Potential Damage PKT
Potential Damage PKT
It is considered that a risk based approach to assessment of plant has resulted in the avoidance of a
significant number of possible failures which had the potential to cause significant loss of life,
damage to plant or both. A listing of many of these is included in Table 1 -1.
Table 1-1 Summary of Problems Found on Eight Ammonia and Downstream Plants Through a Risk- Based Assessment Analysis
Process
Plant Age (y) Equipment type Damage mechanism highlighted On-stream failure prevented
type
A1 Ammonia 35 Reformer outlet Leaking reformed gas to atmosphere,
Creep fatigue cracking – bend- ing
manifold tee- risk
moments in manifold arms
cone of fire & personnel injury; 2-3
weeks lost production
Process
Plant Age (y) Equipment type Damage mechanism highlighted On-stream failure prevented
type
Mixed feed coil Potential for equipment
(reformer Creep - localised damage due to coil
damage, 2-3 weeks lost
effluent) design (hot spots)
production
Potential for tube failures, 1-2
Hydrogen damage / creep – long
Reformed gas weeks to plug failed tubes / 6
term localised overheating of
WHB weeks to re-tube
tubes
boiler
Leaking process gas to atmosphere,
H2-assisted cracking – PWHT soak
HT shift risk
temperature too low, HAZ
converter of fire & personnel injury; 2-3
too hard
weeks lost production
Leaking process gas to atmosphere,
Stress corrosion cracking of
Mixed-feed risk
expansion bellows – low level
preheater of fire & personnel injury; 2-3
chlorides in steam
weeks lost production
Tube failure; 2-3 days to plug failed
Microbial induced corrosion –
Sulfinol cooler tubes / 6 weeks to re-tube
cooling water velocities too low
exchanger.
Leaking process gas to atmosphere,
H2-assisted cracking – PWHT soak
risk
temperature too low, HAZ
Methanator of fire & personnel injury; 2-3
too hard
weeks lost production
Leaking process gas to atmosphere,
H2-assisted thermal fatigue
Ammonia risk
cracking – S/up procedure &
converters of fire, explosion & personnel
material properties
injury; >3 weeks lost production
Localised corrosion of liner –
operational problems with purge Corrosion damage to shell; plant
Urea reactor off line for 2-3 weeks to repair.
water
Potential for catastrophic failure of
Potential for brittle fracture
Ammonia pressure vessel, severe property
A2 Urea 35 during low temperature/re-
collector damage, high personnel safety &
pressure excursion
environment risk.
Localised corrosion adjacent
baffles – stainless steel baffles, Perforation of shell; cooler off line
MEA coolers for 1-2 days to repair.
steel shell
B1 Ammonia 35 Potential for equipment
HT S/H steam coil Carbon steel sections - end of
damage, 2-3 weeks lost
- reformer creep life, CrMo sections - OK
production
Leaking reformed gas to
Reformer outlet Localised creep fatigue damage atmosphere, risk of fire & personnel
manifold due to manifold design. injury; 2-3 weeks lost production
Potential for tube failures, 1-2 weeks
Hydrogen damage / creep – long
Reformed gas to
term localised overheating of
WHB plug failed tubes / 6 weeks to
tubes
re-tube boiler
Potential for catastrophic failure of
Potential for brittle fracture
Purge gas pressure vessel, severe property
during low temperature/re-
separator damage, high personnel safety &
pressure excursion
environment risk.
Creep - localised damage due to coil Potential for equipment
Auxiliary boiler
design (hot spots) damage, 2-3 weeks lost
Process
Plant Age (y) Equipment type Damage mechanism highlighted On-stream failure prevented
type
production
Potential for catastrophic failure of
HTHA of C 0.5Mo steel
pressure vessel, severe property
operating above CS Nelson
Methanator damage, high personnel safety &
Curve.
environment risk.
Potential for catastrophic failure of
HTHA of C 0.5Mo steel
NH3 converter pressure vessel, severe property
operating above CS Nelson
effluent exch. damage, high personnel safety &
Curve.
environment risk.
Potential for catastrophic failure of
HTHA of C 0.5Mo steel pressure system, severe property
NH3 converter operating above CS Nelson damage,
Effluent piping Curve. high personnel safety & environment
risk.
Leaking process gas to atmosphere,
Chloride induced stress
CO2 stripper risk
corrosion cracking beneath
gas reboiler of fire & personnel injury; 2-3
lagging
weeks lost production
Leaking process gas to
Chloride induced stress
Shift effluent atmosphere, risk of fire &
corrosion cracking beneath
BFW heater personnel injury; 2-3 weeks lost
lagging
production
Potential for catastrophic failure of
Transition section Potential for HTHA damage due to pressure system, severe property
– Sec. reformer on-going refractory problems damage, high personnel safety &
environment risk.
Thermal fatigue cracking due to Leaking HP steam to atmosphere; >3
fast start-up procedure (heavy weeks lost production,
Steam drum
wall drum) potential for personnel injury
Localised corrosion from poor
cooling water treatment (scaling Tube failure; 2-3 days to plug failed
Cooler
leading to high tube wall tubes / 10 weeks to re-tube
condenser
B2 Nitric acid 35 temperatures). exchanger.
Tubes at end of life due to
Waste heat prolonged operation 450 Tube failure; 2-3 days to plug failed
boiler embrittlement range. tubes / 6 weeks to re-tube boiler.
