Preliminary Design Review (PDR)
Preliminary Design Review (PDR)
Typical PDR success criteria include affirmative answers to the following exit
questions:
Does the status of the technical effort and design indicate operational
test and evaluation success (operationally effective and suitable)?
Can the preliminary design, as disclosed, satisfy the draft Capability
Development Document?
Has the system allocated baseline been established and documented
to enable detailed design to proceed with proper configuration
management?
Are adequate processes and metrics in place for the program to
succeed?
Have sustainment and human systems integration design factors been
reviewed and included, where needed, in the overall system design?
Are the risks known and manageable for integrated testing and
developmental and operational evaluation?
Is the program schedule executable (technical/cost risks)?
Is the program properly staffed?
Have the program„s cost estimate been updated?
Is the program executable within the existing budget and with the
approved system allocated baseline?
Is the preliminary system level design producible within the production
budget?
Is the updated CARD consistent with the approved allocated baseline?
With the additional emphasis on software development and the critical role it
plays in providing system functionality, the following exit questions should
also be addressed for the system‟s software component:
The PDR should be conducted when the allocated baseline has been
achieved, allowing detailed design of hardware and software CIs to proceed.
A rule of thumb is that 10 percent to 25 percent of product drawings and
associated instructions should be complete, and that 100 percent of all
safety‐critical component (Critical Safety Items and Critical Application
Items) drawings are complete.
The PDR should be conducted when all major design issues have been
resolved and work can begin on detailed design. The PDR should address
and resolve critical, system‐wide issues before detailed design begins.