12 - Control and Monitoring
12 - Control and Monitoring
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
To guarantee energy availability and reduce energy bills, industrial installations require optimal
management of their electrical networks.
A control and monitoring system enables optimisation of network management through the use
of automatic functions such as:
- supply changeover
- loop reconfiguration
- load shedding/restoration
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
The speed and effectiveness of network diagnosis and intervention are improved through the
following functions:
- fault recording
- tariff management
- time-dependent programming
n optimising maintenance
Using the system's recorded count of switching device operations and equipment operating
times, maintenance can be optimised.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
- a standing charge related to the subscribed demand (not to be exceeded). The lower the
subscribed demand, the lower the standing charge
- any penalty payments related to power consumption exceeding the subscribed demand
- an eventual charge for reactive power consumption, in units of kvarh, once its value
exceeds the supplier's uninvoiced consumption threshold during certain tariff periods.
The different energy cost components vary according to the month of the year and the hour of
the day or night, i.e. the tariff periods.
One important function of any control and monitoring system is to manage tariff variations in
the best possible way in order to reduce energy costs. The means used are described in the
following paragraphs.
The cost of energy produced by internal generator sets can be less than that charged by the
energy utility. Economic reasons therefore exist for supplying the network from internal
generator sets.
Where generators can supply more power than that demanded internally, the excess can be
sold to the utility.
- calculates the economic benefit of supplying all or part of the load from internal generator
sets
- automatically handles the changeover from utility supply to generator supply (for operation
disconnected from the utility)
- controls the active and reactive powers supplied by the generator sets (see § 12.1.4.).
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
To avoid penalty charges, as far as possible the power supplied by the utility should not
exceed the subscribed demand.
The control and monitoring system manages automatic load shedding together with the power
supplied by internal generators in order to keep within the subscribed demand.
Since energy costs vary according to the time of day, the energy related costs of these
processes may be reduced by running them during the least expensive tariff periods.
The control and monitoring system function carries out tariff management.
- limit capital costs, Joule losses and voltage dips where the capacitors are installed close to
highly reactive loads.
- installation of capacitors
- increasing the reactive power supplied by the generator sets, where it exists.
The control and monitoring system manages capacitor control and the reactive power supplied
by the generator sets.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
n energy sub-metering
Sub-metering - that is, measuring energy consumption for a given production unit, workshop or
activity sector - allows energy costs to be more clearly defined and apportioned, as well as
alerting the operator to situations deviating from the norm, thus enabling energy costs to be
shared between the various workshops and production units.
Control of the automatic devices which contribute to improving energy availability is one of the
most important considerations on which control and monitoring systems are based.
For loads where continuity of supply is critical, there are redundant sources of power.
The control and monitoring system handles the automatic changeover from a faulty supply to
the back-up.
- loop reconfiguration.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
- a load in excess of the production capacity results in generators being taken out of service
- after supply interruption, load restoration must be carried out step by step to avoid
unacceptable voltage and frequency variations.
Once the internal generators are operating an electrical fault can provoke network instability
(see § 9) and, as a consequence, the loss of the internal supply.
The control and monitoring system controls automatic load shedding/restoration which is
adapted to the nature of the situations encountered:
- protecting the network and contributing to its dynamic stability under fault conditions
Interlocking of switching and isolating devices avoids operational errors which might otherwise
lead to electrical faults.
The control and monitoring system supervises the interlocking of switching and isolating
devices.
The control and monitoring system controls the intertripping of switching devices.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
Consider the case of a network equipped with two busbars with coupler, each having an
earthing transformer installed.
When the two busbars are connected together only one earthing transformer should be on line
(see § 2.3.1 of the Industrial network protection guide).
The control and monitoring system provides the automatic control necessary to ensure only
one earthing transformer is on line when the two busbars are connected together.
To ensure the proper functioning of loads and long service life of electrical apparatus the
quality of the energy supply is of paramount importance.