Leaking reformed gas to
Reformer outlet Localised creep fatigue damage atmosphere, risk of fire & personnel
manifold due to manifold sag. injury; 2-3 weeks lost
production
Leaking reformed gas to
Primary to sec Localised creep fatigue damage of atmosphere, risk of fire & personnel
C Ammonia 30 reformer pipe Inconel 182 welds injury; 2-3 weeks lost production
Reformed gas Localised corrosion of tubes in Tube failure; 1 week to plug failed
WHB tube to tubesheet crevice tubes / 4 weeks to re-tube boiler.
Potential for tube failures, 1-2
Hydrogen damage / creep – long
Reformed gas weeks to plug failed tubes / 6
term localised overheating of
WHB weeks to re-tube
tubes
boiler
Process
Plant Age (y) Equipment type Damage mechanism highlighted On-stream failure prevented
type
Potential for catastrophic failure of
HTHA of C 0.5Mo steel
pressure vessel, severe property
operating above CS Nelson
HT shift damage, high personnel safety &
Curve.
environment risk.
Reformed gas Localised corrosion of tubes in Tube failure; 1 week to plug failed
WHB tube to tubesheet crevice tubes / 4 weeks to re-tube boiler.
Potential for tube failures, 1-2
Reformed gas Hydrogen damage / creep – long
weeks to plug failed tubes / 6
WHB term localised overheating of tubes
weeks to re-tube boiler
D Ammonia 35 Potential for equipment
Sec process
Coils approaching end of creep life damage, 2-3 weeks lost
steam S/H
production
Perforation of shell, process gas
Localised pitting from carbonic acid
to atmosphere; 1 week lost
attack in high impingement
Knock-out pot production to
areas
repair, potential fire risk
Potential for catastrophic failure of
HTHA of C 0.5Mo steel
pressure system, severe property
operating above CS Nelson
Synloop piping damage, high personnel safety &
Curve.
environment risk.
Leaking reformed gas to atmosphere,
Reformer outlet Localised creep fatigue damage risk
manifold due to manifold sag. of fire & personnel injury; 2-3 weeks
lost production
E Ammonia 20
Leaking reformed gas to atmosphere,
Ref product / feed Hydrogen embrittlement of risk
gas exch Inconel 600 bellows. of fire & personnel injury; 2-3
weeks lost production
Leaking reformed gas to
Hydrogen assisted cracking of
Syn Loop BFW atmosphere, risk of fire & personnel
channel to tubesheet weld
Pre-heater injury; 2-3 weeks lost
(PWHT inadequate)
F Ammonia 2 production
Risk of tube to tubesheet weld Tube failure; 2 weeks to repair/plug
cracking – weld procedure cracked welds / 6 weeks to re-tube
Synloop WHB
inadequate boiler.
Potential for tube failures, 1-2 weeks
Hydrogen damage / creep – long
Reformed gas to
term localised overheating of
WHB plug failed tubes / 6 weeks to
tubes
re-tube boiler
Burner failure; plant off line for 1-2
Sec reformer Creep fatigue cracking at
weeks to repair existing / install
Burner dissimilar metal weld
new burner
Potential for catastrophic failure of
Potential for brittle fracture
Purge gas pressure vessel, severe property
during low temperature/re-
separator damage, high personnel safety &
pressure excursion
environment risk.
Cracking of non annealed
Steam pre Inconel 600 exchanger tube Tube failure; 2 weeks to plug failed
super-heater return bends tubes / 6 weeks to re-tube boiler.
Process
Plant Age (y) Equipment type Damage mechanism highlighted On-stream failure prevented
type
SCC of tube to tubesheet welds Tube failure; 2 weeks to repair/plug
MP reformed gas – caustic wash during cracked welds / 6 weeks to re-tube
cooler commission boiler.
Potential for tube failures, 1-2
Reformed gas Hydrogen damage / creep – long
weeks to plug failed tubes / 6
WHB term localised overheating of tubes
weeks to re-tube boiler
G Ammonia 2 Leaking reformed gas to atmosphere,
Creep fatigue cracking of outlet risk
Reformer manifold tee to cone weld of fire & personnel injury; 2-3
weeks lost production
Potential for catastrophic failure of
Potential for brittle fracture
pressure vessel, severe property
during low temperature/re-
MP flash drum damage, high personnel safety &
pressure excursion
environment risk.
Leaking reformed gas to
Creep fatigue cracking of outlet atmosphere, risk of fire & personnel
Reformer manifold tee to cone weld injury; 2-3 weeks lost
production
Potential for tube failures, 1-2 weeks
Hydrogen damage / creep – long
Reformed gas to
term localised overheating of
WHB plug failed tubes / 6 weeks to
tubes
re-tube boiler
Leaking reformed gas to atmosphere,
H2-assisted cracking of inlet
H1 Ammonia 2 Reformed gas risk
nozzle to channel weld;
WHB of fire & personnel injury; 2-3
inadequate PWHT
weeks lost production
Tube failure; 2-3 days to plug failed
Synloop Microbial Induced Corrosion –
tubes / 4 weeks to re-tube
intercoolers cooling water velocities too low
exchanger.
Potential for catastrophic failure of
Potential for brittle fracture
pressure vessel, severe property
during low temperature/re-
MP flash drum damage, high personnel safety &
pressure excursion
environment risk.
Cooler SCC of stainless steel inlet
condenser nozzle in cooling water jacket Plant off line for 5-7 days to repair.
H2 Nitric acid 2 Potential for localised pitting Tube failure; 2-3 days to plug failed
corrosion -condensing droplets of tubes / 6 weeks to re-tube
Economiser
nitric acid exchanger.
Ammoni
Pipe reactor Localised corrosion (3mm/yr); Plant off line for 1-2 days,
H3 um 2
separator material inadequate for duty potential for personnel injury.
nitrate