NEW STAIR SYSTEM 1
14
ON OF CH2M HI
1.20
FOR OCS ROOF ACCESS
2.20 4
.5
7
4
.5
+7
ZATI
CE,I
TTEN AUTHORI
ONAL SERVI
ON
2500 KVA 65
. 6.25 1.60
SI
CHK
REVI
6 TRANSFORMER FORCE MAIN
THOUT THE W RI
7 (13.8 Kv - 4160V)
ODOR CONTROL
300 KVA
SYSTEM REFILTER
DR
30" FOUL AIR . (4160V- 480V)
N,AS AN I
B
EBERS
DUCTWORK (TYP)
NCORPORATED HEREI
R.SI
DATE
10' DIA ACTIVATED
CARBON VESSEL (TYP) 40X10 EMERGENCY
4
.5
DSGN
NO.
+7
BALANCING 1.0 GENERATOR 65
.
N W HOLE OR I
GNS I
DAMPER (TYP)
6
ON
7
.
S NOT TO BE USED,I
CUT
+6.75
TY
NEW HAVEN,CONNECTI
LL AND I
07
.
1
CH2M HI
5
. ACCESS PLATFORM/STAIRS
+6
THI
TO EG ENCLOSURE
5 8
.
ON
4
. 6
+6
ON
DWF DIVERSION
TE PLAN
CI
6
SUBMERSIBLE
SI
+6.
5
+6.
45 PUMP STATION
+6.
45
95
6
5.
2.53
D NOTES:
2.83
1. BASE FLOOD ELEV. = 12.0 1"=10'
VERIFY SCALE
MI
N 0 1"
PRELI
1"=10'-0" PROJ 664626
3. DESIGN RESILIENCY PROTECTION ELEV. = 15.0
DWG 300-C-201
SHEET of
GHTS RESERVED.
1 2 3 4 5 6 7 8 1. BASE FLOOD EL (BFE) = 12.00
LL 2016. ALL RI
3. PROJECTED SEA LEVEL RISE EL (SLR) = 15.00
c CH2M HI
SHALL CONFORM WITH THE FOLLOWING:
UP
APVD
A
a. AREA OF FLOOD RELIEF
A
OPENINGS (Ao) = 2.5 in^2/1.0 ft^2
STAIR NO. 2
UP +4'-0"
BY
+4'-0"
+4'-0" 6. AREAS IDENTIFIED FOR DRY FLOOD PROOFING
SHALL CONFORM WITH THE FOLLOWING:
CONTROL
AREA
B a. FLOOD PROOFING PLAN SHALL BE
APVD
APPROVED BY "AHJ".
S THE PROPERTY OF
1 HOUR FIRE FRP STAIRS AND
LL.
RATED MV SWITCHGEAR HANDRAIL, TYP
b. A BUILDING CODE COMPLIANT EXIT DOOR FROM
ON OF CH2M HI
FRP DOOR ROOM UP
BATTERY EACH ISOLATED ROOM WITHIN THE DRY FLOOD
CONTAINMENT PROOF AREA SHALL BE PROVIDED.
C UP
c. ALL ELECTRICAL, LIFE SAFETY AND ESSENTIAL
SCREEN/DEGRIT
EQUIPMENT SHALL BE LOCATED ABOVE THE DFE.
ZATI
CE,I
FRP HANDRAILS AREA
SCRUBBER
TTEN AUTHORI
ONAL SERVI
ON
AREA
SI
CHK
REVI
FRP GRATING,
+4'-0"
TYP
THOUT THE W RI
ELECTRICAL
+4'-0" ROOM
ROOM
C.8
SINK
DR
SERVICE UP
N,AS AN I
B SINK
E
J.OSOKI
BLOWER
ROOM DRINKING
NCORPORATED HEREI
DEMO DOOR AND FOUNTAIN
FRAME, PATCH
DATE
WALLS AND FLOOR
MECHANICAL ROOM
DSGN
E
NO.
N W HOLE OR I
DN
GNS I
DEMO +4'-0" STAIR
NO. 1
ON
GNHW PCA LONG TERM CONTROL PLAN
TANK
S NOT TO BE USED,I
UP
CUT
DN
1 HOUR FIRE
TY
UP
NEW HAVEN,CONNECTI
CONTROL AUTHORI
RATED
AND FRP DOOR
HANDRAIL,
PROVIDE 3'-0" DN
LL AND I
MIN CLEAR
DN
EGRESS PATH FRP DOOR
G BETWEEN STAIR AND
CH2M HI
AND CONVEYOR FRAME, TYP
GARAGE
SUPPORT
THI
REPAIR
ON
NG PLAN
BOULEVARD PUM P STATI
TY
GN
45 M GD CAPACI
ON
STANT DESI
BRICK VENEER
FLOOD PROOFI
BRICK VENEER WALL
NEW PERMITER
EXST CMU WALL CMU WALL
FLOOD RESI
LEGEND
T/ NEW WALL T/ NEW WALL SLR
EL +15.00 EL +15.00 EL +15.00
NEW PERMANENT
NEW PERMITER
NEW INTERIOR CONC WALL CONCRETE WALL
CONC WALL PERMITER
BETWEEN WET AND DRY
FLOOD VENT
DESIGNATED AREAS
PERIMETER FLOOD
T/ GROUND T/ GROUND T/ GROUND BARRICADE
FLOOR FLOOR FLOOR
0"M AX ABOVE
EL +10.70 EL +10.70
GROUND FLOOR
EL +10.70
D REMOVABLE FLOOD
BARRICADE
EXST FDN WALL EXST WALL OR EXST FDN WALL
FRAMING BELOW
DRY FLOOD PROOF 1/8"=1'-0"
-
MI
0 1"
PRELI
WET FLOOD PROOF
1 NTS
1a NTS
DETAIL AREA WITH FLOOD PROJ 664626
2 NTS
VENTS
DWG 300-S-201
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/ST/Dlv/300-S-201_664626.dgn
FILENAME:300-S-201_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:09:05 AM
1 2 3 4 5 6
GHTS RESERVED.
LL 2016. ALL RI
c CH2M HI
APVD
A
6 7 8 6 7 8
BY
APVD
S THE PROPERTY OF
LL.