- power factor
- voltage unbalance
Periodic reports are transmitted to the system enabling problems to be analysed and remedial
action to be taken.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
Active and reactive powers are determined by the load; frequency and voltage are regulated.
o 1st possibility
The active and reactive powers supplied by the generator sets are regulated to pre-set values,
with any load variations then being met by the utility.
o 2nd possibility
The active and reactive powers supplied by the utility are regulated to pre-set values (for
example, subscribed demand), with load variations then being withstood by the generator set
up to the limit of its capacity.
o 3rd possibility
The active power supplied by the generators is regulated to a pre-set value. Variations in
active power demand are then met by the utility.
The reactive power supplied by the utility is regulated to a pre-set value (the uninvoiced limit
consumption, for example). Reactive power variations are then withstood by the generator set
up to the limit of its capacity.
A synchronizing function is installed between each generator and between the generator set
and the utility.
The control and monitoring system controls the operation of the internal generator set.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
Fine time stamping records alarms and switching device operations with a precision that
enables the chronology of events leading up to and following a fault to be determined.
The fault recorder registers changes to analogue values (voltage, current) when specific
events occur (overcurrent, overvoltage).
The control and monitoring system manages these two key functions.
It also offers the operator help and assistance with his work thus leading to improved
productivity and safety.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
- make savings by feeding the switchboard from the most economical source (where one of
the sources is the internal generator sets)
A short-break changeover is carried out if, during the changeover sequence, the disconnected
source and the replacement source do not feed the load in parallel.
This means there is a brief interruption of supply to the load.
A no-break changeover is carried out if, during the changeover sequence, the two supplies
feed the load in parallel, in which case they must be synchronous. There is no interruption of
supply to the load.
Before a changeover can take place, the control and monitoring system must first of all
analyse the necessary operating conditions:
- the correct state of all isolating devices. For example, all isolators are closed or all circuit-
breakers are plugged in
- the voltage is correct, in the case of the replacement supply coming from the same energy
production source
- the voltage and frequency are correct, in the case of a changeover without coupling to an
internal generator set
- the voltage, frequency and phase are correct, in the case of changeover with coupling of
two supplies coming from different production sources
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
- the absence of voltage is not the result of a downstream fault trip (otherwise the back-up
supply would re-supply the fault).
- the remanent voltage on busbars to which motors are connected is below a given threshold.
In fact, following a supply disconnection, the motors maintain a remanent voltage for the
time it takes the flux to collapse (about a second). Rapidly reconnecting the supply whose
phase is in opposition to the remanent voltage could well provoke transient electrical and
mechanical phenomena likely to damage the motor. In the case of a short-break
changeover the control and monitoring system will inhibit supply reconnection until the
remanent busbar voltage is below a predefined threshold value (of the order of 20 % of the
nominal voltage). Where a minimum remanent voltage protection system (code ANSI 27R)
is fitted to the busbar, reconnection is enabled directly through its "digital" output signal.
For a short-break changeover, control and monitoring system performance is such that there is
loss of supply for a period of less than 400 ms (where reconnection is not locked by the
remanent voltage monitoring).
The principle of the 1/2 changeover is shown in the simplified diagram in figure 12.1.
source A source B
busbar
outgoing feeders
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
If one of the busbar supplies is lost the power source acting as back-up is connected
(see fig. 12-2).
1/2 changeover of B to A
The principle of the 2/3c changeover is shown in the simplified diagram in figure 12-3.
source A source B
coupler
outgoing feeders
In normal operation the coupler circuit-breaker is open. Each supply feeds one bus section.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
If one of the supplies is lost the coupler circuit-breaker is closed, and the other supply feeds all
the outgoing feeders (see fig. 12-4).
2/3c changeover of B to A
open closed
- 3 sources feeding a busbar with or without coupler (see fig. 1-25 and 1-26)
- a double busbar, with 2 isolators and a circuit-breaker on each supply and on each outgoing
feeder (see fig. 1-15)
- two interconnected double busbars with 2 isolators and a circuit-breaker on each supply
and outgoing feeder (see fig. 1-16).
