D3 - FTA Calc Numbers Main Body
D3 - FTA Calc Numbers Main Body
High Temperature
TS-1 TS-2
VALVE-SOV 2oo2 VALVE-SOV 2oo2
3.3 E-2 3.3 E-2
l =3*10-5f/h
T= 3 months (2190 h)
SV-1 SOL-1 SV-2 SOL-2 PFDavg= l *T/2 = 3 *10-5 * 2190/2
= 3285 * 10-5 = 3.3 * 10-2
TS-1 TS-2
VALVE-SOV 2oo2 VALVE-SOV 2oo2
3.3 E-2 3.3 E-2
l =9.041*10-6f/h
SV-1 SOL-1 SV-2 SOL-2
T= 3 months (2190 h)
PFDavg= l *T/2 = 9.041 *10-6 * 2190/2
9.9 E-3 9.9 E-3 9.9 E-3 = 9899 * 10-6 = 9.9 * 10-3
9.9 E-3
1
7/27/2012
TS-1 TS-2
VALVE-SOV 2oo2 VALVE-SOV 2oo2
3.3 E-2 3.3 E-2