ON OF CH2M HI
A A
UP
ZATI
CE,I
EYEWASH
TTEN AUTHORI
ONAL SERVI
FRP HANDRAIL, TYP
ON
B B
SI
CHK
REVI
STAIR NO. 2 TYPE 316 SST
WATERTIGHT
THOUT THE W RI
C C
D.M I
FRP HANDRAIL,
WETWELL
TYP
DR
SPRINKLER (2) 55 GAL SPRINKLER
N,AS AN I
B SYSTEM HYDRAULIC SYSTEM
EBERS
LIMITED
FRP GRATING FLUID
HEADROOM
NCORPORATED HEREI
WARNING SIGN,
R.SI
TYP OF 4
DATE
C.8 PUMP
C.8
ROOM
D D
DSGN
NO.
FRP HANDRAIL, TYP
N W HOLE OR I
GNS I
SEAL LEAKS
S NOT TO BE USED,I
WETWELL PENETRATIONS
CUT
TY
NEW HAVEN,CONNECTI
LL AND I
CH2M HI
F F
THI
1 HOUR FIRE 1 HOUR FIRE
UP UP
G G
ON
BOULEVARD PUM P STATI
TY
N N
LOW ER PLANS
45 M GD CAPACI
ON
PLAN AT ELEV -12.00 PLAN AT ELEV -6.00
TECTURAL
ARCHI
D
1/8"=1'-0"
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 300-A-201
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/AR/Dlv/300-A-201_664626.dgn
FILENAME:300-A-201_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:09:08 AM
1 2 3 4 5 6
GHTS RESERVED.
LL 2016. ALL RI
c CH2M HI
APVD
A
BY
1 2 3 4 5 6 7 8
APVD
S THE PROPERTY OF
FRP STAIRS AND FRP GRATING, TYP
LL.
HANDRAIL, TYP
ON OF CH2M HI
UP
UP
ZATI
CE,I
STAIR NO. 2
+4'-0"
TTEN AUTHORI
ONAL SERVI
UP
+4'-0"
ON
+4'-0"
SI
CHK
CONTROL
REVI
AREA
B
THOUT THE W RI
1 HOUR FIRE FRP STAIRS AND
RATED MV SWITCHGEAR HANDRAIL, TYP
FRP DOOR ROOM
D.M I
UP
BATTERY
CONTAINMENT
UP C
DR
N,AS AN I
SCRUBBER
B
AREA
EBERS
FRP GRATING,
NCORPORATED HEREI
+4'-0"
R.SI
TYP
DATE
PUMP
ELECTRICAL
+4'-0" ROOM
ROOM
C.8
DSGN
NO.
SINK
N W HOLE OR I
GNS I
7'-6"
EYEWASH
S NOT TO BE USED,I
BLOWER GENERATOR
CUT
ROOM DRINKING
FOUNTAIN
TY
DEMO DOOR AND
NEW HAVEN,CONNECTI
MECHANICAL ROOM
LL AND I
E
DN
CH2M HI
DEMO +4'-0" STAIR
THI
BIOXIDE NO. 1
TANK
F
ON
AND CONVEYOR FRAME, TYP
GARAGE CLEAN MASONRY,
SUPPORT
TY
CRACKED MASONRY AND COAT
45 M GD CAPACI
CONCRETE CONCRETE, TYP
ON
TECTURAL
ARCHI
D
N
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 300-A-202
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/AR/Dlv/300-A-202_664626.dgn
FILENAME:300-A-202_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:51 AM
1 2 3 4 5 6
GHTS RESERVED.
LL 2016. ALL RI
c CH2M HI
APVD
A
BY
1 2 3 4 5 6 7 8
APVD
S THE PROPERTY OF
LL.
ON OF CH2M HI
OVERFLOW EXISTING ROOF
DRAIN, TYP DRAIN, TYP
ZATI
CE,I
TTEN AUTHORI
AL COPING ON
ONAL SERVI
ON
TREATED WOOD
SI
CHK
BLOCKING, TYP
REVI
B
THOUT THE W RI
NEW ROOF CURBS
AND SST FLASHING,
D.M I
TYP
DR
N,AS AN I
TRANSLUCENT
B PANEL SKYLIGHT,
EBERS
TYP OF 17
NCORPORATED HEREI
R.SI
DATE
C.8
DSGN
NO.
D
N W HOLE OR I
GNS I
GRAVEL SURFACED
S NOT TO BE USED,I
INSUL (R-20) ON
CUT
VAPOR RETARDER, TYP
TY
NEW HAVEN,CONNECTI
LL AND I
E
CH2M HI
THI
F
ON
BOULEVARD PUM P STATI
45 M GD CAPACITY
ON
ROOF PLAN
TECTURAL
N
1/4"=1'-0"
ROOF PLAN VERIFY SCALE
1/8"=1'-0" BAR IS ONE INCH ON
ORIGINAL DRAWING.
MI
0 1"
PRELI
PROJ 664626
DWG 300-A-203
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/AR/Dlv/300-A-203_664626.dgn
FILENAME:300-A-203_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:45 AM
1 2 3 4 5 6
GENERAL NOTES
GHTS RESERVED.
LL 2016. ALL RI
c CH2M HI
Seal
APVD
A
BY
APVD
1 2 3 4 5 6 7 8
S THE PROPERTY OF
LL.
ON OF CH2M HI
QC
5 TON BRIDGE CRANE
EXIST 36"
ZATI
CE,I
DISCHARGE
MANIFOLD
TTEN AUTHORI
ONAL SERVI
SION
CHK
A
REVI
PUMP MOTOR
NO. 4
THOUT THE W RI
NEW PUMP
AND MOTOR B
NO. 4
GRIT WORKS
DR
N,AS AN I
B GRATING (TYP)
C
S.CLARK
GRIT (SEE ARCH. DWG.)
#4
NCORPORATED HEREI
CHANNEL
NO. 4 NEW PUMP
DATE
AND MOTOR
? NO. 3
PUMP MOTOR
?
SUPPORT FROM WALLS NO. 3
#3?
GRIT
DSGN
AND CEILING
NO.
#3 CHANNEL
C
L EL. 19.5(TYP.)
NO. 3
N W HOLE OR I
GNS I
C.8
?
PUMP MOTOR
#2 CHANNEL
S NOT TO BE USED,I
7'-6"
SEE DWG.
NO. 2
M CC #2
? FOR NEW PUMP
?
