Lifting Shifting Plan Panel
Lifting Shifting Plan Panel
Lifting Shifting Plan Panel
(Sub Vendor)
Meghna Electricals
For Project
B
Project: RRTS Duhai Depot Project Ghaziabad UP Date: 22-11-2021
Meerut Road – Village Bikhanpur Revision No: 00
PROJECT DETAILS
PROJECT
CLIENT
Project Manager
d. The necessary safety precautions will be taken in selection of lifting shifting machinery, task briefing to
workers and lifting shifting of work. The work intended to execute under the method statement will be
carried out according to safety provisions.
3. Procedure (Lifting)
a. Clearance and barricade of field area is importance before unloading with nobody around lifting area.
b. The spotter should be given sign to driver where the material should be lifting shifting.
c. Unloading should be possible in dry condition. It shall be observed that any obstruction may change this
situation.
d. Crane position should be able to reach the material as well as length boom of Crane.
e. LT Panel material should tie up well with Weber sling as required weight. Then hook up at boom lower
sheaves with shackle.
f. Lift up material slowly from crane boom on building Floor from GF open area front side
g. Required 20 ton on Lifting Crane to lift to material to Admin Building floor.
h. On Admin Building's Front Side Road Barricading Marked A Is Crane Location Inside Side Of
Barricading Marked On 30Ft radius area,
i. Single LT Panel maxm Dia …………………………… Weight Approximately 200-500 Kg maximum
j. On Photo Marked B Is Material Staking on Ground Floor.
k. Make sure material has landing at floor and loose the weber sling from boom hoist sheaves hook
4. SHE Aspects
Manpower must be use complete PPE (masker, hand glove, safety shoes, helmet) As per requirement.
4.2 Tools
- Shifting Jack or Roller
- Weber Sling if required
- D Shackles
- Barricade Line
- Slings
- 20 Ton Crane.