- short-break changeover. The load is disconnected before the internal generators come on
line. The generators then progressively restore the load
- progressive no-break changeover. The utility and internal generators are connected in
parallel, generator power being progressively increased until it reaches the level required by
the load. The utility supply is then disconnected
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
- changeover for a permanent operation of utility and generators in parallel. The generators
will then either only supply a part of the energy required, or else deliver power to utility
network.
Paralleling up the utility supply with the internal generators requires the installation of a
synchronizer, as well as a fast-acting disconnection protection to enable the industrial network
to be isolated in the case of a short circuit, a supply interruption or high levels of disturbance
on the utility distribution network.
busbar
A1 B1
I > I >
A2 B2
substation 1 substation 5
A3 B3
A4 B4
substation 2 substation 4
A5 B5
A6 B6 open
substation 3
fault detector
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
In normal operation the loop is open. In figure 12-5, we assume that the loop at B6 is open.
The loop head circuit-breakers at A1 and B1 are fitted with an overcurrent protection.
Phase-to-phase and phase-to-earth fault detectors are installed at each switch location. They
indicate the passage of a fault current.
The automatic loop reconfiguration function controls the switches in a way that re-establishes
the supply after a fault on the loop:
- by reconfiguring the loop so as to restore supply to all secondary substations. If the fault is
on a substation busbar, the substation is no longer supplied.
- the overcurrent protection at A1 detects the fault and causes the circuit-breaker A1 to be
tripped
- the fault detectors located at A2 and A3 indicate the passage of a fault current, the other
detectors giving no indication. The fault is located. Automatic loop reconfiguration opens
switches A3 and A4 so as to isolate the faulty zone
- the system then closes switch B6 and circuit-breaker A1 providing supply once more to
substations 1, 2 and 3.
After the faulty cable has been repaired the operator can instruct the system to return to the
normal configuration, i.e. with only switch B6 in the open state.
The control and monitoring system performance is such that loop reconfiguration takes place
in less than 10 seconds, including switch operating times.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
n parameter setting
- the minimum post restoration time, i.e. once a load has been restored, the minimum length
of time which must elapse before the same load can be shed once more (to avoid any
"pumping" effects)
The control and monitoring system controls load shedding/recovery according to the
parameters set by the operator. The choice of loads to shed or to restore is governed by a
hierarchically defined algorithm.
Level n loads are shed one by one, and if the load-shedding requirement is not entirely met by
level n, level n-1 loads follow, and so on. Level 1 loads must never be shed.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
Loads having the highest priority level are restored first, beginning with the last load to have
been shed in the priority level concerned. If the possibility for load restoration has not been
entirely filled by the loads belonging to this level, the loads belonging to the next level may be
restored, and so on.
In any case, a hysteresis type mechanism must be integrated into the operation of the control
and monitoring system, so as to avoid pumping occurring, which could reduce the useful life of
switching devices and loads.
- permanently evaluate the quantity of energy consumed over the contract-based integrating
period to allow any overshoot of subscribed demand to be estimated
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
Estimating the energy which will have been consumed over a complete integrating period is
done using the energy consumed between the start of the period and a time t0 , to which is
added an estimation of the energy that will be consumed from t0 until the end of the period,
i.e. at time T (see fig. 12-6).
Pt
power
power estimated at instant t 0
P$ (t ) 0
0 t0 T time
integrating period T
Figure 12-6: estimating the energy consumed over the integrating period
E$ ( t0 ) = z
0
t0
P ( t ) dt + P$ ( t0 ) × ( T − t0 )
P$ ( t0 ) is the estimated power for the period [t 0 → T ] , at the instant t0 . It is calculated from the
values of power measured over a time λ before the instant t0 :
P$ ( t0 ) =
1 t0
z
λ t0 − λ
P ( t ) dt
P$ ( t0 ) is thus the mean value of consumption at the instant t0 during a period λ . The value of λ
can be set to several minutes.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
Let Ps be the subscribed demand, or the power consumption which must not be exceeded,
and ∆ P the value of power to be shed or restored. We have:
E$ (t 0 )
∆ P = Ps −
T
Estimating energy consumption using a mean value over a period λ enables peaks to be
filtered out, thus avoiding load shedding commands being issued on occurrence of a
temporary overload; motor starting or welding machine operations for example.