CUT
DETAILS AND MOTOR
TY
NEW HAVEN,CONNECTI
NO. 2
LL AND I
BLOWER RM TYP TYP
VALVE VALVE
TYP TYP
MONORAIL
CH2M HI
NEW PUMP E
THI
AND MOTOR
NO. 1 A
RDCR FOT
F
C
TYP
EXIST 30" 12" CHECK
WALL SPOOL VALVE
TYP 30"x18" ECC TYP
RDCR FOT
TYP
ON
BOULEVARD PUM P STATI
LOADING
45 M GD CAPACITY
CAL
ON
PROCESS M ECHANI
VERIFY SCALE
N
BAR IS ONE INCH ON
BOULEVARD PUMP STATION - ALTERNATE 2 PLAN ORIGINAL DRAWING.
MI
0 1"
1/8"=1'-0"
DATE NOVEMBER 2016
PRELI
PROJ 664626
DWG 300-M-201
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/PR/Dlv/300-M-201_664626.dgn
FILENAME:300-M-201_664626.dgn PLOT DATE:11/8/2016 PLOT TIME: 1:21:33 PM
1 2 3 4 5 6
GHTS RESERVED.
LL 2016. ALL RI
ACTIVATED CARBON
VESSEL 1
ACCESS
c CH2M HI
MANWAY
APVD
A FLEX CONNECTION
BY
DAMPER
BACKDRAFT DAMPER
ODOR CONTROL
APVD
S THE PROPERTY OF
EXHAUST FAN
LL.
FLEX CONNECTION, TYP
ON OF CH2M HI
B
ZATI
CE,I
ACTIVATED CARBON
TTEN AUTHORI
ONAL SERVI
VESSEL 1
SION
CHK
ISOLATION
REVI
DAMPER, TYP
THOUT THE W RI
N PART,FOR ANY OTHER PROJECT W I
FLEX CONN
DR
BACKDRAFT
N,AS AN I
B DAMPER ODOR CONTROL
EXHAUST FAN
SECTION
NCORPORATED HEREI
FLEX
A 1/4"=1'-0"
DATE
CONNECTION
DSGN
NO.
A A
N W HOLE OR I
DEAS AND DESIGNS I
ON
GNHW PCA LONG TERM CONTROL PLAN
S NOT TO BE USED,I
ACTIVATED CARBON
VESSEL 2
CUT
TY
NEW HAVEN,CONNECTI
LL AND I
ACTIVATED CARBON ACTIVATED CARBON
CH2M HI
VESSEL 2 VESSEL 1
THI
REUSE OF DOCUM ENTS:
C FLEX
CONNECTION
ON
ONS
ODOR CONTROL
BLVD PUM P STAI
CAL
ON
PLAN & SECTI
PROCESS M ECHANI
SECTION
B 1/4"=1'-0"
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 300-M-215
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/PR/Dlv/300-M-215_664626.dgn
FILENAME:300-M-215_664626.dgn PLOT DATE:11/8/2016 PLOT TIME: 1:21:19 PM
1 2 3 4 5 6
GHTS RESERVED.
LL 2016. ALL RI
c CH2M HI
Seal
APVD
A
BY
APVD
S THE PROPERTY OF
LL.
ON OF CH2M HI
QC
ZATI
CE,I
TTEN AUTHORI
ONAL SERVI
SION
CHK
REVI
THOUT THE W RI
N PART,FOR ANY OTHER PROJECT W I
DR
N,AS AN I
B
S.CLARK
NCORPORATED HEREI
DATE
- 6" ABOVE
SHED
FLOOR
NI
FI
7'
EXIST 36"
DSGN
NO.
DISCHARGE
MANIFOLD
N W HOLE OR I
GNS I
EL 10.95
S NOT TO BE USED,I
CUT
TY
NEW HAVEN,CONNECTI
LL AND I
24" MAGNETIC
15'-8" 15'-8"
FLOWMETER
CH2M HI
11'-3"
TYP
THI
NEW PUMP
7'-6"(TYP.)
AND MOTOR
NO. 1 24" FCA
C
12" FCA 12" FCA
TYP TYP
ON
BOULEVARD PUM P STATI
24"x12" CONC
RDCR
TY
TYP
45 M GD CAPACI
CAL
ON
PROCESS M ECHANI
SECTI
TYP
300-M-201
VERIFY SCALE
MI
0 1"
PRELI
PROJ 664626
DWG 300-M-301
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/PR/Dlv/300-M-301_664626.dgn
FILENAME:300-M-301_664626.dgn PLOT DATE:11/8/2016 PLOT TIME: 1:21:29 PM
1 2 3 4 5 6
GENERAL NOTES
GHTS RESERVED.
1. PROVIDE A CHAIN ON PUMPS FOR REMOVAL
IF NEEDED.
LL 2016. ALL RI
2. PROVIDE A 4' x 6' HATCH PER EACH PUMP
FOR ACCESS. CENTER ACCESS HATCH
24" DIP OVER PUMPS.
24" x 12" REDUCER PUMP 3
(TYP)
3. PROVIDE A BURIED GATE VALVE DOWN
c CH2M HI
STREAM OF THE FLOW METER.
Seal
APVD
A BAFFLE WALL
BY
FL x FL WALL PIPE
APVD
PUMP 2
S THE PROPERTY OF
(TYP) (TYP)
LL.
ON OF CH2M HI
QC
-
16'0"
ZATI
CE,I
12" GV 12" CV
TTEN AUTHORI
ONAL SERVI
(TYP) (TYP)
SION
CHK
REVI
12" DIP 12" PE & PI
A PUMP 1
(TYP) (TYP)
THOUT THE W RI
N PART,FOR ANY OTHER PROJECT W I
20'-0" 20'-0"
DR
N,AS AN I
B
neer
Engi
NCORPORATED HEREI
DATE
DSGN
NO.
