Project Management Essential Notes
Project Management Essential Notes
Management
Essential Notes
Not to end up like the hamster...
2.4 Monitor and Control Project Work 10 7.3 Develop Project Team 22
• A program is a set of related projects • The project life cycle is a set of steps
that are managed in a coordinated way that connect the beginning of the
to gain benefits not obtainable with project to its conclusion
separate management
• For each phase:
• A portfolio is a set of projects/program
grouped together for easy management homogeneous grouping of activity
from business and use of resources
point of view one or more products result
(deliverable)
Figure: balanced matrix organization:
coordination is made by one resource of the
project who is named project
manager/coordinator
It is the only document not in charge of the PM, ● Summary of the critical elements of the
but if the the Project Sponsor. project.
● Purpose and measurable objectives of the ● The relationships and work process
project between actors.
● High-level description of the project, limits ● Frame for Project Launch Meeting & Project
and main deliverables Review.
● Risks analysis shared by Project Team. Executing the work defined in the Project
Management Plan to achieve the project’s
A sample table of contents could be the
requirements defined in the project scope
following:
statement.
• 0. PREAMBULE
• I. GENERAL PRESENTATION OF
THE PROJECT 2.4 Monitor and Control Project
Work
− I.1. CUSTOMER
− II.8. QUALITY
Finalising all activities to formally close the
MANAGEMENT
project phase.
− II.9. PROJECT WORK
PROCESS AND
COMMUNICATION
− II.10. PERFORMANCE
MEASUREMENT
Exhaustiveness
Any unique and verifiable product, result or
capability to perform a service that must be • It covers all the products, services and
produced to complete a process, phase or activities
project. Often used in reference to an external
• One basic rule : Work not in the WBS is
deliverable, which is a deliverable that is subject
outside the scope of the project.
to approval by the sponsor or customer
Stability
• Anticipation
• Risk management
• Coordination of stakeholders
• Resource management
• Measure Progress
− draw the network (PERT) • Free float: maximum delay an activity can be
delayed without delaying downstream activities
− no loop
• Total float: maximum delay an activity can
− no “or” begin without delaying the end of the project
Funding Limit Reconciliation: adjustment of the There are three types of indicators in EVM:
schedule to the needs of economic balance
Variance Indexes
5.3 Control Costs ● Schedule Variance (SV = EV - PV)
This is the process of monitoring the status of ● Cost Variance (CV = EV - AC)
the project to update the project budget and
● >0 ☺
managing changes to the cost baseline.
Performance Indexes
Methods and tools
● Schedule Performance Index (SPI = EV /
● Earned Value Management: the main
PV)
technique to control costs
● Cost Performance Index (CPI = EV / AC)
● Forecasting: estimates of conditions
that may occur in the future of the ● >1 ☺ project ahead the schedule or
project based on services provided to costing less
date (based on EVM) Forecast
● To-Complete Performance Index: it
shows the cost performance that a ● Estimate to Complete (ETC = [BAC –
project should have to achieve certain EV]/CPI) – to complete the project
objectives (based on EVM) ● Estimate at Completion (EAC = BAC/CPI)
● Variance Analysis: analysis of the – revises overall project costs
variations compared to the baseline ● Variance at Completion (VAC =
BAC–EAC) – deviation from original
Earned Value Management (EVM) budget
Three base elements of EVM are:
The processes required to make the most Tracking team member performance, providing
effective use of people involved with the feedback, resolving issues, and coordinating
Project. changes to enhance project performance.
Individual Risks and Opportunities are managed ● Methodology : approaches and tools to be
at Work Package / Task Level used
● Roles and responsibility: people responsible
The impact of the risk can be reduced for management
exclusively by an individual Work Package / Task ● Budgeting: expected costs for risk
Common risks management
● Timing: duration/location of management
Common risks are managed at Project Level activities
● Definitions of risk probability and impact:
The impact of the risk can be reduced only by
acceptable/non acceptable
the coordinated actions of several Work
● Probability and impact matrix: risks are
Packages / Tasks prioritized according to their potential
implications for having an effect on the
project's objectives.
● Tracking: any audit on risk management
processes.
Escalate.
1. Leadership
Management is doing things right; leadership is
doing the right things.
● Speech
● Writing
● Signs (emoticons)
● Jointly
● Timely
● Frequently
Exemples:
Communicative model
Strategy of sharing power and relying to get • Complexity - You have to consider
other people involved on the project to many interrelated factors.
cooperate towards common goals.
• High-risk consequences - The impact of
The DESC method was conceived by Sharon and the decision may be significant.
Gordon Bower and is discussed more fully in
• Alternatives - Each has its own set of
their book, Asserting Yourself.
uncertainties and consequences.
DESC stands for Describe, Express, Specify, and
• Interpersonal issues - It can be difficult
Consequences.
to predict how other people will react.
• Describe the situation as precisely and
There are six steps to make an effective
as objectively as possible.
decision:
• Express one's feelings about the
1. Create a constructive environment.
situation diplomatically.
2. Generate good alternatives, to dig
• Specify solutions in order to reach an
deeper.
agreement with the other person.
3. Explore these alternatives.
• Specify the Consequences (both
positive and negative). 4. Choose the best alternative.
Crushing iceberg
Negotiation tactics:
– Deadline
– Limited Authority
– Missing Man
– Delay
– Extreme Demands
– Withdrawal
– Fait Accompli
11.3 Responsibility
Responsibility is our duty to take ownership for
the decisions we make or fail to make, the
actions we take or fail to take, and the
consequences that result.
11.4 Respect
Respect is our duty to show a high regard for
ourselves, others, and the resources entrusted
to us.
11.5 Fairness
Fairness is our duty to make decisions and act
impartially and objectively. Our conduct must
be free from competing self-interest, prejudice,
and favouritism.
11.6 Honesty
Honesty is our duty to understand the truth and
act in a truthful manner both in our
communications and in our conduct.
Further reading:
https://www.pmi.org/about/ethics/code