EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Fine grout mix proportions shall be: 1 part Portland cement; 0.1 part SAES-M-100
A1
slaked lime; 2.25-3.0 parts fine aggregates.(ACI 530.1, Sec. 2.6B.1) Sec. C.3
Coarse grout mix proportions shall be: 1 part Portland cement; 0.1 part SAES-M-100
A2
slaked lime; 1-2 parts coarse aggregates. (ACI 530.1, Sec. 2.6B.1) Sec. C.3
The mortar used shall be sufficiently plastic and units shall be placed
1997 UBC
A3 with sufficient pressure to extrude mortar from the joint and produce a
Sec. 2104.4.1
tight joint.
Levelness of both bedding joints and tops of walls shall be within + 0.25"
SAES-M-100
A5 (6.4mm) in 10 ft (3.05m) or + 0.5" (12.7mm) maximum.
Sec. C.3
(ACI 530.1, Sec. 3.3.G.2.a)
Surfaces to be in contact with mortar or grout shall be clean and free of 1997 UBC
A7
deleterious materials. Sec. 2104.4.2
1997 UBC
A8 Solid masonry units shall have full head and bed joints.
Sec. 2104.4.3
All head and bed joints in hollow masonry construction shall be filled
1997 UBC
A12 solidly with mortar for a distance in from the face of the units not less
Sec. 2104.4.4
than the thickness of the masonry units shell.
Grouted masonry shall be constructed in such a manner that all 1997 UBC
A13
elements of the masonry act together as a structural element. Sec. 2104.6.1
Page 1 of 3
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Masonry Units and Plaster Installation Inspection SAIC-M-1009 18-May-05 Civil
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Prior to grouting, the grout space shall be clean so that all spaces to be
filled with grout do not contain mortar projections greater than 12.7mm
1997 UBC
A14 (1/2"), mortar droppings or other foreign material. Grout shall be placed
Sec. 2104.6.1
so that all spaces designated to be grouted shall be filled and the grout
shall be confined to those specific places.
Grout shall be poured from less than 5ft (1.52m) and grout lift height less
SAES-M-100
A15 than 5ft (1.52m) consolidated by vibration or puddling.
Sec. C.3
(ACI 530.1, Sec 3.5C. & 3.5D.)
Grout materials and water content shall be controlled to provide 1997 UBC
A16
adequate fluidity for placement without segregation of the constituents. Sec. 2104.6.1
Grouting of any section of wall shall be completed in one day with no 1997 UBC
A17
interruptions greater than one hour. Sec. 2104.6.1
Cleanouts shall be provided for all grout pours over 5 feet (1.52m) in
height. Where required, cleanouts shall be provided in the bottom
1997 UBC
A19 course at every vertical bar but not more than 813mm (32") on center for
Sec. 2104.6.1
solid grouted masonry. Where used, cleanouts they shall be sealed after
inspection and before grouting.
Expanded Metal Lath shall be installed as shown on the IFC Drawings for
A21 IFC Drawings
Portland Cement Plaster or Stucco.
1997 UBC
A23 Grout shall not be handled nor pumped utilizing aluminum equipment.
Sec. 2104.7
Bolts shall be accurately set with templates or approved equivalent 1997 UBC
A24
means and held in place to prevent dislocation during grouting. Sec. 2104.6.2
B Final Inspection
B1 Finished walls are plumb and in alignment as shown on IFC Drawings. IFC Drawings
1997 UBC
B2 All cells and spaces containing reinforcement shall be filled with grout.
Sec. 2104.6.1
Page 2 of 3
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Masonry Units and Plaster Installation Inspection SAIC-M-1009 18-May-05 Civil
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-M-100 -- Saudi Aramco Building Code, 29 January 2003
2- 1997 UBC -- Uniform Building Code, 01 January 1997