N W HOLE OR I
GNS I
DRY WEATHER PUMP STATION
S NOT TO BE USED,I
CUT
4' x 6' HATCH
TY
NEW HAVEN,CONNECTI
(IN CONCRETE)
LL AND I
TOC EL 10.50
GRADE EL 10.00
CH2M HI
THI
12" PE & PI
GUIDE ROD
(TYP)
EL 4.00
ON
PE x MJ WALL PIPE
6"
ON
48" INFLUENT
-
17'
CAL
ON
PLAN & SECTI
BOULEVARD
PROCESS M ECHANI
BAFFLE WALL
EL -2.00
6"
D
-
1'
TOC EL -8.00
VERIFY SCALE
MI
SECTION 0 1"
PRELI
3/8"=1'-0"
PROJ 664626
DWG 310-M-201
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/PR/Dlv/310-M-201_664626.dgn
FILENAME:310-M-201_664626.dgn PLOT DATE:11/8/2016 PLOT TIME: 1:21:21 PM
D
C
A
$PWURL
SCREENI
NG
5
1
GRI
NDER
1
SCREENI
NG
3
COM PACTOR
1
GRI
T
1.5
PUM P 1
1
DRY
W EATHER
1000
GRI
T PUM P 1
MVAFD-1
1.5
PUM P 2
1
1200
DRY
W EATHER
1000
PUM P 2
GRI
T
MVAFD-2
5
BLOW ER 1
1200
2.75 MW
1
MVGEN-1
2
W EATHER
1000
PUM P 3
G
MVAFD-3
GRI
T
5
1200
BLOW ER 2
1
DRY
W EATHER
PUM P 4
1000
(
STANDBY)
MVAFD-4
SCREENI
NG
MVSWGR-1, 4160V, 3Ø, 3W, 60HZ, 1200A, TBD KAIC
1200
1.5
CONVEYOR
1
POW ER
DPM
E
M ETERI
NG
GRI
T
1.5
CONVEYOR
1
125 AT
1200 AF
1200A
CRANE/
5
N
HOI
ST
1
T-1
3
SPD
1200A
3000 KVA
SURGE
15
SLI
DE GATES
MVATS-1
1
PROTECTI
VE
UNITED ILLUMINATING COMPANY (UI)
(
TYP OF 15)
DEVI
CE
4160V, 3Ø, 3W
13.8KV - 4160V,
NTS
3-PHASE, 3 WIRE
1200
POW ER
DPM
M ETERI
NG
1200
T-2
750 KVA
SURGE
30
PROTECTI
VE
SPD
CH2M / GNHWPCA SCOPE
DEVI
CES
4160V - 480V,
3-PHASE, 3 WIRE
15
GATE VALVES
4
1
(
TYP OF 10)
POW ER
DPM
M ETERI
NG
LI
GHTI
NG
PANEL
LP-1
1000 AT
1200 AF
LP-
1
25 KVA
250 AT
400 AF
480V - 208/120V
DRY
3-PHASE, 4 WIRE
W EATHER
80
ODOR
215
PUM P 1
AFD-1
CONTROL
50 KVA
400
DRY
SCREEN 1 W EATHER
215
15
PUM P 2
AFD-2
CONTROL
LCP-X
PANEL
400
5
DRY
W EATHER
SCREEN 2
215
15
PUM P 3
AFD-3
CONTROL
LVSWGR-1, 480V, 3Ø, 3W, 1200A, TBD KAIC
(
STANDBY)
pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/EL/Dlv/300-E-201_664626.dgn
LCP-X
400
PANEL
SURGE
PROTECTI
VE
SPD
SCREEN 3
15
DEVI
CE
CONTROL
30
LCP-X
PANEL
80
HVAC
FILENAME:300-E-201_664626.dgn
50 KVA
SUM P PUM P 1
1/4
15A
6
SUMP PUMP
CONTROLLER
SUM P PUM P 2
1/4
PLOT DATE:11/4/2016
DWG
DATE
PROJ
SHEET
0
ELECTRI
CAL GNHW PCA LONG TERM CONTROL PLAN
CONTROL AUTHORI
TY NO. DATE REVI
SION BY APVD
ORIGINAL DRAWING.
of
SI
NGLE LI
NE DIAGRAM
1"
GHTS RESERVED.
LL 2016. ALL RI
c CH2M HI
APVD
A
BY
6"
32"
APVD
ARCFLASH PLENUM
S THE PROPERTY OF
15A GATE 15A GATE
LL.
HVAC FEED SIZE 1
ON OF CH2M HI
VALVE 1 VALVE 6
SPD SCREENING
15A GATE 15A GATE
HVAC FEED GRINDER
MAIN VALVE 2 VALVE 7
LUGS 15A GATE 15A GATE
HVAC FEED SIZE 1
VALVE 3 VALVE 8
SCREENING
ZATI
CE,I
15A GATE 15A GATE ODOR
COMPACTOR
TTEN AUTHORI
1200AF 1200AF VALVE 4 VALVE 9 CONTROL
ONAL SERVI
LP-1
ON
150AT 150AT 15A GATE 15A GATE 15A SUMP
METERING SPD
SI
208/120V
CHK
MVAFD-1 MVAFD-3 VALVE 5 VALVE 10 PUMP SIZE 1
REVI
FEEDER FEEDER SPACE 30 CKT
15A CRANE GRIT PUMP 1
SPARE SPARE
72"
THOUT THE W RI
15A SLIDE 15A SLIDE 15A SLIDE
SIZE 1 GATE 1 GATE 6 GATE 11 SIZE 1 GRIT
M .REI
GRIT PUMP 2 15A SLIDE 15A SLIDE 15A SLIDE BLOWER 1
90"
DR
480-208/120V CONVEYOR
GATE 4 GATE 9 GATE 14
N,AS AN I
XFMR
B 15A SLIDE 15A SLIDE 15A SLIDE
R.W OOD
1200AF SIZE 1
1200AF 1200AF GATE 5 GATE10 GATE 15
1200AF 100AT GRIT SPARE
150AT 150AT
NCORPORATED HEREI
500AT XFMR-2 & 15A 15A 15A
MVAFD-2 MVAFD-4 CONVEYOR
MAIN BREAKER LVSWGR-1 SCREEN 1 SCREEN 2 SCREEN 3
DATE
FEEDER FEEDER
FEEDER
12"
DSGN
NO.
N W HOLE OR I
GNS I
36" 36" 36" 36"
20" 20" 20" 20" 20" 20"
S NOT TO BE USED,I
CUT
MVSWGR-1 ELEVATION
TY
NEW HAVEN,CONNECTI
MCC-1 ELEVATION
LL AND I
CH2M HI
THI
REUSE OF DOCUM ENTS:
C
ONS
400AF
1 ELEVATI
ON
250AT
METERING
MCC-1
ON
1200AF 400AF
1000AT 400AT
CAL
BREAKER FEEDER
ELECTRI
90"
CABLE CABLE
COMPARTMENT COMPARTMENT
400AF 400AF
400AT 400AT
AFD-2 AFD-3
FEEDER FEEDER
M VSW GR-
400AF
400AT SPD
SPARE
VERIFY SCALE
LVSWGR-1 ELEVATION
MI
0 1"
PRELI
NTS
PROJ 664626
DWG 300-E-202
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/EL/Dlv/300-E-202_664626.dgn
FILENAME:300-E-202_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:13 AM
1 2 3 4 5 6
SHEET KEYNOTES
GHTS RESERVED.