The control and monitoring system is permanently calculating the ∆ P value, and as a result
may issue a load shedding or restoration command.
The load shedding operation itself has no time constraint since the integrating period is quite
long; it can therefore be carried out over several seconds.
These overloads are allowed for periods of several minutes, and there is no time constraint on
transformer protection on occurrence of an overload. For very high currents (in the event of a
short circuit), the transformer will be protected by overcurrent protection devices (see § 10.3. of
the Protection guide).
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
The command to shed load is given by the alarm threshold of a thermal probe or a thermal
overload protection. The value of power to be shed ∆ P is the difference between the power
consumed and the transformer rated power (or a value inferior to it).
After a given period, determined by the time constant of the transformer and its operating
conditions, there is load restoration equal to the difference between the rated power (or a
value inferior to it) and the power consumed.
Load shedding dependent on a thermal overload protection (or thermal probe) threshold allows
transformer load shedding by overcurrent to be avoided for overloads that the transformer is
able to allow for a certain period of time.
Since transformers can tolerate abrupt changes in load it is not necessary to carry out
immediate shedding when one transformer is lost due to a fault. The remaining transformer will
continue supplying the full load power.
Load shedding will, if necessary, take place depending on the power being consumed and
information coming from the transformer thermal overload (or thermal probe) protection, where
such protection exists.
n overload
This situation occurs when a slow increase in load results in a demand for power in excess of
the production capacity.
n a fall in production capacity (operation disconnected from the utility) or the loss of
utility supply (operation connected to the utility)
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
n electrical incidents
They include:
A dynamic stability analysis (see § 11) will clarify which loads need to be shed in order to
maintain the stability of the network.
- carry out load-shedding within a time that enables network stability to be maintained.
n load restoration
Once the network is stable following a load shedding operation, and the available power is
greater than that demanded by the load, restoration operations become possible.
Load restoration must be carried out in stages since generators cannot tolerate large load
impacts.
A stability analysis allows the load restoration stages to be determined, i.e. the load impacts
permitted by the generator sets in relation to the power that they supply.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
o case of motors
Following an interruption of supply, motors maintain a remanent voltage during the time it
takes the flux to collapse (in the order of a second). Rapidly reconnecting the supply could
result in a coupling of opposite phase voltages. The resulting electrical and mechanical
transients could quite easily damage the motor.
Once load shedding has taken place, the control and monitoring system will inhibit restoration
operations involving any busbar which supplies motors until the remanent voltage appearing
on the busbar falls below a predefined threshold (of the order of 20 % of the nominal voltage).
Where a minimum remanent voltage protection system is fitted to the busbar (code ANSI 27R),
reconnection is enabled directly through the protection digital output signal.
- verify the absence of remanent voltages due to motors on the busbars being re-supplied
n time constraints
Given that overload conditions develop relatively slowly, a load shedding response to an
overload need not be rapid, a time of several seconds being allowable.
On the other hand, stability studies may show that when a fault condition occurs load shedding
must happen quickly in order to maintain the stability of the network. In such a case, load
shedding must take no more than several hundred ms.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
For this reason, the simultaneous energizing of all or part of the transformers may cause
spurious tripping of certain overcurrent protections.
To avoid this, the control and monitoring system must handle the supply of power to all or part
of the installation by energizing transformers in groups (including energizing a single
transformer).
The refusal will generate an explanatory message at the operator's control station.
