Nepal Electricity Authority: Detail Feasibility Study OF Chandrapur - Sukdev Chowk 132 KV Transmission Line Project
Nepal Electricity Authority: Detail Feasibility Study OF Chandrapur - Sukdev Chowk 132 KV Transmission Line Project
Nepal Electricity Authority: Detail Feasibility Study OF Chandrapur - Sukdev Chowk 132 KV Transmission Line Project
Final Report
January, 2021
Detailed Feasibility Study Report
Chandrapur – Sukdev Chowk 132 kV Transmission Line Project
Grid Development Department, Nepal Electricity Authority
General Information
Issue Register
Number of
Distribution List Date Issued
Copies
NEC 1
NEC Staff
NEC Board
NEA 23th June 2020 2 Copy
Misc.
www.neaec.com.np
Table of Contents
1 Executive Summary........................................................................................................2
1.1 Introduction................................................................................................................. 2
1.8.1 Assumption......................................................................................................6
2 Introduction..................................................................................................................... 9
4 Desk Study.................................................................................................................... 12
5 Reconnaissance Survey...............................................................................................18
6 Detailed Survey.............................................................................................................21
7.1.5 Altitude........................................................................................................... 27
7.6 Insulators.................................................................................................................. 37
10 Substation Design........................................................................................................58
10.3.4 DC System.....................................................................................................64
11 Technical Specifications..............................................................................................69
13 Cost Estimate..............................................................................................................111
14.2 Assumption.........................................................................................................114
17 Annex........................................................................................................................... 120
List of Tables
Table 12-2: Peak Load at Different Substation Considered for Load Flow..............................97
List of Figures
Figure 11-1: Load Flow Results for Sukdev Chowk Substation at 132 kV Bus.....................105
Figure 11-2: Load Flow Results for Sukdev Chowk Substation at 33 kV Bus.......................106
Abbreviations
AP Angle Point
BS British Standard
CT Current Transformer
DC Direct Current
Hz Hertz
IS Indian Standard
kg Kilograms
km Kilometer
kN Kilo Newton
kV Kilo Volts
M Meter
mm Millimeter
NC Normally Closed
NO Normally Open
PS Protection Special
PT Potential Transformer
S/S Substation
SN Serial Number
TL Transmission Line
ANNEX
Annexure-1 : Transmission Line Tower Structure in Topo Map
Annexure-2 : Transmission Line Plan Profile Drawing
Annexure-3 : Weight Span Report and Material Scheduling Report
Annexure-4 : Electrical and Substation Layout Drawings
Annexure-5 : Cost Estimate of Transmission Lines and Substations
Province 2
Right of way 18 m
1
NEA Engineering Company Limited
Thapathali, Kathmandu
Detailed Feasibility Study Report
Chandrapur – Sukdev Chowk 132 kV Transmission Line Project
Grid Development Department, Nepal Electricity Authority
The tower spotting of the transmission line route is shown in Plan and Profile drawings (Annex
2) and the tower scheduling report showing total number of towers and tower types is as
shown in Section 9.1 Tower Structures below.
The detail tower spotting and scheduling suggests following number of different tower types.
Type of Towers:
- DA: 87
- DB: 11
- DC: 9
- DD: 6
The 113 number of tower structures determined from tower spotting are tabulated below,
along with their coordinates.
2
NEA Engineering Company Limited
Thapathali, Kathmandu
Detailed Feasibility Study Report
Chandrapur – Sukdev Chowk 132 kV Transmission Line Project
Grid Development Department, Nepal Electricity Authority
3
NEA Engineering Company Limited
Thapathali, Kathmandu
Detailed Feasibility Study Report
Chandrapur – Sukdev Chowk 132 kV Transmission Line Project
Grid Development Department, Nepal Electricity Authority
4
NEA Engineering Company Limited
Thapathali, Kathmandu
Detailed Feasibility Study Report
Chandrapur – Sukdev Chowk 132 kV Transmission Line Project
Grid Development Department, Nepal Electricity Authority
8.1
5
NEA Engineering Company Limited
Thapathali, Kathmandu