1. EXISTING GENERATOR TO BE DEMOLISHED.
LL 2016. ALL RI
WEATHERPROOF ENCLOSURE ON PAD AT
ELEVATION 15.00. PROVIDE ACCESS STAIRS AND
WALKWAYS AS REQUIRED.
c CH2M HI
OF PAD AT ELEVATION 15.00.
APVD
A
4. NEW 4160 - 480V, 750 KVA TRANSFORMER. TOP OF
PAD AT ELEVATION 15.00.
BY
5. EXISTING 13.8 KV - 480V TRANSFORMER. REMOVE
AFTER NEW SERVICE INSTALLED.
APVD
TANK OR REUSE EXISTING FUEL TANK. MOUNT
S THE PROPERTY OF
TANK ON NEW PAD AT ELEVATION 15.00 OR
LL.
PROVIDE WATERPROOFING FOR TANK BELOW
ON OF CH2M HI
ELEVATION 15.00. PROVIDE ACCESS STAIRS AND
WALKWAYS AS REQUIRED.
ZATI
CE,I
TTEN AUTHORI
ONAL SERVI
SION
CHK
A
REVI
OPERATOR
STATION
THOUT THE W RI
MVSWGR-1
HMI
M .REI
1000 WORKSTATION
B
MVATS-1
PUMP 4
DR
3
ROOM
N,AS AN I
B C
R.W OOD
SCREEN/DEGRIT 13.8 KV PUMP 3
1
AREA SERVICE
NCORPORATED HEREI
AFD-3
SCRUBBER ENTRANCE 1000 LVSWGR-1
DATE
AREA
GENERATOR ELECTRICAL/ 4
DSGN
NO.
ROOM CONTROL ROOM
N W HOLE OR I
GNS I
AFD-2
C.8
ELECTRICAL AREA
ON
GNHW PCA LONG TERM CONTROL PLAN
D
S NOT TO BE USED,I
MVAFD-4 AFD-1
CUT
1000
TY
NEW HAVEN,CONNECTI
CONTROL AUTHORI
BLOWER
MVAFD-3
ROOM
MECHANICAL ROOM
LL AND I
MCC-1
CH2M HI
MVAFD-2
THI
1000
2
PUMP 1
C
F
ON
BOULEVARD PUM P STATI
G
ON
NARY – NOT FOR CONSTRUCTI
GENERATOR FUEL TANK
CAL
GUARD POST, TYP
6
ELECTRI
FI
D
1/8"=1'-0"
N VERIFY SCALE
MI
0 1"
1/8"=1'-0"
DATE NOVEMBER 2016
PRELI
PROJ 664626
DWG 300-E-203
SHEET of
$PWURL pw://projectwise.ch2m.com:DEN001/Documents/664626&space;-&space;GNHWPCA&space;Long&space;Term&space;Control/DESIGN/300&space;-&space;Boulevard&space;PS/EL/Dlv/300-E-203_664626.dgn
FILENAME:300-E-203_664626.dgn PLOT DATE:11/4/2016 PLOT TIME: 10:08:30 AM
Appendix F
Construction Cost Estimate
Breakdown
Intermediate‐Term Improvements
Capacity Upgrade of East Street Pump
Station
Facility Summary
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
Estimate Totals
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 1
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 2
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 3
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 4
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 6
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 7
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 8
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 10
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 11
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 12
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 13
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 14
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 15
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 16
Detail Report
Project: East Street Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: 1 LS Project No.: 478874 Revision / Date: Rev03/(10-4-2016)
Duration: 1 LS Design Stage: conceptual Estimate Class: 4
Estimate Totals
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\East Street Pump Station 11/4/2016 12:56 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 17
Intermediate‐Term Improvements
Capacity Upgrade of Union Pump
Station
Union Pump Station
Construction Cost Estimate for Concept Design
The construction cost estimate (s) shown herein have been prepared for guidance in project evaluation and implementation from the information available at the time of
the estimate. The final costs of the project will depend on actual labor and material costs, competitive market conditions, final project costs, implementation schedule and
other variable factors. As a result, the final costs will vary from the estimates presented herein. Because of this, project feasibility and funding needs must be carefully
reviewed prior to making specific financial decisions to help ensure proper project evauluation and adequate funding. Our estimate is based on material, equipment, and
labor pricing as of the estimate revision date. The owner should be cautioned that such prices are highly subject to variation as a result of shortages resulting from recent
natural disasters and current escalation trends.
Facility Summary
Project: GNH Union Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev02 (10-3-2016)
Duration: Design Stage: Conceptual Estimate Class: 4
Estimate Totals
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Union Pump Station 10/3/2016 11:09 AM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 1
Detail Report
Project: GNH Union Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev02 (10-3-2016)
Duration: Design Stage: Conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Union Pump Station 10/3/2016 11:09 AM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 2
Detail Report
Project: GNH Union Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev02 (10-3-2016)
Duration: Design Stage: Conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Union Pump Station 10/3/2016 11:09 AM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 4
Detail Report
Project: GNH Union Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev02 (10-3-2016)
Duration: Design Stage: Conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Union Pump Station 10/3/2016 11:09 AM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 5
Detail Report
Project: GNH Union Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev02 (10-3-2016)
Duration: Design Stage: Conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Union Pump Station 10/3/2016 11:09 AM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 6
Detail Report
Project: GNH Union Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev02 (10-3-2016)
Duration: Design Stage: Conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Union Pump Station 10/3/2016 11:09 AM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 7
Detail Report
Project: GNH Union Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev02 (10-3-2016)
Duration: Design Stage: Conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Union Pump Station 10/3/2016 11:09 AM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 8
Detail Report
Project: GNH Union Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev02 (10-3-2016)
Duration: Design Stage: Conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Union Pump Station 10/3/2016 11:09 AM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 9
Detail Report
Project: GNH Union Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev02 (10-3-2016)
Duration: Design Stage: Conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Union Pump Station 10/3/2016 11:09 AM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 10
Detail Report
Project: GNH Union Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev02 (10-3-2016)
Duration: Design Stage: Conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Union Pump Station 10/3/2016 11:09 AM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 11
Detail Report
Project: GNH Union Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev02 (10-3-2016)