CB1 CB2
Sources 1 and 2 are generated completely separately. When both transformers are supplied
the system will refuse to close CB2 if CB1 is also closed, and vice versa.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
upstream circuit-breaker
downstream circuit-breaker
When the operator or protection device opens the upstream circuit-breaker, the control and
monitoring system opens the downstream circuit-breaker.
In addition, closure of the downstream circuit-breaker is not allowed if the upstream device is
open.
Note: in general, a fault detected by the protection system will directly open both circuit-breakers.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
When the two busbars are coupled, only one of the two earthing transformers should be in
service to avoid doubling the value of any potential earth fault current.
After closing the coupler circuit-breaker, the control and monitoring system must eliminate one
of the two earthing transformers.
G G
TR1 TR2
busbar 1
busbar 2
coupler
circuit-breaker
earthing earthing
transformer n° 1 transformer n° 2
Figure 12-9: switching of two earthing transformers on double busbars with coupler
The system controls switched steps capacitor banks so as to maintain the level of reactive
power consumed below the utility's uninvoiced consumption value.
Note: in certain cases, benefit might be obtained by "totally" compensating the reactive energy in
order to reduce the current, Joule losses and voltage dips to a minimum. (see § 7).
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
Reactive power can be supplied from the capacitors and the generators.
The stability of generators is improved when they supply reactive power. As a consequence,
part of the reactive power is provided by the generators, with the remainder being supplied by
the capacitors.
However, in the even of loss or considerable reduction in load, it becomes imperative to take
the capacitors out of service in order to prevent generator instability occurring.
The system controls the reactive power provided by the generators to keep the reactive energy
consumed below the reactive power uninvoiced by the utility.
In this situation the generators are supplying the required reactive power, and therefore the
varometric regulation function is inhibited. On the other hand, voltage regulation works to keep
the reactive power production-consumption balanced.
Typically, generators are rated so as to be capable of supplying a value of cos ϕ = 0.8 on full
load.
If the (inductive) cos ϕ value for the load is below 0.8 (a rare occurrence), the capacitor banks
can supply the difference.
Metering covers a specific period (tariff period, an hour, a day, a week, a month, etc.).
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
- periodically
The measurement results are transmitted to the operator's control station to be analysed. They
could equally trigger off an alarm.
n parameter setting
Parameters are set in order to schedule load operating periods, i.e. the start/stop times.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
12.2.11. Tariff-management
The control and monitoring system must carry out control of loads for which "tariff-
management" has been defined, according to the current tariff period.
- or by the control and monitoring system in relation to the time and the tariff details specified
in the contract with the utility.
n parameter setting
Parameters are set to define load start / stop times in accordance with the tariff period.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
- determine the number of generator sets that need to be started to match the requirement
for power.
- manage active and reactive power sharing between the generator sets (see § 4), i.e. the
percentage power, i % , supplied by each generator set in relation to the power required,
n
where ∑ i % = 100 .
1
- control generator loading; this being carried out in stages so as to maintain the voltage and
frequency within their acceptable ranges
- regulate generator set frequency by adjusting the power supplied by the drive machines
- regulate the voltage supplied by the generator sets by adjusting generator excitation.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
o active and reactive powers supplied by the generator sets are constant
The active and reactive powers supplied by the generator sets are regulated to set-point
values, with any variations in demand then being met by the utility.
- determine the number of generator sets to be started in relation to the power set-point
- manage active and reactive power sharing between the generator sets (see § 4), i.e. the
percentage power, i % , supplied by each generator set in relation to the power set-points,
n
where ∑ i % = 100 .
1
- control the drive machine power so that the generator sets are loaded
- regulate the active power supplied by the generator sets by adjusting the drive machine
power control
- regulate the reactive power supplied by the generator sets by adjusting generator
excitation.
Note: active and reactive powers supplied by the utility can be negative, in which case the generator
sets will supply power to the utility. The control and monitoring system must be able to operate
for positive or negative utility powers.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
The active and reactive powers supplied by the utility are regulated to set-point values
(subscribed demand values for example), with variations in load being withstood by the internal
generator sets up to the limit of their capacity.