Duration: Design Stage: Conceptual Estimate Class: 4
Estimate Totals
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Union Pump Station 10/3/2016 11:09 AM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 12
Intermediate‐Term Improvements
Capacity Upgrade of Boulevard Pump
Station
Facility Summary
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
Estimate Totals
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 1
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 2
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 3
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 4
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 5
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 6
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 7
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 8
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 9
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 10
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 11
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 12
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 13
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 14
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 15
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 16
Detail Report
Project: Boulevard Pump Station Estimator: E.B. Smith/GNV, A. Frisch/PGH
Job Size: Project No.: 478874 Revision / Date: Rev03, (10-4-2016)
Duration: Design Stage: conceptual Estimate Class: 4
Estimate Totals
Contractor Contingency
Subtotal Contingency 14,535,170
M:\WBG-CNSLT\Estimates-CNSLT\2016\WW-Treatment\478874 Greater New Haven Master Plan\01_Est\Boulevard Pump Station 11/4/2016 12:55 PM
Property of CH2M, All Rights Reserved - Copyright 2016 Page 17
Intermediate‐Term Improvements
Yale Campus Trumbull Street Area
Phase 2A Project Sewer Separation
Yale Campus / Trumbull Street Sewer Separation Project - Phase 2A
Cost Estimate - July 30, 2013
CWF 2012-04
DTC# 09-405-116
TOTAL $ 9,960,156.25
Demolition
Existing Garage 3,000 SF $5 $18,144
Existing Maintenance Facility 7,500 SF $8 $68,040
Ecavation
Preliminary Treatment Bldg 6,963 CY $30 $252,673
Dewatering
Preliminary Treatment Bldg 12,000 SF $30 $435,457
Yard Piping
Twin 72 inch Effluent Pipes 850 FT $1,275 $1,310,907
Site Work
Grading and Drainage 1 ALLOWANCE $10,000 $12,096
Roads & paved areas 1,333 SQYDS $45 $72,558
Floodplain Compensation 1 Estimate $300,000 $362,881
Division 3 - Concrete
Truck Bay
Stone Base 6" Thick 80 CY $25 $2,419
Base Slab 470 CY $500 $284,257
3rd Floor Slab 310 CY $1,000 $374,977
Fine Screening
Stone Base 6" Thick 75 CY $25 $2,268
Base Slab 430 CY $500 $260,065
2nd Floor Slab 220 CY $1,000 $266,113
3rd Floor Slab 35 CY $1,000 $42,336
Elec, Control, and HVAC
Stone Base 6" Thick 30 CY $25 $907
Base Slab 180 CY $500 $108,864
2nd Floor Slab 90 CY $1,000 $108,864
3rd Floor Slab 90 CY $1,000 $108,864
Channels
Screening Influent and Effluent 125 CY $1,000 $151,200
Fine Screen Channels 70 CY $1,000 $84,672
Grit Removal Channels 330 CY $1,000 $399,169
Grit Removal
Stone Base 6" Thick 160 CY $25 $4,838
Base Slab 950 CY $500 $574,561
1st Floor Slab 475 CY $1,000 $574,561
Pista Grit 390 CY $1,000 $471,745
Below Grade Wall 360 CY $750 $326,593
Division 4 - Masonry
Included in Div 10
Div. 4 Subtotal:
Project: GNHWPCA Long Term Control Plan Update
Facility: Preliminary Treatment
Estimate Type: Conceptual
Prepared By: J.Ososkie/HRT
Date: 10/4/2016
Division 5 - Metals
Other Metals Included in percentages below
Div. 5 Subtotal:
Division 9 - Finishes
Included in percentages below
Div. 9 Subtotal:
Division 10 - Specialties
Division 11 - Equipment
Fine Screens
Fine Screens (70 MGD, 6mm) 3 EA $290,000 $1,052,354
Screen Presses 3 EA $85,000 $308,449
Transfer Screws (60' long, 15 deg) 3 EA $70,000 $254,017
Sluice Gates 6 EA $55,400 $402,072
Grit Removal
Pista Grit Equipment 3 EA $90,000 $326,593
Grit Pumps 6 EA $20,000 $145,152
Classifier and Concentrator 3 EA $60,000 $217,729
Sluice Gates 6 EA $33,300 $241,679
Truck Bay
Leveling Screws 3 EA $70,000 $254,017
Hoppers with Load Cells 6 EA $100,000 $725,762
Division 12 - Furnishings
Not Used
Div. 12 Subtotal:
Division 15 - Mechanical
Included in Percentages Below
Div. 15 Subtotal:
Division 16 - Electrical
Included in Percentages Below
Div. 16 Subtotal:
Percentage of Costs
Demolition
Demolition of Primary Influent Channel 148 CY
Demolition of Primary Clarifiers Wall and Footing 281 CY
Demolition of Primary Clarifier Floor 329 CY
Demolition of Primary Sludge Pits (3 exist, 2 older) 121 CY
Demolition of Primary Effluent Structure, clarifier 3 18 CY
Demolition I Subtotal: 878 CY $150 $159,315
Excavation
Primary Clarifier 4 9,293 CY $30 $337,237
Primary Clarifier 4 Gallery 2,292 CY $30 $83,167
Gallery Clarifier 1-3 2,095 CY $30 $76,017
Yard Piping
Effluent piping, 84 inch dia 320 FT $335 $129,669
Sludge piping 640 FT $150 $116,122
Scum piping 18 inch dia 260 FT $85 $26,732
Site Work
Grading and Drainage 1 ALLOWANCE $50,000 $60,480
Roads (22 ft wide) 489 SQYDS $45 $26,611
Division 3 - Concrete
Primary Clarifier 4
Stone Base 6" thick 310 CY $25 $9,368
Effluent Structure Walls 28 CY $750 $25,200
Effluent Structure Floor 19 CY $500 $11,290
Primary Clarifier Walls 628 CY $750 $569,723
Primary Clarifier Floor 1,859 CY $500 $1,124,124
Primary Clarifier Footings 244 CY $500 $147,706
Influent Pipe Encasement 1,048 CY $500 $633,549
Primary Clarifier Gallery (1-4)
Stone Base 6" thick 175 CY $25 $5,292
Gallery Walls 756 CY $750 $686,046
Gallery Floor 1,042 CY $500 $630,337
Gallery Roof 521 CY $1,000 $630,337
Gallery Footings 131 CY $500 $79,498
Division 4 - Masonry
Not used
Div. 4 Subtotal:
Division 5 - Metals
Division 9 - Finishes
Included in percentages below
Div. 9 Subtotal:
Division 10 - Specialties
Gallery Exits -2 (stairwells) 700 SF $150 $127,008
Div. 10 Subtotal: $127,008
Division 11 - Equipment
Division 12 - Furnishings
Not used
Div. 12 Subtotal:
Division 15 - Mechanical
Included in percentages below
Div. 15 Subtotal:
Division 16 - Electrical
Included in percentages below
Div. 16 Subtotal:
Percentage of Costs
Demolition
Demolition of existing grit removal equipment 1 ALLOW ANCE $150,000 $181,440
Excavation
CEPT Chemical Containment 259 CY $25 $7,840
Yard Piping
FeCl3 Pipes, 2" PVC 300 FT $65 $23,587
PO Pipes, 2" PVC 300 FT $65 $23,587
Site W ork
Grading and Drainage 1 ALLOW ANCE $10,000 $12,096
Roads (22 ft wide) 222 SQYDS $45 $12,096
Division 3 - Concrete
Basement
Screen channel covers 11 CY $1,000 $13,440
Grit channel covers 59 CY $1,000 $71,680
Grit channel benching 237 CY $500 $143,360
Grit channel modifications at gates 1 ALLOW ANCE $100,000 $120,960
Chemical containment
Stone Base 6" thick 19 CY $25 $560
base slab 111 CY $500 $67,200
walls 39 CY $750 $34,944
Division 4 - Masonry
Not used
Div. 4 Subtotal:
Division 5 - Metals
Included in percentages below
Div. 5 Subtotal:
Division 9 - Finishes
Included in percentages below
Div. 9 Subtotal:
Division 10 - Specialties
Headworks Bldg.