The power that must be supplied by the generator sets (i.e. the power required) is the
difference between the load power and the utility set-point value.
- determine the number of generator sets to be started in relation to the power required
- manage active and reactive power sharing between the generator sets (see § 5), i.e. the
percentage power, i % , supplied by each generator set in relation to the power set-points,
n
where ∑ i % = 100 .
1
- regulate the active power supplied by the utility to the set-point value, by adjusting the
power control of the drive machines so as to maintain:
Pg = Pld − Pusp
- regulate the reactive power supplied by the utility to the set-point value by adjusting
generator excitation so as to maintain:
Qg = Qld − Qusp
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
Note : the utility active and reactive power set-point values can be negative, in which case the
generator sets then supply power to the utility. The control and monitoring system must be able
to operate for positive or negative utility powers.
o the active power supplied by the generator sets and the reactive power supplied by
the utility are constant
The active power supplied by the generator sets is regulated to a set-point value. Variations in
the active power are then met by the utility.
The reactive power supplied by the utility is regulated to a set-point value (uninvoiced limit
value, for example). Variations in reactive power are then withstood by the generator sets up
to the limit of their capacity.
The reactive power that must be supplied by the generator sets is the difference between the
reactive power of the load and the utility set-point value (or cosϕ ).
- determine the number of generator sets to be started in relation to the active power set-
point and the reactive power required
- manage active and reactive power sharing between the generator sets (see § 5), i.e. the
percentage power, i %, supplied by each generator set in relation to the active power set-
n
point and the reactive power required, where ∑ i % = 100
1
- control the drive machine power in order to load the generator sets
- regulate the active power supplied by the generator sets by adjusting the drive machine
power control
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
- regulate the reactive power supplied by the utility to the set-point value by adjusting
generator excitation (or alternatively by adjusting the tap-changer of the transformer
connected to the utility supply) so as to maintain:
Qg = Qld − Qusp
Note: the utility active and reactive power set-point values can be negative, in which case the
generator sets then supply power to the utility. The control and monitoring system must be able
to operate for positive or negative utility powers.
On changeover from operation connected to the utility to operation disconnected from the
utility, the control and monitoring system automatically switches from active and reactive power
regulation to frequency and voltage regulation.
Events are recorded to a precision of 1 ms, with a separating capability between events of
10 ms.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
The record of an event includes pre and post event timings, both of which are configurable.
For example, the pre-event timing may be configured to be between 100 ms and 2 seconds.
Likewise, the post-event timing may be configured to be between 100 ms and 20 seconds.
The fault recorder data collected are transmitted to a dedicated operator terminal via the
control and monitoring system serial link.
The terminal runs software capable of presenting the data in the form of curves or as tables of
values.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
n standard architecture
In order to run an electrical network and its associated automatic systems, a control and
monitoring system uses computer hardware in combination with a set of software applications
all of which communicate over a network.
Figure 12-10 gives a schematic representation of control and monitoring system architecture.
The system must be able to communicate with all low, medium and high-voltage electrical
equipment under its control.
server
computer operator stations
synchro signal
local network
substation
substation
MV switchboard MV switchboard
switchboard
control
centre internal bus
LV switchboard LV switchboard
electrical equipment
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
Carrying out the network supervision data processing, this machine manages the real-time
database and communication with the switchboard control centres.
It must perform well enough to correctly manage the electrical network. For large systems a
mini-computer is generally used while for smaller systems a microcomputer is adequate.
Mains/Standby server redundancy is sometimes built in to improve control and monitoring
system availability.
o operator stations
Operator stations provide the control and monitoring system user graphical interface and they
may be located in the installation control room or in substations. They may comprise either
work stations, PCs or terminals depending on the particular requirements.
o maintenance terminal
The maintenance personnel are equipped with a PC that can be connected to any point on the
communication network (especially in each substation).