Life Safety (egress, fire protcection, NFPA, etc) 10,080 SQFT $75 $914,460
Change of use & Upgrades (doors, windows, thermal protection, etc) 10,080 SQFT $75 $914,460
Chemical containment super structure 1,000 SQFT $250 $302,401
Division 11 - Equipment
Division 12 - Furnishings
Not used
Div. 12 Subtotal:
Division 15 - Mechanical
Included in percentages below
Div. 15 Subtotal:
Division 16 - Electrical
Included in percentages below
Div. 16 Subtotal:
Percentage of Costs
Demolition
Existing CCT1 baffle walls 318 CY $150 $57,607
Effluent channel wall to beach gate 12 CY $150 $2,150
Ecavation
Dry/Wet Weather Flow Split 356 CY $30 $12,902
Chlorine Contact Tanks 8,889 CY $30 $322,561
Wet Weather Conduit 10,276 CY $30 $372,880
Dewatering
Dry/Wet Weather Flow Split 1 ALLOWANCE $50,000 $60,480
Chlorine Contact Tanks 1 ALLOWANCE $150,000 $181,440
Wet Weather Conduit 1 ALLOWANCE $100,000 $120,960
Yard Piping
NaOCl Pipes, 2" PVC 1,200 FT $65 $94,349
Site Work
Grading and Drainage 1 ALLOWANCE $100,000 $120,960
Roads (22 ft wide) 1,333 SQYDS $45 $72,576
Division 3 - Concrete
Dry Weather UV
Channel walls 415 CY $750 $376,321
Channel covers (50%) 117 CY $1,000 $141,120
Division 4 - Masonry
Not used
Div. 4 Subtotal:
Division 5 - Metals
Division 9 - Finishes
Not used
Div. 9 Subtotal:
Division 10 - Specialties
UV Canopy 3,150 SF $150 $571,537
Division 11 - Equipment
Division 12 - Furnishings
Not used
Div. 12 Subtotal:
Division 15 - Mechanical
Included in percentages below
Div. 15 Subtotal:
Division 16 - Electrical
Included in percentages below
Div. 16 Subtotal:
Percentage of Costs
Subtotal: $18,061,472
Division 3 - Concrete
Div. 3 Subtotal:
Division 4 - Masonry
Not used
Div. 4 Subtotal:
Division 5 - Metals
Not used
Div. 5 Subtotal:
Division 9 - Finishes
Not used
Div. 9 Subtotal:
Division 10 - Specialties
Switch Gear Bldg. Suoerstructure 0 SF $250
Div. 10 Subtotal:
Division 11 - Equipment
Main Building
Project: GNHWPCA Long Term Control Plan Update
Facility: Electrical Upgrade
Estimate Type: Conceptual - Capital Improvements Planning
Prepared By: J. Ososkie/HRT
Date: 10/4/2016
Aeration tanks
MCC-A5 (INSTALLED 1996) 0 EA $10,000
MCC-A6 (INSTALLED 1996) 0 EA $10,000
MCC-A7 (INSTALLED 1996) 0 EA $10,000
MCC-A8 (INSTALLED 1996) 0 EA $10,000
MCC-A9 (INSTALLED 1996) 0 EA $10,000
Sludge Building
MCC-S3 0 EA $10,000
MCC-S4 0 EA $10,000
MCC-S5 (INSTALLED 1998) 0 EA $10,000
MCC-S6 (INSTALLED 1998) 0 EA $10,000
Generator Building
MCC-GEN BLDG 6 $10,000 $72,576
Grit Building
MCC-Grit BLDG 10 $10,000 $120,960
Division 12 - Furnishings
Not used
Div. 12 Subtotal:
Not used
Div. 14 Subtotal:
Division 15 - Mechanical
Not used
Div. 15 Subtotal:
Division 16 - Electrical
Included in percentages below
Div. 16 Subtotal:
Percentage of Costs
Metals 0% $3,550,342 $0
Finishes 0% $3,550,342 $0
I&C 0% $3,550,342 $0
Electrical 20% $3,550,342 $710,068
Division 4 - Masonry
Not Used
Div. 4 Subtotal:
Division 5 - Metals
other items included in percentages below
Div. 5 Subtotal:
Division 9 - Finishes
Included in percentages below
Div. 9 Subtotal:
Division 10 - Specialties
Not Used
Div. 10 Subtotal:
Division 11 - Equipment
Division 12 - Furnishings
Not Used
Div. 12 Subtotal:
Division 15 - Mechanical
Included in percentages below
Div. 15 Subtotal:
Division 16 - Electrical
Included in percentages below
Div. 16 Subtotal:
Percentage of Costs
Subtotal: $19,853,394
Sewer Separation
Subtototal $43,478,800
Subtototal $58,261,592
Long‐Term Improvements CSO
Storage Tanks
Great New Haven WWTP Master Plan
Storage Tank Estimate
Construction Cost Estimate for Conceptual Design
Estimate Totals
014 CSO 011 StorageTank 1.33 MG 1,457,023 3,768,114 300,000 105,072 4,233,239.96 /MG 5,630,209 7,938,703.79 /MG 10,558,476
016 CSO 015 StorageTank
13.0 Effluent Pump Station
13-10 Buildings Complete
Effluent Pump Station
Masonry Building
Pump Building Masonry 20' x 20' 400.00 sf 28,638 28,000 - 105,072 - 404.27 /sf 161,710 740.48 /sf 296,191
Masonry Building 400.00 SF 28,638 28,000 105,072 404.27 /SF 161,710 740.48 /SF 296,191
Mechanical, Other
Miscelleneous piping allowance 1.00 ls - - 200,000 - - 200,000.00 /ls 200,000 366,324.79 /ls 366,325
Mechanical, Other 400.00 SF 200,000 500.00 /SF 200,000 915.81 /SF 366,325
Mechanical, HVAC
Condensing unit, air cooled, compressor, 4 ton, includes standard 1.00 ea 3,095 8,500 - - - 11,595.04 /ea 11,595 21,237.75 /ea 21,238
controls
Mechanical, HVAC 400.00 SF 3,095 8,500 28.99 /SF 11,595 53.09 /SF 21,238
Electrical, Other
Miscellaneous electrical and I&C 1.00 ls - - 100,000 - - 100,000.00 /ls 100,000 183,162.40 /ls 183,162
Electrical, Other 400.00 SF 100,000 250.00 /SF 100,000 457.91 /SF 183,162
Electrical Equipment, Generators - >300 to 400 KW
Emergency Generator 400 KW 1.00 E 7,541 120,000 - - - 127,540.92 /E 127,541 233,607.00 /E 233,607
Electrical Equipment, Generators - >300 to 400 KW 1.00 EA 7,541 120,000 127,540.92 /EA 127,541 233,607.00 /EA 233,607
I&C, Flow / Mag Meter / Indicators & Transmitters
Pump Flow Meter including transmitter 2.00 ea 1,194 20,400 - - - 10,796.99 /ea 21,594 19,776.03 /ea 39,552
I&C, Flow / Mag Meter / Indicators & Transmitters 2.00 EA 1,194 20,400 10,796.99 /EA 21,594 19,776.03 /EA 39,552
I&C, Level / Switches
Float switch 8.00 ea 1,203 - - - - 150.40 /ea 1,203 275.48 /ea 2,204
Float switch bracket 2.00 ea 602 300 - - - 450.80 /ea 902 825.70 /ea 1,651
I&C, Level / Switches 10.00 EA 1,805 300 210.48 /EA 2,105 385.52 /EA 3,855
I&C, Panels & Stands
System panel 2.00 ea 1,203 12,000 - - - 6,601.60 /ea 13,203 12,091.65 /ea 24,183
I&C, Panels & Stands 2.00 EA 1,203 12,000 6,601.60 /EA 13,203 12,091.65 /EA 24,183
Submersible Pump: 35Hp
Functional Testing, Submersible Pumps, 21 - 50 hp 2.00 ea 602 100 - - - 350.80 /ea 702 642.53 /ea 1,285
FURNISH Submersible Pump, 35 hp 2.00 EA - 63,000 - - - 31,500.00 /EA 63,000 57,696.15 /EA 115,392
Set base elbow / pump assembly, 35 hp 2.00 ea 5,414 100 - - - 2,757.20 /ea 5,514 5,050.15 /ea 10,100
Stainless steel guide rails, 3", 40.00 lf 1,306 694 - - - 50.00 /lf 2,000 91.58 /lf 3,663
Install upper guide rail bracket 2.00 ea 226 20 - - - 122.80 /ea 246 224.94 /ea 450
Submersible Pump: 35Hp 2.00 EA 7,547 63,914 35,730.80 /EA 71,462 65,445.40 /EA 130,891
Effluent Pump Station 1.00 EA 51,023 253,114 300,000 105,072 709,209.14 /EA 709,209 1,299,004.47 /EA 1,299,004
13-10 Buildings Complete 400.00 SF 51,023 253,114 300,000 105,072 1,773.02 /SF 709,209 3,247.51 /SF 1,299,004
13.0 Effluent Pump Station 400.00 SF 51,023 253,114 300,000 105,072 1,773.02 /SF 709,209 3,247.51 /SF 1,299,004
33.5 Tank Construction
33.90 Tanks
Cast-In-Place Concrete Storage Tank
Tanks, Other
Storage Tanks construction, below grade, cast-in-place concrete, 390,000.00 gal 288,600 288,600 288,600 288,600 288,600 3.70 /gal 1,443,000 6.96 /gal 2,715,183
390,000 gaillons, incluidng sitework, miscellaneous piping excludiing
pump station
Tanks, Other 390,000.00 GAL 288,600 288,600 288,600 288,600 288,600 3.70 /GAL 1,443,000 6.96 /GAL 2,715,183
Cast-In-Place Concrete Storage Tank 390,000.00 GAL 288,600 288,600 288,600 288,600 288,600 3.70 /GAL 1,443,000 6.96 /GAL 2,715,183
33.90 Tanks 390,000.00 GAL 288,600 288,600 288,600 288,600 288,600 3.70 /GAL 1,443,000 6.96 /GAL 2,715,183
33.5 Tank Construction 390,000.00 GAL 288,600 288,600 288,600 288,600 288,600 3.70 /GAL 1,443,000 6.96 /GAL 2,715,183
016 CSO 015 StorageTank 0.39 MG 339,623 541,714 588,600 393,672 288,600 5,518,484.97 /MG 2,152,209 10,292,789.33 /MG 4,014,188
018 CSO 016 StorageTank
13.0 Effluent Pump Station
13-10 Buildings Complete
Effluent Pump Station
Masonry Building
Pump Building Masonry 20' x 20' 400.00 sf 28,638 28,000 - 105,072 - 404.27 /sf 161,710 740.48 /sf 296,191
Masonry Building 400.00 SF 28,638 28,000 105,072 404.27 /SF 161,710 740.48 /SF 296,191
Mechanical, Other
Miscelleneous piping allowance 1.00 ls - - 200,000 - - 200,000.00 /ls 200,000 366,324.80 /ls 366,325
Mechanical, Other 400.00 SF 200,000 500.00 /SF 200,000 915.81 /SF 366,325
Mechanical, HVAC
Estimate Totals
Escalation
Subtotal Escalation 49,820,782