This enables personnel to modify substation controller programmes and monitor the
communication network.
o printers
These supply a printout of information as it becomes available (events or alarms) and printouts
of reports and screen captures.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
These are programmable controllers, or the equivalent, which handle the following functions:
- event dating
The function of the gateway is to allow information to pass between the control and monitoring
system and other existing computer systems (industrial processes, administrative
management, etc.).
Data can either be exchanged with the main server computer database or directly with the
switchboard control centres.
o communication network
It allows:
- exchange of data between the switchboard control centres and the server.
- where necessary, communications between other computer systems via the gateway.
- the constraints of long distance between substations and complicated geographic dispersal
to be overcome.
The use of fibre optic cables enables data communication over long distances, and eliminates
potential problems due to electromagnetic disturbance.
The network data rate is high (greater than 10 Mbits/s); Ethernet for example.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
o internal bus
The internal bus facilitates data communication between a substation's electrical equipment
and the switchboard control centre.
The various elements of the control and monitoring system which receive data about the state
of the electrical network must be synchronized (protection devices, substation controllers,
server, etc.).
Indeed, the system must be able to show that a substation circuit-breaker has been tripped
before another circuit-breaker in another substation, with separating capability between events
of less than 10 ms.
The preferred choice is to use an external, high precision electronic clock operating
independently of the system in case of a supply failure.
The clock supplies a date, and this is used as the reference distributed to all equipment which
records changes of state, alarms, etc.
o upgradability
The architecture of the control and monitoring hardware and software must be designed to be
easily upgradable in terms of functions and processing capacity in order for the electrical
network to be accommodated without sacrificing any of the initial investment.
In the case of installations requiring a high degree of reliability and dependability, redundancy
at server or network level can be built into the system.
For large systems, a dependability analysis is used to establish the determining factors
governing the suitability of the control and monitoring solution proposed (see § 12). It enables
the areas for duplication to be defined, depending on the needs and constraints of each
application.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
They offer the possibility of setting parameters and configuring the control and monitoring
system to adapt it to changing requirements. The operator who interacts with the control and
monitoring system then has access to all real-time variables and recorded variables which give
a global picture of the state of the electrical network.
Following a description of the general principles behind the user interface we will detail the
functions offered to the operator for control and monitoring of the electrical network.
Designing a user interface consists in defining a computer tool corresponding to the user's
needs which is both easy to learn and simple to use.
Different sciences (ergonomics, psychology, etc.) contribute to the inclusion of the specifically
human-related elements in the design. However, other characteristics are based on the actual
practices and customs common to a particular working environment and are therefore
determined through experience.
The graphic user interface is generally developed using a standard "Windows" type system.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
The "look and feel" system is used, based on the principle of uniformity:
- all screens are designed with the same basic structure such that the same information can
always be found in the same screen area.
- to access a function, the operator carries out the same actions whatever the state of the
user interface.
- tables of values.
- curves.
- reports.
- etc.
n system functions
Depending on the operator's duties, the functions offered by the system will allow him/her to
achieve the required end results. They concern real-time system monitoring, analysis or
maintenance operations.
The system generally has built-in access codes limiting the functions available to a user in line
with his/her duties and responsibilities.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
Single-line wiring mimic diagrams offer a dynamic representation of the electrical network
updated in real time.
- the values measured at different points on the network (voltages, currents, powers, etc.)
- the state of the power supply to the different busbars and cables using colours symbolising
the presence, or not, of voltage and its level.
Several mimic diagrams are provided showing different layers of detail, from a global network
diagram down to a detailed representation of each switching device with its measured values.
- a general single-line diagram giving a complete view of the network showing the various
substations and electrical connections.
- a substation single-line diagram (for each substation) showing each switching device, its
open or closed state, the current flowing through it, etc.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
The control and monitoring system dates alarms and events with a separating capability of
ten milliseconds. The system also supplies a chronological, running printout of them.
o events
Each event is logged and stored on the hard disk, allowing the operator to monitor the
installation with precision. If an event has been declared alarmable its occurrence will generate
an alarm.
- events recorded to the millisecond. These come from the electrical network and comprise
switching device changes of state, protection activation, etc. They are presented to the
operator chronologically and are date-stamped either at the device location or by the
switchboard control centre.
- events recorded to the second. These come from the control and monitoring system and
comprise parameter modifications, operator interventions (alarm acknowledgement, remote
commands), communication faults, messages sent to other operators, etc. and are date-
stamped by the main server computer.
- a running printout.
- on the screen which, updated by each new event, only shows the last events which
occurred.
- an audit trail of events recorded on the hard disk. In this way, the event history can be
analysed if a fault occurs, or used to compare the chronology of two situations.
- explanatory message.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
o alarms
An alarm results from the occurrence of an event that has been declared alarmable. Thus an
alarm appears in both the events list and in the list of alarms.
- a control and monitoring system fault (substation controller, communication network, etc.).
In general, a value of importance is assigned which corresponds the seriousness of the alarm.
The operator may acknowledge the alarm once he/she has become aware of it.
- non-activated.
- activated and not acknowledged.
- activated and acknowledged.
- a running printout.
- on the screen. Two lists are displayed, one containing unacknowledged alarms and the
other showing acknowledged alarms. The screen is updated for each new alarm, and only
shows the last alarms to appear.
- alarm history recorded in files on the hard disk, permitting a detailed follow up analysis to be
displayed.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
- explanatory message.
- importance.
A user with the correct access level can remotely control electrical devices from an operator
station.
- generators.
- transformer tap-changers.
- if the command is not executable (interlocking, locally controlled device, faulty device) it is
forbidden. A message is displayed explaining why.
- if the command can be executed the operator must confirm his/her request. The command
is then transmitted to the device via the switchboard control centre.
- when the command has been executed the device returns a "command executed" message
and updates the mimic display.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
n measurement display
Measured (current, voltage) or calculated (power, energy, etc.) electrical values can be
displayed on the mimic diagrams, listed in tables or shown as curves.
Thus on the single-line mimic diagram the main electrical values (current, voltage) are
displayed close to the elements to which they refer. The secondary electrical values are shown
on the detailed diagram associated with the electrical device.
This notion of main and secondary values avoids diagrams being crammed with too much
detail by limiting the display to essential information only.
The numerical values are sent from the network to the computer in cyclical periods, within a
period of several seconds. They are recorded so that reports and analyses can be drawn up.
n curves
The system offers the possibility of displaying curves representing the change in numerical
values over time.
n reports
Reports contain measurements, calculations, operations, etc. and are drawn up for various
periods of time: tariff periods, day, week, month, year.
An operator can therefore keep track of the changes in operation of the electrical installation.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
- events, alarms.
History files are created automatically, and cover predetermined operating periods.
The operator can then refer to a set of history files which correspond to time periods (day,
week, month, etc.).
When accumulated history files begin to take up too much space, in order to avoid the system
becoming saturated they are archived externally on to a magnetic medium.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
n sorting
It is based on different criteria, e.g. dates, equipment reference, alarm importance, etc.
n message list
The system offers a message list which allows the various operators to send one another
instructions and other information relating to the behaviour of the network.
On-line help is a function that offers operators supplementary information on the significance
of a function or the way to complete a sequence of operations.
The operator can also access animated mimic displays of the control and monitoring system.
Since the displays are updated in real time, a faulty system element can quickly be spotted.
For large installations where availability is of paramount importance, the system offers a
function which allows the network behaviour to be simulated in the event of an incident and
when the operator carried out switching operations.
Its use as a training function improves the operators' skills in reacting to incidents on the
network.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
CHAPTER 12 BIBLIOGRAPHY
n standards
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.
Publication, traduction et reproduction totales ou partielles de ce document sont rigoureusement interdites sauf autorisation écrite de nos services.
The publication, translation and reproduction, either wholly or partly, of this document is not allowed without our written consent.